Proyecto:
Ubicacin:
LARGO ANCHO ALTO
AREA LONGITUD KG
01.02 TANQUE IMHOFF
01.02.01 TRABAJOS PRELIMINARES
01.02.01.01 TRAZO Y REPLANTEO m2 90.71
1.00 1.00 11.78 7.70 90.71
01.02.01.02 LIMPIEZA DE TERRENO MANUAL m2 90.71
1.00 1.00 11.78 7.70 90.71
01.02.02 MOVIMIENTO DE TIERRAS
01.02.02.01 EXCAVACION MASIVA A MAQUINA EN TERRENO C/BOLONERIA m32,076.14
A1 (CORTE D-D) 1.00 1.00 167.15
A2 (CORTE E-E) 1.00 1.00 118.82 14.52 2,076.14
01.02.02.02 REFINE Y NIVELACION Y COMPACTACION m2 90.71
1.00 1.00 11.78 7.70 90.71
01.02.02.03 m3 1,058.65
A1 (CORTE D-D) 86.88
01.02.02.04 A2 (CORTE E-E) 1.00 1.00 58.94 14.52 1,058.65
ELIMINACION DE MATERIAL EXCEDENTE m3 1,271.86
VOLUMEN DE EXCAVACION (V1) 2,076.14
VOLUMEN DE EXCAVACION ESPONJADO(1.25XV1) 2,595.18
VOLUMEN DE RELLENO CON MATERIAL PROPIO(V2) 1,058.65
VOLUMEN DE RELLENO CON MATERIAL PROPIO ESPONJADO 1.25XV2 1,323.32
"AMPLIACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO EN EL DISTRITO DE CASCAS"
LA LIBERTAD, GRAN CHIMU, CASCAS
TEM DESCRIPCIN UNID VECES
HOJA DE METRADOS
SUBTOTAL
TOTALCANT.MEDIDAS
RELLENO COMPACATADO PARA ESTRUCTURAS CON MATERIAL PROPIO
ELIMINACION =1.25V1-1.25V2 1,271.86
01.02.03 OBRAS DE CONCRETO SIMPLE
01.02.03.01 SOLADO DE E=4" MEZCLA 1:12 (C:H) m2 128.75
1.00 1.00 10.40 12.38 128.75
01.02.03.02 DADOS DE CONCRETO F'C = 140 KG/CM2 m3 0.80
1.00 4.00 0.80 0.50 0.50 0.80
01.02.04 OBRAS DE CONCRETO ARMADO
01.02.04.01 MUROS REFORZADOS
01.02.04.01.01 CONCRETO F'C=245 KG/CM2 EN MUROS REFORZADOS m3 AREA 133.07
MURO X-X 1.00 2.00 3.22 12.38 79.61
MURO Y-Y 1.00 2.00 3.22 8.30 53.45
01.02.04.01.02 ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS m2 853.34
MUROS INTERIROES
X-X 1.00 2.00 11.78 7.84 184.71
Y-Y 1.00 2.00 11.78 7.70 181.41
MUROS EXTERIORES
X-X 1.00 2.00 11.78 12.38 291.67
Y-Y 1.00 2.00 11.78 8.30 195.55
01.02.04.01.03 ACERO FY= 4200 KG/CM2 EN MUROS REFORZADOS kg 13,201.51
1.00 1.00 13,201.51
01.02.04.02 LOSAS ARMADAS
01.02.04.02.01 CONCRETO F'C=245 KG/CM2 EN LOSAS ARMADAS m3 35.03
1.00 1.00 2.57 13.62 35.03
01.02.04.02.02 ACERO FY= 4200 KG/CM2 EN LOSAS ARMADAS kg 3,192.86
1.00 1.00 3,192.86
7/24/2019 5 Metrado p.t.a.r - 3
2/3
Proyecto:
Ubicacin:
LARGO ANCHO ALTO
AREA LONGITUD KG
"AMPLIACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO EN EL DISTRITO DE CASCAS"
LA LIBERTAD, GRAN CHIMU, CASCAS
TEM DESCRIPCIN UNID VECES
HOJA DE METRADOS
SUBTOTAL
TOTALCANT.MEDIDAS
01.02.04.03 COLUMNAS
01.02.04.03.01 CONCRETO F'C=245 KG/CM2 EN COLUMNAS m3 13.78
1.00 14.00 0.40 0.30 8.20 13.78
01.02.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 57.40
1.00 14.00 0.50 1.00 8.20 57.40
01.02.04.03.03 ACERO FY= 4200 KG/CM2 EN COLUMNAS kg 1,746.82
1.00 1.00 1,746.82
01.02.04.04 VIGAS
01.02.04.04.01 CONCRETO F'C=245 KG/CM2 EN VIGAS m3 16.69
VIGAS V-01 3.00 1.00 7.70 0.30 0.40 2.77
VIGAS V-02 2.00 1.00 11.60 0.30 0.40 2.78
VIGAS V-03 4.00 1.00 11.60 0.30 0.40 5.57
VIGAS V-04 4.00 1.00 11.60 0.30 0.40 5.57
01.02.04.04.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2
97.373.00 1.00 7.70 0.70 16.17
2.00 1.00 11.60 0.70 16.24
4.00 1.00 11.60 0.70 32.48
4.00 1.00 11.60 0.70 32.48
01.02.04.04.03 ACERO FY= 4200 KG/CM2 EN VIGAS kg 2,082.34
1.00 1.00 2,082.34
01.02.04.5 CAMARA DE SEDIMENTACION
' =. . . . .
A1 1.00 2.00 1.10 12.38 27.19
A2 1.00 2.00 1.30 12.38 32.18
01.02.04.05.02 ENCOFRADO Y DESENCOFRADO EN CAMARA DE SEDIMENTACION m2426.34
A1 1.00 2.00 7.94 12.38 196.59
A2 1.00 2.00 9.28 12.38 229.75
01.02.04.05.03 ACERO FY= 4200 KG/CM2 EN CAMARA DE SEDIMENTACION kg 4,170.48
1.00 1.00 4,170.48
01.02.05 REVOQUES Y ENLUCIDOS
01.02.05.01 TARRAJEO CON IMPERMEABILIZANTE 1:2 e=1.5CM m2 LONG 817.18
MUROS 1.00 1.00 AREA 38.96 7.84 305.45
LOSA 1.00 4.00 20.76 83.05
CUNETA 1.00 1.00 1.00 2.34 2.34
CAMARA DE SEDIMENTACION
1.00 2.00 17.22 12.38 426.34
01.02.05.02 SOLAQUEADO MEZCLA 1:4 m2 390.84
MUROS 1.00 1.00 AREA 38.96 7.84 305.45
LOSA 1.00 4.00 20.76 83.05
CUNETA 1.00 1.00 1.00 2.34 2.34
CAMARA DE SEDIMENTACION
01.02.06 INSTALACIONES SANITARIAS
01.02.06.01 TUBERIA PVC ISO 4435 DN=200mm INCLUIDO ANILLO Y PRUEBA m 47.74
1.00 4.00 11.94 47.74
01.02.06.02 UNION CORREDIZA PVC-UF DN=200mm und 6.00
1.00 6.00 6.00
01.02.06.03 ADAPTADOR UF-UR DN=160mm/250mm P/ CANASTILLA DE BRONCE und4.00
4.00
01.02.06.04 CODO PVC SAL SP 200"X45 und 6.00
6.00
01.02.06.05 YEE PVC-SAL DN=200mm und 8.00
8.00
01.02.06.06 VALVULA COMPUERTA DE FF UF DE DN=200mm und 4.00
7/24/2019 5 Metrado p.t.a.r - 3
3/3
Proyecto:
Ubicacin:
LARGO ANCHO ALTO
AREA LONGITUD KG
"AMPLIACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO EN EL DISTRITO DE CASCAS"
LA LIBERTAD, GRAN CHIMU, CASCAS
TEM DESCRIPCIN UNID VECES
HOJA DE METRADOS
SUBTOTAL
TOTALCANT.MEDIDAS
01.02.06.07 CANASTILLA DE BRONCE DN=250mm und 4.00
4.00
01.02.07 VARIOS
01.02.07.01 BAFLE DE MADERA TRATADA e=2" und 4.00
4
01.02.07.02 WATER STOP DE P.V.C. m 50.53
ESQUINAS 1 4 9.17
JUNTAS CONSTRUCCION 1 1 41.36
01.02.07.03 TAPA DE CONCRETO PRE-FABRICADA und 4.00
1.00 4.00 4.00
01.02.07.04 BARANDAS DE PROTECCION DE 1 " ML 14.25
1.00 14.25 14.25