5/28/2018 3 VILLAS BOQ- (323-459)
1/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL OF QUANTITIES
5/28/2018 3 VILLAS BOQ- (323-459)
2/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL #1
GENERAL REQUIREMENTS
5/28/2018 3 VILLAS BOQ- (323-459)
3/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 2
SITE WORKS
5/28/2018 3 VILLAS BOQ- (323-459)
4/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 3
SUB-STRUCTURE
5/28/2018 3 VILLAS BOQ- (323-459)
5/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
SUPER STRUCTURE
BILL # 4
5/28/2018 3 VILLAS BOQ- (323-459)
6/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 5
THERMAL & MOISTURE PROTECTION
5/28/2018 3 VILLAS BOQ- (323-459)
7/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 6
METAL WORKS
5/28/2018 3 VILLAS BOQ- (323-459)
8/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 7
WOODEN & JOINERY WORKS
5/28/2018 3 VILLAS BOQ- (323-459)
9/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 8
FINISHES
5/28/2018 3 VILLAS BOQ- (323-459)
10/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 9
WATER SUPPLY WORKS
5/28/2018 3 VILLAS BOQ- (323-459)
11/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
DRAINAGE WORKS
BILL # 10
5/28/2018 3 VILLAS BOQ- (323-459)
12/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 11
HVAC WORKS
5/28/2018 3 VILLAS BOQ- (323-459)
13/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 12
LPG WORKS
5/28/2018 3 VILLAS BOQ- (323-459)
14/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 13
ELECTRICAL WORKS
5/28/2018 3 VILLAS BOQ- (323-459)
15/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 14
EXTERNAL WORKS WITHIN PLOT LIMIT
5/28/2018 3 VILLAS BOQ- (323-459)
16/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
BILL # 15
PROVISIONAL SUMS
5/28/2018 3 VILLAS BOQ- (323-459)
17/103
EMSQUARE 3 No. B + G + 1 Vill
on Plot No. 323-45
GRAND SUMMARY
5/28/2018 3 VILLAS BOQ- (323-459)
18/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
GENERAL REQUIREMENTS
General
These General Requirements are applicable to the
whole of the works. If the Tenderer wishes to price of
the items contained herein then each such item, clause
or sub-clause must be individually priced. The
Tenderer shall not enter any lump-sums covering more
than one or all items, clauses or sub-clauses. Where
any item, clause or sub-clause of the Preliminaries has
not been priced, it will be deemed that the value of such
item, clause or sub-clause is included in the rates for
measured items elsewhere in the Bills of Quantities.
Form of Tender
A The Contractor shall describe and list below and price 1.00 Item Included
herein any obligation contained in the Form of Tender
and Appendices for which he has not allowed
elsewhere and wishes to price separately
Form of Agreement
B The Contractor shall describe and list below and price 1.00 Item Included
herein any obligation contained in the Form of
Agreement and Appendices for which he has not
allowed elsewhere and wishes to price separately
Conditions of Contract
C The Contractor shall describe and list below and price 1.00 Item Included
herein any obligation contained in the Conditions of
Contract (Part I & II) for which he has not allowed
elsewhere and wishes to price separately
Specifications
D The Contractor shall describe and list below and price 1.00 Item Included
herein any obligation contained in the Specifications
for which he has not allowed elsewhere and wishes to
price separately
Total Carried To Collection -
Bill No. 1 GENERAL REQUIREMENTS
1/18
5/28/2018 3 VILLAS BOQ- (323-459)
19/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 1 GENERAL REQUIREMENTS
GENERAL REQUIREMENTS (Cont'd.)
Preambles
A The Contractor shall describe and list below and price 1.00 Item Included
herein any obligation contained in the Preambles for
which he has not allowed elsewhere and wishes to
price separately
Bill of Quantities
B The Contractor shall describe and list below and price 1.00 Item Included
herein any obligation contained in the Bill of Quantities
for which he has not allowed elsewhere and wishes to
price separately
Provisional Sums
C The Contractor shall be deemed to have allowed here 1.00 Item Included
for any other special preliminaries requirements not
specifically stated in relation to all works listed under
Provisional Sum section of the Contract
Performance Bond
D The Contractor should allow for the provision of the Not Applicable
performance bond in accordance with the
requirements of the Contract
Insurances
E The Contractor should allow for the provision of the 1.00 Item 5,000.00
insurances in accordance with the requirements of the
Contract
Total Carried To Collection 5,000.00
1/19
5/28/2018 3 VILLAS BOQ- (323-459)
20/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 1 GENERAL REQUIREMENTS
GENERAL REQUIREMENTS (Cont'd.)
Construction Plant and Tools
A The Contractor shall provide all constructional plant, 1.00 Item 134,500.00
lifting equipment, transport facilities, tools and
services required for the proper execution of the Works.
The facilities shall include the provision of protective
clothing and safety equipment complete. The
Contractor shall be responsible for delivery to the site
of all constructional plant, which he needs to carry out
the Works. This responsibility shall include shipment,
customs clearance, off-loading, loading and handling
and all transportation to site and the removal of all
redundant plant on completion of the Works.
Building Permits and Statutory Approvals
B The Contractor shall be responsible for obtaining all 1.00 Item Included
approvals necessary for the Government Departments,
the Police, Local Service Authorities (ie. Dubai
Electricity and Water Authority. Etisalat / EITC, Civil
Defence, etc) as required in the performance of this
Contract, and for coordinating approvals and the like
with requirements of the master plan developer and
his representatives necessary for the works to proceed.
Site Boundary Demarcation Certificate
C The Contractor shall be responsible for obtaining the 1.00 Item Included
Site Boundary Demarcation Certificate form the
relevant Section of JAFZA, agree the location of the Site
Boundary markers with the Survey Section and to
carry out permanent demarcations. The Contractor
shall provide the Engineer with a copy of the certificate.
The Contractor shall be responsible for liaising with
JAFZA.
Total Carried To Collection 134,500.00
1/20
5/28/2018 3 VILLAS BOQ- (323-459)
21/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 1 GENERAL REQUIREMENTS
GENERAL REQUIREMENTS (Cont'd.)
Programme and Progress of Works
A In accordance with clause 14 of the Conditions of 1.00 Item Included
Contract the Contractor shall prepare a comprehensive
construction programme setting out the schedule for
completion of the works including that of all
sub-contractors and identifying all critical activities
and milestone dates and interrelationships of various
elements of works.
Quality Control Procedure
B As Built Drawings & Operation and Maintenance 1.00 Item Included
instruction manual
Allow for providing copy of each as-built drawing in
the form and numbers instructed time to time by the
Engineer
Quality Control Programme
C Provide and maintain an effective quality control 1.00 Item Included
programme for all items of work including those of
sub- contractors to ensure compliance with contract
document
Temporary Works
D The Contractor is responsible for the design, 1.00 Item Included
construction, maintenance and removal of all
temporary works. The Contractor to submit to the
Engineer his proposals for all temporary works for
approval. The Engineer's approval will no way relieve
the Contractor of his responsibility for the safety of the
Works, operatives, adjoining property, structure or
services and compliance with specifications,
appropriate regulations and Codes of Practice.
Total Carried To Collection
1/21
5/28/2018 3 VILLAS BOQ- (323-459)
22/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 1 GENERAL REQUIREMENTS
GENERAL REQUIREMENTS (Cont'd.)
Temporary Utilities
A The Contractor shall provide proper and adequate 1.00 Item Included
temporary utilities for his own use and for the use of
his own subcontractors
Existing Services
B The Contractor is to take particular care to avoid 1.00 Item Included
damage to existing service during the course of the
work. The Contractor shall be responsible for the
protection of all existing services within the site and
shall make good any damage to existing services
resulting from his carrying out of the works to the
satisfaction of the Engineer and relevant authority.
Electrical Power and Lighting
C The Contractor shall arrange and provide adequate 1.00 Item 91,500.00
temporary supply of all necessary electrical power and
lighting for the Works including paying all charges for
consumption of electricity or supplying, operating and
maintaining generators at his own expense including
final testing and commissioning and until final
handing over for the Works.
Water
D The Contractor shall arrange for a temporary supply of 1.00 Item Included
water for the Works, suitable for all purpose through
out the duration of the project and including final
testing and commissioning and until final handing
over. Furthermore, the Contractor shall pay all charges
for the consumption of water used. Portable water for
the project will be arranged by the contractor for the
entire duration of the project
Total Carried To Collection 91,500.00
1/22
5/28/2018 3 VILLAS BOQ- (323-459)
23/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 1 GENERAL REQUIREMENTS
GENERAL REQUIREMENTS (Cont'd.)
Temporary Telephones & Internet
A The Contractor is to provide and maintain temporary 1.00 Item 8,000.00
telephone system & internet facility for his own, the
Engineer's and Employer's use. He is to allow in his
Tender for the costs of installation, hire and removal
and for all call charges
Temporary Drainage
B The Contractor is to allow for keeping the site dry at all 1.00 Item Included
times. The Contractor shall provide and maintain
temporary drainage installation as may be necessary
during the period of construction in a manner
approved by the Engineer and in accordance with the
local authorities regulation and direction. At
completion of work Engineer may direct to remove all
temporary drainage installation and make good
existing to Engineer's satisfaction
Fire Hazards
C The Contractor shall be responsible for ensuring that 1.00 Item Included
proper precautions are taken to protect the temporary
buildings and it's contents where naked flame is used.
He shall ensure that the extinguishers are available in
areas where such hazards exist.
Temporary Fire Fighting Services and Precautions
D Provide and maintain efficient fire fighting facilities 1.00 Item Included
and equipment together with personnel trained in its
use as detailed in the specification
Living Quarters / Accommodation
E No temporary living, accommodation will be 1.00 Item 18,000.00
permitted on the site. It is the Contractor'sresponsibility to make any necessary arrangements for
suitable temporary housing of workers.
Total Carried To Collection 26,000.00
1/23
5/28/2018 3 VILLAS BOQ- (323-459)
24/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 1 GENERAL REQUIREMENTS
GENERAL REQUIREMENTS (Cont'd.)
Facilities for the Contractor
A The Contractor shall provide temporary sheds, offices, 1.00 Item Included
mess rooms, sanitary accommodation, welfare
facilities, and like for the use of his agent and site staff
and such office shall be open at all reasonable hours to
receive instructions, notices or other communications
and clear away on completion of the Contract
Facilities for the Engineer & Employer
B The Contractor shall provide and maintain proper 1.00 Item Included
office facilities on site for the sole use of the Employer,
Engineer and their staff complete with furniture and
equipment in accordance with the specification, all as
instructed by the Engineer.
C The construction of this office must be sound/water/ 1.00 Item Included
fireproof and well insulated and the office is to be air
conditioned, carpeted furnished and equipped all to the
satisfaction of the Engineer. The office shall be in a good
state of repair and in any case not more than two years
old As soon as the Contractor has been given
instructions to proceed with the Works, he shall
immediately present to the Engineer location and
layout plan of the office facilities for the approval and
arrange for completion within one week of the
Engineer's approval. The Contractor shall provide all
stationary Items
Temporary Latrines and Ablutions
D The Contractor is to provide and install native pattern 1.00 Item Included
fly proof latrines and urine pans for his employees
adjacent to the work, of a type which shall be approved
by the Local Medical Authorities and Engineer, and
shall be responsible for properly screening and
maintaining the site in a clean and sanitary conditionto the satisfaction of the Engineer through out the
period of the Contract.
Total Carried To Collection
1/24
5/28/2018 3 VILLAS BOQ- (323-459)
25/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 1 GENERAL REQUIREMENTS
GENERAL REQUIREMENTS (Cont'd.)
Temporary Hoardings
A The Contractor shall provide temporary fencing, gates, 1.00 Item 10,000.00
hoardings, fans, flanked footways, guard rails, gantries
and the like as may be necessary for protecting the
public or occupants for the proper execution of the
works
Site Sign Boards
B The Contractor to provide and maintain 1 number site 1.00 Item 2,000.00
sign boards in steel posts painted and fixed in concrete
foundation and with lighting all as per drawing &
approval of Engineer
Security & Safety
C The Contractor shall be responsible for providing 1.00 Item 44,000.00
suitable lights, watchmen's hut, watchmen, etc., for the
protection of the materials and plant etc., as described
in the Specification
Protection
D Adequate protection against any form of damage or 1.00 Item 3,000.00
deterioration shall be provided for all sections of the
Works. This shall include protective tapes, casings,
guard rails and the like, which shall be provided if
necessary.
Safety, Health and Welfare of Workmen.
E The Contractor shall comply with enactments and 1.00 Item Included
regulations relating to safety, health and welfare of
workmen and the public at large. The Contractor shall
provide and maintain first aid facilities on the site to
the approval of the Engineer
Total Carried To Collection 59,000.00
1/25
5/28/2018 3 VILLAS BOQ- (323-459)
26/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 1 GENERAL REQUIREMENTS
GENERAL REQUIREMENTS (Cont'd.)
Supervision and Co-ordination of other works
A The Contractor shall provide all necessary 1.00 Item 221,000.00
superintendence during the execution of works and as
long thereafter as Engineer may instruct as per
specification.
Clearing away Rubbish
B Allow for clearing away rubbish at regular intervals 1.00 Item 25,000.00
during the progress of the work and at the completion
and for leaving the site and perimeter tidy at
completion, to the satisfaction of the Engineer.
Survey Equipment & Setting Out of works
C The contractor shall be responsible for any 1.00 Item Included
investigation and checking the accuracy of the existing
ground and recording. The Contractor shall provide an
adequate supply of surveying instruments for the
proper execution of the works. The site setting out to be
satisfaction of the Engineer
Traffic Regulations / Temporary traffic arrangement
D The Contractor is to observe all traffic regulations, 1.00 Item Included
including those regarding the loading or unloading of
or waiting by vehicles on the public highway and the
Contract Sum is deemed to include for strict
compliance therewith. All access roads are to be
maintained clean at all times.
Tests & Samples
E The Contractor to allow for all tests required by the 1.00 Item 5,000.00
Specification to be carried out including providing all
necessary materials and samples. Duplicate final
approved samples are to be provided for the Engineer,one for office use and one for site. Each sample to be
properly labelled with the following details name,
manufacturer's name, date of submission &
specification reference
Total Carried To Collection 251,000.00
1/26
5/28/2018 3 VILLAS BOQ- (323-459)
27/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 1 GENERAL REQUIREMENTS
GENERAL REQUIREMENTS (Cont'd.)
Progress Photographs / monthly reports
A The Contractor shall provide the Engineer each month 1.00 Item 7,000.00
with thirty coloured photographs showing work in
progress on the site from viewpoints selected by the
Engineer. In addition one set in digital format and two
copies of each progress photograph in post card size
shall be provided with a description of the viewpoint
and the sate of taking written or stamped in ink on the
back. A copy of all the above photographs together
with the negatives shall be forwarded to the Employer
at the same time.
Total Carried To Collection 7,000.00
1/27
5/28/2018 3 VILLAS BOQ- (323-459)
28/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 1 GENERAL REQUIREMENTS
GENERAL REQUIREMENTS (Cont'd.)
Collection
From Page 1/1 -
From Page 1/2 5,000.00
From Page 1/3 134,500.00
From Page 1/4 -
From Page 1/5 91,500.00
From Page 1/6 26,000.00
From Page 1/7 -
From Page 1/8 59,000.00
From Page 1/9 251,000.00
From Page 1/10 7,000.00
Total Bill No.1- Carried To General Summary 574,000.00
1/28
5/28/2018 3 VILLAS BOQ- (323-459)
29/103
EMSQUARE 3 No. B+G+1 VILLA
CONTRACT BOQ PLOT NO. 323-45
Item
No.Description Qty Unit Rate Amount / Dhs
SITE WORKS
(Including Servant Block & Guard Room)
A Site Cleaning including removal of vegetation,
shrubs, bushes and surface excavation 1 LS 8,316.0
EARTHWORK SUPPORT
B Allow for earthwork earthwork support for
excavation classified shoring design &
construction to the satisfaction and approval of
engineer. ( if any) EXCLUDED
DE-WATERING
C Design, supply & install and maintain dewatering
system complete as per the approval and to the
satisfaction of the engineer (if any) EXCLUDED
EXCAVATION & EARTHWORKS
Excavation in any type of a classified soil or hard
strata as per the site levels and depth
recommended on drawings and specification.
D Mass Excavation up to required depth 3497 m3 22.00 76,934.0
E Extra over excavation of additional thickening along
retaining wall & footing 109 m3 22.00 2,398.0
F Excavation for Ground floor footing 320 m3 22.00 7,040.0
G Excavation for tie beam 25 m3 22.00 550.0
DISPOSAL
H Disposal of unsuitable excavated and other
material from site as per engineers instruction 1 LS Include
Total Carried To Collection 95,238.0
Bill No. 2 SITE WORKS
2/29
5/28/2018 3 VILLAS BOQ- (323-459)
30/103
EMSQUARE 3 No. B+G+1 VILLA
CONTRACT BOQ PLOT NO. 323-45
Item
No.Description Qty Unit Rate Amount / Dhs
Bill No. 2 SITE WORKS
SITE WORKS (cont'd)
ANTI TERMITE TREATMENT
A Anti termite horizontally and vertically for
foundations floors, joints and all structures
which is in contact with soil shall be applied
as per specification. 1 LS 5,895.0
COMPACTION & BACKFILLING (IMPORTED MATERIAL)
B Initial compaction of sub stratum to achieve
minimum 95% of MDD maximum dry density at
optimum moisture content, and back filling inlayers not more than 250mm thick with watering
and compaction to attain a minimum 98% of the
MDD at OMC , backfilling material should be
imported back fill of approved quality and
specification. (Subkha) 270 m3 70.00 18,900.0
Total Carried To Collection 24,795.0
2/30
5/28/2018 3 VILLAS BOQ- (323-459)
31/103
EMSQUARE 3 No. B+G+1 VILLA
CONTRACT BOQ PLOT NO. 323-45
Item
No.Description Qty Unit Rate Amount / Dhs
Bill No. 2 SITE WORKS
SITE WORKS (cont'd)
ADDITIONAL ITEMS
The tenderer is to detail below any additional
items with quantities and rates not previously
included to complete the build up of lumpsum
tender price for this section of the works. Should
the tenderer fail to insert any items here, it will
be deemed that his lumpsum price for the tender
includes all items and no subsequent claim for
any additional item will be entertained.
Total Carried To Collection -
2/31
5/28/2018 3 VILLAS BOQ- (323-459)
32/103
EMSQUARE 3 No. B+G+1 VILLA
CONTRACT BOQ PLOT NO. 323-45
Item
No.Description Qty Unit Rate Amount / Dhs
Bill No. 2 SITE WORKS
SITE WORKS (Cont'd.)
Collection
From Page 2/1 95,238.0
From Page 2/2 24,795.0
From Page 2/3 -
Total Bill No.2- Carried To Summary 120,033.0
2/32
5/28/2018 3 VILLAS BOQ- (323-459)
33/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
SUB STRUCTURE
(Including Servant Block & Guard Room)
All works shall be carried out as perspecifications and Drawings and to the
approval and satisfaction of the Engineer
CONCRETE
Plain cement concrete of gradeSRC C20
including all necessary form work complete as
required
A 75 mm thick below raft slab, ramp slab and footings. 1227 m2 50.00 61,350.00
B 100 mm thick below tie beam and solid block work 65 m2 55.00 3,575.00
Reinforced cement concrete compressive
characteristic strength 40 N/mm2 of grade SRC
including reinforcement & form work as per
drawings & specification to the approval of
Engineer
C Raft Slab 97 m3 1,389.00 134,733.00
D Column Footings (Additional thickening) 69 m3 1,389.00 95,841.00
E Retaing wall Footing (Additional thickening) 120 m3 1,389.00 166,680.00
F Stub columns 4 m3 1,469.00 5,876.00
G Basement Column 15 m3 1,469.00 22,035.00
H Ground Floor Footings 58 m3 1,332.00 77,256.00
J In Ramp Slab 15 m3 1,389.00 20,835.00
K Extra over thickening of grade slab (wall footing) 9 m3 1,332.00 11,988.00
Total Carried To Collection 600,169.00
Bill No. 3 SUB STRUCTURE
3/33
5/28/2018 3 VILLAS BOQ- (323-459)
34/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 3 SUB STRUCTURE
SUB STRUCTURE (cont'd)
Reinforced cement concrete compressivecharacteristic strength 40 N/mm2 of grade SRC
including reinforcement & form work as per
drawings & specification to the approval of
Engineer
A Basement Wall 134 m3 1,290.00 172,860.00
B Tie Beams at Ground Floor level 24 m3 1,212.00 29,088.00
C Grade slab 150mm thick 68 m3 805.00 54,740.00
D Suspended slab 250mm thick 175 m3 1,159.00 202,825.00
E Spiral stair case Base 3 m3 1,113.00 3,339.00
Total Carried To Collection 462,852.00
3/34
5/28/2018 3 VILLAS BOQ- (323-459)
35/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 3 SUB STRUCTURE
SUB STRUCTURE (cont'd)
Thermal & Moisture protection
A 1000 Gauge polythene sheet of approved 1745 m2 2.00 3,490.00
quality, for PCC bedding in footing & Ground
slab
B 2 layer of 4mm thick approved water proofing 1268 m2 66.00 83,688.00
membrane to foundations, beams & raft slab
as per drawing and specification
C Polystyrene 50mm thermal insulation 463 m2 19.00 8,797.00
perimeter ground beam and retaing wall
D Damp proof course as per drawings and 108 m2 7.00 756.00
specification
E Two coats of approved rubber base bitumen 930 m2 7.00 6,510.00
paint for Tie beam block works
F 50mm thick protection screed for Basement raft 624 m2 39.00 24,336.00
slab and footings (horizontal)
G Protection board to retaining wall vertical surface 644 m2 21.00 13,524.00
H 12mm thick Flexcell board with joint filleraround the slab jointing. 1 LS 1,100.00 1,100.00
Masnory works
J 200mm thick block wall below the tie beam 144 m2 77.00 11,088.00
Total Carried To Collection 153,289.00
3/35
5/28/2018 3 VILLAS BOQ- (323-459)
36/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 3 SUB STRUCTURE
SUB STRUCTURE (cont'd)
ADDITIONAL ITEMS
The tenderer is to detail below any
additional items with quantities and rates not
previously included to complete the build
up of lumpsum tender price for this section
of the works. Should the tenderer fail to
insert any items here, it will be deemed that
his lumpsum price for the tender includes all
items and no subsequent claim for any
additional item will be entertained.
A Pvc water stop 174 m 242.00 42,108.00
Total Carried To Collection 42,108.00
3/36
5/28/2018 3 VILLAS BOQ- (323-459)
37/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 3 SUB STRUCTURE
SUB STRUCTURE (cont'd)
Collection
From Page 3/1 600,169.00
From Page 3/2 462,852.00
From Page 3/3 153,289.00
From Page 3/4 42,108.00
Total Bill No. 3- Carried to Summary 1,258,418.00
3/37
5/28/2018 3 VILLAS BOQ- (323-459)
38/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
SUPER STRUCTURE
(Including Servant Block & Guard Rooms)
Reinforced cement concrete compressive
characteristic strength 40 N/mm2 with of grade
OPC type II with necessary Approved
plasticizer and admixture. Cost inclusive of
Necessary form work, Reinforcement as per
the drawings, specifications. etc complete.
The reinforcement shall comply with relevant
British Standards.
A Columns (GF,FF & Roof) 70 m3 1,658.00 116,060.00
B Beams (GF,FF & Roof) 66 m3 1,400.00 92,400.00
C 250mm thick Suspended slabs (GF,FF & Roof) 545 m3 1,092.00 595,140.00
(Including 200mm & 140mm thk)
D Staircase 25 m3 1,323.00 33,075.00
E Parapets & Upstands 66 m3 1,439.00 94,974.00
F Equipment bases 2 m3 1,100.00 2,200.00
Total Carried To Collection 933,849.00
Bill No. 4 SUPER STRUCTURE
4/38
5/28/2018 3 VILLAS BOQ- (323-459)
39/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 4 SUPER STRUCTURE
SUPER STRUCTURE (cont'd)
BLOCK WORK
Block work shall be with complete accessories
like Expanded mesh, wall ties, reinforcement
bars, head restraints, joints, stiffener columns
and beams etc as per the specifications,
drawings to engineer's approval, the works
Shall be protected from rapid drying by
Approved means. also the blocks shall be
comply with the B.S.
External
A 350mm thick insulated block work 1394 m2 127.00 177,038.00
(Cavity wall 200mm solid + 50mm
insulation+100mm solid)
Internal
B 200mm thick Solid block work 2298 m2 88.00 202,224.00
C 100mm thick Solid block work 232 m2 77.00 17,864.00
Lintel
D Lintel to the window opening 1 LS 5,500.00 5,500.00
Total Carried To Collection 402,626.00
4/39
5/28/2018 3 VILLAS BOQ- (323-459)
40/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 4 SUPER STRUCTURE
SUPER STRUCTURE (cont'd)
ADDITIONAL ITEMS
The tenderer is to detail below any
additional items with quantities and rates not
previously included to complete the build
up of lumpsum tender price for this section
of the works. Should the tenderer fail to
insert any items here, it will be deemed that
his lumpsum price for the tender includes all
items and no subsequent claim for any
additional item will be entertained.
A Core wall 46 m3 1,131.00 52,026.00
Total Carried To Collection 52,026.00
4/40
5/28/2018 3 VILLAS BOQ- (323-459)
41/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 4 SUPER STRUCTURE
SUPERSTRUCTURE (cont'd)
Collection
From Page 4/1 933,849.00
From Page 4/2 402,626.00
From Page 4/3 52,026.00
Total Bill No. 4- Carried to Summary 1,388,501.00
4/41
5/28/2018 3 VILLAS BOQ- (323-459)
42/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
I tem
No .Desc r ip t ion Qty Un it Rate Amoun t / Dhs.
THERMAL & MOISTURE PROTECTION
(Including Servant Block & Guard Room)
Roofing & Moisture protection
The Water proofing work shall be carried out By a
Professional agency. The system and Material shall be tothe approval of the engineer as per drawing and
specification. Main and subcontractor shall provide
10years Guarantee against any leakage or Dampness of
the structure.
Roofing
A Flat roof water proofing system as shown in the drawing 1043 m2 94.00 98,042.00
and specification etc., complete including below roof clay
tiles
B 600 x 600 x 50mm reinforced concrete tiles with sulphate
resisting additives and chamfered top edges laid loose 1043 m2 39.00 40,677.00
C Extra over for Rainwater outlets 1.00 LS 2,750.00 2,750.00
Moisture Protection
D 50mm thick polystyrene insulation at exposed
concrete surface and connecting area of Masnory and
concrete as per drawings and specification 1 LS 16,500.00 16,500.00
Wet Area Waterproofing
Supply and Apply, liquid applied polyurethane rubber
waterproofing as per drawing and specifications etc
complete.
E Floor 346 m2 28.00 9,688.00
F To Walls 442 m 28.00 12,376.00
Sundries
G Planter wall water proofing as per 40 m2 33.00 1,320.00
Drawing & specification
Total Carried To Collection 181,353.00
Bill No. 5 THERMAL & MOISTURE PROTECTION
5/42
5/28/2018 3 VILLAS BOQ- (323-459)
43/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
I tem
No .Desc r ip t ion Qty Un it Rate Amoun t / Dhs.
Bill No. 5 THERMAL & MOISTURE PROTECTION
THERMAL & MOISTURE PROTECTION (Cont'd )
ADDITIONAL ITEMS
The tenderer is to detail below any additional items with
quantities and rates not previously included to complete
the build up of lumpsum tender price for this section of the
works. Should the tenderer fail to insert any items here, it
will be deemed that his lumpsum price for the tender
includes all items and no subsequent claim for any
additional item will be entertained.
A Waterproofing to upstands / Parapets 509 m 39.00 19,851.00
B Skirting to upstands /Parapets 509 m 22.00 11,198.00
Total Carried To Collection 31,049.00
5/43
5/28/2018 3 VILLAS BOQ- (323-459)
44/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
I tem
No .Desc r ip t ion Qty Un it Rate Amoun t / Dhs.
Bill No. 5 THERMAL & MOISTURE PROTECTION
THERMAL & MOISTURE PROTECTION (Cont'd )
Collection
From page 5/1 181,353.00
From page 5/2 31,049.00
Total Bill No.5- Carried to Summary 212,402.00
5/44
5/28/2018 3 VILLAS BOQ- (323-459)
45/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
METAL WORKS
(Including Servant Block & Guard Room)
ALUMINIUM DOORS AND WINDOWS
Supply & Installation of complete Aluminium and glazing
works including all accessories, fittings, hardware,
architraves and ironmongery, signage , all as per the
drawings, specifications and to the approval of Engineer.
A Double Leaf - W/01
size 1700x2220 mm high 2 No. 4,015.00 8,030.00
B Full height fixed with Automatic Sliding Door
Size (3167+1415+5830+3000+1790) 2220mm high
Door Size-3000x2220mm high (Automatic) W/02 1 No. 40,673.00 40,673.00
C Fixed Panel with Automatic sliding Door
Size 6700x2220 mm high
Door Size-3000x2220mm high (Automatic) W/03 1 No. 24,173.00 24,173.00
D Double leaf Swing Door-W/05
Size 2000x2200 high (o/A size-2000x2800mm (h)) 1 No. 5,467.00 5,467.00
E Fixed Panel with sliding Door
O/A Size 4000x2700 mm high - W/10
Door Size-2000x2200mm high 2 No. 6,798.00 13,596.00
F Fixed panel with 2 nos Sliding Door
O/A Size 5400x2800 - W/14
Door Size 1700x2200mm high- 2 Nos. 2 No. 9,416.00 18,832.00
G Top Fixed Panel with sliding Door
O/A Size 2600x2800 mm high - W/15
Door Size-2600x2200mm high 1 No. 3,894.00 3,894.00
H Top Fixed Panel with sliding Door
O/A Size 2400x2800 mm high - W/16
Door Size-2400x2200mm high 1 No. 3,691.00 3,691.00
J Top Fixed Panel with sliding Door
O/A Size 3000x2800 mm high - W/18
Door Size-3000x2200mm high 1 No. 2,849.00 2,849.00
Total Carried To Collection 121,205.00
Bill No. 6 METAL WORKS
6/45
5/28/2018 3 VILLAS BOQ- (323-459)
46/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 6 METAL WORKS
METAL WORKS (Cont'd).
ALUMINIUM DOORS AND WINDOWS (Cont'd).
Supply & Installation of complete Aluminium and glazing
works including all accessories, fittings, hardware,
architraves and ironmongery, signage , all as per the
drawings, specifications and to the approval of Engineer.
A Top Fixed Panel with sliding Door
O/A Size 1450x2800 mm high - W/19
Door Size-1450x2200mm high 1 No. 2,486.00 2,486.00
B Top Fixed Panel with sliding DoorO/A Size 3900x2800 mm high - W/20
Door Size-3900x2200mm high 2 No. 5,885.00 11,770.00
C Top Fixed Panel with sliding Door
O/A Size 2200x2800 mm high - W/22
Door Size-2200x2200mm high 2 No. 3,652.00 7,304.00
D Top Fixed Panel with sliding Door
O/A Size 2200x2500 mm high - W/23
Door Size-2200x2050mm high 2 No. 3,278.00 6,556.00
E Top Fixed Panel with sliding Door
O/A Size 2700x2800 mm high - W/26
Door Size-2200x2200mm high 1 No. 4,081.00 4,081.00
F Top Fixed Panel with Single leaf swing Door
O/A Size 1000x2800 mm high - W/06C
Door Size-1000x2200mm high 5 No. 1,914.00 9,570.00
G Top Fixed Panel with Sliding Door
O/A Size 1600x2800 mm high - W/31
Door Size-1600x2200mm high 2 No. 2,662.00 5,324.00
H Top Fixed Panel with Sliding Door
O/A Size 1750x2800 mm high - W/32Door Size-1750x2200mm high 4 No. 2,783.00 11,132.00
J Top Fixed Panel with Sliding Door
O/A Size 3600x2800 mm high - W/21A
Door Size-3600x2200mm high 2 No. 4,477.00 8,954.00
Total Carried To Collection 67,177.00
6/46
5/28/2018 3 VILLAS BOQ- (323-459)
47/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 6 METAL WORKS
METAL WORKS (Cont'd).
ALUMINIUM DOORS AND WINDOWS (Cont'd).
Supply & Installation of complete Aluminium and glazing
works including all accessories, fittings, hardware,
architraves and ironmongery, signage , all as per the
drawings, specifications and to the approval of Engineer.
A Window W/04
Size 5000x400mmhigh 2 No. 1,397.00 2,794.00
B Window W/06
Size 1000x2700mmhigh 13 No. 1,188.00 15,444.00
C Window W/07
Size 1200x2700mmhigh 12 No. 2,063.00 24,756.00
D Window W/07A
Size 1200x2800mmhigh 4 No. 2,063.00 8,252.00
E Window W/08
Size 1500x2700mmhigh 4 No. 1,562.00 6,248.00
F Window W/09
Size 1200x1800mmhigh 6 No. 1,562.00 9,372.00
G Window W/10
Size 1500x2700mmhigh 2 No. 6,798.00 13,596.00
H Window W/11
Size 1500x2700mmhigh 7 No. 2,541.00 17,787.00
J Window W/12
Size 950x2700mmhigh 5 No. 1,925.00 9,625.00
K Window W/13
Size 1800x2700mmhigh 7 No. 2,750.00 19,250.00
Total Carried To Collection 127,124.00
6/47
5/28/2018 3 VILLAS BOQ- (323-459)
48/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 6 METAL WORKS
METAL WORKS (Cont'd).
ALUMINIUM DOORS AND WINDOWS (Cont'd).
Supply & Installation of complete Aluminium and glazing
works including all accessories, fittings, hardware,
architraves and ironmongery, signage , all as per the
drawings, specifications and to the approval of Engineer.
A Window W/17
Size 800x1800mmhigh 3 No. 1,155.00 3,465.00
B Window W/21Size 3000x2700mmhigh 4 No. 4,978.00 19,912.00
C Window W/25
Size 5000x1800mmhigh 1 No. 5,324.00 5,324.00
D Window W/07B
Size 950x2700mmhigh 1 No. 1,782.00 1,782.00
E Window W/27
Size 2200x2800mmhigh(Fixed) 1 No. 2,409.00 2,409.00
F Window W/28
Size 3100x2700mmhigh 2 No. 4,422.00 8,844.00
G Window W/29
Size 3300x2700mmhigh 2 No. 4,703.00 9,406.00
H Window W/30
Size 3800x2700mmhigh 2 No. 5,357.00 10,714.00
J Window W/11F
Size 3800x2700mmhigh 2 No.2,519.00 5,038.00
Total Carried To Collection 66,894.00
6/48
5/28/2018 3 VILLAS BOQ- (323-459)
49/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 6 METAL WORKS
METAL WORKS (Cont'd).
ALUMINIUM DOORS AND WINDOWS (Cont'd).
Supply & Installation of complete Aluminium and glazing
works including all accessories, fittings, hardware,
architraves and ironmongery, signage , all as per the
drawings, specifications and to the approval of Engineer.
A Window W/06B
Size 1000x1900mmhigh 8 No. 908.00 7,264.00
B Window W/022A
2200x2700mm high 4 No. 3,658.00 14,632.00
C Window W/07FW
Size 1200x1900mmhigh 2 No. 1,056.00 2,112.00
D Window W/08FW
Size 1500x1900mmhigh 1 No. 1,254.00 1,254.00
E Window W/08B
Size 1600x1800mm high 1 No. 1,898.00 1,898.00
F Window W/08C
Size 1150x1800mmhigh 3 No. 1,513.00 4,539.00
G Window W/07C
Size 1200x2200mmhigh 2 No. 1,826.00 3,652.00
H Window W/08D
Size 1500x2200mm high 1 No. 2,013.00 2,013.00
J Window W/08E
Size 1200x1800mmhigh 5 No. 1,562.00 7,810.00
K Window W/06FW
Size 1000x2700mmhigh 2 No. 1,463.00 2,926.00
L Window W24,
Size 2250x2700mmhigh 1 No. 2,673.00 2,673.00
Total Carried To Collection 50,773.00
6/49
5/28/2018 3 VILLAS BOQ- (323-459)
50/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 6 METAL WORKS
METAL WORKS (Cont'd).
ALUMINIUM DOORS AND WINDOWS (Cont'd).
Supplying & Fixing of Powder coated Aluminium
heavy duty lower panels and framed panel as per
the drawing.
A AL-01 Size; 4800x2100mm high 1 No. 10,175.00 10,175.00
B AL-02 Size; 4100x2100mm high 1 No. 9,548.00 9,548.00
C AL-03 Size; 2750x2100mm high 1 No. 5,115.00 5,115.00
D AL-04 Size; 1600x1400mm high 2 No. 2,079.00 4,158.00
Wrought Iron Hand railing
Supplying & Fixing of floor mounted wrought iron
railing/balustrade as per drawing
(PC supply and fix rate Dhs. 1500/- per Rm)
E Stair Case Railing (Including Skylight void railing) 115 m EXCLUDED
F Balcony Railing 166 m 1,650.00 273,900.00
G Roof Railing 74 m 1,650.00 122,100.00
G.I Railing
H Supply and fix 60mm dia GI pipe railing, painted finish in 8 m 660.00 5,280.00
roof
Spiral StaircaseJ 02 No of Supply & installation of Galvanised steel spiral
stair case as per the drawing - Provisional Sum -
Dhs.22,000.00 Including 10% Overheads & Profit.1 PS 22,000.00
Total Carried To Collection 452,276.00
6/50
5/28/2018 3 VILLAS BOQ- (323-459)
51/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 6 METAL WORKS
METAL WORKS (Cont'd).
Steel Doors
Supply & fixing of fire resistance, smoke proof &
self closing steel door with stell fame and 6mm
thick wired glass panel as per drawing.
A SD1a-1000x2200mm 4 No. 3,080.00 12,320.00
B SD1b-1100x2200mm 7 No. 3,520.00 24,640.00
C SD2-1000x2200mm 8 No. 3,300.00 26,400.00
D SD3-2000x2200mm 1 No. 6,820.00 6,820.00
Miscellaneous
E Supplying & Fixing of 38mm thick Galvanized steel cat
ladder as per the drawings 3 No. 3,025.00 9,075.00
F Supply and installation of Double glazed sky Refer Prov. Sum
light as per drawings
G Supply and fix MS epoxy painted access platform in OTS Not Applicable
H Supply and fix security grills for windows around OTS Not Applicable
J Supply and fix wrought iron grill to basement window 11 m 770.00 8,470.00
(PC supply and fix rate Dhs. 700/- per Rm)
Total Carried To Collection 87,725.00
6/51
5/28/2018 3 VILLAS BOQ- (323-459)
52/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 6 METAL WORKS
METAL WORKS (Cont'd).
ADDITIONAL ITEMS
The tenderer is to detail below any additional items with
quantities and rates not previously included to complete
the build up of lumpsum tender price for this section of
the works. Should the tenderer fail to insert any items
here, it will be deemed that his lumpsum price for the
tender includes all items and no subsequent claim for any
additional item will be entertained.
Servant Block & Guard Room
A W/34 1 No. 2,057.00 2,057.00
B W35 6 No. 479.00 2,874.00
C W36 2 No. 1,403.00 2,806.00
D W37 2 No. 1,056.00 2,112.00
Total Carried To Collection 9,849.00
6/52
5/28/2018 3 VILLAS BOQ- (323-459)
53/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 6 METAL WORKS
METAL WORKS (Cont'd).
Collection
From Page 6/1 121,205.00
From Page 6/2 67,177.00
From Page 6/3 127,124.00
From Page 6/4 66,894.00
From Page 6/5 50,773.00
From Page 6/6 452,276.00
From Page 6/7 87,725.00
From Page 6/8 9,849.00
Total Bill No. 6- Carried To Summary 983,023.00
6/53
5/28/2018 3 VILLAS BOQ- (323-459)
54/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
WOODEN & JOINERY WORKS
(Including Servant Block & Guard Room)
Supply and fixing of 45mm thick semi solid wooden
door frame with flush shutter including all necessaryhardware, ironmongery, HW lippings, Architraves,
signage, sub frames, fire rating with appropriate
smoke seal & intumescent strips to door and meranti
finish/ polished/ painted/ Laminated as specified and
shown in the drawing's and specification, engineers
approval complete. All fire proofing shall be as per
the ID details/ civil defence /authority requirements
A 45mm thick semi solid core single leaf flush door with cherry
wood in laqured finish frames and Architraves as per
eng approval (Shutter External - Cherry wood finish.
Internal Cherry Wood Stained/polished finish)
(PC Rate Dhs. 3000/No)
D4-800x2200mm high 26 No. - -
D5-900x2200mm high 7 No. - -
D6-1000x2200mm high 19 No. - -
D7-600x2200mm high 4 No. - -
B 45mm thick semi solid core flush double leaf door with
cherry wood in laqured finish frames and Architraves with
6mm thick wire transon glass panel and fixed glass at the top
as per eng approval (Shutter External - Cherry wood finish.
Internal Cherry Wood Stained/polished finish)
(PC Supply and Fix Rate Dhs. 4000/No)
D3-1550x2200mm high - nil
D8-1000x2200mm high 5 No.- -D10-1100x2800mm high 2 No. - -
EXCLUDED
C 45mm thick semi solid core flush double leaf door with cherry
wood in laqured finish frames and Architraves as per eng
approval (Shutter External - Cherry wood finish. Internal Cherry
Wood Stained/polished finish)
(PC Supply and Fix Rate Dhs. 4000/No)
D9-1700x2200mm high 1 No. - -
D 54 mm thick solid core fire rated flush door with intumesent
sealing strips round, frames and Architraves as per eng approval
(Shutter External - Cherry wood finish. Internal Cherry Wood
Stained/polished finish) as per the drawing(PC Supply and Fix Rate Dhs. 5000/No)
D2-1300x2200mm high 4 No. - -
Total Carried To Collection -
Bill No. 7 WOODEN & JOINERY WORKS
7/54
5/28/2018 3 VILLAS BOQ- (323-459)
55/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 7 WOODEN & JOINERY WORKS
WOOD WORKS & JOINERY (cont'd)
WARDROBES
Supply and install wardrobes with all accessories as per
drawing & specification
A Wooden Wardrobes 106 m - -
(PC Supply and Fix Rate Dhs.1500/m)
VANITY CABINETS
Supply and Install vanity cabinets with Marble Top as
per Drawing & specification
B Vanity Counter with marble Top 29 m - -(PC Supply and Fix Rate Dhs.2000/m)
SHELVES
EXCLUDED
Supplying and fixing of shelves As per Drawing & specification
C Shelves for Store (Villa 2) 9 m - -
D Shelves for Store (Villa 3) 5 m - -
E Shelves for Library (Villa 2) 6 m - -
TIMBER PERGOLA
F Supply and fixing of hardwood pergola in balcony/terraces 9 m2 - -
(PC Supply and Fix Rate Dhs.1000/m2)
Total Carried To Collection -
7/55
5/28/2018 3 VILLAS BOQ- (323-459)
56/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 7 WOODEN & JOINERY WORKS
WOODEN & JOINERY WORKS (Cont'd.)
ADDITIONAL ITEMS
The tenderer is to detail below any additional items with
quantities and rates not previously included to complete the
build up of lumpsum tender price for this section of the works.
Should the tenderer fail to insert any items here, it will be
deemed that his lumpsum price for the tender includes all
items and no subsequent claim for any additional item will be
entertained.
Total Carried To Collection -
7/56
5/28/2018 3 VILLAS BOQ- (323-459)
57/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 7 WOODEN & JOINERY WORKS
WOODEN & JOINERY WORKS (Cont'd.)
Collection
From Page 7/1 -
From Page 7/2 -
From Page 7/3
Total Bill No. 7- Carried To Summary -
7/57
5/28/2018 3 VILLAS BOQ- (323-459)
58/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
FINISHES(Including Servant Block & Guard Room)
All the finishing items shall be as per theschedule of finishes. The floor and wall tiles
Shall be fixed using approved epoxy adhesive
and epoxy grout Colour matching to the tiles,
and to approval. All the curved joint shall be
cut with water jet cutting as per drawing and
specification. (The material and workmanship
shall be to the approval of The engineer.)
INTERNAL
Floor Finishes
A Powder Floated Epoxy paint finish with sand
granulated texture floor finish 90 m2 - -
B Powder Floated concrete with Epoxy paint 280 m2 - -
C 50mm thick screed with hardner smooth finish 84 m2 - -
D1 300x300mm 'Graniti tiles' 180 m2 - -
PC Supply Rate Dhs.75/m2
D2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed (O/A 50mm thick)- and wastage factor 180 m2 - -EXCLUDED
D3 Main Contractors OHP percentage on D1 & D2 10% % - -
E1 300x300mm non-slip ceramic tile finish with cemnt
sand screed (O/A 50mm thick) 132 m2 - -PC Supply Rate Dhs.45/m2
E2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed (O/A 50mm thick)- and wastage factor 132 m2 - -
E3 Main Contractors OHP percentage on E1 & E2 10% % - -
Total Carried To Collection
Bill No. 8 FINISHES
8/58
5/28/2018 3 VILLAS BOQ- (323-459)
59/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
INTERNAL FINISHES (Cont'd)
Floor Finishes (Cont'd).
A Supply and fix 60mm thick interlock paving tiles on
cement bed (Basement); colour to approval 111 m2 72.00 7,992.00
B1 Cut to size polished granite to approved pattern 678 m2 - -PC Supply Rate Dhs.500/m2
B2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed (O/A 50mm thick)- and wastage factor 678 m2 - -
B3 Main Contractors OHP percentage on B1 & B2 10% % - -
EXCLUDED
C1 300x300 Granite tile 53 m2 - -PC Supply Rate Dhs.200/m2
C2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed (O/A 50mm thick)- and wastage factor 53 m2 - -
C3 Main Contractors OHP percentage on C1 & C2 10% % - -
Total Carried To Collection 7,992.00
8/59
5/28/2018 3 VILLAS BOQ- (323-459)
60/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
INTERNAL FINISHES (Cont'd)
Floor Finishes (Cont'd).
A1 Fully Vitrified porcelain tiles with to approved 295 m2 - -pattern
PC Supply Rate Dhs.75/m2
A2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed (O/A 50mm thick)- and wastage factor 295 m2 - -
A3 Main Contractors OHP percentage on A1 & A2 10% % - -
B1 Non - slip ceramic tiles 93 m2 - -PC Supply Rate Dhs.45/m2
B2 Main Contractors rate for fixing with all items EXCLUDED
necessary for fixing, etc including Cement Sand
Screed (O/A 50mm thick)- and wastage factor 93 m2 - -
B3 Main Contractors OHP percentage on B1 & B2 10% % - -
C1 Non-slip fully Vitrified porcelain ti les 142 m2 - -PC Supply Rate Dhs.75/m2
C2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed (O/A 50mm thick)- and wastage factor 142 m2 - -
C3 Main Contractors OHP percentage on C1 & C2 10% % - -
Total Carried To Collection
8/60
5/28/2018 3 VILLAS BOQ- (323-459)
61/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
INTERNAL FINISHES (Cont'd)
Floor Finishes (Cont'd).
A1 Non-slipCeramic floor tile 53 m2 - -PC Supply Rate Dhs.25/m2
A2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed (O/A 50mm thick)- and wastage factor 53 m2 - -
A3 Main Contractors OHP percentage on A1 & A2 10% % - -
Non-Slip Procelain tiles Tread & riser with, cement
sand screed for staircase steps 300mm tread & EXCLUDED
180mm rise
B1 Main Stair Case 326 m - -PC Supply Rate Dhs.75/m
B2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed (O/A 50mm thick)- and wastage factor 326 m - -
B3 Main Contractors OHP percentage on B1 & B2 10% % - -
C1 Service Stair Case Not ApplicablePC Supply Rate Dhs.65/m
C2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed Not Applicable
C3 Main Contractors OHP percentage on C1 & C2 10% Not Applicable
Non-Slip Procelain tiles for stair case landing with,
cement sand screed
D1 Main Staircase 38 m2 - -PC Supply Rate Dhs.50/m2
D2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand EXCLUDED
Screed (O/A 50mm thick)- and wastage factor 38 m2 - -
D3 Main Contractors OHP percentage on D1 & D2 10% % - -
Total Carried To Collection
8/61
5/28/2018 3 VILLAS BOQ- (323-459)
62/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
INTERNAL FINISHES (Cont'd)
A1 Service Staircase Not ApplicablePC Supply Rate Dhs.45/m2
A2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed Not Applicable
A3 Main Contractors OHP percentage on A1 & A2 10% Not Applicable
B1 Supply and fixing of high pressurised Laminate
flooring with necessary under lay as per drawing
and specfication 523 m2 - -(PC Supply and Fix rate Dhs.100/m2) - Including
wastage
B2 Main Contractors OHP percentage on B1 10% % - -
Skirting
D 100mm high epoxy paint 70 m - EXCLUDED
D1 Procelain tile skirting match to the floor 314 m - -(PC Supply Rate Dhs. 15/Rm)
D2 Main Contractors rate for fixing with all items
necessary for fixing, etc Including Cement
mortar/glue and wastage factor 314 m- -
D3 Main Contractors OHP percentage on D1 & D2 10% % - -
Total Carried To Collection
8/62
5/28/2018 3 VILLAS BOQ- (323-459)
63/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
INTERNAL FINISHES (Cont'd)
Skirting (Cont'd)
A1 100mm high Granite Skirting 399 m - -(PC Supply Rate Dhs. 20/Rm)
A2 Main Contractors rate for fixing with all items
necessary for fixing, etc Including Cement
mortar/glue and wastage factor 399 m - -
A3 Main Contractors OHP percentage on A1 & A2 10% % - -
B1 100mm high Ceramic tile Skirting 144 m - -(PC Supply Rate Dhs. 10/Rm)
B2 Main Contractors rate for fixing with all itemsnecessary for fixing, etc Including Cement
mortar/glue and wastage factor 144 m - -
B3 Main Contractors OHP percentage on B1 & B2 10% % - -
C1 100mm high ceramic tile skirting for Stair case 145 m - -(Main Staircase - PC Supply Rate Dhs. 15/Rm)
C2 Main Contractors rate for fixing with all items EXCLUDED
necessary for fixing, etc Including Cement
mortar/glue and wastage factor 145 m - -
C3 Main Contractors OHP percentage on C1 & C2 10% % - -
D1 Ceramic tile skirting to Toilet 326 m - -(PC Supply Rate Dhs. 15/Rm)
D2 Main Contractors rate for fixing with all items
necessary for fixing, etc Including Cement
mortar/glue and wastage factor 326 m - -
D3 Main Contractors OHP percentage on D1 & D2 10% % - -
E1 100mm high pressurised laminate skirting to 400 m - -match floor(PC Supply Rate Dhs. 50/Rm)
E2 Main Contractors rate for fixing with all items
necessary for fixing, etc. including wastage factor 400 m - -
E3 Main Contractors OHP percentage on E1 & E2 10% % - -
Total Carried To Collection
8/63
5/28/2018 3 VILLAS BOQ- (323-459)
64/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
INTERNAL FINISHES (Cont'd)
Threshold
A1 350mm wide threshold for doors as per site 30 m - -measurement (PC Supply rate = Dhs. 150/M)
A2 Main Contractors rate for fixing with all items
necessary for fixing, etc Including Cement
mortar/glue 30 m - -
A3 Main Contractors OHP percentage on A1 & A2 10% % - -
B1 200mm wide threshold for doors as per site 87 m - -measurement(PC Supply rate = AED 50/M)
B2 Main Contractors rate for fixing with all items
necessary for fixing, etc Including Cement EXCLUDED
mortar/glue 87 m - -
B3 Main Contractors OHP percentage on B1 & B2 10% % - -
C1 100mm wide threshold for doors as per site 3 m - -measurement(PC Supply rate = AED 50/M)
C2 Main Contractors rate for all items necessary
For fixing, etc as described in preambles 3 m - -
C3 Main Contractors OHP percentage on C1 & C2
10% % - -
Total Carried To Collection
8/64
5/28/2018 3 VILLAS BOQ- (323-459)
65/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
INTERNAL FINISHES (Cont'd)
Wall Finishes
Plastering for the walls shall be including all
accessories as per drawings / specifications
The spills shall be cleaned and touch up shall
be done wherever required.
A 12mm thick Internal wall plastering 6440 m2 31.00 199,640.00
B Emulsion Painting 1 coat Primer only for the plastered 4729 m2 3.00 14,187.00
C Epoxy Coating System1 coat primer only 275 m2 3.00 825.00
D Oil Paint System1 coat primer only 500 m2 3.00 1,500.00
E 20mm thick render with matt finish sandtec or 80 m2 33.00 2,640.00
approved similar
Porcelain tile / Ceramic tiles / Glossy-Ceramic
Tiles/ Vitrified Ceramic tile / Marble stone
wall finishes laying to pattern as per drawing
& specification, including back ground
Plaster & adhesives/glue, grouting to approval
of the Engineer;
F1 300x300-Glazed ceramic tiles 977 m2 - -
PC Suply Rate Dhs 30/m2
F2 Main Contractors rate for fixing with all items EXCLUDED
necessary For fixing, etc 977 m2 - -Including background plaster
F3 Main Contractors OHP percentage on F1 & F2 10% % - -
Total Carried To Collection 218,792.00
8/65
5/28/2018 3 VILLAS BOQ- (323-459)
66/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
INTERNAL FINISHES (Cont'd)
Ceiling finishes
A 12mm thick Ceiling Plaster 556 m2 - EXCLUDED
B Complete false ceiling with bulkhead, Cove Refer Provisional Sum
light, Cornice and curtain box detail
C Epoxy Paint on Plaster 280 m2 - EXCLUDED
D Oil Paint on Plaster 179 m2 - EXCLUDED
E Emulsion Paint on plaster 97 m2 - EXCLUDED
Total Carried To Collection
8/66
5/28/2018 3 VILLAS BOQ- (323-459)
67/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
INTERNAL FINISHES (Cont'd)
ACCESSORIES
Sanitary Fittings
Supply & Install the following Sanitarywares &
accessories Complete with Fittings , Taps &
Mixers, Traps And accessories as per drawing &
specification
A1 Bathroom Set (Master bathroom & Secondary 13 Sets - -
Bedroom Bathroom) including mirrors
PC Rate.Dhs.7000/Each set
A2 Main Contractors rate for all items necessary
For fixing, etc as described in preambles 13 Set - -
A3 Main Contractors OHP percentage on A1 & A2 10% % - -
B1 Toilets including mirrors 16 No - -
PC Rate.Dhs.5000/Each Toilet
B2 Main Contractors rate for all items necessary
For fixing, etc as described in preambles 16 No - -
B3 Main Contractors OHP percentage on B1 & B2 10% % - -
EXCLUDED
C1 Toilet Maid Room including mirrors 5 No - -
PC Rate.Dhs.1500/Each Toilet
C2 Main Contractors rate for all items necessary
For fixing, etc as described in preambles 5 No - -
C3 Main Contractors OHP percentage on C1 & C2 10% % - -
D1 Jacuzzi with necessary mixer (Master Bathroom 3 Set - -
Villa 1,2&3)
PC Rate Dhs.10,000/set
D2 Main Contractors rate for all items necessary 3 Set - -
For fixing, etc as described in preambles
D3 Main Contractors OHP percentage on D1 & D2 10% % - -
Total Carried To Collection
8/67
5/28/2018 3 VILLAS BOQ- (323-459)
68/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
INTERNAL FINISHES (Cont'd)
Accessories (Cont'd)
Sundries
A Supply and fix corner gaurds, wall guard as per DM
requirement to basement parking 12 No - -
B Floor marking to basement parking 1 LS - -
C Concave mirrors as per requirement for basement 2 Nos - -
parking
D Internal signage on staircase doors, landing, 1 LS - EXCLUDEDcorridor, service room etc., as per civil
Defence/DEWA requirement
E Garbage Container as per DM requirement 1 LS - -
F MR Gypsum board ducts for vertical down take pipe. 1 LS - -
Total Carried To Collection
8/68
5/28/2018 3 VILLAS BOQ- (323-459)
69/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
FINISHES (Cont'd)
EXTERNAL
External Entrance Finishes
A1 Supply and fix of granite bushed hammer finish for
external entrance Ramps 8 m2 - -
PC Supply Rate Dhs.200/m2
A2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed 8 m2 - -
A3 Main Contractors OHP percentage on A1 & A2 10% % - -
B1 Supply and fix of Polished granite finish for EXCLUDED
external steps tread & riser 67 m - -
PC Supply Rate Dhs.300/m
B2 Main Contractors rate for fixing with all items
necessary for fixing, etc including Cement Sand
Screed 67 m - -
B3 Main Contractors OHP percentage on B1 & B2 10% % - -
External wall Finishes
C 20mm thick cement & sand render with
paint finish. 3075 m2 55.00 169,125.00
D1 Natural Stone Cladding to the wall 178 m2 200.00 35,600.00
PC Supply Rate.Dhs.200/m2
D2 Main Contractors rate for fixing with all items
necessary For fixing, etc 178 m2 170.00 30,260.00
D3 Main Contractors OHP percentage on D1 & D2 10% % 65,860.00 6,586.00
E 50mm Depth Punch Hole Groove in Plaster wall as Included
per Drawing & Specification
F Heavy Texture 4 coats solvent based epoxy paint 3075 m2 39.00 119,925.00
system for all exposed surface
G Extra over for Grooves in Plaster with 12mm wide x
10mm deep aluminium channel 1 LS 27,500.00 27,500.00
Total Carried To Collection 388,996.00
8/69
5/28/2018 3 VILLAS BOQ- (323-459)
70/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
EXTERNAL FINISHES (Cont'd)
EXTERNAL (Cont'd)
A Supply and install 60mm thick inter lock paver with Refer Provisional Sum
all necessary base and kerb stone as per the
drawings
Pitched Roof
B1 Clay roof tiles red colour including Eaves, Ridges 135 m2 55.00 7,425.00
(PC Supply Rate Dhs.55/m2)
B2 Main Contractors rate for all items necessary 135 m2 100.00 13,500.00For fixing, etc
B3 Main Contractors OHP percentage on B1 & B2 10% % 20,925.00 2,093.00
GRC WORKS
C Supply & Fixing GRC Elements as per drawing and Refer Provisional Sum
specification.
Total Carried To Collection 23,018.00
8/70
5/28/2018 3 VILLAS BOQ- (323-459)
71/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
EXTERNAL FINISHES (Cont'd)
ADDITIONAL ITEMS
The tenderer is to detail below any
additional items with quantities and rates not
previously included to complete the build
up of lumpsum tender price for this section
of the works. Should the tenderer fail to
insert any items here, it will be deemed that
his lumpsum price for the tender includes all
items and no subsequent claim for any
additional item will be entertained.
Finishes to Ponds / Fountain
A Mosaic tile for ponds/Fountains By Client
B Mosaic skirting for ponds & fountain By Client
C WC back wall top as per drawings 1 LS - -
Total Carried To Collection
8/71
5/28/2018 3 VILLAS BOQ- (323-459)
72/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
EXTERNAL FINISHES (Cont'd)
Collection
From Page 8/1
From Page 8/2 7,992.00
From Page 8/3
From Page 8/4
From Page 8/5
From Page 8/6
From Page 8/7
From Page 8/8 218,792.00
From Page 8/9
Total Carried To Page 8/15 226,784.00
8/72
5/28/2018 3 VILLAS BOQ- (323-459)
73/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 8 FINISHES
EXTERNAL FINISHES (Cont'd)
Collection
From Page 8/15 (B/F) 226,784.00
From Page 8/10
From Page 8/11
From Page 8/12 388,996.00
From Page 8/13 23,018.00
From Page 8/14
Total Bill No. 8- Carried To Summary 638,798.00
8/73
5/28/2018 3 VILLAS BOQ- (323-459)
74/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
WATER SUPPLY WORKS
A Supply & installation of pumps complete with
accessories ,pressure vessel ,valves, strainers,
controls, electrical panels, vibration isolators
as per drawings and specifications 1 LS 242,000.00 242,000.00
B Supply & installation of water tank complete with
accessories,valves,vent ,drain,supports,controls,
float valves as per drawings and specification
C Supply & installation of water supply pipe
works with fitting, accessories, supports,
sleeves as per drawings and specification
D Supply & installation of water supply
accessories with fitting, accessories ,sleeves as
per drawings and specification
E Supply & installation electric water heaters
complete with accessories,controls,supports,
drain piping as per drawings and
specification
Included in above Item-A
F Identification ,protective painting ,labeling
G Testing and commissioning
H Builders works during execution of the works
J Allow for providing shopdrawings, co-ordination
and as-built drawings
K Allow for instructing selected employer's
personnel on all aspects of the operation of
systems and equipment
L Allow for the provision of operation and
maintenance manuals
Total Carried To Collection 242,000.00
Bill No. 9 WATER SUPPLY WORKS
9/74
5/28/2018 3 VILLAS BOQ- (323-459)
75/103
Item
No.Description Qty Unit Rate Amount / Dhs.
WATER SUPPLY (Cont'd)
EXTERNAL WORKS
Supply & installation of external water supply pipe
works from water meter cabinet to villa with fitting,
accessories, supports, sleeves as per drawings and
specification
A Main water meter connection with accessories, Included in above Item-A, Page 9/1
valves, meter cabinet (meter by DEWA)
B ADDITIONAL ITEMS
The tenderer is to detail below any additional
Items with quantities and rates not previously
included to complete the build up of the lump
sum tender price for this section of the works.
Should the tenderer fail to insert any items here,
it will be deemed that his lump sum price for
the tender includes all items and no subsequent
claim for additional item will be entertained.
Total Carried To Collection
9/75
5/28/2018 3 VILLAS BOQ- (323-459)
76/103
Item
No.Description Qty Unit Rate Amount / Dhs.
WATER SUPPLY WORKS (Cont'd)
Collection
Page 9/1 242,000.00
Page 9/2
Total Bill No. 9- Carried To Summary 242,000.00
9/76
5/28/2018 3 VILLAS BOQ- (323-459)
77/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
MECHANICAL WORKS
DRAINAGE WORKS
A Supply & installation of soil, waste,
rain water, condensate ,vent piping
complete with accessories ,insulation,
supports, coatings as per drawings and
specification (Underground) 1 LS 236,432.00 236,432.00
B Supply & installation of soil, waste, rain water
condensate ,vent piping complete withaccessories, insulation, supports, coatings as
per drawings and specification (Above ground)
C Supply, Installation of drainage accessories
traps, covers sewage pumps, interceptors
as per drawings and specification
D Installation of sanitary wares with fixture
(Sanitary wares supply is included in Bill No.8)
E Related drainage works for HVAC
F Identification ,protective painting ,labeling
Included in above Item-A
G Testing and commissioning
H Builders works during execution of the works
J Allow for providing shop drawings, co-ordination
and as-built drawings
K Allow for instructing selected employer's
personnel on all aspects of the operation ofsystems and equipment
L Allow for the provision of operation and
maintenance manuals
Total Carried To Collection 236,432.00
Bill No. 10 DRAINAGE WORKS
10/77
5/28/2018 3 VILLAS BOQ- (323-459)
78/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 10 DRAINAGE WORKS
DRAINAGE WORKS (Cont'd)
EXTERNAL
A Supply & installation of soil, waste, rain water
condensate ,vent piping complete with
accessories ,insulation, supports, coatings as per
drawings and specification (Under ground -
outside the villa) Included in above Item-A, Page 10/1
B Supply & installation of drainage accessories
traps, manholes, sewage pumps, interceptors
ADDITIONAL ITEMS
C The tenderer is to detail below any additional
Items with quantities and rates not previously
included to complete the build up of the lump
sum tender price for this section of the works.
Should the tenderer fail to insert any items here,
it will be deemed that his lump sum price for
the tender includes all items and no subsequent
claim for additional item will be entertained.
Total Carried To Collection -
10/78
5/28/2018 3 VILLAS BOQ- (323-459)
79/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No.Description Qty Unit Rate Amount / Dhs.
Bill No. 10 DRAINAGE WORKS
DRAINAGE WORKS (Cont'd)
Collection
Page 10/1 236,432.00
Page 10/2 -
Total Bill No. 10 Carried to Summary 236,432.00
10/79
5/28/2018 3 VILLAS BOQ- (323-459)
80/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No. Description Qty Unit Rate Amount / Dhs.
MECHANICAL WORKS
HVAC
Supply and installation of complete HVAC works Refer Provisional
(excluding related electrical, drainage and Sum
builders works)
Total Carried To Collection
Bill No. 11 HVAC WORKS
11/80
5/28/2018 3 VILLAS BOQ- (323-459)
81/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No. Description Qty Unit Rate Amount / Dhs.
Bill No. 11 HVAC WORKS
HVAC (Cont'd)
Collection
Page 11/1
Total Bill No. 11 - Carried To Summary
11/81
5/28/2018 3 VILLAS BOQ- (323-459)
82/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No. Description Qty Unit Rate Amount / Dhs.
LPG WORKS
A Supply ,installation of LPG main line
with accessories,valves,supports ,controls asper
drawings, specification and local authorities
requirements - Provisional Sum of Dhs. 44,000/=
Including MainContractors Overheads & Profit1 PS 44,000.00
B Identification ,protective painting ,labeling Included in above Provisional Sum Item-A
C Testing and commissioning
D Builders works during execution of the works 1 LS 11,000.00 11,000.00
E Allow for providing shop, co-ordination and
as-built drawings
F Allow for instructing selected employer's
personnel on all aspects of the operation of
systems and equipment
G Allow for the provision of operation and
maintenance manuals
ADDITIONAL ITEMS Included in above Provisional Sum Item-A
H The tenderer is to detail below any
additional Items with quantities and rates not
previously included to complete the build up
of the lump sum tender price for this section
of the works. Should the tenderer fail to
insert any items here, it will be deemed that
his lump sum price for the tender includes all
items and no subsequent claim for additional
item will be entertained.
Total Carried To Collection 55,000.00
Bill No. 12 LPG WORKS
12/82
5/28/2018 3 VILLAS BOQ- (323-459)
83/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No. Description Qty Unit Rate Amount / Dhs.
Bill No. 12 LPG WORKS
LPG Works (Cont'd).
Collection
From Page 12/1 55,000.00
Total Bill No. 12 - Carried To Summary 55,000.00
12/83
5/28/2018 3 VILLAS BOQ- (323-459)
84/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No. Description Qty Unit Rate Amount / Dhs.
ELECTRICAL WORKS
A Low Voltage Distribution Boards in accordance
with DEWA standards, drawings and
specifications. 1 LS 770,000.00 770,000.00
B Supply, Install, Test & Commission the
LV Panels complete with necessary enclosures,
bus bars, circuit breakers, measurement devices,
selector switches, phase indicators,
termination, etc. including support frame
all complete as shown on drawing and as
specified
C Power factor correction Capacitor Panel (PFCC)/
Supply, Install, Test & Commission the Power
Factor Correction Capacitor Bank complete
with all necessary, switches, shut off contactors, Included in above Item-
bus bars, termination, etc. including support
frame all complete as shown on drawing
and as specified
D Final Distribution Board ( DB )
Supply, Install, Test & Commission the
Distribution Board complete with all
necessary circuit breakers, bus bars, protection
devices, termination, etc. including support
frame all complete as shown on drawing
and as specified
Total Carried To Collection 770,000.0
Bill No. 13 ELECTRICAL WORKS
13/84
5/28/2018 3 VILLAS BOQ- (323-459)
85/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No. Description Qty Unit Rate Amount / Dhs.
Bill No. 13 ELECTRICAL WORKS
ELECTRICAL WORKS (Cont'd)
Low voltage cables
A Supply, Install, Test & Commission the Low
Voltage Cables complete with necessary
conduits, accessories, supports, terminations
as specified and as shown on drawings.
B Install Lighting Fixtures (free issue by Client)
complete with accessories, supports as specified
in drawings/specifications and as per the approvalof the Engineer.
C Supply, install Lighting Fixtures Wiring Points
complete with conduit, boxes, ceiling rose,
wires, termination, final connection, accessories, Included in above Item-A, Page 13/
supports as specified in drawings/specifications
and as per the approval of the Engineer.
D Disconnection Switches / Isolators
in accordance with relevant standards,drawings and specifications.
Supply and Install Disconnection switches/
Isolators complete with final sub circuit,
wiring, conduits, trunking, mounting,
accessories, supports, hardware's etc.
Total Carried To Collection
13/85
5/28/2018 3 VILLAS BOQ- (323-459)
86/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No. Description Qty Unit Rate Amount / Dhs.
Bill No. 13 ELECTRICAL WORKS
ELECTRICAL WORKS (Cont'd)
A Lighting Switches in accordance with relevant
standards, drawings and specifications.
Supply and Install Lighting switches
complete with final sub circuit, wiring, boxes,
conduits, trunking, mounting, accessories,
supports, hardware's etc.
B Socket outlets, in accordance with relevant
standards, drawings and specifications.
Supply and Install Socket Outlet complete
with final sub circuit, wiring, boxes, conduits,
trunking, mounting, accessories, supports,
hardware's etc.
C Install Emergency Lighting Fixtures
complete with lamps, tubes, luminaries, Included in above Item-A, Page 13/
accessories, supports, as specified in drawings/
specifications and as per the approval of the
Engineer.
ELV SYSTEM
D Conventional TypeFire Alarm Systemin
accordance with standard, drawing and
specifications.
Supply and install and maintain the Fire Alarm
and detection system including all necessary
cables, wiring, conduits, trunking, mounting
accessories hardware, support etc.
Total Carried To Collection
13/86
5/28/2018 3 VILLAS BOQ- (323-459)
87/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No. Description Qty Unit Rate Amount / Dhs.
Bill No. 13 ELECTRICAL WORKS
ELECTRICAL WORKS (Cont'd)
ELV SYSTEM (Cont'd)
A Telephone, Data, Intercom & CATV System Provisional sum
in accordance with relevant standards, drawings
and specifications.
B Supply and install Complete Telephone/Data/
Intercom CATV System comprising of outlets
with necessary cables, wiring, conduits,
trunking, Cable tray mounting accessories
supports, etc. all as specified in drawing /
C Home Automation System in accordance Provisional sum
with relevant standards, drawings, and
specifications.
D Supply, install, test & commission Home
Automation System complete with necessary
cables, wirings, conduits, supports, accessories,
hardware's, etc. all as specified in drawing.
Containment System.
Included in above Item-A, Page 13/
E Supply and Install complete containment system
including cable tray, cable trunking, conduit,
ladder, covers, fittings, accessories, hardware's,
supports, etc. all as specified in drawing /
specification.
Heavy duty GI cable trays with necessary
accessories, supports, earthing links etc.
Total Carried To Collection
13/87
5/28/2018 3 VILLAS BOQ- (323-459)
88/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No. Description Qty Unit Rate Amount / Dhs.
Bill No. 13 ELECTRICAL WORKS
ELECTRICAL WORKS (Cont'd)
Electrical Miscellaneous Work.
A Electrical Miscellaneous Work complete with
conduit, manholes, trenches, all required civil
work as shown on drawing and as specified.
For B/wall works
For HVAC works
For Entrance gates
For Roof skylights
For Lifts
Sundries / General items
B Allow for inspection associated with the
electrical installations by utility and statutory Included in above Item-A, Page 13/
authorities.
C Allow for all protective painting and cleaning of
pipes, fittings and equipment
D Allow for setting out the works, marking
positions of holes, mortices, chases or the like
E Allow for testing and commissioning and
production of test certificates for all systems.
Total Carried To Collection
13/88
5/28/2018 3 VILLAS BOQ- (323-459)
89/103
EMSQUARE 3 No. B+G+1 VILLAS
CONTRACT BOQ PLOT NO. 323-459
Item
No. Description Qty Unit Rate Amount / Dhs.
Bill No. 13 ELECTRICAL WORKS
ELECTRICAL WORKS (Cont'd)
External Electrical Works.
Incoming power supply from DEWA in
accordance with the standards and
specifications.
A Supply, install, test and commission the
Electrical (kwh) meter complete with W/P