Jens Petur Bærentsen SimprentisMarcos Monteferrante

Schedule - Example

Monday 20 August 16.00 Introduction to OILSIM Exploration 16.30 Simulation Phase 1 starts (Find Basins) 17.00 Phase 1 Deadline. Phase 2 (First Licensing Round opens) 18.00 End Day 1Tuesday 21 August 16.00 Oilsim Exploration continues 16.30 First Licensing Round deadline 16.45 Phase 3 starts: Farm-In, Order Rig, Providers, Drilling

Location, Testing (continues the rest of the day) 17.45 2nd Licensing Round opens 18:15 2nd Licensing Round deadline 18:55 Simulation ends 18.55 Debriefing 19.00 End Day 2

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Schedule - Example

OilSim Field DevelopmentWednesday 22 August 10.00 Introduction to OilSim Field Dev. 10.30 Challenge 1 Reservoir characterization 11.00 Challenge 2 – Design Basis 11.30 Challenge 3 – Concept Solutions 12.00 End first part ------------------------------------------------------------------------- 16.00 Challenge 4 – Planning 16.30 End of the 1 Cycle (Results) 17.00 2nd Cycle starts - Challenge 1 Reservoir characterization 17.30 Challenge 2 – Design Basis 18.00 Challenge 3 – Concept Solutions 18.30 Challenge 4 – Planning 18.50 End of simulation 18.50 Debriefing 19.00 Course ends

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Schedule - Example

OilSim Exploration Competition

Thursday 23 August 09.30 Simulation Phase 1 starts (Find Basins) 09.40 Phase 1 Deadline. Phase 2 (First Licensing Round

opens) 10.20 First Licensing Round deadline 10.20 Phase 3 starts: Farm-In, Order Rig, Providers, Drilling

Location, Testing (continues the rest of the day) 10.40 2nd Licensing Round opens 11.10 2nd Licensing Round deadline 11.45 Simulation ends 11.45 Debriefing 12.00 End

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Overview

• Enhance your overall understanding of petroleum exploration

• Common platform to work on• Multidisciplinary challenge• You are an exploration team in

charge of a new petroleum province• Your task is to get maximum return

on investment (ROI)

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Money

• You start with $200M– You can apply for more money later

• Earnings:– Net value of the oil fields discovered– MINUS costs (surveys, wells, etc.)

• Winning team: – highest return on investment (ROI)– ROI = Earnings / Funds received

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Learning Points

• Where and how to find oil• Surveys used in exploration• Licensing rounds• Farm-in and Partnerships• Rigs and Sub-contractors• Reducing uncertainty• Economically viable volumes

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Oil & Gas Industry

• Upstream– Exploration– Production

• Downstream– Refining– Distribution

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Structure

• Phase 1: Find Basins• Phase 2: Bid for Licences• Phase 3: Drilling

– 3.1 Farm-in– 3.2 Order Rig– 3.3 Select Providers– 3.4 Select Position– 3.5 Testing

Jens Petur Bærentsen SimprentisMarcos Monteferrante

MapColumns (1 to 112)

Row

s (1

to 1

52)

1000 m deep

Cell (112,89)

Block 168

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Login

www.oilsim.com

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Main screen

Jens Petur Bærentsen SimprentisMarcos Monteferrante

First task

• Find the 3 basins in the area• Basin: Sedimentary rocks in the deep

subsurface where oil and gas was generated

• Procedure1.Buy and study magnetic and gravimetric

surveys2.Submit 3 block numbers; one for each basin

centre

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Surveys

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Gravimetric surveys

• Gravimetric surveys show the gravity in the sub-surface

• Sedimentary rocks (“basins”) have lower densities than the surrounding crystalline rocks

• Low gravity (green) -> Basins• High gravity (red) -> Crystalline

rocks

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Gravimetric surveys

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Magnetic surveys

Jens Petur Bærentsen SimprentisMarcos Monteferrante

More detail

NorthEast

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Quarter map survey

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Enter decision

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 1

• Possible to get between 0 and 100 knowledge points (KP)– KP’s can be used e.g. when you apply

for money

• Must be solved before deadline• After the deadline, all submissions

are evaluated

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 1 solved

• All basins are located• Message sent to all teams with the

results• Oil and gas is close to the basins• Next step: First licensing round

– The blocks around one of the basins are on offer

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Second task

• Bid to get an exploration licence• Exploration licence: A permission from

the Government to explore a block• Procedure

1. Buy and study Common Risk Segment Maps and 2D Seismic surveys

2. Submit 3 bids– Block number– Amount offered to Government (“bonus”)

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Migration

Basin

Prospect

Play

Migration

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Prospect

Migration

ReservoirSeal

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Real Seismic

                                                                                                                                                                       

Jens Petur Bærentsen SimprentisMarcos Monteferrante

2D Seismic surveys

• A 2D Seismic survey is a cross section of the geological layers– along either a column or a row

• Is used for locating prospects• Look out for traps• Three separate geological layers

Jens Petur Bærentsen SimprentisMarcos Monteferrante

2D Seismic example

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Prospects

Top of sealing rock

Top of reservoir rock

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Cross-sections

Column

Row

Prospect, ReservoirBasin, Source

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Wells

179

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Remarks

• In OILSIM, there is only one type of trap: the four-way closure structural trap– in reality, there are several other types

• Three prospecting systems– 3. Eocene (1.500 m below seabed)– 2. Paleocene (2.500 m -)– 1. Cretaceous (3.500 m -)

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Common Risk Segment

• Prospect probability– Red: low– Orange: medium– Green: high

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Tips

• Use CRS to see which blocks to study

• Buy and study many 2D surveys• Focus on shallow water blocks

– It is cheaper to drill exploration wells in shallow water

– It is more economically viable to produce oil and gas in shallow water

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Enter bid

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Remarks

• Minimum bonus: 1000000• You will only get one licence• Highest bid gets the licence• If you lose on all three blocks, you

will get a random licence (of the ones that are left)

• Do submit 3 bids -> more KP’s and higher probability for success

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 2

• Submit your bid before the deadline

• After the deadline, all bids are evaluated, and each team gets one and only one licence

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 2 solved

• Every team has got one exploration licence

• Message sent to all teams with the results

• Knowledge Points: a measure of how prosperous the blocks the team bid for were

• Next step: Farm-in

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Farm-in & -out

• The headquarters of you company has evaluated the licence that you got awarded

• Although the possibility of finding oil is fair, the costs involved are large, and the headquarters wants you to spread the risk.

• This is accomplished by:– investing in other licences (farm-in), and– letting other invest in your licence (farm-out)

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 3.1 Farm-out

• Get other’s to invest 20% or more in your licence (“farm-out”)

• You can only send farm-in offers (!)– Offers to buy parts of other licences

• Procedure for farming in:1.Study 2D Seismic surveys

2.Submit one offer for each viable licence– Amount offered– Share wanted (in whole %)

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Farm-in

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Send an offer

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Partnerships

• Partners pay their share of all future costs incurred by the partnership.

• Partners receive their share of the net proceedings from any oil found on the licence

• The operator team takes all decisions regarding acquirement of 3D seismic, drilling of wells and testing of wells

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 3.1

• Study 2D seismic surveys of the other licences

• Submit your bids– Minimum amount 100,000 for 1%

• You are not allowed to drill before at least 20% of your licence has been farmed out

• You can farm-in & -out at any time• Partners in a block get all info about

drilled wells and discovered prospects

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 3.1

• Partnerships will be established every time a seller accepts an offer

• On the main page, you can see all the licences– The licences you operate– The licences you have invested in– Other licences

• Next task: order rig

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 3.2 Rig

• 3 rig types– Drillships– Semi-submersibles– Jack-up rigs

• Different water depths, Different day rates– Rig cost = drilling days * day rate

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Available Rigs

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Drilling days

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Drilling Depths

Seabed

3500 m below seabed

Layer 3

Layer 2

Layer 1

1500 m below seabed

2500 m below seabed

“water depth”

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Seabed Depth

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 3.2 Rigs

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Rigs

• Limited number of rigs available• You can order a rig

– use it within 20 minutes

• Not enough for all– Wait in a queue, if another team is

using the rig

• Rig day rates are dynamic

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 3.3 Providers

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Track Record

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Select Providers

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 3.4 Position

• You have to choose where to drill– Which cells?

• ..and how deep to drill– Either to the Eocene horizon– Through the Eocene to the Paleocene

horizon, – or through the Eocene, the Paleocene,

and to the Cretaceous horizon

Jens Petur Bærentsen SimprentisMarcos Monteferrante

3D Seismic

• Shows the structure:– in one (of the three) horizons– in one block

• Look out for “tops”– a top = a trap = a prospect

Jens Petur Bærentsen SimprentisMarcos Monteferrante

3D Seismic

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Three targets

Layer 1

Layer 2

Layer 3

Column 60, Row 79

Column 60, Row 78

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Select Positions

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Summary

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Drilling position 3

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Drilling position 2

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Conf. & Budget

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Drilling results

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Drilling result

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Task 3.5 Testing

• If you discover a field-> decide whether you want more information about that field

• You get more information by doing a production test (and other tests)

• Tests take 10 days per field• Tests have the same day-rate as the

drilling (you use the same providers)

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Test decision

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Field value

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Prospects

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Licence Value

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Appraisal

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Narrowing ranges

• First well:– 0 to 572 MBO (after drilling)– 11 to 266 MBO (after testing)– Proven volume: 11 MBO

• Second well– 11 to 233 MBO (after drilling)– 35 to 210 MBO– Proven volume: 35 MBO

Jens Petur Bærentsen SimprentisMarcos Monteferrante

Continue...

• Drill appraisal wells to narrow the uncertainty (get proven volumes)

• Drill into other prospects• Farm-in and -out• Two additional licensing rounds• Apply for more money, if you run

out of cash

• Winner: highest ROI

Recommended