RELACION DE MATERIALESMINISTERIO DE EDUCACION
INSTITUCIONES EDUCATIVAS: RED YATIQAÑA
FECHA : 2012
MANO DE OBRA
TOPOGRAFO hh S/. 16.08
OPERARIO hh S/. 16.08
OFICIAL hh S/. 13.79
PEON hh S/. 12.43
MATERIALES
BOLSA DE YESO DE 25 KG bls S/. 8.50
OCRE ROJO kg S/. 10.50
AGUA m3 S/. 13.00
CLAVOS kg S/. 5.80
AFIRMADO m3 S/. 35.20
CEMENTO PORTLAND TIPO I (42.5 kg) bls S/. 19.65
ACERO CORRUGADO FY=4200KG/CM2 kg S/. 4.60
LADRILLO KING KONG DE ARCILLA 18 HUECOS HECHO A MAQUINA 9 X 14 X 24 cm und S/. 1.30
BLOQUE DE CONCRETO 20 X 20 X 40 cm und S/. 2.30
ARENA FINA m3 S/. 45.50
ARENA GRUESA m3 S/. 42.30
MADERA TORNILLO p2 S/. 5.95
CLAVOS PARA MADERA CON CABEZA DE 2" A 4" kg S/. 4.00
CLAVOS PARA MADERA CON CABEZA DE 2" kg S/. 4.00
CLAVOS PARA MADERA CON CABEZA DE 4" kg S/. 4.00
PIEDRA ZARANDEADA 1/2" m3 S/. 51.00
PIEDRA ZARANDEADA 1/4" m3 S/. 55.00
HORMIGON m3 S/. 30.00
PIEDRA GRANDE 8" m3 S/. 30.00
PIEDRA MEDIANA 4" m3 S/. 30.00
PIEDRA GRANDE m3 S/. 30.00
COMBUSTIBLE (GASOLINA) gln S/. 11.10
ADITIVO CURADO QUIMICO gln S/. 48.00
ALAMBRE N° 16 kg S/. 3.81
ALAMBRE N° 8 kg S/. 3.81
ASFALTO m3 S/. 30.00
GRASS bls S/. 10.17
TIERRA DE CHACRA m3 S/. 17.00
PINTURA ESMALTE SINTETICO EN GALON und S/. 30.00
PINTURA ESMALTE SINTETICO ANTICORROSIVO EN GALON und S/. 33.00
PLANCHA NEGRA LAF 0.50X920X2400mm und S/. 125.30
TRIPLAY 6mm m2 S/. 12.00
PERNO INC. TUERCA 3/4"X6" und S/. 3.20
PLANTONES und S/. 15.00
JUEGOS INFANTILES METALICOS und S/. 1,250.00
ANGULO FIERRO NEGRO 1"X1"X3/16"X6m und S/. 22.44
PUNTO AZUL E-6011 1/8" 25 Kg kg S/. 13.50
TUBO ACERO NEGRO ELECTROSOLDADO REDONDO 2"X2mmX6m und S/. 68.00
MALLA GALVANIZADA DE #10 DE 2"x2" m2 S/. 19.00
TANQUE ETERNIT 1.100 LT C/FILTRO INC. ACCESORIOS und S/. 415.51
ELECTROBOMBA DE 0.5HP und S/. 575.20
TUBERIA PVC SAP C-10 C/R 1'' ml S/. 2.47
TUBERIA PVC SAP C-10 C/R 3/4'' ml S/. 1.62
REDUCCION PVC SAP S/P 3/4"-1/2" und S/. 0.55
REDUCCION PVC SAP S/P 1"-3/4" und S/. 0.77
TEE DESAGUE SANITARIA 2" PVC und S/. 3.75
CINTA TEFLON DE MEDIA und S/. 2.00
NIPLE F°G° 1/2" x 1½" und S/. 1.50
VALVULA ESFERICA REDGAL CIM. 1/2" und S/. 17.50
VALVULA CHECK SWING 1/2" und S/. 43.63
CODOS PVC SP 1/2"x90° und S/. 1.10
ADAPTADOR PVC PR 1/2" und S/. 1.25
REDUCC. CAMP GALV 3/4"x1/2" und S/. 2.38
UNION PVC R 3/4" PU und S/. 1.63
REDUCC. PVC-P 3/4"x1/2" C/R und S/. 0.88
PEGAMENTO PVC 32 ONZ. und S/. 28.13
FORMADOR DE EMPAQUETADURAS 3-H und S/. 7.75
TEE DESAGUE 4"x2" PVC und S/. 5.63
SOMBRERO DE VENTILACION DESAGUE 2" PVC und S/. 5.63
CODO DESAGUE 2"x90° PVC und S/. 1.50
CODO DESAGUE 2"x45° PVC und S/. 1.50
TUBO DESAGUE 2"x 3m. PVC und S/. 10.25
CONSTRUCCION DE ALMACEN, CAMPAMENTO Y OFICINA PROVISIONAL glb S/. 5,000.00
VALV.PASO TERMOP. C/NIPLE TELESCOPICO und S/. 21.00
VALV.PASO TERMOP. C/SAL. AUX. 15N und S/. 16.56
UNION PRESION ROSCA 1/2" und S/. 0.60
NIPLE REEMPLAZO MEDIDOR 3/4" und S/. 2.14
CAJA DE REGISTRO DE CONCRETO PARA AGUA (INC. CUERPO Y SOLADO) und S/. 35.30
CAJA DE CONCRETO PARA REGISTRO DE DESAGUE (INC. BASE, INTERMEDIO,MARCO Y TAPA) und S/. 42.50
BIODIGESTOR AUTOLIMPIABLE 1300LT, INC. ACCESORIOS und S/. 1,395.25
BIODIGESTOR AUTOLIMPIABLE 3000LT, INC. ACCESORIOS und S/. 4,796.30
RED INTERNA DE AGUA HASTA 25m. glb S/. 1,000.00
RED INTERNA DE DESAGUE HASTA 25m. glb S/. 2,000.00
RED INTERNA DE AGUA HASTA 50m. glb S/. 2,000.00
RED INTERNA DE DESAGUE HASTA 50m. glb S/. 4,000.00
RED INTERNA DE AGUA HASTA 80m. glb S/. 3,200.00
RED INTERNA DE DESAGUE HASTA 80m. glb S/. 6,400.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 01 AULA A MAS DE 3600msnm glb S/. 3,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 02 AULAS A MAS DE 3600msnm glb S/. 6,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 05 AULAS A MAS DE 3600msnm glb S/. 15,000.00
EQUIPOS
NIVEL TOPOGRAFICO hm S/. 3.00
MIRA TOPOGRAFICA hm S/. 0.50
CAMION VOLQUETE 12M3 hm S/. 77.00
CARGADOR FRONTAL 200HP hm S/. 150.00
ANDAMIO METAL TABLAS ALQUILER d S/. 9.00
VIBRADOR DE CONCRETO 4 HP 2.5" hm S/. 6.60
MEZCLADORA DE CONCRETO 12 P3 hm S/. 7.00
COMPACTADOR VIBRATORIO TIPO PLANCHA 5.8 HP hm S/. 6.00
CARTEL DE OBRA DE 3.60 X 2.40 und S/. 900.00
BOLETINES INFORMATIVOS glb S/. 480.00
LETRINA SANITARIA INC. SERV MANTENIMIENTO und S/. 3,000.00
CONTENEDORES DE RESIDUOS SOLIDOS und S/. 150.00
LETREROS INFORMATIVOS PREVENTIVOS Y DE REGLAMENTACION und S/. 800.00
MITIGACION DE IMPACTO AMBIENTAL DURANTE LA EJECUCION
FLETE TERRESTRE P/TRANSPORTE DE MATERIALES glb S/. 9,000.00
FLETE TERRESTRE P/TRANSPORTE DE MATERIALES glb S/. 10,000.00
SUBCONTRATO
SC. REGILLA METALICA BORDE DE ANGULOS1"X1" Y PLATINA 1" A=0.30m ml S/. 180.00
SC CORTE DE ROCA CON MAQUINARIA PESADA hm S/. 300.00
SC. ELABORACION JUEGOS INFANTILES METALICOS und S/. 1,250.00
SC. TRANSPORTE DE JUEGOS INFANTILES vje S/. 500.00
SC. M.O. COLOCACION DE MALLA GALVANIZADA m2 S/. 30.00
SC. COLOCACION DE REJA METALICA m2 S/. 67.80
SC. ELABORACION Y COLOCACION PUERTA METALICA 2.65X3.00 und S/. 4,770.00
SC. ELABORACION Y COLOCACION PUERTA METALICA 0.90X3.00 und S/. 1,620.00
SC. INSTALACION Y COLOC. POZO A TIERRA Y PARARRAYOS glb S/. 3,000.00
SC. M.O. ELABORACION E INSTALACION DE ARMAZON METALICO DE 1.00mX1.00m Y H=3.00m glb S/. 720.00
SC. PRUEBA DE CALIDAD DE CONCRETO A LA COMPRESION und S/. 25.50
SC. INSTALACION Y COLOC. DE 10 PANELES SOLARES FOTOVOLATICOS 100W und S/. 19,305.00
SUBPARTIDAS DE RAHABILITACION, REFACCION Y DEMOLICION
PINTADO DE MUROS m2 S/. 6.78
TARRAJEO DE MUROS m2 S/. 15.10
COLOCACION DE CERAMICO m2 S/. 47.30
DEMOLICION DE MODULO ESTRUCTURA EXSISTENTE m2 S/. 17.00
DEMOLICION DE CERCO PERIMETRICO ml S/. 7.50
PINTADO DE LOSA DEPORTIVA m2 S/. 2.00
PINTADO DE ARCOS METALICOS und S/. 60.00
DEMOLICION DE COLUMNETAS DE CONCRETO und S/. 7.50
DEMOLICION DE PORTICO DE INGRESO DE CONCRETO (EXISTENTE) und S/. 150.00
RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/. 35.22
COLOCACION PUERTA METALICA PARA VIVIENDA DOCENTE und S/. 750.50
ANALISIS DE PRECIOS UNITARIOS
PARTIDAS
CONSTRUCCION DE ALMACEN, CAMPAMENTO Y OFICINA PROVISIONAL glb S/. 5,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 5,000.00
CONSTRUCCION DE ALMACEN, CAMPAMENTO Y OFICINA PROVISIONAL glb 1.0000 S/. 5,000.00 S/. 5,000.00
CARTEL DE IDENTIFICACION DE OBRA 3.60X2.40m und S/. 1,667.46
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 309.20
OFICIAL hh 1.000 8.0000 S/. 13.79 S/. 110.32
PEON hh 2.000 16.0000 S/. 12.43 S/. 198.88
MATERIALES S/. 1,348.99
CEMENTO PORTLAND TIPO I (42.5 kg) bls 0.9000 S/. 19.65 S/. 17.69
CARTEL DE OBRA DE 3.60 X 2.40 und 1.00 S/. 900.00 S/. 900.00
CLAVOS PARA MADERA CON CABEZA DE 2" kg 1.0000 S/. 4.00 S/. 4.00
HORMIGON m3 0.3600 S/. 30.00 S/. 10.80
MADERA TORNILLO p2 70.0000 S/. 5.95 S/. 416.50
EQUIPOS Y HERRAMIENTAS S/. 9.28
HERRAMIENTAS MANUALES %M.O. %mo 3.0000 S/. 3.09 S/. 9.28
PUERTA PRINCIPAL DE INGRESO METALICA L=4.00m INC. PORTICO DE C.A. Y MURO DE BLOQUES DE C° L=13.66m und S/. 15,034.52
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 15,034.52
EXCAVACION ZANJA PARA CIMENTACION m3 9.7200 S/. 34.14 S/. 331.84
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 7.2900 S/. 208.80 S/. 1,522.15
CONCRETO 1:8+25%PM SOBRECIMIENTO m3 0.6120 S/. 292.11 S/. 178.77
CORTE Y HABILITACION DE ACERO CORRUGADO FY=4200kg/cm2 kg 363.3553 S/. 5.72 S/. 2,078.39
CONCRETO F'c = 175 Kg/cm2 COLUMNAS m3 0.3065 S/. 414.72 S/. 127.11
CONCRETO F'c = 175 Kg/cm2 VIGAS m3 0.3600 S/. 377.90 S/. 136.04
CONCRETO F'c = 175 Kg/cm2 LOSA MACIZA m3 0.7680 S/. 377.90 S/. 290.23
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 34.2600 S/. 56.62 S/. 1,939.80
MURO DE SOGA CON BLOQUES DE CONCRETO 20x20x40 m2 26.5200 S/. 76.93 S/. 2,040.18
SC. ELAVORACION Y COLOCACION PUERTA METALICA 2.65X3.00 und 1.0000 S/. 4,770.00 S/. 4,770.00
SC. ELAVORACION Y COLOCACION PUERTA METALICA 0.90X3.00 und 1.0000 S/. 1,620.00 S/. 1,620.00
INST. Y COLOC. POZO A TIERRA Y PARARRAYOS und S/. 3,000.00
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 3,000.00
SC. INSTALACION Y COLOC. POZO A TIERRA Y PARARRAYOS glb 1.0000 S/. 3,000.00 S/. 3,000.00
SC. INSTALACION Y COLOC. DE 10 PANELES SOLARES FOTOVOLATICOS 100W glb S/. 19,305.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 19,305.00
SC. INSTALACION Y COLOC. DE 10 PANELES SOLARES FOTOVOLATICOS 100W und 1.0000 S/. 19,305.00 S/. 19,305.00
INST. Y COLOC. DE TANQUE DE POLIETILENO DE AGUA 1100 lt. SOBRE ARMAZON METALICO H=3.00 und S/. 1,564.62
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 1,564.62
EXCAVACION ZANJA PARA CIMENTACION m3 0.5120 S/. 34.14 S/. 17.48
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.3200 S/. 56.62 S/. 18.12
CONCRETO SIMPLE 1:8+25%PM PARA DADOS DE CIMENTACION 0.40X0.40 m3 0.1600 S/. 292.11 S/. 46.74
ELABORAC. Y COLOC. DE ARMAZON METALICO PARA TANQUE DE POLIETILENO DE H=3.00 und 1.0000 S/. 834.71 S/. 834.71
INST. Y COLOC. DE TANQUE DE POLIETILENO DE AGUA 1100 lt. und 1.0000 S/. 647.57 S/. 647.57
INST. Y COLOC. DE TANQUE CISTERNA DE POLIETILENO DE AGUA 1100 lt. INC. ELECTROBOMBA DE 0.5HP und S/. 1,612.32
REND 3 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 142.32
OPERARIO hh 1.000 2.6667 S/. 16.08 S/. 42.88
PEON hh 3.000 8.0000 S/. 12.43 S/. 99.44
MATERIALES S/. 1,465.73
TANQUE ETERNIT 1.100 LT C/FILTRO INC. ACCESORIOS und 1.0000 S/. 415.51 S/. 415.51
ELECTROBOMBA DE 0.5HP und 1.0000 S/. 575.20 S/. 575.20
TUBERIA PVC SAP C-10 C/R 1'' ml 3.0000 S/. 2.47 S/. 7.41
TUBERIA PVC SAP C-10 C/R 3/4'' ml 18.0000 S/. 1.62 S/. 29.16
REDUCCION PVC SAP S/P 3/4"-1/2" und 3.0000 S/. 0.55 S/. 1.65
REDUCCION PVC SAP S/P 1"-3/4" und 2.0000 S/. 0.77 S/. 1.54
CINTA TEFLON DE MEDIA und 1.0000 S/. 2.00 S/. 2.00
LADRILLO KING KONG DE ARCILLA 18 HUECOS HECHO A MAQUINA 9 X 14 X 24 cm und 324.0000 S/. 1.30 S/. 421.20
ARENA FINA m3 0.2650 S/. 45.50 S/. 12.06
EQUIPOS Y HERRAMIENTAS S/. 4.27
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.42 S/. 4.27
CERCO PERIMETRICO CON BLOQUE DE CONCRETO CONFINADO H=3.00 m ml S/. 635.36
REND 1 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 635.36
EXCAVACION ZANJA PARA CIMENTACION m3 0.7200 S/. 34.14 S/. 24.58
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 0.5400 S/. 208.80 S/. 112.75
CONCRETO 1:8+25%PM SOBRECIMIENTO m3 0.0800 S/. 292.11 S/. 23.37
CORTE Y HABILITACION DE ACERO CORRUGADO FY=4200kg/cm2 kg 14.8679 S/. 5.72 S/. 85.04
CONCRETO F'c = 175 Kg/cm2 COLUMNAS m3 0.0370 S/. 414.72 S/. 15.34
CONCRETO F'c = 175 Kg/cm2 VIGAS m3 0.1800 S/. 377.90 S/. 68.02
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 2.0800 S/. 56.62 S/. 117.77
MURO DE SOGA CON BLOQUES DE CONCRETO 20x20x40 m2 2.4500 S/. 76.93 S/. 188.48
CERCO PERIMETRICO DE PAÑOS MIXTOS CON BLOQUE DE CONCRETO CONFINADO Y REJA METALICA H=3.00 m ml S/. 632.90
REND 1 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 632.90
EXCAVACION ZANJA PARA CIMENTACION m3 0.7200 S/. 34.14 S/. 24.58
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 0.5400 S/. 208.80 S/. 112.75
CONCRETO 1:8+25%PM SOBRECIMIENTO m3 0.0800 S/. 292.11 S/. 23.37
CORTE Y HABILITACION DE ACERO CORRUGADO FY=4200kg/cm2 kg 14.8679 S/. 5.72 S/. 85.04
CONCRETO F'c = 175 Kg/cm2 COLUMNAS m3 0.0370 S/. 414.72 S/. 15.34
CONCRETO F'c = 175 Kg/cm2 VIGAS m3 0.1800 S/. 377.90 S/. 68.02
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 2.0800 S/. 56.62 S/. 117.77
MURO DE SOGA CON BLOQUES DE CONCRETO 20x20x40 m2 2.1800 S/. 76.93 S/. 167.71
COLOCACION DE REJA METALICA m2 0.2700 S/. 67.80 S/. 18.31
VEREDAS DE CONCRETO 140Kg/cm2, E= 4" m2 S/. 85.32
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 85.32
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 0.15 S/. 41.21 S/. 6.18
CONFORMACION DE BASE AFIRMADA EN VEREDAS H=0.10 m2 1.00 S/. 15.71 S/. 15.71
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.40 S/. 56.62 S/. 22.65
CONCRETO PARA VEREDAS F'=140KG/CM2 , e=4" m2 1.20 S/. 33.98 S/. 40.78
PATIO DE CONCRETO FROTACHADO Y BRUÑADO ml S/. 74.10
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 74.10
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 0.15 S/. 41.21 S/. 6.18
CONFORMACION DE BASE AFIRMADA EN VEREDAS H=0.10 m2 1.00 S/. 15.71 S/. 15.71
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.28 S/. 56.62 S/. 15.85
PISO CEMENTO FROTACHADO Y BRUÑADO E=4" m2 1.07 S/. 33.98 S/. 36.36
JUNTA DE DILATACION e=1" ml 1.33 S/. 1.99 S/. 2.65
LOSA DE CONCRETO FROTACHADO Y BRUÑADO m2 S/. 74.10
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 74.10
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 0.15 S/. 41.21 S/. 6.18
CONFORMACION DE BASE AFIRMADA EN VEREDAS H=0.10 m2 1.00 S/. 15.71 S/. 15.71
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.28 S/. 56.62 S/. 15.85
PISO CEMENTO FROTACHADO Y BRUÑADO E=4" m2 1.07 S/. 33.98 S/. 36.36
JUNTA DE DILATACION e=1" ml 1.33 S/. 1.99 S/. 2.65
CUNETA 0.30X0.30 PARA DRENAJE PLUVIAL INC. REG. METALICA ANCHO 0.30m ml S/. 272.40
REND 1 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 272.40
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 0.03 S/. 41.21 S/. 1.24
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.95 S/. 56.62 S/. 53.79
REGILLA METALICA BORDE DE ANGULOS1"X1" Y PLATINA 1" A=0.30m ml 1.00 S/. 180.00 S/. 180.00
CONCRETO CANALETA DE DRENAJE PLUVIAL INC. REGILLA METALICA m2 1.10 S/. 33.98 S/. 37.38
RAMPAS DE CONCRETO 140Kg/cm2, E= 4" m2 S/. 85.32
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 85.32
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 0.15 S/. 41.21 S/. 6.18
CONFORMACION DE BASE AFIRMADA EN VEREDAS H=0.10 m2 1.00 S/. 15.71 S/. 15.71
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.40 S/. 56.62 S/. 22.65
PISO CEMENTO FROTACHADO Y BRUÑADO E=4" m2 1.20 S/. 33.98 S/. 40.78
MURO DE CONTENCION CºCº H=0.80m ml S/. 500.97
REND 1 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 500.97
EXCAVACION ZANJA PARA CIMENTACION m3 0.9000 S/. 34.14 S/. 30.73
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 0.9000 S/. 208.80 S/. 187.92
CONCRETO 1:8+25%PM MURO DE CONTENCION m3 0.4000 S/. 309.46 S/. 123.78
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 2.8000 S/. 56.62 S/. 158.54
MURO DE MAMPOSTERIA DE PIEDRA H=0.80 ml S/. 500.97
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 500.97
EXCAVACION ZANJA PARA CIMENTACION m3 0.9000 S/. 34.14 S/. 30.73
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 0.9000 S/. 208.80 S/. 187.92
CONCRETO 1:8+25%PM MURO DE CONTENCION m3 0.4000 S/. 309.46 S/. 123.78
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 2.8000 S/. 56.62 S/. 158.54
MURO DE CONTENCION CºCº H=2.00m ml S/. 1,106.09
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 1,106.09
EXCAVACION ZANJA PARA CIMENTACION m3 1.8000 S/. 34.14 S/. 61.45
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 1.8000 S/. 208.80 S/. 375.84
CONCRETO 1:8+25%PM MURO DE CONTENCION m3 1.1000 S/. 309.46 S/. 340.41
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 5.8000 S/. 56.62 S/. 328.40
MURO DE CONTENCION DE PIRCA DE PIEDRA H=1.20 ml S/. 214.00
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 214.00
MURO DE PIRCA DE PIEDRA H=1.20 m2 1.200 S/. 161.62 S/. 193.94
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.300 S/. 56.62 S/. 16.99
EXCAVACION ZANJA PARA CIMENTACION m3 0.090 S/. 34.14 S/. 3.07
CERCO DE PIRCA DE PIEDRA A=0.50m, H=0.80m ml S/. 207.85
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 207.85
MURO DE PIRCA DE PIEDRA H=0.80 m2 1.2000 S/. 156.49 S/. 187.79
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.3000 S/. 56.62 S/. 16.99
EXCAVACION ZANJA PARA CIMENTACION m3 0.0900 S/. 34.14 S/. 3.07
PLAN DE MANEJO AMBIENTAL DURANTE LA EJECUCION und S/. 7,880.00
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 7,880.00
BOLETINES INFORMATIVOS glb 1.000 S/. 480.00 S/. 480.00
LETRINA SANITARIA INC. SERV MANTENIMIENTO und 2.000 S/. 3,000.00 S/. 6,000.00
CONTENEDORES DE RESIDUOS SOLIDOS und 4.000 S/. 150.00 S/. 600.00
LETREROS INFORMATIVOS PREVENTIVOS Y DE REGLAMENTACION und 1.000 S/. 800.00 S/. 800.00
PATIO DE JUEGOS AREA=118.26m2 INC. SARDINEL DE CONCRETO 0.10X0.30m Y 04 UNID DE JUEGOS METALICOS und S/. 7,373.87
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 1,873.87
SARDINEL DE CONCRETO 0.10X0.30m ml 43.7000 S/. 20.34 S/. 888.86
ACARREO, COLOCACION Y TENDIDO DE PIEDRA CONFITILLO PARA JUEGOS INFANTILES m2 110.8000 S/. 8.89 S/. 985.01
SUBCONTRATO S/. 5,500.00
SC. ELABORACION JUEGOS INFANTILES METALICOS und 4.0000 S/. 1,250.00 S/. 5,000.00
SC. TRANSPORTE DE JUEGOS INFANTILES vje 1.0000 S/. 500.00 S/. 500.00
PRUEBAS DE CALIDAD DE CONCRETO (PRUEBA A LA COMPRESION) und S/. 25.50
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 25.50
SC. PRUEBA DE CALIDAD DE CONCRETO A LA COMPRESION und 1.0000 S/. 25.50 S/. 25.50
COLOCACION CAJA REGISTRO Y CONECCION A RED DE AGUA und S/. 104.21
REND 10 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 27.78
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 1.500 1.2000 S/. 12.43 S/. 14.92
MATERIALES S/. 75.60
VALV.PASO TERMOP. C/NIPLE TELESCOPICO und 1.0000 S/. 21.00 S/. 21.00
VALV.PASO TERMOP. C/SAL. AUX. 15N und 1.0000 S/. 16.56 S/. 16.56
UNION PRESION ROSCA 1/2" und 1.0000 S/. 0.60 S/. 0.60
NIPLE REEMPLAZO MEDIDOR 3/4" und 1.0000 S/. 2.14 S/. 2.14
CAJA DE REGISTRO DE CONCRETO PARA AGUA (INC. CUERPO Y SOLADO) und 1.0000 S/. 35.30 S/. 35.30
EQUIPOS Y HERRAMIENTAS S/. 0.83
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.28 S/. 0.83
COLOCACION CAJA REGISTRO Y CONECCION A BIODIGESTOR und S/. 71.11
REND 10 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 27.78
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 1.500 1.2000 S/. 12.43 S/. 14.92
MATERIALES S/. 42.50
CAJA DE CONCRETO PARA REGISTRO DE DESAGUE (INC. BASE, INTERMEDIO,MARCO Y TAPA) und 1.0000 S/. 42.50 S/. 42.50
EQUIPOS Y HERRAMIENTAS S/. 0.83
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.28 S/. 0.83
INSTALACION Y COLOCACION DE BIODIGESTOR AUTOLIMPIABLE 1300LT, INC. ACCESORIOS und S/. 1,663.46
REND 2 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 213.48
OPERARIO hh 1.000 4.0000 S/. 16.08 S/. 64.32
PEON hh 3.000 12.0000 S/. 12.43 S/. 149.16
MATERIALES S/. 1,443.57
BIODIGESTOR AUTOLIMPIABLE 1300LT, INC. ACCESORIOS und 1.0000 S/. 1,395.25 S/. 1,395.25
ARENA FINA m3 1.0620 S/. 45.50 S/. 48.32
EQUIPOS Y HERRAMIENTAS S/. 6.40
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 2.13 S/. 6.40
INSTALACION Y COLOCACION DE BIODIGESTOR AUTOLIMPIABLE 3000LT, INC. ACCESORIOS und S/. 5,064.51
REND 2 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 213.48
OPERARIO hh 1.000 4.0000 S/. 16.08 S/. 64.32
PEON hh 3.000 12.0000 S/. 12.43 S/. 149.16
MATERIALES S/. 4,844.62
BIODIGESTOR AUTOLIMPIABLE 3000LT, INC. ACCESORIOS und 1.0000 S/. 4,796.30 S/. 4,796.30
ARENA FINA m3 1.0620 S/. 45.50 S/. 48.32
EQUIPOS Y HERRAMIENTAS S/. 6.40
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 2.13 S/. 6.40
CONSTRUCCION DE CERCO PERIMETRICO DE ADOBE H=1.80m ml S/. 180.73
REND 3 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 175.47
OPERARIO hh 1.000 2.6667 S/. 16.08 S/. 42.88
PEON hh 4.000 10.6667 S/. 12.43 S/. 132.59
EQUIPOS Y HERRAMIENTAS S/. 5.26
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.75 S/. 5.26
CONSTRUCCION DE CERCO PERIMETRICO DE TAPIAL H=1.50m ml S/. 54.22
REND 10 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 52.64
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 4.000 3.2000 S/. 12.43 S/. 39.78
EQUIPOS Y HERRAMIENTAS S/. 1.58
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.53 S/. 1.58
REHABILITACION DE CERCO PERIMETRICO DE ADOBE H=1.80m ml S/. 45.18
REND 8 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 45.18
CONSTRUCCION DE CERCO PERIMETRICO DE ADOBE H=1.80m ml 0.25 S/. 180.73 S/. 45.18
REHABILITACION DE CERCO PERIMETRICO DE TAPIAL H=1.50m ml S/. 13.56
REND 8 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 13.56
CONSTRUCCION DE CERCO PERIMETRICO DE TAPIAL H=1.50m ml 0.25 S/. 54.22 S/. 13.56
REHABILITACION DE LOSA DEPORTIVA EXISTENTE DE C° f'c=140kg/cm2 e=4" m2 S/. 49.83
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 49.83
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.28 S/. 56.62 S/. 15.85
PISO CEMENTO FROTACHADO Y BRUÑADO E=4" m2 1.00 S/. 33.98 S/. 33.98
JUNTA DE DILATACION e=1" ml 1.33 S/. 1.99 S/. 2.65
REHABILITACION DE LOSA DEPORTIVA Y ARCOS METALICOS EXISTENTE : PINTADO m2 S/. 2.90
REND 8 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 2.90
PINTADO DE LOSA DEPORTIVA m2 1.0000 S/. 2.00 S/. 2.00
PINTADO DE ARCOS METALICOS und 0.0150 S/. 60.00 S/. 0.90
DESMONTAJE DE PUERTA TIPO REJA Y DEMOLICION DE COLUMNETAS DE CONCRETO und S/. 48.73
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 48.73
DESMONTAJE DE PUERTA TIPO REJA m2 1.0000 S/. 33.73 S/. 33.73
DEMOLICION DE COLUMNETAS DE CONCRETO und 2.0000 S/. 7.50 S/. 15.00
DEMOLICION DE VEREDAS m2 S/. 16.39
REND 25 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 15.91
PEON hh 4.000 1.2800 S/. 12.43 S/. 15.91
EQUIPOS Y HERRAMIENTAS S/. 0.48
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.16 S/. 0.48
DEMOLICION DE COLUMNETAS DE CONCRETO und S/. 7.50
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 7.50
DEMOLICION DE COLUMNETAS DE CONCRETO und 1.00 S/. 7.50 S/. 7.50
DEMOLICION DE PORTICO DE INGRESO DE CONCRETO (EXISTENTE) und S/. 150.00
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 150.00
DEMOLICION DE PORTICO DE INGRESO DE CONCRETO (EXISTENTE) und 1.00 S/. 150.00 S/. 150.00
DEMOLICION MODULO m2 S/. 17.00
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 17.00
DEMOLICION DE MODULO ESTRUCTURA EXSISTENTE ml 1.00 S/. 17.00 S/. 17.00
DEMOLICION DE CERCO PERIMETRICO ml S/. 7.50
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 7.50
DEMOLICION DE CERCO PERIMETRICO ml 1.00 S/. 7.50 S/. 7.50
RED INTERNA DE AGUA HASTA 25m. glb S/. 1,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 1,000.00
RED INTERNA DE AGUA HASTA 25m. glb 1.0000 S/. 1,000.00 S/. 1,000.00
RED INTERNA DE DESAGUE HASTA 25m. glb S/. 2,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 2,000.00
RED INTERNA DE DESAGUE HASTA 25m. glb 1.0000 S/. 2,000.00 S/. 2,000.00
RED INTERNA DE AGUA HASTA 50m. glb S/. 2,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 2,000.00
RED INTERNA DE AGUA HASTA 50m. glb 1.0000 S/. 2,000.00 S/. 2,000.00
RED INTERNA DE DESAGUE HASTA 50m. glb S/. 4,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 4,000.00
RED INTERNA DE DESAGUE HASTA 50m. glb 1.0000 S/. 4,000.00 S/. 4,000.00
RED INTERNA DE AGUA HASTA 80m. glb S/. 3,200.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 3,200.00
RED INTERNA DE AGUA HASTA 80m. glb 1.0000 S/. 3,200.00 S/. 3,200.00
RED INTERNA DE DESAGUE HASTA 80m. glb S/. 6,400.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 6,400.00
RED INTERNA DE DESAGUE HASTA 80m. glb 1.0000 S/. 6,400.00 S/. 6,400.00
REFACCION MODULO A EXISTENTE :PINTADO DE MUROS,TARRAJEADO MUROS, COLOCACION DE CERAMICO m2 S/. 78.56
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 78.56
PINTADO DE MUROS m2 2.8000 S/. 6.78 S/. 18.98
TARRAJEO DE MUROS m2 0.5000 S/. 15.10 S/. 7.55
COLOCACION DE CERAMICO m2 1.1000 S/. 47.30 S/. 52.03
REFACCION MODULO A EXISTENTE :PINTADO DE MUROS,TARRAJEADO MUROS m2 S/. 26.53
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 26.53
PINTADO DE MUROS m2 2.8000 S/. 6.78 S/. 18.98
TARRAJEO DE MUROS m2 0.5000 S/. 15.10 S/. 7.55
REFACCION MODULO B EXISTENTE :PINTADO DE MUROS,TARRAJEADO MUROS m2 S/. 26.53
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 26.53
PINTADO DE MUROS m2 2.8000 S/. 6.78 S/. 18.98
TARRAJEO DE MUROS m2 0.5000 S/. 15.10 S/. 7.55
REFACCION MODULO C EXISTENTE :PINTADO DE MUROS,TARRAJEADO MUROS m2 S/. 26.53
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 26.53
PINTADO DE MUROS m2 2.8000 S/. 6.78 S/. 18.98
TARRAJEO DE MUROS m2 0.5000 S/. 15.10 S/. 7.55
ACONDICIONAMIENTO BIOCLIMATICO PARA 01 AULA A MAS DE 3600msnm glb S/. 3,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 3,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 01 AULA A MAS DE 3600msnm glb 1.0000 S/. 3,000.00 S/. 3,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 02 AULAS A MAS DE 3600msnm glb S/. 6,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 6,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 02 AULAS A MAS DE 3600msnm glb 1.0000 S/. 6,000.00 S/. 6,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 05 AULAS A MAS DE 3600msnm glb S/. 15,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 15,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 02 AULAS A MAS DE 3600msnm glb 1.0000 S/. 15,000.00 S/. 15,000.00
RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/. 35.22
REND 1 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDA S/. 35.22
RELLENO COMPACTADO CON MATERIAL PROPIO m3 1.0000 S/. 35.22 S/. 35.22
COLOCACION PUERTA METALICA PARA VIVIENDA DOCENTE und S/. 750.50
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 750.50
PINTADO DE MUROS und 1.0000 S/. 750.50 S/. 750.50
REHABILITACION DE CERCO PERIMETRICO CON BLOQUES DE CONCRETO 20x20x40 : CIERRE DE VANOS m2 S/. 70.53
REND 8 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 22.29
OPERARIO hh 1.000 1.0000 S/. 16.08 S/. 16.08
PEON hh 0.500 0.5000 S/. 12.43 S/. 6.22
MATERIALES S/. 38.57
CEMENTO PORTLAND TIPO I (42.5 kg) bls 0.5200 S/. 19.65 S/. 10.22
BLOQUE DE CONCRETO 20 X 20 X 40 cm und 11.0000 S/. 2.30 S/. 25.30
ARENA GRUESA m3 0.0620 S/. 42.30 S/. 2.62
MADERA TORNILLO p2 0.0580 S/. 5.95 S/. 0.35
CLAVOS PARA MADERA CON CABEZA DE 2" A 4" kg 0.0200 S/. 4.00 S/. 0.08
EQUIPOS Y HERRAMIENTAS S/. 9.67
ANDAMIO METAL TABLAS ALQUILER d 1.0000 S/. 9.00 S/. 9.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.22 S/. 0.67
SUBPARTIDAS
EXCAVACION ZANJA PARA CIMENTACION m3 S/. 34.14
REND 3 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 33.15
PEON hh 1.000 2.6667 S/. 12.43 S/. 33.15
EQUIPOS Y HERRAMIENTAS S/. 0.99
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.33 S/. 0.99
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 S/. 41.21
REND 10 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 22.81
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 1.000 0.8000 S/. 12.43 S/. 9.94
MATERIALES S/. 17.71
AGUA m3 0.0126 S/. 13.00 S/. 0.16
MADERA TONILLO p2 2.9400 S/. 5.95 S/. 17.49
CLAVOS KG 0.0100 S/. 5.80 S/. 0.06
EQUIPOS Y HERRAMIENTAS S/. 0.68
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.23 S/. 0.68
CORTE Y HABILITACION DE ACERO CORRUGADO FY=4200kg/cm2 kg S/. 5.72
REND 400 kg/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 0.85
OPERARIO hh 1.000 0.0200 S/. 16.08 S/. 0.32
OFICIAL hh 1.000 0.0200 S/. 13.79 S/. 0.28
PEON hh 1.000 0.0200 S/. 12.43 S/. 0.25
MATERIALES S/. 4.85
ACERO CORRUGADO FY=4200KG/CM2 kg 1.0300 S/. 4.60 S/. 4.74
ALAMBRE N° 16 kg 0.0289 S/. 3.81 S/. 0.11
EQUIPOS Y HERRAMIENTAS S/. 0.03
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.01 S/. 0.03
INST. Y COLOC. DE TANQUE DE POLIETILENO DE AGUA 1100 lt. und S/. 647.57
REND 4 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 57.02
OPERARIO hh 1.000 2.0000 S/. 16.08 S/. 32.16
PEON hh 1.000 2.0000 S/. 12.43 S/. 24.86
MATERIALES S/. 588.84
TANQUE ETERNIT 1.100 LT C/FILTRO INC. ACCESORIOS und 1.0000 S/. 415.51 S/. 415.51
TEE DESAGUE SANITARIA 2" PVC und 1.0000 S/. 3.75 S/. 3.75
CINTA TEFLON DE MEDIA und 1.0000 S/. 2.00 S/. 2.00
NIPLE F°G° 1/2" x 1½" und 1.0000 S/. 1.50 S/. 1.50
VALVULA ESFERICA REDGAL CIM. 1/2" und 1.0000 S/. 17.50 S/. 17.50
VALVULA CHECK SWING 1/2" und 2.0000 S/. 43.63 S/. 87.26
CODOS PVC SP 1/2"x90° und 2.0000 S/. 1.10 S/. 2.20
ADAPTADOR PVC PR 1/2" und 6.0000 S/. 1.25 S/. 7.50
REDUCC. CAMP GALV 3/4"x1/2" und 1.0000 S/. 2.38 S/. 2.38
UNION PVC R 3/4" PU und 1.0000 S/. 1.63 S/. 1.63
REDUCC. PVC-P 3/4"x1/2" C/R und 1.0000 S/. 0.88 S/. 0.88
PEGAMENTO PVC 32 ONZ. und 0.2500 S/. 28.13 S/. 7.03
FORMADOR DE EMPAQUETADURAS 3-H und 0.2500 S/. 7.75 S/. 1.94
TEE DESAGUE 4"x2" PVC und 1.0000 S/. 5.63 S/. 5.63
SOMBRERO DE VENTILACION DESAGUE 2" PVC und 1.0000 S/. 5.63 S/. 5.63
CODO DESAGUE 2"x90° PVC und 3.0000 S/. 1.50 S/. 4.50
CODO DESAGUE 2"x45° PVC und 1.0000 S/. 1.50 S/. 1.50
TUBO DESAGUE 2"x 3m. PVC und 2.0000 S/. 10.25 S/. 20.50
EQUIPOS Y HERRAMIENTAS S/. 1.71
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.57 S/. 1.71
ELABORAC. Y COLOC. DE ARMAZON METALICO PARA TANQUE DE POLIETILENO DE H=3.00 und S/. 834.71
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 114.71
MADERA TORNILLO p2 16.4042 S/. 5.95 S/. 97.60
TUBO ACERO NEGRO ELECTROSOLDADO REDONDO 2"X2mmX6m und 0.2480 S/. 68.00 S/. 16.86
PUNTO AZUL E-6011 1/8" 25 Kg kg 0.0176 S/. 13.50 S/. 0.24
SUBCONTRATOS S/. 720.00
SC. M.O. ELABORACION E INSTALACION DE ARMAZON METALICO DE 1.00mX1.00m Y H=3.00m glb 1.0000 S/. 720.00 S/. 720.00
CONCRETO SIMPLE 1:8+25%PM PARA DADOS DE CIMENTACION 0.40X0.40 m3 S/. 292.11
REND 8 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 160.11
OPERARIO hh 3.000 3.0000 S/. 16.08 S/. 48.24
PEON hh 9.000 9.0000 S/. 12.43 S/. 111.87
MATERIALES S/. 120.19
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 3.8000 S/. 19.65 S/. 74.67
HORMIGON m3 0.8500 S/. 30.00 S/. 25.50
PIEDRA MEDIANA 4" m3 0.5000 S/. 30.00 S/. 15.00
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.0500 S/. 11.10 S/. 0.56
MADERA TORNILLO p2 0.0260 S/. 5.95 S/. 0.15
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 11.80
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 1.0000 S/. 7.00 S/. 7.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.60 S/. 4.80
MURO DE SOGA LADRILLO KK DE ARCILLA 18 HUECOS m2 S/. 96.01
REND 8 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 22.29
OPERARIO hh 1.000 1.0000 S/. 16.08 S/. 16.08
PEON hh 0.500 0.5000 S/. 12.43 S/. 6.22
MATERIALES S/. 64.05
CEMENTO PORTLAND TIPO I (42.5 kg) bls 0.2600 S/. 19.65 S/. 5.11
LADRILLO KING KONG DE ARCILLA 18 HUECOS HECHO A MAQUINA 9 X 14 X 24 cm und 44.0000 S/. 1.30 S/. 57.20
ARENA GRUESA m3 0.0310 S/. 42.30 S/. 1.31
MADERA TORNILLO p2 0.0580 S/. 5.95 S/. 0.35
CLAVOS PARA MADERA CON CABEZA DE 2" A 4" kg 0.0200 S/. 4.00 S/. 0.08
EQUIPOS Y HERRAMIENTAS S/. 9.67
ANDAMIO METAL TABLAS ALQUILER d 1.0000 S/. 9.00 S/. 9.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.22 S/. 0.67
MURO DE SOGA CON BLOQUES DE CONCRETO 20x20x40 m2 S/. 76.93
REND 8 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 28.51
OPERARIO hh 1.000 1.0000 S/. 16.08 S/. 16.08
PEON hh 1.000 1.0000 S/. 12.43 S/. 12.43
MATERIALES S/. 38.57
CEMENTO PORTLAND TIPO I (42.5 kg) bls 0.5200 S/. 19.65 S/. 10.22
BLOQUE DE CONCRETO 20 X 20 X 40 cm und 11.0000 S/. 2.30 S/. 25.30
ARENA GRUESA m3 0.0620 S/. 42.30 S/. 2.62
MADERA TORNILLO p2 0.0580 S/. 5.95 S/. 0.35
CLAVOS PARA MADERA CON CABEZA DE 2" A 4" kg 0.0200 S/. 4.00 S/. 0.08
EQUIPOS Y HERRAMIENTAS S/. 9.86
ANDAMIO METAL TABLAS ALQUILER d 1.0000 S/. 9.00 S/. 9.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.29 S/. 0.86
COLOCACION DE REJA METALICA m2 S/. 67.80
REND 20 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBCONTRATO S/. 67.80
SC. COLOCACION DE REJA METALICA m2 1.0000 S/. 67.80 S/. 67.80
m2 S/. 62.29
REND 20 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 32.29
MALLA GALVANIZADA DE #10 DE 2"x2" m2 0.7994 S/. 19.00 S/. 15.19
PUNTO AZUL E-6011 1/8" 25 Kg kg 0.0176 S/. 13.50 S/. 0.24
TUBO ACERO NEGRO ELECTROSOLDADO REDONDO 2"X2mmX6m und 0.2480 S/. 68.00 S/. 16.86
SUBCONTRATO S/. 30.00
SC. M.O. COLOCACION DE MALLA GALVANIZADA m2 1.0000 S/. 30.00 S/. 30.00
COLOCACION DE MALLA GALVANIZADA #10 DE 2" INC MARCO TUBO ELECTROSOLDADO Ø 2"
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 S/. 208.80
REND 20 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 78.96
OPERARIO hh 3.000 1.2000 S/. 16.08 S/. 19.30
PEON hh 12.000 4.8000 S/. 12.43 S/. 59.66
MATERIALES S/. 119.39
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 3.6000 S/. 19.65 S/. 70.74
HORMIGON m3 0.8300 S/. 30.00 S/. 24.90
PIEDRA GRANDE 8" m3 0.5000 S/. 30.00 S/. 15.00
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.4000 S/. 11.10 S/. 4.44
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 10.45
VIBRADOR DE CONCRETO 4 HP 2.5" hm 2.000 0.8000 S/. 6.60 S/. 5.28
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.4000 S/. 7.00 S/. 2.80
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.79 S/. 2.37
CONCRETO 1:8+25%PM SOBRECIMIENTO m3 S/. 292.11
REND 8 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 160.11
OPERARIO hh 3.000 3.0000 S/. 16.08 S/. 48.24
PEON hh 9.000 9.0000 S/. 12.43 S/. 111.87
MATERIALES S/. 120.19
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 3.8000 S/. 19.65 S/. 74.67
HORMIGON m3 0.8500 S/. 30.00 S/. 25.50
PIEDRA MEDIANA 4" m3 0.5000 S/. 30.00 S/. 15.00
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.0500 S/. 11.10 S/. 0.56
MADERA TORNILLO p2 0.0260 S/. 5.95 S/. 0.15
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 11.80
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 1.0000 S/. 7.00 S/. 7.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.60 S/. 4.80
CONCRETO F'c = 175 Kg/cm2 COLUMNAS m3 S/. 414.72
REND 8 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 160.11
OPERARIO hh 3.000 3.0000 S/. 16.08 S/. 48.24
PEON hh 9.000 9.0000 S/. 12.43 S/. 111.87
MATERIALES S/. 236.20
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 8.8500 S/. 19.65 S/. 173.90
ARENA GRUESA m3 0.5400 S/. 42.30 S/. 22.84
PIEDRA ZARANDEADA 1/2" m3 0.5500 S/. 51.00 S/. 28.05
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.5000 S/. 11.10 S/. 5.55
MADERA TORNILLO p2 0.2600 S/. 5.95 S/. 1.55
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 18.40
VIBRADOR DE CONCRETO 4 HP 2.5" hm 1.000 1.0000 S/. 6.60 S/. 6.60
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 1.0000 S/. 7.00 S/. 7.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.60 S/. 4.80
CONCRETO F'c = 175 Kg/cm2 VIGAS m3 S/. 377.90
REND 10 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 128.09
OPERARIO hh 3.000 2.4000 S/. 16.08 S/. 38.59
PEON hh 9.000 7.2000 S/. 12.43 S/. 89.50
MATERIALES S/. 235.09
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 8.8500 S/. 19.65 S/. 173.90
ARENA GRUESA m3 0.5400 S/. 42.30 S/. 22.84
PIEDRA ZARANDEADA 1/2" m3 0.5500 S/. 51.00 S/. 28.05
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.4000 S/. 11.10 S/. 4.44
MADERA TORNILLO p2 0.2600 S/. 5.95 S/. 1.55
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 14.72
VIBRADOR DE CONCRETO 4 HP 2.5" hm 1.000 0.8000 S/. 6.60 S/. 5.28
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.8000 S/. 7.00 S/. 5.60
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.28 S/. 3.84
CONCRETO F'c = 175 Kg/cm2 LOSA MACIZA m3 S/. 377.90
REND 10 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 128.09
OPERARIO hh 3.000 2.4000 S/. 16.08 S/. 38.59
PEON hh 9.000 7.2000 S/. 12.43 S/. 89.50
MATERIALES S/. 235.09
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 8.8500 S/. 19.65 S/. 173.90
ARENA GRUESA m3 0.5400 S/. 42.30 S/. 22.84
PIEDRA ZARANDEADA 1/2" m3 0.5500 S/. 51.00 S/. 28.05
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.4000 S/. 11.10 S/. 4.44
MADERA TORNILLO p2 0.2600 S/. 5.95 S/. 1.55
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 14.72
VIBRADOR DE CONCRETO 4 HP 2.5" hm 1.000 0.8000 S/. 6.60 S/. 5.28
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.8000 S/. 7.00 S/. 5.60
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.28 S/. 3.84
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 S/. 56.62
REND 10 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 22.81
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 1.000 0.8000 S/. 12.43 S/. 9.94
MATERIALES S/. 33.13
ALAMBRE N° 8 kg 0.3000 S/. 3.81 S/. 1.14
CLAVOS PARA MADERA CON CABEZA DE 2" kg 0.1600 S/. 4.00 S/. 0.64
CLAVOS PARA MADERA CON CABEZA DE 4" kg 0.1600 S/. 4.00 S/. 0.64
MADERA TORNILLO p2 5.1600 S/. 5.95 S/. 30.70
EQUIPOS Y HERRAMIENTAS S/. 0.68
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.23 S/. 0.68
PISO CEMENTO FROTACHADO Y BRUÑADO E=4" m2 S/. 33.98
REND 70 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 19.72
OPERARIO hh 3.000 0.3429 S/. 16.08 S/. 5.51
PEON hh 10.000 1.1429 S/. 12.43 S/. 14.21
MATERIALES S/. 13.66
CEMENTO PORTLAND bls 0.5460 S/. 19.65 S/. 10.73
HORMIGON m3 0.0252 S/. 30.00 S/. 0.76
AGUA m3 0.0200 S/. 13.00 S/. 0.26
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 0.59
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.1143 S/. 7.00 S/. 0.80
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.20 S/. 0.59
CONCRETO PARA VEREDAS F'=140KG/CM2 , e=4" m2 S/. 33.98
REND 70 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 19.72
OPERARIO hh 3.000 0.3429 S/. 16.08 S/. 5.51
PEON hh 10.000 1.1429 S/. 12.43 S/. 14.21
MATERIALES S/. 13.66
CEMENTO PORTLAND TIPO I bls 0.5460 S/. 19.65 S/. 10.73
HORMIGON m3 0.0252 S/. 30.00 S/. 0.76
AGUA m3 0.0200 S/. 13.00 S/. 0.26
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 0.59
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.1143 S/. 7.00 S/. 0.80
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.20 S/. 0.59
JUNTA DE DILATACION e=1" ml S/. 1.99
REND 100 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 1.78
OPERARIO hh 1.000 0.0800 S/. 16.08 S/. 1.29
PEON hh 0.500 0.0400 S/. 12.43 S/. 0.50
MATERIALES S/. 0.16
ASFALTO m3 0.0052 S/. 30.00 S/. 0.16
EQUIPOS Y HERRAMIENTAS S/. 0.05
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.02 S/. 0.05
CONFORMACION DE BASE AFIRMADA EN VEREDAS H=0.10 m2 S/. 15.71
REND 70 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 8.94
OPERARIO hh 1.000 0.1143 S/. 16.08 S/. 1.84
PEON hh 5.000 0.5714 S/. 12.43 S/. 7.10
MATERIALES S/. 5.81
AGUA m3 0.1000 S/. 13.00 S/. 1.30
AFIRMADO m3 0.1250 S/. 35.20 S/. 4.40
COMBUSTIBLE (GASOLINA) gln 0.0100 S/. 11.10 S/. 0.11
EQUIPOS Y HERRAMIENTAS S/. 0.95
COMPACTADOR VIBRATORIO TIPO PLANCHA 5.8 HP hm 1.000 0.11 S/. 6.00 S/. 0.69
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.09 S/. 0.27
ml S/. 180.00
REND 60 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBCONTRATO S/. 180.00
SC. REGILLA METALICA BORDE DE ANGULOS1"X1" Y PLATINA 1" A=0.30m ml 1.0000 S/. 180.00 S/. 180.00
CONCRETO CANALETA DE DRENAJE PLUVIAL INC. REGILLA METALICA m2 S/. 33.98
REND 70 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 19.72
OPERARIO hh 3.000 0.3429 S/. 16.08 S/. 5.51
PEON hh 10.000 1.1429 S/. 12.43 S/. 14.21
MATERIALES S/. 13.66
CEMENTO PORTLAND TIPO I (42.5 kg) bls 0.5460 S/. 19.65 S/. 10.73
HORMIGON m3 0.0252 S/. 30.00 S/. 0.76
AGUA m3 0.0200 S/. 13.00 S/. 0.26
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 0.59
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.1143 S/. 7.00 S/. 0.80
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.20 S/. 0.59
CONCRETO 1:8+25%PM MURO DE CONTENCION m3 S/. 309.46
REND 8 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 160.11
OPERARIO hh 3.000 3.0000 S/. 16.08 S/. 48.24
PEON hh 9.000 9.0000 S/. 12.43 S/. 111.87
MATERIALES S/. 137.55
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 4.2000 S/. 19.65 S/. 82.53
HORMIGON m3 0.8500 S/. 30.00 S/. 25.50
PIEDRA MEDIANA 4" m3 0.6500 S/. 30.00 S/. 19.50
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.5000 S/. 11.10 S/. 5.55
MADERA TORNILLO p2 0.0260 S/. 5.95 S/. 0.15
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 11.80
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 1.0000 S/. 7.00 S/. 7.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.60 S/. 4.80
MURO DE PIRCA DE PIEDRA H=0.80 m2 S/. 156.49
REND 10 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 102.36
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 9.000 7.2000 S/. 12.43 S/. 89.50
MATERIALES S/. 51.06
CEMENTO PORTLAND TIPO I (42.5 kg) bls 1.5000 S/. 19.65 S/. 29.47
PIEDRA GRANDE m3 0.3300 S/. 30.00 S/. 9.90
ARENA GRUESA m3 0.2000 S/. 42.30 S/. 8.46
AGUA m3 0.1000 S/. 13.00 S/. 1.30
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 3.07
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.02 S/. 3.07
REGILLA METALICA BORDE DE ANGULOS1"X1" Y PLATINA 1" A=0.30m
MURO DE PIRCA DE PIEDRA H=1.20 m2 S/. 161.62
REND 10 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 102.36
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 9.000 7.2000 S/. 12.43 S/. 89.50
MATERIALES S/. 56.18
CEMENTO PORTLAND TIPO I (42.5 kg) bls 1.5000 S/. 19.65 S/. 29.47
PIEDRA GRANDE m3 0.3600 S/. 30.00 S/. 10.80
ARENA GRUESA m3 0.3000 S/. 42.30 S/. 12.69
AGUA m3 0.1000 S/. 13.00 S/. 1.30
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 3.07
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.02 S/. 3.07
ACARREO, COLOCACION Y TENDIDO DE PIEDRA CONFITILLO PARA JUEGOS INFANTILES m2 S/. 8.89
REND 80 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 3.29
OPERARIO hh 0.500 0.0500 S/. 16.08 S/. 0.80
PEON hh 2.000 0.2000 S/. 12.43 S/. 2.49
MATERIALES S/. 5.50
PIEDRA ZARANDEADA 1/4" m3 0.1000 S/. 55.00 S/. 5.50
EQUIPOS Y HERRAMIENTAS S/. 0.10
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.03 S/. 0.10
SARDINEL DE CONCRETO 0.10X0.30m ml S/. 20.34
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 20.34
EXCAVACION ZANJA PARA CIMENTACION m3 0.02 S/. 34.14 S/. 0.68
CORTE Y HABILITACION DE ACERO CORRUGADO FY=4200kg/cm2 kg 1.43 S/. 5.72 S/. 8.16
CONCRETO 1:8+25%PM SOBRECIMIENTO m3 0.0200 S/. 292.11 S/. 5.84
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.1000 S/. 56.62 S/. 5.66
DESMONTAJE DE PUERTA TIPO REJA und S/. 33.73
REND 10 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 32.75
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 2.000 1.6000 S/. 12.43 S/. 19.89
EQUIPOS Y HERRAMIENTAS S/. 0.98
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.33 S/. 0.98
RELACION DE MATERIALESMINISTERIO DE EDUCACION
INSTITUCIONES EDUCATIVAS: RED YATIQAÑA
FECHA : 2012
MANO DE OBRA
CAPATAZ hh S/. 19.30
TOPOGRAFO hh S/. 16.08
OPERARIO hh S/. 16.08
OFICIAL hh S/. 13.79
PEON hh S/. 12.43
MATERIALES
BOLSA DE YESO DE 25 KG bls S/. 8.50
OCRE ROJO kg S/. 10.50
AGUA m3 S/. 13.00
CLAVOS kg S/. 5.80
AFIRMADO m3 S/. 35.20
CEMENTO PORTLAND TIPO I (42.5 kg) bls S/. 19.65
ACERO CORRUGADO FY=4200KG/CM2 kg S/. 4.60
LADRILLO KING KONG DE ARCILLA 18 HUECOS HECHO A MAQUINA 9 X 14 X 24 cm und S/. 1.30
BLOQUE DE CONCRETO 20 X 20 X 40 cm und S/. 2.30
ARENA FINA m3 S/. 45.50
ARENA GRUESA m3 S/. 42.30
MADERA TORNILLO p2 S/. 5.95
CLAVOS PARA MADERA CON CABEZA DE 2" A 4" kg S/. 4.00
CLAVOS PARA MADERA CON CABEZA DE 2" kg S/. 4.00
CLAVOS PARA MADERA CON CABEZA DE 3" kg S/. 4.00
CLAVOS PARA MADERA CON CABEZA DE 4" kg S/. 4.00
PIEDRA ZARANDEADA 1/2" m3 S/. 51.00
PIEDRA ZARANDEADA 1/4" m3 S/. 55.00
HORMIGON m3 S/. 30.00
PIEDRA GRANDE 8" m3 S/. 30.00
PIEDRA MEDIANA 4" m3 S/. 30.00
PIEDRA GRANDE m3 S/. 30.00
COMBUSTIBLE (GASOLINA) gln S/. 11.10
ADITIVO CURADO QUIMICO gln S/. 48.00
ALAMBRE N° 16 kg S/. 3.81
ALAMBRE N° 8 kg S/. 3.81
ASFALTO m3 S/. 30.00
GRASS bls S/. 10.17
TIERRA DE CHACRA m3 S/. 17.00
PINTURA ESMALTE SINTETICO EN GALON und S/. 30.00
PINTURA ESMALTE SINTETICO ANTICORROSIVO EN GALON und S/. 33.00
PLANCHA NEGRA LAF 0.50X920X2400mm und S/. 125.30
TRIPLAY 6mm m2 S/. 12.00
PERNO INC. TUERCA 3/4"X6" und S/. 3.20
PLANTONES und S/. 15.00
JUEGOS INFANTILES METALICOS und S/. 1,250.00
ANGULO FIERRO NEGRO 1"X1"X3/16"X6m und S/. 22.44
PUNTO AZUL E-6011 1/8" 25 Kg kg S/. 13.50
TUBO ACERO NEGRO ELECTROSOLDADO REDONDO 2"X2mmX6m und S/. 68.00
MALLA GALVANIZADA DE #10 DE 2"x2" m2 S/. 19.00
TANQUE ETERNIT 1.100 LT C/FILTRO INC. ACCESORIOS und S/. 415.51
ELECTROBOMBA DE 0.5HP und S/. 575.20
TUBERIA PVC SAP C-10 C/R 1'' ml S/. 2.47
TUBERIA PVC SAP C-10 C/R 3/4'' ml S/. 1.62
REDUCCION PVC SAP S/P 3/4"-1/2" und S/. 0.55
REDUCCION PVC SAP S/P 1"-3/4" und S/. 0.77
TEE DESAGUE SANITARIA 2" PVC und S/. 3.75
CINTA TEFLON DE MEDIA und S/. 2.00
NIPLE F°G° 1/2" x 1½" und S/. 1.50
VALVULA ESFERICA REDGAL CIM. 1/2" und S/. 17.50
VALVULA CHECK SWING 1/2" und S/. 43.63
CODOS PVC SP 1/2"x90° und S/. 1.10
ADAPTADOR PVC PR 1/2" und S/. 1.25
REDUCC. CAMP GALV 3/4"x1/2" und S/. 2.38
UNION PVC R 3/4" PU und S/. 1.63
REDUCC. PVC-P 3/4"x1/2" C/R und S/. 0.88
PEGAMENTO PVC 32 ONZ. und S/. 28.13
FORMADOR DE EMPAQUETADURAS 3-H und S/. 7.75
TEE DESAGUE 4"x2" PVC und S/. 5.63
SOMBRERO DE VENTILACION DESAGUE 2" PVC und S/. 5.63
CODO DESAGUE 2"x90° PVC und S/. 1.50
CODO DESAGUE 2"x45° PVC und S/. 1.50
TUBO DESAGUE 2"x 3m. PVC und S/. 10.25
CONSTRUCCION DE ALMACEN, CAMPAMENTO Y OFICINA PROVISIONAL glb S/. 5,000.00
VALV.PASO TERMOP. C/NIPLE TELESCOPICO und S/. 21.00
VALV.PASO TERMOP. C/SAL. AUX. 15N und S/. 16.56
UNION PRESION ROSCA 1/2" und S/. 0.60
NIPLE REEMPLAZO MEDIDOR 3/4" und S/. 2.14
CAJA DE REGISTRO DE CONCRETO PARA AGUA (INC. CUERPO Y SOLADO) und S/. 35.30
CAJA DE CONCRETO PARA REGISTRO DE DESAGUE (INC. BASE, INTERMEDIO,MARCO Y TAPA) und S/. 42.50
BIODIGESTOR AUTOLIMPIABLE 1300LT, INC. ACCESORIOS und S/. 1,395.25
BIODIGESTOR AUTOLIMPIABLE 3000LT, INC. ACCESORIOS und S/. 4,796.30
RED INTERNA DE AGUA HASTA 25m. glb S/. 1,000.00
RED INTERNA DE DESAGUE HASTA 25m. glb S/. 2,000.00
RED INTERNA DE AGUA HASTA 50m. glb S/. 2,000.00
RED INTERNA DE DESAGUE HASTA 50m. glb S/. 4,000.00
RED INTERNA DE AGUA HASTA 80m. glb S/. 3,200.00
RED INTERNA DE DESAGUE HASTA 80m. glb S/. 6,400.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 01 AULA A MAS DE 3600msnm glb S/. 3,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 02 AULAS A MAS DE 3600msnm glb S/. 6,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 05 AULAS A MAS DE 3600msnm glb S/. 15,000.00
EQUIPOSNIVEL TOPOGRAFICO hm S/. 3.00
MIRA TOPOGRAFICA hm S/. 0.50
CAMION VOLQUETE 12M3 hm S/. 77.00
CARGADOR FRONTAL 200HP hm S/. 150.00
ANDAMIO METAL TABLAS ALQUILER d S/. 9.00
VIBRADOR DE CONCRETO 4 HP 2.5" hm S/. 6.60
MEZCLADORA DE CONCRETO 12 P3 hm S/. 7.00
COMPACTADOR VIBRATORIO TIPO PLANCHA 5.8 HP hm S/. 6.00
CIZALLA ELECTRICA DE FIERRO hm S/. 22.60
CARTEL DE OBRA DE 3.60 X 2.40 und S/. 900.00
BOLETINES INFORMATIVOS glb S/. 480.00
LETRINA SANITARIA INC. SERV MANTENIMIENTO und S/. 3,000.00
CONTENEDORES DE RESIDUOS SOLIDOS und S/. 150.00
LETREROS INFORMATIVOS PREVENTIVOS Y DE REGLAMENTACION und S/. 800.00
MITIGACION DE IMPACTO AMBIENTAL DURANTE LA EJECUCION
FLETE TERRESTRE P/TRANSPORTE DE MATERIALES glb S/. 9,000.00
FLETE TERRESTRE P/TRANSPORTE DE MATERIALES glb S/. 10,000.00
SUBCONTRATO
SC. REGILLA METALICA BORDE DE ANGULOS1"X1" Y PLATINA 1" A=0.30m ml S/. 180.00
SC CORTE DE ROCA CON MAQUINARIA PESADA hm S/. 300.00
SC. ELABORACION JUEGOS INFANTILES METALICOS und S/. 1,250.00
SC. TRANSPORTE DE JUEGOS INFANTILES vje S/. 500.00
SC. M.O. COLOCACION DE MALLA GALVANIZADA m2 S/. 30.00
SC. COLOCACION DE REJA METALICA m2 S/. 67.80
SC. ELABORACION Y COLOCACION PUERTA METALICA 2.65X3.00 und S/. 4,770.00
SC. ELABORACION Y COLOCACION PUERTA METALICA 0.90X3.00 und S/. 1,620.00
SC. INSTALACION Y COLOC. POZO A TIERRA Y PARARRAYOS glb S/. 3,000.00
SC. M.O. ELABORACION E INSTALACION DE ARMAZON METALICO DE 1.00mX1.00m Y H=3.00m glb S/. 720.00
SC. PRUEBA DE CALIDAD DE CONCRETO A LA COMPRESION und S/. 25.50
SUBPARTIDAS DE RAHABILITACION, REFACCION Y DEMOLICION
PINTADO DE MUROS m2 S/. 6.78
TARRAJEO DE MUROS m2 S/. 15.10
COLOCACION DE CERAMICO m2 S/. 47.30
DEMOLICION DE MODULO ESTRUCTURA EXSISTENTE m2 S/. 17.00
DEMOLICION DE CERCO PERIMETRICO ml S/. 7.50
PINTADO DE LOSA DEPORTIVA m2 S/. 2.00
PINTADO DE ARCOS METALICOS und S/. 60.00
DEMOLICION DE COLUMNETAS DE CONCRETO und S/. 7.50
DEMOLICION DE PORTICO DE INGRESO DE CONCRETO (EXISTENTE) und S/. 150.00
RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/. 35.22
COLOCACION PUERTA METALICA PARA VIVIENDA DOCENTE und S/. 750.50
ANALISIS DE PRECIOS UNITARIOS
PARTIDAS
CONSTRUCCION DE ALMACEN, CAMPAMENTO Y OFICINA PROVISIONAL glb S/. 5,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 5,000.00
CONSTRUCCION DE ALMACEN, CAMPAMENTO Y OFICINA PROVISIONAL glb 1.0000 S/. 5,000.00 S/. 5,000.00
CARTEL DE IDENTIFICACION DE OBRA 3.60X2.40m und S/. 1,667.46
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 309.20
OFICIAL hh 1.000 8.0000 S/. 13.79 S/. 110.32
PEON hh 2.000 16.0000 S/. 12.43 S/. 198.88
MATERIALES S/. 1,348.99
CEMENTO PORTLAND TIPO I (42.5 kg) bls 0.9000 S/. 19.65 S/. 17.69
CARTEL DE OBRA DE 3.60 X 2.40 und 1.00 S/. 900.00 S/. 900.00
CLAVOS PARA MADERA CON CABEZA DE 2" kg 1.0000 S/. 4.00 S/. 4.00
HORMIGON m3 0.3600 S/. 30.00 S/. 10.80
MADERA TORNILLO p2 70.0000 S/. 5.95 S/. 416.50
EQUIPOS Y HERRAMIENTAS S/. 9.28
HERRAMIENTAS MANUALES %M.O. %mo 3.0000 S/. 3.09 S/. 9.28
PUERTA PRINCIPAL DE INGRESO METALICA L=4.00m INC. PORTICO DE C.A. Y MURO DE BLOQUES DE C° L=13.66m und S/. 15,034.52
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 15,034.52
EXCAVACION ZANJA PARA CIMENTACION m3 9.7200 S/. 34.14 S/. 331.84
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 7.2900 S/. 208.80 S/. 1,522.15
CONCRETO 1:8+25%PM SOBRECIMIENTO m3 0.6120 S/. 292.11 S/. 178.77
CORTE Y HABILITACION DE ACERO CORRUGADO FY=4200kg/cm2 kg 363.3553 S/. 5.72 S/. 2,078.39
CONCRETO F'c = 175 Kg/cm2 COLUMNAS m3 0.3065 S/. 414.72 S/. 127.11
CONCRETO F'c = 175 Kg/cm2 VIGAS m3 0.3600 S/. 377.90 S/. 136.04
CONCRETO F'c = 175 Kg/cm2 LOSA MACIZA m3 0.7680 S/. 377.90 S/. 290.23
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 34.2600 S/. 56.62 S/. 1,939.80
MURO DE SOGA CON BLOQUES DE CONCRETO 20x20x40 m2 26.5200 S/. 76.93 S/. 2,040.18
SC. ELAVORACION Y COLOCACION PUERTA METALICA 2.65X3.00 und 1.0000 S/. 4,770.00 S/. 4,770.00
SC. ELAVORACION Y COLOCACION PUERTA METALICA 0.90X3.00 und 1.0000 S/. 1,620.00 S/. 1,620.00
LIMPIEZA MANUAL DE TERRENO NATURAL m2 S/. 2.56
REND 80 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 2.49
PEON hh 2.000 0.2000 S/. 12.43 S/. 2.49
EQUIPOS Y HERRAMIENTAS S/. 0.07
HERRAMIENTAS MANUALES %M.O. %mo 3.0000 S/. 0.02 S/. 0.07
TRAZO Y REPLANTEO GENERAL DE OBRA m2 S/. 1.68
REND 350 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 0.98
CAPATAZ hh 0.1 0.0023 S/. 19.30 S/. 0.04
TOPOGRAFO hh 1.000 0.0229 S/. 16.08 S/. 0.37
PEON hh 2.000 0.0457 S/. 12.43 S/. 0.57
MATERIALES S/. 0.59
BOLSA DE YESO DE 25 KG bls 0.0500 S/. 8.50 S/. 0.43
OCRE ROJO kg 0.0040 S/. 10.50 S/. 0.04
MADERA TORNILLO p2 0.0200 S/. 5.95 S/. 0.12
EQUIPOS Y HERRAMIENTAS S/. 0.11
NIVEL TOPOGRAFICO hm 1.000 0.0229 S/. 3.00 S/. 0.07
MIRA TOPOGRAFICA hm 1.000 0.0229 S/. 0.50 S/. 0.01
HERRAMIENTAS MANUALES %M.O. %mo 3.0000 S/. 0.01 S/. 0.03
MOVIMIENTO DE TIERRASEXCAVACION ZANJA PARA CIMENTACION m3 S/. 34.14
REND 3 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 33.15
PEON hh 1.000 2.6667 S/. 12.43 S/. 33.15
EQUIPOS Y HERRAMIENTAS S/. 0.99
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.33 S/. 0.99
EXCAVACION PARA ZAPATAS m3 S/. 36.41
REND 3.25 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIOS (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 35.35
CAPATAZ hh 0.100 0.2462 S/. 19.30 S/. 4.75
PEON hh 1.000 2.4615 S/. 12.43 S/. 30.60
EQUIPO, HERRAMIENTAS S/. 1.06
HERRRAMIENTAS MANUALES % M.O. %mo 3.0000 S/. 0.35 S/. 1.06
ACARREO DE MATERIAL EXEDENTE m3 S/. 23.66
REND 5 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIOS (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 22.98
CAPATAZ hh 0.100 0.1600 S/. 19.30 S/. 3.09
PEON hh 1.000 1.6000 S/. 12.43 S/. 19.89
EQUIPO, HERRAMIENTAS S/. 0.69
HERRRAMIENTAS MANUALES % M.O. %mo 3.0000 S/. 0.23 S/. 0.69
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 S/. 41.21
REND 10 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 22.81
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 1.000 0.8000 S/. 12.43 S/. 9.94
MATERIALES S/. 17.71
AGUA m3 0.0126 S/. 13.00 S/. 0.16
MADERA TONILLO p2 2.9400 S/. 5.95 S/. 17.49
CLAVOS KG 0.0100 S/. 5.80 S/. 0.06
EQUIPOS Y HERRAMIENTAS S/. 0.68
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.23 S/. 0.68
CONCRETO SIMPLE
SOLADO PARA ZAPATAS DE 3" DE ESPESOR m3 S/. 19.60
REND 80 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 10.81
CAPATAZ hh 0.2 0.0200 S/. 19.30 S/. 0.39
OFICIAL hh 1.000 0.1000 S/. 13.79 S/. 1.38
OPERARIO hh 2.000 0.2000 S/. 16.08 S/. 3.22
PEON hh 5.000 0.5000 S/. 12.43 S/. 6.22
MATERIALES S/. 3.92
HORMIGON m3 0.0900 S/. 8.50 S/. 0.77
CEMENTO PORTLAND TIPO I (42.5Kg) bol 0.3000 S/. 10.50 S/. 3.15
EQUIPOS Y HERRAMIENTAS S/. 4.87
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.1000 S/. 45.50 S/. 4.55
HERRAMIENTAS MANUALES %M.O. %mo 3.0000 S/. 0.11 S/. 0.32
CONCRETO ARMADO
ZAPATA DE f'c = 175 kg/cm2 m3 S/. 285.28
REND 25 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 52.17CAPATAZ hh 0.200 0.0640 S/. 19.30 S/. 1.23
OPERARIO hh 2.000 0.6400 S/. 16.08 S/. 10.29
OFICIAL hh 2.000 0.6400 S/. 13.79 S/. 8.83
PEON hh 8.000 2.5600 S/. 12.43 S/. 31.82
MATERIALES S/. 227.19CEMENTO PORTLAND TIPO I (42.5Kg) bls 8.8500 S/. 19.65 S/. 173.90
ARENA GRUESA m3 0.5400 S/. 42.30 S/. 22.84
PIEDRA ZARANDEADA 1/2" m3 0.5500 S/. 51.00 S/. 28.05
AGUA m3 0.1840 S/. 13.00 S/. 2.39
EQUIPOS Y HERRAMIENTAS S/. 5.92MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.3200 S/. 7.00 S/. 2.24
VIBRADOR DE CONCRETO 4 HP 2.5" hm 1.000 0.3200 S/. 6.60 S/. 2.11
HERRAMIENTAS MANUALES %M.O. %mo 3.0000 S/. 0.52 S/. 1.57
ENCONFRADO Y DESENCOFRADO DE ZAPATA m2 S/. 62.06
REND 40 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 14.09CAPATAZ hh 0.1000 0.0200 S/. 19.30 S/. 0.39
OPERARIO hh 1.0000 0.2000 S/. 16.08 S/. 3.22
OFICIAL hh 2.0000 0.4000 S/. 13.79 S/. 5.52
PEON hh 2.0000 0.4000 S/. 12.43 S/. 4.97
MATERIALES S/. 47.55MADERA TORNILLO p2 7.8900 S/. 5.95 S/. 46.95
CLAVOS DE 3" kg 0.1500 S/. 4.00 S/. 0.60
EQUIPOS Y HERRAMIENTAS S/. 0.42HERRAMIENTAS MANUALES %M.O. %mo 3.0000 S/. 0.14 S/. 0.42
CONCRETO F'c = 175 Kg/cm2 COLUMNAS m3 S/. 411.25
REND 8 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 160.11
OPERARIO hh 3.000 3.0000 S/. 16.08 S/. 48.24
PEON hh 9.000 9.0000 S/. 12.43 S/. 111.87
MATERIALES S/. 232.74
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 8.8500 S/. 19.65 S/. 173.90
ARENA GRUESA m3 0.5400 S/. 42.30 S/. 22.84
PIEDRA ZARANDEADA 1/2" m3 0.5500 S/. 51.00 S/. 28.05
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.5000 S/. 11.10 S/. 5.55
EQUIPOS Y HERRAMIENTAS S/. 18.40
VIBRADOR DE CONCRETO 4 HP 2.5" hm 1.000 1.0000 S/. 6.60 S/. 6.60
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 1.0000 S/. 7.00 S/. 7.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.60 S/. 4.80
ENCONFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 S/. 34.15
REND 10 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 25.44
CAPATAZ hh 0.1000 0.0800 S/. 19.30 S/. 1.54
OPERARIO hh 1.0000 0.8000 S/. 16.08 S/. 12.86
OFICIAL hh 1.0000 0.8000 S/. 13.79 S/. 11.03
MATERIALES S/. 7.94ALAMBRE N° 8 kg 0.3000 S/. 3.81 S/. 1.14
MADERA TORNILLO p2 5.3200 S/. 1.25 S/. 6.65
CLAVOS DE 3" kg 0.1700 S/. 0.88 S/. 0.15
EQUIPOS Y HERRAMIENTAS S/. 0.76HERRAMIENTAS MANUALES %M.O. %mo 3.0000 S/. 0.25 S/. 0.76
ENCONFRADO Y DESENCOFRADO NORMAL EN COLUMNAS kg S/. 8.11
REND 216 kg
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 2.10CAPATAZ hh 0.1000 0.0037 S/. 19.30 S/. 0.07
OPERARIO hh 1.0000 0.0370 S/. 16.08 S/. 0.60
OFICIAL hh 1.0000 0.0370 S/. 13.79 S/. 0.51
PEON hh 2.0000 0.0741 S/. 12.43 S/. 0.92
MATERIALES S/. 5.11ALAMBRE N°16 kg 0.0500 S/. 3.81 S/. 0.19
ACERO CORRUGADO FY=4200KG/CM2 kg 1.0700 S/. 4.60 S/. 4.92
EQUIPOS Y HERRAMIENTAS S/. 0.90HERRAMIENTAS MANUALES %M.O. %mo 3.0000 S/. 0.02 S/. 0.06
CIZALLA ELECTRICA DE FIERRO hm 1.0000 0.0370 S/. 22.60 S/. 0.84
CONCRETO F'c = 175 Kg/cm2 VIGAS m3 S/. 377.90
REND 10 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 128.09
OPERARIO hh 3.000 2.4000 S/. 16.08 S/. 38.59
PEON hh 9.000 7.2000 S/. 12.43 S/. 89.50
MATERIALES S/. 235.09
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 8.8500 S/. 19.65 S/. 173.90
ARENA GRUESA m3 0.5400 S/. 42.30 S/. 22.84
PIEDRA ZARANDEADA 1/2" m3 0.5500 S/. 51.00 S/. 28.05
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.4000 S/. 11.10 S/. 4.44
MADERA TORNILLO p2 0.2600 S/. 5.95 S/. 1.55
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 14.72
VIBRADOR DE CONCRETO 4 HP 2.5" hm 1.000 0.8000 S/. 6.60 S/. 5.28
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.8000 S/. 7.00 S/. 5.60
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.28 S/. 3.84
INST. Y COLOC. POZO A TIERRA Y PARARRAYOS und S/. 3,000.00
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 3,000.00
SC. INSTALACION Y COLOC. POZO A TIERRA Y PARARRAYOS glb 1.0000 S/. 3,000.00 S/. 3,000.00
INST. Y COLOC. DE TANQUE DE POLIETILENO DE AGUA 1100 lt. SOBRE ARMAZON METALICO H=3.00 und S/. 1,564.62
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 1,564.62
EXCAVACION ZANJA PARA CIMENTACION m3 0.5120 S/. 34.14 S/. 17.48
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.3200 S/. 56.62 S/. 18.12
CONCRETO SIMPLE 1:8+25%PM PARA DADOS DE CIMENTACION 0.40X0.40 m3 0.1600 S/. 292.11 S/. 46.74
ELABORAC. Y COLOC. DE ARMAZON METALICO PARA TANQUE DE POLIETILENO DE H=3.00 und 1.0000 S/. 834.71 S/. 834.71
INST. Y COLOC. DE TANQUE DE POLIETILENO DE AGUA 1100 lt. und 1.0000 S/. 647.57 S/. 647.57
INST. Y COLOC. DE TANQUE CISTERNA DE POLIETILENO DE AGUA 1100 lt. INC. ELECTROBOMBA DE 0.5HP und S/. 1,612.32
REND 3 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 142.32
OPERARIO hh 1.000 2.6667 S/. 16.08 S/. 42.88
PEON hh 3.000 8.0000 S/. 12.43 S/. 99.44
MATERIALES S/. 1,465.73
TANQUE ETERNIT 1.100 LT C/FILTRO INC. ACCESORIOS und 1.0000 S/. 415.51 S/. 415.51
ELECTROBOMBA DE 0.5HP und 1.0000 S/. 575.20 S/. 575.20
TUBERIA PVC SAP C-10 C/R 1'' ml 3.0000 S/. 2.47 S/. 7.41
TUBERIA PVC SAP C-10 C/R 3/4'' ml 18.0000 S/. 1.62 S/. 29.16
REDUCCION PVC SAP S/P 3/4"-1/2" und 3.0000 S/. 0.55 S/. 1.65
REDUCCION PVC SAP S/P 1"-3/4" und 2.0000 S/. 0.77 S/. 1.54
CINTA TEFLON DE MEDIA und 1.0000 S/. 2.00 S/. 2.00
LADRILLO KING KONG DE ARCILLA 18 HUECOS HECHO A MAQUINA 9 X 14 X 24 cm und 324.0000 S/. 1.30 S/. 421.20
ARENA FINA m3 0.2650 S/. 45.50 S/. 12.06
EQUIPOS Y HERRAMIENTAS S/. 4.27
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.42 S/. 4.27
CERCO PERIMETRICO CON BLOQUE DE CONCRETO CONFINADO H=3.00 m ml S/. 635.36
REND 1 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 635.36
EXCAVACION ZANJA PARA CIMENTACION m3 0.7200 S/. 34.14 S/. 24.58
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 0.5400 S/. 208.80 S/. 112.75
CONCRETO 1:8+25%PM SOBRECIMIENTO m3 0.0800 S/. 292.11 S/. 23.37
CORTE Y HABILITACION DE ACERO CORRUGADO FY=4200kg/cm2 kg 14.8679 S/. 5.72 S/. 85.04
CONCRETO F'c = 175 Kg/cm2 COLUMNAS m3 0.0370 S/. 414.72 S/. 15.34
CONCRETO F'c = 175 Kg/cm2 VIGAS m3 0.1800 S/. 377.90 S/. 68.02
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 2.0800 S/. 56.62 S/. 117.77
MURO DE SOGA CON BLOQUES DE CONCRETO 20x20x40 m2 2.4500 S/. 76.93 S/. 188.48
CERCO PERIMETRICO DE PAÑOS MIXTOS CON BLOQUE DE CONCRETO CONFINADO Y REJA METALICA H=3.00 m ml S/. 632.90
REND 1 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 632.90
EXCAVACION ZANJA PARA CIMENTACION m3 0.7200 S/. 34.14 S/. 24.58
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 0.5400 S/. 208.80 S/. 112.75
CONCRETO 1:8+25%PM SOBRECIMIENTO m3 0.0800 S/. 292.11 S/. 23.37
CORTE Y HABILITACION DE ACERO CORRUGADO FY=4200kg/cm2 kg 14.8679 S/. 5.72 S/. 85.04
CONCRETO F'c = 175 Kg/cm2 COLUMNAS m3 0.0370 S/. 414.72 S/. 15.34
CONCRETO F'c = 175 Kg/cm2 VIGAS m3 0.1800 S/. 377.90 S/. 68.02
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 2.0800 S/. 56.62 S/. 117.77
MURO DE SOGA CON BLOQUES DE CONCRETO 20x20x40 m2 2.1800 S/. 76.93 S/. 167.71
COLOCACION DE REJA METALICA m2 0.2700 S/. 67.80 S/. 18.31
VEREDAS DE CONCRETO 140Kg/cm2, E= 4" m2 S/. 85.32
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 85.32
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 0.15 S/. 41.21 S/. 6.18
CONFORMACION DE BASE AFIRMADA EN VEREDAS H=0.10 m2 1.00 S/. 15.71 S/. 15.71
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.40 S/. 56.62 S/. 22.65
CONCRETO PARA VEREDAS F'=140KG/CM2 , e=4" m2 1.20 S/. 33.98 S/. 40.78
PATIO DE CONCRETO FROTACHADO Y BRUÑADO ml S/. 74.10
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 74.10
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 0.15 S/. 41.21 S/. 6.18
CONFORMACION DE BASE AFIRMADA EN VEREDAS H=0.10 m2 1.00 S/. 15.71 S/. 15.71
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.28 S/. 56.62 S/. 15.85
PISO CEMENTO FROTACHADO Y BRUÑADO E=4" m2 1.07 S/. 33.98 S/. 36.36
JUNTA DE DILATACION e=1" ml 1.33 S/. 1.99 S/. 2.65
LOSA DE CONCRETO FROTACHADO Y BRUÑADO m2 S/. 74.10
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 74.10
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 0.15 S/. 41.21 S/. 6.18
CONFORMACION DE BASE AFIRMADA EN VEREDAS H=0.10 m2 1.00 S/. 15.71 S/. 15.71
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.28 S/. 56.62 S/. 15.85
PISO CEMENTO FROTACHADO Y BRUÑADO E=4" m2 1.07 S/. 33.98 S/. 36.36
JUNTA DE DILATACION e=1" ml 1.33 S/. 1.99 S/. 2.65
CUNETA 0.30X0.30 PARA DRENAJE PLUVIAL INC. REG. METALICA ANCHO 0.30m ml S/. 272.40
REND 1 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 272.40
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 0.03 S/. 41.21 S/. 1.24
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.95 S/. 56.62 S/. 53.79
REGILLA METALICA BORDE DE ANGULOS1"X1" Y PLATINA 1" A=0.30m ml 1.00 S/. 180.00 S/. 180.00
CONCRETO CANALETA DE DRENAJE PLUVIAL INC. REGILLA METALICA m2 1.10 S/. 33.98 S/. 37.38
RAMPAS DE CONCRETO 140Kg/cm2, E= 4" m2 S/. 85.32
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 85.32
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 0.15 S/. 41.21 S/. 6.18
CONFORMACION DE BASE AFIRMADA EN VEREDAS H=0.10 m2 1.00 S/. 15.71 S/. 15.71
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.40 S/. 56.62 S/. 22.65
PISO CEMENTO FROTACHADO Y BRUÑADO E=4" m2 1.20 S/. 33.98 S/. 40.78
MURO DE CONTENCION CºCº H=0.80m ml S/. 500.97
REND 1 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 500.97
EXCAVACION ZANJA PARA CIMENTACION m3 0.9000 S/. 34.14 S/. 30.73
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 0.9000 S/. 208.80 S/. 187.92
CONCRETO 1:8+25%PM MURO DE CONTENCION m3 0.4000 S/. 309.46 S/. 123.78
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 2.8000 S/. 56.62 S/. 158.54
MURO DE MAMPOSTERIA DE PIEDRA H=0.80 ml S/. 500.97
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 500.97
EXCAVACION ZANJA PARA CIMENTACION m3 0.9000 S/. 34.14 S/. 30.73
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 0.9000 S/. 208.80 S/. 187.92
CONCRETO 1:8+25%PM MURO DE CONTENCION m3 0.4000 S/. 309.46 S/. 123.78
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 2.8000 S/. 56.62 S/. 158.54
MURO DE CONTENCION CºCº H=2.00m ml S/. 1,106.09
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 1,106.09
EXCAVACION ZANJA PARA CIMENTACION m3 1.8000 S/. 34.14 S/. 61.45
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 1.8000 S/. 208.80 S/. 375.84
CONCRETO 1:8+25%PM MURO DE CONTENCION m3 1.1000 S/. 309.46 S/. 340.41
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 5.8000 S/. 56.62 S/. 328.40
PLAN DE MANEJO AMBIENTAL DURANTE LA EJECUCION und S/. 7,880.00
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 7,880.00
BOLETINES INFORMATIVOS glb 1.000 S/. 480.00 S/. 480.00
LETRINA SANITARIA INC. SERV MANTENIMIENTO und 2.000 S/. 3,000.00 S/. 6,000.00
CONTENEDORES DE RESIDUOS SOLIDOS und 4.000 S/. 150.00 S/. 600.00
LETREROS INFORMATIVOS PREVENTIVOS Y DE REGLAMENTACION und 1.000 S/. 800.00 S/. 800.00
PATIO DE JUEGOS AREA=118.26m2 INC. SARDINEL DE CONCRETO 0.10X0.30m Y 04 UNID DE JUEGOS METALICOS und S/. 7,373.87
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 1,873.87
SARDINEL DE CONCRETO 0.10X0.30m ml 43.7000 S/. 20.34 S/. 888.86
ACARREO, COLOCACION Y TENDIDO DE PIEDRA CONFITILLO PARA JUEGOS INFANTILES m2 110.8000 S/. 8.89 S/. 985.01
SUBCONTRATO S/. 5,500.00
SC. ELABORACION JUEGOS INFANTILES METALICOS und 4.0000 S/. 1,250.00 S/. 5,000.00
SC. TRANSPORTE DE JUEGOS INFANTILES vje 1.0000 S/. 500.00 S/. 500.00
PRUEBAS DE CALIDAD DE CONCRETO (PRUEBA A LA COMPRESION) und S/. 25.50
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 25.50
SC. PRUEBA DE CALIDAD DE CONCRETO A LA COMPRESION und 1.0000 S/. 25.50 S/. 25.50
COLOCACION CAJA REGISTRO Y CONECCION A RED DE AGUA und S/. 104.21
REND 10 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 27.78
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 1.500 1.2000 S/. 12.43 S/. 14.92
MATERIALES S/. 75.60
VALV.PASO TERMOP. C/NIPLE TELESCOPICO und 1.0000 S/. 21.00 S/. 21.00
VALV.PASO TERMOP. C/SAL. AUX. 15N und 1.0000 S/. 16.56 S/. 16.56
UNION PRESION ROSCA 1/2" und 1.0000 S/. 0.60 S/. 0.60
NIPLE REEMPLAZO MEDIDOR 3/4" und 1.0000 S/. 2.14 S/. 2.14
CAJA DE REGISTRO DE CONCRETO PARA AGUA (INC. CUERPO Y SOLADO) und 1.0000 S/. 35.30 S/. 35.30
EQUIPOS Y HERRAMIENTAS S/. 0.83
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.28 S/. 0.83
COLOCACION CAJA REGISTRO Y CONECCION A BIODIGESTOR und S/. 71.11
REND 10 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 27.78
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 1.500 1.2000 S/. 12.43 S/. 14.92
MATERIALES S/. 42.50
CAJA DE CONCRETO PARA REGISTRO DE DESAGUE (INC. BASE, INTERMEDIO,MARCO Y TAPA) und 1.0000 S/. 42.50 S/. 42.50
EQUIPOS Y HERRAMIENTAS S/. 0.83
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.28 S/. 0.83
INSTALACION Y COLOCACION DE BIODIGESTOR AUTOLIMPIABLE 1300LT, INC. ACCESORIOS und S/. 1,663.46
REND 2 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 213.48
OPERARIO hh 1.000 4.0000 S/. 16.08 S/. 64.32
PEON hh 3.000 12.0000 S/. 12.43 S/. 149.16
MATERIALES S/. 1,443.57
BIODIGESTOR AUTOLIMPIABLE 1300LT, INC. ACCESORIOS und 1.0000 S/. 1,395.25 S/. 1,395.25
ARENA FINA m3 1.0620 S/. 45.50 S/. 48.32
EQUIPOS Y HERRAMIENTAS S/. 6.40
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 2.13 S/. 6.40
INSTALACION Y COLOCACION DE BIODIGESTOR AUTOLIMPIABLE 3000LT, INC. ACCESORIOS und S/. 5,064.51
REND 2 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 213.48
OPERARIO hh 1.000 4.0000 S/. 16.08 S/. 64.32
PEON hh 3.000 12.0000 S/. 12.43 S/. 149.16
MATERIALES S/. 4,844.62
BIODIGESTOR AUTOLIMPIABLE 3000LT, INC. ACCESORIOS und 1.0000 S/. 4,796.30 S/. 4,796.30
ARENA FINA m3 1.0620 S/. 45.50 S/. 48.32
EQUIPOS Y HERRAMIENTAS S/. 6.40
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 2.13 S/. 6.40
REHABILITACION DE LOSA DEPORTIVA EXISTENTE DE C° f'c=140kg/cm2 e=4" m2 S/. 49.83
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 49.83
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.28 S/. 56.62 S/. 15.85
PISO CEMENTO FROTACHADO Y BRUÑADO E=4" m2 1.00 S/. 33.98 S/. 33.98
JUNTA DE DILATACION e=1" ml 1.33 S/. 1.99 S/. 2.65
REHABILITACION DE LOSA DEPORTIVA Y ARCOS METALICOS EXISTENTE : PINTADO m2 S/. 2.90
REND 8 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 2.90
PINTADO DE LOSA DEPORTIVA m2 1.0000 S/. 2.00 S/. 2.00
PINTADO DE ARCOS METALICOS und 0.0150 S/. 60.00 S/. 0.90
DESMONTAJE DE PUERTA TIPO REJA Y DEMOLICION DE COLUMNETAS DE CONCRETO und S/. 48.73
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 48.73
DESMONTAJE DE PUERTA TIPO REJA m2 1.0000 S/. 33.73 S/. 33.73
DEMOLICION DE COLUMNETAS DE CONCRETO und 2.0000 S/. 7.50 S/. 15.00
DEMOLICION DE VEREDAS m2 S/. 16.39
REND 25 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 15.91
PEON hh 4.000 1.2800 S/. 12.43 S/. 15.91
EQUIPOS Y HERRAMIENTAS S/. 0.48
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.16 S/. 0.48
DEMOLICION DE COLUMNETAS DE CONCRETO und S/. 7.50
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 7.50
DEMOLICION DE COLUMNETAS DE CONCRETO und 1.00 S/. 7.50 S/. 7.50
DEMOLICION DE PORTICO DE INGRESO DE CONCRETO (EXISTENTE) und S/. 150.00
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 150.00
DEMOLICION DE PORTICO DE INGRESO DE CONCRETO (EXISTENTE) und 1.00 S/. 150.00 S/. 150.00
DEMOLICION MODULO m2 S/. 17.00
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 17.00
DEMOLICION DE MODULO ESTRUCTURA EXSISTENTE ml 1.00 S/. 17.00 S/. 17.00
DEMOLICION DE CERCO PERIMETRICO ml S/. 7.50
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 7.50
DEMOLICION DE CERCO PERIMETRICO ml 1.00 S/. 7.50 S/. 7.50
RED INTERNA DE AGUA HASTA 25m. glb S/. 1,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 1,000.00
RED INTERNA DE AGUA HASTA 25m. glb 1.0000 S/. 1,000.00 S/. 1,000.00
RED INTERNA DE DESAGUE HASTA 25m. glb S/. 2,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 2,000.00
RED INTERNA DE DESAGUE HASTA 25m. glb 1.0000 S/. 2,000.00 S/. 2,000.00
RED INTERNA DE AGUA HASTA 50m. glb S/. 2,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 2,000.00
RED INTERNA DE AGUA HASTA 50m. glb 1.0000 S/. 2,000.00 S/. 2,000.00
RED INTERNA DE DESAGUE HASTA 50m. glb S/. 4,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 4,000.00
RED INTERNA DE DESAGUE HASTA 50m. glb 1.0000 S/. 4,000.00 S/. 4,000.00
RED INTERNA DE AGUA HASTA 80m. glb S/. 3,200.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 3,200.00
RED INTERNA DE AGUA HASTA 80m. glb 1.0000 S/. 3,200.00 S/. 3,200.00
RED INTERNA DE DESAGUE HASTA 80m. glb S/. 6,400.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 6,400.00
RED INTERNA DE DESAGUE HASTA 80m. glb 1.0000 S/. 6,400.00 S/. 6,400.00
REFACCION MODULO A EXISTENTE :PINTADO DE MUROS,TARRAJEADO MUROS, COLOCACION DE CERAMICO m2 S/. 78.56
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 78.56
PINTADO DE MUROS m2 2.8000 S/. 6.78 S/. 18.98
TARRAJEO DE MUROS m2 0.5000 S/. 15.10 S/. 7.55
COLOCACION DE CERAMICO m2 1.1000 S/. 47.30 S/. 52.03
REFACCION MODULO A EXISTENTE :PINTADO DE MUROS,TARRAJEADO MUROS m2 S/. 26.53
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 26.53
PINTADO DE MUROS m2 2.8000 S/. 6.78 S/. 18.98
TARRAJEO DE MUROS m2 0.5000 S/. 15.10 S/. 7.55
REFACCION MODULO B EXISTENTE :PINTADO DE MUROS,TARRAJEADO MUROS m2 S/. 26.53
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 26.53
PINTADO DE MUROS m2 2.8000 S/. 6.78 S/. 18.98
TARRAJEO DE MUROS m2 0.5000 S/. 15.10 S/. 7.55
REFACCION MODULO C EXISTENTE :PINTADO DE MUROS,TARRAJEADO MUROS m2 S/. 26.53
REND 1 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 26.53
PINTADO DE MUROS m2 2.8000 S/. 6.78 S/. 18.98
TARRAJEO DE MUROS m2 0.5000 S/. 15.10 S/. 7.55
ACONDICIONAMIENTO BIOCLIMATICO PARA 01 AULA A MAS DE 3600msnm glb S/. 3,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 3,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 01 AULA A MAS DE 3600msnm glb 1.0000 S/. 3,000.00 S/. 3,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 02 AULAS A MAS DE 3600msnm glb S/. 6,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 6,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 02 AULAS A MAS DE 3600msnm glb 1.0000 S/. 6,000.00 S/. 6,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 05 AULAS A MAS DE 3600msnm glb S/. 15,000.00
REND 1 glb/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 15,000.00
ACONDICIONAMIENTO BIOCLIMATICO PARA 02 AULAS A MAS DE 3600msnm glb 1.0000 S/. 15,000.00 S/. 15,000.00
RELLENO COMPACTADO CON MATERIAL PROPIO m3 S/. 35.22
REND 1 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDA S/. 35.22
RELLENO COMPACTADO CON MATERIAL PROPIO m3 1.0000 S/. 35.22 S/. 35.22
COLOCACION PUERTA METALICA PARA VIVIENDA DOCENTE und S/. 750.50
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 750.50
PINTADO DE MUROS und 1.0000 S/. 750.50 S/. 750.50
REHABILITACION DE CERCO PERIMETRICO CON BLOQUES DE CONCRETO 20x20x40 : CIERRE DE VANOS m2 S/. 70.53
REND 8 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 22.29
OPERARIO hh 1.000 1.0000 S/. 16.08 S/. 16.08
PEON hh 0.500 0.5000 S/. 12.43 S/. 6.22
MATERIALES S/. 38.57
CEMENTO PORTLAND TIPO I (42.5 kg) bls 0.5200 S/. 19.65 S/. 10.22
BLOQUE DE CONCRETO 20 X 20 X 40 cm und 11.0000 S/. 2.30 S/. 25.30
ARENA GRUESA m3 0.0620 S/. 42.30 S/. 2.62
MADERA TORNILLO p2 0.0580 S/. 5.95 S/. 0.35
CLAVOS PARA MADERA CON CABEZA DE 2" A 4" kg 0.0200 S/. 4.00 S/. 0.08
EQUIPOS Y HERRAMIENTAS S/. 9.67
ANDAMIO METAL TABLAS ALQUILER d 1.0000 S/. 9.00 S/. 9.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.22 S/. 0.67
SUBPARTIDAS
EXCAVACION ZANJA PARA CIMENTACION m3 S/. 34.14
REND 3 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 33.15
PEON hh 1.000 2.6667 S/. 12.43 S/. 33.15
EQUIPOS Y HERRAMIENTAS S/. 0.99
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.33 S/. 0.99
NIVELACION Y COMP. DE TERRENO CON MATERIAL DE PRESTAMO m3 S/. 41.21
REND 10 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 22.81
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 1.000 0.8000 S/. 12.43 S/. 9.94
MATERIALES S/. 17.71
AGUA m3 0.0126 S/. 13.00 S/. 0.16
MADERA TONILLO p2 2.9400 S/. 5.95 S/. 17.49
CLAVOS KG 0.0100 S/. 5.80 S/. 0.06
EQUIPOS Y HERRAMIENTAS S/. 0.68
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.23 S/. 0.68
CORTE Y HABILITACION DE ACERO CORRUGADO FY=4200kg/cm2 kg S/. 5.72
REND 400 kg/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 0.85
OPERARIO hh 1.000 0.0200 S/. 16.08 S/. 0.32
OFICIAL hh 1.000 0.0200 S/. 13.79 S/. 0.28
PEON hh 1.000 0.0200 S/. 12.43 S/. 0.25
MATERIALES S/. 4.85
ACERO CORRUGADO FY=4200KG/CM2 kg 1.0300 S/. 4.60 S/. 4.74
ALAMBRE N° 16 kg 0.0289 S/. 3.81 S/. 0.11
EQUIPOS Y HERRAMIENTAS S/. 0.03
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.01 S/. 0.03
INST. Y COLOC. DE TANQUE DE POLIETILENO DE AGUA 1100 lt. und S/. 647.57
REND 4 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 57.02
OPERARIO hh 1.000 2.0000 S/. 16.08 S/. 32.16
PEON hh 1.000 2.0000 S/. 12.43 S/. 24.86
MATERIALES S/. 588.84
TANQUE ETERNIT 1.100 LT C/FILTRO INC. ACCESORIOS und 1.0000 S/. 415.51 S/. 415.51
TEE DESAGUE SANITARIA 2" PVC und 1.0000 S/. 3.75 S/. 3.75
CINTA TEFLON DE MEDIA und 1.0000 S/. 2.00 S/. 2.00
NIPLE F°G° 1/2" x 1½" und 1.0000 S/. 1.50 S/. 1.50
VALVULA ESFERICA REDGAL CIM. 1/2" und 1.0000 S/. 17.50 S/. 17.50
VALVULA CHECK SWING 1/2" und 2.0000 S/. 43.63 S/. 87.26
CODOS PVC SP 1/2"x90° und 2.0000 S/. 1.10 S/. 2.20
ADAPTADOR PVC PR 1/2" und 6.0000 S/. 1.25 S/. 7.50
REDUCC. CAMP GALV 3/4"x1/2" und 1.0000 S/. 2.38 S/. 2.38
UNION PVC R 3/4" PU und 1.0000 S/. 1.63 S/. 1.63
REDUCC. PVC-P 3/4"x1/2" C/R und 1.0000 S/. 0.88 S/. 0.88
PEGAMENTO PVC 32 ONZ. und 0.2500 S/. 28.13 S/. 7.03
FORMADOR DE EMPAQUETADURAS 3-H und 0.2500 S/. 7.75 S/. 1.94
TEE DESAGUE 4"x2" PVC und 1.0000 S/. 5.63 S/. 5.63
SOMBRERO DE VENTILACION DESAGUE 2" PVC und 1.0000 S/. 5.63 S/. 5.63
CODO DESAGUE 2"x90° PVC und 3.0000 S/. 1.50 S/. 4.50
CODO DESAGUE 2"x45° PVC und 1.0000 S/. 1.50 S/. 1.50
TUBO DESAGUE 2"x 3m. PVC und 2.0000 S/. 10.25 S/. 20.50
EQUIPOS Y HERRAMIENTAS S/. 1.71
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.57 S/. 1.71
ELABORAC. Y COLOC. DE ARMAZON METALICO PARA TANQUE DE POLIETILENO DE H=3.00 und S/. 834.71
REND 1 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 114.71
MADERA TORNILLO p2 16.4042 S/. 5.95 S/. 97.60
TUBO ACERO NEGRO ELECTROSOLDADO REDONDO 2"X2mmX6m und 0.2480 S/. 68.00 S/. 16.86
PUNTO AZUL E-6011 1/8" 25 Kg kg 0.0176 S/. 13.50 S/. 0.24
SUBCONTRATOS S/. 720.00
SC. M.O. ELABORACION E INSTALACION DE ARMAZON METALICO DE 1.00mX1.00m Y H=3.00m glb 1.0000 S/. 720.00 S/. 720.00
CONCRETO SIMPLE 1:8+25%PM PARA DADOS DE CIMENTACION 0.40X0.40 m3 S/. 292.11
REND 8 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 160.11
OPERARIO hh 3.000 3.0000 S/. 16.08 S/. 48.24
PEON hh 9.000 9.0000 S/. 12.43 S/. 111.87
MATERIALES S/. 120.19
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 3.8000 S/. 19.65 S/. 74.67
HORMIGON m3 0.8500 S/. 30.00 S/. 25.50
PIEDRA MEDIANA 4" m3 0.5000 S/. 30.00 S/. 15.00
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.0500 S/. 11.10 S/. 0.56
MADERA TORNILLO p2 0.0260 S/. 5.95 S/. 0.15
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 11.80
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 1.0000 S/. 7.00 S/. 7.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.60 S/. 4.80
MURO DE SOGA LADRILLO KK DE ARCILLA 18 HUECOS m2 S/. 96.01
REND 8 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 22.29
OPERARIO hh 1.000 1.0000 S/. 16.08 S/. 16.08
PEON hh 0.500 0.5000 S/. 12.43 S/. 6.22
MATERIALES S/. 64.05
CEMENTO PORTLAND TIPO I (42.5 kg) bls 0.2600 S/. 19.65 S/. 5.11
LADRILLO KING KONG DE ARCILLA 18 HUECOS HECHO A MAQUINA 9 X 14 X 24 cm und 44.0000 S/. 1.30 S/. 57.20
ARENA GRUESA m3 0.0310 S/. 42.30 S/. 1.31
MADERA TORNILLO p2 0.0580 S/. 5.95 S/. 0.35
CLAVOS PARA MADERA CON CABEZA DE 2" A 4" kg 0.0200 S/. 4.00 S/. 0.08
EQUIPOS Y HERRAMIENTAS S/. 9.67
ANDAMIO METAL TABLAS ALQUILER d 1.0000 S/. 9.00 S/. 9.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.22 S/. 0.67
MURO DE SOGA CON BLOQUES DE CONCRETO 20x20x40 m2 S/. 76.93
REND 8 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 28.51
OPERARIO hh 1.000 1.0000 S/. 16.08 S/. 16.08
PEON hh 1.000 1.0000 S/. 12.43 S/. 12.43
MATERIALES S/. 38.57
CEMENTO PORTLAND TIPO I (42.5 kg) bls 0.5200 S/. 19.65 S/. 10.22
BLOQUE DE CONCRETO 20 X 20 X 40 cm und 11.0000 S/. 2.30 S/. 25.30
ARENA GRUESA m3 0.0620 S/. 42.30 S/. 2.62
MADERA TORNILLO p2 0.0580 S/. 5.95 S/. 0.35
CLAVOS PARA MADERA CON CABEZA DE 2" A 4" kg 0.0200 S/. 4.00 S/. 0.08
EQUIPOS Y HERRAMIENTAS S/. 9.86
ANDAMIO METAL TABLAS ALQUILER d 1.0000 S/. 9.00 S/. 9.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.29 S/. 0.86
COLOCACION DE REJA METALICA m2 S/. 67.80
REND 20 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBCONTRATO S/. 67.80
SC. COLOCACION DE REJA METALICA m2 1.0000 S/. 67.80 S/. 67.80
m2 S/. 62.29
REND 20 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MATERIALES S/. 32.29
MALLA GALVANIZADA DE #10 DE 2"x2" m2 0.7994 S/. 19.00 S/. 15.19
PUNTO AZUL E-6011 1/8" 25 Kg kg 0.0176 S/. 13.50 S/. 0.24
TUBO ACERO NEGRO ELECTROSOLDADO REDONDO 2"X2mmX6m und 0.2480 S/. 68.00 S/. 16.86
SUBCONTRATO S/. 30.00
SC. M.O. COLOCACION DE MALLA GALVANIZADA m2 1.0000 S/. 30.00 S/. 30.00
COLOCACION DE MALLA GALVANIZADA #10 DE 2" INC MARCO TUBO ELECTROSOLDADO Ø 2"
CONCRETO 1:10+30%PG CIMIENTO CORRIDO m3 S/. 208.80
REND 20 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 78.96
OPERARIO hh 3.000 1.2000 S/. 16.08 S/. 19.30
PEON hh 12.000 4.8000 S/. 12.43 S/. 59.66
MATERIALES S/. 119.39
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 3.6000 S/. 19.65 S/. 70.74
HORMIGON m3 0.8300 S/. 30.00 S/. 24.90
PIEDRA GRANDE 8" m3 0.5000 S/. 30.00 S/. 15.00
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.4000 S/. 11.10 S/. 4.44
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 10.45
VIBRADOR DE CONCRETO 4 HP 2.5" hm 2.000 0.8000 S/. 6.60 S/. 5.28
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.4000 S/. 7.00 S/. 2.80
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.79 S/. 2.37
CONCRETO 1:8+25%PM SOBRECIMIENTO m3 S/. 292.11
REND 8 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 160.11
OPERARIO hh 3.000 3.0000 S/. 16.08 S/. 48.24
PEON hh 9.000 9.0000 S/. 12.43 S/. 111.87
MATERIALES S/. 120.19
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 3.8000 S/. 19.65 S/. 74.67
HORMIGON m3 0.8500 S/. 30.00 S/. 25.50
PIEDRA MEDIANA 4" m3 0.5000 S/. 30.00 S/. 15.00
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.0500 S/. 11.10 S/. 0.56
MADERA TORNILLO p2 0.0260 S/. 5.95 S/. 0.15
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 11.80
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 1.0000 S/. 7.00 S/. 7.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.60 S/. 4.80
CONCRETO F'c = 175 Kg/cm2 COLUMNAS m3 S/. 414.72
REND 8 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 160.11
OPERARIO hh 3.000 3.0000 S/. 16.08 S/. 48.24
PEON hh 9.000 9.0000 S/. 12.43 S/. 111.87
MATERIALES S/. 236.20
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 8.8500 S/. 19.65 S/. 173.90
ARENA GRUESA m3 0.5400 S/. 42.30 S/. 22.84
PIEDRA ZARANDEADA 1/2" m3 0.5500 S/. 51.00 S/. 28.05
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.5000 S/. 11.10 S/. 5.55
MADERA TORNILLO p2 0.2600 S/. 5.95 S/. 1.55
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 18.40
VIBRADOR DE CONCRETO 4 HP 2.5" hm 1.000 1.0000 S/. 6.60 S/. 6.60
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 1.0000 S/. 7.00 S/. 7.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.60 S/. 4.80
CONCRETO F'c = 175 Kg/cm2 VIGAS m3 S/. 377.90
REND 10 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 128.09
OPERARIO hh 3.000 2.4000 S/. 16.08 S/. 38.59
PEON hh 9.000 7.2000 S/. 12.43 S/. 89.50
MATERIALES S/. 235.09
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 8.8500 S/. 19.65 S/. 173.90
ARENA GRUESA m3 0.5400 S/. 42.30 S/. 22.84
PIEDRA ZARANDEADA 1/2" m3 0.5500 S/. 51.00 S/. 28.05
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.4000 S/. 11.10 S/. 4.44
MADERA TORNILLO p2 0.2600 S/. 5.95 S/. 1.55
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 14.72
VIBRADOR DE CONCRETO 4 HP 2.5" hm 1.000 0.8000 S/. 6.60 S/. 5.28
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.8000 S/. 7.00 S/. 5.60
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.28 S/. 3.84
CONCRETO F'c = 175 Kg/cm2 LOSA MACIZA m3 S/. 377.90
REND 10 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 128.09
OPERARIO hh 3.000 2.4000 S/. 16.08 S/. 38.59
PEON hh 9.000 7.2000 S/. 12.43 S/. 89.50
MATERIALES S/. 235.09
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 8.8500 S/. 19.65 S/. 173.90
ARENA GRUESA m3 0.5400 S/. 42.30 S/. 22.84
PIEDRA ZARANDEADA 1/2" m3 0.5500 S/. 51.00 S/. 28.05
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.4000 S/. 11.10 S/. 4.44
MADERA TORNILLO p2 0.2600 S/. 5.95 S/. 1.55
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 14.72
VIBRADOR DE CONCRETO 4 HP 2.5" hm 1.000 0.8000 S/. 6.60 S/. 5.28
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.8000 S/. 7.00 S/. 5.60
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.28 S/. 3.84
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 S/. 56.62
REND 10 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 22.81
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 1.000 0.8000 S/. 12.43 S/. 9.94
MATERIALES S/. 33.13
ALAMBRE N° 8 kg 0.3000 S/. 3.81 S/. 1.14
CLAVOS PARA MADERA CON CABEZA DE 2" kg 0.1600 S/. 4.00 S/. 0.64
CLAVOS PARA MADERA CON CABEZA DE 4" kg 0.1600 S/. 4.00 S/. 0.64
MADERA TORNILLO p2 5.1600 S/. 5.95 S/. 30.70
EQUIPOS Y HERRAMIENTAS S/. 0.68
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.23 S/. 0.68
PISO CEMENTO FROTACHADO Y BRUÑADO E=4" m2 S/. 33.98
REND 70 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 19.72
OPERARIO hh 3.000 0.3429 S/. 16.08 S/. 5.51
PEON hh 10.000 1.1429 S/. 12.43 S/. 14.21
MATERIALES S/. 13.66
CEMENTO PORTLAND bls 0.5460 S/. 19.65 S/. 10.73
HORMIGON m3 0.0252 S/. 30.00 S/. 0.76
AGUA m3 0.0200 S/. 13.00 S/. 0.26
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 0.59
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.1143 S/. 7.00 S/. 0.80
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.20 S/. 0.59
CONCRETO PARA VEREDAS F'=140KG/CM2 , e=4" m2 S/. 33.98
REND 70 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 19.72
OPERARIO hh 3.000 0.3429 S/. 16.08 S/. 5.51
PEON hh 10.000 1.1429 S/. 12.43 S/. 14.21
MATERIALES S/. 13.66
CEMENTO PORTLAND TIPO I bls 0.5460 S/. 19.65 S/. 10.73
HORMIGON m3 0.0252 S/. 30.00 S/. 0.76
AGUA m3 0.0200 S/. 13.00 S/. 0.26
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 0.59
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.1143 S/. 7.00 S/. 0.80
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.20 S/. 0.59
JUNTA DE DILATACION e=1" ml S/. 1.99
REND 100 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 1.78
OPERARIO hh 1.000 0.0800 S/. 16.08 S/. 1.29
PEON hh 0.500 0.0400 S/. 12.43 S/. 0.50
MATERIALES S/. 0.16
ASFALTO m3 0.0052 S/. 30.00 S/. 0.16
EQUIPOS Y HERRAMIENTAS S/. 0.05
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.02 S/. 0.05
CONFORMACION DE BASE AFIRMADA EN VEREDAS H=0.10 m2 S/. 15.71
REND 70 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 8.94
OPERARIO hh 1.000 0.1143 S/. 16.08 S/. 1.84
PEON hh 5.000 0.5714 S/. 12.43 S/. 7.10
MATERIALES S/. 5.81
AGUA m3 0.1000 S/. 13.00 S/. 1.30
AFIRMADO m3 0.1250 S/. 35.20 S/. 4.40
COMBUSTIBLE (GASOLINA) gln 0.0100 S/. 11.10 S/. 0.11
EQUIPOS Y HERRAMIENTAS S/. 0.95
COMPACTADOR VIBRATORIO TIPO PLANCHA 5.8 HP hm 1.000 0.11 S/. 6.00 S/. 0.69
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.09 S/. 0.27
ml S/. 180.00
REND 60 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBCONTRATO S/. 180.00
SC. REGILLA METALICA BORDE DE ANGULOS1"X1" Y PLATINA 1" A=0.30m ml 1.0000 S/. 180.00 S/. 180.00
CONCRETO CANALETA DE DRENAJE PLUVIAL INC. REGILLA METALICA m2 S/. 33.98
REND 70 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 19.72
OPERARIO hh 3.000 0.3429 S/. 16.08 S/. 5.51
PEON hh 10.000 1.1429 S/. 12.43 S/. 14.21
MATERIALES S/. 13.66
CEMENTO PORTLAND TIPO I (42.5 kg) bls 0.5460 S/. 19.65 S/. 10.73
HORMIGON m3 0.0252 S/. 30.00 S/. 0.76
AGUA m3 0.0200 S/. 13.00 S/. 0.26
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 0.59
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 0.1143 S/. 7.00 S/. 0.80
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.20 S/. 0.59
CONCRETO 1:8+25%PM MURO DE CONTENCION m3 S/. 309.46
REND 8 m3/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 160.11
OPERARIO hh 3.000 3.0000 S/. 16.08 S/. 48.24
PEON hh 9.000 9.0000 S/. 12.43 S/. 111.87
MATERIALES S/. 137.55
CEMENTO PORTLAND SOL TIPO I (42.5 kg) bls 4.2000 S/. 19.65 S/. 82.53
HORMIGON m3 0.8500 S/. 30.00 S/. 25.50
PIEDRA MEDIANA 4" m3 0.6500 S/. 30.00 S/. 19.50
AGUA m3 0.1840 S/. 13.00 S/. 2.39
COMBUSTIBLE (GASOLINA) gln 0.5000 S/. 11.10 S/. 5.55
MADERA TORNILLO p2 0.0260 S/. 5.95 S/. 0.15
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 11.80
MEZCLADORA DE CONCRETO 12 P3 hm 1.000 1.0000 S/. 7.00 S/. 7.00
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.60 S/. 4.80
MURO DE PIRCA DE PIEDRA H=0.80 m2 S/. 156.49
REND 10 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 102.36
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 9.000 7.2000 S/. 12.43 S/. 89.50
MATERIALES S/. 51.06
CEMENTO PORTLAND TIPO I (42.5 kg) bls 1.5000 S/. 19.65 S/. 29.47
PIEDRA GRANDE m3 0.3300 S/. 30.00 S/. 9.90
ARENA GRUESA m3 0.2000 S/. 42.30 S/. 8.46
AGUA m3 0.1000 S/. 13.00 S/. 1.30
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 3.07
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.02 S/. 3.07
REGILLA METALICA BORDE DE ANGULOS1"X1" Y PLATINA 1" A=0.30m
MURO DE PIRCA DE PIEDRA H=1.20 m2 S/. 161.62
REND 10 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 102.36
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 9.000 7.2000 S/. 12.43 S/. 89.50
MATERIALES S/. 56.18
CEMENTO PORTLAND TIPO I (42.5 kg) bls 1.5000 S/. 19.65 S/. 29.47
PIEDRA GRANDE m3 0.3600 S/. 30.00 S/. 10.80
ARENA GRUESA m3 0.3000 S/. 42.30 S/. 12.69
AGUA m3 0.1000 S/. 13.00 S/. 1.30
ADITIVO CURADO QUIMICO gln 0.0400 S/. 48.00 S/. 1.92
EQUIPOS Y HERRAMIENTAS S/. 3.07
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 1.02 S/. 3.07
ACARREO, COLOCACION Y TENDIDO DE PIEDRA CONFITILLO PARA JUEGOS INFANTILES m2 S/. 8.89
REND 80 m2/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 3.29
OPERARIO hh 0.500 0.0500 S/. 16.08 S/. 0.80
PEON hh 2.000 0.2000 S/. 12.43 S/. 2.49
MATERIALES S/. 5.50
PIEDRA ZARANDEADA 1/4" m3 0.1000 S/. 55.00 S/. 5.50
EQUIPOS Y HERRAMIENTAS S/. 0.10
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.03 S/. 0.10
SARDINEL DE CONCRETO 0.10X0.30m ml S/. 20.34
REND 1 ml/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
SUBPARTIDAS S/. 20.34
EXCAVACION ZANJA PARA CIMENTACION m3 0.02 S/. 34.14 S/. 0.68
CORTE Y HABILITACION DE ACERO CORRUGADO FY=4200kg/cm2 kg 1.43 S/. 5.72 S/. 8.16
CONCRETO 1:8+25%PM SOBRECIMIENTO m3 0.0200 S/. 292.11 S/. 5.84
ENCOFRADO Y DESENCOFRADO DE MADERA TORNILLO EN BRUTO m2 0.1000 S/. 56.62 S/. 5.66
DESMONTAJE DE PUERTA TIPO REJA und S/. 33.73
REND 10 und/dia
DESCRIPCION UND CUADRILLA CANTIDAD PRECIO (S/.) PARCIAL (S/.)
MANO DE OBRA S/. 32.75
OPERARIO hh 1.000 0.8000 S/. 16.08 S/. 12.86
PEON hh 2.000 1.6000 S/. 12.43 S/. 19.89
EQUIPOS Y HERRAMIENTAS S/. 0.98
HERRAMIENTAS MANUALES %M.O. %mo 3.00 S/. 0.33 S/. 0.98