No. URAIAN KOEFISIEN SAT HARGA SATUAN JUMLAH (RP)
I PEKERJAAN PERSIAPAN 1 1 M¹ PAGAR SENG GELOMBANG TINGGI : 2 M a Tiang kayu borneo 4/6 0.05 m3 5,400,000.00 270,000.00 b Semen PC (abu-abu) 0.05 sak 54,000.00 2,700.00 c Seng gelombang 1.20 sak 57,500.00 69,000.00 d Pasir beton 0.01 m3 92,000.00 460.00 e Split (batu pecah) 0.01 m3 270,000.00 2,430.00 f Balok kayu borneo 4/6 0.05 m3 5,400,000.00 270,000.00 g Paku 5 - 10 cm 0.06 kg 17,500.00 1,050.00 h Meni Besi 0.45 kg 22,000.00 9,900.00 i Tukang kayu 0.20 org 87,500.00 17,500.00 j Pembantu tukang 0.10 org 50,000.00 5,000.00 Jumlah 648,040.00 Dibulatkan 648,040.00 2 1 M¹ PAGAR KAWAT BERDURI TINGGI : 1,8 M a Tiang kayu borneo 4/6 0.05 m3 5,400,000.00 270,000.00 b Semen PC (abu-abu) 0.04 sak 54,000.00 2,160.00 c Kawat Duri 2.50 kg 155,000.00 387,500.00 d Pasir beton 0.01 m3 92,000.00 460.00 e Split (batu pecah) 0.01 m3 270,000.00 2,430.00 f Paku 5 - 10 cm 0.06 kg 17,500.00 1,050.00 g Tukang kayu 0.20 org 87,500.00 17,500.00 h Pembantu tukang 0.30 org 50,000.00 15,000.00
Jumlah 696,100.00 Dibulatkan 696,100.00 3 1 M1 PENGUKURAN & PEMASANGAN BOWPLANK a Kayu kaso 5/7 borneo 0.02 m3 5,400,000.00 108,000.00 b Paku 5 - 10 cm 0.02 kg 17,500.00 350.00 c Papan papan kayu terentang 2/20 0.00 m3 1,448,200.00 5,792.80 d Tukang kayu 0.10 org 87,500.00 8,750.00 e Pembantu tukang 0.10 org 50,000.00 5,000.00 Jumlah 127,892.80 Dibulatkan 127,890.00 4 1 M2 PEMBUATAN KANTOR DIREKSI a Kayu kaso 5/7 borneo 0.02 m3 5,400,000.00 108,000.00 b Papan kayu terentang 0.18 m3 1,448,200.00 260,676.00 c Paku semua ukuran 0.85 kg 17,500.00 14,875.00 d Besi strip 1.10 kg 14,100.00 15,510.00 e Semen PC (abu-abu) 35.00 kg 54,000.00 1,890,000.00 f Pasir pasang 0.15 m3 84,000.00 12,600.00 g Pasir beton 0.10 m3 92,000.00 9,200.00 h Split (batu pecah) 0.15 m3 270,000.00 40,500.00 i Bata merah 30.00 bh 650.00 19,500.00 j Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 61,750.00 74,100.00 k Seng Plat BJLS 32 1.00 m2 33,300.00 33,300.00 l Kawat harmonika 2.00 m2 24,500.00 49,000.00 m Kaca polos 3 mm 0.08 m2 90,000.00 7,200.00 n Kunci tanam standart 0.15 bh 55,000.00 8,250.00 o Triplek 120 x 240 x 0,4 cm 0.06 lbr 53,750.00 3,225.00 p Tukang kayu 2.00 org 87,500.00 175,000.00 q Tukang batu 1.00 org 87,500.00 87,500.00 r Pembantu tukang 2.00 org 50,000.00 100,000.00 Jumlah 2,908,436.00
Dibulatkan 2,908,430.00 5 1 M2 PEMBUATAN GUDANG PROYEK a Kayu kaso 5/7 borneo 0.02 m3 5,400,000.00 108,000.00 b Papan kayu terentang 0.10 m3 1,448,200.00 144,820.00 c Paku 0.30 kg 17,500.00 5,250.00 d Semen PC (abu-abu) 0.21 sak 54,000.00 11,340.00 e Pasir beton 0.03 m3 92,000.00 2,760.00 f Split (batu pecah) 0.05 m3 270,000.00 13,500.00 g Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 61,750.00 74,100.00 h Tukang kayu 1.00 org 87,500.00 87,500.00 i Pembantu tukang 1.00 org 50,000.00 50,000.00 Jumlah 497,270.00 Dibulatkan 497,270.00 6 1 M2 MEMBERSIHKAN LOKASI ROYEK a Pembantu tukang 0.10 org 50,000.00 5,000.00 Jumlah 5,000.00 Dibulatkan 5,000.00 7 1 M2 MEMBERSIHKAN PUING-PUING a Pembantu tukang 0.20 org 50,000.00 10,000.00 Jumlah 10,000.00 Dibulatkan 10,000.00 8 1 BH MEMBERSIHKAN TUNGGUL TANAMAN a Pembantu tukang 2.00 org 50,000.00 100,000.00 Jumlah 100,000.00 Dibulatkan 100,000.00 9 1M2 PEMBUATAN JALAN MASUK PROYEK a Batu belah 15/20 0.10 m3 128,200.00 12,820.00 b Koral 5/7 ( sirtu ) 0.05 m3 82,000.00 4,100.00 c Pasir urug 0.01 m3 67,000.00 670.00 d Pembantu tukang 1.00 org 50,000.00 50,000.00
Jumlah 67,590.00 Dibulatkan 67,500.00 10 1 M3 PEMBONGKARAN BETON a Pembantu tukang 6.20 org 50,000.00 310,000.00 Jumlah 310,000.00 Dibulatkan 310,000.00 11 1 M3 PEMBONGKARAN DINDING BATA a Pembantu tukang 4.60 org 50,000.00 230,000.00 Jumlah 230,000.00 Dibulatkan 230,000.00 12 1 M2 PEKERJAAN PAGAR PAPAN RANGKA BALOK a Papan kayu borneo 0.02 m3 5,660,000.00 113,200.00 b Balok kayu borneo 5/7 0.02 m3 5,400,000.00 108,000.00 c Pasir beton 0.08 m3 92,000.00 7,360.00 d Split (batu pecah) 0.15 m3 270,000.00 40,500.00 e Semen abu - abu 0.50 sak 54,000.00 27,000.00 f Tukang kayu 0.13 org 87,500.00 11,375.00 g Pembantu tukang 0.38 org 50,000.00 19,000.00 Jumlah 326,435.00
Dibulatkan 326,400.00
II PEKERJAAN TANAH 1 1 M3 GALIAN TANAH SEDALAM 1 M a Pembantu tukang 0.40 org 50,000.00 20,000.00 b Tukang gali 0.02 org 75,000.00 1,500.00 Jumlah 21,500.00 Dibulatkan 21,500.00 2 1 M3 GALIAN TANAH SEDALAM 2 M
a Pembantu tukang 0.53 org 50,000.00 26,500.00 b Tukang gali 0.02 org 75,000.00 1,500.00 Jumlah 28,000.00 Dibulatkan 28,000.00 3 1 M3 GALIAN TANAH SEDALAM 3 M a Pembantu tukang 0.74 org 50,000.00 37,000.00 b Tukang gali 0.02 org 75,000.00 1,500.00 Jumlah 38,500.00 Dibulatkan 38,500.00 4 1 M3 GALIAN TANAH KERAS SEDALAM 1 M a Pembantu tukang 0.45 org 50,000.00 22,500.00 b Tukang gali 0.02 org 75,000.00 1,500.00 Jumlah 24,000.00 Dibulatkan 24,000.00 5 1 M2 PEKERJAAN PENGUPASAN TANAH SETEBAL 10 CM a Pembantu tukang 0.05 org 50,000.00 1,250.00 b Tukang gali 0.02 org 75,000.00 1,125.00 Jumlah 2,375.00 Dibulatkan 2,370.00 6 1 M3 PEMBUANGAN TANAH SEJAUH 150 M a Pembantu tukang 0.42 org 50,000.00 21,000.00 b Tukang gali 0.02 org 75,000.00 1,500.00 Jumlah 22,500.00 Dibulatkan 22,500.00 7 1 M3 URUGAN TANAH KEMBALI a Pembantu tukang 0.19 org 50,000.00 9,500.00 b Tukang gali 0.02 org 75,000.00 1,500.00 Jumlah 11,000.00 Dibulatkan 11,000.00 8 1 M3 PEMADATAN TANAH
a Pembantu tukang 0.50 org 50,000.00 25,000.00 b Tukang gali 0.02 org 75,000.00 1,500.00 Jumlah 26,500.00 Dibulatkan 26,500.00 9 1 M3 URUGAN PASIR a Pasir urug 1.20 m3 67,000.00 80,400.00 b Pembantu tukang 0.30 org 50,000.00 15,000.00 c Tukang gali 0.02 org 75,000.00 1,500.00 Jumlah 96,900.00 Dibulatkan 96,900.00 10 1 M3 URUGAN TANAH a Tanah urug 1.20 m3 78,000.00 93,600.00 b Pembantu tukang 0.30 org 50,000.00 15,000.00 c Tukang gali 0.02 org 75,000.00 1,500.00 Jumlah 110,100.00 Dibulatkan 110,100.00 11 1 M3 URUGAN SIRTU a Sirtu ( koral ) 1.20 m3 82,000.00 98,400.00 b Pembantu tukang 0.25 org 50,000.00 12,500.00 c Tukang gali 0.02 org 75,000.00 1,500.00 Jumlah 112,400.00 Dibulatkan 112,400.00
III PEKERJAAN PONDASI 1 1 M3 PASANG PONDASI BT KALI , 1 Pc : 3 Ps a Batu belah 1.10 m3 128,200.00 141,020.00 b Semen PC (abu-abu) 4.04 sak 54,000.00 218,160.00 c Pasir pasang 0.49 m3 84,000.00 40,740.00
d Pembantu tukang 1.50 org 50,000.00 75,000.00 e Tukang batu 0.60 org 87,500.00 52,500.00 Jumlah 527,420.00 Dibulatkan 527,420.00 2 1 M3 PASANG PONDASI BT KALI , 1 Pc : 4 Ps a Batu belah 1.10 m3 128,200.00 141,020.00 b Semen PC (abu-abu) 3.26 sak 54,000.00 176,040.00 c Pasir pasang 0.52 m3 84,000.00 43,680.00 d Pembantu tukang 1.50 org 50,000.00 75,000.00 e Tukang batu 0.60 org 87,500.00 52,500.00 Jumlah 488,240.00 Dibulatkan 488,240.00 3 1 M3 PASANG PONDASI BT KALI , 1 Pc : 5 Ps a Batu belah 1.10 m3 128,200.00 141,020.00 b Semen PC (abu-abu) 2.72 sak 54,000.00 146,880.00 c Pasir pasang 0.54 m3 84,000.00 45,696.00 d Pembantu tukang 1.50 org 50,000.00 75,000.00 e Tukang batu 0.60 org 87,500.00 52,500.00 Jumlah 461,096.00 Dibulatkan 461,090.00 4 1 M3 PASANG PONDASI BATU KOSONG ( AANSTAMPING ) a Batu belah 1.20 m3 128,200.00 153,840.00 b Pasir urug 0.30 m3 67,000.00 20,100.00 c Pembantu tukang 0.78 org 50,000.00 39,000.00 d Tukang batu 0.39 org 87,500.00 34,125.00 Jumlah 247,065.00 Dibulatkan 247,000.00 5 1 M3 MEMBUAT BETON BERTULANG UNTUK PONDASI 1 Pc : 2 Ps : 3 Kr a Semen PC (abu-abu) 6.72 sak 54,000.00 362,880.00 b Pasir beton 0.54 m3 92,000.00 49,680.00
c Split (batu pecah) 0.81 m3 270,000.00 218,700.00 d Pembantu tukang 2.00 org 50,000.00 100,000.00 e Tukang batu 0.35 org 87,500.00 30,625.00 Jumlah 761,885.00 Dibulatkan 761,800.00 6 1 Kg PENULANGAN BETON PONDASI a Besi beton polos 1.05 kg 13,950.00 14,647.50 b Kawat beton 0.02 kg 13,400.00 201.00 c Pembantu tukang 0.01 org 50,000.00 350.00 d Tukang besi 0.01 org 87,500.00 612.50 Jumlah 15,811.00 Dibulatkan 15,800.00 7 1 M2 PEKERJAAN BEKISTING UNTUK PONDASI a Papan kayu terentang 0.04 m3 1,448,200.00 57,928.00 b Paku 5 - 12 cm 0.30 kg 1,900.00 570.00 c Pelumas begisting (oli/minyak) 0.10 Ltr 12,500.00 1,250.00 d Pembantu tukang 0.30 org 50,000.00 15,000.00 e Tukang kayu 0.26 org 87,500.00 22,750.00 Jumlah 97,498.00 Dibulatkan 97,400.00 8 1 M3 PASANG PONDASI CYCLOOP (60 %BETON : 40% BATU KALI) a Besi beton polos 50.00 kg 13,950.00 697,500.00 b Semen PC (abu-abu) 4.04 sak 54,000.00 218,160.00 c Pasir beton 0.32 m3 92,000.00 29,440.00 d Split (batu pecah) 0.49 m3 270,000.00 132,300.00 e Kawat beton 0.80 kg 13,400.00 10,720.00 f Batu belah 0.40 m3 128,200.00 51,280.00 g Pembantu tukang 2.00 org 50,000.00 100,000.00 h Tukang batu 0.85 org 87,500.00 74,375.00 Jumlah 1,313,775.00
Dibulatkan 1,313,700.00 9 1 M3 PASANG PONDASI SUMURAN DIAMETER 100 cm a Batu belah 0.45 m3 128,200.00 57,690.00 b Semen PC (abu-abu) 5.60 sak 54,000.00 302,400.00 c Pasir beton 0.45 m3 92,000.00 41,400.00 d Split (batu pecah) 0.67 m3 270,000.00 180,900.00 e Pembantu tukang 2.38 org 50,000.00 119,000.00 f Tukang batu 0.30 org 87,500.00 26,250.00 Jumlah 727,640.00 Dibulatkan 727,600.00 10 1 M¹ PEMBUATAN PONDASI TIANG BETON BERTULANG UKURAN 40 X 40 Cm a Pasir beton 0.10 m3 92,000.00 9,200.00 b Split (batu pecah) 0.15 m3 270,000.00 40,500.00 c Semen PC (abu-abu) 1.21 sak 54,000.00 65,340.00 d Besi beton polos 45.00 kg 13,950.00 627,750.00 e Kawat beton 0.90 kg 13,400.00 12,060.00 f Balok kayu borneo super 5/7 0.03 m3 5,400,000.00 172,800.00 g Papan kayu terentang 0.01 m3 5,660,000.00 56,600.00 h Paku 5 - 12 cm 0.12 kg 17,500.00 2,100.00 i Pelumas begisting (oli/minyak) 0.09 Ltr 12,500.00 1,125.00 j Plamir tembok 0.24 kg 25,000.00 6,000.00 k Pembantu tukang 1.00 org 50,000.00 50,000.00 l Tukang batu 0.67 org 87,500.00 58,625.00 Jumlah 1,102,100.00 Dibulatkan 1,102,100.00 11 1 M¹ PEMBUATAN PONDASI TIANG BETON BERTULANG UKURAN 35 X 35 CM a Pasir beton 0.08 m3 92,000.00 7,360.00 b Split (batu pecah) 0.13 m3 270,000.00 35,100.00 c Semen PC (abu-abu) 0.98 sak 54,000.00 52,920.00 d Besi beton polos 34.50 kg 13,950.00 481,275.00
e Kawat beton 0.70 kg 13,400.00 9,380.00 f Balok kayu borneo super 5/7 0.03 m3 5,400,000.00 162,000.00 g Papan kayu terentang 0.01 m3 5,660,000.00 56,600.00 h Paku 5 - 12 cm 0.12 kg 17,500.00 2,100.00 i Pelumas begisting (oli/minyak) 0.09 Ltr 12,500.00 1,125.00 j Plamir tembok 0.20 kg 25,000.00 5,000.00 k Pembantu tukang 0.80 org 50,000.00 40,000.00 l Tukang batu 0.50 org 87,500.00 43,750.00 Jumlah 896,610.00 Dibulatkan 896,600.00 12 1 M3 MEMBUAT PONDASI TIANG PANCANG UKURAN 25 X 25 a Pasir beton 0.06 m3 92,000.00 5,520.00 b Split (batu pecah) 0.11 m3 270,000.00 29,700.00 c Semen PC (abu-abu) 0.82 sak 54,000.00 44,280.00 d Besi beton polos 34.50 kg 13,950.00 481,275.00 e Kawat beton 0.60 kg 13,400.00 8,040.00 f Balok kayu borneo super 5/7 0.03 m3 5,400,000.00 162,000.00 g Papan kayu terentang 0.01 m3 5,660,000.00 56,600.00 h Paku 5 - 12 cm 0.11 kg 17,500.00 1,925.00 i Pelumas begisting (oli/minyak) 0.08 Ltr 12,500.00 1,000.00 j Plamir tembok 0.20 kg 25,000.00 5,000.00 k Pembantu tukang 0.80 org 50,000.00 40,000.00 l Tukang batu 0.50 org 87,500.00 43,750.00 Jumlah 879,090.00 Dibulatkan 879,000.00 13 1 M3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 125 kg + BEKISTING ) a Papan kayu terentang 0.20 m3 1,448,200.00 289,640.00 b Paku 5 - 12 cm 1.50 kg 17,500.00 26,250.00 c Pelumas begisting (oli/minyak) 0.40 Ltr 12,500.00 5,000.00 d Besi beton polos 125.00 kg 13,950.00 1,743,750.00
e Kawat beton 2.25 kg 13,400.00 30,150.00 f Semen PC (abu-abu) 6.46 sak 54,000.00 348,840.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Pembantu tukang 3.90 org 50,000.00 195,000.00 j Tukang batu 0.35 org 87,500.00 30,625.00 k Tukang kayu 1.04 org 87,500.00 91,000.00 l Tukang besi 1.05 org 87,500.00 91,875.00 Jumlah 3,110,570.00 Dibulatkan 3,110,500.00 14 1 M3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 150 kg + BEKISTING ) a Papan kayu terentang 0.20 m3 1,448,200.00 289,640.00 b Paku 5 - 12 cm 1.50 kg 17,500.00 26,250.00 c Pelumas begisting (oli/minyak) 0.40 ltr 12,500.00 5,000.00 d Besi beton polos Polos 150.00 kg 13,950.00 2,092,500.00 e Kawat beton 2.25 kg 13,400.00 30,150.00 f Semen PC (abu-abu) 6.46 sak 54,000.00 348,840.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Pembantu tukang 4.00 org 50,000.00 200,000.00 j Tukang batu 0.40 org 87,500.00 35,000.00 k Tukang kayu 1.00 org 87,500.00 87,500.00 l Tukang besi 1.00 org 87,500.00 87,500.00 Jumlah 3,460,820.00 Dibulatkan 3,460,800.00 15 1 M3 MEMBUAT PONDASI BETON BOREPILE (PENULANGAN 125 kg + BEKISTING ) a Papan kayu terentang 0.20 m3 1,448,200.00 289,640.00 b Paku 5 - 12 cm 1.50 kg 17,500.00 26,250.00 c Pelumas begisting (oli/minyak) 0.40 ltr 12,500.00 5,000.00 d Besi beton polos Polos 125.00 kg 13,950.00 1,743,750.00
e Kawat beton 2.10 kg 13,400.00 28,140.00 f Semen PC (abu-abu) 6.46 sak 54,000.00 348,840.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Pembantu tukang 3.90 org 50,000.00 195,000.00 j Tukang batu 0.40 org 87,500.00 35,000.00 k Tukang kayu 1.00 org 87,500.00 87,500.00 l Tukang besi 1.00 org 87,500.00 87,500.00 Jumlah 3,105,060.00 Dibulatkan 3,105,000.00 16 1 M3 MEMBUAT PONDASI BETON BOREPILE (PENULANGAN 150 kg + BEKISTING ) a Papan kayu terentang 0.20 m3 1,448,200.00 289,640.00 b Paku 5 - 12 cm 1.50 kg 17,500.00 26,250.00 c Pelumas begisting (oli/minyak) 0.40 ltr 12,500.00 5,000.00 d Besi beton polos 150.00 kg 13,950.00 2,092,500.00 e Kawat beton 2.25 kg 13,400.00 30,150.00 f Semen PC (abu-abu) 6.46 sak 54,000.00 348,840.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Pembantu tukang 4.00 org 50,000.00 200,000.00 j Tukang batu 0.40 org 87,500.00 35,000.00 k Tukang kayu 1.00 org 87,500.00 87,500.00 l Tukang besi 1.00 org 87,500.00 87,500.00 Jumlah 3,460,820.00 Dibulatkan 3,460,800.00
IVPEKERJAAN BETON NON STRUKTUR DAN BETON STRUKTUR
A PEKERJAAN BETON 1 1 M3 MEMBUAT BETON NON STRUKTUR, 1 Pc : 3 Ps : 5 Splt a Semen PC (abu-abu) 4.36 sak 54,000.00 235,440.00 b Pasir beton 0.52 m3 92,000.00 47,840.00 c Split (batu pecah) 0.87 m3 270,000.00 234,900.00 d Pembantu tukang 2.00 org 50,000.00 100,000.00 e Tukang batu 0.35 org 87,500.00 30,625.00 Jumlah 648,805.00 Dibulatkan 648,800.00 2 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 4 Splt a Semen PC (abu-abu) 4.64 sak 54,000.00 250,560.00 b Pasir beton 0.52 m3 92,000.00 47,840.00 c Split (batu pecah) 0.78 m3 270,000.00 210,600.00 d Pembantu tukang 2.00 org 50,000.00 100,000.00 e Tukang batu 0.35 org 87,500.00 30,625.00 Jumlah 639,625.00 Dibulatkan 639,600.00 3 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 3 Splt a Semen PC (abu-abu) 6.72 sak 54,000.00 362,880.00 b Pasir beton 0.54 m3 92,000.00 49,680.00 c Split (batu pecah) 0.81 m3 270,000.00 218,700.00 d Pembantu tukang 2.00 org 50,000.00 100,000.00 e Tukang batu 0.35 org 87,500.00 30,625.00 Jumlah 761,885.00 Dibulatkan 761,800.00 4 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 225 a Semen PC (abu-abu) 7.76 sak 54,000.00 419,040.00 b Pasir beton 0.65 m3 92,000.00 59,800.00 c Split (batu pecah) 0.65 m3 270,000.00 175,500.00 d Pembantu tukang 2.00 org 50,000.00 100,000.00
e Tukang batu 0.35 org 87,500.00 30,625.00 Jumlah 784,965.00 Dibulatkan 784,900.00 5 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 275 a Semen PC (abu-abu) 8.00 sak 54,000.00 432,000.00 b Pasir beton 0.55 m3 92,000.00 50,600.00 c Split (batu pecah) 0.70 m3 270,000.00 189,000.00 d Pembantu tukang 2.02 org 50,000.00 101,000.00 e Tukang batu 0.40 org 87,500.00 35,000.00 Jumlah 807,600.00 Dibulatkan 807,600.00 B PEKERJAAN PEMBESIAN 1 1 KG PENULANGAN BETON/BESI BETON POLOS a Besi beton polos 1.05 kg 13,950.00 14,647.50 b Kawat beton 0.02 kg 13,400.00 268.00 c Pembantu tukang 0.01 org 50,000.00 500.00 d Tukang besi 0.01 org 87,500.00 875.00 Jumlah 16,290.50 Dibulatkan 16,200.00 2 1 KG PENULANGAN BETON/BESI BETON ULIR a Besi Beton Ulir 1.10 kg 15,100.00 16,610.00 b Kawat beton 0.02 kg 13,400.00 201.00 c Pembantu tukang 0.01 org 50,000.00 500.00 d Tukang besi 0.02 org 87,500.00 1,750.00 Jumlah 19,061.00 Dibulatkan 19,000.00 C PEKERJAAN BEGISTING 1 1 M2 PASANG BEKISTING UNTUK SLOOF a Papan kayu terentang 0.05 m3 1,448,200.00 65,169.00 b Paku 5 - 12 cm 0.30 kg 17,500.00 5,250.00
c Pelumas begisting (oli/minyak) 0.10 Ltr 12,500.00 1,250.00 d Pembantu tukang 0.30 org 50,000.00 15,000.00 e Tukang kayu 0.26 org 87,500.00 22,750.00 Jumlah 109,419.00 Dibulatkan 109,400.00 2 1 M2 PASANG BEKISTING UNTUK KOLOM a Papan kayu terentang 0.04 m3 1,448,200.00 57,928.00 b Paku 5 - 12 cm 0.40 kg 17,500.00 7,000.00 c Pelumas begisting (oli/minyak) 0.20 Ltr 12,500.00 2,500.00 d Balok Kayu Borneo 0.04 m3 5,400,000.00 216,000.00 e Multiplex 120 x 240 x 9 mm 0.35 lbr 120,950.00 42,332.50 f Pembantu tukang 0.30 org 50,000.00 15,000.00 g Tukang kayu 0.33 org 87,500.00 28,875.00 Jumlah 369,635.50 Dibulatkan 369,600.00 3 1M2 PASANG BEKISTING UNTUK BALOK a Papan kayu terentang 0.04 m3 1,448,200.00 57,928.00 b Paku 5 - 12 cm 0.40 kg 17,500.00 7,000.00 c Pelumas begisting (oli/minyak) 0.20 Ltr 12,500.00 2,500.00 d Balok Kayu Borneo 0.04 m3 5,400,000.00 216,000.00 e Multiplex 120 x 240 x 9 mm 0.35 lbr 120,950.00 42,332.50 f Pembantu tukang 0.32 org 50,000.00 16,000.00 g Tukang kayu 0.33 org 87,500.00 28,875.00 Jumlah 370,635.50 Dibulatkan 370,600.00 4 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI a Papan kayu terentang 0.04 m3 1,448,200.00 57,928.00 b Paku 5 - 12 cm 0.40 kg 17,500.00 7,000.00 c Pelumas begisting (oli/minyak) 0.20 Ltr 12,500.00 2,500.00 d Balok Kayu Borneo 0.04 m3 5,400,000.00 216,000.00
e Multiplex 120 x 240 x 9 mm 0.35 lbr 120,950.00 42,332.50 f Pembantu tukang 0.32 org 50,000.00 16,000.00 g Tukang kayu 0.33 org 87,500.00 28,875.00 Jumlah 370,635.50 Dibulatkan 370,600.00 5 1 M2 PASANG BEKISTING UNTUK TANGGA a Papan kayu terentang 0.03 m3 1,448,200.00 43,446.00 b Paku 5 - 12 cm 0.40 kg 17,500.00 7,000.00 c Pelumas begisting (oli/minyak) 0.15 Ltr 12,500.00 1,875.00 d Balok kayu borneo 0.02 m3 5,400,000.00 108,000.00 e Multiplex 120 x 240 x 9 mm 0.35 lbr 120,950.00 42,332.50 f Pembantu tukang 0.32 org 50,000.00 16,000.00 g Tukang kayu 0.33 org 87,500.00 28,875.00 Jumlah 247,528.50 Dibulatkan 247,500.00 D PEKERJAAN BETON BERTULANG 1 1 M3 MEMBUAT SLOOF BETON BERTULANG ( 200 kg BESI + BEKISTING ) K225 a Papan kayu terentang 0.27 m3 1,448,200.00 391,014.00 b Paku 5 - 12 cm 2.00 kg 17,500.00 35,000.00 c Pelumas begisting (oli/minyak) 0.60 Ltr 12,500.00 7,500.00 d Besi beton polos 200.00 kg 13,950.00 2,790,000.00 e Kawat beton 3.00 kg 13,400.00 40,200.00 f Semen PC (abu-abu) 8.00 sak 54,000.00 432,000.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Pembantu tukang 4.50 org 50,000.00 225,000.00 j Tukang batu 0.35 org 87,500.00 30,625.00 k Tukang kayu 1.56 org 87,500.00 136,500.00 l Tukang besi 1.40 org 87,500.00 122,500.00 Jumlah 4,468,779.00
Dibulatkan 4,468,700.00 2 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 125 kg BESI + BEKISTING ) a Papan kayu terentang 0.40 m3 1,448,200.00 579,280.00 b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00 d Besi beton polos 125.00 kg 13,950.00 1,743,750.00 e Kawat beton 4.50 kg 13,400.00 60,300.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Balok kayu Borneo Super 0.30 m3 5,400,000.00 1,620,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00 k Pembantu tukang 7.30 org 50,000.00 365,000.00 l Tukang batu 0.35 org 87,500.00 30,625.00 m Tukang kayu 3.30 org 87,500.00 288,750.00 n Tukang besi 2.10 org 87,500.00 183,750.00 Jumlah 5,996,520.00 Dibulatkan 5,996,500.00 3 1 M3 MEMBUAT KOLOM BETON BERTULANG (150 kg BESI + BEKISTING) a Papan kayu terentang 0.40 m3 1,448,200.00 579,280.00 b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00 d Besi beton polos 150.00 kg 13,950.00 2,092,500.00 e Kawat beton 4.50 kg 13,400.00 60,300.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Balok kayu Borneo Super 0.30 m3 5,400,000.00 1,620,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00 k Pembantu tukang 7.30 org 50,000.00 365,000.00
l Tukang batu 0.35 org 87,500.00 30,625.00 m Tukang kayu 3.30 org 87,500.00 288,750.00 n Tukang besi 2.10 org 87,500.00 183,750.00 Jumlah 6,345,270.00 Dibulatkan 6,345,200.00 4 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 160 kg BESI + BEKISTING ) a Papan kayu terentang 0.40 m3 1,448,200.00 579,280.00 b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00 d Besi beton polos 160.00 kg 13,950.00 2,232,000.00 e Kawat beton 4.50 kg 13,400.00 60,300.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Balok kayu Borneo Super 0.30 m3 5,400,000.00 1,620,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00 k Pembantu tukang 7.30 org 50,000.00 365,000.00 l Tukang batu 0.35 org 87,500.00 30,625.00 m Tukang kayu 3.30 org 87,500.00 288,750.00 n Tukang besi 2.10 org 87,500.00 183,750.00 Jumlah 6,484,770.00 Dibulatkan 6,484,700.00 5 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 175 kg BESI + BEKISTING ) a Papan kayu terentang 0.40 m3 1,448,200.00 579,280.00 b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00 d Besi beton polos 175.00 kg 13,950.00 2,441,250.00 e Kawat beton 4.50 kg 13,400.00 60,300.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00
h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Balok kayu Borneo Super 0.30 m3 5,400,000.00 1,620,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00 k Pembantu tukang 7.30 org 50,000.00 365,000.00 l Tukang batu 0.35 org 87,500.00 30,625.00 m Tukang kayu 3.30 org 87,500.00 288,750.00 n Tukang besi 2.10 org 87,500.00 183,750.00 Jumlah 6,694,020.00 Dibulatkan 6,694,000.00 6 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 200 kg BESI + BEKISTING ) a Papan kayu terentang 0.40 m3 1,448,200.00 579,280.00 b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00 d Besi beton polos 200.00 kg 13,950.00 2,790,000.00 e Kawat beton 4.50 kg 13,400.00 60,300.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Balok kayu Borneo Super 0.30 m3 5,400,000.00 1,620,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00 k Pembantu tukang 7.30 org 50,000.00 365,000.00 l Tukang batu 0.35 org 87,500.00 30,625.00 m Tukang kayu 3.30 org 87,500.00 288,750.00 n Tukang besi 2.10 org 87,500.00 183,750.00 Jumlah 7,042,770.00 Dibulatkan 7,042,700.00 7 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 250 kg BESI + BEKISTING ) a Papan kayu terentang 0.40 m3 1,448,200.00 579,280.00 b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00
d Besi beton polos 250.00 kg 13,950.00 3,487,500.00 e Kawat beton 4.50 kg 13,400.00 60,300.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Balok kayu Borneo Super 0.30 m3 5,400,000.00 1,620,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00 k Pembantu tukang 7.30 org 50,000.00 365,000.00 l Tukang batu 0.35 org 87,500.00 30,625.00 m Tukang kayu 3.30 org 87,500.00 288,750.00 n Tukang besi 2.10 org 87,500.00 183,750.00 Jumlah 7,740,270.00 Dibulatkan 7,740,200.00 8 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 300 kg BESI + BEKISTING ) a Papan kayu terentang 0.40 m3 1,448,200.00 579,280.00 b Paku 5 - 12 cm 4.00 kg 17,500.00 70,000.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 12,500.00 25,000.00 d Besi beton polos 300.00 kg 13,950.00 4,185,000.00 e Kawat beton 4.50 kg 13,400.00 60,300.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Balok kayu Borneo Super 0.30 m3 5,400,000.00 1,620,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 120,950.00 423,325.00 k Pembantu tukang 7.30 org 50,000.00 365,000.00 l Tukang batu 0.35 org 87,500.00 30,625.00 m Tukang kayu 3.30 org 87,500.00 288,750.00 n Tukang besi 2.10 org 87,500.00 183,750.00 Jumlah 8,437,770.00 Dibulatkan 8,437,700.00
9 1 M3 MEMBUAT BALOK BETON BERTULANG ( 125 kg BESI + BEKISTING ) a Papan kayu terentang 0.32 m3 1,448,200.00 463,424.00 b Paku 5 - 12 cm 3.20 kg 17,500.00 56,000.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 12,500.00 20,000.00 d Besi beton polos 125.00 kg 13,950.00 1,743,750.00 e Kawat beton 2.25 kg 13,400.00 30,150.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Balok kayu Borneo Super 0.12 m3 5,400,000.00 648,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 120,950.00 338,660.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 32.00 btg 8,000.00 256,000.00 l Pembantu tukang 5.80 org 50,000.00 290,000.00 m Tukang batu 0.35 org 87,500.00 30,625.00 n Tukang kayu 2.80 org 87,500.00 245,000.00 o Tukang besi 1.05 org 87,500.00 91,875.00 Jumlah 4,820,224.00 Dibulatkan 4,820,200.00 10 1 M3 MEMBUAT BALOK BETON BERTULANG ( 150 kg BESI + BEKISTING ) a Papan kayu terentang 0.32 m3 1,448,200.00 463,424.00 b Paku 5 - 12 cm 3.20 kg 17,500.00 56,000.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 12,500.00 20,000.00 d Besi beton polos 150.00 kg 13,950.00 2,092,500.00 e Kawat beton 2.25 kg 10,000.00 22,500.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 10,000.00 7,800.00 i Balok kayu Borneo Super 0.12 m3 5,400,000.00 648,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 120,950.00 338,660.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 32.00 btg 8,000.00 256,000.00
l Pembantu tukang 5.80 org 50,000.00 290,000.00 m Tukang batu 0.35 org 87,500.00 30,625.00 n Tukang kayu 2.80 org 87,500.00 245,000.00 o Tukang besi 1.05 org 87,500.00 91,875.00 Jumlah 4,958,524.00 Dibulatkan 4,958,500.00 11 1 M3 MEMBUAT BALOK BETON BERTULANG ( 200 kg BESI + BEKISTING ) a Papan kayu terentang 0.32 m3 1,448,200.00 463,424.00 b Paku 5 - 12 cm 3.20 kg 17,500.00 56,000.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 12,500.00 20,000.00 d Besi beton polos 200.00 kg 13,950.00 2,790,000.00 e Kawat beton 3.00 kg 13,400.00 40,200.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 140,000.00 109200 i Balok kayu Borneo Super 0.14 m3 4,000,000.00 560,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 18,000.00 288,000.00 l Pembantu tukang 5.96 org 27,500.00 163,900.00 m Tukang batu 0.35 org 42,000.00 14,700.00 n Tukang kayu 2.80 org 42,000.00 117,600.00 o Tukang besi 1.40 org 42,000.00 58,800.00 Jumlah 5,371,964.00 Dibulatkan 5,371,900.00 12 1 M3 MEMBUAT BALOK BETON BERTULANG (200 kg BESI + BEKISTING) a Papan kayu terentang 0.32 m3 1,750,000.00 560,000.00 b Paku 5 - 12 cm 3.20 kg 17,500.00 56,000.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00 d Besi beton polos 225.00 kg 8,750.00 1,968,750.00 e Kawat beton 4.00 kg 15,000.00 60,000.00
f Semen PC (abu-abu) 6.45 sak 49,500.00 319,275.00 g Pasir beton 0.52 m3 140,000.00 72,800.00 h Split (batu pecah) 0.78 m3 140,000.00 109,200.00 i Balok kayu Borneo Super 0.14 m3 4,000,000.00 560,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 120,950.00 338,660.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 8,000.00 128,000.00 l Pembantu tukang 5.96 org 50,000.00 298,000.00 m Tukang batu 0.35 org 87,500.00 30,625.00 n Tukang kayu 2.80 org 87,500.00 245,000.00 o Tukang besi 1.40 org 87,500.00 122,500.00 Jumlah 4,884,810.00 Dibulatkan 4,884,800.00 13 1 M3 MEMBUAT BALOK BETON BERTULANG ( 250 kg BESI + BEKISTING ) a Papan kayu terentang 0.32 m3 1,448,200.00 463,424.00 b Paku 5 - 12 cm 3.20 kg 17,500.00 56,000.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 12,500.00 20,000.00 d Besi beton polos 250.00 kg 13,950.00 3,487,500.00 e Kawat beton 6.00 kg 13,400.00 80,400.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Balok kayu Borneo Super 0.14 m3 5,400,000.00 756,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 120,950.00 338,660.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 8,000.00 128,000.00 l Pembantu tukang 5.96 org 50,000.00 298,000.00 m Tukang batu 0.35 org 87,500.00 30,625.00 n Tukang kayu 2.80 org 87,500.00 245,000.00 o Tukang besi 1.40 org 87,500.00 122,500.00 Jumlah 6,632,849.00 Dibulatkan 6,632,800.00
14 1 M3 MEMBUAT TANGGA BETON BERTULANG ( 200 kg BESI + BEKISTING ) a Papan kayu terentang 0.25 m3 1,448,200.00 362,050.00 b Paku 5 - 12 cm 3.00 kg 17,500.00 52,500.00 c Pelumas begisting (oli/minyak) 1.20 Ltr 12,500.00 15,000.00 d Besi beton polos 200.00 kg 13,950.00 2,790,000.00 e Kawat beton 3.00 kg 13,400.00 40,200.00 f Semen PC (abu-abu) 6.45 sak 54,000.00 348,300.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Balok kayu Borneo Super 0.30 m3 5,400,000.00 1,620,000.00 j Multiplex 120 x 240 x 9 mm 2.50 lbr 120,950.00 302,375.00 k Pembantu tukang 5.60 org 50,000.00 280,000.00 l Tukang batu 0.35 org 87,500.00 30,625.00 m Tukang kayu 2.30 org 87,500.00 201,250.00 n Tukang besi 1.40 org 87,500.00 122,500.00 Jumlah 6,423,240.00 Dibulatkan 6,423,200.00 15 1 M3 MEMBUAT PLAT LANTAI Tb. 10 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING ) a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 761,800.00 761,800.00 b Pasang Bekisting untuk lantai 10.00 m2 370,600.00 3,706,000.00 c Besi Beton rakit 100.00 kg 13,950.00 1,395,000.00 Jumlah 5,862,800.00 Dibulatkan 5,862,800.00 16 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING ) a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 761,800.00 761,800.00 b Pasang Bekisting untuk lantai 8.33 m2 370,600.00 3,087,098.00 c Besi Beton rakit 115.00 kg 16,200.00 1,863,000.00 Jumlah 5,711,898.00 Dibulatkan 5,711,800.00 17 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 125 kg BESI + BEKISTING )
a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 761,800.00 761,800.00 b Pasang Bekisting untuk lantai 8.33 m2 370,600.00 3,087,098.00 c Besi Beton rakit 125.00 kg 16,200.00 2,025,000.00 Jumlah 5,873,898.00 Dibulatkan 5,873,800.00 18 1 M3 MEMBUAT PLAT LANTAI Tb. 15 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING ) a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 761,800.00 761,800.00 b Pasang Bekisting untuk lantai 6.67 m2 370,600.00 2,471,902.00 c Besi Beton rakit 100.00 kg 16,200.00 1,620,000.00 Jumlah 4,853,702.00 Dibulatkan 4,853,700.00 19 1 M3 MEMBUAT PLAT LANTAI Tb. 20 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING ) a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 761,800.00 761,800.00 b Pasang Bekisting untuk lantai 7.50 m2 370,600.00 2,779,500.00 c Besi Beton rakit 115.00 kg 16,200.00 1,863,000.00 Jumlah 5,404,300.00 Dibulatkan 5,404,300.00 20 1M3 MEMBUAT RING BALK BETON BERTULANG ( 175 kg BESI + BEKISTING ) K225 a Papan kayu terentang 0.27 m3 1,448,200.00 391,014.00 b Paku 5 - 12 cm 2.00 kg 17,500.00 35,000.00 c Pelumas begisting (oli/minyak) 0.60 Ltr 12,500.00 7,500.00 d Besi beton polos 175.00 kg 13,950.00 2,441,250.00 e Kawat beton 3.00 kg 13,400.00 40,200.00 f Semen PC (abu-abu) 8.00 sak 54,000.00 432,000.00 g Pasir beton 0.52 m3 92,000.00 47,840.00 h Split (batu pecah) 0.78 m3 270,000.00 210,600.00 i Pembantu tukang 4.85 org 50,000.00 242,500.00 j Tukang batu 0.40 org 87,500.00 35,000.00 k Tukang kayu 1.75 org 87,500.00 153,125.00 l Tukang besi 1.45 org 87,500.00 126,875.00
Jumlah 4,162,904.00 Dibulatkan 4,162,900.00
V PEKERJAAN DINDING 1 1 M2 PASANGAN Bata merah TEBAL 1 BATA, CAMPURAN 1 Pc : 3 Ps a Bata merah 140.00 bh 650.00 91,000.00 b Semen PC (abu-abu) 0.65 sak 54,000.00 35,100.00 c Pasir pasang 0.09 m3 84,000.00 7,560.00 d Pembantu tukang 0.65 org 50,000.00 32,500.00 e Tukang batu 0.20 org 87,500.00 17,500.00 Jumlah 183,660.00 Dibulatkan 183,600.00 2 1 M2 PASANGAN Bata merah TEBAL 1 BATA, CAMPURAN 1 Pc : 4 Ps a Bata merah 140.00 bh 650.00 91,000.00 b Semen PC (abu-abu) 0.55 sak 54,000.00 29,700.00 c Pasir pasang 0.09 m3 84,000.00 7,560.00 d Pembantu tukang 0.65 org 50,000.00 32,500.00 e Tukang batu 0.20 org 87,500.00 17,500.00 Jumlah 178,260.00 Dibulatkan 178,200.00 3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, CAMPURAN 1 Pc : 5 Ps a Bata merah 140.00 bh 650.00 91,000.00 b Semen PC (abu-abu) 0.45 sak 54,000.00 24,300.00 c Pasir pasang 0.10 m3 84,000.00 8,400.00 d Pembantu tukang 0.65 org 50,000.00 32,500.00 e Tukang batu 0.20 org 87,500.00 17,500.00 Jumlah 173,700.00 Dibulatkan 173,700.00 4 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 3 Ps
a Bata merah 70.00 bh 650.00 45,500.00 b Semen PC (abu-abu) 0.29 sak 54,000.00 15,660.00 c Pasir pasang 0.04 m3 84,000.00 3,360.00 d Pembantu tukang 0.32 org 50,000.00 16,000.00 e Tukang batu 0.10 org 87,500.00 8,750.00 Jumlah 89,270.00 Dibulatkan 89,200.00 5 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 4 Ps a Bata merah 70.00 bh 650.00 45,500.00 b Semen PC (abu-abu) 0.25 sak 54,000.00 13,500.00 c Pasir pasang 0.05 m3 84,000.00 4,200.00 d Pembantu tukang 0.32 org 50,000.00 16,000.00 e Tukang batu 0.10 org 87,500.00 8,750.00 Jumlah 87,950.00 Dibulatkan 87,900.00 6 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 5 Ps a Bata merah 70.00 bh 650.00 45,500.00 b Semen PC (abu-abu) 0.22 sak 54,000.00 11,880.00 c Pasir pasang 0.05 m3 84,000.00 4,200.00 d Pembantu tukang 0.32 org 50,000.00 16,000.00 e Tukang batu 0.10 org 87,500.00 8,750.00 Jumlah 86,330.00 Dibulatkan 86,300.00 7 1 M2 PASANG DINDING BATA ROOSTER / BATA TERAWANG a Rooster / Terawang ukuran 12 x 11 x 24 37.00 bh 4,200.00 155,400.00 b Semen PC (abu-abu) 0.27 sak 54,000.00 14,580.00 c Pasir pasang 0.04 m3 84,000.00 3,360.00 d Pembantu tukang 0.30 org 50,000.00 15,000.00 e Tukang batu 0.10 org 87,500.00 8,750.00 Jumlah 197,090.00
Dibulatkan 197,000.00 8 1 M2 PASANG DINDING GLASSBLOCK a Glassblock ukuran 18 x 18 cm 30.00 bh 21,500.00 645,000.00 b Semen putih 0.27 sak 12,700.00 3,429.00 c Pembantu tukang 0.30 org 50,000.00 15,000.00 d Tukang batu 0.10 org 87,500.00 8,750.00 Jumlah 672,179.00 Dibulatkan 672,100.00 9 1 M2 PASANGAN BATACO PUTIH, CAMPURAN 1 Pc : 5 Ps a Bataco putih 15.00 bh 4,000.00 60,000.00 b Semen PC (abu-abu) 0.25 sak 54,000.00 13,500.00 c Pasir pasang 0.03 m3 84,000.00 2,520.00 d Pembantu tukang 0.30 org 50,000.00 15,000.00 e Tukang batu 0.15 org 87,500.00 13,125.00 Jumlah 104,145.00 Dibulatkan 104,100.00 10 1 M2 PASANGAN BATACO PRES SEMEN, CAMPURAN 1 Pc : 5 Ps a Bataco press semen 15.00 bh 4,200.00 63,000.00 b Semen PC (abu-abu) 0.20 sak 54,000.00 10,800.00 c Pasir pasang 0.02 m3 84,000.00 1,680.00 d Pembantu tukang 0.30 org 50,000.00 15,000.00 e Tukang batu 0.15 org 87,500.00 13,125.00 Jumlah 103,605.00 Dibulatkan 103,600.00 11 1 M2 PASANGAN BATA RINGAN ( HEBEL/CELCON ). a Bata Ringan ( hebel/celcon ) 8.00 bh 3,500.00 28,000.00 b Semen Instan 11.45 kg 2,450.00 28,052.50 c Pembantu tukang 0.30 org 50,000.00 15,000.00 d Tukang batu 0.20 org 87,500.00 17,500.00 Jumlah 88,552.50
Dibulatkan 88,500.00
VI PEKERJAAN PLESTERAN/ACCI 1 1 M2 PLESTERAN CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm a Semen PC (abu-abu) 0.14 sak 54,000.00 7,560.00 b Pasir pasang 0.02 m3 84,000.00 1,680.00 c Pembantu tukang 0.20 org 50,000.00 10,000.00 d Tukang batu 0.15 org 87,500.00 13,125.00 Jumlah 32,365.00 Dibulatkan 32,300.00 2 1 M2 PLESTERAN CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm a Semen PC (abu-abu) 0.13 sak 54,000.00 7,020.00 b Pasir pasang 0.02 m3 84,000.00 1,680.00 c Pembantu tukang 0.20 org 50,000.00 10,000.00 d Tukang batu 0.15 org 87,500.00 13,125.00 Jumlah 31,825.00 Dibulatkan 31,800.00 3 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 1,5 cm a Semen PC (abu-abu) 0.10 sak 54,000.00 5,400.00 b Pasir pasang 0.02 m3 84,000.00 1,680.00 c Pembantu tukang 0.20 org 50,000.00 10,000.00 d Tukang batu 0.15 org 87,500.00 13,125.00 Jumlah 30,205.00 Dibulatkan 30,200.00 4 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm a Semen PC (abu-abu) 0.09 sak 54,000.00 4,860.00 b Pasir pasang 0.02 m3 84,000.00 1,680.00 c Pembantu tukang 0.20 org 50,000.00 10,000.00 d Tukang batu 0.15 org 87,500.00 13,125.00
Jumlah 29,665.00 Dibulatkan 29,600.00 5 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 2,0 cm a Semen PC (abu-abu) 0.17 sak 54,000.00 9,180.00 b Pasir pasang 0.03 m3 84,000.00 2,520.00 c Pembantu tukang 0.22 org 50,000.00 11,000.00 d Tukang batu 0.16 org 87,500.00 14,000.00 Jumlah 36,700.00 Dibulatkan 36,700.00 6 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 2,0 cm a Semen PC (abu-abu) 0.15 sak 54,000.00 8,100.00 b Pasir pasang 0.03 m3 84,000.00 2,520.00 c Pembantu tukang 0.25 org 50,000.00 12,500.00 d Tukang batu 0.20 org 87,500.00 17,500.00 Jumlah 40,620.00 Dibulatkan 40,600.00 7 1 M2 BERAPEN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm a Semen PC (abu-abu) 0.11 sak 54,000.00 5,940.00 b Pasir pasang 0.03 m3 84,000.00 2,100.00 c Pembantu tukang 0.15 org 50,000.00 7,500.00 d Tukang batu 0.07 org 87,500.00 6,125.00 Jumlah 21,665.00 Dibulatkan 21,600.00 8 1 M2 PLESTERAN BETON CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm a Semen PC (abu-abu) 0.19 sak 54,000.00 10,260.00 b Pasir pasang 0.02 m3 84,000.00 1,680.00 c Pembantu tukang 0.26 org 50,000.00 13,000.00 d Tukang batu 0.20 org 87,500.00 17,500.00 Jumlah 42,440.00 Dibulatkan 42,400.00
9 1 M2 PLESTERAN BETON CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm a Semen PC (abu-abu) 0.15 sak 54,000.00 8,100.00 b Pasir pasang 0.02 m3 84,000.00 1,680.00 c Pembantu tukang 0.26 org 50,000.00 13,000.00 d Tukang batu 0.20 org 87,500.00 17,500.00 Jumlah 40,280.00 Dibulatkan 40,200.00 10 1 M2 PLESTERAN SKONENG CAMPURAN 1 Pc : 2 Ps a Semen PC (abu-abu) 0.01 sak 54,000.00 540.00 b Pasir pasang 0.01 m3 84,000.00 840.00 c Pembantu tukang 0.06 org 50,000.00 3,000.00 d Tukang batu 0.04 org 87,500.00 3,500.00 Jumlah 7,880.00 Dibulatkan 7,800.00 11 1 M2 ACCIAN PLESTERAN a Semen PC (abu-abu) 0.08 sak 54,000.00 4,320.00 b Pembantu tukang 0.14 org 50,000.00 7,000.00 c Tukang batu 0.11 org 87,500.00 9,625.00 Jumlah 20,945.00 Dibulatkan 20,900.00 12 1 M2 PLESTERAN SIAR CAMPURAN 1 Pc : 2 Ps a Semen PC (abu-abu) 0.09 sak 54,000.00 4,860.00 b Pasir pasang 0.02 m3 84,000.00 1,680.00 c Pembantu tukang 0.15 org 50,000.00 7,500.00 d Tukang batu 0.07 org 87,500.00 6,125.00 Jumlah 20,165.00 Dibulatkan 20,100.00
VII PEKERJAAN PELAPIS LANTAI
1 1 M2 PASANG LANTAI KERAMIK UKURAN 40 x 40 cm POLISHED a Keramik ukuran 40 x 40 cm 1.00 m2 225,000.00 225,000.00 b Semen PC (abu-abu) 0.16 sak 54,000.00 8,640.00 c Pasir pasang 0.02 m3 84,000.00 1,806.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.25 org 50,000.00 12,500.00 f Tukang batu 0.12 org 87,500.00 10,500.00 Jumlah 258,700.00 Dibulatkan 258,700.00 2 1 M2 PASANG LANTAI KERAMIK UKURAN 40 x 40 cm UNPOLISH a Keramik ukuran 40 x 40 cm 1.00 m2 202,000.00 202,000.00 b Semen PC (abu-abu) 0.16 sak 54,000.00 8,640.00 c Pasir pasang 0.02 m3 84,000.00 1,680.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.26 org 50,000.00 13,000.00 f Tukang batu 0.13 org 87,500.00 10,937.50 Jumlah 236,511.50 Dibulatkan 236,510.00 3 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 60 cm a Keramik ukuran 60 x 60 cm 1.00 m2 298,000.00 298,000.00 b Semen PC (abu-abu) 0.18 sak 54,000.00 9,720.00 c Pasir pasang 0.02 m3 84,000.00 1,806.00 d Semen warna 0.01 kg 12,700.00 165.10 e Pembantu tukang 0.25 org 50,000.00 12,500.00 f Tukang batu 0.12 org 87,500.00 10,500.00 Jumlah 332,691.10 Dibulatkan 332,690.00 4 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 90 cm a Keramik ukuran 60 x 90 cm 1.00 m2 340,000.00 340,000.00 b Semen PC (abu-abu) 0.17 sak 54,000.00 9,180.00
c Pasir pasang 0.02 m3 84,000.00 1,806.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.26 org 50,000.00 13,000.00 f Tukang batu 0.14 org 87,500.00 12,250.00 Jumlah 376,490.00 Dibulatkan 376,490.00 5 1 M2 PASANG LANTAI KERAMIK 10 x 20 cm a Keramik lantai 10 x 20 cm 1.00 m2 34,000.00 34,000.00 b Semen PC ( abu-abu ) 0.18 sak 54,000.00 9,720.00 c Pasir pasang 0.02 m3 84,000.00 1,680.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.22 org 50,000.00 11,000.00 f Tukang batu 0.40 org 87,500.00 35,000.00 Jumlah 91,654.00 Dibulatkan 91,650.00 6 1 M2 PASANG LANTAI KERAMIK POLOS 20 x 20 cm a Keramik polos 20 x 20 cm 1.00 m2 37,000.00 37,000.00 b Semen PC (abu-abu) 0.17 sak 54,000.00 9,180.00 c Pasir pasang 0.02 m3 84,000.00 1,806.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.30 org 50,000.00 15,000.00 f Tukang batu 0.15 org 87,500.00 13,125.00 Jumlah 76,365.00 Dibulatkan 76,360.00 7 1 M2 PASANG LANTAI KERAMIK MOTIF 20 x 20 cm a Keramik motif 20 x 20 cm 1.00 m2 39,000.00 39,000.00 b Semen PC (abu-abu) 0.17 sak 54,000.00 9,180.00 c Pasir pasang 0.02 m3 84,000.00 1,806.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.30 org 50,000.00 15,000.00
f Tukang batu 0.15 org 87,500.00 13,125.00 Jumlah 78,365.00 Dibulatkan 78,360.00 8 1 M2 PASANG LANTAI KERAMIK POLOS 30 x 30 cm a Keramik polos 30 x 30 cm 1.00 m2 39,000.00 39,000.00 b Semen PC (abu-abu) 0.16 sak 54,000.00 8,640.00 c Pasir pasang 0.02 m3 84,000.00 1,680.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.25 org 50,000.00 12,500.00 f Tukang batu 0.12 org 87,500.00 10,500.00 Jumlah 72,574.00 Dibulatkan 72,570.00 9 1 M2 PASANG LANTAI KERAMIK MOTIF 30 x 30 cm a Keramik motif 30 x 30 cm 1.00 m2 43,000.00 43,000.00 b Semen PC (abu-abu) 0.16 sak 54,000.00 8,640.00 c Pasir pasang 0.02 m3 84,000.00 1,680.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.25 org 50,000.00 12,500.00 f Tukang batu 0.12 org 87,500.00 10,500.00 Jumlah 76,574.00 Dibulatkan 76,570.00 10 1 M2 PASANG LANTAI MARMER a marmer standar 1.00 m2 212,000.00 212,000.00 b Semen PC (abu-abu) 0.48 sak 54,000.00 25,920.00 c Pasir pasang 0.10 m3 84,000.00 8,400.00 d Semen warna 0.20 sak 12,700.00 2,540.00 e Pembantu tukang 0.62 org 50,000.00 31,000.00 f Tukang batu 0.35 org 87,500.00 30,625.00 Jumlah 310,485.00 Dibulatkan 310,480.00
11 1 M2 PASANG LANTAI PARQUET JATI a Parquet jati 1.05 m2 276,000.00 289,800.00 b Lem vinyl 0.60 kg 32,000.00 19,200.00 c Pembantu tukang 0.65 org 50,000.00 32,500.00 d Tukang 0.35 org 87,500.00 30,625.00 Jumlah 372,125.00 Dibulatkan 372,120.00 12 1 M2 PASANG LANTAI GRANIT a Granit standar 1.00 m2 750,000.00 750,000.00 b Semen PC (abu-abu) 0.48 sak 54,000.00 25,920.00 c Pasir pasang 0.08 m3 84,000.00 6,720.00 d Semen warna 0.10 sak 12,700.00 1,270.00 e Pembantu tukang 0.60 org 50,000.00 30,000.00 f Tukang batu 0.48 org 87,500.00 42,000.00 Jumlah 855,910.00 Dibulatkan 855,910.00
VIII PEKERJAAN PELAPIS DINDING 1 1 M2 PASANG DINDING KERAMIK MOTIF 10 x 20 cm a Keramik motif 10 x 20 cm 1.00 m2 38,000.00 38,000.00 b Semen PC ( abu-abu ) 0.18 sak 54,000.00 9,720.00 c Pasir pasang 0.02 m3 84,000.00 1,680.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.22 org 50,000.00 11,000.00 f Tukang batu 0.40 org 87,500.00 35,000.00 Jumlah 95,654.00 Dibulatkan 95,650.00 2 1 M2 PASANG DINDING KERAMIK POLOS 10 x 20 cm
a Keramik polos 10 x 20 cm 1.00 m2 36,000.00 36,000.00 b Semen PC ( abu-abu ) 0.18 sak 54,000.00 9,720.00 c Pasir pasang 0.02 m3 84,000.00 1,680.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.22 org 50,000.00 11,000.00 f Tukang batu 0.40 org 87,500.00 35,000.00 Jumlah 93,654.00 Dibulatkan 93,650.00 3 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 20 cm a Keramik motif 20 x 20 cm 1.00 m2 39,000.00 39,000.00 b Semen PC ( abu-abu ) 0.17 sak 54,000.00 9,180.00 c Pasir pasang 0.02 m3 84,000.00 1,680.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.20 org 50,000.00 10,000.00 f Tukang batu 0.39 org 87,500.00 34,125.00 Jumlah 94,239.00 Dibulatkan 94,230.00 4 1 M2 PASANG DINDING KERAMIK POLOS 20 x 20 cm a Keramik polos 20 x 20 cm 1.00 m2 37,000.00 37,000.00 b Semen PC ( abu-abu ) 0.17 sak 54,000.00 9,180.00 c Pasir pasang 0.02 m3 84,000.00 1,680.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.20 org 50,000.00 10,000.00 f Tukang batu 0.39 org 87,500.00 34,125.00 Jumlah 92,239.00 Dibulatkan 92,230.00 5 1 M2 PASANG DINDING KERAMIK POLOS 20 x 25 cm a Keramik polos 20 x 25 cm 1.00 m2 38,000.00 38,000.00 b Semen PC ( abu-abu ) 0.16 sak 54,000.00 8,640.00 c Pasir pasang 0.02 m3 84,000.00 1,512.00
d Semen warna 0.01 kg 12,700.00 165.10 e Pembantu tukang 0.19 org 50,000.00 9,375.00 f Tukang batu 0.38 org 87,500.00 32,812.50 Jumlah 90,504.60 Dibulatkan 90,500.00 6 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 25 cm a Keramik motif 20 x 25 cm 1.00 m2 39,000.00 39,000.00 b Semen PC ( abu-abu ) 0.16 sak 54,000.00 8,640.00 c Pasir pasang 0.02 m3 84,000.00 1,512.00 d Semen warna 0.01 kg 12,700.00 165.10 e Pembantu tukang 0.19 org 50,000.00 9,375.00 f Tukang batu 0.38 org 87,500.00 32,812.50 Jumlah 91,504.60 Dibulatkan 91,500.00 7 1 M2 PASANG DINDING MARMER a Marmer standar 1.00 m2 212,000.00 212,000.00 b Paku sekrup 4.00 bh 600.00 2,400.00 c Semen PC ( abu-abu ) 0.25 sak 54,000.00 13,500.00 d Pasir pasang 0.03 m3 84,000.00 2,100.00 e Semen warna 1.50 kg 12,700.00 19,050.00 f Kawat ikat 0.03 kg 13,400.00 335.00 g Paku 0.03 kg 17,500.00 437.50 h Pembantu tukang 0.72 org 50,000.00 36,000.00 i Tukang batu 0.65 org 87,500.00 56,875.00 Jumlah 342,697.50 Dibulatkan 342,690.00 8 1 M2 PASANG DINDING GRANIT a Granit standar 1.00 m2 750,000.00 750,000.00 b Paku sekrup 2.00 bh 600.00 1,200.00 c Semen PC ( abu-abu ) 0.25 sak 54,000.00 13,500.00
d Pasir pasang 0.03 m3 84,000.00 2,100.00 e Semen warna 1.50 kg 12,700.00 19,050.00 f Kawat ikat 0.03 kg 13,400.00 335.00 g Paku 0.03 kg 17,500.00 437.50 h Pembantu tukang 0.72 org 50,000.00 36,000.00 i Tukang batu 0.65 org 87,500.00 56,875.00 Jumlah 879,497.50 Dibulatkan 879,490.00 9 1 M2 PASANG DINDING BATU TEMPEL HITAM a Batu tempel hitam 1.00 m2 108,200.00 108,200.00 b Semen PC ( abu-abu ) 0.24 sak 54,000.00 12,960.00 c Pasir pasang 0.04 m3 84,000.00 2,940.00 d Pembantu tukang 0.32 org 50,000.00 16,000.00 e Tukang batu 0.25 org 87,500.00 21,875.00 Jumlah 161,975.00 Dibulatkan 161,970.00 10 1 M2 PASANG DINDING BATU ALAM a Batu alam 1.00 m2 157,900.00 157,900.00 b Semen PC ( abu-abu ) 0.25 sak 54,000.00 13,500.00 c Pasir pasang 0.04 m3 84,000.00 2,940.00 d Pembantu tukang 0.32 org 50,000.00 16,000.00 e Tukang batu 0.25 org 87,500.00 21,875.00 Jumlah 212,215.00 Dibulatkan 212,210.00 11 1 M¹ PASANG PLINT KERAMIK UKURAN 10 x 40 cm a Plint Keramik ukuran 10 x 40 cm 2.65 bh 10,000.00 26,500.00 b Semen PC (abu-abu) 0.02 sak 54,000.00 1,080.00 c Pasir pasang 0.01 m3 84,000.00 840.00 d Semen warna 0.10 kg 12,700.00 1,270.00 e Pembantu tukang 0.06 org 50,000.00 3,000.00
f Tukang batu 0.03 org 87,500.00 2,625.00 Jumlah 35,315.00 Dibulatkan 35,310.00 12 1 m¹ PASANG PLINT KERAMIK UKURAN 10 x 30 cm a Plint Keramik ukuran 10 x 30 cm 3.30 bh 8,000.00 26,400.00 b Semen PC (abu-abu) 0.02 sak 54,000.00 1,080.00 c Pasir pasang 0.01 m3 84,000.00 840.00 d Semen warna 0.12 kg 12,700.00 1,524.00 e Pembantu tukang 0.06 org 50,000.00 3,000.00 f Tukang batu 0.03 org 87,500.00 2,625.00 Jumlah 35,469.00 Dibulatkan 35,460.00
IX PEKERJAAN KUSEN, PINTU, JENDELA, PARTISI 1 1 M3 PASANG KUSEN PINTU & JENDELA KAYU KAMPER SAMARINDA a Balok kayu kamper samarinda 1.20 m3 9,670,000.00 11,604,000.00 b Pembantu tukang 6.00 org 50,000.00 300,000.00 c Tukang kayu 15.00 org 87,500.00 1,312,500.00 Jumlah 13,216,500.00 Dibulatkan 13,216,500.00 2 1 M3 PASANG KUSEN PINTU & JENDELA KAYU KAMPER MEDAN / KRUING a Balok kayu kamper medan 1.20 m3 6,550,000.00 7,860,000.00 b Pembantu tukang 6.00 org 50,000.00 300,000.00 c Tukang kayu 15.00 org 87,500.00 1,312,500.00 Jumlah 9,472,500.00 Dibulatkan 9,472,500.00 3 1 M3 PASANG KUSEN PINTU & JENDELA KAYU BORNEO SUPER a Kayu balok borneo super 1.20 m3 5,400,000.00 6,480,000.00
b Pembantu tukang 6.00 org 50,000.00 300,000.00 c Tukang kayu 15.00 org 87,500.00 1,312,500.00 Jumlah 8,092,500.00 Dibulatkan 8,092,500.00 4 1 M2 PASANG PINTU PANEL KAYU KAMPER SAMARINDA a Papan kayu kamper samarinda 0.04 m3 9,980,000.00 399,200.00 b Pembantu tukang 1.00 org 50,000.00 50,000.00 c Tukang kayu 2.50 org 87,500.00 218,750.00 Jumlah 667,950.00 Dibulatkan 667,950.00 5 1 M2 PASANG PINTU PANEL KAYU KAMPER MEDAN / KRUING a Papan kayu kamper medan 0.04 m3 6,750,000.00 270,000.00 b Pembantu tukang 1.00 org 50,000.00 50,000.00 c Tukang kayu 2.50 org 87,500.00 218,750.00 Jumlah 538,750.00 Dibulatkan 538,750.00 6 1 M2 PASANG PINTU DAN JENDELA KACA KAYU KAMPER MEDAN a Papan kayu kamper medan 0.04 m3 6,750,000.00 245,000.00 b Pembantu tukang 0.80 org 50,000.00 91,875.00 c Tukang kayu 2.00 org 87,500.00 245,000.00 Jumlah 581,875.00 Dibulatkan 581,800.00 7 1 M2 PASANG PINTU DAN JENDELA KACA KAYU BORNEO a Papan kayu borneo super 0.04 m3 5,660,000.00 56,000.00 b Pembantu tukang 0.80 org 50,000.00 20,000.00 c Tukang kayu 2.00 org 87,500.00 175,000.00 Jumlah 251,000.00 Dibulatkan 251,000.00 8 1 M2 PASANG PINTU DAN JENDELA JALUSI KAYU KAMPER MEDAN a Papan kayu Kamper Medan 0.06 m3 6,750,000.00 432,000.00
b Pembantu tukang 1.00 org 50,000.00 50,000.00 c Tukang kayu 3.00 org 87,500.00 262,500.00 Jumlah 744,500.00 Dibulatkan 744,500.00 9 1 M2 PASANG PINTU TRIPLEK RANGKAP , RANGKA KAYU KAMPER MEDAN a Papan kayu kamper medan 0.02 m3 6,750,000.00 132,300.00 b Paku 1 s/d 5 cm 0.03 kg 17,500.00 525.00 c Lem Kayu 0.30 Ltr 27,000.00 8,100.00 d Triplek 0,4 cm ukuran pintu 1.00 lbr 42,000.00 42,000.00 e Pembantu tukang 0.60 org 50,000.00 30,000.00 f Tukang kayu 2.00 org 87,500.00 175,000.00 Jumlah 387,925.00 Dibulatkan 387,900.00 10 1 M2 PASANG JALUSI MATI KUSEN KAYU KAMPER MEDAN a Papan kayu kamper medan 0.06 m3 6,750,000.00 405,000.00 b Paku 1 s/d 5 cm 0.15 kg 17,500.00 2,625.00 c Pembantu tukang 0.50 org 50,000.00 25,000.00 d Tukang kayu 2.00 org 87,500.00 175,000.00 Jumlah 607,625.00 Dibulatkan 607,600.00 11 1 M2 PASANG PINTU TRIPLEK RANGKAP , RANGKA KAYU BORNEO SUPER a Papan kayu borneo super 0.02 m3 5,660,000.00 110,936.00 b Paku 1 s/d 5 cm 0.03 kg 17,500.00 525.00 c Lem kayu 0.30 Ltr 27,000.00 8,100.00 d Triplek 0,4 cm ukuran pintu 1.00 lbr 42,000.00 42,000.00 e Pembantu tukang 0.60 org 50,000.00 30,000.00 f Tukang kayu 2.00 org 87,500.00 175,000.00 Jumlah 366,561.00 Dibulatkan 366,500.00 12 1 M2 PASANG PINTU TEAKWOOD RANGKAP , RANGKA KAYU KAMPER MEDAN
a Papan kayu Kamper Medan 0.02 m3 6,750,000.00 132,300.00 b Paku 1 s/d 5 cm 0.30 kg 17,500.00 5,250.00 c Lem Kayu 0.30 Ltr 27,000.00 8,100.00 d Teakwood 120 x 240 x 0,4 cm 1.00 lbr 82,000.00 82,000.00 e Pembantu tukang 0.60 org 50,000.00 30,000.00 f Tukang kayu 2.00 org 87,500.00 175,000.00 Jumlah 432,650.00 Dibulatkan 432,600.00 13 1 M2 PASANG PINTU TRIPLEK & FORMIKA RANGKA KAYU KAMPER MEDAN a Papan kayu kamper medan 0.02 m3 6,750,000.00 132,300.00 b Paku 1 s/d 5 cm 0.30 kg 17,500.00 5,250.00 c Lem kayu 0.80 Ltr 27,000.00 21,600.00 d Triplek 0,4 cm ukuran pintu 1.00 lbr 42,000.00 42,000.00 e Formica 3" x 6" 0.50 lbr 166,700.00 83,350.00 f Pembantu tukang 0.80 org 50,000.00 40,000.00 g Tukang kayu 2.50 org 87,500.00 218,750.00 Jumlah 543,250.00 Dibulatkan 543,200.00 14 1 M2 PASANG PINTU TEAKWOOD & FORMIKA RANGKA KAYU KAMPER MEDAN a Papan kayu kamper medan 0.02 m3 6,750,000.00 132,300.00 b Paku 1 s/d 5 cm 0.30 kg 17,500.00 5,250.00 c Lem Kayu 0.80 Ltr 27,000.00 21,600.00 d Teakwood 120 x 240 x 0,4 cm 0.50 lbr 82,000.00 41,000.00 e Vernis 0.50 Ltr 50,000.00 25,000.00 a Formica 4" x 8" 0.50 lbr 166,700.00 83,350.00 b Pembantu tukang 0.80 org 50,000.00 40,000.00 c Tukang kayu 2.50 org 87,500.00 218,750.00 Jumlah 567,250.00 Dibulatkan 567,200.00 15 1 M2 PASANG DINDING PEMISAH DOUBLE TEAKWOOD, RANGKA KAYU KAMPER MEDAN
a Balok kayu Kamper Medan 0.02 m3 6,550,000.00 127,725.00 b Papan kayu Kamper Medan 0.01 m3 6,750,000.00 47,250.00 c Paku 5 - 12 cm 0.10 kg 17,500.00 1,750.00 d Lem Kayu 0.56 Ltr 27,000.00 15,120.00 e Teakwood 120 x 240 x 0,4 cm 1.00 lbr 82,000.00 82,000.00 f Pembantu tukang 0.15 org 50,000.00 7,500.00 g Tukang kayu 0.45 org 87,500.00 39,375.00 Jumlah 320,720.00 Dibulatkan 320,700.00 16 1 M2 PASANG DINDING PEMISAH DOUBLE GRC, RANGKA KAYU KAMPER MEDAN a Balok kayu Kamper Medan 0.02 m3 6,550,000.00 127,725.00 b Papan kayu Kamper Medan 0.01 m3 6,750,000.00 47,250.00 c Paku 5 - 12 cm 0.10 kg 17,500.00 1,750.00 d Lem Kayu 0.56 Ltr 27,000.00 15,120.00 e Triplek 0,4 cm ukuran pintu 1.00 lbr 42,000.00 42,000.00 f Pembantu tukang 0.20 org 50,000.00 10,000.00 g Tukang kayu 0.60 org 87,500.00 52,500.00 Jumlah 296,345.00 Dibulatkan 296,300.00 17 1 BH PASANG PINTU ALUMINIUM / PINTU PVC a Pintu Aluminium / Pintu PVC 1.00 bh 400,000.00 400,000.00 b Alat bantu 10 % harga material 1.00 ls 40,000.00 40,000.00 c Tukang kayu 0.02 org 87,500.00 1,837.50 Jumlah 441,837.50 Dibulatkan 441,800.00 18 1 M2 PASANG KUSEN PARTISI DOUBLE TRIPLEK a Balok kayu borneo super 0.11 m3 5,400,000.00 567,000.00 b Triplek 0,4 cm ukuran pintu 5.00 lbr 42,000.00 210,000.00 c Paku 1 s/d 3 cm 2.00 kg 17,500.00 35,000.00 d Ampelas 2.00 lbr 2,500.00 5,000.00
e Engsel 4.00 bh 25,000.00 100,000.00 f Grendel / slot 4.00 bh 33,000.00 132,000.00 g Pembantu tukang 0.30 org 50,000.00 15,000.00 h Tukang kayu terampil 1.30 org 87,500.00 113,750.00 Jumlah 1,177,750.00 Dibulatkan 129,530.00 19 1 M2 PASANG KUSEN PARTISI DOUBLE GYPSUM + RANGKA KAYU a Balok kayu borneo super 0.11 m3 5,400,000.00 567,000.00 b Gypsum board ( 120 x 240 x 9 ) mm 0.72 lbr 86,000.00 61,920.00 c Paku 1 s/d 3 cm 2.00 kg 17,500.00 35,000.00 d Ampelas 2.00 lbr 2,500.00 5,000.00 e Engsel 4.00 bh 25,000.00 100,000.00 f Grendel / Slot 4.00 bh 33,000.00 132,000.00 g Pembantu tukang 0.30 org 50,000.00 15,000.00 h Tukang kayu 1.30 org 87,500.00 113,750.00 Jumlah 1,029,670.00 Dibulatkan 129,530.00 20 1 M2 PASANG DINDING PARTISI GYPSUM BOARD + RANGKA BESI HOLLOW a Hollow 4/4 Zincromate 0.42 btg 48,000.00 20,160.00 b Hollow 2/4 Zincromate 0.15 btg 35,000.00 5,250.00 c Gypsum board ( 120 x 240 x 9 ) mm 0.72 lbr 86,000.00 61,920.00 d Paku sekrup 25.00 bh 600.00 15,000.00 e Ramset / dina bolt 4.00 bh 2,800.00 11,200.00 f Cotton plaster 0.10 bh 55,500.00 5,550.00 g Compoun 0.13 kg 30,000.00 3,900.00 h Pembantu tukang 0.10 org 50,000.00 5,000.00 i Tukang kayu 0.05 org 87,500.00 4,375.00 Jumlah 132,355.00 Dibulatkan 132,350.00
X PEKERJAAN RANGKA ATAP DAN PENUTUP ATAPA PEKERJAAN RANGKA ATAP 1 1 M3 PEKERJAAN KONSTRUKSI KUDA - KUDA KAYU KAMPER MEDAN a Balok kayu kamper medan 1.10 m3 6,550,000.00 7,205,000.00 b Besi strip 15.00 kg 14,100.00 211,500.00 c Paku ukuran besar 0.80 kg 17,500.00 14,000.00 d Meni kayu 0.40 kg 17,000.00 6,800.00 e Pembantu tukang 4.00 org 50,000.00 200,000.00 f Tukang kayu 12.00 org 87,500.00 1,050,000.00 Jumlah 8,687,300.00 Dibulatkan 8,687,300.00 2 1 M3 PEKERJAAN KONSTRUKSI KUDA - KUDA KAYU BORNEO SUPER a Balok kayu borneo super 1.10 m3 5,400,000.00 5,940,000.00 b Besi strip 15.00 kg 14,100.00 211,500.00 c Paku ukuran besar 0.80 kg 17,500.00 14,000.00 d Meni kayu 0.40 kg 17,000.00 6,800.00 e Pembantu tukang 4.00 org 50,000.00 200,000.00 f Tukang kayu 12.00 org 87,500.00 1,050,000.00 Jumlah 7,422,300.00 Dibulatkan 7,422,300.00 3 1 M2 PASANG KASO + RENG GENTENG PLENTONG KAYU BORNEO SUPER a Balok kayu borneo super 0.01 m3 5,400,000.00 64,800.00 b Paku 7 - 10 cm 0.15 kg 17,500.00 2,625.00 c Pembantu tukang 0.10 org 50,000.00 5,000.00 d Tukang kayu 0.10 org 87,500.00 8,750.00 Jumlah 81,175.00 Dibulatkan 81,100.00
4 1 M2 PASANG KASO + RENG GENTENG BETON KAYU BORNEO SUPER a Balok kayu borneo super 0.01 m3 5,400,000.00 75,600.00 b Paku 7 - 10 cm 0.15 kg 17,500.00 2,625.00 c Pembantu tukang 0.10 org 50,000.00 5,000.00 d Tukang kayu 0.10 org 87,500.00 8,750.00 Jumlah 91,975.00 Dibulatkan 91,900.00 5 1 M1 PASANG LISPLANG KAYU KAMPER MEDAN UKURAN 3 X 20 cm a Papan kayu kamper medan 0.01 m3 6,750,000.00 48,600.00 b Paku 7 - 10 cm 0.05 kg 17,500.00 875.00 c Pembantu tukang 0.10 org 50,000.00 5,000.00 d Tukang kayu 0.20 org 87,500.00 17,500.00 Jumlah 71,975.00 Dibulatkan 71,900.00 6 1 M2 PASANG LISPLANG KAYU KAMPER MEDAN UKURAN 3 X 30 cm a Papan kayu kamper medan 0.01 m3 6,750,000.00 74,250.00 b Paku 7 - 10 cm 0.05 kg 17,500.00 875.00 c Pembantu tukang 0.11 org 50,000.00 5,500.00 d Tukang kayu 0.22 org 87,500.00 19,250.00 Jumlah 99,875.00 Dibulatkan 99,800.00 7 1 M3 PEKERJAAN NOK/GORDING/JURAY KAYU BORNEO SUPER a Balok kayu borneo super 1.05 m3 5,400,000.00 5,670,000.00 b Paku 10 - 15 cm 0.20 kg 17,500.00 3,500.00 c Pembantu tukang 2.00 org 50,000.00 100,000.00 d Tukang kayu 2.00 org 87,500.00 175,000.00 Jumlah 5,948,500.00 Dibulatkan 5,948,500.00 B PEKERJAAN PENUTUP ATAP 1 1 M2 PASANG ATAP GENTENG PLENTONG
a Genteng palentong 25.00 bh 800.00 20,000.00 b Pembantu tukang 0.15 org 50,000.00 7,500.00 c Tukang kayu 0.08 org 87,500.00 6,562.50 Jumlah 34,062.50 Dibulatkan 34,060.00 2 1 M2 PASANG NOK/BUBUNGAN GENTENG KERAMIK GLAZUR a Genteng nok/bubungan plentong 5.00 bh 24,000.00 120,000.00 b Semen PC (abu-abu) 0.16 sak 54,000.00 8,640.00 c Pasir pasang 0.03 m3 84,000.00 2,688.00 d Pembantu tukang 0.30 org 50,000.00 15,000.00 e Tukang kayu 0.20 org 87,500.00 17,500.00 Jumlah 163,828.00 Dibulatkan 163,820.00 3 1 M2 PASANG ATAP FIBREGLASS UKURAN 180 X 90 cm a Atap fibreglass 0.60 lbr 72,500.00 43,500.00 b Paku 2 - 5 cm 0.05 kg 17,500.00 875.00 c Pembantu tukang 0.14 org 50,000.00 7,000.00 d Tukang kayu 0.07 org 87,500.00 5,862.50 Jumlah 57,237.50 Dibulatkan 57,230.00 4 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,70 x 1,05 m TEBAL 4 mm a Asbes gelombang 0.35 lbr 70,000.00 24,500.00 b Paku payung 0.12 kg 17,500.00 2,100.00 c Pembantu tukang 0.14 org 50,000.00 7,000.00 d Tukang kayu 0.07 org 87,500.00 6,125.00 Jumlah 39,725.00 Dibulatkan 39,720.00 5 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,40 x 1,05 m TEBAL 4 mm a Asbes gelombang 0.42 lbr 62,000.00 26,040.00 b Paku payung 0.12 kg 17,500.00 2,100.00
c Pembantu tukang 0.14 org 50,000.00 7,000.00 d Tukang kayu 0.07 org 87,500.00 6,125.00 Jumlah 41,265.00 Dibulatkan 41,260.00 6 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,70 x 1,02 m TEBAL 5 mm a Asbes gelombang 0.44 lbr 92,000.00 40,480.00 b Paku payung 0.12 kg 17,500.00 2,100.00 c Pembantu tukang 0.14 org 50,000.00 7,000.00 d Tukang kayu 0.07 org 87,500.00 5,862.50 Jumlah 55,442.50 Dibulatkan 55,440.00 7 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,40 x 1,02 m TEBAL 5 mm a Asbes gelombang 0.51 lbr 84,000.00 42,840.00 b Paku payung 0.12 kg 17,500.00 2,100.00 c Pembantu tukang 0.14 org 50,000.00 7,000.00 d Tukang kayu 0.07 org 87,500.00 5,862.50 Jumlah 57,802.50 Dibulatkan 57,800.00 8 1 M2 PASANG ATAP ASBES GELOMBANG ( 1,50 x 1,02 m ) x 5 mm a Asbes gelombang 0.80 lbr 48,000.00 38,400.00 b Paku payung 0.12 kg 17,500.00 2,100.00 c Pembantu tukang 0.14 org 50,000.00 7,000.00 d Tukang kayu 0.07 org 87,500.00 6,125.00 Jumlah 53,625.00 Dibulatkan 53,620.00 9 1 M¹ PASANG ATAP SIRAP a Genteng sirap 80.00 bh 1,100.00 88,000.00 b Paku 0.20 kg 17,500.00 3,500.00 c Pembantu tukang 0.10 org 50,000.00 5,000.00 d Tukang kayu 0.20 org 87,500.00 17,500.00
Jumlah 114,000.00 Dibulatkan 114,000.00 10 1 M2 PASANG ATAP GENTENG BETON a Genteng beton 1.10 bh 70,000.00 77,000.00 b Paku 5 - 12 cm 0.03 kg 17,500.00 525.00 c Pembantu tukang 0.20 org 50,000.00 10,000.00 d Tukang kayu 0.10 org 87,500.00 8,750.00 Jumlah 96,275.00 Dibulatkan 96,270.00 11 1 M2 PASANG ATAP GENTENG METAL + C301 a Genteng metal 1.02 lbr 134,000.00 136,680.00 b Paku 5 - 12 cm 0.20 kg 17,500.00 3,500.00 c Pembantu tukang 0.20 org 50,000.00 10,000.00 d Tukang kayu 0.10 org 87,500.00 8,750.00 Jumlah 158,930.00 Dibulatkan 158,930.00 12 1 M¹ PASANG NOK GENTENG BETON a Nok genteng beton 3.50 bh 15,000.00 52,500.00 b Paku 5 - 12 cm 0.05 kg 17,500.00 875.00 c Semen PC (abu-abu) 0.22 sak 54,000.00 11,664.00 d Pasir pasang 0.03 m3 84,000.00 2,688.00 e Semen warna 1.00 kg 12,700.00 12,700.00 f Pembantu tukang 0.40 org 50,000.00 20,000.00 g Tukang kayu 0.20 org 87,500.00 17,500.00 Jumlah 117,927.00 Dibulatkan 117,920.00 13 1 M¹ PASANG NOK GENTENG METAL a Nok genteng metal 1.10 bh 60,000.00 66,000.00 b Paku payung 0.05 kg 17,500.00 875.00 c Pembantu tukang 0.25 org 50,000.00 12,500.00
d Tukang kayu 0.15 org 87,500.00 13,125.00 Jumlah 92,500.00 Dibulatkan 92,500.00 14 1 M2 PASANG ATAP SENG GELOMBANG a Seng gelombang 0.70 lbr 57,500.00 40,250.00 b Paku payung 0.02 kg 17,500.00 350.00 c Pembantu tukang 0.12 org 50,000.00 6,000.00 d Tukang kayu 0.06 org 87,500.00 5,250.00 Jumlah 51,850.00 Dibulatkan 51,850.00 15 1 M2 PASANG NOK SENG UNTUK ATAP SENG GELOMBANG a Seng plat BJLS 1.05 M1 33,300.00 34,965.00 b Paku payung 0.04 kg 17,500.00 700.00 c Pembantu tukang 0.15 org 50,000.00 7,500.00 d Tukang kayu 0.07 org 87,500.00 6,125.00 Jumlah 49,290.00 Dibulatkan 49,290.00 16 1 M2 PASANG ATAP POLYCARBONATE a Polycarbonate 1.05 m2 215,000.00 225,750.00 b Besi Hollow 1.50 btg 48,000.00 72,000.00 c Alat bantu 20 % harga material 1.00 ls 45,150.00 45,150.00 d Pembantu tukang 0.15 org 50,000.00 7,500.00 e Tukang kayu 0.05 org 87,500.00 4,375.00 Jumlah 354,775.00 Dibulatkan 354,770.00 17 1 M2 PASANG ALUMINIUM FOIL a Aluminium foil 1.05 m2 5,500.00 5,775.00 b Alat bantu 20 % harga material 1.00 ls 1,155.00 1,155.00 c Pembantu tukang 0.15 org 50,000.00 7,500.00 d Tukang kayu 0.05 org 87,500.00 4,375.00
Jumlah 18,805.00 Dibulatkan 18,800.00
XI PEKERJAAN PENUTUP PLAFON 1 1 M2 PASANG RANGKA PLAFON ( UKRN 0,50 X 1,00 ) M, KAYU BORNEO SUPER a Balok kayu borneo super 4 x 6 cm 0.01 m3 5,400,000.00 64,800.00 b Paku 5 - 12 cm 0.10 kg 17,500.00 1,750.00 c Pembantu tukang 0.15 org 50,000.00 7,500.00 d Tukang kayu 0.25 org 87,500.00 21,875.00 Jumlah 95,925.00 Dibulatkan 95,900.00 2 1 M2 PLAFON GRC ( 60 X 1,20 ) M, TEBAL 4 MM a Pelat GRC tebal 4 mm 1.10 lbr 47,500.00 52,250.00 b Paku 1 cm 0.01 kg 17,500.00 175.00 c Pembantu tukang 0.03 org 50,000.00 1,500.00 d Tukang kayu 0.07 org 87,500.00 6,125.00 Jumlah 60,050.00 Dibulatkan 60,050.00 3 1 M2 PLAFON Asbes ( 1,00 x 1,00 ) m, tebal 5 mm a Pelat asbes tebal 5 mm 1.10 lbr 13,500.00 14,850.00 b Paku 1 cm 0.01 kg 17,500.00 175.00 c Pembantu tukang 0.03 org 50,000.00 1,500.00 d Tukang kayu 0.07 org 87,500.00 6,125.00 Jumlah 22,650.00 Dibulatkan 22,650.00 4 1 M2 PLAFON Akustik ( 60 x 120 ) cm a Akustik 600 x 1200 x 15 mm 1.50 lbr 70,000.00 105,000.00 b Paku 2 - 5 cm 0.05 kg 17,500.00 875.00
c Pembantu tukang 0.06 org 50,000.00 3,000.00 d Tukang kayu 0.10 org 87,500.00 8,750.00 Jumlah 117,625.00 Dibulatkan 117,620.00 5 1 M2 PLAFON AKUSTIK ( 60 X 120 ) CM + RANGKA ALLUMINIUM a Profil Alluminium "T" 3.60 M¹ 32,000.00 115,200.00 b Kawat seng polos 0.15 kg 13,400.00 2,010.00 c Ramset / dina bolt 1.00 bh 2,800.00 2,800.00 d Akustik 600 x 1200 x 15 mm 1.50 lbr 70,000.00 105,000.00 e Pembantu tukang 0.15 org 50,000.00 7,500.00 f Tukang kayu 0.20 org 87,500.00 17,500.00 Jumlah 250,010.00 Dibulatkan 250,010.00 6 1 M¹ LIST PLAFON PROFIL KAYU a Listp profil kayu 1.10 M¹ 6,800.00 7,480.00 b Paku 2 cm 0.01 kg 17,500.00 175.00 c Pembantu tukang 0.05 org 50,000.00 2,500.00 d Tukang kayu 0.05 org 87,500.00 4,375.00 Jumlah 14,530.00 Dibulatkan 14,530.00 7 1 M¹ LIST PLAFON KAYU 1/4 a List kayu 1/4 1.10 M¹ 1,900.00 2,090.00 b Paku 2 cm 0.01 kg 17,500.00 175.00 c Pembantu tukang 0.05 org 50,000.00 2,500.00 d Tukang kayu 0.05 org 87,500.00 4,375.00 Jumlah 9,140.00 Dibulatkan 9,140.00 8 1 M2 PLAFON TRIPLEK 4 MM + RANGKA KAYU BORNEO SUPER a Balok kayu borneo super 0.02 m3 5,400,000.00 124,200.00 b Paku 1- 12 cm 0.06 kg 17,500.00 1,050.00
c Triplek 120 cm x 240 cm x 0,4 cm 0.39 lbr 42,000.00 16,380.00 d Pembantu tukang 0.27 org 50,000.00 13,500.00 e Tukang kayu 0.40 org 87,500.00 35,000.00 Jumlah 190,130.00 Dibulatkan 190,130.00 9 1 M2 PLAFON TEAKWOOD 4 MM + RANGKA KAYU BORNEO SUPER a Balok kayu borneo super 0.02 m3 5,400,000.00 124,200.00 b Paku 1 - 12 cm 0.06 kg 17,500.00 1,050.00 c Teakwood 120 cm x 240 cm x 0,4 cm 0.39 lbr 82,000.00 31,980.00 d Pembantu tukang 0.27 org 50,000.00 13,500.00 e Tukang kayu 0.40 org 87,500.00 35,000.00 Jumlah 205,730.00
Dibulatkan 205,730.00 10 1 M2 Plafon PAPAN 10 CM, TEBAL 1 CM + RANGKA KAYU BORNEO SUPER a Balok kayu borneo super 0.02 m3 5,400,000.00 124,200.00 b Paku 2 - 12 cm 0.20 kg 17,500.00 3,500.00 c Papan kayu kamper 0.02 m3 9,980,000.00 199,600.00 d Pembantu tukang 0.35 org 50,000.00 17,500.00 e Tukang kayu 0.50 org 87,500.00 43,750.00 Jumlah 388,550.00
Dibulatkan 388,550.00 11 1 M2 Plafon GYPSUM BOARD, TEBAL 9 MM + RANGKA BESI HOLLOW a Hollow 4/4 Zincromate 0.42 btg 48,000.00 19,920.00 b Hollow 2/4 Zincromate 0.15 btg 35,000.00 5,250.00 c Gypsum board ( 120 x 240 x 9 ) mm 0.36 lbr 86,000.00 31,304.00 d Paku sekrup 25.00 bh 600.00 15,000.00 e Ramset / dina bolt 4.00 bh 2,800.00 11,200.00 f Cotton plaster 0.07 bh 55,500.00 3,996.00 g Compoun 0.13 kg 30,000.00 3,750.00 h Pembantu tukang 0.10 org 50,000.00 5,000.00
i Tukang kayu 0.05 org 87,500.00 4,375.00 Jumlah 99,795.00 Dibulatkan 99,790.00
XII PEKERJAAN SANITAIR 1 MEMASANG 1 BUAH KLOSET DUDUK / MONOBLOK a Kloset duduk / monoblok 1.00 bh 2,300,000.00 2,300,000.00 b Perlengkapan ( 10% hrg kloset ) 230,000.00 230,000.00 c Pembantu tukang 3.30 org 50,000.00 165,000.00 d Tukang batu 1.10 org 87,500.00 96,250.00 Jumlah 2,791,250.00 Dibulatkan 2,791,250.00 2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN a Kloset jongkok porselen 1.00 bh 170,000.00 170,000.00 b Semen PC (abu-abu) 0.12 sak 54,000.00 6,480.00 c Pasir pasang 0.01 m3 84,000.00 840.00 d Pembantu tukang 1.00 org 50,000.00 50,000.00 e Tukang batu 1.50 org 87,500.00 131,250.00 Jumlah 358,570.00 Dibulatkan 358,570.00 3 MEMASANG 1 BUAH URINOIR a Urinoir 1.00 bh 380,000.00 380,000.00 b Perlengkapan ( 30% hrg urinoir ) 114,000.00 114,000.00 c Semen PC (abu-abu) 0.12 sak 54,000.00 6,480.00 d Pasir pasang 0.01 m3 84,000.00 840.00 e Pembantu tukang 1.00 org 50,000.00 50,000.00 f Tukang batu 1.00 org 87,500.00 87,500.00 Jumlah 638,820.00 Dibulatkan 638,820.00 4 MEMASANG 1 BUAH WASTAFEL DINDING
a Wastafel 1.00 bh 220,000.00 220,000.00 b Perlengkapan ( 12% hrg kloset ) 26,400.00 26,400.00 c Semen PC ( abu-abu ) 0.12 sak 54,000.00 6,480.00 d Pasir pasang 0.01 m3 84,000.00 840.00 e Pembantu tukang 1.20 org 50,000.00 60,000.00 f Tukang batu 1.45 org 87,500.00 126,875.00 Jumlah 440,595.00 Dibulatkan 440,590.00 5 MEMASANG 1 BUAH WASTAFEL KAKI a Wastafel 1.00 bh 255,000.00 255,000.00 b Perlengkapan ( 12% hrg kloset ) 30,600.00 30,600.00 c Semen PC ( abu-abu ) 0.12 sak 54,000.00 6,480.00 d Pasir pasang 0.01 m3 84,000.00 840.00 e Pembantu tukang 1.20 org 50,000.00 60,000.00 f Tukang batu 1.45 org 87,500.00 126,875.00 Jumlah 479,795.00 Dibulatkan 479,790.00 6 MEMASANG 1 BH SHOWER DINDING a Shower dinding 1.00 bh 132,000.00 132,000.00 b Pembantu tukang 0.01 org 50,000.00 500.00 c Tukang batu 0.10 org 87,500.00 8,750.00 Jumlah 141,250.00 Dibulatkan 141,250.00 7 MEMASANG BAK MANDI FIBERGLASS UKURAN SEDANG a Bak fibreglass 1.00 bh 178,000.00 178,000.00 b Perlengkapan ( 20% hrg bak ) 32,040.00 32,040.00 c Pembantu tukang 1.80 org 50,000.00 90,000.00 d Tukang batu 2.70 org 87,500.00 236,250.00 Jumlah 536,290.00 Dibulatkan 536,290.00
8 MEMASANG BAK KONTROL PASANGAN BATU BATA UKURAN 30 X 30 CM, TINGGI 35 CM a Batu bata 0.15 m3 650.00 97.50 b Semen PC (abu-abu) 0.88 sak 54,000.00 47,520.00 c Pasir pasang 0.07 m3 84,000.00 5,880.00 d Batu kerikil 0.07 m3 157,900.00 11,053.00 e Besi beton 1.60 kg 15,100.00 24,160.00 f Pasir beton 0.06 m3 92,000.00 5,520.00 g Pembantu tukang 3.20 org 50,000.00 160,000.00 h Tukang batu 1.02 org 87,500.00 89,250.00 Jumlah 343,480.50 Dibulatkan 343,480.00 9 MEMASANG KICHEN ZINK/BAK CUCI PIRING STAINLESS STEEL a Bak cuci stainless steel 1.00 bh 191,500.00 191,500.00 b Water Drain + Asesories 1.00 Set 88,000.00 88,000.00 c Pembantu tukang 0.03 org 50,000.00 1,500.00 d Tukang batu 0.30 org 87,500.00 26,250.00 Jumlah 307,250.00 Dibulatkan 307,250.00 10 MEMASANG 1 BH KRAN DIAMETER 3/4 " ATAU 1/2 " a Kran air 1.00 bh 56,000.00 56,000.00 b Perlengkapan ( 2% hrg kran ) 1.00 ls 1,120.00 1,120.00 c Pembantu tukang 0.01 org 50,000.00 500.00 d Tukang batu 0.10 org 87,500.00 8,750.00 Jumlah 66,370.00 Dibulatkan 66,370.00 11 MEMASANG 1 BH KRAN AIR ANGSA a Kran air angsa 1.00 bh 157,500.00 157,500.00 b Perlengkapan ( 2% hrg kran ) 1.00 ls 3,150.00 3,150.00 c Pembantu tukang 0.01 org 50,000.00 500.00 d Tukang batu 0.10 org 87,500.00 8,750.00
Jumlah 169,900.00 Dibulatkan 169,900.00 12 MEMASANG 1 BH FLOOR DRAIN a Floor drain 1.00 bh 62,000.00 62,000.00 b Pembantu tukang 0.01 org 50,000.00 500.00 c Tukang batu 0.10 org 87,500.00 8,750.00 Jumlah 71,250.00 Dibulatkan 71,250.00 13 MEMASANG 1 BH TEMPAT SABUN a Tempat Sabun 1.00 bh 32,000.00 32,000.00 b Pembantu tukang 0.01 org 50,000.00 500.00 c Tukang batu 0.10 org 87,500.00 8,750.00 Jumlah 41,250.00 Dibulatkan 41,250.00
XIII PEKERJAAN PERPIPAAN DAN POMPA 1 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER ½" a Pipa galvanis dia 1/2" 1.10 M¹ 15,300.00 16,830.00 b Perlengkapan ( 30% harga pipa ) 4,590.00 4,590.00 c Pembantu tukang 0.05 org 50,000.00 2,700.00 d Tukang pipa 0.09 org 87,500.00 7,875.00 Jumlah 31,995.00 Dibulatkan 31,990.00 2 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER ¾" a Pipa galvanis 1.10 M¹ 20,850.00 22,935.00 b Perlengkapan ( 30% harga pipa ) 6,255.00 6,255.00 c Pembantu tukang 0.05 org 50,000.00 2,700.00 d Tukang pipa 0.09 org 87,500.00 7,875.00 Jumlah 39,765.00
Dibulatkan 39,760.00 3 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER 1" a Pipa galvanis 1.10 M¹ 30,500.00 33,550.00 b Perlengkapan ( 30% harga pipa ) 9,150.00 9,150.00 c Pembantu tukang 0.05 org 50,000.00 2,700.00 d Tukang pipa 0.09 org 87,500.00 7,875.00 Jumlah 53,275.00 Dibulatkan 53,270.00 4 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER 1½" a Pipa galvanis 1.10 M¹ 34,750.00 38,225.00 b Perlengkapan ( 30% harga pipa ) 10,425.00 10,425.00 c Pembantu tukang 0.11 org 50,000.00 5,400.00 d Tukang pipa 0.18 org 87,500.00 15,750.00 Jumlah 69,800.00 Dibulatkan 69,800.00 5 MEMASANG 1 M¹ PIPA PVC TYPE D DIAMETER 3" a Pipa PVC type D 1.10 M¹ 6,750.00 7,425.00 b Perlengkapan ( 30% harga pipa ) 2,025.00 2,025.00 c Pembantu tukang 0.10 org 50,000.00 5,000.00 d Tukang pipa 0.18 org 87,500.00 15,750.00 Jumlah 30,200.00 Dibulatkan 30,200.00 6 MEMASANG 1 M¹ PIPA PVC TYPE D DIAMETER 4" a Pipa PVC type D 1.10 M¹ 9,000.00 9,900.00 b Perlengkapan ( 30% harga pipa ) 2,700.00 2,700.00 c Pembantu tukang 0.13 org 50,000.00 6,500.00 d Tukang pipa 0.22 org 87,500.00 19,250.00 Jumlah 38,350.00 Dibulatkan 38,350.00 7 MEMASANG 1 M¹ PVC TIPE AW DIAMETER ½"
a Pipa PVC 1.10 M¹ 5,750.00 6,325.00 b Perlengkapan ( 30% harga pipa ) 1,725.00 1,725.00 c Pembantu tukang 0.04 org 50,000.00 1,800.00 d Tukang pipa 0.06 org 87,500.00 5,250.00 Jumlah 15,100.00 Dibulatkan 15,100.00 8 MEMASANG 1 M¹ PVC TIPE AW DIAMETER ¾" a Pipa PVC 1.10 M¹ 7,700.00 8,470.00 b Perlengkapan ( 30% harga pipa ) 2,310.00 2,310.00 c Pembantu tukang 0.03 org 50,000.00 1,500.00 d Tukang pipa 0.06 org 87,500.00 5,250.00 Jumlah 17,530.00
Dibulatkan 17,530.00 9 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 1" a Pipa PVC 1.10 M¹ 14,000.00 15,400.00 b Perlengkapan ( 30% harga pipa ) 4,200.00 4,200.00 c Pembantu tukang 0.04 org 50,000.00 1,800.00 d Tukang pipa 0.06 org 87,500.00 5,250.00 Jumlah 26,650.00 Dibulatkan 26,650.00 10 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 2" a Pipa PVC 1.10 M¹ 24,000.00 26,400.00 b Perlengkapan ( 30% harga pipa ) 7,200.00 7,200.00 c Pembantu tukang 0.05 org 50,000.00 2,700.00 d Tukang pipa 0.09 org 87,500.00 7,875.00 Jumlah 44,175.00 Dibulatkan 44,170.00 11 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 4" a Pipa PVC 1.10 M¹ 51,700.00 56,870.00 b Perlengkapan ( 30% harga pipa ) 15,510.00 15,510.00
c Pembantu tukang 0.08 org 50,000.00 4,050.00 d Tukang pipa 0.14 org 87,500.00 11,812.50 Jumlah 88,242.50 Dibulatkan 88,240.00 12 MEMBUAT 1 BH SEPTICTANK PASANGAN BATU BATA DAN REMBESAN a Galian tanah Septictank & rembesan 7.5 m3 38,500.00 288,750.00 b Pasir urug 0.21 m3 67,000.00 14,070.00 c Lantai kerja 2.25 m3 648,800.00 1,459,800.00 d Pasang bata 1 Pc : 2 Psr 15.00 m2 89,270.00 1,339,050.00 e Pelat beton penutup dan balok 0.30 m3 5,711,800.00 1,713,540.00 f Pipa PVC 4 inci AW & perlengkapannya 5.40 M1 51,700.00 279,180.00 g Plesteran 1 Pc : 3 Psr 30.00 m2 31,800.00 954,000.00 h Pasangan ijuk 5.00 IKAT 7,500.00 37,500.00 i Urugan kerikil 3,5 cm 1.05 m3 112,400.00 118,020.00 j Pipa PVC 4 inci AW dilobang 9.00 M1 51,700.00 465,300.00 k Urugan kembali 1.13 m3 11,000.00 12,430.00 l Pembantu tukang 4.00 org 50,000.00 200,000.00 m Tukang batu 3.00 org 87,500.00 262,500.00 Jumlah 7,144,140.00 Dibulatkan 7,144,140.00 13 MEMASANG 1 BH POMPA AIR a Pompa Air 100 Watt 1.00 bh 800,000.00 800,000.00 b Perlengkapan ( 25% harga pompa ) 200,000.00 200,000.00 c Pembantu tukang 0.08 org 50,000.00 4,050.00 d Tukang Pipa 0.14 org 87,500.00 11,812.50 Jumlah 1,015,862.50 Dibulatkan 1,015,860.00
XIV PEKERJAAN PENUTUP BESI DAN BAJA 1 1 KG PASANG RANGKA ATAP BAJA a Besi profil WF 1.10 kg 16,550.00 18,205.00 b Meni besi 0.08 kg 27,500.00 2,200.00 c Peralatan las ( 5 % material ) 1.00 ls 910.25 910.25 d Elektroda 0.20 ls 18,000.00 3,600.00 e Tukang besi 0.04 org 87,500.00 3,500.00 f Pembantu tukang 0.06 org 50,000.00 3,000.00 Jumlah 31,415.25 Dibulatkan 31,410.00 2 1 KG PASANG RANGKA ATAP BESI SIKU a Besi Siku 1.10 kg 16,550.00 18,205.00 b Meni besi 0.10 kg 27,500.00 2,750.00 c Peralatan las ( 5 % material ) 1.00 ls 910.25 910.25 d Elektroda 0.15 ls 18,000.00 2,700.00 e Baud 0.20 kg 15,100.00 3,020.00 f Tukang besi 0.04 org 87,500.00 3,500.00 g Pembantu tukang 0.06 org 50,000.00 3,000.00 Jumlah 34,085.25 Dibulatkan 34,080.00 3 1 KG PASANG GORDING BESI C a Besi C 1.10 kg 14,100.00 15,510.00 b Meni besi 0.10 kg 27,500.00 2,750.00 c Peralatan las ( 5 % material ) 1.00 ls 775.50 775.50 d Elektroda 0.15 ls 18,000.00 2,700.00 e Baud 0.20 kg 15,100.00 3,020.00 f Tukang besi 0.04 org 87,500.00 3,500.00 g Pembantu tukang 0.06 org 50,000.00 3,000.00 Jumlah 31,255.50 Dibulatkan 31,250.00
4 1 M2 PASANG PINTU ROLLING DOOR BESI a Rolling door besi 1.00 m2 782,000.00 782,000.00 b Tukang besi 1.50 org 87,500.00 131,250.00 c Pembantu tukang 1.05 org 50,000.00 52,500.00 Jumlah 965,750.00 Dibulatkan 965,750.00 5 1 BH PASANG PINTU BESI UKURAN 0,8 X 2 M a Pintu besi jadi 1.00 bh 400,000.00 400,000.00 b Tukang besi 1.05 org 87,500.00 91,875.00 c Pembantu tukang 1.05 org 50,000.00 52,500.00 Jumlah 544,375.00 Dibulatkan 544,370.00 6 1 M2 PASANG TERALIS BESI a Besi strip 2 mm x 3 cm 11.50 M¹ 14,100.00 162,150.00 b Tukang las 1.20 org 75,000.00 90,000.00 c Pembantu tukang 1.20 org 50,000.00 60,000.00 Jumlah 312,150.00 Dibulatkan 312,150.00 7 1 M2 PASANG KAWAT HARMONIKA a Kawat harmonika 1.10 m2 18,000.00 19,800.00 b Paku 2 - 5 cm 0.02 kg 17,500.00 350.00 c Papan kayu kamper medan 0.00 m3 6,750,000.00 12,150.00 d Pembantu tukang 0.10 org 50,000.00 5,000.00 e Tukang kayu 0.10 org 87,500.00 8,750.00 Jumlah 46,050.00 Dibulatkan 46,050.00 8 1 M1 PASANG TALANG DATAR, SENG PLAT BJLS a Seng plat BJLS 1.00 M1 33,300.00 33,300.00 b Paku 2 - 5 cm 0.02 kg 17,500.00 262.50 c Papan kayu borneo super 0.01 m3 5,660,000.00 54,336.00
d Flincote / meni besi 0.25 kg 22,000.00 5,500.00 e Pembantu tukang 0.15 org 50,000.00 7,500.00 f Tukang kayu 0.40 org 87,500.00 35,000.00 Jumlah 135,898.50 Dibulatkan 135,890.00 9 1 M1 PASANG TALANG MIRING, SENG PLAT BJLS a Seng plat BJLS 0.50 M1 33,300.00 16,650.00 b Paku 2 - 5 cm 0.02 kg 17,500.00 262.50 c Papan kayu borneo super 0.02 m3 5,660,000.00 107,540.00 d Flincote / meni besi 0.30 kg 22,000.00 6,600.00 e Pembantu tukang 0.04 org 50,000.00 2,000.00 f Tukang kayu 0.40 org 87,500.00 35,000.00 Jumlah 168,052.50 Dibulatkan 168,050.00
XV PEKERJAAN ALUMINIUM 1 1 M2 PASANG PINTU ROLLING DOOR ALUMINIUM a Rolling door aluminium 1.00 m2 782,000.00 782,000.00 b Tukang besi konstruksi 1.50 org 87,500.00 131,250.00 c Pembantu tukang 1.05 org 50,000.00 52,500.00 Jumlah 965,750.00 Dibulatkan 965,750.00 2 1 M2 PASANG PINTU ALUMINIUM PABRIKAN a Pintu alluminium 1.00 bh 400,000.00 400,000.00 b Tukang batu 1.05 org 75,671.00 79,454.55 c Pembantu tukang 1.05 org 50,000.00 52,500.00 Jumlah 531,954.55 Dibulatkan 531,950.00
3 1 UNIT KUSEN JENDELA ALUMINIUM 2 LUBANG DGN 2 DAUN JENDELA (UKURAN 1,6 X 1,5 M) a Profil aluminium 4" natural (+ spare 20 %) 9.24 M1 78,000.00 720,720.00 b Profil daun jendela alm.( + spare 20%) 11.04 M1 75,600.00 834,624.00 c Kaca polos 3 mm 2.40 m2 90,000.00 216,000.00 d Engsel jendela 4.00 ps 22,000.00 88,000.00 e Grendel jendela 2.00 bh 19,500.00 39,000.00 f Kait angin 2.00 bh 19,800.00 39,600.00 g Acesories ( 6 % harga bahan) 1.00 ls 106,280.64 106,280.64 h Upah pembuatan profil ( 20 % bahan ) 1.00 ls 144,144.00 144,144.00 i Upah pembuatan daun jendela (20 % bahan) 1.00 ls 166,924.80 166,924.80 Jumlah 2,355,293.44 Dibulatkan 2,355,290.00
41 UNIT KUSEN JENDELA ALUMINIUM 3 LUBANG DGN 2 DAUN JENDELA DAN 1 KACA MATI (UKURAN 2 X 1,5 M)
a Profil aluminium 4" natural (+ spare 20 %) 12.00 M1 78,000.00 936,000.00 b Profil daun jendela alm.( + spare 20%) 11.04 M1 75,600.00 834,624.00 c Kaca polos 3 mm 3.00 m2 90,000.00 270,000.00 d Engsel jendela 4.00 ps 22,000.00 88,000.00 e Grendel jendela 2.00 bh 19,500.00 39,000.00 f Kait angin 2.00 bh 19,800.00 39,600.00 g Acesories ( 6 % harga bahan ) 1.00 ls 122,437.44 122,437.44 h Upah pembuatan profil ( 20 % bahan ) 1.00 ls 187,200.00 187,200.00 i Upah pembuatan daun jendela (20 % bahan) 1.00 ls 166,924.80 166,924.80 Jumlah 2,329,661.44 Dibulatkan 2,329,660.00
51 UNIT KUSEN PINTU JENDELA GENDONG ALUMINIUM DGN 2 JNDL DAN 1 PNT TEAKWOOD (UKR 2,2 X 2,7 M)
a Profil aluminium 4" natural (+ spare 20 %) 17.04 M1 78,000.00 1,329,120.00 b Profil daun jendela alm.( + spare 20%) 14.88 M1 75,600.00 1,124,928.00 c Kaca polos 3 mm 3.96 m2 90,000.00 356,400.00
d Daun pintu teakwood 1.80 m2 432,600.00 778,680.00 e Engsel jendela 4.00 ps 22,000.00 88,000.00 f Grendel jendela 2.00 bh 19,500.00 39,000.00 g Kait angin 4.00 bh 19,800.00 79,200.00 h Engsel pintu 3.00 ps 25,000.00 75,000.00 i Grendel pintu 1.00 bh 33,000.00 33,000.00 j Kunci tanam 1.00 bh 22,000.00 22,000.00 k Acesories ( 6 % harga bahan ) 1.00 ls 140,522.40 140,522.40 l Upah pembuatan profil ( 20 % bahan ) 1.00 ls 17,600.00 17,600.00 m Upah pembuatan daun jendela (20 % bahan) 1.00 ls 7,800.00 7,800.00 Jumlah 4,091,250.40 Dibulatkan 4,091,250.00 6 1 UNIT KUSEN PINTU ALUMINIUM UKR 0.9 X 2,7 M a Profil aluminium 4" natural (+ spare 20 %) 7.56 M1 78,000.00 589,680.00 b Kaca polos 3 mm untuk bovenlight 0.45 m2 90,000.00 40,500.00 c Daun pintu tekwood 1.68 m2 432,600.00 726,768.00 d Engsel pintu 3.00 ps 25,000.00 75,000.00 e Grendel pintu 1.00 bh 33,000.00 33,000.00 f Kunci tanam 1.00 bh 22,000.00 22,000.00 g Acesories ( 6 % ) 1.00 ls 37,810.80 37,810.80 h Upah pembuatan profil ( 20 % bahan ) 1.00 ls 117,936.00 117,936.00 Jumlah 1,642,694.80 Dibulatkan 1,642,690.00 7 1 BH BOVENLIGHT ALMUNIUM DENGAN KISI-KISI ALMUNIUM PLAT (UKURAN 0,5 X 1 M) a Profil Aluminium 4" natural + upah 20% 3.60 M1 90,000.00 324,000.00 b Plat Aluminium untuk Jalusi 5.00 M1 20,000.00 100,000.00 c Acesories ( 6 % ) 1.00 ls 19,440.00 19,440.00 d Upah pembuatan profil ( 20 % bahan ) 1.00 ls 23,587.20 23,587.20 Jumlah 467,027.20 Dibulatkan 467,020.00
8 1 BH BOVENLIGHT ALMUNIUM UKURAN 0,5 X 1 M DENGAN BAGIAN DALAM KACA a Profil Aluminium 4" natural + upah 20% 3.60 M1 78,000.00 280,800.00 b Kaca Polos 3 mm 0.50 m2 90,000.00 45,000.00 c Acesories ( 6 % ) 1.00 ls 16,848.00 16,848.00 d Upah pembuatan profil ( 20 % bahan ) 1.00 ls 4,717.44 4,717.44 Jumlah 347,365.44 Dibulatkan 347,360.00
XVI PEKERJAAN KACA & PENGGANTUNG 1 1 BUAH PASANG KUNCI TANAM BESAR a Kunci tanam besar 1.00 bh 189,000.00 189,000.00 b Pembantu tukang 0.06 org 50,000.00 3,000.00 c Tukang kayu 0.60 org 87,500.00 52,500.00 Jumlah 244,500.00 Dibulatkan 244,500.00 2 1 BUAH PASANG KUNCI TANAM SEDANG a Kunci tanam sedang 1.00 bh 55,000.00 55,000.00 b Pembantu tukang 0.01 org 50,000.00 500.00 c Tukang kayu 0.50 org 87,500.00 43,750.00 Jumlah 99,250.00 Dibulatkan 99,250.00 3 1 BUAH PASANG KUNCI BULAT PUTAR KAMAR MANDI a Kunci bulat putar kamar mandi 1.00 bh 55,000.00 55,000.00 b Pembantu tukang 0.01 org 50,000.00 250.00 c Tukang kayu 0.50 org 87,500.00 43,750.00 Jumlah 99,000.00
Dibulatkan 99,000.00 4 1 BUAH PASANG ENGSEL PINTU a Engsel pintu 1.00 bh 25,000.00 25,000.00 b Pembantu tukang 0.02 org 50,000.00 750.00 c Tukang kayu 0.15 org 87,500.00 13,125.00 Jumlah 38,875.00 Dibulatkan 38,870.00 5 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU a Engsel jendela 1.00 bh 22,000.00 22,000.00 b Pembantu tukang 0.01 org 50,000.00 500.00 c Tukang kayu 0.10 org 87,500.00 8,750.00 Jumlah 31,250.00 Dibulatkan 31,250.00 6 1 BUAH PASANG KAIT ANGIN a Kait angin 1.00 bh 19,800.00 19,800.00 b Pembantu tukang 0.02 org 50,000.00 750.00 c Tukang kayu 0.15 org 87,500.00 13,125.00 Jumlah 33,675.00 Dibulatkan 33,670.00 7 1 BUAH PASANG DOOR CLOSER a Door closer 1.00 bh 380,000.00 380,000.00 b Pembantu tukang 0.05 org 50,000.00 2,500.00 c Tukang kayu 0.50 org 87,500.00 43,750.00 Jumlah 426,250.00 Dibulatkan 426,250.00 8 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER a Door holder 1.00 bh 50,000.00 50,000.00 b Pembantu tukang 0.05 org 50,000.00 2,500.00 c Tukang kayu 0.50 org 87,500.00 43,750.00 Jumlah 96,250.00
Dibulatkan 96,250.00 9 1 BUAH PASANG PENAHAN PINTU / DOOR STOPER a Door stoper 1.00 bh 66,000.00 66,000.00 b Pembantu tukang 0.05 org 50,000.00 2,500.00 c Tukang kayu 0.50 org 87,500.00 43,750.00 Jumlah 112,250.00 Dibulatkan 112,250.00 10 1 BUAH PASANG GRENDEL / SLOOT PINTU a Grendel / sloot pintu 1.00 bh 33,000.00 33,000.00 b Pembantu tukang 0.05 org 50,000.00 2,500.00 c Tukang kayu 0.50 org 87,500.00 43,750.00 Jumlah 79,250.00 Dibulatkan 79,250.00 11 1 BUAH PASANG GRENDEL / SLOOT JENDELA a Grendel / sloot jendela 1.00 bh 19,500.00 19,500.00 b Pembantu tukang 0.05 org 50,000.00 2,500.00 c Tukang kayu 0.50 org 87,500.00 43,750.00 Jumlah 65,750.00 Dibulatkan 65,750.00 12 1 BUAH PASANG TARIKAN JENDELA a Tarikan jendela 1.00 bh 18,000.00 18,000.00 b Pembantu tukang 0.05 org 50,000.00 2,500.00 c Tukang kayu 0.50 org 87,500.00 43,750.00 Jumlah 64,250.00 Dibulatkan 64,250.00 13 1 M2 PASANG KACA POLOS, TEBAL 3 MM a Kaca polos 1.10 m2 90,000.00 99,000.00 b Pembantu tukang 0.02 org 50,000.00 750.00 c Tukang kayu 0.15 org 87,500.00 13,125.00 Jumlah 112,875.00
Dibulatkan 112,870.00 14 1 M2 PASANG KACA POLOS, TEBAL 5 MM a Kaca polos 1.10 m2 150,000.00 165,000.00 b Pembantu tukang 0.02 org 50,000.00 750.00 c Tukang kayu 0.15 org 87,500.00 13,125.00 Jumlah 178,875.00 Dibulatkan 178,870.00 15 1 M2 PASANG KACA RAY BAND, TEBAL 5 MM a Kaca 1.10 m2 199,000.00 218,900.00 b Pembantu tukang 0.02 org 50,000.00 750.00 c Tukang kayu 0.15 org 87,500.00 13,125.00 Jumlah 232,775.00 Dibulatkan 232,770.00
XVII PEKERJAAN PENGECATAN 1 1 M2 MENGIKIS / MENGEROK / MENGELUPAS PERMUKAAN CAT TEMBOK LAMA a Soda api 0.05 kg 44,000.00 2,200.00 b Pembantu tukang 0.05 org 50,000.00 2,500.00 c Tukang cat 0.02 org 87,500.00 1,750.00 Jumlah 6,450.00 Dibulatkan 6,450.00 2 1 M2 MENDEMPUL DAN MENGGOSOK KAYU a Dempul jadi 0.10 kg 24,000.00 2,400.00 b Minyak cat 0.03 kg 19,300.00 579.00 c Ampelas kasar 0.30 lbr 2,500.00 750.00 d Pembantu tukang 0.04 org 50,000.00 2,000.00 e Tukang cat 0.05 org 87,500.00 4,375.00 Jumlah 10,104.00
Dibulatkan 10,100.00 3 1 M2 PENGECATAN KAYU LAMA a Cat meni 0.25 kg 27,500.00 6,875.00 b Plamir 0.15 kg 23,100.00 3,465.00 c Ampelas 1.00 lbr 2,500.00 2,500.00 d Cat dasar 0.15 kg 41,000.00 6,150.00 e Cat penutup kwalitas baik 0.60 kg 39,000.00 23,400.00 f Pembantu tukang 0.05 org 50,000.00 2,500.00 g Tukang cat 0.15 org 87,500.00 13,125.00 Jumlah 58,015.00 Dibulatkan 58,010.00 4 1 M2 PENGECATAN KAYU BARU a Cat meni 0.50 kg 27,500.00 13,750.00 b Plamir 0.15 kg 23,100.00 3,465.00 c Ampelas 1.00 lbr 2,500.00 2,500.00 d Cat dasar 0.15 kg 41,000.00 6,150.00 e Cat penutup kwalitas baik 0.35 kg 39,000.00 13,650.00 f Pembantu tukang 0.05 org 50,000.00 2,500.00 g Tukang cat 0.15 org 87,500.00 13,125.00 Jumlah 55,140.00 Dibulatkan 55,140.00 5 1 M2 PENGECATAN KAYU DENGAN POLITUR a Politur 0.15 Ltr 35,000.00 5,250.00 b Dempul jadi 0.25 kg 24,000.00 6,000.00 c Ampelas 2.00 lbr 2,500.00 5,000.00 d Pembantu tukang 0.05 org 50,000.00 2,500.00 e Tukang cat 0.15 org 87,500.00 13,125.00 Jumlah 31,875.00 Dibulatkan 31,870.00 6 1 M2 PENGECATAN KAYU DENGAN MELAMIK
a Melamik 0.15 Ltr 32,000.00 4,800.00 b Dempul jadi 0.25 kg 24,000.00 6,000.00 c Ampelas 2.00 lbr 2,500.00 5,000.00 d Pembantu tukang 0.05 org 50,000.00 2,500.00 e Tukang cat 0.15 org 87,500.00 13,125.00 Jumlah 31,425.00 Dibulatkan 31,420.00 7 1 M2 PENGECATAN KAYU DENGAN CAT RESIDU/TER a Residu atau ter 0.35 Ltr 6,800.00 2,380.00 b Pembantu tukang 0.15 org 50,000.00 7,500.00 c Tukang cat 0.02 org 87,500.00 1,750.00 Jumlah 11,630.00 Dibulatkan 11,630.00 8 1 M2 PENGECATAN TEMBOK/Plafon BARU KWALITAS SEDANG a Plamir 0.10 kg 25,000.00 2,500.00 b Rol cat 0.01 bh 27,000.00 270.00 c Cat penutup kwalitas sedang 0.45 kg 15,000.00 6,750.00 d Steger ( perancah kerja ) 0.01 Ls 75,000.00 750.00 e Ampelas 0.50 lbr 2,500.00 1,250.00 f Pembantu tukang 0.06 org 50,000.00 3,000.00 g Tukang cat 0.20 org 87,500.00 17,500.00 Jumlah 32,020.00 Dibulatkan 32,020.00 9 1 M2 PENGECATAN TEMBOK/Plafon BARU KWALITAS BAIK a Plamir 0.10 kg 25,000.00 2,500.00 b Rol cat 0.01 bh 27,000.00 270.00 c Cat penutup kwalitas baik 0.50 kg 44,000.00 22,000.00 d Steger ( perancah kerja ) 0.01 Ls 75,000.00 750.00 e Ampelas 0.50 lbr 2,500.00 1,250.00 f Pembantu tukang 0.06 org 50,000.00 3,000.00
g Tukang cat 0.20 org 87,500.00 17,500.00 Jumlah 47,270.00 Dibulatkan 47,270.00 10 1 M2 PENGECATAN TEMBOK LAMA a Cat penutup kwalitas baik 0.40 kg 28,000.00 11,200.00 b Rol cat 0.01 bh 27,000.00 270.00 c Steger ( perancah kerja ) 0.01 Ls 75,000.00 750.00 d Ampelas 0.50 lbr 2,500.00 1,250.00 e Pembantu tukang 0.06 org 50,000.00 3,000.00 f Tukang cat 0.20 org 87,500.00 17,500.00 Jumlah 33,970.00 Dibulatkan 33,970.00 11 1 M2 PENGECATAN EXTERIOR a Cat tembok 0.36 kg 75,000.00 27,000.00 b Plamir tembok 0.16 kg 25,000.00 4,000.00 c Rol cat 0.01 bh 27,000.00 270.00 d Steger ( perancah kerja ) 0.01 Ls 75,000.00 750.00 e Ampelas 0.50 lbr 2,500.00 1,250.00 f Pembantu tukang 0.20 org 50,000.00 10,000.00 g Tukang cat 0.30 org 87,500.00 26,250.00 Jumlah 69,520.00 Dibulatkan 69,520.00 12 1 M2 MEMASANG WALLPAPER a Wallpaper 1.20 m2 23,400.00 28,080.00 b Lem Perekat 0.20 kg 32,000.00 6,400.00 c Pembantu tukang 0.02 org 50,000.00 1,000.00 d Tukang cat 0.15 org 87,500.00 13,125.00 Jumlah 48,605.00 Dibulatkan 48,600.00 13 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI
a Meni besi 0.10 kg 27,500.00 2,750.00 b Kuas 0.01 bh 14,000.00 140.00 c Pembantu tukang 0.02 org 50,000.00 1,000.00 d Tukang cat 0.20 org 87,500.00 17,500.00 Jumlah 21,390.00 Dibulatkan 21,390.00 14 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN CAT a Meni besi 0.10 kg 27,500.00 2,750.00 b Cat besi 0.13 kg 38,500.00 5,005.00 c Kuas 0.01 bh 14,000.00 140.00 d Ampelas 0.50 lbr 2,500.00 1,250.00 e Perancah kayu 0.01 m3 75,000.00 750.00 f Pembantu tukang 0.20 org 50,000.00 10,000.00 g Tukang cat 0.20 org 87,500.00 17,500.00 Jumlah 37,395.00 Dibulatkan 37,390.00
XVIII PEKERJAAN LISTRIK 1 PASANG 1 TITIK STOP KONTAK a Stop kontak 1.00 bh 21,500.00 21,500.00 b Kabel listrik NYM 3 x 2,5 mm 0.25 rol 450,000.00 112,500.00 c Aksesoris ( 20 % material ) 1.00 ls 22,500.00 22,500.00 d Pembantu tukang 0.20 org 50,000.00 10,000.00 e Tukang listrik 0.60 org 87,500.00 52,500.00 Jumlah 219,000.00 Dibulatkan 219,000.00 2 PASANG 1 TITIK LAMPU a Saklar 1.00 bh 21,500.00 21,500.00 b Kabel Listrik NYM 2 x 2,5 mm 0.25 rol 415,000.00 103,750.00
c Aksesoris ( 20 % material ) 1.00 ls 20,750.00 20,750.00 d Pembantu tukang 0.20 org 50,000.00 10,000.00 e Tukang listrik 0.60 org 87,500.00 52,500.00 Jumlah 208,500.00 Dibulatkan 208,500.00 3 PASANG 1 BUAH LAMPU SL a Lampu SL 1.00 bh 55,500.00 55,500.00 b Aksesoris ( 1 % alat ) 1.00 ls 555.00 555.00 c Tukang listrik 0.10 org 87,500.00 8,750.00 Jumlah 64,805.00 Dibulatkan 64,800.00 4 PASANG 1 BUAH LAMPU TL a Lampu TL 1.00 bh 55,500.00 55,500.00 b Aksesoris ( 1 % alat ) 1.00 ls 555.00 555.00 c Tukang listrik 0.12 org 87,500.00 10,500.00 Jumlah 66,555.00 Dibulatkan 66,550.00 5 PASANG 1 BUAH LAMPU BARET a Lampu Baret 1.00 bh 92,000.00 92,000.00 b Aksesoris ( 1 % alat ) 1.00 ls 920.00 920.00 c Tukang listrik 0.15 org 87,500.00 13,125.00 Jumlah 106,045.00 Dibulatkan 106,040.00 6 PASANG 1 BUAH LAMPU PIJAR a Lampu Pijar 1.00 bh 6,000.00 6,000.00 b Aksesoris ( 1 % alat ) 1.00 ls 60.00 60.00 c Tukang listrik 0.10 org 87,500.00 8,750.00 Jumlah 14,810.00 Dibulatkan 14,810.00 7 PASANG 1 BUAH LAMPU TAMAN
a Lampu Taman 1.00 bh 175,000.00 175,000.00 b Aksesoris ( 1 % alat ) 1.00 ls 1,750.00 1,750.00 c Tukang listrik 0.35 org 87,500.00 30,625.00 Jumlah 207,375.00 Dibulatkan 207,370.00 8 PASANG 1 BUAH PANEL a Panel Listrik standart untuk Rumah 1.00 bh 300,000.00 300,000.00 b Aksesoris ( 10 % alat ) 1.00 ls 30,000.00 30,000.00 c Tukang listrik 1.00 org 87,500.00 87,500.00 Jumlah 417,500.00 Dibulatkan 417,500.00 XIX PEKERJAAN WATERPROOFING 1 PASANG 1 M2 WATERPROOFING MEMBRAN a Material Primer 2.50 kg 2,450.00 6,125.00 b Waterproofing Membrane 1.10 m2 75,000.00 82,500.00 c Pengetesan ( 10 % material ) 1.00 ls 8,250.00 8,250.00 d Pembantu tukang 0.20 org 50,000.00 10,000.00 e Tukang batu 0.60 org 87,500.00 52,500.00 Jumlah 159,375.00 Dibulatkan 159,370.00 2 PASANG 1 M2 WATERPROOFING COATING a Pre treatment / Cleaning ( 10 % material ) 1.00 m2 4,400.00 4,400.00 b Bahan Waterproofing Coating 1.00 kg 44,000.00 44,000.00 c Kuas 3 " 0.25 bh 14,000.00 3,500.00 d Pembantu tukang 0.20 org 50,000.00 10,000.00 e Tukang batu 0.60 org 87,500.00 52,500.00 Jumlah 114,400.00 Dibulatkan 114,400.00 3 PASANG 1 M2 FLOOR HARDERNER
a Material Natural non Metalic 1.10 kg 44,000.00 48,400.00 b Aksesoris ( 10 % alat ) 1.00 ls 484.00 484.00 c Pembantu tukang 0.20 org 50,000.00 10,000.00 d Tukang batu 0.60 org 87,500.00 52,500.00 Jumlah 111,384.00 Dibulatkan 111,380.00