17292

  • Upload
    eayujig

  • View
    223

  • Download
    0

Embed Size (px)

Citation preview

  • 7/22/2019 17292

    1/23

    THOMAS BOEHME, DNV KEMA

    Managing Subsea Power Cable Risks

    1315 May 2013, Bremen, Germany

  • 7/22/2019 17292

    2/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Content

    ExperienceAction required

    RisksAssessment and management

    DesignConsiderations

    Conclusions2

    Export cable installation Picture source: DNV

  • 7/22/2019 17292

    3/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Part I

    Experience to Date

    3

  • 7/22/2019 17292

    4/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Experience

    4

    7,000 kmMore than 7,000 km of HV ( 60 kV)cables are in service (onshore,offshore), many more system-kilometres at 33 kV and below.

    80% claimsMany offshore wind farms haveexperienced problems with subseapower cables. Claim amounts*related to cables top the list.

    120 yearsPower cables have been around fora long time. Designs have evolved,new materials are being used.Challenges offshore remain.

    Data source: CIGR (2009);* Codan data, 2002-2011, claim cost

    BA

  • 7/22/2019 17292

    5/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Experience: Offshore Wind

    5

    Data source: DNV research(Shown: Reported in public domain)

    20112005 2006 2007 2008 2009 20102004200320022001

    Blyth

    Delays

    Inter-arraycables

    Problem

    Damage

    Exportcables

    Problem

    Damage

    Middelgrunden3 damages

    Horns Rev ICable damage

    North HoylePlanning deficiencies

    UtgrundenCable replacement

    UtgrundenCable replacement

    Q7Vessel substitution

    Robin RiggBarge evacuation

    BarrowRemedial burial

    Burbo BankCable damage

    Burbo BankCable damage

    ThanetRemedial work

    Arklow BankAnchor damage

    BarrowInstallation problems

    BlythCable damage

    Scroby SandsCable replacement

    ThanetKink discovered

    Walney IRegulator fine

    Greater GabbardContractor bankruptcy

    LincsRoute problems

    Bard Offshore I

    Diver fatality

    2012

    London ArrayCable damage

    GalloperRoute issues

    BarrowStanding loops

    Alpha VentusCable damage

    Gwynt y MrCable damage

    Lynn & Inner DowsingCable repair

    TeessideInstallation delays

    WalneyOutage of string

  • 7/22/2019 17292

    6/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Offshore Wind Investigation

    6

    Strong focus on price , not enough on risk

    New staff Lack of knowledge transfer

    Industry best practiceyet to be developed

    Incidentsin virtually every wind farm

    Most often during construction (95%*)

    Sometimes during operation (5%*)

    Data source: DNV stakeholder consultation* Codan data, 2002-2011, claim cost

    Failure stat ist icsnot yet available

  • 7/22/2019 17292

    7/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Response: CableRisk Joint Industry Project

    15 Participants Objective

    - Develop a guidelinefor subseapower cablesin renewable energyapplications which- covers the cable lifecycle

    - provides technical guidance

    - improves communication betweenstakeholders

    - helps managing the risks

    Application

    - Inter-array cables

    - Export cables

    - (Interconnectors)

    Timeline

    - Project: Aug 2012Jun 2013

    - Industry review: May 2013

    7

    INCH CAPE

    Project responsible:

  • 7/22/2019 17292

    8/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Part II

    Adopting a

    Risk-Based View

    8

  • 7/22/2019 17292

    9/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Risk Basis

    9

    Wind turbine

    Substation

    Subsea

    export

    cable

    to shore

    Subseainter-array

    cable 19

    1

    1217

    13

    14

    7

    8

    9

    10

    2

    3

    4

    5

    206

    1116

    15

    18

    Damage

    What targetsexistdescribing good

    (or good enough)

    cable connections?

    Target MTTR (days)?

    Annual target

    failure rate (%)?

    Different targets for

    - Construction phase?- Operations phase?

    Different targets for

    - Whole cable system?- Single cable?- Cable section?

    Acceptable level of

    injuries / fatalities?Environmental

    impact?

    NPV ()?

  • 7/22/2019 17292

    10/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Hazards, Threats Risk

    Hazard= Something that can cause harm (to people, environment, project)

    Event= Hazard realisation

    Risk = Event severity event probability

    10

    Hazard realisation,event, incident ConsequencesCauses

    Escalation

    Prevent barriers

    (facilities, processes, people)

    Detect / control / mitigate /

    recover barriers

    Immediatecause

    Rootcause

    (consequence) (likelihood)

    H&SEQ

  • 7/22/2019 17292

    11/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Acceptable

    Intolerable

    Tolerable

    Lower Higher

    Severity (log scale)

    Lower

    High

    er

    Pro

    bability(logscale)

    Risk Assessment Qualitativeassessment

    simple, quick, provides an overview

    subjective, needs scrapping (Chapman & Ward)

    Quantitativeassessment

    relatively objective, scientific backing

    requires effort, more suitable for focus areas

    11

    Sources: ISO 31000, ISO 31010, Chapman & Ward(2011), Kristiansen (2005)

    Mitigation

    H&S (or) E (or) Q

    Cumul.probability(%)

    100

    50

    0Lower Higher

    Impact (, days)

    Scenario A

    Scenario B

    P

    robability(logscale)

    Lower Higher

    Severity (log scale)

    Lower

    Higher

    Scenario A

    Scenario B

    H&S, E

    Q

    H&S, E, Q

    Risk identificationanalysisevaluationtreatment (ISO 31000)

    Management: PlanDoCheckAct

    Risk management to be integrated intoproject management

    H

    Pro

    bability

    Severity

    Acceptable

    Intolerable

    TolerableM

    L

    L M H

  • 7/22/2019 17292

    12/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    RisksHealth & Safety

    Generally considered to be

    relatively lowin cabling Mitigation (reduction) to as low

    as reasonably practicable

    (ALARP)

    12

    Lower Higher

    Severity

    Lo

    wer

    Higher

    Probab

    ility

    Diving fatality (2010)Bard Offshore I, Germany

    A diver ... was diving at approximately 41

    metres, and his air supply was cut off due

    to an unintended squeezing of his

    umbilical... The task was to removebottom material from the seabed [in front

    of J-tubes]. A dredger pipe was being

    positioned on the seabed, ... a job whose

    execution deviated from the method

    statementin which it is described it

    should be done by ROV.

    Diving

    activities

    All data: Illustrative only

    Access &

    transfer tooffshore units

    HV test work

    Work on cable

    laying vessel

    Confined

    space work

    (TP, MP)

    Sources: Maersk (2011)

    Working at

    height

    Escalation during

    emergency response

  • 7/22/2019 17292

    13/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    RisksEnvironment

    Risks require site-specific

    assessment Mitigation (reduction), e.g. to as

    low as reasonably practicable

    (ALARP)

    13

    Lower Higher

    Severity

    Lo

    wer

    High

    er

    Probab

    ility

    Seabed,

    mudflats

    disturbance

    All data: Illustrative only

    Disturbance

    of fauna

    Magnetic

    fields

    Construction

    noise

    Thermal

    impact (?)(esp. Germany)

    Sources: Centrica (2011, 2012), Bridgewatch (2011)

    Construction delays (2011-2012)Lincs, United Kingdom

    CREL ... tried to install two cable ducts

    under the salt marsh and sea defences last

    summer [2010], but this was not

    successful. As the saltmarsh is of highconservation value, a new solution was

    needed.

    Nessie is now [2012] laying the 2ndcable

    across the intertidal area, incorporating

    knowledge ... gained from laying the 1st

    cable in 2011.

    Introduction of

    new materials

    (e.g. rocks)

  • 7/22/2019 17292

    14/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    RisksProject (Quality, Cost, Time)

    Currently considered to be very

    highin cabling Optimisationto a desirable and

    appropriate level (threat vs.opportunity)

    14

    Lower Higher

    Severity

    Lower

    High

    er

    Probab

    ility

    Anchor

    impact

    All data: Illustrative only

    Unexpected soil

    conditions

    Free spans

    Sand waves

    Fishing gear

    impact

    Sources: Thanet Offshore Limited (2005),reNews (2011), Windpower Offshore (2012)

    Export cable repair (2012)Thanet, United Kingdom

    A section of the export link in the inter-

    tidal area of Pegwell Bay [has to be

    replaced] ... the radius of the loop is

    currently more acute (1.35 m) than therecommended 3.3 m.

    The problem was resolved on 13 April

    [2012]. The total cost to Vattenfall was

    about 5.6m.

    Weather

    delays

    Poor WTG

    interface

    design

    Unsuitable

    burial tool

    Installation

    delays Cable fault

    Natural

    catastrophe

  • 7/22/2019 17292

    15/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Part III

    From Good Design

    to Successful

    Projects

    15

  • 7/22/2019 17292

    16/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Scope of GuidelineDraft

    General

    - Introduction, references, definitions,abbreviations

    Design philosophy

    - HSEQ, risk basis, assessment andmanagement

    - System design principles

    - Stakeholder interfacemanagement

    Concept development and design- Field layout

    - Regulatory requirements

    - Site surveys

    - Cable route engineering and burialassessment

    - Marine conditions

    - Seabed properties, sand waves,

    - Infrastructure, navigation, living environment

    - Cable specificationfor

    - Site conditions

    - Offshore construction, O&M

    - Cableoffshore structure interface design

    Manufacturing & testing

    Installation and commissioning

    - Marine operations planning (vessels,anchoring, positioning, human factors)

    - Cable

    - Route preparation

    - Pull-in at offshore structure

    - Laying and protection

    - Landfall

    -

    Jointing, termination, testing- As-built survey

    Operation and maintenance

    - Remote monitoring

    - Surveys, remedial work

    - Fault detection, repair planning andexecution

    16

    Orange: Focus area

    Overall status: 90% completion

  • 7/22/2019 17292

    17/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Cable ProjectsAppreciating Complexity

    Quality checks

    All relevant stakeholders consulted?

    Started early with the planning and design?

    Optimised and planned with contingencies?

    17

    Electrical Thermal

    Mechanical

    Certifier, MWS

  • 7/22/2019 17292

    18/23

    Managing Subsea Power Cable Risks

    IQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    HV AC cableOffshore substationWind turbine generator Onshore substationMV AC cable

    Electrical Considerations

    Quality checks

    Reliability targets set?

    Failure rates applicable?

    18

    3 x 1 x 240 mm2Cu33 (36) kV, 880 m

    3 x 1 x 630 mm2Cu150 kV, 20,500 m

    3 x 1 x 800 mm2Cu150 kV, 1,350 m

    Ampacity

    estimation

    Topology

    selection

    Cablechoice

    Reliability

    check

    Basic

    power flow

    LayoutMW, kV

    R,XC

    p.u., Mvar

    Length

    Choiceof mm2

    Failure rate

    NPV ()

    Data sheets

  • 7/22/2019 17292

    19/23

    Managing Subsea Power Cable RisksIQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    HV AC cableOffshore substationWind turbine generator Onshore substationMV AC cable

    Thermal Considerations

    Quality checks

    Site data available?

    Hotspots ok?- J-tubes

    - Soils with low conductivity

    - Landfall

    19

    th

    Survey

    Cable route

    desktop study

    Burialassessment

    Cooling

    verification

    Constraints

    Depth

    Proposed corridor

    Electricallosses

    Back toelectrical study?

    Siteparameters

    , th

    y

    y

    Losses

    Example: 3 x 1 x 240 mm2Cu, 33 (36) kV

    - Cable A: 467 A (< 20

    C, < 1.0 K m / W)

    - Cable B: 590 A (< 10

    C, < 0.7 K m / W)

    Pel

    s

    w

    Data

    Hazards

    s

    w

  • 7/22/2019 17292

    20/23

    Managing Subsea Power Cable RisksIQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    HV AC cableOffshore substationWind turbine generator Onshore substationMV AC cable

    Mechanical Considerations

    Quality checks

    Installation weather dependent?

    Optimised for smooth installation?

    20

    Foundation

    designConstruction

    engineering

    Warranty surveyor

    verification

    Trials

    Cable properties

    Methodstatements

    Insurancecover?

    Back toelectrical / thermal

    study?

    Site, vessel data

    Radius,tension,

    frictionFpull Movement

  • 7/22/2019 17292

    21/23

    Managing Subsea Power Cable RisksIQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Example from Guideline: J-tubes

    Main text: When designing J-tubes, the

    following shall be considered:- adequate tube sizing (pull-in forces, cooling

    of cable)

    - avoidance of multiple bends

    - smoothness of inner surface

    - ...

    Guidance note:- The inner diameter of the J-tube should not

    be less than 2.5 cable outer diameter D tofacilitate cable cooling and avoid excessivepull-in forces.

    -

    The bending radius of the J-tube, measuredat the centre of the J-tube, should not be lessthan 20 cable outer diameter D, or larger, ifspecified by the cable manufacturer in orderto facilitate cable installation.

    - ...

    21

    Draft

    Subject to project + industry review

    Angle to seabed

    Straight length

    Flangefor cover

    Distance toseabed

    Bellmouth

    Smoothtransition

    Seabed

    Bending radius

    Inner diameter

    Distance between tubes

  • 7/22/2019 17292

    22/23

    Managing Subsea Power Cable RisksIQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    Conclusions

    Subsea power cabling is

    - multi-disciplinary

    - has frequently been underestimated

    Cable risks require assessment over whole life cycle

    Industry guidance is being developed22

    Array cable pull-in Picture source: DNV

  • 7/22/2019 17292

    23/23

    Managing Subsea Power Cable RisksIQPC Offshore Cabling, 13 - 15 May 2013, Bremen, Germany

    www.dnv.com

    Joint Industry Project: [email protected]