01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOS REFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012 INSUMOS (ORDENADOS ALFABETICAMENTE) (TODOS los precios con ITBIS incluido) INACE 50000 ACEROS Y ALAMBRE GALVANIZADO: INACE 50001 Acero ¼" x 20' qq 1,433.13 101.72% 1,408.84 INACE 50002 Acero grado 40, 3/8" x 20' qq 2,044.81 101.72% 2,010.15 INACE 50003 Acero grado 40, 3/8" x 25' qq 2,002.92 101.72% 1,968.97 INACE 50004 Acero grado 40, 3/8" x 30' qq 2,002.92 101.72% 1,968.97 INACE 50005 Acero grado 40, ½" x 20' qq 2,052.19 101.72% 2,017.40 INACE 50006 Acero grado 40, ½" x 25' qq 2,009.22 101.72% 1,975.17 INACE 50007 Acero grado 40, ½" x 30' qq 2,009.22 101.72% 1,975.17 INACE 50008 Acero grado 40, ¾" x 20' qq 2,007.42 101.72% 1,973.39 INACE 50009 Acero grado 40, ¾" x 25' qq 2,007.42 101.72% 1,973.39 INACE 50010 Acero grado 40, ¾" x 30' qq 2,007.42 101.72% 1,973.39 INACE 50011 Acero grado 40, 1" x 20' qq 1,989.53 101.72% 1,955.81 INACE 50012 Acero grado 40, 1" x 25' qq 1,989.53 101.72% 1,955.81 INACE 50013 Acero grado 40, 1" x 30' qq 1,989.53 101.72% 1,955.81 INACE 50014 Acero grado 60, 3/8" x 20' qq 2,281.91 101.72% 2,243.23 INACE 50015 Acero grado 60, 3/8" x 25' qq 2,362.89 101.72% 2,322.84 INACE 50016 Acero grado 60, 3/8" x 30' qq 2,351.63 101.72% 2,311.78 INACE 50017 Acero grado 60, ½" x 20' qq 2,344.68 101.72% 2,304.94 INACE 50018 Acero grado 60, ½" x 25' qq 2,340.35 101.72% 2,300.69 INACE 50019 Acero grado 60, ½" x 30' qq 2,357.29 101.72% 2,317.33 INACE 50020 Acero grado 60, ¾" x 20' qq 2,338.43 101.72% 2,298.80 INACE 50021 Acero grado 60, ¾" x 25' qq 2,303.78 101.72% 2,264.74 INACE 50022 Acero grado 60, ¾" x 30' qq 2,307.24 101.72% 2,268.14 INACE 50023 Acero grado 60, 1" x 20' qq 2,313.66 101.72% 2,274.45 INACE 50024 Acero grado 60, 1" x 25' qq 2,292.56 101.72% 2,253.71 INACE 50025 Acero grado 60, 1" x 30' qq 2,319.86 101.72% 2,280.54 INACE 50026 Alambre galv. Calibre 14 (Para reforzar encofrados) lb 34.64 101.70% 34.06 INACE 50027 Alambre galv. Calibre 18 (Para amarrar varillas) lb 34.64 101.70% 34.06 INACE 50028 Acero malla (D2.3 x D2.3, 100 x 100,Rollo 2.40 x 40.00 m., 4.85 qq) rollo 14,248.50 101.72% 14,007.00 INACE 50029 Acero malla (D2.3 x D2.3, 150 x 150,Rollo 2.40 x 40.00 m., 3.32 qq) rollo 9,481.30 101.72% 9,320.60 INACE 50030 Acero malla (D2.3 x D2.3, 200 x 200,Rollo 2.40 x 40.00 m., 2.48 qq) rollo 7,109.50 101.72% 6,989.00 INACE 50031 Acero malla (D2.5 x D2.5, 100 x 100,Rollo 2.40 x 40.00 m., 5.35 qq) rollo 13,529.31 101.72% 13,300.00 INACE 50032 Acero malla (D2.5 x D2.5, 150 x 150,Rollo 2.40 x 40.00 m., 3.66 qq) rollo 9,073.80 101.72% 8,920.01 INACE 50033 Acero malla (D2.5 x D2.5, 200 x 200,Rollo 2.40 x 40.00 m., 2.74 qq) rollo 6,932.50 101.72% 6,815.00 INACE 50034 Acero malla (D2.7 x D2.7, 100 x 100,Rollo 2.40 x 40.00 m., 5.87 qq) rollo 14,928.01 101.72% 14,675.00 INACE 50035 Acero malla (D2.7 x D2.7, 150 x 150,Rollo 2.40 x 40.00 m., 3.90 qq) rollo 9,933.36 101.72% 9,765.00 INACE 50036 Acero malla (D2.9 x D2.9, 100 x 100,Rollo 2.40 x 40.00 m., 6.21 qq) rollo 15,514.97 101.72% 15,252.00 INACE 50037 Acero malla (D2.9 x D2.9, 150 x 150,Rollo 2.40 x 40.00 m., 4.25 qq) rollo 10,426.73 101.72% 10,250.00 INACE 50038 Acero malla (D2.9 x D2.9, 200 x 200,Rollo 2.40 x 40.00 m., 3.18 qq) rollo 8,000.60 101.72% 7,865.00 INACE 60000 AGREGADOS, BOTES, CALICHE Y TIERRA NEGRA: INACE 60001 Arena fina para empañete m3 963.94 101.72% 947.60 INACE 60002 Arena gruesa lavada m3 963.94 101.72% 947.60 INACE 60003 Arena itabo de mina m3 880.93 101.72% 866.00 INACE 60004 Arena triturada y lavada, azul (Para hormigón) m3 1,292.28 101.72% 1,270.37 INACE 60005 Bote de materiales (Con paleros) m3 351.88 101.73% 345.91 INACE 60006 Bote de materiales (Con equipo) m3 233.99 101.72% 230.03 INACE 60007 Caliche m3 329.57 101.72% 323.99 INACE 60008 Cascajo de mina m3 880.93 101.72% 866.00 INACE 60009 Granzote fino m3 587.29 101.73% 577.33 INACE 60010 Granzote grueso m3 499.32 101.73% 490.85 INACE 60011 Grava ¾" - ½" triturada m3 880.93 101.72% 866.00 INACE 60012 Tierra negra m3 880.93 101.72% 866.00 INASC 70000 ASCENSORES: INASC 70001 Ascensor 8 personas, 8 niv., 3 ph. "Mitsubishi" u 2,902,593.40 101.72% 2,853,396.90 INACE 70002 Ascensor para 10 personas, 6 niv., Gen2 Confort, 1 m/seg., 3 ph. "Otis" u 1,793,389.94 101.72% 1,762,993.50 INBAL 80000 BALAUSTRES Y PASAMANOS: Precios estimados INBAL 80001 Balaustre 45 cms. Gris u 147.21 101.73% 144.71 INBAL 80002 Balaustre 45 cms. Bco. Cep. u 230.31 101.72% 226.41 INBAL 80003 Balaustre 50 cms. Gris u 161.91 101.73% 159.16 INBAL 80004 Balaustre 50 cms. Bco. Cep. u 257.16 101.72% 252.80 INBAL 80005 Balaustre 55 cms. Gris u 175.77 101.72% 172.79 INBAL 80006 Balaustre 55 cms. Bco. Cep. u 278.81 101.73% 274.08 INBAL 80007 Balaustre 64 cms. Gris u 203.48 101.72% 200.03 INBAL 80008 Balaustre 64 cms. Bco. Cep. u 325.57 101.72% 320.06 INBAL 80009 Balaustre 67 cms. Gris u 214.74 101.72% 211.10 INBAL 80010 Balaustre 67 cms. Bco. Cep. u 337.69 101.72% 331.97 INBAL 80011 Balaustre 72 cms. Gris u 223.40 101.73% 219.61 INBAL 80012 Balaustre 72 cms. Bco. Cep. u 359.33 101.72% 353.24 INBAL 80013 Balaustre 74 cms. Gris Cep. u 241.57 101.72% 237.48 INBAL 80014 Balaustre 74 cms. Bco. Cep. u 386.17 101.73% 379.62 INBAL 80015 Pasamano bco. Cep. 30 bocel cuadrado m 646.51 101.72% 635.55 INBAL 80016 Pasamano bco. Cep. 30 bocel redondo m 754.27 101.72% 741.48 INBAL 80017 Pasamano bco. Pul. 30 bocel cuadrado m 765.80 101.72% 752.82 INBAL 80018 Pasamano bco. Pul. 30 bocel redondo m 834.12 101.72% 819.98 INBAL 80019 Pasamano súper bocel cuadrado m 797.56 101.72% 784.04 INBAL 80020 Pasamano súper bocel redondo m 938.97 101.72% 923.06 INBAL 80021 Transp. balaustre u 2.61 101.95% 2.56 INBAL 80022 Transp. pasamano m 10.41 101.76% 10.23 INBAÑ 90000 BAÑOS, FREGADEROS , CALENT. ELECT. Y ACCESORIOS: INBAÑ 90001 Accesorios 5 piezas, Bco., porcelana u 1,351.10 101.72% 1,328.20 INBAÑ 90002 Accesorios 5 piezas, cromo, corriente, sup. u 415.36 101.72% 408.32 INBAÑ 90003 Accesorios 6 piezas, cromo, sup., 5706 u 1,750.87 101.72% 1,721.20 INBAÑ 90004 Arandela plástica 3" ó 4", para inodoro u 48.38 101.72% 47.56 INBAÑ 90005 Aro Olimpia Tatay 63071-6 u 253.70 101.72% 249.40 INBAÑ 90006 Asiento p/inod., Bone redondo, D60 J. V., "Sadosa" u 302.22 101.72% 297.10 INBAÑ 90007 Bañera hierro fundido, color, "Naple" sin mescl. y sin ducha u 13,924.00 101.72% 13,688.00 INBAÑ 90008 Bañera hierro fundido, blanca, "Naple" sin mescl. y sin ducha u 15,222.00 101.72% 14,964.00 INBAÑ 90009 Bañera hidroneumasaje blanca con asiento y reclinacabeza u 59,843.70 101.72% 58,829.40 PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 1

2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

Embed Size (px)

Citation preview

Page 1: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012

INSUMOS (ORDENADOS ALFABETICAMENTE) (TODOS los precios con ITBIS incluido)INACE 50000 ACEROS Y ALAMBRE GALVANIZADO:INACE 50001 Acero ¼" x 20' qq 1,433.13 101.72% 1,408.84INACE 50002 Acero grado 40, 3/8" x 20' qq 2,044.81 101.72% 2,010.15INACE 50003 Acero grado 40, 3/8" x 25' qq 2,002.92 101.72% 1,968.97INACE 50004 Acero grado 40, 3/8" x 30' qq 2,002.92 101.72% 1,968.97INACE 50005 Acero grado 40, ½" x 20' qq 2,052.19 101.72% 2,017.40INACE 50006 Acero grado 40, ½" x 25' qq 2,009.22 101.72% 1,975.17INACE 50007 Acero grado 40, ½" x 30' qq 2,009.22 101.72% 1,975.17INACE 50008 Acero grado 40, ¾" x 20' qq 2,007.42 101.72% 1,973.39INACE 50009 Acero grado 40, ¾" x 25' qq 2,007.42 101.72% 1,973.39INACE 50010 Acero grado 40, ¾" x 30' qq 2,007.42 101.72% 1,973.39INACE 50011 Acero grado 40, 1" x 20' qq 1,989.53 101.72% 1,955.81INACE 50012 Acero grado 40, 1" x 25' qq 1,989.53 101.72% 1,955.81INACE 50013 Acero grado 40, 1" x 30' qq 1,989.53 101.72% 1,955.81INACE 50014 Acero grado 60, 3/8" x 20' qq 2,281.91 101.72% 2,243.23INACE 50015 Acero grado 60, 3/8" x 25' qq 2,362.89 101.72% 2,322.84INACE 50016 Acero grado 60, 3/8" x 30' qq 2,351.63 101.72% 2,311.78INACE 50017 Acero grado 60, ½" x 20' qq 2,344.68 101.72% 2,304.94INACE 50018 Acero grado 60, ½" x 25' qq 2,340.35 101.72% 2,300.69INACE 50019 Acero grado 60, ½" x 30' qq 2,357.29 101.72% 2,317.33INACE 50020 Acero grado 60, ¾" x 20' qq 2,338.43 101.72% 2,298.80INACE 50021 Acero grado 60, ¾" x 25' qq 2,303.78 101.72% 2,264.74INACE 50022 Acero grado 60, ¾" x 30' qq 2,307.24 101.72% 2,268.14INACE 50023 Acero grado 60, 1" x 20' qq 2,313.66 101.72% 2,274.45INACE 50024 Acero grado 60, 1" x 25' qq 2,292.56 101.72% 2,253.71INACE 50025 Acero grado 60, 1" x 30' qq 2,319.86 101.72% 2,280.54INACE 50026 Alambre galv. Calibre 14 (Para reforzar encofrados) lb 34.64 101.70% 34.06INACE 50027 Alambre galv. Calibre 18 (Para amarrar varillas) lb 34.64 101.70% 34.06INACE 50028 Acero malla (D2.3 x D2.3, 100 x 100,Rollo 2.40 x 40.00 m., 4.85 qq) rollo 14,248.50 101.72% 14,007.00INACE 50029 Acero malla (D2.3 x D2.3, 150 x 150,Rollo 2.40 x 40.00 m., 3.32 qq) rollo 9,481.30 101.72% 9,320.60INACE 50030 Acero malla (D2.3 x D2.3, 200 x 200,Rollo 2.40 x 40.00 m., 2.48 qq) rollo 7,109.50 101.72% 6,989.00INACE 50031 Acero malla (D2.5 x D2.5, 100 x 100,Rollo 2.40 x 40.00 m., 5.35 qq) rollo 13,529.31 101.72% 13,300.00INACE 50032 Acero malla (D2.5 x D2.5, 150 x 150,Rollo 2.40 x 40.00 m., 3.66 qq) rollo 9,073.80 101.72% 8,920.01INACE 50033 Acero malla (D2.5 x D2.5, 200 x 200,Rollo 2.40 x 40.00 m., 2.74 qq) rollo 6,932.50 101.72% 6,815.00INACE 50034 Acero malla (D2.7 x D2.7, 100 x 100,Rollo 2.40 x 40.00 m., 5.87 qq) rollo 14,928.01 101.72% 14,675.00INACE 50035 Acero malla (D2.7 x D2.7, 150 x 150,Rollo 2.40 x 40.00 m., 3.90 qq) rollo 9,933.36 101.72% 9,765.00INACE 50036 Acero malla (D2.9 x D2.9, 100 x 100,Rollo 2.40 x 40.00 m., 6.21 qq) rollo 15,514.97 101.72% 15,252.00INACE 50037 Acero malla (D2.9 x D2.9, 150 x 150,Rollo 2.40 x 40.00 m., 4.25 qq) rollo 10,426.73 101.72% 10,250.00INACE 50038 Acero malla (D2.9 x D2.9, 200 x 200,Rollo 2.40 x 40.00 m., 3.18 qq) rollo 8,000.60 101.72% 7,865.00

INACE 60000 AGREGADOS, BOTES, CALICHE Y TIERRA NEGRA:INACE 60001 Arena fina para empañete m3 963.94 101.72% 947.60INACE 60002 Arena gruesa lavada m3 963.94 101.72% 947.60INACE 60003 Arena itabo de mina m3 880.93 101.72% 866.00INACE 60004 Arena triturada y lavada, azul (Para hormigón) m3 1,292.28 101.72% 1,270.37INACE 60005 Bote de materiales (Con paleros) m3 351.88 101.73% 345.91INACE 60006 Bote de materiales (Con equipo) m3 233.99 101.72% 230.03INACE 60007 Caliche m3 329.57 101.72% 323.99INACE 60008 Cascajo de mina m3 880.93 101.72% 866.00INACE 60009 Granzote fino m3 587.29 101.73% 577.33INACE 60010 Granzote grueso m3 499.32 101.73% 490.85INACE 60011 Grava ¾" - ½" triturada m3 880.93 101.72% 866.00INACE 60012 Tierra negra m3 880.93 101.72% 866.00

INASC 70000 ASCENSORES:INASC 70001 Ascensor 8 personas, 8 niv., 3 ph. "Mitsubishi" u 2,902,593.40 101.72% 2,853,396.90INACE 70002 Ascensor para 10 personas, 6 niv., Gen2 Confort, 1 m/seg., 3 ph. "Otis" u 1,793,389.94 101.72% 1,762,993.50

INBAL 80000 BALAUSTRES Y PASAMANOS: Precios estimadosINBAL 80001 Balaustre 45 cms. Gris u 147.21 101.73% 144.71INBAL 80002 Balaustre 45 cms. Bco. Cep. u 230.31 101.72% 226.41INBAL 80003 Balaustre 50 cms. Gris u 161.91 101.73% 159.16INBAL 80004 Balaustre 50 cms. Bco. Cep. u 257.16 101.72% 252.80INBAL 80005 Balaustre 55 cms. Gris u 175.77 101.72% 172.79INBAL 80006 Balaustre 55 cms. Bco. Cep. u 278.81 101.73% 274.08INBAL 80007 Balaustre 64 cms. Gris u 203.48 101.72% 200.03INBAL 80008 Balaustre 64 cms. Bco. Cep. u 325.57 101.72% 320.06INBAL 80009 Balaustre 67 cms. Gris u 214.74 101.72% 211.10INBAL 80010 Balaustre 67 cms. Bco. Cep. u 337.69 101.72% 331.97INBAL 80011 Balaustre 72 cms. Gris u 223.40 101.73% 219.61INBAL 80012 Balaustre 72 cms. Bco. Cep. u 359.33 101.72% 353.24INBAL 80013 Balaustre 74 cms. Gris Cep. u 241.57 101.72% 237.48INBAL 80014 Balaustre 74 cms. Bco. Cep. u 386.17 101.73% 379.62INBAL 80015 Pasamano bco. Cep. 30 bocel cuadrado m 646.51 101.72% 635.55INBAL 80016 Pasamano bco. Cep. 30 bocel redondo m 754.27 101.72% 741.48INBAL 80017 Pasamano bco. Pul. 30 bocel cuadrado m 765.80 101.72% 752.82INBAL 80018 Pasamano bco. Pul. 30 bocel redondo m 834.12 101.72% 819.98INBAL 80019 Pasamano súper bocel cuadrado m 797.56 101.72% 784.04INBAL 80020 Pasamano súper bocel redondo m 938.97 101.72% 923.06INBAL 80021 Transp. balaustre u 2.61 101.95% 2.56INBAL 80022 Transp. pasamano m 10.41 101.76% 10.23

INBAÑ 90000 BAÑOS, FREGADEROS , CALENT. ELECT. Y ACCESORIOS:INBAÑ 90001 Accesorios 5 piezas, Bco., porcelana u 1,351.10 101.72% 1,328.20INBAÑ 90002 Accesorios 5 piezas, cromo, corriente, sup. u 415.36 101.72% 408.32INBAÑ 90003 Accesorios 6 piezas, cromo, sup., 5706 u 1,750.87 101.72% 1,721.20INBAÑ 90004 Arandela plástica 3" ó 4", para inodoro u 48.38 101.72% 47.56INBAÑ 90005 Aro Olimpia Tatay 63071-6 u 253.70 101.72% 249.40INBAÑ 90006 Asiento p/inod., Bone redondo, D60 J. V., "Sadosa" u 302.22 101.72% 297.10INBAÑ 90007 Bañera hierro fundido, color, "Naple" sin mescl. y sin ducha u 13,924.00 101.72% 13,688.00INBAÑ 90008 Bañera hierro fundido, blanca, "Naple" sin mescl. y sin ducha u 15,222.00 101.72% 14,964.00INBAÑ 90009 Bañera hidroneumasaje blanca con asiento y reclinacabeza u 59,843.70 101.72% 58,829.40

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 1

Page 2: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012

INBAÑ 90010 Bañera liviana, color, sin mescl. y sin ducha u 7,115.55 101.72% 6,994.95INBAÑ 90011 Bañera liviana, blanca, sin mescl. y sin ducha u 6,843.62 101.72% 6,727.63INBAÑ 90012 Bañera PVC blanca, 1.4 m., "Virgo" u 6,637.50 101.72% 6,525.00INBAÑ 90013 Bañera PVC color, 1.4 m., "Virgo" u 6,637.50 101.72% 6,525.00INBAÑ 90014 Barra de seguridad 16", cromo, JOFEL AV-40400 u 1,588.28 101.72% 1,561.36INBAÑ 90015 Barra de seguridad 24",cromo, JOFEL AV-40600 u 1,801.22 101.72% 1,770.69INBAÑ 90016 Barra para cortina de baño, 1" x 6' 1847-AL/15103 u 171.10 101.72% 168.20INBAÑ 90017 Bidet a color "Royal", sin mescl. y sin acces. u 3,051.73 101.72% 3,000.00INBAÑ 90018 Bidet bco. "Royal", sin mescl. y sin acces. u 2,708.10 101.72% 2,662.20INBAÑ 90019 Boquilla lavamanos, automática, cromo, "Price Pfister" u 454.30 101.72% 446.60INBAÑ 90020 Boquilla lavamanos, pvc, sencilla u 107.57 101.72% 105.75INBAÑ 90021 Boquilla fregadero, 4 ½", cromo (c/u) u 179.66 101.73% 176.61INBAÑ 90022 Boquilla lavadero, cromo, con tapón u 132.83 101.72% 130.58INBAÑ 90023 Boquilla lavadero 2 ½", pvc, con tapón u 126.78 101.73% 124.63INBAÑ 90024 Botiquín 1 pta., 2 luces, cromo, corriente, R1102/R201 u 2,312.41 101.72% 2,273.22INBAÑ 90025 Botiquín 1 pta, Bco., mad. prens., Danubio 700, 27 ½"x26 ½", "Salgar" u 5,443.26 101.72% 5,351.00INBAÑ 90026 Botiquín 2 ptas., 2 luces, cromo, Salgar, (Bot 48) (Sin Invent.) u 4,388.38 101.72% 4,314.01INBAÑ 90027 Botiquín 2 ptas., 2 luces, cromo, 3 cajones (Bot 90 C/cajones) u 2,731.70 101.72% 2,685.40INBAÑ 90028 Botiquín 2 pta, Bco., mad. prens., Danubio 850, 33 ½"x26 ½", "Salgar" u 7,254.97 101.72% 7,132.00INBAÑ 90029 Botiquín 3 ptas., 2 luces, cromo, Salgar, (Bot 60) u 4,171.30 101.72% 4,100.60INBAÑ 90030 Calent. eléct. 06 gls. "Premium" u 5,412.26 101.72% 5,320.53INBAÑ 90031 Calent. eléct. 08 gls. "Premium" u 5,782.00 101.72% 5,684.00INBAÑ 90032 Calent. eléct. 12 gls. "Premium" u 6,348.40 101.72% 6,240.80INBAÑ 90033 Calent. eléct. 15 gls. "Premium" u 7,371.06 101.72% 7,246.13INBAÑ 90034 Calent. eléct. 20 gls. "Premium" u 7,865.88 101.72% 7,732.56INBAÑ 90035 Calent. eléct. 6 gls., USA "Duraheat" u 4,578.40 101.72% 4,500.80INBAÑ 90036 Calent. eléct. 8 gls., USA "Duraheat" u 4,963.86 101.72% 4,879.73INBAÑ 90037 Calent. eléct. 12 gls., USA "Duraheat" u 5,514.53 101.72% 5,421.06INBAÑ 90038 Calent. eléct. 15 gls., USA "Duraheat" u 5,882.30 101.72% 5,782.60INBAÑ 90039 Calent. eléct. 20 gls., USA "Duraheat" u 7,001.33 101.72% 6,882.66INBAÑ 90040 Calent. eléct. 30 gls., USA "American" u 18,148.40 101.72% 17,840.80INBAÑ 90041 Calent. eléct. 40 gls., USA "American" u 24,740.66 101.72% 24,321.33INBAÑ 90042 Calent. eléct. 80 gls., USA "American" u 37,909.46 101.72% 37,266.93INBAÑ 90043 Calent. de gas 12 litros por minuto, JSD-24 u 10,779.30 101.72% 10,596.60INBAÑ 90044 Calent. de gas 15 litros por minuto u 15,990.09 101.72% 15,719.07INBAÑ 90045 Calent. de gas 16 litros por minuto, "Best" u 17,674.34 101.72% 17,374.77INBAÑ 90046 Calent. de gas 22 litros por minuto, "Lorenzetti" u 28,478.12 101.72% 27,995.44INBAÑ 90047 Cepillera clásica II, sup., cromo 207 u 857.40 101.72% 842.87INBAÑ 90048 Cepillera Nuva cristal, sup., cromo 9107_C u 3,339.72 101.72% 3,283.11INBAÑ 90049 Cola ext. lavamanos 1 ¼"x6", cromo u 141.60 101.72% 139.20INBAÑ 90050 Cola ext. fregadero 1 ½"x8", pvc u 78.51 101.74% 77.17INBAÑ 90051 Cola ext. fregadero 1 ½"x8", pvc, 10-8w u 32.52 101.72% 31.97INBAÑ 90052 Cubrefalta 3/8", cromo, HP323F D-382A u 12.98 101.72% 12.76INBAÑ 90053 Cubrefalta ½", cromo, HP323F D-382B u 9.44 101.72% 9.28INBAÑ 90054 Cubrefalta ¾", cromo u 17.70 101.72% 17.40INBAÑ 90055 Desagüe bañera, "Price Pfister", pvc u 2,578.30 101.72% 2,534.60INBAÑ 90056 Desagüe jacuzzi de cable, pvc u 1,356.71 101.72% 1,333.71INBAÑ 90057 Desagüe fregadero, 1 ½"x16, pvc, doble, 130-16 u 170.46 101.72% 167.57INBAÑ 90058 Desagüe lavamanos, 1 ¼", pvc, terminación cromo u 196.67 101.72% 193.34INBAÑ 90059 Dispensador papel sanit., gris, Jofel AE43000 u 1,681.50 101.72% 1,653.00INBAÑ 90060 Dispensador papel toalla, bco., Jofel AG16000 u 3,995.48 101.72% 3,927.76INBAÑ 90061 Dispensador papel toalla, gris, Jofel AG15000 u 3,935.30 101.72% 3,868.60INBAÑ 90062 Dosificador jabón líquido, bco., Jofel 400ML u 867.30 101.72% 852.60INBAÑ 90063 Dosificador jabón líquido, inox., Jofel AC21100 u 1,150.50 101.72% 1,131.00INBAÑ 90064 Ducha "Price Pfister", Ref. 413-0100, cromo u 1,044.30 101.72% 1,026.60INBAÑ 90065 Ducha plástica completa, cromo u 101.09 101.72% 99.38INBAÑ 90066 Freg. 1B. bar, a. inox, 15"x15", sin mescl. y sin acces. "Teka" u 1,580.66 101.72% 1,553.87INBAÑ 90067 Freg. 1B. bar, a. inox, 20"x21", sin mescl. y sin acces. "Teka" u 1,482.16 101.72% 1,457.04INBAÑ 90068 Freg. 1B. a. inox, 25"x22", sin mescl. y sin acces. "Teka" u 1,736.25 101.72% 1,706.82INBAÑ 90069 Freg. 2B. a. inox, 33"x22", ANGULAR sin mescl. y sin acces. "Teka" u 10,504.24 101.72% 10,326.20INBAÑ 90070 Freg. 2B. a. inox, 33"x22", sin mescl. y sin acces. "Teka" u 1,056.10 101.72% 1,038.20INBAÑ 90071 Freg. 3B. a. inox, 1000X510, 1hoyo, sin mescl. y sin acces. "Teka" u 12,178.71 101.72% 11,972.29INBAÑ 90072 Gabinete contra incendio, 1 ½" x 33 metros u 8,850.00 101.72% 8,700.00INBAÑ 90073 Gancho colgador, cromo sencillo "Tatay" 64230-6 u 360.45 101.72% 354.35INBAÑ 90074 Inodoro bco., alargado, tapa, sin acces, "Royal" u 6,334.24 101.72% 6,226.88INBAÑ 90075 Inodoro bco., tapa, sin acces, "Simplex" u 3,675.70 101.72% 3,613.40INBAÑ 90076 Inodoro color, tapa, sin acces, "Simplex" u 3,919.96 101.72% 3,853.52INBAÑ 90077 Inodoro bco., tapa, sin acces, "Taino" u 2,460.30 101.72% 2,418.60INBAÑ 90078 Inodoro color, alargado, tapa, sin acces, "Royal" u 6,965.45 101.72% 6,847.39INBAÑ 90079 Inodoro color, corriente, tapa, sin acces, "Azteca" u 5,350.65 101.72% 5,259.96INBAÑ 90080 Inodoro natural, silencioso, tapa, sin acces, "Ellisse natural" u 23,450.87 101.72% 23,053.40INBAÑ 90081 Inodoro natural, silencioso, tapa, sin acces, "Petit Garson" u 13,711.60 101.72% 13,479.20INBAÑ 90082 Inodoro fluxómetro bco., sin tapa, sin válvula, "Royal" u 4,985.50 101.72% 4,901.00INBAÑ 90083 Jabonera bañera, sin agarradera, cromo, corriente, Ref. 5759 u 291.99 101.72% 287.04INBAÑ 90084 Jabonera líquida, cromo, corriente (sin el jabón) u 547.93 101.72% 538.65INBAÑ 90085 Jabonera Nuva senc. cristal, Jofel cromo 9108-C u 3,040.86 101.72% 2,989.32INBAÑ 90086 Jabonera sencilla Clásica II, sup., cromo 208 u 914.39 101.72% 898.90INBAÑ 90087 Jacuzzi beige, acces. cromo, con bomba, "Cadenza" u 38,373.60 101.72% 37,723.20INBAÑ 90088 Juego baño 3 pzas color, sin acces. jgo 7,834.39 101.72% 7,701.60INBAÑ 90089 Juego baño 3 pzas, bco., sin acces. jgo 15,988.27 101.72% 15,717.28INBAÑ 90090 Junta de cera u 43.74 101.72% 43.00INBAÑ 90091 Lavamanos color, 19"x"17", sin mescl. y sin acces, "Embajador" u 1,544.29 101.72% 1,518.12INBAÑ 90092 Lavamanos Pedestal, color ovalado, sin mescl. y sin acces, "Royal" u 2,620.83 101.72% 2,576.41INBAÑ 90093 Lavamanos bco., 19"x"17", sin mescl. y sin acces, "Isabela" u 1,342.51 101.72% 1,319.76INBAÑ 90094 Lavamanos bco., pequeño, 1 hoyo, sin acces, "Simplex" u 953.24 101.72% 937.08INBAÑ 90095 Lavamanos ovalado color, 4" sin mescl. y sin acces, "Saona" u 2,482.52 101.72% 2,440.44INBAÑ 90096 Lavamanos ovalado bco., 8" sin mescl. y sin acces, "Saona" u 2,243.79 101.72% 2,205.76INBAÑ 90097 Llave angular ½" ó 3/8", "USA" u 177.00 101.72% 174.00INBAÑ 90098 Llave chorro ½", "Urrea" u 324.50 101.72% 319.00INBAÑ 90099 Llave chorro ¾", "Urrea" u 401.20 101.72% 394.40INBAÑ 90100 Llave empotrar de ½", cromo, "Urrea" u 413.00 101.72% 406.00INBAÑ 90101 Llave lavamanos peq., sencilla cromo, "Urrea" u 619.22 101.72% 608.72INBAÑ 90102 Manguera negra ¾" con tuercas, p/montar calentador u 333.68 101.73% 328.02INBAÑ 90103 Mezcl. baño, 1ra., desagüe, cromo, 01-311 "Bedford" u 5,628.60 101.72% 5,533.20

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 2

Page 3: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012

INBAÑ 90104 Mezcl. baño, 3 puños, desagüe, "Sayco" u 3,481.00 101.72% 3,422.00INBAÑ 90105 Mezcl. baño Monom., Nuva, cromo HM211028C u 15,735.70 101.72% 15,468.99INBAÑ 90106 Mezcl. bidet, completa, monomando, "Salus" u 587.97 101.72% 578.00INBAÑ 90107 Mezcl. freg. con manguera, H35-121 "Price Pfister" u 2,082.30 101.72% 2,047.01INBAÑ 90108 Mezcl. freg. Monom., cuello largo, cromo 034-1NCC "Price Pfister" u 3,574.59 101.72% 3,514.00INBAÑ 90109 Mezcl. Lavam., boquilla, "Sayco" Ref. 400 u 2,448.50 101.72% 2,407.00INBAÑ 90110 Mezcl. Lavam., boquilla, 1ra., H43-128 "Bedford" u 3,338.59 101.72% 3,282.00INBAÑ 90111 Mezcl. Lavam. Cachera Albatros, 4", cromo HM15C u 3,574.59 101.72% 3,514.00INBAÑ 90112 Mezcl. Lavam. Nuva E2006, 8", cromo HL1531C u 9,233.50 101.72% 9,077.00INBAÑ 90113 Mescl. Orinal, Llave cromo completa (Sin Invent.) u 565.17 101.72% 555.59INBAÑ 90114 Niple 3/8"x2 ½", cromo u 29.50 101.72% 29.00INBAÑ 90115 Orinal pequeño, bco., sin la llave "Simplex" Ozama 15510 u 2,441.54 101.72% 2,400.16INBAÑ 90116 Orinal ½ falda flux., , bco., sin llave y sin válvula "Yaque" u 9,987.93 101.72% 9,818.65INBAÑ 90117 Palometa doble alum., fijar lavamanos par 90.53 101.72% 89.00INBAÑ 90118 Papelera Clásica II, sup., cromo 215 u 1,899.16 101.72% 1,866.97INBAÑ 90119 Papelera Nuva sencilla I, sup., cromo 9117_C u 2,354.10 101.72% 2,314.20INBAÑ 90120 Porta papel de inodoro, cromo, superficie, Ref. 5756 u 475.01 101.72% 466.96INBAÑ 90121 Porta servilletas, bco., Jofel AH-31000 u 751.96 101.72% 739.21INBAÑ 90122 Porta servilletas, gris, Jofel AH-32000 u 1,177.64 101.72% 1,157.68INBAÑ 90123 Rejilla 3", de 2" p/piso, Redonda, Reforzada, "Helvex" cromo u 1,248.23 101.72% 1,227.07INBAÑ 90124 Rejilla 3", de 2" p/piso, Redonda, sencilla, cromo u 69.62 101.72% 68.44INBAÑ 90125 Rejilla 3"x3" p/piso, Cuadrada, Reforzada, "Helvex" cromo u 1,202.38 101.72% 1,182.01INBAÑ 90126 Rejilla 4 5/8" p/piso, aluminio u 45.54 101.74% 44.76INBAÑ 90127 Secador de manos, Sensor eléctrico, bco., Helvex u 19,493.60 101.72% 19,163.20INBAÑ 90128 Secador de manos Standard, bco., Jofel AA-11000 u 10,177.50 101.72% 10,005.00INBAÑ 90129 Sifón fregadero doble 1 ½", pvc u 169.92 101.72% 167.04INBAÑ 90130 Sifón fregadero sencillo 1 ½", pvc u 71.92 101.73% 70.70INBAÑ 90131 Sifón lavamanos, 1 ¼", cromo, completo, USA u 465.90 101.72% 458.00INBAÑ 90132 Sifón lavamanos, 1 ¼", cromo, completo, corriente 300-SN u 465.90 101.72% 458.00INBAÑ 90133 Sifón lavamanos, 1 ¼", pvc 400-TTWBAG EASTMA u 71.92 101.73% 70.70INBAÑ 90134 Tapa p/Cisterna, 27"x27", aluminio u 2,708.10 101.72% 2,662.20INBAÑ 90135 Tornillos p/bacineta, ¼"x2 ½", HP167 R-801AA jgo 23.42 101.69% 23.03INBAÑ 90136 Toallero 24" cromo, 5724 u 542.72 101.72% 533.52INBAÑ 90137 Toallero 24" cromo, corriente u 198.36 101.72% 195.00INBAÑ 90138 Toallero 24" sencillo Barra Elegance, cromo 8105 C u 3,581.30 101.72% 3,520.60INBAÑ 90139 Toallero 24" sencillo Barra Nuva, cromo 9105 C u 3,847.25 101.72% 3,782.04INBAÑ 90140 Toallero 24" Mult. Barra Elegance, cromo 8124 C u 4,796.70 101.72% 4,715.40INBAÑ 90141 Toallero 8 ½" Nuva, sencillo, cromo 9109_C u 1,622.50 101.72% 1,595.00INBAÑ 90142 Tubo flexible para lavamanos, tuerca, ½"x3/8" 40 cm., EVL-B40 u 144.05 101.72% 141.61INBAÑ 90143 Tubo flexible para inodoro, tuerca, 3/8"x7/8" 50 cm., EVS-B50 u 122.61 101.72% 120.54INBAÑ 90144 Válvula de llenado p/inodoro 200A133 "Fuid Master" u 254.54 101.73% 250.22INBAÑ 90145 Válvula de seg. ¾" p/calentador, bronce u 394.44 101.73% 387.75INBAÑ 90146 Válvula flux. ¾" p/inod. HELVEX 11038 u 4,210.24 101.72% 4,138.88INBAÑ 90147 Válvula flux. ¾" p/orinal, HELVEX 18519 u 4,211.42 101.72% 4,140.04INBAÑ 90148 Válvula flux. ¾" p/orinal, Sensor eléctrico u 22,656.00 101.72% 22,272.00

INBAR 100000 BARRO, PRODUCTOS:INBAR 100001 Bloques de barro 4" u 49.56 101.72% 48.72INBAR 100002 Bloques de barro 6" u 70.80 101.72% 69.60INBAR 100003 Bloques de barro 8" u 94.40 101.72% 92.80INBAR 100004 Caballete triangular oscuro (3.5 unid en 1.00 metro) u 58.13 101.73% 57.14INBAR 100005 Calados corrientes de barro en 6"x6"x6" u 37.02 101.70% 36.40INBAR 100006 Calados corrientes de barro en 8"x8"x6" tipo bandera u 47.20 101.72% 46.40INBAR 100007 Ladrillos macizos 2"x4"x8" (42 unid en 1.00 metro) u 18.88 101.72% 18.56INBAR 100008 Ladrillos biscochos 2"x2"x8" (42 unid en 1.00 metro) u 11.80 101.72% 11.60INBAR 100009 Losa de barro 10"x10" Almendro (16 unid en 1.00 metro) u 43.97 101.71% 43.23INBAR 100010 Losa de barro tipo FERIA grande (28 unid en 1.00 metro) u 10.15 101.70% 9.98INBAR 100011 Losa de barro tipo FERIA pequeña (58 unid en 1.00 metro) u 5.22 101.75% 5.13INBAR 100012 Losa de barro hexagonal grande (23 unid en 1.00 metro) u 12.36 101.73% 12.15INBAR 100013 Losa de barro hexagonal pequeña (50 unid en 1.00 metro) u 5.68 101.61% 5.59INBAR 100014 Teja criolla curva 16" x 7" (28 unid en 1.00 metro) u 14.38 101.70% 14.14INBAR 100015 Teja criolla curva 16" x 7", oscura (28 unid en 1.00 metro) u 18.48 101.71% 18.17INBAR 100016 Teja Francesa plana (ya no la fabrican) u 48.49 101.74% 47.66INBAR 100017 Teja Francesa plana, oscura (ya no la fabrican) u 65.79 101.72% 64.68INBAR 100018 Tejas tipo "S" roja, criolla (12 unid en 1.00 metro) u 33.49 101.73% 32.92INBAR 100019 Zócalos de barro de 25 x 3 cms. u 8.91 101.71% 8.76INBAR 100020 Transp. Mínimo Sto. Dgo. vje 1,051.38 101.72% 1,033.56INBAR 100021 Transp. Teja 16" 5,000 unid Sto. Dgo. vje 6,184.38 101.72% 6,079.56INBAR 100022 Transp. Teja 16" al interior u 4.64 101.75% 4.56

INBLC 110000 BLOQUES DE CEMENTO: (INDUSTRIAS AGUAYO 809 533-3161)INBLC 110001 Bloque 4"x8"x16" liso u 21.37 101.71% 21.01INBLC 110002 Bloque 5"x8"x16" liso u 21.46 101.71% 21.10INBLC 110003 Bloque 6"x8"x 8", liso (½ bloque 6") u 21.24 101.72% 20.88INBLC 110004 Bloque 6"x8"x16" liso u 23.48 101.73% 23.08INBLC 110005 Bloque 6"x8"x16" p/varilla, liso u 33.21 101.75% 32.64INBLC 110006 Bloque 6"x8"x16", texturizado u 33.23 101.71% 32.67INBLC 110007 Bloque 8"x8"x 8", liso (½ bloque 8") u 24.66 101.73% 24.24INBLC 110008 Bloque 8"x8"x16" liso u 31.40 101.72% 30.87INBLC 110009 Bloque 8"x8"x16" p/varilla, liso u 42.08 101.72% 41.37INBLC 110010 Bloque 8"x8"x16", texturizado u 43.88 101.72% 43.14INBLC 110011 Bloque 12"x8"x 8", liso (½ bloque 12") u 76.02 101.73% 74.73INBLC 110012 Bloque 12"x8"x16" liso u 102.84 101.73% 101.09INBLC 110013 Bloque calado 6"x8"x16" tipo persiana u 70.80 101.72% 69.60INBLC 110014 Bloque decorativo 6"x8"x16" gris, 1 ranura u 31.27 101.72% 30.74INBLC 110015 Bloque decorativo 8"x8"x16" gris, 1 ranura u 43.00 101.73% 42.27INBLC 110016 Bloque Dintel 6"x8"x 8" liso, medio bloque u 21.71 101.73% 21.34INBLC 110017 Bloque Dintel 8"x8"x 8" liso, medio bloque u 23.92 101.74% 23.51INBLC 110018 Bloviga 6"x8"x16" u 43.12 101.72% 42.39INBLC 110019 Bloviga 8"x8"x16" u 56.85 101.72% 55.89INBLC 110020 Transp. bloque Dintel 6"x8"x 8", medio bloque, Zona metropol. u 1.66 101.84% 1.63INBLC 110021 Transp. bloque Dintel 8"x8"x 8", medio bloque, Zona metropol. u 1.95 101.56% 1.92INBLC 110022 Transp. Bloque 4"x8"x16", Zona metropolitana u 2.54 101.60% 2.50INBLC 110023 Transp. Bloque 5"x8"x16", Zona metropolitana u 2.66 101.92% 2.61

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 3

Page 4: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012INBLC 110024 Transp. Bloque 6"x8"x 8", liso (½ bloque 6"), Zona metropol. u 1.66 101.84% 1.63INBLC 110025 Transp. Bloque 6"x8"x16", Zona metropolitana u 2.77 101.47% 2.73INBLC 110026 Transp. Bloque 6"x8"x16", texturizado, Zona metropolitana u 2.77 101.47% 2.73INBLC 110027 Transp. Bloque 8"x8"x 8", liso (½ bloque 8"), Zona metropol. u 1.95 101.56% 1.92INBLC 110028 Transp. Bloque 8"x8"x16", Zona metropolitana u 3.07 101.66% 3.02INBLC 110029 Transp. Bloque 8"x8"x16", texturizado, Zona metropolitana u 3.07 101.66% 3.02INBLC 110030 Transp. Bloque 12"x8"x 8", liso (½ bloque 12"), Zona metropol. u 2.91 101.75% 2.86INBLC 110031 Transp. Bloque 12"x8"x16", Zona metropolitana u 5.81 101.75% 5.71INBLC 110032 Transp. Bloque calado 6" tipo persiana, Zona metropolitana u 5.08 101.60% 5.00INBLC 110033 Transp. Bloque decorativo 6"x8"x16", Zona metropolitana u 2.77 101.47% 2.73INBLC 110034 Transp. Bloque decorativo 8"x8"x16", Zona metropolitana u 3.07 101.66% 3.02INBLC 110035 Transp. Bloviga 6"x8"x16", Zona metropolitana u 1.48 101.37% 1.46INBLC 110036 Transp. Bloviga 8"x8"x16", Zona metropolitana u 1.50 101.35% 1.48INBLC 110037 Transporte mínimo por viaje, Zona metropolitana vje 4,065.10 101.72% 3,996.20

INBLV 120000 BLOQUES DE CRISTAL:INBLV 120001 Bloque de Cristal 20 x 20, clear lb 136.82 101.72% 134.50

INBOM 130000 BOMBAS DE AGUA Y TANQUES DE PRESION :INBOM 130001 Bomba ½ HP, "Myers" 110/220 v, HR50S, sin tanque u 9,204.00 101.72% 9,048.00INBOM 130002 Bomba ¾ HP, "Myers" 110/220 v, HJ75S, sin tanque u 10,538.03 101.72% 10,359.41INBOM 130003 Bomba 1 HP, "Myers" 110/220 v, sin tanque u 16,667.50 101.72% 16,385.00INBOM 130004 Bomba 5 HP, "Myers" 230 v 1PH,200M-5FA, sin tanque u 45,843.00 101.72% 45,066.00INBOM 130005 Bomba sumerg. 1 HP, "Myers" 3ST102-20 + caja control u 25,891.23 101.72% 25,452.40INBOM 130006 Bomba sumerg. 1 HP, "Myers" 3ST102-20 sin caja control u 22,481.03 101.72% 22,100.00INBOM 130007 Bomba sumerg. 1 ½ HP, "Myers" 3ST152-20 + caja control u 31,942.39 101.72% 31,401.00INBOM 130008 Bomba sumerg. 1 ½ HP, "Myers" 3ST152-20 sin caja control u 28,431.89 101.72% 27,950.00INBOM 130009 Bomba sumerg. 2 HP, "Myers" J2025B/SS20-25 + caja control u 27,237.16 101.72% 26,775.51INBOM 130010 Bomba sumerg. 2 HP, "Myers" J2025B/SS20-25 sin caja control u 21,823.10 101.72% 21,453.21INBOM 130011 Bomba sumerg. 5 HP, "Myers" J5050B/SS50-50 + caja control u 45,548.94 101.72% 44,776.93INBOM 130012 Bomba sumerg. 5 HP, "Myers" J5050B/SS50-50 sin caja control u 35,843.51 101.72% 35,236.00INBOM 130013 Caja control 1 "Myers" HP SMC-CR1021 u 3,410.20 101.72% 3,352.40INBOM 130014 Caja control 1 1/2 HP "Myers" SMC-CR1521 u 3,510.50 101.72% 3,451.00INBOM 130015 Caja control 2HP M-CJ20-21 u 5,414.06 101.72% 5,322.30INBOM 130016 Caja control 5HP M-CJ50-21 u 9,705.43 101.72% 9,540.93INBOM 130017 Tanque hidr. 42 gls., criollo, fibra, Economax u 5,564.09 101.72% 5,469.78INBOM 130018 Tanque hidr. 42 gls., USA, "Well-x-Troll" "WX-202P" u 8,037.00 101.72% 7,900.78INBOM 130019 Tanque hidr. 82 gls., criollo, fibra, Economax u 9,273.48 101.72% 9,116.30INBOM 130020 Tanque hidr. 82 gls., USA, "Well-x-Troll" "WX-203P" u 13,452.77 101.72% 13,224.75INBOM 130021 Tanque hidr. 120 gls., criollo, fibra, Economax u 13,106.50 101.72% 12,884.35INBOM 130022 Tanque hidr. 120 gls., USA, "Well-x-Troll" "WX-250P" u 11,800.00 101.72% 11,600.00INBOM 130023 Tanque hidr. 180 gls., USA, "Well-x-Troll" "WX-302P" u 17,110.00 101.72% 16,820.00

INBOV 140000 BOVEDILLAS DE "FOAM":INBOV 140001 Bovedilla de .40 x 1.00 x .15 m., macizas, "EHI" m 225.33 101.72% 221.51INBOV 140002 Transporte bovedillas macizas .40 x .15, "EHI" % 4.00% 100.00% 4.00%

INCEM 150000 CEMENTOS, CAL, ADITIVOS, CURADORES, ENDURECEDORES, SELLADORES:INCEM 150001 Aditivo impermeabilizante "SX-PEL", 5 gl. gl 336.30 101.72% 330.60INCEM 150002 Aditivo retardante "SX-KRETE-R", 5 gl. gl 336.30 101.72% 330.60INCEM 150003 Cal Hidratada 20 Kilos, "Perla" fda 283.20 101.72% 278.40INCEM 150004 Cemento Bco. 40 kilos, "Cisne" fda 649.00 101.72% 638.00INCEM 150005 Cemento Gris 94 lb. "Portland" gris fda 320.43 101.72% 315.00INCEM 150006 Curador-sellador "SUPRACURE PLUS", 5 gl., 20 m2/gl. gl 979.40 101.72% 962.80INCEM 150007 Endur. Met. / pisos "DURAPLATE NR", 100 lb., .10 m2/lb., Fda.=55 lb. fda 4,602.00 101.72% 4,524.00INCEM 150008 Mortero "Aguayo" para bloques, 94 lb., 13-15 Unid., 1 Cm. Esp. fda 172.81 101.72% 169.88INCEM 150009 Mortero "Aguayo" para empañete, 94 lb., 1.90 m2 en 1 Cm. Esp. fda 190.50 101.72% 187.27INCEM 150010 Resina epóxica "Pro-flex" para junta de piso, 231 pulg.3/gl. 3 gl 3,676.88 101.72% 3,614.56INCEM 150011 Sellador hormigón visto "SUPRACURE PX", 5gl., 20 m2/gl. gl 784.70 101.72% 771.40

INCER 160000 CERAMICAS:INCER 160001 Cenefa pared baño 04x20 Bco. u 170.60 101.72% 167.71INCER 160002 Cenefa pared baño 06x20 Gris u 16.63 101.71% 16.35INCER 160003 Cenefa pared baño 06x31 Azul u 195.32 101.72% 192.01INCER 160004 Cenefa pared baño 07x27 Bco. u 248.98 101.72% 244.76INCER 160005 Cenefa pared baño 08x20 Crema u 37.35 101.74% 36.71INCER 160006 Cenefa pared baño 08x20, serie Trama u 150.04 101.73% 147.49INCER 160007 Cenefa pared baño 08x25 AC1325 u 31.12 101.70% 30.60INCER 160008 Cenefa pared baño 08x33 Beige u 68.47 101.72% 67.31INCER 160009 Cenefa pared baño 08x33 Beige con marrón u 62.25 101.73% 61.19INCER 160010 Cenefa pared baño 08x33 Rústico u 68.47 101.72% 67.31INCER 160011 Cenefa pared cocina 07.5x25 Dinora u 109.46 101.72% 107.61INCER 160012 Cenefa pared cocina 08x25 25F4BW u 31.12 101.70% 30.60INCER 160013 Cenefa pared cocina 10x33 Agato Bco. mate u 143.81 101.73% 141.37INCER 160014 Cerámica criolla tipo 01 m2 378.87 101.72% 372.45INCER 160015 Cerámica criolla tipo 02 m2 410.44 101.72% 403.49INCER 160016 Cerámica criolla tipo 03 m2 442.03 101.73% 434.53INCER 160017 Cerámica criolla tipo 04 m2 505.17 101.72% 496.61INCER 160018 Cerámica criolla tipo 05 m2 631.46 101.72% 620.76INCER 160019 Cerámica importada tipo 06 m2 694.60 101.72% 682.83INCER 160020 Cerámica importada tipo 07 m2 820.90 101.72% 806.99INCER 160021 Cerámica importada tipo 08 m2 947.18 101.72% 931.13INCER 160022 Cerámica importada tipo 09 m2 1,073.48 101.72% 1,055.28INCER 160023 Cerámica importada tipo 10 m2 1,168.20 101.72% 1,148.40INCER 160024 Cerámica importada tipo 11 m2 1,262.91 101.72% 1,241.51INCER 160025 Cerámica importada tipo 12 m2 1,389.21 101.72% 1,365.66INCER 160026 Corte de chazos de cerámica u 7.57 101.75% 7.44INCER 160027 Derretido p/ceram. s/arena, bco. 25 lb. (rinde 25 m2/fda.) fda 363.56 101.72% 357.40INCER 160028 Estopa (hilacha indust.) lb 68.44 101.72% 67.28INCER 160029 Listelo 8x20, import., serie Trama u 138.92 101.73% 136.56INCER 160030 Pegamento K18 (rinde 6.5 m2/fda.) fda 536.74 101.72% 527.64INCER 160031 Perfil esquinero PVC, 2.5 m. u 189.44 101.72% 186.23INCER 160032 Porcelanato 30x30 Otawa Rosa u 70.19 101.72% 69.00INCER 160033 Porcelanato 30x30 Otawa Verde u 72.23 101.73% 71.00

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 4

Page 5: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012INCER 160034 Zócalo cerámica 8x34, import. u 63.15 101.72% 62.08

INCEJ 170000 CERRAJERIA:INCEJ 170001 Arandela plana ½" lb 97.94 101.72% 96.28INCEJ 170002 Bisagra recta, cromo 6877 4710 u 73.16 101.72% 71.92INCEJ 170003 Bisagras ''Stanley'' 2 ½''x2 ½'', tipo libro, doradas par 84.96 101.72% 83.52INCEJ 170004 Bisagras ''Stanley'' 3''x3'', tipo libro, doradas par 88.50 101.72% 87.00INCEJ 170005 Bisagras "Stanley" 3 ½"x3 ½", tipo libro, doradas 82-100 par 102.66 101.72% 100.92INCEJ 170006 Bisagras ''Stanley'' 4''x4'', tipo libro, doradas par 123.90 101.72% 121.80INCEJ 170007 Bisagra "Vaivén" de piso, Spartan (Sin Invent.) u 742.59 101.72% 730.00INCEJ 170008 Cable de acero 3/8" (10 mm) con forro, 7x19 pie 29.50 101.72% 29.00INCEJ 170009 Cadena galv. 5/16" (8mm) pie 47.20 101.72% 46.40INCEJ 170010 Candado 50 mm "Corbin". u 601.80 101.72% 591.60INCEJ 170011 Cerrojo doble, Acero Inox., "Stanley" 38391-AC u 696.20 101.72% 684.40INCEJ 170012 Falleba 3500-150 Latón u 409.46 101.72% 402.52INCEJ 170013 Falleba 3700-200 Latón u 867.30 101.72% 852.60INCEJ 170014 Hoja de segueta Roja "Nich." 18T/12" NF-1218 u 39.65 101.72% 38.98INCEJ 170015 Llavín corriente, doble puño, llave y seguro, "Yale" u 660.80 101.72% 649.60INCEJ 170016 Llavín de calidad, doble puño, llave y seguro, ref. 640, "Weslock" CLS-NS u 1,770.00 101.72% 1,740.00INCEJ 170017 Llavín de seguridad "Yale" Der c/f 63000401 (630.40) u 1,410.10 101.72% 1,386.20INCEJ 170018 Pestillo 60 MM corriente Bicromado 384-60 u 47.20 101.72% 46.40INCEJ 170019 Pestillo de cadena st. 4" 75-7030 u 424.80 101.72% 417.60INCEJ 170020 Portacandado 4" corriente u 56.64 101.72% 55.68INCEJ 170021 Tarugo de plomo 5/16" x 1 3/4" u 9.20 101.66% 9.05INCEJ 170022 Tarugos plásticos 1/4"x1", verde u 0.68 101.49% 0.67INCEJ 170023 Tarugos plásticos 3/8"x2 ½", mamey u 2.01 102.03% 1.97INCEJ 170024 Tensor zincado anilla-anilla TAA110 u 94.40 101.72% 92.80INCEJ 170025 Tornillos 3"x16, Estría R/M 40207 u 12.98 101.72% 12.76INCEJ 170026 Tornillos 3"x3/8" electro galv. cabeza hexagonal u 11.80 101.72% 11.60INCEJ 170027 Tornillo cabeza exag. ½"x4" u 25.96 101.72% 25.52INCEJ 170028 Tornillo de ojo 3/8"x4", c/tuerca u 26.02 101.72% 25.58INCEJ 170029 Tornillo tirafondo 1 ½"x14, estriado u 3.25 101.88% 3.19

INCOM 180000 COMBUSTIBLES Y LUBRICANTES:INCOM 180001 Gasoil Premium gl 210.30 100.48% 209.30INCOM 180002 Gasoil regular gl 203.60 100.49% 202.60INCOM 180003 Gasolina Premium gl 233.10 100.87% 231.10INCOM 180004 Gasolina regular gl 216.00 100.93% 214.00INCOM 180005 Lubricantes Aceite Citgo Supergard Sae 40, 1/4 gl. 1/4 gl 213.62 101.73% 209.99

INDIV 190000 DIVISAS:INDIV 190001 EURO$1.00 comprado en el mercado local $ 52.85 97.96% 53.95INDIV 190002 US$1.00 comprado en el mercado local $ 39.95 99.25% 40.25

INEBA 200000 EBANISTERIA:INEBA 200001 Barra p/armario, zinc St. 18"-30" 93-008 (Sin inst.) u 236.00 101.72% 232.00INEBA 200002 Barra p/armario, zinc St. 30"-48" 93-028 (Sin inst.) u 277.30 101.72% 272.60INEBA 200003 Barra p/armario, zinc St. 48"-72" 19-3038 (Sin inst.) u 324.50 101.72% 319.00INEBA 200004 Barra p/armario, zinc St. 72"-96" 93-05 (Sin inst.) u 519.20 101.72% 510.40INEBA 200005 Clavos de acero 1½", caja con 100 unidades lb 53.10 101.72% 52.20INEBA 200006 Cola amarilla "Lanco" WA-505-A gl 543.21 101.72% 534.01INEBA 200007 Cortar y preparar media caña 1"x1", hasta 0.50 m2 por tramo u 46.02 101.72% 45.24INEBA 200008 Cortar y preparar tramos p/closets, hasta 0.50 m2 por tramo u 46.02 101.72% 45.24INEBA 200009 Gabinete pared Caoba, 2 pie de alto, ¾" (Todo Costo) p 2,897.61 101.72% 2,848.50INEBA 200010 Gabinete pared Caoba y "Plywood", 2 pie de alto, ¾" (Todo Costo) p 1,888.81 101.72% 1,856.80INEBA 200011 Gabinete pared Pino (Todo Costo) p 1,126.85 101.72% 1,107.75INEBA 200012 Gabinete pared Pino y "Plywood" (Todo Costo) p 939.04 101.72% 923.13INEBA 200013 Gabinete piso Caoba (Todo Costo) p 3,155.18 101.72% 3,101.70INEBA 200014 Gabinete piso Caoba y "Plywood" (Todo Costo) p 2,081.99 101.72% 2,046.70INEBA 200015 Gabinete piso Pino (Todo Costo) p 1,384.41 101.72% 1,360.95INEBA 200016 Gabinete piso Pino y "Plywood" (Todo Costo) p 1,126.85 101.72% 1,107.75INEBA 200017 Instalar tramos de closets, hasta 0.50 m2 por tramo u 155.76 101.72% 153.12INEBA 200018 Marco en caoba 1 ½"x4" (Hechura) p 145.95 101.72% 143.48INEBA 200019 Marco en pino 1 ½"x4" (Hechura) p 47.22 101.72% 46.42INEBA 200020 Pintar con sellador tramos closets, hasta 0.50 m2 por tramo u 123.90 101.72% 121.80INEBA 200021 Puerta Caoba panelada especial (Hechura) p2 617.08 101.72% 606.63INEBA 200022 Puerta Caoba panelada sencilla (Hechura) p2 566.64 101.72% 557.04INEBA 200023 Puerta Caoba tipo francesa (Hechura) p2 590.25 101.72% 580.25INEBA 200024 Puerta "Plywood" 3/16" (Hechura) p2 91.23 101.73% 89.68INEBA 200025 Puerta Pino panelada (Hechura) p2 165.27 101.72% 162.47INEBA 200026 Puerta Pino y marco, hueco .80 X 2.10 m., 2 paneles (medida fija) (Hechura) u 2,387.85 101.72% 2,347.38INEBA 200027 Puerta Pino y marco, hueco .80x2.10 m., 4-6 paneles (medida fija) (Hechura) u 2,833.22 101.72% 2,785.20INEBA 200028 Puerta Plegable sin marco, color caoba o bco., hueco .865x2.03 m., cristales (Hechura) u 2,962.00 101.72% 2,911.80INEBA 200029 Tope marmolite, Sánchez 547-8920 (Todo Costo) Cel. 330-3872 p2 248.98 101.72% 244.76INEBA 200030 Transporte mínimo en camioneta desde taller a obra u 708.00 101.72% 696.00

INELL 210000 ELECTRICIDAD (LAMPARAS Y GLOBOS):INELL 210001 Globo 6", cristal 50/927 (Solo el globo) u 303.14 101.72% 298.00INELL 210002 Base con globo, blanca, 3606 u 263.56 101.72% 259.10INELL 210003 Lámpara empotrar 4" diam. J5T-403C, Rosca normal u 466.10 101.72% 458.20INELL 210004 Lámpara empotrar 6" diam. C/V J5L-603P, Rosca normal u 560.50 101.72% 551.00INELL 210005 Lámpara flluor. 2'x2', p/plafón, dif. Parabólico, sin tubos 1047159 u 3,680.42 101.72% 3,618.04INELL 210006 Lámpara flluor. 2'x4', p/plafón, dif. Parabólico, sin tubos u 3,585.78 101.72% 3,525.01INELL 210007 Lámpara flluor. 2'x4', p/plafón, sin tubos u 2,986.58 101.72% 2,935.96INELL 210008 Lámpara fluor. 2x32 w., superficie, difusor transparente, "Stanca" u 2,183.00 101.72% 2,146.00INELL 210009 Lámpara p/gab. T5 21W 65k "Faca" u 365.30 101.72% 359.11INELL 210010 Ojos de buey 11 w. 6000 hr., bajo consumo, alum., plafón u 375.95 101.72% 369.58INELL 210011 Tubo fluor 4', 32 w., 2 patas u 70.80 101.72% 69.60

INELR 220000 ELECTRICIDAD RESIDENCIAL:INELR 220001 Abrazadera ¾" h.g. para pvc u 7.08 101.72% 6.96INELR 220002 Abrazadera 1" h.g. para pvc u 8.26 101.72% 8.12INELR 220003 Abrazadera 1½" EMT u 15.99 101.72% 15.72INELR 220004 Abrazadera 2" h.g. para pvc u 17.79 101.72% 17.49

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 5

Page 6: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012INELR 220005 Abrazadera 3" h.g. para pvc u 72.12 101.72% 70.90INELR 220006 Alambre THHW-/THHN # 1/0, Str. p 134.44 101.73% 132.16INELR 220007 Alambre THHW-/THHN # 2/0, Str. p 160.98 101.73% 158.25INELR 220008 Alambre THHW-/THHN # 3/0, Str. p 206.38 101.73% 202.88INELR 220009 Alambre THHW-/THHN # 4/0, Str. p 252.33 101.73% 248.05INELR 220010 Alambre THHW-/THHN # 2, Str. p 91.28 101.72% 89.74INELR 220011 Alambre THHW-/THHN # 4, Str. p 54.41 101.72% 53.49INELR 220012 Alambre THHW-/THHN # 6, Str. p 34.40 101.75% 33.81INELR 220013 Alambre THHW-/THHN # 8, Str. p 25.20 101.69% 24.78INELR 220014 Alambre THHW-/THHN #10, Str., bco. p 12.43 101.80% 12.21INELR 220015 Alambre THHW-/THHN #12, Str., bco. p 7.87 101.68% 7.74INELR 220016 Alambre THHW-/THHN #14, Str. p 5.32 101.72% 5.23INELR 220017 Alambre duplo #18, Str. p 5.43 101.69% 5.34INELR 220018 Bombillo 23 w. bajo consumo MS/2350 u 219.48 101.72% 215.76INELR 220019 Botón timbre "Bticino" u 169.52 101.73% 166.64INELR 220020 Breakers 15 - 30 amp, 1 ph , GE u 152.22 101.72% 149.64INELR 220021 Breakers 40 amp, 2ph, doble, GE u 483.93 101.72% 475.73INELR 220022 Breakers 60 amp, 2ph, doble, GE u 600.97 101.72% 590.79INELR 220023 Caja octagonal de ½-¾", americana u 38.33 101.73% 37.68INELR 220024 Caja metal 2"x4" de ½", americana u 32.67 101.71% 32.12INELR 220025 Caja metal 2"x4" de ¾", americana u 36.05 101.72% 35.44INELR 220026 Caja metal 4"x4" de ½-¾", americana u 47.20 101.72% 46.40INELR 220027 Cinta de peligro, rollo 3"x1000' u 702.10 101.72% 690.20INELR 220028 Codo pvc eléct. ½" x 90º u 5.88 101.73% 5.78INELR 220029 Codo pvc eléct. ¾" x 90º u 6.68 101.67% 6.57INELR 220030 Codo pvc eléct. 1" x 90º u 11.48 101.68% 11.29INELR 220031 Codo pvc eléct. 1 ½" x 90º u 34.18 101.70% 33.61INELR 220032 Codo pvc eléct. 2" x 90º u 33.45 101.70% 32.89INELR 220033 Codo pvc eléct. 3" x 90º u 134.58 101.72% 132.30INELR 220034 Codo pvc eléct. 4" x 90º u 213.73 101.72% 210.11INELR 220035 Condulet EMT ½" TOPAZ u 71.52 101.72% 70.31INELR 220036 Condulet EMT ¾" TOPAZ u 105.32 101.73% 103.53INELR 220037 Condulet EMT 1" TOPAZ u 118.00 101.72% 116.00INELR 220038 Condulet EMT 1½" TOPAZ u 229.29 101.73% 225.40INELR 220039 Condulet EMT 2" TOPAZ u 302.43 101.72% 297.31INELR 220040 Condulet EMT 3" TOPAZ u 1,498.09 101.72% 1,472.70INELR 220041 Condulet EMT 4" TOPAZ u 2,145.24 101.72% 2,108.88INELR 220042 Conector EMT ½" TOPAZ u 8.60 101.65% 8.46INELR 220043 Conector EMT ¾" TOPAZ u 14.62 101.74% 14.37INELR 220044 Conector EMT 1" TOPAZ u 20.64 101.72% 20.29INELR 220045 Conector EMT 1 ½" TOPAZ u 53.25 101.72% 52.35INELR 220046 Conector EMT 2" TOPAZ u 76.25 101.72% 74.96INELR 220047 Conector EMT 3" TOPAZ u 135.84 101.72% 133.54INELR 220048 Conector LT RECTO ½" TOPAZ u 30.80 101.72% 30.28INELR 220049 Conector LT RECTO ¾" TOPAZ u 60.62 101.73% 59.59INELR 220050 Conector LT RECTO 1" TOPAZ u 76.62 101.73% 75.32INELR 220051 Conector LT RECTO 1 ½" TOPAZ u 157.16 101.72% 154.50INELR 220052 Conector LT RECTO 2" TOPAZ u 187.17 101.72% 184.00INELR 220053 Conector LT RECTO 3" TOPAZ u 829.25 101.72% 815.19INELR 220054 Conector PIN P/Term. #2 PSS-12- 6 ½ u 607.09 101.72% 596.80INELR 220055 Coupling EMT ½" TOPAZ u 10.31 101.68% 10.14INELR 220056 Coupling EMT ¾" TOPAZ u 12.63 101.77% 12.41INELR 220057 Coupling EMT 1" TOPAZ u 24.95 101.75% 24.52INELR 220058 Coupling EMT 1 ½" TOPAZ u 62.39 101.73% 61.33INELR 220059 Coupling EMT 2" TOPAZ u 77.23 101.73% 75.92INELR 220060 Coupling EMT 3" TOPAZ u 247.14 101.72% 242.95INELR 220061 Coupling IMC 3" u 495.60 101.72% 487.20INELR 220062 Curva EMT ½" u 18.17 101.74% 17.86INELR 220063 Curva EMT ¾" u 31.27 101.72% 30.74INELR 220064 Curva EMT 1" u 65.42 101.73% 64.31INELR 220065 Curva EMT 1 ½" u 139.24 101.72% 136.88INELR 220066 Curva EMT 2" u 239.68 101.72% 235.62INELR 220067 Curva EMT 3" 799.57 101.72% 786.02INELR 220068 Conector 5/8" para varilla de tierra u 76.70 101.72% 75.40INELR 220069 Interruptor 1 sencillo, sin tapa, "Leviton" 1451-ICP u 47.68 101.71% 46.88INELR 220070 Interruptor 2 doble, sin tapa, "Leviton" u 163.69 101.72% 160.92INELR 220071 Interruptor 2 doble, sin tapa, "Bticino", Modus 1200MM u 84.35 101.72% 82.92INELR 220072 Interruptor 3 triple, sin tapa, "Bticino", Modus plus 1313MM u 184.08 101.72% 180.96INELR 220073 Interruptor 3 vías, sencillo "Bticino", Modus plus 1101MAB u 85.22 101.72% 83.78INELR 220074 Interruptor 4 vías, sencillo sin tapa, "Leviton" 1204-2w u 438.42 101.72% 430.99INELR 220075 Interruptor piloto crema, sin tapa, "Leviton" 5226-I u 220.21 101.72% 216.48INELR 220076 Interruptor seg. 30 a, 2 polos, 250 v., GE u 1,359.17 101.72% 1,336.13INELR 220077 Interruptor seg. 30 a, 3 polos, 250 v., GE u 2,178.76 101.72% 2,141.84INELR 220078 Interruptor seg. 60 a, 2 polos, 250 v., GE u 2,383.66 101.72% 2,343.26INELR 220079 Interruptor seg. 100 a, 2 polos 250 v., GE u 5,033.37 101.72% 4,948.06INELR 220080 Panel 1 contador ELECTRO, "breakers" 60 amp., 2 ph. u 2,828.81 101.72% 2,780.87INELR 220081 Panel 1 contador ELECTRO, "breakers" 100 amp., 2 ph. u 421.76 101.72% 414.61INELR 220082 Panel distrib. 1 ph, 2 a 4 ctos., 40 amp. GE u 489.70 101.72% 481.40INELR 220083 Panel distrib. 1 ph, 4 a 8 ctos., 125 amp. GE u 820.10 101.72% 806.20INELR 220084 Panel distrib. 1 ph, 6 a 12 ctos., 125 amp. GE u 1,232.81 101.72% 1,211.91INELR 220085 Panel distrib. 1 ph, 8 a 16 ctos., 125 amp. GE u 2,188.90 101.72% 2,151.80INELR 220086 Panel distrib. 1 ph, 12 a 24 ctos., 125 amp. GE u 2,188.90 101.72% 2,151.80INELR 220085 Panel distrib. 3 ph, 12 espacios, 150 amp. GE u 3,723.03 101.72% 3,659.93INELR 220086 Panel distrib. 3 ph, 24 espacios, 150 amp. GE u 5,642.87 101.72% 5,547.22INELR 220087 Panel distrib. 3 ph, 30 espacios, 200 amp. GE u 6,464.95 101.72% 6,355.37INELR 220088 Portero electrónico "Bticino" (Kit video de 2 piezas) u 20,104.08 101.72% 19,763.33INELR 220089 Registro 4"x4", ko ½" - ¾", galv. USA u 55.81 101.71% 54.87INELR 220090 Registro 5"x5", ko 1 ¼", galv. USA u 74.69 101.72% 73.43INELR 220091 Registro 6"x6"x4", galv. criollo u 132.16 101.72% 129.92INELR 220092 Registro 8"x8"x4", galv. criollo u 495.60 101.72% 487.20INELR 220093 Registro 10"x10"x4", galv. criollo u 330.40 101.72% 324.80INELR 220094 Registro 12"x12"x4", galv. criollo u 611.24 101.72% 600.88INELR 220095 Registro 24"x24"x4", galv. criollo p 1,938.74 101.72% 1,905.88INELR 220096 Registro 24"x24"x6", galv. criollo p 2,890.38 101.72% 2,841.39

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 6

Page 7: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012INELR 220097 Roseta "Leviton" 9875, porcelana americana u 51.92 101.72% 51.04INELR 220098 Sistema Intercom vía telefónica, micro cámara 1/4" "Quaddrix" u 74,076.29 101.72% 72,820.76INELR 220099 Tapa 2"x4" ciega ko ½", metálica. u 16.11 101.77% 15.83INELR 220100 Tapa 2"x4" ciega o para interruptor, crema "Leviton" PVC. u 23.60 101.72% 23.20INELR 220101 Tapa 2"x4" ciega o para tomacorriente, crema "Leviton" PVC. u 18.88 101.72% 18.56INELR 220102 Tapa 2"x4" para tomacorriente, metálica. u 16.11 101.77% 15.83INELR 220103 Tape vinyl ''3M'', No. 23, ¾" u 607.70 101.72% 597.40INELR 220104 Tape vinyl "3M", súper 33T u 209.39 101.72% 205.84INELR 220105 Tarugo plástico ¼" x 1 ½" u 0.96 102.13% 0.94INELR 220106 Timbre "Bticino" 73Z, "Din-Don" u 671.42 101.72% 660.04INELR 220107 Timbre corriente, tipo chicharra u 491.33 101.72% 483.00INELR 220108 Tomacorriente doble, 110 v., 15 A., de piso u 887.12 101.72% 872.09INELR 220109 Tomacorriente doble, 110 v., 15 A. "Leviton" 5320-ICP u 36.34 101.71% 35.73INELR 220110 Tomacorriente sencillo, 220 v., 15 A., "Leviton" 5029-I u 96.56 101.73% 94.92INELR 220111 Varilla de puesta a tierra, 5/8" x 6' sin Conector u 319.05 101.72% 313.64

INELA 230000 ELECTRICIDAD INDUSTRIAL:INELA 230001 Alambre URD No. 02, 33% neutro, concéntrico p 184.08 101.72% 180.96INELA 230002 Breakers 2/p. 60 a., grueso, GE 1/5 u 542.06 101.72% 532.87INELA 230003 Breakers 3/p. 30 a., GE u 2,229.19 101.72% 2,191.40INELA 230004 Breakers 3/p. 100 a., GE 1/3 u 2,796.60 101.72% 2,749.20INELA 230005 Breakers Industrial 2 ph 100 amp., 240 v., GE, 1/1 u 2,412.20 101.72% 2,371.32INELA 230006 Breakers Industrial 3 ph 100 amp., 240 v., GE, 1/1 u 4,031.33 101.72% 3,963.00INELA 230007 Breakers Industrial 3 ph 500 amp., 240 v., GE, 1/1 u 30,986.04 101.72% 30,460.86INELA 230008 Codo 3/4" galv. Topaz u 48.55 101.74% 47.72INELA 230009 Codo 2" galv. SL u 394.83 101.72% 388.14INELA 230010 Codo 3" IMC galv. 1/1 u 1,829.00 101.72% 1,798.00INELA 230011 Codo 4" IMC galv. 1/1 u 3,448.37 101.72% 3,389.93INELA 230012 Cono de alivio exterior #2 u 2,869.76 101.72% 2,821.12INELA 230013 Conector empalme #2, Topaz (Split B 1/25) u 74.41 101.72% 73.15INELA 230014 Conector empalme #3/0 Topaz 1/25 u 199.03 101.72% 195.66INELA 230015 Conector empalme #4, Topaz (Split 1/25) u 51.06 101.73% 50.19INELA 230016 Conector p/empalme #6 Mattburgs u 28.77 101.73% 28.28INELA 230017 Conector p/empalme #8 1/100 u 31.28 101.72% 30.75INELA 230018 Conector URD #2, T/codo 90r 1/1 u 2,017.63 101.72% 1,983.44INELA 230019 Coupling IMC 1/2", galv. u 9.99 101.63% 9.83INELA 230020 Coupling IMC 3/4", galv. u 15.97 101.78% 15.69INELA 230021 Coupling IMC 1", galv. u 20.61 101.68% 20.27INELA 230022 Coupling IMC 1 1/2", galv. u 51.92 101.72% 51.04INELA 230023 Coupling IMC 2", galv. u 70.56 101.72% 69.37INELA 230024 Coupling IMC 3", galv. u 253.70 101.72% 249.40INELA 230025 Coupling IMC 4", galv. u 488.17 101.73% 479.89INELA 230026 Cut Out 200 a., 15 kv ABB 1/1 u 5,022.29 101.72% 4,937.17INELA 230027 Elbow Conector #02 (Elast./Hub.) u 2,211.32 101.72% 2,173.84INELA 230028 Eliminar Espiga p/Terminación #2, 10' Ext. 1/5 u 1,048.90 101.72% 1,031.12INELA 230029 Fusible tipo cartucho, 8 amp., 1/25 u 80.72 101.71% 79.36INELA 230030 Grúa, alquiler hr 4,720.00 101.72% 4,640.00INELA 230031 Módulo contador, 22 zóc., 500/3 a.,208 v., 1 zóc. 100/3, 21 zóc. 100/2 u 150,131.40 101.72% 147,586.80INELA 230032 Pararrayo polimérico 9 KV HUBBELL u 1,917.85 101.72% 1,885.35INELA 230033 Piezas p/soporte estructura mediana tensión u 2,353.98 101.72% 2,314.08INELA 230034 Soporte simple unidad Cutout/Pararrayo CL u 728.58 101.72% 716.23INELA 230035 Transformador 150 kva, Pad Mounted, 7200, 120/204/240 v. u 346,920.00 101.72% 341,040.00INELA 230036 Transformador 225 kva, Pad Mounted, 7200, 120/204/240 v. u 421,260.00 101.72% 414,120.00INELA 230037 Tubería BX 1/2"x10' Topaz p 16.51 101.73% 16.23INELA 230038 Tubería BX 3/4"x10' Topaz p 18.51 101.70% 18.20INELA 230039 Tubería BX 1"x10' Topaz p 34.48 101.71% 33.90INELA 230040 Tubería BX 1 1/2"x10' Topaz p 70.69 101.71% 69.50INELA 230041 Tubería BX 2"x10' Topaz p 94.53 101.72% 92.93INELA 230042 Tubería BX 3"x10' Topaz p 194.04 101.72% 190.75INELA 230043 Tubería BX 4"x10' Topaz u 242.97 101.72% 238.86INELA 230044 Tubo EMT 1/2"x10' u 100.71 101.72% 99.01INELA 230045 Tubo EMT 3/4"x10' u 159.30 101.72% 156.60INELA 230046 Tubo EMT 1"x10' u 265.55 101.72% 261.05INELA 230047 Tubo EMT 1 1/2"x10' u 491.26 101.72% 482.93INELA 230048 Tubo EMT 2"x10' u 761.41 101.72% 748.50INELA 230049 Tubo EMT 3"x10' u 1,204.61 101.72% 1,184.20INELA 230050 Tubería Liquid Tight 1/2" p 26.60 101.72% 26.15INELA 230051 Tubería Liquid Tight 3/4" p 22.80 101.74% 22.41INELA 230052 Tubería Liquid Tight 1" p 35.40 101.72% 34.80INELA 230053 Tubería Liquid Tight 1 1/2" p 64.90 101.72% 63.80INELA 230054 Tubería Liquid Tight 2" p 84.37 101.72% 82.94INELA 230055 Tubería Liquid Tight 3" p 419.47 101.72% 412.36INELA 230056 Tubería Liquid Tight 4" p 554.00 101.72% 544.61INELA 230057 Tubo Galv. IMC 1/2"x10' u 346.13 101.73% 340.26INELA 230058 Tubo Galv. IMC 3/4"x10' u 501.72 101.72% 493.22INELA 230059 Tubo Galv. IMC 1"x10' u 715.19 101.73% 703.06INELA 230060 Tubo Galv. IMC 1 1/2"x10' u 1,155.50 101.72% 1,135.92INELA 230061 Tubo Galv. IMC 2"x10' uINELA 230062 Tubo Galv. IMC 3"x10' u 3,347.01 101.72% 3,290.28INELA 230063 Tubo Galv. IMC 4"x10' u 6,437.07 101.72% 6,327.96

INESC 240000 ESCALONES Y MESETAS GRANITO: Israel Thomas 809 229-4442INESC 240001 H., C. H., 2 y 3, fondo bco., 0.34x1.10 m. + 0.17x1.10 m. + Transp. u 1,000.64 101.72% 983.68INESC 240002 H., C. H., Granimármol, 0.34x1.10 m. + 0.17x1.10 m. + Transp. u 1,000.64 101.72% 983.68INESC 240003 H., C. H., Mármol aglomerado, Perlatto Royal, 0.34x1.10 m. + 0.17x1.10 m. + Transp. u 1,125.72 101.72% 1,106.64INESC 240004 Huella y C. H. super chapa, fondo bco. + Transp. m 1,876.20 101.72% 1,844.40INESC 240005 Meseta, 2 y 3, fondo bco. + Transp. m2 2,251.44 101.72% 2,213.28INESC 240006 Meseta Granito super chapa, fondo bco. + Transp. m2 1,876.20 101.72% 1,844.40INESC 240007 Transporte lavadero doble (12 unid. Mínimo) u 118.00 101.72% 116.00INESC 240008 Transporte lavadero sencillo (20 unid. Mínimo) u 88.50 101.72% 87.00INESC 240009 Transporte por viaje vje 1,298.00 101.72% 1,276.00INESC 240010 Transporte Vertedero (20 unid. Mínimo) u 88.50 101.72% 87.00INESC 240011 Zócalo escalón, 2 y 3, bco. + Transp. p 200.13 101.72% 196.74INESC 240012 Zócalo escalón, Súper Chapa + Transp. p 218.89 101.72% 215.18

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 7

Page 8: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012

INEST 250000 ESTRUCTURA METALICA Y PUERTA ENROLLABLE:INEST 250001 Bajantes pluviales en aluzinc m 754.02 101.72% 741.24INEST 250002 Caballete p/aluzinc 8'x14" m2 270.69 101.72% 266.10INEST 250003 Caballete p/aluzinc 8'x21" m2 378.90 101.72% 372.48INEST 250004 Caballete p/aluzinc 8'x24" m2 474.71 101.72% 466.67INEST 250005 Correa metálica 2"x6"x1/16" galv. m2 1,104.01 101.72% 1,085.30INEST 250006 Correa metálica 3"x8"x1/16" galv. m2 1,282.19 101.72% 1,260.46INEST 250007 Colectores pluviales en aluzinc m 892.32 101.72% 877.19INEST 250008 Cubierta "Aluzinc", calibre 26 (m2) m2 2,008.36 101.72% 1,974.32INEST 250009 Cubierta "Aluzinc", calibre 26 (pie2) p2 196.00 101.72% 192.68INEST 250010 Estruct. (col., vigas, correas 3"x8", cub.) 15 x 24 m., Alto=7.65m Pend.=15% Area Cub. 374.40 m2 m2 13,568.68 101.72% 13,338.70INEST 250011 Planchas traslúcidas de 11 pies u 4,439.49 101.72% 4,364.24INEST 250012 Puerta Enrollable (hueco: 3.00 ancho x 2.70 m. alto = 8.10 m2) m2 8,151.76 101.72% 8,013.59INEST 250013 Ventilador eólico 18" galv. (turbina circular) u 11,741.00 101.72% 11,542.00

INHER 260000 HERRERIA:INHER 260001 Angular ½"x1/8"x20' u 1,399.70 101.72% 1,375.97INHER 260002 Angular ½"x3/16"x20' u 2,048.27 101.72% 2,013.55INHER 260003 Angular ¾"x1/8"x20' u 324.50 101.72% 319.00INHER 260004 Angular ¾"x3/16"x20' u 2,046.39 101.72% 2,011.71INHER 260005 Angular 1"x1/8"x20' u 460.20 101.72% 452.40INHER 260006 Angular 1"x¼"x20' u 1,430.16 101.72% 1,405.92INHER 260007 Angular 1 ½"x¼"x20' u 1,362.90 101.72% 1,339.80INHER 260008 Angular 2"x¼"x20' u 2,013.08 101.72% 1,978.96INHER 260009 Angular 2 ½"x¼"x20' u 2,198.34 101.72% 2,161.08INHER 260010 Angular 3"x¼"x20' u 2,973.60 101.72% 2,923.20INHER 260011 Barras cuadradas ½"x20' u 472.00 101.72% 464.00INHER 260012 Barras cuadradas 5/8"x20' u 737.50 101.72% 725.00INHER 260013 Barras cuadradas ¾"x20' u 1,056.10 101.72% 1,038.20INHER 260014 Barrote forjado 11 ½"x39", P-1417 (Sin Invent.) u 1,579.27 101.72% 1,552.50INHER 260015 Empalme forjado cuadr. ½", 219 (Sin Invent.) u 24.37 101.71% 23.96INHER 260016 Empalme forjado redondo ½", Q-19 (Sin Invent.) u 30.22 101.72% 29.71INHER 260017 Malla tipo piñonate, 4' x 8' de 3/8" u 1,416.00 101.72% 1,392.00INHER 260018 Planchuela ½"x1/8"x20' u 95.58 101.72% 93.96INHER 260019 Planchuela ½"x3/16"x20' u 135.70 101.72% 133.40INHER 260020 Planchuela ¾"x3/16"x20' u 286.74 101.72% 281.88INHER 260021 Planchuela ¾"x¼"x20' u 5,156.60 101.72% 5,069.20INHER 260022 Planchuela 1 ½"x¼"x20' u 1,239.00 101.72% 1,218.00INHER 260023 Planchuela 2"x¼"x20' u 1,091.50 101.72% 1,073.00INHER 260024 Planchuela 3"x¼"x20' u 1,445.50 101.72% 1,421.00INHER 260025 Planchuela 4"x¼"x20' u 2,135.13 101.72% 2,098.94INHER 260026 Rejas livianas diseño sencillo a todo costo p2 306.80 101.72% 301.60INHER 260027 Rejas reforzadas diseño sencillo a todo costo p2 495.60 101.72% 487.20INHER 260028 Roseta forjada 10", RO-1620 (Sin Invent.) u 719.59 101.72% 707.39INHER 260029 Roseta forjada 15", RO-1610 (Sin Invent.) u 1,127.46 101.72% 1,108.35INHER 260030 Rueda para portón corredizo, tipo caja de bola 3" u 309.40 101.73% 304.15INHER 260031 Soldadura Universal lb 46.57 101.70% 45.79INHER 260032 Terminal forjado cuadr. ½", 215 (Sin Invent.) u 16.82 101.69% 16.54INHER 260033 Terminal forjado cuadr. ½", 217 u 14.42 101.76% 14.17INHER 260034 Terminal forjado cuadr. ½", Q-96 u 41.19 101.70% 40.50INHER 260035 Terminal forjado cuadr. 5/8", 227 (Sin Invent.) u 25.74 101.70% 25.31INHER 260036 Terminal forjado cuadr. 5/8", A-10 (Sin Invent.) u 40.51 101.73% 39.82INHER 260037 Tope forjado completo 36"x9 ¾", GT-2200 (Sin Invent.) u 2,691.63 101.72% 2,646.01INHER 260038 Tope forjado completo 56 ¾"x14", GT-2204 (Sin Invent.) u 3,869.89 101.72% 3,804.30INHER 260039 Tubo redondo negro 2"x20' u 2,301.00 101.72% 2,262.00INHER 260040 Tubo redondo negro 3"x20' u 5,015.00 101.72% 4,930.00INHER 260041 Tubo redondo negro 4"x20' u 5,310.00 101.72% 5,220.00INHER 260042 Perfil ¾"x¾"x20', 1.2 mm., galv. u 407.10 101.72% 400.20INHER 260043 Perfil 1"x1"x20' 1.6 mm, negro u 611.24 101.72% 600.88INHER 260044 Perfil 1"x2"x20', 1.6 mm, negro u 905.06 101.72% 889.72INHER 260045 Perfil 1 ½"x1 ½"x20' u 903.88 101.72% 888.56INHER 260046 Perfil 1 ½"x1 ½"x20', 1.6 mm, galv. u 1,020.70 101.72% 1,003.40INHER 260047 Perfil 2"x2"x20' 1.6 mm, negro u 1,256.70 101.72% 1,235.40INHER 260048 Perfil 2"x2"x20', 1.6 mm., galv. u 1,646.10 101.72% 1,618.20INHER 260049 Perfil 2"x3"x20' 1.6 mm, negro u 1,571.76 101.72% 1,545.12INHER 260050 Perfil 2"x3"x20', 1.6 mm., galv. u 1,669.70 101.72% 1,641.40INHER 260051 Perfil 2"x4"x20' u 1,593.00 101.72% 1,566.00INHER 260052 Perfil 3"x3"x20', 1.6 mm, negro u 1,929.30 101.72% 1,896.60INHER 260053 Perfil 4"x4"x20', negro u 4,100.50 101.72% 4,031.00

INHOR 270000 HORMIGONES INDUSTRIALES Y VACIADOS: (HORM. FERNANDEZ)INHOR 270001 Acarreo hormigón 1 m3 a 1.75 m3 (Nuevo) m3 4,720.00 101.72% 4,640.00INHOR 270002 Acarreo hormigón 2 m3 a 3 m3 (Nuevo) m3 4,130.00 101.72% 4,060.00INHOR 270003 Acarreo hormigón 3 m3 a 4 m3 (Nuevo) m3 3,540.00 101.72% 3,480.00INHOR 270004 Acarreo hormigón 4 m3 a 5 m3 (Nuevo) m3 2,950.00 101.72% 2,900.00INHOR 270005 Acelerante del fraguado (Nuevo) m3 472.00 101.72% 464.00INHOR 270006 Agua, camión 2,000 gls. gl 0.61 101.67% 0.60INHOR 270007 Fibras de vidrio, trozos pequeños (Nuevo) m3 507.40 101.72% 498.80INHOR 270008 Gravilla 3/8" (Nuevo) m3 354.00 101.72% 348.00INHOR 270009 Horm. 080 kg/cm2 (Relleno fluído) (Nuevo) m3 6,136.00 101.72% 6,032.00INHOR 270010 Horm. 100 kg/cm2 m3 5,498.80 101.72% 5,405.60INHOR 270011 Horm. 140 kg/cm2 m3 5,752.50 101.72% 5,655.00INHOR 270012 Horm. 160 kg/cm2 m3 5,864.60 101.72% 5,765.20INHOR 270013 Horm. 180 kg/cm2 m3 6,053.40 101.72% 5,950.80INHOR 270014 Horm. 210 kg/cm2 m3 6,242.20 101.72% 6,136.40INHOR 270015 Horm. 240 kg/cm2 m3 6,726.00 101.72% 6,612.00INHOR 270016 Horm. 245 kg/cm2 (Nuevo) m3 7,212.24 101.72% 7,090.00INHOR 270017 Horm. 250 kg/cm2 m3 7,038.70 101.72% 6,919.40INHOR 270018 Horm. 260 kg/cm2 m3 7,245.20 101.72% 7,122.40INHOR 270019 Horm. 280 kg/cm2 m3 7,327.80 101.72% 7,203.60INHOR 270021 Horm. 300 kg/cm2 m3 7,552.00 101.72% 7,424.00INHOR 270020 Horm. 315 kg/cm2 (Nuevo) m3 8,035.80 101.72% 7,899.60INHOR 270022 Horm. 350 kg/cm2 m3 8,413.40 101.72% 8,270.80

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 8

Page 9: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012

INHOR 270023 Horm. 400 kg/cm2 m3 8,926.70 101.72% 8,775.40INHOR 270024 Horm. 450 kg/cm2 (Nuevo) m3 9,227.60 101.72% 9,071.20INHOR 270025 Horm. 500 kg/cm2 (Nuevo) m3 9,499.00 101.72% 9,338.00INHOR 270026 Mortero p/Fino de techo (210 kg/cm2) (Nuevo) m3 8,687.24 101.72% 8,540.00INHOR 270027 Retardante de fraguado (Nuevo) m3 413.00 101.72% 406.00INHOR 270028 Slump 7" - 8" (Nuevo) m3 413.00 101.72% 406.00INHOR 270029 Slump 9" - 10" (Nuevo) m3 531.00 101.72% 522.00INHOR 270030 Vaciado con bomba, 10 m3 mínimo m3 5,310.00 101.72% 5,220.00INHOR 270031 Vaciado con bomba, 10 m3 en adelante m3 531.00 101.72% 522.00INHOR 270032 Vaciado con bomba adicional p/planta después 4to. Nivel. m3 236.00 101.72% 232.00

INIMP 280000 IMPERMEABILIZANTES:INIMP 280001 ALM, lata de 5 gl. lta 3,426.25 101.72% 3,368.18INIMP 280002 Bitupol inst., 2.5 mm., 5 años gar. m2 385.08 101.73% 378.55INIMP 280003 Bitupol inst., 3 mm., reforz. con poliester, 10 años gar. m2 470.65 101.72% 462.68INIMP 280004 Bitupol inst., 4 mm., reforz. con poliester, 10 años gar. m2 599.00 101.72% 588.85INIMP 280005 Sellador de techo "Tropitech" Tropical gl 751.66 101.72% 738.92INIMP 280006 Sellador de techo "Domatecho", Bco., lata 5 gl. lta 3,471.97 101.72% 3,413.13INIMP 280007 Sellador de techo "Lanco", import., lata 5 gl. lta 3,758.30 101.72% 3,694.60INIMP 280008 Sellador de techo "Ultra Siliconizer", lata 5 gl. lta 5,538.88 101.72% 5,445.01

INLAB 290000 LABORATORIO MECANICA DE SUELOS>INLAB 290001 Rotura de probetas y análisis de resultados u 785.88 101.72% 772.56

INLAV 300000 LAVADEROS Y VERTEDEROS DE GRANITO:INLAV 300001 Lavadero doble granito, 1.50x0.50 m. u 4,084.51 101.72% 4,015.28INLAV 300002 Lavadero sencillo granito, 1.25x0.50 m. u 2,603.63 101.72% 2,559.50INLAV 300003 Tina o vertedero granito, hasta 0.60x0.60 m., gris u 2,026.23 101.72% 1,991.89INLAV 300004 Tina o vertedero granito, hasta 0.60x0.60 m., blanco u 2,432.52 101.72% 2,391.29INLAV 300005 Transp. lavadero y tina u 144.60 101.72% 142.15

INLLA 310000 LLAVES DE PASO, VALVULAS, CHEQUES Y TAPAS CISTERNA: INLLA 310001 Cheque horiz. ½" "Urrea", 85N-13 u 540.44 101.72% 531.28INLLA 310002 Cheque horiz. ¾" "Urrea", 85N-19 u 713.90 101.72% 701.80INLLA 310003 Cheque horiz. 1" "Urrea", 85N-25 u 1,250.80 101.72% 1,229.60INLLA 310004 Cheque horiz. 1 ½" "Urrea", 85N-38 u 1,947.00 101.72% 1,914.00INLLA 310005 Cheque horiz. 2" "Urrea", 85N-51 u 3,392.50 101.72% 3,335.00INLLA 310006 Cheque horiz. 2 ½" "Europa", 100 ITAP u 3,056.20 101.72% 3,004.40INLLA 310007 Cheque horiz. 3" "Europa", 100 ITAP u 3,824.38 101.72% 3,759.56INLLA 310008 Cheque horiz. 4" "Europa" 100-ITAP u 7,555.54 101.72% 7,427.48INLLA 310009 Cheque vert. ¾" "Europa" 105-ITAP u 497.96 101.72% 489.52INLLA 310010 Cheque vert. 1" "Europa" 105-ITAP u 552.24 101.72% 542.88INLLA 310011 Cheque vert. 1 ½" "Europa" 105-ITAP u 962.88 101.72% 946.56INLLA 310012 Cheque vert. 2" "Europa" 105-ITAP u 1,708.64 101.72% 1,679.68INLLA 310013 Cheque vert. 2 ½" "Europa", 105 ITAP u 3,350.91 101.72% 3,294.11INLLA 310014 Cheque vert. 3" "Europa", 105 ITAP u 4,977.24 101.72% 4,892.88INLLA 310015 Cheque vert. 4" "Europa", 105 ITAP u 7,855.26 101.72% 7,722.12INLLA 310016 Llave de paso ½" de bola, 090 ITAP u 211.22 101.72% 207.64INLLA 310017 Llave de paso ¾" de bola, 090 ITAP u 384.68 101.72% 378.16INLLA 310018 Llave de paso 1" de bola, 090 ITAP u 417.72 101.72% 410.64INLLA 310019 Llave de paso 1 ½" "Urrea" u 1,475.00 101.72% 1,450.00INLLA 310020 Llave de paso 2" de bola, 090 ITAP u 1,871.54 101.72% 1,839.82INLLA 310021 Llave de paso 2 ½" de bola, 111 ITAP u 2,728.57 101.72% 2,682.33INLLA 310022 Llave de paso 3" de bola, 111 ITAP u 5,103.50 101.72% 5,017.00INLLA 310023 Tapa cisterna 24''x24'', tola verde u 2,596.00 101.72% 2,552.00INLLA 310024 Tapa cisterna 27"x27", aluminio u 3,097.50 101.72% 3,045.00INLLA 310025 Tapa cisterna 30''x30'', acero inox. u 6,490.00 101.72% 6,380.00INLLA 310026 Tapa cisterna 30"x30", tola u 3,097.50 101.72% 3,045.00INLLA 310027 Válvula cisterna, ½" "Urrea", 04N-13 u 261.96 101.72% 257.52INLLA 310028 Válvula cisterna, ¾" "Urrea", 04N-19 u 501.50 101.72% 493.00INLLA 310029 Válvula cisterna, 1" "Urrea" u 934.56 101.72% 918.72INLLA 310030 Válvula ¾", flux. p/orinal, HELVEX 18519 u 4,211.42 101.72% 4,140.04INLLA 310031 Válvula ¾", seguridad p/calentador tw, R-125C u 286.19 101.72% 281.34INLLA 310032 Válvula 1",flux. p/ inod., HELVEX 11038 u 4,210.24 101.72% 4,138.88

INMAD 320000 MADERAS, CLAVOS, PLYWOOD, ZINC Y OTROS:INMAD 320001 Caoba bruta, larga (Valiente Fernández) pt 127.16 101.73% 125.00INMAD 320002 Caballete de zinc 6', cal. 34 u 129.80 101.72% 127.60INMAD 320003 Caballete de zinc 6', cal. 29 u 188.80 101.72% 185.60INMAD 320004 Cedro bruto, largo con olor (Valiente Fernández) pt 122.07 101.73% 120.00INMAD 320005 Clavo corriente, metalizado c/cabeza 2 ½"x10 lb 30.43 101.70% 29.92INMAD 320006 Clavo de acero 1 ½" u 1.00 101.01% 0.99INMAD 320007 Clavo de acero 2 ½" lb 53.10 101.72% 52.20INMAD 320008 Clavo de zinc 2 ½" lb 52.68 101.74% 51.78INMAD 320009 Clavo galv. ¾" para cartón lb 49.44 101.73% 48.60INMAD 320010 Clavo galv. 2 ½"x9 c/cabeza lb 44.25 101.72% 43.50INMAD 320011 Pino amer. 1"x4"x10' bruto (3.33 pt) pt 35.79 101.73% 35.18INMAD 320012 Pino amer. 1"x4"x10' bruto tratado (3.33 pt) pt 37.21 101.75% 36.57INMAD 320013 Pino amer. 1"x4"x12' hasta 1"x10"x12' bruto (10 pt) pt 35.70 101.74% 35.09INMAD 320014 Pino amer. 1"x12"x12' bruto (12 pt) pt 30.68 101.72% 30.16INMAD 320015 Pino amer. 1"x12"x12' bruto tratado (12 pt) pt 24.39 101.71% 23.98INMAD 320016 Pino amer. 2"x4" hasta 2"x12"x12' bruto (24 pt) pt 35.31 101.73% 34.71INMAD 320017 Pino amer. 3"x4" hasta 3"x12"x12' bruto (36 pt) pt 39.29 101.71% 38.63INMAD 320018 Pino amer. 3"x6"x10' bruto (15 pt) pt 40.12 101.72% 39.44INMAD 320019 Pino amer. 3"x8"x12' bruto tratado (24 pt) pt 37.37 101.71% 36.74INMAD 320020 Pino amer. 4"x4"x12' bruto (16 pt) pt 33.34 101.74% 32.77INMAD 320021 Pino amer. 4"x4"x12' bruto tratado (16 pt) pt 36.21 101.71% 35.60INMAD 320022 Plywood Brasil 4'x8'x¼", 6 mm., plancha u 737.50 101.72% 725.00INMAD 320023 Plywood Brasil 4'x8'x½", plancha u 1,150.50 101.72% 1,131.00INMAD 320024 Plywood Brasil 4'x8'x3/16", plancha u 590.00 101.72% 580.00INMAD 320025 Plywood Brasil 4'x8'x3/8", plancha u 908.60 101.72% 893.20INMAD 320026 Plywood Brasil 4'x8'x¾", plancha u 1,663.80 101.72% 1,635.60INMAD 320027 Plywood Formaleta 4'x8'x¾" USA, una cara, plancha u 1,607.24 101.72% 1,580.00INMAD 320028 Regla para empañete (Preparada) pt 169.55 101.72% 166.68

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 9

Page 10: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012

INMAD 320029 Roble brasileño bruto, largo (IMDOMACA) pt 180.06 101.73% 177.00INMAD 320030 Tratamiento madera pt 3.95 101.54% 3.89INMAD 320031 Zinc acanalado, 3'x6', cal. 34 u 202.96 101.72% 199.52INMAD 320032 Zinc acanalado, 3'x6', cal. 27 u 548.70 101.72% 539.40INMAD 320033 Zinc acanalado, 3'x6', cal. 26 u 637.20 101.72% 626.40INMAD 320034 Zinc acanalado, 3'x6', cal. 24 (Sin Invent.) u 51.92 101.72% 51.04

INMAL 330000 MALLAS CICLONICAS Y ACCESORIOS:INMAL 330001 Abrazadera redonda 1 ½" u 35.40 101.72% 34.80INMAL 330002 Abrazadera redonda 2 ½" u 29.50 101.72% 29.00INMAL 330003 Alambre de púas #14x110 m, rollo u 908.60 101.72% 893.20INMAL 330004 Alambre de púas #16x110 m, rollo u 560.50 101.72% 551.00INMAL 330005 Alambre de púas #16x250 m, rollo u 1,905.57 101.72% 1,873.27INMAL 330006 Barra tensora de 4', hierro pintado u 139.24 101.72% 136.88INMAL 330007 Barra tensora de 6', hierro pintado u 145.14 101.72% 142.68INMAL 330008 Barra tensora de 7', hierro pintado u 177.00 101.72% 174.00INMAL 330009 Barra tensora de 10', hierro pintado u 202.96 101.72% 199.52INMAL 330010 Copa final 2" u 55.46 101.72% 54.52INMAL 330011 Grapas 1" para alambre de púas lb 43.07 101.72% 42.34INMAL 330012 Malla ciclónica 6' cal. 9 pie 141.60 101.72% 139.20INMAL 330013 Malla ciclónica 7' cal. 9 pie 179.36 101.72% 176.32INMAL 330014 Palometa 1 ½"x1 ¼", 3 cuerdas, sencilla u 123.90 101.72% 121.80INMAL 330015 Palometa 1 ½"x1 ¼", 3 cuerdas, doble u 188.80 101.72% 185.60INMAL 330016 Terminal de 1 ¼" u 53.10 101.72% 52.20INMAL 330017 Tubo 1 ½"x15', galv. ligero u 725.70 101.72% 713.40INMAL 330018 Tubo 1 ¼"x20', galv. ligero u 821.28 101.72% 807.36

INMAT 340000 MATERIALES INSTALADOS:INMAT 340001 Caballete en teja asfáltica inst. todo costo m 116.78 101.72% 114.81INMAT 340002 Felpa impermeable, 3' ancho x 15' de largo pie 16.02 101.71% 15.75INMAT 340003 Línea doble teja asfáltica inst. todo costo, en bordes m 116.78 101.72% 114.81INMAT 340004 Plafón Fibra Mineral 2'x2'x9/16", Futura u 122.07 101.73% 120.00INMAT 340005 Plafón PVC cruadrado 2'x2', instalado a todo costo m2 841.78 101.72% 827.51INMAT 340006 Plafón PVC machiembrado, instalado a todo costo m2 1,270.19 101.72% 1,248.66INMAT 340007 Plafón PVC rectangular 2'x4' bco., instalado a todo costo m2 202.94 101.72% 199.50INMAT 340008 Teja asfáltica 3'x1' inst. todo costo m2 329.69 101.72% 324.10INMAT 340009 Teja asfáltica 3'x1', gris, paq. 26 piezas de 1'x3', 3.07 m2) paq 1,228.50 101.72% 1,207.68INMAT 340010 Teja asfáltica 3'x1', marrón, paq. 26 piezas de 1'x3', 3.07 m2) paq 1,419.06 101.72% 1,395.00INMAT 340011 Teja asfáltica 3'x1', roja, paq. 26 piezas de 1'x3', 3.07 m2) paq 1,419.06 101.72% 1,395.00INMAT 340012 Teja asfáltica 3'x1', verde claro, paq. 26 piezas de 1'x3', 3.07 m2) paq 1,012.16 101.72% 995.00INMAT 340013 Teja asfáltica 3'x1', verde senc., paq. 26 piezas de 1'x3', 3.07 m2) paq 1,419.06 101.72% 1,395.00

INMOT 350000 MOTORES ELECTRICOS PARA PORTONESINMOT 350001 Motor eléct. Kit, p/portón corredizo, "Came", 800 kg. u 1,735.41 101.72% 1,706.00INMOT 350002 Motor eléct. Kit, p/portón corredizo, "Came", 1,800 kg. u 50,467.89 101.72% 49,612.50INMOT 350003 Motor eléct. Kit, p/portón corredizo, "Came", 2,200 kg. u 65,608.25 101.72% 64,496.24

INPIE 360000 PIEDRAS EN LAJAS PARA PISOS:INPIE 360001 Piedra color claro m2 295.00 101.72% 290.00INPIE 360002 Piedra color gris m2 790.60 101.72% 777.20INPIE 360003 Piedra coralina biselada m2 1,298.00 101.72% 1,276.00INPIE 360004 Piedra coralina sin bisel m2 1,062.00 101.72% 1,044.00

INPIN 370000 PINTURAS:INPIN 370001 Acrílica "Popular" 50, blanco gl 705.64 101.72% 693.68INPIN 370002 Acrílica "Popular" 73, blanco hueso gl 705.64 101.72% 693.68INPIN 370003 Acrílica "Tropical" 81, verde manzana gl 705.64 101.72% 693.68INPIN 370004 Acrílica, Tropical, Beep (colores preparados) gl 1,076.53 101.72% 1,058.29INPIN 370005 Aguarrás "Popular" gl 319.70 101.72% 314.28INPIN 370006 Blanco de España lb 13.02 101.80% 12.79INPIN 370007 Epóxica "Popular" bco. 50 gl 2,041.40 101.72% 2,006.80INPIN 370008 Latex "Económica" "Tropical" Bco. gl 292.64 101.72% 287.68INPIN 370009 Mantenimiento "Popular" bco. 50 gl 1,073.80 101.72% 1,055.60INPIN 370010 Oxido Rojo "Popular" k-09 gl 708.00 101.72% 696.00INPIN 370011 Sellador de poros a la madera, plywood, etc. (Sealer Tropical) gl 929.33 101.72% 913.58INPIN 370012 Semi-Gloss "Popular" 50, blanco gl 1,010.08 101.72% 992.96INPIN 370013 "Thinner" AAA-500 "Popular" gl 624.50 101.72% 613.92

INPIS 380000 PISOS Y ADOQUINES:INPIS 380001 Adoquín 500 8x10x20 cm. Haina gris 80 m2 1,925.41 101.72% 1,892.77INPIS 380002 Adoquín 500 8x10x20 cm. Haina rojo 80 m2 2,386.82 101.72% 2,346.37INPIS 380003 Adoquín 511 Barahona gris 60 m2 1,126.36 101.72% 1,107.27INPIS 380004 Adoquín 511 Barahona rojo 60 m2 1,396.15 101.72% 1,372.49INPIS 380005 Adoquín 604 6x20.2x20.2 cm. Higuey gris 60 m2 1,067.23 101.72% 1,049.14INPIS 380006 Adoquín 604 6x20.2x20.2 cm. rojo m2 1,322.70 101.72% 1,300.28INPIS 380007 Baldosa p/exterior 30x30, Crema y Aurora, tipo Vibrazo m2 637.72 101.72% 626.91INPIS 380008 Baldosa p/exterior 30x30, Gris, tipo Vibrazo m2 447.76 101.72% 440.17INPIS 380009 Baldosa p/exterior 30x30, Verde, tipo Vibrazo m2 903.22 101.72% 887.91INPIS 380010 Baldosa p/exterior 40x40, Laja Gris m2 671.72 101.72% 660.33INPIS 380011 Borde p/pavimento y jardinería GPVT, espesor = .08 m. m 533.30 101.72% 524.26INPIS 380012 Corte chazos 25 u 9.44 101.72% 9.28INPIS 380013 Corte chazos 30 u 12.98 101.72% 12.76INPIS 380014 Corte chazos 40 u 16.52 101.72% 16.24INPIS 380015 Corte ladrillos y adoquines u 38.94 101.72% 38.28INPIS 380016 Corte zócalos u 7.08 101.72% 6.96INPIS 380017 Derretido blanco fda 861.11 101.72% 846.51INPIS 380018 Derretido gris fda 408.87 101.72% 401.94INPIS 380019 Derretido verde fda 861.11 101.72% 846.51INPIS 380020 Granimármol 30x30 fondo blanco m2 582.27 101.72% 572.40INPIS 380021 Granimármol 40x40 fondo blanco m2 682.84 101.73% 671.26INPIS 380022 Granito 1 2 y 3 30x30 fondo blanco m2 396.43 101.72% 389.71INPIS 380023 Granito 1 2 y 3 30x30 fondo gris m2 336.97 101.72% 331.26INPIS 380024 Granito 1 2 y 3 40x40 fondo blanco m2 574.44 101.72% 564.70INPIS 380025 Granito 1 2 y 3 40x40 fondo gris m2 418.09 101.73% 411.00

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 10

Page 11: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012INPIS 380026 Mármol 30x60 Travertino m2 1,241.48 101.72% 1,220.44INPIS 380027 Mármol 40x40 Aglomerado Perlatto Royal m2 681.45 101.72% 669.90INPIS 380028 Mármol 40x40 Crema Marfil bruto m2 1,425.47 101.72% 1,401.31INPIS 380029 Mármol 40x60 Crema Marfil bruto m2 1,511.96 101.72% 1,486.34INPIS 380030 Mosaico 25x25 rojo m2 1,126.35 101.72% 1,107.25INPIS 380031 Paragomas 15" x 2.00 m. u 1,006.29 101.72% 989.24INPIS 380032 Piedra p/pavimento G3 espesor = .045 m., 12 adoquines integrados m2 1,236.52 101.72% 1,215.56INPIS 380033 Piedra p/pavimento G15 espesor = .045 m., 5 adoquines inseparables m2 1,169.62 101.72% 1,149.79INPIS 380034 Piedra p/pavim. DGVE 2.5 espesor = .045 m., 3 losas Galo-Romanas m2 778.80 101.72% 765.60INPIS 380035 Tableta 2"x8"x16" gris m2 520.38 101.72% 511.56INPIS 380036 Tableta 2"x8"x16" roja m2 658.44 101.72% 647.28INPIS 380037 Transp. adoquín 500-80 u 1.06 101.92% 1.04INPIS 380038 Transp. Adoquín 511 Barahona gris 60 u 0.83 102.47% 0.81INPIS 380039 Transp. adoquín 604 u 1.03 101.98% 1.01INPIS 380040 Transp. Baldosa 30x30 u 1.06 101.92% 1.04INPIS 380041 Transp. Baldosa 40x40 u 1.53 101.32% 1.51INPIS 380042 Transp. Baldosa 40x60 u 2.30 101.77% 2.26INPIS 380043 Transp. Mosaico 25X25 u 0.89 102.30% 0.87INPIS 380044 Transp. Paragomas u 52.33 101.71% 51.45INPIS 380045 Transp. tableta u 1.00 101.01% 0.99INPIS 380046 Transp. zócalo granito y mosaico u 1.06 101.92% 1.04INPIS 380047 Zócalo Granimármol 30x07 m 69.77 101.72% 68.59INPIS 380048 Zócalo Granimármol 40x07 m 69.38 101.72% 68.21INPIS 380049 Zócalo Granito 1 2 y 3 30x07 fondo blanco m 75.54 101.72% 74.26INPIS 380050 Zócalo Granito 1 2 y 3 30x07 fondo gris m 47.40 101.72% 46.60INPIS 380051 Zócalo Granito 1 2 y 3 40x07 fondo blanco m 84.48 101.73% 83.04INPIS 380052 Zócalo Granito 1 2 y 3 40x07 fondo gris m 61.95 101.72% 60.90INPIS 380053 Zócalo Mármol 30x07 Crema Marfil recto m 546.03 101.73% 536.77INPIS 380054 Zócalo Mármol 30x10 Crema Marfil recto m 461.47 101.73% 453.64INPIS 380055 Zócalo Mármol 40x07 Crema Marfil recto m 546.03 101.73% 536.77INPIS 380056 Zócalo Mármol 40x10 Crema Marfil recto m 461.47 101.73% 453.64INPIS 380057 Zócalo Mármol 60x10 Crema Marfil recto m 469.20 101.73% 461.24INPIS 380058 Zócalo Mármol aglomerado Perlatto Royal 40x07 redondeado m 195.76 101.73% 192.44INPIS 380059 Zócalo Mármol aglomerado Perlatto Royal 40x07 recto m 109.24 101.72% 107.39INPIS 380060 Zócalo Mosaico rojos 25x07 u 197.13 101.72% 193.79

INPLA 390000 PLANTAS ELECTRICAS:INPLA 390001 Planta 60 Kilos 3 ph, Kholer, silenciosa u 712,017.66 103.48% 688,086.02

INPOZ 400000 POZOS FILTRANTES:INPOZ 400001 Pozo filtrante 8" + camisa 6" x 10', PVC SDR-26 u 15,340.00 101.72% 15,080.00INPOZ 400002 Pozo filtrante 10" + camisa 8" x 10', PVC SDR-26 u 18,290.00 101.72% 17,980.00

INPUE 410000 PUERTAS DE ALUMINIO:INPUE 410001 Cerradura eléctrica para portones "Yale" 67400401 (674-40) u 3,510.50 101.72% 3,451.00INPUE 410002 Cerradura eléctrica para puertas u 1,917.70 101.72% 1,885.20INPUE 410003 Cierre botella grande p/puerta com. normal (alum. nat.) u 1,626.83 101.72% 1,599.26INPUE 410004 Cierre botella pequeño p/puerta com. normal (alum. nat.) u 1,159.20 101.72% 1,139.55INPUE 410005 Cierre botella pequeño p/puerta com. normal (alum. bce.) u 1,064.44 101.72% 1,046.40INPUE 410006 Cilindros p/puerta comercial (2 unid.) u 430.87 101.73% 423.56INPUE 410007 Cubre falta p/cerradura eléctrica normal u 42.89 101.71% 42.17INPUE 410008 Pta. corred. alum. anod. normal, v. claro (w2.86 x h2.1 m.) m2 2,857.42 101.72% 2,808.99INPUE 410009 Pta. corred. alum. anod. normal, v. claro mart. (w2.86 x h2.1 m.) m2 2,824.53 101.72% 2,776.66INPUE 410010 Pta. corred. alum. anod. normal, v. bce. liso (w2.86 x h2.1 m.) m2 2,964.64 101.72% 2,914.40INPUE 410011 Pta. corred. alum. anod. normal, v. bce. mart. (w2.86 x h2.1 m.) m2 2,925.57 101.72% 2,875.99INPUE 410012 Pta. corred. alum. anod. normal, v. "Bluegreen" (w2.86 x h2.1 m.) m2 3,213.61 101.72% 3,159.14INPUE 410013 Pta. corred. alum. anod. normal, v. reflect. claro (w2.86 x h2.1 m.) m2 3,373.18 101.72% 3,316.01INPUE 410014 Pta. corred. alum. anod. normal, con espejo (w2.86 x h2.1 m.) m2 3,668.07 101.72% 3,605.89INPUE 410015 Pta. corred. alum. anod. bce., v. claro (w2.86 x h2.1 m.) m2 2,489.62 101.72% 2,447.43INPUE 410016 Pta. corred. alum. anod. bce., v. claro mart. (w2.86 x h2.1 m.) m2 2,456.82 101.72% 2,415.18INPUE 410017 Pta. corred. alum. anod. bce., v. bce. liso (w2.86 x h2.1 m.) m2 2,596.92 101.72% 2,552.90INPUE 410018 Pta. corred. alum. anod. bce., v. bce. mart. (w2.86 x h2.1 m.) m2 2,562.70 101.72% 2,519.26INPUE 410019 Pta. corred. alum. anod. bce., v. reflect. claro (w2.86 x h2.1 m.) m2 3,005.38 101.72% 2,954.44INPUE 410020 Pta. corred. alum. anod. bce., con espejos (w2.86 x h2.1 m.) m2 3,300.26 101.72% 3,244.32INPUE 410021 Pta. corred. alum. bco., v. claro (w2.86 x h2.1 m.) m2 2,792.82 101.72% 2,745.49INPUE 410022 Pta. corred. alum. bco., v. claro mart. (w2.86 x h2.1 m.) m2 2,756.02 101.72% 2,709.31INPUE 410023 Pta. corred. alum. bco., v. bce. liso (w2.86 x h2.1 m.) m2 2,900.04 101.72% 2,850.89INPUE 410024 Pta. corred. alum. bco., v. bce. mart. (w2.86 x h2.1 m.) m2 2,861.82 101.72% 2,813.31INPUE 410025 Pta. corred. alum. bco., v. "Bluegreen" (w2.86 x h2.1 m.) m2 3,149.01 101.72% 3,095.63INPUE 410026 Pta. corred. alum. bco., v. reflect. claro (w2.86 x h2.1 m.) m2 3,308.58 101.72% 3,252.50INPUE 410027 Pta. corred. alum. bco., con espejo (w2.86 x h2.1 m.) m2 3,585.89 101.72% 3,525.11INPUE 410028 Pta. com. 1 hoja, 1 m.,7', alum. anod. normal, v. claro u 14,708.46 101.72% 14,459.17INPUE 410029 Pta. com. 1 hoja, 1 m.,7', alum. anod. normal, v. claro mart. u 14,514.64 101.72% 14,268.63INPUE 410030 Pta. com. 1 hoja, 1 m.,7', alum. anod. normal, v. bce. liso u 14,901.28 101.72% 14,648.71INPUE 410031 Pta. com. 1 hoja, 1 m.,7', alum. anod. normal, v. bce. mart. u 14,704.90 101.72% 14,455.66INPUE 410032 Pta. com. 1 hoja, 1 m.,7', alum. anod. bce., v. claro u 14,499.16 101.72% 14,253.41INPUE 410033 Pta. com. 1 hoja, 1 m.,7', alum. anod. bce., v. claro mart. u 14,308.08 101.72% 14,065.57INPUE 410034 Pta. com. 1 hoja, 1 m.,7', alum. anod. bce., v. bce. liso u 14,692.44 101.72% 14,443.42INPUE 410035 Pta. com. 1 hoja, 1 m.,7', alum. anod. bce., v. bce. mart. u 14,498.81 101.72% 14,253.07INPUE 410036 Pta. com. 1 hoja, 1 m., 7', alum. Bco, v. claro u 15,723.88 101.72% 15,457.37INPUE 410037 Pta. com. 1 hoja, 1 m., 7', alum. Bco, v. claro mart. u 15,516.66 101.72% 15,253.66INPUE 410038 Pta. com. 1 hoja, 1 m., 7', alum. Bco, v. bce. liso u 15,916.69 101.72% 15,646.92INPUE 410039 Pta. com. 1 hoja, 1 m., 7', alum. Bco, v. bce. mart. u 15,706.93 101.72% 15,440.71INPUE 410040 Pta. com. 2 hojas, 2 m., 7', alum. anod. normal, v. claro u 19,122.75 101.72% 18,798.64INPUE 410041 Pta. com. 2 hojas, 2 m., 7', alum. anod. normal, v. mart. u 18,870.75 101.72% 18,550.91INPUE 410042 Pta. com. 2 hojas, 2 m., 7', alum. anod. normal, v. bce. liso u 19,560.21 101.72% 19,228.68INPUE 410043 Pta. com. 2 hojas, 2 m., 7', alum. anod. normal, v. bce. mart. u 19,302.44 101.72% 18,975.28INPUE 410044 Pta. com. 2 hojas, 2 m., 7', alum. anod. bce., v. claro u 18,294.96 101.72% 17,984.87INPUE 410045 Pta. com. 2 hojas, 2 m., 7', alum. anod. bce., v. claro mart. u 18,053.86 101.72% 17,747.86INPUE 410046 Pta. com. 2 hojas, 2 m., 7', alum. anod. bce., v. bce. liso u 18,732.42 101.72% 18,414.92INPUE 410047 Pta. com. 2 hojas, 2 m., 7', alum. anod. bce., v. bce. mart. u 18,485.56 101.72% 18,172.25INPUE 410048 Pta. com. 2 hojas, 2 m., 7', alum. Bco., v. claro u 20,343.70 101.72% 19,998.89INPUE 410049 Pta. com. 2 hojas, 2 m., 7', alum. Bco., v. claro mart. u 20,075.60 101.72% 19,735.34INPUE 410050 Pta. com. 2 hojas, 2 m., 7', alum. Bco., v. bce. liso u 20,781.17 101.72% 20,428.95

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 11

Page 12: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012INPUE 410051 Pta. com. 2 hojas, 2 m., 7', alum. Bco., v. bce. mart. u 20,507.30 101.72% 20,159.72INPUE 410052 Puño anodizado normal p/puerta eléctrica u 362.99 101.72% 356.84INPUE 410053 Push boton p/cerradura eléctrica normal u 277.67 101.73% 272.96INPUE 410054 Transformador p/puerta com. eléctrica u 1,143.17 101.72% 1,123.80INPUE 410055 Transporte e instalación (Porcentaje sobre el costo) % 12.00% 100.00% 12.00%

INPPV 420000 PUERTAS DE PVC: (Pendiente)INPPV 420010 uINPPV 420020 u

INTIN 430000 TINACOS:INTIN 430001 Tinaco 150 gl. "Aquaplástica" u 2,312.80 101.72% 2,273.60INTIN 430002 Tinaco 265 gl. "Tinacom" u 4,584.30 101.72% 4,506.60INTIN 430003 Tinaco 400 gl. "Tinacom" u 7,417.48 101.72% 7,291.76INTIN 430004 Tinaco 500 gl."Aquaplástica" u 9,896.66 101.72% 9,728.92INTIN 430005 Tinaco 530 gl. "Tinacom" u 9,422.30 101.72% 9,262.60INTIN 430006 Tinaco 1000 gl "Tinacom" u 12,862.00 101.72% 12,644.00INTIN 430007 Tornillo exag. p/madera, h.g. ¼"x4" (23 unid/lb) u 9.79 101.66% 9.63

INCOB 440000 TUBERIAS Y PIEZAS COBRE: (Pendiente)INCOB 440010 uINCOB 440020 u

INTCP 450000 TUBERIAS Y PIEZAS CPVC:INTCP 450001 Adaptador hembra ½" cpvc u 27.26 101.72% 26.80INTCP 450002 Adaptador hembra ¾" cpvc u 23.85 101.75% 23.44INTCP 450003 Adaptador macho ½" cpvc u 8.32 101.71% 8.18INTCP 450004 Adaptador macho ¾" cpvc u 15.10 101.68% 14.85INTCP 450005 Cemento cpvc, 8 onzas, pinta u 215.66 101.73% 212.00INTCP 450006 Cemento cpvc, 32 onzas u 499.47 101.73% 491.00INTCP 450007 Codo ½''x90, cpvc u 11.35 101.70% 11.16INTCP 450008 Codo ¾''x90, cpvc u 23.25 101.75% 22.85INTCP 450009 Limpiador tubo cpvc, "Cleaner OATEY" 8 onzas, pinta u 125.08 101.72% 122.96INTCP 450010 Limpiador tubo cpvc, "Cleaner OATEY" 16 onzas u 199.42 101.72% 196.04INTCP 450011 Reduc. bushing ¾"x½", cpvc u 6.37 101.76% 6.26INTCP 450012 Reduc. bushing 1'' x ¾", cpvc u 29.50 101.72% 29.00INTCP 450013 Tee ½'', cpvc u 11.73 101.73% 11.53INTCP 450014 Tee ¾'', cpvc u 29.98 101.70% 29.48INTCP 450015 Tubo ½''x10', cpvc u 106.79 101.72% 104.98INTCP 450016 Tubo ¾''x10', cpvc u 223.60 101.72% 219.81

INGAS 460000 TUBERIAS Y PIEZAS GAS:INCOB 460010 Llave r. control gas 1/2NPTX3/8 IP-200P u 247.80 101.72% 243.60INCOB 460020 Manguera c/regulador p/gas EPG3-B150 u 719.80 101.72% 707.60INCOB 460030 Regulador de gas de una vía c/punta RN-PME u 318.60 101.72% 313.20INCOB 460040 Regulador de gas doble c/pistel RN-2AE u 560.50 101.72% 551.00INCOB 460050 Tubería cobre 1/2" u 73.16 101.72% 71.92INCOB 460060 Tubería cobre 3/8" u 53.10 101.72% 52.20INCOB 460070 Tubería cobre 5/8" u 96.76 101.72% 95.12INCOB 460080 Válvula p/tanque de gas 718 u 472.25 101.73% 464.24

INTHG 470000 TUBERIAS Y PIEZAS H.G. (HIERRO GALVANIZADO):INTHG 470001 Codo ½"x90, h.g. u 27.77 101.76% 27.29INTHG 470002 Codo ¾"x90, h.g. u 25.96 101.72% 25.52INTHG 470003 Codo 1"x90, h.g. u 41.30 101.72% 40.60INTHG 470004 Codo 1 ¼"x90, h.g. u 66.22 101.72% 65.10INTHG 470005 Codo 1 ½"x90, h.g. u 91.72 101.72% 90.17INTHG 470006 Codo 2"x90, h.g. u 214.10 101.72% 210.47INTHG 470007 Codo 2 ½"x90, h.g. u 147.50 101.72% 145.00INTHG 470008 Codo 3"x90, h.g. u 233.64 101.72% 229.68INTHG 470009 Codo 4"x90, h.g. u 415.62 101.72% 408.58INTHG 470010 Codo niple ½", h.g. u 22.30 101.73% 21.92INTHG 470011 Codo niple ¾", h.g. u 25.96 101.72% 25.52INTHG 470012 Codo niple 1", h.g. u 53.10 101.72% 52.20INTHG 470013 Codo niple 1 ¼", h.g. u 81.42 101.72% 80.04INTHG 470014 Codo niple 1 ½", h.g. u 78.06 101.73% 76.73INTHG 470015 Codo niple 2", h.g. u 118.00 101.72% 116.00INTHG 470016 Codo niple 2 ½", h.g. u 115.35 101.72% 113.40INTHG 470017 Codo niple 3", h.g. u 248.90 101.72% 244.68INTHG 470018 Codo niple 4", h.g. u 267.90 101.72% 263.36INTHG 470019 Coupling ½" h.g. u 20.06 101.72% 19.72INTHG 470020 Coupling ¾" h.g. u 17.70 101.72% 17.40INTHG 470021 Coupling 1" h.g. u 28.90 101.72% 28.41INTHG 470022 Coupling 1 ½" h.g. u 46.55 101.73% 45.76INTHG 470023 Coupling 2" h.g. u 105.32 101.73% 103.53INTHG 470024 Coupling 2 ½" h.g. u 129.99 101.72% 127.79INTHG 470025 Coupling 3" h.g. u 188.80 101.72% 185.60INTHG 470026 Coupling 4" h.g. u 331.97 101.73% 326.34INTHG 470027 Niple ½"x4", h.g. u 44.76 101.73% 44.00INTHG 470028 Niple ¾"x4", h.g. u 49.82 101.71% 48.98INTHG 470029 Niple 1"x4", h.g. u 65.05 101.72% 63.95INTHG 470030 Niple 1 ¼"x4", h.g. u 91.56 101.73% 90.00INTHG 470031 Niple 1 ½"x3 ½", h.g. u 80.36 101.72% 79.00INTHG 470032 Niple 1 ½"x6" h.g. u 123.37 101.72% 121.28INTHG 470033 Niple 1 ½"x8" h.g. u 161.07 101.72% 158.34INTHG 470034 Niple 2"x4", h.g. u 100.30 101.72% 98.60INTHG 470035 Niple 2"x6" h.g. u 170.90 101.73% 168.00INTHG 470036 Niple 2 ½"x3 ½", h.g. u 446.04 101.72% 438.48INTHG 470037 Niple 3"x3 ½" h.g. u 650.48 101.72% 639.45INTHG 470038 Niple 3"x4" h.g. u 569.94 101.72% 560.28INTHG 470039 Niple 3"x6" h.g. u 173.29 101.73% 170.35INTHG 470040 Niple 3"x12" h.g. u 929.25 101.72% 913.50INTHG 470041 Niple 4"x3 ½", h.g. u 712.43 101.72% 700.35INTHG 470042 Reduc. "bushing" ½"x3/8", h.g. u 14.16 101.72% 13.92

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 12

Page 13: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012

INTHG 470043 Reduc. "bushing" ¾"x½", h.g. u 18.38 101.72% 18.07INTHG 470044 Reduc. "bushing" 1"x¾", h.g. u 21.24 101.72% 20.88INTHG 470045 Reduc. "bushing" 1 ½"x1", h.g. u 52.04 101.72% 51.16INTHG 470046 Reduc. "bushing" 2"x¾", h.g. u 64.09 101.73% 63.00INTHG 470047 Reduc. "bushing" 2"x1", h.g. u 70.62 101.71% 69.43INTHG 470048 Reduc. "bushing" 2 ½"x1", h.g. u 115.64 101.72% 113.68INTHG 470049 Reduc. "bushing" 3"x2 ½", h.g. u 322.14 101.72% 316.68INTHG 470050 Reduc. copa ½"x3/8", h.g. u 14.16 101.72% 13.92INTHG 470051 Reduc. copa ¾"x½", h.g. u 24.78 101.72% 24.36INTHG 470052 Reduc. copa 1"x¾", h.g. u 40.14 101.72% 39.46INTHG 470053 Reduc. copa 2"x¾", h.g. u 53.41 101.73% 52.50INTHG 470054 Reduc. copa 2"x1 ½", h.g. u 88.50 101.72% 87.00INTHG 470055 Reduc. copa 2 ½"x1", h.g. u 37.64 101.73% 37.00INTHG 470056 Rollo teflón ¾" u 10.80 101.79% 10.61INTHG 470057 Tapón hembra ½", h.g. u 21.49 101.75% 21.12INTHG 470058 Tapón hembra ¾", h.g. u 28.90 101.72% 28.41INTHG 470059 Tapón hembra 1", h.g. u 35.85 101.73% 35.24INTHG 470060 Tapón hembra 1 ½", h.g. u 61.95 101.72% 60.90INTHG 470061 Tapón hembra 2", h.g. u 70.80 101.72% 69.60INTHG 470062 Tapón hembra 2 ½", h.g. u 119.75 101.72% 117.72INTHG 470063 Tapón hembra 3", h.g. u 155.76 101.72% 153.12INTHG 470064 Tapón hembra 4", h.g. u 264.32 101.72% 259.84INTHG 470065 Tapón macho ½", h.g. u 10.44 101.66% 10.27INTHG 470066 Tapón macho ¾", h.g. u 16.52 101.72% 16.24INTHG 470067 Tapón macho 1", h.g. u 18.66 101.74% 18.34INTHG 470068 Tapón macho 1 ½", h.g. u 37.76 101.72% 37.12INTHG 470069 Tapón macho 2", h.g. u 57.99 101.74% 57.00INTHG 470070 Tapón macho 2 ½", h.g. u 35.25 101.73% 34.65INTHG 470071 Tapón macho 3", h.g. u 146.32 101.72% 143.84INTHG 470072 Tapón macho 4", h.g. u 253.70 101.72% 249.40INTHG 470073 Tee ½", h.g. u 39.40 101.73% 38.73INTHG 470074 Tee ¾", h.g. u 29.50 101.72% 29.00INTHG 470075 Tee 1", h.g. u 64.10 101.73% 63.01INTHG 470076 Tee 1 ¼", h.g. u 115.64 101.72% 113.68INTHG 470077 Tee 1 ½", h.g. u 120.43 101.72% 118.39INTHG 470078 Tee 2", h.g. u 149.87 101.72% 147.33INTHG 470079 Tee 2 ½", h.g. u 225.14 101.72% 221.33INTHG 470080 Tee 3", h.g. u 336.70 101.73% 330.99INTHG 470081 Tee 4", h.g. u 513.30 101.72% 504.60INTHG 470082 Tubo ½"x20', h.g., mamey u 495.60 101.72% 487.20INTHG 470083 Tubo ¾"x20', h.g. mamey u 693.84 101.72% 682.08INTHG 470084 Tubo 1"x20', h.g. mamey u 922.76 101.72% 907.12INTHG 470085 Tubo 1 ¼"x20', h.g. mamey u 1,177.64 101.72% 1,157.68INTHG 470086 Tubo 1 ½"x20', h.g. mamey u 1,486.80 101.72% 1,461.60INTHG 470087 Tubo 2"x20', h.g. mamey u 1,858.50 101.72% 1,827.00INTHG 470088 Tubo 2 ½"x20', h.g. mamey u 2,601.90 101.72% 2,557.80INTHG 470089 Tubo 3"x20', h.g. mamey u 4,602.00 101.72% 4,524.00INTHG 470090 Tubo 4"x20', h.g. mamey u 3,964.80 101.72% 3,897.60INTHG 470091 Unión univ. ½", h.g. u 76.57 101.73% 75.27INTHG 470092 Unión univ. ¾", h.g. u 87.07 101.72% 85.60INTHG 470093 Unión univ. 1", h.g. u 102.44 101.73% 100.70INTHG 470094 Unión univ. 1 ¼", h.g. u 167.56 101.72% 164.72INTHG 470095 Unión univ. 1 ½", h.g. u 185.85 101.72% 182.70INTHG 470096 Unión univ. 2", h.g. u 292.71 101.72% 287.75INTHG 470097 Unión univ. 2 ½", h.g. u 403.56 101.72% 396.72INTHG 470098 Unión univ. 3", h.g. u 683.59 101.72% 672.00INTHG 470099 Unión univ. 4", h.g. u 851.28 101.72% 836.85

INPOL 480000 TUBERIAS Y PIEZAS POLIETILENO: (Pendiente)INPOL 480001 uINPOL 480002 u

INPOP 490000 TUBERIAS Y PIEZAS POLIPROPILENO: (Pendiente)INPOP 490001 uINPOP 490002 u

INTDR 500000 TUBERIAS Y PIEZAS PVC DRENAJE:INTDR 500001 Cemento pvc criollo, 1 gl. Cano u 734.44 101.72% 722.00INTDR 500002 Cemento pvc criollo, ¼ gl., Cano u 289.10 101.72% 284.20INTDR 500003 Cemento pvc criollo, 1/32 gl., pinta, Cano u 57.02 101.73% 56.05INTDR 500004 Cemento pvc USA 920 gr., Tangit u 1,368.80 101.72% 1,345.60INTDR 500005 Cemento pvc USA 460 gr., Tangit u 761.10 101.72% 748.20INTDR 500006 Cemento pvc USA 240 gr., Tangit u 572.30 101.72% 562.60INTDR 500007 Cemento pvc USA 125 gr. Tubo, Tangit u 230.10 101.72% 226.20INTDR 500008 Codo 2"x90, pvc dren. u 24.01 101.69% 23.61INTDR 500009 Codo 3"x90, pvc dren. u 44.84 101.72% 44.08INTDR 500010 Codo 4"x90, pvc dren. u 100.30 101.72% 98.60INTDR 500011 Codo 6"x90, pvc dren. u 928.65 101.72% 912.91INTDR 500012 Codo 2"x45, pvc dren. u 19.33 101.74% 19.00INTDR 500013 Codo 3"x45, pvc dren. u 33.04 101.72% 32.48INTDR 500014 Codo 4"x45, pvc dren. u 81.43 101.72% 80.05INTDR 500015 Codo 6"x45, pvc dren. u 849.98 101.72% 835.57INTDR 500016 Red. 3"x1 ½", pvc dren. u 75.27 101.72% 74.00INTDR 500017 Red. 3"x2", pvc dren. u 21.59 101.70% 21.23INTDR 500018 Red. 4"x2", pvc dren. u 56.97 101.73% 56.00INTDR 500019 Red. 4"x3", pvc dren. u 42.48 101.72% 41.76INTDR 500020 Red. 6"x4", pvc dren. u 694.77 101.72% 683.00INTDR 500021 Sifón 1 ½", p/lav., pvc u 114.51 101.72% 112.57INTDR 500022 Sifón 2", pvc dren. u 94.40 101.72% 92.80INTDR 500023 Sifón 3", pvc dren. (Sin Invent.) u 186.92 101.73% 183.75INTDR 500024 Sifón 4", pvc dren. u 1,882.23 101.72% 1,850.32INTDR 500025 Tapón reg. 2", pvc dren. u 25.55 101.75% 25.11INTDR 500026 Tapón reg. 3", pvc dren. u 60.16 101.72% 59.14INTDR 500027 Tapón reg. 4", pvc dren. u 107.50 101.72% 105.68

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 13

Page 14: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012

INTDR 500028 Tee 2"x 2", pvc dren. u 42.00 101.74% 41.28INTDR 500029 Tee 3"x3", pvc dren. u 71.10 101.73% 69.89INTDR 500030 Tee 4"x4", pvc dren. u 139.03 101.73% 136.67INTDR 500031 Tee 6"x6", pvc dren. u 1,279.06 101.72% 1,257.38INTDR 500032 Tee red. 3"x2", pvc dren. u 50.32 101.74% 49.46INTDR 500033 Tee red. 4"x3", pvc dren. u 89.24 101.72% 87.73INTDR 500034 Tee red. 4"x2", pvc dren. u 83.04 101.73% 81.63INTDR 500035 Tee red. 6"x3", pvc dren. u 2,260.23 101.72% 2,221.92INTDR 500036 Tee red. 6"x4", pvc dren. u 660.80 101.72% 649.60INTDR 500037 Tubo 1 ½"x19', pvc dren. u 127.44 101.72% 125.28INTDR 500038 Tubo 2"x19', pvc dren. u 155.65 101.72% 153.02INTDR 500039 Tubo 3"x19', pvc dren. u 298.04 101.72% 292.99INTDR 500040 Tubo 4"x19', pvc dren. u 383.71 101.72% 377.21INTDR 500041 Tubo 6"x19', pvc dren. u 1,052.80 101.72% 1,034.95INTDR 500042 Tubo 8"x19', pvc dren. u 2,460.30 101.72% 2,418.60INTDR 500043 Tubo 2"x19', pvc SDR-21 u 560.49 101.72% 550.99INTDR 500044 Tubo 3"x19', pvc SDR-21 u 1,261.42 101.72% 1,240.04INTDR 500045 Tubo 4"x19', pvc SDR-21 u 2,059.14 101.72% 2,024.23INTDR 500046 Tubo 6"x19', pvc SDR-21 u 4,436.84 101.72% 4,361.63INTDR 500047 Tubo 8"x19', pvc SDR-21 u 7,502.91 101.72% 7,375.74INTDR 500048 Tubo ½"x19', pvc SDR-26 u 61.80 101.73% 60.75INTDR 500049 Tubo ¾"x19', pvc SDR-26 u 86.15 101.72% 84.69INTDR 500050 Tubo 1"x19', pvc SDR-26 u 167.76 101.72% 164.92INTDR 500051 Tubo 1 ½"x19', pvc SDR-26 u 315.90 101.73% 310.54

500052 Tubo 2"x19', pvc SDR-26 u 389.40 101.72% 382.80INTDR 500053 Tubo 3"x19', pvc SDR-26 u 984.01 101.72% 967.34INTDR 500054 Tubo 4"x19', pvc SDR-26 u 1,601.71 101.72% 1,574.56INTDR 500055 Tubo 6"x19', pvc SDR-26 u 3,532.33 101.72% 3,472.46INTDR 500056 Tubo 8"x19', pvc SDR-26 u 6,206.38 101.72% 6,101.18INTDR 500057 Tubo 2"x19', pvc SDR-32.5 u 384.92 101.73% 378.39INTDR 500058 Tubo 3"x19', pvc SDR-32.5 u 848.66 101.72% 834.27INTDR 500059 Tubo 4"x19', pvc SDR-32.5 u 1,301.96 101.72% 1,279.90INTDR 500060 Tubo 6"x19', pvc SDR-32.5 u 2,797.00 101.72% 2,749.59INTDR 500061 Tubo 8"x19', pvc SDR-32.5 u 4,748.74 101.72% 4,668.26INTDR 500062 Tubo 2"x19', pvc SDR-41 u 249.77 101.72% 245.54INTDR 500063 Tubo 3"x19', pvc SDR-41 u 537.56 101.72% 528.45INTDR 500064 Tubo 4"x19', pvc SDR-41 u 873.01 101.72% 858.21INTDR 500065 Tubo 6"x19', pvc SDR-41 u 2,242.54 101.72% 2,204.53INTDR 500066 Tubo 8"x19', pvc SDR-41 u 3,785.84 101.72% 3,721.67INTDR 500067 Yee 2"x2", pvc dren. u 35.84 101.73% 35.23INTDR 500068 Yee 3"x3", pvc dren. u 80.83 101.72% 79.46INTDR 500069 Yee 4"x4", pvc dren. u 164.69 101.72% 161.90INTDR 500070 Yee 6"x6", pvc dren. u 1,636.54 101.72% 1,608.80INTDR 500071 Yee red. 3"x2", pvc dren. u 47.92 101.72% 47.11INTDR 500072 Yee red. 4"x2", pvc dren. u 70.03 101.71% 68.85INTDR 500073 Yee red. 4"x3", pvc dren. u 99.43 101.73% 97.74INTDR 500074 Yee red. 6"x4", pvc dren. u 1,001.82 101.72% 984.84

INTPR 510000 TUBERIAS Y PIEZAS PVC PRESION:INTPR 510001 Adapt. hembra ½", pvc presión u 4.32 101.65% 4.25INTPR 510002 Adapt. hembra ¾", pvc presión u 8.02 101.65% 7.89INTPR 510003 Adapt. hembra 1", pvc presión u 9.89 101.75% 9.72INTPR 510004 Adapt. hembra 1 ½", pvc presión u 18.82 101.73% 18.50INTPR 510005 Adapt. hembra 2", pvc presión u 30.80 101.72% 30.28INTPR 510006 Adapt. hembra 3", pvc presión u 57.84 101.72% 56.86INTPR 510007 Adapt. hembra 4", pvc presión u 70.67 101.73% 69.47INTPR 510008 Adapt. hembra 8", pvc presión u 1,911.78 101.72% 1,879.37INTPR 510009 Adapt. macho ½", pvc presión u 3.62 101.69% 3.56INTPR 510010 Adapt. macho ¾", pvc presión u 4.26 101.67% 4.19INTPR 510011 Adapt. macho 1", pvc presión u 7.87 101.68% 7.74INTPR 510012 Adapt. macho 1 ½", pvc presión u 14.75 101.72% 14.50INTPR 510013 Adapt. macho 2", pvc presión u 24.78 101.72% 24.36INTPR 510014 Adapt. macho 3", pvc presión u 66.67 101.72% 65.54INTPR 510015 Adapt. macho 4", pvc presión u 95.96 101.73% 94.33INTPR 510016 Adapt. macho 6", pvc presión u 304.15 101.73% 298.99INTPR 510017 Codo ½"x90, pvc presión u 5.19 101.76% 5.10INTPR 510018 Codo ¾"x90, pvc presión u 6.93 101.76% 6.81INTPR 510019 Codo 1"x90, pvc presión u 13.09 101.79% 12.86INTPR 510020 Codo 1 ½"x90, pvc presión u 37.00 101.70% 36.38INTPR 510021 Codo 2"x90, pvc presión u 40.82 101.74% 40.12INTPR 510022 Codo 3"x90, pvc presión u 153.23 101.72% 150.64INTPR 510023 Codo 4"x90, pvc presión u 265.50 101.72% 261.00INTPR 510024 Codo 6"x90, pvc presión u 601.41 101.72% 591.22INTPR 510025 Reduc. 1"x½", pvc presión u 4.66 101.75% 4.58INTPR 510026 Reduc. 1" x ¾'', pvc presión u 3.91 101.82% 3.84INTPR 510027 Reduc. 1 ½"x1", pvc presión u 16.52 101.72% 16.24INTPR 510028 Reduc. 2"x1", pvc presión u 29.50 101.72% 29.00INTPR 510029 Reduc. 3" x 1 ½'', pvc presión u 64.90 101.72% 63.80INTPR 510030 Reduc. 4"x2", pvc presión u 145.14 101.72% 142.68INTPR 510031 Reduc. 4"x3", pvc presión u 145.14 101.72% 142.68INTPR 510032 Tee ½", pvc presión u 6.34 101.77% 6.23INTPR 510033 Tee ¾", pvc presión u 9.44 101.72% 9.28INTPR 510034 Tee 1", pvc presión u 15.81 101.74% 15.54INTPR 510035 Tee 1 ½", pvc presión u 37.21 101.75% 36.57INTPR 510036 Tee 2", pvc presión u 56.25 101.72% 55.30INTPR 510037 Tee 3", pvc presión u 127.58 101.72% 125.42INTPR 510038 Tee 4", pvc presión u 253.70 101.72% 249.40INTPR 510039 Tee 6", pvc presión u 751.73 101.72% 738.99INTPR 510040 Tubo ½"x19', pvc SCH-40 u 142.90 101.72% 140.48INTPR 510041 Tubo ¾"x19', pvc SCH-40 u 190.05 101.72% 186.83INTPR 510042 Tubo 1"x19', pvc SCH-40 u 278.74 101.72% 274.02INTPR 510043 Tubo 1 ½"x19', pvc SCH-40 u 450.08 101.72% 442.45INTPR 510044 Tubo 2"x19', pvc SCH-40 u 600.30 101.72% 590.13INTPR 510045 Tubo 3"x19', pvc SCH-40 u 1,244.65 101.72% 1,223.56

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 14

Page 15: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUL 2012INTPR 510046 Tubo 4"x19', pvc SCH-40 u 2,155.67 101.72% 2,119.13INTPR 510047 Tubo 6"x19', pvc SCH-40 u 3,797.31 101.72% 3,732.95INTPR 510048 Unión univ. ½", pvc presión u 22.30 101.73% 21.92INTPR 510049 Unión univ. ¾", pvc presión u 34.52 101.74% 33.93INTPR 510050 Unión univ. 1", pvc presión u 52.04 101.72% 51.16INTPR 510051 Unión univ. 1 ½", pvc presión u 147.50 101.72% 145.00INTPR 510052 Unión univ. 2", pvc presión u 231.78 101.72% 227.85INTPR 510053 Unión univ. 3", pvc presión u 460.20 101.72% 452.40INTPR 510054 Unión univ. 4", pvc presión u 719.80 101.72% 707.60

INVEN 520000 VENTANAS DE ALUMINIO Y MASILLAS EN TUBO:INVEN 520001 Masilla blanca siliconada, tubo u 114.70 101.73% 112.75INVEN 520002 Masilla bronce siliconada, tubo u 95.23 101.73% 93.61INVEN 520003 Molduras alum. bce., base, para vidrios fijos. 19 pies m 109.79 101.72% 107.93INVEN 520004 Molduras alum. bce., tapa, para vidrios fijos. 19 pies m 66.49 101.71% 65.37INVEN 520005 Operador p/vent. manig. AA alum. nat. u 113.14 101.73% 111.22INVEN 520006 Operador p/vent. manig. AA alum. bce. u 113.61 101.73% 111.68INVEN 520007 Operador ojo p/vent. "estándar" alum. nat. u 31.12 101.73% 30.59INVEN 520008 Palo de 6' para operadores u 196.60 101.72% 193.27INVEN 520009 "Silicone" claro en tubo u 181.72 101.72% 178.64INVEN 520010 Transporte e instalación (Porcentaje sobre el costo) % 12.00% 100.00% 12.00%INVEN 520011 Tubular 4"x1 ¾" alum. anodiz. bce., 19 pie m 483.97 101.73% 475.76INVEN 520012 Tubular 4"x1 ¾" alum. anodiz. normal, 19 pie m 477.78 101.72% 469.68INVEN 520013 Tubular 4"x1 ¾" alum. bco., 19 pie m 545.82 101.72% 536.57INVEN 520014 Vent. abisagr. alum. anod. normal, v. claro mart. (w2.5 x h1.2 m.) m2 3,246.29 101.72% 3,191.26INVEN 520015 Vent. abisagr. alum. anod. normal, v. bce. mart. (w2.5 x h1.2 m.) m2 3,301.76 101.72% 3,245.80INVEN 520016 Vent. abisagr. alum. anod. bce., v. claro mart. (w2.5 x h1.2 m.) m2 3,331.14 101.72% 3,274.68INVEN 520017 Vent. abisagr. alum. anod. bce., v. bce. mart. (w2.5 x h1.2 m.) m2 3,386.77 101.72% 3,329.36INVEN 520018 Vent. corred. alum. anod. normal, v. claro mart. (w2.5 x h1.2 m.) m2 3,457.16 101.72% 3,398.57INVEN 520019 Vent. corred. alum. anod. normal, v. bce. mart. (w2.5 x h1.2 m.) m2 3,509.96 101.72% 3,450.47INVEN 520020 Vent. corred. alum. anod. normal, v. "Bluegreen" (w2.5 x h1.2 m.) m2 3,839.94 101.72% 3,774.86INVEN 520021 Vent. corred. alum. anod. normal, v. reflect. claro (w2.5 x h1.2 m.) m2 4,213.61 101.72% 4,142.20INVEN 520022 Vent. corred. alum. anod. normal, con espejo (w2.5 x h1.2 m.) m2 3,999.44 101.72% 3,931.66INVEN 520023 Vent. corred. alum. anod. bce., v. claro mart. (w2.5 x h1.2 m.) m2 3,004.76 101.72% 2,953.84INVEN 520024 Vent. corred. alum. anod. bce., v. bce. mart. (w2.5 x h1.2 m.) m2 3,057.57 101.72% 3,005.75INVEN 520025 Vent. corred. alum. anod. bce., v. reflectivo (w2.5 x h1.2 m.) m2 3,761.23 101.72% 3,697.48INVEN 520026 Vent. corred. alum. anod. bce., con espejo (w2.5 x h1.2 m.) m2 3,547.20 101.72% 3,487.08INVEN 520027 Vent. corred. alum. bco., v. claro (w2.5 x h1.2 m.) m2 3,497.86 101.72% 3,438.58INVEN 520028 Vent. corred. alum. bco., v. bce. liso (w2.5 x h1.2 m.) m2 3,603.30 101.72% 3,542.22INVEN 520029 Vent. corred. alum. bco., v. "Bluegreen" (w2.5 x h1.2 m.) m2 3,848.28 101.72% 3,783.05INVEN 520030 Vent. corred. alum. bco., v. reflect. claro (w2.5 x h1.2 m.) m2 4,005.26 101.72% 3,937.38INVEN 520031 Vent. corred. alum. bco., con espejo (w2.5 x h1.2 m.) m2 4,007.78 101.72% 3,939.85INVEN 520032 Vent. proyect. alum. anod. normal, v. claro mart. (w2.73 x h1.47 m.) m2 2,223.43 101.72% 2,185.74INVEN 520033 Vent. proyect. alum. anod. normal, v. bce. mart. (w2.73 x h1.47 m.) m2 2,280.40 101.72% 2,241.75INVEN 520034 Vent. proyect. alum. bce., v. claro mart. (w2.73 x h1.47 m.) m2 2,479.75 101.72% 2,437.72INVEN 520035 Vent. proyect. alum. bce., v. bce. mart. (w2.73 x h1.47 m.) m2 2,536.72 101.72% 2,493.72INVEN 520036 Vent. Salom AA manig, alum. blanco (w0.83 x h1.2 m.) m2 3,558.29 101.72% 3,497.98INVEN 520037 Vent. Salom AA manig, alum. Blanco, reforzada (w0.83 x h1.2 m.) m2 5,958.41 101.72% 5,857.42INVEN 520038 Vent. Salom AA manig, alum. bce., reforzada (w0.83 x h1.2 m.) m2 6,089.05 101.72% 5,985.84INVEN 520039 Vent. Salom AA manig, alum. bce. (w0.83 x h1.2 m.) m2 3,688.93 101.72% 3,626.40INVEN 520040 Vent. Salom AA manig, alum. nat. (w0.83 x h1.2 m.) m2 2,282.27 101.72% 2,243.59INVEN 520041 Vent. Salom AA manig, alum nat. v. claro (w0.83 x h1.2 m.) m2 4,176.48 101.72% 4,105.69INVEN 520042 Vent. Salom AA manig, alum nat., v. claro mart. (w0.83 x h1.2 m.) m2 4,017.39 101.72% 3,949.30INVEN 520043 Vent. Salom AA manig, alum nat., v. bce. mart. (w0.83 x h1.2 m.) m2 3,765.60 101.72% 3,701.78INVEN 520044 Vent. Salom AA manig, alum bco., v. claro (w0.83 x h1.2 m.) m2 3,914.69 101.72% 3,848.33INVEN 520045 Vent. Salom AA manig, alum bco., v. bce. mart. (w0.83 x h1.2 m.) m2 3,765.60 101.72% 3,701.78INVEN 520046 Vent. Salom AA manig, alum bce., vidrio claro mart. (w0.83 x h1.2 m.) m2 4,148.50 101.72% 4,078.19INVEN 520047 Vent. Salom AA manig, alum bce., vidrio bce. mart. (w0.83 x h1.2 m.) m2 3,896.70 101.72% 3,830.66INVEN 520048 Vent. Salom AA manig, alum bce. v. bce. liso (w0.83 x h1.2 m.) m2 4,172.17 101.72% 4,101.46INVEN 520049 Vent. Salom BB Pal. alum. blanco (w0.83 x h1.2 m.) m2 3,565.39 101.72% 3,504.96INVEN 520050 Vent. Salom BB Pal. alum. bce. (w0.83 x h1.2 m.) m2 2,290.79 101.72% 2,251.97INVEN 520051 Vent. Salom BB Pal. alum. nat. (w0.83 x h1.2 m.) m2 2,581.39 101.72% 2,537.64INVEN 520052 Vent. Salom BB Pal. alum. bco., v. bce. mart. (w0.83 x h1.2 m.) m2 3,194.79 101.72% 3,140.64INVEN 520053 Vent. Salom BB Pal. alum. bco., v. claro mart. (w0.83 x h1.2 m.) m2 3,446.59 101.72% 3,388.17INVEN 520054 Vent. Salom BB Pal. alum. bce., v. bce. mart. (w0.83 x h1.2 m.) m2 2,616.90 101.72% 2,572.54INVEN 520055 Vent. Salom BB Pal. alum. bce., v. claro mart. (w0.83 x h1.2 m.) m2 2,868.69 101.72% 2,820.06INVEN 520056 Vent. Salom BB Pal. alum. nat., v. claro (w0.83 x h1.2 m.) m2 3,055.65 101.72% 3,003.85INVEN 520057 Vent. Salom BB Pal. alum. nat., v. claro mart. (w0.83 x h1.2 m.) m2 3,200.48 101.72% 3,146.23INVEN 520058 Vent. Salom BB Pal. alum. nat., v. bce. mart. (w0.83 x h1.2 m.) m2 2,906.08 101.72% 2,856.82INVEN 520059 Vidrio bce. transp. o mart. de ¼" m2 982.92 101.72% 966.26INVEN 520060 Vidrio claro transp. o mart. de ¼" m2 856.87 101.72% 842.35

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 15

Page 16: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. HERRAMIENTASREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUN 2011

HERRAMIENTAS DE TRABAJO: (Ordenado alfabéticamente)HERALB 700000 HERRAMIENTAS PARA ALBAÑILERIA:HERALB 700001 Barra de fuerza 5 St. 55-150 u 2,891.00 101.72% 2,842.00HERALB 700002 Bordeador Surtek 123194 u 182.90 101.72% 179.80HERALB 700003 Cabo para zapapico, natural, 33", Ref. 1556/94 1565/94 u 212.40 101.72% 208.80HERALB 700004 Carretilla metal "Jeep", "Surtek", 5.5 p3, Mexicana u 3,422.00 101.72% 3,364.00HERALB 700005 Cincel St. Puntero 3/4"x12 18-043/16-319 u 306.80 101.72% 301.60HERALB 700006 Cincel St. Plano 3/4"x12 18-059/16-314 u 247.80 101.72% 243.60HERALB 700007 Cortadora de cerámica de 16" St. 94-809 u 3,481.00 101.72% 3,422.00HERALB 700008 Cortadora de cerámica de 24" St. 94-811 u 4,714.10 101.72% 4,634.20HERALB 700009 Cortadora de cerámica speed 75 IW14132 u 3,837.81 101.72% 3,772.76HERALB 700010 Cubeta plástica 5 gl., con tapa, para agua u 259.39 101.73% 254.99HERALB 700011 Cubo de goma #8 u 307.89 101.72% 302.67HERALB 700012 Cubo de goma #10 u 204.91 101.73% 201.43HERALB 700013 Escoba plástica c/mango Ames, 19260-70 u 452.67 101.72% 445.00HERALB 700014 Escuadra de aluminio 24"x2" St. 0445-300 u 389.40 101.72% 382.80HERALB 700015 Escuadra de metal 24"x2" St. 0445-600 u 333.94 101.72% 328.28HERALB 700016 Hilo de "nylon" No. 8, (1 lbr) u 106.29 101.72% 104.49HERALB 700017 Frota de goma c/madera u 48.65 101.71% 47.83HERALB 700018 Ligadora hidráulica, 2 fundas, 13 HP "Joper" u 133,421.38 101.72% 131,160.01HERALB 700019 Llana dentada 77375/115 u 316.24 101.72% 310.88HERALB 700020 Llana dentada Collins 24-500D u 312.70 101.72% 307.40HERALB 700021 Llana lisa 77370/115 u 316.24 101.72% 310.88HERALB 700022 Llana plástica 77380/118 u 127.44 101.72% 125.28HERALB 700023 Llana plástica c/esponja 77385/118 u 194.70 101.72% 191.40HERALB 700024 Mandarria "Stanley" 2 lb., Ref. 6456-399 u 401.20 101.72% 394.40HERALB 700025 Manguera reforzada p/jardín ¾" x 75' u 1,703.88 101.72% 1,675.01HERALB 700026 Pala cuadrada "Tramontina", Ref. 77472/424 u 377.60 101.72% 371.20HERALB 700027 Pala redonda "Tramontina", Ref. 77470/424 u 342.20 101.72% 336.40HERALB 700028 Pinza para mosaico 115 u 849.60 101.72% 835.20HERALB 700029 Plana p/albañil 6" 77358/065 u 139.24 101.72% 136.88HERALB 700030 Plana p/albañil 8" 77358/085 u 1,484.44 101.72% 1,459.28HERALB 700031 Plana p/albañil 9" 77358/095 u 159.30 101.72% 156.60HERALB 700032 Rastrillo curvo largo c/mango, Tramont. 77101/64, USA u 342.20 101.72% 336.40HERALB 700033 Tanque plástico de 55 gl., para agua u 885.00 101.72% 870.00HERALB 700034 Zapapico "Tramontina", 5 lb., sin cabo, Ref. 77303/503, 5 lb. u 489.70 101.72% 481.40

HERCAR 710000 HERRAMIENTAS PARA CARPINTERIA:HERCAR 710001 Pata de cabra 5/8" x 18" St. 0455-118 u 371.70 101.72% 365.40HERCAR 710002 Pata de cabra 5/8" x 24" St. 0455-124 u 531.00 101.72% 522.00HERCAR 710003 Pata de cabra 5/8" x 30" St. 0455-130 u 601.80 101.72% 591.60HERCAR 710004 Pata de cabra 5/8" x 36" St. 0455-136 u 578.20 101.72% 568.40HERCAR 710005 Serrucho Luctador 22" St. 15-472 u 247.80 101.72% 243.60HERCAR 710006 Serrucho Luctador 24" St. 15-473 u 277.30 101.72% 272.60HERCAR 710007 Serrucho Profesional 22" St. 15-560 u 460.20 101.72% 452.40

HERELE 720000 HERRAMIENTAS PARA ELECTRICIDAD:HERELE 720001 Doblador de tubos 1" 35225 u 4,395.50 101.72% 4,321.00HERELE 720002 Doblador de tubos 3/4" 35220 u 2,832.00 101.72% 2,784.00HERELE 720003 Doblador de tubos mult. 6, 8, 10 mm 7610000 u 924.83 101.72% 909.15

HERMED 730000 HERRAMIENTAS PARA MEDIR:HERMED 730001 Medidor con 1 rueda, DIGITAL, St. 77-176 u 5,310.00 101.72% 5,220.00HERMED 730002 Medidor con 2 ruedas MW-20M 84-77175 u 2,271.50 101.72% 2,233.00HERMED 730003 Pie de rey digital 6" St. 78-440 u 2,153.50 101.72% 2,117.00HERMED 730004 Pie de rey manual 6" St. 78-201 u 991.20 101.72% 974.40

HERPIN 740000 HERRAMIENTAS PARA PINTURA:HERPIN 740001 Bandeja plástica c/rolo Roma 640-00 u 159.30 101.72% 156.60HERPIN 740002 Bandeja plástica sin rolo Roma 420-23 u 50.74 101.72% 49.88HERPIN 740003 Brocha Durawork Prof. 1 1/2" u 61.15 101.73% 60.11HERPIN 740004 Brocha Durawork Prof. 3" u 153.52 101.72% 150.92HERPIN 740005 Brocha Durawork Prof. 3/4" u 23.61 101.72% 23.21HERPIN 740006 Brocha Durawork Prof. 4" u 221.82 101.72% 218.06HERPIN 740007 Brocha Durawork Prof. 5" u 230.10 101.72% 226.20HERPIN 740008 Espátula de metal, St. 1 1/2" 6028-080 u 73.16 101.72% 71.92HERPIN 740009 Espátula de metal, St. 2 1/2" 6028-082 u 80.24 101.72% 78.88HERPIN 740010 Espátula de metal, St. 2" 6028-081 u 82.60 101.72% 81.20HERPIN 740011 Espátula de metal, St. 3" 6028-083 u 88.50 101.72% 87.00HERPIN 740012 Espátula de metal, St. 4" 6028-084 u 97.94 101.72% 96.28HERPIN 740013 Espátula de metal, St. 5" 6028-085 u 108.56 101.72% 106.72HERPIN 740014 Espátula plástica 6" Lanco PA-157-19 u 21.51 101.70% 21.15HERPIN 740015 Espátula plástica 7 x 9 cms. Roma 230-M u 8.26 101.72% 8.12HERPIN 740016 Espátula plástica 9 x 13 cms. Roma 230-GG u 14.16 101.72% 13.92HERPIN 740017 Extensión telesc. alum. 1.5 m., Roma 1500 u 204.14 101.72% 200.68HERPIN 740018 Extensión telesc. alum. 3.0 m., Roma 3000 u 265.50 101.72% 261.00HERPIN 740019 Extensión telesc. alum. 4-8' 1309137 u 429.32 101.72% 422.04HERPIN 740020 Extensión telesc. alum. 4-8' 1309178 u 702.10 101.72% 690.20HERPIN 740021 Extensión telesc. alum. 8' 27AB u 361.99 101.73% 355.85HERPIN 740022 Mota p/rolo 9 1/4" Perfect u 52.04 101.72% 51.16HERPIN 740023 Mota p/rolo antigota 23 Ccms. Roma 825-23 u 141.60 101.72% 139.20HERPIN 740024 Mota p/rolo antigota Lanco PA-580-19/581-19 u 153.41 101.72% 150.81HERPIN 740025 Mota p/rolo p/esmalte, 9 1 1/4", Lanco u 88.89 101.73% 87.38HERPIN 740026 Mota p/rolo p/sup. rugosa, 9 3/4", Lanco u 74.55 101.72% 73.29HERPIN 740027 Mota p/rolo pelo carnero Roma 270-1 u 238.36 101.72% 234.32HERPIN 740037 Portarolo prof. Lanco PA-576-19 u 82.60 101.72% 81.20

HERPLO 750000 HERRAMIENTAS PARA PLOMERIA:HERPLO 750001 Avellanador ST 95IB93-040 u 719.80 101.72% 707.60HERPLO 750002 Llave Stillson 8" St. 95IB87-621 u 318.60 101.72% 313.20HERPLO 750003 Llave Stillson 10" St. 95IB87-622 u 584.10 101.72% 574.20HERPLO 750004 Llave Stillson 12" St. 95IB87-623 u 507.40 101.72% 498.80HERPLO 750005 Llave Stillson 14" St. 95IB87-624 u 613.60 101.72% 603.20

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 16

Page 17: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. HERRAMIENTASREFERENCIA D E S C R I P C I O N U. P.U. + ITBIS INDICE JUN 2011

HERPLO 750006 Llave Stillson 18" St. 95IB87-625 u 896.80 101.72% 881.60HERPLO 750007 Llave Stillson 24" St. 95IB87-626 u 1,357.00 101.72% 1,334.00HERPLO 750008 Llave Stillson 36" St. 95IB87-627 u 2,743.50 101.72% 2,697.00HERPLO 750009 Llave Stillson S. Ego 48" 1024800 u 11,434.20 101.72% 11,240.40HERPLO 750010 Llave ajustable 6" Negra St. 89-045 u 226.56 101.72% 222.72HERPLO 750011 Llave ajustable 8" Negra St. 89-046 u 259.60 101.72% 255.20HERPLO 750012 Llave ajustable 10" cromo St. 87-433 u 454.30 101.72% 446.60HERPLO 750013 Llave ajustable 12" cromo St. 87-434 u 584.10 101.72% 574.20HERPLO 750014 Llave ajustable 15" cromo St. 87-435 u 1,056.10 101.72% 1,038.20HERPLO 750015 Llave ajustable 18" 44022/118 u 3,445.60 101.72% 3,387.20HERPLO 750016 Llave combinada 14 mm 9786-859 u 330.60 101.72% 325.00HERPLO 750017 Corta PVC 0 a 1-5/8" St. 95IB14-442 u 908.60 101.72% 893.20HERPLO 750018 Tijera corta tubo PVC 568 5680200 u 1,905.70 101.72% 1,873.40

HERSEG 760000 HERRAMIENTAS PARA SEGURIDAD:HERSEG 760001 Bota de goma # 9 Goliat I, baja u 375.65 101.72% 369.29HERSEG 760002 Bota de goma #10 Goliat II, alta u 394.77 101.72% 388.08HERSEG 760003 Bota de goma #11 Goliat I, baja u 375.65 101.72% 369.29HERSEG 760004 Bota de goma #12 Goliat I, baja u 375.65 101.72% 369.29HERSEG 760005 Bota de goma #41 Aguila u 954.27 101.72% 938.09HERSEG 760006 Bota de goma #43 Aguila u 954.27 101.72% 938.09HERSEG 760007 Capa p/agua, c/pantalón, verde GR332G u 609.58 101.73% 599.24HERSEG 760008 Capa p/agua, tipo bata, amarilla, GR331Y u 473.32 101.72% 465.30HERSEG 760009 Capa p/agua, tipo bata, verde, GR331G u 473.32 101.72% 465.30HERSEG 760010 Careta p/esmerilar 9014-2 u 424.80 101.72% 417.60HERSEG 760011 Cartucho p/amoníaco 9-244 u 188.80 101.72% 185.60HERSEG 760012 Cartucho p/gas 9-243 u 141.60 101.72% 139.20HERSEG 760013 Cartucho p/humo 9-246 u 141.60 101.72% 139.20HERSEG 760014 Cartucho p/pintura 9-245 u 147.50 101.72% 145.00HERSEG 760015 Cartucho p/plaguicida 9248 u 147.50 101.72% 145.00HERSEG 760016 Cartucho p/vapores orgánicos 9-241 u 141.60 101.72% 139.20HERSEG 760017 Casco ind. Arseg c/rachet, blanco, 10096AR9 u 483.80 101.72% 475.60HERSEG 760018 Casco p/obrero, amarillo 5131AM amarillo u 135.70 101.72% 133.40HERSEG 760019 Casco p/obrero, naranja 5131NA naranja u 135.70 101.72% 133.40HERSEG 760020 Casco p/obrero, rojo 5131RJ u 188.80 101.72% 185.60HERSEG 760021 Cinturón de seguridad 9-017-1 u 2,537.00 101.72% 2,494.00HERSEG 760022 Cinturón de seguridad 9-017-4 u 7,670.00 101.72% 7,540.00HERSEG 760023 Cinturón de seguridad 9-058 u 1,475.00 101.72% 1,450.00HERSEG 760024 Cinturón ergonómico p/fuerza 9-071/S, L, M, X u 601.80 101.72% 591.60HERSEG 760025 Mascarilla cara completa 9-035 u 2,596.00 101.72% 2,552.00HERSEG 760026 Mascarilla de seguridad Arseg 18000 u 306.80 101.72% 301.60HERSEG 760027 Mascarilla desechable B627/B626/112 u 7.38 101.79% 7.25HERSEG 760028 Monogafas transparentes 9007 u 141.60 101.72% 139.20HERSEG 760029 Protector auditivo DPG62 u 944.00 101.72% 928.00HERSEG 760030 Respirador doble c/visor 9-00038-2 u 578.20 101.72% 568.40HERSEG 760031 Respirador p/polvo 10-012 u 64.90 101.72% 63.80HERSEG 760032 Respirador p/polvo D 9-018-2 u 271.40 101.72% 266.80HERSEG 760033 Respirador sencillo c/visor 900038 u 460.20 101.72% 452.40HERSEG 760034 Respirador sencillo s/cartucho 9-038 u 206.50 101.72% 203.00HERSEG 760035 Timeliner for eyes smoke u 470.99 101.73% 463.00

HERSUB 770000 HERRAMIENTAS PARA SUBIR:HERALB 770001 Diferencial eléctrico 2,000 kilos, 2SS-1G-15 151067 u 133,512.93 101.72% 131,250.00HERALB 770002 Escalera 8-16' Ext. Aluminio 554-16 u 4,248.00 101.72% 4,176.00HERALB 770003 Escalera 10-20' Ext. Aluminio 494-20 u 6,018.00 101.72% 5,916.00HERALB 770004 Escalera 12-24' Ext. Aluminio 494-24 u 7,729.00 101.72% 7,598.00HERALB 770005 Escalera 4' tipo tijera alum. Reforz. 708-04 u 1,976.50 101.72% 1,943.00HERALB 770006 Escalera 5' tipo tijera alum. Reforz. 708-05 u 2,283.30 101.72% 2,244.60HERALB 770007 Escalera 6' tipo tijera alum. Reforz. 708-06 u 2,596.00 101.72% 2,552.00HERALB 770008 Escalera 8' tipo tijera alum. Reforz. 708-08 u 4,041.50 101.72% 3,973.00HERALB 770009 Escalera 10' fibra 686-10 F1510 u 10,148.00 101.72% 9,976.00

HERVAR 780000 HERRAMIENTAS PARA VARILLAS:HERVAR 780001 Cizalla 18" St. 14-318/14-376 u 1,298.00 101.72% 1,276.00HERVAR 780002 Cizalla 24" St. 14-324/14-377 u 1,687.40 101.72% 1,658.80HERVAR 780003 Cizalla 36" St. 14-336/14-379 u 2,891.00 101.72% 2,842.00HERVAR 780004 Cizalla p/cortar varillas CR-22 u 15,576.00 101.72% 15,312.00HERVAR 780005 Cizalla p/cortar varillas CR-28 u 23,364.00 101.72% 22,968.00HERVAR 780015 Cizalla p/cortar varillas CR-32 u 25,960.00 101.72% 25,520.00

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 17

Page 18: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. REND. MAT.REFERENCIA D E S C R I P C I O N U. REND.RENDI 5000000 RENDIMIENTO DE MATERIALES

RENDI 5020000 ACEROS Y ALAMBRES GALVANIZADOS:RENDI 5020100 Alambre galv. #10, 1.00 lb. (Datos de Ferretería Americana) m / lb 5.49RENDI 5020200 Alambre galv. #12, 1.00 lb. (Datos de Ferretería Americana) m / lb 5.49RENDI 5020300 Alambre galv. #14, 1.00 lb. (Datos de Ferretería Americana) m / lb 8.54RENDI 5020400 Alambre galv. #16, 1.00 lb. (Datos de Ferretería Americana) m / lb 43.90RENDI 5020500 Alambre galv. #18, 1.00 lb. (Datos de Ferretería Americana) m / lb 43.90RENDI 5020300 Atado varillas redondas 3/8" x 20' 20 qq 22.26RENDI 5020301 Atado varillas redondas 3/8" x 25' 25 qq 22.28RENDI 5020302 Atado varillas redondas 3/8" x 30' 30 qq 22.11RENDI 5020303 Atado varillas redondas 3/8" x 35' 35 qqRENDI 5020304 Atado varillas redondas 3/8" x 40' 40 qq 22.26RENDI 5020305 Atado varillas redondas 3/8" x 45' 45 qqRENDI 5020306 Atado varillas redondas 3/8" x 50' 50 qqRENDI 5020400 Atado varillas redondas 1/2" x 20' 20 qq 22.18RENDI 5020401 Atado varillas redondas 1/2" x 25' 25 qq 22.21RENDI 5020402 Atado varillas redondas 1/2" x 30' 30 qq 22.24RENDI 5020403 Atado varillas redondas 1/2" x 35' 35 qq 22.21RENDI 5020404 Atado varillas redondas 1/2" x 40' 40 qq 22.18RENDI 5020405 Atado varillas redondas 1/2" x 45' 45 qqRENDI 5020406 Atado varillas redondas 1/2" x 50' 50 qqRENDI 5020500 Atado varillas redondas 3/4" x 20' 20 qq 22.23RENDI 5020501 Atado varillas redondas 3/4" x 25' 25 qq 22.53RENDI 5020502 Atado varillas redondas 3/4" x 30' 30 qq 22.53RENDI 5020503 Atado varillas redondas 3/4" x 35' 35 qq 22.08RENDI 5020504 Atado varillas redondas 3/4" x 40' 40 qq 22.23RENDI 5020505 Atado varillas redondas 3/4" x 45' 45 qq 22.30RENDI 5020506 Atado varillas redondas 3/4" x 50' 50 qq 22.53RENDI 5020600 Atado varillas redondas 1" x 20' 20 qq 22.43RENDI 5020601 Atado varillas redondas 1" x 25' 25 qq 22.70RENDI 5020602 Atado varillas redondas 1" x 30' 30 qq 22.43RENDI 5020603 Atado varillas redondas 1" x 35' 35 qq 22.43RENDI 5020604 Atado varillas redondas 1" x 40' 40 qq 22.43RENDI 5020605 Atado varillas redondas 1" x 45' 45 qq 22.83RENDI 5020606 Atado varillas redondas 1" x 50' 50 qqRENDI 5020700 Cant. varillas redondas por Atado 3/8" x 20' 20 u 296RENDI 5020701 Cant. varillas redondas por Atado 3/8" x 25' 25 u 237RENDI 5020702 Cant. varillas redondas por Atado 3/8" x 30' 30 u 196RENDI 5020703 Cant. varillas redondas por Atado 3/8" x 35' 35 uRENDI 5020704 Cant. varillas redondas por Atado 3/8" x 40' 40 u 148RENDI 5020705 Cant. varillas redondas por Atado 3/8" x 45' 45 uRENDI 5020706 Cant. varillas redondas por Atado 3/8" x 50' 50 uRENDI 5020800 Cant. varillas redondas por Atado 1/2" x 20' 20 u 166RENDI 5020801 Cant. varillas redondas por Atado 1/2" x 25' 25 u 133RENDI 5020802 Cant. varillas redondas por Atado 1/2" x 30' 30 u 111RENDI 5020803 Cant. varillas redondas por Atado 1/2" x 35' 35 u 95RENDI 5020804 Cant. varillas redondas por Atado 1/2" x 40' 40 u 83RENDI 5020805 Cant. varillas redondas por Atado 1/2" x 45' 45 uRENDI 5020806 Cant. varillas redondas por Atado 1/2" x 50' 50 uRENDI 5020900 Cant. varillas redondas por Atado 3/4" x 20' 20 u 74RENDI 5020901 Cant. varillas redondas por Atado 3/4" x 25' 25 u 60RENDI 5020902 Cant. varillas redondas por Atado 3/4" x 30' 30 u 50RENDI 5020903 Cant. varillas redondas por Atado 3/4" x 35' 35 u 42RENDI 5020904 Cant. varillas redondas por Atado 3/4" x 40' 40 u 37RENDI 5020905 Cant. varillas redondas por Atado 3/4" x 45' 45 u 33RENDI 5020906 Cant. varillas redondas por Atado 3/4" x 50' 50 u 30RENDI 5021000 Cant. varillas redondas por Atado 1" x 20' 20 u 42RENDI 5021001 Cant. varillas redondas por Atado 1" x 25' 25 u 34RENDI 5021002 Cant. varillas redondas por Atado 1" x 30' 30 u 28RENDI 5021003 Cant. varillas redondas por Atado 1" x 35' 35 u 24RENDI 5021004 Cant. varillas redondas por Atado 1" x 40' 40 u 21RENDI 5021005 Cant. varillas redondas por Atado 1" x 45' 45 u 19RENDI 5021006 Cant. varillas redondas por Atado 1" x 50' 50 uRENDI 5021100 Cant. varillas redondas por Quintal 3/8" x 20' 20 u 13.30RENDI 5021101 Cant. varillas redondas por Quintal 3/8" x 25' 25 u 10.64RENDI 5021102 Cant. varillas redondas por Quintal 3/8" x 30' 30 u 8.87RENDI 5021103 Cant. varillas redondas por Quintal 3/8" x 35' 35 u 7.60RENDI 5021104 Cant. varillas redondas por Quintal 3/8" x 40' 40 u 6.65RENDI 5021105 Cant. varillas redondas por Quintal 3/8" x 45' 45 u 5.91RENDI 5021106 Cant. varillas redondas por Quintal 3/8" x 50' 50 u 5.32RENDI 5021200 Cant. varillas redondas por Quintal 1/2" x 20' 20 u 7.49RENDI 5021201 Cant. varillas redondas por Quintal 1/2" x 25' 25 u 5.99RENDI 5021202 Cant. varillas redondas por Quintal 1/2" x 30' 30 u 4.99RENDI 5021203 Cant. varillas redondas por Quintal 1/2" x 35' 35 u 4.28RENDI 5021204 Cant. varillas redondas por Quintal 1/2" x 40' 40 u 3.74RENDI 5021205 Cant. varillas redondas por Quintal 1/2" x 45' 45 u 3.33RENDI 5021206 Cant. varillas redondas por Quintal 1/2" x 50' 50 u 2.99RENDI 5021300 Cant. varillas redondas por Quintal 3/4" x 20' 20 u 3.33RENDI 5021301 Cant. varillas redondas por Quintal 3/4" x 25' 25 u 2.66RENDI 5021302 Cant. varillas redondas por Quintal 3/4" x 30' 30 u 2.22RENDI 5021303 Cant. varillas redondas por Quintal 3/4" x 35' 35 u 1.90RENDI 5021304 Cant. varillas redondas por Quintal 3/4" x 40' 40 u 1.66RENDI 5021305 Cant. varillas redondas por Quintal 3/4" x 45' 45 u 1.48RENDI 5021306 Cant. varillas redondas por Quintal 3/4" x 50' 50 u 1.33RENDI 5021400 Cant. varillas redondas por Quintal 1" x 20' 20 u 1.87RENDI 5021401 Cant. varillas redondas por Quintal 1" x 25' 25 u 1.50RENDI 5021402 Cant. varillas redondas por Quintal 1" x 30' 30 u 1.25RENDI 5021403 Cant. varillas redondas por Quintal 1" x 35' 35 u 1.07RENDI 5021404 Cant. varillas redondas por Quintal 1" x 40' 40 u 0.94RENDI 5021405 Cant. varillas redondas por Quintal 1" x 45' 45 u 0.83RENDI 5021406 Cant. varillas redondas por Quintal 1" x 50' 50 u 0.75RENDI 5021500 Peso en Quintales, varillas redondas 3/8" x 20' 20 u 0.0752

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 18

Page 19: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. REND. MAT.REFERENCIA D E S C R I P C I O N U. REND.RENDI 5021501 Peso en Quintales, varillas redondas 3/8" x 25' 25 u 0.0940RENDI 5021502 Peso en Quintales, varillas redondas 3/8" x 30' 30 u 0.1128RENDI 5021503 Peso en Quintales, varillas redondas 3/8" x 35' 35 u 0.1316RENDI 5021504 Peso en Quintales, varillas redondas 3/8" x 40' 40 u 0.1504RENDI 5021505 Peso en Quintales, varillas redondas 3/8" x 45' 45 u 0.1692RENDI 5021506 Peso en Quintales, varillas redondas 3/8" x 50' 50 u 0.1880RENDI 5021600 Peso en Quintales, varillas redondas 1/2" x 20' 20 u 0.1336RENDI 5021601 Peso en Quintales, varillas redondas 1/2" x 25' 25 u 0.1670RENDI 5021602 Peso en Quintales, varillas redondas 1/2" x 30' 30 u 0.2004RENDI 5021603 Peso en Quintales, varillas redondas 1/2" x 35' 35 u 0.2338RENDI 5021604 Peso en Quintales, varillas redondas 1/2" x 40' 40 u 0.2672RENDI 5021605 Peso en Quintales, varillas redondas 1/2" x 45' 45 u 0.3006RENDI 5021606 Peso en Quintales, varillas redondas 1/2" x 50' 50 u 0.3340RENDI 5021700 Peso en Quintales, varillas redondas 3/4" x 20' 20 u 0.3004RENDI 5021701 Peso en Quintales, varillas redondas 3/4" x 25' 25 u 0.3755RENDI 5021702 Peso en Quintales, varillas redondas 3/4" x 30' 30 u 0.4506RENDI 5021703 Peso en Quintales, varillas redondas 3/4" x 35' 35 u 0.5257RENDI 5021704 Peso en Quintales, varillas redondas 3/4" x 40' 40 u 0.6008RENDI 5021705 Peso en Quintales, varillas redondas 3/4" x 45' 45 u 0.6759RENDI 5021706 Peso en Quintales, varillas redondas 3/4" x 50' 50 u 0.7510RENDI 5021800 Peso en Quintales, varillas redondas 1" x 20' 20 u 0.5340RENDI 5021801 Peso en Quintales, varillas redondas 1" x 25' 25 u 0.6675RENDI 5021802 Peso en Quintales, varillas redondas 1" x 30' 30 u 0.8010RENDI 5021803 Peso en Quintales, varillas redondas 1" x 35' 35 u 0.9345RENDI 5021804 Peso en Quintales, varillas redondas 1" x 40' 40 u 1.0680RENDI 5021805 Peso en Quintales, varillas redondas 1" x 45' 45 u 1.2015RENDI 5021806 Peso en Quintales, varillas redondas 1" x 50' 50 u 1.3350

RENDI 5040000 BLOQUES:RENDI 5040001 Bloques de cualquier tipo 20 x 40 cms. u / m2 12.50RENDI 5040002 Medios Bloques 20 x 20 cms. u / m2 25.00

RENDI 5060000 CAL, CEMENTOS, ADITIVOS, CURADORES, ENDURECEDORES, SELLADORES:RENDI 5060001 Aditivo imperm. P/horm. 180 kg/cm2 "SX-PEL", 5 gl. gl / m3 0.26RENDI 5060002 Aditivo imperm. P/horm. 210 kg/cm2 "SX-PEL", 5 gl. gl / m3RENDI 5060003 Aditivo imperm. P/horm. 240 kg/cm2 "SX-PEL", 5 gl. gl / m3RENDI 5060004 Aditivo imperm. P/horm. 280 kg/cm2 "SX-PEL", 5 gl. gl / m3RENDI 5060005 Aditivo retard. "SX-KRETE-R", 5 gl. gl / m3 0.2063RENDI 5060006 Cal "Pomier" o similar, 50 lbs. (en mortero empañete) fda / m3 3.06RENDI 5060007 Curad., sellad. "SUPRACURE PLUS", 5 gl., 20 m2/gl. gl / m2 0.05RENDI 5060008 Curad., sellad., endur. "SUPRACURE", 5gls., 20 m2/gl. gl / m2 0.05RENDI 5060009 Endur. Met. / pisos "DURAPLATE NR", 100 lb., .10 m2/lb. Lb / m2 0.10RENDI 5060010 Resina epóxica "Pro-flex" para junta de piso, 231 pulg.3/gl. gl / pulg3 0.004329RENDI 5060011 Sellad. horm. visto "SUPRACURE PX", 5gl., 20 m2/gl. gl / m2 0.05

RENDI 5080000 CEMENTO PVC (NUMERO DE JUNTAS POR GL.):RENDI 5080001 En ½" juntas 2,800.00RENDI 5080002 En ¾" juntas 1,600.00RENDI 5080003 En 1" juntas 1,200.00RENDI 5080004 En 1 ½" juntas 640.00RENDI 5080005 En 2" juntas 360.00RENDI 5080006 En 3" juntas 280.00RENDI 5080007 En 4" juntas 200.00RENDI 5080008 En 6" juntas 64.00RENDI 5080009 En 8" juntas 32.00RENDI 5080010 En 10" juntas 24.00RENDI 5080011 En 12" juntas 16.00

RENDI 5100000 CEMENTO PVC (NUMERO DE JUNTAS POR KILO):RENDI 5100001 En ½" juntas 700.00RENDI 5100002 En ¾" juntas 400.00RENDI 5100003 En 1" juntas 300.00RENDI 5100004 En 1 ½" juntas 160.00RENDI 5100005 En 2" juntas 90.00RENDI 5100006 En 3" juntas 70.00RENDI 5100007 En 4" juntas 50.00RENDI 5100008 En 6" juntas 16.00RENDI 5100009 En 8" juntas 8.00RENDI 5100010 En 10" juntas 6.00RENDI 5100011 En 12" juntas 4.00

RENDI 5120000 CEMENTO PVC (NUMERO DE JUNTAS POR PINTA):RENDI 5120001 En ½" juntas 350.00RENDI 5120002 En ¾" juntas 200.00RENDI 5120003 En 1" juntas 150.00RENDI 5120004 En 1 ½" juntas 80.00RENDI 5120005 En 2" juntas 45.00RENDI 5120006 En 3" juntas 35.00RENDI 5120007 En 4" juntas 25.00RENDI 5120008 En 6" juntas 8.00RENDI 5120009 En 8" juntas 4.00RENDI 5120010 En 10" juntas 3.00RENDI 5120011 En 12" juntas 2.00

RENDI 5140000 CLAVOS (CANTIDAD x LIBRA):RENDI 5140001 Clavos acero 1" lb 445.00RENDI 5140002 Clavos acero 1 ½" lb 137.00RENDI 5140003 Clavos acero 2" lb 105.00RENDI 5140004 Clavos acero 2 ½" lb 75.00RENDI 5140005 Clavos acero 3" lb 67.00RENDI 5140006 Clavos acero 4" lb 52.00RENDI 5140007 Clavos corrientes ¾" lb 2,064.00RENDI 5140008 Clavos corrientes 1" lb 1,513.00RENDI 5140009 Clavos corrientes 1 ½" lb 445.00

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 19

Page 20: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. REND. MAT.REFERENCIA D E S C R I P C I O N U. REND.RENDI 5140010 Clavos corrientes 2" lb 206.00RENDI 5140011 Clavos corrientes 2 ½" lb 87.00RENDI 5140012 Clavos corrientes 3" lb 63.00RENDI 5140013 Clavos corrientes 4" lb 29.00RENDI 5140014 Clavos galv. para cartón ¾" lb 322.00RENDI 5140015 Clavos de zinc 2 ½" lb 56.00

RENDI 5160000 IMPERMEABILIZANTES:RENDI 5160001 ALM, lata de 5 gl. gl / m2 0.09RENDI 5160002 Bitupol instalado, 3 mm., reforz. fibra vidrio, 5 años gar. rollo / m2RENDI 5160003 Bitupol instalado, 3 mm., reforz. con poliester, 10 años gar. rollo / m2RENDI 5160004 Bitupol instalado, 4 mm., reforz. con poliester, 10 años gar. rollo / m2RENDI 5160005 Sellador de techo "Popular" gl / m2 0.09RENDI 5160006 Sellador de techo "Sureseal", import., lata 5 gl. gl / m2 0.09RENDI 5160007 Sellador de techo "Lanco", import., lata 5 gl. gl / m2 0.09RENDI 5160008 Silicool, lata 5 gl., Criollo, (2 manos) gl / m2 0.09

RENDI 5180000 MATERIALES INSTALADOS:RENDI 5180001 Caballete en teja asfáltica instalado a todo costo rollo / mRENDI 5180002 Línea doble teja asfáltica instalada a todo costo, en bordes rollo / mRENDI 5180003 Teja asfáltica 3' x 1' instalada todo costo rollo / m2

RENDI 5200000 PINTURAS:RENDI 5200001 Acrílica, 2 manos gl / m2 0.100RENDI 5200002 Aguarrás en 2 manos pintura mantenimiento gl / m2 0.080RENDI 5200003 Epóxica gl / m2 0.080RENDI 5200004 Latex "Económica" o "Pintex", 2 manos gl / m2 0.100RENDI 5200005 Mantenimiento, 2 manos gl / m2 0.080RENDI 5200006 Oxido Rojo, 2 manos gl / m2 0.080RENDI 5200007 "Thinner" en 2 manos pintura mantenimiento gl / m2 0.130

RENDI 5220000 PISOS, ADOQUINES Y TABLETAS:RENDI 5220001 Adoquín 500-80 AGUAYO 10 x 20 cm. aprox. u / m2 50.000RENDI 5220002 Adoquín 511 AGUAYO tipo paleta u / m2 39.000RENDI 5220003 Adoquín 604 AGUAYO 10.20 x 20.20 cm. aprox. u / m2 48.530RENDI 5220004 Adoquín clásico 10x20x20 cm. u / m2 25.000RENDI 5220005 Adoquín colonial 05x20x20 cm. u / m2 50.000RENDI 5220006 Adoquín mediterraneo gris u / m2 36.650RENDI 5220007 Adoquín olympus 08x12x23 cm. u / m2 36.230RENDI 5220008 Derretido p/pisos de granito fda / m2 0.03125RENDI 5220009 Baldosa de .10 x .10 m. u / m2 100.000RENDI 5220010 Baldosa de .125 x .20 m. u / m2 40.000RENDI 5220011 Baldosa de .125 x .25 m. u / m2 32.000RENDI 5220012 Baldosa de .15 x .15 m. u / m2 44.440RENDI 5220013 Baldosa de .15 x .20 m. u / m2 33.333RENDI 5220014 Baldosa de .20 x .20 m. u / m2 25.000RENDI 5220015 Baldosa de .20 x .25 m. u / m2 20.000RENDI 5220016 Baldosa de .20 x .30 m. u / m2 16.667RENDI 5220017 Baldosa de .20 x .40 m. u / m2 12.500RENDI 5220018 Baldosa de .20 x .50 m. u / m2 10.000RENDI 5220019 Baldosa de .25 x .25 m. u / m2 16.000RENDI 5220020 Baldosa de .25 x .30 m. u / m2 13.333RENDI 5220021 Baldosa de .25 x .40 m. u / m2 10.000RENDI 5220022 Baldosa de .25 x .50 m. u / m2 8.000RENDI 5220023 Baldosa de .30 x .30 m. u / m2 11.110RENDI 5220024 Baldosa de .30 x .40 m. u / m2 8.333RENDI 5220025 Baldosa de .30 x .50 m. u / m2 6.667RENDI 5220026 Baldosa de .30 x .60 m. u / m2 5.550RENDI 5220027 Baldosa de .40 x .40 m. u / m2 6.250RENDI 5220028 Baldosa de .40 x .50 m. u / m2 5.000RENDI 5220029 Baldosa de .40 x .60 m. u / m2 4.170RENDI 5220030 Baldosa de .40 x .80 m. u / m2 3.125RENDI 5220031 Baldosa de .50 x .50 m. u / m2 4.000RENDI 5220032 Baldosa de .50 x .60 m. u / m2 3.333RENDI 5220033 Baldosa de .50 x .70 m. u / m2 2.857RENDI 5220034 Baldosa de .50 x .80 m. u / m2 2.500RENDI 5220035 Baldosa de .50 x .90 m. u / m2 2.222RENDI 5220036 Baldosa de .50 x 1.00 m. u / m2 2.000RENDI 5220037 Tabletas 20 x 40 cm. u / m2 12.500RENDI 5220038 Zócalos de cualquier alto x .15 m. u / m 6.667RENDI 5220039 Zócalos de cualquier alto x .20 m. u / m 5.000RENDI 5220040 Zócalos de cualquier alto x .25 m. u / m 4.000RENDI 5220041 Zócalos de cualquier alto x .30 m. u / m 3.333RENDI 5220042 Zócalos de cualquier alto x .33 m. u / m 3.000RENDI 5220043 Zócalos de cualquier alto x .40 m. u / m 2.500RENDI 5220044 Zócalos de cualquier alto x .50 m. u / m 2.000RENDI 5220045 Zócalos de cualquier alto x .60 m. u / m 1.667RENDI 5220046 Zócalos de cualquier alto x .70 m. u / m 1.430RENDI 5220047 Zócalos de cualquier alto x .80 m. u / m 1.250RENDI 5220048 Zócalos de cualquier alto x .90 m. u / m 1.111RENDI 5220049 Zócalos de cualquier alto x 1.00 m. u / m 1.000RENDI 5220050 Derretido p/cerámica (rinde 25 m2/fda.) fda / m2 0.150RENDI 5220051 Pegamento K18 fda / m2 6.500RENDI 5220052 Perfil esquinero PVC u / m 0.400

RENDI 5240000 TEFLON: Diám. Tub. # Vueltas Unid. Long.RENDI 5240001 Rollo teflón (Longitud del rollo) m 4.800RENDI 5240002 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 1 rollo 0.029924RENDI 5240003 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 2 rollo 0.059847RENDI 5240004 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 3 rollo 0.089771RENDI 5240005 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 4 rollo 0.119695RENDI 5240006 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 5 rollo 0.149618RENDI 5240007 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 6 rollo 0.179542RENDI 5240008 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 7 rollo 0.209466

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 20

Page 21: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. REND. MAT.REFERENCIA D E S C R I P C I O N U. REND.RENDI 5240009 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 8 rollo 0.239389RENDI 5240010 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 9 rollo 0.269313RENDI 5240011 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 10 rollo 0.299237RENDI 5240012 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 1 rollo 0.039898RENDI 5240013 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 2 rollo 0.079796RENDI 5240014 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 3 rollo 0.119695RENDI 5240015 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 4 rollo 0.159593RENDI 5240016 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 5 rollo 0.199491RENDI 5240017 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 6 rollo 0.239389RENDI 5240018 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 7 rollo 0.279288RENDI 5240019 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 8 rollo 0.319186RENDI 5240020 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 9 rollo 0.359084RENDI 5240021 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 10 rollo 0.398982RENDI 5240022 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 1 rollo 0.059847RENDI 5240023 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 2 rollo 0.119695RENDI 5240024 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 3 rollo 0.179542RENDI 5240025 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 4 rollo 0.239389RENDI 5240026 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 5 rollo 0.299237RENDI 5240027 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 6 rollo 0.359084RENDI 5240028 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 7 rollo 0.418931RENDI 5240029 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 8 rollo 0.478779RENDI 5240030 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 9 rollo 0.538626RENDI 5240031 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 10 rollo 0.598473RENDI 5240032 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1 rollo 0.079796RENDI 5240033 Rollo teflón (Rend. según diámetro y # de vueltas) 1 2 rollo 0.159593RENDI 5240034 Rollo teflón (Rend. según diámetro y # de vueltas) 1 3 rollo 0.239389RENDI 5240035 Rollo teflón (Rend. según diámetro y # de vueltas) 1 4 rollo 0.319186RENDI 5240036 Rollo teflón (Rend. según diámetro y # de vueltas) 1 5 rollo 0.398982RENDI 5240037 Rollo teflón (Rend. según diámetro y # de vueltas) 1 6 rollo 0.478779RENDI 5240038 Rollo teflón (Rend. según diámetro y # de vueltas) 1 7 rollo 0.558575RENDI 5240039 Rollo teflón (Rend. según diámetro y # de vueltas) 1 8 rollo 0.638372RENDI 5240040 Rollo teflón (Rend. según diámetro y # de vueltas) 1 9 rollo 0.718168RENDI 5240041 Rollo teflón (Rend. según diámetro y # de vueltas) 1 10 rollo 0.797965RENDI 5240042 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 1 rollo 0.099746RENDI 5240043 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 2 rollo 0.199491RENDI 5240044 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 3 rollo 0.299237RENDI 5240045 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 4 rollo 0.398982RENDI 5240046 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 5 rollo 0.498728RENDI 5240047 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 6 rollo 0.598473RENDI 5240048 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 7 rollo 0.698219RENDI 5240049 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 8 rollo 0.797965RENDI 5240050 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 9 rollo 0.897710RENDI 5240051 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 10 rollo 0.997456RENDI 5240052 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 1 rollo 0.119695RENDI 5240053 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 2 rollo 0.239389RENDI 5240054 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 3 rollo 0.359084RENDI 5240055 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 4 rollo 0.478779RENDI 5240056 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 5 rollo 0.598473RENDI 5240057 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 6 rollo 0.718168RENDI 5240058 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 7 rollo 0.837863RENDI 5240059 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 8 rollo 0.957557RENDI 5240060 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 9 rollo 1.077252RENDI 5240061 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 10 rollo 1.196947RENDI 5240062 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1 rollo 0.159593RENDI 5240063 Rollo teflón (Rend. según diámetro y # de vueltas) 2 2 rollo 0.319186RENDI 5240064 Rollo teflón (Rend. según diámetro y # de vueltas) 2 3 rollo 0.478779RENDI 5240065 Rollo teflón (Rend. según diámetro y # de vueltas) 2 4 rollo 0.638372RENDI 5240066 Rollo teflón (Rend. según diámetro y # de vueltas) 2 5 rollo 0.797965RENDI 5240067 Rollo teflón (Rend. según diámetro y # de vueltas) 2 6 rollo 0.957557RENDI 5240068 Rollo teflón (Rend. según diámetro y # de vueltas) 2 7 rollo 1.117150RENDI 5240069 Rollo teflón (Rend. según diámetro y # de vueltas) 2 8 rollo 1.276743RENDI 5240070 Rollo teflón (Rend. según diámetro y # de vueltas) 2 9 rollo 1.436336RENDI 5240071 Rollo teflón (Rend. según diámetro y # de vueltas) 2 10 rollo 1.595929RENDI 5240072 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 1 rollo 0.199491RENDI 5240073 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 2 rollo 0.398982RENDI 5240074 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 3 rollo 0.598473RENDI 5240075 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 4 rollo 0.797965RENDI 5240076 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 5 rollo 0.997456RENDI 5240077 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 6 rollo 1.196947RENDI 5240078 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 7 rollo 1.396438RENDI 5240079 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 8 rollo 1.595929RENDI 5240080 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 9 rollo 1.795420RENDI 5240081 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 10 rollo 1.994911RENDI 5240082 Rollo teflón (Rend. según diámetro y # de vueltas) 3 1 rollo 0.239389RENDI 5240083 Rollo teflón (Rend. según diámetro y # de vueltas) 3 2 rollo 0.478779RENDI 5240084 Rollo teflón (Rend. según diámetro y # de vueltas) 3 3 rollo 0.718168RENDI 5240085 Rollo teflón (Rend. según diámetro y # de vueltas) 3 4 rollo 0.957557RENDI 5240086 Rollo teflón (Rend. según diámetro y # de vueltas) 3 5 rollo 1.196947RENDI 5240087 Rollo teflón (Rend. según diámetro y # de vueltas) 3 6 rollo 1.436336RENDI 5240088 Rollo teflón (Rend. según diámetro y # de vueltas) 3 7 rollo 1.675726RENDI 5240089 Rollo teflón (Rend. según diámetro y # de vueltas) 3 8 rollo 1.915115RENDI 5240090 Rollo teflón (Rend. según diámetro y # de vueltas) 3 9 rollo 2.154504RENDI 5240091 Rollo teflón (Rend. según diámetro y # de vueltas) 3 10 rollo 2.393894RENDI 5240092 Rollo teflón (Rend. según diámetro y # de vueltas) 4 1 rollo 0.319186RENDI 5240093 Rollo teflón (Rend. según diámetro y # de vueltas) 4 2 rollo 0.638372RENDI 5240094 Rollo teflón (Rend. según diámetro y # de vueltas) 4 3 rollo 0.957557RENDI 5240095 Rollo teflón (Rend. según diámetro y # de vueltas) 4 4 rollo 1.276743RENDI 5240096 Rollo teflón (Rend. según diámetro y # de vueltas) 4 5 rollo 1.595929RENDI 5240097 Rollo teflón (Rend. según diámetro y # de vueltas) 4 6 rollo 1.915115RENDI 5240098 Rollo teflón (Rend. según diámetro y # de vueltas) 4 7 rollo 2.234301RENDI 5240099 Rollo teflón (Rend. según diámetro y # de vueltas) 4 8 rollo 2.553487RENDI 5240100 Rollo teflón (Rend. según diámetro y # de vueltas) 4 9 rollo 2.872672RENDI 5240101 Rollo teflón (Rend. según diámetro y # de vueltas) 4 10 rollo 3.191858RENDI 5240102 Rollo teflón (Rend. según diámetro y # de vueltas) 6 1 rollo 0.478779

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 21

Page 22: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. REND. MAT.REFERENCIA D E S C R I P C I O N U. REND.RENDI 5240103 Rollo teflón (Rend. según diámetro y # de vueltas) 6 2 rollo 0.957557RENDI 5240104 Rollo teflón (Rend. según diámetro y # de vueltas) 6 3 rollo 1.436336RENDI 5240105 Rollo teflón (Rend. según diámetro y # de vueltas) 6 4 rollo 1.915115RENDI 5240106 Rollo teflón (Rend. según diámetro y # de vueltas) 6 5 rollo 2.393894RENDI 5240107 Rollo teflón (Rend. según diámetro y # de vueltas) 6 6 rollo 2.872672RENDI 5240108 Rollo teflón (Rend. según diámetro y # de vueltas) 6 7 rollo 3.351451RENDI 5240109 Rollo teflón (Rend. según diámetro y # de vueltas) 6 8 rollo 3.830230RENDI 5240110 Rollo teflón (Rend. según diámetro y # de vueltas) 6 9 rollo 4.309008RENDI 5240111 Rollo teflón (Rend. según diámetro y # de vueltas) 6 10 rollo 4.787787RENDI 5240112 Rollo teflón (Rend. según diámetro y # de vueltas) 8 1 rollo 0.638372RENDI 5240113 Rollo teflón (Rend. según diámetro y # de vueltas) 8 2 rollo 1.276743RENDI 5240114 Rollo teflón (Rend. según diámetro y # de vueltas) 8 3 rollo 1.915115RENDI 5240115 Rollo teflón (Rend. según diámetro y # de vueltas) 8 4 rollo 2.553487RENDI 5240116 Rollo teflón (Rend. según diámetro y # de vueltas) 8 5 rollo 3.191858RENDI 5240117 Rollo teflón (Rend. según diámetro y # de vueltas) 8 6 rollo 3.830230RENDI 5240118 Rollo teflón (Rend. según diámetro y # de vueltas) 8 7 rollo 4.468601RENDI 5240119 Rollo teflón (Rend. según diámetro y # de vueltas) 8 8 rollo 5.106973RENDI 5240120 Rollo teflón (Rend. según diámetro y # de vueltas) 8 9 rollo 5.745345RENDI 5240121 Rollo teflón (Rend. según diámetro y # de vueltas) 8 10 rollo 6.383716

RENDI 5260000 TRANSPORTE BLOQUES / VIAJERENDI 5260001 Bintel 6"x8"x 8", medio bloque u 1,600.000RENDI 5260002 Bintel 8"x8"x 8", medio bloque u 1,200.000RENDI 5260003 Bloque 4"x8"x16" u 1,200.000RENDI 5260004 Bloque 5"x8"x16" u 960.000RENDI 5260005 Bloque 6"x8"x 8", liso (½ bloque 6") u 1,600.000RENDI 5260006 Bloque 6"x8"x16" u 800.000RENDI 5260007 Bloque 6"x8"x16", texturizado u 800.000RENDI 5260008 Bloque 8"x8"x 8", liso (½ bloque 8") u 1,200.000RENDI 5260009 Bloque 8"x8"x16" u 600.000RENDI 5260010 Bloque 8"x8"x16", texturizado u 600.000RENDI 5260011 Bloque 12"x8"x 8", liso (½ bloque 12") u 800.000RENDI 5260012 Bloque 12"x8"x16" u 400.000RENDI 5260013 Bloque calado 6" tipo persiana u 800.000RENDI 5260014 Bloque decorativo 6"x8"x16" u 800.000RENDI 5260015 Bloque decorativo 8"x8"x16" u 600.000RENDI 5260016 Bloviga 6"x8"x16" u 800.000RENDI 5260017 Bloviga 8"x8"x16" u 600.000

RENDI 5280000 TRANSPORTE PIEZAS DE GRANITO / VIAJERENDI 5280001 Lavaderos dobles (1.40 m. hasta 1.60 m.) u 12.000RENDI 5280002 Lavaderos sencillos (0.80 m. hasta 1.20 m.) u 20.000RENDI 5280003 Vertederos (0.40 m. hasta 0.60 m.) u 20.000

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 22

Page 23: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOAL 6000000 M.O. ALBAÑILERIA

*MOAL 6000100 M.O. ALB., ACCESORIOS DE BAÑOS, INST.:*MOAL 6000101 Montar accesorio atornillado 150.60 100.00% u 10.00 1 1 150.60*MOAL 6000102 Montar accesorio empotrado 215.14 100.00% u 7.00 1 1 215.14*MOAL 6000103 Montar botiquín corriente empotrado 602.40 100.00% u 2.50 1 1 602.40*MOAL 6000104 Montar botiquín corriente, superficie 167.33 100.00% u 9.00 1 1 167.33*MOAL 6000105 Montar botiquín lujo empotrado 1,506.00 100.00% u 1.00 1 1 1,506.00*MOAL 6000106 Montar botiquín lujo superficie 1,004.00 100.00% u 1.50 1 1 1,004.00*MOAL 6000107 Montar papelera porta servilletas 150.60 100.00% u 10.00 1 1 150.60*MOAL 6000108 Montar repisa corriente para baño 251.00 100.00% u 6.00 1 1 251.00

*MOAL 6000200 M.O. ALB., ACERA Y CONTENES:*MOAL 6000201 Base para contenes Telford con mezcla 359.43 100.00% m3 3.50 1 1 359.43*MOAL 6000202 Const. acera frot., viol., .10 m. esp., coloc. horm. 1,217.56 100.00% m3 2.05 1 1 1 1 1,217.56*MOAL 6000203 Contén con bordillo 25x15 cm 113.45 100.00% m 22.00 1 1 1 1 113.45*MOAL 6000204 Contén con bordillo 30x8x10 cm 78.00 100.00% m 32.00 1 1 1 1 78.00*MOAL 6000205 Contén con bordillo 40 cm alto x 20 cm ancho 192.00 100.00% m 13.00 1 1 1 1 192.00*MOAL 6000206 Contén de 55x30x15 cm 126.70 100.00% m 19.70 1 1 1 1 126.70

*MOAL 6000300 M.O. ALB., ADICIONAL P/PLANTA, COLOC.:*MOAL 6000301 Albañilería por cada piso (según unid de cada partida) 5.00% u 5.00%

*MOAL 6000400 M.O. ALB., BADENES Y COLECTORES:

*MOAL 6000401Badén ciclópeo hasta 40 cm ancho, 10 a 20 cm esp., frotado, pulido en centro (sin varillas) 998.40 100.00% m3 2.50 1 1 1 1 998.40

*MOAL 6000402Badén ciclópeo hasta 40 cm ancho, > 20 cm esp., frotado, pulido en centro (sin varillas) 998.40 100.00% m3 2.50 1 1 1 1 998.40

*MOAL 6000202 Conf. anillo de filtrante 687.67 100.00% u 3.00 1 1 1 687.67

*MOAL 6000203Conf. tapa colector o pozo séptico, encofrado, envarillado, vaciado, coloc. tapa, hasta 2.00 metros cuadrados 1,146.11 100.00% u 1.80 1 1 1 1,146.11

*MOAL 6000204Conf. tapa colector o pozo séptico, encofrado, envarillado, vaciado, coloc. tapa, > 2.00 m2 (Precio proporc.)

P. A. P. A.

*MOAL 6000205 Conf. tragante de hasta 50 cm long. 468.86 100.00% u 4.40 1 1 1 468.86*MOAL 6000203 Const. pozo séptico, incluyendo terminación P. A. u P. A.*MOAL 6000204 Const zapatas y piso colector horm., envarillado y frotado 998.40 100.00% m3 2.50 1 1 1 1 998.40

*MOAL 6000500 M.O. ALB., BLOQUES, COLOCACION*MOAL 6000501 Coloc. bloque 4x 8 x16 pulgs. 14.85 100.00% u 125.00 1 1 1 14.85*MOAL 6000502 Coloc. bloque 5x8x16 pulgs. 11.60 100.00% u 160.00 1 1 1 11.60*MOAL 6000503 Coloc. bloque 6x8x16 pulgs. 12.37 100.00% u 150.00 1 1 1 12.37*MOAL 6000504 Coloc. bloque 6x8x18 pulgs. 13.75 100.00% u 135.00 1 1 1 13.75*MOAL 6000505 Coloc. bloque 8x8x16 pulgs. 13.75 100.00% u 135.00 1 1 1 13.75*MOAL 6000506 Coloc. bloque 12x8x16 pulgs. 25.43 100.00% u 90.00 1 1 1 1 25.43*MOAL 6000507 Coloc. bloque ornamental 5x25x20 pulgs. 21.19 100.00% u 75.00 1 1 21.19*MOAL 6000508 Coloc. bloque ornamental barro o cemento 27.38 100.00% u 55.00 1 1 27.38*MOAL 6000509 Coloc. bloque cristal 75.30 100.00% u 20.00 1 1 75.30*MOAL 6000510 Coloc. bloque irregular 27.88 100.00% u 57.00 1 1 27.88*MOAL 6000511 Violinar junta horiz. y vert. con regla (cada cara) 1.65 100.00% u 785.00 1 1 1.65

*MOAL 6000600 M.O. ALB., DESAGÜES:*MOAL 6000601 Conf. desagüe 20x20 cm cubierto 216.50 100.00% u 6.00 1 1 216.50*MOAL 6000602 Conf. desagüe 20x20 cm descubierto 129.90 100.00% u 10.00 1 1 129.90

*MOAL 6000700 M.O. ALB., EMPAÑETES, TERM. PAREDES Y TECHOS:*MOAL 6000701 Bajo relieve, incluye canto 173.20 100.00% m 7.50 1 1 173.20*MOAL 6000702 Canto 43.30 100.00% m 30.00 1 1 43.30*MOAL 6000703 Capitel 20 a 30 cm P. A. u 1 1 P. A.*MOAL 6000704 Careteo con llana 23.62 100.00% m2 55.00 1 1 23.62*MOAL 6000705 Cornisa, hasta 12 cm, cemento 229.22 100.00% m 9.00 1 1 1 229.22*MOAL 6000706 Empañete columnas desde 20 cm ancho en adelante 185.73 100.00% m2 15.00 1 1 1 1 185.73*MOAL 6000707 Empañete ext., maestrado, a plomo (sin andamios) 126.64 100.00% m2 22.00 1 1 1 1 126.64*MOAL 6000708 Empañete HI-RIB, 3 capas 206.30 100.00% m2 10.00 1 1 1 206.30*MOAL 6000709 Empañete int., en paredes, maestrado, a plomo 99.50 100.00% m2 28.00 1 1 1 1 99.50*MOAL 6000710 Empañete pulido a color 121.35 100.00% m2 17.00 1 1 1 121.35*MOAL 6000711 Empañete pulido sin color 108.58 100.00% m2 19.00 1 1 1 108.58*MOAL 6000712 Empañete rasgado 171.92 100.00% m2 12.00 1 1 1 171.92*MOAL 6000713 Empañete rateado horiz. y vertical, punta llana 44.19 100.00% m2 42.00 1 1 1 44.19*MOAL 6000714 Empañete techos y vigas 128.95 100.00% m2 20.00 1 1 1 1 128.95*MOAL 6000715 Empañete techos, maestrado, a nivel, 2 cm Mín. 142.28 100.00% m2 14.50 1 1 1 142.28*MOAL 6000716 Enpañete en ladrillos P. A. m2 1 1 1 P. A.*MOAL 6000717 Estría 81.19 100.00% m 16.00 1 1 81.19*MOAL 6000718 Fragüache con escoba 14.94 100.00% m2 69.00 1 1 14.94*MOAL 6000719 Gotero colgante 99.92 100.00% m 13.00 1 1 99.92*MOAL 6000720 Gotero en ranura 86.60 100.00% m 15.00 1 1 86.60*MOAL 6000721 Lágrima en cemento 188.25 100.00% m2 8.00 1 1 188.25*MOAL 6000722 Marmolina con piedras 257.88 100.00% m2 8.00 1 1 1 257.88*MOAL 6000723 Marmolina frotada 206.30 100.00% m2 10.00 1 1 1 206.30*MOAL 6000724 Natilla 57.92 100.00% m2 26.00 1 1 57.92*MOAL 6000725 Perrilla 206.30 100.00% m2 10.00 1 1 1 206.30*MOAL 6000726 Repello maestrado paredes 59.05 100.00% m2 22.00 1 1 59.05*MOAL 6000727 Repello maestrado techo, hasta 2 cm esp. 99.31 100.00% m2 16.00 1 1 99.31*MOAL 6000728 Repello sin maestrar 28.24 100.00% m2 46.00 1 1 28.24*MOAL 6000729 Resane con goma 35.69 100.00% m2 52.00 1 1 1 35.69*MOAL 6000730 Resane frotado 22.40 100.00% m2 58.00 1 1 22.40*MOAL 6000731 Rústico con escoba, plana o llana (sin repello) 75.30 100.00% m2 20.00 1 1 75.30*MOAL 6000732 Rústico en decoraciones P. A. m2 P. A.*MOAL 6000733 Term medio punto o arcos hasta 40 cm, 2 caras, fondo, cantos 687.67 100.00% m 3.00 1 1 1 687.67*MOAL 6000734 Vuelo aistlado de .80 hasta 2.00 m. 182.96 100.00% m 7.10 1 1 182.96

*MOAL 6000800 M.O. ALB., ESCALONES:PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 23

Page 24: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOAL 6000801 Confección escalón y revestir en ladrillo 386.15 100.00% m 3.90 1 1 386.15*MOAL 6000802 Escalón revestido cerám. criolla, H. y C. H. y vuelo 404.08 100.00% m 4.90 1 2 404.08*MOAL 6000803 Escalón revestido cerám. import., H. y C. H. y vuelo 495.00 100.00% m 4.00 1 2 495.00*MOAL 6000804 Escalón revestido en mezcla 162.38 100.00% m 8.00 1 1 162.38*MOAL 6000805 Montar escalón en accesos de granito 215.14 100.00% m 7.00 1 1 215.14*MOAL 6000806 Montar escalón escalera (H. y C. H.) 188.25 100.00% m 8.00 1 1 188.25*MOAL 6000807 Revestir escalón en ladrillo 317.05 100.00% m 4.75 1 1 317.05*MOAL 6000808 Revestir escalón en mosaico 158.53 100.00% m 9.50 1 1 158.53*MOAL 6000809 Terminar escalón de cemento 96.22 100.00% m 13.50 1 1 96.22

*MOAL 6000900 M.O. ALB., INST. VENTANAS: (ITBIS incluido por subcontrato)*MOAL 6000901 Inst. ventana alum., altura normal 9.74 101.78% p2 100.00 1 9.57*MOAL 6000902 Inst. ventana alum. con escalera o andamio 11.73 101.73% p2 83.00 1 11.53

*MOAL 6001000 M.O. ALB., LABORES VARIAS:*MOAL 6001001 Acuñe de marco 136.74 100.00% u 9.50 1 1 136.74*MOAL 6001002 Coloc. caballete de tejas 206.30 100.00% m 10.00 1 1 1 206.30*MOAL 6001003 Coloc. Teja 257.88 100.00% m2 8.00 1 1 1 257.88*MOAL 6001004 Corte y amarre varilla bloques a 020 m. 1.65 100.00% u 785.00 1 1 1.65*MOAL 6001005 Corte y amarre varilla bloques a 0.40 m. 1.11 100.00% u 1,175.00 1 1 1.11*MOAL 6001006 Corte y amarre varilla bloques a 0.60 m. 0.83 100.00% u 1,565.00 1 1 0.83*MOAL 6001007 Corte y amarre varilla bloques a 0.80 m. 0.55 100.00% u 2,350.00 1 1 0.55*MOAL 6001008 Llenar hueco bloque a 020 m. 4.12 100.00% u 315.00 1 1 4.12*MOAL 6001009 Llenar hueco bloque a 0.40 m. 2.22 100.00% u 585.00 1 1 2.22*MOAL 6001010 Llenar hueco bloque a 0.60 m. 1.65 100.00% u 785.00 1 1 1.65*MOAL 6001011 Llenar hueco bloque a 0.80 m. 1.11 100.00% u 1,175.00 1 1 1.11*MOAL 6001012 Montura "Brissoleil" de 05x40x200 m. 577.33 100.00% m2 3.00 1 1 1 577.33

*MOAL 6001100 M.O. ALB., LADRILLOS:*MOAL 6001101 Arco de ladrillo P. A. P. A.*MOAL 6001102 Ladrillo limpio 1 cara 7.53 100.00% u 200.00 1 1 7.53*MOAL 6001103 Ladrillo limpio 2 caras 9.59 100.00% u 157.00 1 1 9.59*MOAL 6001104 Ladrillo no especificado 7.17 100.00% u 210.00 1 1 7.17*MOAL 6001105 Ladrillo para empañetar en muros 5.28 100.00% u 285.00 1 1 5.28*MOAL 6001106 Ladrillo refractario 5x10x25 cm 7.93 100.00% u 190.00 1 1 7.93

*MOAL 6001200 M.O. ALB., LAVADEROS Y VERT.:*MOAL 6001201 Lavadero pulido hasta .60x1.5 m., Const. 2,312.00 100.00% u 1.00 1 1 1 2,312.00*MOAL 6001202 Lavadero pulido, > 1.5 m., adicional / recipiente, Const. 1,156.00 100.00% u 2.00 1 1 1 1,156.00*MOAL 6001203 Lavadero, 1 y 2 bocas, con azulejos arriba, Const. P. A. P. A.*MOAL 6001204 Vertedero 60x60 cm, azulejos, Conf. 1,939.00 100.00% u 1.00 1 1 1 1,939.00*MOAL 6001205 Vertedero 60x60 cm, pulido, Conf. 866.00 100.00% u 1.50 1 1 866.00

*MOAL 6001300 M.O. ALB., MALLA CICLONICA (ZAB., TUBOS, MALLA, PALOMETAS, ALAMBRE PUAS):*MOAL 6001301 Coloc. malla ciclónica 3' 245.50 100.00% m 10.00 1 1 2 245.50*MOAL 6001302 Coloc. malla ciclónica 4' 272.78 100.00% m 9.00 1 1 2 272.78*MOAL 6001303 Coloc. malla ciclónica 6' 288.82 100.00% m 8.50 1 1 2 288.82*MOAL 6001304 Coloc. malla ciclónica 7' 303.09 100.00% m 8.10 1 1 2 303.09*MOAL 6001305 Coloc. malla ciclónica 10' 316.37 100.00% m 7.76 1 1 2 316.37

*MOAL 6001400 M.O. ALB., MARMOL:*MOAL 6001401 Mármol criollo en escaleras 376.50 100.00% m 4.00 1 1 376.50*MOAL 6001402 Mármol criollo en revest. paredes 602.40 100.00% m2 2.50 1 1 602.40*MOAL 6001403 Marmol en pedazos 502.00 100.00% m2 3.00 1 1 502.00*MOAL 6001404 Mármol fachaico en 1sola pieza 602.40 100.00% m2 2.50 1 1 602.40*MOAL 6001405 Mármol import. en escaleras 463.38 100.00% m 3.25 1 1 463.38*MOAL 6001406 Mármol import. en revest. paredes 700.47 100.00% m2 2.15 1 1 700.47*MOAL 6001407 Mármol picado 1,158.46 100.00% m2 1.30 1 1 1,158.46*MOAL 6001408 Marmol travertino en tiritas 753.00 100.00% m2 2.00 1 1 753.00

*MOAL 6001500 M.O. ALB., PIEDRA:*MOAL 6001501 Piedra caliza aserrada 430.29 100.00% m2 3.50 1 1 430.29*MOAL 6001502 Piedra caliza labrada 376.50 100.00% m2 4.00 1 1 376.50*MOAL 6001503 Piedra blanca (San Cristóbal, Cambita, Azulada, La Cumbre, Callao de rio, etc.) 430.29 100.00% m2 3.50 1 1 430.29*MOAL 6001504 Roca o cantos rodados, muros mampost., con fines decor. 1,585.26 100.00% m3 0.95 1 1 1,585.26*MOAL 6001505 Roca o cantos rodados en muros mampostería 552.77 100.00% m3 2.35 1 1 552.77

*MOAL 6001506Roca o cantos rodados, tipo encache, 20 a 30 cm espesor, revest. terraplenes, canales y cunetas 147.61 100.00% m2 8.80 1 1 147.61

*MOAL 6001507Roca o cantos rodados, tipo encache, 20 a 30 cm espesor, revest. terraplenes, con fines decorativos 391.17 100.00% m2 3.85 1 1 391.17

*MOAL 6001600 M.O. ALB., PISOS Y ZOCALOS:*MOAL 6001601 Piso Adoquines 68.45 100.00% m2 22.00 1 1 68.45*MOAL 6001602 Piso Cemento pulido (fino solo) 59.05 100.00% m2 22.00 1 1 59.05*MOAL 6001603 Piso Cerám. criolla 15x15 hasta 20x20 cm, sin base y nivel 251.00 100.00% m2 6.00 1 1 251.00*MOAL 6001604 Piso Cerám. criolla 15x15 hasta 20x20 cm, + base y nivel 301.20 100.00% m2 5.00 1 1 301.20*MOAL 6001605 Piso Cerám. criolla 30x30 hasta 40x40 cm, sin base y nivel 286.86 100.00% m2 5.25 1 1 286.86*MOAL 6001606 Piso Cerámica criolla 30x30 hasta 40x40 cm, + base y nivel 350.23 100.00% m2 4.30 1 1 350.23*MOAL 6001607 Piso Cerámica import. 15x15 hasta 20x20 cm, sin base y nivel 264.21 100.00% m2 5.70 1 1 264.21*MOAL 6001608 Piso Cerámica import. 15x15 hasta 20x20 cm, + base y nivel 317.05 100.00% m2 4.75 1 1 317.05*MOAL 6001609 Piso Cerámica import. 30x30 hasta 40x40 cm, sin base y nivel 327.39 100.00% m2 4.60 1 1 327.39*MOAL 6001610 Piso Cerámica import. 30x30 hasta 40x40 cm, + base y nivel 376.50 100.00% m2 4.00 1 1 376.50*MOAL 6001611 Piso Horm. ESTAMPADO, terminación superficie 221.96 100.00% m2 10.3125 1 1 1 1 221.96*MOAL 6001612 Piso Horm. frotado 10 cm esp. 95.38 100.00% m2 24.00 1 1 1 1 95.38*MOAL 6001613 Piso Horm. frotado y violinado, 10 cm esp. 127.17 100.00% m2 18.00 1 1 1 1 127.17*MOAL 6001614 Piso Horm. pulido, violinado, 10 cm esp. 134.65 100.00% m2 17.00 1 1 1 1 134.65*MOAL 6001615 Piso Loseta ladrillo 12 ½x25 cm 171.14 100.00% m2 8.80 1 1 171.14*MOAL 6001616 Piso Loseta ladrillo 15x15 y 20x20 cm 171.14 100.00% m2 8.80 1 1 171.14*MOAL 6001617 Piso Loseta ladrillo o cemento / pisos exagonales, ferias y otros 221.47 100.00% m2 6.80 1 1 221.47*MOAL 6001618 Piso Loseta mármol criollo, base y nivel 361.14 100.00% m2 4.40 1 1 361.14*MOAL 6001619 Piso Loseta mármol imp., base y nivel 418.16 100.00% m2 3.80 1 1 418.16*MOAL 6001620 Piso Mosaico 20x20 cm y 25x25 cm, corriente 137.53 100.00% m2 15.00 1 1 1 137.53

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 24

Page 25: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOAL 6001621 Piso Mosaico en cartabón 187.55 100.00% m2 11.00 1 1 1 187.55*MOAL 6001622 Piso Mosaico en plumilla 187.55 100.00% m2 11.00 1 1 1 187.55*MOAL 6001623 Piso Mosaico granito 25x25 cm 147.36 100.00% m2 14.00 1 1 1 147.36*MOAL 6001624 Piso Mosaico granito 30x30 cm 158.69 100.00% m2 13.00 1 1 1 158.69*MOAL 6001625 Piso Mosaico granito 33x33 cm 158.69 100.00% m2 13.00 1 1 1 158.69*MOAL 6001626 Piso Mosaico granito 40x40 cm 187.55 100.00% m2 11.00 1 1 1 187.55*MOAL 6001627 Piso Mosaico granito 50x50 cm 196.48 100.00% m2 10.50 1 1 1 196.48*MOAL 6001628 Piso Mosaico granito en plumilla o cartabón 196.48 100.00% m2 10.50 1 1 1 196.48*MOAL 6001629 Piso Mosaico gravilla 20x20 cm 137.53 100.00% m2 15.00 1 1 1 137.53*MOAL 6001630 Piso Mosaico gravilla 25x25 cm 137.53 100.00% m2 15.00 1 1 1 137.53*MOAL 6001631 Piso Mosaico gravilla 30x30 cm 147.36 100.00% m2 14.00 1 1 1 147.36*MOAL 6001632 Piso Mosaico gravilla 40x40 cm 158.69 100.00% m2 13.00 1 1 1 158.69*MOAL 6001633 Piso Mosaico gravilla 50x50 cm 187.55 100.00% m2 11.00 1 1 1 187.55*MOAL 6001634 Piso Rejonado pulido, sin color 95.38 100.00% m2 24.00 1 1 1 1 95.38*MOAL 6001635 Piso Rejonado pulido y marcado a hilo, color 127.17 100.00% m2 18.00 1 1 1 1 127.17*MOAL 6001636 Piso Rejonado sin pulir 81.75 100.00% m2 28.00 1 1 1 1 81.75*MOAL 6001637 Piso Torcho 20x20 y 25x25 cm 137.53 100.00% m2 15.00 1 1 1 137.53*MOAL 6001638 Piso Vibrazo (parques y terrazas) 165.04 100.00% m2 12.50 1 1 1 165.04*MOAL 6001639 Quicio y entre puertas 113.66 100.00% m 13.25 1 1 113.66*MOAL 6001640 Zócalo corriente 50.20 100.00% m 30.00 1 1 50.20*MOAL 6001641 Zócalo corriente en escalera 88.59 100.00% m 17.00 1 1 88.59*MOAL 6001642 Zócalo granito en escalera 115.85 100.00% m 13.00 1 1 115.85*MOAL 6001643 Zócalo granito en piso 68.45 100.00% m 22.00 1 1 68.45

*MOAL 6001700 M.O. ALB., PULIMENTO Y BRILLADO PISOS: (ITBIS incluido por subcontrto)*MOAL 6001701 Cristalizado pisos (40 m2 mínimo) 107.36 101.72% m2 20.41 1 1 105.54*MOAL 6001702 Limpieza escalón 87.65 101.73% m 25.00 1 1 86.16*MOAL 6001703 Limpieza zócalos 61.05 101.72% m 35.89 1 1 60.02*MOAL 6001704 Limpieza, sal y cera 122.69 101.72% m2 17.86 1 1 120.61*MOAL 6001705 Pulimento básico 197.23 101.72% m2 11.11 1 1 193.89*MOAL 6001706 Pulimento escalón 236.64 101.72% m 9.26 1 1 232.63*MOAL 6001707 Pulimento mesetas 217.17 101.72% m2 10.09 1 1 213.49*MOAL 6001708 Pulimento Super Chapa 263.06 101.72% m2 8.33 1 1 258.60*MOAL 6001709 Pulimento y cristalizado 304.76 101.72% m2 7.19 1 1 299.60*MOAL 6001710 Pulimento y reparación piso viejo 328.52 101.72% m2 6.67 1 1 322.96

*MOAL 6001800 M.O. ALB., REGISTROS Y TRAMPA GRASA:*MOAL 6001801 Conf. registro hasta 60x60 cm (medida interior) 866.00 100.00% u 1.50 1 1 866.00*MOAL 6001802 Conf. registro más de 60x60 cm (medida interior) 1,039.20 100.00% u 1.25 1 1 1,039.20*MOAL 6001803 Conf. trampa de grasa 1,732.00 100.00% u 1.00 1 1 1 1,732.00

*MOAL 6001900 M.O. ALB., REVESTIMIENTO PAREDES:*MOAL 6001901 Azulejo 10x10 cm, plumilla 602.40 100.00% m2 2.50 1 1 602.40*MOAL 6001902 Azulejo 10x10 cm, junta corrida 502.00 100.00% m2 3.00 1 1 502.00*MOAL 6001903 Azulejo 15x15 cm, junta corrida 286.86 100.00% m2 5.25 1 1 286.86*MOAL 6001904 Azulejo 15x15 cm, junta trabada 301.20 100.00% m2 5.00 1 1 301.20*MOAL 6001905 Azulejo en combinación 350.23 100.00% m2 4.30 1 1 350.23*MOAL 6001906 Bañera cónica P. A. P. A.*MOAL 6001907 Bañera empotrada revestida cerámica criolla P. A. P. A.*MOAL 6001908 Bañera empotrada revestida cerámica import. P. A. P. A.*MOAL 6001909 Bañera revest. 30 cm alto, 1.56 hasta 180 m. largo 2,316.92 100.00% u 0.65 1 1 2,316.92*MOAL 6001910 Bañera revest. 30 cm alto hasta 1.55 m. largo 2,008.00 100.00% u 0.75 1 1 2,008.00*MOAL 6001911 Base para bañera 251.00 100.00% u 6.00 1 1 251.00*MOAL 6001912 Cerámica criolla 15x15 hasta 29x29 cm 286.86 100.00% m2 5.25 1 1 286.86*MOAL 6001913 Cerámica criolla 30x30 hasta 40x40 cm 376.50 100.00% m2 4.00 1 1 376.50*MOAL 6001914 Cerámica import. 15x15 hasta 29x29 cm 317.05 100.00% m2 4.75 1 1 317.05*MOAL 6001915 Cerámica import. 30x30 hasta 40x40 cm 430.29 100.00% m2 3.50 1 1 430.29*MOAL 6001916 Fachaico 288.67 100.00% m2 4.50 1 1 288.67*MOAL 6001917 Loseta 5x20 cm en revest. muro 502.00 100.00% m2 3.00 1 1 502.00*MOAL 6001918 Loseta 8x20 cm en revest. muro 430.29 100.00% u 3.50 1 1 430.29*MOAL 6001919 Loseta de cemento 12.5x25 cm 188.25 100.00% m2 8.00 1 1 188.25*MOAL 6001920 Loseta ornamental en paredes 376.50 100.00% m2 4.00 1 1 376.50*MOAL 6001921 Meseta de baño 654.78 100.00% u 2.30 1 1 654.78*MOAL 6001922 Mocheta en azulejo 188.25 100.00% m 8.00 1 1 188.25*MOAL 6001923 Mocheta en cerámica criolla 215.14 100.00% m 7.00 1 1 215.14*MOAL 6001924 Mocheta en cerámica import. 231.69 100.00% m 6.50 1 1 231.69*MOAL 6001925 Prep. superficie p/colocar piso 34.23 100.00% m2 44.00 1 1 34.23

*MOAL 6002000 M.O. ALB., SUBIR MATERIALES / PLANTA:*MOAL 6002001 Subir arena por meseta un nivel 88.88 100.00% m3 16.00 3 88.88*MOAL 6002002 Subir arena por polea 2do nivel 142.20 100.00% m3 10.00 3 142.20*MOAL 6002003 Subir arena por polea 3er nivel 203.14 100.00% m3 7.00 3 203.14*MOAL 6002004 Subir arena por polea 4to nivel 284.40 100.00% m3 5.00 3 284.40*MOAL 6002005 Subir arena por polea 5to nivel 355.50 100.00% m3 4.00 3 355.50*MOAL 6002006 Subir arena por polea 6to nivel 474.00 100.00% m3 3.00 3 474.00*MOAL 6002007 Subir bloques 4" por meseta 2do nivel 0.79 100.00% u 1,800.00 3 0.79*MOAL 6002008 Subir bloques 4" por meseta 3er nivel 0.95 100.00% u 1,500.00 3 0.95*MOAL 6002009 Subir bloques 4" por meseta 4to nivel 1.26 100.00% u 1,125.00 3 1.26*MOAL 6002010 Subir bloques 4" por meseta 5to nivel 1.58 100.00% u 900.00 3 1.58*MOAL 6002011 Subir bloques 4" por meseta 6to nivel 1.90 100.00% u 750.00 3 1.90*MOAL 6002012 Subir bloques 4" por polea 2do nivel 1.29 100.00% u 1,100.00 3 1.29*MOAL 6002013 Subir bloques 4" por polea 3er nivel 2.19 100.00% u 650.00 3 2.19*MOAL 6002014 Subir bloques 4" por polea 4to nivel 2.84 100.00% u 500.00 3 2.84*MOAL 6002015 Subir bloques 4" por polea 5to nivel 4.06 100.00% u 350.00 3 4.06*MOAL 6002016 Subir bloques 4" por polea 6to nivel 4.74 100.00% u 300.00 3 4.74*MOAL 6002017 Subir bloques 6" por meseta 2do nivel 0.95 100.00% u 1,500.00 3 0.95*MOAL 6002018 Subir bloques 6" por meseta 3er nivel 1.42 100.00% u 1,000.00 3 1.42*MOAL 6002019 Subir bloques 6" por meseta 4to nivel 1.90 100.00% u 750.00 3 1.90*MOAL 6002020 Subir bloques 6" por meseta 5to nivel 2.37 100.00% u 600.00 3 2.37*MOAL 6002021 Subir bloques 6" por meseta 6to nivel 2.84 100.00% u 500.00 3 2.84*MOAL 6002022 Subir bloques 6" por polea 2do nivel 1.58 100.00% u 900.00 3 1.58*MOAL 6002023 Subir bloques 6" por polea 3er nivel 2.37 100.00% u 600.00 3 2.37*MOAL 6002024 Subir bloques 6" por polea 4to nivel 3.16 100.00% u 450.00 3 3.16

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 25

Page 26: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOAL 6002025 Subir bloques 6" por polea 5to nivel 4.38 100.00% u 325.00 3 4.38*MOAL 6002026 Subir bloques 6" por polea 6to nivel 5.17 100.00% u 275.00 3 5.17*MOAL 6002027 Subir bloques 8" por meseta 2do nivel 1.19 100.00% u 1,200.00 3 1.19*MOAL 6002028 Subir bloques 8" por meseta 3er nivel 1.78 100.00% u 800.00 3 1.78*MOAL 6002029 Subir bloques 8" por meseta 4to nivel 2.37 100.00% u 600.00 3 2.37*MOAL 6002030 Subir bloques 8" por meseta 5to nivel 2.96 100.00% u 480.00 3 2.96*MOAL 6002031 Subir bloques 8" por meseta 6to nivel 3.56 100.00% u 400.00 3 3.56*MOAL 6002032 Subir bloques 8" por polea 2do nivel 2.00 100.00% u 710.00 3 2.00*MOAL 6002033 Subir bloques 8" por polea 3er nivel 2.99 100.00% u 475.00 3 2.99*MOAL 6002034 Subir bloques 8" por polea 4to nivel 4.01 100.00% u 355.00 3 4.01*MOAL 6002035 Subir bloques 8" por polea 5to nivel 4.99 100.00% u 285.00 3 4.99*MOAL 6002036 Subir bloques 8" por polea 6to nivel 6.05 100.00% u 235.00 3 6.05*MOAL 6002037 Subir bloques 10" por meseta 2do nivel 1.42 100.00% u 1,000.00 3 1.42*MOAL 6002038 Subir bloques 10" por meseta 3er nivel 2.14 100.00% u 665.00 3 2.14*MOAL 6002039 Subir bloques 10" por meseta 4to nivel 2.84 100.00% u 500.00 3 2.84*MOAL 6002040 Subir bloques 10" por meseta 5to nivel 3.56 100.00% u 400.00 3 3.56*MOAL 6002041 Subir bloques 10" por meseta 6to nivel 4.24 100.00% u 335.00 3 4.24*MOAL 6002042 Subir bloques 10" por polea 2do nivel 2.37 100.00% u 600.00 3 2.37*MOAL 6002043 Subir bloques 10" por polea 3er nivel 3.56 100.00% u 400.00 3 3.56*MOAL 6002044 Subir bloques 10" por polea 4to nivel 4.74 100.00% u 300.00 3 4.74*MOAL 6002045 Subir bloques 10" por polea 5to nivel 5.93 100.00% u 240.00 3 5.93*MOAL 6002046 Subir bloques 10" por polea 6to nivel 7.11 100.00% u 200.00 3 7.11*MOAL 6002047 Subir bloques 12" por meseta 2do nivel 1.67 100.00% u 850.00 3 1.67*MOAL 6002048 Subir bloques 12" por meseta 3er nivel 2.59 100.00% u 550.00 3 2.59*MOAL 6002049 Subir bloques 12" por meseta 4to nivel 3.43 100.00% u 415.00 3 3.43*MOAL 6002050 Subir bloques 12" por meseta 5to nivel 4.24 100.00% u 335.00 3 4.24*MOAL 6002051 Subir bloques 12" por meseta 6to nivel 5.08 100.00% u 280.00 3 5.08*MOAL 6002052 Subir bloques 12" por polea 2do nivel 2.84 100.00% u 500.00 3 2.84*MOAL 6002053 Subir bloques 12" por polea 3er nivel 4.24 100.00% u 335.00 3 4.24*MOAL 6002054 Subir bloques 12" por polea 4to nivel 5.69 100.00% u 250.00 3 5.69*MOAL 6002055 Subir bloques 12" por polea 5to nivel 7.11 100.00% u 200.00 3 7.11*MOAL 6002056 Subir bloques 12" por polea 6to nivel 8.62 100.00% u 165.00 3 8.62*MOAL 6002057 Subir fundas tipo cem. por polea 2do nivel 5.93 100.00% fda 240.00 3 5.93*MOAL 6002058 Subir fundas tipo cem. por polea 3er nivel 9.48 100.00% fda 150.00 3 9.48*MOAL 6002059 Subir fundas tipo cem. por polea 4to nivel 12.93 100.00% fda 110.00 3 12.93*MOAL 6002060 Subir fundas tipo cem. por polea 5to nivel 16.73 100.00% fda 85.00 3 16.73*MOAL 6002061 Subir fundas tipo cem. por polea 6to nivel 21.88 100.00% fda 65.00 3 21.88*MOAL 6002062 Subir grava por meseta un nivel 118.50 100.00% m3 12.00 3 118.50*MOAL 6002063 Subir grava por polea 2do nivel 177.75 100.00% m3 8.00 3 177.75*MOAL 6002064 Subir grava por polea 3er nivel 284.40 100.00% m3 5.00 3 284.40*MOAL 6002065 Subir grava por polea 4to nivel 355.50 100.00% m3 4.00 3 355.50*MOAL 6002066 Subir grava por polea 5to nivel 474.00 100.00% m3 3.00 3 474.00*MOAL 6002067 Subir grava por polea 6to nivel 646.36 100.00% m3 2.20 3 646.36

*MOAL 6002100 M.O. ALB., TECHOS, TERMINACION:*MOAL 6002101 Capa atérmica, sin subir mat. 60.24 100.00% m2 25.00 1 1 60.24*MOAL 6002102 Fino techo Bermuda, cantos, sin subir mat. 214.31 100.00% m2 13.00 1 1 1 1 214.31*MOAL 6002103 Fino techo horiz., sin subir mat. 86.38 100.00% m2 16.00 1 1 86.38*MOAL 6002104 Fino techo inclinado, sin subir mat. 53.15 100.00% m2 26.00 1 1 53.15*MOAL 6002105 Zabaleta en piso 30.71 100.00% m 45.00 1 1 30.71*MOAL 6002106 Zabaleta en techo 46.07 100.00% m 30.00 1 1 46.07

*MOAL 6002200 M.O. ALB., VACIADOS:*MOAL 6002201 Vaciado y ligado a mano (Ver análisis) 664.21 100.62% m3 660.13*MOAL 6002202 Vaciado y ligado con ligadora (Ver análisis) 287.19 100.19% m3 286.64

*MOAL 6002300 M.O. ALB., YESO A TODO COSTO:*MOAL 6002301 Capitel (anillo en columna) 2,163.44 100.00% u 2.27 1 1 1 1 1 1 2,163.44*MOAL 6002302 Cornisa 288.88 100.00% m 17.00 1 1 1 1 1 1 288.88*MOAL 6002303 Pandereta 1,805.51 100.00% m2 2.72 1 1 1 1 1 1 1,805.51*MOAL 6002304 Plafón (directo sobre techo horm.) 288.88 100.00% m2 17.00 1 1 1 1 1 1 288.88*MOAL 6002305 Plafón en láminas 1,805.51 100.00% m2 2.72 1 1 1 1 1 1 1,805.51*MOAL 6002306 Roseta 16" 361.10 100.00% u 13.60 1 1 1 1 1 1 361.10*MOAL 6002307 Roseta 24" 541.46 100.00% u 9.07 1 1 1 1 1 1 541.46

*MOCA 6100000 M.O. CARPINTERIA:

*MOCA 6100100 M.O. CARPINT., COL. CONICAS Y RED., CONF.:*MOCA 6100001 Col. cónica diám. hasta 50 cm 438.24 100.00% m 4.897 1 2 438.24*MOCA 6100002 Col. redonda diám. hasta 50 cm 338.34 100.00% m 6.3427 1 2 338.34*MOCA 6100003 Col. cón. o red. adic. p/c 10 cm diám. > 50 cm 20.00% 100.00% m 20.00%

*MOCA 6100200 M.O. CARPINT., COL. CONICAS Y RED., INST.:*MOCA 6100201 Col. cónica diám. hasta 50 cm 178.83 100.00% m 12.000 1 2 178.83*MOCA 6100202 Col. redonda diám. hasta 50 cm 178.83 100.00% m 12.000 1 2 178.83*MOCA 6100203 Col. cón. o red. adic. p/c 10 cm diám. > 50 cm 20.00% 100.00% m 20.00%

*MOCA 6100300 M.O. CARPINT., COL. CUADRADAS O RECTANG., CONF.:*MOCA 6100301 Col. 20x20 hasta 30x30 cm 120.83 100.00% m 17.760 1 2 120.83*MOCA 6100302 Col. >30x30 hasta 40x40 cm 138.56 100.00% m 15.488 1 2 138.56*MOCA 6100303 Col. >40x40 hasta 50x50 cm 159.51 100.00% m 13.454 1 2 159.51*MOCA 6100304 Col. >50x50 hasta 60x60 cm 199.78 100.00% m 10.742 1 2 199.78*MOCA 6100305 Col. >60x60 hasta 70x70 cm 238.44 100.00% m 9.000 1 2 238.44*MOCA 6100306 Col. >70x70 hasta 80x80 cm 278.74 100.00% m 7.6990 1 2 278.74*MOCA 6100307 Col. >80x80 hasta 1.00x1.00 m. 317.41 100.00% m 6.7610 1 2 317.41

*MOCA 6100400 M.O. CARPINT., COL. CUADRADAS O RECTANG., INST.:*MOCA 6100401 Col. 20x20 hasta 30x30 cm 138.56 100.00% m 15.488 1 2 138.56*MOCA 6100402 Col. >30x30 hasta 40x40 cm 178.83 100.00% m 12.000 1 2 178.83*MOCA 6100403 Col. >40x40 hasta 50x50 cm 199.78 100.00% m 10.742 1 2 199.78*MOCA 6100404 Col. >50x50 hasta 60x60 cm 317.41 100.00% m 6.7610 1 2 317.41*MOCA 6100405 Col. >60x60 hasta 70x70 cm 359.29 100.00% m 5.9729 1 2 359.29*MOCA 6100406 Col. >70x70 hasta 80x80 cm 396.34 100.00% m 5.4145 1 2 396.34

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 26

Page 27: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOCA 6100407 Col. >80x80 hasta 1.00x1.00 m. 476.90 100.00% m 4.4999 1 2 476.90

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 27

Page 28: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOCA 6100500 M.O. CARPINT., COL., TAPAS, CONF. E INST.:*MOCA 6100501 Col. 2 tapas c/retalle >2 hasta 10 cm 159.51 100.00% m 13.454 1 2 159.51*MOCA 6100502 Col. 2 tapas c/retalle >10 hasta 20 cm 178.83 100.00% m 12.000 1 2 178.83*MOCA 6100503 Col. 2 tapas c/retalle >20 hasta 30 cm 199.78 100.00% m 10.742 1 2 199.78*MOCA 6100504 Col. Tapa y tapa hasta 30 cm ancho 99.89 100.00% m 21.483 1 2 99.89*MOCA 6100505 Col. Tapa y tapa >30 hasta 40 cm ancho 120.83 100.00% m 17.760 1 2 120.83*MOCA 6100506 Col. Tapa y tapa >40 hasta 50 cm ancho 138.56 100.00% m 15.488 1 2 138.56

*MOCA 6100600 M.O. CARPINT., DESENCOFRADOS (AREA CONTACTO FORRO-CONCRETO):*MOCA 6100601 Columna 20.94 100.00% m2 102.459 1 2 20.94*MOCA 6100602 Arco 24.17 100.00% m2 88.798 1 2 24.17*MOCA 6100603 Dintel 24.17 100.00% m2 88.798 1 2 24.17*MOCA 6100604 Falso Piso, hasta 2.75 m. alt. 25.78 100.00% m2 83.248 1 2 25.78*MOCA 6100605 Falso Piso, >2.75 m. alt., p/c m. adic. 1.98 100.00% m2 1,083.33 1 2 1.98*MOCA 6100606 Viga 24.17 100.00% m2 88.798 1 2 24.17

*MOCA 6100700 M.O. CARPINT., ESTRUCT. VARIAS, INST. (HASTA 4 M. ALTURA):*MOCA 6100701 Caballete asbesto, inst. alto 4 m. 41.89 100.00% u 51.227 1 2 41.89*MOCA 6100702 Caballete zinc, inst. alto 4 m. 42.30 100.00% u 37.567 1 1 42.30*MOCA 6100703 Plancha asb. cem. 3'x6', con enlatado, inst. alto 4 m. 59.61 100.00% u 35.998 1 2 59.61*MOCA 6100704 Plancha asb. cem. 3'x6', sin enlatado, inst. alto 4 m. 46.73 100.00% u 45.928 1 2 46.73*MOCA 6100705 Plancha asb. cem. 3'x8', con enlatado, inst. alto 4 m. 67.67 100.00% u 31.712 1 2 67.67*MOCA 6100706 Plancha asb. cem. 3'x8', sin enlatado, inst. alto 4 m. 59.61 100.00% u 35.998 1 2 59.61*MOCA 6100707 Plancha Sisal cemento 3'x2', con enlatado, inst. alto 4 m. 99.89 100.00% u 21.483 1 2 99.89*MOCA 6100708 Plancha zinc, con enlatado, inst. alto 4 m. 53.17 100.00% u 40.361 1 2 53.17*MOCA 6100709 Plancha zinc, sin enlatado, inst. alto 4 m. 32.22 100.00% u 66.596 1 2 32.22*MOCA 6100710 Tijerilla atornillada p/c p2 madera utiliz., conf. e inst. 41.89 100.00% p2 51.227 1 2 41.89*MOCA 6100711 Tijerilla clavada p/c p2 madera utiliz., conf. e inst. 24.17 100.00% p2 88.794 1 2 24.17

*MOCA 6100800 M.O. CARPINT., FALSO PISO, HECHURA:*MOCA 6100801 Falso piso >2.75 hasta 3.00 m. alto o vuelo cont. 138.56 100.00% m2 15.488 1 2 138.56*MOCA 6100802 Falso piso >3.00 hasta 4.00 m. alto o vuelo cont. 159.51 100.00% m2 13.454 1 2 159.51*MOCA 6100803 Falso piso >4.00 hasta 5.00 m. alto o vuelo cont. 178.83 100.00% m2 12.000 1 2 178.83*MOCA 6100804 Falso piso >5.00 hasta 6.00 m. alto o vuelo cont. 199.78 100.00% m2 10.742 1 2 199.78*MOCA 6100805 Falso piso 3 ó más aguas. 314.27 100.00% m2 6.8285 1 2 314.27*MOCA 6100806 Falso piso forma especial P. A. m2 1 2 P. A.*MOCA 6100807 Falso piso hasta 2.75 m. alto o vuelo cont. 120.83 100.00% m2 17.7600 1 2 120.83*MOCA 6100808 Vuelo 10 cm (no cont. fallso piso) 41.89 100.00% m 51.227 1 2 41.89*MOCA 6100809 Vuelo 20 cm (no cont. fallso piso) 83.78 100.00% m 25.6135 1 2 83.78*MOCA 6100810 Vuelo 30 cm (no cont. fallso piso) 125.68 100.00% m 17.0757 1 2 125.68*MOCA 6100811 Vuelo 40 cm (no cont. fallso piso) 167.57 100.00% m 12.8068 1 2 167.57*MOCA 6100812 Vuelo 50 hasta 90 cm (no cont. fallso piso) 209.46 100.00% m 10.2454 1 2 209.46*MOCA 6100813 Vuelo 1.00 m. en adelante = Falso piso 120.83 100.00% m2 17.7600 1 2 120.83*MOCA 6100814 Vuelo con ménsula P. A. 1 2 P. A.

*MOCA 6100900 M.O. CARPINT., MUROS, CONF. E INST. MOLDE:*MOCA 6100901 Molde pref. múlt., transp. mecán., c/cara instalada 26.41 100.00% m2 81.250 1 2 26.41*MOCA 6100902 Muro H.A. c/cara lisa, confección 145.00 100.00% m2 14.800 1 2 145.00*MOCA 6100903 Muro H.A. c/cara lisa, instalación 182.06 100.00% m2 11.787 1 2 182.06

*MOCA 6101000 M.O. CARPINT., OTROS, CONF. E INST. MOLDE:*MOCA 6101001 Antepecho hasta 50 cm; cada 10 cm altura, conf. 41.89 100.00% m 51.230 1 2 41.89*MOCA 6101002 Arco hasta 20 fondo y hasta 30 cm radio, conf. e inst. 396.34 100.00% m2 5.4145 1 2 396.34*MOCA 6101003 Otros arcos P. A. 1 2 P. A.*MOCA 6101004 Rampa lisa 396.34 100.00% m2 5.4145 1 2 396.34*MOCA 6101005 Rampa otro tipo no especif. P. A. u 1 2 P. A.

*MOCA 6101100 M.O. CARPINT., TODO COSTO: (ITBIS incluido por subcontrto)*MOCA 6101101 Andamios 79.22 101.72% m2 63.932 2 4 77.88*MOCA 6101102 Encof. y desenc. antepecho 203.71 101.73% m 24.862 2 4 200.25*MOCA 6101103 Encof. y desenc. Cisterna (mínimo 10.00 m2) 3,500.04 101.72% u 1.447 2 4 3,440.72*MOCA 6101104 Encof. y desenc. Col. 40 hasta 50 cm 537.58 101.72% m 9.421 2 4 528.47*MOCA 6101105 Encof. y desenc. Col. cilíndrica 20 cm diám., c/ coloc. molde 1,090.56 101.72% molde 4.644 2 4 1,072.08*MOCA 6101106 Encof. y desenc. Col. cilíndrica 30 cm diám., c/ coloc. molde 1,387.93 101.72% molde 3.649 2 4 1,364.41*MOCA 6101107 Encof. y desenc. Col. cilíndrica 40 cm diám. 991.88 101.72% m 5.106 2 4 975.07*MOCA 6101108 Encof. y desenc. Col. hasta 30x30 cm 427.89 101.72% m 11.836 2 4 420.64*MOCA 6101109 Encof. y desenc. Col. y viga amarre 203.71 101.73% m 24.862 2 4 200.25*MOCA 6101110 Encof. y desenc. Corniza en losa, c/cara 152.51 101.73% m 33.209 2 4 149.92*MOCA 6101111 Encof. y desenc. Dintel 20 ó 30 cm, hasta 2.00 m. 228.14 101.72% m 22.199 2 4 224.28*MOCA 6101112 Encof. y desenc. Guardera en losa 99.02 101.72% m 51.145 2 4 97.35*MOCA 6101113 Encof. y desenc. Guardera en platea hasta 20 cm 118.83 101.73% m 42.621 2 4 116.81*MOCA 6101114 Encof. y desenc. Losa 3 ó más aguas 635.85 101.72% m2 7.965 2 4 625.07*MOCA 6101115 Encof. y desenc. Losa inclinada 1 dirección, hasta 3 m. alt. 301.00 101.73% m2 16.826 2 4 295.89*MOCA 6101116 Encof. y desenc. Losa inclinada 2 direcciones, hasta 3 m. alt. 326.85 101.72% m2 15.495 2 4 321.31*MOCA 6101117 Encof. y desenc. Losa plana, hasta 2.75 m. alto 297.37 101.72% m2 17.031 2 4 292.33*MOCA 6101118 Encof. y desenc. Muro / cara 696.45 101.72% m2 7.272 2 4 684.64*MOCA 6101119 Encof. y desenc. Pérgola hasta 20 x 40 cm 396.10 101.72% m 12.786 2 4 389.39*MOCA 6101120 Encof. y desenc. Rampa escalera 3,667.31 101.72% rampa 1.381 2 4 3,605.16*MOCA 6101121 Encof. y desenc. Viga 20x40 cm, hasta 3.6 m. 395.27 101.72% m 12.813 2 4 388.57*MOCA 6101122 Encof. y desenc. Viga 30x50 cm, hasta 3.6 m. 525.70 101.72% m 9.634 2 4 516.79*MOCA 6101123 Encof. y desenc. Viga 30x60 cm, hasta 3.6 m. 586.79 101.72% m 8.631 2 4 576.84*MOCA 6101124 Encof. y desenc. Viga 40x80 cm, hasta 3.6 m. 778.09 101.72% m 6.509 2 4 764.90*MOCA 6101125 Encof. y desenc. Viga de amarre hasta 30 cm 227.78 101.72% m 22.234 2 4 223.92*MOCA 6101126 Encof. y desenc. Viga inv. >20 ancho, adic. c/cm hasta 50 cm, >50 cm = muro11.88 101.71% m 426.212 2 4 11.68*MOCA 6101127 Encof. y desenc. Viga inv. hasta 20x>40 alt., adic. c/cm hasta 80 cm 11.88 101.71% m 426.212 2 4 11.68*MOCA 6101128 Encof. y desenc. Viga inv. hasta 20 x hasta 40 cm alt. 370.38 101.72% m 13.674 2 4 364.10*MOCA 6101129 Encof. y desenc. Viga sobre muro >30 cm Hasta 50 cm 326.85 101.72% m 15.495 2 4 321.31*MOCA 6101130 Encof. y desenc. Viga sobre muro hasta 30 cm 257.50 101.72% m 19.668 2 4 253.14*MOCA 6101131 Encof. y desenc. Vuelo >3 m. alt., adic. c/50 cm hasta 6.00 m. alt. 37.63 101.73% m 134.594 2 4 36.99*MOCA 6101132 Encof. y desenc. Vuelo inclinado losa >3 direcciones, hasta 3 m. alt. 594.15 101.72% m 8.524 2 4 584.08*MOCA 6101133 Encof. y desenc. Vuelo inclinado losa 1 dirección, hasta 3 m. alt. 301.00 101.73% m 16.826 2 4 295.89*MOCA 6101134 Encof. y desenc. Vuelo inclinado losa 2 direcciones, hasta 3 m. alt. 326.85 101.72% m 15.495 2 4 321.31*MOCA 6101135 Encof. y desenc. Vuelo inclinado losa 3 direcciones, hasta 3 m. alt. 370.38 101.72% m 13.674 2 4 364.10

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 28

Page 29: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOCA 6101136 Encof. y desenc. Vuelo plano hasta 2.60 m. alt. 257.50 101.72% m 19.668 2 4 253.14

*MOCA 6101200 M.O. CARPINT., TRABAJOS DE TERMINACION:*MOCA 6101201 Cielo raso de asbesto en cuadros 2'x2' 217.51 100.00% m2 9.866 1 2 217.51*MOCA 6101202 Cielo raso de cartón acústico, encostillado 217.51 100.00% m2 9.866 1 2 217.51*MOCA 6101203 Cielo raso de plywood en cuadros 2'x2' 199.80 100.00% m2 10.741 1 2 199.80*MOCA 6101204 Cielo raso de plywood o cartón piedra 159.51 100.00% m2 13.454 1 2 159.51*MOCA 6101205 Conf. Puerta biselada clavada 46.73 100.00% u 45.928 1 2 46.73*MOCA 6101206 Conf. Puerta clavada 24.17 100.00% p2 88.794 1 2 24.17*MOCA 6101207 Conf. Puerta en plumilla 46.73 100.00% p2 45.928 1 2 46.73*MOCA 6101208 Conf. Puerta forrada en zinc 59.61 100.00% p2 35.998 1 2 59.61*MOCA 6101209 División plywood, 1 lado 138.57 100.00% m2 15.487 1 2 138.57*MOCA 6101210 División plywood, 2 lados 199.80 100.00% m2 10.741 1 2 199.80*MOCA 6101211 Montar cerradura corriente 296.46 100.00% u 7.2387 1 2 296.46*MOCA 6101212 Montar marco mad. corriente 46.73 100.00% u 45.928 1 2 46.73*MOCA 6101213 Montar marco mad. preciosa 59.61 100.00% u 35.998 1 2 59.61*MOCA 6101214 Montar marco metal 78.95 100.00% u 27.182 1 2 78.95*MOCA 6101215 Montar puerta panelada corriente 0.9x2.10 m. 496.25 100.00% u 4.3244 1 2 496.25*MOCA 6101216 Montar puerta pino 0.9x2.10 m. 396.36 100.00% u 5.4143 1 2 396.36*MOCA 6101217 Montar puerta plegadiza corredera 0.9x2.10 m. 596.14 100.00% u 3.5998 1 2 596.14*MOCA 6101218 Montar puerta plegadiza moldura o cubrefalta 0.9x2.10 m. 794.31 100.00% u 2.7017 1 2 794.31*MOCA 6101219 Montar puerta plumilla con cáncamo 0.9x2.10 m. 794.31 100.00% u 2.7017 1 2 794.31*MOCA 6101220 Montar puerta plywood 0.9x2.10 m. 396.36 100.00% u 5.4143 1 2 396.36*MOCA 6101221 Montar puerta vaivén 0.9x2.10 m. 596.14 100.00% u 3.5998 1 2 596.14

*MOCA 6101300 M.O. CARPINT., VIGAS Y DINTELES, CONF. E INST. MOLDE:*MOCA 6101301 Dintel 2 m. largo, hasta 20 cm, conf. e inst. 199.78 100.00% m 10.742 1 2 199.78*MOCA 6101302 Dintel >2 m. largo, conf. e inst. = Vigas ver Vigas m ver Vigas*MOCA 6101303 Dintel hasta 2 m. largo, >20 hasta 40 cm, conf. e inst. 278.73 100.00% m 7.6992 1 2 278.73*MOCA 6101304 Viga invertida, c/10 cm alto, 2 caras, conf. e inst. 59.61 100.00% m 36.000 1 2 59.61*MOCA 6101305 Viga amarre 15 ó 20x20 cm alto, conf. e inst. 120.83 100.00% m 17.760 1 2 120.83*MOCA 6101306 Viga amarre 15 ó 20x30 cm alto, conf. e inst. 138.56 100.00% m 15.488 1 2 138.56*MOCA 6101307 Viga amarre 15 ó 20x40 cm alto, conf. e inst. 159.51 100.00% m 13.454 1 2 159.51*MOCA 6101308 Viga amarre 15 ó 20x50 cm alto, conf. e inst. 178.83 100.00% m 12.000 1 2 178.83*MOCA 6101309 Viga, c/10 cm alto, apunt. >3.6, adic. c/m. conf. e inst. 20.00% 100.00% m 20.00%*MOCA 6101310 Viga, c/10 cm alto, apunt. hasta 3.6 m., conf. e inst. 41.89 100.00% m 51.230 1 2 41.89*MOCA 6101311 Viga, c/10 cm Fondo 29.00 100.00% m 73.998 1 2 29.00*MOCA 6101312 Viga zap. hasta 40x40 cm, conf. e inst. 145.00 100.00% m 14.800 1 2 145.00*MOCA 6101313 Viga zap. >40x40 hasta 50x50 cm, conf. e inst. 99.89 100.00% m 21.483 1 2 99.89*MOCA 6101314 Viga zap. >50x50 hasta 60x60 cm, conf. e inst. 120.83 100.00% m 17.760 1 2 120.83

*MODE 6200000 M.O. DEMOLICIONES:*MODE 6200001 Cimiento de horm. armado 948.00 100.00% m3 0.50 1 948.00*MODE 6200002 Cimiento de piedra 316.00 100.00% m3 1.50 1 316.00*MODE 6200003 Cimiento viejo de horm. simple 557.65 100.00% m3 0.85 1 557.65*MODE 6200004 Murs de horm. armado 948.00 100.00% m3 0.50 1 948.00*MODE 6200005 Muro de piedra 270.86 100.00% m3 1.75 1 270.86*MODE 6200006 Muro de tapia 118.50 100.00% m3 4.00 1 118.50*MODE 6200007 Techo de tejas 47.40 100.00% m2 10.00 1 47.40*MODE 6200008 Techo horm. armado con mallas 118.50 100.00% m2 4.00 1 118.50*MODE 6200009 Techo horm. armado con varillas 237.00 100.00% m2 2.00 1 237.00

*Acero recuperable: 0.50 quintal por cada metro cúbico

*MOEB 6300000 M.O. EBANISTERIA:*MOEB 6300001 Aplicar laca, todo costo (2 caras) 1,665.00 100.00% m2 1.40 1 1 1 1,665.00*MOEB 6300002 Montar puerta, marco y llavín 1,165.50 100.00% u 2.00 1 1 1 1,165.50

*MOEL 6400000 M.O. ELECTRICIDAD:

*MOEL 6400100 M.O. ELECTRICIDAD, CONEXIÓN APARATOS:*MOEL 6400001 Aire acond. hasta 2 hp (montura sin materiales) 1,196.88 100.00% u 1.9133 1 1 1 1,196.88*MOEL 6400002 Aire acond., si corriente está distante, cobrar inst. eléct. aparte P. A. u 1 1 1 P. A.*MOEL 6400003 Aire acond., si requiere reformas constr., cobrar estas aparte P. A. u 1 1 1 P. A.*MOEL 6400004 Breaker, instalación 100.41 100.00% u 22.8054 1 1 1 100.41*MOEL 6400005 Cada número de los cuadros de timbres 200.83 100.00% u 11.4027 1 1 1 200.83*MOEL 6400006 Calentador 110 v sin estar provisto un plot y cordón 398.42 100.00% u 5.7477 1 1 1 398.42*MOEL 6400007 Calentador 220 v sin estar provisto un plot y cordón 599.26 100.00% u 3.8214 1 1 1 599.26*MOEL 6400008 Estufa eléctrica 220 v. 599.26 100.00% u 3.8214 1 1 1 599.26*MOEL 6400009 Extractor de aire 110 v. 398.42 100.00% u 5.7477 1 1 1 398.42*MOEL 6400010 Pago mínimo por visita, hecho o no el trabajo, motivo ajeno elect. 132.75 100.00% u 17.2500 1 1 1 132.75*MOEL 6400011 Moledor de desperdicios 110 v. 398.42 100.00% u 5.7477 1 1 1 398.42*MOEL 6400012 Regulador de intensidad (dimmer) 319.06 100.00% u 7.1773 1 1 1 319.06*MOEL 6400013 Reparar a domicilio y de apar. Eléctr. Según el caso requiera P. A. u 1 1 1 P. A.*MOEL 6400014 Timbre campana de 4 notas 599.26 100.00% u 3.8214 1 1 1 599.26

*MOEL 6400200 M.O. ELECTRICIDAD, INTERRUPTOR DE SEGURIDAD:*MOEL 6400201 Interruptor seg. inst. en los paneles, por cada 10 amp. 103.65 100.00% u 22.0927 1 1 1 103.65*MOEL 6400202 Interruptor seg. 30 amp. 311.01 100.00% u 7.3632 1 1 1 311.01*MOEL 6400203 Interruptor seg. 60 amp. 621.93 100.00% u 3.6821 1 1 1 621.93*MOEL 6400204 Interruptor seg. 100 amp. 1,036.53 100.00% u 2.2093 1 1 1 1,036.53*MOEL 6400205 Interruptor seg. 125 amp. 1,295.69 100.00% u 1.7674 1 1 1 1,295.69*MOEL 6400206 Interruptor seg. 150 amp. 1,554.86 100.00% u 1.4728 1 1 1 1,554.86*MOEL 6400207 Interruptor seg. 200 amp. 2,072.21 100.00% u 1.1051 1 1 1 2,072.21*MOEL 6400208 Interruptor seg. 250 amp. 2,591.38 100.00% u 0.8837 1 1 1 2,591.38

*MOEL 6400300 M.O. ELECTRICIDAD, SALIDAS DE TIMBRES, TELEF. Y CABLE:*MOEL 6400301 Timbre, Teléf. y Cable en la misma tub. de conduct. 443.77 100.00% u 5.1603 1 1 1 443.77*MOEL 6400302 Timbre, Teléf. y Cable en tub. 1/2" independiente 537.71 100.00% u 4.2588 1 1 1 537.71*MOEL 6400303 Timbre, Teléf. y Cable en tub. 3/4" independiente 699.62 100.00% u 3.2732 1 1 1 699.62*MOEL 6400304 Timbre, Teléf. y Cable en tub. 1" independiente 861.65 100.00% u 2.6577 1 1 1 861.65

*MOEL 6400400 M.O. ELECTRICIDAD, RESIDENCIAS ECONOMICAS EN SERIE :*MOEL 6400401 Similares a casas "A" y "B" en tub. 1/2" 340.12 100.00% u 6.7330 1 1 1 340.12

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 29

Page 30: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOEL 6400402 Similares a casas "C" y "D" en tub. 1/2" 295.08 100.00% u 7.7605 1 1 1 295.08

*MOEL 6400403Estas casas con timbres, teléf., cable, ext. visible, waterp., explotionp., pagar según establecen los demás renglones

Según aplique

uSegún aplique

*MOEL 6400500 M.O. ELECTRICIDAD, SALIDAS EN TUB. EXTERIOR VISIBLE:*MOEL 6400501 Salida ext. visible tipo industrial, 1/2" 630.63 100.00% u 3.6313 1 1 1 630.63*MOEL 6400502 Salida ext. visible tipo industrial, 1/2" con registro tipo letra 763.38 100.00% u 2.9998 1 1 1 763.38*MOEL 6400503 Salida ext. visible tipo industrial, 3/4" 819.82 100.00% u 2.7933 1 1 1 819.82*MOEL 6400504 Salida ext. visible tipo industrial, 3/4" con registro tipo letra 952.58 100.00% u 2.4040 1 1 1 952.58*MOEL 6400505 Salida ext. visible tipo industrial, 1" 1,008.99 100.00% u 2.2696 1 1 1 1,008.99*MOEL 6400506 Salida ext. visible tipo industrial, 1" con registro tipo letra 1,141.75 100.00% u 2.0057 1 1 1 1,141.75

*MOEL 6400600 M.O. ELECTRICIDAD, SALIDAS EN TUB. OCULTA:*MOEL 6400601 Salida Botón de timbre, 1/2" 443.77 100.00% u 5.1603 1 1 1 443.77*MOEL 6400602 Salida en tub. de 1/2" 443.77 100.00% u 5.1603 1 1 1 443.77*MOEL 6400603 Salida Interruptor piloto, 1/2" 537.71 100.00% u 4.2588 1 1 1 537.71*MOEL 6400604 Salida Interruptor 1, 1/2" 443.77 100.00% u 5.1603 1 1 1 443.77*MOEL 6400605 Salida Interruptor 2, 1/2" 537.71 100.00% u 4.2588 1 1 1 537.71*MOEL 6400606 Salida Interruptor 3, 1/2" 599.26 100.00% u 3.8214 1 1 1 599.26*MOEL 6400607 Salida Interruptor 3 vías, 1/2" 537.71 100.00% u 4.2588 1 1 1 537.71*MOEL 6400608 Salida Interruptor 4 vías, 1/2" 659.18 100.00% u 3.4740 1 1 1 659.18*MOEL 6400609 Salida Luces, 1/2" 443.77 100.00% u 5.1603 1 1 1 443.77*MOEL 6400610 Salida Tomacorriente 110 v., 1/2" 443.77 100.00% u 5.1603 1 1 1 443.77*MOEL 6400611 Salida Tomacorriente 220 v., 3/4" 505.14 100.00% u 4.5334 1 1 1 505.14*MOEL 6400612 Panel distribución 621.93 100.00% u 3.6821 1 1 1 621.93*MOEL 6400613 Por cada 1/4" superior a 1/2", hasta 1", 30% adic. al precio 132.81 100.00% u 17.2431 1 1 1 132.81*MOEL 6400614 Por cada switch adic. o de combinación, 50% adic. al precio 221.88 100.00% u 10.3207 1 1 1 221.88

*MOEL 6400700 M.O. ELECTRICIDAD, SALIDAS TIPO ECONOMICO EN TUB.:*MOEL 6400701 Salida sin tub. exteriormente visible 200.83 100.00% u 11.4027 1 1 1 200.83*MOEL 6400702 Salida sin tub. oculta en plafón, cielo raso, etc. 295.08 100.00% u 7.7605 1 1 1 295.08

*MOEL 6400800 M.O. ELECTRICIDAD, SALIDAS WATERPROOF Y EXPLOTIONPROOF:*MOEL 6400801 Estas salidas se cobrará un precio convencional superior a todas P. A. u 1 1 1 P. A.

*MOEX 6500000 M.O. EXCAVACIONES Y CORTES CON EQUIPO:*MOEX 6500001 Corte con PALA MECANICA en tierra P. A. m3 P. A.*MOEX 6500002 Exc. Caliche a mano 3.00 m. prof. 441.84 100.00% m3 0.98 1 441.84*MOEX 6500003 Exc. Caliche a mano 3.01 - 5.00 m. prof. 486.52 100.00% m3 0.89 1 486.52*MOEX 6500004 Exc. Caliche a mano 5.01 - 7.00 m. prof. 534.57 100.00% m3 0.81 1 534.57*MOEX 6500005 Exc. Horm. armado, 3.00 m. prof. 1,124.68 100.00% m3 0.77 2 1,124.68*MOEX 6500006 Exc. Roca blanda a mano 3.00 m. prof. 709.84 100.00% m3 0.61 1 709.84*MOEX 6500007 Exc. Roca blanda a mano 3.01 - 5.00 m. prof. 746.55 100.00% m3 0.58 1 746.55*MOEX 6500008 Exc. Roca blanda a mano 5.01 - 7.00 m. prof. 816.98 100.00% m3 0.53 1 816.98*MOEX 6500009 Exc. Roca compresor 3.00 m. prof. 1,772.87 100.00% m3 1,772.87*MOEX 6500010 Exc. Roca compresor 3.01 - 5.00 m. prof. 1,950.16 100.00% m3 1,950.16*MOEX 6500011 Exc. Roca compresor 5.01 - 7.00 m. prof. 2,127.44 100.00% m3 2,127.44*MOEX 6500012 Exc. Roca dura a mano 3.00 m. prof. 902.08 100.00% m3 0.48 1 902.08*MOEX 6500013 Exc. Roca dura a mano 3.01 - 5.00 m. prof. 941.30 100.00% m3 0.46 1 941.30*MOEX 6500014 Exc. Roca dura a mano 5.01 - 7.00 m. prof. 1,006.98 100.00% m3 0.43 1 1,006.98*MOEX 6500015 Exc. Roca tosca a mano 3.00 m. prof. 609.86 100.00% m3 0.71 1 609.86*MOEX 6500016 Exc. Roca tosca a mano 3.01 - 5.00 m. prof. 646.27 100.00% m3 0.67 1 646.27*MOEX 6500017 Exc. Roca tosca a mano 5.01 - 7.00 m. prof. 698.39 100.00% m3 0.62 1 698.39*MOEX 6500018 Exc. Tierra a mano 3.00 m. prof. 272.33 100.00% m3 1.59 1 272.33*MOEX 6500019 Exc. Tierra a mano 3.01 - 5.00 m. prof. 304.93 100.00% m3 1.42 1 304.93*MOEX 6500020 Exc. Tierra a mano 5.01 - 7.00 m. prof. 333.08 100.00% m3 1.30 1 333.08

*MOPI 6600000 M.O. PINTURA:*MOPI 6600001 Barniz, 1ra. mano 22.01 100.00% m2 84.375 1 1 22.01*MOPI 6600002 Barniz, 2da. mano 22.01 100.00% m2 84.375 1 1 22.01*MOPI 6600003 Cal y Carburo, 1ra. mano 12.38 100.00% m2 150.000 1 1 12.38*MOPI 6600004 Cal y Carburo, 2da. mano 8.25 100.00% m2 225.000 1 1 8.25*MOPI 6600005 Cornisa 27.51 100.00% m 67.500 1 1 27.51*MOPI 6600006 De agua, 1ra. mano, p. LISA, masilla, lija y piedra 20.63 100.00% m2 90.000 1 1 20.63*MOPI 6600007 De agua, 2da. mano, pared LISA 13.76 100.00% m2 135.000 1 1 13.76*MOPI 6600008 De agua, 2 manos, p. LISA, masilla, lija, piedra 34.39 100.00% m2 54.000 1 1 34.39*MOPI 6600009 De agua, 1ra. mano, pared RUSTICA 34.39 100.00% m2 54.000 1 1 34.39*MOPI 6600010 De agua, 2da. mano, pared RUSTICA 28.89 100.00% m2 64.286 1 1 28.89*MOPI 6600011 De agua, 2 manos, pared RUSTICA 63.28 100.00% m2 29.348 1 1 63.28*MOPI 6600012 Imperm., 1ra. Mano, limpieza y sellar grietas 23.38 100.00% m2 79.410 1 1 23.38*MOPI 6600013 Impermeabilizante, 2da. mano 13.76 100.00% m2 135.000 1 1 13.76*MOPI 6600014 Mant., 1ra. mano, p. LISA, masilla, lija sin piedra 22.01 100.00% m2 84.375 1 1 22.01*MOPI 6600015 Mant., 2da. mano, pared LISA, sin piedra 20.63 100.00% m2 90.000 1 1 20.63*MOPI 6600016 Mant., 2 manos, p. LISA, masilla, lija sin piedra 42.64 100.00% m2 43.548 1 1 42.64*MOPI 6600017 Oxido de Zinc, 1ra. mano 16.51 100.00% m2 112.50 1 1 16.51*MOPI 6600018 Oxido de Zinc, 2da. mano 12.38 100.00% m2 150.000 1 1 12.38*MOPI 6600019 Piedra sobre paredes 6.96 100.00% m2 80.000 1 6.96*MOPI 6600020 Rapilla total y/o parcial 27.85 100.00% m2 20.000 1 27.85*MOPI 6600021 Volutas en ventanas y en muros 23.38 100.00% m 79.410 1 1 23.38

*MOPL 6700000 M.O. PLOMERIA:

*MOPL 6700100 M.O. PLOMERIA, ACOMETIDA URBANA, INCLUYE LLAVE CHORO:*MOPL 6700001 Acomet. ½" y ¾", hasta 8.00 m. tub. h.g. 763.43 100.00% u 2.43243 1 1 763.43*MOPL 6700002 Acomet. ½" y ¾", hasta 12.00 m. tub. h.g. 374.15 100.00% u 4.96324 1 1 374.15*MOPL 6700003 Acomet. ½" y ¾", hasta 12.00 m. tub. pvc y h.g. en extr. 288.87 100.00% u 6.42857 1 1 288.87

*MOPL 6700100 M.O. PLOMERIA, ARRASTRE DOMIC. Y PLUVIAL:*MOPL 6700101 Arrastre, tub. 2" 37.14 100.00% m 50.00000 1 1 37.14*MOPL 6700102 Arrastre, tub. 3" ó 4" 45.39 100.00% m 40.90909 1 1 45.39*MOPL 6700103 Arrastre, tub. 5" 75.66 100.00% m 24.54545 1 1 75.66*MOPL 6700104 Arrastre, tub. 6" 94.91 100.00% m 19.56522 1 1 94.91

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 30

Page 31: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOPL 6700200 M.O. PLOMERIA, AUMENTO POR PLANTA EN EDIFICIOS:*MOPL 6700201 Valor adic. 2da. planta 5.00% 100.00% u 5.00%*MOPL 6700202 Valor adic. 3ra. planta 10.00% 100.00% u 10.00%*MOPL 6700203 Valor adic. 4ta. hasta 7ma. Planta 20.00% 100.00% u 20.00%*MOPL 6700204 Valor adic. 7ma. hasta 10ma. planta 25.00% 100.00% u 25.00%*MOPL 6700205 Valor adic. 10ma. Planta y siguientes / piso 35.00% 100.00% u 35.00%

*MOPL 6700300 M.O. PLOMERIA, BAJANTE O VENTILACION / PLANTA:*MOPL 6700301 Bajante o vent. dren. 2" 592.86 100.00% u 3.13225 1 1 592.86*MOPL 6700302 Bajante o vent. dren. 3" 678.15 100.00% u 2.73834 1 1 678.15*MOPL 6700303 Bajante o vent. dren. 4" 763.43 100.00% u 2.43243 1 1 763.43*MOPL 6700304 Bajante o vent. dren. 5" o más 1,016.54 100.00% u 1.82679 1 1 1,016.54

*MOPL 6700400 M.O. PLOMERIA, BOMBA DE AGUA, INST. CIRCUITO COMPLETO:*MOPL 6700401 Montar bomba c/circ. tub. ¾"-1" 6,778.73 100.00% u 0.27395 1 1 6,778.73*MOPL 6700402 Montar bomba c/circ. tub. 1 ¼ en adelante 6,778.73 100.00% u 0.27395 1 1 6,778.73

*MOPL 6700500 M.O. PLOMERIA, BOMBA DE AGUA, SIN EL CIRCUITO:*MOPL 6700501 Montar bomba s/circ. tub. ¾" 2,321.25 100.00% u 0.80 1 1 2,321.25*MOPL 6700502 Montar bomba s/circ. tub. 1"-1 ¼" 3,376.36 100.00% u 0.55 1 1 3,376.36*MOPL 6700503 Montar bomba s/circ. tub. 1 ½"-2" 4,642.50 100.00% u 0.40 1 1 4,642.50

*MOPL 6700600 M.O. PLOMERIA, CALENTADOR DE AGUA EXCLUSIV.:*MOPL 6700601 Montar calent. de gas 1,857.00 100.00% u 1.00 1 1 1,857.00*MOPL 6700602 Montar calent. eléct. hasta 12 gl. 1,356.30 100.00% u 1.36917 1 1 1,356.30*MOPL 6700603 Montar calent. eléct. 18-50 gl. 1,628.95 100.00% u 1.14 1 1 1,628.95*MOPL 6700604 Montar calent. industrial P. A. u 1 1 P. A.

*MOPL 6700700 M.O. PLOMERIA, COL. ABASTECER AGUA, COBRE, POR PLANTA:*MOPL 6700701 Col. agua ½" cobre , soldada o roscada, 848.72 100.00% u 2.188006 1 1 848.72*MOPL 6700702 Col. agua ¾" cobre , soldada o roscada, 1,187.10 100.00% u 1.564311 1 1 1,187.10*MOPL 6700703 Col. agua 1" cobre, soldada o roscada, 1,356.30 100.00% u 1.36917 1 1 1,356.30*MOPL 6700704 Col. agua 1 ¼" en adelante, cobre, soldar o rosca P. A. u 1 1 P. A.

*MOPL 6700800 M.O. PLOMERIA, COL. ABASTECER AGUA, H.G., POR PLANTA:*MOPL 6700801 Col. agua ½" ó ¾", h.g. o pvc 285.69 100.00% u 6.50 1 1 285.69*MOPL 6700802 Col. agua 1" ó 1 ¼", h.g. o pvc 325.79 100.00% u 5.70 1 1 325.79*MOPL 6700803 Col. agua 1 ½", h.g. o pvc 508.96 100.00% u 3.65 1 1 508.96*MOPL 6700804 Col. agua 2", h.g. o pvc 592.86 100.00% u 3.13225 1 1 592.86*MOPL 6700805 Col. agua 3", h.g. o pvc 678.15 100.00% u 2.73834 1 1 678.15*MOPL 6700806 Col. agua 4", h.g. o pvc 848.72 100.00% u 2.18800 1 1 848.72*MOPL 6700807 Col. agua 5" o más, h.g. o pvc 1,016.54 100.00% u 1.82679 1 1 1,016.54

*MOPL 6700900 M.O. PLOMERIA, COL. DESAGÜE PLUVIAL, POR PLANTA:*MOPL 6700901 Col. desagüe pluvial 2" 508.96 100.00% u 3.65 1 1 508.96*MOPL 6700902 Col. desagüe pluvial 3" 592.86 100.00% u 3.13225 1 1 592.86*MOPL 6700903 Col. desagüe pluvial 4" 678.15 100.00% u 2.73834 1 1 678.15*MOPL 6700904 Col. desagüe pluvial 5" ó 6" 848.72 100.00% u 2.18800 1 1 848.72

*MOPL 6701000 M.O. PLOMERIA, CONEXION AL SEPTICO Y FILTRANTE:*MOPL 6701001 Conextar a cloaca 928.50 100.00% u 2.00 1 1 928.50*MOPL 6701002 Conectar séptico 1 cám. y filt., tub. 4" 3,049.61 100.00% u 0.60893 1 1 3,049.61*MOPL 6701003 Conectar séptico 1 cám. y filt., tub. 5" 3,049.61 100.00% u 0.60893 1 1 3,049.61*MOPL 6701004 Conectar séptico 1 cám. y filt., tub. 6" 3,389.37 100.00% u 0.54789 1 1 3,389.37*MOPL 6701005 Conectar séptico 1 cám. y filt., tub. 8" 3,727.76 100.00% u 0.498155 1 1 3,727.76*MOPL 6701006 Conectar séptico 2 cám. y filt., tub. 4" 3,810.29 100.00% u 0.487365 1 1 3,810.29*MOPL 6701007 Conectar séptico 2 cám. y filt., tub. 5" 3,810.29 100.00% u 0.487365 1 1 3,810.29*MOPL 6701008 Conectar séptico 2 cám. y filt., tub. 6" 4,236.72 100.00% u 0.43831 1 1 4,236.72*MOPL 6701009 Conectar séptico 2 cám. y filt., tub. 8" 4,663.13 100.00% u 0.39823 1 1 4,663.13

*MOPL 6701100 M.O. PLOMERIA, DESAGÜE APARATOS, POR SALIDA:*MOPL 6701101 Desagüe 2" 592.86 100.00% u 3.13225 1 1 592.86*MOPL 6701102 Desagüe 3" y 4" 763.43 100.00% u 2.43243 1 1 763.43*MOPL 6701103 Desagüe inodoro de pared 931.25 100.00% u 1.99 1 1 931.25*MOPL 6701104 Desagüe piso 2", con parrilla 678.15 100.00% u 2.74 1 1 678.15*MOPL 6701105 Desagüe piso 3" y 4", con parrilla 763.43 100.00% u 2.43243 1 1 763.43

*MOPL 6701200 M.O. PLOMERIA, DESMONTAR APARATOS:*MOPL 6701201 Desmontar cualquier aparato 50.00% u 50.00%

*MOPL 6701300 M.O. PLOMERIA, EMPALME A TUB. AGUA EXIST.:*MOPL 6701301 Empalme tub. ½" ó ¾" 678.15 100.00% u 2.73834 1 1 678.15*MOPL 6701302 Empalme tub. 1" 848.72 100.00% u 2.18801 1 1 848.72*MOPL 6701303 Empalme tub. 1 ¼" - 1 ½" 1,016.54 100.00% u 1.82679 1 1 1,016.54*MOPL 6701305 Empalme tub. 2" 1,187.10 100.00% u 1.564311 1 1 1,187.10*MOPL 6701304 Empalme tub. 2 ½" en adelante P. A. u 1 1 P. A.

*MOPL 6701400 M.O. PLOMERIA, EMPALME A TUB. ARRASTRE EXIST.:*MOPL 6701401 Empalme tub. 2" 508.96 100.00% u 3.64865 1 1 508.96*MOPL 6701402 Empalme tub. 3" 678.15 100.00% u 2.73834 1 1 678.15*MOPL 6701403 Empalme tub. 4" 848.72 100.00% u 2.18801 1 1 848.72*MOPL 6701404 Empalme tub. 6" 1,016.54 100.00% u 1.82679 1 1 1,016.54

*MOPL 6701500 M.O. PLOMERIA, INST. CAJA DE VALVULA:*MOPL 6701501 Inst. caja válvula sencillas 94.91 100.00% u 19.56522 1 1 94.91*MOPL 6701502 Inst. caja válvula telescópica 112.80 100.00% u 16.46341 1 1 112.80

*MOPL 6701600 M.O. PLOMERIA, INST. HIDRANTE:*MOPL 6701601 Instalación hidrante 2,881.80 100.00% u 0.64439 1 1 2,881.80

*MOPL 6701700 M.O. PLOMERIA, INST. LAVADORA:*MOPL 6701701 Inst. lavadora automát., doméstica 1,356.30 100.00% u 1.36917 1 1 1,356.30*MOPL 6701702 Inst. lavadora automát., Industriales o comerciales P. A. u 1 1 P. A.

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 31

Page 32: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOPL 6701800 M.O. PLOMERIA, INST. LLAVE PASO Y CHORRO:*MOPL 6701801 Inst. llave chorro ½" ó ¾", línea máx. 3.00 m. 763.43 100.00% u 2.43243 1 1 763.43*MOPL 6701802 Inst. llave paso ½", cobre 1,016.54 100.00% u 1.82679 1 1 1,016.54*MOPL 6701803 Inst. llave paso ¾", cobre 1,187.10 100.00% u 1.564311 1 1 1,187.10*MOPL 6701804 Inst. llave paso 1" ó 1 ¼", cobre 1,269.64 100.00% u 1.46262 1 1 1,269.64*MOPL 6701805 Inst. llave paso 1 ½", cobre 1,356.30 100.00% u 1.36917 1 1 1,356.30*MOPL 6701806 Inst. llave paso 2" en adelante, cobre P. A. u 1 1 P. A.*MOPL 6701807 Inst. llave paso ½", h.g. o pvc 338.39 100.00% u 5.48781 1 1 338.39*MOPL 6701808 Inst. llave paso ¾", h.g. o pvc 508.96 100.00% u 3.64865 1 1 508.96*MOPL 6701809 Inst. llave paso 1" ó 1 ¼", h.g. o pvc 931.25 100.00% u 1.9941 1 1 931.25

*MOPL 6701900 M.O. PLOMERIA, INST. MANGA O NIPLE:*MOPL 6701901 Inst. manga o niple 2" de diámetro de tub. 94.91 100.00% u 19.56522 1 1 94.91*MOPL 6701902 Inst. manga o niple 3" de diámetro de tub. 112.80 100.00% u 16.46341 1 1 112.80*MOPL 6701903 Inst. manga o niple 4" de diámetro de tub. 185.70 100.00% u 10.00000 1 1 185.70*MOPL 6701904 Inst. manga o niple 6" de diámetro de tub. 374.15 100.00% u 4.96324 1 1 374.15*MOPL 6701905 Inst. manga o niple 8" de diámetro de tub. 474.57 100.00% u 3.91304 1 1 474.57

*MOPL 6702000 M.O. PLOMERIA, INST. MEDIDOR DE AGUA:*MOPL 6702001 Inst. medidor en tub. ¾" 321.88 100.00% u 5.76923 1 1 321.88*MOPL 6702002 Inst. medidor en tub. 1" 374.15 100.00% u 4.96324 1 1 374.15*MOPL 6702003 Inst. medidor en tub. 1 ½" 407.16 100.00% u 4.56082 1 1 407.16*MOPL 6702004 Inst. medidor en tub. 2" 456.68 100.00% u 4.06627 1 1 456.68*MOPL 6702005 Inst. medidor en tub. 3" 592.86 100.00% u 3.13225 1 1 592.86*MOPL 6702006 Inst. medidor en tub. 4" 931.25 100.00% u 1.99409 1 1 931.25

*MOPL 6702100 M.O. PLOMERIA, INST. NEVERA, BEBEDERO Y FILTRO:*MOPL 6702101 Inst. bebedero animales 371.40 100.00% u 5.00 1 1 371.40*MOPL 6702102 Inst. filtro doméstico 495.20 100.00% u 3.75 1 1 495.20*MOPL 6702103 Inst. Nevera de pie, de tomar agua 530.57 100.00% u 3.50 1 1 530.57

*MOPL 6702200 M.O. PLOMERIA, INST. PIEZA ESP., CAMPANA, POR DIAM., C/BOCA:*MOPL 6702201 Inst. campana 3" 75.66 100.00% u 24.54545 1 1 75.66*MOPL 6702202 Inst. campana 4" 85.28 100.00% u 21.77419 1 1 85.28*MOPL 6702203 Inst. campana 6" 94.91 100.00% u 19.56522 1 1 94.91*MOPL 6702204 Inst. campana 8" 118.30 100.00% u 15.69767 1 1 118.30*MOPL 6702205 Inst. campana 10" 185.70 100.00% u 10.00000 1 1 185.70*MOPL 6702206 Inst. campana 12" 222.84 100.00% u 8.33333 1 1 222.84*MOPL 6702207 Inst. campana 16" 288.87 100.00% u 6.42857 1 1 288.87*MOPL 6702208 Inst. campana 20" 321.88 100.00% u 5.76923 1 1 321.88

*MOPL 6702300 M.O. PLOMERIA, INST. PIEZA ESP., GIBAULT, POR DIAM., C/BOCA:*MOPL 6702301 Inst. Gibault 2" 57.77 100.00% u 32.14286 1 1 57.77*MOPL 6702302 Inst. Gibault 3" 64.65 100.00% u 28.72340 1 1 64.65*MOPL 6702303 Inst. Gibault 4" 64.65 100.00% u 28.72340 1 1 64.65*MOPL 6702304 Inst. Gibault 6" 75.66 100.00% u 24.54545 1 1 75.66*MOPL 6702305 Inst. Gibault 8" 136.18 100.00% u 13.63636 1 1 136.18*MOPL 6702306 Inst. Gibault 10" 152.69 100.00% u 12.16216 1 1 152.69*MOPL 6702307 Inst. Gibault 12" 185.70 100.00% u 10.00000 1 1 185.70*MOPL 6702308 Inst. Gibault 16" 222.84 100.00% u 8.33333 1 1 222.84*MOPL 6702309 Inst. Gibault 20" 288.87 100.00% u 6.42857 1 1 288.87

*MOPL 6702400 M.O. PLOMERIA, INST. PIEZA ESP., PVC, POR DIAM., C/BOCA:*MOPL 6702401 Inst. pieza especial pvc 1" 12.38 100.00% u 150.00000 1 1 12.38*MOPL 6702402 Inst. pieza especial pvc 1 ¼" 17.88 100.00% u 103.84615 1 1 17.88*MOPL 6702403 Inst. pieza especial pvc 1 ½" 17.88 100.00% u 103.84615 1 1 17.88*MOPL 6702404 Inst. pieza especial pvc 2" 17.88 100.00% u 103.84615 1 1 17.88*MOPL 6702405 Inst. pieza especial pvc 3" 22.01 100.00% u 84.37500 1 1 22.01*MOPL 6702406 Inst. pieza especial pvc 4" 27.51 100.00% u 67.50000 1 1 27.51*MOPL 6702407 Inst. pieza especial pvc 6" 33.01 100.00% u 56.25000 1 1 33.01*MOPL 6702408 Inst. pieza especial pvc 8" 45.39 100.00% u 40.90909 1 1 45.39*MOPL 6702409 Inst. pieza especial pvc 10" 57.77 100.00% u 32.142857 1 1 57.77*MOPL 6702410 Inst. pieza especial pvc 12" 64.65 100.00% u 28.72340 1 1 64.65*MOPL 6702411 Inst. pieza especial pvc 16" 75.66 100.00% u 24.54545 1 1 75.66*MOPL 6702412 Inst. pieza especial pvc 20" 94.91 100.00% u 19.56522 1 1 94.91

*MOPL 6702500 M.O. PLOMERIA, INST. PIEZA ESP., ROSCA, POR DIAM., C/BOCA:*MOPL 6702501 Inst. pieza especial con rosca 1" 27.51 100.00% u 67.50000 1 1 27.51*MOPL 6702502 Inst. pieza especial con rosca 1 ¼" 37.14 100.00% u 50.00000 1 1 37.14*MOPL 6702503 Inst. pieza especial con rosca 1 ½" 45.39 100.00% u 40.90909 1 1 45.39*MOPL 6702504 Inst. pieza especial con rosca 2" 57.77 100.00% u 32.14286 1 1 57.77*MOPL 6702505 Inst. pieza especial con rosca 3" 64.65 100.00% u 28.72340 1 1 64.65*MOPL 6702506 Inst. pieza especial con rosca 4" 75.66 100.00% u 24.54545 1 1 75.66*MOPL 6702507 Inst. pieza especial con rosca 6" 112.80 100.00% u 16.46341 1 1 112.80*MOPL 6702508 Inst. pieza especial con rosca 8" 185.70 100.00% u 10.00000 1 1 185.70*MOPL 6702509 Inst. pieza especial con rosca 10" 222.84 100.00% u 8.33333 1 1 222.84*MOPL 6702510 Inst. pieza especial con rosca 12" 288.87 100.00% u 6.42857 1 1 288.87

*MOPL 6702600 M.O. PLOMERIA, INST. TINACO DE AGUA:*MOPL 6702601 Inst. tinaco 3,095.00 100.00% u 0.60 1 1 3,095.00

*MOPL 6702700 M.O. PLOMERIA, INST. TRAMPA GRASA Y CAMARA INSP.:*MOPL 6702701 Inst. cámara insp., tub. 2" 931.25 100.00% u 1.9941 1 1 931.25*MOPL 6702702 Inst. cámara insp., tub. 3" y 4" 931.25 100.00% u 1.9941 1 1 931.25*MOPL 6702703 Inst. cámara insp. tub. 5" y 6" 1,241.64 100.00% u 1.4956 1 1 1,241.64*MOPL 6702704 Inst. trampa de grasa 1 cámara 1,526.86 100.00% u 1.22 1 1 1,526.86*MOPL 6702705 Inst. trampa de grasa 2 cámaras 2,372.83 100.00% u 0.78 1 1 2,372.83

*Para + de 2 entradas, 20% adic. por entrada extra

*MOPL 6702800 M.O. PLOMERIA, INST. VALVULA DE AIRE:*MOPL 6702801 Inst. válvula de aire + Clamps y acces. 678.15 100.00% u 2.73834 1 1 678.15

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 32

Page 33: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOPL 6702900 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, CAMPANA:*MOPL 6702901 Inst. válvula compuerta, campana 2" 288.87 100.00% u 6.42857 1 1 288.87*MOPL 6702902 Inst. válvula compuerta, campana 3" 321.88 100.00% u 5.769231 1 1 321.88*MOPL 6702903 Inst. válvula compuerta, campana 4" 407.17 100.00% u 4.5608 1 1 407.17*MOPL 6702904 Inst. válvula compuerta, campana 6" 745.55 100.00% u 2.490775 1 1 745.55*MOPL 6702905 Inst. válvula compuerta, campana 8" 931.25 100.00% u 1.99409 1 1 931.25*MOPL 6702906 Inst. válvula compuerta, campana 10" 1,305.40 100.00% u 1.42255 1 1 1,305.40*MOPL 6702907 Inst. válvula compuerta, campana 12" 1,865.25 100.00% u 0.995575 1 1 1,865.25*MOPL 6702908 Inst. válvula compuerta, campana 16" 2,372.83 100.00% u 0.78261 1 1 2,372.83

*MOPL 6703000 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, PLATILLO:*MOPL 6703001 Inst. válvula compuerta, platillo 2" 222.84 100.00% u 8.33333 1 1 222.84*MOPL 6703002 Inst. válvula compuerta, platillo 3" 288.87 100.00% u 6.42857 1 1 288.87*MOPL 6703003 Inst. válvula compuerta, platillo 4" 374.15 100.00% u 4.9632 1 1 374.15*MOPL 6703004 Inst. válvula compuerta, platillo 6" 474.57 100.00% u 3.913040 1 1 474.57*MOPL 6703005 Inst. válvula compuerta, platillo 8" 678.15 100.00% u 2.73834 1 1 678.15*MOPL 6703006 Inst. válvula compuerta, platillo 10" 745.55 100.00% u 2.490775 1 1 745.55*MOPL 6703007 Inst. válvula compuerta, platillo 12" 931.25 100.00% u 1.99409 1 1 931.25*MOPL 6703008 Inst. válvula compuerta, platillo 16" 1,354.92 100.00% u 1.37056 1 1 1,354.92

*MOPL 6703100 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, ROSCA:*MOPL 6703101 Inst. válvula compuerta, rosca 2" 152.69 100.00% u 12.16216 1 1 152.69*MOPL 6703102 Inst. válvula compuerta, rosca 3" 222.84 100.00% u 8.33333 1 1 222.84*MOPL 6703103 Inst. válvula compuerta, rosca 4" 288.87 100.00% u 6.42857 1 1 288.87*MOPL 6703104 Inst. válvula compuerta, rosca 6" 374.15 100.00% u 4.9632 1 1 374.15*MOPL 6703105 Inst. válvula compuerta, rosca 8" 474.57 100.00% u 3.913040 1 1 474.57

*MOPL 6703200 M.O. PLOMERIA, MONTAR BAÑERA Y DUCHA:*MOPL 6703201 Montar bañera de hierro, especial 1,908.50 100.00% u 1.88053 1 1 4 1,908.50*MOPL 6703202 Montar bañera de hierro, corriente 1,356.30 100.00% u 1.36917 1 1 1,356.30*MOPL 6703203 Montar bañera pesada de hierro 1,435.60 100.00% u 2.5000 1 1 4 1,435.60*MOPL 6703204 Montar bañera plástica o vidriada 931.25 100.00% u 1.9941 1 1 931.25*MOPL 6703205 Montar ducha tipo teléfono 338.39 100.00% u 5.4878 1 1 338.39*MOPL 6703206 Montar llave empotrada para ducha 338.39 100.00% u 5.4878 1 1 338.39*MOPL 6703207 Montar mezcladora de baño 592.86 100.00% u 3.13225 1 1 592.86*MOPL 6703208 Terminación de baño 185.70 100.00% u 10.00 1 1 185.70

*MOPL 6703300 M.O. PLOMERIA, MONTAR FREGADERO Y LAVAPLATO:*MOPL 6703301 Montar freg. acero inox. 1 cámara 848.72 100.00% u 2.188 1 1 848.72*MOPL 6703302 Montar freg. acero inox., 2 cámaras 1,086.69 100.00% u 1.70886 1 1 1,086.69*MOPL 6703303 Montar freg. corriente 848.72 100.00% u 2.188 1 1 848.72*MOPL 6703304 Montar freg. especial 1 cámara 931.25 100.00% u 1.9941 1 1 931.25*MOPL 6703305 Montar freg. especial 2 cámara 1,187.10 100.00% u 1.56431 1 1 1,187.10*MOPL 6703306 Montar lavaplato automático, deméstico 1,356.30 100.00% u 1.36917 1 1 1,356.30*MOPL 6703307 Montar lavaplato automático, industrial o comercial P. A. u 1 1 P. A.*MOPL 6703308 Montar trituradora de hueso, doméstica 1,865.25 100.00% u 0.995575 1 1 1,865.25*MOPL 6703309 Montar trituradora de hueso, industrial o comercial P. A. u 1 1 P. A.

*MOPL 6703400 M.O. PLOMERIA, MONTAR INODORO:*MOPL 6703401 Montar inodoro corriente dos cuerpos 678.15 100.00% u 2.73833 1 1 678.15*MOPL 6703402 Montar inodoro especial, 1 cuerpo 931.25 100.00% u 1.9941 1 1 931.25*MOPL 6703403 Montar inodoro especial, 2 cuerpos 1,526.86 100.00% u 1.21622 1 1 1,526.86*MOPL 6703404 Montar inodoro especial, pared 1,526.86 100.00% u 1.21622 1 1 1,526.86*MOPL 6703405 Montar inodoro fluxómetro o automát. 1,119.70 100.00% u 1.65848 1 1 1,119.70

*MOPL 6703500 M.O. PLOMERIA, MONTAR LAVAMANOS Y BIDET:*MOPL 6703501 Montar bidet 1,016.54 100.00% u 1.82679 1 1 1,016.54*MOPL 6703502 Montar lavamanos clínico, unidad conjunto 5,084.05 100.00% u 0.36526 1 1 5,084.05*MOPL 6703503 Montar lavamanos c/patas 825.33 100.00% u 2.25 1 1 825.33*MOPL 6703504 Montar lavamanos s/patas 678.15 100.00% u 2.73833 1 1 678.15*MOPL 6703505 Montar lavamanos empotrado 1,187.10 100.00% u 1.56431 1 1 1,187.10*MOPL 6703506 Montar lavamanos especial c/patas 1,187.10 100.00% u 1.56431 1 1 1,187.10*MOPL 6703507 Montar lavamanos especial s/patas 931.25 100.00% u 1.9941 1 1 931.25*MOPL 6703508 Montar lavamanos pedestal 928.50 100.00% u 2.00 1 1 928.50*MOPL 6703509 Montar lavamanos salón de belleza 1,187.10 100.00% u 1.56431 1 1 1,187.10

*MOPL 6703600 M.O. PLOMERIA, MONTAR ORINAL:*MOPL 6703601 Montar orinal ½ falda 763.43 100.00% u 2.43243 1 1 763.43*MOPL 6703602 Montar orinal de cemento, terminación 423.67 100.00% u 4.3831 1 1 423.67*MOPL 6703603 Montar orinal falda completa 1,187.10 100.00% u 1.56431 1 1 1,187.10*MOPL 6703604 Montar orinal sencillo 848.72 100.00% u 2.188 1 1 848.72

*MOPL 6703700 M.O. PLOMERIA, SALIDAS DE AGUA, APARATO SANIT., COBRE:*MOPL 6703701 Salida tub. ½", cobre, soldada o roscada 848.72 100.00% u 2.188006 1 1 848.72*MOPL 6703702 Salida tub. ¾", cobre, soldada o roscada 1,016.54 100.00% u 1.82679 1 1 1,016.54*MOPL 6703703 Salida tub. 1", cobre, soldada o roscada 1,187.10 100.00% u 1.56431 1 1 1,187.10*MOPL 6703704 Salida tub. 1 ¼" en adelante, cobre, soldada o roscada P. A. u 1 1 P. A.

*MOPL 6703800 M.O. PLOMERIA, SALIDAS DE AGUA, APARATO SANIT., H. G. o PVC:*MOPL 6703801 Montar filtro de agua, domiciliario 763.43 100.00% u 2.43243 1 1 763.43*MOPL 6703802 Montar filtro de agua, industrial o comercial P. A. u 1 1 P. A.*MOPL 6703803 Salida de agua tub. ½", h.g. o pvc 592.86 100.00% u 3.13225 1 1 592.86*MOPL 6703804 Salida de agua tub. ¾", h.g. o pvc 592.86 100.00% u 3.13225 1 1 592.86*MOPL 6703805 Salida de agua fria y caliente calentador domestico 763.43 100.00% u 2.43243 1 1 763.43*MOPL 6703806 Salida de agua fria y caliente calentador industrial P. A. u 1 1 P. A.*MOPL 6703807 Salida de agua inodoro corriente 763.43 100.00% u 2.43243 1 1 763.43*MOPL 6703808 Salida de agua inodoro y orinal fluxómetro 1,187.10 100.00% u 1.56431 1 1 1,187.10*MOPL 6703809 Salida de agua orinal de falda completa, no fluxómetro 763.43 100.00% u 2.43243 1 1 763.43*MOPL 6703810 Salida de agua tub. 1", h.g. o pvc 1,187.10 100.00% u 1.56431 1 1 1,187.10*MOPL 6703811 Salida de agua tub. 1 ¼", h.g. o pvc 1,187.10 100.00% u 1.56431 1 1 1,187.10*MOPL 6703812 Salida de agua tub. 1 ½", h.g. o pvc 1,187.10 100.00% u 1.56431 1 1 1,187.10*MOPL 6703813 Salida de agua tub. 2", h.g. o pvc 1,319.00 100.00% u 1.40788 1 1 1,319.00

Nota: Salida agua colgante, pagar 35% del costo establecido

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 33

Page 34: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOPL 6703900 M.O. PLOMERIA, TERM. LAVADERO Y VERTEDERO:*MOPL 6703901 Term. lavadero 1 cám. c/vert. 931.25 100.00% u 1.9941 1 1 931.25*MOPL 6703902 Term. lavadero 1 cám. s/vert. 592.86 100.00% u 3.13225 1 1 592.86*MOPL 6703903 Term. lavadero 2 cám. c/vert. 931.25 100.00% u 1.9941 1 1 931.25*MOPL 6703904 Term. lavadero 2 cám. s/vert. 763.43 100.00% u 2.43243 1 1 763.43*MOPL 6703905 Term. vertedero de cem. o granito 170.57 100.00% u 10.8871 1 1 170.57*MOPL 6703906 Term. vertedero de hierro 931.25 100.00% u 1.9941 1 1 931.25

*MOPL 6704000 M.O. PLOMERIA, TUB. ALCANTARILLADO SANIT. Y PLUVIAL PROF. HASTA 3.00 M.:*MOPL 6704001 Tub. alcant., 6" 45.52 100.00% m 53.0303 1 2 45.52*MOPL 6704002 Tub. alcant., 8" 57.94 100.00% m 41.6667 1 2 57.94*MOPL 6704003 Tub. alcant., 12" 65.02 100.00% m 54.26 1 4 65.02*MOPL 6704004 Tub. alcant., 15" 85.78 100.00% m 41.13 1 4 85.78*MOPL 6704005 Tub. alcant., 21" 159.11 100.00% m 22.173 1 4 159.11*MOPL 6704006 Tub. alcant., 24" 224.13 100.00% m 15.7411 1 4 224.13*MOPL 6704007 Tub. alcant., 30" 323.75 100.00% m 10.8974 1 4 323.75*MOPL 6704008 Tub. alcant., 36" 376.32 100.00% m 9.375 1 4 376.32

*Bajar tub. hasta 8" al fondo zanja y colocar asiento arena corre por plomeros. Diámetro mayor corre por patrono o empleador

*MOPL 6704100 M.O. PLOMERIA, TUB. ALCANTARILLADO SANIT. Y PLUVIAL PROF. MAYOR DE 3.00 M.:*MOPL 6704101 Tub. alcant., 6" 64.83 100.00% m 37.23404 1 2 64.83*MOPL 6704102 Tub. alcant., 8" 75.87 100.00% m 31.81818 1 2 75.87*MOPL 6704103 Tub. alcant., 12" 85.78 100.00% m 41.13 1 4 85.78*MOPL 6704104 Tub. alcant., 15" 103.76 100.00% m 34.00 1 4 103.76*MOPL 6704105 Tub. alcant., 21" 186.78 100.00% m 18.89 1 4 186.78*MOPL 6704106 Tub. alcant., 24" 290.54 100.00% m 12.143 1 4 290.54*MOPL 6704107 Tub. alcant., 30" 376.32 100.00% m 9.375 1 4 376.32*MOPL 6704108 Tub. alcant., 36" 480.08 100.00% m 7.3487 1 4 480.08

*Bajar tub. hasta 8" al fondo zanja y colocar asiento arena corre por plomeros. Diámetro mayor corre por patrono o empleador

*MOPL 6704200 M.O. PLOMERIA, TUB. ASBESTO CEMENTO:*MOPL 6704201 Tub. 3" asbesto cemento 22.01 100.00% m 84.375 1 1 22.01*MOPL 6704202 Tub. 4" asbesto cemento 22.01 100.00% m 84.375 1 1 22.01*MOPL 6704203 Tub. 6" asbesto cemento 30.26 100.00% m 61.36 1 1 30.26*MOPL 6704204 Tub. 8" asbesto cemento 37.14 100.00% m 50.00 1 1 37.14*MOPL 6704205 Tub. 12" asbesto cemento 45.66 100.00% m 77.27 1 4 45.66*MOPL 6704206 Tub. 16" asbesto cemento 76.10 100.00% m 46.36 1 4 76.10*MOPL 6704207 Tub. 20" asbesto cemento 95.47 100.00% m 36.955 1 4 95.47

*Tub. 3" y 4" serán bajados al fondo zanja por plomeros. Diám. Mayor corre por patrono o empleador

*MOPL 6704300 M.O. PLOMERIA, TUB. HIERRO FUNDIDO O ACERO:*MOPL 6704301 Tub. 3" hierro fudido o acero 37.14 100.00% m 50.00 1 1 37.14*MOPL 6704302 Tub. 4" hierro fudido o acero 45.39 100.00% m 40.90909 1 1 45.39*MOPL 6704303 Tub. 6" hierro fudido o acero 57.77 100.00% m 32.14286 1 1 57.77*MOPL 6704304 Tub. 8" hierro fudido o acero 64.65 100.00% m 28.7234 1 1 64.65*MOPL 6704305 Tub. 10" hierro fudido o acero 88.54 100.00% m 39.845 1 4 88.54*MOPL 6704306 Tub. 12" hierro fudido o acero 136.97 100.00% m 25.758 1 4 136.97

*Tub. 3" y 4" serán bajados al fondo zanja por plomeros. Diám. Mayor corre por patrono o empleador

*MOPL 6704400 M.O. PLOMERIA, TUB. HIERRO GALV.:*MOPL 6704401 Tub. ½" galv. 12.38 100.00% m 150.00 1 1 12.38*MOPL 6704402 Tub. ¾" galv. 15.13 100.00% m 122.72727 1 1 15.13*MOPL 6704403 Tub. 1" a 1 ½" galv. 22.01 100.00% m 84.375 1 1 22.01*MOPL 6704404 Tub. 2" galv. 27.51 100.00% m 67.50 1 1 27.51*MOPL 6704405 Tub. 2 ½" galv. 33.01 100.00% m 56.25 1 1 33.01*MOPL 6704406 Tub. 3" galv. 37.14 100.00% m 50.00 1 1 37.14*MOPL 6704407 Tub. 4" galv. 45.39 100.00% m 40.90909 1 1 45.39*MOPL 6704408 Tub. 6" galv. 57.77 100.00% m 32.14286 1 1 57.77*MOPL 6704409 Tub. 8" galv. 64.65 100.00% m 28.72340 1 1 64.65*MOPL 6704410 Tub. 10" galv. 71.94 100.00% m 49.04 1 4 71.94*MOPL 6704411 Tub. 12" galv. P. A. m 1 4 P. A.

*Tub. Hasta 6" serán bajados al fondo zanja por plomeros. Diám. Mayor corre por patrono o empleador

*MOPL 6704500 M.O. PLOMERIA, TUB. PVC:*MOPL 6704501 Tub. ½" pvc y ¾" pvc 5.02 100.00% m 369.86301 1 1 5.02*MOPL 6704502 Tub. ¾" pvc 10.04 100.00% m 184.93150 1 1 10.04*MOPL 6704503 Tub. 1 ¼" y 1 ½" pvc 12.56 100.00% m 147.86418 1 1 12.56*MOPL 6704504 Tub. 2" pvc 12.56 100.00% m 147.86418 1 1 12.56*MOPL 6704505 Tub. 3" pvc 17.88 100.00% m 103.84615 1 1 17.88*MOPL 6704506 Tub. 4" pvc 20.63 100.00% m 90.00 1 1 20.63*MOPL 6704507 Tub. 6" pvc 25.10 100.00% m 73.97260 1 1 25.10*MOPL 6704508 Tub. 8" pvc 27.51 100.00% m 67.50 1 1 27.51*MOPL 6704509 Tub. 10" pvc 33.20 100.00% m 106.25 1 4 33.20*MOPL 6704510 Tub. 12" pvc 35.97 100.00% m 98.09 1 4 35.97

*MOVA 6800000 M.O. VARILLEROS:*MOVA 6800001 Coloc. acero ¼" en piso o losa 364.85 100.00% qq 6.389 1 1 1 364.85*MOVA 6800002 Coloc. acero alta resistencia 366.08 100.00% qq 7.889 1 2 1 366.08*MOVA 6800003 Coloc. acero col. 3/8" ó ½", hasta 6 de ½" 81.08 100.00% m 28.750 1 1 1 81.08*MOVA 6800004 Coloc. acero col. Redonda 6 de ½" hasta 4 de ¾" 121.62 100.00% m 19.167 1 1 1 121.62*MOVA 6800005 Coloc. acero dintel y v. Amarre hasta 20x.40 y ½" ó 3/8" 81.08 100.00% m 28.750 1 1 1 81.08*MOVA 6800006 Coloc. Acero fuera ciudad (30 km. o más) (25% adic.) P. A. P. A.*MOVA 6800007 Coloc. acero losa con Lima Hoya o Lima Tesa (50% adic.) 366.08 100.00% qq 7.889 1 2 1 366.08*MOVA 6800008 Coloc. acero malla electrosoldada 364.85 100.00% qq 6.389 1 1 1 364.85

h 6800009 Coloc. acero normal 243.24 100.00% qq 9.583 1 1 1 243.24*MOVA 6800010 Coloc. acero rampa escalera corriente 2,406.67 100.00% rampa 1.200 1 2 1 2,406.67*MOVA 6800011 Coloc. acero viga 6 de ½" ó ¾", 2 de 1" y 2 de ¾", 25x40 81.35 100.00% m 35.500 1 2 1 81.35*MOVA 6800012 Coloc. acero viga postens. y pórticos en col. 386.61 100.00% qq 7.470 1 2 1 386.61*MOVA 6800013 Coloc. acero zapata de muros 81.08 100.00% m 28.750 1 1 1 81.08*MOVA 6800014 Subir acero techo 2do. Nivel (10%) 24.74 100.00% qq 70.000 4 24.74*MOVA 6800015 Subir acero techo 3er. Nivel (15%) 37.11 100.00% qq 46.667 4 37.11*MOVA 6800016 Subir acero techo 4to. Nivel (20%) 49.49 100.00% qq 35.000 4 49.49

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 34

Page 35: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLASREFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3 AY TC TNC JUL 2012

*MOVA 6800017 Subir acero techo 5to. Nivel (25%) 61.86 100.00% qq 28.000 4 61.86*MOVA 6800018 Subir acero techo 6to. Nivel (30%) 74.23 100.00% qq 23.333 4 74.23*MOVA 6800019 Trasladar acero distancia > 10 m. (10% adicional) 10.00% 100.00% qq 10.00%

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 35

Page 36: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. MANO DE OBRA CUADRILLAS

REFERENCIA D E S C R I P C I O N JORNAL DIARIO INDICE U. JORNAL X

HORAJORNAL

MENSUALJornal Diario

JUL 2012

SALARIO MENSUAL MINIMO EN RD$ 6,451.50 100.00% 6,451.50ORDENADO ALFABETICAMENTE

MANO DE OBRA JORNALES DIARIO (Sin ITBIS)*MOJO 6940000 MANO DE OBRA JORNALES DIARIOS:*MOJO 6940001 Ayudante (AY) 557.00 100.00% día 69.625 13,273.31 557.00*MOJO 6940021 Ayudante Carpintero (AYCA) 557.00 100.00% día 69.625 13,273.31 557.00*MOJO 6940041 Ayudante Demolición (AYDE) 557.00 100.00% día 69.625 13,273.31 557.00*MOJO 6940061 Ayudante Electricista (AYEL) 557.00 100.00% día 69.625 13,273.31 557.00*MOJO 6940081 Ayudante Pintor (AYPI) 557.00 100.00% día 69.625 13,273.31 557.00*MOJO 6940101 Ayudante Plomero (AYPL) 557.00 100.00% día 69.625 13,273.31 557.00*MOJO 6940121 Ayudante Varillero (AYVA) 557.00 100.00% día 69.625 13,273.31 557.00*MOJO 6940400 Brigada topográfica, Estación Total (BT) 5,075.00 100.00% día 634.375 120,937.25 5,075.00*MOJO 6940900 Ebanista Instalador (EBAINS) 2,000.00 100.00% día 250.000 47,660.00 2,000.00*MOJO 6941400 Ebanista OP1 (EBAOP1) 1,100.00 100.00% día 137.500 26,213.00 1,100.00*MOJO 6941900 Ebanista Pintor (EBAPIN) 1,100.00 100.00% día 137.500 26,213.00 1,100.00*MOJO 6942400 Ebanista Pulidor (EBAPUL) 675.00 100.00% día 84.375 16,085.25 675.00*MOJO 6940122 Maestro de área (MA) 1,300.00 100.00% día 162.500 30,979.00 1,300.00*MOJO 6940142 Maestro de Área Carpintero (MACA) 1,300.00 100.00% día 162.500 30,979.00 1,300.00*MOJO 6940162 Maestro de Área Demolición (MADE) 1,300.00 100.00% día 162.500 30,979.00 1,300.00*MOJO 6940182 Maestro de Área Electricista (MAEL) 1,300.00 100.00% día 162.500 30,979.00 1,300.00*MOJO 6940202 Maestro de Área Pintor (MAPI) 1,300.00 100.00% día 162.500 30,979.00 1,300.00*MOJO 6940222 Maestro de Área Plomero (MAPL) 1,300.00 100.00% día 162.500 30,979.00 1,300.00*MOJO 6940242 Maestro de Área Varillero (MAVA) 1,300.00 100.00% día 162.500 30,979.00 1,300.00*MOJO 6940123 Operario primera categoría (OP1) 1,032.00 100.00% día 129.000 24,592.56 1,032.00*MOJO 6940143 Operario 1ra. Categoría Carpintero (OP1CA) 1,032.00 100.00% día 129.000 24,592.56 1,032.00*MOJO 6940163 Operario 1ra. Categoría Demolición (OP1DE) 1,032.00 100.00% día 129.000 24,592.56 1,032.00*MOJO 6940183 Operario 1ra. Categoría Electricista (OP1EL) 1,032.00 100.00% día 129.000 24,592.56 1,032.00*MOJO 6940203 Operario 1ra. Categoría Pintor (OP1PI) 1,032.00 100.00% día 129.000 24,592.56 1,032.00*MOJO 6940223 Operario 1ra. Categoría Plomero (OP1PL) 1,032.00 100.00% día 129.000 24,592.56 1,032.00*MOJO 6940243 Operario 1ra. Categoría Varillero (OP1VA) 1,032.00 100.00% día 129.000 24,592.56 1,032.00*MOJO 6940124 Operario Segunda categoría (OP2) 825.00 100.00% día 103.125 19,659.75 825.00*MOJO 6940144 Operario 2da. Categoría Carpintero (OP2CA) 825.00 100.00% día 103.125 19,659.75 825.00*MOJO 6940164 Operario 2da. Categoría Demolición (OP2DE) 825.00 100.00% día 103.125 19,659.75 825.00*MOJO 6940184 Operario 2da. Categoría Electricista (OP2EL) 825.00 100.00% día 103.125 19,659.75 825.00*MOJO 6940204 Operario 2da. Categoría Pintor (OP2PI) 825.00 100.00% día 103.125 19,659.75 825.00*MOJO 6940224 Operario 2da. Categoría Plomero (OP2PL) 825.00 100.00% día 103.125 19,659.75 825.00*MOJO 6940244 Operario 2da. Categoría Varillero (OP2VA) 825.00 100.00% día 103.125 19,659.75 825.00*MOJO 6940125 Operario tercera categoría - Terminador (OP3) 723.00 100.00% día 90.375 17,229.09 723.00*MOJO 6940126 Técnico calificado (TC) 474.00 100.00% día 59.250 11,295.42 474.00*MOJO 6940146 Técnico Calificado Carpintero (TCCA) 474.00 100.00% día 59.250 11,295.42 474.00*MOJO 6940166 Técnico Calificado Demolición (TCDE) 474.00 100.00% día 59.250 11,295.42 474.00*MOJO 6940186 Técnico Calificado Electricista (TCEL) 474.00 100.00% día 59.250 11,295.42 474.00*MOJO 6940206 Técnico Calificado Pintor (TCPI) 474.00 100.00% día 59.250 11,295.42 474.00*MOJO 6940226 Técnico Calificado Plomero (TCPL) 474.00 100.00% día 59.250 11,295.42 474.00*MOJO 6940246 Técnico Calificado Varillero (TCVA) 474.00 100.00% día 59.250 11,295.42 474.00*MOJO 6940127 Técnico no calificado o PEON (TNC) 433.00 100.00% día 54.125 10,318.39 433.00*MOJO 6940147 Técnico no Calificado o PEON Carpintero (TNCCA) 433.00 100.00% día 54.125 10,318.39 433.00*MOJO 6940167 Técnico no Calificado o PEON Demolición (TNCDE) 433.00 100.00% día 54.125 10,318.39 433.00*MOJO 6940187 Técnico no Calificado o PEON Electricista (TNCEL) 433.00 100.00% día 54.125 10,318.39 433.00*MOJO 6940207 Técnico no Calificado o PEON Pintor (TNCPI) 433.00 100.00% día 54.125 10,318.39 433.00*MOJO 6940227 Técnico no Calificado o PEON Plomero (TNCPL) 433.00 100.00% día 54.125 10,318.39 433.00*MOJO 6940247 Técnico no Calificado o PEON Varillero (TNCVA) 433.00 100.00% día 54.125 10,318.39 433.00

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 34

Page 37: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

* 10000000 ANALISIS DE COSTOS (Con ITBIS incluido)*ACE 10010000 A C E R O S

*ACE 10010100 ACERO DE ¼":1 Acero ¼" 1.00 qq 1,433.13 1,433.13 101.72% 1,408.842 Alambre #18 2.50 lb 34.64 86.60 101.70% 85.15

QQ $1,519.73 101.72% 1,493.99*ACE 10010101 ACERO GRADO 40, 3/8" x 20':

1 Acero 3/8" 1.00 qq 2,044.81 2,044.81 101.72% 2,010.152 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,114.09 101.72% 2,078.27*ACE 10010102 ACERO GRADO 40, 3/8" x 25':

1 Acero 3/8" 1.00 qq 2,002.92 2,002.92 101.72% 1,968.972 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,072.20 101.72% 2,037.09*ACE 10010103 ACERO GRADO 40, ½" x 20':

1 Acero ½" 1.00 qq 2,052.19 2,052.19 101.72% 2,017.402 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,121.47 101.72% 2,085.52*ACE 10010104 ACERO GRADO 40, ½" x 25':

1 Acero ½" 1.00 qq 2,009.22 2,009.22 101.72% 1,975.172 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,078.50 101.72% 2,043.29*ACE 10010105 ACERO GRADO 40, ¾":

1 Acero ¾" 1.00 qq 2,007.42 2,007.42 101.72% 1,973.392 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,076.70 101.72% 2,041.51*ACE 10010106 ACERO GRADO 40, DE 1":

1 Acero 1" 1.00 qq 1,989.53 1,989.53 101.72% 1,955.812 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,058.81 101.72% 2,023.93*ACE 10010107 ACERO GRADO 60, 3/8" x 20':

1 Acero 3/8" 1.00 qq 2,281.91 2,281.91 101.72% 2,243.232 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,351.19 101.72% 2,311.35*ACE 10010108 ACERO GRADO 60, 3/8" x 25':

1 Acero 3/8" 1.00 qq 2,362.89 2,362.89 101.72% 2,322.842 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,432.17 101.72% 2,390.96*ACE 10010109 ACERO GRADO 60, ½" x 20':

1 Acero ½" 1.00 qq 2,344.68 2,344.68 101.72% 2,304.942 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,413.96 101.72% 2,373.06*ACE 10010110 ACERO GRADO 60, ½" x 25':

1 Acero ½" 1.00 qq 2,340.35 2,340.35 101.72% 2,300.692 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,409.63 101.72% 2,368.81*ACE 10010111 ACERO GRADO 60, ¾":

1 Acero ¾" 1.00 qq 2,338.43 2,338.43 101.72% 2,298.802 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,407.71 101.72% 2,366.92*ACE 10010112 ACERO GRADO 60, DE 1":

1 Acero 1" 1.00 qq 2,313.66 2,313.66 101.72% 2,274.452 Alambre #18 2.00 lb 34.64 69.28 101.70% 68.12

QQ $2,382.94 101.72% 2,342.57

*BLO 10030000 BLOQUES, MUROS DE

*BLO 10030001 BLOQUES HORM. 4", ¼" A .80 M.:1 Bloques horm. + 3% desp. 12.875 u 23.91 307.84 101.70% 302.692 Mortero 1:3 en juntas + 30% desp. 0.0200 m3 4,929.27 98.59 101.64% 97.003 Horm. en cámaras + 2% desp. 0.0092 m3 4,432.36 40.78 101.49% 40.184 Acero ¼" + 20% desp. 0.0112 qq 1,519.73 17.02 101.73% 16.735 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 35.70 0.08 100.00% 0.086 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 1,032.00 23.74 100.00% 23.747 Corte y amarre varilla 13.00 u 0.55 7.15 100.00% 7.158 Llenado huecos 13.00 u 1.11 14.43 100.00% 14.439 Coloc. bloques 13.00 u 14.85 193.05 100.00% 193.05

M2 $702.68 101.10% 695.05*BLO 10030002 BLOQUES HORM. 5", 3/8" A .80 M.:

1 Bloques horm. + 3% desp. 12.875 u 24.12 310.55 101.73% 305.272 Mortero 1:3 en juntas + 30% desp. 0.0260 m3 4,929.27 128.16 101.64% 126.093 Horm. en cámaras + 2% desp. 0.0200 m3 4,432.36 88.65 101.50% 87.344 Acero 3/8" x 20' grado 40 + 20% desp. 0.0247 qq 2,114.09 52.22 101.73% 51.335 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 35.70 0.08 100.00% 0.086 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 1,032.00 23.74 100.00% 23.747 Corte y amarre varilla 13.00 u 0.55 7.15 100.00% 7.158 Llenado huecos 13.00 u 1.11 14.43 100.00% 14.439 Coloc. bloques 13.00 u 12.37 160.81 100.00% 160.81

M2 $785.79 101.23% 776.24*BLO 10030003 BLOQUES HORM. 6", 3/8" A .40 M.:

1 Bloques horm. + 3% desp. 12.875 u 26.25 337.97 101.71% 332.302 Mortero 1:3 en juntas + 30% desp. 0.0312 m3 4,929.27 153.79 101.64% 151.313 Horm. en cámaras + 2% desp. 0.0480 m3 4,432.36 212.75 101.49% 209.624 Acero 3/8" x 20' grado 40 + 20% desp. 0.0493 qq 2,114.09 104.22 101.72% 102.465 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 35.70 0.08 100.00% 0.086 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 1,032.00 23.74 100.00% 23.747 Corte y amarre varilla 13.00 u 1.11 14.43 100.00% 14.438 Llenado huecos 13.00 u 2.22 28.86 100.00% 28.869 Coloc. bloques 13.00 u 12.37 160.81 100.00% 160.81

M2 $1,036.65 101.27% 1,023.61

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 35

Page 38: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012*BLO 10030004 BLOQUES HORM. 6", 3/8" A .80 M.:

1 Bloques horm. + 3% desp. 12.875 u 26.25 337.97 101.71% 332.302 Mortero 1:3 en juntas + 30% desp. 0.0312 m3 4,929.27 153.79 101.64% 151.313 Horm. en cámaras + 2% desp. 0.0240 m3 4,432.36 106.38 101.50% 104.814 Acero 3/8" x 20' grado 40 + 20% desp. 0.0247 qq 2,114.09 52.22 101.73% 51.335 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 35.70 0.08 100.00% 0.086 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 1,032.00 23.74 100.00% 23.747 Corte y amarre varilla 13.00 u 0.55 7.15 100.00% 7.158 Llenado huecos 13.00 u 1.11 14.43 100.00% 14.439 Coloc. bloques 13.00 u 12.37 160.81 100.00% 160.81

M2 $856.57 101.25% 845.96*BLO 10030005 BLOQUES HORM. 6" VIOL. 2 CARAS, 3/8" A .80 M.:

1 Bloques horm. + 3% desp. 12.875 u 26.25 337.97 101.71% 332.302 Mortero de juntas + 30% desp. 0.0312 m3 4,929.27 153.79 101.64% 151.313 Horm. en cámaras + 2% desp. 0.0240 m3 4,432.36 106.38 101.50% 104.814 Acero 3/8" x 20' grado 40 + 20% desp. 0.0247 qq 2,114.09 52.22 101.73% 51.335 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 35.70 0.08 100.00% 0.086 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 1,032.00 23.74 100.00% 23.747 Corte y amarre varilla 13.00 u 0.55 7.15 100.00% 7.158 Llenado huecos 13.00 u 1.11 14.43 100.00% 14.439 Coloc. bloques + violinado ambas caras. 13.00 u 15.67 203.71 100.00% 203.71

M2 $899.47 101.19% 888.86*BLO 10030006 BLOQUES 8", 3/8" A .20 M. + 2 HORIZ. DE 3/8" CADA 0.40 M.: 9.15 M2

1 Bloques horm. + 3% desp. 12.875 u 34.47 443.80 101.71% 436.332 Mortero 1:3 en juntas + 30% desp. 0.0390 m3 4,929.27 192.24 101.64% 189.143 Horm. en cámaras + 2% desp. 0.0916 m3 4,432.36 406.00 101.49% 400.034 Acero horiz. 3/8" x 20' grado 40 + 20% desp. 0.0740 qq 2,114.09 156.44 101.72% 153.795 Acero vert. 3/8" x 20' grado 60 + 20% desp. 0.0678 qq 2,351.19 159.41 101.72% 156.716 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 35.70 0.08 100.00% 0.087 Andamios. 0.1818 pt 35.70 6.49 101.72% 6.388 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 1,032.00 23.74 100.00% 23.749 Corte y amarre varilla. 13.00 u 2.13 27.65 100.00% 27.6510 Llenado huecos. 13.00 u 2.22 28.86 100.00% 28.8611 Coloc. bloques. 13.00 u 13.75 178.75 100.00% 178.75

M2 $1,623.46 101.37% 1,601.46*BLO 10030007 BLOQUES HORM. 8", 3/8" A .20 M.:

1 Bloques horm. + 3% desp. 12.875 u 34.47 443.80 101.71% 436.332 Mortero 1:3 en juntas + 30% desp. 0.0390 m3 4,929.27 192.24 101.64% 189.143 Horm. en cámaras + 2% desp. 0.0916 m3 4,432.36 406.00 101.49% 400.034 Acero 3/8" x 20' grado 40 + 20% desp. 0.0740 qq 2,114.09 156.44 101.72% 153.795 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 35.70 0.08 100.00% 0.086 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 1,032.00 23.74 100.00% 23.747 Corte y amarre varilla 13.00 u 1.65 21.45 100.00% 21.458 Llenado huecos 13.00 u 4.12 53.56 100.00% 53.569 Coloc. bloques 13.00 u 13.75 178.75 100.00% 178.75

M2 $1,476.06 101.32% 1,456.87*BLO 10030008 BLOQUES HORM. 8", 3/8" A .40 M.:

1 Bloques horm. + 3% desp. 12.875 u 34.47 443.80 101.71% 436.332 Mortero 1:3 en juntas + 30% desp. 0.0390 m3 4,929.27 192.24 101.64% 189.143 Horm. en cámaras + 2% desp. 0.0612 m3 4,432.36 271.26 101.49% 267.274 Acero 3/8" x 20' grado 40 + 20% desp. 0.0493 qq 2,114.09 104.22 101.72% 102.465 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 35.70 0.08 100.00% 0.086 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 1,032.00 23.74 100.00% 23.747 Corte y amarre varilla 13.00 u 1.11 14.43 100.00% 14.438 Llenado huecos 13.00 u 2.22 28.86 100.00% 28.869 Coloc. bloques 13.00 u 13.75 178.75 100.00% 178.75

M2 $1,257.38 101.32% 1,241.06*BLO 10030009 BLOQUES HORM. 8", 3/8" A .80 M.:

1 Bloques horm. + 3% desp. 12.875 u 34.47 443.80 101.71% 436.332 Mortero 1:3 en juntas + 30% desp. 0.0390 m3 4,929.27 192.24 101.64% 189.143 Horm. en cámaras + 2% desp. 0.0306 m3 4,432.36 135.63 101.49% 133.644 Acero 3/8" x 20' grado 40 + 20% desp. 0.0247 qq 2,114.09 52.22 101.73% 51.335 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 35.70 0.08 100.00% 0.086 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 1,032.00 23.74 100.00% 23.747 Corte y amarre varilla 13.00 u 0.55 7.15 100.00% 7.158 Llenado huecos 13.00 u 1.11 14.43 100.00% 14.439 Coloc. bloques 13.00 u 13.75 178.75 100.00% 178.75

M2 $1,048.04 101.30% 1,034.59*BLO 10030010 BLOQUES HORM. 8", C. LLENAS, 3/8" A 0.40 M.:

1 Bloques horm. + 3% desp. 12.875 u 34.47 443.80 101.71% 436.332 Mortero 1:3 en juntas + 30% desp. 0.0390 m3 4,929.27 192.24 101.64% 189.143 Horm. en cámaras + 2% desp. 0.0916 m3 4,432.36 406.00 101.49% 400.034 Acero 3/8" x 20' grado 40 + 20% desp. 0.0493 qq 2,114.09 104.22 101.72% 102.465 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 35.70 0.08 100.00% 0.086 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 1,032.00 23.74 100.00% 23.747 Corte y amarre varilla 13.00 u 1.10 14.30 100.00% 14.308 Llenado huecos 13.00 u 2.22 28.86 100.00% 28.869 Coloc. bloques 13.00 u 13.75 178.75 100.00% 178.75

M2 $1,391.99 101.33% 1,373.69*BLO 10030011 BLOQUES HORM. 12", 3/8" A .80 M.:

1 Bloques horm. + 3% desp. 12.875 u 108.65 1,398.87 101.73% 1,375.052 Mortero 1:3 en juntas + 30% desp. 0.0593 m3 4,929.27 292.31 101.64% 287.593 Horm. en cámaras + 2% desp. 0.0178 m3 4,432.36 78.90 101.49% 77.744 Acero 3/8" x 20' grado 40 + 20% desp. 0.0247 qq 2,114.09 52.22 101.73% 51.335 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 35.70 0.08 100.00% 0.086 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 1,032.00 23.74 100.00% 23.747 Corte y amarre varilla 13.00 u 0.55 7.15 100.00% 7.158 Llenado huecos 13.00 u 1.11 14.43 100.00% 14.439 Coloc. bloques 13.00 u 25.43 330.59 100.00% 330.59

M2 $2,198.29 101.41% 2,167.70*BLO 10030012 BLOQUES CALADOS LADRILLO 6"x6"x6":

1 Mortero 1:4 para empañete + 10% desp. 0.0180 m3 5,595.53 100.72 101.57% 99.162 Bloques calados + 5% desp. 46.67 u 39.56 1,846.27 101.70% 1,815.46

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 36

Page 39: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

3 Colocación bloques calados. 46.67 u 27.38 1,277.82 100.00% 1,277.82M2 $3,224.81 101.01% 3,192.44

*BLO 10030013 BLOQUES CALADOS LADRILLO 8"x8"x6":1 Mortero 1:4 para empañete + 10% desp. 0.0116 m3 5,595.53 64.91 101.56% 63.912 Bloques calados + 5% desp. 26.25 u 40.83 1,071.79 101.69% 1,053.943 Colocación bloques calados. 26.25 u 27.38 718.73 100.00% 718.73

M2 $1,855.43 101.03% 1,836.58*BLO 10030014 BLOQUES CALADOS TIPO PERSIANA 15x20x40:

1 Mortero 1:4 para empañete + 10% desp. 0.0086 m3 5,595.53 48.12 101.56% 47.382 Bloques calados + 5% desp. 13.13 u 75.88 996.30 101.72% 979.503 Colocación bloques calados. 13.13 u 27.38 359.50 100.00% 359.50

M2 $1,403.92 101.27% 1,386.38

*BOR 10050000 BORDILLOS DE BLOQUES DE HORM.

*BOR 10050001 BORDILLO 4", 2 LINEAS, 1:2:4, ZAP. .20x.15 M.)1 Excavación (1.00 x .20 x .55 m.) 0.11 m3 272.33 29.96 100.00% 29.962 Relleno de reposición 0.0400 m3 225.68 9.03 100.22% 9.013 Bote material excavado sobrante 0.0900 m3 351.88 31.67 101.73% 31.134 Horm. 1:2:4 en zapata (2 de 3/8" + 3/8 a .30 m.) 0.0300 m3 10,104.70 303.14 101.20% 299.565 Bloques de 4" 0.4000 m2 702.68 281.07 101.10% 278.026 Empañete 0.7000 m2 256.87 179.81 100.82% 178.357 Cantos 1.10 m 82.38 90.62 100.79% 89.918 Pintura acrílica 0.70 m2 152.96 107.07 101.15% 105.85

M $1,032.37 101.04% 1,021.79*BOR 10050002 BORDILLO 6", 2 LINEAS, 1:2:4, ZAP. .30x.15 M.)

1 Excavación (1.00 x .30 x .55 m.) 0.17 m3 272.33 46.30 100.00% 46.302 Relleno de reposición 0.0636 m3 225.68 14.36 100.14% 14.343 Bote material excavado sobrante 0.1400 m3 351.88 49.26 101.71% 48.434 Horm. 1:2:4 en zapata (2 de 3/8" + 3/8 a .30 m.) 0.0500 m3 8,450.78 422.54 101.28% 417.205 Bloques de 6" 0.4000 m2 856.57 342.63 101.26% 338.386 Empañete 0.8000 m2 256.87 205.50 100.82% 203.827 Cantos 1.10 m 82.38 90.62 100.79% 89.918 Pintura acrílica 0.80 m2 152.96 122.37 101.16% 120.97

M $1,293.58 101.11% 1,279.35*BOR 10050003 BORDILLO 6", 2 LINEAS, 1:2:4, ZAP. .40x.15 M.)

1 Excavación (1.00 x .40 x .55 m.) 0.22 m3 272.33 59.91 100.00% 59.912 Relleno de reposición 0.0800 m3 225.68 18.05 100.11% 18.033 Bote material excavado sobrante 0.1800 m3 351.88 63.34 101.73% 62.264 Horm. 1:2:4 en zapata (2 de 3/8" + 3/8 a .30 m.) 0.0600 m3 7,625.55 457.53 101.33% 451.515 Bloques de 6" 0.4000 m2 1,048.04 419.22 101.30% 413.846 Empañete 0.8000 m2 256.87 205.50 100.82% 203.827 Cantos 1.10 m 82.38 90.62 100.79% 89.918 Pintura acrílica 0.80 m2 152.96 122.37 101.16% 120.97

M $1,436.54 101.15% 1,420.25

*CAS 10070000 CASETAS DE MATERIALES

*CAS 10070001 CASETA MAT. 12'x16', P/200 F. CEMENTO:Area de caseta 17.86 m2Parales pino bruto amer. (14 de 2"x4"x12') 112.00 ptDurmientes pino bruto amer. (7 de 2"x4"x8') 37.33 ptCargaderas pino bruto amer. (5 de 2"x4"x14') 18.67 ptEnlates pino bruto amer. (5 de 2"x4"x18') 24.00 ptPuerta pino bruto amer. (4 de 1"x4"x8') 10.67 pt

1 Total pino bruto amer. (4 usos + 25% desp.) 63.33 pt 35.70 2,260.88 101.74% 2,222.252 Plywood 4'x8'x¾", 2 caras, 6 usos (13 unid.) 2.17 u 1,607.24 3,487.71 101.72% 3,428.603 Puerta en Plywood 4'x8'x¾", 2 caras, 6 usos (1 unid.) 0.17 u 1,607.24 273.23 101.72% 268.604 Zinc acanalado 3'x7' cal. 26, 4 usos (14 / 4) 3.50 u 637.20 2,230.20 101.72% 2,192.405 Clavos corrientes (5 lb. / 100 pie madera) 10.13 lb 30.43 308.36 101.71% 303.196 Clavos de zinc + 5% desp. (.133 lb. / plancha) 1.86 lb 52.68 97.98 101.73% 96.317 Bisagras 3 ½" x 3 ½" 2.00 pares 102.66 205.32 101.72% 201.848 Pestillo 1.00 u 47.20 47.20 101.72% 46.409 Portacandado 1.00 u 56.64 56.64 101.72% 55.6810 Candado 1.00 u 601.80 601.80 101.72% 591.6011 Salida luces 2.00 u 1,109.64 2,219.28 100.87% 2,200.0412 Salida interruptor sencillo 2.00 u 1,104.82 2,209.64 100.87% 2,190.5813 Salida tomacorrientes 110 v. 1.00 u 1,287.14 1,287.14 100.98% 1,274.6014 Replanteo y excavación 14 hoyos de .2x.2x.3 m. 14.00 u 43.30 606.20 100.00% 606.2015 Carpintero 2da., montar y desmontar 4.00 días 825.00 3,300.00 100.00% 3,300.0016 AY carpintero, montar y desmontar 4.00 días 557.00 2,228.00 100.00% 2,228.00

Unid. $21,419.58 101.01% 21,206.29M2 $1,199.30 101.01% 1,187.36

*CAS 10070002 CASETA MAT. 12'x32', P/500 F. CEMENTO:Area de la caseta 33.67 m2Parales pino bruto amer. (4 de 4"x4"x12') 64.00 ptParales pino bruto amer. (5 de 4"x4"x10') 66.67 ptParales pino bruto amer. (12 de 2"x4"x12') 96.00 ptParales pino bruto amer. (5 de 2"x4"x10') 33.33 ptDurmientes pino bruto amer. (9 de 2"x4"x14') 84.00 ptDurmientes pino bruto amer. (18 de 2"x4"x12') 144.00 ptCargaderas pino bruto amer. (9 de 2"x4"x16') 96.00 ptCorreas pino bruto amer. (7 de 1"x4"x18') 42.00 ptCorreas pino bruto amer. (7 de 1"x4"x16') 37.33 ptEnlates pino bruto amer. (3 de 1"x4"x14') 14.00 ptEnlates pino bruto amer. (5 de 1"x4"x12') 20.00 ptEnlates pino bruto amer. (2 de 1"x4"x10') 6.67 ptEnlates pino bruto amer. (2 de 1"x4"x8') 5.33 ptPuertas (2), pino bruto amer. (8 de 1"x4"x8') 21.33 ptVentanas (5 de 4'x4'), pino bruto amer. (15 de 1"x8"x8') 80.00 ptVentanas (5 de 4'x4'), pino bruto amer. (5 de 1"x4"x8') 13.33 ptVentanas (5 de 4'x4'), pino bruto amer. (5 de 1"x4"x6') 10.00 pt

1 Total pino bruto amer. (4 usos + 25% desp.) 260.62 pt 35.70 9,304.13 101.74% 9,145.162 Plywood 4'x8'x¾", 2 caras, 6 usos (17 unid.) 2.83 u 1,607.24 4,548.49 101.72% 4,471.40

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 37

Page 40: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

3 Puerta en Plywood 4'x8'x¾", 2 caras, 6 usos (2 unid.) 0.33 u 1,607.24 530.39 101.72% 521.404 Zinc acanalado 3'x7' cal. 26, 4 usos (27 / 4) 6.75 u 548.70 3,703.73 101.72% 3,640.955 Clavos corrientes (5 lb. / 100 pie madera) 41.70 lb 30.43 1,268.92 101.70% 1,247.656 Clavos de zinc + 5% desp. (.133 lb. / plancha) 3.59 lb 52.68 189.12 101.74% 185.897 Bisagras 3 ½" x 3 ½" 8.00 pares 102.66 821.28 101.72% 807.368 Pestillo 7.00 u 47.20 330.40 101.72% 324.809 Portacandado 2.00 u 56.64 113.28 101.72% 111.3610 Candado 2.00 u 601.80 1,203.60 101.72% 1,183.2011 Salida luces 3.00 u 1,109.64 3,328.92 100.87% 3,300.0612 Salida interruptor sencillo 3.00 u 1,104.82 3,314.46 100.87% 3,285.8713 Salida tomacorrientes 110 v. 1.00 u 1,287.14 1,287.14 100.98% 1,274.6014 Replanteo y excavación 14 hoyos de .2x.2x.3 m. 26.00 u 43.30 1,125.80 100.00% 1,125.8015 Carpintero 2da., montar y desmontar 8.00 días 825.00 6,600.00 100.00% 6,600.0016 AY carpintero, montar y desmontar 8.00 días 557.00 4,456.00 100.00% 4,456.00

Unid. $42,125.66 101.07% 41,681.50M2 $1,251.13 101.07% 1,237.94

*CON 10090000 CONTEN (TELFORD)Area de sección: 0.10 m2Volumen / metro: 0.10 m3Vol. analizado: 1.00 m3Longitud total: 10.00 m

1 Madera (110 p2 / 10 usos + 10% desp.). 12.10 pt 35.70 431.97 101.74% 424.592 Clavos (5 lb. / 100 p2) 5.50 lb 30.43 167.37 101.71% 164.563 Hormigón 1:3:5 contén + 2% desp. 1.02 m3 4,432.36 4,521.01 101.49% 4,454.514 Base horm. 1:3:5 + 85% de piedras, 0.15 m. espesor + 10% desp. 0.74 m3 1,413.64 1,046.09 101.61% 1,029.475 Mortero 1:2 para pulido. 0.10 m3 7,806.60 780.66 101.67% 767.846 Base contén (mano de obra solamente). 0.08 m3 359.43 28.75 100.00% 28.757 Construcción contén. 10.00 m 126.70 1,267.00 100.00% 1,267.00

M3 $8,242.85 101.30% 8,136.72M $824.29 101.31% 813.67

*DES 10110000 DESAGÜES PLUVIALES

*DES 10110001 DESAGÜES PLUVIALES 3": (Vivienda de un nivel)1 Tubo 3"x20' PVC SDR-26 + 10% desp. 0.500 tubo 984.01 492.01 101.72% 483.672 Codo 3" PVC drenaje 1.00 u 44.84 44.84 101.72% 44.083 Cemento PVC + 25% desp. (¼ galón). 0.040 u 289.10 11.56 101.67% 11.374 Ttapado ranura ambas caras en la pared. 0.20 día 433.00 86.60 100.00% 86.605 Mano de obra plomero 1.00 u 592.86 592.86 100.00% 592.86

Unid. $1,227.87 100.76% 1,218.58*DES 10110002 DESAGÜES PLUVIALES 4":: (Vivienda de un nivel)

1 Tubo 4"x20' PVC SDR-26 + 10% desp. 0.500 tubo 1,601.71 800.86 101.72% 787.282 Codo 4" PVC drenaje 1.00 u 44.84 44.84 101.72% 44.083 Cemento PVC + 25% desp. (¼ galón). 0.040 u 289.10 11.56 101.67% 11.374 Ttapado ranura ambas caras en la pared. 0.20 día 433.00 86.60 100.00% 86.605 Mano de obra plomero 1.00 m 678.15 678.15 100.00% 678.15

Unid. $1,622.01 100.90% 1,607.48

*EMP 10130000 EMPAÑETES

*EMP 10130001 CANTOS:1 Mortero 1:4 p/empañete + 10% desp., 1.67 cm. 0.00367 m3 5,595.53 20.54 101.58% 20.222 Reglas (2 de 1"x4"x3.28' / 10 usos) 0.1093 pt 169.55 18.54 101.76% 18.223 Mano de obra 1.00 m 43.30 43.30 100.00% 43.30

M $82.38 100.78% 81.74*EMP 10130002 CARETEO CON LLANA, SIN ANDAMIOS:

1 Mortero 1:4 p/empañete + 30% desp., 1.5 mm. esp. 0.00195 m3 5,595.53 10.91 101.58% 10.742 Mano de obra 1.00 m2 23.62 23.62 100.00% 23.62

M2 $34.53 100.49% 34.36*EMP 10130003 EMPAÑETE maestrado COLUMNAS:

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. esp. 0.02171 m3 5,595.53 121.48 101.57% 119.602 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 169.55 5.65 101.80% 5.553 Andamios (1.091 p2 / 6 usos) 0.1820 pt 35.70 6.50 101.72% 6.394 Conf. andamios 0.0230 día 1,032.00 23.74 100.00% 23.745 Mano de obra 1.00 m2 185.73 185.73 100.00% 185.73

M2 $343.10 100.61% 341.01*EMP 10130004 EMPAÑETE maestrado EXTERIOR:

1 Mortero 1:4 p/empañete + 30% desp., 2.0 cm. esp. 0.02600 m3 5,595.53 145.48 101.56% 143.242 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 169.55 5.65 101.80% 5.553 andamios 1.4402 pt 35.70 51.42 101.74% 50.544 Conf. andamios 0.0703 día 1,032.00 72.55 100.00% 72.555 Clavos corrientes 0.1590 lb 30.43 4.84 101.68% 4.766 Mano de obra 1.00 m2 126.64 126.64 100.00% 126.64

M2 $406.58 100.82% 403.28*EMP 10130005 EMPAÑETE maestrado INTERIOR:

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. esp. 0.02171 m3 5,595.53 121.48 101.57% 119.602 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 169.55 5.65 101.80% 5.553 Andamios (1.091 p2 / 6 usos) 0.1820 pt 35.70 6.50 101.72% 6.394 Conf. andamios 0.0230 día 1,032.00 23.74 100.00% 23.745 Mano de obra 1.00 m2 99.50 99.50 100.00% 99.50

M2 $256.87 100.82% 254.78*EMP 10130006 EMPAÑETE maestrado TECHOS Y VIGAS:

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. esp. 0.02171 m3 5,595.53 121.48 101.57% 119.602 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 169.55 5.65 101.80% 5.553 Andamios (.25 planchas plywood / 10 usos) 0.0250 u 1,607.24 40.18 101.72% 39.504 Conf. andamios 0.0703 día 1,032.00 72.55 100.00% 72.555 Clavos corrientes 0.1590 lb 30.43 4.84 101.68% 4.766 Mano de obra 1.00 m2 142.28 142.28 100.00% 142.28

M2 $386.98 100.71% 384.24*EMP 10130007 EMPAÑETE PULIDO SIN COLOR:

1 Mortero 1:4 p/empañete + 30% desp., 1.52 cm. esp. 0.01976 m3 5,595.53 110.57 101.57% 108.862 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 169.55 5.65 101.80% 5.553 Andamios (1.091 p2 / 6 usos) 0.1820 pt 35.70 6.50 101.72% 6.394 Conf. andamios 0.0230 día 1,032.00 23.74 100.00% 23.74

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 38

Page 41: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

5 Cemento 2da. capa + 30% desp. 0.0530 fda 320.43 16.98 101.68% 16.706 Mano de obra 1.00 m2 108.58 108.58 100.00% 108.58

M2 $272.02 100.82% 269.82*EMP 10130008 EMPAÑETE RASGADO:

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. esp. 0.02171 m3 5,595.53 121.48 101.57% 119.602 Regla (2 de 1"x4"x10' / 100 usos) 0.0667 pt 169.55 11.31 101.71% 11.123 andamios 1.4402 pt 35.70 51.42 101.74% 50.544 Conf. andamios 0.0703 día 1,032.00 72.55 100.00% 72.555 Clavos corrientes 0.1590 lb 30.43 4.84 101.68% 4.766 Mano de obra 1.00 m2 126.64 126.64 100.00% 126.64

M2 $388.24 100.79% 385.21*EMP 10130009 EMPAÑETE RUSTICO (ESCOBA, PAPEL O BROCHA):

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. esp. 0.02171 m3 5,595.53 121.48 101.57% 119.602 Andamios (1.091 p2 / 6 usos) 1.4402 pt 169.55 244.19 101.72% 240.053 Conf. andamios 0.0703 día 1,032.00 72.55 100.00% 72.554 Clavos corrientes 0.1590 lb 30.43 4.84 101.68% 4.765 Mano de obra 1.00 m2 75.30 75.30 100.00% 75.30

M2 $518.36 101.19% 512.26*EMP 10130010 ESTRIAS:

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. 0.00868 m3 5,595.53 48.57 101.57% 47.822 Reglas (1 de 1"x1"x3.28'). 0.2700 pt 169.55 45.78 101.73% 45.003 Mano de obra 1.00 m 81.19 81.19 100.00% 81.19

M $175.54 100.88% 174.01*EMP 10130011 FRAGÜACHE, SIN ANDAMIOS:

1 Mortero 1:4 p/empañete + 50% desp., 0.5 mm. esp. (Rend. 200 m2 / m3) 0.00750 m3 5,595.53 41.97 101.57% 41.322 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 169.55 5.65 101.80% 5.553 Mano de obra 1.00 m2 14.94 14.94 100.00% 14.94

M2 $62.56 101.21% 61.81*EMP 10130012 GOTEROS COLGANTES:

1 Mortero 1:4 p/empañete + 30% desp. 0.00954 m3 5,595.53 53.38 101.56% 52.562 Reglas (2 de 1"x4"x3.28' / 10 usos) 0.2180 pt 169.55 36.96 101.71% 36.343 Mano de obra 1.00 m 99.92 99.92 100.00% 99.92

M $190.26 100.76% 188.82*EMP 10130013 GOTEROS DE RANURA:

1 Mortero 1:4 p/empañete + 30% desp. 0.00477 m3 5,595.53 26.69 101.56% 26.282 Reglas (1 de 1"x4"x3.28' / 10 usos) 0.1090 pt 169.55 18.48 101.71% 18.173 Mano de obra 1.00 m 86.60 86.60 100.00% 86.60

M $131.77 100.55% 131.05*EMP 10130014 LECHADA CEMENTO BLANCO:

1 Cemento gris +20% desp. (50 m2 / funda) 0.02400 m3 649.00 15.58 101.76% 15.312 Agua 0.11229 gl 0.61 0.07 100.00% 0.07

M2 $15.65 101.76% 15.38*EMP 10130015 LECHADA CEMENTO GRIS:

1 Cemento blanco +20% desp. (50 m2 / funda) 0.02400 m3 320.43 7.69 101.72% 7.562 Agua 0.11229 gl 0.61 0.07 100.00% 0.07

M2 $7.76 101.70% 7.63*EMP 10130016 NATILLA, SIN ANDAMIOS:

1 Agua 0.06281 gl 0.61 44.23 100.00% 44.232 Cemento gris (15 m2 / funda) 0.06667 m3 320.43 21.36 101.71% 21.003 Mano de obra 1.00 m2 57.92 57.92 100.00% 57.92

M2 $79.28 100.46% 78.92*EMP 10130017 REPELLO maestrado TECHOS, 2 capas de 1.5 cm. c/u. (SIN ANDAMIOS):

1 Mortero 1:4 p/empañete + 30% desp., 2 capas (Rend. 33.33 m2/m3, 2 capas) 0.03900 m3 5,595.53 218.23 101.57% 214.862 Regla (1 de 1"x4"x10' / 10 usos) 0.0333 pt 169.55 5.65 101.80% 5.553 Mano de obra 1.00 m2 99.31 99.31 100.00% 99.31

M2 $323.19 101.09% 319.72*EMP 10130018 RESANE, SIN ANDAMIOS:

1 Mortero 1:4 p/empañete + 30% desp., 0.5 mm. Esp. (Rendim. 200 m2 / m3) 0.00650 m3 5,595.53 36.37 101.56% 35.812 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 169.55 5.65 101.80% 5.553 Mano de obra 1.00 m2 35.69 35.69 100.00% 35.69

M2 $77.71 100.86% 77.05

*ESC 10150000 ESCALONES

*ESC 10150001 ESCALON GRANITO 2 y 3 BLANCO1 Escalón .17 x .30 m. Bocel redondo + 10% desp. 1.10 m 1,000.64 1,100.70 101.72% 1,082.052 Mortero de fijación + 10% desp. 0.0561 m3 4,929.27 276.53 101.64% 272.073 Colocación Huella y Contra Huella (No aplica) 1.00 m 188.254 Pulido y brillado 1.00 m 279.24 279.24 103.48% 269.85

M $1,656.47 102.00% 1,623.97*ESC 10150002 ESCALON MARMOL AGLOMERADO (PERLATTO ROYAL) 1.10 M.

1 Escalón .17x1.10 m. + .34x1.10 m., Bocel redondo + 10% desp. 1.10 u 1,125.72 1,238.29 101.72% 1,217.302 Mortero de fijación + 10% desp. 0.0561 m3 4,929.27 276.53 101.64% 272.073 Colocación Huella y Contra Huella 1.10 m 188.25 207.08 100.00% 207.084 Pulido y brillado 1.10 m 279.24 307.16 103.48% 296.84

U $2,029.06 101.79% 1,993.29M 1,844.60 101.79% 1,812.08

*ESC 10150003 ESCALON SUPER CHAPA BLANCO1 Escalón .17 x .30 m. Bocel redondo + 10% desp. 1.10 m 1,876.20 2,063.82 101.72% 2,028.842 Mortero de fijación + 10% desp. 0.0561 m3 4,929.27 276.53 101.64% 272.073 Colocación Huella y Contra Huella (No aplica) 1.00 m 188.254 Pulido y brillado 1.00 m 279.24 279.24 103.48% 269.85

M $2,619.59 101.90% 2,570.76*ESC 10150004 ZOCALO P/ESCALONES, GRANITO 2 y3 BLANCO:

1 Escalón + transporte + 10% desp. + itbis 1.10 u 201.19 221.312 Mortero 1:3 + 5% desp. 0.0063 m3 4,929.27 31.05

U $31.05 101.64% 30.55

*HAANT 10170000 HORM. ARMADO ANTEPECHOS

*HAANT 10170001 ANTEPECHO .40x.15, 1:2:4, 3/8" grado 40 A .40 + 2 DE 3/8":1 Acero 3/8" x 20' grado 40 + 10% desp. 1.6338 qq 2,114.09 3,454.00 101.72% 3,395.482 M.O. acero 1.6338 qq 243.24 397.41 100.00% 397.413 Subida acero 1.6338 qq 24.32 39.73 100.00% 39.73

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 39

Page 42: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

4 Madera bruta amer. (4 usos) 183.06 pt 35.70 6,535.24 101.74% 6,423.585 Clavos corrientes (5 lb. / 100 pie madera) 36.61 lb 30.43 1,114.04 101.70% 1,095.376 Clavos de acero (¼ lb / metro) 8.34 lb 53.10 442.85 101.72% 435.357 Alambre calibre #14 (¼ lb. / metro) 8.34 lb 34.64 288.90 101.70% 284.068 Confección e instalación de madera 33.35 m 167.56 5,588.13 100.00% 5,588.139 Desencofrado 26.68 m2 24.17 644.86 100.00% 644.8610 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 4,604.00 5,064.40 101.54% 4,987.39

M3 $23,569.56 101.19% 23,291.36*HAANT 10170002 ANTEPECHO .40x.15, 180 kg/Cm², 3/8" grado 40 A .40, 2 DE 3/8":

1 Partidas comunes del análisis anterior (1-9) 1.00 m3 18,505.16 18,505.16 101.10% 18,303.972 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $25,748.00 101.27% 25,424.05*HAANT 10170003 ANTEPECHO .40x.15, 210 kg/Cm², 3/8" grado 40 A .40, 2 DE 3/8":

1 Partidas comunes del análisis anterior (1-9) 1.00 m3 18,505.16 18,505.16 101.10% 18,303.972 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $25,955.68 101.28% 25,628.21*HAANT 10170004 ANTEPECHO .40x.15, 240 kg/Cm², 3/8" grado 40 A .40, 2 DE 3/8":

1 Partidas comunes del análisis anterior (1-9) 1.00 m3 18,505.16 18,505.16 101.10% 18,303.972 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $26,487.86 101.29% 26,151.37

*HABAD 10190000 HORM. ARMADO BADENES (TIPO CUNETA) Notas:Llene solo las letras en AZUL y cuyas celdas no estén sombreadas en verde.

*HABAD 10190001 BADEN SOBRE HORM CICLOPESO, ACERO GRADO 40: No toque las celdas que tengan color verde o las que aparecen en las columnas I en adelante.Tipo acero y espac. 3/8 @ 0.20 a.d. Llene las dimensiones del baden: ancho "X", largo "Y" y por último el espesor "Z".Dimens. badén: ancho, Y, Z 1.75 x 10.00 x 0.25 El lado corto no tiene considerado el solape del acero, ya que no es necesario.Espesor horm. ciclópeo: 0.30 m Opciones para el hormigón: 1:3:5, 1:2:4, 140, 180, 210 y 240Pendiente: 20.00% Esta hoja y las anteriores no están protegidas.Desperdicio del acero: 5.00% Guarde este archivo en lugar seguro y trabaje en una copia.Area del badén: 17.50 m2 Este documento solo se actualiza con este mismo archivo.Vol. H.A. del Badén: 2.8438 m3 Para actualizar los precios, actualice solo la columna de p. unit. en los análisis.

1 Acero grado 40 + alambre dulce + 10% desp. (Ver análisis aceros) 0.8712 qq 2,114.09 1,841.80 101.72% 1,810.592 M.O. acero. 0.8712 qq 243.24 211.91 100.00% 211.913 Hormigón del badén + 2% desp. Tipo: 1:3:5 1.02 m3 4,432.36 4,521.01 101.49% 4,454.514 Base del badén, horm. ciclópeo, 1:3:5 (15% del vol. total) + 10% desp. 0.30 m3 4,432.36 1,329.71 101.49% 1,310.155 Base del badén, piedras grandes (85% del vol. total) + 10% desp. 1.73 m3 880.93 1,524.01 101.72% 1,498.186 Base del badén (mano de obra colocar las piedras solamente). 1.73 m3 359.43 621.81 100.00% 621.817 Mortero 1:2 para pulido, .005 m. de espesor. 0.0308 m3 7,806.60 240.44 101.67% 236.498 M. O. pulido del piso 6.15 m2 108.58 667.77 100.00% 667.77

M3 $10,958.46 101.36% 10,811.41*HABAD 10190002 BADEN SOBRE HORM CICLOPESO, ACERO GRADO 40:

Tipo acero y espac. 3/8 @ 0.20 a.d.Dimens. badén: ancho, Y, Z 1.75 x 10.00 x 0.25Espesor horm. ciclópeo: 0.30 mPendiente: 20.00%Desperdicio del acero: 5.00%Area del badén: 17.50 m2Vol. H.A. del Badén: 2.8438 m3

1 Acero grado 40 + alambre dulce + 10% desp. (Ver análisis aceros) 0.8712 qq 2,114.09 1,841.80 101.72% 1,810.592 M.O. acero. 0.8712 qq 243.24 211.91 100.00% 211.913 Hormigón del badén + 2% desp. Tipo: 1:2:4 1.02 m3 4,940.47 5,039.28 101.52% 4,963.794 Base del badén, horm. ciclópeo, 1:3:5 (15% del vol. total) + 10% desp. 0.30 m3 4,432.36 1,329.71 101.49% 1,310.155 Base del badén, piedras grandes (85% del vol. total) + 10% desp. 1.73 m3 880.93 1,524.01 101.72% 1,498.186 Base del badén (mano de obra colocar las piedras solamente). 1.73 m3 359.43 621.81 100.00% 621.817 Mortero 1:2 para pulido, .005 m. de espesor. 0.0308 m3 7,806.60 240.44 101.67% 236.498 M. O. pulido del piso 6.15 m2 108.58 667.77 100.00% 667.77

M3 $11,476.73 101.38% 11,320.69*HABAD 10190003 BADEN SOBRE HORM CICLOPESO, ACERO GRADO 40:

Tipo acero y espac. 3/8 @ 0.20 a.d.Dimens. badén: ancho, Y, Z 1.75 x 10.00 x 0.25Espesor horm. ciclópeo: 0.30 mPendiente: 20.00%Desperdicio del acero: 5.00%Area del badén: 17.50 m2Vol. H.A. del Badén: 2.8438 m3

1 Acero grado 40 + alambre dulce + 10% desp. (Ver análisis aceros) 0.8712 qq 2,114.09 1,841.80 101.72% 1,810.592 M.O. acero. 0.8712 qq 243.24 211.91 100.00% 211.913 Hormigón del badén + 2% desp. Tipo: 180 Kg/Cm2 1.02 m3 7,242.84 7,387.70 101.72% 7,262.484 Base del badén, horm. ciclópeo, 1:3:5 (15% del vol. total) + 10% desp. 0.30 m3 4,432.36 1,329.71 101.49% 1,310.155 Base del badén, piedras grandes (85% del vol. total) + 10% desp. 1.73 m3 880.93 1,524.01 101.72% 1,498.186 Base del badén (mano de obra colocar las piedras solamente). 1.73 m3 359.43 621.81 100.00% 621.817 Mortero 1:2 para pulido, .005 m. de espesor. 0.0308 m3 7,806.60 240.44 101.67% 236.498 M. O. pulido del piso 6.15 m2 108.58 667.77 100.00% 667.77

M3 $13,825.15 101.51% 13,619.38*HABAD 10190004 BADEN SOBRE HORM CICLOPESO, ACERO GRADO 40:

Tipo acero y espac. 3/8 @ 0.20 a.d.Dimens. badén: ancho, Y, Z 1.75 x 10.00 x 0.25Espesor horm. ciclópeo: 0.30 mPendiente: 20.00%Desperdicio del acero: 5.00%Area del badén: 17.50 m2Vol. H.A. del Badén: 2.8438 m3

1 Acero grado 40 + alambre dulce + 10% desp. (Ver análisis aceros) 0.8712 qq 2,114.09 1,841.80 101.72% 1,810.592 M.O. acero. 0.8712 qq 243.24 211.91 100.00% 211.913 Hormigón del badén + 2% desp. Tipo: 210 Kg/Cm2 1.02 m3 7,450.52 7,599.53 101.72% 7,470.724 Base del badén, horm. ciclópeo, 1:3:5 (15% del vol. total) + 10% desp. 0.30 m3 4,432.36 1,329.71 101.49% 1,310.155 Base del badén, piedras grandes (85% del vol. total) + 10% desp. 1.73 m3 880.93 1,524.01 101.72% 1,498.186 Base del badén (mano de obra colocar las piedras solamente). 1.73 m3 359.43 621.81 100.00% 621.817 Mortero 1:2 para pulido, .005 m. de espesor. 0.0308 m3 7,806.60 240.44 101.67% 236.49

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 40

Page 43: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

8 M. O. pulido del piso 6.15 m2 108.58 667.77 100.00% 667.77M3 $14,036.98 101.51% 13,827.62

*HACOL 10210000 HORM. ARMADO COLUMNAS

*HACOL 10210001 COL. 20x20, 1:2:4, 40,4 DE 3/8", ¼" A 20, LIG.:1 Acero ¼" + 10% desp. 0.804 qq 1,519.73 1,221.86 101.72% 1,201.172 Acero 3/8" x 20' grado 40 + 10% desp. 1.462 qq 2,114.09 3,090.80 101.72% 3,038.433 M.O. acero 25.00 m 81.08 2,027.00 100.00% 2,027.004 Madera bruta amer. (4 usos) 254.77 pt 35.70 9,095.29 101.74% 8,939.885 Clavos corrientes (5 lb. / 100 pie madera) 50.95 lb 30.43 1,550.41 101.70% 1,524.426 Clavos de acero (¼ lb / metro) 6.25 lb 53.10 331.88 101.73% 326.257 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 34.64 216.50 101.70% 212.888 Confección madera 25.00 m 120.83 3,020.75 100.00% 3,020.759 Instalación madera 25.00 m 138.56 3,464.00 100.00% 3,464.0010 Desencofrado 20.00 m2 20.94 418.80 100.00% 418.8011 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $29,311.94 101.17% 28,972.04*HACOL 10210002 COL. 20x20, 1:2:4, 40, 4 DE 3/8", ¼" A 20 A MANO:

1 Partidas comunes de la analizada anteriormente (1-10) 1.000 m3 24,437.29 24,437.29 101.09% 24,173.582 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $29,871.81 101.17% 29,526.69*HACOL 10210003 COL. 20x20, 1:2:4, 40, 4 DE ½", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.778 qq 1,519.73 2,702.08 101.72% 2,656.312 Acero ½" x 20' grado 40 + 10% desp. 2.598 qq 2,121.47 5,511.58 101.72% 5,418.183 Partidas comunes de la analizada completa anterior (3-11) 1.000 m3 24,999.28 24,999.28 101.08% 24,732.44

M3 $33,212.94 101.24% 32,806.93*HACOL 10210004 COL. 20x20, 1:2:4, 40, 4 DE ½", 3/8" A 20 A MANO:

1 Partidas comunes de la analizada completa anterior (1-10) 1.000 m3 33,212.94 33,212.94 101.24% 32,806.932 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $38,647.46 101.28% 38,160.04*HACOL 10210005 COL. 20x30, 1:2:4, 40, 4 DE ½", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.506 qq 2,114.09 3,183.82 101.72% 3,129.872 Acero ½" x 20' grado 40 + 10% desp. 1.732 qq 2,121.47 3,674.39 101.72% 3,612.123 M.O. acero 13.13 m 81.08 1,064.58 100.00% 1,064.584 Madera bruta amer. (4 usos) 130.36 pt 35.70 4,653.85 101.74% 4,574.335 Clavos corrientes (5 lb. / 100 pie madera) 26.07 lb 30.43 793.31 101.71% 780.016 Clavos de acero (¼ lb / metro) 3.28 lb 53.10 174.17 101.72% 171.227 Alambre calibre #14 (¼ lb. / metro) 3.28 lb 34.64 113.62 101.70% 111.728 Confección madera 13.13 m 120.83 1,586.50 100.00% 1,586.509 Instalación madera 13.13 m 138.56 1,819.29 100.00% 1,819.2910 Desencofrado 13.13 m2 20.94 274.94 100.00% 274.9411 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $22,213.12 101.32% 21,923.04*HACOL 10210006 COL. 20x30, 1:2:4, 40, 4 DE ½", 3/8" A 20 A MANO:

1 Partidas comunes de la analizada completa anterior (1-10) 1.000 m3 17,338.47 17,338.47 101.25% 17,124.582 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $22,772.99 101.31% 22,477.69*HACOL 10210007 COL. 30x30, 1:2:4, 40, 8 DE ½", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.144 qq 2,114.09 2,418.52 101.72% 2,377.542 Acero ½" x 20' grado 40 + 10% desp. 2.278 qq 2,121.47 4,832.71 101.72% 4,750.813 M.O. acero 3.422 qq 243.24 832.37 100.00% 832.374 Madera bruta amer. (4 usos) 134.11 pt 35.70 4,787.73 101.74% 4,705.925 Clavos corrientes (5 lb. / 100 pie madera) 26.82 lb 30.43 816.13 101.70% 802.456 Clavos de acero (¼ lb / metro) 2.78 lb 53.10 147.62 101.72% 145.127 Alambre calibre #14 (¼ lb. / metro) 2.78 lb 34.64 96.30 101.70% 94.698 Confección madera 11.11 m 120.83 1,342.42 100.00% 1,342.429 Instalación madera 11.11 m 138.56 1,539.40 100.00% 1,539.4010 Desencofrado 13.33 m2 20.94 279.13 100.00% 279.1311 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $21,966.98 101.38% 21,668.31*HACOL 10210008 COL. 30x30, 1:2:4, 40, 8 DE ½", 3/8" A 20 A MANO:

1 Partidas comunes de la analizada completa anterior (1-10) 1.000 m3 17,092.33 17,092.33 101.32% 16,869.852 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $22,526.85 101.37% 22,222.96*HACOL 10210009 COL. 30x40, 1:2:4, 40, 4 DE ¾", 3/8" A 30, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.744 qq 2,114.09 1,572.88 101.72% 1,546.232 Acero ¾" grado 40 + 10% desp. 1.979 qq 2,076.70 4,109.79 101.72% 4,040.153 M.O. acero 2.723 qq 243.24 662.34 100.00% 662.344 Madera bruta amer. (4 usos) 76.99 pt 35.70 2,748.54 101.74% 2,701.585 Clavos corrientes (5 lb. / 100 pie madera) 15.4 lb 30.43 468.62 101.70% 460.776 Clavos de acero (¼ lb / metro) 2.08 lb 53.10 110.45 101.72% 108.587 Alambre calibre #14 (¼ lb. / metro) 2.08 lb 34.64 72.05 101.71% 70.848 Confección madera 8.33 m 138.56 1,154.20 100.00% 1,154.209 Instalación madera 8.33 m 178.83 1,489.65 100.00% 1,489.6510 Desencofrado 11.66 m2 20.94 244.16 100.00% 244.1611 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $17,507.33 101.33% 17,276.96*HACOL 10210010 COL. 30x40, 1:2:4, 40, 4 DE ¾", 3/8" A 30 A MANO:

1 Partidas comunes de la analizada completa anterior (1-10) 1.000 m3 12,632.68 12,632.68 101.24% 12,478.502 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $18,067.20 101.32% 17,831.61*HACOL 10210011 COL. 40x40, 1:2:4, 40, 4 DE ½" + 4 DE ¾", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 2,114.09 1,818.12 101.72% 1,787.312 Acero ½" x 20' grado 40 + 10% desp. 0.640 qq 2,121.47 1,357.74 101.72% 1,334.733 Acero ¾" grado 40 + 10% desp. 1.481 qq 2,076.70 3,075.59 101.72% 3,023.484 M.O. acero 2.981 qq 243.24 725.10 100.00% 725.105 Madera bruta amer. (4 usos) 87.25 pt 35.70 3,114.83 101.74% 3,061.606 Clavos corrientes (5 lb. / 100 pie madera) 17.45 lb 30.43 531.00 101.70% 522.107 Clavos de acero (¼ lb / metro) 1.56 lb 53.10 82.84 101.73% 81.438 Alambre calibre #14 (¼ lb. / metro) 1.56 lb 34.64 54.04 101.71% 53.139 Confección madera 6.25 m 138.56 866.00 100.00% 866.0010 Instalación madera 6.25 m 178.83 1,117.69 100.00% 1,117.6911 Desencofrado 10.00 m2 20.94 209.40 100.00% 209.40

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 41

Page 44: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

12 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46M3 $17,827.00 101.40% 17,580.43

*HACOL 10210012 COL. 40x40, 1:2:4, 40, 4 DE ½" + 4 DE ¾", 3/8" A 20 A MANO:1 Partidas comunes de la analizada completa anterior (1-11) 1.000 m3 11,134.23 11,134.23 101.27% 10,994.662 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $16,568.75 101.35% 16,347.77*HACOL 10210013 COL. 50x50, 1:2:4, 40, 4 DE ¾" + 4 DE 1", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.687 qq 2,114.09 1,452.38 101.72% 1,427.772 Acero ¾" x 20' grado 40 + 10% desp. 0.948 qq 2,076.70 1,968.71 101.72% 1,935.353 Acero 1" x 20' grado 40 + 10% desp. 1.733 qq 2,058.81 3,567.92 101.72% 3,507.474 M.O. acero 3.368 qq 243.24 819.23 100.00% 819.235 Madera bruta amer. (4 usos) 63.41 pt 35.70 2,263.74 101.74% 2,225.066 Clavos corrientes (5 lb. / 100 pie madera) 12.68 lb 30.43 385.85 101.70% 379.397 Clavos de acero (¼ lb / metro) 1.00 lb 53.10 53.10 101.72% 52.208 Alambre calibre #14 (¼ lb. / metro) 1.00 lb 34.64 34.64 101.70% 34.069 Confección madera 4.00 m 159.51 638.04 100.00% 638.0410 Instalación madera 4.00 m 199.78 799.12 100.00% 799.1211 Desencofrado 8.00 m2 20.94 167.52 100.00% 167.5212 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $17,584.77 101.42% 17,338.32*HACOL 10210014 COL. 50x50, 1:2:4, 40, 4 DE ¾" + 4 DE 1", 3/8" A 20 A MANO:

1 Partidas comunes de la analizada completa anterior (1-11) 1.000 m3 10,697.87 10,697.87 101.33% 10,557.442 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $15,572.52 101.41% 15,355.90*HACOL 10210015 COL. 60x60, 1:2:4, 40, 12 DE 1", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.718 qq 2,114.09 3,632.01 101.72% 3,570.472 Acero 1" x 20' grado 40 + 10% desp. 3.612 qq 2,058.81 7,436.42 101.72% 7,310.443 M.O. acero 5.330 qq 243.24 1,296.47 100.00% 1,296.474 Madera bruta amer. (4 usos) 49.29 pt 35.70 1,759.65 101.74% 1,729.595 Clavos corrientes (5 lb. / 100 pie madera) 9.86 lb 30.43 300.04 101.71% 295.016 Clavos de acero (¼ lb / metro) 0.70 lb 53.10 37.17 101.72% 36.547 Alambre calibre #14 (¼ lb. / metro) 0.70 lb 34.64 24.25 101.72% 23.848 Confección madera 2.78 m 199.78 555.39 100.00% 555.399 Instalación madera 2.78 m 317.41 882.40 100.00% 882.4010 Desencofrado 6.67 m2 20.94 139.67 100.00% 139.6711 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $21,497.99 101.44% 21,192.93*HACOL 10210016 COL. 60x60, 1:2:4, 40, 12 DE 1", 3/8" A 20 A MANO:

1 Partidas comunes de la analizada completa anterior (1-11) 1.000 m3 16,063.47 16,063.47 101.41% 15,839.822 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $20,938.12 101.45% 20,638.28*HACOL 10210017 COL. 20x20, 180 kg/Cm², 40, 4 DE ½", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.778 qq 2,114.09 3,758.85 101.72% 3,695.162 Acero ½" x 20' grado 40 + 10% desp. 2.598 qq 2,121.47 5,511.58 101.72% 5,418.183 M.O. acero 25.00 m 81.08 2,027.00 100.00% 2,027.004 Madera bruta amer. (4 usos) 177.79 pt 35.70 6,347.10 101.74% 6,238.655 Clavos corrientes (5 lb. / 100 pie madera) 35.56 lb 30.43 1,082.09 101.70% 1,063.966 Clavos de acero (¼ lb / metro) 6.25 lb 53.10 331.88 101.73% 326.257 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 34.64 216.50 101.70% 212.888 Confección madera 25.00 m 120.83 3,020.75 100.00% 3,020.759 Instalación madera 25.00 m 138.56 3,464.00 100.00% 3,464.0010 Desencofrado 20.00 m2 20.94 418.80 100.00% 418.8011 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $33,421.39 101.26% 33,005.71*HACOL 10210018 COL. 20x20, 180 kg/Cm², 40, 4 DE ½" x 25', 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.778 qq 2,114.09 3,758.85 101.72% 3,695.162 Acero ½" x 25' grado 40 + 10% desp. 2.598 qq 2,078.50 5,399.94 101.72% 5,308.473 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 24,150.96 24,150.96 101.08% 23,892.37

M3 $33,309.75 101.26% 32,896.00*HACOL 10210019 COL. 20x20, 180 kg/Cm², 60, 4 DE ½" x 20', 3/8" x 20' A 20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.778 qq 2,351.19 4,180.42 101.72% 4,109.582 Acero ½" x 20' grado 60 + 10% desp. 2.598 qq 2,413.96 6,271.47 101.72% 6,165.213 Partidas comunes de la analizada completa anterior (3-11) 1.00 m3 24,150.96 24,150.96 101.08% 23,892.37

M3 $34,602.85 101.28% 34,167.16*HACOL 10210020 COL. 20x20, 180 kg/Cm², 60, 4 DE ½" x 25', 3/8" x 20' A 20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.778 qq 2,351.19 4,180.42 101.72% 4,109.582 Acero ½" x 25' grado 60 + 10% desp. 2.598 qq 2,409.63 6,260.22 101.72% 6,154.173 Partidas comunes de la analizada completa anterior (3-11) 1.00 m3 24,150.96 24,150.96 101.08% 23,892.37

M3 $34,591.60 101.27% 34,156.12*HACOL 10210021 COL. 20x30, 180 kg/Cm², 60, 4 DE ½", 3/8" A 20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.506 qq 2,351.19 3,540.89 101.72% 3,480.892 Acero ½" x 20' grado 60 + 10% desp. 1.732 qq 2,413.96 4,180.98 101.72% 4,110.143 M.O. acero 13.13 m 81.08 1,064.58 100.00% 1,064.584 Madera bruta amer. (4 usos) 130.36 pt 35.70 4,653.85 101.74% 4,574.335 Clavos corrientes (5 lb. / 100 pie madera) 26.07 lb 30.43 793.31 101.71% 780.016 Clavos de acero (¼ lb / metro) 3.28 lb 53.10 174.17 101.72% 171.227 Alambre calibre #14 (¼ lb. / metro) 3.28 lb 34.64 113.62 101.70% 111.728 Confección madera 13.13 m 120.83 1,586.50 100.00% 1,586.509 Instalación madera 13.13 m 138.56 1,819.29 100.00% 1,819.2910 Desencofrado 13.13 m2 20.94 274.94 100.00% 274.9411 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $25,444.97 101.40% 25,093.70*HACOL 10210022 COL. 20x30, 180 kg/Cm², 60, 4 DE ½" x 25', 3/8" x 20' A 20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.506 qq 2,351.19 3,540.89 101.72% 3,480.892 Acero ½" x 25' grado 60 + 10% desp. 1.732 qq 2,409.63 4,173.48 101.72% 4,102.783 Partidas comunes de la analizada completa anterior (3-11) 1.00 m3 17,723.10 17,723.10 101.26% 17,502.67

M3 $25,437.47 101.40% 25,086.34*HACOL 10210023 COL. 30x30, 180 kg/Cm², 40, 8 DE ½", 3/8" A 30:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.144 qq 2,114.09 2,418.52 101.72% 2,377.542 Acero ½" x 20' grado 40 + 10% desp. 2.278 qq 2,121.47 4,832.71 101.72% 4,750.813 M.O. acero 3.422 qq 243.24 832.37 100.00% 832.374 Madera bruta amer. (4 usos) 134.11 pt 35.70 4,787.73 101.74% 4,705.925 Clavos corrientes (5 lb. / 100 pie madera) 26.82 lb 30.43 816.13 101.70% 802.456 Clavos de acero (¼ lb / metro) 2.78 lb 53.10 147.62 101.72% 145.12

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 42

Page 45: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

7 Alambre calibre #14 (¼ lb. / metro) 2.78 lb 34.64 96.30 101.70% 94.698 Confección madera 11.11 m 120.83 1,342.42 100.00% 1,342.429 Instalación madera 11.11 m 138.56 1,539.40 100.00% 1,539.4010 Desencofrado 13.33 m2 20.94 279.13 100.00% 279.1311 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $24,335.17 101.44% 23,989.93*HACOL 10210024 COL. 30x30, 180 kg/Cm², 40, 8 DE ½", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 7,251.23 7,251.23 101.72% 7,128.352 M.O. acero 3.422 qq 386.61 1,322.98 100.00% 1,322.983 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,251.57 16,251.57 101.39% 16,029.21

M3 $24,825.78 101.41% 24,480.54*HACOL 10210025 COL. 30x30, 180 kg/Cm², 40, 8 DE ½" x 25', 3/8" A:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.144 qq 2,114.09 2,418.52 101.72% 2,377.542 Acero ½" x 25' grado 40 + 10% desp. 2.278 qq 2,078.50 4,734.82 101.72% 4,654.613 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 17,083.94 17,083.94 101.32% 16,861.58

M3 $24,237.28 101.44% 23,893.73*HACOL 10210026 COL. 30x30, 180 kg/Cm², 40, 8 DE ½"x25', 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 7,153.34 7,153.34 101.72% 7,032.152 M.O. acero 3.422 qq 386.61 1,322.98 100.00% 1,322.983 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,251.57 16,251.57 101.39% 16,029.21

M3 $24,727.89 101.41% 24,384.34*HACOL 10210027 COL. 30x30, 180 kg/Cm², 60, 8 DE ½", 3/8" A 30:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.144 qq 2,351.19 2,689.76 101.72% 2,644.182 Acero ½" x 20' grado 60 + 10% desp. 2.278 qq 2,413.96 5,499.00 101.72% 5,405.833 M.O. acero 3.422 qq 366.08 1,252.73 100.00% 1,252.734 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,251.57 16,251.57 101.39% 16,029.21

M3 $25,693.06 101.43% 25,331.95*HACOL 10210028 COL. 30x30, 180 kg/Cm², 60, 8 DE ½", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 8,188.76 8,188.76 101.72% 8,050.012 M.O. acero 3.422 qq 386.61 1,322.98 100.00% 1,322.983 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,251.57 16,251.57 101.39% 16,029.21

M3 $25,763.31 101.42% 25,402.20*HACOL 10210029 COL. 30x30, 180 kg/Cm², 60, 8 DE ½"x25', 3/8" x 20' A 30:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.144 qq 2,351.19 2,689.76 101.72% 2,644.182 Acero ½" x 25' grado 60 + 10% desp. 2.278 qq 2,409.63 5,489.14 101.72% 5,396.153 M.O. acero 3.422 qq 366.08 1,252.73 100.00% 1,252.733 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,251.57 16,251.57 101.39% 16,029.21

M3 $25,683.20 101.43% 25,322.27*HACOL 10210030 COL. 30x30, 180 kg/Cm², 60, 8 DE ½"x25', 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 8,178.90 8,178.90 101.72% 8,040.332 M.O. acero 3.422 qq 386.61 1,322.98 100.00% 1,322.983 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,251.57 16,251.57 101.39% 16,029.21

M3 $25,753.45 101.42% 25,392.52*HACOL 10210031 COL. 30x40, 180 kg/Cm², 40, 4 DE ¾", 3/8" A 30:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.744 qq 2,114.09 1,572.88 101.72% 1,546.232 Acero ¾" grado 40 + 10% desp. 1.979 qq 2,076.70 4,109.79 101.72% 4,040.153 M.O. acero 2.723 qq 243.24 662.34 100.00% 662.344 Madera bruta amer. (4 usos) 76.990 pt 35.70 2,748.54 101.74% 2,701.585 Clavos corrientes (5 lb. / 100 pie madera) 15.4 lb 30.43 468.62 101.70% 460.776 Clavos de acero (¼ lb / metro) 2.08 lb 53.10 110.45 101.72% 108.587 Alambre calibre #14 (¼ lb. / metro) 2.08 lb 34.64 72.05 101.71% 70.848 Confección madera 8.33 m 138.56 1,154.20 100.00% 1,154.209 Instalación madera 8.33 m 178.83 1,489.65 100.00% 1,489.6510 Desencofrado 11.66 m2 20.94 244.16 100.00% 244.1611 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $19,875.52 101.41% 19,598.58*HACOL 10210032 COL. 30x40, 180 kg/Cm², 40, 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 5,682.67 5,682.67 101.72% 5,586.382 M.O. acero 2.723 qq 386.61 1,052.74 100.00% 1,052.743 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,530.51 13,530.51 101.35% 13,349.86

M3 $20,265.92 101.39% 19,988.98*HACOL 10210033 COL. 30x40, 180 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.744 qq 2,351.19 1,749.29 101.72% 1,719.642 Acero ¾" x 20' grado 60 + 10% desp. 1.979 qq 2,407.71 4,764.86 101.72% 4,684.133 M.O. acero 2.723 qq 366.08 996.84 100.00% 996.844 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,530.51 13,530.51 101.35% 13,349.86

M3 $21,041.50 101.40% 20,750.47*HACOL 10210034 COL. 30x40, 180 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 6,514.15 6,514.15 101.72% 6,403.772 M.O. acero 2.723 qq 386.61 1,052.74 100.00% 1,052.743 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,530.51 13,530.51 101.35% 13,349.86

M3 $21,097.40 101.40% 20,806.37*HACOL 10210035 COL. 40x40, 180 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 2,114.09 1,818.12 101.72% 1,787.312 Acero ½" x 20' grado 40 + 10% desp. 0.640 qq 2,121.47 1,357.74 101.72% 1,334.733 Acero ¾" + 10% desp. 1.481 qq 2,076.70 3,075.59 101.72% 3,023.484 M.O. acero 2.981 qq 243.24 725.10 100.00% 725.105 Madera bruta amer. (4 usos) 87.25 pt 35.70 3,114.83 101.74% 3,061.606 Clavos corrientes (5 lb. / 100 pie madera) 17.45 lb 30.43 531.00 101.70% 522.107 Clavos de acero (¼ lb / metro) 1.56 lb 53.10 82.84 101.73% 81.438 Alambre calibre #14 (¼ lb. / metro) 1.56 lb 34.64 54.04 101.71% 53.139 Confección madera 6.25 m 138.56 866.00 100.00% 866.0010 Instalación madera 6.25 m 178.83 1,117.69 100.00% 1,117.6911 Desencofrado 10.00 m2 20.94 209.40 100.00% 209.4012 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $20,195.19 101.47% 19,902.05*HACOL 10210036 COL. 40x40, 180 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,251.45 6,251.45 101.72% 6,145.522 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.483 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,218.64 13,218.64 101.44% 13,031.43

M3 $20,622.57 101.44% 20,329.43*HACOL 10210037 COL. 40x40, 180 kg/Cm², 40, 4 DE ½"x25' + 4 DE ¾"x25', 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 2,114.09 1,818.12 101.72% 1,787.312 Acero ½" x 25' grado 40 + 10% desp. 0.640 qq 2,078.50 1,330.24 101.72% 1,307.71

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 43

Page 46: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

3 Acero ¾" + 10% desp. 1.481 qq 2,076.70 3,075.59 101.72% 3,023.484 Partidas comunes de la analizada completa anterior (4-12) 1.00 u 13,943.74 13,943.74 101.36% 13,756.53

M3 $20,167.69 101.47% 19,875.03*HACOL 10210038 COL. 40x40, 180 kg/Cm², 40, 4 DE ½"x25' + 4 DE ¾"x25', 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,223.95 6,223.95 101.72% 6,118.502 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.483 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,218.64 13,218.64 101.44% 13,031.43

M3 $20,595.07 101.44% 20,302.41*HACOL 10210039 COL. 40x40, 180 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,351.19 2,022.02 101.72% 1,987.762 Acero ½" x 20' grado 60 + 10% desp. 0.640 qq 2,413.96 1,544.93 101.72% 1,518.763 Acero ¾" + 10% desp. 1.481 qq 2,407.71 3,565.82 101.72% 3,505.414 M.O. acero 2.981 qq 366.08 1,091.28 100.00% 1,091.285 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,218.64 13,218.64 101.44% 13,031.43

M3 $21,442.69 101.46% 21,134.64*HACOL 10210040 COL. 40x40, 180 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 7,132.77 7,132.77 101.72% 7,011.932 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.483 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,218.64 13,218.64 101.44% 13,031.43

M3 $21,503.89 101.45% 21,195.84*HACOL 10210041 COL. 40x40, 180 kg/Cm², 60, 4 DE ½"x25' + 4 DE ¾"x25', 3/8" A 30:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,351.19 2,022.02 101.72% 1,987.762 Acero ½" x 25' grado 60 + 10% desp. 0.640 qq 2,409.63 1,542.16 101.72% 1,516.043 Acero ¾" grado 60 + 10% desp. 1.481 qq 2,407.71 3,565.82 101.72% 3,505.414 M.O. acero 2.981 qq 366.08 1,091.28 100.00% 1,091.285 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,218.64 13,218.64 101.44% 13,031.43

M3 $21,439.92 101.46% 21,131.92*HACOL 10210042 COL. 40x40, 180 kg/Cm², 60, 4 DE ½" x 25' + 4 DE 4/4", 3/8" x 20' A 30: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 7,130.00 7,130.00 101.72% 7,009.212 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.483 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,218.64 13,218.64 101.44% 13,031.43

M3 $21,501.12 101.45% 21,193.12*HACOL 10210043 COL. 50x50, 180 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.687 qq 2,114.09 1,452.38 101.72% 1,427.772 Acero ¾" + 10% desp. 0.948 qq 2,076.70 1,968.71 101.72% 1,935.353 Acero 1" + 10% desp. 1.733 qq 2,058.81 3,567.92 101.72% 3,507.474 M.O. acero 3.368 qq 243.24 819.23 100.00% 819.235 Madera bruta amer. (4 usos) 63.41 pt 35.70 2,263.74 101.74% 2,225.066 Clavos corrientes (5 lb. / 100 pie madera) 12.68 lb 30.43 385.85 101.70% 379.397 Clavos de acero (¼ lb / metro) 1.00 lb 53.10 53.10 101.72% 52.208 Alambre calibre #14 (¼ lb. / metro) 1.00 lb 34.64 34.64 101.70% 34.069 Confección madera 4.00 m 159.51 638.04 100.00% 638.0410 Instalación madera 4.00 m 199.78 799.12 100.00% 799.1211 Desencofrado 8.00 m2 20.94 167.52 100.00% 167.5212 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $19,393.09 101.51% 19,105.29*HACOL 10210044 COL. 50x50, 180 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,536.63 5,536.63 101.72% 5,442.822 M.O. acero 3.368 qq 386.61 1,302.10 100.00% 1,302.103 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,584.85 11,584.85 101.48% 11,415.47

M3 $18,423.58 101.45% 18,160.39*HACOL 10210045 COL. 50x50, 180 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.687 qq 2,351.19 1,615.27 101.72% 1,587.902 Acero ¾" x 20' grado 60 + 10% desp. 0.948 qq 2,407.71 2,282.51 101.72% 2,243.843 Acero 1" + 10% desp. 1.733 qq 2,382.94 4,129.64 101.72% 4,059.674 M.O. acero 3.368 qq 366.08 1,232.96 100.00% 1,232.965 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,584.85 11,584.85 101.48% 11,415.47

M3 $20,845.23 101.49% 20,539.84*HACOL 10210046 COL. 50x50, 180 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 8,027.42 8,027.42 101.72% 7,891.412 M.O. acero 3.368 qq 386.61 1,302.10 100.00% 1,302.103 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,584.85 11,584.85 101.48% 11,415.47

M3 $20,914.37 101.48% 20,608.98*HACOL 10210047 COL. 60x60, 180 kg/Cm², 40, 12 DE 1", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.718 qq 2,114.09 3,632.01 101.72% 3,570.472 Acero 1" x 20' grado 40 + 10% desp. 3.612 qq 2,058.81 7,436.42 101.72% 7,310.443 M.O. acero 5.330 qq 243.24 1,296.47 100.00% 1,296.474 Madera bruta amer. (4 usos) 49.29 pt 35.70 1,759.65 101.74% 1,729.595 Clavos corrientes (5 lb. / 100 pie madera) 9.86 lb 30.43 300.04 101.71% 295.016 Clavos de acero (¼ lb / metro) 1.00 lb 53.10 53.10 101.72% 52.207 Alambre calibre #14 (¼ lb. / metro) 1.00 lb 34.64 34.64 101.70% 34.068 Confección madera 4.00 m 159.51 638.04 100.00% 638.049 Instalación madera 4.00 m 199.78 799.12 100.00% 799.1210 Desencofrado 8.00 m2 20.94 167.52 100.00% 167.5211 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $23,359.85 101.51% 23,013.00*HACOL 10210048 COL. 60x60, 180 kg/Cm², 40, 12 DE 1", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 11,068.43 11,068.43 101.72% 10,880.912 M.O. acero 5.330 qq 386.61 2,060.63 100.00% 2,060.633 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 10,994.95 10,994.95 101.47% 10,835.62

M3 $24,124.01 101.46% 23,777.16*HACOL 10210049 COL. 60x60, 180 kg/Cm², 60, 12 DE 1", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.718 qq 2,351.19 4,039.34 101.72% 3,970.902 Acero 1" x 20' grado 60 + 10% desp. 3.612 qq 2,382.94 8,607.18 101.72% 8,461.363 M.O. acero 5.330 qq 366.08 1,951.21 100.00% 1,951.214 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 10,994.95 10,994.95 101.47% 10,835.62

M3 $25,592.68 101.48% 25,219.09*HACOL 10210050 COL. 60x60, 180 kg/Cm², 60, 12 DE 1", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 12,646.52 12,646.52 101.72% 12,432.262 M.O. acero 5.330 qq 386.61 2,060.63 100.00% 2,060.633 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 10,994.95 10,994.95 101.47% 10,835.62

M3 $25,702.10 101.47% 25,328.51*HACOL 10210051 COL. 30x30, 210 kg/Cm², 40, 4 DE ¾", 3/8" A 30:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.144 qq 2,114.09 2,418.52 101.72% 2,377.54PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 44

Page 47: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

2 Acero ¾" x 20' grado 40 + 10% desp. 2.278 qq 2,121.47 4,832.71 101.72% 4,750.813 M.O. acero 3.422 qq 243.24 832.37 100.00% 832.374 Madera bruta amer. (4 usos) 134.11 pt 35.70 4,787.73 101.74% 4,705.925 Clavos corrientes (5 lb. / 100 pie madera) 26.82 lb 30.43 816.13 101.70% 802.456 Clavos de acero (¼ lb / metro) 2.78 lb 53.10 147.62 101.72% 145.127 Alambre calibre #14 (¼ lb. / metro) 2.78 lb 34.64 96.30 101.70% 94.698 Confección madera 11.11 m 120.83 1,342.42 100.00% 1,342.429 Instalación madera 11.11 m 138.56 1,539.40 100.00% 1,539.4010 Desencofrado 13.33 m2 20.94 279.13 100.00% 279.1311 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $24,542.85 101.44% 24,194.09*HACOL 10210052 COL. 30x30, 210 kg/Cm², 40, 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 7,251.23 7,251.23 101.72% 7,128.352 M.O. acero 3.422 qq 386.61 1,322.98 100.00% 1,322.983 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,459.25 16,459.25 101.39% 16,233.37

M3 $25,033.46 101.41% 24,684.70*HACOL 10210053 COL. 30x30, 210 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.144 qq 2,351.19 2,689.76 101.72% 2,644.182 Acero ¾" x 20' grado 60 + 10% desp. 2.278 qq 2,382.94 5,428.34 101.72% 5,336.373 M.O. acero 3.422 qq 366.08 1,252.73 100.00% 1,252.734 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,459.25 16,459.25 101.39% 16,233.37

M3 $25,830.08 101.43% 25,466.65*HACOL 10210054 COL. 30x30, 210 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 8,118.10 8,118.10 101.72% 7,980.552 M.O. acero 3.422 qq 386.61 1,322.98 100.00% 1,322.983 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,459.25 16,459.25 101.39% 16,233.37

M3 $25,900.33 101.42% 25,536.90*HACOL 10210055 COL. 30x40, 210 kg/Cm², 40, 4 DE ¾", 3/8" A 30:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.744 qq 2,114.09 1,572.88 101.72% 1,546.232 Acero ¾" x 20' grado 40 + 10% desp. 1.979 qq 2,076.70 4,109.79 101.72% 4,040.153 M.O. acero 2.723 qq 243.24 662.34 100.00% 662.344 Madera bruta amer. (4 usos) 76.99 pt 35.70 2,748.54 101.74% 2,701.585 Clavos corrientes (5 lb. / 100 pie madera) 15.4 lb 30.43 468.62 101.70% 460.776 Clavos de acero (¼ lb / metro) 2.08 lb 53.10 110.45 101.72% 108.587 Alambre calibre #14 (¼ lb. / metro) 2.08 lb 34.64 72.05 101.71% 70.848 Confección madera 8.33 m 138.56 1,154.20 100.00% 1,154.209 Instalación madera 8.33 m 178.83 1,489.65 100.00% 1,489.6510 Desencofrado 11.66 m2 20.94 244.16 100.00% 244.1611 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $20,083.20 101.42% 19,802.74*HACOL 10210056 COL. 30x40, 210 kg/Cm², 40, 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 5,682.67 5,682.67 101.72% 5,586.382 M.O. acero 2.723 qq 386.61 1,052.74 100.00% 1,052.743 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,738.19 13,738.19 101.36% 13,554.02

M3 $20,473.60 101.39% 20,193.14*HACOL 10210057 COL. 30x40, 210 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.744 qq 2,351.19 1,749.29 101.72% 1,719.642 Acero ¾" x 20' grado 60 + 10% desp. 1.979 qq 2,382.94 4,715.84 101.72% 4,635.953 M.O. acero 2.723 qq 366.08 996.84 100.00% 996.844 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,738.19 13,738.19 101.36% 13,554.02

M3 $21,200.16 101.40% 20,906.45*HACOL 10210058 COL. 30x40, 210 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 6,465.13 6,465.13 101.72% 6,355.592 M.O. acero 2.723 qq 386.61 1,052.74 100.00% 1,052.743 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,738.19 13,738.19 101.36% 13,554.02

M3 $21,256.06 101.40% 20,962.35*HACOL 10210059 COL. 40x40, 210 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 2,114.09 1,818.12 101.72% 1,787.312 Acero ½" x 20' grado 40 + 10% desp. 0.640 qq 2,121.47 1,357.74 101.72% 1,334.733 Acero ¾" x 20' grado 40 + 10% desp. 1.481 qq 2,076.70 3,075.59 101.72% 3,023.484 M.O. acero 2.981 qq 243.24 725.10 100.00% 725.105 Madera bruta amer. (4 usos) 87.25 pt 35.70 3,114.83 101.74% 3,061.606 Clavos corrientes (5 lb. / 100 pie madera) 17.45 lb 30.43 531.00 101.70% 522.107 Clavos de acero (¼ lb / metro) 1.56 lb 53.10 82.84 101.73% 81.438 Alambre calibre #14 (¼ lb. / metro) 1.56 lb 34.64 54.04 101.71% 53.139 Confección madera 6.25 m 138.56 866.00 100.00% 866.0010 Instalación madera 6.25 m 178.83 1,117.69 100.00% 1,117.6911 Desencofrado 10.00 m2 20.94 209.40 100.00% 209.4012 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $20,402.87 101.48% 20,106.21*HACOL 10210060 COL. 40x40, 210 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,251.45 6,251.45 101.72% 6,145.522 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.483 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,426.32 13,426.32 101.44% 13,235.59

M3 $20,830.25 101.44% 20,533.59*HACOL 10210061 COL. 40x40, 210 kg/Cm², 40, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 2,114.09 1,818.12 101.72% 1,787.312 Acero ½" x 25' grado 40 + 10% desp. 0.640 qq 2,078.50 1,330.24 101.72% 1,307.713 Acero ¾" + 10% desp. 1.481 qq 2,076.70 3,075.59 101.72% 3,023.484 Partidas comunes de la analizada completa anterior (4-12) 1.00 u 14,151.42 14,151.42 101.37% 13,960.69

M3 $20,375.37 101.48% 20,079.19*HACOL 10210062 COL. 40x40, 210 kg/Cm², 40, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,223.95 6,223.95 101.72% 6,118.502 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.483 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,426.32 13,426.32 101.44% 13,235.59

M3 $20,802.75 101.44% 20,506.57*HACOL 10210063 COL. 40x40, 210 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,351.19 2,022.02 101.72% 1,987.762 Acero ½" x 20' grado 60 + 10% desp. 0.640 qq 2,413.96 1,544.93 101.72% 1,518.763 Acero ¾" + 10% desp. 1.481 qq 2,407.71 3,565.82 101.72% 3,505.414 M.O. acero 2.981 qq 366.08 1,091.28 100.00% 1,091.285 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,426.32 13,426.32 101.44% 13,235.59

M3 $21,650.37 101.46% 21,338.80

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 45

Page 48: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

*HACOL 10210064 COL. 40x40, 210 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30, x 20': PORTICO1 Partidas comunes del análisis anterior (1-3) 1.00 u 7,132.77 7,132.77 101.72% 7,011.932 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.483 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,426.32 13,426.32 101.44% 13,235.59

M3 $21,711.57 101.46% 21,400.00*HACOL 10210065 COL. 40x40, 210 kg/Cm², 60, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 30 x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,351.19 2,022.02 101.72% 1,987.762 Acero ½" x 25' grado 60 + 10% desp. 0.640 qq 2,409.63 1,542.16 101.72% 1,516.043 Acero ¾" grado 60 + 10% desp. 1.481 qq 2,382.94 3,529.13 101.72% 3,469.354 M.O. acero 2.981 qq 366.08 1,091.28 100.00% 1,091.285 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,426.32 13,426.32 101.44% 13,235.59

M3 $21,610.91 101.46% 21,300.02*HACOL 10210066 COL. 40x40, 210 kg/Cm², 60, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 30 x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 7,093.31 7,093.31 101.72% 6,973.152 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.483 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,426.32 13,426.32 101.44% 13,235.59

M3 $21,672.11 101.46% 21,361.22*HACOL 10210067 COL. 50x50, 210 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.687 qq 2,114.09 1,452.38 101.72% 1,427.772 Acero ¾" x 20' grado 40 + 10% desp. 0.948 qq 2,076.70 1,968.71 101.72% 1,935.353 Acero 1" x 20' grado 40 + 10% desp. 1.733 qq 2,058.81 3,567.92 101.72% 3,507.474 M.O. acero 3.368 qq 243.24 819.23 100.00% 819.235 Madera bruta amer. (4 usos) 63.41 pt 35.70 2,263.74 101.74% 2,225.066 Clavos corrientes (5 lb. / 100 pie madera) 12.68 lb 30.43 385.85 101.70% 379.397 Clavos de acero (¼ lb / metro) 1.00 lb 53.10 53.10 101.72% 52.208 Alambre calibre #14 (¼ lb. / metro) 1.00 lb 34.64 34.64 101.70% 34.069 Confección madera 4.00 m 159.51 638.04 100.00% 638.0410 Instalación madera 4.00 m 199.78 799.12 100.00% 799.1211 Desencofrado 8.00 m2 20.94 167.52 100.00% 167.5212 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $19,600.77 101.51% 19,309.45*HACOL 10210068 COL. 50x50, 210 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,536.63 5,536.63 101.72% 5,442.822 M.O. acero 3.368 qq 386.61 1,302.10 100.00% 1,302.103 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,792.53 11,792.53 101.49% 11,619.63

M3 $18,631.26 101.45% 18,364.55*HACOL 10210069 COL. 50x50, 210 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.687 qq 2,351.19 1,615.27 101.72% 1,587.902 Acero ¾" x 20' grado 60 + 10% desp. 0.948 qq 2,407.71 2,282.51 101.72% 2,243.843 Acero 1" + 10% desp. 1.733 qq 2,382.94 4,129.64 101.72% 4,059.674 M.O. acero 3.368 qq 366.08 1,232.96 100.00% 1,232.965 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,792.53 11,792.53 101.49% 11,619.63

M3 $21,052.91 101.49% 20,744.00*HACOL 10210070 COL. 50x50, 210 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 8,027.42 8,027.42 101.72% 7,891.412 M.O. acero 3.368 qq 386.61 1,302.10 100.00% 1,302.103 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,792.53 11,792.53 101.49% 11,619.63

M3 $21,122.05 101.48% 20,813.14*HACOL 10210071 COL. 60x60, 210 kg/Cm², 40, 12 DE 1", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.718 qq 2,114.09 3,632.01 101.72% 3,570.472 Acero 1" x 20' grado 40 + 10% desp. 3.612 qq 2,058.81 7,436.42 101.72% 7,310.443 M.O. acero 5.330 qq 243.24 1,296.47 100.00% 1,296.474 Madera bruta amer. (4 usos) 49.29 pt 35.70 1,759.65 101.74% 1,729.595 Clavos corrientes (5 lb. / 100 pie madera) 9.86 lb 30.43 300.04 101.71% 295.016 Clavos de acero (¼ lb / metro) 0.70 lb 53.10 37.17 101.72% 36.547 Alambre calibre #14 (¼ lb. / metro) 0.70 lb 34.64 24.25 101.72% 23.848 Confección madera 2.78 m 199.78 555.39 100.00% 555.399 Instalación madera 2.78 m 317.41 882.40 100.00% 882.4010 Desencofrado 6.67 m2 20.94 139.67 100.00% 139.6711 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $23,513.99 101.51% 23,164.06*HACOL 10210072 COL. 60x60, 210 kg/Cm², 40, 12 DE 1", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 11,068.43 11,068.43 101.72% 10,880.912 M.O. acero 5.330 qq 386.61 2,060.63 100.00% 2,060.633 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,149.09 11,149.09 101.48% 10,986.68

M3 $24,278.15 101.46% 23,928.22*HACOL 10210073 COL. 60x60, 210 kg/Cm², 60, 12 DE 1", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.718 qq 2,351.19 4,039.34 101.72% 3,970.902 Acero 1" x 20' grado 60 + 10% desp. 3.612 qq 2,382.94 8,607.18 101.72% 8,461.363 M.O. acero 5.330 qq 366.08 1,951.21 100.00% 1,951.214 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,149.09 11,149.09 101.48% 10,986.68

M3 $25,746.82 101.48% 25,370.15*HACOL 10210074 COL. 60x60, 210 kg/Cm², 60, 12 DE 1", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 12,646.52 12,646.52 101.72% 12,432.262 M.O. acero 5.330 qq 386.61 2,060.63 100.00% 2,060.633 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,149.09 11,149.09 101.48% 10,986.68

M3 $25,856.24 101.48% 25,479.57*HACOL 10210075 COL. 30x30, 240 kg/Cm², 40, 4 DE ¾", 3/8" A 30:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.144 qq 2,114.09 2,418.52 101.72% 2,377.542 Acero ¾" x 20' grado 40 + 10% desp. 2.278 qq 2,121.47 4,832.71 101.72% 4,750.813 M.O. acero 3.422 qq 243.24 832.37 100.00% 832.374 Madera bruta amer. (4 usos) 134.11 pt 35.70 4,787.73 101.74% 4,705.925 Clavos corrientes (5 lb. / 100 pie madera) 26.82 lb 30.43 816.13 101.70% 802.456 Clavos de acero (¼ lb / metro) 2.78 lb 53.10 147.62 101.72% 145.127 Alambre calibre #14 (¼ lb. / metro) 2.78 lb 34.64 96.30 101.70% 94.698 Confección madera 11.11 m 120.83 1,342.42 100.00% 1,342.429 Instalación madera 11.11 m 138.56 1,539.40 100.00% 1,539.4010 Desencofrado 13.33 m2 20.94 279.13 100.00% 279.1311 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $25,075.03 101.45% 24,717.25*HACOL 10210076 COL. 30x30, 240 kg/Cm², 40, 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 7,251.23 7,251.23 101.72% 7,128.352 M.O. acero 3.422 qq 386.61 1,322.98 100.00% 1,322.98

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 46

Page 49: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

3 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,991.43 16,991.43 101.40% 16,756.53M3 $25,565.64 101.42% 25,207.86

*HACOL 10210077 COL. 30x30, 240 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20':1 Acero 3/8" x 20' grado 60 + 10% desp. 1.144 qq 2,351.19 2,689.76 101.72% 2,644.182 Acero ¾" x 20' grado 60 + 10% desp. 2.278 qq 2,382.94 5,428.34 101.72% 5,336.373 M.O. acero 3.422 qq 366.08 1,252.73 100.00% 1,252.734 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,991.43 16,991.43 101.40% 16,756.53

M3 $26,362.26 101.43% 25,989.81*HACOL 10210078 COL. 30x30, 240 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 8,118.10 8,118.10 101.72% 7,980.552 M.O. acero 3.422 qq 386.61 1,322.98 100.00% 1,322.983 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 16,991.43 16,991.43 101.40% 16,756.53

M3 $26,432.51 101.43% 26,060.06*HACOL 10210079 COL. 30x40, 240 kg/Cm², 40, 4 DE ¾", 3/8" A 30:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.744 qq 2,114.09 1,572.88 101.72% 1,546.232 Acero ¾" x 20' grado 40 + 10% desp. 1.979 qq 2,076.70 4,109.79 101.72% 4,040.153 M.O. acero 2.723 qq 243.24 662.34 100.00% 662.344 Madera bruta amer. (4 usos) 76.99 pt 35.70 2,748.54 101.74% 2,701.585 Clavos corrientes (5 lb. / 100 pie madera) 15.4 lb 30.43 468.62 101.70% 460.776 Clavos de acero (¼ lb / metro) 2.08 lb 53.10 110.45 101.72% 108.587 Alambre calibre #14 (¼ lb. / metro) 2.08 lb 34.64 72.05 101.71% 70.848 Confección madera 8.33 m 138.56 1,154.20 100.00% 1,154.209 Instalación madera 8.33 m 178.83 1,489.65 100.00% 1,489.6510 Desencofrado 11.66 m2 20.94 244.16 100.00% 244.1611 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $20,615.38 101.42% 20,325.90*HACOL 10210080 COL. 30x40, 240 kg/Cm², 40, 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 5,682.67 5,682.67 101.72% 5,586.382 M.O. acero 2.723 qq 386.61 1,052.74 100.00% 1,052.743 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 14,270.37 14,270.37 101.37% 14,077.18

M3 $21,005.78 101.40% 20,716.30*HACOL 10210081 COL. 30x40, 240 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.744 qq 2,351.19 1,749.29 101.72% 1,719.642 Acero ¾" x 20' grado 60 + 10% desp. 1.979 qq 2,382.94 4,715.84 101.72% 4,635.953 M.O. acero 2.723 qq 366.08 996.84 100.00% 996.844 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 14,270.37 14,270.37 101.37% 14,077.18

M3 $21,732.34 101.41% 21,429.61*HACOL 10210082 COL. 30x40, 240 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 6,465.13 6,465.13 101.72% 6,355.592 M.O. acero 2.723 qq 386.61 1,052.74 100.00% 1,052.743 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 14,270.37 14,270.37 101.37% 14,077.18

M3 $21,788.24 101.41% 21,485.51*HACOL 10210083 COL. 40x40, 240 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 2,114.09 1,818.12 101.72% 1,787.312 Acero ½" x 20' grado 40 + 10% desp. 0.640 qq 2,121.47 1,357.74 101.72% 1,334.733 Acero ¾" x 20' grado 40 + 10% desp. 1.481 qq 2,076.70 3,075.59 101.72% 3,023.484 M.O. acero 2.981 qq 243.24 725.10 100.00% 725.105 Madera bruta amer. (4 usos) 87.25 pt 35.70 3,114.83 101.74% 3,061.606 Clavos corrientes (5 lb. / 100 pie madera) 17.45 lb 30.43 531.00 101.70% 522.107 Clavos de acero (¼ lb / metro) 1.56 lb 53.10 82.84 101.73% 81.438 Alambre calibre #14 (¼ lb. / metro) 1.56 lb 34.64 54.04 101.71% 53.139 Confección madera 6.25 m 138.56 866.00 100.00% 866.0010 Instalación madera 6.25 m 178.83 1,117.69 100.00% 1,117.6911 Desencofrado 10.00 m2 20.94 209.40 100.00% 209.4012 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $20,935.05 101.48% 20,629.37*HACOL 10210084 COL. 40x40, 240 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,251.45 6,251.45 101.72% 6,145.522 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.483 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,958.50 13,958.50 101.45% 13,758.75

M3 $21,362.43 101.45% 21,056.75*HACOL 10210085 COL. 40x40, 240 kg/Cm², 40, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 2,114.09 1,818.12 101.72% 1,787.312 Acero ½" x 25' grado 40 + 10% desp. 0.640 qq 2,078.50 1,330.24 101.72% 1,307.713 Acero ¾" + 10% desp. 1.481 qq 2,076.70 3,075.59 101.72% 3,023.484 Partidas comunes de la analizada completa anterior (4-12) 1.00 u 14,683.60 14,683.60 101.38% 14,483.85

M3 $20,907.55 101.48% 20,602.35*HACOL 10210086 COL. 40x40, 240 kg/Cm², 40, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,223.95 6,223.95 101.72% 6,118.502 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.483 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,958.50 13,958.50 101.45% 13,758.75

M3 $21,334.93 101.45% 21,029.73*HACOL 10210087 COL. 40x40, 240 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,351.19 2,022.02 101.72% 1,987.762 Acero ½" x 20' grado 60 + 10% desp. 0.640 qq 2,413.96 1,544.93 101.72% 1,518.763 Acero ¾" + 10% desp. 1.481 qq 2,407.71 3,565.82 101.72% 3,505.414 M.O. acero 2.981 qq 366.08 1,091.28 100.00% 1,091.285 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,958.50 13,958.50 101.45% 13,758.75

M3 $22,182.55 101.47% 21,861.96*HACOL 10210088 COL. 40x40, 240 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 7,132.77 7,132.77 101.72% 7,011.932 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.483 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,958.50 13,958.50 101.45% 13,758.75

M3 $22,243.75 101.46% 21,923.16*HACOL 10210089 COL. 40x40, 240 kg/Cm², 60, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 30 x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,351.19 2,022.02 101.72% 1,987.762 Acero ½" x 25' grado 60 + 10% desp. 0.640 qq 2,409.63 1,542.16 101.72% 1,516.043 Acero ¾" grado 60 + 10% desp. 1.481 qq 2,382.94 3,529.13 101.72% 3,469.353 M.O. acero 2.981 qq 366.08 1,091.28 100.00% 1,091.283 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,958.50 13,958.50 101.45% 13,758.75

M3 $22,143.09 101.47% 21,823.18*HACOL 10210090 COL. 40x40, 240 kg/Cm², 60, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 30 x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 7,093.31 7,093.31 101.72% 6,973.152 M.O. acero 2.981 qq 386.61 1,152.48 100.00% 1,152.48

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 47

Page 50: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

3 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,958.50 13,958.50 101.45% 13,758.75M3 $22,204.29 101.46% 21,884.38

*HACOL 10210091 COL. 50x50, 240 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20:1 Acero 3/8" x 20' grado 40 + 10% desp. 0.687 qq 2,114.09 1,452.38 101.72% 1,427.772 Acero ¾" x 20' grado 40 + 10% desp. 0.948 qq 2,076.70 1,968.71 101.72% 1,935.353 Acero 1" x 20' grado 40 + 10% desp. 1.733 qq 2,058.81 3,567.92 101.72% 3,507.474 M.O. acero 3.368 qq 243.24 819.23 100.00% 819.235 Madera bruta amer. (4 usos) 63.41 pt 35.70 2,263.74 101.74% 2,225.066 Clavos corrientes (5 lb. / 100 pie madera) 12.68 lb 30.43 385.85 101.70% 379.397 Clavos de acero (¼ lb / metro) 1.00 lb 53.10 53.10 101.72% 52.208 Alambre calibre #14 (¼ lb. / metro) 1.00 lb 34.64 34.64 101.70% 34.069 Confección madera 4.00 m 159.51 638.04 100.00% 638.0410 Instalación madera 4.00 m 199.78 799.12 100.00% 799.1211 Desencofrado 8.00 m2 20.94 167.52 100.00% 167.5212 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $20,132.95 101.51% 19,832.61*HACOL 10210092 COL. 50x50, 240 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,536.63 5,536.63 101.72% 5,442.822 M.O. acero 3.368 qq 386.61 1,302.10 100.00% 1,302.103 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,324.71 12,324.71 101.50% 12,142.79

M3 $19,163.44 101.46% 18,887.71*HACOL 10210093 COL. 50x50, 240 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.687 qq 2,351.19 1,615.27 101.72% 1,587.902 Acero ¾" x 20' grado 60 + 10% desp. 0.948 qq 2,407.71 2,282.51 101.72% 2,243.843 Acero 1" + 10% desp. 1.733 qq 2,382.94 4,129.64 101.72% 4,059.674 M.O. acero 3.368 qq 366.08 1,232.96 100.00% 1,232.965 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,324.71 12,324.71 101.50% 12,142.79

M3 $21,585.09 101.49% 21,267.16*HACOL 10210094 COL. 50x50, 240 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 8,027.42 8,027.42 101.72% 7,891.412 M.O. acero 3.368 qq 386.61 1,302.10 100.00% 1,302.103 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,324.71 12,324.71 101.50% 12,142.79

M3 $21,654.23 101.49% 21,336.30*HACOL 10210095 COL. 60x60, 240 kg/Cm², 40, 12 DE 1", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.718 qq 2,114.09 3,632.01 101.72% 3,570.472 Acero 1" x 20' grado 40 + 10% desp. 3.612 qq 2,058.81 7,436.42 101.72% 7,310.443 M.O. acero 5.330 qq 243.24 1,296.47 100.00% 1,296.474 Madera bruta amer. (4 usos) 49.29 pt 35.70 1,759.65 101.74% 1,729.595 Clavos corrientes (5 lb. / 100 pie madera) 9.86 lb 30.43 300.04 101.71% 295.016 Clavos de acero (¼ lb / metro) 0.70 lb 53.10 37.17 101.72% 36.547 Alambre calibre #14 (¼ lb. / metro) 0.70 lb 34.64 24.25 101.72% 23.848 Confección madera 2.78 m 199.78 555.39 100.00% 555.399 Instalación madera 2.78 m 317.41 882.40 100.00% 882.4010 Desencofrado 6.67 m2 20.94 139.67 100.00% 139.6711 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $24,046.17 101.52% 23,687.22*HACOL 10210096 COL. 60x60, 240 kg/Cm², 40, 12 DE 1", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 11,068.43 11,068.43 101.72% 10,880.912 M.O. acero 5.330 qq 386.61 2,060.63 100.00% 2,060.633 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,681.27 11,681.27 101.49% 11,509.84

M3 $24,810.33 101.47% 24,451.38*HACOL 10210097 COL. 60x60, 240 kg/Cm², 60, 12 DE 1", 3/8" A 20, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.718 qq 2,351.19 4,039.34 101.72% 3,970.902 Acero 1" x 20' grado 60 + 10% desp. 3.612 qq 2,382.94 8,607.18 101.72% 8,461.363 M.O. acero 5.330 qq 366.08 1,951.21 100.00% 1,951.214 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,681.27 11,681.27 101.49% 11,509.84

M3 $26,279.00 101.49% 25,893.31*HACOL 10210098 COL. 60x60, 240 kg/Cm², 60, 12 DE 1", 3/8" A 20, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 12,646.52 12,646.52 101.72% 12,432.262 M.O. acero 5.330 qq 386.61 2,060.63 100.00% 2,060.633 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,681.27 11,681.27 101.49% 11,509.84

M3 $26,388.42 101.48% 26,002.73

*HACOLC 10230000 HORM. ARMADO COL. CIRCULARES

*HACOLC 10230001 COL. CIRCULAR, 1:2:4, 6 DE 3/8" grado 60, 3/8" A 10 LIGADORA:1 Acero 3/8" x 20' grado 60 + 10% desp.. Diámetro: 0.300 1.7027 qq 2,351.19 4,003.37 101.72% 3,935.542 Acero ½" x 20' grado 60 + 10% desp.. Area: 0.0707 5.6896 qq 2,413.96 13,734.47 101.72% 13,501.763 M.O. acero. Perímetro: 0.9425 14.14 m 81.08 1,146.82 100.00% 1,146.824 Madera bruta amer. (4 usos). 73.71 pt 35.70 2,631.45 101.74% 2,586.485 Clavos corrientes (5 lb. / 100 pie madera). 11.79 lb 30.43 358.77 101.70% 352.766 Clavos de acero (¼ lb / metro). 3.54 lb 53.10 187.97 101.72% 184.797 Alambre calibre #14 (¼ lb. / metro). 3.54 lb 34.64 122.63 101.71% 120.578 Confección de madera. 14.14 m 338.34 4,785.57 100.00% 4,785.579 Instalación de madera. 14.14 m 178.83 2,529.42 100.00% 2,529.4210 Desencofrado. 13.33 m2 20.94 279.13 100.00% 279.1311 Horm. 1:2:4 ligadora + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $34,654.25 101.27% 34,221.30*HACOLC 10230002 COL. CIRCULAR, 1:2:4, 6 DE 3/8" grado 60, 3/8" A 10 A MANO:

1 Acero 3/8" x 20' grado 60 + 10% desp.. Diámetro: 0.300 1.7027 qq 2,351.19 4,003.37 101.72% 3,935.542 Acero ½" x 20' grado 60 + 10% desp.. Area: 0.0707 5.6896 qq 2,413.96 13,734.47 101.72% 13,501.763 M.O. acero. Perímetro: 0.9425 14.14 m 81.08 1,146.82 100.00% 1,146.824 Madera bruta amer. (4 usos). 73.71 pt 35.70 2,631.45 101.74% 2,586.485 Clavos corrientes (5 lb. / 100 pie madera). 11.79 lb 30.43 358.77 101.70% 352.766 Clavos de acero (¼ lb / metro). 3.54 lb 53.10 187.97 101.72% 184.797 Alambre calibre #14 (¼ lb. / metro). 3.54 lb 34.64 122.63 101.71% 120.578 Confección de madera. 14.14 m 338.34 4,785.57 100.00% 4,785.579 Instalación de madera. 14.14 m 178.83 2,529.42 100.00% 2,529.4210 Desencofrado. 13.33 m2 20.94 279.13 100.00% 279.1311 Horm. 1:2:4 ligadora + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $35,214.12 101.26% 34,775.95

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 48

Page 51: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

*HACOLA 10250000 HORM. ARMADO COL. DE AMARRE

*HACOLA 10250001 COL. AMARRE 15x20, 1:2:4, 40, 4 DE 3/8", ¼" A 20, LIG.:1 Acero ¼" + 10% desp. 0.779 qq 1,519.73 1,183.87 101.72% 1,163.822 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 2,114.09 4,014.66 101.72% 3,946.633 M.O. acero 33.33 m 81.08 2,702.40 100.00% 2,702.404 Madera bruta amer. (4 usos) 97.97 pt 35.70 3,497.53 101.74% 3,437.775 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 30.43 596.12 101.70% 586.136 Clavos de acero (¼ lb / metro) 8.33 lb 53.10 442.32 101.72% 434.837 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 34.64 288.55 101.70% 283.728 Confección e instalación de madera 33.33 m 99.89 3,329.33 100.00% 3,329.339 Desencofrado 13.33 m2 20.94 279.13 100.00% 279.1310 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $21,208.56 101.18% 20,962.22*HACOLA 10250002 COL. AMARRE 15x20, 1:2:4, 40, 4 DE 3/8", ¼" A 20 A MANO:

1 Acero ¼" + 10% desp. 0.779 qq 1,519.73 1,183.87 101.72% 1,163.822 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 2,114.09 4,014.66 101.72% 3,946.633 M.O. acero 33.33 m 81.08 2,702.40 100.00% 2,702.404 Madera bruta amer. (4 usos) 97.97 pt 35.70 3,497.53 101.74% 3,437.775 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 30.43 596.12 101.70% 586.136 Clavos de acero (¼ lb / metro) 8.33 lb 53.10 442.32 101.72% 434.837 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 34.64 288.55 101.70% 283.728 Confección e instalación de madera 33.33 m 99.89 3,329.33 100.00% 3,329.339 Desencofrado 13.33 m2 20.94 279.13 100.00% 279.1310 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $21,768.43 101.17% 21,516.87*HACOLA 10250003 COL. AMARRE 15x20, 1:2:4, 40, 4 DE 3/8", 3/8" A 20, LIG.:

1 Acero 3/8" + 10% desp. en entribos 1.723 qq 2,114.09 3,642.58 101.72% 3,580.862 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 2,114.09 4,014.66 101.72% 3,946.633 M.O. acero 33.33 m 81.08 2,702.40 100.00% 2,702.404 Madera bruta amer. (4 usos) 97.97 pt 35.70 3,497.53 101.74% 3,437.775 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 30.43 596.12 101.70% 586.136 Clavos de acero (¼ lb / metro) 8.33 lb 53.10 442.32 101.72% 434.837 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 34.64 288.55 101.70% 283.728 Confección e instalación de madera 33.33 m 99.89 3,329.33 100.00% 3,329.339 Desencofrado 13.33 m2 20.94 279.13 100.00% 279.1310 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $23,667.27 101.23% 23,379.26*HACOLA 10250004 COL. AMARRE 15x20, 1:2:4, 40, 4 DE 3/8", 3/8" A 20 A MANO:

1 Acero 3/8" + 10% desp. en entribos 1.723 qq 2,114.09 3,642.58 101.72% 3,580.862 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 2,114.09 4,014.66 101.72% 3,946.633 M.O. acero 33.33 m 81.08 2,702.40 100.00% 2,702.404 Madera bruta amer. (4 usos) 97.97 pt 35.70 3,497.53 101.74% 3,437.775 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 30.43 596.12 101.70% 586.136 Clavos de acero (¼ lb / metro) 8.33 lb 53.10 442.32 101.72% 434.837 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 34.64 288.55 101.70% 283.728 Confección e instalación de madera 33.33 m 99.89 3,329.33 100.00% 3,329.339 Desencofrado 13.33 m2 20.94 279.13 100.00% 279.1310 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $24,227.14 101.23% 23,933.91*HACOLA 10250005 COL. AMARRE 20x20, 1:2:4, 40, 4 DE 3/8", ¼" A 20, LIG.:

1 Acero ¼" + 10% desp. 0.668 qq 1,519.73 1,015.18 101.72% 997.992 Acero 3/8" x 20' grado 40 + 10% desp. 1.424 qq 2,114.09 3,010.46 101.72% 2,959.463 M.O. acero 25.00 m 81.08 2,027.00 100.00% 2,027.004 Madera bruta amer. (4 usos) 94.36 pt 35.70 3,368.65 101.74% 3,311.095 Clavos corrientes (5 lb. / 100 pie madera) 18.87 lb 30.43 574.21 101.70% 564.596 Clavos de acero (¼ lb / metro) 6.25 lb 53.10 331.88 101.73% 326.257 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 34.64 216.50 101.70% 212.888 Confección e instalación de madera 25.00 m 99.89 2,497.25 100.00% 2,497.259 Desencofrado 10.00 m2 20.94 209.40 100.00% 209.4010 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $18,125.18 101.23% 17,904.37*HACOLA 10250006 COL. AMARRE 20x20, 1:2:4, 40, 4 DE 3/8", ¼" A 20 A MANO:

1 Acero ¼" + 10% desp. 0.668 qq 1,519.73 1,015.18 101.72% 997.992 Acero 3/8" x 20' grado 40 + 10% desp. 1.424 qq 2,114.09 3,010.46 101.72% 2,959.463 M.O. acero 25.00 m 81.08 2,027.00 100.00% 2,027.004 Madera bruta amer. (4 usos) 94.36 pt 35.70 3,368.65 101.74% 3,311.095 Clavos corrientes (5 lb. / 100 pie madera) 18.87 lb 30.43 574.21 101.70% 564.596 Clavos de acero (¼ lb / metro) 6.25 lb 53.10 331.88 101.73% 326.257 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 34.64 216.50 101.70% 212.888 Confección e instalación de madera 25.00 m 99.89 2,497.25 100.00% 2,497.259 Desencofrado 10.00 m2 20.94 209.40 100.00% 209.4010 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $18,685.05 101.22% 18,459.02

*HADIN 10270000 HORM. ARMADO DINTELES

*HADIN 10270001 DINTEL 10x20, 1:2:4, 40, 2 DE ½"-2 DE 3/8", ¼" A .20, LIG.:1 Acero ¼" + 10% desp. 0.998 qq 1,519.73 1,516.69 101.72% 1,491.002 Acero 3/8" x 20' grado 40 + 10% desp. 1.424 qq 2,114.09 3,010.46 101.72% 2,959.463 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 2,121.47 5,503.09 101.72% 5,409.844 M.O. acero 50.00 m 81.08 4,054.00 100.00% 4,054.005 Madera bruta amer. (4 usos) 242.18 pt 35.70 8,645.83 101.74% 8,498.106 Clavos corrientes (5 lb. / 100 pie madera) 48.44 lb 30.43 1,474.03 101.70% 1,449.327 Clavos de acero (¼ lb / metro) 12.50 lb 53.10 663.75 101.72% 652.508 Alambre calibre #14 (¼ lb. / metro) 12.50 lb 34.64 433.00 101.70% 425.759 Confección e instalación de madera 50.00 m 199.78 9,989.00 100.00% 9,989.0010 Desencofrado 20.00 m2 24.17 483.40 100.00% 483.4011 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $40,647.90 101.09% 40,210.83*HADIN 10270002 DINTEL 10x20, 1:2:4, 40, 2 DE ½"-2 DE 3/8", ¼" A .20 A MANO:

1 Acero ¼" + 10% desp. 0.998 qq 1,519.73 1,516.69 101.72% 1,491.002 Acero 3/8" x 20' grado 40 + 10% desp. 1.424 qq 2,114.09 3,010.46 101.72% 2,959.463 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 2,121.47 5,503.09 101.72% 5,409.84

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 49

Page 52: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

4 M.O. acero 50.00 m 81.08 4,054.00 100.00% 4,054.005 Madera bruta amer. (4 usos) 242.18 pt 35.70 8,645.83 101.74% 8,498.106 Clavos corrientes (5 lb. / 100 pie madera) 48.44 lb 30.43 1,474.03 101.70% 1,449.327 Clavos de acero (¼ lb / metro) 12.50 lb 53.10 663.75 101.72% 652.508 Alambre calibre #14 (¼ lb. / metro) 12.50 lb 34.64 433.00 101.70% 425.759 Confección e instalación de madera 50.00 m 199.78 9,989.00 100.00% 9,989.0010 Desencofrado 20.00 m2 24.17 483.40 100.00% 483.4011 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $41,207.77 101.08% 40,765.48*HADIN 10270003 DINTEL 15x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", ¼" A .20, LIG.:

1 Acero ¼" + 10% desp. 0.779 qq 1,519.73 1,183.87 101.72% 1,163.822 Acero 3/8" x 20' grado 40 + 10% desp. 0.950 qq 2,114.09 2,008.39 101.72% 1,974.363 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 2,121.47 5,503.09 101.72% 5,409.844 M.O. acero 33.33 m 81.08 2,702.40 100.00% 2,702.405 Madera bruta amer. (4 usos) 169.13 pt 35.70 6,037.94 101.74% 5,934.776 Clavos corrientes (5 lb. / 100 pie madera) 33.83 lb 30.43 1,029.45 101.71% 1,012.197 Clavos de acero (¼ lb / metro) 8.33 lb 53.10 442.32 101.72% 434.838 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 34.64 288.55 101.70% 283.729 Confección e instalación de madera 33.33 m 199.78 6,658.67 100.00% 6,658.6710 Desencofrado 13.33 m2 24.17 322.19 100.00% 322.1911 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $31,051.52 101.16% 30,695.25*HADIN 10270004 DINTEL 15x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", ¼" A .20 A MANO:

1 Acero ¼" + 10% desp. 0.779 qq 1,519.73 1,183.87 101.72% 1,163.822 Acero 3/8" x 20' grado 40 + 10% desp. 0.950 qq 2,114.09 2,008.39 101.72% 1,974.363 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 2,121.47 5,503.09 101.72% 5,409.844 M.O. acero 33.33 m 81.08 2,702.40 100.00% 2,702.405 Madera bruta amer. (4 usos) 169.13 pt 35.70 6,037.94 101.74% 5,934.776 Clavos corrientes (5 lb. / 100 pie madera) 33.83 lb 30.43 1,029.45 101.71% 1,012.197 Clavos de acero (¼ lb / metro) 8.33 lb 53.10 442.32 101.72% 434.838 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 34.64 288.55 101.70% 283.729 Confección e instalación de madera 33.33 m 199.78 6,658.67 100.00% 6,658.6710 Desencofrado 13.33 m2 24.17 322.19 100.00% 322.1911 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $31,611.39 101.16% 31,249.90*HADIN 10270005 DINTEL 15x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", " 3/8" A .20, LIG.:

1 Acero 3/8" + 10% desp. en estribos 1.723 qq 2,114.09 3,642.58 101.72% 3,580.862 Acero 3/8" x 20' grado 40 + 10% desp. 0.950 qq 2,114.09 2,008.39 101.72% 1,974.363 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 2,121.47 5,503.09 101.72% 5,409.844 M.O. acero 33.33 m 81.08 2,702.40 100.00% 2,702.405 Madera bruta amer. (4 usos) 169.13 pt 35.70 6,037.94 101.74% 5,934.776 Clavos corrientes (5 lb. / 100 pie madera) 33.83 lb 30.43 1,029.45 101.71% 1,012.197 Clavos de acero (¼ lb / metro) 8.33 lb 53.10 442.32 101.72% 434.838 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 34.64 288.55 101.70% 283.729 Confección e instalación de madera 33.33 m 199.78 6,658.67 100.00% 6,658.6710 Desencofrado 13.33 m2 24.17 322.19 100.00% 322.1911 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $33,510.23 101.20% 33,112.29*HADIN 10270006 DINTEL 15x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", 3/8" A .20 A MANO:

1 Acero 3/8" + 10% desp. en estribos 1.723 qq 2,114.09 3,642.58 101.72% 3,580.862 Acero 3/8" x 20' grado 40 + 10% desp. 0.950 qq 2,114.09 2,008.39 101.72% 1,974.363 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 2,121.47 5,503.09 101.72% 5,409.844 M.O. acero 33.33 m 81.08 2,702.40 100.00% 2,702.405 Madera bruta amer. (4 usos) 169.13 pt 35.70 6,037.94 101.74% 5,934.776 Clavos corrientes (5 lb. / 100 pie madera) 33.83 lb 30.43 1,029.45 101.71% 1,012.197 Clavos de acero (¼ lb / metro) 8.33 lb 53.10 442.32 101.72% 434.838 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 34.64 288.55 101.70% 283.729 Confección e instalación de madera 33.33 m 199.78 6,658.67 100.00% 6,658.6710 Desencofrado 13.33 m2 24.17 322.19 100.00% 322.1911 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $34,070.10 101.20% 33,666.94*HADIN 10270007 DINTEL 20x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", 3/8" A .20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 2.069 qq 2,114.09 4,374.05 101.72% 4,299.942 Acero ½" x 20' grado 40 + 10% desp. 1.945 qq 2,121.47 4,126.26 101.72% 4,056.343 M.O. acero 25.00 m 81.08 2,027.00 100.00% 2,027.004 Madera bruta amer. (4 usos) 132.62 pt 35.70 4,734.53 101.74% 4,653.645 Clavos corrientes (5 lb. / 100 pie madera) 26.52 lb 30.43 807.00 101.70% 793.486 Clavos de acero (¼ lb / metro) 6.25 lb 53.10 331.88 101.73% 326.257 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 34.64 216.50 101.70% 212.888 Confección e instalación de madera 25.00 m 199.78 4,994.50 100.00% 4,994.509 Desencofrado 10.00 m2 24.17 241.70 100.00% 241.7010 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $26,728.07 101.23% 26,404.19*HADIN 10270008 DINTEL 20x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", 3/8" A .20 A MANO:

1 Acero 3/8" x 20' grado 40 + 10% desp. 2.069 qq 2,114.09 4,374.05 101.72% 4,299.942 Acero ½" x 20' grado 40 + 10% desp. 1.945 qq 2,121.47 4,126.26 101.72% 4,056.343 M.O. acero 25.00 m 81.08 2,027.00 100.00% 2,027.004 Madera bruta amer. (4 usos) 132.62 pt 35.70 4,734.53 101.74% 4,653.645 Clavos corrientes (5 lb. / 100 pie madera) 26.52 lb 30.43 807.00 101.70% 793.486 Clavos de acero (¼ lb / metro) 6.25 lb 53.10 331.88 101.73% 326.257 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 34.64 216.50 101.70% 212.888 Confección e instalación de madera 25.00 m 199.78 4,994.50 100.00% 4,994.509 Desencofrado 10.00 m2 24.17 241.70 100.00% 241.7010 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $27,287.94 101.22% 26,958.84*HADIN 10270009 DINTEL 10x20, 180 kg/Cm², 40, 2 DE ½"-2 DE 3/8", ¼" A .20:

1 Acero ¼" + 10% desp. 0.998 qq 1,519.73 1,516.69 101.72% 1,491.002 Acero 3/8" x 20' grado 40 + 10% desp. 1.424 qq 2,114.09 3,010.46 101.72% 2,959.463 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 2,121.47 5,503.09 101.72% 5,409.844 M.O. acero 50.00 m 81.08 4,054.00 100.00% 4,054.005 Madera bruta amer. (4 usos) 242.18 pt 35.70 8,645.83 101.74% 8,498.106 Clavos corrientes (5 lb. / 100 pie madera) 48.44 lb 30.43 1,474.03 101.70% 1,449.327 Clavos de acero (¼ lb / metro) 12.50 lb 53.10 663.75 101.72% 652.508 Alambre calibre #14 (¼ lb. / metro) 12.50 lb 34.64 433.00 101.70% 425.75

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 50

Page 53: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

9 Confección e instalación de madera 50.00 m 199.78 9,989.00 100.00% 9,989.0010 Desencofrado 20.00 m2 24.17 483.40 100.00% 483.4011 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $43,016.09 101.14% 42,532.45*HADIN 10270010 DINTEL 15x20, 180 kg/Cm², 40, 3 DE ½"-2 DE 3/8", ¼" A .20:

1 Acero ¼" + 10% desp. 0.779 qq 1,519.73 1,183.87 101.72% 1,163.822 Acero 3/8" x 20' grado 40 + 10% desp. 0.950 qq 2,114.09 2,008.39 101.72% 1,974.363 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 2,121.47 5,503.09 101.72% 5,409.844 M.O. acero 33.33 m 81.08 2,702.40 100.00% 2,702.405 Madera bruta amer. (4 usos) 169.13 pt 35.70 6,037.94 101.74% 5,934.776 Clavos corrientes (5 lb. / 100 pie madera) 33.83 lb 30.43 1,029.45 101.71% 1,012.197 Clavos de acero (¼ lb / metro) 8.33 lb 53.10 442.32 101.72% 434.838 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 34.64 288.55 101.70% 283.729 Confección e instalación de madera 33.33 m 199.78 6,658.67 100.00% 6,658.6710 Desencofrado 13.33 m2 24.17 322.19 100.00% 322.1911 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $33,419.71 101.22% 33,016.87*HADIN 10270011 DINTEL 20x20, 180 kg/Cm², 40, 3 DE ½"-2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 2.069 qq 2,114.09 4,374.05 101.72% 4,299.942 Acero ½" x 20' grado 40 + 10% desp. 1.945 qq 2,121.47 4,126.26 101.72% 4,056.343 M.O. acero 25.00 m 81.08 2,027.00 100.00% 2,027.004 Madera bruta amer. (4 usos) 132.62 pt 35.70 4,734.53 101.74% 4,653.645 Clavos corrientes (5 lb. / 100 pie madera) 26.52 lb 30.43 807.00 101.70% 793.486 Clavos de acero (¼ lb / metro) 6.25 lb 53.10 331.88 101.73% 326.257 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 34.64 216.50 101.70% 212.888 Confección e instalación de madera 25.00 m 199.78 4,994.50 100.00% 4,994.509 Desencofrado 10.00 m2 24.17 241.70 100.00% 241.7010 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $29,096.26 101.29% 28,725.81

*HALOSM 10290000 HORM. ARMADO LOSAS MONOLITICAS

*HALOSM 10290001 LOSA H=10, 1:2:4, 40, 3/8" x 20' A 25 A. D. LIG. Y WINCHE:1 Acero 3/8" x 20' grado 40 + 10% desp. 1.819 qq 2,114.09 3,845.53 101.72% 3,780.372 M.O. acero 1.819 qq 243.24 442.45 100.00% 442.453 Subida acero 1.819 qq 24.32 44.24 100.00% 44.244 Madera bruta amer. (4 usos) 69.89 pt 35.70 2,495.07 101.74% 2,452.445 Clavos corrientes (5 lb. / 100 pie madera) 13.98 lb 30.43 425.41 101.70% 418.286 Clavos de acero (.08 lb / m2) 0.80 lb 53.10 42.48 101.72% 41.767 Alambre calibre #14 (.15 lb. / m2) 1.50 lb 34.64 51.96 101.70% 51.098 Confección madera 10.00 m2 120.83 1,208.30 100.00% 1,208.309 Desencofrado 10.00 m2 25.78 257.80 100.00% 257.8010 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 4,604.00 5,064.40 101.54% 4,987.39

M3 $13,877.64 101.41% 13,684.12*HALOSM 10290002 LOSA H=10, 1:2:4, 40, 3/8" >20' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.819 qq 2,072.20 3,769.33 101.72% 3,705.472 Partidas comunes del análisis anterior (2-10) 1.00 u 10,032.11 10,032.11 101.30% 9,903.75

M3 $13,801.44 101.41% 13,609.22*HALOSM 10290003 LOSA H=10, 1:2:4, 60, 3/8" x 20' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.819 qq 2,351.19 4,276.81 101.72% 4,204.352 M.O. acero 1.819 qq 366.08 665.90 100.00% 665.903 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 9,589.66 9,589.66 101.36% 9,461.30

M3 $14,532.37 101.40% 14,331.55*HALOSM 10290004 LOSA H=10, 1:2:4, 60, 3/8" x 25' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.819 qq 2,351.19 4,276.81 101.72% 4,204.352 M.O. acero 1.819 qq 366.08 665.90 100.00% 665.903 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 9,589.66 9,589.66 101.36% 9,461.30

M3 $14,532.37 101.40% 14,331.55*HALOSM 10290005 LOSA H=12, 1:2:4, 40, 3/8" x 20' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.496 qq 2,114.09 3,162.68 101.72% 3,109.092 M.O. acero 1.496 qq 243.24 363.89 100.00% 363.893 Subida acero 1.496 qq 24.32 36.38 100.00% 36.384 Madera bruta amer. (4 usos) 56.95 pt 35.70 2,033.12 101.74% 1,998.385 Clavos corrientes (5 lb. / 100 pie madera) 11.39 lb 30.43 346.60 101.70% 340.796 Clavos de acero (.08 lb / m2) 0.67 lb 53.10 35.58 101.74% 34.977 Alambre calibre #14 (.15 lb. / m2) 1.25 lb 34.64 43.30 101.69% 42.588 Confección 8.35 m2 120.83 1,008.93 100.00% 1,008.939 Desencofrado 8.35 m2 25.78 215.26 100.00% 215.2610 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 4,604.00 5,064.40 101.54% 4,987.39

M3 $12,310.14 101.42% 12,137.66*HALOSM 10290006 LOSA H=12 1:2:4, 40, 3/8" >20' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.496 qq 2,072.20 3,100.01 101.72% 3,047.492 Partidas comunes del análisis anterior (2-10) 1.00 u 9,147.46 9,147.46 101.32% 9,028.57

M3 $12,247.47 101.42% 12,076.06*HALOSM 10290007 LOSA H=12, 1:2:4, 60, 3/8" x 20' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.496 qq 2,351.19 3,517.38 101.72% 3,457.782 M.O. acero 1.496 qq 366.08 547.66 100.00% 547.663 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 8,783.57 8,783.57 101.37% 8,664.68

M3 $12,848.61 101.41% 12,670.12*HALOSM 10290008 LOSA H=12, 1:2:4, 60, 3/8" x 25' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.496 qq 2,432.17 3,638.53 101.72% 3,576.882 M.O. acero 1.496 qq 366.08 547.66 100.00% 547.663 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 8,783.57 8,783.57 101.37% 8,664.68

M3 $12,969.76 101.41% 12,789.22*HALOSM 10290009 LOSA H=10, 180 kg/Cm², 40, 3/8" x 20' A 25 A. D.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.819 qq 2,114.09 3,845.53 101.72% 3,780.372 M.O. acero 1.819 qq 243.24 442.45 100.00% 442.453 Subida acero 1.819 qq 24.32 44.24 100.00% 44.244 Madera bruta amer. (4 usos) 69.89 pt 35.70 2,495.07 101.74% 2,452.445 Clavos corrientes (5 lb. / 100 pie madera) 13.98 lb 30.43 425.41 101.70% 418.286 Clavos de acero (.08 lb / m2) 0.80 lb 53.10 42.48 101.72% 41.767 Alambre calibre #14 (.15 lb. / m2) 1.50 lb 34.64 51.96 101.70% 51.098 Confección madera 10.00 m2 120.83 1,208.30 100.00% 1,208.309 Desencofrado 10.00 m2 25.78 257.80 100.00% 257.80

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 51

Page 54: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

10 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08M3 $16,056.08 101.51% 15,816.81

*HALOSM 10290010 LOSA H=10, 180 kg/Cm², 40, 3/8" >20' A 25 A. D., HORM. IND.:1 Acero 3/8" x 25' grado 40 + 10% desp. 1.819 qq 2,072.20 3,769.33 101.72% 3,705.472 Partidas comunes del análisis anterior (2-10) 1.00 u 12,210.55 12,210.55 101.45% 12,036.44

M3 $15,979.88 101.51% 15,741.91*HALOSM 10290011 LOSA H=10, 180 kg/Cm², 60, 3/8" x 20' A 25 A. D., HORM. IND.:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.819 qq 2,351.19 4,276.81 101.72% 4,204.352 M.O. acero 1.819 qq 366.08 665.90 100.00% 665.903 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 11,768.10 11,768.10 101.50% 11,593.99

M3 $16,710.81 101.50% 16,464.24*HALOSM 10290012 LOSA H=10, 180 kg/Cm², 60, 3/8" x 25' A 25 A. D., HORM. IND.:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.819 qq 2,432.17 4,424.12 101.72% 4,349.162 M.O. acero 1.819 qq 366.08 665.90 100.00% 665.903 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 11,768.10 11,768.10 101.50% 11,593.99

M3 $16,858.12 101.50% 16,609.05*HALOSM 10290013 LOSA H=12, 180 kg/Cm², 40, 3/8" x 20' A 25 A. D., HORM. IND.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.496 qq 2,114.09 3,162.68 101.72% 3,109.092 M.O. acero 1.496 qq 243.24 363.89 100.00% 363.893 Subida acero 1.496 qq 24.32 36.38 100.00% 36.384 Madera bruta amer. (4 usos) 56.95 pt 35.70 2,033.12 101.74% 1,998.385 Clavos corrientes (5 lb. / 100 pie madera) 11.39 lb 30.43 346.60 101.70% 340.796 Clavos de acero (.08 lb / m2) 0.67 lb 53.10 35.58 101.74% 34.977 Alambre calibre #14 (.15 lb. / m2) 1.25 lb 34.64 43.30 101.69% 42.588 Confección madera 8.35 m2 120.83 1,008.93 100.00% 1,008.939 Desencofrado 8.35 m2 25.78 215.26 100.00% 215.2610 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $14,488.58 101.53% 14,270.35*HALOSM 10290014 LOSA H=12 180 kg/Cm², 40, 3/8" >20' A 25 A. D., HORM. IND.:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.496 qq 2,072.20 3,100.01 101.72% 3,047.492 Partidas comunes del análisis anterior (2-10) 1.00 u 11,325.90 11,325.90 101.48% 11,161.26

M3 $14,425.91 101.53% 14,208.75*HALOSM 10290015 LOSA H=12, 180 Kg/Cm², 60, 3/8" x 20' A 25 A., D. HORM. IND.:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.496 qq 2,351.19 3,517.38 101.72% 3,457.782 M.O. acero 1.496 qq 366.08 547.66 100.00% 547.663 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 10,962.01 10,962.01 101.52% 10,797.37

M3 $15,027.05 101.51% 14,802.81*HALOSM 10290016 LOSA H=12, 180 Kg/Cm², 60, 3/8" x 25' A 25 A. D., HORM. IND.:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.496 qq 2,432.17 3,638.53 101.72% 3,576.882 M.O. acero 1.496 qq 366.08 547.66 100.00% 547.663 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 10,962.01 10,962.01 101.52% 10,797.37

M3 $15,148.20 101.52% 14,921.91

*HAMUR 10310000 HORM. ARMADO MUROS

*HAMUR 10310001 MUROS 0.15, 180 Kg/Cm², 40, 3/8" x 20' A .20 A.D., 2 CARAS: Espesor = 0.151 Acero 3/8" x 20' grado 40 + 10% desp. 1.8156 qq 2,114.09 3,838.34 101.72% 3,773.312 M.O. acero 1.8156 qq 243.24 441.63 100.00% 441.633 Planchas plywood 4'x8'x¾" (8 usos) 0.56 u 1,607.24 900.05 101.72% 884.804 Madera bruta amer. (4 usos) 46.33 pt 35.70 1,653.98 101.74% 1,625.725 Clavos corrientes (10 lb. / 100 pie madera) 18.53 lb 30.43 563.87 101.70% 554.426 Clavos de acero (½ lb / m²) 6.67 lb 53.10 354.18 101.73% 348.177 Alambre calibre #14 (½ lb. / m²) 6.67 lb 34.64 231.05 101.70% 227.188 Confección madera (dos caras) 13.333 m2 145.00 1,933.29 100.00% 1,933.299 Instalación madera (dos caras) 13.333 m2 182.06 2,427.41 100.00% 2,427.4110 Desencofrado 13.333 m2 20.94 279.19 100.00% 279.1911 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $19,865.83 101.28% 19,615.20*HAMUR 10310002 MUROS 0.15, 180 Kg/Cm², 40, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.8156 qq 2,072.20 3,762.29 101.72% 3,698.542 Partidas comunes del análisis anterior (2-11) 1.00 u 16,027.49 16,027.49 101.17% 15,841.89

M3 $19,789.78 101.28% 19,540.43*HAMUR 10310003 MUROS 0.15, 180 Kg/Cm², 60, 3/8" x 20' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.8156 qq 2,351.19 4,268.82 101.72% 4,196.492 M.O. acero 1.8156 qq 366.08 664.65 100.00% 664.653 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 15,585.86 15,585.86 101.21% 15,400.26

M3 $20,519.33 101.27% 20,261.40*HAMUR 10310004 MUROS 0.15, 180 Kg/Cm², 60, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.8156 qq 2,432.17 4,415.85 101.72% 4,341.032 M.O. acero 1.8156 qq 366.08 664.65 100.00% 664.653 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 15,585.86 15,585.86 101.21% 15,400.26

M3 $20,666.36 101.28% 20,405.94*HAMUR 10310005 MUROS 0.15, 210 Kg/Cm², 40 3/8" x 20' A .20 A.D., 2 CARAS: Espesor = 0.15

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.8156 qq 2,114.09 3,838.34 101.72% 3,773.312 M.O. acero 1.8156 qq 243.24 441.63 100.00% 441.633 Planchas plywood 4'x8'x¾" (8 usos) 0.56 u 1,607.24 900.05 101.72% 884.804 Madera bruta amer. (4 usos) 46.33 pt 35.70 1,653.98 101.74% 1,625.725 Clavos corrientes (10 lb. / 100 pie madera) 18.53 lb 30.43 563.87 101.70% 554.426 Clavos de acero (½ lb / m²) 6.67 lb 53.10 354.18 101.73% 348.177 Alambre calibre #14 (½ lb. / m²) 6.67 lb 34.64 231.05 101.70% 227.188 Confección madera (dos caras) 13.333 m2 145.00 1,933.29 100.00% 1,933.299 Instalación madera (dos caras) 13.333 m2 182.06 2,427.41 100.00% 2,427.4110 Desencofrado 13.333 m2 20.94 279.19 100.00% 279.1911 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $20,073.51 101.28% 19,819.36*HAMUR 10310006 MUROS 0.15, 210 Kg/Cm², 40 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.8156 qq 2,072.20 3,762.29 101.72% 3,698.542 Partidas comunes del análisis anterior (2-11) 1.00 u 16,235.17 16,235.17 101.18% 16,046.05

M3 $19,997.46 101.28% 19,744.59*HAMUR 10310007 MUROS 0.15, 210 Kg/Cm², 60, 3/8" x 20' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.8156 qq 2,351.19 4,268.82 101.72% 4,196.492 M.O. acero 1.8156 qq 366.08 664.65 100.00% 664.653 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 15,793.54 15,793.54 101.21% 15,604.42

M3 $20,727.01 101.28% 20,465.56PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 52

Page 55: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

*HAMUR 10310008 MUROS 0.15, 210 Kg/Cm², 60, 3/8" x 25' A .20 A.D., 2 CARAS:1 Acero 3/8" x 25' grado 60 + 10% desp. 1.8156 qq 2,432.17 4,415.85 101.72% 4,341.032 M.O. acero 1.8156 qq 366.08 664.65 100.00% 664.653 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 15,793.54 15,793.54 101.21% 15,604.42

M3 $20,874.04 101.28% 20,610.10*HAMUR 10310009 MUROS 0.15, 240 Kg/Cm², 40, 3/8" x 20' A .20 A.D., 2 CARAS: Espesor = 0.15

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.8156 qq 2,114.09 3,838.34 101.72% 3,773.312 M.O. acero 1.8156 qq 243.24 441.63 100.00% 441.633 Planchas plywood 4'x8'x¾" (8 usos) 0.56 u 1,607.24 900.05 101.72% 884.804 Madera bruta amer. (4 usos) 46.33 pt 35.70 1,653.98 101.74% 1,625.725 Clavos corrientes (10 lb. / 100 pie madera) 18.53 lb 30.43 563.87 101.70% 554.426 Clavos de acero (½ lb / m²) 6.67 lb 53.10 354.18 101.73% 348.177 Alambre calibre #14 (½ lb. / m²) 6.67 lb 34.64 231.05 101.70% 227.188 Confección madera (dos caras) 13.333 m2 145.00 1,933.29 100.00% 1,933.299 Instalación madera (dos caras) 13.333 m2 182.06 2,427.41 100.00% 2,427.4110 Desencofrado 13.333 m2 20.94 279.19 100.00% 279.1911 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $20,605.69 101.29% 20,342.52*HAMUR 10310010 MUROS 0.15, 240 Kg/Cm², 40, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.8156 qq 2,072.20 3,762.29 101.72% 3,698.542 Partidas comunes del análisis anterior (2-11) 1.00 u 16,767.35 16,767.35 101.20% 16,569.21

M3 $20,529.64 101.29% 20,267.75*HAMUR 10310011 MUROS 0.15, 240 Kg/Cm², 60, 3/8" x 20' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.8156 qq 2,351.19 4,268.82 101.72% 4,196.492 M.O. acero 1.8156 qq 366.08 664.65 100.00% 664.653 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 16,325.72 16,325.72 101.23% 16,127.58

M3 $21,259.19 101.29% 20,988.72*HAMUR 10310012 MUROS 0.15, 240 Kg/Cm², 60, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.8156 qq 2,432.17 4,415.85 101.72% 4,341.032 M.O. acero 1.8156 qq 366.08 664.65 100.00% 664.653 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 16,325.72 16,325.72 101.23% 16,127.58

M3 $21,406.22 101.29% 21,133.26*HAMUR 10310013 MUROS 0.20, 180 Kg/Cm², 40, 3/8" x 20' A .20 A.D., 2 CARAS: Espesor = 0.20

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.3634 qq 2,114.09 2,882.35 101.72% 2,833.512 M.O. acero 1.3634 qq 243.24 331.63 100.00% 331.633 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,607.24 675.04 101.72% 663.604 Madera bruta amer. (4 usos) 34.79 pt 35.70 1,242.00 101.74% 1,220.785 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 30.43 423.59 101.70% 416.496 Clavos de acero (½ lb / m²) 5.00 lb 53.10 265.50 101.72% 261.007 Alambre calibre #14 (½ lb. / m²) 5.00 lb 34.64 173.20 101.70% 170.308 Confección madera (dos caras) 10.000 m2 145.00 1,450.00 100.00% 1,450.009 Instalación madera (dos caras) 10.000 m2 182.06 1,820.60 100.00% 1,820.6010 Desencofrado 10.000 m2 20.94 209.40 100.00% 209.4011 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $16,716.15 101.33% 16,497.39*HAMUR 10310014 MUROS 0.20, 180 Kg/Cm², 40, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.3634 qq 2,072.20 2,825.24 101.72% 2,777.372 Partidas comunes del análisis anterior (2-11) 1.00 u 13,833.80 13,833.80 101.24% 13,663.88

M3 $16,659.04 101.32% 16,441.25*HAMUR 10310015 MUROS 0.20, 180 Kg/Cm², 60, 3/8" x 20' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.3634 qq 2,351.19 3,205.61 101.72% 3,151.292 M.O. acero 1.3634 qq 366.08 499.11 100.00% 499.113 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,502.17 13,502.17 101.27% 13,332.25

M3 $17,206.89 101.32% 16,982.65*HAMUR 10310016 MUROS 0.20, 180 Kg/Cm², 60, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.3634 qq 2,432.17 3,316.02 101.72% 3,259.832 M.O. acero 1.3634 qq 366.08 499.11 100.00% 499.113 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,502.17 13,502.17 101.27% 13,332.25

M3 $17,317.30 101.32% 17,091.19*HAMUR 10310017 MUROS 0.20, 210 Kg/Cm², 40, 3/8" x 20' A .20 A.D., 2 CARAS: Espesor = 0.20

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.3634 qq 2,114.09 2,882.35 101.72% 2,833.512 M.O. acero 1.3634 qq 243.24 331.63 100.00% 331.633 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,607.24 675.04 101.72% 663.604 Madera bruta amer. (4 usos) 34.79 pt 35.70 1,242.00 101.74% 1,220.785 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 30.43 423.59 101.70% 416.496 Clavos de acero (½ lb / m²) 5.00 lb 53.10 265.50 101.72% 261.007 Alambre calibre #14 (½ lb. / m²) 5.00 lb 34.64 173.20 101.70% 170.308 Confección madera (dos caras) 10.000 m2 145.00 1,450.00 100.00% 1,450.009 Instalación madera (dos caras) 10.000 m2 182.06 1,820.60 100.00% 1,820.6010 Desencofrado 10.000 m2 20.94 209.40 100.00% 209.4011 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $16,923.83 101.33% 16,701.55*HAMUR 10310018 MUROS 0.20, 210 Kg/Cm², 40, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.3634 qq 2,072.20 2,825.24 101.72% 2,777.372 Partidas comunes del análisis anterior (2-11) 1.00 u 14,041.48 14,041.48 101.25% 13,868.04

M3 $16,866.72 101.33% 16,645.41*HAMUR 10310019 MUROS 0.20, 210 Kg/Cm², 60, 3/8" x 20' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.3634 qq 2,351.19 3,205.61 101.72% 3,151.292 M.O. acero 1.3634 qq 366.08 499.11 100.00% 499.113 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,709.85 13,709.85 101.28% 13,536.41

M3 $17,414.57 101.33% 17,186.81*HAMUR 10310020 MUROS 0.20, 210 Kg/Cm², 60, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.3634 qq 2,432.17 3,316.02 101.72% 3,259.832 M.O. acero 1.3634 qq 366.08 499.11 100.00% 499.113 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,709.85 13,709.85 101.28% 13,536.41

M3 $17,524.98 101.33% 17,295.35*HAMUR 10310021 MUROS 0.20, 210 Kg/Cm², 40, ½" x 20' A .10 A.D., 2 CARAS: Espesor = 0.20

1 Acero ½" x 20' grado 40 + 10% desp. 4.8444 qq 2,121.47 10,277.25 101.72% 10,103.092 M.O. acero 4.8444 qq 243.24 1,178.35 100.00% 1,178.353 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,607.24 675.04 101.72% 663.604 Madera bruta amer. (4 usos) 34.79 pt 35.70 1,242.00 101.74% 1,220.785 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 30.43 423.59 101.70% 416.496 Clavos de acero (½ lb / m²) 5.00 lb 53.10 265.50 101.72% 261.007 Alambre calibre #14 (½ lb. / m²) 5.00 lb 34.64 173.20 101.70% 170.30

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 53

Page 56: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

8 Confección madera (dos caras) 10.000 m2 145.00 1,450.00 100.00% 1,450.009 Instalación madera (dos caras) 10.000 m2 182.06 1,820.60 100.00% 1,820.6010 Desencofrado 10.000 m2 20.94 209.40 100.00% 209.4011 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $25,165.45 101.40% 24,817.85*HAMUR 10310022 MUROS 0.20, 210 Kg/Cm², 40, ½" x 25' A .10 A.D., 2 CARAS:

1 Acero ½" x 25' grado 40 + 10% desp. 4.8444 qq 2,078.50 10,069.09 101.72% 9,898.512 Partidas comunes del análisis anterior (2-11) 1.00 u 14,888.20 14,888.20 101.18% 14,714.76

M3 $24,957.29 101.40% 24,613.27*HAMUR 10310023 MUROS 0.20, 210 Kg/Cm², 60, ½" x 20' A .10 A.D., 2 CARAS:

1 Acero ½" x 20' grado 60 + 10% desp. 4.8444 qq 2,413.96 11,694.19 101.72% 11,496.052 M.O. acero 4.8444 qq 366.08 1,773.44 100.00% 1,773.443 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,709.85 13,709.85 101.28% 13,536.41

M3 $27,177.48 101.39% 26,805.90*HAMUR 10310024 MUROS 0.20, 210 Kg/Cm², 60, ½" >20' A .10 A.D., 2 CARAS:

1 Acero ½" x 25' grado 60 + 10% desp. 4.8444 qq 2,409.63 11,673.21 101.72% 11,475.462 M.O. acero 4.8444 qq 366.08 1,773.44 100.00% 1,773.443 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,709.85 13,709.85 101.28% 13,536.41

M3 $27,156.50 101.39% 26,785.31*HAMUR 10310025 MUROS 0.20, 210 Kg/Cm², 40, ½" x 20' A .20 A.D., 2 CARAS: Espesor = 0.20

1 Acero ½" x 20' grado 40 + 10% desp. 2.4222 qq 2,121.47 5,138.62 101.72% 5,051.552 M.O. acero 2.4222 qq 243.24 589.18 100.00% 589.183 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,607.24 675.04 101.72% 663.604 Madera bruta amer. (4 usos) 34.79 pt 35.70 1,242.00 101.74% 1,220.785 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 30.43 423.59 101.70% 416.496 Clavos de acero (½ lb / m²) 5.00 lb 53.10 265.50 101.72% 261.007 Alambre calibre #14 (½ lb. / m²) 5.00 lb 34.64 173.20 101.70% 170.308 Confección madera (dos caras) 10.000 m2 145.00 1,450.00 100.00% 1,450.009 Instalación madera (dos caras) 10.000 m2 182.06 1,820.60 100.00% 1,820.6010 Desencofrado 10.000 m2 20.94 209.40 100.00% 209.4011 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $19,437.65 101.36% 19,177.14*HAMUR 10310026 MUROS 0.20, 210 Kg/Cm², 40, ½" x 25' A .20 A.D., 2 CARAS:

1 Acero ½" x 25' grado 40 + 10% desp. 2.4222 qq 2,078.50 5,034.54 101.72% 4,949.262 Partidas comunes del análisis anterior (2-11) 1.00 u 14,299.03 14,299.03 101.23% 14,125.59

M3 $19,333.57 101.36% 19,074.85*HAMUR 10310027 MUROS 0.20, 210 Kg/Cm², 60, ½" x 20' A .20 A.D., 2 CARAS:

1 Acero ½" x 20' grado 60 + 10% desp. 2.4222 qq 2,413.96 5,847.09 101.72% 5,748.032 M.O. acero 2.4222 qq 366.08 886.72 100.00% 886.723 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,709.85 13,709.85 101.28% 13,536.41

M3 $20,443.66 101.35% 20,171.16*HAMUR 10310028 MUROS 0.20, 210 Kg/Cm², 60, ½" x 25' A .20 A.D., 2 CARAS:

1 Acero ½" x 25' grado 60 + 10% desp. 2.4222 qq 2,409.63 5,836.61 101.72% 5,737.732 M.O. acero 2.4222 qq 366.08 886.72 100.00% 886.723 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,709.85 13,709.85 101.28% 13,536.41

M3 $20,433.18 101.35% 20,160.86*HAMUR 10310029 MUROS 0.20, 240 Kg/Cm², 40, ½" x 20' A .10 A.D., 2 CARAS: Espesor = 0.20

1 Acero ½" x 20' grado 40 + 10% desp. 4.8444 qq 2,121.47 10,277.25 101.72% 10,103.092 M.O. acero 4.8444 qq 243.24 1,178.35 100.00% 1,178.353 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,607.24 675.04 101.72% 663.604 Madera bruta amer. (4 usos) 34.79 pt 35.70 1,242.00 101.74% 1,220.785 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 30.43 423.59 101.70% 416.496 Clavos de acero (½ lb / m²) 5.00 lb 53.10 265.50 101.72% 261.007 Alambre calibre #14 (½ lb. / m²) 5.00 lb 34.64 173.20 101.70% 170.308 Confección madera (dos caras) 10.000 m2 145.00 1,450.00 100.00% 1,450.009 Instalación madera (dos caras) 10.000 m2 182.06 1,820.60 100.00% 1,820.6010 Desencofrado 10.000 m2 20.94 209.40 100.00% 209.4011 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $25,697.63 101.41% 25,341.01*HAMUR 10310030 MUROS 0.20, 240 Kg/Cm², 40, ½" x 25' A .10 A.D., 2 CARAS:

1 Acero ½" x 25' grado 40 + 10% desp. 4.8444 qq 2,078.50 10,069.09 101.72% 9,898.512 Partidas comunes del análisis anterior (2-11) 1.00 u 15,420.38 15,420.38 101.20% 15,237.92

M3 $25,489.47 101.40% 25,136.43*HAMUR 10310031 MUROS 0.20, 240 Kg/Cm², 60, ½" x 20' A .10 A.D., 2 CARAS:

1 Acero ½" x 20' grado 60 + 10% desp. 4.8444 qq 2,413.96 11,694.19 101.72% 11,496.052 M.O. acero 4.8444 qq 366.08 1,773.44 100.00% 1,773.443 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 14,242.03 14,242.03 101.30% 14,059.57

M3 $27,709.66 101.39% 27,329.06*HAMUR 10310032 MUROS 0.20, 240 Kg/Cm², 60, ½" x 25' A .10 A.D., 2 CARAS:

1 Acero ½" x 25' grado 60 + 10% desp. 4.8444 qq 2,409.63 11,673.21 101.72% 11,475.462 M.O. acero 4.8444 qq 366.08 1,773.44 100.00% 1,773.443 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 14,242.03 14,242.03 101.30% 14,059.57

M3 $27,688.68 101.39% 27,308.47*HAMUR 10310033 MUROS 0.20, 240 Kg/Cm², 40, ½" x 20' A .20 A.D., 2 CARAS: Espesor = 0.20

1 Acero ½" x 20' grado 40 + 10% desp. 2.4222 qq 2,121.47 5,138.62 101.72% 5,051.552 M.O. acero 2.4222 qq 243.24 589.18 100.00% 589.183 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,607.24 675.04 101.72% 663.604 Madera bruta amer. (4 usos) 34.79 pt 35.70 1,242.00 101.74% 1,220.785 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 30.43 423.59 101.70% 416.496 Clavos de acero (½ lb / m²) 5.00 lb 53.10 265.50 101.72% 261.007 Alambre calibre #14 (½ lb. / m²) 5.00 lb 34.64 173.20 101.70% 170.308 Confección madera (dos caras) 10.000 m2 145.00 1,450.00 100.00% 1,450.009 Instalación madera (dos caras) 10.000 m2 182.06 1,820.60 100.00% 1,820.6010 Desencofrado 10.000 m2 20.94 209.40 100.00% 209.4011 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $19,969.83 101.37% 19,700.30*HAMUR 10310034 MUROS 0.20, 240 Kg/Cm², 40, ½" x 25' A .20 A.D., 2 CARAS:

1 Acero ½" x 25' grado 40 + 10% desp. 2.4222 qq 2,078.50 5,034.54 101.72% 4,949.262 Partidas comunes del análisis anterior (2-11) 1.00 u 14,831.21 14,831.21 101.25% 14,648.75

M3 $19,865.75 101.37% 19,598.01*HAMUR 10310035 MUROS 0.20, 240 Kg/Cm², 60, ½" x 20' A .20 A.D., 2 CARAS:

1 Acero ½" x 20' grado 60 + 10% desp. 2.4222 qq 2,413.96 5,847.09 101.72% 5,748.032 M.O. acero 2.4222 qq 366.08 886.72 100.00% 886.72

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 54

Page 57: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

3 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 14,242.03 14,242.03 101.30% 14,059.57M3 $20,975.84 101.36% 20,694.32

*HAMUR 10310036 MUROS 0.20, 240 Kg/Cm², 60, ½" x 25' A .20 A.D., 2 CARAS:1 Acero ½" x 25' grado 60 + 10% desp. 2.4222 qq 2,409.63 5,836.61 101.72% 5,737.732 M.O. acero 2.4222 qq 366.08 886.72 100.00% 886.723 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 14,242.03 14,242.03 101.30% 14,059.57

M3 $20,965.36 101.36% 20,684.02

*HARAM 10330000 HORM. ARMADO RAMPAS DE ESCALERAS

*HARAM 10330001 RAMPAS H=12, 1:2:4, 40, ½" A .20, 3/8" A .20, LIG. Y WINCHE:1 Acero 3/8" x 20' grado 40 + 10% desp. 1.140 qq 2,114.09 2,410.06 101.72% 2,369.232 Acero ½" x 20' grado 40 + 10% desp. 1.620 qq 2,121.47 3,436.78 101.72% 3,378.543 M.O. acero (rampa) 3.00 u 2,406.67 7,220.01 100.00% 7,220.014 Madera bruta amer. (4 usos) 42.22 pt 35.70 1,507.25 101.74% 1,481.505 Clavos corrientes (10 lb. / 100 pie madera) 16.89 lb 30.43 513.96 101.70% 505.356 Clavos de acero (.10 lb / m2) 0.92 lb 53.10 48.85 101.73% 48.027 Alambre calibre #14 (.30 lb. / m2) 2.75 lb 34.64 95.26 101.70% 93.678 Encofrado 9.17 m2 396.34 3,634.44 100.00% 3,634.449 Desencofrado 9.17 m2 25.78 236.40 100.00% 236.4010 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 4,604.00 5,064.40 101.54% 4,987.39

M3 $24,167.41 100.89% 23,954.55*HARAM 10330002 RAMPAS H=12, 1:2:4, 40, ½"X25' A .20, 3/8" A .20, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.140 qq 2,114.09 2,410.06 101.72% 2,369.232 Acero ½" x 25' grado 40 + 10% desp. 1.620 qq 2,078.50 3,367.17 101.72% 3,310.133 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 18,320.57 18,320.57 100.62% 18,206.78

M3 $24,097.80 100.89% 23,886.14*HARAM 10330003 RAMPAS H=12, 1:2:4, 60, ½" X 20' A .20, 3/8" A .20, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.140 qq 2,351.19 2,680.36 101.72% 2,634.942 Acero ½" x 20' grado 60 + 10% desp. 1.620 qq 2,413.96 3,910.62 101.72% 3,844.363 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 18,320.57 18,320.57 100.62% 18,206.78

M3 $24,911.55 100.91% 24,686.08*HARAM 10330004 RAMPAS H=12, 1:2:4, 60, ½"X25' A .20, 3/8" A .20, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.140 qq 2,351.19 2,680.36 101.72% 2,634.942 Acero ½" x 25' grado 60 + 10% desp. 1.620 qq 2,409.63 3,903.60 101.72% 3,837.473 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 18,320.57 18,320.57 100.62% 18,206.78

M3 $24,904.53 100.91% 24,679.19*HARAM 10330005 RAMPAS H=12, 1:2:4, 40, ½" A .20, 3/8" A .20, A MANO:

1 Partidas comunes de la analizada completa anterior (1-9) 1.000 u 19,103.01 19,103.01 100.72% 18,967.162 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $24,537.53 100.89% 24,320.27*HARAM 10330006 RAMPAS H=12, 1:2:4, 40, ½"X25' A .20, 3/8" A .20, A MANO:

1 Acero ½" x 25' grado 40 + 10% desp. 1.620 qq 2,078.50 3,367.17 101.72% 3,310.132 Partidas comunes de la analizada completa anterior (1, 3-9) 1.00 u 15,666.23 15,666.23 100.50% 15,588.623 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $24,467.92 100.89% 24,251.86*HARAM 10330007 RAMPAS H=12, 1:2:4, 60, ½" X 20' A .20, 3/8" A .20, A MANO:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.140 qq 2,351.19 2,680.36 101.72% 2,634.942 Acero ½" x 20' grado 60 + 10% desp. 1.620 qq 2,413.96 3,910.62 101.72% 3,844.363 Partidas comunes de la analizada completa anterior (3-9) 1.000 u 13,256.17 13,256.17 100.28% 13,219.394 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $25,281.67 100.92% 25,051.80*HARAM 10330008 RAMPAS H=12, 1:2:4, 60, ½"X25' A .20, 3/8" A .20, A MANO:

1 Acero ½" x 25' grado 60 + 10% desp. 1.620 qq 2,409.63 3,903.60 101.72% 3,837.472 Partidas comunes de la analizada completa anterior (1, 3-9) 1.00 u 15,936.53 15,936.53 100.52% 15,854.333 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $25,274.65 100.92% 25,044.91*HARAM 10330009 RAMPAS H=12, 180 kg/Cm², 40, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.140 qq 2,114.09 2,410.06 101.72% 2,369.232 Acero ½" x 20' grado 40 + 10% desp. 1.620 qq 2,121.47 3,436.78 101.72% 3,378.543 M.O. acero (rampa) 3.00 u 2,406.67 7,220.01 100.00% 7,220.014 Madera bruta amer. (4 usos) 42.22 pt 35.70 1,507.25 101.74% 1,481.505 Clavos corrientes (10 lb. / 100 pie madera) 16.89 lb 30.43 513.96 101.70% 505.356 Clavos de acero (.10 lb / m2) 0.92 lb 53.10 48.85 101.73% 48.027 Alambre Calibre #14 (.30 lb. / m2) 2.75 lb 34.64 95.26 101.70% 93.678 Encofrado 9.17 m2 396.34 3,634.44 100.00% 3,634.449 Desencofrado 9.17 m2 25.78 236.40 100.00% 236.4010 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $26,345.85 100.99% 26,087.24*HARAM 10330010 RAMPAS H=12, 180 kg/Cm², 40, ½"X25' A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.1400 qq 2,114.09 2,410.06 101.72% 2,369.232 Acero ½" x 25' grado 40 + 10% desp. 1.6200 qq 2,078.50 3,367.17 101.72% 3,310.133 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 20,499.01 20,499.01 100.78% 20,339.47

M3 $26,276.24 100.99% 26,018.83*HARAM 10330011 RAMPAS H=12, 180 kg/Cm², 60, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,351.19 2,680.36 101.72% 2,634.942 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,413.96 3,910.62 101.72% 3,844.363 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 20,499.01 20,499.01 100.78% 20,339.47

M3 $27,089.99 101.01% 26,818.77*HARAM 10330012 RAMPAS H=12, 180 kg/Cm², 60, ½"X25' A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,351.19 2,680.36 101.72% 2,634.942 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,409.63 3,903.60 101.72% 3,837.473 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 20,499.01 20,499.01 100.78% 20,339.47

M3 $27,082.97 101.01% 26,811.88*HARAM 10330013 RAMPAS H=12, 210 kg/Cm², 40, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.140 qq 2,114.09 2,410.06 101.72% 2,369.232 Acero ½" x 20' grado 40 + 10% desp. 1.620 qq 2,121.47 3,436.78 101.72% 3,378.543 M.O. acero (rampa) 3.00 u 2,406.67 7,220.01 100.00% 7,220.014 Madera bruta amer. (4 usos) 42.22 pt 35.70 1,507.25 101.74% 1,481.505 Clavos corrientes (10 lb. / 100 pie madera) 16.89 lb 30.43 513.96 101.70% 505.356 Clavos de acero (.10 lb / m2) 0.92 lb 53.10 48.85 101.73% 48.027 Alambre Calibre #14 (.30 lb. / m2) 2.75 lb 34.64 95.26 101.70% 93.678 Encofrado 9.17 m2 396.34 3,634.44 100.00% 3,634.449 Desencofrado 9.17 m2 25.78 236.40 100.00% 236.40

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 55

Page 58: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

10 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24M3 $26,553.53 101.00% 26,291.40

*HARAM 10330014 RAMPAS H=12, 210 kg/Cm², 40, ½"X25' A .20 Y 3/8" A .20:1 Acero 3/8" x 20' grado 40 + 10% desp. 1.1400 qq 2,114.09 2,410.06 101.72% 2,369.232 Acero ½" x 25' grado 40 + 10% desp. 1.6200 qq 2,078.50 3,367.17 101.72% 3,310.133 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 20,706.69 20,706.69 100.79% 20,543.63

M3 $26,483.92 101.00% 26,222.99*HARAM 10330015 RAMPAS H=12, 210 kg/Cm², 60, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,351.19 2,680.36 101.72% 2,634.942 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,413.96 3,910.62 101.72% 3,844.363 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 20,706.69 20,706.69 100.79% 20,543.63

M3 $27,297.67 101.02% 27,022.93*HARAM 10330016 RAMPAS H=12, 210 kg/Cm², 60, ½"X25' A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,351.19 2,680.36 101.72% 2,634.942 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,409.63 3,903.60 101.72% 3,837.473 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 20,706.69 20,706.69 100.79% 20,543.63

M3 $27,290.65 101.02% 27,016.04*HARAM 10330017 RAMPAS H=12, 240 kg/Cm², 40, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.140 qq 2,114.09 2,410.06 101.72% 2,369.232 Acero ½" x 20' grado 40 + 10% desp. 1.620 qq 2,121.47 3,436.78 101.72% 3,378.543 M.O. acero (rampa) 3.00 u 2,406.67 7,220.01 100.00% 7,220.014 Madera bruta amer. (4 usos) 42.22 pt 35.70 1,507.25 101.74% 1,481.505 Clavos corrientes (10 lb. / 100 pie madera) 16.89 lb 30.43 513.96 101.70% 505.356 Clavos de acero (.10 lb / m2) 0.92 lb 53.10 48.85 101.73% 48.027 Alambre Calibre #14 (.30 lb. / m2) 2.75 lb 34.64 95.26 101.70% 93.678 Encofrado 9.17 m2 396.34 3,634.44 100.00% 3,634.449 Desencofrado 9.17 m2 25.78 236.40 100.00% 236.4010 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $27,085.71 101.01% 26,814.56*HARAM 10330018 RAMPAS H=12, 240 kg/Cm², 40, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.1400 qq 2,114.09 2,410.06 101.72% 2,369.232 Acero ½" x 25' grado 40 + 10% desp. 1.6200 qq 2,078.50 3,367.17 101.72% 3,310.133 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 21,238.87 21,238.87 100.82% 21,066.79

M3 $27,016.10 101.01% 26,746.15*HARAM 10330019 RAMPAS H=12, 240 kg/Cm², 60, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,351.19 2,680.36 101.72% 2,634.942 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,413.96 3,910.62 101.72% 3,844.363 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 21,238.87 21,238.87 100.82% 21,066.79

M3 $27,829.85 101.03% 27,546.09*HARAM 10330020 RAMPAS H=12, 240 kg/Cm², 60, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,351.19 2,680.36 101.72% 2,634.942 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,409.63 3,903.60 101.72% 3,837.473 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 21,238.87 21,238.87 100.82% 21,066.79

M3 $27,822.83 101.03% 27,539.20

*HAV 10350000 HORM. ARMADO VIGAS

*HAV 10350001 H. A. VIGA 20X40, 1:2:4, 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20, LIG. Y WINCHE:1 Acero 3/8" x 20' grado 40 + 10% desp. 1.502 qq 2,114.09 3,175.36 101.72% 3,121.562 Acero ¾" grado 40 + 10% desp. 2.226 qq 2,076.70 4,622.73 101.72% 4,544.403 M.O. acero 3.728 qq 243.24 906.80 100.00% 906.804 Madera bruta amer. (4 usos) 84.25 pt 35.70 3,007.73 101.74% 2,956.335 Clavos corrientes (5 lb. / 100 pie madera) 16.85 lb 30.43 512.75 101.71% 504.156 Clavos de acero (¼ lb / metro) 3.13 lb 53.10 166.20 101.72% 163.397 Alambre calibre #14 (¼ lb. / metro) 3.13 lb 34.64 108.42 101.70% 106.618 Encofrado tapas laterales 12.50 m 167.56 2,094.50 100.00% 2,094.509 Encofrado fondo 12.50 m 58.00 725.00 100.00% 725.0010 Desencofrado 12.50 m2 24.17 302.13 100.00% 302.1311 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 4,604.00 5,064.40 101.54% 4,987.39

M3 $20,686.02 101.34% 20,412.26*HAV 10350002 H. A. VIGA 20X40, 1:2:4, 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,351.19 3,531.49 101.72% 3,471.652 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,407.71 5,359.56 101.72% 5,268.763 M.O. acero 3.728 qq 366.08 1,364.75 100.00% 1,364.754 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,981.13 11,981.13 101.20% 11,839.50

M3 $22,236.93 101.33% 21,944.66*HAV 10350003 H. A. VIGA 25X50, 1:2:4, 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.967 qq 2,114.09 2,044.33 101.72% 2,009.692 Acero ¾" grado 40 + 10% desp. 1.899 qq 2,076.70 3,943.65 101.72% 3,876.833 M.O. acero 2.866 qq 243.24 697.13 100.00% 697.134 Madera bruta amer. (4 usos) 61.51 pt 35.70 2,195.91 101.74% 2,158.395 Clavos corrientes (5 lb. / 100 pie madera) 12.30 lb 30.43 374.29 101.70% 368.026 Clavos de acero (¼ lb / metro) 2.00 lb 53.10 106.20 101.72% 104.407 Alambre calibre #14 (¼ lb. / metro) 2.00 lb 34.64 69.28 101.70% 68.128 Encofrado tapas laterales 8.00 m 209.45 1,675.60 100.00% 1,675.609 Encofrado fondo 8.00 m 72.50 580.00 100.00% 580.0010 Desencofrado 10.00 m2 24.17 241.70 100.00% 241.7011 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 4,604.00 5,064.40 101.54% 4,987.39

M3 $16,992.49 101.34% 16,767.27*HAV 10350004 H. A. VIGA 25X50, 1:2:4, 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,351.19 2,273.60 101.72% 2,235.082 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,407.71 4,572.24 101.72% 4,494.783 M.O. acero 2.866 qq 366.08 1,049.19 100.00% 1,049.194 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 10,307.38 10,307.38 101.22% 10,183.62

M3 $18,202.41 101.33% 17,962.67*HAV 10350005 H. A. VIGA 30X60, 1:2:4, 40, 4 DE 1", 2 DE 3/8", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.776 qq 2,114.09 1,640.53 101.72% 1,612.742 Acero 1" grado 40 + 10% desp. 2.400 qq 2,058.81 4,941.14 101.72% 4,857.433 M.O. acero 3.176 qq 243.24 772.53 100.00% 772.534 Madera bruta amer. (4 usos) 48.02 pt 35.70 1,714.31 101.74% 1,685.025 Clavos corrientes (5 lb. / 100 pie madera) 9.60 lb 30.43 292.13 101.71% 287.236 Clavos de acero (¼ lb / metro) 1.39 lb 53.10 73.81 101.72% 72.567 Alambre calibre #14 (¼ lb. / metro) 1.39 lb 34.64 48.15 101.71% 47.348 Encofrado tapas laterales 5.56 m 251.34 1,397.45 100.00% 1,397.45

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 56

Page 59: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

9 Encofrado fondo 5.56 m 87.00 483.72 100.00% 483.7210 Desencofrado 8.34 m2 24.17 201.58 100.00% 201.5811 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 4,604.00 5,064.40 101.54% 4,987.39

M3 $16,629.75 101.37% 16,404.99*HAV 10350006 H. A. VIGA 30X60, 1:2:4, 60, 4 DE 1", 2 DE 3/8", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,351.19 1,824.52 101.72% 1,793.612 Acero 1" grado 60 + 10% desp. 2.400 qq 2,407.71 5,778.50 101.72% 5,680.613 M.O. acero 3.176 qq 366.08 1,162.67 100.00% 1,162.674 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 9,275.55 9,275.55 101.24% 9,162.29

M3 $18,041.24 101.36% 17,799.18*HAV 10350007 H. A. VIGA 40X80, 1:2:4, 40, 5 DE 1", 2 DE ½", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.752 qq 2,114.09 1,589.80 101.72% 1,562.862 Acero ½" x 20' grado 40 + 10% desp. 0.162 qq 2,121.47 343.68 101.73% 337.853 Acero 1" grado 40 + 10% desp. 1.689 qq 2,058.81 3,477.33 101.72% 3,418.424 M.O. acero 2.441 qq 243.24 593.75 100.00% 593.755 Madera bruta amer. (4 usos) 39.23 pt 35.70 1,400.51 101.74% 1,376.586 Clavos corrientes (5 lb. / 100 pie madera) 7.85 lb 30.43 238.88 101.71% 234.877 Clavos de acero (¼ lb / metro) 0.78 lb 53.10 41.42 101.72% 40.728 Alambre calibre #14 (¼ lb. / metro) 0.78 lb 34.64 27.02 101.69% 26.579 Encofrado tapas laterales 3.13 m 335.12 1,048.93 100.00% 1,048.9310 Encofrado fondo 3.13 m 116.00 363.08 100.00% 363.0811 Desencofrado 6.26 m2 24.17 151.30 100.00% 151.3012 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 4,604.00 5,064.40 101.54% 4,987.39

M3 $14,340.10 101.40% 14,142.32*HAV 10350008 H. A. VIGA 40X80, 1:2:4, 40, 5 DE 1", 2 DE ½" X 25', 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.752 qq 2,114.09 1,589.80 101.72% 1,562.862 Acero ½" x 25' grado 40 + 10% desp. 0.162 qq 2,078.50 336.72 101.73% 331.013 Partidas comunes de la analizada completa anterior (3-12) 1.00 u 12,406.62 12,406.62 101.35% 12,241.61

M3 $14,333.14 101.40% 14,135.48*HAV 10350009 H. A. VIGA 40X80, 1:2:4, 60, 5 DE 1", 2 DE ½", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,413.96 391.06 101.72% 384.443 Acero 1" grado 60 + 10% desp. 1.689 qq 2,382.94 4,024.79 101.72% 3,956.604 M.O. acero 2.441 qq 366.08 893.60 100.00% 893.605 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 8,335.54 8,335.54 101.29% 8,229.44

M3 $15,413.08 101.39% 15,202.22*HAV 10350010 H. A. VIGA 20X40, 180 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.502 qq 2,114.09 3,175.36 101.72% 3,121.562 Acero ¾" grado 40 + 10% desp. 2.226 qq 2,076.70 4,622.73 101.72% 4,544.403 M.O. acero 3.728 qq 243.24 906.80 100.00% 906.804 Madera bruta amer. (4 usos) 84.25 pt 35.70 3,007.73 101.74% 2,956.335 Clavos corrientes (5 lb. / 100 pie madera) 16.85 lb 30.43 512.75 101.71% 504.156 Clavos de acero (¼ lb / metro) 3.13 lb 53.10 166.20 101.72% 163.397 Alambre calibre #14 (¼ lb. / metro) 3.13 lb 34.64 108.42 101.70% 106.618 Encofrado tapas laterales 12.50 m 167.56 2,094.50 100.00% 2,094.509 Encofrado fondo 12.50 m 58.00 725.00 100.00% 725.0010 Desencofrado 12.50 m2 24.17 302.13 100.00% 302.1311 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $22,864.46 101.42% 22,544.95*HAV 10350011 H. A. VIGA 20X40, 180 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 7,798.09 7,798.09 101.72% 7,665.962 M.O. acero 3.728 qq 386.61 1,441.28 100.00% 1,441.283 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 14,159.57 14,159.57 101.34% 13,972.19

M3 $23,398.94 101.38% 23,079.43*HAV 10350012 H. A. VIGA 20X40, 180 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,351.19 3,531.49 101.72% 3,471.652 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,407.71 5,359.56 101.72% 5,268.763 M.O. acero 3.728 qq 366.08 1,364.75 100.00% 1,364.754 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 14,159.57 14,159.57 101.34% 13,972.19

M3 $24,415.37 101.40% 24,077.35*HAV 10350013 H. A. VIGA 20X40, 180 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,351.19 3,531.49 101.72% 3,471.652 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,407.71 5,359.56 101.72% 5,268.763 M.O. acero 3.728 qq 386.61 1,441.28 100.00% 1,441.284 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 14,159.57 14,159.57 101.34% 13,972.19

M3 $24,491.90 101.40% 24,153.88*HAV 10350014 H. A. VIGA 25X50, 180 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.967 qq 2,114.09 2,044.33 101.72% 2,009.692 Acero ¾" grado 40 + 10% desp. 1.899 qq 2,076.70 3,943.65 101.72% 3,876.833 M.O. acero 2.866 qq 243.24 697.13 100.00% 697.134 Madera bruta amer. (4 usos) 61.51 pt 35.70 2,195.91 101.74% 2,158.395 Clavos corrientes (5 lb. / 100 pie madera) 12.30 lb 30.43 374.29 101.70% 368.026 Clavos de acero (¼ lb / metro) 2.00 lb 53.10 106.20 101.72% 104.407 Alambre calibre #14 (¼ lb. / metro) 2.00 lb 34.64 69.28 101.70% 68.128 Encofrado tapas laterales 8.00 m 209.45 1,675.60 100.00% 1,675.609 Encofrado fondo 8.00 m 72.50 580.00 100.00% 580.0010 Desencofrado 10.00 m2 24.17 241.70 100.00% 241.7011 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $19,170.93 101.43% 18,899.96*HAV 10350015 H. A. VIGA 20X50, 180 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 5,987.98 5,987.98 101.72% 5,886.522 M.O. acero 2.866 qq 386.61 1,108.02 100.00% 1,108.023 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,485.82 12,485.82 101.38% 12,316.31

M3 $19,581.82 101.40% 19,310.85*HAV 10350016 H. A. VIGA 20X50, 180 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,351.19 2,273.60 101.72% 2,235.082 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,407.71 4,572.24 101.72% 4,494.783 M.O. acero 2.866 qq 366.08 1,049.19 100.00% 1,049.194 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,485.82 12,485.82 101.38% 12,316.31

M3 $20,380.85 101.42% 20,095.36*HAV 10350017 H. A. VIGA 20X50, 180 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,351.19 2,273.60 101.72% 2,235.082 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,407.71 4,572.24 101.72% 4,494.783 M.O. acero 2.866 qq 386.61 1,108.02 100.00% 1,108.02

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 57

Page 60: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

4 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,485.82 12,485.82 101.38% 12,316.31M3 $20,439.68 101.42% 20,154.19

*HAV 10350018 H. A. VIGA 30X60, 180 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25:1 Acero 3/8" x 20' grado 40 + 10% desp. 0.776 qq 2,114.09 1,640.53 101.72% 1,612.742 Acero 1" grado 40 + 10% desp. 2.400 qq 2,058.81 4,941.14 101.72% 4,857.433 M.O. acero 3.176 qq 243.24 772.53 100.00% 772.534 Madera bruta amer. (4 usos) 48.02 pt 35.70 1,714.31 101.74% 1,685.025 Clavos corrientes (5 lb. / 100 pie madera) 9.60 lb 30.43 292.13 101.71% 287.236 Clavos de acero (¼ lb / metro) 1.39 lb 53.10 73.81 101.72% 72.567 Alambre calibre #14 (¼ lb. / metro) 1.39 lb 34.64 48.15 101.71% 47.348 Encofrado tapas laterales 5.56 m 251.34 1,397.45 100.00% 1,397.459 Encofrado fondo 5.56 m 87.00 483.72 100.00% 483.7210 Desencofrado 8.34 m2 24.17 201.58 100.00% 201.5811 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $18,808.19 101.46% 18,537.68*HAV 10350019 H. A. VIGA 30X60, 180 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 6,581.67 6,581.67 101.72% 6,470.172 M.O. acero 3.176 qq 386.61 1,227.87 100.00% 1,227.873 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,453.99 11,453.99 101.41% 11,294.98

M3 $19,263.53 101.42% 18,993.02*HAV 10350020 H. A. VIGA 30X60, 180 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,351.19 1,824.52 101.72% 1,793.612 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,407.71 5,778.50 101.72% 5,680.613 M.O. acero 3.176 qq 366.08 1,162.67 100.00% 1,162.674 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,453.99 11,453.99 101.41% 11,294.98

M3 $20,219.68 101.44% 19,931.87*HAV 10350021 H. A. VIGA 30X60, 180 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,351.19 1,824.52 101.72% 1,793.612 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,407.71 5,778.50 101.72% 5,680.613 M.O. acero 3.176 qq 386.61 1,227.87 100.00% 1,227.874 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,453.99 11,453.99 101.41% 11,294.98

M3 $20,284.88 101.44% 19,997.07*HAV 10350022 H. A. VIGA 40X80, 180 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.752 qq 2,114.09 1,589.80 101.72% 1,562.862 Acero ½" x 20' grado 40 + 10% desp. 0.162 qq 2,121.47 343.68 101.73% 337.853 Acero 1" grado 40 + 10% desp. 1.689 qq 2,058.81 3,477.33 101.72% 3,418.424 M.O. acero 2.441 qq 243.24 593.75 100.00% 593.755 Madera bruta amer. (4 usos) 39.23 pt 35.70 1,400.51 101.74% 1,376.586 Clavos corrientes (5 lb. / 100 pie madera) 7.85 lb 30.43 238.88 101.71% 234.877 Clavos de acero (¼ lb / metro) 0.78 lb 53.10 41.42 101.72% 40.728 Alambre calibre #14 (¼ lb. / metro) 0.78 lb 34.64 27.02 101.69% 26.579 Encofrado tapas laterales 3.13 m 335.12 1,048.93 100.00% 1,048.9310 Encofrado fondo 3.13 m 116.00 363.08 100.00% 363.0811 Desencofrado 6.26 m2 24.17 151.30 100.00% 151.3012 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $16,518.54 101.50% 16,275.01*HAV 10350023 H. A. VIGA 40X80, 180 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-3) 1.000 u 5,410.81 5,410.81 101.72% 5,319.132 M.O. acero 2.441 qq 386.61 943.72 100.00% 943.723 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,513.98 10,513.98 101.47% 10,362.13

M3 $16,868.51 101.46% 16,624.98*HAV 10350024 H. A. VIGA 40X80, 180 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,413.96 391.06 101.72% 384.443 Acero 1" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 366.08 893.60 100.00% 893.605 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,513.98 10,513.98 101.47% 10,362.13

M3 $17,633.35 101.48% 17,376.04*HAV 10350025 H. A. VIGA 40X80, 180 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,413.96 391.06 101.72% 384.443 Acero 1" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 386.61 943.72 100.00% 943.725 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,513.98 10,513.98 101.47% 10,362.13

M3 $17,683.47 101.48% 17,426.16*HAV 10350026 H. A. VIGA 40X80, 180 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,409.63 390.36 101.72% 383.753 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 366.08 893.60 100.00% 893.605 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,513.98 10,513.98 101.47% 10,362.13

M3 $17,632.65 101.48% 17,375.35*HAV 10350027 H. A. VIGA 40X80, 180 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,409.63 390.36 101.72% 383.753 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 386.61 943.72 100.00% 943.725 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,513.98 10,513.98 101.47% 10,362.13

M3 $17,682.77 101.48% 17,425.47*HAV 10350028 H. A. VIGA 20X40, 210 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.502 qq 2,114.09 3,175.36 101.72% 3,121.562 Acero ¾" grado 40 + 10% desp. 2.226 qq 2,076.70 4,622.73 101.72% 4,544.403 M.O. acero 3.728 qq 243.24 906.80 100.00% 906.804 Madera bruta amer. (4 usos) 84.25 pt 35.70 3,007.73 101.74% 2,956.335 Clavos corrientes (5 lb. / 100 pie madera) 16.85 lb 30.43 512.75 101.71% 504.156 Clavos de acero (¼ lb / metro) 3.13 lb 53.10 166.20 101.72% 163.397 Alambre calibre #14 (¼ lb. / metro) 3.13 lb 34.64 108.42 101.70% 106.618 Encofrado tapas laterales 12.50 m 167.56 2,094.50 100.00% 2,094.509 Encofrado fondo 12.50 m 58.00 725.00 100.00% 725.0010 Desencofrado 12.50 m2 24.17 302.13 100.00% 302.1311 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $23,072.14 101.42% 22,749.11*HAV 10350029 H. A. VIGA 20X40, 210 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 7,798.09 7,798.09 101.72% 7,665.96PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 58

Page 61: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

2 M.O. acero 3.728 qq 386.61 1,441.28 100.00% 1,441.283 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 14,367.25 14,367.25 101.35% 14,176.35

M3 $23,606.62 101.39% 23,283.59*HAV 10350030 H. A. VIGA 20X40, 210 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,351.19 3,531.49 101.72% 3,471.652 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,407.71 5,359.56 101.72% 5,268.763 M.O. acero 3.728 qq 366.08 1,364.75 100.00% 1,364.754 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 14,367.25 14,367.25 101.35% 14,176.35

M3 $24,623.05 101.41% 24,281.51*HAV 10350031 H. A. VIGA 20X40, 210 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,351.19 3,531.49 101.72% 3,471.652 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,407.71 5,359.56 101.72% 5,268.763 M.O. acero 3.728 qq 386.61 1,441.28 100.00% 1,441.284 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 14,367.25 14,367.25 101.35% 14,176.35

M3 $24,699.58 101.40% 24,358.04*HAV 10350032 H. A. VIGA 25X50, 210 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.967 qq 2,114.09 2,044.33 101.72% 2,009.692 Acero ¾" grado 40 + 10% desp. 1.899 qq 2,076.70 3,943.65 101.72% 3,876.833 M.O. acero 2.866 qq 243.24 697.13 100.00% 697.134 Madera bruta amer. (4 usos) 61.51 pt 35.70 2,195.91 101.74% 2,158.395 Clavos corrientes (5 lb. / 100 pie madera) 12.30 lb 30.43 374.29 101.70% 368.026 Clavos de acero (¼ lb / metro) 2.00 lb 53.10 106.20 101.72% 104.407 Alambre calibre #14 (¼ lb. / metro) 2.00 lb 34.64 69.28 101.70% 68.128 Encofrado tapas laterales 8.00 m 209.45 1,675.60 100.00% 1,675.609 Encofrado fondo 8.00 m 72.50 580.00 100.00% 580.0010 Desencofrado 10.00 m2 24.17 241.70 100.00% 241.7011 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $19,378.61 101.44% 19,104.12*HAV 10350033 H. A. VIGA 25X50, 210 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 5,987.98 5,987.98 101.72% 5,886.522 M.O. acero 2.866 qq 386.61 1,108.02 100.00% 1,108.023 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,693.50 12,693.50 101.38% 12,520.47

M3 $19,789.50 101.41% 19,515.01*HAV 10350034 H. A. VIGA 25X50, 210 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,351.19 2,273.60 101.72% 2,235.082 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,407.71 4,572.24 101.72% 4,494.783 M.O. acero 2.866 qq 366.08 1,049.19 100.00% 1,049.194 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,693.50 12,693.50 101.38% 12,520.47

M3 $20,588.53 101.42% 20,299.52*HAV 10350035 H. A. VIGA 25X50, 210 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,351.19 2,273.60 101.72% 2,235.082 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,407.71 4,572.24 101.72% 4,494.783 M.O. acero 2.866 qq 386.61 1,108.02 100.00% 1,108.024 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,693.50 12,693.50 101.38% 12,520.47

M3 $20,647.36 101.42% 20,358.35*HAV 10350036 H. A. VIGA 30X60, 210 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.776 qq 2,114.09 1,640.53 101.72% 1,612.742 Acero 1" grado 40 + 10% desp. 2.400 qq 2,058.81 4,941.14 101.72% 4,857.433 M.O. acero 3.176 qq 243.24 772.53 100.00% 772.534 Madera bruta amer. (4 usos) 48.02 pt 35.70 1,714.31 101.74% 1,685.025 Clavos corrientes (5 lb. / 100 pie madera) 9.60 lb 30.43 292.13 101.71% 287.236 Clavos de acero (¼ lb / metro) 1.39 lb 53.10 73.81 101.72% 72.567 Alambre calibre #14 (¼ lb. / metro) 1.39 lb 34.64 48.15 101.71% 47.348 Encofrado tapas laterales 5.56 m 251.34 1,397.45 100.00% 1,397.459 Encofrado fondo 5.56 m 87.00 483.72 100.00% 483.7210 Desencofrado 8.34 m2 24.17 201.58 100.00% 201.5811 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $19,015.87 101.46% 18,741.84*HAV 10350037 H. A. VIGA 30X60, 210 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 6,581.67 6,581.67 101.72% 6,470.172 M.O. acero 3.176 qq 386.61 1,227.87 100.00% 1,227.873 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,661.67 11,661.67 101.41% 11,499.14

M3 $19,471.21 101.43% 19,197.18*HAV 10350038 H. A. VIGA 30X60, 210 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,351.19 1,824.52 101.72% 1,793.612 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,407.71 5,778.50 101.72% 5,680.613 M.O. acero 3.176 qq 366.08 1,162.67 100.00% 1,162.674 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,661.67 11,661.67 101.41% 11,499.14

M3 $20,427.36 101.45% 20,136.03*HAV 10350039 H. A. VIGA 30X60, 210 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,351.19 1,824.52 101.72% 1,793.612 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,407.71 5,778.50 101.72% 5,680.613 M.O. acero 3.176 qq 386.61 1,227.87 100.00% 1,227.874 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,661.67 11,661.67 101.41% 11,499.14

M3 $20,492.56 101.44% 20,201.23*HAV 10350040 H. A. VIGA 40X80, 210 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.752 qq 2,114.09 1,589.80 101.72% 1,562.862 Acero ½" x 20' grado 40 + 10% desp. 0.162 qq 2,121.47 343.68 101.73% 337.853 Acero 1" grado 40 + 10% desp. 1.689 qq 2,058.81 3,477.33 101.72% 3,418.424 M.O. acero 2.441 qq 243.24 593.75 100.00% 593.755 Madera bruta amer. (4 usos) 39.23 pt 35.70 1,400.51 101.74% 1,376.586 Clavos corrientes (5 lb. / 100 pie madera) 7.85 lb 30.43 238.88 101.71% 234.877 Clavos de acero (¼ lb / metro) 0.78 lb 53.10 41.42 101.72% 40.728 Alambre calibre #14 (¼ lb. / metro) 0.78 lb 34.64 27.02 101.69% 26.579 Encofrado tapas laterales 3.13 m 335.12 1,048.93 100.00% 1,048.9310 Encofrado fondo 3.13 m 116.00 363.08 100.00% 363.0811 Desencofrado 6.26 m2 24.17 151.30 100.00% 151.3012 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $16,726.22 101.50% 16,479.17*HAV 10350041 H. A. VIGA 40X80, 210 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-3) 1.000 u 5,410.81 5,410.81 101.72% 5,319.132 M.O. acero 2.441 qq 386.61 943.72 100.00% 943.723 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,721.66 10,721.66 101.47% 10,566.29

M3 $17,076.19 101.47% 16,829.14PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 59

Page 62: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012*HAV 10350042 H. A. VIGA 40X80, 210 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,413.96 391.06 101.72% 384.443 Acero 1" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 366.08 893.60 100.00% 893.605 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,721.66 10,721.66 101.47% 10,566.29

M3 $17,841.03 101.48% 17,580.20*HAV 10350043 H. A. VIGA 40X80, 210 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,413.96 391.06 101.72% 384.443 Acero 1" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 386.61 943.72 100.00% 943.725 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,721.66 10,721.66 101.47% 10,566.29

M3 $17,891.15 101.48% 17,630.32*HAV 10350044 H. A. VIGA 40X80, 210 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,409.63 390.36 101.72% 383.753 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 366.08 893.60 100.00% 893.605 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,721.66 10,721.66 101.47% 10,566.29

M3 $17,840.33 101.48% 17,579.51*HAV 10350045 H. A. VIGA 40X80, 210 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,409.63 390.36 101.72% 383.753 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 386.61 943.72 100.00% 943.725 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,721.66 10,721.66 101.47% 10,566.29

M3 $17,890.45 101.48% 17,629.63*HAV 10350046 H. A. VIGA 20X40, 240 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.502 qq 2,114.09 3,175.36 101.72% 3,121.562 Acero ¾" grado 40 + 10% desp. 2.226 qq 2,076.70 4,622.73 101.72% 4,544.403 M.O. acero 3.728 qq 243.24 906.80 100.00% 906.804 Madera bruta amer. (4 usos) 84.25 pt 35.70 3,007.73 101.74% 2,956.335 Clavos corrientes (5 lb. / 100 pie madera) 16.85 lb 30.43 512.75 101.71% 504.156 Clavos de acero (¼ lb / metro) 3.13 lb 53.10 166.20 101.72% 163.397 Alambre calibre #14 (¼ lb. / metro) 3.13 lb 34.64 108.42 101.70% 106.618 Encofrado tapas laterales 12.50 m 167.56 2,094.50 100.00% 2,094.509 Encofrado fondo 12.50 m 58.00 725.00 100.00% 725.0010 Desencofrado 12.50 m2 24.17 302.13 100.00% 302.1311 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $23,604.32 101.43% 23,272.27*HAV 10350047 H. A. VIGA 20X40, 240 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 7,798.09 7,798.09 101.72% 7,665.962 M.O. acero 3.728 qq 386.61 1,441.28 100.00% 1,441.283 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 14,899.43 14,899.43 101.36% 14,699.51

M3 $24,138.80 101.39% 23,806.75*HAV 10350048 H. A. VIGA 20X40, 240 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,351.19 3,531.49 101.72% 3,471.652 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,407.71 5,359.56 101.72% 5,268.763 M.O. acero 3.728 qq 366.08 1,364.75 100.00% 1,364.754 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 14,899.43 14,899.43 101.36% 14,699.51

M3 $25,155.23 101.41% 24,804.67*HAV 10350049 H. A. VIGA 20X40, 240 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,351.19 3,531.49 101.72% 3,471.652 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,407.71 5,359.56 101.72% 5,268.763 M.O. acero 3.728 qq 386.61 1,441.28 100.00% 1,441.284 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 14,899.43 14,899.43 101.36% 14,699.51

M3 $25,231.76 101.41% 24,881.20*HAV 10350050 H. A. VIGA 25X50, 240 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.967 qq 2,114.09 2,044.33 101.72% 2,009.692 Acero ¾" grado 40 + 10% desp. 1.899 qq 2,076.70 3,943.65 101.72% 3,876.833 M.O. acero 2.866 qq 243.24 697.13 100.00% 697.134 Madera bruta amer. (4 usos) 61.51 pt 35.70 2,195.91 101.74% 2,158.395 Clavos corrientes (5 lb. / 100 pie madera) 12.30 lb 30.43 374.29 101.70% 368.026 Clavos de acero (¼ lb / metro) 2.00 lb 53.10 106.20 101.72% 104.407 Alambre calibre #14 (¼ lb. / metro) 2.00 lb 34.64 69.28 101.70% 68.128 Encofrado tapas laterales 8.00 m 209.45 1,675.60 100.00% 1,675.609 Encofrado fondo 8.00 m 72.50 580.00 100.00% 580.0010 Desencofrado 10.00 m2 24.17 241.70 100.00% 241.7011 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $19,910.79 101.44% 19,627.28*HAV 10350051 H. A. VIGA 25X50, 240 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 5,987.98 5,987.98 101.72% 5,886.522 M.O. acero 2.866 qq 386.61 1,108.02 100.00% 1,108.023 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,225.68 13,225.68 101.40% 13,043.63

M3 $20,321.68 101.41% 20,038.17*HAV 10350052 H. A. VIGA 25X50, 240 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,351.19 2,273.60 101.72% 2,235.082 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,407.71 4,572.24 101.72% 4,494.783 M.O. acero 2.866 qq 366.08 1,049.19 100.00% 1,049.194 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,225.68 13,225.68 101.40% 13,043.63

M3 $21,120.71 101.43% 20,822.68*HAV 10350053 H. A. VIGA 25X50, 240 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,351.19 2,273.60 101.72% 2,235.082 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,407.71 4,572.24 101.72% 4,494.783 M.O. acero 2.866 qq 386.61 1,768.09 101.72% 1,738.144 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 13,225.68 13,225.68 101.40% 13,043.63

M3 $21,839.61 101.52% 21,511.63*HAV 10350054 H. A. VIGA 30X60, 240 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.776 qq 2,114.09 1,640.53 101.72% 1,612.742 Acero 1" grado 40 + 10% desp. 2.400 qq 2,058.81 4,941.14 101.72% 4,857.433 M.O. acero 3.176 qq 243.24 772.53 100.00% 772.534 Madera bruta amer. (4 usos) 48.02 pt 35.70 1,714.31 101.74% 1,685.025 Clavos corrientes (5 lb. / 100 pie madera) 9.60 lb 30.43 292.13 101.71% 287.23

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 60

Page 63: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

6 Clavos de acero (¼ lb / metro) 1.39 lb 53.10 73.81 101.72% 72.567 Alambre calibre #14 (¼ lb. / metro) 1.39 lb 34.64 48.15 101.71% 47.348 Encofrado tapas laterales 5.56 m 251.34 1,397.45 100.00% 1,397.459 Encofrado fondo 5.56 m 87.00 483.72 100.00% 483.7210 Desencofrado 8.34 m2 24.17 201.58 100.00% 201.5811 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $19,548.05 101.47% 19,265.00*HAV 10350055 H. A. VIGA 30X60, 240 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 6,581.67 6,581.67 101.72% 6,470.172 M.O. acero 3.176 qq 386.61 1,227.87 100.00% 1,227.873 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,193.85 12,193.85 101.43% 12,022.30

M3 $20,003.39 101.44% 19,720.34*HAV 10350056 H. A. VIGA 30X60, 240 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,351.19 1,824.52 101.72% 1,793.612 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,407.71 5,778.50 101.72% 5,680.613 M.O. acero 3.176 qq 366.08 1,162.67 100.00% 1,162.674 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,193.85 12,193.85 101.43% 12,022.30

M3 $20,959.54 101.45% 20,659.19*HAV 10350057 H. A. VIGA 30X60, 240 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,351.19 1,824.52 101.72% 1,793.612 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,407.71 5,778.50 101.72% 5,680.613 M.O. acero 3.176 qq 386.61 1,227.87 100.00% 1,227.874 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,193.85 12,193.85 101.43% 12,022.30

M3 $21,024.74 101.45% 20,724.39*HAV 10350058 H. A. VIGA 40X80, 240 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.752 qq 2,114.09 1,589.80 101.72% 1,562.862 Acero ½" x 20' grado 40 + 10% desp. 0.162 qq 2,121.47 343.68 101.73% 337.853 Acero 1" grado 40 + 10% desp. 1.689 qq 2,058.81 3,477.33 101.72% 3,418.424 M.O. acero 2.441 qq 243.24 593.75 100.00% 593.755 Madera bruta amer. (4 usos) 39.23 pt 35.70 1,400.51 101.74% 1,376.586 Clavos corrientes (5 lb. / 100 pie madera) 7.85 lb 30.43 238.88 101.71% 234.877 Clavos de acero (¼ lb / metro) 0.78 lb 53.10 41.42 101.72% 40.728 Alambre calibre #14 (¼ lb. / metro) 0.78 lb 34.64 27.02 101.69% 26.579 Encofrado tapas laterales 3.13 m 335.12 1,048.93 100.00% 1,048.9310 Encofrado fondo 3.13 m 116.00 363.08 100.00% 363.0811 Desencofrado 6.26 m2 24.17 151.30 100.00% 151.3012 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $17,258.40 101.51% 17,002.33*HAV 10350059 H. A. VIGA 40X80, 240 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-3) 1.000 u 5,410.81 5,410.81 101.72% 5,319.132 M.O. acero 2.441 qq 386.61 943.72 100.00% 943.723 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,253.84 11,253.84 101.48% 11,089.45

M3 $17,608.37 101.48% 17,352.30*HAV 10350060 H. A. VIGA 40X80, 240 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,413.96 391.06 101.72% 384.443 Acero 1" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 366.08 893.60 100.00% 893.605 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,253.84 11,253.84 101.48% 11,089.45

M3 $18,373.21 101.49% 18,103.36*HAV 10350061 H. A. VIGA 40X80, 240 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,413.96 391.06 101.72% 384.443 Acero 1" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 386.61 943.72 100.00% 943.725 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,253.84 11,253.84 101.48% 11,089.45

M3 $18,423.33 101.49% 18,153.48*HAV 10350062 H. A. VIGA 40X80, 240 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,409.63 390.36 101.72% 383.753 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 366.08 893.60 100.00% 893.605 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,253.84 11,253.84 101.48% 11,089.45

M3 $18,372.51 101.49% 18,102.67*HAV 10350063 H. A. VIGA 40X80, 240 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,351.19 1,768.09 101.72% 1,738.142 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,409.63 390.36 101.72% 383.753 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,407.71 4,066.62 101.72% 3,997.734 M.O. acero 2.441 qq 386.61 943.72 100.00% 943.725 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,253.84 11,253.84 101.48% 11,089.45

M3 $18,422.63 101.49% 18,152.79

*HAVA 10370000 HORM. ARMADO VIGAS AMARRE

*HAVA 10370001 VIGA AMARRE 15x20, 1:2:4, 4 DE 3/8" grado 40, ¼" A 20, LIG.:1 Acero ¼" + 10% desp. 0.779 qq 1,519.73 1,183.87 101.72% 1,163.822 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 2,114.09 4,014.66 101.72% 3,946.633 M.O. acero 33.33 m 81.08 2,702.40 100.00% 2,702.404 Madera bruta amer. (4 usos) 97.97 pt 35.70 3,497.53 101.74% 3,437.775 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 30.43 596.12 101.70% 586.136 Clavos de acero (¼ lb / metro) 8.33 lb 53.10 442.32 101.72% 434.837 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 34.64 288.55 101.70% 283.728 Confección e instalación de madera 33.33 m 120.83 4,027.26 100.00% 4,027.269 Desencofrado 13.33 m2 24.17 322.19 100.00% 322.1910 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $21,949.55 101.14% 21,703.21*HAVA 10370002 VIGA AMARRE 15x20, 1:2:4, 4 DE 3/8" grado 40, ¼" A 20 A MANO:

1 Acero ¼" + 10% desp. 0.779 qq 1,519.73 1,183.87 101.72% 1,163.822 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 2,114.09 4,014.66 101.72% 3,946.633 M.O. acero 33.33 m 81.08 2,702.40 100.00% 2,702.404 Madera bruta amer. (4 usos) 97.97 pt 35.70 3,497.53 101.74% 3,437.775 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 30.43 596.12 101.70% 586.136 Clavos de acero (¼ lb / metro) 8.33 lb 53.10 442.32 101.72% 434.837 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 34.64 288.55 101.70% 283.72

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 61

Page 64: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

8 Confección e instalación de madera 33.33 m 120.83 4,027.26 100.00% 4,027.269 Desencofrado 13.33 m2 24.17 322.19 100.00% 322.1910 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $22,509.42 101.13% 22,257.86*HAVA 10370003 VIGA AMARRE 20x20, 1:2:4, 4 DE 3/8", 3/8" A .20 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 2.781 qq 2,114.09 5,879.28 101.72% 5,779.672 M.O. acero 25.00 m 81.08 2,027.00 100.00% 2,027.003 Madera bruta amer. (4 usos) 97.97 pt 35.70 3,497.53 101.74% 3,437.774 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 30.43 596.12 101.70% 586.135 Clavos de acero (¼ lb / metro) 6.25 lb 53.10 331.88 101.73% 326.256 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 34.64 216.50 101.70% 212.887 Confección e instalación de madera 25.00 m 120.83 3,020.75 100.00% 3,020.758 Desencofrado 10.00 m2 24.17 241.70 100.00% 241.709 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 4,431.50 4,874.65 101.59% 4,798.46

M3 $20,685.41 101.25% 20,430.61*HAVA 10370004 VIGA AMARRE 20x20, 1:2:4, 4 DE 3/8", 3/8" A .20 grado 40 A MANO:

1 Acero 3/8" x 20' grado 40 + 10% desp. 2.781 qq 2,114.09 5,879.28 101.72% 5,779.672 M.O. acero 25.00 m 81.08 2,027.00 100.00% 2,027.003 Madera bruta amer. (4 usos) 97.97 pt 35.70 3,497.53 101.74% 3,437.774 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 30.43 596.12 101.70% 586.135 Clavos de acero (¼ lb / metro) 6.25 lb 53.10 331.88 101.73% 326.256 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 34.64 216.50 101.70% 212.887 Confección e instalación de madera 25.00 m 120.83 3,020.75 100.00% 3,020.758 Desencofrado 10.00 m2 24.17 241.70 100.00% 241.709 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 4,940.47 5,434.52 101.52% 5,353.11

M3 $21,245.28 101.24% 20,985.26

*HAVUE 10390000 HORM. ARMADO VUELOS (NO CONTINUA DEL FALSO PISO)

*HAVUE 10390001 VUELOS .40x.10, 1:2:4, 40, 3/8" A .20 + 2 DE 3/8", LIG. Y WINCHE:1 Acero 3/8" x 20' grado 40 + 10% desp. 1.857 qq 2,114.09 3,925.87 101.72% 3,859.352 M.O. acero 1.857 qq 243.24 451.70 100.00% 451.703 Subida acero 1.857 qq 24.32 45.16 100.00% 45.164 Madera bruta amer. (4 usos) 106.34 pt 35.70 3,796.34 101.74% 3,731.475 Clavos corrientes (5 lb. / 100 pie madera) 21.27 lb 30.43 647.25 101.70% 636.406 Clavos de acero (¼ lb / metro) 6.25 lb 53.10 331.88 101.73% 326.257 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 34.64 216.50 101.70% 212.888 Confección e instalación de madera 25.00 m 167.57 4,189.25 100.00% 4,189.259 Desencofrado 10.00 m2 25.78 257.80 100.00% 257.8010 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 4,604.00 5,064.40 101.54% 4,987.39

M3 $18,926.15 101.22% 18,697.65*HAVUE 10390002 VUELOS .40x.10, 1:2:4, 40, 3/8" x 25' A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.857 qq 2,072.20 3,848.08 101.72% 3,782.882 Partidas comunes de la analizada completa anterior (2-10) 1.00 u 15,000.28 15,000.28 101.09% 14,838.30

M3 $18,848.36 101.22% 18,621.18*HAVUE 10390003 VUELOS .40x.10, 1:2:4, 60, 3/8" A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.857 qq 2,351.19 4,366.16 101.72% 4,292.182 M.O. acero 1.857 qq 366.08 679.81 100.00% 679.813 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 14,548.58 14,548.58 101.13% 14,386.60

M3 $19,594.55 101.22% 19,358.59*HAVUE 10390004 VUELOS .40x.10, 1:2:4, 60, 3/8" x 25' A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.857 qq 2,432.17 4,516.54 101.72% 4,440.012 M.O. acero 1.857 qq 366.08 679.81 100.00% 679.813 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 14,548.58 14,548.58 101.13% 14,386.60

M3 $19,744.93 101.22% 19,506.42*HAVUE 10390005 VUELOS .40x.12, 1:2:4, 40, 3/8" A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.548 qq 2,114.09 3,272.61 101.72% 3,217.162 M.O. acero 1.548 qq 243.24 376.54 100.00% 376.543 Subida acero 1.548 qq 24.32 37.65 100.00% 37.654 Madera bruta amer. (4 usos) 90.62 pt 35.70 3,235.13 101.74% 3,179.865 Clavos corrientes (5 lb. / 100 pie madera) 18.12 lb 30.43 551.39 101.70% 542.156 Clavos de acero (¼ lb / metro) 5.21 lb 53.10 276.65 101.72% 271.967 Alambre calibre #14 (¼ lb. / metro) 5.21 lb 34.64 180.47 101.70% 177.458 Confección e instalación de madera 20.83 m 167.57 3,490.48 100.00% 3,490.489 Desencofrado 8.33 m2 25.78 214.80 100.00% 214.8010 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 4,604.00 5,064.40 101.54% 4,987.39

M3 $16,700.12 101.24% 16,495.44*HAVUE 10390006 VUELOS .40x.12, 1:2:4, 40, 3/8" x 25' A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.548 qq 2,072.20 3,207.77 101.72% 3,153.422 Partidas comunes de la analizada completa anterior (2-10) 1.00 u 13,427.51 13,427.51 101.12% 13,278.28

M3 $16,635.28 101.24% 16,431.70*HAVUE 10390007 VUELOS .40x.12, 1:2:4, 60, 3/8" A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.548 qq 2,351.19 3,639.64 101.72% 3,577.972 M.O. acero 1.548 qq 366.08 566.69 100.00% 566.693 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 13,050.97 13,050.97 101.16% 12,901.74

M3 $17,257.30 101.24% 17,046.40*HAVUE 10390008 VUELOS .40x.12, 1:2:4, 60, 3/8" x 25' A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.548 qq 2,432.17 3,765.00 101.72% 3,701.212 M.O. acero 1.548 qq 366.08 566.69 100.00% 566.693 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 13,050.97 13,050.97 101.16% 12,901.74

M3 $17,382.66 101.24% 17,169.64*HAVUE 10390009 VUELOS .40x.10, 180 kg/Cm², 40, 3/8" A .20 + 2 DE 3/8" :

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.857 qq 2,114.09 3,925.87 101.72% 3,859.352 M.O. acero 1.857 qq 243.24 451.70 100.00% 451.703 Subida acero 1.857 qq 24.32 45.16 100.00% 45.164 Madera bruta amer. (4 usos) 106.34 pt 35.70 3,796.34 101.74% 3,731.475 Clavos corrientes (5 lb. / 100 pie madera) 21.27 lb 30.43 647.25 101.70% 636.406 Clavos de acero (¼ lb / metro) 6.25 lb 53.10 331.88 101.73% 326.257 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 34.64 216.50 101.70% 212.888 Confección e instalación de madera 25.00 m 167.57 4,189.25 100.00% 4,189.259 Desencofrado 10.00 m2 25.78 257.80 100.00% 257.8010 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $21,104.59 101.32% 20,830.34

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 62

Page 65: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

*HAVUE 10390010 VUELOS .40x.10, 180 kg/Cm², 40, 3/8" x 25' A .20 + 2 DE 3/8":1 Acero 3/8" x 25' grado 40 + 10% desp. 1.857 qq 2,072.20 3,848.08 101.72% 3,782.882 Partidas comunes de la analizada completa anterior (2-10) 1.00 u 17,178.72 17,178.72 101.22% 16,970.99

M3 $21,026.80 101.32% 20,753.87*HAVUE 10390011 VUELOS .40x.10, 180 kg/Cm², 60, 3/8" A .20 + 2 DE 3/8":

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.857 qq 2,351.19 4,366.16 101.72% 4,292.182 M.O. acero 1.857 qq 366.08 679.81 100.00% 679.813 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 16,727.02 16,727.02 101.26% 16,519.29

M3 $21,772.99 101.31% 21,491.28*HAVUE 10390012 VUELOS .40x.10, 180 kg/Cm², 60, 3/8" x 25' A .20 + 2 DE 3/8":

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.857 qq 2,432.17 4,516.54 101.72% 4,440.012 M.O. acero 1.857 qq 366.08 679.81 100.00% 679.813 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 16,727.02 16,727.02 101.26% 16,519.29

M3 $21,923.37 101.31% 21,639.11*HAVUE 10390013 VUELOS .40x.12, 180 kg/Cm², 40, 3/8" A .20 + 2 DE 3/8":

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.548 qq 2,114.09 3,272.61 101.72% 3,217.162 M.O. acero 1.548 qq 243.24 376.54 100.00% 376.543 Subida acero 1.548 qq 24.32 37.65 100.00% 37.654 Madera bruta amer. (4 usos) 90.62 pt 35.70 3,235.13 101.74% 3,179.865 Clavos corrientes (5 lb. / 100 pie madera) 18.12 lb 30.43 551.39 101.70% 542.156 Clavos de acero (¼ lb / metro) 5.21 lb 53.10 276.65 101.72% 271.967 Alambre calibre #14 (¼ lb. / metro) 5.21 lb 34.64 180.47 101.70% 177.458 Confección e instalación de madera 20.83 m 167.57 3,490.48 100.00% 3,490.489 Desencofrado 8.33 m2 25.78 214.80 100.00% 214.8010 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $18,878.56 101.34% 18,628.13*HAVUE 10390014 VUELOS .40x.12, 180 kg/Cm², 40, 3/8" x 25' A .20 + 2 DE 3/8", :

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.548 qq 2,072.20 3,207.77 101.72% 3,153.422 Partidas comunes de la analizada completa anterior (2-10) 1.00 u 15,605.95 15,605.95 101.27% 15,410.97

M3 $18,813.72 101.34% 18,564.39*HAVUE 10390015 VUELOS .40x.12, 180 kg/Cm², 60, 3/8" A .20 + 2 DE 3/8", :

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.548 qq 2,351.19 3,639.64 101.72% 3,577.972 M.O. acero 1.548 qq 366.08 566.69 100.00% 566.693 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 15,229.41 15,229.41 101.30% 15,034.43

M3 $19,435.74 101.34% 19,179.09*HAVUE 10390016 VUELOS .40x.12, 180 kg/Cm², 60, 3/8" x 25' A .20 + 2 DE 3/8":

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.548 qq 2,432.17 3,765.00 101.72% 3,701.212 M.O. acero 1.548 qq 366.08 566.69 100.00% 566.693 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 15,229.41 15,229.41 101.30% 15,034.43

M3 $19,561.10 101.34% 19,302.33

*HAZAPC1 10410000 HORM. ARMADO ZAP. COLUMNAS (1 CAMADA ACERO)

*HAZAPC1 10410001 ZAP. COL., 1.2x1.2, 1:3:5, 40, 8 DE ½" A.D., LIG.:ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"

1 Acero ½" x 20' grado 40 + 5% desp. 1.299 qq 2,121.47 2,755.79 101.72% 2,709.092 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 2,076.70 909.59 101.72% 894.183 M.O. acero 1.737 qq 243.24 422.51 100.00% 422.514 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $8,078.20 101.55% 7,954.57*HAZAPC1 10410002 ZAP. COL., 1.2x1.2, 1:3:5, 40, 8 DE ½" x 25' A.D., LIG.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 1.299 qq 2,078.50 2,699.97 101.72% 2,654.232 Acero ¾" grado 40 + 5% desp. 0.438 qq 2,076.70 909.59 101.72% 894.183 M.O. acero 1.737 qq 243.24 422.51 100.00% 422.514 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $8,022.38 101.55% 7,899.71*HAZAPC1 10410003 ZAP. COL., 1.2x1.2, 1:3:5, 60, 8 DE ½" A.D., LIG.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 + 5% desp. 1.299 qq 2,413.96 3,135.73 101.72% 3,082.602 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,407.71 1,054.58 101.72% 1,036.713 M.O. acero 1.737 qq 366.08 635.88 100.00% 635.884 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $8,816.50 101.53% 8,683.98*HAZAPC1 10410004 ZAP. COL., 1.2x1.2, 1:3:5, 60, 8 DE ½" x 25' A.D., LIG.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 + 5% desp. 1.299 qq 2,409.63 3,130.11 101.72% 3,077.082 Acero ¾" grado 60 + 5% desp. 0.438 qq 2,407.71 1,054.58 101.72% 1,036.713 M.O. acero 1.737 qq 366.08 635.88 100.00% 635.884 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $8,810.88 101.53% 8,678.46*HAZAPC1 10410005 ZAP. COL., 1.2x1.2, 1:3:5, 40, 8 DE ½" A.D., LIG.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 0.974 qq 2,121.47 2,066.31 101.72% 2,031.302 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 2,076.70 782.92 101.72% 769.653 M.O. acero 1.351 qq 243.24 328.62 100.00% 328.624 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $7,168.16 101.56% 7,058.36*HAZAPC1 10410006 ZAP. COL., 1.2x1.2, 1:3:5, 40, 8 DE ½" x 25' A.D., LIG.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 0.974 qq 2,078.50 2,024.46 101.72% 1,990.162 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 2,076.70 782.92 101.72% 769.653 M.O. acero 1.351 qq 243.24 328.62 100.00% 328.624 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $7,126.31 101.55% 7,017.22*HAZAPC1 10410007 ZAP. COL., 1.2x1.2, 1:3:5, 60, 8 DE ½" A.D., LIG.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 + 5% desp. 0.974 qq 2,413.96 2,351.20 101.72% 2,311.362 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,407.71 907.71 101.72% 892.333 M.O. acero 1.351 qq 366.08 494.57 100.00% 494.574 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $7,743.79 101.53% 7,627.05

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 63

Page 66: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

*HAZAPC1 10410008 ZAP. COL., 1.2x1.2, 1:3:5, 60, 8 DE ½" x 25' A.D., LIG.:ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"

1 Acero ½" x 25' grado 60 + 5% desp. 0.974 qq 2,409.63 2,346.98 101.72% 2,307.222 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,407.71 907.71 101.72% 892.333 M.O. acero 1.351 qq 366.08 494.57 100.00% 494.574 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $7,739.57 101.53% 7,622.91*HAZAPC1 10410009 ZAP. COL., 1.2x1.2, 140, 40, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" y ¾" grado 40 + 5% desp. 1.299 qq 2,121.47 2,755.79 101.72% 2,709.092 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 2,076.70 909.59 101.72% 894.183 M.O. acero 1.737 qq 243.24 422.51 100.00% 422.514 Horm. 140 Kg/Cm² 1.00 m3 6,911.85 6,911.85 101.72% 6,794.70

M3 $10,999.74 101.66% 10,820.48*HAZAPC1 10410010 ZAP. COL., 1.2x1.2, 140, 40, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 1.299 qq 2,078.50 2,699.97 101.72% 2,654.232 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 2,076.70 909.59 101.72% 894.183 M.O. acero 1.737 qq 243.24 422.51 100.00% 422.514 Horm. 140 Kg/Cm² 1.00 m3 6,911.85 6,911.85 101.72% 6,794.70

M3 $10,943.92 101.66% 10,765.62*HAZAPC1 10410011 ZAP. COL., 1.2x1.2, 140, 60, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" y ¾" grado 60 + 5% desp. 1.299 qq 2,413.96 3,135.73 101.72% 3,082.602 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,407.71 1,054.58 101.72% 1,036.713 M.O. acero 1.737 qq 366.08 635.88 100.00% 635.884 Horm. 140 Kg/Cm² 1.00 m3 7,035.16 7,035.16 101.72% 6,915.92

M3 $11,861.35 101.63% 11,671.11*HAZAPC1 10410012 ZAP. COL., 1.2x1.2, 140, 60, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 + 5% desp. 1.299 qq 2,409.63 3,130.11 101.72% 3,077.082 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,407.71 1,054.58 101.72% 1,036.713 M.O. acero 1.737 qq 366.08 635.88 100.00% 635.884 Horm. 140 Kg/Cm² 1.00 m3 7,035.16 7,035.16 101.72% 6,915.92

M3 $11,855.73 101.63% 11,665.59*HAZAPC1 10410013 ZAP. COL., 1.2x1.2, 140, 40, 8 DE ½" A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 0.974 qq 2,121.47 2,066.31 101.72% 2,031.302 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 2,076.70 782.92 101.72% 769.653 M.O. acero 1.351 qq 243.24 328.62 100.00% 328.624 Horm. 140 Kg/Cm² 1.00 m3 6,911.85 6,911.85 101.72% 6,794.70

M3 $10,089.70 101.67% 9,924.27*HAZAPC1 10410014 ZAP. COL., 1.2x1.2, 140, 40, 8 DE ½" x 25' A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 0.974 qq 2,078.50 2,024.46 101.72% 1,990.162 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 2,076.70 782.92 101.72% 769.653 M.O. acero 1.351 qq 243.24 328.62 100.00% 328.624 Horm. 140 Kg/Cm² 1.00 m3 6,911.85 6,911.85 101.72% 6,794.70

M3 $10,047.85 101.67% 9,883.13*HAZAPC1 10410015 ZAP. COL., 1.2x1.2, 140, 60, 8 DE ½" A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 0.974 qq 2,413.96 2,351.20 101.72% 2,311.362 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,407.71 907.71 101.72% 892.333 M.O. acero 1.351 qq 366.08 494.57 100.00% 494.574 Horm. 140 Kg/Cm² 1.00 m3 7,035.16 7,035.16 101.72% 6,915.92

M3 $10,788.64 101.64% 10,614.18*HAZAPC1 10410016 ZAP. COL., 1.2x1.2, 140, 60, 8 DE ½" x 25' A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 0.974 qq 2,409.63 2,346.98 101.72% 2,307.222 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,407.71 907.71 101.72% 892.333 M.O. acero 1.351 qq 366.08 494.57 100.00% 494.574 Horm. 140 Kg/Cm² 1.00 m3 7,035.16 7,035.16 101.72% 6,915.92

M3 $10,784.42 101.64% 10,610.04*HAZAPC1 10410017 ZAP. COL., 1.2x1.2, 180, 40, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 1.299 qq 2,121.47 2,755.79 101.72% 2,709.092 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 2,076.70 909.59 101.72% 894.183 M.O. acero 1.737 qq 243.24 422.51 100.00% 422.514 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $11,330.73 101.66% 11,145.86*HAZAPC1 10410018 ZAP. COL., 1.2x1.2, 180, 40, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 1.299 qq 2,078.50 2,699.97 101.72% 2,654.232 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 2,076.70 909.59 101.72% 894.183 M.O. acero 1.737 qq 243.24 422.51 100.00% 422.514 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $11,274.91 101.66% 11,091.00*HAZAPC1 10410019 ZAP. COL., 1.2x1.2, 180, 60, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 1.299 qq 2,413.96 3,135.73 101.72% 3,082.602 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,407.71 1,054.58 101.72% 1,036.713 M.O. acero 1.737 qq 366.08 635.88 100.00% 635.884 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $12,069.03 101.63% 11,875.27*HAZAPC1 10410020 ZAP. COL., 1.2x1.2, 180, 60, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 1.299 qq 2,409.63 3,130.11 101.72% 3,077.082 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,407.71 1,054.58 101.72% 1,036.713 M.O. acero 1.737 qq 366.08 635.88 100.00% 635.884 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $12,063.41 101.63% 11,869.75*HAZAPC1 10410021 ZAP. COL., 1.2x1.2, 180, 40, 8 DE ½" A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 0.974 qq 2,121.47 2,066.31 101.72% 2,031.30

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 64

Page 67: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

2 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 2,076.70 782.92 101.72% 769.653 M.O. acero 1.351 qq 243.24 328.62 100.00% 328.624 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $10,420.69 101.67% 10,249.65*HAZAPC1 10410022 ZAP. COL., 1.2x1.2, 180, 40, 8 DE ½" x 25' A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 0.974 qq 2,078.50 2,024.46 101.72% 1,990.162 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 2,076.70 782.92 101.72% 769.653 M.O. acero 1.351 qq 243.24 328.62 100.00% 328.624 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $10,378.84 101.67% 10,208.51*HAZAPC1 10410023 ZAP. COL., 1.2x1.2, 180, 60, 8 DE ½" A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 0.974 qq 2,413.96 2,351.20 101.72% 2,311.362 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,407.71 907.71 101.72% 892.333 M.O. acero 1.351 qq 366.08 494.57 100.00% 494.574 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $10,996.32 101.65% 10,818.34*HAZAPC1 10410024 ZAP. COL., 1.2x1.2, 180, 60, 8 DE ½" x 25' A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 0.974 qq 2,409.63 2,346.98 101.72% 2,307.222 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,407.71 907.71 101.72% 892.333 M.O. acero 1.351 qq 366.08 494.57 100.00% 494.574 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $10,992.10 101.65% 10,814.20*HAZAPC1 10410025 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 40, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 1.299 qq 2,121.47 2,755.79 101.72% 2,709.092 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 2,076.70 909.59 101.72% 894.183 M.O. acero 1.737 qq 243.24 422.51 100.00% 422.514 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $11,538.41 101.66% 11,350.02*HAZAPC1 10410026 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 40, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 1.299 qq 2,078.50 2,699.97 101.72% 2,654.232 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 2,076.70 909.59 101.72% 894.183 M.O. acero 1.737 qq 243.24 422.51 100.00% 422.514 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $11,482.59 101.66% 11,295.16*HAZAPC1 10410027 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 60, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 1.299 qq 2,413.96 3,135.73 101.72% 3,082.602 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,407.71 1,054.58 101.72% 1,036.713 M.O. acero 1.737 qq 366.08 635.88 100.00% 635.884 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $12,276.71 101.63% 12,079.43*HAZAPC1 10410028 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 60, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 1.299 qq 2,409.63 3,130.11 101.72% 3,077.082 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,407.71 1,054.58 101.72% 1,036.713 M.O. acero 1.737 qq 366.08 635.88 100.00% 635.884 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $12,271.09 101.63% 12,073.91*HAZAPC1 10410029 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 40, 8 DE ½" A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 0.974 qq 2,121.47 2,066.31 101.72% 2,031.302 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 2,076.70 782.92 101.72% 769.653 M.O. acero 1.351 qq 243.24 328.62 100.00% 328.624 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $10,628.37 101.67% 10,453.81*HAZAPC1 10410030 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 40, 8 DE ½" x 25' A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 0.974 qq 2,078.50 2,024.46 101.72% 1,990.162 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 2,076.70 782.92 101.72% 769.653 M.O. acero 1.351 qq 243.24 328.62 100.00% 328.624 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $10,586.52 101.67% 10,412.67*HAZAPC1 10410031 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 60, 8 DE ½" A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 0.974 qq 2,413.96 2,351.20 101.72% 2,311.362 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,407.71 907.71 101.72% 892.333 M.O. acero 1.351 qq 366.08 494.57 100.00% 494.574 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $11,204.00 101.65% 11,022.50*HAZAPC1 10410032 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 60, 8 DE ½" x 25' A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 0.974 qq 2,409.63 2,346.98 101.72% 2,307.222 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,407.71 907.71 101.72% 892.333 M.O. acero 1.351 qq 366.08 494.57 100.00% 494.574 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $11,199.78 101.65% 11,018.36*HAZAPC1 10410033 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 40, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 1.299 qq 2,121.47 2,755.79 101.72% 2,709.092 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 2,076.70 909.59 101.72% 894.183 M.O. acero 1.737 qq 243.24 422.51 100.00% 422.514 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $12,070.59 101.66% 11,873.18*HAZAPC1 10410034 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 40, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 1.299 qq 2,078.50 2,699.97 101.72% 2,654.232 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 2,076.70 909.59 101.72% 894.183 M.O. acero 1.737 qq 243.24 422.51 100.00% 422.51

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 65

Page 68: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

4 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40M3 $12,014.77 101.66% 11,818.32

*HAZAPC1 10410035 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 60, 8 DE ½" A.D.:ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"

1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 1.299 qq 2,413.96 3,135.73 101.72% 3,082.602 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,407.71 1,054.58 101.72% 1,036.713 M.O. acero 1.737 qq 366.08 635.88 100.00% 635.884 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $12,808.89 101.64% 12,602.59*HAZAPC1 10410036 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 60, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 1.299 qq 2,409.63 3,130.11 101.72% 3,077.082 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,407.71 1,054.58 101.72% 1,036.713 M.O. acero 1.737 qq 366.08 635.88 100.00% 635.884 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $12,803.27 101.64% 12,597.07*HAZAPC1 10410037 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 40, 8 DE ½" A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 0.974 qq 2,121.47 2,066.31 101.72% 2,031.302 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 2,076.70 782.92 101.72% 769.653 M.O. acero 1.351 qq 243.24 328.62 100.00% 328.624 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $11,160.55 101.67% 10,976.97*HAZAPC1 10410038 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 40, 8 DE ½" x 25' A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 0.974 qq 2,078.50 2,024.46 101.72% 1,990.162 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 2,076.70 782.92 101.72% 769.653 M.O. acero 1.351 qq 243.24 328.62 100.00% 328.624 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $11,118.70 101.67% 10,935.83*HAZAPC1 10410039 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 60, 8 DE ½" A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 0.974 qq 2,413.96 2,351.20 101.72% 2,311.362 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,407.71 907.71 101.72% 892.333 M.O. acero 1.351 qq 366.08 494.57 100.00% 494.574 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $11,736.18 101.65% 11,545.66*HAZAPC1 10410040 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 60, 8 DE ½" x 25' A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 0.974 qq 2,409.63 2,346.98 101.72% 2,307.222 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,407.71 907.71 101.72% 892.333 M.O. acero 1.351 qq 366.08 494.57 100.00% 494.574 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $11,731.96 101.65% 11,541.52

*HAZAPC2 10430000 HORM. ARMADO ZAP. COLUMNAS (2 CAMADAS ACERO)

*HAZAPC2 10430001 ZAP. COL., 2.15x2.80, 180, 40, 20 DE ½", 17 DE ½" X 20', 2 CAM.:ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"

1 Acero ½" x 20' grado 40 + 5% desp. 2.737 qq 2,121.47 5,806.46 101.72% 5,708.072 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 2,076.70 776.69 101.72% 763.523 M.O. acero 3.111 qq 243.24 756.72 100.00% 756.724 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $14,582.71 101.63% 14,348.39*HAZAPC2 10430002 ZAP. COL., 2.15x2.80, 180, 40, 20 DE ½", 17 DE ½" x 25', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 2.737 qq 2,078.50 5,688.85 101.72% 5,592.482 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 2,076.70 776.69 101.72% 763.523 M.O. acero 3.111 qq 243.24 756.72 100.00% 756.724 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $14,465.10 101.63% 14,232.80*HAZAPC2 10430003 ZAP. COL., 2.15x2.80, 180, 60, 20 DE ½", 17 DE ½" X 20', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 20' grado 60 + 5% desp. 2.737 qq 2,413.96 6,607.01 101.72% 6,495.072 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,407.71 900.48 101.72% 885.233 M.O. acero 3.111 qq 366.08 1,138.87 100.00% 1,138.874 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $15,889.20 101.60% 15,639.25*HAZAPC2 10430004 ZAP. COL., 2.15x2.80, 180, 60, 20 DE ½", 17 DE ½" x 25', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 25' grado 60 + 5% desp. 2.737 qq 2,409.63 6,595.16 101.72% 6,483.432 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,407.71 900.48 101.72% 885.233 M.O. acero 3.111 qq 366.08 1,138.87 100.00% 1,138.874 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $15,877.35 101.60% 15,627.61*HAZAPC2 10430005 ZAP. COL., 2.15x2.80, 210 Kg/Cm², 40, 20 DE ½", 17 DE ½" X 20', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 20' grado 40 + 5% desp. 2.737 qq 2,121.47 5,806.46 101.72% 5,708.072 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 2,076.70 776.69 101.72% 763.523 M.O. acero 3.111 qq 243.24 756.72 100.00% 756.724 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $14,790.39 101.63% 14,552.55*HAZAPC2 10430006 ZAP. COL., 2.15x2.80, 210 Kg/Cm², 40, 20 DE ½", 17 DE ½" x 25', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 2.737 qq 2,078.50 5,688.85 101.72% 5,592.482 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 2,076.70 776.69 101.72% 763.523 M.O. acero 3.111 qq 243.24 756.72 100.00% 756.724 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $14,672.78 101.63% 14,436.96*HAZAPC2 10430007 ZAP. COL., 2.15x2.80, 210 Kg/Cm², 60, 20 DE ½", 17 DE ½" X 20', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 20' grado 60 + 5% desp. 2.737 qq 2,413.96 6,607.01 101.72% 6,495.072 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,407.71 900.48 101.72% 885.233 M.O. acero 3.111 qq 366.08 1,138.87 100.00% 1,138.87

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 66

Page 69: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

4 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24M3 $16,096.88 101.60% 15,843.41

*HAZAPC2 10430008 ZAP. COL., 2.15x2.80, 210 Kg/Cm², 60, 20 DE ½", 17 DE ½" x 25', 2 CAM.:ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"

1 Acero ½" x 25' grado 60 + 5% desp. 2.737 qq 2,409.63 6,595.16 101.72% 6,483.432 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,407.71 900.48 101.72% 885.233 M.O. acero 3.111 qq 366.08 1,138.87 100.00% 1,138.874 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $16,085.03 101.60% 15,831.77*HAZAPC2 10430009 ZAP. COL., 2.15x2.80, 240 Kg/Cm², 40, 20 DE ½", 17 DE ½" X 20', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 20' grado 40 + 5% desp. 2.737 qq 2,121.47 5,806.46 101.72% 5,708.072 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 2,076.70 776.69 101.72% 763.523 M.O. acero 3.111 qq 243.24 756.72 100.00% 756.724 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $15,322.57 101.64% 15,075.71*HAZAPC2 10430010 ZAP. COL., 2.15x2.80, 240 Kg/Cm², 40, 20 DE ½", 17 DE ½" x 25', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 2.737 qq 2,078.50 5,688.85 101.72% 5,592.482 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 2,076.70 776.69 101.72% 763.523 M.O. acero 3.111 qq 243.24 756.72 100.00% 756.724 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $15,204.96 101.64% 14,960.12*HAZAPC2 10430011 ZAP. COL., 2.15x2.80, 240 Kg/Cm², 60, 20 DE ½", 17 DE ½" X 20', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 20' grado 60 + 5% desp. 2.737 qq 2,413.96 6,607.01 101.72% 6,495.072 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,407.71 900.48 101.72% 885.233 M.O. acero 3.111 qq 366.08 1,138.87 100.00% 1,138.874 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $16,629.06 101.60% 16,366.57*HAZAPC2 10430012 ZAP. COL., 2.15x2.80, 240 Kg/Cm², 60, 20 DE ½", 17 DE ½" x 25', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 25' grado 60 + 5% desp. 2.737 qq 2,409.63 6,595.16 101.72% 6,483.432 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,407.71 900.48 101.72% 885.233 M.O. acero 3.111 qq 366.08 1,138.87 100.00% 1,138.874 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $16,617.21 101.60% 16,354.93

*HAZAPM1 10450000 HORMIGON ARMADO ZAPATAS DE MUROS (1 CAMADA ACERO)

*HAZAPM1 10450001 ZAP. MURO, 30x20, 1:3:5, 2 DE 3/8", 3/8" A .25 grado 40, LIG.:1 Acero ¼" (bastones) + 5% desp. 0.0479 qq 1,519.73 72.80 101.73% 71.562 Acero 3/8" x 20' grado 40 + 5% desp. 0.8082 qq 2,114.09 1,708.61 101.72% 1,679.663 M.O. acero 16.6670 m 81.08 1,351.36 100.00% 1,351.364 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $7,123.08 101.30% 7,031.37*HAZAPM1 10450002 ZAP. MURO, 45x20, 1:3:5, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.8747 qq 2,114.09 1,849.19 101.72% 1,817.862 M.O. acero 11.1110 m 81.08 900.88 100.00% 900.883 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $6,740.38 101.40% 6,647.53*HAZAPM1 10450003 ZAP. MURO, 45x25, 1:3:5, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.7130 qq 2,114.09 1,507.35 101.72% 1,481.812 M.O. acero 8.8890 m 81.08 720.72 100.00% 720.723 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $6,218.38 101.42% 6,131.32*HAZAPM1 10450004 ZAP. MURO, 60x25, 1:3:5, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.5912 qq 2,114.09 1,249.85 101.72% 1,228.672 M.O. acero 6.6670 m 81.08 540.56 100.00% 540.563 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,912.07 3,990.31 101.57% 3,928.79

M3 $5,780.72 101.45% 5,698.02*HAZAPM1 10450005 ZAP. MURO, 20x15, 1:2:4, 2 DE 3/8", 3/8" A .30 grado 40, LIG., para Bordillos:

1 Acero ¼" (bastones) + 5% desp. 0.0766 qq 1,519.73 116.41 101.72% 114.442 Acero 3/8" x 20' grado 40 + 5% desp. 1.3632 qq 2,114.09 2,881.93 101.72% 2,833.103 M.O. acero 33.3330 m 81.08 2,702.64 100.00% 2,702.644 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 4,431.50 4,520.13 101.59% 4,449.48

M3 $10,104.70 101.20% 9,985.22*HAZAPM1 10450006 ZAP. MURO, 30x15, 1:2:4, 2 DE 3/8", 3/8" A .30 grado 40, LIG., para Bordillos:

1 Acero 3/8" (bastones) + 5% desp. 0.1338 qq 2,114.09 282.87 101.73% 278.072 Acero 3/8" x 20' grado 40 + 5% desp. 1.0070 qq 2,114.09 2,128.89 101.72% 2,092.823 M.O. acero 22.2220 m 81.08 1,801.76 100.00% 1,801.764 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 4,431.50 4,520.13 101.59% 4,449.48

M3 $8,450.78 101.28% 8,344.06*HAZAPM1 10450007 ZAP. MURO, 40x15, 1:2:4, 2 DE 3/8", 3/8" A .30 grado 40, LIG., para Bordillos:

1 Acero 3/8" (bastones) + 5% desp. 0.1012 qq 2,114.09 213.95 101.73% 210.322 Acero 3/8" x 20' grado 40 + 5% desp. 0.8297 qq 2,114.09 1,754.06 101.72% 1,724.343 M.O. acero 16.6670 m 81.08 1,351.36 100.00% 1,351.364 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 4,431.50 4,520.13 101.59% 4,449.48

M3 $7,625.55 101.33% 7,525.18*HAZAPM1 10450008 ZAP. MURO, 30x20, 1:2:4, 2 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero ¼" (bastones) + 5% desp. 0.0479 qq 1,519.73 72.80 101.73% 71.562 Acero 3/8" x 20' grado 40 + 5% desp. 0.8082 qq 2,114.09 1,708.61 101.72% 1,679.663 M.O. acero 16.6670 m 81.08 1,351.36 100.00% 1,351.364 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 4,431.50 4,520.13 101.59% 4,449.48

M3 $7,652.90 101.34% 7,552.06*HAZAPM1 10450009 ZAP. MURO, 45x20, 1:2:4, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.8747 qq 2,114.09 1,849.19 101.72% 1,817.862 M.O. acero 11.1110 m 81.08 900.88 100.00% 900.883 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 4,431.50 4,520.13 101.59% 4,449.48

M3 $7,270.20 101.42% 7,168.22*HAZAPM1 10450010 ZAP. MURO, 45x25, 1:2:4, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.7130 qq 2,114.09 1,507.35 101.72% 1,481.812 M.O. acero 8.8890 m 81.08 720.72 100.00% 720.72

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 67

Page 70: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

3 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 4,431.50 4,520.13 101.59% 4,449.48M3 $6,748.20 101.45% 6,652.01

*HAZAPM1 10450011 ZAP. MURO, 60x25, 1:2:4, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:1 Acero 3/8" x 20' grado 40 + 5% desp. 0.5912 qq 2,114.09 1,249.85 101.72% 1,228.672 M.O. acero 6.6670 m 81.08 540.56 100.00% 540.563 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 4,431.50 4,520.13 101.59% 4,449.48

M3 $6,310.54 101.48% 6,218.71*HAZAPM1 10450012 ZAP. MURO, 30x20, 140, 2 DE 3/8", 3/8" A .25 grado 40:

1 Acero ¼" (bastones) + 5% desp. 0.0479 qq 1,519.73 72.80 101.73% 71.562 Acero 3/8" x 20' grado 40 + 5% desp. 0.8082 qq 2,114.09 1,708.61 101.72% 1,679.663 M.O. acero 16.6670 m 81.08 1,351.36 100.00% 1,351.364 Horm. 140 Kg/Cm² 1.00 m3 6,911.85 6,911.85 101.72% 6,794.70

M3 $9,971.82 101.49% 9,825.72*HAZAPM1 10450013 ZAP. MURO, 45x20, 140, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.8747 qq 2,114.09 1,849.19 101.72% 1,817.862 M.O. acero 11.1110 m 81.08 900.88 100.00% 900.883 Horm. 140 Kg/Cm² 1.00 m3 6,911.85 6,911.85 101.72% 6,794.70

M3 $9,661.92 101.56% 9,513.44*HAZAPM1 10450014 ZAP. MURO, 45x25, 140, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.7130 qq 2,114.09 1,507.35 101.72% 1,481.812 M.O. acero 8.8890 m 81.08 720.72 100.00% 720.723 Horm. 140 Kg/Cm² 1.00 m3 6,911.85 6,911.85 101.72% 6,794.70

M3 $9,139.92 101.59% 8,997.23*HAZAPM1 10450015 ZAP. MURO, 60x25, 140, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.5912 qq 2,114.09 1,249.85 101.72% 1,228.672 M.O. acero 6.6670 m 81.08 540.56 100.00% 540.563 Horm. 140 Kg/Cm² 1.00 m3 6,911.85 6,911.85 101.72% 6,794.70

M3 $8,702.26 101.62% 8,563.93*HAZAPM1 10450016 ZAP. MURO, 30x20, 180, 2 DE 3/8", 3/8" A .25 grado 40:

1 Acero ¼" (bastones) + 5% desp. 0.0479 qq 1,519.73 72.80 101.73% 71.562 Acero 3/8" x 20' grado 40 + 5% desp. 0.8082 qq 2,114.09 1,708.61 101.72% 1,679.663 M.O. acero 16.6670 m 81.08 1,351.36 100.00% 1,351.364 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $10,375.61 101.50% 10,222.66*HAZAPM1 10450017 ZAP. MURO, 45x20, 180, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.8747 qq 2,114.09 1,849.19 101.72% 1,817.862 M.O. acero 11.1110 m 81.08 900.88 100.00% 900.883 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $9,992.91 101.57% 9,838.82*HAZAPM1 10450018 ZAP. MURO, 45x25, 180, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.7130 qq 2,114.09 1,507.35 101.72% 1,481.812 M.O. acero 8.8890 m 81.08 720.72 100.00% 720.723 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $9,470.91 101.59% 9,322.61*HAZAPM1 10450019 ZAP. MURO, 60x25, 180, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.5912 qq 2,114.09 1,249.85 101.72% 1,228.672 M.O. acero 6.6670 m 81.08 540.56 100.00% 540.563 Horm. 180 Kg/Cm² 1.00 m3 7,242.84 7,242.84 101.72% 7,120.08

M3 $9,033.25 101.62% 8,889.31*HAZAPM1 10450020 ZAP. MURO, 45x25, 210 Kg/Cm², 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.7170 qq 2,114.09 1,515.80 101.72% 1,490.122 M.O. acero 8.8890 m 81.08 720.72 100.00% 720.723 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $9,687.04 101.59% 9,535.08*HAZAPM1 10450021 ZAP. MURO, 60x25, 210 Kg/Cm², 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.5912 qq 2,114.09 1,249.85 101.72% 1,228.672 M.O. acero 6.6670 m 81.08 540.56 100.00% 540.563 Horm. 210 Kg/Cm² 1.00 m3 7,450.52 7,450.52 101.72% 7,324.24

M3 $9,240.93 101.62% 9,093.47*HAZAPM1 10450022 ZAP. MURO, 45x25, 240 Kg/Cm², 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 60 + 5% desp. 0.7130 qq 2,351.19 1,676.40 101.72% 1,647.992 M.O. acero 8.8890 m 81.08 720.72 100.00% 720.723 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $10,379.82 101.60% 10,216.11*HAZAPM1 10450023 ZAP. MURO, 60x25, 240 Kg/Cm², 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 60 + 5% desp. 0.5912 qq 2,351.19 1,390.02 101.72% 1,366.472 M.O. acero 6.6670 m 81.08 540.56 100.00% 540.563 Horm. 240 Kg/Cm² 1.00 m3 7,982.70 7,982.70 101.72% 7,847.40

M3 $9,913.28 101.63% 9,754.43

*HORIND 10470000 HORMIGONES INDUSTRIALES

*HORIND 10470001 HORM. 140 Kg/Cm²:1 Horm. industrial + 10% desp. 1.10 m3 5,752.50 6,327.75 101.72% 6,220.502 Bomba + personal + 10% desp. 1.10 m3 531.00 584.10 101.72% 574.203 Aditivo 0.1289 gl 336.30

M3 $6,911.85 101.72% 6,794.70*HORIND 10470002 HORM. 160 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 5,864.60 6,451.06 101.72% 6,341.722 Bomba + personal + 10% desp. 1.10 m3 531.00 584.10 101.72% 574.203 Aditivo 0.1558 gl 336.30

M3 $7,035.16 101.72% 6,915.92*HORIND 10470003 HORM. 180 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 6,053.40 6,658.74 101.72% 6,545.882 Bomba + personal + 10% desp. 1.10 m3 531.00 584.10 101.72% 574.203 Aditivo 0.1805 gl 336.30

M3 $7,242.84 101.72% 7,120.08*HORIND 10470004 HORM. 210 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 6,242.20 6,866.42 101.72% 6,750.042 Bomba + personal + 10% desp. 1.10 m3 531.00 584.10 101.72% 574.203 Aditivo 0.2063 gl 336.30

M3 $7,450.52 101.72% 7,324.24*HORIND 10470005 HORM. 240 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 6,726.00 7,398.60 101.72% 7,273.20PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 68

Page 71: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

2 Bomba + personal + 10% desp. 1.10 m3 531.00 584.10 101.72% 574.203 Aditivo 0.2063 gl 336.30

M3 $7,982.70 101.72% 7,847.40*HORIND 10470006 HORM. 250 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 7,038.70 7,742.57 101.72% 7,611.342 Bomba + personal + 10% desp. 1.10 m3 531.00 584.10 101.72% 574.203 Aditivo 0.2063 gl 336.30

M3 $8,326.67 101.72% 8,185.54*HORIND 10470007 HORM. 260 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 7,245.20 7,969.72 101.72% 7,834.642 Bomba + personal + 10% desp. 1.10 m3 531.00 584.10 101.72% 574.203 Aditivo 0.2063 gl 336.30

M3 $8,553.82 101.72% 8,408.84*HORIND 10470008 HORM. 280 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 7,327.80 8,060.58 101.72% 7,923.962 Bomba + personal + 10% desp. 1.10 m3 531.00 584.10 101.72% 574.203 Aditivo 0.2063 gl 336.30

M3 $8,644.68 101.72% 8,498.16*HORIND 10470009 HORM. 300 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 7,552.00 8,307.20 101.72% 8,166.402 Bomba + personal + 10% desp. 1.10 m3 531.00 584.10 101.72% 574.203 Aditivo 0.2063 gl 336.30

M3 $8,891.30 101.72% 8,740.60*HORIND 10470010 HORM. 350 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 8,413.40 9,254.74 101.72% 9,097.882 Bomba + personal + 10% desp. 1.10 m3 531.00 584.10 101.72% 574.203 Aditivo 0.2063 gl 336.30

M3 $9,838.84 101.72% 9,672.08*HORIND 10470011 HORM. 400 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 8,926.70 9,819.37 101.72% 9,652.942 Bomba + personal + 10% desp. 1.10 m3 531.00 584.10 101.72% 574.203 Aditivo 0.2063 gl 336.30

M3 $10,403.47 101.72% 10,227.14

*HORSIM 10490000 HORMIGONES SIMPLES

*HORSIM 10490001 LIGADO Y VACIADO A MANO:1400 m3 horm. 1:3:5 vaciados en 8 horas, a 1.75 m3 por hora.

1 Madera para puentes (4 de 2"x10"x 12', 6 usos) 14.00 pt 35.70 499.80 101.74% 491.262 Carretilla (7 meses de uso) 5.00 u 409.00 2,045.00 101.80% 2,008.753 Palas (7 meses de uso) 6.00 u 44.70 268.20 101.82% 263.404 Tanques de agua (7 meses de uso) 4.00 u 90.05 360.20 101.73% 354.085 Cubetas para medir el agua (7 meses de uso) 2.00 u 42.86 85.72 101.73% 84.266 Maestro 1.00 u 1,300.00 1,300.00 100.00% 1,300.007 Llenador de agregados (TC) 1.00 u 474.00 474.00 100.00% 474.008 Maleteros o acarreadores de agregados (TC) 2.00 u 474.00 948.00 100.00% 948.009 Ligadores (TC) 4.00 u 474.00 1,896.00 100.00% 1,896.0010 Cementero (acarreador de cemento) (TC) 1.00 u 474.00 474.00 100.00% 474.0011 Vaciador y tenedor (TC) 1.00 u 474.00 474.00 100.00% 474.0012 Aguatero (TC) 1.00 u 474.00 474.00 100.00% 474.00

Total 9,298.92 100.62% 9,241.75M3 $664.21 100.62% 660.13

*HORSIM 10490002 LIGADORA 2 FUNDAS:1 Rendimiento del equipo: 18.00 m3 horm. 1:3:5 en 5 horas 18.00 m32 Potencia del equipo 20 hp3 Vida útil: 5 años. Veloc. depreciación: 20% / año4 Costo del equipo 133,421.38 $5 Deprec. 40% 1er. año (Doble veloc. deprec.) 53,368.55 $6 Tiempo de trabajo: 1,200 horas / año 1,200 horas7 Deprec. horaria: Deprec. 1er. año ÷ Tiempo trabajo 44.47 $8 Costo inversión: 36% del costo equipo 48,031.70 $9 Costo inv. horario (Costo inversión ÷ Tiempo trabajo) 40.03 $10 Combustible / hora (.05 gls. / HP potencia) 1.00 gl11 Lubricante (15% consumo combustible) 32.40 $

*HORSIM 10490003 WINCHE (ELEVADOR):Capacidad: 2000 kilosAltura elevación: 12 m. Velocidad elevación: 0.50 m./seg.Tiempo elevación: 24 seg. Cant. m3 elevado: 4 m3 / horaVaciado: 18.00 m3 en 5 horas

1 Costo del equipo 133,512.93 $2 Depreciación 40% 1er. año (Doble velocidad deprec.) 53,405.17 $3 Tiempo de trabajo: 1,200 horas / año 1,200 horas4 Deprec. horaria: Deprec. 1er. año ÷ Tiempo trabajo 44.50 $5 Costo inversión: 36% del costo del equipo 48,064.65 $6 Costo inv. horario (Costo inversión ÷ Tiempo trabajo) 40.05 $

*HORSIM 10490004 COSTO USO, LIG. P/HORA:1 Depreciación horaria 1.00 u 44.47 44.47 101.72% 43.722 Costo inversión horaria 1.00 u 40.03 40.03 101.73% 39.353 Mant. y reparaciones (75% Deprec. horaria) 1.00 u 33.36 33.36 101.74% 32.794 Combustible 1.00 gl 216.00 216.00 100.00% 216.005 Lubricante (15% valor combustible consumido) 15% 32.40 100.00% 32.40

Hora $366.26 100.55% 364.26*HORSIM 10490005 COSTO USO WINCHE (ELEVADOR) P/HORA:

1 Depreciación horaria 1.00 u 44.50 44.50 101.71% 43.752 Costo inversión horaria 1.00 u 40.05 40.05 101.70% 39.383 Mant. y reparaciones (75% Deprec. horaria) 1.00 u 33.38 33.38 101.74% 32.814 Combustible 0.90 gl 216.00 194.40 100.00% 194.405 Lubricante (15% valor combustible consumido) 15% 29.16 100.00% 29.16

Hora $341.49 100.59% 339.50

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 69

Page 72: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

*HORSIM 10490006 LIGADO Y VACIADO,, LIG. 2 FUNDAS: 18.00 m31 Uso ligadora 5.00 horas 366.26 1,831.30 100.55% 1,821.302 Maestro 5.00 horas 162.50 812.50 100.00% 812.503 Cargadores agregados y cemento (3 hombres) 15.00 horas 59.25 888.75 100.00% 888.754 Operador 5.00 horas 59.25 296.25 100.00% 296.255 Transp. horm. (3 hombres) 15.00 horas 59.25 888.75 100.00% 888.756 Tendedor 5.00 horas 90.38 451.90 100.00% 451.90

Total $5,169.45 100.19% 5,159.45M3 $287.19 100.19% 286.64

*HORSIM 10490007 LIGADO Y VACIADO, LIG. 2 FDA. Y WINCHE: 18.00 m31 Uso ligadora 5.00 horas 366.26 1,831.30 100.55% 1,821.302 Uso Winche 5.00 horas 341.49 1,707.45 100.59% 1,697.503 Maestro 5.00 horas 162.50 812.50 100.00% 812.504 Cargadores agregados y cemento (3 hombres) 15.00 horas 59.25 888.75 100.00% 888.755 Operador 5.00 horas 59.25 296.25 100.00% 296.256 Operador Winche (cargador) 5.00 horas 59.25 296.25 100.00% 296.257 Transp. horm. (3 hombres) 15.00 horas 59.25 888.75 100.00% 888.758 Vaciador en Winche (cargador) 5.00 horas 59.25 296.25 100.00% 296.259 Tendedor 5.00 horas 90.38 451.90 100.00% 451.90

Total $7,469.40 100.27% 7,449.45M3 $414.97 100.27% 413.86

*HORSIM 10490008 HORMIGON (1:3:5) A MANO:1 Arena gruesa lavada 0.5229 m3 1,292.28 675.73 101.72% 664.282 Grava combinada 0.8544 m3 880.93 752.67 101.72% 739.913 agua 60.00 gl 0.61 36.60 101.67% 36.004 Cemento gris 6.40 fda 320.43 2,050.75 101.72% 2,016.005 Vaciado a mano 1.38 m3 664.21 916.61 100.62% 910.98

M3 $4,432.36 101.49% 4,367.17*HORSIM 10490009 HORMIGON (1:3:5), LIG.:

1 Arena gruesa lavada 0.5229 m3 1,292.28 675.73 101.72% 664.282 Grava combinada 0.8544 m3 880.93 752.67 101.72% 739.913 agua 60.00 gl 0.61 36.60 101.67% 36.004 Cemento gris 6.40 fda 320.43 2,050.75 101.72% 2,016.005 Vaciado con ligadora 1.38 m3 287.19 396.32 100.19% 395.56

M3 $3,912.07 101.57% 3,851.75*HORSIM 10490010 HORMIGON (1:3:5) LIG. Y WINCHE:

1 Arena gruesa lavada 0.5229 m3 1,292.28 675.73 101.72% 664.282 Grava combinada 0.8544 m3 880.93 752.67 101.72% 739.913 agua 60.00 gl 0.61 36.60 101.67% 36.004 Cemento gris 6.40 fda 320.43 2,050.75 101.72% 2,016.005 Vaciado con ligadora y winche 1.38 m3 414.97 572.66 100.27% 571.13

M3 $4,088.41 101.52% 4,027.32*HORSIM 10490011 HORMIGON (1:2:4) A MANO:

1 Arena gruesa lavada 0.4483 m3 1,292.28 579.33 101.72% 569.512 Grava combinada 0.8976 m3 880.93 790.72 101.72% 777.323 agua 60.00 gl 0.61 36.60 101.67% 36.004 Cemento gris 8.23 fda 320.43 2,637.14 101.72% 2,592.455 Vaciado a mano 1.35 m3 664.21 896.68 100.62% 891.18

M3 $4,940.47 101.52% 4,866.46*HORSIM 10490012 HORMIGON (1:2:4), LIG.:

1 Arena gruesa lavada 0.4483 m3 1,292.28 579.33 101.72% 569.512 Grava combinada 0.8976 m3 880.93 790.72 101.72% 777.323 agua 60.00 gl 0.61 36.60 101.67% 36.004 Cemento gris 8.23 fda 320.43 2,637.14 101.72% 2,592.455 Vaciado con ligadora 1.35 m3 287.19 387.71 100.19% 386.96

M3 $4,431.50 101.59% 4,362.24*HORSIM 10490013 HORMIGON (1:2:4) LIG. Y WINCHE:

1 Arena gruesa lavada 0.4483 m3 1,292.28 579.33 101.72% 569.512 Grava combinada 0.8976 m3 880.93 790.72 101.72% 777.323 agua 60.00 gl 0.61 36.60 101.67% 36.004 Cemento gris 8.23 fda 320.43 2,637.14 101.72% 2,592.455 Vaciado con ligadora y winche 1.35 m3 414.97 560.21 100.27% 558.71

M3 $4,604.00 101.54% 4,533.99

*IMP 10510000 IMPERMEABILIZANTES

*IMP 10510001 SX-PEL + SUPRACURE PLUS (IMPERM. ESTRUCTURAL):1 Limpieza superficie 1.00 m2 34.23 34.23 100.00% 34.232 "SX-PEL" para .2125 m3 horm. 180 0.26 gl 336.30 87.44 101.72% 85.963 Sellador "SUPRACURE PLUS" sobre área expuesta 0.042 gl 979.40 41.13 101.71% 40.444 Mano de obra 1.00 m2 86.38 86.38 100.00% 86.38

M2 $249.18 100.88% 247.01*IMP 10510002 SILICOOL:

1 Limpieza superficie 1.00 m2 34.23 34.23 100.00% 34.232 Sellador ALM + 10% desp. 0.090 gl 685.25 61.67 101.72% 60.633 Silicool + 10% desp. 0.090 gl 1,107.78 99.70 101.72% 98.014 Mano de obra 1.00 m2 42.64 42.64 100.00% 42.64

M2 $238.24 101.16% 235.51

*IEACO 10530000 INSTALACION ELECTRICA: ACOMETIDAS

*IEACO 10530001 ACOM. PRIM. 3 PH., DESDE POSTE HASTA TRANSF., SOTERRADA: 26.00 m1 Adaptador hembra 3", PVC 1 u 57.84 57.84 101.72% 56.862 Alambre URD #2, 33% neutro, concéntrico, 1 cond. por fase 282.00 p 184.08 51,910.56 101.72% 51,030.723 Bote material excavado en zanja 9.40 m3 351.88 3,307.67 101.73% 3,251.554 Cemento PVC Cano, ¼ gl. 0.0503 u 289.10 14.54 101.68% 14.305 Cinta de peligro (rollo) 1 u 702.10 702.10 101.72% 690.206 Codo 3"x90, PVC 2 u 134.58 269.16 101.72% 264.607 Condulet 3", hg 2 u 1,498.09 2,996.18 101.72% 2,945.408 Cono de alivio 3 u 2,869.76 8,609.28 101.72% 8,463.369 Cut Out 200 a., 15 kv 3 u 5,022.29 15,066.87 101.72% 14,811.5110 Elbow Conector 3 u 2,211.32 6,633.96 101.72% 6,521.5211 Excavación zanja para tuberías, roca Long. Zanja (m.): 9.00 6.48 m3 2,127.44 13,785.81 100.00% 13,785.8112 Fusible tipo cartucho, 8 amp. 3 u 80.72 242.16 101.71% 238.08

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 70

Page 73: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

13 Pararrayo 9 kva (Arrester) 3 u 1,917.85 5,753.55 101.72% 5,656.0514 Piezas p/soporte Estructura SS-1 1 u 2,353.98 2,353.98 101.72% 2,314.0815 Relleno granular 6.48 m3 1,203.70 7,799.98 101.52% 7,683.3416 Tubería 3", BX 10.00 p 23.08 3,456.67 100.00% 3,456.6717 Tubo 3"x19', PVC SDR-26 + 10% desp. 3 u 984.01 2,952.03 101.72% 2,902.0218 Tubo IMC 3"x20', hg 1 u 242.97 242.97 101.72% 238.86

Subtotal 126,155.31 101.47% 124,324.9319 Miscelaneos 2.00% 2,523.11 101.47% 2,486.5020 Mano de obra especializada y beneficios sub-contratista 25.00% 31,538.83 101.47% 31,081.23

Acometida 160,217.25 101.47% 157,892.66m $6,162.20 101.47% 6,072.79

*IEACO 10530002 ACOM. AL-01 DESDE TRANSF. HASTA MOD. MEDICION 8.00 m1 Alambre #3/0 THW, 9 cond., 3 por fase 260.00 p 206.38 53,658.80 101.73% 52,748.802 Alambre #3/0 THW, 2 cond., neutro 58.00 p 206.38 11,970.04 101.73% 11,767.043 Alambre #3/0 THW, 1 cond. pelado, tierra 29.00 p 206.38 5,985.02 101.73% 5,883.524 Cemento PVC Cano, ¼ gl. 0.1241 u 289.10 35.88 101.73% 35.275 Codo 2"x90, PVC 2 u 33.45 66.90 101.70% 65.786 Codo 3"x90, PVC 6 u 134.58 807.48 101.72% 793.807 Tubos 2"x19', PVC SDR-26 + 10% desp. 2 u 389.40 778.80 101.72% 765.608 Tubos 3"x19', PVC SDR-26 + 10% desp., 4 alambres p/tubo 5 u 984.01 4,920.05 101.72% 4,836.70

Subtotal 78,222.97 101.72% 76,896.519 Miscelaneos 2.00% 1,564.46 101.73% 1,537.9310 Mano de obra especializada y beneficios sub-contratista 25.00% 19,555.74 101.72% 19,224.13

Acometida 99,343.17 101.72% 97,658.57m $12,417.90 101.73% 12,207.32

*IEACO 10530003 ACOM. AL-02 DESDE MOD. MEDICION HASTA PANEL AREA COMUN 38.00 m1 Alambre No. 2 THW, 3 cond. 412.00 p 91.28 37,607.36 101.72% 36,972.882 Alambre No. 4 THW, 1 cond., neutro 138.00 p 54.41 7,508.58 101.72% 7,381.623 Alambre No. 4 THW, 1 cond., tierra 138.00 p 54.41 7,508.58 101.72% 7,381.624 Bote material excavado en zanja 3.99 m3 351.88 1,404.00 101.73% 1,380.185 Cemento PVC Cano, ¼ gl. 0.0769 u 289.10 22.23 101.74% 21.856 Codo 3"x90, PVC 2 u 134.58 269.16 101.72% 264.607 Excavación zanja para tuberías, roca Long. Zanja (m.): 30.50 2.75 m3 2,127.44 5,850.46 100.00% 5,850.468 Relleno granular 2.75 m3 1,203.70 3,310.18 101.52% 3,260.689 Tubo 3"x19', PVC SDR-26 + 10% desp. 8 u 984.01 7,872.08 101.72% 7,738.72

Subtotal 71,352.63 101.57% 70,252.6110 Miscelaneos 2.00% 1,427.05 101.57% 1,405.0511 Mano de obra especializada 25.00% 17,838.16 101.57% 17,563.15

Acometida 90,617.84 101.57% 89,220.81m $2,384.68 101.57% 2,347.92

*IEACO 10530004 ACOM. AL-02 DESDE PLANTA EMERG. HASTA MODULO MEDICION 8.00 m1 Alambre No. 12 THW, 2 cond. 58.00 p 91.28 5,294.24 101.72% 5,204.921 Alambre No. 2 THW, 3 cond. 87.00 p 91.28 7,941.36 101.72% 7,807.382 Alambre No. 4 THW, 1 cond., neutro 29.00 p 54.41 1,577.89 101.72% 1,551.213 Alambre No. 4 THW, 1 cond., tierra 29.00 p 54.41 1,577.89 101.72% 1,551.214 Cemento PVC Cano, ¼ gl. 0.0683 u 289.10 19.75 101.75% 19.414 Codo ½"x90, PVC 2 u 134.58 269.16 101.72% 264.605 Codo 3"x90, PVC 2 u 134.58 269.16 101.72% 264.605 Tubo ½"x19', PVC SDR-26 + 10% desp. 2 u 984.01 1,968.02 101.72% 1,934.686 Tubo 3"x19', PVC SDR-26 + 10% desp. 2 u 984.01 1,968.02 101.72% 1,934.68

Subtotal 20,885.49 101.72% 20,532.697 Miscelaneos 2.00% 417.71 101.72% 410.658 Mano de obra especializada 25.00% 5,221.37 101.72% 5,133.17

Acometida 26,524.57 101.72% 26,076.51m $3,315.57 101.72% 3,259.56

*IEACO 10530005 ACOM. AL-03 DESDE MODULO MEDICION HASTA PA, PB y PC 56.00 m1 Alambre No. 2 THW, 2 cond. (1 en c/fase) 405.00 p 91.28 36,968.40 101.72% 36,344.702 Alambre No. 4 THW, 1 cond., neutro 203.00 p 54.41 11,045.23 101.72% 10,858.473 Alambre No. 10 THW, 1 cond., tierra 203.00 p 12.43 2,523.29 101.80% 2,478.634 Bote material excavado en zanja 1.65 m3 351.88 580.60 101.73% 570.755 Cemento PVC Cano, ¼ gl. 0.0369 u 289.10 10.67 101.72% 10.496 Codo 1½"x90, PVC 2 u 34.18 68.36 101.70% 67.227 Excavación zanja para tuberías, roca Long. Zanja (m.): 28.50 1.14 m3 2,127.44 2,425.28 100.00% 2,425.288 Relleno granular 1.14 m3 1,203.70 1,372.22 101.52% 1,351.709 Tubo 1½"x19', PVC SDR-26 + 10% desp. 11 u 315.90 3,474.90 101.73% 3,415.94

Subtotal 58,468.95 101.64% 57,523.1810 Miscelaneos 2.00% 1,169.38 101.64% 1,150.4611 Mano de obra especializada 25.00% 14,617.24 101.64% 14,380.80

Acometida 74,255.57 101.64% 73,054.44m $1,325.99 101.64% 1,304.54

*IEACO 10530006 ACOM. CABLE Y TELEF. 1ER. N., CASETA HASTA REG. ESCALERA 58.00 m1 Alambre dulce #18 como mensajero 3.00 lb 34.64 103.92 101.70% 102.182 Bote material excavado en zanja 2.67 m3 351.88 939.52 101.73% 923.583 Cemento PVC Cano, ¼ gl. 0.0879 u 289.10 25.41 101.72% 24.984 Codo 2"x90, PVC 6 u 33.45 200.70 101.70% 197.345 Excavación zanja para tuberías, roca Long. Zanja (m.): 46.00 1.84 m3 2,127.44 3,914.49 100.00% 3,914.496 Registro 24"x24", usa, hg 4 u 1,938.74 7,754.96 101.72% 7,623.527 Relleno granular 1.84 m3 1,203.70 2,214.81 101.52% 2,181.698 Tubo 2"x19', PVC SDR-26 + 10% desp. 12 u 389.40 4,672.80 101.72% 4,593.60

Subtotal 19,826.61 101.36% 19,561.389 Miscelaneos 2.00% 396.53 101.35% 391.2310 Mano de obra especializada 25.00% 4,956.65 101.36% 4,890.35

Acometida 25,179.79 101.36% 24,842.96m $434.13 101.35% 428.33

Registro $6,294.95 101.36% 6,210.74*IEACO 10530007 ACOM. CABLE Y TELEF. , CADA NIVEL EN ESCALERA 2.80 m

1 Alambre dulce #18 como mensajero 1.00 lb 34.64 34.64 101.70% 34.062 Cemento PVC Cano, ¼ gl. 0.0261 u 289.10 7.55 101.75% 7.423 Codo 2"x90, PVC 2 u 33.45 66.90 101.70% 65.784 Registro 24"x24", usa, hg 3 u 1,938.74 5,816.22 101.72% 5,717.645 Tubo 2"x19', PVC SDR-26 + 10% desp. 1 u 389.40 389.40 101.72% 382.80

Subtotal 6,314.71 101.72% 6,207.706 Miscelaneos 2.00% 126.29 101.72% 124.157 Mano de obra especializada 25.00% 1,578.68 101.72% 1,551.93

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 71

Page 74: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

Acometida 8,019.68 101.72% 7,883.78m $2,864.17 101.72% 2,815.64

Registro $2,673.23 101.72% 2,627.93*IEACO 10530008 ACOM. CABLE, CADA NIVEL DESDE ESCALERA HACIA ADENTRO 8.30 m

1 Alambre dulce #18 como mensajero 1.00 lb 34.64 34.64 101.70% 34.062 Cemento PVC Cano, ¼ gl. 0.0109 u 289.10 3.15 101.61% 3.103 Codo ¾"x90, PVC 2 u 6.68 13.36 101.67% 13.144 Registro 6"x6", criollo, hg 1 u 132.16 132.16 101.72% 129.925 Tubo ¾"x19', PVC SDR-26 + 10% desp. 2 u 86.15 172.30 101.72% 169.38

Subtotal 355.61 101.72% 349.606 Miscelaneos 2.00% 7.11 101.72% 6.997 Mano de obra especializada 25.00% 88.90 101.72% 87.40

Acometida 807.23 101.72% 793.59m $97.26 101.73% 95.61

Registro $807.23 101.72% 793.59*IEACO 10530009 ACOM. TELEF., CADA NIVEL DESDE ESCALERA HACIA ADENTRO 8.30 m

1 Alambre dulce #18 como mensajero 1.00 lb 34.64 34.64 101.70% 34.062 Cemento PVC Cano, ¼ gl. 0.0005 u 289.10 0.14 100.00% 0.143 Codo ½"x90, PVC 0 u 5.88 0.00 0.004 Registro 4"x4", USA, hg 1 u 55.81 55.81 101.71% 54.875 Tubo ½"x19', PVC SDR-26 + 10% desp. 2 u 61.80 123.60 101.73% 121.50

Subtotal 214.19 101.72% 210.576 Miscelaneos 2.00% 4.28 101.66% 4.217 Mano de obra especializada 25.00% 53.55 101.73% 52.64

Acometida 486.21 101.72% 477.99m $58.58 101.72% 57.59

Registro $486.21 101.72% 477.99*IEACO 10530010 ACOM. TRIF. DESDE PANEL "PAC" HASTA ASCENSOR 30.50 m

1 Alambre No. 6 THW, 3 cond. (1 en c/fase) 331.00 p 91.28 30,213.68 101.72% 29,703.942 Alambre No. 6 THW, 1 cond., neutro 111.00 p 54.41 6,039.51 101.72% 5,937.393 Alambre No. 6 THW, 1 cond., tierra 111.00 p 12.43 1,379.73 101.80% 1,355.314 Bote material excavado en zanja 0.23 m3 351.88 80.93 101.72% 79.565 Cemento PVC Cano, ¼ gl. 0.0315 u 289.10 9.11 101.79% 8.956 Codo 1½"x90, PVC 2 u 34.18 68.36 101.70% 67.227 Excavación zanja para tuberías, roca Long. Zanja (m.): 4.00 0.16 m3 2,127.44 340.39 100.00% 340.398 Relleno granular 0.16 m3 1,203.70 192.59 101.52% 189.719 Tubo 1½"x19', PVC SDR-26 + 10% desp. 6 u 315.90 1,895.40 101.73% 1,863.24

Subtotal 40,219.70 101.70% 39,545.7110 Miscelaneos 2.00% 804.39 101.70% 790.9111 Mano de obra especializada 25.00% 10,054.93 101.70% 9,886.43

Acometida 51,079.02 101.70% 50,223.05m $1,674.72 101.70% 1,646.66

*IEACO 10530011 ACOM. TRIF. DESDE PANEL "PAC" HASTA BOMBAS DE AGUA 31.50 m1 Alambre No. 2 THW, 3 alambres 341.00 p 91.28 31,126.48 101.72% 30,601.342 Alambre No. 4 THW, 1 alambre, neutro 114.00 p 54.41 6,202.74 101.72% 6,097.863 Alambre No. 10 THW, 1 alambre, tierra 114.00 p 12.43 1,417.02 101.80% 1,391.944 Bote material excavado en zanja 1.68 m3 351.88 591.16 101.73% 581.135 Cemento PVC Cano, ¼ gl. 0.0315 u 289.10 9.11 101.79% 8.956 Codo 1½"x90, PVC 2 u 34.18 68.36 101.70% 67.227 Excavación zanja para tuberías, roca Long. Zanja (m.): 29.00 1.16 m3 2,127.44 2,467.83 100.00% 2,467.838 Relleno granular 1.16 m3 1,203.70 1,396.29 101.52% 1,375.419 Tubo 1½"x19', PVC SDR-26 + 10% desp. 6 u 315.90 1,895.40 101.73% 1,863.24

Subtotal 45,174.39 101.62% 44,454.9210 Miscelaneos 2.00% 903.49 101.62% 889.1011 Mano de obra especializada 25.00% 11,293.60 101.62% 11,113.73

Acometida 57,371.48 101.62% 56,457.75m $1,821.32 101.62% 1,792.31

*IESAL 10550000 INSTALACION ELECTRICA: SALIDAS Y PANELES

*IESAL 10550001 LUZ CENITAL:1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 61.80 61.80 101.73% 60.752 Caja octagonal 1.00 u 38.33 38.33 101.73% 37.683 Alambre #12 TW 40.00 p 7.87 314.80 101.68% 309.604 Roseta de porcelana 1.00 u 51.92 51.92 101.72% 51.045 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.296 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.557 Mano de obra 1.00 u 443.77 443.77 100.00% 443.778 Gastos indirectos contratistas eléctricos 20.00% 184.94 100.87% 183.34

Unid. $1,109.64 100.87% 1,100.02*IESAL 10550002 INTERRUPTOR SENCILLO:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 61.80 61.80 101.73% 60.752 Caja rectangular de ½" 1.00 u 32.67 32.67 101.71% 32.123 Alambre #12 TW 40.00 p 7.87 314.80 101.68% 309.604 Accesorio 1.00 u 47.68 47.68 101.71% 46.885 Codos plásticos ½" 1.00 u 5.88 5.88 101.73% 5.786 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.297 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.558 Mano de obra 1.00 u 443.77 443.77 100.00% 443.779 Beneficios contratistas eléctricos 20.00% 184.14 100.87% 182.55

Unid. $1,104.82 100.87% 1,095.29*IESAL 10550003 INTERRUPTOR DOBLE:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 61.80 61.80 101.73% 60.752 Caja rectangular ½" 1.00 u 32.67 32.67 101.71% 32.123 Alambre #12 TW 60.00 p 7.87 472.20 101.68% 464.404 Accesorio 1.00 u 163.69 163.69 101.72% 160.925 Codos plásticos ½" 1.00 u 5.88 5.88 101.73% 5.786 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.297 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.558 Mano de obra 1.00 u 537.71 537.71 100.00% 537.719 Beneficios contratistas eléctricos 20.00% 257.61 100.98% 255.10

Unid. $1,545.64 100.98% 1,530.62*IESAL 10550004 INTERRUPTOR TRIPLE:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 61.80 61.80 101.73% 60.75PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 72

Page 75: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

2 Caja rectangular ½" 1.00 u 32.67 32.67 101.71% 32.123 Alambre #12 TW 80.00 p 7.87 629.60 101.68% 619.204 Accesorio 1.00 u 184.08 184.08 101.72% 180.965 Codos plásticos ½" 1.00 u 5.88 5.88 101.73% 5.786 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.297 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.558 Mano de obra 1.00 u 599.26 599.26 100.00% 599.269 Beneficios contratistas eléctricos 20.00% 305.47 101.02% 302.38

Unid. $1,832.84 101.02% 1,814.29*IESAL 10550005 INTERRUPTOR TRES VIAS:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 61.80 61.80 101.73% 60.752 Caja rectangular ½" 1.00 u 32.67 32.67 101.71% 32.123 Alambre #12 TW 60.00 p 7.87 472.20 101.68% 464.404 Accesorio 1.00 u 85.22 85.22 101.72% 83.785 Codos plásticos ½" 1.00 u 5.88 5.88 101.73% 5.786 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.297 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.558 Mano de obra 1.00 u 537.71 537.71 100.00% 537.719 Beneficios contratistas eléctricos 20.00% 241.91 100.93% 239.68

Unid. $1,451.47 100.93% 1,438.06*IESAL 10550006 INTERRUPTOR CUATRO VIAS:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 61.80 61.80 101.73% 60.752 Caja rectangular ½" 1.00 u 32.67 32.67 101.71% 32.123 Alambre #12 TW 80.00 p 7.87 629.60 101.68% 619.204 Accesorio 1.00 u 438.42 438.42 101.72% 430.995 Codos plásticos ½" 1.00 u 5.88 5.88 101.73% 5.786 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.297 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.558 Mano de obra 1.00 u 659.18 659.18 100.00% 659.189 Beneficios contratistas eléctricos 20.00% 368.33 101.09% 364.37

Unid. $2,209.96 101.09% 2,186.23*IESAL 10550007 INTERRUPTOR PILOTO:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 61.80 61.80 101.73% 60.752 Caja rectangular ½" 1.00 u 32.67 32.67 101.71% 32.123 Alambre #12 TW 60.00 p 7.87 472.20 101.68% 464.404 Accesorio 1.00 u 220.21 220.21 101.72% 216.485 Codos plásticos ½" 1.00 u 5.88 5.88 101.73% 5.786 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.297 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.558 Mano de obra 1.00 u 537.71 537.71 100.00% 537.719 Beneficios contratistas eléctricos 20.00% 268.91 101.01% 266.22

Unid. $1,613.46 101.01% 1,597.30*IESAL 10550008 TOMACORRIENTE DOBLE 110 V.:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 61.80 61.80 101.73% 60.752 Caja rectangular ½" 1.00 u 32.67 32.67 101.71% 32.123 Alambre #12 TW+ 5% desp. 60.00 p 7.87 472.20 101.68% 464.404 Accesorio 1.00 u 36.34 36.34 101.71% 35.735 Codos plásticos ½" 2.00 u 5.88 11.76 101.73% 11.566 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.297 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.558 Mano de obra 1.00 u 443.77 443.77 100.00% 443.779 Beneficios contratistas eléctricos 20.00% 214.52 100.98% 212.43

Unid. $1,287.14 100.98% 1,274.60*IESAL 10550009 TOMACORRIENTE SENCILLO 220 V.:

1 Tubo ¾"x10' PVC SDR-26 + 15% desp. 2.00 u 86.15 172.30 101.72% 169.382 Caja rectangular ¾". 1.00 u 36.05 36.05 101.72% 35.443 Alambre #10 TW + 5% desp. 80.00 p 12.43 994.40 101.80% 976.804 Alambre #12 TW+ 5% desp. 40.00 p 7.87 314.80 101.68% 309.605 Accesorio 1.00 u 96.56 96.56 101.73% 94.926 Codos plásticos ¾". 2.00 u 6.68 13.36 101.67% 13.147 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.298 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.559 Mano de obra 1.00 u 505.14 505.14 100.00% 505.1410 Beneficios contratistas eléctricos 20.00% 429.34 101.34% 423.65

Unid. $2,576.03 101.34% 2,541.91*IESAL 10550010 SALIDA CALENTADOR:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 2.00 u 61.80 123.60 101.73% 121.502 Caja rectangular ½" 1.00 u 32.67 32.67 101.71% 32.123 Alambre #12 TW+ 5% desp. 40.00 p 7.87 314.80 101.68% 309.604 Accesorio 1.00 u 96.56 96.56 101.73% 94.925 Codos plásticos ½" 2.00 u 5.88 11.76 101.73% 11.566 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.297 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.558 Mano de obra 1.00 u 505.14 505.14 100.00% 505.149 Beneficios contratistas eléctricos 20.00% 219.72 100.91% 217.74

Unid. $1,318.33 100.91% 1,306.42*IESAL 10550011 SALIDA TELEFONO:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 2.00 u 61.80 123.60 101.73% 121.502 Caja rectangular ½" 1.00 u 32.67 32.67 101.71% 32.123 Alambre dulce #18+ 5% desp. 0.33 lb 34.64 11.43 101.69% 11.244 Accesorio (tapa ciega pvc). 1.00 u 18.88 18.88 101.72% 18.565 Codos plásticos ½" 2.00 u 5.88 11.76 101.73% 11.566 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.557 Mano de obra 1.00 u 443.77 443.77 100.00% 443.778 Beneficios contratistas eléctricos 20.00% 129.14 100.53% 128.46

Unid. $774.86 100.53% 770.76*IESAL 10550012 TIMBRE CORRIENTE:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.50 u 61.80 92.70 101.72% 91.132 Caja rectangular ½" 1.00 u 32.67 32.67 101.71% 32.123 Alambre #14 TW+ 5% desp. 100.00 p 5.32 532.00 101.72% 523.004 Accesorio 1.00 u 491.33 491.33 101.72% 483.005 Codos plásticos ½" 1.00 u 5.88 5.88 101.73% 5.786 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.297 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.55

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 73

Page 76: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

8 Mano de obra 1.00 u 443.77 443.77 100.00% 443.779 Beneficios contratistas eléctricos 20.00% 322.49 101.24% 318.53

Unid. $1,934.92 101.24% 1,911.17*IESAL 10550013 BOTON DE TIMBRE:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.50 u 61.80 92.70 101.72% 91.132 Caja rectangular ½" 1.00 u 32.67 32.67 101.71% 32.123 Alambre #14 TW + 5% desp. 50.00 p 5.32 266.00 101.72% 261.504 Accesorio 1.00 u 169.52 169.52 101.73% 166.645 Codos plásticos ½" 2.00 u 5.88 11.76 101.73% 11.566 Cinta adhesiva "3M" (rollo) 0.05 u 209.39 10.47 101.75% 10.297 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 289.10 3.61 101.69% 3.558 Mano de obra 1.00 u 443.77 443.77 100.00% 443.779 Beneficios contratistas eléctricos 20.00% 206.10 100.97% 204.11

Unid. $1,236.60 100.97% 1,224.67*IESAL 10550014 PANEL DISTRIBUCION 2 ESPACIOS, 1 PH:

1 "Breakers" 15 A. 2.00 u 152.22 304.44 101.72% 299.282 Panel distribución. 1.00 u 489.70 489.70 101.72% 481.403 Hacer hueco y colocar panel 1.00 u 621.93 621.93 100.00% 621.934 Coloc. "Breakers" 2.00 u 100.41 200.82 100.00% 200.825 Beneficios contratistas eléctricos 20.00% 323.38 100.84% 320.69

Unid. $1,940.27 100.84% 1,924.12*IESAL 10550015 PANEL DISTRIBUCION 4 ESPACIOS, 1 PH:

1 "Breakers" 15 A. 4.00 u 152.22 608.88 101.72% 598.562 Panel distribución. 1.00 u 820.10 820.10 101.72% 806.203 Hacer hueco y colocar panel 1.00 u 621.93 621.93 100.00% 621.934 Coloc. "Breakers" 4.00 u 100.41 401.64 100.00% 401.645 Beneficios contratistas eléctricos 20.00% 490.51 101.00% 485.67

Unid. $2,943.06 101.00% 2,914.00*IESAL 10550016 PANEL DISTRIBUCION 6 ESPACIOS, 1 PH:

1 "Breakers" 15 y 20 A. 6.00 u 152.22 913.32 101.72% 897.842 Panel distribución. 1.00 u 1,232.81 1,232.81 101.72% 1,211.913 Hacer hueco y colocar panel 1.00 u 621.93 621.93 100.00% 621.934 Coloc. "Breakers" 6.00 u 100.41 602.46 100.00% 602.465 Beneficios contratistas eléctricos 20.00% 674.10 101.09% 666.83

Unid. $4,044.62 101.09% 4,000.97*IESAL 10550017 PANEL DISTRIBUCION 8 ESPACIOS, 1 PH:

1 "Breakers" 15 y 20 A. 8.00 u 152.22 1,217.76 101.72% 1,197.122 Panel distribución. 1.00 u 2,188.90 2,188.90 101.72% 2,151.803 Hacer hueco y colocar panel 1.00 u 621.93 621.93 100.00% 621.934 Coloc. "Breakers" 8.00 u 100.41 803.28 100.00% 803.285 Beneficios contratistas eléctricos 20.00% 966.37 101.21% 954.83

Unid. $5,798.24 101.21% 5,728.96*IESAL 10550018 PANEL DISTRIBUCION 12 ESPACIOS, 1 PH:

1 "Breakers" 15 y 20 A. 12.00 u 152.22 1,826.64 101.72% 1,795.682 Panel distribución. 1.00 u 2,188.90 2,188.90 101.72% 2,151.803 Hacer hueco y colocar panel 1.00 u 621.93 621.93 100.00% 621.934 Coloc. "Breakers" 12.00 u 100.41 1,204.92 100.00% 1,204.925 Beneficios contratistas eléctricos 20.00% 1,168.48 101.18% 1,154.87

Unid. $7,010.87 101.18% 6,929.20*IESAL 10550019 PANEL DISTRIBUCION 16 ESPACIOS, 1 PH:

1 "Breakers" 15 y 20 A. 16.00 u 152.22 2,435.52 101.72% 2,394.242 Panel distribución. 1.00 u 2,188.90 2,188.90 101.72% 2,151.803 Hacer hueco y colocar panel 1.00 u 621.93 621.93 100.00% 621.934 Coloc. "Breakers" 16.00 u 100.41 1,606.56 100.00% 1,606.565 Beneficios contratistas eléctricos 20.00% 1,370.58 101.16% 1,354.91

Unid. $8,223.49 101.16% 8,129.44*IESAL 10550020 PANEL DISTRIBUCION 24 ESPACIOS, 1 PH:

1 "Breakers" 15 y 20 A. 24.00 u 152.22 3,653.28 101.72% 3,591.362 Panel distribución. 1.00 u 2,188.90 2,188.90 101.72% 2,151.803 Hacer hueco y colocar panel 1.00 u 621.93 621.93 100.00% 621.934 Coloc. "Breakers" 24.00 u 100.41 2,409.84 100.00% 2,409.845 Beneficios contratistas eléctricos 20.00% 1,774.79 101.13% 1,754.99

Unid. $10,648.74 101.13% 10,529.92*IESAL 10550021 PANEL DISTRIB., 30 ESPACIOS, 3 PH.:

1 "Breakers" 20 A., 1 ph 9.00 u 152.22 1,369.98 101.72% 1,346.762 "Breakers" 30 A., 2 ph 1.00 u 483.93 483.93 101.72% 475.733 "Breakers" 60 A., 3 ph 2.00 u 2,796.60 5,593.20 101.72% 5,498.404 Cemento PVC Cano, ¼ gl. 0.0505 u 289.10 14.60 101.74% 14.355 Codos plásticos ½". 6.00 u 5.88 35.28 101.73% 34.686 Codos plásticos ¾". 6.00 u 6.68 40.08 101.67% 39.427 Coloc. "Breakers". 12.00 u 100.41 1,204.92 100.00% 1,204.928 Hacer hueco y colocar panel. 1.00 u 621.93 621.93 100.00% 621.939 Mortero 1:3 p/remendar para empotrar panel y tuberías 0.06 m3 4,929.27 295.76 101.64% 290.9910 Panel distribución. 1.00 u 6,464.95 6,464.95 101.72% 6,355.3711 Tubo ½"x20' PVC SDR-26 + 15% desp. 12.00 u 61.80 741.60 101.73% 729.0012 Tubo ¾"x20' PVC SDR-26 + 15% desp. 1.00 u 86.15 86.15 101.72% 84.6913 Beneficios contratistas eléctricos. 15.00% 2,529.93 101.53% 2,491.73

Unid. $19,482.31 101.53% 19,187.97*IESAL 10550022 TRANSFORMADOR PADMOUNTED, 225 KVA: (EN TORRES)

1 Base horm. 210 kg/cm2, 3/8" a 0.20 m. a. d., 1.50X1.20X0.20 M. 0.36 m3 2,110.47 759.77 101.57% 748.052 Tranformador 225 KVA, Pad-Mounted, 3ph, 7200, 120/208/240 v. 1 u 421,260.00 421,260.00 101.72% 414,120.00

Subtotal 422,019.77 101.72% 414,868.053 Miscelaneos 1.00% 4,220.20 101.72% 4,148.684 Mano de obra especializada y beneficios sub-contratista 25.00% 105,504.94 101.72% 103,717.015 Uso de grúa 1 hr. 4,720.00 4,720.00 101.72% 4,640.00

Unid. $536,464.91 101.72% 527,373.74

*ISASHG 10570000 INST. SANITARIA: APARATOS SANIT., TUB. HG Y M. DE OBRA

*ISASHG 10550023 BAJANTE O VENT. SANIT. 3" PVC SDR-411 Cemento pvc "Tangit", 460 gramos + 25% desp.. 0.0357 u 761.10 27.172 Codo 3"x90, pvc dren. 1.00 u 44.84 44.843 Mano de obra Bajante o Vent. p/piso 1.00 u 678.15 678.15 100.00% 678.15

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 74

Page 77: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

4 Tubo 3", pvc SDR-41 + 10% desp. 0.67 tubo 537.56 360.17Unid. $1,083.16 100.64% 1,076.29

*ISASHG 10550024 BAJANTE O VENT. SANIT. 4" PVC SDR-411 Cemento pvc "Tangit", 460 gramos + 25% desp.. 0.0500 u 761.10 38.062 Codo 4"x90, pvc dren. 1.00 u 100.30 100.303 Mano de obra Bajante o Vent. p/piso 1.00 u 763.43 763.43 100.00% 763.434 Tubo 4", pvc SDR-41 + 10% desp. 0.67 tubo 873.01 584.92

Unid. $1,448.65 100.81% 1,437.03*ISASHG 10550025 BAÑERA LIVIANA, BLANCA O A COLOR:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 249.77 42.46 101.72% 41.742 Sifón 2", pvc drenaje 1.00 u 94.40 94.40 101.72% 92.803 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.854 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.005 Codo 2"x90, pvc dren. 1.00 u 24.01 24.01 101.69% 23.616 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.457 Tee ½" h.g. (fría y cal.) 2.00 u 39.40 78.80 101.73% 77.468 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.90 tubo 495.60 446.04 101.72% 438.489 Codo ½" h.g. (fría y cal.) 3.00 u 27.77 83.31 101.76% 81.8710 Unión univ. ½", h.g. 2.00 u 76.57 153.14 101.73% 150.5411 Niple ½"x4", h.g. 2.00 u 44.76 89.52 101.73% 88.0012 Pintura OXIDO ROJO en tub. h.g. 0.09 gl 708.00 63.72 101.72% 62.6413 BAÑERA liviana blanca o a color 1.00 u 6,843.62 6,843.62 101.72% 6,727.6314 Mezcl. p/bañera, 3 puños, "SAYCO" 1.00 u 3,481.00 3,481.00 101.72% 3,422.0015 Desagüe autom. p/bañera, pvc 1.00 u 2,578.30 2,578.30 101.72% 2,534.6016 Sifón 2", pvc 1.00 u 94.40 94.40 101.72% 92.8017 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1418 Teflón + 25% desp. 1.50 rollo 10.80 16.20 101.76% 15.9219 Horm. frotado en base p/bañera 1.20 m2 798.93 958.72 101.21% 947.3020 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9621 Mano de obra desagüe de 2. 1.00 u 592.86 592.86 100.00% 592.8622 Mano de obra salidas ½" 3.00 u 592.86 1,778.58 100.00% 1,778.5823 Mano de obra albañilería, base p/bañera 1.00 u 251.00 251.00 100.00% 251.0024 Mano de obra coloc. mezcl. 1.00 u 592.86 592.86 100.00% 592.8625 Mano de obra coloc. bañera liviana. 1.00 u 1,356.30 1,356.30 100.00% 1,356.30

Unid. $19,793.71 101.29% 19,541.39*ISASHG 10550026 BAÑERA HIERRO FUNDIDO, BLANCA:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 249.77 42.46 101.72% 41.742 Sifón 2", pvc dren. 1.00 u 94.40 94.40 101.72% 92.803 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.854 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.005 Codo 2"x90, pvc dren. 1.00 u 24.01 24.01 101.69% 23.616 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.457 Tee ½" h.g. (fría y cal.) 2.00 u 39.40 78.80 101.73% 77.468 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.90 tubo 495.60 446.04 101.72% 438.489 Codo ½" h.g. (fría y cal.) 3.00 u 27.77 83.31 101.76% 81.8710 Unión univ. ½", h.g. 2.00 u 76.57 153.14 101.73% 150.5411 Niple ½"x4", h.g. 2.00 u 44.76 89.52 101.73% 88.0012 Pintura OXIDO ROJO en tub. h.g. 0.09 gl 708.00 63.72 101.72% 62.6413 BAÑERA hierro fundido bca. 1.00 u 15,222.00 15,222.00 101.72% 14,964.0014 Mezcl. p/bañera, 3 puños, "SAYCO" 1.00 u 3,481.00 3,481.00 101.72% 3,422.0015 Desagüe autom. p/bañera, pvc 1.00 u 2,578.30 2,578.30 101.72% 2,534.6016 Sifón 2", pvc 1.00 u 94.40 94.40 101.72% 92.8017 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1418 Teflón + 25% desp. 1.50 rollo 10.80 16.20 101.76% 15.9219 Horm. frotado en base p/bañera 1.20 m2 798.93 958.72 101.21% 947.3020 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9621 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8622 Mano de obra salidas ½" 3.00 u 592.86 1,778.58 100.00% 1,778.5823 Mano de obra albañilería, base p/bañera 1.00 u 251.00 251.00 100.00% 251.0024 Mano de obra coloc. mezcl. 1.00 u 592.86 592.86 100.00% 592.8625 Mano de obra coloc. bañera hierro fundido 1.00 u 1,435.60 1,435.60 100.00% 1,435.60

Unid. $28,251.39 101.42% 27,857.06*ISASHG 10550027 BAÑERA HIERRO FUNDIDO, A COLOR:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 249.77 42.46 101.72% 41.742 Sifón 2", pvc dren. 1.00 u 94.40 94.40 101.72% 92.803 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.854 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.005 Codo 2"x90, pvc dren. 1.00 u 24.01 24.01 101.69% 23.616 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.457 Tee ½" h.g. (fría y cal.) 2.00 u 39.40 78.80 101.73% 77.468 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.90 tubo 495.60 446.04 101.72% 438.489 Codo ½" h.g. (fría y cal.) 3.00 u 27.77 83.31 101.76% 81.8710 Unión univ. ½", h.g. 2.00 u 76.57 153.14 101.73% 150.5411 Niple ½"x4", h.g. 2.00 u 44.76 89.52 101.73% 88.0012 Pintura OXIDO ROJO en tub. h.g. 0.09 gl 708.00 63.72 101.72% 62.6413 BAÑERA hierro fundido a color 1.00 u 13,924.00 13,924.00 101.72% 13,688.0014 Mezcl. p/bañera, 3 puños, "SAYCO" 1.00 u 3,481.00 3,481.00 101.72% 3,422.0015 Desagüe autom. p/bañera, pvc 1.00 u 2,578.30 2,578.30 101.72% 2,534.6016 Sifón 2", pvc 1.00 u 94.40 94.40 101.72% 92.8017 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1418 Teflón + 25% desp. 1.50 rollo 10.80 16.20 101.76% 15.9219 Horm. frotado en base p/bañera 1.20 m2 798.93 958.72 101.21% 947.3020 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9621 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8622 Mano de obra salidas ½" 3.00 u 592.86 1,778.58 100.00% 1,778.5823 Mano de obra albañilería, base p/bañera 1.00 u 251.00 251.00 100.00% 251.0024 Mano de obra coloc. mezcl. 1.00 u 592.86 592.86 100.00% 592.8625 Mano de obra coloc. bañera hierro fundido 1.00 u 1,435.60 1,435.60 100.00% 1,435.60

Unid. $26,953.39 101.40% 26,581.06*ISASHG 10550028 BIDET BLANCO:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 249.77 42.46 101.72% 41.742 Sifón 2", pvc dren. 1.00 u 94.40 94.40 101.72% 92.803 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.854 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.00

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 75

Page 78: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

5 Codo 2"x90, pvc dren. 1.00 u 24.01 24.01 101.69% 23.616 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.457 Tee ½" h.g. (fría y cal.) 2.00 u 39.40 78.80 101.73% 77.468 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.20 tubo 495.60 99.12 101.72% 97.449 Codo ½" h.g. (fría y cal.) 4.00 u 27.77 111.08 101.76% 109.1610 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 14.16 28.32 101.72% 27.8411 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 708.00 14.16 101.72% 13.9212 BIDET bco. 1.00 u 2,708.10 2,708.10 101.72% 2,662.2013 Mezcl. p/bidet, completa, con boquilla 1.00 u 587.97 587.97 101.72% 578.0014 Tornillos fijación 1.00 juego 23.42 23.42 101.69% 23.0315 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1416 Llave angular 3/8" 2.00 u 177.00 354.00 101.72% 348.0017 Niple 3/8"x2 ½", cromo 2.00 u 29.50 59.00 101.72% 58.0018 Tubo flexible con tuerca 2.00 u 144.05 288.10 101.72% 283.2219 Cubrefalta 3/8", cromo 2.00 u 12.98 25.96 101.72% 25.5220 Teflón + 25% desp. 1.40 rollo 10.80 15.12 101.82% 14.8521 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9622 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8623 Mano de obra salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.7224 Mano de obra coloc. bidet 1.00 u 1,016.54 1,016.54 100.00% 1,016.54

Unid. $7,523.61 101.07% 7,444.31*ISASHG 10550029 BIDET A COLOR:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 249.77 42.46 101.72% 41.742 Sifón 2", pvc dren. 1.00 u 94.40 94.40 101.72% 92.803 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.854 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.005 Codo 2"x90, pvc dren. 1.00 u 24.01 24.01 101.69% 23.616 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.457 Tee ½" h.g. (fría y cal.) 2.00 u 39.40 78.80 101.73% 77.468 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.20 tubo 495.60 99.12 101.72% 97.449 Codo ½" h.g. (fría y cal.) 4.00 u 27.77 111.08 101.76% 109.1610 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 14.16 28.32 101.72% 27.8411 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 708.00 14.16 101.72% 13.9212 BIDET a color 1.00 u 3,051.73 3,051.73 101.72% 3,000.0013 Mezcl. p/bidet, completa, con boquilla 1.00 u 587.97 587.97 101.72% 578.0014 Tornillos fijación 1.00 juego 23.42 23.42 101.69% 23.0315 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1416 Llave angular 3/8" 2.00 u 177.00 354.00 101.72% 348.0017 Niple 3/8"x2 ½", cromo 2.00 u 29.50 59.00 101.72% 58.0018 Tubo flexible con tuerca 2.00 u 144.05 288.10 101.72% 283.2219 Cubrefalta 3/8", cromo 2.00 u 12.98 25.96 101.72% 25.5220 Teflón + 25% desp. 1.40 rollo 10.80 15.12 101.82% 14.8521 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9622 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8623 Mano de obra salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.7224 Mano de obra coloc. bidet 1.00 u 1,016.54 1,016.54 100.00% 1,016.54

Unid. $7,867.24 101.09% 7,782.11*ISASHG 10550030 DESAGÜE DE PISO 2", INSTALADO (TUB. MATRIZ 4"):

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 249.77 42.46 101.72% 41.742 Sifón 2", pvc dren. 1.00 u 94.40 94.40 101.72% 92.803 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.854 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.005 Codo 2"x90, pvc dren. 1.00 u 24.01 24.01 101.69% 23.616 Rejilla de piso 2", cromo 1.00 u 69.62 69.62 101.72% 68.447 Cemento pvc criollo, PINTA + 25% desp. 0.16 pinta 57.02 9.12 101.67% 8.978 Mano de obra desagüe 2" con parrilla 1.00 u 678.15 678.15 100.00% 678.15

Unid. $1,007.12 100.56% 1,001.56*ISASHG 10550031 DESAGÜE DE PISO 3", INSTALADO (TUB. MATRIZ 4"):

1 Tubo 3", pvc SDR-41 + 10% desp. 0.17 tubo 537.56 91.39 101.73% 89.842 Sifón 3", pvc dren. 1.00 u 186.92 186.92 101.73% 183.753 Yee red. 4"x3", pvc dren. 1.00 u 99.43 99.43 101.73% 97.744 Codo 3"x45, pvc dren. 1.00 u 33.04 33.04 101.72% 32.485 Codo 3"x90, pvc dren. 1.00 u 44.84 44.84 101.72% 44.086 Rejilla de piso 3" x 1 ½", cromo 1.00 u 69.62 69.62 101.72% 68.447 Cemento pvc criollo, PINTA + 25% desp. 0.23 pinta 57.02 13.11 101.71% 12.898 Mano de obra desagüe 3" con parrilla 1.00 u 763.43 763.43 100.00% 763.43

Unid. $1,301.78 100.71% 1,292.65*ISASHG 10550032 DESAGÜE DE PISO 4", INSTALADO (TUB. MATRIZ 4"):

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 873.01 148.41 101.72% 145.902 Sifón 4", pvc dren. 1.00 u 1,882.23 1,882.23 101.72% 1,850.323 Yee de 4"x4", pvc dren. 1.00 u 164.69 164.69 101.72% 161.904 Codo 4"x45, pvc dren. 1.00 u 81.43 81.43 101.72% 80.055 Codo 4"x90, pvc dren. 1.00 u 100.30 100.30 101.72% 98.606 Rejilla de piso 4", aluminio 1.00 u 45.54 45.54 101.74% 44.767 Cemento pvc criollo, PINTA + 25% desp. 0.30 pinta 57.02 17.11 101.72% 16.828 Mano de obra desagüe 4" con parrilla 1.00 u 763.43 763.43 100.00% 763.43

Unid. $3,203.14 101.31% 3,161.78*ISASHG 10550033 DESAGÜE DE PISO 4", INSTALADO (TUB. MATRIZ 6"):

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 873.01 148.41 101.72% 145.902 Sifón 4", pvc dren. 1.00 u 1,882.23 1,882.23 101.72% 1,850.323 Yee de 6"x4", pvc dren. 1.00 u 1,001.82 1,001.82 101.72% 984.844 Codo 4"x45, pvc dren. 1.00 u 81.43 81.43 101.72% 80.055 Codo 4"x90, pvc dren. 1.00 u 100.30 100.30 101.72% 98.606 Rejilla de piso 4", aluminio 1.00 u 45.54 45.54 101.74% 44.767 Cemento pvc criollo, PINTA + 25% desp. 0.30 pinta 57.02 17.11 101.72% 16.828 Mano de obra desagüe 4" 1.00 u 763.43 763.43 100.00% 763.43

Unid. $4,040.27 101.39% 3,984.72*ISASHG 10550034 DUCHA: (Agua fría solamente)

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 249.77 42.46 101.72% 41.742 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 1.00 u 24.01 24.01 101.69% 23.615 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.456 Tee ½" h.g. (fría y cal.) 1.00 u 39.40 39.40 101.73% 38.73

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 76

Page 79: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

7 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.51 tubo 495.60 252.76 101.73% 248.478 Codo ½" h.g. (fría y cal.) 2.00 u 27.77 55.54 101.76% 54.589 Unión univ. ½", h.g. 2.00 u 76.57 153.14 101.73% 150.5410 Niple ½"x4", h.g. 2.00 u 44.76 89.52 101.73% 88.0011 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 708.00 35.40 101.72% 34.8012 Ducha cte. plástica, ½", cromo 1.00 u 101.09 101.09 101.72% 99.3813 Llave de empotrar ½", cromo, NIBCO 1.00 u 413.00 413.00 101.72% 406.0014 Sifón 2", pvc + rejilla de piso 2" 1.00 u 164.02 164.02 101.72% 161.2415 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1416 Teflón + 25% desp. 1.00 rollo 10.80 10.80 101.79% 10.6117 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9618 Mano de obra desagüe de 2 con parrilla 1.00 u 678.15 678.15 100.00% 678.1519 Mano de obra salidas ½" 1.00 u 592.86 592.86 100.00% 592.8620 Mano de obra coloc. llave de empotrar 1.00 u 338.39 338.39 100.00% 338.3921 Mano de obra coloc. ducha 1.00 u 338.39 338.39 100.00% 338.39

Unid. $3,503.40 100.73% 3,477.89*ISASHG 10550035 FREG. A. INOX. DOBLE, H.G., MANGUERA:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 249.77 82.42 101.72% 81.032 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 2.00 u 24.01 48.02 101.69% 47.225 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.456 Tee ½" h.g. (fría y cal.) 3.00 u 39.40 118.20 101.73% 116.197 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 495.60 232.93 101.73% 228.988 Codo ½" h.g. (fría y cal.) 5.00 u 27.77 138.85 101.76% 136.459 Red. bushing ½" a 3/8", h.g. (fría y cal.) 3.00 u 14.16 42.48 101.72% 41.7610 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 708.00 35.40 101.72% 34.8011 FREG. DOBLE a. inox.. 1.00 u 1,056.10 1,056.10 101.72% 1,038.2012 Mezcl. "SAYCO" con manguera 1.00 u 2,082.30 2,082.30 101.72% 2,047.0113 Boquilla para freg., cromo 2.00 u 179.66 359.32 101.73% 353.2214 Sifón 1 ½", pvc 1.00 u 169.92 169.92 101.72% 167.0415 Desagüe doble para freg., pvc 1.00 u 170.46 170.46 101.72% 167.5716 "Silicone" para sellar (tubo) 1.00 u 181.72 181.72 101.72% 178.6417 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1418 Llave angular 3/8" 2.00 u 177.00 354.00 101.72% 348.0019 Niple 3/8"x2 ½", cromo 2.00 u 29.50 59.00 101.72% 58.0020 Cubrefalta 3/8", cromo 2.00 u 12.98 25.96 101.72% 25.5221 Tubo flexible con tuerca 2.00 u 144.05 288.10 101.72% 283.2222 Teflón + 25% desp. 2.00 rollo 10.80 21.60 101.79% 21.2223 Excavar y tapar zanja (tierra) 0.25 día 433.00 108.25 100.00% 108.2524 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8625 Mano de obra salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.7226 Mano de obra coloc. fregadero doble 1.00 u 1,086.69 1,086.69 100.00% 1,086.69

Unid. $8,562.81 101.12% 8,468.03*ISASHG 10550036 FREG. A. INOX. SENCILLO, H.G., MANGUERA:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 249.77 82.42 101.72% 81.032 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 2.00 u 24.01 48.02 101.69% 47.225 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.456 Tee ½" h.g. (fría y cal.) 3.00 u 39.40 118.20 101.73% 116.197 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 495.60 232.93 101.73% 228.988 Codo ½" h.g. (fría y cal.) 5.00 u 27.77 138.85 101.76% 136.459 Red. bushing ½" a 3/8", h.g. (fría y cal.) 3.00 u 14.16 42.48 101.72% 41.7610 Pintura OXIDO ROJO en tub.s h.g. 0.05 gl 708.00 35.40 101.72% 34.8011 FREG. SENCILLO a. inox. 1.00 u 1,736.25 1,736.25 101.72% 1,706.8212 Mezcl. "SAYCO" con manguera 1.00 u 2,082.30 2,082.30 101.72% 2,047.0113 Boquilla para freg., cromo 2.00 u 179.66 359.32 101.73% 353.2214 Sifón 1 ½", pvc 1.00 u 169.92 169.92 101.72% 167.0415 Desagüe doble para fregadero, pvc 1.00 u 170.46 170.46 101.72% 167.5716 "Silicone" para sellar (tubo) 1.00 u 181.72 181.72 101.72% 178.6417 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1418 Llave angular 3/8" 2.00 u 177.00 354.00 101.72% 348.0019 Niple 3/8"x2 ½", cromo 2.00 u 29.50 59.00 101.72% 58.0020 Cubrefalta 3/8", cromo 2.00 u 12.98 25.96 101.72% 25.5221 Tubo flexible con tuerca 2.00 u 144.05 288.10 101.72% 283.2222 Teflón + 25% desp. 2.00 rollo 10.80 21.60 101.79% 21.2223 Excavar y tapar zanja (tierra) 0.25 día 433.00 108.25 100.00% 108.2524 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8625 Mano de obra salidas ½" 2.00 u 763.43 1,526.86 100.00% 1,526.8626 Mano de obra coloc. fregadero sencillo 1.00 u 848.72 848.72 100.00% 848.72

Unid. $9,346.13 101.15% 9,239.82*ISASHG 10550037 INODORO BCO., TAPA: BAÑO SERVICIO

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 873.01 148.41 101.72% 145.902 Yee de 4"x4", pvc dren. 1.00 u 164.69 164.69 101.72% 161.903 Codo 4"x45, pvc dren. 1.00 u 81.43 81.43 101.72% 80.054 Codo 4"x90, pvc dren. 1.00 u 100.30 100.30 101.72% 98.605 Cemento pvc criollo, PINTA + 25% desp. 0.35 pinta 57.02 19.96 101.73% 19.626 Tee ½" h.g. (fría y cal.) 1.00 u 39.40 39.40 101.73% 38.737 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.17 tubo 495.60 84.25 101.73% 82.828 Codo ½" h.g. (fría y cal.) 2.00 u 27.77 55.54 101.76% 54.589 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 14.16 14.16 101.72% 13.9210 Pintura OXIDO ROJO en tub.s h.g. 0.02 gl 708.00 14.16 101.72% 13.9211 INODORO corriente, bco., CON tapa 1.00 u 3,675.70 3,675.70 101.72% 3,613.4012 Arandela pvc 4", para fijar inodoro 1.00 u 48.38 48.38 101.72% 47.5613 Tornillos fijación 1.00 juego 23.42 23.42 101.69% 23.0314 Junta de cera. 1.00 u 43.74 43.74 101.72% 43.0015 Cemento bco. 0.04 fda 649.00 25.96 101.72% 25.5216 Llave angular 3/8" 1.00 u 177.00 177.00 101.72% 174.0017 Niple 3/8"x2 ½", cromo 1.00 u 29.50 29.50 101.72% 29.0018 Cubrefalta 3/8", cromo 1.00 u 12.98 12.98 101.72% 12.7619 Tubo flexible con tuerca 1.00 u 122.61 122.61 101.72% 120.5420 Teflón + 25% desp. 0.70 rollo 10.80 7.56 101.75% 7.4321 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.96

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 77

Page 80: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

22 Mano de obra desagüe 4" 1.00 u 763.43 763.43 100.00% 763.4323 Mano de obra salidas ½" 1.00 u 763.43 763.43 100.00% 763.4324 Mano de obra coloc. Inodoro 1.00 u 678.15 678.15 100.00% 678.15

Unid. $7,146.12 101.17% 7,063.25*ISASHG 10550038 INODORO, BCO., TAPA: BAÑO SERV.

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 873.01 148.41 101.72% 145.902 Yee de 4"x4", pvc dren. 1.00 u 164.69 164.69 101.72% 161.903 Codo 4"x45, pvc dren. 1.00 u 81.43 81.43 101.72% 80.054 Codo 4"x90, pvc dren. 1.00 u 100.30 100.30 101.72% 98.605 Cemento pvc criollo, PINTA + 25% desp. 0.35 pinta 57.02 19.96 101.73% 19.626 Tee ½" h.g. (fría y cal.) 1.00 u 39.40 39.40 101.73% 38.737 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.17 tubo 495.60 84.25 101.73% 82.828 Codo ½" h.g. (fría y cal.) 2.00 u 27.77 55.54 101.76% 54.589 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 14.16 14.16 101.72% 13.9210 Pintura OXIDO ROJO en tub.s h.g. 0.02 gl 708.00 14.16 101.72% 13.9211 INODORO corriente, bco., tapa 1.00 u 3,919.96 3,919.96 101.72% 3,853.5212 Arandela pvc 4", para fijar inodoro 1.00 u 48.38 48.38 101.72% 47.5613 Tornillos fijación 1.00 juego 23.42 23.42 101.69% 23.0314 Junta de cera. 1.00 u 43.74 43.74 101.72% 43.0015 Cemento bco. 0.04 fda 649.00 25.96 101.72% 25.5216 Llave angular 3/8" 1.00 u 177.00 177.00 101.72% 174.0017 Niple 3/8"x2 ½", cromo 1.00 u 29.50 29.50 101.72% 29.0018 Cubrefalta 3/8", cromo 1.00 u 12.98 12.98 101.72% 12.7619 Tubo flexible con tuerca 1.00 u 122.61 122.61 101.72% 120.5420 Teflón + 25% desp. 0.70 rollo 10.80 7.56 101.75% 7.4321 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9622 Mano de obra desagüe 4" 1.00 u 763.43 763.43 100.00% 763.4323 Mano de obra salidas ½" 1.00 u 763.43 763.43 100.00% 763.4324 Mano de obra coloc. Inodoro 1.00 u 678.15 678.15 100.00% 678.15

Unid. $7,390.38 101.19% 7,303.37*ISASHG 10550039 INODORO ALARGADO BCO.:

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 873.01 148.41 101.72% 145.902 Yee de 4"x4", pvc dren. 1.00 u 164.69 164.69 101.72% 161.903 Codo 4"x45, pvc dren. 1.00 u 81.43 81.43 101.72% 80.054 Codo 4"x90, pvc dren. 1.00 u 100.30 100.30 101.72% 98.605 Cemento pvc criollo, PINTA + 25% desp. 0.35 pinta 57.02 19.96 101.73% 19.626 Tee ½" h.g. (fría y cal.) 1.00 u 39.40 39.40 101.73% 38.737 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.17 tubo 495.60 84.25 101.73% 82.828 Codo ½" h.g. (fría y cal.) 2.00 u 27.77 55.54 101.76% 54.589 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 14.16 14.16 101.72% 13.9210 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 708.00 14.16 101.72% 13.9211 INODORO alargado, bco., tapa 1.00 u 6,334.24 6,334.24 101.72% 6,226.8812 Arandela pvc 4", para fijar inodoro 1.00 u 48.38 48.38 101.72% 47.5613 Tornillos fijación 1.00 juego 23.42 23.42 101.69% 23.0314 Junta de cera. 1.00 u 43.74 43.74 101.72% 43.0015 Cemento bco. 0.04 fda 649.00 25.96 101.72% 25.5216 Llave angular 3/8" 1.00 u 177.00 177.00 101.72% 174.0017 Niple 3/8"x2 ½", cromo 1.00 u 29.50 29.50 101.72% 29.0018 Cubrefalta 3/8", cromo 1.00 u 12.98 12.98 101.72% 12.7619 Tubo flexible con tuerca 1.00 u 122.61 122.61 101.72% 120.5420 Teflón + 25% desp. 0.70 rollo 10.80 7.56 101.75% 7.4321 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9622 Mano de obra desagüe 4" 1.00 u 763.43 763.43 100.00% 763.4323 Mano de obra salidas ½" 1.00 u 763.43 763.43 100.00% 763.4324 Mano de obra coloc. Inodoro 1.00 u 678.15 678.15 100.00% 678.15

Unid. $9,804.66 101.32% 9,676.73*ISASHG 10550040 INODORO ALARGADO A COLOR:

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 873.01 148.41 101.72% 145.902 Yee de 4"x4", pvc dren. 1.00 u 164.69 164.69 101.72% 161.903 Codo 4"x45, pvc dren. 1.00 u 81.43 81.43 101.72% 80.054 Codo 4"x90, pvc dren. 1.00 u 100.30 100.30 101.72% 98.605 Cemento pvc criollo, PINTA + 25% desp. 0.35 pinta 57.02 19.96 101.73% 19.626 Tee ½" h.g. (fría y cal.) 1.00 u 39.40 39.40 101.73% 38.737 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.17 tubo 495.60 84.25 101.73% 82.828 Codo ½" h.g. (fría y cal.) 2.00 u 27.77 55.54 101.76% 54.589 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 14.16 14.16 101.72% 13.9210 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 708.00 14.16 101.72% 13.9211 INODORO alargado, color, tapa 1.00 u 6,965.45 6,965.45 101.72% 6,847.3912 Arandela pvc de 4", para fijar inodoro 1.00 u 48.38 48.38 101.72% 47.5613 Tornillos fijación 1.00 juego 23.42 23.42 101.69% 23.0314 Junta de cera. 1.00 u 43.74 43.74 101.72% 43.0015 Cemento bco. 0.04 fda 649.00 25.96 101.72% 25.5216 Llave angular 3/8" 1.00 u 177.00 177.00 101.72% 174.0017 Niple 3/8"x2 ½", cromo 1.00 u 29.50 29.50 101.72% 29.0018 Cubrefalta 3/8", cromo 1.00 u 12.98 12.98 101.72% 12.7619 Tubo flexible con tuerca 1.00 u 122.61 122.61 101.72% 120.5420 Teflón + 25% desp. 0.70 rollo 10.80 7.56 101.75% 7.4321 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9622 Mano de obra desagüe 4" 1.00 u 763.43 763.43 100.00% 763.4323 Mano de obra salidas ½" 1.00 u 763.43 763.43 100.00% 763.4324 Mano de obra coloc. Inodoro 1.00 u 678.15 678.15 100.00% 678.15

Unid. $10,435.87 101.35% 10,297.24*ISASHG 10550041 LAVADERO GRANITO BCO., DOBLE:

1 Tubo 2", pvc SDR-41 + 10% desp. (enterrado). 0.17 tubo 249.77 42.46 101.72% 41.742 Tubo 1 ½", pvc dren. + 10% desp. (visible). 0.22 tubo 127.44 28.04 101.74% 27.563 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.854 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.005 Codo 2"x90, pvc dren. 1.00 u 24.01 24.01 101.69% 23.616 Sifón 2", pvc 1.00 u 94.40 94.40 101.72% 92.807 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.458 Tee ½" h.g. (fría y cal.) 2.00 u 39.40 78.80 101.73% 77.469 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.46 tubo 495.60 227.98 101.73% 224.1110 Codo ½" h.g. (fría y cal.) 4.00 u 27.77 111.08 101.76% 109.1611 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 708.00 35.40 101.72% 34.80

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 78

Page 81: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

12 Lavadero GRANITO, doble 1.00 u 4,084.51 4,084.51 101.72% 4,015.2813 Transporte lavadero Sto. Dgo., (variable) 1.00 u 118.00 118.00 101.72% 116.0014 Boquilla para lavadero, cromo, con tapón 2.00 u 132.83 265.66 101.72% 261.1615 Parrilla de piso 4", aluminio 1.00 u 45.54 45.54 101.74% 44.7616 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1417 Llave de chorro ½" 2.00 u 324.50 649.00 101.72% 638.0018 Teflón + 25% desp. 1.10 rollo 10.80 11.88 101.80% 11.6719 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9620 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8621 Mano de obra salida ½" 2.00 u 592.86 1,185.72 100.00% 1,185.7222 Mano de obra coloc. lavadero doble 1.00 u 763.43 763.43 100.00% 763.43

Unid. $8,533.24 101.19% 8,432.52*ISASHG 10550042 LAVADERO GRANITO BCO., SENCILLO:

1 Tubo 2", pvc SDR-41 + 10% desp. (enterrado). 0.17 tubo 249.77 42.46 101.72% 41.742 Tubo 1 ½", pvc dren. + 10% desp. (visible). 0.11 tubo 127.44 14.02 101.74% 13.783 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.854 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.005 Codo 2"x90, pvc dren. 1.00 u 24.01 24.01 101.69% 23.616 Sifón 2", pvc 1.00 u 94.40 94.40 101.72% 92.807 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.458 Tee ½" h.g. (fría y cal.) 1.00 u 39.40 39.40 101.73% 38.739 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.37 tubo 495.60 183.37 101.73% 180.2610 Codo ½" h.g. (fría y cal.) 2.00 u 27.77 55.54 101.76% 54.5811 Pintura OXIDO ROJO en tub. h.g. 0.04 gl 708.00 28.32 101.72% 27.8412 Lavadero GRANITO, sencillo 1.00 u 2,603.63 2,603.63 101.72% 2,559.5013 Transporte lavadero Sto. Dgo., (variable) 1.00 u 88.50 88.50 101.72% 87.0014 Boquilla para lavadero, cromo, con tapón 1.00 u 132.83 132.83 101.72% 130.5815 Parrilla de piso 4", aluminio 1.00 u 45.54 45.54 101.74% 44.7616 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1417 Llave de chorro ½" 1.00 u 324.50 324.50 101.72% 319.0018 Teflón + 25% desp. 0.50 rollo 10.80 5.40 101.69% 5.3119 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9620 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8621 Mano de obra salida ½" 1.00 u 592.86 592.86 100.00% 592.8622 Mano de obra tub. ½" en piso 0.60 m 12.38 7.43 100.00% 7.4323 Mano de obra coloc. lavadero sencillo 1.00 u 592.86 592.86 100.00% 592.86

Unid. $5,642.40 101.16% 5,577.90*ISASHG 10550043 LAVAMANOS 19"x17", BCO.:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 249.77 82.42 101.72% 81.032 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 2.00 u 24.01 48.02 101.69% 47.225 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.456 Tee ½" h.g. (fría y cal.) 2.00 u 39.40 78.80 101.73% 77.467 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 495.60 232.93 101.73% 228.988 Codo ½" h.g. (fría y cal.) 4.00 u 27.77 111.08 101.76% 109.169 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 14.16 28.32 101.72% 27.8410 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 708.00 35.40 101.72% 34.8011 Lavamanos 19"x17", BCO. 1.00 u 1,342.51 1,342.51 101.72% 1,319.7612 Mezcl. "SAYCO" con boquilla cromo 1.00 u 2,448.50 2,448.50 101.72% 2,407.0013 Sifón 1 ¼", cromo, NIBCO 1.00 u 465.90 465.90 101.72% 458.0014 Cola ext. 1 ¼"x8", cromo 1.00 u 141.60 141.60 101.72% 139.2015 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1416 Llave angular 3/8" 2.00 u 177.00 354.00 101.72% 348.0017 Niple 3/8"x2 ½", cromo 2.00 u 29.50 59.00 101.72% 58.0018 Cubrefalta 3/8", cromo 2.00 u 12.98 25.96 101.72% 25.5219 Tubo flexible con tuerca 2.00 u 144.05 288.10 101.72% 283.2220 Teflón + 25% desp. 1.40 rollo 10.80 15.12 101.82% 14.8521 Excavar y tapar zanja (tierra) 0.25 día 433.00 108.25 100.00% 108.2522 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8623 Mano de obra salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.7224 Mano de obra coloc. lavamanos 1.00 u 678.15 678.15 100.00% 678.15

Unid. $8,445.15 101.19% 8,345.46*ISASHG 10550044 LAVAMANOS 19"x17", COLOR:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 249.77 82.42 101.72% 81.032 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 2.00 u 24.01 48.02 101.69% 47.225 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.456 Tee ½" h.g. (fría y cal.) 2.00 u 39.40 78.80 101.73% 77.467 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 495.60 232.93 101.73% 228.988 Codo ½" h.g. (fría y cal.) 4.00 u 27.77 111.08 101.76% 109.169 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 14.16 28.32 101.72% 27.8410 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 708.00 35.40 101.72% 34.8011 Lavamanos 19"x17", color 1.00 u 1,544.29 1,544.29 101.72% 1,518.1212 Mezcl. "SAYCO" con boquilla cromo 1.00 u 2,448.50 2,448.50 101.72% 2,407.0013 Sifón 1 ¼", cromo, NIBCO 1.00 u 465.90 465.90 101.72% 458.0014 Cola ext. 1 ¼"x8", cromo 1.00 u 141.60 141.60 101.72% 139.2015 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1416 Llave angular 3/8" 2.00 u 177.00 354.00 101.72% 348.0017 Niple 3/8"x2 ½", cromo 2.00 u 29.50 59.00 101.72% 58.0018 Cubrefalta 3/8", cromo 2.00 u 12.98 25.96 101.72% 25.5219 Tubo flexible con tuerca 2.00 u 144.05 288.10 101.72% 283.2220 Teflón + 25% desp. 1.40 rollo 10.80 15.12 101.82% 14.8521 Excavar y tapar zanja (tierra) 0.25 día 433.00 108.25 100.00% 108.2522 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8623 Mano de obra salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.7224 Mano de obra coloc. lavamanos 1.00 u 678.15 678.15 100.00% 678.15

Unid. $8,646.93 101.21% 8,543.82*ISASHG 10550045 LAVAMANOS OVALADO BCO., empotrar:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 249.77 82.42 101.72% 81.032 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 2.00 u 24.01 48.02 101.69% 47.22

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 79

Page 82: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

5 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.456 Tee ½" h.g. (fría y cal.) 2.00 u 39.40 78.80 101.73% 77.467 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 495.60 232.93 101.73% 228.988 Codo ½" h.g. (fría y cal.) 4.00 u 27.77 111.08 101.76% 109.169 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 14.16 28.32 101.72% 27.8410 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 708.00 35.40 101.72% 34.8011 Lav. ovalado, BCO., empotrar, "SAONA" 1.00 u 2,243.79 2,243.79 101.72% 2,205.7612 Mezcl. "SAYCO" con boquilla cromo 1.00 u 2,448.50 2,448.50 101.72% 2,407.0013 Sifón 1 ¼", cromo, NIBCO 1.00 u 465.90 465.90 101.72% 458.0014 Cola ext. 1 ¼"x8", cromo 1.00 u 141.60 141.60 101.72% 139.2015 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1416 Llave angular 3/8" 2.00 u 177.00 354.00 101.72% 348.0017 Niple 3/8"x2 ½", cromo 2.00 u 29.50 59.00 101.72% 58.0018 Cubrefalta 3/8", cromo 2.00 u 12.98 25.96 101.72% 25.5219 Tubo flexible con tuerca 2.00 u 144.05 288.10 101.72% 283.2220 Teflón + 25% desp. 1.40 rollo 10.80 15.12 101.82% 14.8521 "Silicone" para sellar (tubo) 0.25 u 181.72 45.43 101.72% 44.6622 Excavar y tapar zanja (tierra) 0.25 día 433.00 108.25 100.00% 108.2523 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8624 Mano de obra salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.7225 Mano de obra coloc. lavamanos 1.00 u 678.15 678.15 100.00% 678.15

Unid. $9,391.86 101.25% 9,276.12*ISASHG 10550046 LAVAMANOS OVALADO COLOR, empotrar:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 249.77 82.42 101.72% 81.032 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 2.00 u 24.01 48.02 101.69% 47.225 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.456 Tee ½" h.g. (fría y cal.) 2.00 u 39.40 78.80 101.73% 77.467 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 495.60 232.93 101.73% 228.988 Codo ½" h.g. (fría y cal.) 4.00 u 27.77 111.08 101.76% 109.169 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 14.16 28.32 101.72% 27.8410 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 708.00 35.40 101.72% 34.8011 Lavamanos ovalado, COLOR, "SAONA" 1.00 u 2,482.52 2,482.52 101.72% 2,440.4412 Mezcl. "SAYCO" con boquilla cromo 1.00 u 2,448.50 2,448.50 101.72% 2,407.0013 Sifón 1 ¼", cromo, NIBCO 1.00 u 465.90 465.90 101.72% 458.0014 Cola ext. 1 ¼"x8", cromo 1.00 u 141.60 141.60 101.72% 139.2015 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1416 Llave angular 3/8" 2.00 u 177.00 354.00 101.72% 348.0017 Niple 3/8"x2 ½", cromo 2.00 u 29.50 59.00 101.72% 58.0018 Cubrefalta 3/8", cromo 2.00 u 12.98 25.96 101.72% 25.5219 Tubo flexible con tuerca 2.00 u 144.05 288.10 101.72% 283.2220 Teflón + 25% desp. 1.40 rollo 10.80 15.12 101.82% 14.8521 "Silicone" para sellar (tubo) 0.25 u 181.72 45.43 101.72% 44.6622 Excavar y tapar zanja (tierra) 0.25 día 433.00 108.25 100.00% 108.2523 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8624 Mano de obra salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.7225 Mano de obra coloc. lavamanos 1.00 u 678.15 678.15 100.00% 678.15

Unid. $9,630.59 101.26% 9,510.80*ISASHG 10550047 LAVAMANOS PEQUEÑO, BCO.: BAÑO SERV.

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 249.77 82.42 101.72% 81.032 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 2.00 u 24.01 48.02 101.69% 47.225 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.456 Tee ½" h.g. (fría y cal.) 1.00 u 39.40 39.40 101.73% 38.737 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.24 tubo 495.60 118.94 101.72% 116.938 Codo ½" h.g. (fría y cal.) 2.00 u 27.77 55.54 101.76% 54.589 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 14.16 14.16 101.72% 13.9210 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 708.00 14.16 101.72% 13.9211 Lavamanos BCO. pequeño, "SIMPLEX" 1.00 u 953.24 953.24 101.72% 937.0812 Llave sencilla, cromo 1.00 u 619.22 619.22 101.72% 608.7213 Boquilla para lavamanos, pvc 1.00 u 107.57 107.57 101.72% 105.7514 Sifón 1 ¼", pvc 1.00 u 71.92 71.92 101.73% 70.7015 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1416 Llave angular 3/8" 1.00 u 177.00 177.00 101.72% 174.0017 Niple 3/8"x2 ½", cromo 1.00 u 29.50 29.50 101.72% 29.0018 Cubrefalta 3/8", cromo 1.00 u 12.98 12.98 101.72% 12.7619 Tubo flexible con tuerca 1.00 u 144.05 144.05 101.72% 141.6120 Teflón + 25% desp. 0.70 rollo 10.80 7.56 101.75% 7.4321 Excavar y tapar zanja (tierra) 0.25 día 433.00 108.25 100.00% 108.2522 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8623 Mano de obra salidas ½" 1.00 u 592.86 592.86 100.00% 592.8624 Mano de obra coloc. lavamanos 1.00 u 678.15 678.15 100.00% 678.15

Unid. $4,590.31 100.98% 4,545.94*ISASHG 10550048 ORINAL ½ FALDA, BCO.:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 249.77 82.42 101.72% 81.032 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 2.00 u 24.01 48.02 101.69% 47.225 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.456 Tee ½" h.g. (fría y cal.) 1.00 u 39.40 39.40 101.73% 38.737 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.24 tubo 495.60 118.94 101.72% 116.938 Codo ½" h.g. (fría y cal.) 2.00 u 27.77 55.54 101.76% 54.589 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 14.16 14.16 101.72% 13.9210 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 708.00 14.16 101.72% 13.9211 Orinal ½ falda "Yaque" 1.00 u 9,987.93 9,987.93 101.72% 9,818.6512 Llave cromada p/orinal 1.00 u 565.17 565.17 101.72% 555.5913 Niple 3/8"x2 ½", cromo 1.00 u 29.50 29.50 101.72% 29.0014 Cubrefalta 3/8", cromo 1.00 u 12.98 12.98 101.72% 12.7615 Tubo flexible con tuerca 1.00 u 144.05 144.05 101.72% 141.6116 Teflón + 25% desp. 0.70 rollo 10.80 7.56 101.75% 7.4317 Excavar y tapar zanja (tierra) 0.25 día 433.00 108.25 100.00% 108.2518 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.86

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 80

Page 83: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

19 Mano de obra salidas ½" 1.00 u 592.86 592.86 100.00% 592.8620 Mano de obra coloc. Orinal ½ falda 1.00 u 763.43 763.43 100.00% 763.43

Unid. $13,280.27 101.45% 13,090.07*ISASHG 10550049 ORINAL ½ FALDA, BCO., FLUXOMETRO:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 249.77 82.42 101.72% 81.032 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 2.00 u 24.01 48.02 101.69% 47.225 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.456 Tee ¾" h.g. 1.00 u 29.50 29.50 101.72% 29.007 Tubo ¾" h.g. + 10% desp. 0.24 tubo 693.84 166.52 101.72% 163.708 Codo ¾" h.g. 2.00 u 25.96 51.92 101.72% 51.049 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 708.00 14.16 101.72% 13.9210 Orinal ½ falda "Yaque" 1.00 u 9,987.93 9,987.93 101.72% 9,818.6511 Válvula fluxómetro ¾" 1.00 u 4,211.42 4,211.42 101.72% 4,140.0412 Teflón + 25% desp. 0.50 rollo 10.80 5.40 101.69% 5.3113 Excavar y tapar zanja (tierra) 0.25 día 433.00 108.25 100.00% 108.2514 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8615 Mano de obra salidas ½" 1.00 u 763.43 763.43 100.00% 763.4316 Mano de obra coloc. Orinal ½ falda 1.00 u 763.43 763.43 100.00% 763.43

Unid. $16,928.30 101.49% 16,679.18*ISASHG 10550052 ORINAL PEQUEÑO, BCO.:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 249.77 82.42 101.72% 81.032 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 2.00 u 24.01 48.02 101.69% 47.225 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.456 Tee ½" h.g. (fría y cal.) 1.00 u 39.40 39.40 101.73% 38.737 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.24 tubo 495.60 118.94 101.72% 116.938 Codo ½" h.g. (fría y cal.) 2.00 u 27.77 55.54 101.76% 54.589 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 14.16 14.16 101.72% 13.9210 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 708.00 14.16 101.72% 13.9211 Orinal pequeño, bco. "Simplex" 1.00 u 2,441.54 2,441.54 101.72% 2,400.1612 Llave cromada p/orinal pequeño 1.00 u 565.17 565.17 101.72% 555.5913 Niple 3/8"x2 ½", cromo 1.00 u 29.50 29.50 101.72% 29.0014 Cubrefalta 3/8", cromo 1.00 u 12.98 12.98 101.72% 12.7615 Tubo flexible con tuerca 1.00 u 144.05 144.05 101.72% 141.6116 Teflón + 25% desp. 0.70 rollo 10.80 7.56 101.75% 7.4317 Excavar y tapar zanja (tierra) 0.25 día 433.00 108.25 100.00% 108.2518 Mano de obra desagüe 2" 1.00 u 592.86 592.86 100.00% 592.8619 Mano de obra salidas ½" 1.00 u 592.86 592.86 100.00% 592.8620 Mano de obra coloc. Orinal pequeño 1.00 u 848.72 848.72 100.00% 848.72

Unid. $5,819.17 101.08% 5,756.87*ISASHG 10550053 VERTEDERO O TINA DE GRANITO, GRIS:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 249.77 42.46 101.72% 41.742 Yee red. 4"x2", pvc dren. 1.00 u 70.03 70.03 101.71% 68.853 Codo 2"x45, pvc dren. 1.00 u 19.33 19.33 101.74% 19.004 Codo 2"x90, pvc dren. 1.00 u 24.01 24.01 101.69% 23.615 Sifón 2", pvc 1.00 u 94.40 94.40 101.72% 92.806 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 57.02 13.68 101.71% 13.457 Tee ½" galv. 1.00 u 39.40 39.40 101.73% 38.738 Tubo ½" galv. + 10% desp. 0.24 tubo 495.60 118.94 101.72% 116.939 Codo ½" galv. 2.00 u 27.77 55.54 101.76% 54.5810 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 708.00 14.16 101.72% 13.9211 Vertedero de GRANITO de una boca 1.00 u 2,026.23 2,026.23 101.72% 1,991.8912 Transporte vertedero en Sto. Dgo. (variable) 1.00 u 88.50 88.50 101.72% 87.0013 Parrilla de piso 4", aluminio 1.00 u 45.54 45.54 101.74% 44.7614 Cemento bco. 0.03 fda 649.00 19.47 101.72% 19.1415 Llave de chorro ½" 1.00 u 324.50 324.50 101.72% 319.0016 Teflón + 25% desp. 0.50 rollo 10.80 5.40 101.69% 5.3117 Excavar y tapar zanja (tierra) 0.12 día 433.00 51.96 100.00% 51.9618 Mano de obra desagüe 2" 1.00 u 678.15 678.15 100.00% 678.1519 Mano de obra salida ½" 1.00 u 592.86 592.86 100.00% 592.8620 Mano de obra tub. ½" en piso 0.30 m 12.38 3.71 100.00% 3.7121 Mano de obra coloc. vertedero sencillo 1.00 u 170.57 170.57 100.00% 170.57

Unid. $4,498.84 101.14% 4,447.96

*ISCIS 10590000 INST. SANITARIA: CAMARAS INSP., CISTERNAS, SEPTICOS Y TRAMPAS DE GRASA

*ISCIS 10590001 CAMARA INSP., CALICHE, .60X.60X.60 M. INT.:1 Excavación caliche (.8x.8x.8 m.). 0.512 m3 441.84 226.22 100.00% 226.222 Bote material excavado 0.690 m3 351.88 242.80 101.73% 238.683 Horm. 1:3:5 en losas 0.049 m3 4,432.36 217.19 101.50% 213.994 Acero ¼" incrustado losa 0.003 qq 1,519.73 4.56 101.79% 4.485 Acero 3/8" x 20' grado 40 en tapa 0.180 qq 2,114.09 380.54 101.72% 374.096 Bloques 4" sin mano de obra albañilería 1.646 m2 464.23 764.12 101.67% 751.567 Horm. 1:3:5 en int. 0.029 m3 4,432.36 128.54 101.49% 126.658 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0069 m3 7,806.60 53.87 101.68% 52.989 Mano de obra 1.00 u 866.00 866.00 100.00% 866.00

Unid. $2,883.84 101.02% 2,854.65*ISCIS 10590002 CAMARA INSP., ROCA, .60X.60X.60 M. INT.:

1 Excavación roca (.8x.8x.8 m.). 0.512 m3 1,772.87 907.71 100.00% 907.712 Bote material excavado 0.820 m3 351.88 288.54 101.72% 283.653 Horm. 1:3:5 en losas 0.049 m3 4,432.36 217.19 101.50% 213.994 Acero ¼" incrustado losa 0.003 qq 1,519.73 4.56 101.72% 4.485 Acero 3/8" x 20' grado 40 en tapa 0.180 qq 2,114.09 380.54 101.72% 374.096 Bloques 4" sin mano de obra albañilería 1.646 m2 464.23 764.12 101.67% 751.567 Horm. 1:3:5 en int. 0.029 m3 4,432.36 128.54 101.49% 126.658 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0069 m3 7,806.60 53.87 101.68% 52.989 Mano de obra 1.00 u 866.00 866.00 100.00% 866.00

Unid. $3,611.07 100.84% 3,581.11*ISCIS 10590003 CAMARA INSP., TIERRA, .60X.60X.60 M. INT.:

1 Excavación en tierra (.8x.8x.8 m.). 0.512 m3 272.33 139.43 100.00% 139.432 Bote material excavado 0.670 m3 351.88 235.76 101.73% 231.76

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 81

Page 84: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

3 Horm. 1:3:5 en losas 0.049 m3 4,432.36 217.19 101.50% 213.994 Acero ¼" incrustado losa 0.003 qq 1,519.73 4.56 101.79% 4.485 Acero 3/8" x 20' grado 40 en tapa 0.180 qq 2,114.09 380.54 101.72% 374.096 Bloques 4" sin mano de obra albañilería 1.800 m2 464.23 835.61 101.67% 821.887 Horm. 1:3:5 en int. 0.029 m3 4,432.36 128.54 101.49% 126.658 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0069 m3 7,806.60 53.87 101.68% 52.989 Mano de obra 1.00 u 866.00 866.00 100.00% 866.00

Unid. $2,861.50 101.07% 2,831.26*ISCIS 10590004 CAMARA SEPTICA, CALICHE, 1.70X3.40X1.60 M. INT.:

1 Excav. caliche (2.00x3.70x2.00 mt.). 14.80 m3 441.84 6,539.23 100.00% 6,539.232 Bote material excavado 19.98 m3 351.88 7,030.56 101.73% 6,911.283 Horm. 1:2:4 en losas 1.156 m3 4,940.47 5,711.18 101.52% 5,625.634 Acero 3/8" x 20' grado 40 en losas 1.550 qq 2,114.09 3,276.84 101.72% 3,221.325 Bloques 6" 18.20 m2 856.57 15,589.57 101.25% 15,396.476 Horm. 1:3:5 llenado todos los hoyos 0.568 m3 4,432.36 2,517.58 101.49% 2,480.557 Madera bruta amer. (4 usos) 40.40 pt 35.70 1,442.28 101.74% 1,417.648 Clavos corrientes (5 lb. / 100 pie madera) 8.08 lb 30.43 245.87 101.70% 241.759 Clavos de acero (.08 lb / m2) 0.46 lb 53.10 24.43 101.75% 24.0110 Alambre calibre #14 (.15 lb. / m2) 0.87 lb 34.64 30.14 101.72% 29.6311 Confección madera 5.78 m2 120.83 698.40 100.00% 698.4012 Desencofrado 5.78 m2 25.78 149.01 100.00% 149.0113 Empañete pulido int. 22.10 m2 272.02 6,011.64 100.82% 5,963.02

Unid. $49,266.73 101.17% 48,697.94*ISCIS 10590005 CAMARA SEPTICA, ROCA, 1.70X3.40X1.60 M. INT.:

1 Excav. roca a mano (2.00x3.70x2.00 mt.). 14.80 m3 902.08 13,350.78 100.00% 13,350.782 Bote material excavado 23.68 m3 351.88 8,332.52 101.73% 8,191.153 Horm. 1:2:4 en losas 1.156 m3 4,940.47 5,711.18 101.52% 5,625.634 Acero 3/8" x 20' grado 40 en losas 1.550 qq 2,114.09 3,276.84 101.72% 3,221.325 Bloques 6" 18.20 m2 856.57 15,589.57 101.25% 15,396.476 Horm. 1:3:5 llenado todos los hoyos 0.568 m3 4,432.36 2,517.58 101.49% 2,480.557 Madera bruta amer. (4 usos) 40.40 pt 35.70 1,442.28 101.74% 1,417.648 Clavos corrientes (5 lb. / 100 pie madera) 8.08 lb 30.43 245.87 101.70% 241.759 Clavos de acero (.08 lb / m2) 0.46 lb 53.10 24.43 101.75% 24.0110 Alambre calibre #14 (.15 lb. / m2) 0.87 lb 34.64 30.14 101.72% 29.6311 Confección madera 5.78 m2 120.83 698.40 100.00% 698.4012 Desencofrado 5.78 m2 25.78 149.01 100.00% 149.0113 Empañete pulido int. 22.10 m2 272.02 6,011.64 100.82% 5,963.02

Unid. $57,380.24 101.04% 56,789.36*ISCIS 10590006 CAMARA SEPTICA, TIERRA, 1.70X3.40X1.60 M. INT.:

1 Excav. tierra (2.00x3.70x2.00 mt.). 14.80 m3 272.33 4,030.48 100.00% 4,030.482 Bote material excavado 19.24 m3 351.88 6,770.17 101.73% 6,655.313 Horm. 1:2:4 en losas 1.156 m3 4,940.47 5,711.18 101.52% 5,625.634 Acero 3/8" x 20' grado 40 en losas 1.550 qq 2,114.09 3,276.84 101.72% 3,221.325 Bloques 6" 18.20 m2 856.57 15,589.57 101.25% 15,396.476 Horm. 1:3:5 llenado todos los hoyos 0.568 m3 4,432.36 2,517.58 101.49% 2,480.557 Madera bruta amer. (4 usos) 40.40 pt 35.70 1,442.28 101.74% 1,417.648 Clavos corrientes (5 lb. / 100 pie madera) 8.08 lb 30.43 245.87 101.70% 241.759 Clavos de acero (.08 lb / m2) 0.46 lb 53.10 24.43 101.75% 24.0110 Alambre calibre #14 (.15 lb. / m2) 0.87 lb 34.64 30.14 101.72% 29.6311 Confección madera 5.78 m2 120.83 698.40 100.00% 698.4012 Desencofrado 5.78 m2 25.78 149.01 100.00% 149.0113 Empañete pulido int. 22.10 m2 272.02 6,011.64 100.82% 5,963.02

Unid. $46,497.59 101.23% 45,933.22*ISCIS 10590007 CISTERNA 4,000 GLS., CALICHE, 2.50X3.50X2.00 M. INT.:

1 Excav. en caliche (3.00x4.00x2.50 m.). 30.00 m3 441.84 13,255.20 100.00% 13,255.202 Bote material excavado 40.50 m3 351.88 14,251.14 101.73% 14,009.363 Horm. 1:2:4 en losas (losa piso y losa superior h=0.12 m.). 2.49 m3 4,940.47 12,301.77 101.52% 12,117.494 Acero 3/8" x 20' grado 40 en losa piso 1.56 qq 2,114.09 3,297.98 101.72% 3,242.105 Acero 3/8" x 20' grado 40 en losa superior 3.12 qq 2,114.09 6,595.96 101.72% 6,484.206 Bloques 8" todos los hoyos llenos 25.60 m2 1,391.99 35,634.94 101.33% 35,166.467 Madera bruta amer. (4 usos) 61.15 pt 35.70 2,183.06 101.74% 2,145.758 Clavos corrientes (5 lb. / 100 pie madera) 12.23 lb 30.43 372.16 101.71% 365.929 Clavos de acero (.08 lb / m2) 0.70 lb 53.10 37.17 101.72% 36.5410 Alambre calibre #14 (.15 lb. / m2) 1.31 lb 34.64 45.38 101.70% 44.6211 Confección madera 8.75 m2 120.83 1,057.26 100.00% 1,057.2612 Desencofrado 8.75 m2 25.78 225.58 100.00% 225.5813 Empañete pulido int. 32.75 m2 272.02 8,908.66 100.82% 8,836.6114 Zabaletas en esq. paredes int. y en piso 20.00 m 82.47 1,649.40 101.03% 1,632.6015 Bloques 6" en tapa 2.04 m2 856.57 1,747.40 101.25% 1,725.7616 Empañete liso en tapa 4.59 m2 406.58 1,866.20 100.82% 1,851.0617 Cantos en tapa 9.20 m 82.38 757.90 100.78% 752.0118 Tapa de hierro 1.00 u 3,097.50 3,097.50 101.72% 3,045.00

Unid. $107,284.66 101.22% 105,993.52*ISCIS 10590008 CISTERNA 4,000 GLS., ROCA, 2.50X3.50X2.00 M. INT.:

1 Excav. roca a mano (3.00x4.00x2.50 m.). 30.00 m3 902.08 27,062.40 100.00% 27,062.402 Bote material excavado 48.00 m3 351.88 16,890.24 101.73% 16,603.683 Horm. 1:2:4 en losas (losa piso y losa superior h=0.12 m.). 2.49 m3 4,940.47 12,301.77 101.52% 12,117.494 Acero 3/8" x 20' grado 40 en losa piso 1.56 qq 2,114.09 3,297.98 101.72% 3,242.105 Acero 3/8" x 20' grado 40 en losa superior 3.12 qq 2,114.09 6,595.96 101.72% 6,484.206 Bloques 8" todos los hoyos llenos 25.60 m2 1,391.99 35,634.94 101.33% 35,166.467 Madera bruta amer. (4 usos) 61.15 pt 35.70 2,183.06 101.74% 2,145.758 Clavos corrientes (5 lb. / 100 pie madera) 12.23 lb 30.43 372.16 101.71% 365.929 Clavos de acero (.08 lb / m2) 0.70 lb 53.10 37.17 101.72% 36.5410 Alambre calibre #14 (.15 lb. / m2) 1.31 lb 34.64 45.38 101.70% 44.6211 Confección madera 8.75 m2 120.83 1,057.26 100.00% 1,057.2612 Desencofrado 8.75 m2 25.78 225.58 100.00% 225.5813 Empañete pulido int. 32.75 m2 272.02 8,908.66 100.82% 8,836.6114 Zabaletas en esq. paredes int. y en piso 20.00 m 82.47 1,649.40 101.03% 1,632.6015 Bloques 6" en tapa 2.04 m2 856.57 1,747.40 101.25% 1,725.7616 Empañete liso en tapa 4.59 m2 406.58 1,866.20 100.82% 1,851.0617 Cantos en tapa 9.20 m 82.38 757.90 100.78% 752.0118 Tapa de hierro 1.00 u 3,097.50 3,097.50 101.72% 3,045.00

Unid. $123,730.96 101.09% 122,395.04

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 82

Page 85: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

*ISCIS 10590009 CISTERNA 4,000 GLS., TIERRA, 2.50X3.50X2.00 M. INT.:1 Excav. en tierra (3.00x4.00x2.50 m.). 30.00 m3 272.33 8,169.90 100.00% 8,169.902 Bote material excavado 39.00 m3 351.88 13,723.32 101.73% 13,490.493 Horm. 1:2:4 en losas (losa piso y losa superior h=0.12 m.). 2.49 m3 4,940.47 12,301.77 101.52% 12,117.494 Acero 3/8" x 20' grado 40 en losa piso 1.56 qq 2,114.09 3,297.98 101.72% 3,242.105 Acero 3/8" x 20' grado 40 en losa superior 3.12 qq 2,114.09 6,595.96 101.72% 6,484.206 Bloques 8" todos los hoyos llenos 25.60 m2 1,391.99 35,634.94 101.33% 35,166.467 Madera bruta amer. (4 usos) 61.15 pt 35.70 2,183.06 101.74% 2,145.758 Clavos corrientes (5 lb. / 100 pie madera) 12.23 lb 30.43 372.16 101.71% 365.929 Clavos de acero (.08 lb / m2) 0.70 lb 53.10 37.17 101.72% 36.5410 Alambre calibre #14 (.15 lb. / m2) 1.31 lb 34.64 45.38 101.70% 44.6211 Confección madera 8.75 m2 120.83 1,057.26 100.00% 1,057.2612 Desencofrado 8.75 m2 25.78 225.58 100.00% 225.5813 Empañete pulido int. (paredes y piso). 32.75 m2 272.02 8,908.66 100.82% 8,836.6114 Zabaletas en esq. paredes int. y en piso 20.00 m 82.47 1,649.40 101.03% 1,632.6015 Bloques 6" en tapa 2.04 m2 856.57 1,747.40 101.25% 1,725.7616 Empañete liso en tapa 4.59 m2 406.58 1,866.20 100.82% 1,851.0617 Cantos en tapa 9.20 m 82.38 757.90 100.78% 752.0118 Tapa de hierro 1.00 u 3,097.50 3,097.50 101.72% 3,045.00

Unid. $101,671.54 101.28% 100,389.35*ISCIS 10590010 TRAMPA GRASA, CALICHE, 1.00X1.00X1.00 M. INT.:

1 Excav. caliche (1.20x1.20x1.20 mt.). 1.73 m3 441.84 764.38 100.00% 764.382 Bote material excavado 2.34 m3 351.88 823.40 101.73% 809.433 Horm. 1:3:5 en losas 0.288 m3 4,432.36 1,276.52 101.49% 1,257.744 Acero 3/8" x 20' grado 40 en tapa 0.361 qq 2,114.09 763.19 101.72% 750.265 Bloques 4" sin mano de obra albañilería 4.00 m2 464.23 1,856.92 101.67% 1,826.406 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0192 m3 7,806.60 149.89 101.68% 147.427 Mano de obra albañilería 1.00 u 1,732.00 1,732.00 100.00% 1,732.00

Unid. $7,366.30 101.08% 7,287.63*ISCIS 10590011 TRAMPA GRASA, ROCA, 1.00X1.00X1.00 M. INT.:

1 Excav. roca a mano (1.20x1.20x1.20 mt.). 1.73 m3 902.08 1,560.60 100.00% 1,560.602 Bote material excavado 2.77 m3 351.88 974.71 101.73% 958.173 Horm. 1:3:5 en losas 0.288 m3 4,432.36 1,276.52 101.49% 1,257.744 Acero 3/8" x 20' grado 40 en tapa 0.361 qq 2,114.09 763.19 101.72% 750.265 Bloques 4" sin mano de obra albañilería 4.00 m2 464.23 1,856.92 101.67% 1,826.406 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0192 m3 7,806.60 149.89 101.68% 147.427 Mano de obra albañilería 1.00 u 1,732.00 1,732.00 100.00% 1,732.00

Unid. $8,313.83 100.99% 8,232.59*ISCIS 10590012 TRAMPA GRASA, TIERRA, 1.00X1.00X1.00 M. INT.:

1 Excav. tierra (1.20x1.20x1.20 m.). 1.73 m3 272.33 471.13 100.00% 471.132 Bote material excavado 2.25 m3 351.88 791.73 101.73% 778.303 Horm. 1:3:5 en losas 0.288 m3 4,432.36 1,276.52 101.49% 1,257.744 Acero 3/8" x 20' grado 40 en tapa 0.361 qq 2,114.09 763.19 101.72% 750.265 Bloques 4" sin mano de obra albañilería 4.00 m2 464.23 1,856.92 101.67% 1,826.406 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0192 m3 7,806.60 149.89 101.68% 147.427 Mano de obra albañilería 1.00 u 1,732.00 1,732.00 100.00% 1,732.00

Unid. $7,041.38 101.12% 6,963.25

*ISCISSD 10610000 INST. SANITARIA: CISTERNAS Y SEPTICOS SEGÚN DISEÑO:

*ISCISSD 10610001 CISTERNA S/DISEÑO, EN CALICHE: (En prueba) Cambie solo los valores en AZUL.Tipo de Bloque Ancho int. X Y Alto int. Z Cám. aire M3 Agua Hueco Long. Exc. X

0.20 2.20 1.60 2.50 0.20 8.10 Int. Tapa 2.70H Losa Piso Techo Tierra Cist. Tot. M3 Agua En X Long. Exc. Y

0.15 0.20 0.30 8 64.80 0.80 14.70Gl. / Cist. En Y Alto Exc.

Direc. X Direc. Y Direc. X Direc. Y 2,140 0.80 3.150.20 0.20 0.20 0.20 Tot. GL Agua Abult. Volumen Exc.

Diámetro ( " ) --> 3/8 3/8 1/2 1/2 17,118 25.00% 125.02

1 Acero en losa de piso de 3*8" 3.51 qq 2,114.09 7,410.94 101.72% 7,285.382 Acero en losa superior de 1/2" 4.56 qq 2,121.47 9,673.01 101.72% 9,509.103 Alambre calibre #14 (.15 lb. / m2). 4.22 lb 34.64 146.18 101.70% 143.734 Bloques 6" en tapa. 6.72 m2 856.57 5,756.15 101.25% 5,684.855 Bloques 8" todos los hoyos llenos. 90.72 m2 1,476.06 133,908.16 101.32% 132,167.256 Bote material excavado 156.50 m3 351.88 55,069.22 101.73% 54,134.927 Cantos en tapa. 67.20 m 82.38 5,535.94 100.78% 5,492.938 Clavos corrientes (5 lb. / 100 pie madera). 64.3 lb 30.43 1,956.65 101.70% 1,923.869 Clavos de acero (.08 lb / m2). 2.25 lb 53.10 119.48 101.73% 117.4510 Confección madera. 28.16 m2 120.83 3,402.57 100.00% 3,402.5711 Desencofrado. 28.16 m2 25.78 725.96 100.00% 725.9612 Empañete liso en tapa. 8.64 m2 256.87 2,219.36 100.82% 2,201.3013 Empañete paredes int 75.00 m2 272.02 20,401.50 100.82% 20,236.5014 Empañete pulido piso 28.16 m2 272.02 7,660.08 100.82% 7,598.1315 Excavación + 0.10 m. a cada lado 125.02 m3 441.84 55,238.84 100.00% 55,238.8416 Horm. 1:2:4 en losa piso 10.00 m3 4,940.47 49,404.70 101.52% 48,664.6017 Horm. 1:2:4 en losa superior 12.42 m3 4,940.47 61,340.88 101.52% 60,421.9718 Madera bruta amer. (4 usos). 321.52 pt 35.70 11,478.26 101.74% 11,282.1419 Mano de obra Varillero losa de piso y superior 8.07 pt 243.24 1,961.75 100.00% 1,961.7519 Zabaletas en esq. paredes int. y en piso. 87.60 m 82.47 7,224.37 101.03% 7,150.79

Unid. $440,634.00 101.22% 435,344.02*ISCISSD 10610002 CISTERNA S/DISEÑO, EN ROCA: (En prueba) Cambie solo los valores en AZUL.

Tipo de Bloque Ancho int. X Y Alto int. Z Cám. aire M3 Agua Hueco Long. Exc. X0.20 2.20 1.60 2.50 0.20 8.10 Int. Tapa 2.70

H Losa Piso Techo Tierra Cist. Tot. M3 Agua En X Long. Exc. Y0.15 0.20 0.30 8 64.80 0.80 14.70

Gl. / Cist. En Y Alto Exc.Direc. X Direc. Y Direc. X Direc. Y 2,140 0.80 3.150.20 0.20 0.20 0.20 Tot. GL Agua Abult. Volumen Exc.

Diámetro ( " ) --> 3/8 3/8 1/2 1/2 17,118 60.00% 125.02

Espac. Acero TechoCISTERNAS EN

HILERA Espac. Acero Piso

CISTERNAS EN HILERA Espac. Acero Piso Espac. Acero Techo

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 83

Page 86: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

1 Acero en losa de piso de 3*8" 3.51 qq 2,114.09 7,410.94 101.72% 7,285.382 Acero en losa superior de 1/2" 4.56 qq 2,121.47 9,673.01 101.72% 9,509.103 Alambre calibre #14 (.15 lb. / m2). 4.22 lb 34.64 146.18 101.70% 143.734 Bloques 6" en tapa. 6.72 m2 856.57 5,756.15 101.25% 5,684.855 Bloques 8" todos los hoyos llenos. 90.72 m2 1,476.06 133,908.16 101.32% 132,167.256 Bote material excavado 200.50 m3 351.88 70,551.94 101.73% 69,354.967 Cantos en tapa. 67.20 m 82.38 5,535.94 100.78% 5,492.938 Clavos corrientes (5 lb. / 100 pie madera). 64.3 lb 30.43 1,956.65 101.70% 1,923.869 Clavos de acero (.08 lb / m2). 2.25 lb 53.10 119.48 101.73% 117.4510 Confección madera. 28.16 m2 120.83 3,402.57 100.00% 3,402.5711 Desencofrado. 28.16 m2 25.78 725.96 100.00% 725.9612 Empañete liso en tapa. 8.64 m2 256.87 2,219.36 100.82% 2,201.3013 Empañete paredes int 75.00 m2 272.02 20,401.50 100.82% 20,236.5014 Empañete pulido piso 28.16 m2 272.02 7,660.08 100.82% 7,598.1315 Excavación + 0.10 m. a cada lado 125.02 m3 902.08 112,778.04 100.00% 112,778.0416 Horm. 1:2:4 en losa piso 10.00 m3 4,940.47 49,404.70 101.52% 48,664.6017 Horm. 1:2:4 en losa superior 12.42 m3 4,940.47 61,340.88 101.52% 60,421.9718 Madera bruta amer. (4 usos). 321.52 pt 35.70 11,478.26 101.74% 11,282.1419 Mano de obra Varillero losa de piso y superior 8.07 pt 243.24 1,961.75 100.00% 1,961.7519 Zabaletas en esq. paredes int. y en piso. 87.60 m 82.47 7,224.37 101.03% 7,150.79

Unid. $513,655.92 101.09% 508,103.26*ISCISSD 10610003 CISTERNA S/DISEÑO, EN TIERRA: (En prueba) Cambie solo los valores en AZUL.

Tipo de Bloque Ancho int. X Y Alto int. Z Cám. aire M3 Agua Hueco Long. Exc. X0.20 2.20 1.60 2.50 0.20 8.10 Int. Tapa 2.70

H Losa Piso Techo Tierra Cist. Tot. M3 Agua En X Long. Exc. Y0.15 0.20 0.30 8 64.80 0.80 14.70

Gl. / Cist. En Y Alto Exc.Direc. X Direc. Y Direc. X Direc. Y 2,140 0.80 3.150.20 0.20 0.20 0.20 Tot. GL Agua Abult. Volumen Exc.

Diámetro ( " ) --> 3/8 3/8 1/2 1/2 17,118 20.00% 125.02

1 Acero en losa de piso de 3*8" 3.51 qq 2,114.09 7,410.94 101.72% 7,285.382 Acero en losa superior de 1/2" 4.56 qq 2,121.47 9,673.01 101.72% 9,509.103 Alambre calibre #14 (.15 lb. / m2). 4.22 lb 34.64 146.18 101.70% 143.734 Bloques 6" en tapa. 6.72 m2 856.57 5,756.15 101.25% 5,684.855 Bloques 8" todos los hoyos llenos. 90.72 m2 1,476.06 133,908.16 101.32% 132,167.256 Bote material excavado 150.50 m3 351.88 52,957.94 101.73% 52,059.467 Cantos en tapa. 67.20 m 82.38 5,535.94 100.78% 5,492.938 Clavos corrientes (5 lb. / 100 pie madera). 64.3 lb 30.43 1,956.65 101.70% 1,923.869 Clavos de acero (.08 lb / m2). 2.25 lb 53.10 119.48 101.73% 117.4510 Confección madera. 28.16 m2 120.83 3,402.57 100.00% 3,402.5711 Desencofrado. 28.16 m2 25.78 725.96 100.00% 725.9612 Empañete liso en tapa. 8.64 m2 256.87 2,219.36 100.82% 2,201.3013 Empañete paredes int 75.00 m2 272.02 20,401.50 100.82% 20,236.5014 Empañete pulido piso 28.16 m2 272.02 7,660.08 100.82% 7,598.1315 Excavación + 0.10 m. a cada lado 125.02 m3 272.33 34,046.70 100.00% 34,046.7016 Horm. 1:2:4 en losa piso 10.00 m3 4,940.47 49,404.70 101.52% 48,664.6017 Horm. 1:2:4 en losa superior 12.42 m3 4,940.47 61,340.88 101.52% 60,421.9718 Madera bruta amer. (4 usos). 321.52 pt 35.70 11,478.26 101.74% 11,282.1419 Mano de obra Varillero losa de piso y superior 8.07 pt 243.24 1,961.75 100.00% 1,961.7519 Zabaletas en esq. paredes int. y en piso. 87.60 m 82.47 7,224.37 101.03% 7,150.79

Unid. $417,330.58 101.28% 412,076.42

*ISCAMO 10630000 INST. SANITARIA: COLOC. APARATOS SIN ITBIS (SOLO M. O.)

*ISCAMO 10630001 M.O. PLOM. COLOC. BAÑERA LIVIANA CON MEZCLADORA:1 M.O. Alb., base p/bañera. 1.00 u 251.00 251.00 100.00% 251.002 M.O. Plom. coloc. bañera liv. 1.00 u 1,356.30 1,356.30 100.00% 1,356.303 M.O. Plom. coloc. mezcl.. 1.00 u 592.86 592.86 100.00% 592.864 M.O. Plom. desagüe de 2. 1.00 u 592.86 592.86 100.00% 592.865 M.O. Plom. salidas ½". 2.00 u 592.86 1,185.72 100.00% 1,185.72

Unid. $3,978.74 100.00% 3,978.74*ISCAMO 10630002 M.O. PLOM. COLOC. BAÑERA PESADA CON MEZCLADORA:

1 M.O. Alb., base p/bañera. 1.00 u 251.00 251.00 100.00% 251.002 M.O. Plom. coloc. bañera hierro fund. 1.00 u 1,435.60 1,435.60 100.00% 1,435.603 M.O. Plom. coloc. mezcl.. 1.00 u 592.86 592.86 100.00% 592.864 M.O. Plom. desagüe de 2. 1.00 u 592.86 592.86 100.00% 592.865 M.O. Plom. salidas ½". 2.00 u 592.86 1,185.72 100.00% 1,185.72

Unid. $4,058.04 100.00% 4,058.04*ISCAMO 10630003 M.O. PLOM. COLOC. BIDET:

1 M.O. Plom. coloc. bidet. 1.00 u 1,016.54 1,016.54 100.00% 1,016.542 M.O. Plom. desagüe 2". 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½". 2.00 u 592.86 1,185.72 100.00% 1,185.72

Unid. $2,795.12 100.00% 2,795.12*ISCAMO 10630004 M.O. PLOM. COLOC. DUCHA: Agua caliente y fría, arriba y abajo, mezcladora

1 M.O. Plom. coloc. mezcl.. 1.00 u 592.86 592.86 100.00% 592.862 M.O. Plom. desagüe de 2. 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½". 2.00 u 592.86 1,185.72 100.00% 1,185.72

Unid. $2,371.44 100.00% 2,371.44*ISCAMO 10630005 M.O. PLOM. COLOC. DUCHA: Agua fría solamente

1 M.O. Plom. coloc.llave de empotrar ½" 1.00 u 338.39 338.39 100.00% 338.392 M.O. Plom. desagüe de 2. 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½". 1.00 u 592.86 592.86 100.00% 592.86

Unid. $1,524.11 100.00% 1,524.11*ISCAMO 10630006 M.O. PLOM. COLOC. FREG. A. INOX. DOBLE, MANGUERA:

1 M.O. Plom. coloc. Fregadero 1.00 u 1,086.69 1,086.69 100.00% 1,086.692 M.O. Plom. desagüe 2". 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½". 2.00 u 592.86 1,185.72 100.00% 1,185.72

Unid. $2,865.27 100.00% 2,865.27*ISCAMO 10630007 M.O. PLOM. COLOC. FREG. A. INOX. SENCILLO, MANGUERA:

1 M.O. Plom. coloc. Fregadero 1.00 u 848.72 848.72 100.00% 848.722 M.O. Plom. desagüe 2". 1.00 u 592.86 592.86 100.00% 592.86

CISTERNAS EN HILERA Espac. Acero Piso Espac. Acero Techo

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 84

Page 87: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

3 M.O. Plom. salidas ½". 1.00 u 592.86 592.86 100.00% 592.86Unid. $2,034.44 100.00% 2,034.44

*ISCAMO 10630008 M.O. PLOM. COLOC. INODORO:1 M.O. Plom. coloc. inodoro. 1.00 u 678.15 678.15 100.00% 678.152 M.O. Plom. desagüe 4". 1.00 u 763.43 763.43 100.00% 763.433 M.O. Plom. salidas ½". 1.00 u 763.43 763.43 100.00% 763.43

Unid. $2,205.01 100.00% 2,205.01*ISCAMO 10630009 M.O. PLOM. COLOC. LAVADERO GRANITO, DOBLE:

1 M.O. Plom. coloc. lavadero 2 cámara2 1.00 u 763.43 763.43 100.00% 763.432 M.O. Plom. desagüe 2". 3.00 u 592.86 1,778.58 100.00% 1,778.583 M.O. Plom. salida ½". 2.00 u 592.86 1,185.72 100.00% 1,185.72

Unid. $3,727.73 100.00% 3,727.73*ISCAMO 10630010 M.O. PLOM. COLOC. LAVADERO GRANITO, SENCILLO:

1 M.O. Plom. coloc. lavadero 1 cámara 1.00 u 592.86 592.86 100.00% 592.862 M.O. Plom. desagüe 2". 2.00 u 592.86 1,185.72 100.00% 1,185.723 M.O. Plom. salida ½". 1.00 u 592.86 592.86 100.00% 592.86

Unid. $2,371.44 100.00% 2,371.44*ISCAMO 10630011 M.O. PLOM. COLOC. LAVAMANOS CON PATAS:

1 M.O. Plom. coloc. lavamanos con patas 1.00 u 825.33 825.33 100.00% 825.332 M.O. Plom. desagüe 2" 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.72

Unid. $2,603.91 100.00% 2,603.91*ISCAMO 10630012 M.O. PLOM. COLOC. LAVAMANOS EMPOTRADO:

1 M.O. Plom. coloc. lavamanos empotrado 1.00 u 1,187.10 1,187.10 100.00% 1,187.102 M.O. Plom. desagüe 2" 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.72

Unid. $2,965.68 100.00% 2,965.68*ISCAMO 10630013 M.O. PLOM. COLOC. LAVAMANOS PEDESTAL:

1 M.O. Plom. coloc. lavamanos pedestal 1.00 u 928.50 928.50 100.00% 928.502 M.O. Plom. desagüe 2" 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.72

Unid. $2,707.08 100.00% 2,707.08*ISCAMO 10630014 M.O. PLOM. COLOC. LAVAMANOS SALON DE BELLEZA:

1 M.O. Plom. coloc. lavamanos salón de belleza 1.00 u 1,187.10 1,187.10 100.00% 1,187.102 M.O. Plom. desagüe 2" 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.72

Unid. $2,965.68 100.00% 2,965.68*ISCAMO 10630015 M.O. PLOM. COLOC. LAVAMANOS SIN PATAS:

1 M.O. Plom. coloc. lavamanos sin patas 1.00 u 678.15 678.15 100.00% 678.152 M.O. Plom. desagüe 2" 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½" 2.00 u 592.86 1,185.72 100.00% 1,185.72

Unid. $2,456.73 100.00% 2,456.73*ISCAMO 10630016 M.O. PLOM. COLOC. ORINAL ½ FALDA:

1 M.O. Plom. coloc. Orinal ½ falda 1.00 u 763.43 763.43 100.00% 763.432 M.O. Plom. desagüe 2". 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½". 1.00 u 763.43 763.43 100.00% 763.43

Unid. $2,119.72 100.00% 2,119.72*ISCAMO 10630017 M.O. PLOM. COLOC. ORINAL FALDA COMPLETA, FLUX.:

1 M.O. Plom. coloc. Orinal falda completa 1.00 u 1,187.10 1,187.10 100.00% 1,187.102 M.O. Plom. desagüe 2". 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½". 1.00 u 763.43 763.43 100.00% 763.43

Unid. $2,543.39 100.00% 2,543.39*ISCAMO 10630018 M.O. PLOM. COLOC. ORINAL PEQUEÑO:

1 M.O. Plom. coloc. Orinal pequeño 1.00 u 848.72 848.72 100.00% 848.722 M.O. Plom. desagüe 2". 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salidas ½". 1.00 u 763.43 763.43 100.00% 763.43

Unid. $2,205.01 100.00% 2,205.01*ISCAMO 10630019 M.O. PLOM. COLOC. VERTEDERO O TINA GRANITO:

1 M.O. Plom. coloc. vertedero sencillo. 1.00 u 170.57 170.57 100.00% 170.572 M.O. Plom. desagüe 2". 1.00 u 592.86 592.86 100.00% 592.863 M.O. Plom. salida ½". 1.00 u 592.86 592.86 100.00% 592.864 M.O. Plom. tub. ½" en piso. 0.30 m 12.38 3.71 100.00% 3.71

Unid. $1,360.00 100.00% 1,360.00

*MALCIC 10650000 MALLAS CICLONICAS

*MALCIC 10650001 MALLA CICLONICA DE 6 PIES DE ALTO, LIGERA:1 Abrazadera de 1 ½" 0.780 u 29.50 23.01 101.72% 22.622 Alambre de puas cal. 16 x 90 m. (rollo) 0.040 u 560.50 22.42 101.72% 22.043 Alambre galvanizado #14 0.050 lb 34.64 1.73 101.76% 1.704 Barra tensora de 6' 0.080 u 145.14 11.61 101.75% 11.415 Bote material excavado 0.160 m3 351.88 56.30 101.72% 55.356 Carpintería columnas de amarre 0.264 m 203.71 53.78 101.72% 52.877 Colocar mallas 1.000 m 288.82 288.82 100.00% 288.828 Copa Final 1 ½" 0.060 u 55.46 3.33 101.83% 3.279 Corte y soldadura de abrazaderas 0.260 u 31.42 8.17 101.74% 8.0310 Empañete liso (en 3 líneas de bloques) 1.200 m2 256.87 308.24 100.82% 305.7411 Excación zapata (tierra) 0.18 día 272.33 49.02 100.00% 49.0212 Hoja de segueta 0.050 u 39.65 1.98 101.54% 1.9513 Horm. 1:2:4 en columnas de amarre (.15 x .20 x .80 m.) 0.008 m3 4,431.50 35.45 101.58% 34.9014 Horm. armado zapata (1:3:5, .45 x .20, 3 de 3/8" y 3/8" a .25 m.) 0.090 m3 5,780.72 520.26 101.45% 512.8215 Malla ciclónica 6 pies, cal. 9 + 5% desp. 3.50 pie 141.60 495.60 101.72% 487.2016 Muro de bloques de 6" x 8" x 16" (4 líneas) 0.800 m2 856.57 685.26 101.25% 676.7717 Reata de amarre (zabaleta doble sin mano de obra) 2.000 m 103.52 207.04 101.65% 203.6818 Relleno de reposición 0.060 m3 225.68 13.54 100.15% 13.5219 Palometa 1 ½" doble, en aluminio fundido 0.280 u 188.80 52.86 101.71% 51.9720 Terminal de 1 ¼" + abrazadera de 1 ½" 0.200 u 82.60 16.52 101.72% 16.2421 Tubo HG de agua, de 1" x 20" para unir tubos de 1 ¼" 0.120 u 922.76 110.73 101.73% 108.8522 Tubo HG ligero de 1 ½" x 15' 0.180 u 725.70 130.63 101.73% 128.4123 Tubo HG ligero de 1 ¼" x 20' 0.160 u 821.28 131.40 101.72% 129.18

M $3,227.70 101.30% 3,186.36

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 85

Page 88: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012*MOR 10670000 M O R T E R O S

*MOR 10670001 MEZCLA DE EMPAÑETE:1 Arena fina + 2% desp. 1.02 m3 963.94 983.22 101.72% 966.552 Cal hidratada + 2% desp. (50 lbs.) 3.06 fda 283.20 866.59 101.72% 851.903 Mano de obra mezclado (un peón) 0.50 día 474.00 237.00 100.00% 237.00

M3 $2,086.81 101.53% 2,055.45*MOR 10670002 MEZCLA CAL Y ARENA, P/MORTERO COLOC. PISO:

1 Arena gruesa lavada + 2% desp. 1.02 m3 963.94 983.22 101.72% 966.552 Cal hidratada + 2% desp. (50 lbs.) 3.06 fda 283.20 866.59 101.72% 851.903 Mano de obra mezclado (un peón) 0.50 día 474.00 237.00 100.00% 237.00

M3 $2,086.81 101.53% 2,055.45*MOR 10670003 MORTERO 1: 1 (Nuevo)

1 Agua 71.96 gl 0.61 43.90 101.67% 43.182 Arena gruesa lavada + 2% desp. 0.694 m3 963.94 668.97 101.72% 657.633 Cemento gris 24.01 fda 320.43 7,693.52 101.72% 7,563.154 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 474.00 237.00 100.00% 237.00

M3 $8,643.39 101.68% 8,500.96*MOR 10670004 MORTERO 1: 2 (Nuevo)

2 Agua 70.10 gl 0.61 42.76 101.66% 42.061 Arena gruesa lavada + 2% desp. 0.900 m3 963.94 867.55 101.72% 852.843 Cemento gris 15.57 fda 320.43 4,989.10 101.72% 4,904.554 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 474.00 237.00 100.00% 237.00

M3 $6,136.41 101.66% 6,036.45*MOR 10670005 MORTERO 1: 2 PARA PULIDO (ENLUCIDO IMPERMEABLE):

2 Agua 100.00 gl 0.61 61.00 101.67% 60.001 Arena fina + 2% desp. 1.02 m3 963.94 983.22 101.72% 966.553 Cal hidratada + 2% desp. (50 lbs.) 3.06 fda 283.20 866.59 101.72% 851.904 Cemento gris 17.66 fda 320.43 5,658.79 101.72% 5,562.905 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 474.00 237.00 100.00% 237.00

M3 $7,806.60 101.67% 7,678.35*MOR 10670006 MORTERO 1: 3, P/COLOCAR BLOQUES:

2 Agua 69.04 gl 0.61 42.11 101.67% 41.421 Arena gruesa lavada + 2% desp. 0.998 m3 963.94 962.01 101.72% 945.703 Cemento gris 11.51 fda 320.43 3,688.15 101.72% 3,625.654 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 474.00 237.00 100.00% 237.00

M3 $4,929.27 101.64% 4,849.77*MOR 10670007 MORTERO 1: 4 PARA EMPAÑETE:

3 Agua 45.24 gl 0.61 27.60 101.69% 27.142 Cemento gris 9.46 fda 320.43 3,031.27 101.72% 2,979.904 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 474.00 237.00 100.00% 237.001 Mezcla de empañete + 3% desp. 1.102 m3 2,086.81 2,299.66 101.53% 2,265.11

M3 $5,595.53 101.57% 5,509.15*MOR 10670008 MORTERO 1: 5: (Nuevo)

2 Agua 67.99 gl 0.61 41.47 101.67% 40.791 Arena gruesa lavada + 2% desp. 1.091 m3 963.94 1,051.66 101.72% 1,033.833 Cemento gris 7.56 fda 320.43 2,422.45 101.72% 2,381.404 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 474.00 237.00 100.00% 237.00

M3 $3,752.58 101.61% 3,693.02*MOR 10670009 MORTERO 1: 6: (Nuevo)

2 Agua 67.72 gl 0.61 41.31 101.67% 40.631 Arena gruesa lavada + 2% desp. 1.120 m3 963.94 1,079.61 101.72% 1,061.313 Cemento gris 6.46 fda 320.43 2,069.98 101.72% 2,034.904 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 474.00 237.00 100.00% 237.00

M3 $3,427.90 101.60% 3,373.84*MOR 10670010 MORTERO 1:10, COLOCAR PISOS:

3 Agua 70.00 gl 0.61 42.70 101.67% 42.002 Cemento gris 5.24 fda 320.43 1,679.05 101.72% 1,650.604 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 474.00 237.00 100.00% 237.001 Mezcla cal y arena para pisos + 20% desp. 1.20 m3 2,086.81 2,504.17 101.53% 2,466.54

M3 $4,462.92 101.52% 4,396.14

*MOVTIE 10690000 MOVIMIENTO DE TIERRAS

*MOVTIE 10690001 RELLENO ARENA O CASCAJO (A MANO):1 Arena o cascajo de mina + 15% abult. + 3% 1.185 m3 880.93 1,043.90 101.72% 1,026.212 Agua 15.22 gl 0.72 10.96 102.91% 10.653 Traslado material (1 TC = 5.00 m3 / día) 0.237 día 474.00 112.34 100.00% 112.344 Regar, mojar y apis. (1 TC = 15.45 m3 / día) 0.077 día 474.00 36.50 100.00% 36.50

M3 $1,203.70 101.52% 1,185.70*MOVTIE 10690002 RELLENO ARENA O CASCAJO (CON EQUIPO):

1 Alquiler compactador mecánico + transporte 0.375 hr 157.08 58.91 101.73% 57.912 Arena o cascajo de mina + 15% abult. + 3% 1.185 m3 880.93 1,043.90 101.72% 1,026.213 Agua 15.22 gl 0.72 10.96 102.91% 10.654 Traslado material (1 TC = 5.00 m3 / día) 0.237 día 474.00 112.34 100.00% 112.345 Regar, mojar y apis. (1 TC = 23.18 m3 / día) 0.051 día 474.00 24.17 100.00% 24.17

M3 $1,250.28 101.54% 1,231.28*MOVTIE 10690003 RELLENO CALICHE (A MANO):

1 Caliche fino + 30 % abult. + 3% desp. 1.339 m3 329.57 441.29 101.72% 433.822 Agua 15.22 gl 0.72 10.96 102.91% 10.653 Traslado material (1 TC = 3.33 m3 / día) 0.402 día 474.00 190.55 100.00% 190.554 Regar, mojar y apis. (1 TC = 9.80 m3 / día) 0.137 día 474.00 64.94 100.00% 64.94

M3 $707.74 101.11% 699.96*MOVTIE 10690004 RELLENO CALICHE (CON EQUIPO):

1 Alquiler compactador mecánico + transporte 0.375 hr 157.08 58.91 101.73% 57.912 Caliche fino + 30 % abult. + 3% desp. 1.339 m3 329.57 441.29 101.72% 433.823 Agua 15.22 gl 0.72 10.96 102.91% 10.654 Traslado material (1 TC = 3.33 m3 / día) 0.402 día 474.00 190.55 100.00% 190.555 Regar, mojar y apis. (1 TC = 1470 m3 / día) 0.091 día 474.00 43.13 100.00% 43.13

M3 $744.84 101.19% 736.06*MOVTIE 10690005 RELLENO CALICHE Y ARENA O CASCAJO (A MANO):

1 Caliche fino + 30 % abult. + 3% desp. 0.670 m3 329.57 220.81 101.72% 217.072 Arena itabo o cascajo fino + 15% abult. + 3% 0.592 m3 880.93 521.51 101.72% 512.673 Agua 15.22 gl 0.72 10.96 102.91% 10.65

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 86

Page 89: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

4 Traslado del material (1 TC = 4.00 m3 / día) 0.316 día 474.00 149.78 100.00% 149.785 Regar, mojar y apis. (1 TC = 13.17 m3 / día) 0.096 día 474.00 45.50 100.00% 45.50

M3 $948.56 101.38% 935.67*MOVTIE 10690006 RELLENO CALICHE Y ARENA O CASCAJO (CON EQUIPO):

1 Alquiler compactador mecánico + transporte 0.375 hr 157.08 58.91 101.73% 57.912 Caliche fino + 30 % abult. + 3% desp. 0.670 m3 329.57 220.81 101.72% 217.073 Arena itabo o cascajo fino + 15% abult. + 3% 0.592 m3 880.93 521.51 101.72% 512.674 Agua 15.22 gl 0.72 10.96 102.91% 10.655 Traslado del material (1 TC = 4.00 m3 / día) 0.316 día 474.00 149.78 100.00% 149.786 Regar, mojar y apis. (1 TC = 19.76 m3 / día) 0.051 día 474.00 24.17 100.00% 24.17

M3 $986.14 101.43% 972.25*MOVTIE 10690007 RELLENO DE REPOSICION CALICHE SUELTO (A MANO):

1 Agua 15.22 gl 0.72 10.96 102.91% 10.652 Traslado del material (1 TC = 4.00 m3 / día) 0.316 día 474.00 149.78 100.00% 149.783 Regar, mojar y apisonar (1 TC = 9.80 m3 compactado / día) 0.137 día 474.00 64.94 100.00% 64.94

M3 $225.68 100.14% 225.37*MOVTIE 10690008 RELLENO DE REPOSICION SUELTO (Caliche) (CON EQUIPO):

1 Alquiler compactador mecánico + transporte 0.375 hr 157.08 58.91 101.73% 57.912 Agua 15.22 gl 0.72 10.96 102.91% 10.653 Traslado del material (1 TC = 4.00 m3 / día) 0.316 día 474.00 149.78 100.00% 149.784 Regar, mojar (1 TC = 1470 m3 compactado / día) 0.091 día 474.00 43.13 100.00% 43.13

M3 $262.78 100.50% 261.47*MOVTIE 10690009 REMOCION CAPA VEGETAL (A MANO):

1 Excavación a mano 1.00 m3 272.33 272.33 100.00% 272.332 Traslado del material (1 TC = 3.33 m3 / día) 0.300 día 474.00 142.20 100.00% 142.20

M3 $414.53 100.00% 414.53

*PIN 10710000 PINTURAS

*PIN 10710001 PINTURA ACRILICA EXTERIOR:1 Pintura colores preparados 0.08 gl 1,076.53 86.12 101.72% 84.662 Piedra sobre paredes 1.00 m2 6.96 6.96 100.00% 6.963 Aplicación dos manos 1.00 m2 34.39 34.39 100.00% 34.394 Desperdicios y retoques 20.00% 25.49 101.15% 25.20

M2 $152.96 101.16% 151.21*PIN 10710002 PINTURA ACRILICA INTERIOR:

1 Pintura 0.08 gl 705.64 56.45 101.73% 55.492 Piedra sobre paredes 1.00 m2 6.96 6.96 100.00% 6.963 Aplicación dos manos 1.00 m2 34.39 34.39 100.00% 34.394 Desperdicios y retoques 20.00% 19.56 100.98% 19.37

M2 $117.36 100.99% 116.21*PIN 10710003 PINTURA ACRILICA EXTERIOR CON ANDAMIOS:

1 Pintura colores preparados 0.08 gl 1,076.53 86.12 101.72% 84.662 Piedra sobre paredes 1.00 m2 6.96 6.96 100.00% 6.963 Aplicación dos manos 1.00 m2 34.39 34.39 100.00% 34.394 Andamios y Gindolas 1.00 m2 79.22 79.22 101.72% 77.885 Desperdicios y retoques 20.00% 25.49 101.15% 25.20

M2 $232.18 101.35% 229.09*PIN 10710004 PINTURA EPOXICA:

1 Pintura 0.08 gl 2,041.40 163.31 101.73% 160.542 Thinner 0.13 gl 624.50 81.19 101.73% 79.813 Piedra sobre paredes 1.00 m2 6.96 6.96 100.00% 6.964 Aplicación dos manos 1.00 m2 42.64 42.64 100.00% 42.645 Desperdicios y retoques 20.00% 58.82 101.43% 57.99

M2 $352.92 101.43% 347.94*PIN 10710005 PINTURA LACA PARA PUERTAS:

1 Pintura 0.10 gl 731.60 73.16 101.72% 71.922 Piedra sobre paredes 1.00 m2 6.96 6.96 100.00% 6.963 Aplicación dos manos 1.00 m2 34.39 34.39 100.00% 34.394 Desperdicios y retoques 20.00% 22.90 101.10% 22.65

M2 $137.41 101.10% 135.92*PIN 10710006 PINTURA LATEX "ECONOMICA" O "PINTEX":

1 Pintura 0.10 gl 292.64 29.26 101.70% 28.772 Piedra sobre paredes 1.00 m2 6.96 6.96 100.00% 6.963 Aplicación dos manos 1.00 m2 34.39 34.39 100.00% 34.394 Desperdicios y retoques 20.00% 14.12 100.71% 14.02

M2 $84.73 100.70% 84.14*PIN 10710007 PINTURA MANTENIMIENTO:

1 Pintura 0.08 gl 1,073.80 85.90 101.72% 84.452 Thinner 0.13 gl 624.50 81.19 101.73% 79.813 Piedra sobre paredes 1.00 m2 6.96 6.96 100.00% 6.964 Aplicación dos manos 1.00 m2 42.64 42.64 100.00% 42.645 Desperdicios y retoques 20.00% 43.34 101.33% 42.77

M2 $260.03 101.32% 256.63*PIN 10710008 PINTURA MANTENIMIENTO CON ANDAMIOS:

1 Pintura 0.08 gl 1,073.80 85.90 101.72% 84.452 Thinner 0.13 gl 624.50 81.19 101.73% 79.813 Piedra sobre paredes 1.00 m2 6.96 6.96 100.00% 6.964 Aplicación dos manos 1.00 m2 42.64 42.64 100.00% 42.645 Andamios y Gindolas 1.00 m2 79.22 79.22 101.72% 77.886 Desperdicios y retoques 20.00% 43.34 101.33% 42.77

M2 $339.25 101.42% 334.51

*PIS 10730000 PISOS

*PIS 10730001 ACERA FROTADA Y VIOLINADA:1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Horm. 1:3:5 + 5% desp. 0.105 m3 4,432.36 465.40 101.49% 458.553 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.204 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 169.55 14.92 101.70% 14.675 Elaboración, vaciado y frotado 1.00 m2 121.76 121.76 100.00% 121.766 Cantos laterales 0.80 m 82.38 65.90 100.78% 65.39

M2 $825.31 101.17% 815.80

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 87

Page 90: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

*PIS 10730002 ADOQUIN 500-80 AGUAYO 8X10X20 CM., GRIS:1 Preparación terreno 1.00 m2 51.35 51.35 100.00% 51.352 Arena lavada 0.08 m3 1,292.28 103.38 101.72% 101.633 Baldosas + transporte + 5% desp. 1.00 m2 1,926.47 1,926.47 101.72% 1,893.814 Corte de chazos 0.15 u 38.94 5.84 101.74% 5.745 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 169.55 29.84 101.70% 29.346 Cantos laterales 0.80 m 82.38 65.90 100.78% 65.397 Colocación 1.00 m2 68.45 68.45 100.00% 68.45

M2 $2,251.23 101.60% 2,215.71*PIS 10730003 ADOQUIN 500-80 AGUAYO 8X10X20 CM., ROJO:

1 Preparación terreno 1.00 m2 51.35 51.35 100.00% 51.352 Arena lavada 0.08 m3 1,292.28 103.38 101.72% 101.633 Baldosas + transporte + 5% desp. 1.00 m2 2,387.88 2,387.88 101.72% 2,347.414 Corte de chazos 0.15 u 38.94 5.84 101.74% 5.745 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 169.55 29.84 101.70% 29.346 Cantos laterales 0.80 m 82.38 65.90 100.78% 65.397 Colocación 1.00 m2 68.45 68.45 100.00% 68.45

M2 $2,712.64 101.62% 2,669.31*PIS 10730004 ADOQUIN 511 AGUAYO TIPO PALETA, GRIS:

1 Preparación terreno 1.00 m2 51.35 51.35 100.00% 51.352 Arena lavada 0.08 m3 1,292.28 103.38 101.72% 101.633 Baldosas + transporte + 5% desp. 1.00 m2 1,127.19 1,127.19 101.72% 1,108.084 Corte de chazos 0.15 u 38.94 5.84 101.74% 5.745 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 169.55 29.84 101.70% 29.346 Cantos laterales 0.80 m 82.38 65.90 100.78% 65.397 Colocación 1.00 m2 68.45 68.45 100.00% 68.45

M2 $1,451.95 101.54% 1,429.98*PIS 10730005 ADOQUIN 511 AGUAYO TIPO PALETA, ROJO:

1 Preparación terreno 1.00 m2 51.35 51.35 100.00% 51.352 Arena lavada 0.08 m3 1,292.28 103.38 101.72% 101.633 Baldosas + transporte + 5% desp. 1.00 m2 1,396.98 1,396.98 101.72% 1,373.304 Corte de chazos 0.15 u 38.94 5.84 101.74% 5.745 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 169.55 29.84 101.70% 29.346 Cantos laterales 0.80 m 82.38 65.90 100.78% 65.397 Colocación 1.00 m2 68.45 68.45 100.00% 68.45

M2 $1,721.74 101.57% 1,695.20*PIS 10730006 ADOQUIN 604 AGUAYO 6X10.2X20.2 CM., GRIS:

1 Preparación terreno 1.00 m2 51.35 51.35 100.00% 51.352 Arena lavada 0.08 m3 1,292.28 103.38 101.72% 101.633 Baldosas + transporte + 5% desp. 1.00 m2 1,068.26 1,068.26 101.72% 1,050.154 Corte de chazos 0.15 u 38.94 5.84 101.74% 5.745 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 169.55 29.84 101.70% 29.346 Cantos laterales 0.80 m 82.38 65.90 100.78% 65.397 Colocación 1.00 m2 68.45 68.45 100.00% 68.45

M2 $1,393.02 101.53% 1,372.05*PIS 10730007 ADOQUIN 604 AGUAYO 6X10.2X20.2 CM., ROJO:

1 Preparación terreno 1.00 m2 51.35 51.35 100.00% 51.352 Arena lavada 0.08 m3 1,292.28 103.38 101.72% 101.633 Baldosas + transporte + 5% desp. 1.00 m2 1,323.73 1,323.73 101.72% 1,301.294 Corte de chazos 0.15 u 38.94 5.84 101.74% 5.745 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 169.55 29.84 101.70% 29.346 Cantos laterales 0.80 m 82.38 65.90 100.78% 65.397 Colocación 1.00 m2 68.45 68.45 100.00% 68.45

M2 $1,648.49 101.56% 1,623.19*PIS 10730008 CERAMICA CRIOLLA TIPO 01:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Horm. 1:3:5 + 5% desp. h=.10 m. 0.105 m3 4,432.36 465.40 101.49% 458.553 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.704 Baldosas + transporte + 10% desp. 1.10 m2 447.07 491.78 103.48% 475.245 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.206 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.057 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.368 Colocación 1.00 m2 301.20 301.20 100.00% 301.20

M2 $1,396.67 101.83% 1,371.53*PIS 10730009 CERAMICA IMPORTADA TIPO 09:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Horm. 1:3:5 + 5% desp. h=.10 m. 0.105 m3 4,432.36 465.40 101.49% 458.553 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.704 Baldosas + transporte + 10% desp. 1.10 m2 1,266.71 1,393.38 103.48% 1,346.535 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.206 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.057 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.368 Colocación 1.00 m2 317.05 317.05 100.00% 317.05

M2 $2,314.12 102.45% 2,258.67*PIS 10730010 GRANITO 40x40, AGLOMERADO PERLATTO ROYAL:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Mortero 1:10 + 5% desp. 0.0315 m3 4,462.92 140.58 101.52% 138.483 Baldosas + transporte + 10% desp. 1.10 m2 691.01 760.11 101.72% 747.274 Corte de chazos 2.50 u 16.52 41.30 101.72% 40.605 Derretido color + 10% desp. 0.0344 fda 861.11 29.62 101.72% 29.126 Colocación 1.00 m2 187.55 187.55 100.00% 187.557 Pulido y cristalizado 1.00 m2 304.76 304.76 101.72% 299.60

M2 $1,498.15 101.44% 1,476.85*PIS 10730011 GRANITO 30x30, 1-2-3, FONDO BLANCO:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Mortero 1:10 + 5% desp. 0.0315 m3 4,462.92 140.58 101.52% 138.483 Baldosas + transporte + 10% desp. 1.10 m2 408.21 449.03 101.73% 441.394 Corte de chazos 3.33 u 12.98 43.22 101.72% 42.495 Derreterido blanco + 10% desp. 0.0344 fda 861.11 29.62 101.72% 29.126 Colocación 1.00 m2 158.69 158.69 100.00% 158.697 Pulido y cristalizado 1.00 m2 304.76 304.76 101.72% 299.60

M2 $1,160.13 101.41% 1,144.00*PIS 10730012 GRANITO 30x30, 1-2-3, FONDO GRIS:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.23PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 88

Page 91: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

2 Mortero 1:10 + 5% desp. 0.0315 m3 4,462.92 140.58 101.52% 138.483 Baldosas + transporte + 10% desp. 1.10 m2 348.75 383.63 101.73% 377.094 Corte de chazos 3.33 u 12.98 43.22 101.72% 42.495 Derreterido gris + 10% desp. 0.0344 fda 408.87 14.07 101.74% 13.836 Colocación 1.00 m2 158.69 158.69 100.00% 158.697 Pulido y cristalizado 1.00 m2 304.76 304.76 101.72% 299.60

M2 $1,079.18 101.39% 1,064.41*PIS 10730013 GRANITO 40x40, 1-2-3, FONDO BLANCO:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Mortero 1:10 + 5% desp. 0.0315 m3 4,462.92 140.58 101.52% 138.483 Baldosas + transporte + 10% desp. 1.10 m2 584.00 642.40 101.72% 631.554 Corte de chazos 2.5 u 16.52 41.30 101.72% 40.605 Derreterido blanco + 10% desp. 0.0344 fda 861.11 29.62 101.72% 29.126 Colocación 1.00 m2 187.55 187.55 100.00% 187.557 Pulido y cristalizado 1.00 m2 304.76 304.76 101.72% 299.60

M2 $1,380.44 101.42% 1,361.13*PIS 10730014 HORMIGON ARMADO 3/8" A 20, 1:2:4, PISO .10 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 1:2:4 + 5% desp. 0.105 m3 4,432.36 465.40 101.49% 458.555 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 169.55 14.92 101.70% 14.677 Elaboración, vaciado y frotado 1.00 m2 95.38 95.38 100.00% 95.38

12,581.62 M3 M2 $1,070.17 101.31% 1,056.29*PIS 10730015 HORMIGON ARMADO 3/8" A 20, 1:2:4, PISO .12 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 1:2:4 + 5% desp. 0.130 m3 4,432.36 576.21 101.49% 567.735 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.110 pt 169.55 18.65 101.75% 18.337 Elaboración, vaciado y frotado 1.00 m2 95.38 95.38 100.00% 95.38

10,162.08 M3 M2 $1,184.71 101.33% 1,169.13*PIS 10730016 HORMIGON ARMADO 3/8" A 20, 1:2:4, PISO .15 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 1:2:4 + 5% desp. 0.160 m3 4,432.36 709.18 101.49% 698.755 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.130 pt 169.55 22.04 101.71% 21.677 Elaboración, vaciado y frotado 1.00 m2 95.38 95.38 100.00% 95.38

8,256.69 M3 M2 $1,321.07 101.35% 1,303.49*PIS 10730017 HORMIGON ARMADO 3/8" A 20, 1:2:4, PISO .20 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 1:2:4 + 5% desp. 0.210 m3 4,432.36 930.80 101.49% 917.115 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.180 pt 169.55 30.52 101.73% 30.007 Elaboración, vaciado y frotado 1.00 m2 95.38 95.38 100.00% 95.38

6,290.81 M3 M2 $1,551.17 101.37% 1,530.18*PIS 10730018 HORMIGON ARMADO 3/8" A 20, 140 Kg/Cm², PISO .10 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 140 Kg/Cm² 0.100 m3 6,911.85 691.19 101.72% 679.475 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 169.55 14.92 101.70% 14.677 frotado 1.00 m2 95.38 95.38 100.00% 95.38

13,210.70 M3 M2 $1,295.96 101.47% 1,277.21*PIS 10730019 HORMIGON ARMADO 3/8" A 20, 140 Kg/Cm², PISO .12 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 140 Kg/Cm² 0.120 m3 6,911.85 829.42 101.72% 815.365 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.110 pt 169.55 18.65 101.75% 18.337 frotado 1.00 m2 95.38 95.38 100.00% 95.38

11,008.92 M3 M2 $1,437.92 101.49% 1,416.76*PIS 10730020 HORMIGON ARMADO 3/8" A 20, 140 Kg/Cm², PISO .15 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 140 Kg/Cm² 0.150 m3 6,911.85 1,036.78 101.72% 1,019.215 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.130 pt 169.55 22.04 101.71% 21.677 frotado 1.00 m2 95.38 95.38 100.00% 95.38

8,807.13 M3 M2 $1,648.67 101.52% 1,623.95*PIS 10730021 HORMIGON ARMADO 3/8" A 20, 140 Kg/Cm², PISO .20 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 140 Kg/Cm² 0.200 m3 6,911.85 1,382.37 101.72% 1,358.945 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.180 pt 169.55 30.52 101.73% 30.007 frotado 1.00 m2 95.38 95.38 100.00% 95.38

6,605.35 M3 M2 $2,002.74 101.56% 1,972.01*PIS 10730022 HORMIGON ARMADO 3/8" A 20, 180 Kg/Cm², PISO .10 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 180 Kg/Cm² 0.100 m3 7,242.84 724.28 101.72% 712.015 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.20

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 89

Page 92: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

6 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 169.55 14.92 101.70% 14.677 frotado 1.00 m2 95.38 95.38 100.00% 95.38

13,210.70 M3 M2 $1,329.05 101.47% 1,309.75*PIS 10730023 HORMIGON ARMADO 3/8" A 20, 180 Kg/Cm², PISO .12 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 180 Kg/Cm² 0.120 m3 7,242.84 869.14 101.72% 854.415 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.110 pt 169.55 18.65 101.75% 18.337 frotado 1.00 m2 95.38 95.38 100.00% 95.38

11,008.92 M3 M2 $1,477.64 101.50% 1,455.81*PIS 10730024 HORMIGON ARMADO 3/8" A 20, 180 Kg/Cm², PISO .15 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 180 Kg/Cm² 0.150 m3 7,242.84 1,086.43 101.72% 1,068.015 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.130 pt 169.55 22.04 101.71% 21.677 frotado 1.00 m2 95.38 95.38 100.00% 95.38

8,807.13 M3 M2 $1,698.32 101.53% 1,672.75*PIS 10730025 HORMIGON ARMADO 3/8" A 20, 180 Kg/Cm², PISO .20 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 180 Kg/Cm² 0.200 m3 7,242.84 1,448.57 101.72% 1,424.025 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.180 pt 169.55 30.52 101.73% 30.007 frotado 1.00 m2 95.38 95.38 100.00% 95.38

6,605.35 M3 M2 $2,068.94 101.56% 2,037.09*PIS 10730026 HORMIGON ARMADO 3/8" A 20, 210 Kg/Cm², PISO .10 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 210 Kg/Cm² 0.100 m3 7,450.52 745.05 101.72% 732.425 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 169.55 14.92 101.70% 14.677 frotado 1.00 m2 95.38 95.38 100.00% 95.38

13,210.70 M3 M2 $1,349.82 101.48% 1,330.16*PIS 10730027 HORMIGON ARMADO 3/8" A 20, 210 Kg/Cm², PISO .12 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 210 Kg/Cm² 0.120 m3 7,450.52 894.06 101.72% 878.915 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.110 pt 169.55 18.65 101.75% 18.337 frotado 1.00 m2 95.38 95.38 100.00% 95.38

11,008.92 M3 M2 $1,502.56 101.50% 1,480.31*PIS 10730028 HORMIGON ARMADO 3/8" A 20, 210 Kg/Cm², PISO .15 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 210 Kg/Cm² 0.150 m3 7,450.52 1,117.58 101.72% 1,098.645 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.130 pt 169.55 22.04 101.71% 21.677 frotado 1.00 m2 95.38 95.38 100.00% 95.38

8,807.13 M3 M2 $1,729.47 101.53% 1,703.38*PIS 10730029 HORMIGON ARMADO 3/8" A 20, 210 Kg/Cm², PISO .20 M. ESP.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Acero de 3/8" + 10% desp. 0.136 qq 2,114.09 287.52 101.73% 282.643 Mano de obra acero 0.136 qq 364.85 49.62 100.00% 49.624 Horm. 210 Kg/Cm² 0.200 m3 7,450.52 1,490.10 101.72% 1,464.855 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.206 Regla (1 de 1"x4"x2.62' / 10 usos) 0.180 pt 169.55 30.52 101.73% 30.007 frotado 1.00 m2 95.38 95.38 100.00% 95.38

6,605.35 M3 M2 $2,110.47 101.57% 2,077.92*PIS 10730030 HORMIGON FROTADO, PISO 10 CM.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Horm. 1:3:5 + 5% desp. 0.105 m3 4,432.36 465.40 101.49% 458.553 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.204 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 169.55 14.92 101.70% 14.675 Elaboración, vaciado y frotado 1.00 m2 95.38 95.38 100.00% 95.386 Cantos laterales 0.80 m 82.38 65.90 100.78% 65.39

12,581.62 M3 M2 $798.93 101.20% 789.42*PIS 10730031 HORMIGON FROTADO Y VIOLINADO, PISO 10 CM.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Horm. 1:3:5 + 5% desp. 0.105 m3 4,432.36 465.40 101.49% 458.553 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.204 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 169.55 14.92 101.70% 14.675 Elaboración, vaciado, frotado y pulido 1.00 m2 127.17 127.17 100.00% 127.176 Cantos laterales 0.80 m 82.38 65.90 100.78% 65.39

12,581.62 M3 M2 $830.72 101.16% 821.21*PIS 10730032 HORMIGON PULIDO, PISO 10 CM.:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Horm. 1:3:5 + 5% desp. 0.105 m3 4,432.36 465.40 101.49% 458.553 Mortero 1:4 + 5% desp. 0.022 m3 5,595.53 123.10 101.57% 121.204 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 169.55 14.92 101.70% 14.675 Elaboración, vaciado, frotado y pulido 1.00 m2 134.65 134.65 100.00% 134.656 Cantos laterales 0.80 m 82.38 65.90 100.78% 65.397 Cemento gris para pulido. 0.04 fda 320.43 12.82 101.75% 12.60

12,581.62 M3 M2 $851.02 101.16% 841.29*PIS 10730033 LADRILLO EXAGONAL PEQUEÑA, PISO:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Mortero 1:10 + 5% desp. 0.0315 m3 4,462.92 140.58 101.52% 138.48

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 90

Page 93: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

3 Baldosas + transporte + 10% desp. 55.00 u 6.57 361.35 101.70% 355.304 Corte de chazos 6.00 u 9.44 56.64 101.72% 55.685 Derretido gris + 10% desp. 0.0344 fda 408.87 14.07 101.74% 13.836 Colocación 1.00 m2 171.14 171.14 100.00% 171.14

M2 $778.01 101.22% 768.66*PIS 10730034 LADRILLO TIPO FERIA PEQUEÑA, PISO:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Mortero 1:10 + 5% desp. 0.0315 m3 4,462.92 140.58 101.52% 138.483 Baldosas + transporte + 10% desp. 71.50 u 6.11 436.87 101.83% 429.004 Corte de chazos 3.00 u 9.44 28.32 101.72% 27.845 Derretido gris + 10% desp. 0.0344 fda 408.87 14.07 101.74% 13.836 Colocación 1.00 m2 221.47 221.47 100.00% 221.47

M2 $875.54 101.24% 864.85*PIS 10730035 MOSAICOS 25x25, ROJO:

1 Preparación terreno 1.00 m2 34.23 34.23 100.00% 34.232 Mortero 1:10 + 5% desp. 0.0315 m3 4,462.92 140.58 101.52% 138.483 Baldosas + transporte + 10% desp. 1.10 m2 1,140.59 1,254.65 101.73% 1,233.294 Corte de chazos 4.00 u 9.44 37.76 101.72% 37.125 Derretido gris + 10% desp. 0.0344 fda 408.87 14.07 101.74% 13.836 Colocación 1.00 m2 137.53 137.53 100.00% 137.53

M2 $1,618.82 101.53% 1,594.48*PIS 10730036 QUICIO GRANITO 30x07, BLANCO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 4,929.27 10.35 101.67% 10.182 Baldosas + transporte + 10% desp. 1.10 m 76.60 84.26 101.73% 82.833 Corte de chazos 1.00 u 12.98 12.98 101.72% 12.764 Lechada cemento blanco + 10% desp. 0.001 fda 861.11 0.86 101.18% 0.855 Colocación 1.00 m 113.66 113.66 100.00% 113.66

M $222.11 100.83% 220.28*PIS 10730037 QUICIO GRANITO 40x07, BLANCO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 4,929.27 10.35 101.67% 10.182 Baldosas + transporte + 10% desp. 1.10 m 85.54 94.09 101.73% 92.493 Corte de chazos 1.00 u 16.52 16.52 101.72% 16.244 Lechada cemento blanco + 10% desp. 0.001 fda 861.11 0.86 101.18% 0.855 Colocación 1.00 m 113.66 113.66 100.00% 113.66

M $235.48 100.88% 233.42*PIS 10730038 QUICIO MOSAICOS 25x07, ROJO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 4,929.27 10.35 101.67% 10.182 Baldosas + transporte + 10% desp. 1.10 m 198.19 218.01 101.73% 214.313 Corte de chazos 1.00 u 16.52 16.52 101.72% 16.244 Lechada cemento gris + 10% desp. 0.001 fda 408.87 0.41 102.50% 0.405 Colocación 1.00 m 113.66 113.66 100.00% 113.66

M $358.95 101.17% 354.79*PIS 10730039 QUICIO LADRILLO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 4,929.27 10.35 101.67% 10.182 Baldosas + transporte + 10% desp. 4.40 u 9.97 43.87 101.74% 43.123 Corte de chazos 1.00 u 7.08 7.08 101.72% 6.964 Lechada cemento gris + 10% desp. 0.001 fda 408.87 0.41 102.50% 0.405 Colocación 1.00 m 113.66 113.66 100.00% 113.66

M $175.37 100.60% 174.32*PIS 10730040 ZABALETA DE PISO:

1 Mortero 1:3. 0.0105 m3 4,929.27 51.76 101.65% 50.922 Mano de obra 1.00 m 30.71 30.71 100.00% 30.71

M $82.47 101.03% 81.63*PIS 10730041 ZOCALO GRANITO PERLATTO ROYAL 40x07:

1 Mortero 1:3 + 5% desp. 0.0021 m3 4,929.27 10.35 101.67% 10.182 Baldosas + transporte + 10% desp. 1.10 m 110.30 121.33 101.73% 119.273 Corte de chazos 1.00 u 7.08 7.08 101.72% 6.964 Lechada cemento con color + 10% desp. 0.001 fda 861.11 0.86 101.18% 0.855 Colocación 1.00 m 68.45 68.45 100.00% 68.45

M $208.07 101.15% 205.71*PIS 10730042 ZOCALO P/ESCALONES, SUPER CHAPA CREMA MARFIL:

1 Mortero 1:3 + 5% desp. 0.0063 m3 4,929.27 31.05 101.64% 30.552 Baldosas + transporte + 10% desp. 1.25 p 240.16 300.20 101.72% 295.113 Colocación 1.00 u 115.85 115.85 100.00% 115.85

U $447.10 101.27% 441.51*PIS 10730043 ZOCALO GRANITO 30x07, BLANCO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 4,929.27 10.35 101.67% 10.182 Baldosas + transporte + 10% desp. 1.10 m 76.60 84.26 101.73% 82.833 Corte de chazos 1.00 u 7.08 7.08 101.72% 6.964 Lechada cemento blanco + 10% desp. 0.001 fda 861.11 0.86 101.18% 0.855 Colocación 1.00 m 68.45 68.45 100.00% 68.45

M $171.00 101.02% 169.27*PIS 10730044 ZOCALO GRANITO 30x07, GRIS:

1 Mortero 1:3 + 5% desp. 0.0021 m3 4,929.27 10.35 101.67% 10.182 Baldosas + transporte + 10% desp. 1.10 m 48.46 53.31 101.74% 52.403 Corte de chazos 1.00 u 7.08 7.08 101.72% 6.964 Lechada cemento gris + 10% desp. 0.001 fda 408.87 0.41 102.50% 0.405 Colocación 1.00 m 68.45 68.45 100.00% 68.45

M $139.60 100.87% 138.39*PIS 10730045 ZOCALO GRANITO 40x07, BLANCO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 4,929.27 10.35 101.67% 10.182 Baldosas + transporte + 10% desp. 1.10 m 85.54 94.09 101.73% 92.493 Corte de chazos 1.00 u 7.08 7.08 101.72% 6.964 Lechada cemento blanco + 10% desp. 0.001 fda 861.11 0.86 101.18% 0.855 Colocación 1.00 m 68.45 68.45 100.00% 68.45

M $180.83 101.06% 178.93*PIS 10730046 ZOCALO LADRILLOS 28x7:

1 Mortero 1:3 + 5% desp. 0.0021 m3 4,929.27 10.35 101.67% 10.182 Baldosas + transporte + 10% desp. 3.93 u 9.97 39.18 101.74% 38.513 Corte de chazos 1.00 u 7.08 7.08 101.72% 6.964 Lechada cemento gris + 10% desp. 0.001 fda 408.87 0.41 102.50% 0.405 Colocación 1.00 m 68.45 68.45 100.00% 68.45

M $125.47 100.78% 124.50

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 91

Page 94: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

*PIS 10730047 ZOCALO MOSAICOS 25x07, ROJO:1 Mortero 1:3 + 5% desp. 0.0021 m3 4,929.27 10.35 101.67% 10.182 Baldosas + transporte + 10% desp. 1.10 m 198.19 218.01 101.73% 214.313 Corte de chazos 1.00 u 7.08 7.08 101.72% 6.964 Lechada cemento gris + 10% desp. 0.001 fda 408.87 0.41 102.50% 0.405 Colocación 1.00 m 50.20 50.20 100.00% 50.20

M $286.05 101.42% 282.05

*PORMAD 10750000 PORTAJE DE MADERA

*PORMAD 10750001 PUERTA DE PLYWOOD 3'x7':1 Marco de pino 16.73 p 47.22 789.99 101.72% 776.612 Puerta plywood 3'x7' 21.00 pt 91.23 1,915.83 101.73% 1,883.283 Bisagras "STANLEY" 3 ½"x3 ½" 1.50 par 102.66 153.99 101.72% 151.384 Tornillos 3"x14 7.00 u 12.98 90.86 101.72% 89.325 Tarugos 3/8" plásticos 7.00 u 2.01 14.07 102.03% 13.796 Llavín corriente 1.00 u 660.80 660.80 101.72% 649.607 Montura todo costo 1.00 u 1,165.50 1,165.50 100.00% 1,165.50

M2 $2,454.84 Unid. $4,791.04 101.30% 4,729.48*PORMAD 10750002 PUERTA DE PINO panel 3'x7':

1 Marco de pino 16.73 p 47.22 789.99 101.72% 776.612 Puerta pino 3'x7' 21.00 pt 165.27 3,470.67 101.72% 3,411.873 Bisagras "STANLEY" 3 ½"x3 ½" 1.50 par 102.66 153.99 101.72% 151.384 Tornillos 3"x14 7.00 u 12.98 90.86 101.72% 89.325 Tarugos 3/8" plásticos 7.00 u 2.01 14.07 102.03% 13.796 Llavín corriente 1.00 u 660.80 660.80 101.72% 649.607 Montura todo costo 1.00 u 1,165.50 1,165.50 100.00% 1,165.50

M2 $3,251.51 Unid. $6,345.88 101.40% 6,258.07*PORMAD 10750003 PUERTA DE CAOBA panel 3'x7':

1 Marco de caoba. 16.73 p 145.95 2,441.74 101.72% 2,400.422 Puerta caoba 3'x7' 21.00 pt 566.64 11,899.44 101.72% 11,697.843 Bisagras "STANLEY" 3 ½"x3 ½" 1.50 par 102.66 153.99 101.72% 151.384 Tornillos 3"x14 7.00 u 12.98 90.86 101.72% 89.325 Tarugos 3/8" plásticos 7.00 u 2.01 14.07 102.03% 13.796 Llavín de calidad. 1.00 u 1,770.00 1,770.00 101.72% 1,740.007 Montura todo costo 1.00 u 1,165.50 1,165.50 100.00% 1,165.50

M2 $8,984.91 Unid. $17,535.60 101.61% 17,258.25*PORMAD 10750004 PUERTA DE CAOBA panel ESP. 3'x7':

1 Marco de caoba. 16.73 p 145.95 2,441.74 101.72% 2,400.422 Puerta caoba 3'x7' 21.00 pt 581.64 12,214.44 101.68% 12,012.843 Bisagras "STANLEY" 3 ½"x3 ½" 1.50 par 102.66 153.99 101.72% 151.384 Tornillos 3"x14 7.00 u 12.98 90.86 101.72% 89.325 Tarugos 3/8" plásticos 7.00 u 2.01 14.07 102.03% 13.796 Llavín especial 1.00 u 5,310.00 5,310.00 101.72% 5,220.007 Montura todo costo 1.00 u 1,165.50 1,165.50 100.00% 1,165.50

M2 $10,960.14 Unid. $21,390.60 101.60% 21,053.25*PORMAD 10750005 PUERTA DE CAOBA, VAIVEN 3'x7':

1 Marco de caoba. 16.73 p 145.95 2,441.74 101.72% 2,400.422 Puerta caoba 3'x7' 21.00 pt 566.64 11,899.44 101.72% 11,697.843 Bisagra vaiven de piso 1.00 u 742.59 742.59 101.72% 730.004 Tornillos 3"x14 7.00 u 12.98 90.86 101.72% 89.325 Tarugos 3/8" plásticos 7.00 u 2.01 14.07 102.03% 13.796 Montura todo costo 1.00 u 1,165.50 1,165.50 100.00% 1,165.50

M2 $8,379.58 Unid. $16,354.20 101.60% 16,096.87*PORMAD 10750006 PUERTA DE CAOBA, FRANCESA: (Ancho = 2.8 m.)

1 Marco caoba (4 de 7' + 9.18') 37.18 p 145.95 5,426.42 101.72% 5,334.592 Puerta caoba 9.18'x7' 63.27 pt 566.64 35,851.31 101.72% 35,243.923 Bisagras "STANLEY" 3 ½"x3 ½" 3.00 par 102.66 307.98 101.72% 302.764 Tornillos 3"x14 10.00 u 12.98 129.80 101.72% 127.605 Tarugos 3/8" plásticos 10.00 u 2.01 20.10 102.03% 19.706 Fallebas 6" 1.00 u 409.46 409.46 101.72% 402.527 Fallebas 10" 1.00 u 867.30 867.30 101.72% 852.608 Clavos 2" 0.50 lb 30.43 15.22 101.74% 14.969 Llavín de calidad 1.00 u 1,770.00 1,770.00 101.72% 1,740.0010 Montura todo costo 4.00 u 1,165.50 4,662.00 100.00% 4,662.00

M2 $8,411.34 Unid. $49,459.59 101.56% 48,700.65

*REP 10710000 REPLANTEO SEGUN DISEÑO

*REP 10710001 CHARRANCHA, CALCULO DEL COSTO Cambie solo los valores en AZUL.Perímetro 68.00 m.

Rectángulo EDIFICADO 200.00 m2Lado X de edificación 10.00 m.Lado Y de edificación 20.00 m.

Cant. Ejes de Col. y Muros en X-X 12 u.Cant. Ejes de Col. y Muros en Y-Y 11 u.Separación Charrancha de cimiento 1.000 m.

Cant. estacas./enlates. 2 u.Cant. Usos madera 4 usosDesperdicio clavos 25%

Desperdicio madera 10%Dim. enlate (pulg. x pulg. x pies) 1 4 10 pies 25.00 uDim. etaca (pulg. x pulg. x pies) 1 4 2.500 pies 50.00 u

Cant. clavos por estaca (fijación) 4 u.

1 Clavos corrientes 2 ½" Rend./lb. 87 u. 5.52 lb 30.43 167.97 101.70% 165.162 Cal 50 lbs. Rend./m. 0.040 funda 3.00 fda 283.20 849.60 101.72% 835.203 Madera, pino bruto americano 34.38 pt 35.70 1,227.19 101.74% 1,206.224 Hilo de nylon Rend./m. 0.005 rollo 1.00 u 106.29 106.29 101.72% 104.495 Técnico Calificado (TC) Rend./m. 0.034 día 2.50 u 474.00 1,185.00 100.00% 1,185.006 Carpintero de segunda (OP2) Rend./m. 0.015 día 1.50 u 825.00 1,237.50 100.00% 1,237.507 Maestro de área (MA) Rend./m. 0.015 día 1.50 u 1,300.00 1,950.00 100.00% 1,950.00

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 92

Page 95: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

8 Brigada topográfica Rend./m. 0.015 día 1.50 u 5,075.00 7,612.50 100.00% 7,612.50Unid. $14,336.05 100.28% 14,296.07

M $210.82 100.28% 210.24M2 $71.68 100.28% 71.48

*REV 10730000 REVESTIMIENTO EN PAREDES

*REV 10730001 CERAMICA CRIOLLA TIPO 01:1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 447.07 491.78 103.48% 475.243 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.366 Colocación 1.00 m2 286.86 286.86 100.00% 286.86

M2 $882.70 102.12% 864.41*REV 10730002 CERAMICA CRIOLLA TIPO 02:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 484.32 532.75 103.47% 514.863 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.366 Colocación 1.00 m2 286.86 286.86 100.00% 286.86

M2 $923.67 102.17% 904.03*REV 10730003 CERAMICA CRIOLLA TIPO 03:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 521.60 573.76 103.48% 554.463 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.366 Colocación 1.00 m2 286.86 286.86 100.00% 286.86

M2 $964.68 102.23% 943.63*REV 10730004 CERAMICA CRIOLLA TIPO 04:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 596.10 655.71 103.48% 633.683 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.366 Colocación 1.00 m2 286.86 286.86 100.00% 286.86

M2 $1,046.63 102.32% 1,022.85*REV 10730005 CERAMICA CRIOLLA TIPO 05:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 745.12 819.63 103.48% 792.093 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.366 Colocación 1.00 m2 286.86 286.86 100.00% 286.86

M2 $1,210.55 102.48% 1,181.26*REV 10730006 CERAMICA CRIOLLA TIPO 06:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 819.63 901.59 103.48% 871.293 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.366 Colocación 1.00 m2 286.86 286.86 100.00% 286.86

M2 $1,292.51 102.54% 1,260.46*REV 10730007 CERAMICA CRIOLLA TIPO 07:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 968.66 1,065.53 103.48% 1,029.723 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.366 Colocación 1.00 m2 286.86 286.86 100.00% 286.86

M2 $1,456.45 102.65% 1,418.89*REV 10730008 CERAMICA CRIOLLA TIPO 08:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 1,117.67 1,229.44 103.48% 1,188.123 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.366 Colocación 1.00 m2 286.86 286.86 100.00% 286.86

M2 $1,620.36 102.73% 1,577.29*REV 10730009 CERAMICA IMPORT. TIPO 09:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 1,266.71 1,393.38 103.48% 1,346.533 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.366 Colocación 1.00 m2 317.05 317.05 100.00% 317.05

M2 $1,814.49 102.75% 1,765.89*REV 10730010 CERAMICA IMPORT. TIPO 10:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 1,378.48 1,516.33 103.48% 1,465.353 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.366 Colocación 1.00 m2 317.05 317.05 100.00% 317.05

M2 $1,937.44 102.80% 1,884.71*REV 10730011 CERAMICA IMPORT. TIPO 11:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 1,490.23 1,639.25 103.48% 1,584.173 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.36

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 93

Page 96: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

6 Colocación 1.00 m2 317.05 317.05 100.00% 317.05M2 $2,060.36 102.84% 2,003.53

*REV 10730012 CERAMICA IMPORT. TIPO 12:1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 7,806.60 41.37 101.65% 40.702 Baldosas + 10% desp. 1.10 m2 1,639.27 1,803.20 103.48% 1,742.593 Corte de chazos 5.00 u 7.57 37.85 101.75% 37.204 Lechada cemento bco. + 10% desp. 0.0330 fda 649.00 21.42 101.76% 21.055 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.366 Colocación 1.00 m2 317.05 317.05 100.00% 317.05

M2 $2,224.31 102.88% 2,161.95*REV 10730013 LADRILLO BISCOCHO 2"x2"x8":

1 Mortero 1:2 imp. + 20% desp. 0.0120 m3 7,806.60 93.68 101.67% 92.142 Ladrillos + transporte + 5% desp. 58.00 u 12.83 744.14 101.74% 731.383 Corte de chazos 5.80 u 38.94 225.85 101.73% 222.024 Colocación 58.00 u 7.17 415.86 100.00% 415.86

M2 $1,479.53 101.24% 1,461.40*REV 10730014 LADRILLO 2"x4"x8":

1 Mortero 1:2 imp. + 20% desp. 0.0120 m3 7,806.60 93.68 101.67% 92.142 Ladrillos + transporte + 5% desp. 58.00 u 19.91 1,154.78 101.74% 1,135.063 Corte de chazos 5.80 u 38.94 225.85 101.73% 222.024 Estopa (1 lb. / 20 m2) 0.05 lb 68.44 3.42 101.79% 3.365 Colocación 58.00 u 7.17 415.86 100.00% 415.86

M2 $1,893.59 101.35% 1,868.44

*TEC 10750000 TECHOS DE MADERA CON FORRO DE MADERA

*TEC 10750001 TECHO TEJA ASF., FORRADO EN CAOBA (SOBRE DINTEL CORRIDO):Durmientes: 2" x 4" Vigas (Limatesa): 2" x 6"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 6"Tablas (borde perimetral): 1" x 6"

1 Durmientes en caoba sobre dintel + 25% desp. 1.39 pt 127.16 176.75 101.73% 173.752 Vigas (limatesa) en caoba + 25% desp. 1.63 pt 127.16 207.27 101.73% 203.753 Bajantes o cargaderas en caoba + 25% desp. 7.75 pt 127.16 985.49 101.73% 968.754 Separadores de Bajantes en caoba + 25% desp. 3.66 pt 127.16 465.41 101.73% 457.505 Tablas en caoba en borde perimetral + 25% desp. 1.17 pt 127.16 148.78 101.73% 146.256 Tablas (forro) en caoba + 25% desp. 16.50 pt 127.16 2,098.14 101.73% 2,062.507 Teja asfáltica 3' x 1', Felpa, instadada + 10% desp. 1.16 m2 329.69 382.44 101.72% 375.968 Transporte teja asfáltica 34.84 u 0.49 17.07 100.00% 17.079 Caballete de teja asfáltica + 10% desp. 0.40 m 116.78 46.71 101.72% 45.9210 Línea doble teja asfáltica inst. todo costo, en bordes 0.60 m 116.78 70.07 101.71% 68.8911 Clavos corrientes (5 lb. / 100 p2) 0.78 lb 30.43 23.74 101.71% 23.3412 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 44.25 36.51 101.73% 35.8913 Clavos galv. ¾" para cartón (125 unid. / m2) 0.43 lb 49.44 21.26 101.72% 20.9014 Andamios 1.11 m2 79.22 87.93 101.71% 86.4515 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 2,973.60 327.10 101.73% 321.5516 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,319.00 2,374.20 101.72% 2,333.9717 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 12.39 156.24 101.73% 153.5918 Mano de obra madera sin forro 15.60 pt 53.55 835.38 101.73% 821.1819 Mano de obra madera del forro + laqueado 11.93 pt 112.46 1,341.65 101.75% 1,318.62

M2 $9,802.14 101.73% 9,635.83*TEC 10750002 TECHO TEJA ASF., FORRADO EN CEDRO (SOBRE DINTEL CORRIDO):

Durmientes: 2" x 4" Vigas (Limatesa): 2" x 6"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 6"Tablas (borde perimetral): 1" x 6"

1 Durmientes en cedro sobre dintel + 25% desp. 1.39 pt 122.07 169.68 101.73% 166.802 Vigas (limatesa) en cedro + 25% desp. 1.63 pt 122.07 198.97 101.72% 195.603 Bajantes o cargaderas en cedro + 25% desp. 7.75 pt 122.07 946.04 101.72% 930.004 Separadores de Bajantes en cedro + 25% desp. 3.66 pt 122.07 446.78 101.73% 439.205 Tablas en cedro en borde perimetral + 25% desp. 1.17 pt 122.07 142.82 101.72% 140.406 Tablas (forro) en cedro + 25% desp. 16.50 pt 122.07 2,014.16 101.73% 1,980.007 Teja asfáltica 3' x 1', Felpa, instadada + 10% desp. 1.16 m2 329.69 382.44 101.72% 375.968 Transporte 34.84 u 0.49 17.07 100.00% 17.079 Caballete de teja asfáltica + 10% desp. 0.40 m 116.78 46.71 101.72% 45.9210 Línea doble teja asfáltica inst. todo costo, en bordes 0.60 m 116.78 70.07 101.71% 68.8911 Clavos corrientes (5 lb. / 100 p2) 0.78 lb 30.43 23.74 101.71% 23.3412 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 44.25 36.51 101.73% 35.8913 Clavos galv. ¾" para cartón (125 unid. / m2) 0.43 lb 49.44 21.26 101.72% 20.9014 Andamios 1.11 m2 79.22 87.93 101.71% 86.4515 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 2,973.60 327.10 101.73% 321.5516 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,319.00 2,374.20 101.72% 2,333.9717 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 12.39 156.24 101.73% 153.5918 Mano de obra madera sin forro 15.60 pt 53.55 835.38 101.73% 821.1819 Mano de obra madera del forro + laqueado 11.93 pt 112.46 1,341.65 101.75% 1,318.62

M2 $9,638.75 101.72% 9,475.33*TEC 10750003 TECHO TEJA ASF., FORRADO EN PINO TRAT. (SOBRE DINTEL CORRIDO):

Durmientes: 2" x 4" Vigas (Limatesa): 2" x 6"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 6"Tablas (borde perimetral): 1" x 6"

1 Durmientes en pino trat. sobre dintel + 25% desp. 1.39 pt 24.39 33.90 101.71% 33.332 Vigas (limatesa) en pino trat. + 25% desp. 1.63 pt 24.39 39.76 101.71% 39.093 Bajantes o cargaderas en pino trat. + 25% desp. 7.75 pt 24.39 189.02 101.71% 185.854 Separadores de Bajantes en pino trat. + 25% desp. 3.66 pt 24.39 89.27 101.71% 87.775 Tablas en pino trat. en borde perimetral + 25% desp. 1.17 pt 24.39 28.54 101.71% 28.066 Tablas (forro) en pino trat. + 25% desp. 16.50 pt 24.39 402.44 101.71% 395.677 Teja asfáltica 3' x 1', Felpa, instadada + 10% desp. 1.16 m2 329.69 382.44 101.72% 375.968 Transporte teja asfáltica 34.84 u 0.49 17.07 100.00% 17.079 Caballete de teja asfáltica + 10% desp. 0.40 m 116.78 46.71 101.72% 45.9210 Línea doble teja asfáltica inst. todo costo, en bordes 0.60 m 116.78 70.07 101.71% 68.8911 Clavos corrientes (5 lb. / 100 p2) 0.78 lb 30.43 23.74 101.71% 23.3412 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 44.25 36.51 101.73% 35.8913 Clavos galv. ¾" para cartón (125 unid. / m2) 0.43 lb 49.44 21.26 101.72% 20.9014 Andamios 1.11 m2 79.22 87.93 101.71% 86.4515 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 2,973.60 327.10 101.73% 321.5516 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,319.00 2,374.20 101.72% 2,333.97

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 94

Page 97: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

17 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 12.39 156.24 101.73% 153.5918 Mano de obra madera sin forro 15.60 pt 53.55 835.38 101.73% 821.1819 Mano de obra madera del forro + laqueado 11.93 pt 112.46 1,341.65 101.75% 1,318.62

M2 $6,503.23 101.72% 6,393.10*TEC 10750004 TECHO TEJA ASF., FORRADO EN ROBLE BRASILEÑO (SOBRE DINTEL CORRIDO):

Durmientes: 2" x 4" Vigas (Limatesa): 2" x 6"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 6"Tablas (borde perimetral): 1" x 6"

1 Durmientes en roble sobre dintel + 25% desp. 1.39 pt 180.06 250.28 101.73% 246.032 Vigas (limatesa) en roble + 25% desp. 1.63 pt 180.06 293.50 101.73% 288.513 Bajantes o cargaderas en roble + 25% desp. 7.75 pt 180.06 1,395.47 101.73% 1,371.754 Separadores de Bajantes en roble + 25% desp. 3.66 pt 180.06 659.02 101.73% 647.825 Tablas en roble en borde perimetral + 25% desp. 1.17 pt 180.06 210.67 101.73% 207.096 Tablas (forro) en roble + 25% desp. 16.50 pt 180.06 2,970.99 101.73% 2,920.507 Teja asfáltica 3' x 1', Felpa, instadada + 10% desp. 1.16 m2 329.69 382.44 101.72% 375.968 Transporte teja asfáltica 34.84 u 0.49 17.07 100.00% 17.079 Caballete de teja asfáltica + 10% desp. 0.40 m 116.78 46.71 101.72% 45.9210 Línea doble teja asfáltica inst. todo costo, en bordes 0.60 m 116.78 70.07 101.71% 68.8911 Clavos corrientes (5 lb. / 100 p2) 0.78 lb 30.43 23.74 101.71% 23.3412 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 44.25 36.51 101.73% 35.8913 Clavos galv. ¾" para cartón (125 unid. / m2) 0.43 lb 49.44 21.26 101.72% 20.9014 Andamios 1.11 m2 79.22 87.93 101.71% 86.4515 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 2,973.60 327.10 101.73% 321.5516 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,319.00 2,374.20 101.72% 2,333.9717 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 12.39 156.24 101.73% 153.5918 Mano de obra madera sin forro 15.60 pt 53.55 835.38 101.73% 821.1819 Mano de obra madera del forro + laqueado 11.93 pt 112.46 1,341.65 101.75% 1,318.62

M2 $11,500.23 101.73% 11,305.03*TEC 10750005 TECHO TEJA CURVA BARRO, FORRADO EN CAOBA (SOBRE DINTEL CORRIDO):

Durmientes: 3" x 6" Vigas (Limatesa): 2" x 10"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 10"Tablas (borde perimetral): 1" x 10"

1 Durmientes en caoba sobre dintel + 25% desp. 3.13 pt 127.16 398.01 101.73% 391.252 Vigas (limatesa) en caoba + 25% desp. 2.71 pt 127.16 344.60 101.73% 338.753 Bajantes o cargaderas en caoba + 25% desp. 12.92 pt 127.16 1,642.91 101.73% 1,615.004 Separadores de Bajantes en caoba + 25% desp. 6.09 pt 127.16 774.40 101.73% 761.255 Tablas en caoba en borde perimetral + 25% desp. 1.94 pt 127.16 246.69 101.73% 242.506 Tablas (forro) en caoba + 25% desp. 16.50 pt 127.16 2,098.14 101.73% 2,062.507 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 16.97 591.25 103.48% 571.398 Mortero 1:2 imp. + 10% desp. 0.055 m3 7,806.60 429.36 101.67% 422.319 Estopa (1 lb. / 20 m2) 0.06 lb 68.44 4.11 101.73% 4.0410 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 1.24 43.20 101.62% 42.5111 Caballete de teja 0.20 u 68.59 13.94 103.49% 13.4712 Clavos corrientes (5 lb. / 100 p2) 1.34 lb 30.43 40.78 101.72% 40.0913 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 44.25 36.51 101.73% 35.8914 Andamios 1.11 m2 79.22 87.93 101.71% 86.4515 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 2,973.60 327.10 101.73% 321.5516 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,319.00 2,374.20 101.72% 2,333.9717 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 12.39 156.24 101.73% 153.5918 Mano de obra madera sin forro 26.79 pt 53.55 1,434.60 101.73% 1,410.2319 Mano de obra madera del forro + laqueado 11.93 pt 112.46 1,341.65 101.75% 1,318.6220 Bitupol 4 mm., reforz. poliester, 10 años gar. 1.11 m2 599.00 664.89 101.72% 653.6221 Coloc. de tejas 1.00 m2 257.88 257.88 100.00% 257.8822 Coloc. Caballete 0.20 u 41.89 8.51 100.00% 8.51

M2 $13,316.90 101.77% 13,085.37*TEC 10750006 TECHO TEJA CURVA BARRO, FORRADO EN CEDRO (SOBRE DINTEL CORRIDO):

Durmientes: 3" x 6" Vigas (Limatesa): 2" x 10"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 10"Tablas (borde perimetral): 1" x 10"

1 Durmientes en cedro sobre dintel + 25% desp. 3.13 pt 122.07 382.08 101.73% 375.602 Vigas (limatesa) en cedro + 25% desp. 2.71 pt 122.07 330.81 101.73% 325.203 Bajantes o cargaderas en cedro + 25% desp. 12.92 pt 122.07 1,577.14 101.72% 1,550.404 Separadores de Bajantes en cedro + 25% desp. 6.09 pt 122.07 743.41 101.73% 730.805 Tablas en cedro en borde perimetral + 25% desp. 1.94 pt 122.07 236.82 101.73% 232.806 Tablas (forro) en cedro + 25% desp. 16.50 pt 122.07 2,014.16 101.73% 1,980.007 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 16.97 591.25 103.48% 571.398 Mortero 1:2 imp. + 10% desp. 0.055 m3 7,806.60 429.36 101.67% 422.319 Estopa (1 lb. / 20 m2) 0.06 lb 68.44 4.11 101.73% 4.0410 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 1.24 43.20 101.62% 42.5111 Caballete de teja. 0.20 u 58.13 11.81 101.72% 11.6112 Clavos corrientes (5 lb. / 100 p2) 1.34 lb 30.43 40.78 101.72% 40.0913 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 44.25 36.51 101.73% 35.8914 Andamios 1.11 m2 79.22 87.93 101.71% 86.4515 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 2,973.60 327.10 101.73% 321.5516 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,319.00 2,374.20 101.72% 2,333.9717 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 12.39 156.24 101.73% 153.5918 Mano de obra madera sin forro 26.79 pt 53.55 1,434.60 101.73% 1,410.2319 Mano de obra madera del forro + laqueado 11.93 pt 112.46 1,341.65 101.75% 1,318.6220 Bitupol 4 mm., reforz. poliester, 10 años gar. 1.11 m2 599.00 664.89 101.72% 653.6221 Coloc. de tejas 1.00 m2 257.88 257.88 100.00% 257.8822 Coloc. Caballete 0.20 u 41.89 8.51 100.00% 8.51

M2 $13,094.44 101.77% 12,867.06*TEC 10750007 TECHO TEJA CURVA BARRO, FORRADO EN PINO TRAT. (SOBRE DINTEL CORRIDO):

Durmientes: 3" x 6" Vigas (Limatesa): 2" x 10"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 10"Tablas (borde perimetral): 1" x 10"

1 Durmientes en pino sobre dintel + 25% desp. 3.13 pt 24.39 76.34 101.71% 75.062 Vigas (limatesa) en pino + 25% desp. 2.71 pt 24.39 66.10 101.71% 64.993 Bajantes o cargaderas en pino + 25% desp. 12.92 pt 24.39 315.12 101.71% 309.824 Separadores de Bajantes en pino + 25% desp. 6.09 pt 24.39 148.54 101.71% 146.045 Tablas en pino en borde perimetral + 25% desp. 1.94 pt 24.39 47.32 101.72% 46.526 Tablas (forro) en pino + 25% desp. 16.50 pt 24.39 402.44 101.71% 395.677 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 16.97 591.25 103.48% 571.398 Mortero 1:2 imp. + 10% desp. 0.055 m3 7,806.60 429.36 101.67% 422.31

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 95

Page 98: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

9 Estopa (1 lb. / 20 m2) 0.06 lb 68.44 4.11 101.73% 4.0410 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 1.24 43.20 101.62% 42.5111 Caballete de teja. 0.20 u 58.13 11.81 101.72% 11.6112 Clavos corrientes (5 lb. / 100 p2) 1.34 lb 30.43 40.78 101.72% 40.0913 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 44.25 36.51 101.73% 35.8914 Andamios 1.11 m2 79.22 87.93 101.71% 86.4515 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 2,973.60 327.10 101.73% 321.5516 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,319.00 2,374.20 101.72% 2,333.9717 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 12.39 156.24 101.73% 153.5918 Mano de obra madera sin forro 26.79 pt 53.55 1,434.60 101.73% 1,410.2319 Mano de obra madera del forro + laqueado 11.93 pt 112.46 1,341.65 101.75% 1,318.6220 Bitupol 4 mm., reforz. poliester, 10 años gar. 1.11 m2 599.00 664.89 101.72% 653.6221 Coloc. de tejas 1.00 m2 257.88 257.88 100.00% 257.8822 Coloc. Caballete 0.20 u 41.89 8.51 100.00% 8.51

M2 $8,865.88 101.79% 8,710.36*TEC 10750008 TECHO TEJA CURVA BARRO, FORRADO EN ROBLE BRASILEÑO (SOBRE DINTEL CORRIDO):

Durmientes: 3" x 6" Vigas (Limatesa): 2" x 10"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 10"Tablas (borde perimetral): 1" x 10"

1 Durmientes en roble sobre dintel + 25% desp. 3.13 pt 180.06 563.59 101.73% 554.012 Vigas (limatesa) en roble + 25% desp. 2.71 pt 180.06 487.96 101.73% 479.673 Bajantes o cargaderas en roble + 25% desp. 12.92 pt 180.06 2,326.38 101.73% 2,286.844 Separadores de Bajantes en roble + 25% desp. 6.09 pt 180.06 1,096.57 101.73% 1,077.935 Tablas en roble en borde perimetral + 25% desp. 1.94 pt 180.06 349.32 101.73% 343.386 Tablas (forro) en roble + 25% desp. 16.50 pt 180.06 2,970.99 101.73% 2,920.507 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 16.97 591.25 103.48% 571.398 Mortero 1:2 imp. + 10% desp. 0.055 m3 7,806.60 429.36 101.67% 422.319 Estopa (1 lb. / 20 m2) 0.06 lb 68.44 4.11 101.73% 4.0410 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 1.24 43.20 101.62% 42.5111 Caballete de teja. 0.20 u 58.13 11.81 101.72% 11.6112 Clavos corrientes (5 lb. / 100 p2) 1.34 lb 30.43 40.78 101.72% 40.0913 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 44.25 36.51 101.73% 35.8914 Andamios 1.11 m2 79.22 87.93 101.71% 86.4515 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 2,973.60 327.10 101.73% 321.5516 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,319.00 2,374.20 101.72% 2,333.9717 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 12.39 156.24 101.73% 153.5918 Mano de obra madera sin forro 26.79 pt 53.55 1,434.60 101.73% 1,410.2319 Mano de obra madera del forro + laqueado 11.93 pt 112.46 1,341.65 101.75% 1,318.6220 Bitupol 4 mm., reforz. poliester, 10 años gar. 1.11 m2 599.00 664.89 101.72% 653.6221 Coloc. de tejas 1.00 m2 257.88 257.88 100.00% 257.8822 Coloc. Caballete 0.20 u 41.89 8.51 100.00% 8.51

M2 $15,604.83 101.76% 15,334.59*TEC 10750009 TECHO TEJA CURVA BARRO SOBRE FINO DE HORM. IMPERMEABILIZADO:

1 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 16.97 591.25 103.48% 571.392 Mortero 1:2 imp. + 10% desp. 0.055 m3 7,806.60 429.36 101.67% 422.313 Estopa (1 lb. / 20 m2) 0.06 lb 68.44 4.11 101.73% 4.044 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 1.24 43.20 101.62% 42.515 Caballete de teja. 0.20 u 58.13 11.81 101.72% 11.616 Bitupol 4 mm., reforz. poliester, 10 años gar. 1.11 m2 599.00 664.89 101.72% 653.627 Coloc. de tejas 1.00 m2 257.88 257.88 100.00% 257.888 Coloc. Caballete 0.20 u 41.89 8.51 100.00% 8.51

M2 $2,011.01 101.98% 1,971.87*TEC 10750010 TECHO TEJA CURVA BARRO Y TIJERILLA EN PINO:

1 Madera tijerilla + 25% desp. 2.91 pt 35.70 103.74 101.75% 101.962 Correas, .948 piezas 2"x4"x10' + 25% desp., pino am. bruto. 7.90 pt 35.70 282.03 101.74% 277.213 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 16.97 591.25 103.48% 571.394 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 1.24 43.20 101.62% 42.515 Caballete de teja. 0.20 u 58.13 11.81 101.72% 11.616 Alambre #18 (0.5 lb. / m2) 0.50 lb 34.64 17.32 101.70% 17.037 Clavos corrientes (5 lb. / 100 p2) 0.54 lb 30.43 16.53 101.72% 16.258 Mano de obra madera 10.86 pt 53.55 581.71 101.73% 571.839 Coloc. de tejas 1.00 m2 257.88 257.88 100.00% 257.8810 Coloc. Caballete 0.20 u 41.89 8.51 100.00% 8.51

M2 $1,913.98 102.01% 1,876.18*TEC 10750011 TECHO ZINC CAL. 26 Y TIJERILLA EN PINO:

1 Madera tijerilla + 25% desp. 2.9058 pt 35.70 103.74 101.75% 101.962 Correas, .677 piezas 2"x4"x10' + 25% desp., pino am. Bruto 5.6417 pt 35.70 201.41 101.74% 197.973 Planchas de ZINC ACANALADO cal. 26, de 3'x6' + 25% desp. 1.05 u 637.20 669.06 101.72% 657.724 Caballete de zinc de 3', cal. 29 0.1354 m 188.80 25.56 101.71% 25.135 Clavos corrientes (5 lb. / 100 p2) 0.43 lb 30.43 13.08 101.63% 12.876 Clavos de zinc + 5% desp. 0.14 lb 52.68 7.38 101.79% 7.257 Mano de obra madera 8.55 pt 53.55 457.72 101.73% 449.948 Coloc. láminas de zinc 1.33 u 32.22 42.85 100.00% 42.859 Coloc. caballete de zinc 0.14 u 42.30 5.73 100.00% 5.73

M2 $1,526.53 101.67% 1,501.42

*TERTEC 10770000 TECHOS (TERMINACION)

*TERTEC 10770001 FINO TECHO BERMUDA:1 Fino inclinado para preparar superficie 1.00 m2 344.59 344.59 101.31% 340.122 Mortero 1:3 + 5% desp., 4.5 cm. espesor 0.0473 m3 4,929.27 233.15 101.64% 229.393 Reglas (1 de 1"x4"x10' / 10 usos) 0.3333 pt 169.55 56.51 101.73% 55.554 Subida materiales 0.0473 m3 664.21 31.42 100.64% 31.225 Mano de obra Bermuda, sin los cantos 1.00 m2 214.31 214.31 100.00% 214.316 Cantos cada 0.40 m. 3.00 m 43.30 129.90 100.00% 129.90

M2 $1,009.88 100.94% 1,000.49*TERTEC 10770002 FINO TECHO INCLINADO:

1 Mortero 1:3 + 5% desp., 4 cm. espesor 0.0420 m3 4,929.27 207.03 101.64% 203.692 Reglas (1 de 1"x4"x10' / 10 usos) 0.3333 pt 169.55 56.51 101.73% 55.553 Subida materiales 0.0420 m3 664.21 27.90 100.61% 27.734 Mano de obra 1.00 m2 53.15 53.15 100.00% 53.15

M2 $344.59 101.31% 340.12*TERTEC 10770003 FINO TECHO PLANO:

1 Mortero 1:3 + 5% desp. (6 cm. espesor promedio). 0.0630 m3 4,929.27 310.54 101.64% 305.54PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 96

Page 99: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

2 Reglas (1 de 1"x4"x10' / 10 usos) 0.3333 pt 169.55 56.51 101.73% 55.553 Subida materiales 0.0630 m3 664.21 41.85 100.63% 41.594 Mano de obra 1.00 m2 86.38 86.38 100.00% 86.38

M2 $495.28 101.27% 489.06*TERTEC 10770004 ZABALETA DE TECHO:

1 Mortero 1:3. 0.0105 m3 4,929.27 51.76 101.65% 50.922 Subida materiales 0.0105 m3 664.21 6.97 100.58% 6.933 Mano de obra 1.00 m 46.07 46.07 100.00% 46.07

M $104.80 100.85% 103.92

*VEN 10790000 VENTANAS DE ALUMINIO

*VEN 10790001 VENTANA SALOM. ALUM. NAT. Y VIDRIO CLARO, MANIG. AA:1 Ventana 1.00 m2 4,017.39 4,017.39 101.72% 3,949.302 Operador de manigueta 2.0833 u 113.14 235.70 101.73% 231.703 Transporte + Instalación (12.00%) 12.00% 510.37 101.72% 501.72

P2 $442.70 M2 $4,763.46 101.72% 4,682.72

*VEN 10790002 VENTANA SALOM. ALUMINIO BCO., MANIG. AA:1 Ventana 1.00 m2 3,558.29 3,558.29 101.72% 3,497.982 Operador de manigueta 2.0833 u 113.14 235.70 101.73% 231.703 Transporte + Instalación (12.00%) 12.00% 455.28 101.72% 447.56

P2 $394.91 M2 $4,249.27 101.72% 4,177.24

*VEN 10790003 VENTANA SALOM. ALUMINIO BRONCE, MANIG. AA:1 Ventana 1.00 m2 3,765.60 3,765.60 101.72% 3,701.782 Operador de manigueta 2.0833 u 113.14 235.70 101.73% 231.703 Transporte + Instalación (12.00%) 12.00% 480.16 101.72% 472.02

P2 $416.49 M2 $4,481.46 101.72% 4,405.50

*VEN 10790004 VENTANA SALOM. ALUM. Y VIDRIO, TODO BRONCE,MANIG. AA:1 Ventana 1.00 m2 3,688.93 3,688.93 101.72% 3,626.402 Operador de manigueta 2.0833 u 113.14 235.70 101.73% 231.703 Transporte + Instalación (12.00%) 12.00% 470.96 101.73% 462.97

P2 $408.51 M2 $4,395.59 101.72% 4,321.07

*VEN 10790005 VENTANA SALOM. ALUM. NAT. Y VIDRIO CLARO, PALANCA:1 Ventana 1.00 m2 3,055.65 3,055.65 101.72% 3,003.852 Operador de palanca 2.0833 u 31.12 64.83 101.73% 63.733 Transporte + Instalación (12.00%) 12.00% 374.46 101.73% 368.11

P2 $324.81 M2 $3,494.94 101.72% 3,435.69

*VEN 10790006 VENTANA SALOM. ALUMINIO BCO., PALANCA:1 Ventana 1.00 m2 3,565.39 3,565.39 101.72% 3,504.962 Operador de palanca 2.0833 u 31.12 64.83 101.73% 63.733 Transporte + Instalación (12.00%) 12.00% 435.63 101.73% 428.24

P2 $377.87 M2 $4,065.85 101.72% 3,996.93

*VEN 10790007 VENTANA SALOM. ALUM. NAT., VIDRIO BRONCE, PALANCA:1 Ventana 1.00 m2 2,616.90 2,616.90 101.72% 2,572.542 Operador de palanca 2.0833 u 31.12 64.83 101.73% 63.733 Transporte + Instalación (12.00%) 12.00% 321.81 101.73% 316.35

P2 $279.14 M2 $3,003.54 101.72% 2,952.62

*VERBLO 10810000 VERJAS DE BLOQUES DE HORMIGON

*VERBLO 10810001 VERJA DE BLOQUES 5", RETALLE, COL. AMARRE CADA 3.00 m., CALICHE, Sin empañete:Largo: 32.00 H bloques: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,062.36

1 Excación de zapata 0.45 x 0.45 m., CALICHE a mano 6.48 m3 441.84 2,863.122 Regar material producto de excavación 8.100 m3 225.68 1,828.013 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 2,114.09 5,327.514 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 2,114.09 6,553.685 M. O. acero zapata del muro 33.00 m 81.08 2,675.646 M. O. acero col. amarre del muro 30.33 m 81.08 2,459.167 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,912.07 11,266.768 Horm. 1:2:4 en columnas de amarre de .175 x .20 m. Col. Cada: 3.00 0.92 m3 4,431.50 4,076.989 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 35.70 4,734.1810 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 30.43 807.0011 Clavos de acero (¼ lb / metro). 6.42 lb 53.10 340.9012 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 34.64 222.3913 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 159.51 4,094.6214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 20.94 215.0515 Muro de bloques de 5" x 8" x 16" 65.27 m2 785.79 51,285.89

3,085.97 M U $98,750.89 101.20% 97,582.42M2 Verja $1,402.71 101.20% 1,386.11

*VERBLO 10810002 VERJA DE BLOQUES 6", RETALLE, COL. AMARRE CADA 3.00 m., CALICHE, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,134.90 101.24% 1,121.00

1 Excación de zapata 0.45 x 0.45 m., CALICHE a mano 6.48 m3 441.84 2,863.12 100.00% 2,863.122 Regar material producto de excavación 8.100 m3 225.68 1,828.01 100.14% 1,825.503 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 2,114.09 5,327.51 101.72% 5,237.244 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 2,114.09 6,553.68 101.72% 6,442.645 M. O. acero zapata del muro 33.00 m 81.08 2,675.64 100.00% 2,675.646 M. O. acero col. amarre del muro 30.33 m 81.08 2,459.16 100.00% 2,459.167 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,912.07 11,266.76 101.57% 11,093.048 Horm. 1:2:4 en columnas de amarre de .20 x .20 m. Col. Cada: 3.00 1.03 m3 4,431.50 4,564.45 101.59% 4,493.119 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 35.70 4,734.18 101.74% 4,653.2810 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 30.43 807.00 101.70% 793.4811 Clavos de acero (¼ lb / metro). 6.42 lb 53.10 340.90 101.72% 335.1212 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 34.64 222.39 101.70% 218.6713 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 159.51 4,094.62 100.00% 4,094.6214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 20.94 215.05 100.00% 215.0515 Muro de bloques de 6" x 8" x 16" 65.27 m2 856.57 55,905.47 101.25% 55,212.99

3,245.56 M U $103,857.94 101.21% 102,612.66M2 Verja $1,475.25 101.21% 1,457.57

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 97

Page 100: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

*VERBLO 10810003 VERJA DE BLOQUES 8", RETALLE, COL. AMARRE CADA 3.00 m., CALICHE, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,328.14 101.28% 1,311.36

1 Excación de zapata 0.6 x 0.45 m., CALICHE a mano 8.64 m3 441.84 3,817.50 100.00% 3,817.502 Regar material producto de excavación 10.800 m3 225.68 2,437.34 100.14% 2,434.003 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.840 qq 2,114.09 6,004.02 101.72% 5,902.294 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 2,114.09 6,553.68 101.72% 6,442.645 M. O. acero zapata del muro 33.00 m 81.08 2,675.64 100.00% 2,675.646 M. O. acero col. amarre del muro 30.33 m 81.08 2,459.16 100.00% 2,459.167 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,912.07 11,266.76 101.57% 11,093.048 Horm. 1:2:4 en columnas de amarre de .25 x .20 m. Col. Cada: 3.00 1.28 m3 4,431.50 5,672.32 101.59% 5,583.679 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 35.70 4,734.18 101.74% 4,653.2810 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 30.43 807.00 101.70% 793.4811 Clavos de acero (¼ lb / metro). 6.42 lb 53.10 340.90 101.72% 335.1212 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 34.64 222.39 101.70% 218.6713 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 159.51 4,094.62 100.00% 4,094.6214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 20.94 215.05 100.00% 215.0515 Muro de bloques de 8" x 8" x 16" 65.27 m2 1,048.04 68,402.08 101.30% 67,524.24

3,740.71 M U $119,702.64 101.23% 118,242.40M2 Verja $1,700.32 101.23% 1,679.58

*VERBLO 10810004 VERJA DE BLOQUES 5", RETALLE, COL. AMARRE CADA 3.00 m., ROCA, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,062.36 101.22% 1,049.54

1 Excación de zapata 0.45 x 0.45 m., ROCA a mano 6.48 m3 1,772.87 11,488.20 100.00% 11,488.202 Regar material producto de excavación 10.370 m3 225.68 2,340.30 100.14% 2,337.093 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 2,114.09 5,327.51 101.72% 5,237.244 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 2,114.09 6,553.68 101.72% 6,442.645 M. O. acero zapata del muro 33.00 m 81.08 2,675.64 100.00% 2,675.646 M. O. acero col. amarre del muro 30.33 m 81.08 2,459.16 100.00% 2,459.167 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,912.07 11,266.76 101.57% 11,093.048 Horm. 1:2:4 en columnas de amarre de .175 x .20 m. Col. Cada: 3.00 0.92 m3 4,431.50 4,076.98 101.59% 4,013.269 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 35.70 4,734.18 101.74% 4,653.2810 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 30.43 807.00 101.70% 793.4811 Clavos de acero (¼ lb / metro). 6.42 lb 53.10 340.90 101.72% 335.1212 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 34.64 222.39 101.70% 218.6713 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 159.51 4,094.62 100.00% 4,094.6214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 20.94 215.05 100.00% 215.0515 Muro de bloques de 5" x 8" x 16" 65.27 m2 785.79 51,285.89 101.23% 50,662.60

3,371.51 M U $107,888.26 101.10% 106,719.09M2 Verja $1,532.50 101.10% 1,515.90

*VERBLO 10810005 VERJA DE BLOQUES 6", RETALLE, COL. AMARRE CADA 3.00 m., ROCA, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,134.90 101.24% 1,121.00

1 Excación de zapata 0.45 x 0.45 m., ROCA a mano 6.48 m3 1,772.87 11,488.20 100.00% 11,488.202 Regar material producto de excavación 10.370 m3 225.68 2,340.30 100.14% 2,337.093 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 2,114.09 5,327.51 101.72% 5,237.244 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 2,114.09 6,553.68 101.72% 6,442.645 M. O. acero zapata del muro 33.00 m 81.08 2,675.64 100.00% 2,675.646 M. O. acero col. amarre del muro 30.33 m 81.08 2,459.16 100.00% 2,459.167 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,912.07 11,266.76 101.57% 11,093.048 Horm. 1:2:4 en columnas de amarre de .20 x .20 m. Col. Cada: 3.00 1.03 m3 4,431.50 4,564.45 101.59% 4,493.119 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 35.70 4,734.18 101.74% 4,653.2810 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 30.43 807.00 101.70% 793.4811 Clavos de acero (¼ lb / metro). 6.42 lb 53.10 340.90 101.72% 335.1212 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 34.64 222.39 101.70% 218.6713 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 159.51 4,094.62 100.00% 4,094.6214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 20.94 215.05 100.00% 215.0515 Muro de bloques de 6" x 8" x 16" 65.27 m2 856.57 55,905.47 101.25% 55,212.99

3,531.10 M U $112,995.31 101.11% 111,749.33M2 Verja $1,605.05 101.12% 1,587.35

*VERBLO 10810006 VERJA DE BLOQUES 8", RETALLE, COL. AMARRE CADA 3.00 m., ROCA, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,150.64 101.25% 1,136.49

1 Excación de zapata 0.45 x 0.45 m., ROCA a mano 8.64 m3 1,772.87 15,317.60 100.00% 15,317.602 Regar material producto de excavación 13.820 m3 225.68 3,118.90 100.14% 3,114.613 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.840 qq 2,114.09 6,004.02 101.72% 5,902.294 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 2,114.09 6,553.68 101.72% 6,442.645 M. O. acero zapata del muro 33.00 m 81.08 2,675.64 100.00% 2,675.646 M. O. acero col. amarre del muro 30.33 m 81.08 2,459.16 100.00% 2,459.167 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,912.07 11,266.76 101.57% 11,093.048 Horm. 1:2:4 en columnas de amarre de .25 x .20 m. Col. Cada: 3.00 1.28 m3 4,431.50 5,672.32 101.59% 5,583.679 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 35.70 4,734.18 101.74% 4,653.2810 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 30.43 807.00 101.70% 793.4811 Clavos de acero (¼ lb / metro). 6.42 lb 53.10 340.90 101.72% 335.1212 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 34.64 222.39 101.70% 218.6713 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 159.51 4,094.62 100.00% 4,094.6214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 20.94 215.05 100.00% 215.0515 Muro de bloques de 8" x 8" x 16" 65.27 m2 856.57 55,905.47 101.25% 55,212.99

3,730.87 M U $119,387.69 101.08% 118,111.86M2 Verja $1,695.85 101.08% 1,677.73

*VERBLO 10810007 VERJA DE BLOQUES 5", RETALLE, COL. AMARRE CADA 3.00 m., TIERRA, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,062.36 101.22% 1,049.54

1 Excación de zapata 0.45 x 0.45 m., TIERRA a mano 6.48 m3 272.33 1,764.70 100.00% 1,764.702 Regar material producto de excavación 7.780 m3 225.68 1,755.79 100.14% 1,753.383 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 2,114.09 5,327.51 101.72% 5,237.244 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 2,114.09 6,553.68 101.72% 6,442.645 M. O. acero zapata del muro 33.00 m 81.08 2,675.64 100.00% 2,675.646 M. O. acero col. amarre del muro 30.33 m 81.08 2,459.16 100.00% 2,459.167 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,912.07 11,266.76 101.57% 11,093.048 Horm. 1:2:4 en columnas de amarre de .175 x .20 m. Col. Cada: 3.00 0.92 m3 4,431.50 4,076.98 101.59% 4,013.269 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 35.70 4,734.18 101.74% 4,653.2810 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 30.43 807.00 101.70% 793.4811 Clavos de acero (¼ lb / metro). 6.42 lb 53.10 340.90 101.72% 335.1212 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 34.64 222.39 101.70% 218.6713 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 159.51 4,094.62 100.00% 4,094.6214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 20.94 215.05 100.00% 215.05

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 98

Page 101: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. ANALISIS DE COSTOSREFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL INDICE JUL 2012

15 Muro de bloques de 5" x 8" x 16" 65.27 m2 785.79 51,285.89 101.23% 50,662.603,049.38 M U $97,580.25 101.21% 96,411.88

M2 Verja $1,386.08 101.21% 1,369.49*VERBLO 10810008 VERJA DE BLOQUES 6", RETALLE, COL. AMARRE CADA 3.00 m., TIERRA, Sin empañete:

Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,134.90 101.24% 1,121.001 Excación de zapata 0.45 x 0.45 m., TIERRA a mano 6.48 m3 272.33 1,764.70 100.00% 1,764.702 Regar material producto de excavación 7.780 m3 225.68 1,755.79 100.14% 1,753.383 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 2,114.09 5,327.51 101.72% 5,237.244 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 2,114.09 6,553.68 101.72% 6,442.645 M. O. acero zapata del muro 33.00 m 81.08 2,675.64 100.00% 2,675.646 M. O. acero col. amarre del muro 30.33 m 81.08 2,459.16 100.00% 2,459.167 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,912.07 11,266.76 101.57% 11,093.048 Horm. 1:2:4 en columnas de amarre de .20 x .20 m. Col. Cada: 3.00 1.03 m3 4,431.50 4,564.45 101.59% 4,493.119 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 35.70 4,734.18 101.74% 4,653.2810 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 30.43 807.00 101.70% 793.4811 Clavos de acero (¼ lb / metro). 6.42 lb 53.10 340.90 101.72% 335.1212 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 34.64 222.39 101.70% 218.6713 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 159.51 4,094.62 100.00% 4,094.6214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 20.94 215.05 100.00% 215.0515 Muro de bloques de 5" x 8" x 16" 65.27 m2 856.57 55,905.47 101.25% 55,212.99

3,208.98 M U $102,687.30 101.23% 101,442.12M2 Verja $1,458.63 101.23% 1,440.94

*VERBLO 10810009 VERJA DE BLOQUES 8", RETALLE, COL. AMARRE CADA 3.00 m., TIERRA, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,150.64 101.25% 1,136.49

1 Excación de zapata 0.60 x 0.40 x 32.20 m., tierra a mano 8.64 m3 272.33 2,352.93 100.00% 2,352.932 Regar material producto de excavación 10.370 m3 225.68 2,340.30 100.14% 2,337.093 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.840 qq 2,114.09 6,004.02 101.72% 5,902.294 Acero col. amarre: 3/8" en 4 varillas long. y cangrejos a 0.20 m. + 10% desp. 3.100 qq 2,114.09 6,553.68 101.72% 6,442.645 M. O. acero zapata del muro 33.00 m 81.08 2,675.64 100.00% 2,675.646 M. O. acero col. amarre del muro 30.33 m 81.08 2,459.16 100.00% 2,459.167 Horm. 1:3:5 en zapata de .60 x .25 x 32.20 m. 2.88 m3 3,912.07 11,266.76 101.57% 11,093.048 Horm. 1:2:4 en columnas de amarre de .25 x .20 m. Col. Cada: 3.00 1.28 m3 4,431.50 5,672.32 101.59% 5,583.679 Madera de pino americano, bruto, 4 usos + 25% desp. 132.61 pt 35.70 4,734.18 101.74% 4,653.2810 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 30.43 807.00 101.70% 793.4811 Clavos de acero (¼ lb / metro). 6.42 lb 53.10 340.90 101.72% 335.1212 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 34.64 222.39 101.70% 218.6713 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 159.51 4,094.62 100.00% 4,094.6214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 20.94 215.05 100.00% 215.0515 Muro de bloques de 8" x 8" x 16", 11 líneas 65.27 m2 856.57 55,905.47 101.25% 55,212.99

3,301.39 M U $105,644.42 101.22% 104,369.67M2 Verja $1,500.63 101.22% 1,482.52

End Printing pág. 95

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 99

Page 102: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.PAG.

HIPERVINCULO

INSUMOS (ORDENADOS ALFABETICAMENTE) (TODOS los precios con ITBIS incluido)INACE 50000 ACEROS Y ALAMBRE GALVANIZADO: 1INACE 60000 AGREGADOS, BOTES, CALICHE Y TIERRA NEGRA: 1INASC 70000 ASCENSORES: 1INBAL 80000 BALAUSTRES Y PASAMANOS: Precios estimados 1INBAÑ 90000 BAÑOS, FREGADEROS , CALENT. ELECT. Y ACCESORIOS: 1INBAR 100000 BARRO, PRODUCTOS: 3INBLC 110000 BLOQUES DE CEMENTO: (INDUSTRIAS AGUAYO 809 533-3161) 3INBLV 120000 BLOQUES DE CRISTAL: 4

INBOM 130000 BOMBAS DE AGUA Y TANQUES DE PRESION : 4INBOV 140000 BOVEDILLAS DE "FOAM": 4INCEM 150000 CEMENTOS, CAL, ADITIVOS, CURADORES, ENDURECEDORES, SELLADORES: 4INCER 160000 CERAMICAS: 4INCEJ 170000 CERRAJERIA: 5

INCOM 180000 COMBUSTIBLES Y LUBRICANTES: 5INDIV 190000 DIVISAS: 5INEBA 200000 EBANISTERIA: 5INELL 210000 ELECTRICIDAD (LAMPARAS Y GLOBOS): 5INELR 220000 ELECTRICIDAD RESIDENCIAL: 5INELA 230000 ELECTRICIDAD INDUSTRIAL: 7INESC 240000 ESCALONES Y MESETAS GRANITO: Israel Thomas 809 229-4442 7INEST 250000 ESTRUCTURA METALICA Y PUERTA ENROLLABLE: 8INHER 260000 HERRERIA: 8INHOR 270000 HORMIGONES INDUSTRIALES Y VACIADOS: (HORM. FERNANDEZ) 8INIMP 280000 IMPERMEABILIZANTES: 9INLAB 290000 LABORATORIO MECANICA DE SUELOS> 9INLAV 300000 LAVADEROS Y VERTEDEROS DE GRANITO: 9INLLA 310000 LLAVES DE PASO, VALVULAS, CHEQUES Y TAPAS CISTERNA: 9

INMAD 320000 MADERAS, CLAVOS, PLYWOOD, ZINC Y OTROS: 9INMAL 330000 MALLAS CICLONICAS Y ACCESORIOS: 10INMAT 340000 MATERIALES INSTALADOS: 10INMOT 350000 MOTORES ELECTRICOS PARA PORTONES 10

INPIE 360000 PIEDRAS EN LAJAS PARA PISOS: 10INPIN 370000 PINTURAS: 10INPIS 380000 PISOS Y ADOQUINES: 10

INPLA 390000 PLANTAS ELECTRICAS: 11INPOZ 400000 POZOS FILTRANTES: 11INPUE 410000 PUERTAS DE ALUMINIO: 11INPPV 420000 PUERTAS DE PVC: (Pendiente) 12INTIN 430000 TINACOS: 12

INCOB 440000 TUBERIAS Y PIEZAS COBRE: (Pendiente) 12INTCP 450000 TUBERIAS Y PIEZAS CPVC: 12INGAS 460000 TUBERIAS Y PIEZAS GAS: 12INTHG 470000 TUBERIAS Y PIEZAS H.G. (HIERRO GALVANIZADO): 12INPOL 480000 TUBERIAS Y PIEZAS POLIETILENO: (Pendiente) 13INPOP 490000 TUBERIAS Y PIEZAS POLIPROPILENO: (Pendiente) 13INTDR 500000 TUBERIAS Y PIEZAS PVC DRENAJE: 13INTPR 510000 TUBERIAS Y PIEZAS PVC PRESION: 14INVEN 520000 VENTANAS DE ALUMINIO Y MASILLAS EN TUBO: 15

HERRAMIENTAS DE TRABAJO: (Ordenado alfabéticamente)HERALB 700000 HERRAMIENTAS PARA ALBAÑILERIA: 16HERCAR 710000 HERRAMIENTAS PARA CARPINTERIA: 16HERELE 720000 HERRAMIENTAS PARA ELECTRICIDAD: 16

HERMED 730000 HERRAMIENTAS PARA MEDIR: 16HERPIN 740000 HERRAMIENTAS PARA PINTURA: 16HERPLO 750000 HERRAMIENTAS PARA PLOMERIA: 16HERSEG 760000 HERRAMIENTAS PARA SEGURIDAD: 17HERSUB 770000 HERRAMIENTAS PARA SUBIR: 17HERVAR 780000 HERRAMIENTAS PARA VARILLAS: 17

RENDIMIENTO DE MATERIALESRENDI 5020000 ACEROS Y ALAMBRES GALVANIZADOS: 18RENDI 5040000 BLOQUES: 19RENDI 5060000 CAL, CEMENTOS, ADITIVOS, CURADORES, ENDURECEDORES, SELLADORES: 19RENDI 5080000 CEMENTO PVC (NUMERO DE JUNTAS POR GL.): 19RENDI 5100000 CEMENTO PVC (NUMERO DE JUNTAS POR KILO): 19RENDI 5120000 CEMENTO PVC (NUMERO DE JUNTAS POR PINTA): 19RENDI 5140000 CLAVOS (CANTIDAD x LIBRA): 19RENDI 5160000 IMPERMEABILIZANTES: 20RENDI 5180000 MATERIALES INSTALADOS: 20RENDI 5200000 PINTURAS: 20

PARTIDA No. I N D I C E

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 100

Page 103: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.PAG.

HIPERVINCULOPARTIDA No. I N D I C E

RENDI 5220000 PISOS, ADOQUINES Y TABLETAS: 20RENDI 5240000 TEFLON: 20RENDI 5260000 TRANSPORTE BLOQUES / VIAJE 22RENDI 5280000 TRANSPORTE PIEZAS DE GRANITO / VIAJE 22

MANO DE OBRA CUADRILLAS DE TRABAJO (Agregar ITBIS en Subcontratos, si no lo incluye)*MOAL 6000000 M.O. ALBAÑILERIA 23*MOAL 6000100 M.O. ALB., ACCESORIOS DE BAÑOS, INST.: 23*MOAL 6000200 M.O. ALB., ACERA Y CONTENES: 23*MOAL 6000300 M.O. ALB., ADICIONAL P/PLANTA, COLOC.: 23*MOAL 6000400 M.O. ALB., BADENES Y COLECTORES: 23*MOAL 6000500 M.O. ALB., BLOQUES, COLOCACION 23*MOAL 6000600 M.O. ALB., DESAGÜES: 23*MOAL 6000700 M.O. ALB., EMPAÑETES, TERM. PAREDES Y TECHOS: 23*MOAL 6000800 M.O. ALB., ESCALONES: 24*MOAL 6000900 M.O. ALB., INST. VENTANAS: (ITBIS incluido por subcontrato) 24*MOAL 6001000 M.O. ALB., LABORES VARIAS: 24*MOAL 6001100 M.O. ALB., LADRILLOS: 24*MOAL 6001200 M.O. ALB., LAVADEROS Y VERT.: 24*MOAL 6001300 M.O. ALB., MALLA CICLONICA (ZAB., TUBOS, MALLA, PALOMETAS, ALAMBRE PUAS): 24*MOAL 6001400 M.O. ALB., MARMOL: 24*MOAL 6001500 M.O. ALB., PIEDRA: 24*MOAL 6001600 M.O. ALB., PISOS Y ZOCALOS: 24*MOAL 6001700 M.O. ALB., PULIMENTO Y BRILLADO PISOS: (ITBIS incluido por subcontrto) 25*MOAL 6001800 M.O. ALB., REGISTROS Y TRAMPA GRASA: 25*MOAL 6001900 M.O. ALB., REVESTIMIENTO PAREDES: 25*MOAL 6002000 M.O. ALB., SUBIR MATERIALES / PLANTA: 25*MOAL 6002100 M.O. ALB., TECHOS, TERMINACION: 26*MOAL 6002200 M.O. ALB., VACIADOS: 26*MOAL 6002300 M.O. ALB., YESO A TODO COSTO: 26*MOCA 6100000 M.O. CARPINTERIA: 26*MOCA 6100100 M.O. CARPINT., COL. CONICAS Y RED., CONF.: 26*MOCA 6100200 M.O. CARPINT., COL. CONICAS Y RED., INST.: 26*MOCA 6100300 M.O. CARPINT., COL. CUADRADAS O RECTANG., CONF.: 26*MOCA 6100400 M.O. CARPINT., COL. CUADRADAS O RECTANG., INST.: 27*MOCA 6100500 M.O. CARPINT., COL., TAPAS, CONF. E INST.: 27*MOCA 6100600 M.O. CARPINT., DESENCOFRADOS (AREA CONTACTO FORRO-CONCRETO): 27*MOCA 6100700 M.O. CARPINT., ESTRUCT. VARIAS, INST. (HASTA 4 M. ALTURA): 27*MOCA 6100800 M.O. CARPINT., FALSO PISO, HECHURA: 27*MOCA 6100900 M.O. CARPINT., MUROS, CONF. E INST. MOLDE: 27*MOCA 6101000 M.O. CARPINT., OTROS, CONF. E INST. MOLDE: 27*MOCA 6101100 M.O. CARPINT., TODO COSTO: (ITBIS incluido por subcontrto) 27*MOCA 6101200 M.O. CARPINT., TRABAJOS DE TERMINACION: 28*MOCA 6101300 M.O. CARPINT., VIGAS Y DINTELES, CONF. E INST. MOLDE: 28*MODE 6200000 M.O. DEMOLICIONES: 28*MOEB 6300000 M.O. EBANISTERIA: 28*MOEL 6400000 M.O. ELECTRICIDAD: 28*MOEL 6400100 M.O. ELECTRICIDAD, CONEXIÓN APARATOS: 28*MOEL 6400200 M.O. ELECTRICIDAD, INTERRUPTOR DE SEGURIDAD: 28*MOEL 6400300 M.O. ELECTRICIDAD, SALIDAS DE TIMBRES, TELEF. Y CABLE: 28*MOEL 6400400 M.O. ELECTRICIDAD, RESIDENCIAS ECONOMICAS EN SERIE : 28*MOEL 6400500 M.O. ELECTRICIDAD, SALIDAS EN TUB. EXTERIOR VISIBLE: 29*MOEL 6400600 M.O. ELECTRICIDAD, SALIDAS EN TUB. OCULTA: 29*MOEL 6400700 M.O. ELECTRICIDAD, SALIDAS TIPO ECONOMICO EN TUB.: 29*MOEL 6400800 M.O. ELECTRICIDAD, SALIDAS WATERPROOF Y EXPLOTIONPROOF: 29*MOEX 6500000 M.O. EXCAVACIONES Y CORTES CON EQUIPO: 29*MOPI 6600000 M.O. PINTURA: 29*MOPL 6700000 M.O. PLOMERIA: 29*MOPL 6700100 M.O. PLOMERIA, ACOMETIDA URBANA, INCLUYE LLAVE CHORO: 30*MOPL 6700100 M.O. PLOMERIA, ARRASTRE DOMIC. Y PLUVIAL: 30*MOPL 6700200 M.O. PLOMERIA, AUMENTO POR PLANTA EN EDIFICIOS: 30*MOPL 6700300 M.O. PLOMERIA, BAJANTE O VENTILACION / PLANTA: 30*MOPL 6700400 M.O. PLOMERIA, BOMBA DE AGUA, INST. CIRCUITO COMPLETO: 30*MOPL 6700500 M.O. PLOMERIA, BOMBA DE AGUA, SIN EL CIRCUITO: 30*MOPL 6700600 M.O. PLOMERIA, CALENTADOR DE AGUA EXCLUSIV.: 30*MOPL 6700700 M.O. PLOMERIA, COL. ABASTECER AGUA, COBRE, POR PLANTA: 30*MOPL 6700800 M.O. PLOMERIA, COL. ABASTECER AGUA, H.G., POR PLANTA: 30*MOPL 6700900 M.O. PLOMERIA, COL. DESAGÜE PLUVIAL, POR PLANTA: 30*MOPL 6701000 M.O. PLOMERIA, CONEXION AL SEPTICO Y FILTRANTE: 30*MOPL 6701100 M.O. PLOMERIA, DESAGÜE APARATOS, POR SALIDA: 30*MOPL 6701200 M.O. PLOMERIA, DESMONTAR APARATOS: 30*MOPL 6701300 M.O. PLOMERIA, EMPALME A TUB. AGUA EXIST.: 30

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 101

Page 104: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.PAG.

HIPERVINCULOPARTIDA No. I N D I C E

*MOPL 6701400 M.O. PLOMERIA, EMPALME A TUB. ARRASTRE EXIST.: 30*MOPL 6701500 M.O. PLOMERIA, INST. CAJA DE VALVULA: 30*MOPL 6701600 M.O. PLOMERIA, INST. HIDRANTE: 30*MOPL 6701700 M.O. PLOMERIA, INST. LAVADORA: 30*MOPL 6701800 M.O. PLOMERIA, INST. LLAVE PASO Y CHORRO: 31*MOPL 6701900 M.O. PLOMERIA, INST. MANGA O NIPLE: 31*MOPL 6702000 M.O. PLOMERIA, INST. MEDIDOR DE AGUA: 31*MOPL 6702100 M.O. PLOMERIA, INST. NEVERA, BEBEDERO Y FILTRO: 31*MOPL 6702200 M.O. PLOMERIA, INST. PIEZA ESP., CAMPANA, POR DIAM., C/BOCA: 31*MOPL 6702300 M.O. PLOMERIA, INST. PIEZA ESP., GIBAULT, POR DIAM., C/BOCA: 31*MOPL 6702400 M.O. PLOMERIA, INST. PIEZA ESP., PVC, POR DIAM., C/BOCA: 31*MOPL 6702500 M.O. PLOMERIA, INST. PIEZA ESP., ROSCA, POR DIAM., C/BOCA: 31*MOPL 6702600 M.O. PLOMERIA, INST. TINACO DE AGUA: 31*MOPL 6702700 M.O. PLOMERIA, INST. TRAMPA GRASA Y CAMARA INSP.: 31*MOPL 6702800 M.O. PLOMERIA, INST. VALVULA DE AIRE: 31*MOPL 6702900 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, CAMPANA: 31*MOPL 6703000 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, PLATILLO: 32*MOPL 6703100 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, ROSCA: 32*MOPL 6703200 M.O. PLOMERIA, MONTAR BAÑERA Y DUCHA: 32*MOPL 6703300 M.O. PLOMERIA, MONTAR FREGADERO Y LAVAPLATO: 32*MOPL 6703400 M.O. PLOMERIA, MONTAR INODORO: 32*MOPL 6703500 M.O. PLOMERIA, MONTAR LAVAMANOS Y BIDET: 32*MOPL 6703600 M.O. PLOMERIA, MONTAR ORINAL: 32*MOPL 6703700 M.O. PLOMERIA, SALIDAS DE AGUA, APARATO SANIT., COBRE: 32*MOPL 6703800 M.O. PLOMERIA, SALIDAS DE AGUA, APARATO SANIT., H. G. o PVC: 32*MOPL 6703900 M.O. PLOMERIA, TERM. LAVADERO Y VERTEDERO: 32*MOPL 6704000 M.O. PLOMERIA, TUB. ALCANTARILLADO SANIT. Y PLUVIAL PROF. HASTA 3.00 M.: 33*MOPL 6704100 M.O. PLOMERIA, TUB. ALCANTARILLADO SANIT. Y PLUVIAL PROF. MAYOR DE 3.00 M.: 33*MOPL 6704200 M.O. PLOMERIA, TUB. ASBESTO CEMENTO: 33*MOPL 6704300 M.O. PLOMERIA, TUB. HIERRO FUNDIDO O ACERO: 33*MOPL 6704400 M.O. PLOMERIA, TUB. HIERRO GALV.: 33*MOPL 6704500 M.O. PLOMERIA, TUB. PVC: 33

*MOVA 6800000 M.O. VARILLEROS: 33*MOVO 6900000 M.O. VARIOS: 33

MANO DE OBRA JORNALES DIARIO (Sin ITBIS)*MOJO 6940000 MANO DE OBRA JORNALES DIARIOS: 35

ANALISIS DE COSTOS (Con ITBIS incluido)*ACE 10010000 A C E R O S 35*BLO 10030000 BLOQUES, MUROS DE 35*BOR 10050000 BORDILLOS DE BLOQUES DE HORM. 37*CAS 10070000 CASETAS DE MATERIALES 37*CON 10090000 CONTEN (TELFORD) 38*DES 10110000 DESAGÜES PLUVIALES 38*EMP 10130000 EMPAÑETES 38*ESC 10150000 ESCALONES 39

*HAANT 10170000 HORM. ARMADO ANTEPECHOS 39*HABAD 10190000 HORM. ARMADO BADENES (TIPO CUNETA) 40*HACOL 10210000 HORM. ARMADO COLUMNAS 41

*HACOLC 10230000 HORM. ARMADO COL. CIRCULARES 48*HACOLA 10250000 HORM. ARMADO COL. DE AMARRE 48

*HADIN 10270000 HORM. ARMADO DINTELES 49*HALOSM 10290000 HORM. ARMADO LOSAS MONOLITICAS 51*HAMUR 10310000 HORM. ARMADO MUROS 52*HARAM 10330000 HORM. ARMADO RAMPAS DE ESCALERAS 55

*HAV 10350000 HORM. ARMADO VIGAS 56*HAVA 10370000 HORM. ARMADO VIGAS AMARRE 61

*HAVUE 10390000 HORM. ARMADO VUELOS (NO CONTINUA DEL FALSO PISO) 62*HAZAPC1 10410000 HORM. ARMADO ZAP. COLUMNAS (1 CAMADA ACERO) 63*HAZAPC2 10430000 HORM. ARMADO ZAP. COLUMNAS (2 CAMADAS ACERO) 66*HAZAPM1 10450000 HORMIGON ARMADO ZAPATAS DE MUROS (1 CAMADA ACERO) 67

*HORIND 10470000 HORMIGONES INDUSTRIALES 68*HORSIM 10490000 HORMIGONES SIMPLES 69

*IMP 10510000 IMPERMEABILIZANTES 70*IEACO 10530000 INSTALACION ELECTRICA: ACOMETIDAS 70*IESAL 10550000 INSTALACION ELECTRICA: SALIDAS Y PANELES 72

*ISASHG 10570000 INST. SANITARIA: APARATOS SANIT., TUB. HG Y M. DE OBRA 74*ISCIS 10590000 INST. SANITARIA: CAMARAS INSP., CISTERNAS, SEPTICOS Y TRAMPAS DE GRASA 81

*ISCISSD 10610000 INST. SANITARIA: CISTERNAS Y SEPTICOS SEGÚN DISEÑO: 83*ISCAMO 10630000 INST. SANITARIA: COLOC. APARATOS SIN ITBIS (SOLO M. O.) 84*MALCIC 10650000 MALLAS CICLONICAS 85

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 102

Page 105: 2013 01ene 03 Txt 11va Edic, Cuadrillas (2)

01 ENE. 2013 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.PAG.

HIPERVINCULOPARTIDA No. I N D I C E

*MOR 10670000 M O R T E R O S 85*MOVTIE 10690000 MOVIMIENTO DE TIERRAS 86

*PIN 10710000 PINTURAS 87*PIS 10730000 PISOS 87

*PORMAD 10750000 PORTAJE DE MADERA 92*REP 10710000 REPLANTEO SEGUN DISEÑO 92*REV 10730000 REVESTIMIENTO EN PAREDES 92*TEC 10750000 TECHOS DE MADERA CON FORRO DE MADERA 94

*TERTEC 10770000 TECHOS (TERMINACION) 96*VEN 10790000 VENTANAS DE ALUMINIO 97

*VERBLO 10810000 VERJAS DE BLOQUES DE HORMIGON 97

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 103