Samuel Engineering, Inc.8450 E. Crescent Pkwy. Ste 200Greenwood Village, CO 80111-2816
Phone: 303.714.4840Fax: 303.714.4800
SE
CLIENT:
LOCATION: NORTHERN PERU
NEWMONT MINING CORP.
IMPORTANT NOTES FOR CONTRACTOR
1. 6mm GAP IS REQUIRED BETWEEN PIPE TO PIPE/FITTING LOCATIONS WHERE A FLEXIBLE
COUPLING IS UTILIZED.
2. DIMENSIONS AND LENGTHS IN MILLIMETERS SHOULD BE CONVERTED TO IMPERIAL USING
25.4mm = 1 INCH.
3. PIPE SUPPORTS TO BE FABRICATED AND INSTALLED IN ACCORDANCE WITH PIPE
SUPPORT DETAIL DRAWINGS PROVIDED BY MECHANICAL CONTRACTOR.
4. MECHANICAL CONTRACTOR TO SUPPLY AND INSTALL ANY ADDITIONAL MISCELLANEOUS