Upload
vuongque
View
216
Download
2
Embed Size (px)
Citation preview
भारत सरकार
GOVERNMENT OF INDIA
विद्युत मंत्रालय
MINISTRY OF POWER
कें द्रीय विद्युत प्राविकरण
CENTRAL ELECTRICITY AUTHORITY
दविण िेत्रीय विदु्यत सवमवत
SOUTHERN REGIONAL POWER COMMITTEE
ददनाकं 25 जुलाई 2014 को चेन्नई मैं सम्पन्न द क्षे वि स के टी सी सी की चौबीसिीीं बठैक के कार्यितृ
MINUTES OF THE 24TH MEETING OF TCC OF SRPC
HELD AT CHENNAI ON 25TH JULY 2014
बेंगलरू
BANGALORE
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 1 of 83
CONTENTS 1. INTRODUCTION ................................................................................................................................ 3
2. CONFIRMATION OF THE MINUTES OF 23rdMEETING OF TCC .......................................................... 6
3. UTILIZATION OF 220 kV UPPER SILERU-BALIMELA (SR-ER), LOWER SILERU – BARASUR (SR-ER)
& CHIKKODI – KOLHAPUR (SR-WR) LINKS AS INTER-REGIONAL LINKS ............................................ 6
4. FIXING UP LIMIT FOR 400 KV KOLAR-HOSUR D/C LINES ................................................................ 10
5. SYNCHRONISATION OF SR WITH NEWGRID / 765 kV RAICHUR-SHOLAPUR LINE ......................... 13
6. UPCOMING TRANSMISSION SYTEM, TRANSMISSION CONSTRAINTS & LOADGENERATION
BALANCE ........................................................................................................................................ 18
7. AUGMENTATION OF TALCHER- II TRANSMISSION SYSTEM ........................................................... 25
8. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINTVENTURE& UMPP ................................................... 26
9. COAL STOCKPOSITION IN THERMAL STATIONS OF SOUTHERN REGION ....................................... 33
10. LTA QUANTUM IN RESPECT OF UPCL / SCHEDULING OF POWER TO PUNJAB FROM UPCL
(HASSAN – MYSORE 400 KV D/C LINE UNDER SYSTEM STRENGTHENING SCHEME) ..................... 35
11. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR ............................................... 38
12. AVAILABLE TRANSFER CAPABLITY (ATC) /TOTAL TRANSFER CAPABLITY (TTC) .............................. 40
13. IEGC RELATED ISSUES ..................................................................................................................... 45
14. OPERATION OF FILTERS AT HVDC KOLAR ...................................................................................... 58
15. KKNPP RELATED ISSUES ................................................................................................................. 59
16. ALTERNATE / RELIABLE AUXILIARY SUPPLY AT HVDC BHADRAWATHI .......................................... 61
17. PSS TUNING /SYSTEM STUDIES ...................................................................................................... 62
18. IMPLEMENTATION OF ENQUIRYCOMMITTEE RECOMMENDATIONS ............................................ 62
19. REVIEW OF PERFORMANCE OF ULDC SCHEME ............................................................................. 65
20. NON-PAYMENT OF TRANSFORMER CHARGES TO TN BYSOUTHERN REGION CONSTITUENTS
AND PENDING ARREARS PAYMENT BETWEEN BENEFICIARY STATES IN SR .................................. 66
21. OUTSTANDING DUES BETWEEN WR & SR ..................................................................................... 68
22. GRID OPERATION ........................................................................................................................... 69
23. DEMAND VARIATION (Peak Vs Off-peak) ...................................................................................... 71
24. FREQUENCY OF OPERATION OF SOUTHERN GRID ......................................................................... 73
25. TRIPPING DETAILS .......................................................................................................................... 73
26. OPERATION OF TALCHER-KOLAR HVDC TRANSMISSIONSYSTEM IN GROUNDRETURN MODE ..... 74
27. PHYSICAL AND CYBER SECURITY/ CRISISMANAGEMENT PLAN/ BLACKSTART PROCEDURES ....... 75
28. MODIFICATIONS IN OPGW LINKS UNDER FIBRE EXPANSION PROJECT OF SR ............................... 76
29. REPLACEMENT OF PRIMARY MULTIPLEXER EQUIPMENTS INSTALLED UNDER SR-ULDC
PROJECT ......................................................................................................................................... 76
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 2 of 83
30. DIFFERENCE IN COMPUTATION OF CAPACITY CHARGES OF NTPC STATIONS AS PER NEW
CERC REGULATIONS (2014-19) ...................................................................................................... 76
31. ARBITRARY CURTAILMENT OF STOA AND DENIAL OF URS ............................................................ 77
32. PREPAREDNESS FOR BAD MONSOON............................................................................................ 77
33. UTILIZATION OF EXISTING ROW OF 66KV KUTHUMUNDA – UPPATTY FEEDER .......................... 78
34. PROGRESS OF VARIOUS TRANSMISSION AND GENERATING CAPACITY WORKS ........................... 78
35. START UP POWER DRAWAL BY IL&FS TAMIL NADU POWER COMPANY LIMITED......................... 78
36. UDUMALPET &GAZUWAKA ICTs - STATUS OF CERC PETITION ...................................................... 79
37. SCHEDULING POWER TO TELANGANA & ANDHRA PRADESH FROM SHARED STATIONS, IPPs
AND SIMHADRI STPS STAGE-I ........................................................................................................ 80
38. COLLECTION OF DATA REGARDING POWER SUPPLY TO RURAL AREAS ........................................ 81
39. SNAPPING OF POWER CONDUCTORS OVER TRACTION LINES- SOTHERN RAILWAY ..................... 82
40. TRANSMISSION LINE PATROLLING PROTOCOLS/ GUIDELINES ...................................................... 82
41. DATE & VENUE OF THE NEXT TCC MEETING.................................................................................. 83
42. VOTE OF THANKS ........................................................................................................................... 83
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 3 of 83
SOUTHERN REGIONAL POWER COMMITTEE
BANGALORE
MINUTES OF THE 24th
MEETING OF TCC OF SRPC HELD AT
CHENNAI ON 25th
JULY 2014
1. INTRODUCTION
1.1 The 24th
Meeting of Technical Coordination Committee of SRPC was held at
Chennai on 25th
July 2014. The list of participants is furnished at Annexure-I.
1.2 Shri C.Kaliaperumal, Chief Engineer/Operation, TANTRANSCO on behalf of
TANTRANSCO, TANGEDCO & TNEB expressed immense pleasure and privilege
in welcoming Shri S.Sumanth, Chairperson TCC, Shri S.R.Bhat, Member Secretary
(I/c), SRPC and other TCC Members to the 24th
Meeting of TCC. He also extended a
Special Welcome to the Members from the newly formed State of Telangana. He
stated that main purpose of grid security was to ensure availability of power supply.
He requested Honorable Members of the TCC to kindly deliberate and evolve
measures to ensure reliable power supply. He pointed out that from the year 1965
onwards; incidents of major grid failure around the world were only around five in
number. There had been no instances of major grid failure in Southern Region. He
requested Managing Director, TANTRANSCO to deliver a few words about the
growth and glorious achievements of TNEB.
1.3 Shri R.V.Sundararaman, Managing Director, TANTRANSCO welcomed all the
delegates to the Meeting. He said that initially there was Composite Madras State
Electricity Department with British Engineer John G. Henry Howard as the Chief
Electrical Engineer. TNEB was constituted in the year 1957 and came to be known
as “Madras State Electricity Board” with Padmashri V.P.Appadurai as Chief
Engineer (Electricity). The first hydro generating station at Pykara (6.65 MW) was
started in 1932 which is still running now. In 1971, the first Thermal power plant at
Ennore was started with 60 MW capacity. First gas station was started in 1992 at
Narimanam. The process of wind power generation started in the year 1986 and 120
wind mill generators with a total capacity of 19 MW were commissioned during the
period 1986-93. In 1992, the power sector was opened to private participation and
GMR Vasavi was the first to establish independent power project. Kadamparai
pumped Storage scheme with an installed capacity of 4x100MW is useful during
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 4 of 83
peak hour operation. Tamil Nadu is the first state to achieve “all village
electrification” in India. TNEB also stood first in maximum utilization of fly ash in
thermal stations. As on date, the installed capacity of the state was 11,884 MW
serving a consumer base of about 2.52 crore. After a long journey of 53 years, on
01.11.2010 TNEB was restructured into TNEB Ltd., (holding company),
TANGEDCO Ltd. & TANTRANSCO Ltd. Most of the Thermal generating stations
in TN were running at PLF between 80 – 92% even after completion of 25 years
service.
Managing Director, TANTRANSCO proudly announced charging of the 362 KM
long 400 kV Pugalur- Kalavinthapattu line on 23rd
July 2014. This line was part of
the backbone transmission network of Tamil Nadu. 400 KV Kayathar – Karaikudi –
Pugalur line works were nearing completion and would be commissioned shortly.
He added that an all time high peak demand of 13,775 MW had been met on 24th
June 2014 with the help of wind energy with Energy consumption of 294 MU on
20th
June 2014. Recently about 2,500 MW of capacity had been added. Medium term
power purchase agreement up to 2016 for 500 MW and also 15 years long term
power purchase agreement of 3,330 MW had been tied up. A target of 3,000 MW in
3 years for solar energy resources had been planned and was being executed. The
installed capacity of Wind Power in Tamil Nadu as on date was 7,276 MW.
Around 134 sub stations in various places had been commissioned during the
period 2011 to 2013. Around 3,363 circuit KM of EHT lines was charged during
the period 2011 to 2013. The transmission infrastructure in Chennai was being
strengthened at a project cost of Rs. 5,000 Crores with a loan assistance of Rs.3,572
Crores from JICA. Tamil Nadu was going for a long underground cable system in
Chennai city soon. In order to evacuate power from other states, Tiruvalam
substation was under construction and was expected to be ahead of schedule. For the
purpose of evacuation of wind power, 400 kV Substations at Thappagunda,
Anaikadavu and Rasipalayam along with associated lines were under execution.
Schemes at a cost of about Rs.1,593 crores with financial assistance from the
German Government through KFW would be taken up.
Anticipated future growth would be met through addition of about 6,360 MW of
thermal power during the period 2016-2020. Consumers would then be getting
reliable and quality power as per TNEB motto. A copy of the Presentation is
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 5 of 83
furnished at Annexure- II. The dynamic leadership of Chairman, TNEB in putting
various projects in Tamil Nadu on fast track mode was also placed on record.
1.4 Shri S.R.Bhat, Member Secretary I/c, welcomed Shri S.Sumanth, Chairperson TCC
& Director (Transmission), KPTCL, other Members and Participants to the 24th
Meeting of TCC. On behalf of TCC, he also placed on record the services rendered
by Shri Mohd. Anwaruddin, Director (Grid & Tr. Management), APTRANSCO the
outgoing Chairperson TCC. He thanked Shri R.V.Sundararaman, MD,
TANTRANSCO, Shri C. Kaliaperumal, CE/Operation & Shri Raja Gunanidhi, EE
and other officers from TANTRANSCO/TANGEDCO for the excellent
arrangements made for the Meeting. TANTRANSCO/TANGEDCO had provided
wonderful ambience for conduct of the Meeting and for comfortable stay.
1.5 Shri S.Sumanth, Chairperson TCC & Director (Transmission), KPTCL welcomed
all the Members to the Meeting. He thanked Tamil Nadu Electricity Sector for
hosting the Meeting in a nice atmosphere. He congratulated Shri R.V.Sundararaman
for taking over as Managing Director of TANTRANSCO. He also welcomed the
Directors from the State of Telangana.
1.6 TCC welcomed the following new Members:
Shri S.V.Govindaraju, Chief Engineer (LD), KPTCL
Shri M.G. Suresh Babu, Additional Director (Projects), PCKL
Shri R.V.Sundararaman, Managing Director, TANTRANSCO
Shri Rakesh Samuel, General Manager, NTECL, Vallur STPS
Shri Sunil Agrawal, Director, GMR Energy Trading Ltd.
1.7 TCC also placed on record the excellent services rendered by the following
outgoing Members:
Shri T.Chandrasekhar, Director (Opn), APNPDCL
Shri H.S.Keshavamurthy, Chief Engineer (E), SLDC, KPTCL
Shri S.Akshayakumar, Managing Director I/c, TANTRANSCO
Shri K.Viswanathan, Director ( Opn), TANTRANSCO
Shri Rajendra S.Mirji, Tata Power Trading Company Ltd.
1.8 TCC placed on record the significant contribution of PGCIL in enhancement of the
transmission capacity in Southern Region. PGCIL had recently commissioned a
number of transmission elements (400 kV Nellore – Tiruvalam, 400 kV Thiruvalam
– Kalavinthapattu etc.) under the able leadership of Shri V.Sekhar, ED, SRTS-I &
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 6 of 83
Shri N.Ravi Kumar, ED, SRTS-II. 765 kV Raichur – Sholapur Circuit under TBCB
had also been recently commissioned with the untiring efforts of PGCIL.
1.9 Member Secretary I/c, SRPC observed that SR was facing around 3,200 MU of
deficit in hydro reservoir storage on account of the inadequate monsoon. TCC
would need to finalize suitable measures to ensure secure grid operation in these
circumstances.
2. CONFIRMATION OF THE MINUTES OF 23rd
MEETING OF TCC
The Minutes of 23rd
Meeting of Technical Coordination Committee of SRPC held
on 14th
March 2014 at Chennai were confirmed.
3. UTILIZATION OF 220 kV UPPER SILERU-BALIMELA (SR-ER), LOWER
SILERU – BARASUR (SR-ER) & CHIKKODI – KOLHAPUR (SR-WR)
LINKS AS INTER-REGIONAL LINKS
3.1 220 kV Upper Sileru-Balimela (SR-ER)
3.1.1 In the 24th
Meeting of SRPC it had been agreed that trial operation of 220kV Upper
Sileru – Balimela line would be carried out for about three months with a caveat
that generation would not be backed down. Line could be operated (switched
on/off) as per requirements of APSLDC.
3.1.2 Subsequently the Operational Procedure had been finalized by SRLDC in
consultation with the stakeholders.
3.1.3 Trial operation of 220 kV Upper Sileru – Balimela line had been carried out on
21stApril 2014 by keeping 2 units of Balimela generating station radially
connected with AP system through split bus arrangement at Balimela. The line
was in service form 1230 hrs.to 1745 hrs. Power flow from Balimela to Upper
Sileru was maintained up to 100 MW. APTRANSCO had expressed concern that
it had taken more than ½ hour for exchanging the code and for Odisha SLDC to
take action. SRLDC had assured for review of the process &stated that they would
suitably take up with NLDC / ERLDC for quicker exchange of codes.
3.1.4 Closing of this line had also been stressed in the Meeting taken by Secretary
(Power) on 6th
May 2014 to discuss preparedness of the power sector to tackle
effects of subnormal monsoon.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 7 of 83
3.1.5 AP had placed order for purchase of 150 MW of power on RTC basis from
GRIDCO for the period from 15th
to 30th
June 2014. 220 kV Balimela-Upper
Sileru line was closed from Upper Sileru (AP end) and open at Balimela end.
GRIDCO had not supplied any power to Andhra Pradesh citing shortages due to
unit outages etc.
3.1.6 In the Meeting MS I/c, SRPC informed that a Meeting (through video conference)
with participation of APTRANSCO, TSTRANSCO, OPTCL, GRIDCO, SRPC
Secretariat, ERPC Secretariat, SRLDC, ERLDC and NLDC had been conducted
on 18th
July 2014. It had been decided to initially avail power through UI
mechanism and subsequently scheduled transactions could take place. Approval of
the Govt of Odisha was expected by 28.07.2014.The Minutes of the Meeting is
furnished at Annexure-III.
3.1.7 ED, NLDC said that in view of the deficit in SR and also on account of limited
inter regional corridor availability, operationalization of 220 kV Balimela-Upper
Sileru and Chikkodi – Kolhapur lines had been considered. Efforts were however
on to enhance the inter regional transmission capacity. 220 kV Chikkodi –
Kolhapur line had already been put into operation. Karnataka had started availing
power from Maharashtra in radial mode and about 2 MU of energy was being
drawn on this line daily. Studies had been carried out by SRLDC taking into
consideration the generation level in Sileru complex and line loading. This showed
that about 50 – 100 MW of power could be imported, without causing over
loading of Lower Sileru - Bommur & Upper Sileru - Pendurthi lines. Power could
be availed either on bilateral or on regional basis. However, it appeared that
APTRANSCO had again expressed certain reservations on operationalization of
the line as expressed in their communication dated 24th
July 2014.
3.1.8 Director, APTRANSCO said that during generation in Sileru complex, Lower
Sileru- Bommur & Upper Sileru – Pendurthi lines were getting over loaded.
During the trial operation some units in Sileru Complex were under shut down and
hence overloading of lines had not been experienced. The loading of the Lower
Sileru - Bommur line was around 170 MW. He added that the link could not be
used for import of power in view of generation in Sileru complex and over loading
of lines.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 8 of 83
3.1.9 ED, SRLDC suggested that during at least off peak hours power could be imported
on this link. Total generation was around 6-7 MU/day in the Sileru Complex. The
sensitivity was around 26-27 % on Lower Sileru- Bommur line and around 40 %
on Upper Sileru – Pendurthi. There was ample margin available on the Upper
Sileru – Pendurthi line.
3.1.10 MS I/c, SRPC suggested that import of power be avoided during peak hours and
power in the form of UI be availed during other hours. Higher bodies were
monitoring the operationalization of available regional links. Issues regarding
insufficient inter regional corridor availability were being projected by SR. In this
scenario, keeping the link open was rather not justifiable. NLDC had taken
initiative in this regard. After the concurrence from Odisha Government, power
should be imported without affecting any generation in the Sileru complex.
Import of power under UI would also help obtain necessary operational
experience.
3.1.11 TSTRANSCO stated that Sileru is a shared project of AP & Telangana.
Flexibility in operation was an issue and cooperation of both AP & Telangana
was essential to avail power through this link. At times, split bus operation at
Lower Sileru was carried out to ensure power injection towards Telangana and
avoid overloading of Lower Sileru-Bommur line. They further stated that in case
power is availed, it may be on regional basis or to both AP & Telangana.
3.1.12 APTRANSCO suggested further deliberation on this issue in the SRPC meeting.
3.1.13 It was noted that closing of this line had also been discussed in the Meeting taken
by Secretary (Power), especially in view of weak monsoon.
3.1.14 TCC agreed that further decision in this regard could be taken in the SRPC
Meeting.
3.2 220 kV Chikkodi – Mudsinghi / Talandage (Kolhapur) line
3.2.1 In the 24th
Meeting of SRPC after deliberations, it had been agreed that trial
operation of 220 kV Chikkodi – Kolhapur line would be carried out during
June/July 2014, in radial mode. Subsequently, parallel mode of operation could
be contemplated.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 9 of 83
3.2.2 In the Special TCC Meeting held on 08th
May 2014, KPTCL had agreed for
closing the Chikkodi – Mudshingi / Talandage (Kolhapur) line.
3.2.3 Meetings to check preparedness for rejuvenation of 200 kV Chikkodi – Kolhapur
line were held at Talandage & Mudshingi on 10th
June and at Chikkodi on 11th
June 2014.Representatives from KPTCL, MSETCL, SRLDC, WRLDC, PGCIL
and SRPC Secretariat attended the Meetings. A Meeting through video
conference with participation from KPTCL, MSTECL, SRPC Secretariat, WRPC
Secretariat, SRLDC, WRLDC and NLDC was also conducted on 17th
June 2014.
The Minutes of the Meeting is furnished at Annexure-IV.
3.2.4 In the Meeting, the following was noted:
This line had been closed radially on 11th
July 2014 and about 70-
100 MW of power was being availed by Karnataka on bilateral basis.
POSOCO suggested that the line be tied in parallel mode.
KPTCL expressed that operation in grid mode was not recommended
at this stage since studies showed that flows may come down.
Further, KPTCL had entered into PPA for 6 months and the voltage
conditions were stable with N -1 criterion.
3.3 RoW of Lower Sileru – Barasur (SR-ER)
3.3.1 In the 24th
Meeting of SRPC after deliberations, it had been agreed to put up a
proposal for utilization of RoW of Lower Sileru - Barasur for higher capacity link
to the Standing Committee on Power System Planning.
3.3.2 Subsequently, Member Secretary I/c, SRPC vide letter dated 11th
April 2014
(Annexure-V) had requested Chief Engineer (SP&PA), CEA to examine
possibility of utilization of RoW of Lower Sileru- Barasur link for a higher
capacity link.
3.3.3 In the Meeting the following was noted:
Matter had been taken up with the Standing Committee on Power
System Planning.
TSTRANSCO opined that upstream and downstream evacuation
system was also needed to be kept in view, while planning the ROW
utilization.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 10 of 83
4. FIXING UP LIMIT FOR 400 KV KOLAR-HOSUR D/C LINES
4.1 In the Special Meeting held on 30th
May 2014 with participation of CEA, it had
been agreed that the line loading would be restricted to 580 MW on each circuit of
400 kV Kolar – Hosur D/C line. The flow could be 650 MW on the 400 KV S V
Chatram – Puducherry line.
4.2 TANTRANSCO vide letter dated 3rd
July 2014 (Annexure-VI) had stated power
flow limit on 400 kV Kolar-Hosur D/C line had been fixed at 1,160 MW. This was
not a satisfactory level of operation since assets have been underutilized. It had
also been stated that TN had not been allowed to over draw through UI citing
overloading of 400 kV Kolar-Hosur D/C lines. However, KSEB had been allowed
to over draw about 1,569 MU for the above said period through the same feeders
only. Further, no SPS for overloading of 400 kV Hosur-Salem D/C line had been
provided by KSEB whereas it had been insisted only on Tamil Nadu. It had also
been stated that only STOA had to be curtailed in real time operation to restrict line
loading. Further, priority for reducing STOA/MTOA should be adopted for line
loading before asking for generation reduction in TN. Additional lines planned
between S1-S2 should also be expedited to limit overloading of 400 kV Kolar-
Hosur line. It had also been stated that it could be deliberated whether allowing
1,500 MW power flow through the above Twin Moose conductor would endanger
the lines.
4.3 In the Meeting, MD I/c, TANTRANSCO said that the power flow on this line had
been fixed as 1,160 MW resulting in under utilization of the asset. Maximum limit
of power flow could be raised to 1,500 MW though the thermal limit was about
2,058 MW for both the lines (twin moose conductors) as given in the CEA
Transmission Planning Criteria. Tamil Nadu had been deprived drawal of its
rightful share from the grid where as KSEB has been allowed utilizing the line.
4.4 CE(O), TANTRANSCO observed that 400 KV Kolar- Hosur being a short line
could be easily loaded up to thermal limits. He added that Kerala had over drawn
about 1,569 MU through the same corridor while Tamil Nadu had under drawn 438
MU [2012-13, 2013-14 & 2014-15 (up to May)]. TN had thus been deprived of its
share. This had caused a loss of about Rs 109 crores to TN. Moreover, Kadamparai
pump mode had been asked to stop even during under drawl in high frequency
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 11 of 83
conditions. TN had tied up about 3030 MW of LTA and in case the present limit of
S1 – S 2 corridor is maintained, then it would be a big struggle to draw the power.
4.5 MS I/c, SRPC pointed out the quality of overdrawal / underdrawal also mattered.
Overall figures may not capture the dynamics involved in real time grid operation.
Under drawl could also be on account of any infirm power injection. Over
drawal/Under drawal was being regulated as per the limits specified in DSM/UI
regulations of CERC. Deviations, if any, were supposed to be only unintended.
SRLDC was monitoring the drawals etc in an impartial manner and accordingly
issuing violation messages.
4.6 Director (Tr. & SO), KSEB stated that though there would have been over drawal
of about 1,570 MU, they were adhering to the Regulations. KSEB was also
complying with any direction of SRLDC in maintaining Grid discipline. Violation
messages were being issued by SRLDC in real time to all such constituents
including KSEB in the event of any non-compliance of the Grid code.
4.7 ED, SRLDC pointed out that instantaneous OD/UD was of much greater
significance with regard to Grid Operation. Whole year OD/UD comparison in
terms of MU would not give the correct perception in this regard. 580 MW limit of
power flow on each circuit had been fixed keeping in view N-1 contingency as per
the Planning Criteria of CEA.
4.8 Chief Engineer (O), TANTRANSCO stated that each line (short) could carry 750
MW as per the thermal limits in the Planning Criteria of CEA. Further,
commitment given earlier regarding increase of ATC of S1-S2 corridor had not
been implemented even though SPS on 400 KV Hosur-Salem had been
implemented and was in place.
4.9 MS I/c, SRPC suggested that the SPS at Salem be shifted to Hosur since Hosur
loads were having higher sensitivity with respect to flow on Kolar-Hosur lines.
Additional relief of about 125 to 150% could be provided so as to ensure that N-1
criterion does not get violated. In case regulatory requirements were satisfied (CEA
Planning Criteria/Congestion Regulation) enhancement of S1-S2 ATC could be
considered by NLDC/SRLDC.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 12 of 83
4.10 ED, SRLDC said that N-1 condition needed to be satisfied at all times.
Effectiveness of SPS was also under scrutiny considering past experience. Hence,
ATC enhancement could not be considered with SPS.
4.11 ED, NLDC said that limit of 1,160 MW (thermal limit) was fully in accordance
with provisions of CEA’s Planning Criteria with N-1 contingency. The conductor
was ACSR twin moose conductor. In certain critical corridors, even N-1-1
contingency was being considered. During the past couple of months, North
Chennai Units had tripped more than 75 times resulting in sudden fluctuations in
power flow. At times, N-1 criteria had been violated for Kolar-Hosur lines for
about 70% of the time. Without considering SPS, N-1 contingency was to be
satisfied as per provisions of the Planning Criteria.
4.12 MS I/c, SRPC suggested that ambient temperature/dynamic rating/SPS could be
contemplated for improvement in utilization of transmission assets. In view of the
weak monsoon this year, enhancement could be considered as a special case.
4.13 ED, SRTS-I, PGCIL informed that the 400 kV Kolar-Hosur lines were each
carrying about 650-700 MW of power on a sustained basis for the past two years.
At times, hotspots had been observed. He stated that the line had to exist to
evacuate power and hence sustained over loading may not be recommended.
Though the line could carry power up to thermal limits, the system operator should
feel comfortable.
4.14 Director (Tr.& SO) KSEB stated that lines were designed for loading up to thermal
limits. KSEB was willing to participate in any SPS, in case S1-S2 corridor
enhancement was being considered.
4.15 MD, TANTRANSCO assured effectiveness of the contemplated SPS and requested
NLDC/SRLDC to consider enhancement of ATC. He added that enhancement was
only being requested in the interim period till such time other
evacuation/strengthening schemes are completed.
4.16 Director (Tr), KPTCL suggested that PGCIL may kindly revert back with technical
details and feasibility, if any, of utilization of this link at higher limits with SPS
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 13 of 83
4.17 Summary of deliberations in the Meeting is as follows:
It was suggested that SPS at Hosur for the 400 KV Kolar- Hosur lines
be considered. 125-150% of loads could be ensured. KSEB would also
participate in SPS.
With provision of SPS, NLDC/SRLDC could consider enhancement of
S1-S2 ATC to some extent.
SPS at Salem for 400 KV Hosur – Salem lines could be dismantled.
PGCIL informed that they would revert back with feasibility in this
regard.
5. SYNCHRONISATION OF SR WITH NEWGRID / 765 kV RAICHUR-
SHOLAPUR LINE
5.1 In the 24th
Meeting of SRPC, the following had been noted:
765 kV Raichur –Sholapur S/c line (executed by PGCIL) was synchronized
on 31st December 2013. SRPC had approved the CoD of 765 KV Raichur –
Sholapur S/c line and Raichur 765/400 KV S/S from 1stJanuary 2014.
POSOCO had stated that commissioning of 765 KV Raichur-Sholapur line
was one necessary step towards integrated National Grid. Frequency
fluctuations had come down with the synchronization of SR grid and NEW
grid. The line was carrying up to 900 MW of power in either direction
every day. The issue of oscillations would get resolved with the
commissioning of the other circuit. After commissioning of the
downstream and upstream planned system (18 elements), scheduled
transactions up to 1,200 MW may be allowed. However, other corridors
between NEW Grid and SR Grid were also essential.
TANTRANSCO had stated that long term open access had been granted
for availing power from Chhattisgarh, Orissa & Maharashtra. The
complete system should be in place to ensure transfer of power. Progress of
the 18 identified elements was thus highly critical for the region.
APTRANSCO had suggested proactive action and closer coordination with
the district administration for early resolution of the RoW issues.
PGCIL had stated that despite taking up the issue in Courts and also at
various levels of Administration/Govt. of Karnataka, RoW issues at
Yelahanka and Madhugiri had not yet been resolved. Yelahanka was a GIS
station and could be dismantled and relocated. KPTCL had informed that
about Rs. 9 Crores had been deposited by PGCIL as per directions of the
Court. With additional compensation of about Rs. 1-2 Crores, the issue
could get resolved. KPTCL had invited PGCIL for a Meeting to sort out the
issues in this regard.
KPTCL had stated that PGCIL should not dismantle Yelahanka station and
instead sort out the RoW issues. This was not a stray case as could be seen
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 14 of 83
in the case of other lines such as Edamon-Kochi etc. KPTCL was taking up
the issues seriously and would facilitate a Meeting at the earliest.
5.1.1 The second circuit of 765 kV Sholapur – Raichur line of M/s RSTCL was
synchronized at 1456 hours of 30th
June 2014.
5.1.2 TANTRANSCO vide letter dated 3rd
July 2014 (refer Annexure-VI) had stated
that it had been agreed that a quantum of power of about 2,000 MW could be
imported to SR region after commissioning of 2 Nos. 765 kV lines along with
other transmission elements in WR and SR regions. The status of line had been
proposed to be deliberated in the Meeting.
5.1.3 In the Meeting, MS I/c, SRPC informed about the petition of MSETCL before
Hon’ble CERC for keeping in abeyance the ongoing trial operation of NEW-SR
synchronization till satisfactory resolution of all their concerns arising out of the
trial run. A Meeting on TTC/ATC/LTA issues related to Raichur-Sholapur link
had been conducted on 24th
July 2014 in New Delhi and the outcome was
awaited.
5.1.4 CTU informed that based on the feedback of KPTCL on load generation balance
issues etc. no conclusion could be arrived at. Hence another Meeting in this
regard had been scheduled to be conducted on 30th
July 2014.
5.1.5 Director (Tr), KPTCL also noted that there had been no decision taken regarding
increase of TTC/Allocation of corridor for LTA during the Meeting held on 24th
July 2014. As per their observation there was no need to unnecessarily hurry and
avail more power through existing link. Number of downstream/upstream
lines/system were in various stages of commissioning. Hence, it was needed to be
technically ascertained whether the present system was capable of handling this
additional power. He added that within a period of about 6 months, the Grid
would be strengthened with commissioning of other elements and then additional
power could be availed. It was appreciated that POWERGRID was doing its very
best in early/timely commissioning of the elements.
5.1.6 MD, TANTRANSCO stated that more flexibility was required in allocation of
corridor to ensure higher availability of power to Tamil Nadu. Step by step
enhancement of ATC needed to be considered, with progressive commissioning
of new elements. Hence, waiting for the entire system to be completed before
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 15 of 83
release of ATC may not be the right approach.
5.1.7 ED, SRLDC informed that 200 MW of STOA was being scheduled from 05th
July
2014. Prior to commissioning of the second circuit, flow was within 800 MW
import/export on net nil basis.
5.1.8 Director (Tr. & SO), KSEB observed that since certain downstream lines had
already been commissioned, the study was suggesting additional import. One
could not wait for the whole system to come up to release ATC. The ATC could
be released to the extent possible with the available elements, based on studies.
5.1.9 Chief Engineer (O), TANTRANSCO added that Nellore-Thiruvalam line was
lightly loaded and more power flow could be availed with the commissioning of
other downstream transmission system. He also informed that Thiruvalam-
Melakottiyur and Mellakottiyur-Pugalur lines had been commissioned.
Thiruvalam downstream system was also likely to be commissioned within a
month.
5.1.10 ED, NLDC said that review of available downstream system and commissioning
schedule may also be undertaken in the Meeting scheduled on 30th
July 2014 so as
to take a comprehensive view on the TTC/ATC.
5.1.11 Director (Tr) KPTCL observed that with the commissioning of first Raichur-
Sholapur circuit, there had not been any additional net import to the Southern
Region. Power flow on HVDC links had been modulated so as to accommodate
flow on the Raichur-Sholapur link.
5.1.12 The Schedule of commissioning of the planned (18 Nos.) transmission elements
in WR and SR noted in the Meeting is as follows:
Sl.
No. Name of Transmission Element
Exe.
Agency
Date as
noted in
CEA Mtg.
held on
09.09.2013
Expected
date Remarks
1. Aurangabad-Pune 400 kV D/C Reliance Dec. 2013 Completed
2. Parli-Pune 400 kV D/C Reliance Dec. 2013 Completed
3. Raipur-Wardha 765kV D/C PGCIL May 2014 September
2014
Forest clearance
St-I received in
Jan 14 and St-II
received in Apr.
14.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 16 of 83
4. Raipur 765/400 kV S/S PGCIL Dec. 2013 Completed
5. Wardha-Aurangabad 765kV D/C PGCIL July 2014 Completed
6. Aurangabad 765/400 kV S/S PGCIL July 2014 Completed
7. Sholapur-Pune 765 kV S/C PGCIL Oct.2014 Oct-2014
8. Pune 765/400 kV S/S PGCIL Oct. 2014 Oct./Nov
2014
9. Gooty-Madhugiri 400 kV D/C PGCIL June 2014 Nov/Dec
2014
Severe RoW
Problem near
Madhugiri
10. Madhugiri 400/220 kV S/S PGCIL June 2014 Nov 2014 Engg., supply,
civil works &
erection under
progress
11. Madhugiri-Yelahanka 400 kV D/C line PGCIL June 2014 Mar 2015 Severe Row
Problem
12. Raichur-Kurnool 765 kV S/C PGCIL Aug-2014 Commissioned
13. Kurnool 765/400 kV S/S PGCIL Aug-2014 Commissioned
14. Kurnool-Thiruvalam 765 kV D/C PGCIL Nov.2014 Nov. 2014
15. Thiruvalam 765/400 kV S/S PGCIL Nov 2014 765 kV by
Nov 2014
400 kV
Commissioned
16. Vijayawada-Nellore 400 kV D/C PGCIL Nov. 2014 Nov. 2014 RoW Problem.
17. Nellore-Thiruvalam 400 kV D/C PGCIL Nov.2014 Commissioned
on 14.04.2014
18. Thiruvalam-Melakottaiyur 400 kV
D/C
PGCIL Nov.2014 July 2014 Commissioned
on 24.07.2014
5.2 Review of SPS operation in respect of 765 kV Raichur-Sholapur line
5.2.1 In the Meetings of OCC, constituents had expressed concern over
frequent/spurious SPS signal generation. The SPS which had acted (flow
threshold violation, dp/dt, SPS due to line imp.) and its source (i.e.
Sholapur/Raichur, Wardha & Parli) were not discernible. The source and type of
signal initiation was needed to be ensured to SRLDC/Constituents. There were
instances ‘Nil’ relief by some of the constituents in certain instances.
5.2.2 Based on the operational experience of the All India grid with 765 kV Raichur –
Sholapur I in operation, NLDC vide letter dated 11th
April 2014 had proposed to
revise the SPS settings of some of the schemes. The objective was to minimize
the load or generation loss for normal events while ensuring reliability of All
India Grid. The proposed revisions/modifications suggested by NLDC were
discussed and approved in the 31stMeeting of PCSC. It had been noted that SPS in
SR had been implemented while some SPS implementation/modifications in other
regions were pending. Subsequently NLDC vide letter dated 27th
June 2014 had
intimated that some of the SPS settings had been revised online in Western
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 17 of 83
Region side. The SPS settings have been revised in Southern Region side after
availing shutdown of 765 kV line on 25th
June 2014.
5.2.3 TANTRANSCO vide letter dated 3rd
July 2014 (refer Annexure-VI) had stated
that additional SPS implemented from end January 2014 has caused many number
of spurious trippings thereby causing load interruptions. It has also been stated
that the status of withdrawal of above SPS has to be deliberated. Further, in the
context of commissioning of second circuit of 765 kV Raichur-Sholapur line,
actual requirement of SPS be deliberated.
5.2.4 NLDC vide letter dated 07th
July 2014 had suggested modifications in the SPS
settings consequent to commissioning of second circuit of 765 kV Sholapur –
Raichur line of M/s RSTCL and also 765 kV Wardha – Aurangabad D/C line.
5.2.5 In the Meeting, MS I/c, SRPC informed that NLDC had reviewed the settings
based on operational experience & also commissioning of the second Raichur –
Sholapur circuit. It had therefore recommended increasing the threshold limit to
1,500 MW (2.5 sec delay). He informed that SPS had operated during instances of
unit trippings, load changeovers, LGB changes in either regions etc. Lack of
adequate RGMO response on either sides was also getting reflected in sudden
variations of power flow on the link. The analysis of SPS operation is furnished at
Annexure-VII
5.2.6 ED, SRLDC said that in certain instances, the SPS signal had not been
communicated on account of non-redundancy of transmission channel. Hence,
load shedding in SR which was warranted operationally as per desired logic had
not taken place. Issue regarding provision of additional channel was being
continuously pursued with PGCIL.
5.2.7 ED, SR-1 said that provision of redundant channel would be ensured. PGCIL
also informed that revised settings as suggested by NLDC would be implemented
on 30th
July 2014.
5.2.8 NLDC informed that modification had to be carried out at both WR/SR ends.
They also suggested that the modifications be carried out on one circuit at a time.
5.2.9 CE (O), TANTRANSCO said that it had been informed earlier that the SPS
would be withdrawn after commissioning of the second circuit.
5.2.10 It was noted that SPS logic was undergoing changes based on operational
experience etc. and also with progressive commissioning of
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 18 of 83
downstream/upstream elements. The number of SPS operations of late had also
come down as could be kindly seen from the analysis above. Review of SPS
logic was an ongoing exercise.
5.3 Synchronizing facility at Raichur end of 765 kV Raichur – Sholapur line
5.3.1 In the OCC Meetings, SRLDC had stated that synchronizing facility was
required at Raichur end of 765 kV Raichur – Sholapur line to avoid delay in
restoration of vital inter-regional link. Separate synchronizing facility needed to
be provided for both the lines by PGCIL at both ends. PGCIL had informed that
the process for provision of synchronizing facility had already been initiated and
taken-up with the manufacturer.
5.3.2 In the Meeting, PGCIL informed that synchronizing facility had been provided
for both the circuits at both the ends.
6. UPCOMING TRANSMISSION SYTEM, TRANSMISSION CONSTRAINTS
& LOADGENERATION BALANCE
6.1 In the 24th
Meeting of SRPC, APNPDCL had stated that in respect of PGCIL
lines, the stage at which forest clearance was pending should be made known
clearly, clearances could be pending either at state headquarters or with Central
Empowered Committee etc. This information was essential in estimating whether
the projected commissioning dates were reasonable or not. There could be
instances of shifting bottlenecks also which need to be recognized and prevented.
TANTRANSCO had stated that power supply position and constraints including
state wise plans for the next 5 years should also be presented.
6.2 Accordingly, in consultation with the constituents, upcoming Load Generation
Balance for SR (upto 2019-20), upcoming ISTS including Inter-Regional, Intra-
STS& constraints in transmission requiring immediate attention were prepared
and circulated for comments. The following are the issues in this regard:
Regarding anticipated LGBR, feedback has been received from some
of the constituents. Other constituents had been kindly requested to
furnish feedback with regard to Requirement & Availability after
discussions with the concerned DISCOMs/GENCOs/IPPs. The
objective is to compile a realistic LGBR. Unlike Transmission, there is
no centralized agency which could furnish inputs on power purchases
computed on assessment based on actual progress of the Generating
Stations etc. Similarly, the information with regard to ISTS connected
generators is also not readily available.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 19 of 83
Regarding transmission, constituents had been requested to
communicate the updated progress and timely information. Any
dropped project needs to be removed from the Progress Reports.
Modified schemes also need to be taken care appropriately. Status of
Forest clearance is awaited from all the constituents. Status of RoW
issues also needs to be elaborated.
6.3 In the 24th
Meeting of SRPC the following had also been noted:
SRLDC had pointed out that status of down stream elements from
substations such as Madhugiri, Yelahanka and Thiruvalam S/S was
also needed to be discussed. Monitoring of status of transmission lines
planned by State Utilities and also lines coming under TBCB route
was required to be carried out. Periodic reports from STUs be sought
in this regard.
APTRANSCO had suggested certain modification with respect to the
scheme for evacuation of Hinduja power as discussed in the 36th
Standing Committee Meeting. TCC suggested that any proposal in this
regard was needed to be addressed to the Standing Committee on
Power System Planning.
In view of commissioning of Krishnapattanam JV, APGENCO had
requested that downstream Thiruvalam system of TANTRANSCO be
in place at the earliest. TANTRANSCO had informed that the
construction of these critical elements had been awarded to major
companies like L&T/Gammon to ensure that projects are completed as
per schedule. Incentive for early commissioning was also being
offered. Thiruvalam S/S was being planned to be completed by June
2014. Thiruvalam-Mettur and Almathy-Thiruvalam lines were also
progressing on fast track.
KPTCL had opined that need for the proposed 400 KV UPCL-
Kasargode-Kozhikode line required to be relooked. This may be a case
of over design. 400 kV Mysore-Kozhikode line (quad moose D/C) was
expected to be operational in about six months’ time. 400 kV Mysore-
Kozhikode line with capacity of about 1,600 MW could amply serve
the requirements of North Kerala. The peak demand of Kerala
presently was of the order of 3,300 MW. The need for UPCL-
Kasargode-Kozhikode line was thus to be examined in the scenario of
400 KV Edamon-Kochi and Trichur - Kozhikode lines coming up.
KSEB had stated the UPCL-Kasargode-Kozhikode line had been
approved by Standing Committee on Power System Planning. All the
aspects had been duly considered and deliberated before according
approval for the line. There was need to strengthen supply to North
Kerala. Kerala had several constraints as far as internal generation was
concerned. It was thus forced to get power from other states. It had
been recommended that CEA be kindly requested to form a
Committee to explore space for additional Bays at UPCL.
Chairperson, SRPC had opined that in view of serious RoW issues,
long term requirements needed to be considered especially in respect
of tower design. Re-conductoring could always be carried out, but
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 20 of 83
there was a case for appropriate tower design. Towers may need to be
initially designed keeping in view the anticipated growth over the next
30 to 40 years.
6.4 Subsequently, Member Secretary I/c, SRPC vide letter dated 11th
April 2014 had
requested Chief Engineer (SP&PA), CEA that a visit of CEA officers to UPCL
plant be arranged to explore the possibility of space for the additional bays.
6.5 SRLDC had informed about that transmission constraints being faced by system
operators were being communicated to CEA, CTU and states regularly. The
quarterly operational feedback on transmission feedback is available on the
NLDC web site.
6.6 TANTRANSCO vide letter dated 3rd
July 2014 (refer Annexure-VI) had stated
that STOA is being curtailed on daily basis even though SPS on 400 kV Hosur-
Salem line has been provided only by TN for which the ATC had not been
increased. It had also stated that the to relieve S1-S2 corridor congestion, erection
works of 400 kV D/C lines (Somanahalli - Salem, Mysore - Kozhikode, Edamon
– Cochin, Trichur – Kozhikode) be expedited by POWERGRID. Further,
Karnataka had to cater their Yerandahalli load of about 80 MW from Somanahalli
itself.
6.7 ED, SRTS-I, PGCIL informed that a number of elements had been progressively
commissioned like Gooty-Nellore-Thiruvalam, Raichur-Kurnool, Chittor-
Thiruvalam, Kurnool (new)-Kurnool (AP), LILO of Nagarjuna Sagar-Gooty at
Kurnool, LILO of Kolar- Sriperumbudur at Thiruvalam. Kurnool-Thiruvalam and
Gooty-Madhugiri were critical pending elements. Out of 214 KM of Gooty-
Madhugiri 70 KM was in Karnataka and they were facing RoW issues in a few
locations. Government of Karnataka was extending support to resolve RoW issues
at Madhugiri and similar co-operation was required to address RoW issues at
Yelahanka. In case conditions are favorable, Gooty-Madhugiri and Madhugiri 400
kV S/S would come up by Nov-Dec 2014. In case RoW issues of Madhugiri-
Yelahanka link are addressed they were hopeful to complete the system by March
2015. He requested the states to complete their downstream system also matching
the schedule of POWERGRID at Madhugiri, Yelahanka etc. to ensure better
utilization of the assets.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 21 of 83
6.8 Director (Tr), KPTCL informed that Madhugiri downstream connectivity/loading
had been initiated. Bellary-Madhugiri line was also being undertaken. Yelahanka
(PG) – Yelahanka (KPTCL) connectivity was being planned through UG cable
considering the RoW issues in that area.
6.9 In the Meeting, the progress of the following critical elements had been noted:
S.
No.
Transmission Element Schedule Remarks
1 400 kV Chittoor-Thiruvalam March 2014 Commissioned in March 2014
2 765 kV Salem- Madhugiri March 2015 Severe RoW problem near
Madhugiri
3 765 kV Narendra (Kudgi)-Kolhapur Nov. 2015 Tower Packages awarded (Part-
II) in Nov. 13. Completion
matching with Kudigi SS. Land
acquired in Feb. 2014
4 765 kV Madhugiri-Narendra (Kudgi) Nov. 2015 TBCB
5 400kV Krishnapattanam- Chittoor Oct. 2014 APTRANSCO was requested to
expedite commissioning to
avoid evacuation constraints
6 400/230 kV Thiruvalam S/S ICT-1 by
15.08.2014
ICT-2 by
31.08.2014
LILO of 230 kV D/C line
proposed. Expected load would
be around 200- 300 MW.
7 400 kV Thiruvalam - Melakottaiyur Commissioned on 24.07.2014
8 400 kV Somanahalli- New Salem Dec. 2014 Shut down in September 2014
COD by December 2014
9 400 kV Pugalur- Kalavindapattu Sep. 2014 One Ckt commissioned. 2nd
Ckt
by Sep 2014
10 400 kV Mettur- Singarapet-
Thiruvalam
Sep. 2014 40% of total work completed.
11 LILO of Kolar- Sriperumbudur at
Thiruvalam
Commissioned in March 2014
12 400 kV Mangalore (UPCL ) -
Kasargode-Kozhikode
Approved by Standing
Committee.
6.10 Director (Transmission), KPTCL stated that the issue regarding 400 kV UPCL –
Kasargode – Kozhikode line be discussed in the ensuing Standing Committee. It
was felt that this link may serve no purpose and it would be a wasteful investment
considering the Mysore-Kozhikode line which would be commissioned shortly.
6.11 Director (Tr. & SO), KSEB stated the 400 KV UPCL- Kasargode-Kozhikode line
had been approved by Standing Committee on Power System Planning. He added
that approved issues should not be reopened.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 22 of 83
6.12 PGCIL informed that the proposed 400 kV Mangalore (UPCL)-Kasargode-
Kozhikode line would be through TBCB route.
6.13 MD, TANTRANSCO requested to consider one more ICT at Kalavinthapattu.
PGCIL informed that NIT had been issued and they would expedite to the extent
possible.
6.14 PGCIL informed that shutdown for 45 days of 400 kV Somanahalli-Hosur line for
construction of Somanahalli-New Salem line approved in the 24th
SRPC held on
15th
March 2014 had not been taken up and would be availed in September 2014.
6.15 MD, TANTRANSCO observed that there would be considerable wind generation
reduction from October onwards and PGCIL should make all efforts to avail the
shutdown before September 2014. Shutdown proposal after September may not
be approved keeping in view the operational reasons.
6.16 MS I/c , SRPC informed that the 37th
Meeting of Standing Committee on Power
System Planning was scheduled on 31st of July 2014 wherein the issues could be
deliberated. About 10,000-16,000 MW deficit was anticipated in Southern Region
in 2019-20 as per the agenda circulated. He stated that a Special meeting of TCC
be held to approve the schemes recommended in the 37th
SCPSP SR
.Transmission constraints etc. could be discussed in that Meeting.
6.17 ED, SRLDC stated that unless the 765 kV Narendra (Kudgi)-Kolhapur line was
ready, evacuation of Kudgi generation would not be possible.
6.18 RoW of 400 kV Mysore-Kozhikode D/C line
6.18.1 In the 24th
Meeting of SRPC the following had been noted:
PGCIL had informed that they were receiving assistance from the
Karnataka Administration. Considerable agitation was being
encountered, but works were taken up with police protection. If
conducive environment was maintained, the line could be completed
by January 2015.
KSEB had observed that the line needed to be completed at the
earliest and had requested KPTCL to kindly render all support to
PGCIL.
6.18.2 It was learnt that Karnataka State Government had constituted an Expert
Committee to examine alternative possibilities for the line.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 23 of 83
6.18.3 KSEB vide letter dated 14th
July 2014 (Annexure-VIII) had been stated that
the completion of 400 kV Mysore-Kozhikode (Areakode) D/C line is urgently
required as Northern Kerala was facing acute power shortage. Due to forest
clearance and RoW disputes, the line work is held up in Karnataka. The 400
kV line work in Kerala and the construction of 400 kV substation at Areakode
were completed and kept idle for want of this line.
6.18.4 In the Meeting, Director (Transmission), KPTCL informed that the Karnataka
State Government had constituted an Expert Committee to examine alternative
possibilities for this line. The Committee had almost finalized the Report
which was expected to be submitted shortly.
6.19 Edamon-Cochin 400 kV line
6.19.1 KSEB had stated that completion of this line was essential for increasing the
import capability of Kerala and also for efficient evacuation. Construction of
this line had been held up on account of severe RoW issues.
6.19.2 In the previous SRPC Meetings, the following had been noted:
PGCIL had stated that additional compensation of about Rs.330-
350 Crores was not viable. The matter had been discussed a
number of times with the State Government. Payment of
additional compensation would send wrong signals to various
other projects of PGCIL in the country. The material was lying
unutilized since there was no progress since past 5-6 years. There
had been no progress after the High Level meeting in December
2013.Hon’ble Chief Minister of Kerala had already taken a
couple of Meetings in this connection. They had approached
Court for getting suitable directions to complete the work. The
Court had not passed any orders. PGCIL was also willing to
handover this project to KSEB. PGCIL Board had considered
dismantling of the asset on account of severe RoW problem. It
was stated that they may subsequently approach Hon’ble CERC
for relief since they wanted to minimize losses. Since the project
was much delayed, IDC may also not be approved by
Commission.
KSEB had stated that out of Rs 1,800 Crores scheme cost,
PGCIL had already invested about Rs 1,400 Crores and the
project could not be abandoned at this stage. KSEB had also
surrendered RoW for a section of this line. KSEB also assured
further coordination to sort out this issue. Discussions and efforts
to resolve the issue were under way. During the last one year,
Hon’ble Chief Minister had convened three Meetings on this
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 24 of 83
issue. There were court orders with regard to compensation. In
Kerala, about 30- 40% compensation was payable for the
corridor and 100 % for the tower foot print.
Chairperson, SRPC had suggested that the issue be mutually
discussed between KSEB and PGCIL, once the election process
was over.
6.19.3 POWERGRID had filed a petition before Hon’ble CERC seeking provisional
tariff on the expenditure incurred by PGCIL on construction of Edamon -
Cochin 400 kV D/C (Quad) line till 31.3.2014 and adjudication of dispute
between the petitioner and Govt. of Kerala with regard to the compensation
determined by the latter in terms of Section 67 (4) of the Electricity Act.
Hon’ble CERC had issued RoP in respect of Petition No. MP/083/2014 (date
of hearing 17th
June 2014) wherein the following is stated:
“(d) Under the circumstances, the petitioner finds no way to
complete the Projects and seeks recovery of expenditure already
incurred in a suitablemanner. “
The Petition had been listed for hearing on 12th
August 2014.
6.19.4 In the Meeting, Director (Tr. & SO), KSEB informed that additional
compensation would be met by the Government of Kerala. Therefore there was
likelihood of commissioning of this line which would stabilize power supply to
central Kerala. He requested PGCIL to complete this project at the earliest.
6.20 400 kV Trichur-Kozhikode line (Madakkathara-Areakode)
The following had been noted till 24th
Meeting of SRPC:
KSEB had stated that this line had already been approved as Regional
System Strengthening Scheme. North Kerala would benefit since 400
kV supply could be availed either from Udumalpet or from Mysore
for all the 400 kV substations in Kerala. Multi circuit & multi-level
circuit was their requirement for surrender of corridor.
PGCIL had sought utilization of existing 220 kV Madakkathara-
Malaparamba-Areakode S/C feeder. In the 14th
SRPC Meeting,
KSEB had denied the possibility of surrendering the RoW of the
KSEB line since energy security of Malabar region was involved.
Line could be taken up only after commissioning of the 400 kV
Mysore-Kozhikode line. PGCIL had been requested to initiate the
process so that construction could commence immediately after 400
kV Mysore-Kozhikode line was commissioned.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 25 of 83
7. AUGMENTATION OF TALCHER- II TRANSMISSION SYSTEM
7.1 The following had been noted till 24th
Meeting of SRPC:
Government of India order was required in case PGCIL was to
implement this scheme under “urgency” clause.
TANTRANSCO vide letter dated 5th
January 2013 had stated that all
SR beneficiaries had entered into Transmission Service Agreement
with M/s. TTCL regarding the strengthening of Talcher-II evacuation
system. As per TSA & LOI, M/s. TTCL had to achieve the CoD by
31.03.2013 and submitted bank guarantees were valid up to end of
Jan 2013 with a claim period of one more month. Presently, M/s.
TTCL had approached Hon’ble CERC praying relief in the matter of
extension of time and other issues vide Petition No.
170/MP/2011.Hence, M/s. TTCL had to be instructed to complete the
scheme at the earliest.
Chairperson, SRPC vide letter dated 14th
March 2013 addressed to
Secretary (Power), MoP had invited attention to the matter regarding
delay in execution of augmentation of Talcher-II transmission
system. It had also been requested that MoP may consider issuing
suitable directions to Hon’ble CERC since public interest was also
involved.
In RoP dated 9th
July 2013 Hon’ble CERC had directed NKTCL and
TTCL to hold a Meeting with the Procurers of both projects within a
period of two weeks and file the outcome of the meeting before 30th
July, 2013. The Commission had further directed the lead procurers
of NKTCL, namely MSEDCL and TANGEDCO to coordinate the
LTTCs to facilitate the meeting with NKTCL and TTCL.
In the RoP dated 8th
August 2013, Hon’ble CERC had directed CEA
to submit the present status of the NKTCL & TTCL latest by 30th
August 2013. In the RoP dated 10th
September 2013, it is stated that
CEA vide letter dated 29th
August 2013 had confirmed that no
progress had been made for implementation of the project.
Commission had directed PSPCL to file its reply and submissions
made during the hearing on affidavit, with an advance copy to the
petitioner and NKTCL and TTCL by 20th
September 2013. NKTCL
& TTCL were to file their rejoinders, if any, on or before 27th
September 2013. The Commission had reserved order in the
Petitions.
TANTRANSCO vide letter dated 8th
January 2014 had referred to the
judgment of Hon’ble Appellate Tribunal for Electricity in respect of
Appeal No.140/2013 preferred by Talcher-II Transmission Co.Ltd. It
had been stated that TANTRANSCO was of the view to go for appeal
before Hon’ble Supreme Court. Standing Counsel had been requested
to file the appeal before Hon’ble Supreme Court, on behalf of
TANTRANSCO, on account of the urgency involved.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 26 of 83
TANTRANSCO had informed that after issuance of Orders by
Appellate Tribunal of Electricity, Talcher–II Transmission Company
Ltd. had sought enhancement of transmission charges by about 86%
to compensate increase in cost/expenses. TANTRANSCO had
approached Hon’ble Supreme Court. TANTRANSCO also suggested
that requirement of line (Talcher-Gazuwaka) be reviewed in the
present grid scenario, since other lines were coming up.
SRLDC had stated that all studies were being carried out with
assumed availability of the Talcher backup system, which was also
required to ease congestion. He informed that in the absence on-
availability of adequate transmission corridor, STOA via ER was
being curtailed.
It had been suggested that requirement of Talcher backup system be
taken up with Standing Committee on Power System Planning,
considering the system planned/under execution.
7.2 Subsequently, TANTRANSCO vide letter dated 05th
April 2014 had informed that
they had filed a Civil Appeal before the Hon’ble Supreme Court on 03rd
March 2014.
7.3 The matter had accordingly been taken up with CEA vide SRPC letter dated 24th
April
2014 (Annexure-IX).
7.4 In the Meeting, it was noted that the matter was sub-judice, since an Appeal had been
filed before Hon’ble Supreme Court.
8. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINTVENTURE& UMPP
8.1 NTPC- Kudigi TPS Stage-I (3x800 MW)
8.1.1 In the 24th
Meeting of SRPC, the following had been noted:
Hon’ble CERC vide Order dated 08.01.2014 in Petition No.
190/TT/2013 for adoption of Tariff (Transmission Charges) in respect
of the following Transmission System being established by Kudigi
Transmission Limited under Tariff Based Competitive Bidding
process, had approved levelised transmission charges:
Kudigi TPS- Narendra (New) 400 kV 2xD/C quad lines
Narendra (New)–Madhugiri 765 kV D/C line
Madhugiri–Bidadi 400 kV D/C (quad) line
NTPC had informed that synchronization of Unit-I was expected
during September 2015 and Unit-II during March 2016.
KPTCL had informed that huge chunk of land for Stage-II had been
identified near Stage-I. NTPC could expedite activities relating to
Stage-II also.
NTPC had informed that they were in the process of firming up coal
requirements/availability and subsequently other activities could be
taken up.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 27 of 83
8.1.2 In the Meeting, NTPC informed that progress would be informed in the SRPC
meeting by Regional ED.
8.2 NLC-Neyveli TS-II Expansion (2x 250 MW)
8.2.1 In the 24th
Meeting of SRPC, the following had been noted:
NLC had informed that CoD of Unit-I would be by 31stMarch 2014
while CoD of Unit-II was expected by May 2014.
NLC had also informed that the Petition before Hon’ble CERC for
maintaining status-quo in injection of infirm power under UI
mechanism till declaration of CoD or 31stMarch 2014 had been
heard and Order was awaited. NLC had been requested to obtain
orders from Hon’ble CERC immediately.
8.2.2 Subsequently, Hon’ble CERC vide Order dated 20th
May 2014 had granted
extension of time for injection of infirm power from the generating station for a
further period upto 30th
June 2014. In the Order, it had also been mentioned that
any prayer by the Petitioner for further extension of time beyond 30th
June 2014
shall not be entertained and that the Petitioner shall ensure that the unit is
declared under commercial operation by the said date.
8.2.3 NLC had filed Petition before Hon’ble CERC praying that they be permitted to
continue to inject infirm power for testing and commissioning and the time be
extended until 31st March 2015.
8.2.4 KSEB vide letter dated 14th
July 2014 (refer Annexure-VIII ) had stated that
KSEB had been planning its power purchase annually duly considering the
allocated quantum of power from NLC TPS-II Expansion also, in anticipation of
commissioning the plant. However, due to delay in commissioning of the plant,
KSEB had been forced to avail power through short term markets including
power exchanges at enormous rates and to schedule costly liquid fuel stations
which had affected badly the financials of KSEB and in turn the consumers of
the state.
8.2.5 In the Meeting, MS I/c, SRPC informed that NLC had again filed a Petition for
extension of injection of infirm power until 31st March 2015. CERC had earlier
granted injection of infirm power up to 30th
June 2014. He added that the delay in
commissioning was affecting S1-S2 ATC also.
8.2.6 Director (Tr & SO), KSEB stated that NLC needed to commission the units at
the earliest.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 28 of 83
8.2.7 ED (Thermal), NLC informed that after major modifications in fluidized bed heat
exchanger, the unit was synchronized on 13.02.2014. But during loading beyond
120 MW, they had faced problem with tube failure which was studied by M/s
BHEL. The matter was taken up with Secretary (Coal). A Meeting was taken by
Secretary (Coal) and Secretary (Heavy Industries) with participation of officers
from BHEL & NLC. M/s BHEL had committed to modify heat exchanger and
had engaged Swedish consultant. BHEL had committed synchronization of Unit-
1 by mid August 2014. He further added that CoD of Unit-I was expected during
August 2014 and CoD of Unit-II during September 2014. Regarding petition
filed before Hon’ble CERC seeking infirm power injection until 31st March
2015, he clarified that it was with a view to avoid approaching Hon’ble CERC
repeatedly in case any further delays.
8.3 NLC - New Thermal Power Project (2x 500 MW) at Neyveli
8.3.1 The following had been noted in the 24th
Meeting of SRPC:
There was no change in schedule and CoD of Unit-I & Unit –II
was expected by October 2017 & April 2018 respectively. PGCIL
had enquired whether these dates were firm since the evacuation
system was to come through TBCB route. NLC had confirmed the
dates.
8.3.2 In the Meeting, NLC informed that CoD of Unit-I & Unit –II was expected by
October 2017 & April 2018 respectively. On a query from POWERGRID, they
confirmed the dates as mentioned above.
8.4 NPCIL-Kudankulam Nuclear Power Project (KKNPP) Stage-I (2x1000 MW)
8.4.1 The following had been noted in the 24th
Meeting of SRPC:
Unit-I had been test synchronized on 22nd
October 2013 with about
160 MW generation and was subsequently taken out from the grid
for statutory checks. Unit-1 had resynchronized at 21.43 Hrs. on
25th
October 2013.
NPCIL had informed that they had obtained permission up to 75%
level. All tests at this level were over except net load rejection test
which was being planned for 18th
March 2014. After verification of
test results by the Regulatory authorities, 90% generation level
would be approved. Additional tests were planned at 90% level and
subsequently only 100% generation level would be approved.
About 8 weeks’ time was expected to reach generation level of
100%. They would approach Hon’ble CERC for injection of in firm
power beyond 6 months. Certain plant parameters at rated capacity
were to be demonstrated by the Russian OEM. Regarding Unit-II, it
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 29 of 83
was informed that most of the construction jobs were over. Hydro
test for the entire circuit was being carried out at lower pressure.
Reactor Criticality was expected during October 2014 while first
synchronization was planned around November this year.
Additional manpower from other stations was being mobilized for
expeditious commissioning.
8.4.2 In the 96th
Meeting of OCC, KKNPP had informed that the Unit-1 had achieved
1,000 MW on 07th
June 2014.The unit was under shut down and would come
back after 3-4 days. Six tests had been planned at full load/partial generation and
would be completed during a period of 10 days. Subsequently there would be
mandatory shut down for 20 days. The unit was likely be commissioned by July
2014. It was also noted that Hon’ble CERC had accorded approval for infirm
power injection up to 22nd
July 2014. In case COD was expected beyond that
date, KKNPP would need to approach Hon’ble CERC seeking extension.
8.4.3 KSEB vide letter dated 14th
July 2014 (refer Annexure-VIII) had stated that the
delay in commissioning of the project was seriously affecting the financials of all
Southern Constituents including KSEB.
8.4.4 In the Meeting, MS I/c, SRPC stated that NPCIL had filed Petition before
Hon’ble CERC praying that they be permitted injection of infirm power to the
grid till declaration of CoD of KKNPP Unit-1 or 22.10.2014, whichever is
earlier. He informed that Unit-I had been taken out for shut down from
16.07.2014. The unit was expected to be back by 16.08.2014.
8.4.5 Additional Director, NPCIL informed that final phase of pre CoD tests were
continuing. Unit-I was under shutdown as per AERB requirements and CoD of
the unit was expected by end of August 2014. Synchronization of Unit- II was
planned by December 2014 and CoD by March 2015.
8.5 BHAVINI- Kalpakkam PFBR (500 MW)
In the 24th
Meeting of SRPC, the following had been noted:
TANTRANSCO had informed that tender in respect of Kancheepuram
S/S had been finalized and the substation was expected to be ready by
September 2014.
The Reactor could go critical by September 2014 and power injection
expected by November 2014.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 30 of 83
8.6 NTECL - NTPC & TNEB Joint Venture - Vallur STPS (3x500 MW)
8.6.1 The following had been noted in24th
Meeting of SRPC:
Unit-I (500MW) had been declared under commercial operation with
effect from 00:00 Hrs of 29th
November 2012 and Unit-II (500MW)
with effect from 00:00 Hrs of 25th
August 2013.
NTPC had informed that Unit-III (500 MW) had been synchronized on
28th
February 2014.CoD of Unit-III was expected by August 2014.
They had identified all activities including RGMO which would be
completed before CoD.
8.6.2 In the Meeting, GM, NTECL informed that the works regarding coal handling
system were held up. NTECL had terminated the contract and the work had been
awarded to a new agency and NTECL was facilitating completion of the coal
handling system at the earliest. CoD of Unit-III was expected by end of August
2014.
8.6.3 MS I/c, SRPC pointed out that level of generation in Vallur was less at times,
which had an effect on the S1-S2 ATC. Realistic generation schedule could be
furnished to SRLDC so as to release the corridor for other scheduled transactions.
8.6.4 ED, SRLDC informed that NTECL had committed 800 MW generation up to 15th
August 2014.
8.6.5 GM, NTECL informed that Unit –II would be under shut down from 15th
to 22nd
August and Unit- I from 23rd
August 2014 for 35 days. Generation would be
maintained around 500 MW level with one unit on bar. There would be some
infirm power injection also. The time schedule etc. would be submitted to
SRLDC.
8.7 NLC Tamil Nadu Power Limited (NTPL- JV Company of NLC
&TANGEDCO) at Tuticorin (2x500 MW)
8.7.1 The following had been noted till 24th
Meeting of SRPC:
NLC had informed that Boiler light up of Unit-I was planned by
March 2014 and CoD was expected by June 2014.CoD of Unit-II
was expected by August 2014.
SRLDC had observed that the data and communication links were
yet to be established and requested completion of pending works at
the earliest.
8.7.2 In the Meeting, ED (Thermal), NLC informed that the unit was in the final phase
of commissioning. CoD of Unit-I expected by August 2014 & CoD of Unit- II
expected by September 2014.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 31 of 83
8.8 Krishnapattanam UMPP (6x660 MW)
8.8.1 The following had been noted till 24th
Meeting of SRPC:
The project had been awarded to Reliance in the year 2007. The
initial configuration of 5x800 MW was subsequently revised to
6x660 MW with CERC approval. LOI had been placed with M/s.
Shanghai Electric Corporation.
Maharashtra was yet to enter into PPA with CAPL while the other
beneficiaries had signed the PPA.
The generation developer had stopped the works at site and the
project may get delayed.
In the 19th
SRPC Meeting, APTRANSCO had informed that
APSPDCL the lead procurer had tried to encash the bank guarantee.
However, Reliance had approached Hon’ble Delhi High Court and
obtained stay. Hearing on the petition was again held on 31st May
2012. The present developer could be recommended for
cancellation. SRPC may have to approach MoP for entrusting this
project to some other developer.
PCKL had informed that under the leadership of AP all the
procurers had adopted a tough stand. Concerted action had been
taken and once the stay was vacated the bank guarantee could be
encashed. They were also ready with the Caveat in this regard.
After encashing the BG, future course of action could be decided as
per the terms of PPA. Since bidding route was adopted, there was
no scope for revision of the prices and Reliance should have had
proper back to back arrangement for coal supply.
In the 21stMeeting of SRPC, APTRANSCO had informed that they
had conducted a meeting with the procurers. The consensus was to
go ahead as per PPA. However, it was also learnt that the
developer had approached CERC.
In the 22nd
Meeting of SRPC, APTRANSCO had stated that matter
was still pending before the Division Bench of Delhi High Court
regarding termination of the contract. CAPL petition regarding
revision of tariff was also pending before Hon’ble CERC.
In the 23rd
Meeting of SRPC, KPTCL had informed that it was
learnt that though the stay had been vacated, Reliance had
approached the Bench of Hon’ble Delhi High Court. APPCC had
informed that hearings were still going on in Hon’ble Delhi High
Court.
It had been agreed that AP on behalf of other beneficiary states
would take up the matter regarding early disposal of the petitions.
In the 24th
Meeting of SRPC, APTRANSCO had informed that
petition was being heard by Hon’ble Delhi High Court.
8.8.2 In the Meeting it was noted that the matter was pending in the Delhi High Court.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 32 of 83
8.9. Cheyyur UMPP (4000MW)
In the Meeting, MS I/c, SRPC informed that it was understood that the project had
now been revived. RfQ had been issued and project developer (M/s Coastal Tamil
Nadu Power Ltd. - SPV of PFC) had applied for LTA to CTU.
8.10 Scheduled dates of synchronizing/commissioning of the new projects of NTPC,
NLC, NPCIL, BHAVINI, and Joint Venture & UMPP as noted in the Meeting are
furnished below:
Station Unit Installed
Capacity
MW
Scheduled date of
synchronizing /
commissioning
Remarks
NTPC
Kayamkulam I, II,
III
1050/
1950
12th
Plan Gas supply by 2014. Kerala
requested for 500 MW. TN &
Puducherry would consider after
knowing the tentative tariff. AP
& KAR DISCOMs were not
willing to procure the power.
Kudgi TPS
Stage-I
I,I,
III
3x800=
2400
Unit-I :
synchronization by
September 2015
Unit-II: By March
2016
Construction activities in
progress. Evacuation issues
needed to be addressed.
NLC
Neyveli-II Expn. I 250 CoD by August
2014
Modification of Heat Exchanger
by BHEL
II 250 CoD by September
2014
Work in progress
New Thermal
Power Project
I 500 October 2017
II 500 April 2018
Sirkali TPP I, II,
III
3x660 From GoI approval
Unit I – 52 months
Unit II – 58 months
Unit-III – 64
months
PPA has been signed. Fuel
imported coal. Approval of
Feasibility Report was awaited
from NLC Board.
NPCIL
Kudankulam
Stage-I
I 1000 August 2014 Synchronized on 22nd
October
2013
II 1000 March 2015 Work in progress
BHAVINI
Kalpakkam
(PFBR)
I 500 Expected by:
November 2014
Critical by September 2014
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 33 of 83
NTECL ( NTPC & TNEB JV)
Vallur STPS I 500 Original schedule:
February 2011
CoD on 29.11.2012
II 500 Original schedule:
August 2011
CoD on 25.08.2013
III 500 CoD by August
2014
Synchronized on 28.02.2014
NTPL (JV Company of NLC & TANGEDCO)
Tuticorin I 500 Original schedule:
40 months after
LOA
Anticipated
schedule:
August 2014
LOA signed on 28.01.2009
Commissioning activities started
II 500 Original schedule:
45 months after
LOA
Anticipated
schedule:
September 2014
LOA signed on 28.01.2009
Work in progress
UMPP
Krishnapattanam 3960
(6x660)
Units configured as 6x660 MW.
Amended PPA for 6x660 MW
had been executed with the
procurers. The developer had
stopped the works at site and the
project may get delayed.
Cheyyur 4000 Site finalized during meeting of
CMs held on 04.08.08. RfQ had
been issued and project
developer (M/s Coastal Tamil
Nadu Power Ltd. which is SPV
of PFC) had applied for LTA to
CTU.
8.11 Statement showing details of MoP allocation/power requirements indicated by
various constituents of SR from the New Projects is furnished at Annexure-X.
9. COAL STOCKPOSITION IN THERMAL STATIONS OF SOUTHERN
REGION
9.1 Need for maintaining statutory coal stock position in all the thermal stations at all
times had been deliberated in various forum of SRPC. Constituents/Generating
Companies had been requested to kindly apprise the Committee of the coal stock
position in thermal stations.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 34 of 83
9.2 In the 24th
Meeting of SRPC the following had been noted:
In the Meeting held on 28th
February 2014, MCL had
committed supply of coal as per programme. MCL had also
sought legal opinion on the MoEF Notification. The Matter
regarding indemnification was also to be considered. Higher
realization of coal supply has been observed in RSR Mode
rather than all Rail Mode. Chairperson, SRPC had taken up the
issues with Member (Traffic), Railway Board.
NTPC had informed that coal being utilized at Ramagundam
STPS was having ash content of around 31-32%.
It was observed that generating stations could suitably blend
domestic coal with imported coal, so as to ensure average ash
content (on quarterly basis) less than 34%.
APGENCO had informed that washery could be installed either
by generators or Coal Company. Washery of 11 MT capacity
was ready for APGENCO and they would avail the facility
shortly. He opined that it would be much easier for coal
companies to establish washeries at the source itself. The cost
in this regard could be borne by the generating companies.
TANTRANSCO had opined that generators in Southern Region
may not get affected since they were utilizing imported coal for
blending. Ash content of imported coal was low.
After discussions, it had been agreed that the matter would be
taken up with the coal companies for supply of washed coal as
per requirements.
9.3 Subsequently, MS I/c, SRPC vide letter dated 24th
April2014 (Annexure -XI) had
taken up the issue with MCL for supply of washed coal as per requirements.
MCL in its reply dated 05.05.2014 (Annexure-XII) had informed that they had a
plan of establishing washery at source itself. In Phase-I, there are 4 (four)
washeries of capacity 10 Mtpa each, which are in pipeline and expected to be in
operation by FY 2016-17 & FY 2017-18. Also for Phase-II, 20 Mtpa & 10 Mtpa
capacity washeries had been identified. The beneficial coal from these washeries
would have ash content of 33.5 ± 5%.
9.4 In the Meeting taken by Secretary (Power) on 6th
May 2014, the need to evolve a
Mechanism to build up coal stock in the power stations was agreed. CIL was to
indicate the sources from where additional coal could be supplied to NTPC
stations/other stations which are having critical coal stock. Ministry of Railways
was to ensure availability of rakes for transportation of additional coal to the
power stations. NTPC was to consider diversion of coal from its power stations
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 35 of 83
like Farakka STPS, Kahalgaon STPS where adequate coal stock is already
available to its other power stations where coal stock is critical. Adequate stock
of liquid fuel was also to be maintained by NTPC at its RGCCPP plant in
Kayamkulam.
9.5 In the Meeting, MS I/c, SRPC informed that M/s MCL and Railway had been
invited to kindly attend the SRPC Meeting. Railway Board had nominated
Members from East Coast Railway & Southern Railway for the same.
Constituents could take up the issues with Railways appropriately. He further
informed that Unit 6 of Ramagundam STPS was out ( 22nd
July 2014) on account
of coal shortage. Subsequently the unit had been brought back on 25th
July 2014.
He also enquired about the status of diversion of coal from NTPC Farakka &
Kahalgaon to NTPC Stations of SR.
9.6 NTPC informed that diverted coal from NTPC stations of ER had been received
at Simahadri. There was about 60% realization with respect to FSA of Simhadri
from MCL. Supply had been augmented through import of coal for RSTPS and
Simhadri STPS.
9.7 MD, TANTRANSCO noted that cost of power was increasing due to enhanced
usage of imported coal and hence NTPC could try to arrange indigenous supply
as per FSA.
9.8 TCC noted that coal stock position in Vijayawada TPS, Rayalseema TPS,
Simhadri STPS, Ramagundam and Raichur TPS was critical. TCC recommended
that Chairperson, SRPC be kindly requested to take up this matter with Secretary
(Power).
10. LTA QUANTUM IN RESPECT OF UPCL / SCHEDULING OF POWER TO
PUNJAB FROM UPCL (HASSAN – MYSORE 400 KV D/C LINE UNDER
SYSTEM STRENGTHENING SCHEME)
10.1 In the 24th
Meeting of SRPC, the following had been noted:
Hon’ble CERC had passed order dated 20th
February 2014 in
respect of tariff for UPCL valid till 31stMarch 2014. UPCL was
an ISG Station with more than one beneficiary and had
accordingly availed benefits. UPCL should hence initiate
necessary action to ensure that power from the project is
availed by the identified beneficiaries.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 36 of 83
UPCL had informed that PSPCL had signed PPA while LTA
had been granted by CTU. It was learnt that PSPCL was
examining the tariff order of UPCL after which Government
approval would be required.
KSEB had stated that in case Punjab was not willing to avail
power, UPCL should take necessary steps to terminate the PPA
and identify another beneficiary. RTA should contain both
Karnataka and Punjab LTA portions, from the date of CoD.
UPCL had opined that LTA granted be cancelled by CTU, if
deemed fit. CTU however clarified that as per Regulations,
beneficiaries were deemed signatories and LTA could not be
cancelled.
TCC had recommended that Chairperson SRPC be kindly
requested to take up with PSPCL for resolution of this issue by
15th
April 2014. In case PSPCL did not revert back favorably,
UPCL could be asked to initiate necessary action for
termination of the PPA and identification of new beneficiary by
30th
April 2014. The following had also been noted:
CTU/ NLDC had not communicated LTA details in
respect of UPCL/KPTCL/PSPCL to be accounted in
Regional Transmission Account/ Regional Energy
Account.
Since the issue (LTA quantum to Karnataka) was not
apparently getting resolved, the affected utility may
need to approach Hon’ble CERC.
10.2 Subsequently, Chairperson SRPC vide letter dated 24th
March 2014 addressed to
CMD, PSPCL (Annexure-XIII)had sought cooperation in resolution of the long
pending issue of scheduling of UPCL power to Punjab.
10.3 Hon’ble CERC had passed orders dated 20.06.2014 in respect of Petition No.
SM/10/2014. This was with regard to non-Compliance of Regulation 8 (6)
Central Electricity Regulatory Commission (Sharing of Inter State Transmission
Charges and Losses) Regulations, 2010. The following had been stated the Order:
“5. In the above background, we direct CTU to clarify its position in
regard to the following:
(a) Whether LTA has been granted to UPCL? If yes, details of LTA
granted and date of its effectiveness.
(b) Whether UPCL has signed the BPTA or long-term access
agreement with CTU? if yes, a copy of the same be placed on
record. If no, the reasons for not cancelling LTA be furnished.
(c) Whether data regarding LTA of UPCL was shared with the
Implementing Agency for PoC computation? If not, the reasons
for not sharing the information may be furnished.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 37 of 83
6. It has come to our notice that the matter regarding non-inclusion of
UPCL for PoC computation has been discussed in various meetings
at SRPC Forum. We direct SRPC Secretariat to submit the details
of deliberations held and recommendations of SRPC in this regard.
7. NLDC is directed to explain as to whether non-inclusion of UPCL in
the PoC charges was brought to the notice of CTU and if so, the
response of CTU thereon.
8. SRLDC is directed to explain as to how injection of UPCL is
reflected in the schedule of Karnataka and Punjab.”
10.4 MS I/c, SRPC had vide letter dated 26.06.2014 addressed to Hon’ble CERC
submitted the details of deliberations held and recommendations of SRPC. The
matter was further heard on 8th
July 2014.
10.5 KSEB vide letter dated 14th
July 2014 (refer Annexure-VIII) had requested
review of action taken by SRPC in this regard and present status.
10.6 In the Meeting, it was noted that the matter was before Hon’ble CERC.
10.7 Denial of Consent (NOC) by KPTCL for Open Access for Power Contracted
From Udupi Power Corporation Ltd To KSEB
10.7.1 KSEB vide letter dated 14th
July 2014 (refer Annexure-VIII) had stated that
KSEB Ltd had contracted 18.5 MW of RTC power from UPCL for the period
1st June 2014 to 31
st May 2015 through Tariff Based Bidding Process. The PPA
was executed on 9th
April 2014. However, KPTCL SLDC has been denying the
NOC for this purpose. It is also stated that Karnataka SLDC had informed that
100% power generated by UPCL is to be made available to ESCOMs of
Karnataka State. UPCL had stated that only 90 % of the plant capacity was tied
up with the ESCOMs of Karnataka. 18.5 MW of power offered to KSEB Ltd.
had not been tied up with any other utility.
10.7.2 In the Meeting, Director (Tr. & SO), KSEB said that 18.5 MW for which no
beneficiaries had signed long term PPA with UPCL had been contracted by
them through Tariff Based Bidding. However, Karnataka SLDC had denied
Open Access and the reason for denial was not clear.
10.7.3 Director (Transmission), KPTCL informed that reason for refusal had already
been communicated by Karnataka SLDC to KSEB.
10.7.4 Additional Director (Projects), PCKL informed that 100% tariff was being
loaded to the beneficiaries (Karnataka and Punjab). Further, during non-availing
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 38 of 83
of power, if any, by Punjab the first right of rejection was vested with the
Discoms of Karnataka.
10.7.5 UPCL informed that the station capacity had been enhanced from 1,050 MW to
1,200 MW. Punjab had entered into PPA for its 10 % share of 1,050 MW.
Hence 18.5 MW of the augmented capacity (10 % of 185 MW) had been
offered to KSEB. The same had also been intimated to Punjab.
10.7.6 Additional Director (Projects), PCKL pointed out that the tariff petition had
been filed for 1,200 MW (90 % Karnataka & 10 % Punjab).
10.7.7 UPCL informed that tariff petition filed and approved was valid up to 31st
March 2014. Presently, new petition as per provisions of the 2014-19
Regulations notified by Hon’ble CERC was likely to be filed by August 2014.
11. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR
11.1 In the 24th
Meeting of SRPC, the following had been noted:
LANCO had agreed for utilization of the Reactor for voltage
management at Kondapalli. As agreed in the earlier SRPC/TCC
Meeting, energy consumption by Reactor would be considered as
Regional loss. A Meeting with LANCO, SRLDC and SRPC
Secretariat was also held in this regard.
NPCIL had made a presentation on the voltage/tripping issues at Kaiga
GS NPCIL had expressed concern over the frequent trippings of 400
KV Kaiga-Guttur lines and requested that recommendations of
Protection Committee be implemented urgently. They had also
requested that installation of bus reactor at Guttur be expedited by
KPTCL.
CTU had informed that they were examining the issue regarding 125
MVAR reactor at Kaiga and would furnish their comments shortly.
11.2 Updated information in the meeting in respect of pending Bus/Line reactors to be
commissioned by the SR constituents as identified in the 22nd
Standing
Committee Meeting on Power System Planning of Southern Region, and as
approved in the 4th
SRPC Meeting held on 7th
June 2007 is furnished below:
Entity Bus Name Status
KPCL Raichur TPS By October 2014
KPTCL
Hoody
By October 2014 Davanagere
Nelamangala
Talaguppa
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 39 of 83
KPCL informed that out of 6 foundations, 5 had been completed and
the reactor at Raichur would be commissioned within next 2-3 months.
KPTCL informed that the Hoody reactor had been erected and oil
filtration work was being undertaken. BHEL was not responding
despite the issue being followed at the highest level. In case BHEL
comes forward all the pending works were likely to be completed
within 2 months.
Lanco informed that the reactor at LKPL had been put in service on 7th
July 2014 for voltage regulation of SR Grid in line with the decision in
the earlier Meetings.
TCC placed on record the efforts of LKPL and SR-I PGCIL in making
available the LKPL reactor for regional use.
MS I/c , SRPC informed that the issue regarding 125 MVAR reactor at
Kaiga would be discussed in the 37th
Standing Committee Meeting.
11.3 Details of other Bus / Line Reactors /Dynamic Compensation approved in the
Standing Committee / SRPC are furnished below:
Entity Bus Name
Capacity
in
MVAR
Approved
in Type Remarks
PGCIL
Vijayawada 2x125 20
th SRPC/
34th
SC Bus
Likely
commissioni
ng during
December
2015- March
2016
Nagarjuna Sagar 125 21
st SRPC/
34th
SC Bus
Narendra 125 21
st SRPC/
34th
SC Bus
Hyderabad 125 21st SRPC
Gooty 125 22
nd SRPC
/ 36th
SC Bus
Hassan 12
36th
SC
Bus
Khammam 125 Bus
Narendra (New) 125 Bus
Trivandrum 125 Bus
Nellore (Existing) 125 Bus
Yelahanka 2x63 Bus
Nellore PS on
NPS-Gooty Line 2x80 Line
Narendra–
Madhugiri D/C at
each end
4x63 Line
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 40 of 83
APTRANSCO
Vemagiri 125 21
st SRPC/
34th
SC Bus
By August
2014
Vemagiri 125
36th
SC
Bus
By Dec 2015
(APERC
approval is
awaited)
Kurnool 125 Bus
Kalpakka 125 Bus
TSTRANSCO
Mamidipalli 125 Bus
Gajwel 125 Bus
Sankarapalli 125 Bus
Mehboob Nagar 125 Bus
PGCIL informed that the reactor at Hyderabad had been dropped in view of the
STATCOM being planned at Hyderabad. It was suggested that PGCIL may
revert back with ratification/approval of Standing Committee in this regard.
Dynamic Compensation (Approved in 36th
SC)
Entity Bus Name
SC
MVA
GVA /
KA
Dynamic
Compensation
(STATCOM)
Mechanically
Switched
Compensation
(MVAR)
Remarks
Reactor Capacitor
PGCIL
Hyderabad 18.4/
26.5
+ 200 MVAR 2x125 1x125
2015-16 Udumalpet 19.4/
28.0
+ 200 MVAR 2x125 1x125
Trichy 12.5/
18.0
+ 200 MVAR 2x125 1x125
12. AVAILABLE TRANSFER CAPABLITY (ATC) /TOTAL TRANSFER
CAPABLITY (TTC)
12.1 SRLDC vide letter dated 15th
May 2014 (Annexure-XIV) had communicated that
due to large variations in LGB, variability of wind generation and frequent outage
of units , computation of ATC/TTC would be carried out flow gate wise from the
month of May 2014 rather than the scheduling limit which was in vogue.
Accordingly, the ATC/TTC for May 2014 to Aug 2014 had been revised flow gate
basis and is available on NLDC website. Salient points of the
computations/procedures under this methodology are as below:
The actual prevalent LTA & MTOA had been considered for May
2014(from 16.05.2014)
Normative ex-bus excluding the units under prolonged outage had
been considered for LTA calculation
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 41 of 83
In case of real time congestion of S1-S2 flow gate, following measures
had been proposed:
The constituents would be directed to make the injection/drawal
deviations to ‘Zero’
If deviation of injection/deviation persisted, congestion charges as
per CERC (Measures to relieve congestion in real- time)
Regulations 2009 would be kicked in.
When no significant deviation of injection/drawal but congestion
existed, curtailment of transactions would be effected in the
following order:
a) URS power from generating station of S1(on pro-rata basis)
to S2 constituents
b) STOA(on pro-rata basis) of S2 constituents
c) After exhausting STOA curtailment, MTOA (on pro-rata
basis) of S2 constituents.
Reallocation of URS power followed by Contingency Applications
would be considered based on ATC declared on NLDC website
subject to margins available.
Revision of ATC would be done in case of ISGS unit outage for
longer duration and sustained LGB changes (to be intimated in writing
by constituents) which may necessitate a relook into ATC/TTC. The
same would be published as a revision in NLDC website.
Any condition like line outage/tripping which necessitates downward
revisions of ATC/TTC for the period of outage would be displayed on
the homepage of SRLDC website as a marquee and curtailment would
be effected.
12.2 The following are the issues which had been deliberated in OCC Meetings:
Availability of units not under COD would not be considered for
ATC/TTC computations.
Constituents specifically KSEB & TANTRANSCO had raised issues
on TTC/ATC in real time on S1-S2 seam. Some include instances of
curtailment of scheduled transactions citing N-1 violations while others
include non-approval of CA/DA/URS applications though real time
margins were available.
For any change of status in Transmission line, Generator etc which was
not considered while computing ATC, SRLDC had agreed to carryout
studies accordingly and revise ATC for the rest of the period.
SRLDC had informed that Real Time TTC/ATC would not be
computed by them and the matter was to be taken up with NLDC.
Regarding real time flows for revision of ATC, SRLDC had stated that
ATC declaration was for future time horizon. In case of significant
change in LGB for longer duration, the responsible constituent/s may
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 42 of 83
submit revised LGB for a specific period, preferably on day ahead basis
for validation of SRPC and subsequent revision of ATC by SRLDC.
SRPC had clarified that there was no role of SRPC Secretariat for
validation in real time or on day ahead basis. Neither any Regulation
mandated such requirement nor did they have the infrastructure (24 hrs
Control Room) to take up such works. Clause 4.5 of Detailed Procedure
for Relieving Congestion in Real Time Operation was brought to kind
notice as reproduced below:
“ NLDC may revise the TTC/TRM and ATC due to change in
system conditions(including commissioning of new
transmission lines/generation), vis-à-vis earlier anticipated
conditions which included change in network topology or
change in anticipated active or reactive generation or load at
any of the nodes in the study. Revisions may be done by NLDC
based on its own observations or based on inputs received
from SLDCs/RLDCs. Revised TTC, TRM and ATC shall be
published on website of NLDC and RLDCs along with reasons
thereof. ”
On perusal of the above, it can be seen that ATC/TTC may
have to be revised in real time even for Load Generation
Balance change. There was no role of SRPC Secretariat after
LGBR validation on monthly basis.
The following was also noted from Para 54 of Order dated 22nd
February 2014 in respect of Petition No. 167/Suo-Motu/2012 as
reproduced below:
“ NLDC further states that Enquiry Committee has recommended
the following:
NLDC and each RLDC should have one real-time security desk in
all the shifts to be manned by engineer capable of carrying out TTC
calculations. To facilitate this, manpower at NLDC and RLDCs
need to be enhanced with regulatory support to take care of
financial aspects. Till this arrangement can be firmed up, various
scenarios of outages could be built, which then can be used by
despatcher in real time. Faster algorithm for calculation of TTC
may be adopted by the load despatchers to update it in real time
under outage conditions. Post disturbance NLDC/RLDCs are
taking up the above recommendation for manning of security desk
at each RLDC and NLDC by engineers capable of carrying out
TTC calculations….”
SRLDC had observed that System Studies / Security analysis being
carried out in real time are primarily meant for demand management,
clearance of emergency outages, averting any eventuality due to lack of
meeting n-1 criteria etc.
Need for having quality node wise data from the constituents (for 96
time blocks / different scenario like peak / off-peak) was also
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 43 of 83
emphasized before computation of ATC for optimal utilization of
transmission system. Constituents were requested to furnish Block
wise/Day-wise LGBR figures (Node-wise) for the coming five months
and the system should be in place by September 2014.
12.3 TANTRANSCO vide letter dated 3rd
July 2014 (refer Annexure-VI) has stated a
migration of TTC methodology to flow gate all of a sudden has been done by
SRLDC without discussion in any forum. Further, the method adopted has not been
described to the SR constituents. Levy of congestion charges would only add
commercial burden to the constituents and would not be the proper solution for
restricting overloading of line. Therefore, instead of applying congestion charges,
curtailment of STOA power, URS and MTOA power should be made.
12.4 In the Meeting, MS I/c, SRPC informed that the issue had been deliberated in
various forums/OCC meetings. It was perceived that there were no issues regarding
study part, and issues pertained to procedure, real time ATC, curtailments etc. As
per Congestion Regulations SLDC’s had to carry out the computations of
TTC/ATC of their intra-state system keeping in view load generation balance. They
needed to furnish node wise LGB details to RLDC. However, except KSEB no
other state was furnishing the details to SRLDC. It had been agreed in the OCC
forum that node wise/day wise/period wise/block wise load and generation details
for next 5 months were to be furnished for validation. SLDC’s had expressed
constraints stating that dedicated studies team was not available with them and they
were facing manpower crunch. Dedicated system studies group was necessary for
this purpose.
12.5 ED, SRLDC stated that real time flows could not be considered for release of ATC.
SRLDC was always trying to optimize flows keeping in view the grid security.
Input data in the requisite format was not being received from the SLDCs. Block
wise/node wise data could be furnished which may enable release of higher ATC
during off peak hours. Such inputs and cooperation of SLDC’s would enable
RLDC/NLDC to compute ATC in a more scientific manner.
12.6 CE (O), TANTRANSCO enquired about furnishing of similar information by other
states in other regions. He opined that furnishing node wise data was difficult. He
informed that they were having more than 100 nodes at 230 KV level. He therefore
suggested that system for furnishing node wise data could commence at 400 kV
level.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 44 of 83
12.7 Director (Tr. & SO), KSEB pointed out that the net ATC to S2 constituents had
been reduced from 15th
May 2014. This happened due to migration to flow gate
based methodology without any proper justification. During real time, the flows
were less than the ATC. Hence, additional corridor needed to be released to ensure
that transmission assets are utilized optimally.
12.8 ED, NLDC informed that Regulations mandated computation of ATC/TTC by
SLDCs in respect of their control area. While carrying out this exercise, Punjab had
realized the constraints in the intra state network and power procurement was done
accordingly. Gujarat though being surplus state with good wind generation had
observed intra-State constraints. In the interest of constituents, more than 30 to 50
revisions were being done monthly so as to optimize utilization of the corridor.
More validated data in the requisite format would help in assessment of ATC/TTC
more accurately.
12.9 TSTRANSCO informed that for proper ATC/TTC computation by SLDC, firm and
accurate inputs of load and generation etc were required from the Discoms and
State Generating Companies. In the absence of Intra-State ABT, there was some
degree of uncertainty in respect of embedded generators. Generators were citing
poor coal quality/shortage, restrictions on sudden variations in loading etc as
constraints. Hence the entire system needed to contribute accurately in turn to
enable SLDCs to furnish realistic ATC/TTC computations to RLDC.
12.10 TANGEDCO stated that a pragmatic and practical view was very essential to take in
this regard. All constituents were expressing the constraints in furnishing the data
desired by SRLDC. The matter was needed to be taken in the appropriate forum so
that necessary amendments could be suggested and implemented in the Regulations
12.11 Director (Tr.), KPTCL suggested that issues in this regard be further discussed in
the proposed TCC meeting.
12.12 After deliberations it was agreed that the issue would further be discussed in the
Special Meeting of TCC. In the Special meeting, constituents would revert back on
the issues being faced (with facts/figures) with regard to the data to be furnished by
SLDC. SRLDC would also present about the need for getting such data for ATC
computations.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 45 of 83
13. IEGC RELATED ISSUES
13.1 Restricted Governor Mode of Operation (RGMO)/FGMO of Generating
Units & MVAR Interchange
RGMO response had been deliberated in various Meetings held on the issue. The
issue had been further highlighted in the 23rd
/24th
SRPC Meetings. Inadequate
response is an area of serious concern and there was no noticeable improvement. In
this regard, there is an ongoing Petition (No.302/MP/2013) being heard by Hon’ble
CERC. The issue was further deliberated in the Meeting held in MoP on
13.01.2014 & 07.02.2014. RGMO response was again analyzed in a Special
Meeting on RGMO/MVAR held on 23rd
June 2014 with participation from CERC
staff.
The Summary of deliberation is as follows:
It was noted that response at times being reported by generators was
in variance with the response being observed by the SLDC/SRLDC.
Data validation was thus needed to be carried out between state
generators and the respective SLDCs and the ISGS generators and
SRLDC.
DC declaration by generators could be made appropriately to ensure
RGMO response. State Load Despatch Centers could also schedule
appropriately so as to ensure the response.
Ramagundam to study the RGMO response of its units and
specifically Unit-7 and revert back with details.
It was suggested that the STOAs should not be transacted/permitted
by SLDC beyond MCR to ensure that response is available for
purpose of grid security.
KPCL to appropriately take up the issue regarding up rating/installed
capacity of Nagjheri units.
Reasons for non-performance needed to be qualified with proper
technical justification by the generators.
TTPS to discuss with M/s NTPC/BHEL regarding implementation of
RGMO in Unchahar and Korba and compare the scheme provided in
TTPS.
All technical issues needed to be taken up with OEM and concrete
action plan to be ensured within two months.
It was noted that instances of frequency excursion were still
continuing. States were therefore requested to stagger the
changeover and minimize the effect on the Regional Grid/generators.
It was recommended that all the stations should have data logging
facility (up to six months) for fruitful analysis/deliberation.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 46 of 83
RGMO should always be in service including at technical minimum.
Generators to initiate steps to ensure visibility of RGMO status in
the SCADA.
Parameters needed to be maintained so as to ensure that RGMO
response is available at all instances.
SLDCs to take proactive role for RGMO implementation/
monitoring.
TN SLDC to ensure participation/data furnishing from STCMS units
also.
KSEB was suggested to ensure FGMO response of balance units not
under FGMO, through their internal maintenance team, wherever
possible.
It was noted that individual GENCOs needed to approach through
petition to Hon’ble CERC for obtaining any exemption/extension of
RGMO/FGMO compliance.
In accordance with RoP on Petition No.302/MP/2013 all SLDCs
need to furnish the following on affidavit by 6th
July 2014:
Report with details of RGMO/FGMO response of each
generating station within their control areas and
Details of having taken up the matter with respective SERC
in case lack of response or inadequate response from the
generating units within their respective states.
In the Meeting it was again suggested that SLDCs may take up with
their respective State Commissions the lack of response/inadequate
response of the generators of their control area.
In accordance with RoP on Petition No.302/MP/2013, TANGEDCO
and APGENCO had been directed to submit on affidavit detailed
note explaining how irrigation requirement is coming in the way of
implementation of FGMO/RGMO, after discussing the matter, if
required, with their State Irrigation Department by 6th
July 2014.
It was suggested that the GENCOs/SLDCs may please take up the
issue with their Irrigation Department.
Adequate RGMO response and UFR/df/dt relief in other regions was
also required to be ensured / monitored to avoid sudden change of
direction of flow on 765 KV Raichur-Sholapur line. NLDC/SRLDC
were requested to take steps accordingly.
In the OCC Meetings, constituents had expressed that 40% ideal
response in FRC computation was not appropriate in present Indian
power scenario. FRC computations for load/generation change of
more than 1,000 MW could be considered for enhancement since
NEWS Grid had been operational.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 47 of 83
Generators were expected to give response of 5% of the current
generation subject to 105% of MCR and analysis would be carried
out accordingly for new instances.
13.2.1 In the Meeting, ED, SRLDC stated that SLDCs were not according due
importance to analysis of RGMO performance. It had been observed that the
response was only upto about 40 to 50 %. SLDCs had therefore to play a more
proactive role in this regard.
13.2.2 MS I/c, SRPC pointed out that inadequate response was required to be taken up
with concerned SERC by SLDCs. Visibility of RGMO status in SCADA was also
required for better monitoring. Taking out of RGMO if at all was needed to be
carried under due intimation to RLDC/SLDC along with valid reasons.
13.2.3 ED, NLDC informed that in the recent meeting of NRPC, it had been decided that
RLDC would broadcast 2 to 3 instances every month. The generating stations
would furnish their response to RLDC/RPC for analysis/validation. MS I/c, SRPC
informed that similar practice was already in vogue in SR. A Group had been
formed where the instances were getting posted. A number of Meetings had
already been convened.
13.2.4 TS SLDC observed that the Southern Region states were facing power deficit.
Decision regarding sacrificing of 5% generation so as to ensure RGMO response
was needed to be taken up at SRPC level also. Also, there was no margin
available at times with all mills in operation due to poor fuel quality.
13.2.5 NTPC stated that response at that instant may vary with respect to coal quality
and system parameter. Hence, to expect 5 % response in all instances may not be
feasible.
13.2.6 Chairperson TCC, observed that adequate RGMO response was very necessary
for Grid stability. He urged that generators make all efforts to improve the
response. Unit wise response etc could be deliberated in the special RGMO
Meeting. He added that there should a sense of urgency for improvement of the
RGMO performance.
13.2.7 After deliberations, the following was summarized:
All GENCOs would endeavor to ensure RGMO response as mandated
in the Regulations.
Response would be analyzed further in a Special Meeting of Generators
to be held during August 2014.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 48 of 83
13.2.8 Regarding MVAR, the action plan recommended in the Meeting held on
23rd
June 2014 is furnished below:
GT tap positions to be changed as per recommendations. All other
stations to ensure their GT Tap positions are optimized so as to bring
Grid Voltages to Nominal values.
Respective SLDCs would monitor VAR Interchange of the generators
in their control area and also ensure better voltage profile.
Respective SLDCs would participate in reactive power demonstration
testing along with the testing team for the units under their control
area.
SRLDC could issue messages for Violation under IEGC clause 6.6.6
All Generators agreed to initiate timely action on the
recommendations. Dates of Tap changes and set tap positions need to
be communicated to SRPC/SRLDC as and when changes are carried
out. Same should also be reflected in the information which would be
furnished for future analysis
400kV Tap changing is to be carried out only after due concurrence of
SRLDC.
Number of Generators were not furnishing timely information in
correct format. It was suggested that information should be furnished
in a timely manner.
Calibration of meters to be under taken so as to ensure accurate
visibility of the parameters to the plant operators.
Limiter setting would be as per the capability curve.
Some of the stations AVR voltage control was not going to± 5%. The
same would be examined and rectified.
Stations could themselves conduct reactive demonstration, periodically
as per the agreed procedure.
It was agreed that the demonstration of MVAR would be carried out
only up to 95% of the rated auxiliary voltage.
MVAR data to be posted on [email protected]. Data for
state generators needed to be validated by the respective SLDC.
It was recommended that all the stations should have data logging
facility (up to six months) for fruitful analysis/deliberation.
Any, change in capability curves w.r.t. data furnished for MVAR
document would be communicated. Wherever CC is not clear,
information could be sent in table format also.
The following had been noted in the 24th
SRPC meeting :
SRLDC had also informed that MVAR demonstration had been
carried out at Srisailam (LB and RB) and Vijayawada units.
Against MVAR absorption capability of 100 MVAR/unit, units at
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 49 of 83
Srisailam were absorbing only about 60 MVAR each. APGENCO
had been requested to take up this matter immediately with the
OEM. Higher absorption would help improve the voltage profile
with use of existing resources itself. MVAR absorption by VTPS
(500 MW) unit had improved to about 140 MVAR as against
earlier level of about 70 MVAR. MVAR demonstration had also
been carried out at Raichur, Kadra, Kodasalli and Nagjheri units of
KPCL. Calibration of all the meters (other than Energy meters
also) and data logging facility was however highly necessary.
Testing at Raichur TPS could not be completed on account of
mismatch of system parameters in various meters. It was also
requested that the concerned generators may study the reports and
arrange for necessary remedial measures.
13.2.9 In the Meeting MS I/c, SRPC requested the constituents to kindly comply the
decisions taken in various Meetings in this regard.
13.2.10 ED, SRLDC informed that Raichur STPS was yet to rectify the mismatch between
SCADA and generator meter data which was observed during the MVAR testing.
KPCL informed that works had been taken up and would be completed in 3 to 4
months.
13.3 Arranging of interruptible loads in four groups
In the OCC meetings, it was noted that as per IEGC, to maintain
the frequency within stipulated band and also to ensure network
security, interruptible loads are to be arranged in four groups of
loads. This was for the purpose of scheduled power cuts/load
shedding, loads for unscheduled load shedding, loads to be shed
through UF relays, df/dt relays and loads to be shed under any SPS
Scheme. These loads are to be grouped in such a manner that
there was no overlapping between different groups of loads.
SRLDC & SRPC Secretariat pointed out that existing schemes
were not meeting the Regulatory requirement fully and further
action was required in this regard.
13.4 Automatic Demand Management Schemes
13.4.1 Automatic Demand Management Scheme in line with clause 5.4.2 (d) of the
IEGC was to be provided by all the constituents by 1stJanuary 2011.SRLDC &
SRPC Secretariat had pointed out that automated scheme was to be in place to
meet Regulatory requirement.
13.4.2 In the 24th
SRPC Meeting the following had been noted :
Hon’ble Commission’s Order dated 18.12.2013 in respect of Petition
No. 208/SM/2011 was noted.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 50 of 83
In CERC’s Order dated 22nd
February 2014 in Petition No. 120/2011
regarding Maintaining grid security of the Southern Regional Grid
by curbing over drawal and effecting proper load management by
Tamil Nadu Electricity Board the following had been stated:
Respondent to take necessary steps to implement automatic
demand management scheme to deal with the emergency
situations such as sudden variation of wind generation or
forced outages etc. and submit the monthly progress report
to SRLDC and SRPC in this regard.
SRPC shall inform the Commission about any deficiency in
the action taken by the respondent and non-compliance
with the directions of the Commission.
TN was to submit monthly progress report to SRPC and
SRLDC.
13.4.3 In the OCC meetings the following had been noted:
KSEB vide their letter dated 20th
May 2014 had informed that
ADMS has been implemented. Kerala had been requested to
demonstrate the functioning of ADMS to SRPC/ SRLDC.
TANTRANSCO had informed that they had identified the feeders
of quantum of 650 MW and the P&C wing of TANTRANSCO was
implementing the scheme.
All the SLDCs except KSEB had been requested to finalize the
scheme and get it approved through their management for
implementation by June 2014 end.
13.4.4 Hon’ble CERC had heard the Petition No 005/SM/2014 on 22nd
May 2014. In
the RoP, it had been stated that the Commission observed that despite
understanding the scheme technically, SLDCs are not implementing the
scheme which is of national importance. The Commission had directed the
respondents to implement ADMS in pro-active manner and approach the
Commission if they face any difficulty in implementation of scheme. The
Commission had also directed the respondents to submit on affidavit, by 30th
June 2014 an action plan and PERT chart clearly mentioning the targets and
deadline to achieve the same, with an advance copy to RLDCs.
13.4.5 In the Meeting, MS I/c, SRPC informed that in compliance of Order dated
22nd
February 2014 of CERC in respect of Petition No. 120/2011, it was learnt
that TANTRANSCO had finalized the scheme and communicated to P&C
Wing for implementation. Since considerable time had lapsed, the scheme
needed to be in place at the earliest. Other Constituents (other than KSEB)
also needed to put the ADMS in place.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 51 of 83
13.4.6 Director (Tr.), KPTCL informed that 350 MW loads had been identified for
ADMS. Initially the loads would be tripped manually, but within a period of
three months, the same would be automated.
13.4.7 Director, APTRANSCO informed that 60 RTUs had been planned to be
installed and they were also planning to have a Meeting with DISCOMs to
finalize ADMS.
13.4.8 AP & Telangana informed that the new upgraded SCADA system was likely
to be in place by October 2014 and ADMS would be subsequently
implemented.
13.4.9 KSEB informed that the scheme (320 MW) had already been implemented.
13.4.10 Director, TANTRANSCO informed that 650 MW of loads (110 KV radial)
had been identified and logic had been received by P&C wing and they were
on the job. The scheme was expected to be operational by October 2014.
13.4.11 ED, SRLDC stated that ADMS for TN should also address the sudden
variations of wind generation.
13.5 Automatic Load Disconnection Schemes for overdrawing constituents
In the 14th
Meeting of SRPC held on 27th
August 2010, it had been agreed to
implement Automatic Load Disconnection Scheme for overdrawing constituents
with the following relief:
Sl. No. Constituents Load Relief
1 APTRANSCO 450 MW
2 KPTCL 350 MW
3 KSEB 125 MW
4 TANTRANSCO 650 MW
5 Puducherry 25 MW
It was noted that the Automatic Load Disconnection Scheme was part
of Automatic Demand Management Scheme.
States had been requested to ensure adequate load relief in the interest
of grid security.
SRLDC & SRPC Secretariat had pointed out that the scheme needed
to be in automated so as to meet the Regulatory requirements.
13.6 Sudden Change in Drawal/Frequency Excursion
13.6.1 States had been requested to adhere to drawal schedule and also not to under
draw during high frequency conditions.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 52 of 83
13.6.2 In the earlier Meetings, SRLDC had brought to kind attention provisions of
clause 5.2 (j) of the IEGC Regulations. No user was to cause sudden variation
in its load by more than 100 MW without prior intimation to and consent of
the RLDC. Similarly no user should reduce the generating unit output by more
than 100 MW without prior intimation to and consent of the RLDC. Necessary
action was sought in respect of demand and generation management as well as
power purchases, so that clause 5.2 (j) of IEGC Regulations is not violated.
13.6.3 SRLDC had been reporting instances of violation of IEGC clause 5.2(j) with
the constituents for necessary compliance. In the 96th
Meeting of OCC,
SRLDC had stated that the issue of sudden change in drawal pattern to
extreme level was being continuously taken-up under IEGC clause 1.5 but the
improvement of situation was not to the desired level. During load
changeover, it had been observed drawal deviation vary between – 300 MW to
+300 MW in many instances. Proper implementation of ADMS and
staggering of loads was essential to avoid sudden changes in load. In the
absence of effective RGMO / FGMO, the changeover impact was getting
reflected in inrush of flow on critical lines and was posing threat to security of
the grid. Hence, the constituents had been requested to kindly ensure strict
compliance of IEGC by ensuring the changes not more than 100 MW and also
to ensure smooth load changeover in a staggered manner to avoid sudden
changes. In case, the situation did not improve to the mandated level, SRLDC
may be constrained to approach Hon’ble CERC in this matter.
13.6.4 In the Meeting, ED, SRLDC expressed concern that despite this issue being
flagged in various forums for the past two years, the load change over
staggering still needed refinement. Earlier the problem was restricted to SR
alone but was now getting reflected on flows on Raichur-Sholapur link. Thus,
it was affecting operation in other Regions also. Summary of violation
messages issued by SRLDC in this regard is furnished at Annexure-XV
13.6.5 Director (Tr.), KPTCL said that with increases in size of the system and EHV
lumped loads coming and going out of the system, it was difficult to manage
sudden variations in loads. Earlier, changeover in BESCOM was coinciding
with changeover in GESCOM which had been staggered to avoid sudden
jumps.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 53 of 83
13.6.6 MD, TANTRANSCO said that it was very difficult to manage such
limitations during high wind conditions. About 1,200 MW of unscheduled
load shedding was being carried out at times.
13.6.7 CEO, JSWEL said that this issue had to be seen keeping in view the tie up of
power purchase in different time blocks. Presently more tie ups were for RTC
power, with wide load variations in the system, leading to such variations.
13.6.8 Chairperson, TCC stated that SLDCs needed to monitor change overs
meticulously and requested them to comply with the Regulations and avoid
sudden changes in the drawal pattern.
13.7 Inadequate UFRs and df/dt reliefs
13.7.1 Issue regarding inadequate relief through UFRs and df/dt relays had
consistently been raised by SRLDC & SRPC Secretariat. SRLDC had also
reported the issue under 1.5 of IEGC on a number of occasions. SRPC
Secretariat had taken up the matter with Constituents for necessary
compliance.
13.7.2 On 19th
December 2013,Hon’ble CERC had issued its Order in respect of
Petition No 263/MP/2012.It had been directed that SR constituents identify
additional feeders and install UFR and df/dt relays to ensure relief as decided
by SRPC from time to time. Compliance Report duly certified by SRLDC and
SRPC was to be submitted regarding implementation of quantum of relief of
AUFR as per the table furnished in the Order and also proper functioning of
df/dt relays within one month of issuing the Order. SLDCs had also been
directed to map the relays on the SCADA system within three months of
issuance of the Orders. The certified relief quantum by SRLDC and SRPC
had been furnished to the constituents.
13.7.3 In the OCC meetings, it had been noted that in compliance of orders of
Hon’ble CERC, SRPC vide letter dated 23.04.2014 had communicated
compliance report in respect of the following:
Status of the additional identified loads which were to be
implemented.
Status of additional loads to be identified and implemented.
Status of SCADA mapping and the action plan to achieve 100 %
mapping.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 54 of 83
SRLDC has been continuously monitoring on its SCADA system the feeders
connected with AUFR & df/dt protection (as available in SCADA). This has
been done to ascertain the extent of protection available in the event of any
contingency. SRLDC has also been addressing regular communications in this
regard conveying the observations. The matter regarding in adequate quantum
of relief is being constantly reported by SRLDC under clause 1.5 of IEGC.
13.7.4 In the Meeting ED, SRLDC presented the status of SCADA mapping and visible
relief (Annexure-XVI). He expressed concern over the moderate quantum of relief
visible. ED, NLDC said that absence of strong safety net also inhibited release of
higher TTC/ATC. Only about 70% relief was visible and in real time it was always
in doubt whether any untoward incident could be managed.
13.7.5 CE (O), TANTRANSCO said that most of the feeders had been identified for
various schemes and availability of radial feeders was limited. He added that the
relief provided was adequate for the purpose of grid security. Expecting constant
relief all the time did not appear feasible keeping in view variability in loading of
the feeders. Actual relief at any instant would naturally be based on the prevailing
load on the system. The expected relief should have some correlation with the
system load and could not be constant.
13.7.6 MS I/c, SRPC said that the relief figures had been finalized by NPC as per the
recommendations of Zhalte Committee. 1Hz jump had been envisaged at each of
the four stages. Relief was to be ensured on average value as directed by Hon’ble
CERC. Relief could also be provided at lower voltage levels as had been
implemented by KSEB.
13.7.7 KSEB informed that they had gone up to 11 kV level and overlap had also been
avoided.
13.7.8 Chairperson TCC, suggested that the visible reliefs/reliefs provided be reviewed by
SLDCs in consultation with Discoms.
13.7.9 After deliberations SLDCs were requested to examine the matter in consultation
with the Discoms. Endeavour to improve the relief figures by about 20 % (at least
up to 70 % ) would be ensured by the next SRPC Meeting.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 55 of 83
13.8 Demand Estimation for Operational Purpose (Clause 5.3 of IEGC)
13.8.1 Each SLDC was to create mechanism and facilities to facilitate on-line
demand estimation of demand for daily operational purpose for each 15
minutes block by 01.01.2011.
13.8.2 In this regard, following may kindly be noted as contained in Order dated 19th
December 2013 of Hon’ble CERC in Petition No. 249/250/251/MP/2012:
“We direct all STUs/SLDCs of the Northern Region, Southern Region
and Eastern Region to forecast their demand and make adequate
arrangements to avoid dependence on Unscheduled Interchange for
meeting their demand or for injecting short term surplus power,
irrespective of the frequency.”
13.8.3 In the 24th
Meeting of SRPC it had been noted that day ahead (block wise)
demand forecast along with portfolio management was to be displayed in
website of SLDCs as per directions of MoP.
13.8.4 In the meeting the following was noted:
KSEB informed that they were displaying the Demand forecast on
their website
KPTCL informed that they were sending the information to
SRLDC/SRPC through e-mail
TANTRANSCO observed that they were ready to share information
with SRLDC/SRPC but were constrained not to share this
information in public domain.
13.8.5 SRPC Secretariat pointed out that Demand forecasting tool for operational
purposes was yet to be developed to meet regulatory requirement.
13.9 Low Voltage and installation of UV Relay
13.9.1 In the earlier OCC Meetings the following had been noted:
SRLDC had expressed concern about the low voltages in Mysore,
Bangalore, Udumalpet, Madakkathara, Palakkad, Kochi and North
Kerala areas.
KPTCL had informed that higher management had been apprised of
the UV relays requirement. In order to maintain the voltages, they
were taking immediate actions and all the circles had been directed
to rectify/replace faulty capacitor banks and directives had been
issued in this regard. Tenders had been floated for procurement of
500 MVAR Capacitor banks for which budget provisions was also
made.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 56 of 83
KSEB had informed that a scheme to implement the UV relays had
been prepared and would be finalized within a couple of weeks.
SRPC and SRLDC had suggested that specifications mentioned in
the NLDC document (Stage I: V < 200 or 198 (IEGC) KV for more
than 5 Minutes, Stage II: V < 185 KV for 30 seconds) for GSES
maybe followed in this regard.
TANTRANSCO had informed that 1,005 MVAR of capacitors at
distribution level were under various stages of installation.
In the 96th
OCCM, after deliberations, it had been concluded to
identify list of feeders that may be suitable for physical regulatory
measures by SRLDC in case of consistent low voltage situation at
specific nodes since there was delay in implementation of Under
Voltage Relays which was IEGC mandated provision and approved
by SRPC in earlier meeting. This interim measure of physical
regulation may be implemented till installation of sufficient
capacitors / UV relays. All the constituents had been kindly
requested to furnish action plan for installation of UV relays by
26.06.2014, else physical regulations may need to be taken up in the
interest of system security.
13.9.2 In the Meeting, MS I/c, SRPC informed that despite earlier approval of SRPC
regarding UVR implementation, there had been no progress in Karnataka and Tamil
Nadu. Karnataka and Tamil Nadu were however informing about the progress of
capacitor installation. KSEB had finalized the scheme which had been put to higher
management and approval was awaited.
13.9.3 ED, SRLDC said that this issue was being followed up since last couple of years
and they may be constrained to go for physical regulation measures in low voltage
areas. In the OCC Meeting the list of low voltage nodes and the proposed feeders to
be tripped for voltage regulation had been discussed.
13.9.4 Director (Tr), KPTCL agreed to implement UV relay scheme. He added that steps
would also be taken to provide capacitor of adequate capacity at low voltage nodes.
13.9.5 CE (O), TANTRANSCO said that they would maintain the voltage levels within
limits at 230 kV level and below. SRLDC should monitor the voltage level at 400
kV level. He added that with commissioning of a number of 400 kV lines, the
voltage profile had improved. 400 kV Chittor – Thiruvalam line was even tripping
on high voltage.
13.9.6 MS I/c, SRPC observed that loss of wind generation had taken place due to low
voltage scenario. States were to maintain voltages within IEGC range and in case
voltages are not maintained, then UVR is to be provided as per IEGC.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 57 of 83
13.10 Low Voltage Ride Through (LVRT)
13.10.1 In the Meeting, MS I/c, SRPC informed that there had been 3-4 incidences of wind
generation withdrawal of around 1,000 MW in the past one year. This was on
account of non availability of LVRT feature which was a matter of great concern
to grid security. Special Meeting of Protection Sub-Group had been held in this
regard on 08th
July 2014 (recommendations at Annexure-XVII).
13.10.2 MD, TANTRANSCO informed that the old generators were getting phased out and
new generators were coming up. Lot of capacitor installation was also being
undertaken to improve the voltage profile. Wind generation was also being backed
down to contain voltage fluctuations. The matter regarding provision of LVRT
features was being taken up with the wind developers.
13.10.3 ED, NLDC stated that sudden loss of about 1,000 MW of generation due to
uncleared faults/voltage dips was a serious threat. This assumed greater
significance since it would reflect in sudden inrush of power towards SR on
Raichur-Sholapur link. Hence, TN needed to take up the issue of LVRT/FRT in a
time bound manner so as to ensure that grid security is not endangered. This was
especially required since around 7,000 MW of wind generation was already
installed in the TN grid.
13.10.4 Director (Tr), KPTCL informed that they were viewing the issue with concern
since about 70% of the wind mills in Karnataka Grid may not be equipped with
LVRT feature presently. They would take up the issue with wind developers.
Compliance in this regard could be planned only in a phased manner. Most of the
wind mills (about 95 %) were privately owned and commissioned over a period of
6 to 8 years.
13.10.5 ED, SRLDC said that action with regard to the Report on Low Voltage in
Udumalpet was awaited from TANTRANSCO. TANTRANSCO informed that 24
MVAR capacitor out of 120 MVAR had been installed in Udumalpet area and
works were under progress for balance capacitors. In addition capacitors at
distribution level were also being added. Further, 200 MVAR of dynamic
compensation would be commissioned by PGCIL at Udumalpet. They requested
for early commissioning of the same. It was also informed by TN that LVRT
characteristics would be provided in the windmills (around 7,000 MW) before the
wind season next year. Presently about 1,087 MW of wind mills were equipped
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 58 of 83
with this characteristics.
13.10.6 After deliberations, it was agreed that new upcoming units would be ensured with
LVRT features as mandated under the Regulations. Tamil Nadu & Karnataka
were requested to kindly take up the recommendations finalized in the Meeting
held on 08th
July 2014.
14. OPERATION OF FILTERS AT HVDC KOLAR
14.1 In the OCC meetings, it had been pointed out by SRLDC that Kolar Control
Room was refusing to switch on the filters (capacitors) on being directed by
SRLDC in order to control low voltages. SRLDC had suggested PGCIL to switch
on the filter banks at Kolar HVDC when the Kolar bus voltage falls below 395 kV
as per the real time directions of SRLDC as was being done earlier. PGCIL had
stated that set point of capacitor filters were set in 20 kV band in the range 390 –
410 kV. All the logics were in auto mode and there was no scope for manual
intervention. Manual intervention had earlier lead to failure of number of
capacitor bank and hence manual switching was not recommended. PGCIL had
informed that the issue regarding changing the range to 395-415 kV and changing
the band of 20 kV to 15 kV had been referred to M/s Siemens. The OEM had not
accepted for the recommended changes. OEM had expressed that there could be
damages to breakers, filters etc at higher level of the band.
14.2 SRLDC had requested POWERGRID to furnish details of manufacturer’s
response. The case needed to be understood at par with generator’s capability
curve, performance possibility etc. This would facilitate to understand/suggest
any modification / additional requirement of software / hardware items that would
help power system to operate in an efficient manner.
14.3 In the Meeting, ED, SRLDC said that Somanahalli & Hoody voltages were low
and maximum MVAR support from Kolar would help in improving voltage
profile.
14.4 GM, PGCIL informed that changing of band from 390- 410 kV to 395- 415 kV
was not accepted by the OEM. It was pointed out that the availability of the
Talcher-Kolar link was more than 99.90 % and even 100 % in many months with
the cooperation of the states, SRPC & SRLDC. This link was very vital for
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 59 of 83
system operation. It was carrying maximum power flow of 2,300 MW on a daily
basis. Initially a number of capacitor filters had failed due to wear and tear/stress.
From the design point of view and keeping in view long term reliability, it was
not desirable to change the existing set points. It was also to be borne in mind that
the system had aged.
14.5 After deliberations, it was agreed that the existing set points would be continued.
15. KKNPP RELATED ISSUES
15.1 A Special Meeting was held on 12th
March 2014 at SRPC Bangalore to deliberate
on the issues related to KKNPP. The following issues needed resolution:
Implementation of SPS during Tripping of ATS
KKNPP vide letter dated 06th
June 2014 had informed regarding manual
reduction of generation of KKNPP at 50 MW/Min in contingency. It
was once again pointed out the scheme of 50MW/min manual reduction
may not be adequate to ensure the unit survival. The scheme needed to
be automated.
Auto reclose with 11/2 Breaker scheme
SRLDC stated that A/R scheme needs to be implemented before
CoD of unit.
Hot line link between KKNPP and SRLDC
KKNPP had informed that approval for hotline link to SRLDC had
been received and the same would be commissioned shortly.
SCADA Inputs to be ensured from KKNPP
Regarding the pending SCADA input to SRLDC, alternate method
was being studied by KKNPP and they would revert back.
Spurious generation of SPS signal at KKNPP
SR II, PGCIL had completed the necessary modifications.
Interpretation of Capability Curve(limiting MVAR absorption to 100
MVAR)
KKNPP stated that the issues had been taken-up with concerned
agencies and they would revert back soon.
Status review of changing GT tap position at Kudankulam NPP
corresponding to 400 KV & Review of absorption / injection of
MVAR
KKNPP had stated that the issues had been taken-up with concerned
and would revert back soon.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 60 of 83
15.2 In the Meeting, the following was noted:
NPCIL informed that SPS was being reviewed by the designer. In the
interim period, SPS with 100 MW/minute manual reduction could be
utilized. However, as per their assessment, the unit may not survive even
with provision of SPS on account of power swings.
SRLDC stated that in case manual reduction is resorted, there was every
possibility that the existing line would trip. Thus, the complete
connectivity to the station could be lost. Black Start power could take
considerable time (even one day) since power would have to be supplied
after stabilization of Tuticorin generation.
NPCIL vide letter dated 06.06.2014 (Annexure-XVIII) addressed to
CTU had requested for advancing Tuticorin PS- Tirunelveli D/C line and
connecting KKNPP 1&2 – Tirunelveli D/C thus making it KKNPP 1&2-
Tuticorin PS D/C line. This would ensure that KKNPP 1& 2 would have
two corridors and may not call for operational measures during non-
availability of either of the two terminating stations. It was noted that this
issue would be deliberated in 37th
SCPSPSR scheduled to be held on 31st
July 2014.
NPCIL informed that pending SCADA points through alternate methods
would be completed before COD of Unit I. Hot line link with SRLDC had
been established.
NPCIL informed that Auto Reclose with 1½ Breaker scheme had been
implemented at RAPS. After trial run and getting necessary confidence, it
would also be implemented at KKNPP. NPCIL would try to implement
the same before CoD.
PGCIL observed that Auto Reclose feature had to be enabled on 400 KV
Kaiga-Guttur and Kaiga-Narendra lines also.
It was also noted that PGCIL had carried out modifications in the SPS
settings.
NPCIL informed that as per the designer, 100 MVAR absorption by the
unit was only possible. With commissioning of the second unit, line
loadings would increase and high voltage scenario may be relieved. The
GT tap setting would thus be reviewed after commissioning of Unit 2.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 61 of 83
SRLDC pointed that 100 MVAR absorption only in each unit may not be
sufficient to address the high voltage issue. Need for additional reactor at
KKNPP was required to be studied.
PGCIL informed that KKNPP was planned during 2002-03 with
generation expected in December 2007. In view of need of connectivity to
the nearest substation, two D/C 400 kV lines had been planned to
Tirunelveli S/S. Subsequently, in order to improve the reliability, one
Madurai-Tirunelveli line was bypassed and connected to KKNPP. Angular
separation was to be considered for connectivity/evacuation of Nuclear
stations and the line length could not be more. The constraint was coming
up since bypassed Madurai-Tirunelveli line was twin moose while
KKNPP –Tirunelveli portion was Quad. Direct connectivity to Tuticorin
PS was being proposed now to improve the connectivity.
Two reactors of 80 MVAR had been planned. Additional requirement of
reactors may need to be put up to the Standing Committee in view of
limitation of present absorption level as was being stated by NPCIL.
16. ALTERNATE / RELIABLE AUXILIARY SUPPLY AT HVDC
BHADRAWATHI
16.1 In the OCC Meetings it was noted that for a vital element like HVDC Bhadravathi
availability of alternate / reliable auxiliary supply was very critical. The
requirement was in line with CEA Technical Standard on Connectivity to Grid
Regulation. Uninterrupted changeover during failure of existing auxiliary supply
could not happen due to the inherent start-up time lag of DG set. The matter had
been taken up by SRPC with WRTS I, POWERGRID.
16.2 In the Meeting MS I/c, SRPC informed that the reply from WRTS had been
received. (Annexure-XIX) 315 MVA ICT had been planned and award had been
placed in October 2013 by WRTS PGCIL.
16.3 ED, SRLDC informed that there were two more instances on 6th
and 9th
July 2014
of blocking of HVDC poles at Bhadravathi. The number of such instances was
about 7 since 2013.
16.4 ED, SRTS-I, PGCIL said that they would revert back in this regard.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 62 of 83
17. PSS TUNING /SYSTEM STUDIES
17.1 SRLDC had suggested that to prevent instances such as MAPS Unit 2 at 5:23 Hrs
on 06th
May 2014 it was very much essential for reviewing / re-tuning of PSS of all
the major generators in the region. It was requested that a suitable action plan be
evolved in this regard and the services of experts be availed if required. In the
Meeting taken by Secretary (Power) on 11th
March 2014 (copy enclosed as
Annexure-XX) to discuss the Task Force Report, it can be seen that CTU had been
entrusted the responsibility of PSS tuning.
17. 2 It had also been desired that exercises such as analysis of grid conditions, factors
affecting grid operation etc be done by a dedicated system study group in each
utility and load dispatch centres. Details of the same could be communicated to the
respective RPC.
17.3 In the Meeting, CTU informed that they did not have the required expertise to
take up PSS tuning works.
17.4 MS I/c, SRPC noted that PSS tuning works had been entrusted to CTU by MoP
and requested CTU to take up the matter appropriately.
18. IMPLEMENTATION OF ENQUIRYCOMMITTEE RECOMMENDATIONS
18.1 Implementation of measures to prevent Grid Disturbance
(A) Third party Protection Audit
In the 24th
Meeting of SRPC the following had been noted:
Chairperson, SRPC vide letter dated 10th
December 2013
addressed to Secretary (Power), Government of India had
requested for 100% funding from PSDF for renovation and
up gradation works of protection system in Southern Region.
Hon’ble CERC had pronounced Orders in respect of the
Petition No. 146/MP/2013 with I.A 36/2013, dated 20th
February 2014. Following are the salient points for kind
compliance:
Respondents are to implement the works as
mentioned in Phase-I and Phase-II by 1.5.2014
and 1.9.2014 respectively.
SRPC has been directed to coordinate the
protection setting issue and submit a report
regarding implementation of Phase-I activities by
1.6.2014.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 63 of 83
SRPC had been further directed to submit
bimonthly status report for works mentioned in
Phase-II to the Commission.
In OCC Meetings, SRLDC pointed out that in the
compliance report submitted by the states for CERC
compliance, constituents had indicated status as ‘Tendering
in Process’ / ‘Items to be procured’ etc., This nature of
indication of status does not show any timeline / type of
tendering / important or urgency attached by the
constituents/commitment of constituents for compliance.
Therefore, all the constituents were requested to indicate the
break-up details of individual activities involved in a
particular recommendation with target time schedule of
completion.
Hon’ble CERC had already notified the (Power System Development
Fund) Regulations, 2014. Appraisal Committee under chairmanship of
Chairperson, CEA and Monitoring Committee headed by Secretary,
MoP had already been constituted. NLDC has been designated as Nodal
agency for PSDF. All states were requested to kindly prepare the DPR
for R&U as above and resubmit the same to NLDC i.e. Nodal Agency
with a copy to GM Division.
18.1.1 In the Meeting the following was noted:
KSEB had submitted the revised DPR to NLDC (Nodal Agency for PSDF).
Appraisal Committee had approved the DPR of Kerala.
It was requested that other constituents may also submit the DPRs to NLDC
to avail funding from PSDF. The nomination of Nodal Officers as requested
by NLDC could also please be expedited.
As regards Protection Audit, SRLDC/SRPC Secretariat requested all the
concerned utilities to expedite pending works and furnish the status update
to SRLDC/SRPC as per agreed time schedules. Hon’ble CERC was needed
to be approached for time extension, if required. It was noted that KSEB had
already approached Hon’ble CERC with a petition in this regard. It was also
agreed that a Meeting would be convened to assess the progress of
implementation of Phase I and Phase II activities. The report in this regard
had to be submitted to Hon’ble CERC.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 64 of 83
(B) Reactive Power Planning
In the 23rd
Meeting of SRPC, it had been agreed that Utilities
would furnish the schemes relating to Reactive Power
Planning including at distribution level within one month
indicating also the time schedules for implementation.
Progress of these schemes would be monitored in the SRPC
forum. Request for funding through PSDF could be sought at
a later date.
In the Meeting, constituents were requested to please furnish the
schemes at the earliest, wherever due.
(C) Ensuring proper functioning of UFRs and df/dt relays
In the Second Meeting of NPC, it had been decided that all
SLDCs and RLDCs would upload the details of feeders to be
tripped through the UFRs and the expected load relief at
different frequency levels in their respective States/Regions
on operations of UFRs. It had been also decided that RPCs
would submit inspection report of healthiness of UFR and
df/dt regularly on a quarterly basis to the NPC Secretariat.
18.2 Reporting the Status of implementation of the recommendations of the
Enquiry Committee
Status as on last day of the month to be forwarded by 3rd
day of the following
month, and that as on 15th
of the month to be forwarded by 17th
of the month. All
the constituents were requested to furnish timely status updates on the status of
implementation.
18.3 Review of Zone -3 Philosophy
The issue had been deliberated in Protection Sub-Committee Meeting held on 21st
November 2013 and settings for critical 400 kV lines had been finalized for
implementation.
18.4 Ring Fencing of Load Dispatch Centers (LDCs)
18.4.1 The status report on this was to be submitted every month to the NPC Secretariat.
18.4.2 In the 24th
Meeting of SRPC, it had been noted that Chairperson, SRPC vide letter
dated 11th
December 2013 addressed to Chairperson, CEA had conveyed the
opinion expressed by the constituents in the 23rd
SRPC Meeting with regard to
ring fencing of Load Despatch Centres.
18.4.3 In the Meeting it was noted that there was no change in the status.
18.4.4 ED, SRLDC stated that the staff needed to be strengthened in all the SLDCs.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 65 of 83
18.5 Utilization of LDC development fund for System Operators Training
18.5.1 TANTRANSCO vide letter dated 3rd
July 2014 (refer Annexure-VI) had stated as
per Orders of Hon’ble CERC in respect of Petition No.117/MP/2013, training
programmes could be conducted at NPTI and expenditure for the same could be
met from the LDC development fund. It has been stated that confirmation
whether cost for system operators training programme can be utilized from LDC
development fund be given so that SLDC could sponsor Officers for participation
in NPTI courses.
18.5.2 In the Meeting, ED, SRLDC informed that a letter had already been addressed to all
the constituents in this regard
19. REVIEW OF PERFORMANCE OF ULDC SCHEME
19.1 In the 23rd
& 24th
Meetings of SRPC, the following had been noted:
SRLDC had informed that in respect of pending data from
Talcher, all links for ICCP configuration at ERLDC had been
utilized. PGCIL needed to explore provision of hardware splitter at
Talcher.
In accordance with RoP in respect of Petition No. 56/SM/2013,
SRPC vide letter dated 9th
December 2013 had furnished status
update to Hon’ble CERC with copy to utilities for necessary
action.
19.2 In order dated 19th
December 2013 on Suo-Moto petition 56/SM/2013, Hon’ble
Commission had directed all the utilities to provide the required telemetry within
six months of this order. Progress of compliance in this regard by various utilities
wart. the report submitted on 25.09.2013 was compiled and submitted to Hon’ble
Commission in March 2014.
19.3 In the 96th
Meeting of OCC held on11th
June 2014 the following had been noted:
SRLDC had presented the status of data, voice and internet
communication and pending field inputs.
It was stated that the Stand by data channel and Voice Communication
from NTECL Vallur to SRLDC was frequently going out of order.
NTECL Vallur had informed that they had procured four converter
cards and handed over to PGCIL for installation. PGCIL/NTECL were
requested to complete the pending works at the earliest.
Standby data channel from 400 kV SS (SR-1 and SR-2) was to be
made through. Talcher Stage II data was still to be configured. PGCIL
had informed that DCPC for Talcher Stage II data had been installed
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 66 of 83
and extended to SRLDC end. Only integration works at SRLDC end
were pending.
Non availability of data in real time from NLC Stage II was yet to be
rectified. Reliable and dedicated internet communication was to be
ensured by all the users.
SCADA data was not being updated from Puducherry due to Front
End Processor fault at Puducherry Control Centre. Puducherry
informed that procurement of the equipment was under progress.
19.4 Subsequently Hon’ble CERC had issued show cause notice under section 142 to
constituents in its ROP in respect of Suo motu Petition No. 007/SM/2014 listed
for hearing on 22nd
May 2014.
19.5 In the Meeting the following was noted:
SRLDC presented the status of data, voice and internet communication
and pending field inputs. Details are enclosed as Annexure-XXI. It was
requested that other pending points be completed.
SRLDC informed that data for Talcher-II had been extended up to
SRLDC and integration was to be done with the new SCADA system.
SR-II PGCIL informed that the 8 points ( Talcher) pertaining to SR-II
had also been extended to SRLDC.
NTECL informed the Standby data channel and Voice Communication
would be rectified within two days.
Hot line between APSLDC and SRLDC was to be established.
It was noted with appreciation that Southern Region had the minimum
number of pending points as compared to other regions in the country.
20. NON-PAYMENT OF TRANSFORMER CHARGES TO TN BYSOUTHERN
REGION CONSTITUENTS AND PENDING ARREARS PAYMENT
BETWEEN BENEFICIARY STATES IN SR
20.1 In the 24th
Meeting of SRPC, the following had been noted:
TN had agreed to make payments for the undisputed amounts as per
the Minutes of the Meeting held with KPTCL. Similarly, they
requested that undisputed payments, due to TN be released. They
also informed that all relevant documents as per the MoM had been
furnished to KPTCL.
Regarding transformer charges, KPTCL had informed that 3
ESCOMS had paid while TANTRANSCO informed that payment
was being received from one ESCOM only. KPTCL had requested
that TANTRANSCO may coordinate with PCKL in this regard.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 67 of 83
APTRANSCO had informed that they had settled the issue
regarding monetary compensation and due payments had been
released to TANTRANSCO.
On a request, APTRANSCO had informed that they would consider
the issue regarding monetary compensation payment to KSEB
TANTRANSCO had requested APTRANSCO and KPTCL to
finalize a convenient date for a Meeting at Chennai to settle the long
pending issue regarding frequency linked penalty/incentive.
20.2 Subsequently, TANTRANSCO vide letter dated 17th
June 2014 (Annexure-XXII)
had informed that they had received payment of Rs.1,59,07,117/- made by all five
ESCOMs of Karnataka towards transformer charges.
20.3 TANTRANSCO vide letter dated 3rd
July 2014 (refer Annexure-VI) had stated that
an amount of Rs.26.50 Crore has to be paid by Karnataka to TN towards monetary
compensation and payment for the period between December 1998 to March 2001.
As requested by KPTCL, the entire set of documents had been made available to
KPTCL and PCKL. Regarding Frequency Linked Penalty/ Incentive Scheme for
overdrawal/ underdrawal of shares, TANTRANSCO had stated that APTRANSCO
and KPTCL may give suitable date for their visit to Chennai. It had also been stated
that the Nodal Agency SRLDC has to furnish the invoices sought by KPTCL on the
above issue
20.4 KSEB vide letter dated 14th
July 2014 (refer Annexure-VIII) had stated that an
amount of about Rs.4.77 crores is net receivable to KSEB from PCKL. An amount
of Rs.11.58 crores with interest is to be included as payable from KPTCL as
charges towards frequency linked penalty for over drawal during the period April
1994 to May 1997. It is also stated that an amount of Rs.14.5 crores is receivable
from AP towards compensation for frequency linked under drawal/over drawal. An
amount of around Rs.1.46 crores is receivable towards sale of KSEB power for
October 1992. KSEB had admitted APs claim of Rs.35,58,381/- payable by KSEB
towards transmission and wheeling charges for the month of March 2013.
20.5 In the Meeting it was agreed that KPTCL/PCKL and TANTRANSCO would settle
this issue bilaterally. It was also agreed that AP, KPTCL/PCKL and KSEB would
settle the issues bilaterally
20.6 APTRANSCO stated that it had already rejected the claims in respect of frequency
linked penalty/incentive scheme along with valid reasons. It had also been decided
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 68 of 83
that this issue would be resolved bilaterally and was not to be included as agenda in
SRPC meeting.
20.7 KSEB/TANTRANSCO stated that since this issue was not getting resolved
bilaterally, it had been brought to SRPC forum.
20.8 TANTRANSCO stated that SRLDC was the designated agency for frequency
linked penalty/incentive scheme and hence it should provide necessary data for
settling this issue.
20.9 ED, SRLDC informed that in respect of frequency linked penalty/incentive scheme
SRLDC was not in a position to provide any data except for the month wise
summary of the payables and receivables. The hourly data and computation were
stored in floppies which became unusable over a period of about 20 years. This had
already been informed earlier.
20.10 Chairperson TCC suggested that a separate Meeting could be convened and
SRLDC may provide necessary guidance in this regard.
21. OUTSTANDING DUES BETWEEN WR & SR
21.1 Meetings between WR & SR Constituents regarding outstanding payments in
respect of energy transactions between WR & SR for the period prior to January
2003 were held at Mumbai & Bangalore. The fifth Meeting in this regard was held
on 21stMay 2014 at Mumbai, where in it was agreed that by end of June 2014
MSEDCL & MPPMCL would furnish the reconciled statements to SR constituents.
21.2 PTC had deposited an amount of Rs.3,70,85,091/- with Corporate Office
POWERGRID during the year 2002 (Annexure-XXIII). Out of Rs.3,70,85,091/-
Rs.1,80,89,611/- is pertaining to SR beneficiary States/UT and the same was to be
adjusted towards transmission charges payable by SR beneficiary States in the ratio
of transmission charges paid by them for the month of August & September 2002.
WRTS had confirmed that the entire amount deposited by PTC had been fully
adjusted towards WR transmission charges payable by WR Constituents. PGCIL
has therefore to adjust the amount pertaining to SR beneficiary States/UT
appropriately.
21.3 TANTRANSCO vide letter dated 3rd
July 2014 (refer Annexure-VI) had stated that
as agreed in the Meeting held at Mumbai, Maharashtra and MP would furnish the
reconciliation statement to the SR constituents by end of June 2014.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 69 of 83
21.4 KSEB vide letter dated 14th
July 2014 (refer Annexure-VIII) had furnished the
details of outstanding principal amount pending for payment from WR constituents
for the period prior to January 2003.
21.5 In the Meeting, SRTS-II, PGCIL informed that WRTS had taken up the matter with
WR constituents and the amount due to SR constituents would be passed on.
21.6 After deliberations, it was agreed that a Meeting could be held between WR and SR
to settle the issue.
22. GRID OPERATION
22.1 Grid events/highlights during March 2014
Southern Region met demand of 36,985 MW on 24.03.2014 which
was maximum till date.
Sothern Region met a day energy consumption of 856.67 MU on
26.03.2014
Andhra Pradesh met demand of 13,621 MW on 23.03.2014 which
was maximum till date.
Andhra Pradesh met a day energy consumption of 293.84 MU on
22.03.2014 which was maximum till date.
Kerala met demand of 3,588 MW on 18.03.2014 which was
maximum till date.
400 kV Chittoor-Tiruvalam DC quad line and new 400 kV
Tiruvalam Sub Station along with 1x 63 MVAR bus reactor at
Tiruvalam Substation and associated bays and equipment at
Tiruvalam and Chittoor under supplementary Transmission system
associated with Vallur TPS have been put under Commercial
operation w.e.f 01.04.2014 by PGCIL.
Transmission System associated with Krishnapattanam UMPP
Part C1 have been put under commercial operation w.e.f
01.04.2014 by PGCIL:
LILO of 400 kV Nagarjunasagar-Gooty SC line at
Kurnool(new) Substation along with associated bays
and equipment.
400 kV Kurnool (new) – Kurnool (APTRANSCO)
DC quad line along with associated bays and
equipments.
2 x 1500 MVA Transformers at 400kV Kurnool SS
along with associated bays and equipments.
1 x 240 MVAR bus reactor at Kurnool (new) SS
along with associated bays and equipments.
OPGW communication links along with associated
communication equipment under the project establishment of fiber
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 70 of 83
optic communication system for central sector stations project of
Southern Region have been put under CoD w.e.f 01.04.2014 by
PGCIL:
LILO of Bangalore-Salem to Hosur (25.52 kM)
LILO of Madurai- Trichy at Karaikudi (48.87 kM)
Tirunelveli-Kudankualm(72.71 kM)
Chittor- Tiruvalam(21.02 kM)
LILO of Kolar- Sriperumbudur to Tiruvalam(12.07
kM)
Sriperumbudur- Chittoor LILO(95.82 kM)
765/400 kV, 1500 MVA Transformer Bank (2nd ) at Nellore
Pooling Station along with associated bays and equipment was
declared COD from 01.03.2014 by SRTS I, PGCIL.
765 kV, 240 MVAR Bus Reactor at Nellore Pooling Station along
with associated Bay and Equipments was declared COD from
01.03.2014 by SRTS I, PGCIL.
220/132 kV, 2 x 100 MVA Transformer at Sadasivpet was
commissioned by APTRANSCO on 29.03.2014.
LILO line from 220 kV Gachibowli –Tandur to 400 kV
Yeddumailaram of 20ckm was charged by APTRANSCO on
14.03.2014.
220 kV Shadnagar to Yeddumailaram line was charged by
APTRANSCO on 07.03.2014.
220 kV DC Line from 400 kV Yeddumailaram to 220kV
Sadasivpet of 74 ckm was commissioned by APTRANSCO on
29.03.2014.
Wind mills of capacity 17.7 MW had been added in Tamil Nadu.
22.2 Grid events/highlights during April 2014
Karnataka met demand of 9,718 MW on 07.04.2014 which was
maximum till date.
Karnataka met a day energy consumption of 211.22 MU on
07.04.2014 which was maximum till date.
Kerala met a day energy consumption of 70.13 MU on 03.04.2014
which was maximum till date.
Puducherry met a day energy consumption of 7.43 MU on
26.04.2014 which was maximum till date.
Wind mills of capacity 7.58 MW had been added in Tamil Nadu.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 71 of 83
22.3 Grid events/highlights during May 2014
Wind mills of capacity 2.2 MW had been added in Tamil Nadu.
LILO of one ckt of 400 kV Neyveli-Trichy DC line at Nagapattinam
Pooling station under common transmission scheme associated with
ISGS projects in Nagapattinam/Cuddalore area of Tamil Nadu was
ready for the intended use w.e.f. 03.05.2014.
22.4 Grid events/highlights during June 2014
The state of Andhra Pradesh had been bifurcated into two new states
namely Andhra Pradesh and Telangana w.e.f 02.06.2014.
Tamil Nadu daily energy consumption of 294 MU on 20.06.2014
which is maximum till date.
Tamil Nadu met a demand of 13,771 MW on 24.06.2014 which is
maximum till date.
Wind mills of capacity 82.54 MW had been added in Tamil Nadu
during the month of June 2014.
765 kV Kurnool –Raichur 2nd
ckt along with associated bays and
equipments at Kurnool and Raichur SS under ‘Transmission System
associated with ISGS Krishnapattnam’ had been put under
Commercial Operation wef 00:00 hrs of 21st June 2014.
22.5 Installation of Shunt Capacitors
The progress of installation of capacitors by the constituents during the year
2014-15 is furnished in the Table below:
(Figures in MVAR)
State Requirement
for 2014-15
Installed during the year
2014-15 (till 30th
June2014)
Andhra Pradesh 26.20 0.00
Karnataka 56.31 0.00
Kerala 10.00 0.00
Tamil Nadu 122.40 0.00
It was requested that installation of required capacitors works be completed
within six months.
23. DEMAND VARIATION (Peak Vs Off-peak)
23.1 Issue regarding large variation between minimum and maximum demands has
been under the consideration of TCC/SRPC. The issue is also being discussed in
the monthly Meetings of OCC. Following was observed with regard to the period
from March 2014 to June 2014:
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 72 of 83
Month Minimum to Maximum Demand Variation %
Andhra
Pradesh Karnataka Kerala
Tamil
Nadu Puducherry
Southern
Region
March 2014
Highest 28.68 32.02 41.07 23.53 41.66 19.54
Date 4th
(Tue) 27th
(Thu) 3rd
(Mon) 10th
(Mon) 5th
(Wed) 10th
(Mon)
Lowest 13.70 10.45 31.47 6.42 18.35 8.45
Date 27th
(Thu) 28th
(Fri) 1st(Sat) 22
nd(Sat) 30
th (Sun) 29
th (Sat)
Average 19.02 19.88 35.30 15.97 32.72 13.23
April 2014
Highest 17.74 31.73 43.13 20.24 42.46 15.78
Date 5th
(Sat) 17th
(Thu) 9th
(Wed) 25th
(Fri) 24th
(Thu) 28th
(Mon)
Lowest 8.98 14.12 17.98 8.78 15.14 6.63
Date 29th
(Tue) 4th
(Fri) 30th
(Wed) 2nd
(Wed) 20th
(Sun) 17th
(Thu)
Average 13.45 20.36 32.43 12.44 26.43 10.87
May 2014
Highest 30.98 45.38 47.55 22.74 63.32 27.26
Date 27th
(Tue) 9th
(Fri) 9th
(Fri) 10th
(Sat) 15th
(Thu) 9th
(Fri)
Lowest 7.53 17.32 19.60 10.14 16.29 8.89
Date 16th
(Fri) 25th
(Sun) 28th
(Wed) 11th
(Sun) 25th
(Sun) 18th
(Sun)
Average 17.10 25.82 32.35 15.95 29.25 14.94
June
2014
Minimum to Maximum Demand Variation %
Andhra
Pradesh Karnataka Kerala
Tamil
Nadu Telangana Puducherry
Southern
Region
Highest 24.78 49.21 39.82 32.19 36.46 53.56 20.67
Date 13th
(Fri) 3rd
(Tue) 13th
(Fri) 9th
(Mon) 18th
(Wed) 12th
(Thu) 9th
(Sun)
Lowest 9.75 12.78 22.23 10.44 5.02 12.49 9.50
Date 8th
(Sun) 28th
(Sat) 7th
(Sat) 1st (Sun) 29
th (Sun) 29
th (Sun) 26
th (Thu)
Average 16.41 24.61 34.19 18.68 11.94 23.60 13.76
Note: Highest & lowest figures for the month have been computed based on the daily
values.
23.2 Constituents were kindly requested to implement suitable DSM measures and also
share information with other constituents for mutual benefit.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 73 of 83
24. FREQUENCY OF OPERATION OF SOUTHERN GRID
24.1 The frequency of operation of the Southern Grid for the period under review is
furnished below:
Month
Percentage of time when frequency (Hz)was
Month
Avg.
freq.
Less
than
49.5
49.5
to
49.7
49.7
to
49.9
49.9
to
50.0
50.0
to
50.05
50.05
to
50.20
More
than
50.20
Within
IEGC
range
49.9 to
50.05
March 2014 0.01 0.48 19.80 35.36 18.48 23.46 2.41 53.84 49.98
April 2014 0.01 1.83 34.20 36.56 13.94 12.85 0.61 50.50 49.94
May 2014 0.01 1.45 25.42 34.14 17.40 19.66 1.92 51.54 49.97
June 2014 0.25 5.99 34.32 29.95 13.99 14.36 1.04 43.94 49.92
24.2 During the period under review, caution / violation messages (Annexure-XXIV)
were issued to the constituents by SRLDC. Matter regarding overdrawal at low
frequency by some constituents is being regularly deliberated in the OCC forum.
Utilities are requested to kindly adhere to Regulations in this regard.
24.3 In the Meeting on 6th
May 2014 taken by Secretary (Power) to discuss
preparedness of the power sector to tackle effects of subnormal monsoon, it had
been agreed that reservoir based hydro stations would conserve water and utilize
the same optimally with immediate effect so that stored water may be utilized in
the event of deficient monsoon.
25. TRIPPING DETAILS
25.1 Tripping Details/Reports
25.1.1 The following is contained in the RoP of Hon’ble CERC in respect of Petition
No. 146/MP/2013 with IA 36/2013(date of hearing 19th
December2013):
“7 The Commission also noted that the petitioner raised the issue of
Non-compliance of the Regulation 5.2(r) of the Grid Code which
mandated all users to report the disturbance/fault to RLDCs within
24 hours of occurrence. The Commission directed the Petitioner to
submit the instances of non-compliance by SLDC/Users by
10.01.2014.”
25.1.2 Subsequently Para 29 of Order dated 20th
February 2014 in respect of Petition
No. 146/MP/2013 of Hon’ble CERC contains the following:
“29. …... We administer a strong warning to the respondents to
take all possible measures permissible under the Act and the
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 74 of 83
Grid Code to provide data /information to RLDC and RPC for
maintaining reliability and security of the grid. We also make it
clear that failure in this regard will amount to non-compliance
of the directions of this Commission and render the constituent
liable for proceedings under Section 142 of the Electricity Act,
2003 and other relevant provisions. We also direct the petitioner
and SRPC to coordinate and monitor the progress and
compliance of Commission's directions and ensure compliance
of Regulations 5.2 (r) of the Grid Code and report instances of
non-compliance to the Commission...”
25.1.3 In the OCC/Protection Sub Committee Meetings, SRLDC had expressed serious
concern over the fact that information regarding tripping details with relay
indications was awaited from many of the constituents. It had been stated that
entities needed to furnish the preliminary report on ‘events’ in compliance of
IEGC Regulation, 5.9.6(a). Detailed report along with necessary information as
mandated by IEGC should be followed. CEA Regulations mandate furnishing of
the reports within 24 hrs. It was also a matter of concern that certain events had
not been reported at all to SRLDC.
25.1.4 In the Meeting, SRLDC presented the status of tripping details being furnished by
the constituents (Annexure-XXV)
25.1.5 Chairperson TCC said that the tripping details needed to be communicated to
SRLDC/SLDCs in a timely manner to analyze the incidents.
25.1.6 Constituents were requested to furnish the tripping details within the prescribed
time limits.
26. OPERATION OF TALCHER-KOLAR HVDC TRANSMISSIONSYSTEM IN
GROUNDRETURN MODE
26.1 In various forums it had been noted that the flow needed to be restricted to 150
MW in GRM. Till 24th
Meeting of SRPC, the following had been noted:
KPTCL had expressed that the safety of the equipment was of utmost
importance to them. Neutral current beyond the permissible limits
could not be allowed under any circumstances.
PGCIL in consultation with CEA had subsequently appointed
International Consultants with the approved Terms of Reference.
A Special Meeting of TCC with the International Consultants for
Review of Ground Return Mode Operation of Talcher-Kolar HVDC
Link was held on 9th
May 2012 at Bangalore.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 75 of 83
Copy of the Report prepared by the Consultant Group forwarded by
PGCIL was circulated to the Members. As agreed in the 19th
SRPC
Meeting held on 1st June 2012, the matter was to be discussed
bilaterally between KPTCL & PGCIL.
KPTCL had sought opinion of their consultant (M/s PRDC) on the
report furnished by PGCIL. It was also desired that after the
finalization of the issue between PGCIL and KPTCL, the outcome
would be deliberated in the OCC meeting before putting up to
TCC/SRPC. PGCIL had also sought the status of measurement as
recommended by the International Consultants.
KPTCL had informed that PRDC was scheduled to take third set of
readings during April-May 2014.
26.2 In the Meeting, Director (Transmission), KPTCL informed that the next set of
readings could be taken in September 2014.
27. PHYSICAL AND CYBER SECURITY/ CRISISMANAGEMENT PLAN/
BLACKSTART PROCEDURES
27.1 Physical and Cyber Security
27.1.1 Status update on Crisis Management Plan (C&DMP) of Power Sector is to be
furnished quarterly. Information regarding Cyber Security was to be furnished
to Chief Engineer, DPD, CEA, Sewa Bhavan, New Delhi-110066. Report on
Physical Security, other Mock Drills for CMP, Mock Drill for Black Start
Restoration was to be furnished to Chief Engineer, DMLF, CEA, Sewa
Bhavan, New Delhi-66. Copy of the report was to be sent to SRPC
Secretariat ([email protected] and [email protected]). Practices
being followed in respect of Cyber Security/Physical Security/CMP/Mock
Drills w.r.t. Black Start were also required to be communicated
27.1.2 CEA, vide letter dated 26.11.2013 had enclosed MoP letter dated 21.11.2013
regarding Security of power installations and status. It is therefore requested
that the following information in this regard may please be furnished to
Member (GO & D), CEA, New Delhi for onward communication to MoP
with a copy to this office:
Standard Security guidelines for power installations and the status
of implementation including Cyber Security.
Systematic up gradation and modernization of security systems
and procedures.
Coordination and liaison with local police and intelligence units.
27.1.3 The constituents were requested to furnish timely information in this regard.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 76 of 83
27.2 Black Start Procedure
Issue regarding Mock drill on Black Start Procedure was being followed up in the
monthly Meetings of the OCC.
28. MODIFICATIONS IN OPGW LINKS UNDER FIBRE EXPANSION
PROJECT OF SR
28.1 PGCIL vide letter dated 11th
July 2014 (Annexure-XXVI) had been stated that
subsequent to approval of the modified fibre optic network in the 24th
SRPC
Meeting, KPTCL and Puducherry Electricity Department have requested for
changes in the routing of the fibre network.
28.2 TCC recommended for the following changes in the routing of fibre network for
approval by SRPC:
OPGW on Hoody – HSR & Hoody –HAL in place of Hoody – ITPL
OPGW on Neyveli – Bahour instead of Neyveli – Villianur for having dual
path for Bahour station.
29. REPLACEMENT OF PRIMARY MULTIPLEXER EQUIPMENTS
INSTALLED UNDER SR-ULDC PROJECT
29.1 PGCIL vide letter dated 11th
July 2014 (refer Annexure-XXVI) had been stated
that primary multiplexer system has been supplied and installed under SR-ULDC
project for data and speech applications. The multiplexer of Alcatel make had been
in operation for the past 14 years. However, due to technical obsolescence it has
been proposed to replace the multiplexer equipment. The estimated cost of the
equipment has been stated to be around Rs.5.75 crores.
29.2 TCC recommended replacement of multiplexer equipment installed under SR-
ULDC Project for approval by SRPC.
30. DIFFERENCE IN COMPUTATION OF CAPACITY CHARGES OF NTPC
STATIONS AS PER NEW CERC REGULATIONS (2014-19)
30.1 KSEB vide letter dated 14th
July 2014 (refer Annexure-VIII) reference had been
invited to CERC Tariff Regulation 2014-19 regarding payment of capacity charges
to Thermal Generating Station for a calendar month. It had been stated that all
generators have adopted calculation procedure in accordance with CERC Norms
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 77 of 83
whereas NTPC has adopted a different methodology for the same. The amount
claimed towards capacity charges by NTPC is more than the amount permissible as
per CERC Norms.
30.2 In the Meeting, it was noted that the issue would be first discussed in the
Commercial Sub-Committee.
31. ARBITRARY CURTAILMENT OF STOA AND DENIAL OF URS
31.1 KSEB vide letter dated 14th
July 2014 (refer Annexure-VIII) had been stated that
instances of arbitrary denial/unwarranted curtailment of STOA and URS power by
SRLDC is continued in real time even under reduced line flow across S1-S2 seam.
A few typical instances of arbitrary denial by SRLDC have been cited. These
relate to instances that had occurred on 25th
June 2014, 18th
June 2014, 9th
June
2014 and 8th
June 2014.
31.2 In the Meeting, it was noted that the issue was under consideration of Hon’ble
CERC.
32. PREPAREDNESS FOR BAD MONSOON
32.1 KSEB vide letter dated 14th
July 2014 (refer Annexure-VIII) had been stated that
in view of forecast of bad monsoon, KSEB Ltd. has estimated a shortage of
approximately 2,000 MU in inflow. KSEB Ltd. had already entered into PPA for
purchase of 1,600 MW of power on MTOA/LTA basis. However, only 3 MW has
been approved from June 2014. Power arranged in short term contract is not
permitted by SRLDC on account of apprehended transmission constraints and
fixing unrealistic reliability margins. This ultimately results in under utilization of
transmission and generation assets in the country. In order to meet the power
requirement in this scenario, certain measures have been proposed for discussion in
the Meeting.
32.2 In the Meeting, KSEB requested to consider the following proposal:
Additional power transfer of 500 MW in Talcher - Kolar HVDC poles in
enhanced mode.
Enhancement of S1-S2 ATC for transfer of power by considering the
generation at Kudankulam and the SPS scheme.
TRM could be avoided to ensure maximum power transfer.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 78 of 83
32.3 ED, SRLDC informed that the enhanced mode was already being utilized to control
power flow on 765 KV Raichur-Sholapur link.
33. UTILIZATION OF EXISTING ROW OF 66KV KUTHUMUNDA –
UPPATTY FEEDER
33.1 KSEB vide letter dated 14th
July 2014 (refer Annexure-VIII) had been suggested
that feasibility for utilizing ROW of erstwhile 66 kV feeder from Kuthumunda to
Uppatty in Tamil Nadu (lying unutilized for past several years) may be explored
for construction of 220 kV link to Tamil Nadu.
33.2 In the Meeting, TANTRANSCO informed that they were in the process of
upgrading all the existing 66 kV lines to 110 kV. It was not possible to use the
existing RoW of 66 kV Kuthumunda–Uppatty line for construction of 220 kV
link,
33.3 After deliberation, it was agreed that the issue would be discussed bilaterally
between KSEB & TANTRANSCO.
34. PROGRESS OF VARIOUS TRANSMISSION AND GENERATING
CAPACITY WORKS
The Progress of transmission and generating capacity works is furnished at
Annexure-XXVII.
TCC noted the following:
35. START UP POWER DRAWAL BY IL&FS TAMIL NADU POWER
COMPANY LIMITED
35.1 IL&FS Tamil Nadu Power Company Ltd. (ITPCL) is establishing 2x 600 MW
generation project at Cuddalore in Tamil Nadu. As per approved scheme,
evacuation of power from ITPCL would be through PGCIL Nagapattinam
Pooling Station connected through dedicated 400 kV D/C line from ITPCL to
Nagapattinam Pooling Station.
35.2 In its 24th
Meeting held on 15th
March 2014,SRPC had approved LILO of one
circuit of Neyveli – Trichy line at Nagapattinam PS for the purpose of drawal of
startup power by ITPCL.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 79 of 83
35.3 In the 24th
Meeting of Commercial Sub Committee of SRPC held on 13th
May
2014, the following had been noted:
PGCIL had informed that LILO of one circuit of 400kV Neyveli –
Trichy line at Nagapattinam PS was ready and deemed to have
been commissioned with effect from 03rd
May 2014. 400kV D/C
line from ITPCL switch yard to Nagapattinam Pooling Station was
not ready.
SRLDC had stated that as per Regulations, Neyveli and Trichy ends
are the ISTS touch points of ITPCL. Hence drawal or injection is to
be accounted with SEMs at NLC and Trichy end. Any deviation
may have to be brought to the notice of Hon’ble CERC. SRLDC
would not carry out any modifications w.r.t apportionment of losses
etc.
After deliberations, it had been agreed by Commercial Sub-
Committee (except SRLDC) that as an interim measure, the energy
drawal by ITPCL be computed based on the SEMs at ITPCL end.
Further the drawal would be increased (post facto) by the regional
loss percentage (used for scheduling for the week) during
accounting by SRPC Secretariat. This would be an interim measure
till commissioning of Nagapattinam PS.
36. UDUMALPET &GAZUWAKA ICTs - STATUS OF CERC PETITION
36.1 PGCIL vide Notification dated 23rd
March 2010 had notified that Udumalpet ICT-I
(315MVA) was not on commercial operation with effect from 23.03.2010 and
charges would not be claimed till further communication. The ICT was put back on
commercial operation from 01.07.2010. In respect of Gazuwaka ICT also similar
notification had been issued by PGCIL. Gazuwaka ICT was out of commercial
operation from 01.05.2009 to 30.06.2009.
36.2 In the 13th
Meeting of SRPC held on 11th
May 2010, PGCIL had informed that they
would approach CERC with petition. For the period from 23rd
to 31stMarch 2010 the
outage of Udumalpet ICT would be to PGCIL account. From 1stApril 2010, the
element would be taken out from the availability calculations and subsequently
CERC order on the petition would be followed.
36.3 The issue had been discussed in the Special Meeting held on 04th
April 2014 where
in PGCIL representative had informed that they had taken up the issue with their
Commercial Wing and they would revert back.
36.4 The issue was further discussed in the 24th
Meeting of Commercial Sub-Committee
held on 13th
May 2014,wherein PGCIL had informed that tariff adjustment on
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 80 of 83
account of denotification of the subject ICT's for the part of the 2009-14 tariff block
would be carried out in the truing up petition for 2009-14 to be filed before CERC.
37. SCHEDULING POWER TO TELANGANA & ANDHRA PRADESH FROM
SHARED STATIONS, IPPs AND SIMHADRI STPS STAGE-I
37.1 In the Special Meeting of TCC held on 8th
May 2004, TCC had agreed that the
following issues raised by APTRANSCO would be further discussed in the
Commercial Sub Committee Meeting scheduled on 13th
May 2014, wherein the
decision would be taken on the matter:
Issue No.1: APGENCO stations will have PPAs of Discoms from
both States. Because of this, Genco will become inter-state
generators. There are Inter-State Lines between Telangana and AP
owned and operated by Telangana and AP State. There will be net
power transfer either from Telangana to AP or vice versa every
month. Do importing state have to pay charges for such net power
transfer to PGCIL? Or to Other State? And how much?
Issue No.2: Each Discom will be getting power from Genco station
of other state. Will Discom of one state pay Transmission charges &
losses to other State Transco? For example CPDCL (TG State) will
draw power from VTPS (AP State). Will CPDCL pay transmission
charges and losses to AP Transco?
Issue No.3: Is it possible present Energy Billing Centre of
APTRANSCO to finalize the energy transactions between both the
States DISCOMs in every month and also for certification of energy
from various generators i.e. presently being done by SRPC for SR
States against utilization of power from Central Generating Stations
and also inter-state open access transactions?
Issue No.4: Who will work out the losses separately to both the
States for utilization/scheduling of power from the Generating
Stations?
Issue No.5: In which manner, Simhadri Stage-I, UI charges would
be segregated to both the States and also whether Simhadri Stage-I
scheduling would be done by SRLDC or APSLDC?
37.2 In the 24th
Meeting of Commercial Sub-Committee of SRPC held on 13th
May
2014, APPCC had informed that CMD, APTRANSCO had directed him to
convey the following decision on the issues:
Methodology being followed in Northern Region in respect of shared
generators could be similarly adopted in respect of Net Power transfer
from Telangana to AP. As such, transmission charges to PGCIL would
not be payable for the Power Transfer from Telangana to AP or vice
versa
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 81 of 83
State Losses & Transmission Charges would be decided mutually.
Separate charges would not be applicable. (only net schedule being
considered by SRLDC).Existing APERC approved loss percentage
would be used for scheduling of power.
Power from Central Generating Stations as well as STOA transactions
would be scheduled by SRLDC and the details in respect of AP and
Telangana would be shown in the Monthly REA issued by SRPC
Secretariat. Energy Billing Centre would issue Account for the energy
scheduled from respective state generating stations.
Simhadri STPS Stage-I station would be scheduled by APSLDC.
37.2.1 SRLDC had stated that as per PoC Regulations, PoC charges and Losses are
to be applied on four components viz charges for Injection from
AP, withdrawal charges for Telangana’s share and vice-a-versa. SRPC
Secretariat may apprise the issue and request to hold a Validation
Committee meeting on an urgent basis. Matter could be put up to the
Validation Committee for suitable directions. AP SLDC had agreed to
schedule and dispatches Simhadri STPS Stage-I under its control area and
schedule the shares to Telangana. As per clause 6.4.3.of IEGC, which states
that there may be exceptions with respect to above provisions, for reasons of
operational expediency, subject to approval of CERC.
37.2.2 After deliberations, the following had been agreed:
Matter regarding sharing of transmission charges and losses would be
referred to Validation Committee requesting a meeting on urgent
basis.
However, pending decision of Validation Committee, CMD,
APTRANSCO decisions as mentioned above would be followed.
APSLDC would approach CERC for approval for scheduling and
accounting of Simhadri STPS Stage-I by APSLDC.
37.3 The 2nd
Meeting of the Validation Committee for the year 2014-15 (2nd Quarter,
July - September 2014) for implementation of CERC (Sharing of Inter-State
Transmission Charges and Losses) Regulations 2010 was held on 4th
June, 2014,
wherein the issue was discussed. (relevant extract of Minutes enclosed as
Annexure -XXVIII)
38. COLLECTION OF DATA REGARDING POWER SUPPLY TO RURAL
AREAS
CEA had informed that in the Meeting held in MoP on 09.04.2014, it had been
decided to collect the data from DISCOMs in a simplified format. SRPC vide
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 82 of 83
letter dated 11.04.2014 enclosing CEA letter had requested that the data in this
regard in the format may be communicated to SRPC Secretariat at the following
E-mail addresses:
Data is to be communicated by first week of the month in respect of the previous
month. Constituents were kindly requested to furnish the validated data in a
timely manner.
39. SNAPPING OF POWER CONDUCTORS OVER TRACTION LINES-
SOTHERN RAILWAY
39.1 Southern Railways had raised the issue of snapping of earth conductor in KSEB
system between Kazhakuttam-Kochuveli stations on 25th
May 2014 and snapping
of TANTRANSCO 230 kV NCTPS-ETPS phase conductor crossing Railway
traction lines of all four tracks between Ennore-Attippattu on 18th
April 2014 at
about 1003 hrs. The matter had been taken up with KSEB and TANTRANSCO at
Chairman level vide letters dated 26.05.2014 and 22.04.2014 respectively.
39.2 Railways were requested to give such type of operational issues in advance for
fruitful deliberations. It was also pointed out that the Railways should allow
restoration of lines at the earliest and commercial matters could be settled
subsequently. For restoration hot line was available between SLDCs and TPCs
which could be utilized for expediting the works. The TRANSCOs were
requested for periodical inspections/timely maintenance of line crossings railway
traction lines. SLDCs were requested to kindly give similar instructions to
DISCOMs.
40. TRANSMISSION LINE PATROLLING PROTOCOLS/ GUIDELINES
In compliance of Orders of Hon’ble CERC in respect of Petition No. 146/MP/2013
with I.A 36/2013, dated 20th
February 2014, Transmission Line Patrolling Protocols
/ Guide Lines had been submitted to Hon’ble CERC vide SRPC letter dated 21st
May 2014. Communication had also been addressed to the constituents for
implementation/necessary action in this regard.
Minutes of 24th Meeting of TCC of SRPC held on 25th July 2014 Page 83 of 83
41. DATE & VENUE OF THE NEXT TCC MEETING
It was decided to hold the 25th
Meeting of TCC one day prior to the 26th
Meeting of
SRPC.
42. VOTE OF THANKS
Member Secretary I/c, SRPC thanked the Members and other participants for their
active participation in the deliberations.
Chairperson, TCC thanked all the Members for their cooperation.
******