Assemly Line Balancing

Embed Size (px)

Citation preview

  • 7/31/2019 Assemly Line Balancing

    1/11

    Assembly Line Balancing

  • 7/31/2019 Assemly Line Balancing

    2/11

    Line balancing

    The techniques employed for design of

    product layouts is known as line balancing.

    The layout design seeks to identify the

    minimum no. of resources require to meet a

    targeted production rate and the order inwhich these resources are to be arranged so

    that the production process become smooth.

  • 7/31/2019 Assemly Line Balancing

    3/11

    Assembly Line Balancing

    Analysis of production lines

    Nearly equally divides work between

    workstations while meeting requiredoutput

    Objectives

    Maximize efficiency

    Minimize number of

    work stations

  • 7/31/2019 Assemly Line Balancing

    4/11

    An Assembly Line Layout

  • 7/31/2019 Assemly Line Balancing

    5/11

    Line BalancingSome measures of interest

    oductionDesiredActual

    TimeAvailableTimeCycleDesiredActual

    Pr)()(

    TimeCycle

    timestaskallofSumrequiredstationsworkofNoMinimum .

    timeCyclensworkstatioofNumber

    timestaskallofSumnUtilisatiosourceAverage

    *Re

  • 7/31/2019 Assemly Line Balancing

    6/11

    A factory working in 2 shifts each of8 hours produces 24,000 electricbulbs using a set of workstations.

    Using this information compute theactual cycle time of the plantoperation.

    There are 8 tasks required to

    manufacture the bulb. The sum of alltask times is equal to 12 seconds.How many workstations are requiredto maintain this level of production ifcombining of tasks into that many

    workstations is a feasible alternative?

    Example

  • 7/31/2019 Assemly Line Balancing

    7/11

    Solution to example

    Available time = 2*8*60*60 = 57,600 seconds

    Actual production = 24,000 electric bulbs

    Therefore, using equation 8.2

    Cycle time for each bulb is seconds

    This means that the factory is producing a bulb every 2.4 seconds.

    No. of work stations required =

    Therefore the tasks are to be split among the five stations such that each

    workstation will have sum of the task times to be 2.4 seconds.

    4.2000,24

    600,57

    5

    4.2

    12

  • 7/31/2019 Assemly Line Balancing

    8/11

    Example of line balancingA computer manufacturer needs to design assembly stations in the

    factory where the cabinet housing the hard disk, mother board and

    other accessories is to be made. The factory currently works for one

    shift of 8 hrs. The tasks, their duration and their precedence

    relationships are given below:

    Task Description Duration (in sec.) Precedence

    A Assemble & position the base unit 70 -

    B Install hard disk 80 A

    C Install mother board 40 A

    D Insert ports 20 A

    E Install speaker 40 AF Connect relevant modules to disk 30 B,C

    G Install controller 50 C

    H Visually inspect & close with

    a cover plate 50 D,E,F,G

  • 7/31/2019 Assemly Line Balancing

    9/11

    If the cycle time is 80 seconds, what will the daily

    production of cabinets be?

    If the desired production rate is 320 cabinets perday, what is the maximum permissible cycle time?

    What I the maximum and minimum no. of

    workstations required to maintain this daily

    production rate?

    Design an assembly setup with 5 workstations.

  • 7/31/2019 Assemly Line Balancing

    10/11

    Example

    The Model J Wagon is to be assembled on a

    conveyer belt.Five hundred wagons are

    required per day is 420 minutes, and theassembly setups and times for the wagon

    are given in table.

    Find the balance that minimizes the no.ofworkstations, subject to cycle time and

    precedence constraints.

  • 7/31/2019 Assemly Line Balancing

    11/11

    Task Duration Tasks must precede

    A 45 -

    B 11 A

    C 9 B

    D 50 -

    E 15 DF 12 C

    G 12 C

    H 12 E

    I 12 E

    J 8 F,G,H,I

    K 9 K