Upload
saroj-manandhar
View
213
Download
0
Embed Size (px)
Citation preview
7/30/2019 ABC OQ Protocol
1/11
7/30/2019 ABC OQ Protocol
2/11
DJPL/7.5.2/F-5/R3
OPERATIONAL QUALIFICATION PROTOCOL OF
B.O.D. Incubator, Model no.: .Page of
TABLE OF CONTENT
1. Objective
2. Scope3. Responsibility
4. Procedure5. List of measuring devices in the instrument requiring calibration
6. List of standard apparatus and instruments required for performing calibration7. Calibration Record
8. List of attachments9. List of documents (SOPs/manual)
10. List of operators trained11. Acceptance Criteria For Operational Test
a. Test in normal conditionb. Test of worst case situation
12. Deviation Report13. Operational Qualification Report
Appendices
Performed by__________________________________________________ Date ____________________
Verified by ____________________________________________________ Date ____________________
7/30/2019 ABC OQ Protocol
3/11
DJPL/7.5.2/F-5/R3
OPERATIONAL QUALIFICATION PROTOCOL OF
B.O.D. Incubator, Model no.: .Page of
Name of equipment: B.O.D. Incubator Serial no.:
Equipment Identification no.: - Model No.:Manufacturer (Name & address)
Manufactured by ..
Purchase order No.:____________________________________________
Validation protocol no: _________________________________________
Location: Quality Control Department, Microbiology Testing Room
_____________________________________________________________________________________________
Protocol written by: .. Date _______________
Approval: ) Date _______________
.) Date _______________
..) Date _______________
.) Date _______________
. ) Date _______________
.) Date _______________
1. Objective: To determine that B.O. D. low temperature incubator, model no..) operatesaccording to its requirement, and to record all relevant information and data to demonstrate it functions as
expected_____________________________________________________________________________________________
2. Scope: To be performed at time of operation, modification or relocation as per SOP.
_____________________________________________________________________________________________
3. Responsibility:
1. Approving body as listed above will be responsible for approving the protocol prior to the beginning of the
qualification work.2. Qualification performers: Officers from the Engineering Department, Production Department where the
instrument is installed and QA Department. QA Assistant Officers can also be involved during machine
qualification.3. Qualification performers will observe the operation of instrument and collect and verify the test results.4. One of the qualification performers will initial in performed by and HOD QA shall initial in verified by.
5. Validation Manager will approve the OQ report.
Performed by__________________________________________________ Date ____________________
Verified by ____________________________________________________ Date ____________________
7/30/2019 ABC OQ Protocol
4/11
DJPL/7.5.2/F-5/R3
OPERATIONAL QUALIFICATION PROTOCOL OF
B.O.D. Incubator, Model no.: .Page of
4. Procedure:
1. Prepare a checklist for instrument functional test, its functional specification and critical operating
parameters.
2. Prepare and approve SOPs for operation and cleaning of the instrument.
3. Provide training to the operators for the systems ofinstrument and record it.
4. Have OQ protocol approved by the approving body.
5. Test and Record the calibration data for calibrating apparatus and instruments.
6. Measure and record the results of specific challenge to the instruments in worst condition where
appropriate.
7. Record any deviations to the instrument, its operation.
8. Prepare a Deviation Report including the justification of acceptance and impact on the function.
9. Prepare an OQ Report: This should include date of study initiated; completed; observations made;
problems encountered; completeness of information collected; summary of deviation report; results of
tests, location of original data other relevant information; and conclusions on the validity of the
installation.
10. Submit the report for review and approval.
Performed by__________________________________________________ Date ____________________
Verified by ____________________________________________________ Date ____________________
7/30/2019 ABC OQ Protocol
5/11
DJPL/7.5.2/F-5/R3
OPERATIONAL QUALIFICATION PROTOCOL OF
B.O.D. Incubator, Model no.: .Page of
5. List of measuring devices in the instrument requiring calibration.
Name of the monitoring devices
1. Programmable Digital Temperature Controller
2.
3.
4.
5.
6. List of standard apparatus and instruments required for performing calibration:
Name of the Apparatus/instruments Code no: Calibration validity
1. Digital Multi meter -
2. Ammeter -
3. Calibrated Thermometers -
4. Spirit Level -
5. -
7. Calibration Record
Name of the measuring devices Calibrated date Calibration methodAcceptable
Value/RangeObservation
(A/N)
Digital Multi meter NA Acceptable
Calibrated Thermometer(-0 to 360)oC Acceptable
Calibrated Thermometer(0 to 300)oC Acceptable
Note: A- Acceptable and N- Not acceptable
Deviations if any:_______________________________________________________________________________
_____________________________________________________________________________________________
Performed by__________________________________________________ Date ____________________
Verified by ____________________________________________________ Date ____________________
7/30/2019 ABC OQ Protocol
6/11
DJPL/7.5.2/F-5/R3
OPERATIONAL QUALIFICATION PROTOCOL OF
B.O.D. Incubator, Model no.: .Page of
8. List of attachments
Operating Instruction & Warrantee Card
_____________________________________________________
_____________________________________________________
9. List of documents (SOPs and/ or manual required for operation)
QC Sop no of B.O.D Incubator
10. List of operators trained
S. No. Name Sign Date
Deviations if any:_______________________________________________________________________________
_____________________________________________________________________________________________
Performed by__________________________________________________ Date ____________________
Verified by ____________________________________________________ Date ____________________
7/30/2019 ABC OQ Protocol
7/11
DJPL/7.5.2/F-5/R3
OPERATIONAL QUALIFICATION PROTOCOL OF
B.O.D. Incubator, Model no.: .Page of
11. Acceptance Criteria For Operational Test
a. Test in normal condition (if applicable):
S.NO. Operating CriteriaAcceptance
CriteriaPass/Fail Sign Date
1. Electrical Connection
2.
Switch on the main toggle at Switch ON position.
Rotate main heat switch knob.
3. Switch OFF the main toggle at off position
4. Press push button of PLC controller.
5.
Switch ON the mains and load the tray with materials at a
gap of 3 to 4 cm between two articles and the incubatorwall.
Set the temperature (SV) and record the temperature shownin (PV) display.
6. Fluorescence lamp
Deviations if any:______________________________________________________________________________
_____________________________________________________________________________________________
Performed by__________________________________________________ Date ____________________
Verified by ___________________________________________________ Date ____________________
7/30/2019 ABC OQ Protocol
8/11
DJPL/7.5.2/F-5/R3
OPERATIONAL QUALIFICATION PROTOCOL OF
B.O.D. Incubator, Model no.: .Page of
b. Test of worst case situation (if applicable):
Tests ResultsStatus
Pass/FailSign Date
_________________________________________________________________________________________________
Deviations:____________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
Performed by: ______________________________________________________ Date :____________________
Verified by:________________________________________________________ Date: ____________________
7/30/2019 ABC OQ Protocol
9/11
DJPL/7.5.2/F-5/R3
OPERATIONAL QUALIFICATION PROTOCOL OF
B.O.D. Incubator, Model no.: .Page of
12. Deviation Report
Report written by: _____________________________________________________ Date ___________________
Verified by: __________________________________________________________ Date ___________________
7/30/2019 ABC OQ Protocol
10/11
DJPL/7.5.2/F-5/R3
OPERATIONAL QUALIFICATION PROTOCOL OF
B.O.D. Incubator, Model no.: .Page of
13. Operation Qualification Report
Report Written by: __________________ QA, Asst. Officer Date:_____________________
Report Reviewed by: ___________________ HOD QA Date:_____________________
___________________ HOD Engineering Date:_____________________
___________________ HOD QC Date:_____________________
___________________ PMD Manager Date:_____________________
___________________ QMD Manager Date:_____________________
Report Approved by: __________________ VP-Technical Affairs Date:_____________________
7/30/2019 ABC OQ Protocol
11/11
DJPL/7.5.2/F-5/R3
OPERATIONAL QUALIFICATION PROTOCOL OF
B.O.D. Incubator, Model no.: .Page of
APPENDICES