China Offshore Wind Development Status and Outlook Chinese Wind Energy Association Qin Haiyan, Secretary General 2011.09.22 1

China wind energy association

Embed Size (px)

Citation preview

Page 1: China wind energy association

China Offshore Wind Development Status and Outlook

Chinese Wind Energy Association

Qin Haiyan, Secretary General

2011.09.22

1

Page 2: China wind energy association

• About CWEA

• China Wind Power Sector Achievements

• Offshore Wind--Next Hotspot in China

• Offshore Wind Outlook and Sino-British Cooperation

2

Content

Page 3: China wind energy association

1981年成立的非政府团体,目前拥有800多家团体会员,1400多名个人会员.

Chinese Wind Energy Association(CWEA )was founded in 1981, it is a non-profit social

entity. At present, the members consist of more than 800 corporations and more than 1400

individuals.

参展商规模超过500家;

参观人数规模超过3万;

展出面积45000平米.

组织开展风电学术培训;

组织开展技术研讨会;

组织开展丏项讨论会.

学术培训

Organizing academic training, various kinds of

technical workshop, and special seminar of wind

power.

There will be more than 500 exhibitors and

30,000 visitors in the CWP of 2010, Exhibition

area: 45,000 square meters.

About Chinese Wind Energy Association(CWEA)

北京国际风能大会

Page 4: China wind energy association

风能丏业权威刊物;

率先公开出版;

月刊,发行量月均5000余册.

开展风电产业发展研究;

开展风电产业统计;

提供政府决策参考;

丏项定制研究报告;

行业资讯发布.

《风能》杂志

组织考察团国外风电场考察;

组织考察团国外经验交流;

组织参加国外风电展会.

组团学术考察

风电发展研究

Organizing investigation groups to visit

foreign wind farm, exchange information

with experts, and take part in the wind power

exhibition .

Professional publications in wind power

industry: Wind Energy;

First openly published;

Monthly, the volume of circulation is more

than 5,000 copies.

Researching the development of wind power;

To carry out industry statistics;

Providing information for the government

decision-making;

Professional reports tailed to the industry;

Industry News release.

About Chinese Wind Energy Association(CWEA)

Page 5: China wind energy association

• About CWEA

• China Wind Power Sector Achievements

• Offshore Wind--Next Hotspot in China

• Offshore Wind Outlook and Sino-British Cooperation

5

Content

Page 6: China wind energy association

Installed capacity of China wind power doubled in five consecutive years

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

40.0

45.0

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010

Annual 0.1 0.1 0.1 0.2 0.5 1.3 3.3 6.2 13.8 18.9

Total 0.4 0.5 0.6 0.8 1.3 2.6 5.9 12.0 25.8 44.7

Unit: GW

Page 7: China wind energy association

Become No.1 by New and Cumulative Capacity in 2010

Page 8: China wind energy association

Top 10 wind turbine manufacturers in the world(2010)--New installed capacity

中国风电设备制造业

逐步形成

4个企业步入世界前十

Wind manufacturing

industry grow up

4 enterprises step into

the top 10 list

Source: BTM

Wind power equipment manufacturing developing rapidly

Page 9: China wind energy association

9

Top 15 wind farm developers in the world--Cumulative capacity by end of 2010

Source: BTM

Rapid development of wind farms

6家风电场开发商步

入世界前十五

6 China Developers

Ranked TOP 15 in

2010

Page 10: China wind energy association

• About CWEA

• China Wind Power Sector Achievements

• Offshore Wind--Next Hotspot in China

• Offshore Wind Outlook and Sino-British Cooperation

10

Content

Page 11: China wind energy association

Offshore Wind, Next Hotspot

2000年以来,海上风电开发步伐

加快,逐步成为新趋势。

开发海上风电也是中国风电开发

的重要方向。2005年以来,中国逐步

开始中国海上风电示范项目建设,幵通

过政策规划等不断推进海上风电产业的

发展。

3,048

2,064

1,479

1,106

787695

605515

25686

+49%

2010 2009 2008 2007 2006 2005 2004 2003 2002 2001

2001-2010 Global Offshore Wind Installations

Source: GWEC,EWEA, CWEA

Unit:MW

CAGR

• offshore wind is emerging and

becoming a new trend Since 2000.

• Offshore wind is one important

part of China wind development

strategy. Since 2005, China started

offshore wind pilot project and

accelerated offshore wind power

under policy support.

Page 12: China wind energy association

12

Shanghai Donghai Bridge Wind Farm—the 1st Offshore Wind Farm

Shanghai Donghai Bridge Wind Farm Phase I,installed 34 units Sinovel 3MW offshore wind turbinest,of

which 3 turbines were generating power in 2009 and all of them got grid connected in July 2010. As late of Sept.

2011, Donghai Bridge offshore generated more than 20 GWh 。

Shanghai Donghai Bridge Wind Farm Phase I

Sinovel 5MW Offshore Wind Turbine Installed in Shanghai in Sept

Offshore Wind Pilot Projects

Page 13: China wind energy association

13

龙源江苏如东海上潮间带试验风电场位于如东环港外滩离岸3~7km的潮间带区域。这不仅是中国第一个海上潮

间带试验风场,也是世界首个潮间带试验风场。

Longyuan Rudong Intertidal Wind Farm located in the areas, 3-7km distance from the coastline. It’s

the 1st intertidal experiment wind farm in China and also the entire world.

Longyuan Jiangsu Intertidal Wind Farm Phase I

Intertidal Wind Farms

Offshore Wind Pilot Projects

Page 14: China wind energy association

14

1st Round Offshore Wind Concession Projects

滨海海上风电项目,装机规模300MW,

(大唐新能源,华锐, 0.7370元/kWh )

Binhai Offshore 300 MW

Datang, Sinovel, 0.7370 RMB/kWh

射阳海上风电项目,装机规模300MW

Sheyang Offshore 300MW

CPI, Sinovel, 0.7047 RMB/kWh

大丰潮间带风电项目,装机规模200MW

Dafeng Intertidal 200MW

Longyuan, Goldwind, 0.6396

RMB/kWh

东台潮间带风电项目,装机规模200MW Dongtai Intertidal 200 MW Luneng, SEWIND, 0.6235 RMB/kWh

Page 15: China wind energy association

15

No. Name Developer Capacity(MW)

1 东海大桥

Donghai Bridge Offshore Wind Farm

东海风电 (Donghai Offshore)

102

2 绥中

CNOOC Suizhong 36-1 中海油 CNOOC

1.5

3 三峡潮间带(一期) Yangtze New Energy

Intertidal

长江新能源 Yangtze New Energy

4.5

4 荣成华能潮间带

Rongcheng Intertidal 华能

Huaneng 6

5 鲁能潮间带

Luneng Intertidal 鲁能

Luneng 2

6 龙源示范一期

Longyuan Intertidal Phase I 龙源

Longyuan 34

7 中电投大丰 CPI Dafeng

中电投 CPI

2

8 灌云燕尾港

Guanyun Yanweigang 中能联合

8

9 道达重工试验项目

DDHC Intertidal 道达重工

DDHC 2.5

合计 162.5

Offshore Wind Project built in China

Page 16: China wind energy association

3MW and above offshore wind turbines R&D speeding Up

More than 20 companies involved in offshore wind turbine design and manufacture, of which

15 products had their 1st prototype so far. Research on bigger turbines (>10MW) have been

conducted preliminarily.

Offshore Wind Supply Chain

Page 17: China wind energy association

17

Mingyang SCD 3.0 SEWIND 2.0 Envision 2.0

United Power UP100

Haizhuang 2.0

Goldwind GW2500 SANY 2.0 XMEC XE2500 Sinovel SL3000

Wind Turbines Installed at intertidal zones

Offshore Wind Supply Chain

Page 18: China wind energy association

WTG Manufacturers Offshore Wind Power Base

Shandong︱Laizhou

Tianjin︱Vestas V112

Jaingsu︱Dafeng

Jiangsu︱Dongtai

Jiangsu︱Nantong

Shanghai︱Lingang

Jiangsu︱Lianyungang United Power

Jiangsu︱Yancheng

Shanghai Donghai Bridge

Offshore Wind Supply Chain

Page 19: China wind energy association

19

海上风电机组的运输和施工是海上风电场建设的一个重要步骤,海上安装船及其它各种设备的发展成为海

上风电产业链建设中的重要环节。

Offshore wind equipment logistic and construction is obviously important part in offshore wind farm development.

Installation vessels are becoming the key sector in offshore wind construction.

2003年12月,在中国生产的世界第一艘专用海上风电机组安装船“Mayflower Resolution”交付使用。

The very 1st vessel for offshore wind made by China Shanhaiguan Shipyard, Mayflower Resolution had been

delivered in 2003 and employed in many offshore wind porjects.

Breakthrough in logistic and construction equipment

Offshore Wind Supply Chain

Page 20: China wind energy association

20

浮吊 Floating Crane

自升自航式 Jack-Up

基础、桩基&电缆敷设 Foundation and cable laying

注:所列仅为部分船舶 Note: Not all vessels were listed.

蓝疆号 Lanjiang 华天龙号 Huatianlong 四航奋进号 Fenjin

COSCO-Sea Installer DDHC 7000T Longyuan Zhenhua800T Jack-up

南通海建-海洋32号 NTOC-Haiyang 32#

南通海建-海洋11号 NTOC-Haiyang 11#

南通海建-海洋29号 NTOC-Haiyang 29#

Vessels in operation and under R&D in China

Offshore Wind Supply Chain

Page 21: China wind energy association

• About CWEA

• China Wind Power Sector Achievements

• Offshore Wind--Next Hotspot in China

• Offshore Wind Outlook and Sino-British Cooperation

21

Contents

Page 22: China wind energy association

22 China offshore wind power density map depth from 5-25 m

Rich offshore wind resource Make a sense

Depth 104*km2 GW

5-25m 18.8 190

25-50m 20.6 210

根据中国气象局2009年发布的全

国风能资源详查和评价初步成果,中国近

海50米高度层达到3级以上风能资源可满

足的风电装机需求约4亿千瓦。

According to CMA wind energy

resource assessment preliminary results,

China offshore wind technically potential at

50 meter high could be 400 GW.

近海50米高度层,3级及以上风能资源覆盖面积及

风能资源潜在开发量

Table: 50 meters height, level 3 and above wind

resource technical potential and areas

Page 23: China wind energy association

23

东部沿海地区是中国经济发达地区,电力需求巨大,电网基础好。 East China and South China have advanced economy where demand higher electricity

load and better gird infrastructure.

Close to load center where get better grid connection

Page 24: China wind energy association

24

Support by Policy and Regulations

Offshore wind development regulation and guidelines

年份Year 政策名称

Regulation 政策要点 Key points

2010

《海上风电开发建设管理暂行办法》

Interim measures for the development and construction

of offshore wind power management

规范了上风电发展规划、项目授予、项目核准、海域使用和海洋环境保护、施工

和竣工验收等工作:

国家能源主管部门负责组织全国海上风电开发规划以及配套电网工程规划

编制、项目开发权授予、项目核准以及验收等工作;国家海洋行政主管部

门负责海上风电开发建设海域使用和环境保护的管理和监督等

海上风电工程项目优先采取招标方式选择开发投资企业——特许权招标

海上风电项目必须经过核准幵取得海域使用权后,方可开工建设

Specifications on offshore wind plan, consents, approval process, ocean

utilization, ecological protection, project construction & inspection:

NEA take charge of making China offshore wind development and grid

infrastructure construction plan, projects consent& approve and project

inspection, National Bureau of Oceanography take charge of ocean

utilization and ecological protection management and supervision

Concession bidding preferentially used for choosing developers

Projects only could start construction after approved and acquired

ocean utilization files

2011

《海上风电开发建设管理暂行办法实施细则》

Interim measures for the development and construction

of offshore wind power management regulations

对海上风电规划的编制与审查、海上风电项目预可研和可研阶段的工作内容和程

序、建设运行管理中的要求等作了具体规定

Specifications on offshore wind farm plans formation and , feasibility

study and work under feasibility study, construction management

Page 25: China wind energy association

25

海上风电开发规划明确市场规模 Clear Targets for Offshore Wind

Support under Policy and Long term target

5-10年左右的时间打好基础,具备大规模开发的条件

Good preparation for large scale development in 5 to 10 years

在更长的时间里,实现海上风电大规模开发

Larger scale in longer term

Page 26: China wind energy association

26

Finance Shortage

海上风电发展 Offshore Wind

- 金融危机后全球经济尚未复苏 Financial Crisis Impact

- 投资者短期投资信心不足 Investor lack confidence - 融资渠道不畅 Financing Channel constraints

Other

- 海上风电相关技术人才缺乏 Skilled labor Not Enough

- 海洋生态环境协调问题 Ocean Ecological protection

- 多行业用海统筹规划:交通、航运、军事、渔业等 Overall planning of transport , military , fishing & etc.,

- 支持海上风电发展的近期和长期

政策环境是否稳定

Policy supporting offshore wind

unstable

- 审批流程繁杂、冗长

Consent process complexity

Regulation Technology

- 运行环境复杂,技术难度高 Complicated operation environment& higher technology barrier

- 建设成本远高出陆上风电 CAPEX much higher than onshore - 发电成本降低 LCOE decrease speed

Challenges Overhead

Page 27: China wind energy association

27

0.25

30

2010 2015 2020

1.3

8.7

18

2010 2015 2020

China

UK

Unit: GW

Unit: GW

Sino-British Offshore Wind Bilateral Cooperation A Win-win Situation

UK now take lead in offshore wind and has a

lot of experiences which could be reference

for China rapid offshore wind development in

the next few years.

At the meantime, UK and China both have a

big long term offshore wind target to achieve.

UK and China may have good cooperation in

regulation, resource assessment, site

investigation, turbines, engineering, wind

farm investment, operation, labor training

and other areas and hence to achieve both

target by 2020.

Page 28: China wind energy association

28

时 间/Time:2011.10.19-2011.10.21

网 址/Website:www.chinawind.org.cn

主办单位/Organizers:

全球风能理事会

(Global Wind Energy Council, GWEC)

中国资源综合利用协会可再生能源专业委员会

(Chinese Renewable Energy Industries Association, CREIA)

中国可再生能源学会风能专业委员会

(Chinese Wind Energy Association ,CWEA)

谢 谢!

Thanks !