SHAKER Consultancy Group

System Philosophy

Main objective of the systemControl and Monitoring of all HVAC equipments.

Monitoring of all the available electromechanical works (Electrical , Light current , Plumbing and Fire fighting).

Classification of the systemFirst category.

Basic features & functions for controlling and monitoring.

Interfaces for mechanical and electrical systems.

Second category.Maintenance management.

Energy conservation and historical data/events archiving.

Building and Energy Management System 2June 2009

Page 3: BEMS - Presentation

SHAKER Consultancy Group

System Structure

Building and Energy Management System 3June 2009

Page 4: BEMS - Presentation

SHAKER Consultancy Group

System Interfaces

Direct Digital Controllers placed in mechanical rooms controlling and monitoring HVAC equipments.

Interfaces with Plumbing and Fire Fighting

Interfaces with Electrical Power Services

Interfaces with Low-Current Systems

Interfaces with Fire Alarm System

Building and Energy Management System 4June 2009

Page 5: BEMS - Presentation

SHAKER Consultancy Group

Interfaces Between Main MEP Equipments and BEMS - continue

Building and Energy Management System 5June 2009

Page 6: BEMS - Presentation

SHAKER Consultancy Group

Interfaces Between Main MEP Equipments and BEMS - continue

Building and Energy Management System 6June 2009

Page 7: BEMS - Presentation

SHAKER Consultancy Group

HVAC Equipment Control Chilled Water System

Building and Energy Management System 7June 2009

Page 8: BEMS - Presentation

SHAKER Consultancy Group

HVAC Equipment Control Condensed Water System

Building and Energy Management System 8June 2009

Page 9: BEMS - Presentation

SHAKER Consultancy Group

HVAC Equipment Control Circulating Air Handling Unit

Building and Energy Management System 9June 2009

Page 10: BEMS - Presentation

SHAKER Consultancy Group

HVAC Equipment Control TFA - Air Handling Unit

Building and Energy Management System 10June 2009

Page 11: BEMS - Presentation

SHAKER Consultancy Group

HVAC Equipment Control Fan Coil Unit

Building and Energy Management System 11 June 2009

Page 12: BEMS - Presentation

SHAKER Consultancy Group

Lighting Control

Building and Energy Management System 12June 2009

Page 13: BEMS - Presentation

SHAKER Consultancy Group

Electrical Equipment MonitoringTypical MDB Panel

Building and Energy Management System 13June 2009

Page 14: BEMS - Presentation

SHAKER Consultancy Group

Electrical Equipment MonitoringTypical EMDB Panel

Building and Energy Management System 14June 2009

Page 15: BEMS - Presentation

SHAKER Consultancy Group

Electrical Equipment MonitoringRing Main Unit

Building and Energy Management System 15June 2009

Page 16: BEMS - Presentation

SHAKER Consultancy Group

Electrical Equipment MonitoringUninterruptable Power Supply (UPS)

Building and Energy Management System 16 June 2009

Page 17: BEMS - Presentation

SHAKER Consultancy Group

Electrical Equipment MonitoringAutomatic Transfer Switch (ATS)

Building and Energy Management System 17June 2009

Page 18: BEMS - Presentation

SHAKER Consultancy Group

Electrical Equipment MonitoringElevators

Building and Energy Management System 18June 2009

Page 19: BEMS - Presentation

SHAKER Consultancy Group

Electrical Equipment MonitoringGenerator and Fuel System

Building and Energy Management System 19June 2009

Page 20: BEMS - Presentation

SHAKER Consultancy Group

Electrical Equipment MonitoringLight Current Systems