Upload
archna-chaudhary
View
232
Download
0
Embed Size (px)
Citation preview
7/31/2019 Assemly Line Balancing
1/11
Assembly Line Balancing
7/31/2019 Assemly Line Balancing
2/11
Line balancing
The techniques employed for design of
product layouts is known as line balancing.
The layout design seeks to identify the
minimum no. of resources require to meet a
targeted production rate and the order inwhich these resources are to be arranged so
that the production process become smooth.
7/31/2019 Assemly Line Balancing
3/11
Assembly Line Balancing
Analysis of production lines
Nearly equally divides work between
workstations while meeting requiredoutput
Objectives
Maximize efficiency
Minimize number of
work stations
7/31/2019 Assemly Line Balancing
4/11
An Assembly Line Layout
7/31/2019 Assemly Line Balancing
5/11
Line BalancingSome measures of interest
oductionDesiredActual
TimeAvailableTimeCycleDesiredActual
Pr)()(
TimeCycle
timestaskallofSumrequiredstationsworkofNoMinimum .
timeCyclensworkstatioofNumber
timestaskallofSumnUtilisatiosourceAverage
*Re
7/31/2019 Assemly Line Balancing
6/11
A factory working in 2 shifts each of8 hours produces 24,000 electricbulbs using a set of workstations.
Using this information compute theactual cycle time of the plantoperation.
There are 8 tasks required to
manufacture the bulb. The sum of alltask times is equal to 12 seconds.How many workstations are requiredto maintain this level of production ifcombining of tasks into that many
workstations is a feasible alternative?
Example
7/31/2019 Assemly Line Balancing
7/11
Solution to example
Available time = 2*8*60*60 = 57,600 seconds
Actual production = 24,000 electric bulbs
Therefore, using equation 8.2
Cycle time for each bulb is seconds
This means that the factory is producing a bulb every 2.4 seconds.
No. of work stations required =
Therefore the tasks are to be split among the five stations such that each
workstation will have sum of the task times to be 2.4 seconds.
4.2000,24
600,57
5
4.2
12
7/31/2019 Assemly Line Balancing
8/11
Example of line balancingA computer manufacturer needs to design assembly stations in the
factory where the cabinet housing the hard disk, mother board and
other accessories is to be made. The factory currently works for one
shift of 8 hrs. The tasks, their duration and their precedence
relationships are given below:
Task Description Duration (in sec.) Precedence
A Assemble & position the base unit 70 -
B Install hard disk 80 A
C Install mother board 40 A
D Insert ports 20 A
E Install speaker 40 AF Connect relevant modules to disk 30 B,C
G Install controller 50 C
H Visually inspect & close with
a cover plate 50 D,E,F,G
7/31/2019 Assemly Line Balancing
9/11
If the cycle time is 80 seconds, what will the daily
production of cabinets be?
If the desired production rate is 320 cabinets perday, what is the maximum permissible cycle time?
What I the maximum and minimum no. of
workstations required to maintain this daily
production rate?
Design an assembly setup with 5 workstations.
7/31/2019 Assemly Line Balancing
10/11
Example
The Model J Wagon is to be assembled on a
conveyer belt.Five hundred wagons are
required per day is 420 minutes, and theassembly setups and times for the wagon
are given in table.
Find the balance that minimizes the no.ofworkstations, subject to cycle time and
precedence constraints.
7/31/2019 Assemly Line Balancing
11/11
Task Duration Tasks must precede
A 45 -
B 11 A
C 9 B
D 50 -
E 15 DF 12 C
G 12 C
H 12 E
I 12 E
J 8 F,G,H,I
K 9 K