Upload
truonganh
View
214
Download
0
Embed Size (px)
Citation preview
Pipeline Operation and Maintenance | 10.4.2014
25
Internal Company Standard
Basis for Assessment of Pipeline Integrity
Describes basic principles of pipeline
integrity
Describes methods and procedures for
assessment of pipeline condition
Describes type, extent and frequency of
testing and assessment
Contains assessment criteria and limit values
Describes possible mitigating measures.
Standardised Integrity Assessment
Company Standard
Basic Principles of Pipeline Integrity;
Rules and Procedures for Verification
of Technical Pipeline Integrity
Based on EN 16348
Pipeline Operation and Maintenance | 10.4.2014
26 Integrity Risks
Corrosion by Interference
AC corrosion
DC stray current corrosion
General Corrosion
• Under shielding coatings
• Due to insufficient cp
• Within casings
• Under concrete saddles
Cracks
Stress corrosion cracking
…
Mechanical Damage
(Third party interference)
By trenching machines
Drilling
Dents
…
Milling defects
Material defects
Inclusions
Laminations
Rolling defect
Grindings
Routing and Strain
Pipeline displacement
Additional strain
Geometrical Defects
Expansions
Dents
Miscellaneous
Girth weld anomalies
Lightning puncture
…
Pipeline Operation and Maintenance | 10.4.2014
27
1912 1958 1963 today Year of construction
Not piggable
Gas or electrically welded
Old pipe joints
Long operational period without CP
Not piggable
Electrically welded
CP almost since
construction
Piggable
(sections ≥ 20 km, > DN 200)
Electrically welded
CP since construction up to 1954 since 1955
Main Tool for
Integrity Assessment
Pipeline Classification for Integrity Assessment
Joint assessment (PIA2)
Intensive measurement
Casing survey
Intensive measurement
Casing survey
Inline Inspection
(Intelligent Pigging)
Not piggable
(e.g. sections < 20 km)
Electrically welded
CP since construction
Pipeline Category I Pipeline
Category II Pipeline Category III
Based on EN 16348
Pipeline Operation and Maintenance | 10.4.2014
28
Integrity Assessment Process
Inline inspection
Measures (Repair, securing, refurbishment, replacement)
Priorisation and determination
of assessment method
Pipeline category I Sleeve sockets
1912 – 1958
Pipeline category II Not piggable
BJ 1959 - today
Pipeline category III piggable
1963 - today
High voltage assessment
Intensive measurement
Assessment and detail assessment (corrosion protection, materials)
0,0
0,2
0,4
0,6
0,8
1,0
1,2
1,4
1,6
1,8
Ltg 15 Ltg 7 Ltg 6 Ltg 1 Ltg 9 Ltg 5 Ltg 2
Hauptleitung inkl. Anschlüssen
Sch
ad
en
szah
l p
ro J
ah
r &
100 k
m
Assessm. of casing pipes
Sleeve sockets (PIA²)
Verification of Pipeline Integrity (Documentation, definition of expiry date)
Based on EN 16348
Pipeline Operation and Maintenance | 10.4.2014
29
Integrity Measures and Intervals
Integrity Measure or Element Interval Reference
As-built documentation once G 463
Pressure test / stress test once G 463
Verification of CP effectiveness (e.g. by intensive measurement) once GW 10
Check of pressure safeguarding every four years G 495
CP remote monitoring every two months GW 10
Check of CP, off-potential measurements every three years GW 10
Check of AC interference situation every five years GW 10
Pipeline monitoring and maintenance (incl. tightness testing) Depending on
pipeline routing G 466-1
Valve functional testing annual G 466-1
Integrity assessment acc. to integrity
strategy (15 – 25 y)
G 466-1,
RN 210-001
Inline inspection acc. to ILI strategy
(15 – 25 y)
G 466-1,
RN 210-001
Assessment of old joints typically once RN 210-001
Strategy in the case of previous damage Case-by-case …
Excavation, NDT, check for corrosion, ... Case-by-case …
Integrity Assessment Tools
Contents
OGE at a Glance, OGE Pipelines in Germany
Integrated Management System
Pipeline Design & Safety Philosophy
Pipeline Integrity Management System
Corrosion Control
Hydrostatic and Tightness Testing
Inline Inspection Techniques
Defect and Failure Investigation
Troubleshooting & Repair-Techniques
Conclusions
Pipeline Operation and Maintenance | 10.4.2014
30
Pipeline Operation and Maintenance | 10.4.2014
31
CP-Tools/Methods and Intervals
CP-Tool / Method Example Reference Interval
Verification of cp effectiveness e.g. Intensive measurement GW 10 once
CP remote monitoring GW 16 2 month
Off-potantial measurement at
selected test stations GW 10 3 years
CP survey measurements
at casings GW 10, AfK 1 3 years
Review and check of AC
interference situation AfK 3, GL 718-079 5 years
Intensive measurement Integrity assessment G 466-1, RN 210-001 15 – 25 years 1
Intesive fault detection
Location of defects within
warranty period RN 268-022 (TVB)
Case by case AC corrosion assessment AfK 11
Verification of ILI features G 466-1, RN 210-001
Mobile cp probe Verification of cp effectiveness GW 10
Case by case Integrity assessment G 466-1, RN 210-001
Integrity Assessment Tools
1) Depending on condition of pipeline
DVGW G …
Corrosion Protection of Burried Pipelines
Burried pipelines are protected against corrosion by a combination of
electrochemical protection (cathodic corrosion protection) and an electrically insulating
coating (passive corrosion protection).
Cathodic Protection (CP)
Coke Groundbed Reference electrode
Coated pipeline
Anode (+)
Transformer/ Rectifier
Negative drain (-)
Protective current
Coating defect
Test post
Test coupon
Power supply
Earthing strip
Decoupling device
+ -
Passive Corrosion Protection
32
Pipeline Operation and Maintenance | 10.4.2014
EN 12954, DVGW GW 12
Prerequesites for Installation of CP (EN 12954, GW12)
Electrical separation from grounded installations
(e.g. Metering- and compressor stations, grounding systems, e-valves)
Use of unsulating couplings or flanges
Longitudinal electrical conductivity
fullfilled for continuously welded pipelines
Electrically insulating coating
factory and field coating of all installations
33
Pipeline Operation and Maintenance | 10.4.2014
EN 12954, DVGW GW 12
Typical Corrosion Risks on Pipelines
Corrosion under disbonded coatings
Corrosion within
casings
Corrosion under concrete saddles
Corrosion due to insufficient CP
AC corrosion
34
Pipeline Operation and Maintenance | 10.4.2014
Coating insulation test (at construction stage)
Drainage test (at construction stage)
Intensive defect detection survey (within warranty period)
Intensive measurement survey (existing pipelines)
Quality Assurance by Corrosion Protection Measurements
Main objective is to prevent coating defects
35
Pipeline Operation and Maintenance | 10.4.2014
DVGW GW 12, GW 10, …
Intensive Measurement (CIPS + DCVG)
V
V
V
Cable connection
CP protected, coated pipeline
Coating defect
Reference electrode
Voltage
gradient
measurement
Uon, Uoff
Potential measurement
Uon , Uoff
e.g. >10m
e.g. 5 m
36
Pipeline Operation and Maintenance | 10.4.2014
AfK No. 10 DVGW GW 27, EN 13509
Transformer/
Rectifier
Coating defect
Casing pipe Product pipe
Pipeline
Rmi > Ra,min CP is effecitve
Rmi < Ra,min Assessment not possible
Ra,min = Spread resistance of a
coating defect that can just be
protected
Rmi = Calculated spread resistance of
coating defects within the casing pipe
(AfK Recommendation No. 1)
Assessment of Casings (Resistance Comparison Method)
37
Pipeline Operation and Maintenance | 10.4.2014
AfK No 1 DVGW GW 20
High-Voltage Interference
steel pipeline
coating fault
(AC-voltage) corrosion
high voltage line
coating
U AC U AC
High-voltage power line
Coating defect
with AC corrosion
Pipeline IAC
JAC
JAC
max. touch voltage
AC corrosion
Vo
ltag
e U
AC
Vo
ltag
e U
AC
Calculated
voltage without
grounding systems
Calculated
voltage with
grounding systems
Integrity Assessment Tools 38
Pipeline Operation and Maintenance | 10.4.2014
AfK No. 3 DVGW GW 22
Development of a Third Party Interference
Detection System Additional Safety
Benefit:
Real-time identification of a damage (liability)
Increased level of safety
Potential for optimisation of survey cycles
„Hazard“ „Protection“
TPI detection by CP measurement technique
New approach for pipeline protection
against external damage
TGL
W, 39
Beyond DVGW GW …
The Idea
40
Pipeline Operation and Maintenance | 10.4.2014
Beyond DVGW GW …
The Idea
41
Pipeline Operation and Maintenance | 10.4.2014
Beyond DVGW GW …
Realtest 11.03.2009, Test Scenario
TestPipeline DN 300, Length 12 m
Test-
post
Gaspipeline
DN 1200
PN 100
42
Pipeline Operation and Maintenance | 10.4.2014
Real Test
Test Pipeline before Backfilling
Minidigger
22 ton Chain Dredger
43
Pipeline Operation and Maintenance | 10.4.2014
Beyond DVGW GW …
Real Tests
Test 2 Test 4
44
Pipeline Operation and Maintenance | 10.4.2014
Beyond DVGW GW …
Contents
OGE at a Glance, OGE Pipelines in Germany
Integrated Management System
Pipeline Design & Safety Philosophy
Pipeline Integrity Management System
Corrosion Control
Hydrostatic and Tightness Testing
Inline Inspection Techniques
Defect and Failure Investigation
Troubleshooting & Repair-Techniques
Conclusions
Pipeline Operation and Maintenance | 10.4.2014
45
MOP
Pressure test at min. 1.3 MOP
Time
Inte
rnal
pre
ssu
re Rt0.5 = 1.6 MOP
Stress Test = Hydrostatic Test close to yield strength to identify and
eliminate pipe with serious defects, e.g. weld defects, out of spec
material; but no minor defects (VDTÜV Working sheet No. 1060)
Stress Test 46
Pipeline Operation and Maintenance | 10.4.2014
DVGW G 463
Mill Defects found by Stress Test (at / after Construction)
Overlapping from
Plate rolling
Inclusion & Lamination
47
Pipeline Operation and Maintenance | 10.4.2014
DVGW G 463
Cracks & Gouges found by Stress Test (Rehabilitation)
External Interference
Fatigue Crack Girth Weld Defects
SCC
48
Pipeline Operation and Maintenance | 10.4.2014
DVGW G 463