67
1 Weiguo Li Institute of High Energy Phy sics 2002 年 6 年 5 年 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

Embed Size (px)

Citation preview

Page 1: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

1

Weiguo Li

Institute of High Energy Physics

2002 年 6 月 5 日

BEPCII/BESIII PROJECTBESIII Collaboration Meeting

June 5-6, Beijing

Page 2: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

2

Goals of this collaboration meeting• Inform the overall BEPCII/BESII preliminary design and

the project status

• Discuss the status of BESIII preliminary design,

consensus on detector design choices

• Discuss the possible participations from other countries,

from other institutes in China

• Future plan for detector design, R&D, detector

manufacture, schedule and cost

• BESIII collaboration, organization

Page 3: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

3

Introduction

BEPCII Design

BESIII Design

BESIII Collaboration

Summary

Page 4: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

4

Korea (3)

Korea University Seoul National University

Chonbuk National University

Japan (5)

Nikow UniversityTokyo Institute of Technology

Miyazaki UniversityKEK

U. Tokyo

USA (4)

University of HawaiiUniversity of Texas at Dallas

Colorado State University Stanford Linear Accelerator Center

UK (1)Queen Mary University

China (15)IHEP of CAS

Univ. of Sci. and Tech. of ChinaShandong Univ., Zhejiang Univ.

Huazhong Normal Univ. Shanghai Jiaotong Univ.

Peking Univ., CCAST Wuhan Univ., Nankai Univ.

Henan Normal Univ.Hunan Univ., Liaoning Univ.

Tsinghua Univ., Sichuan Univ.

U. Tokyo, Central Univ.,Guangxi normal Univ., Guangxi Univ.

Page 5: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

5

Data Collected with BESI and BESII Ecm (GeV)

Physics BES Data Other Lab.

3.10 J/ 7.8106 8.6106

3.69 (2S) 3.9106 1.8106

4.03 1.0105 LEP

4.03 DS, D 22.3 pb-1 CLEO

3.55 m scan m 5 pb-1

2-5 R scan R value,

QED, (g-2) 6+85 points 2, MarkI

Crystal Ball Pluto……

3.1 3.69 3.78

J/ (2S) (3S)

5.8107

1.46107

~7 pb-1

BES Current StatusBES Current Status

Page 6: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

6

BESII Detector BESII Detector ((1995-1997 upgrade1995-1997 upgrade))

VC: xy = 100 m TOF: T = 180 ps counter: r= 3 cm MDC: xy = 250 m BSC: E/E= 22 % z = 5.5 cm dE/dx= 8.4 % = 7.9 mr B field: 0.4 T p/p=1.8(1+p2) z = 2.3 cm Dead time/event: 〈 10 ms

Page 7: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

7

BESBES Main Physics Results

Precise Mass Measurement of lepton.

2-5 GeV R measurement.

Systematic study of decays.

Systematic study of J/ decays.

Obtain fDs from Ds pure leptonic decay.

Measure Br(DS ) in model independent way.

BES has 116 entries in PDG.

BES has 74 invited talk , published 216 papers , 48 pa

pers in world-class journals.

Page 8: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

8

Physics Window for BEPC Two major directions in world HEP:

– High Energy Frontier : Search for Higgs particle and beyond STM

particles and phenomena.

– High precision frontier : high statistics and high precision , check

STM , search for phenomena beyond STM.

Considering the new developments of world HEP, the main physics window

for BEPC is precise measurement of charm and charmonium physics, and s

earch for new phenomena.

Advantages: huge cross section at J/ 和′ resonance

simple topology and low background at threshold

Important area to study QCD , perturbative and non-perturbative QCD ,can search for new physics.

Page 9: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

9

BEPC II Physic Goals

• Precise measurements of J/、 、 (3S) Decays

• Precise measurement of CKM parameters

• Light quark hadron spectroscopy

• Excited baryon spectroscopy

• Other D and Ds physics: – precise measurement of D and Ds decays

– measurement of fD, fDs – D0 –D0 mixing

• Check VDM, NRQCD, PQCD, study puzzle

Page 10: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

10

BEPC II Physics Goals ( 2 )

• Mechanism of hadron production , low energy QCD :

precise R measurement• physics : charged current , m and m

• Search for new particles: 1P1、 c、 glueballs 、quark-gluon hybrid 、 exotic states…

• Search for new phenomena: – rare decays;– lepton number violation; – CP violation in J/ 和 decays;

Page 11: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

11

BEPC Future Development: BEPCII

• Precise measurements need:– High statistics → high luminosity machine – Small systematic error→ high performance detector

• BEPC will run at J/ and , with huge cross-section,

also at ”

• Need to have major upgrade for machine and detector

(BEPCII / BESIII) , to increase machine luminosity by

more than one order of magnitude with relatively small b

udget and in a relatively short time.

Page 12: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

12

High Energy Physics 1 ) BEPC future development BEPC II:

- BEPC / BES major upgrade, increase luminosity by more than one order of magnitude;

- Main physics goal: J/ , ′and D/DS physics;

2 ) Strength non-accelerator experiments: Cosmic ray,

astro-physics experiments, neutrino experiment…;

3 ) International Collaboration

Chinese Academy of Sciences :The strategy for Chinese HEP and Advanced Accelerator technology

Page 13: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

13

Science-education Leading Group of State Council, the 7th meeting (2000.7.27), discussed the report by CAS about HEP Conclusions :( 1 ) Approval in principle of 《 Report about the future development of Chinese HEP and advanced accelerator technology 》 by CAS. Meanwhile, CAS should consult further with experts in China and abroad , strength and attract more international collaboration. ( 2 ) In view of the success of BEPC, approval of major upgrade of BEPC, with a budget of 400 M RMB.With relatively small invest, continue to obtain high-level achievements. (At that time, it was meant single-ring)

Page 14: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

14

Competition in tau-charm physics• CESR, USA runs at 10GeV for B physics, because it can hardl

y compete with two B factories , on the other hand, there are

important and interesting physics at tau-charm energy region

as demonstrated at BEPC, plans to reduce the collision energy

by installing a series of SC wigglers, expected lum. ( 1.5 – 3)x

1032cm-2s-1 。• VEPP-4M, Novosibirsk, Russia, has a similar plan.

• BEPC/BES can not enjoy the advantage of unique e+e- collider

in this energy region any more , strong competition.

• BEPC II single ring design can not ensure competitive edge in

the race.

Page 15: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

15

BEPC II Double ring DesignBEPC II Double ring Design• In the existing BEPC tunnel, add another ring, cross over at south a

nd north points, two equal rings for electrons and positrons. Advanced double-ring collision technology.

• 93 bunches , total current > 0.9A in each ring. Collision spacing : 8 ns.• In south, collision with large cross-angle ( ±11 mr ) .• Calculated luminosity : 1033 cm-2 s-1 @ 3.78GeV.

• In north cross point, connecting SR beam between two outer rings, in south cross point, use dipole magnet to bend the beam back to out

er ring.• SR run : 250mA @ 2.5 GeV.• Major detector upgrade : BES III.

Luminosity of BEPCII is a factor of 3-7 of that of CESRc, more potential, and technically less challenge. Budget increased by 50 % .

Page 16: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

16

BEPC Upgrade: BEPC II BEPC Upgrade: BEPC II — — double ring double ring

e -

RFRF SR

e+

IP

Page 17: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

17

BEPCIIBEPCII Design GoalsDesign Goals

Beam energy 1 – 2 GeV

Optimal energy 1.89 GeV

Luminosity 1 x 10 33 cm-2s-1 @ 1.89 GeV

Linac requirements Full energy injection: 1.55 1.89 GeV Positron injection rate > 50 mA/min

Dedicated SR 250 mA @ 2.5 GeV

Increase beam current , reduce beam size

Page 18: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

18

Wood Model Space Study for Double Ring

Page 19: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

19

Luminosity Increase

)(

)()()1(1017.2)s(cm

*341-2-

cm

AIkGeVERL

y

bby

Micro-:y*=5cm 1.5 cm

Super-conducting magnetImpedance red. and SC RF cavity

z=5cm <1.5cm

D.R.: multi bunches h~400, kb=1 93

(LBEPCII/ LBEPC) D.R.=(5.5/1.5) 93 9.8/35=96

LBEPC=1.010 31 cm-2s-1 LBEPCII =110 33 cm-2s-1

Ib=9.8mA, y=0.04

Page 20: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

20

Means of lum. incerase (E = 1.89 GeV)

parameter unit BEPC BEPCII

y* cm 5.0 ~ 1.5

Bunch number kb 1 93

y 0.04 0.04

Beam current Ib mA 35 9.8

factor for lum. increase

1 ~ 100

BEPCII cross-angle collision : 2 x 11mr

Page 21: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

21

BEPCII/BEPC/CESRc Comparison

Page 22: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

22

BEPCII BEPCII Key Technologies and ChallengesKey Technologies and Challenges

Linac Injection rate: 5 mA/min.

50 mA/min.

New positron source

Stability and reliability

Einj= 1.55-1.89 GeV

500MHz SC RF System

SC RF Technology

Power source and low level

Cryogenics…

Injection

Magnets

Power supplies

Vacuum system

SC Q magnet and IP

Beam instrumentation

Control system

Page 23: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

23

Linac UpgradeRequirements: Positron injection rate 5mA/min. 50 mA/min.; Energy 1.3 GeV 1.55 ~ 1.89 GeV;

Use 45MW Klystron,upgrade RF source, replace 8 aged acceleration tubes ;Bombarding energy for positron 150 MeV 240 MeV;

Electron gun beam intensity 5A10A ; Produce new positron source, improving efficiency ; Improve focus and orbit-correction system ; Repetition rate 12.5 Hz 50 Hz ; Pulse duration 2.5ns1ns ; Possibility of double pulse injection (fRF/fLinac=7/40);

Page 24: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

24

means and factors for increase injection rate

Page 25: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

25

SC RF System

Requirements : Sufficient voltage Sufficient power reducing coupling instability stability, reliabilit

y

Measures: collaborate with SSRF, Cornell and KEK , using existing technology.

Page 26: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

26

Super-conducting Cavity CESR-type Cavity (ACCEL) KEKB-type Cavity (Mitsubishi )

IHEP/SSRF collaborating group will optimize the cavity design, follow the manufacture process and technology, master the required techniques for operating and repairing the cavities.

Page 27: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

27

Interaction point and SC Q magnet 磁场强度 有效长度(m)

四极线圈 16.7 T/m 0.4

斜四极线圈 0.2 T/m 0.4

SR 偏转线圈 0.645 0.4

反抵螺线管 2.6 0.5

屏蔽螺线管 ~1.2 ~0.4

水平校正线圈 0.0528 0.4

垂直校正线圈 0.0528 0.4

Page 28: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

28

Beam Feedback System Challenge : How to insure collision?

Beam-beam bending and scanning techniques :Beam-beam bending : accelerator physicsBending measurement : beam instrumentationScan feedback : automatic control

IP_Bump

Orbit data SteeringBeam-BeamDeflection

IP-BPM 二极校正铁IP Orbit Feedback

Page 29: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

29

BES III Expected Event Rates

Particle Energy Single Ring ( 1.2fb

-1 )Double Ring (4

fb-1)

D0 7.0106 2.3107

D+ 5.0106 1.7107

Ds 4.14GeV 2.0106 4106

+- 3.57GeV3.67GeV

0.6106

2.91060.2107

0.96107

J/    3-4109 6-10109

   0.6109 2109

Page 30: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

30

BESIII Design Goals

• High event rate : lum. :1033cm-2 s-1 and bunch spacing 8ns , hardware trigger rate: 4000 Hz , putting on mass medium: 3000 Hz.

• Improve detector resolutions , especially for photons

• Improve particle identification

• Enlarge detector solid angle acceptance

• Design interaction region to fit sc Q magnets

Page 31: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

31BESIII BESIII DetectorDetector

Page 32: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

32

BESIII Main Sub-systems• CsI EM Calorimeter: E/E < 3%• MDC: small cell, Al field wire and He-based gas

P/P (1GeV) = 1.25 %@0.4T, 0.5 %@1T, dE/dx = 6 %

• Time of Flight: T: barrel 80 ps ; endcap 100 ps counter(RPC): readout strip width : ~4 cm

• Luminosity Monitor(LM) L/ L = 3 %• SC Solenoid : 1 Tesla, I.D. 1.32 m, Length 3.8 m• New Trigger and Online system for multi-bunch and h

igh lum. Operation, 4000Hz, 3000Hz to mass storage• New Electronics : pipeline operation

• Offline computing: PC farm, mass storage

Page 33: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

33

Item

time measurement Charge measurementCount rateper channel

Information provided to trigger

Number of channel

σtINL Ran

ge

Cross-talk

Number

ofcha

nnels

σQ

INL

Dynamic

range

Cross-talk

Type Quant.

MDC 90000.5-1 ns

≤0.5%

0-400ns

 9000 5fc

≤2%

15 fc -1800fc

1%

30 k/s hit

TOF

+ CCT

 

352+104

≤25ps

0- 60ns

456 12bits(ENOB)

≤2%

20mv –4v

2-4 k/s hit 456

EMCBAR

         8064+1800

0.16 fc 200KeV

1 %

0.5fc -1500fc

0.3 %

1 k/s

SummationOf analog

 

EMC(End)

          1800

0.16fc 1 %

0.5fc -1500fc

0.3 %

1 k/s

SummationOf analog

 

Mu

Chan ~10000

     

Spec 

Considering multiple hit time measurement

Page 34: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

34

Sub-system BES III BESII

XY (m) = 130 250

MDC P/P (0/0) = 0.5 %(1 GeV) SC

1.25 %(1 GeV) Normal

1.7% √2 (1 GeV)

dE/dx (0/0) = 6-7 % 8.5%

EM Calorimeter E/√E(0/0) = 2.5 %(1 GeV)

z(cm) = 0.5cm/√E

20% (1 GeV) 3 cm /√E

Time of Flight T (ps) = 80 ps barrel 100 ps endcap

180 ps barrel

350 ps endcap

Counters 9- 10 layers 3 layers

Magnet 1.0 tesla Option 1 0.4 tesla Option 2

0.4 tesla

Comparisons between BESIII and BESII

Page 35: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

35BESIII detector with existing magnet

Page 36: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

36

Expected physics reaches and background study by MC simulation, D, Ds, J/, (2S) will be covered by

Dr. Wang Yifang

Most of the main detector sub-systems will be covered by other speakers, I will say a few words about these sub-systems which are not presented separately today.

Interaction region

Mechanical preliminary design

Slow Control

Page 37: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

37

Interaction RegionIt is very compact at IR, very close cooperation is needed in the designs of detector and machine components at IR

• Understand the space sharing, the support, vacuum tight

• Understand the backgrounds from machine and how to reduce them,

- Beam loss calculation (masks)

- Synchrotron radiation (masks)

- Heating effect (cooling if necessary)

• Understand the effects of the fringe field from SCQ to the detector

performances, the preliminary study shows that, field uniformity

should be better than 5% in most of the MDC volume

• Center of beam pipe will be a double-wall Be pipe

Page 38: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

38

BESIII Mechanical design and Detector HallDetector on two rail pads to move in south-northIron Yoke Barrel~ 240 tons; endcap ~254 tons.

at both sides between barrel and endcap, there should be a slot of 1100x 80mm for each side of octagon on every terminal surface of the barrel of yoke, for cable space.

Page 39: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

39View from the side of endcap yoke is closed

Page 40: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

40

M24 Bolt

M16 Bolt

Assembled Structure, test assembling at factory

Page 41: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

41

From upper

From bottom Support of SC dewar

Page 42: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

42 Support of inner detector components

Page 43: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

43

Movable endcap yoke; reposition for field stability

endcap EMC supporting and moving design, removing and recollecting cables should not change the gain.

Page 44: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

44 Arrangements of electronic crates, moving with detector

Page 45: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

45Arrangements for cooling water, gas, cables

Page 46: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

1. Temperature measurement: EMC CsI , 600 ; MDC 16;

, 150; electronics crates, 300; cable rack, 100; environment, 100;

2. Humidity measurement: CsI, 200 ; MDC, 8; electronics, 20; environment, 30;

3. Low HV of VME crates: 500.

4. MDC gas : 8.

5. Voltage of power supply: several.

6. Other measurements? Magnetic field; parameters in SC magnet and cryogenics; HV parameters for detectors; radiation dose; He leakage; flammable gas;others.

Slow control system

Required measurements from detector and electronics

Page 47: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

ONE WIRE BUS can be used to read these signals out

Probe/master, doing R&D

64 bit W. A. O ( unique code worldwide), 12 bit DATE

Temperature probe: DS18B20, 22 RMB/probe

humidity probe: LTM8802, ~150 RMB/probe

1. Humidity range: 1~99% , typical precision: 3%.

2. Temperature range: -30 ~60℃ ℃, accuracy 0.5 ℃

D . C voltage probe: DS2438/ LTM8805, several dozens of RMB/probe

analog voltage:0 ~ 10V ( resolution : 0.01V )

Light-decoupling between PC and master to reduce noise

pickup, LTM - 4850/2 dual-port RS - 485 card

Page 48: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

48

BESIII Key Technology and Challenge• Control background (with machine people), take good quality data

at high luminosity. Small ring is more problematic with background

and radiation dose!

• Design and operate SC magnet

• Stable operation of MDC(>30000 wires), obtaining better resolution

• Obtain best possible EMC energy resolution, by quality

control in detector construction and good calibration systems

• Obtain best possible TOF resolution, all factors controlled

• Build a trigger and DAQ system, with required data transfer rate

and good performance (specifications, reliability)

Page 49: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

49

Some preliminary design issues, such as TOF readout electronics, EMC support structure etc are not decided

Decision on the offline system should be taken ASAP, so people can start to work on the software

Determination of some of main design options

• Magnet? super-conducting/existing normal

• Particle ID? (TOF/ Ĉerenkov based)

Cost and schedule concern

• Cost for EMC, SC magnet and electronics is most crucial;

• MDC, EMC and SC magnet (including iron structure) on critical path;

Page 50: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

50

BESIII will be competitive in producing good physics results after its completion; can help to master advanced technology related to detector design and construction, fast electronics, DAQ and data analyses, help to catch up with world level or close the gap.

But, construction of BESIII and obtaining world class results, are big challenge to Chinese HEP experimentalists, need to master new techniques, such as super-conducting, low-Z small cell MDC; high precision EM calorimeter; pipeline fast electronics, fast data acquisition, huge data storage and processing; Need international collaboration ( Japan, US, Korea) 。

Page 51: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

51

• Conceptual design started in 1999.

• Feasibility study started in the summer of 2000 , complete

d in Aug. of 2001.

• Preliminary design started in the summer of 2001 :– Machine finished physics design, requirements for sub-systems are

determined;

– Sub-system designs are progressing well

– Detector design is progressing well

– Expected to finish preliminary design in the summer of 2002

• Upgrade of Linac started.

• R&D for key technologies started : SC cavity, Q magnet

Project Status

Page 52: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

52

Feasibility Study/Design Review•    BEPC II feasibility international review ( 01. 4. 2 – 6, Beijing)

26 experts reviewed the feasibility of machine and detector

•    BEPC II machine feasibility review ( 01. 7. 29 - 30 Beijing)

21 domestic experts reviewed machine feasibility and preliminary

design.

• BESIII International Workshop (01.10.13 – 15 Beijing)

• International technical review of machine preliminary

design at SLAC, May, 2002

BESIII preliminary design review, plan to be in Sep. of 2002

Page 53: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

53

Project Schedule and Budget• Done Feasibility Study Report submitted. End of June of 2002 Preliminary Technical Design Report June 2003 R&D and prototype May 2004 BEPC run• July 2002 June 2006 Construction• May 2004 Nov. 2004 BESII dismounting and Linac upgrade • Nov. 2004 Jan. 2005 Linac commissioning• Jan. 2005 Apr. 2005 SR run• Apr. 2005 Jan. 2006 Storage ring assembling• Jan. 2006 June 2006 Commissioning of storage ring• June 2006 Sep. 2006 BESIII detector moved to beam-line• Sep. 2006 Commissioning machine and detector

Page 54: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

54

BESIII Schedule

 2001.1~2002.6 Preliminary design

2001.7~2003.6 R&D of critical parts

2002.7~2005.9 Construction of detector components

2003.1~2004.6 Construction of return yoke

2002.3~2004.12 Design of super-conducting magnet

2004.7~2004.11 BESII disassembling

2004.12~2005.3 BESIII iron yoke assembling (with magnet)

2005.4 Commissioning of cryogenics

2005.5~2005.8 Magnet field measurement ( with SCQ ) 2005.9~2006.1 Assembling of other detector components

2006.2~2006.6 Commissioning of BESIII detector

2006.7~2006.8 BESIII moved to beam-line

2006.9~2006.12 Commissioning of BEPCII+BESIII

Page 55: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

55

BEPCII Team and Administration

• BEPC II project leaders and headquarter are established;

• 4 Major systems, Linac; Ring; Detector; Technical support( cryogenics).

• Most of responsible persons for sub-systems are appointed.

• Some procedures are established, quality control; budget control; technical review; etc.

Page 56: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

56

BEPC Budget (M RMB)Ⅱ

* Expected contribution from abroad

System Budget Percentage

1 、 Linac 46 7.2%

2 、 Storage Ring 239.2 37.4%

3 、 Detector 219 ( 40* ) 34.2%

4 、 Technical support systems 90 14.0%

5 、 Infrastructure 5.5 0.9%

6 、 Others 10.3 1.6%

7 、 Contingency 30 4.7%

Total   640(40*)  

Page 57: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

57

BEPCII Domestic Collaboration

Welcome participation from other Institutes and Universities,

in charge of one sub-system or collaboration with IHEP• Shanghai Synchrotron Light Source

– 500 MHz RF system

• Shanghai Institute of Ceramics : CsI crystals

• Beijing University : RF system, detector

• Qinghua University : Accelerator technique, detector

• University of Science and Technology of China : Detector,

Readout electronics

Page 58: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

58

BESIII Domestic Collaboration

Design, MC simulation

Sub-detectors R&D and construction

Electronics R&D and manufacture

Online/Offline software

Software package

Reconstructions

Calibration

Physics study

In Charge of some sub-system or send people to IHEP

Page 59: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

59

BEPCII International Collaboration International collaboration played an important roll in B

EPC/BES project , Expect to play major roll in the desi

gn and construction of BEPCII / BESIII :– BNL of US: SC Q magnet;– SLAC of US: Key machine technology, design– KEK of Japan: SC cavity and SC solenoid… reviews; – Improve technical excellency and research capability Advice and help in design and construction in various systems; Technical review and follow-up in detector design, construction and commissioning. BESIII international review, sometime in September.

Page 60: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

60

BEPCII / BESIII can attract international participation, especially in detector and physics; Share cost , improve detector performancesJoin BESIII collaboration and be in charge of some sub-systems U. Hawaii, U. Washington and other US Institutes,KEK and U. of Tokyoare participating in the project, will play important roll. More Institutes from US and Japan may joinKorea has interest in participating

Should form BESIII international collaboration according to international standard:Institution board; Executive board; Spokesperson; etc.

International review/Documentation/video conferencing

Page 61: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

61

Summary BEPC/BES meet opportunity and challenge in the field of tau-cha

rm physics.

BEPCII double-ring design luminosity 1033 cm-2s-1at 1.89 GeV ,with major upgrade of BES , can insure an important roll in world HEP, especially in tau-charm physics.

BEPCII/BESIII is technically feasible, should be started as soon as possible.

BESIII has a baseline design, optimization is needed

Strength domestic collaboration , stimulate developments of relevant technologies in China.

International collaboration in BEPCII/BESIII construction.

BESIII Collaboration should follow international standard.

Page 62: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

62

Hope this collaboration meeting is very successful

Thanks

谢谢

Page 63: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

63

Item cost(10K RMB)

Number Total(10KRMB)

Total(10KRMB)

1 Beam-pipe and masks       120

2 MDC       1800

2-1 End-plates     900  

2-2 Feed-through and wires     340  

2-3 Other mechanical and wire stringing     395  

2-3 HV cards and cables     90

 

2-5 Cosmic ray test     30  

2-6 Others     45  

3 EM Calorimeter       9650

3-1 CsI Crystals   ~10000 7850  

3-2 Si Pin Diode   ~20000 600  

3-3 Crystal measuring devices     200  

3-4 Calibration systems     200  

3-5 Support structure, assembling tool     400  

3-6 Assembling     200  

3-7 Others     200  

BESIII Budget

Page 64: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

64

4 Time of Flight       940

4-1 Scintillator   280 块 160  

4-2 PMT R5924   456 只 600  

4-3 New HV system     60  

4-4 PMT Base     30  

4-5 Machining and assembling     50  

4-6 R&D     40  

5 μcounters       300

5-1 RPC     250  

5-2 R&D     50  

6 Luminosity       50

Page 65: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

65

7 Super-conducting magnet       4000*

8 FED electronics       3680

8-1 MDC  9000T+Q 1800  

8-2 TOF  512 130  

8-3 EMC  10000 1500  

8-4 Muon   10000 250  

9 Trigger and DAQ       1150

10 Old end-door modification       50

11 Gas,environment and monitor       100

12 others       60

  Grand total       21900(4000*)

Page 66: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

66

Infrastructure BEPCII needs some building construction: halls for Cryogenic system and additional magnet power supplier; improving shielding of some buildings, etc. Major systems:

– New cryogenic system: capacity of 1kW/4.5K– BEPCII power consumption to be doubled

• 110kV transformer: 6300kVA 12500kVA• New electric crates and apparatus

– Increase capacity of air-conditioning– Improve water circulation system– Improve pure water system

Page 67: 1 Weiguo Li Institute of High Energy Physics 2002 年 6 月 5 日 BEPCII/BESIII PROJECT BESIII Collaboration Meeting June 5-6, Beijing

67

Sub-system BES III CLEOc

XY (m) = 130 110-130

MDC P/P (0/0) = 0.5 %(1 GeV) SC

1.25 %(1 GeV) normal

0.5 %(1 GeV)

dE/dx (0/0) = 6-7 % 6%

EMC E/√E(0/0) = 2.5 %(1 GeV)

z(cm) = 0.5cm/√E

2.3 %(1 GeV)0.5 cm /√E

TOF T (ps) = 80 ps Barrel 100 ps endcap

RICH

counter 9- 10 layers 3layers

magnet 1.0 tesla option 1 0.4 tesla option 2

1.0 tesla

Comparison Between BESIII and CLEOc