CONTRACT MANAGEMENT BY A POACHER TURNED GAMEKEEPER STEPHEN TENNANT, Director Plus Three Consultants (HK) Ltd CONTRACTS, DISPUTES, ETHICS AND ARCHITECTS

20150818 L&O

Embed Size (px)

Citation preview

Page 1: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

BY  A  POACHER  TURNED  GAMEKEEPER

STEPHEN  TENNANT,  Director  -­ Plus  Three  Consultants  (HK)  Ltd

CONTRACTS,  DISPUTES,ETHICS  AND ARCHITECTS

Page 2: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

Today’s Discussion

• Contracts– Who needs them?

• Disputes– Origins and effect of Change.

• Ethics and Architects– Duties and Liabilities.

• Crystal Ball Gazing

Page 3: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

Why do we need Contracts?• To provide a

description of responsibilities.

• Bind parties to their duties.

• Establish a time frame for duties.

• To secure payment.• To provide recourse

when the relationship falters.

• Best to be in writing, but oral contract can be valid!

Page 4: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

Where do Disputes come from?

Change!!!

Page 5: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

Change?• Revised/New

Drawings.• Revised/New

Specifications.• Revised/New

Timings.• Revised/New

Requirements.

• Changed Law/ Regulations.

• Changed Weather.• Changed Economy.• Changed Labour

Situation.• Changed

Expectations.

Page 6: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

How does the Contract Address Change?

• Does the Change fall within the scope of the Variation Clauses?

• Does the Change fall within the scope of the Claims Clauses?

Page 7: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

What are the Architect’s primary duties?

• Design the Project, or approve the Design for the Project.

• Administer the Contract.

Page 8: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

How does the Architect undertake his duties?

Rule 3.2A member shall inform his client in advance of the Conditions in the HKIA Agreement and shall agree with his client that those Conditions shall be the basis of his appointment.

Page 9: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

How does the Architect undertake his duties?

Rule 1.3A Member shall act impartially in all cases in which he is acting between parties, and shall interpret the conditions of a building contract with fairness.

Page 10: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

Impartiality and the Architect• How do you tell the

client you got it wrong?

• Should I give the client a draft of my award for approvalcomment?

• Its OK to do what the client says, isn’t it?

Reality Check• Who pays the

Architect’s Fees?• Who gives the

Architect more work?

• Who is in charge of the Design?

Page 11: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

Fairness and the Architect• Architect not a party

to Contract (privity of contract!).

• Architect cannot change or ignore terms of Contract.

• Who is the Architect liable to?

Reality Check• Are Contracts fair?• Should the Contract

be fair?• Apply a fair

Contract unfairly?• Apply an unfair

Contract fairly?

Page 12: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

Who is the Architect Liable to?Third Parties

• Liability in Tort (duty of care).

• If acts or omissions cause loss and damage to “other” person or “other” property.

• Subsequent purchasers?

His Client• Express terms under

Contract.• Implied terms under

law.– e.g. reasonable skill

and care– Higher standard if

employed by Contractor under D&C Contract

Page 13: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

Architect Liable to Contractor?

• No privity of contract.• Act /omission of Architect can

adversely affect Contractor directly.• It WAS the law that an Architect does

not owe duty of care (liability under tort) to Contractor in issuing certificates.

Page 14: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

Architect Liable to Contractor?

• In 21st Century, law continues to develop, and change!

• Some Courts now considering liability of Architect to Contractor as certifier.

• Architect has been found, in some cases, as certifier, to owe duty of care to Contractor.

• Developing area of law!

Page 15: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

Liability from BIM?

• Multiple parties inputting into model.• Who owns the model?• Are you jointly and severally liable

(Only 20% to blame but 100% liable!)?• Absence of case law, at the moment!• Does your PI Insurance respond?

Page 16: 20150818 L&O

PLANNINGPROJECT  CONTROL

FINAL  ACCOUNTCONTRACT  CLAIM

ARBITRATIONEXPERT  WITNESS

www.plus3.com.my

COMMERCIALCONTRACT  MANAGEMENT

www.plus3.com.my

Architects and the Future?

• More complex projects.• Increased liabilities for Architects.• You look after your client.

But who looks after You?

Page 17: 20150818 L&O

n Preliminary  Claim  Evaluation  Reportn Technical  Issue  Analysis

n Schedule  and  Delay  Analysisn Loss  of  Productivity,  Acceleration  and  Out  Of  Sequence  Work  Analysis

n Damages  Quantification

n Defective  Plans  and  Specifications  Analysisn Claims  Avoidance

n Quantum  &  Delay  Expert  Reportsn Change  Order/Claims  Evaluation,  Preparation  and  Negotiation  

n Mediationn Documents  Discoveryn Litigation  Support

n Exhibits  Preparationn Expert  Witness  Testimonyn Project  Management  and  Contract  Managementwww.plus3.com.my

PLUS    THREE    CONSULTANTSContractual  &  Commercial  Services  For  Construction,  Infrastructure and  Oil  &  Gas

Thank  You