Coal f ired Fluid bed boiler
PT BASUKI PRATAMA ENGINEERING
Page 1 of 12D:/Adat/Penawar/Std/Spek2008/BHF08-13_08R0.doc
PT BASUKI PRATAMA ENGINEERINGproposes to offer,the equipment and
services contained in this proposalOne Fluid bed Boiler
Boiler Model : BHF-08-13
Nominal Rating (MCR) : 8,000 kg/hrHeat output : 5,873 kW
Design Pressure : 13 bar g
Design Code : Depnaker RI
Fuel Specification : Bituminous coal - Indonesia
Gross Calorific Value : 3500 - 6200 kcal/kg
Electrical power : 380 V 50 Hz 3 phase
SALIENT FEATURES
HIGH EFFICIENCY
FLUID BED COMBUSTION FOR BURNING COAL
WELDED MEMBRANE WALL CONSTRUCTION FORFURNACE WALLS
IN BED TUBE BUNDLE
RELIABLE FIRE TUBE STEAM GENERATOR WITH LARGEWATER VOLUME
PACKAGED BOILER WITH LITTLE SITE WORK
NATURAL CIRCULATION DESIGN
ELECTRIC VARIABLE SPEEED DRIVE FOR FUEL FEEDCONTROL
FULL BOILER CAPACITY WITH ANY KIND OF COAL
8/9/2019 BHF 08-13_08R0.pdf
2/12
COAL fired fluid bed boi ler
PT Basuki Pratama Engineering Page 2 of 12
D:/Adat/Penawar/Std/BHF-New/BHF22013.doc
SCOPE OF SUPPLY
- Fluid bed furnace with casing, refractory lining and air distributor with nozzles
- Water wall assembly with headers
- Fire tube boiler shell with two gas passes and necessary nozzles, manhole, head holes etc.
- In-bed tube bundle with headers.
- Riser and down comers for natural circulation.
- Access ladder and platform for boiler shell
- Insulation and galvanized iron cladding
- Two number screw feeders with variable frequency drives.
- Valves and mountings as shown in the P&I diagram
- Modulating water level control including three way control valve
- Independent extra low level safety
- Two feed water pumps
- Control panel including all panel mounted instruments and starters for all drives.
- Cyclone separator complete with rotary lock valve.
- Floor mounted induced draft fan & forced draft fan
- Operating and maintenance manuals
8/9/2019 BHF 08-13_08R0.pdf
3/12
COAL fired fluid bed boi ler
PT Basuki Pratama Engineering Page 3 of 12
D:/Adat/Penawar/Std/BHF-New/BHF22013.doc
DETAILED EQUIPMENT SPECIFICATIONS
1 Fluid bed Boiler
Boiler Model : BHF-08-13
Type : Horizontal combined
water and fire tube three pass
Fire tube size : 76.1 x 3.2 mm thk
Stay tube size : 76.1 x 5 mm thick
Diameter of shell : 2200 mm
Length of shell : 5400 mm
Total hating area of boiler : 223 m2
Material of construction
Shell : SA 515/516 Gr. 60/70
Tubes : BS 3059 Gr. 320 ERWReversing chamber : Mild steel
Water wall assembly
Tube material : BS 3059 Gr 320 ERW
Tube size : 50.8 x 3.2 mm thk.
Header material : A 106 Gr. B
Total heating surface : 21.4 m2
Construction : Membrane wall
In bed tube bundle
Tubes material : DIN 17175 St 35.8
Seamless tubes
Tube size : 50.8 x 5 mm thk.
2 Fluid bed combustor
Type of combustor : atmospheric fluid bed
Type of distributor : Steel plate with nozzles
Material of nozzle : Stainless steel
Fuel Specification : Bituminous Coal - Indonesia
Gross Calorific Value : 3500 - 6200 kcal/kg
Coal size required : 100 % below 15 mm with max
15% below 2 mm sieve.
Maximum water content : 20 %
Type of sand : Silica sandSize : 0.8 1.2 mm
8/9/2019 BHF 08-13_08R0.pdf
4/12
COAL fired fluid bed boi ler
PT Basuki Pratama Engineering Page 4 of 12
D:/Adat/Penawar/Std/BHF-New/BHF22013.doc
3 Forced draft fan
Quantity : One
Type : Centrifugal fan
Type of fluid : Fresh air
Service temperature : 40 deg. C
Type of drive : Direct
Material : Mild steel
Make : Basuki
Motor protection : IP 55
Paint protection : Industrial paint
Power : 37 kW
4 Induced draft fan
Quantity : One
Type : Centrifugal fan
Type of fluid : Flue gas
Max. Service temperature : 300 deg. C
Type of drive : Indirect drive
Material : Mild steel
Make : Basuki
Motor protection : IP 55
Paint protection : Heat Resistant paint
Power : 40 kW
5 Boiler feed water pump
Quantity : Two
Type : Multi stage centrifugal pump
Orientation : vertical in line
Capacity : 9.6 m3/hr
Head : 155 MLC
Max. Ambient temperature : 40 deg. C
Max. Fluid working temperature : 120 deg. C
Rotation : 2900 Rpm
Connection : Flange
Power : 7.5 kWMake : Grundfos/KSB
6 Dust collector
a. Multicyclone
Quantity : One
Type : Multy cyclone with Rotary
Lock Valve
Gas temperature : 240 C
Gas side pressure drop : 100 mm Wg
Material of construction : Mild steel
8/9/2019 BHF 08-13_08R0.pdf
5/12
COAL fired fluid bed boi ler
PT Basuki Pratama Engineering Page 5 of 12
D:/Adat/Penawar/Std/BHF-New/BHF22013.doc
Attachments to cyclone : Motorized rotary air lock
Power : 0.37 kW
b. Wet Scrubber
Quantity : One
Type : Ventury scrubber
Gas side pressure drop : 100 mm Wg
Material of construction : Stainless steel
Attachments to scrubber : Droplet separator,
Water pump
Water pump
Type : Single stage centrifugal
Orientation : Horizontal
Capacity : 9.6 m3/hr
Service : Fresh water
Connection : Flange PN16
Rotation : 1450 Rpm
Power : 2.2 kW 6
7 Safety valves
Type : Fully lift safety valve with closed
lifting device closed bonnet
Nominal pressure : PN 16
Connection : Flange DIN STD 2533
Body material : GG-25
Range temperature : -1 Deg. C up to 300 deg. CQuantity : Two
Capacity : 8,000 Kg/hr
Set pressure : 13 barg and 12.5 barg
Make : ARI, Germany
8 Thermal insulation
Material : Mineral wool slabs, lightly resin
Bonded
Thickness : 100 mm
Density : 80 kg/m3
Cladding material : Galvanized iron sheetThickness : 0.6 mm
9 Control panel
Type : Self standing
Incomer rating : 380 V 50 Hz, 3 phase, 4 wire
Doors : 1 door front opening type
The panel includes all panel mounted instruments and drives for all connected motors.
8/9/2019 BHF 08-13_08R0.pdf
6/12
COAL fired fluid bed boi ler
PT Basuki Pratama Engineering Page 6 of 12
D:/Adat/Penawar/Std/BHF-New/BHF22013.doc
10 Ducting for air and flue gas (Optional price)
Material of construction : Mild steel
Velocity in ducts : 12 m/s maximum
Finish coat : Heat resistant paint
Color : Silver
11 Coal handling system (Optional price)
We can offer a complete coal handling plant for the boiler. The coal storage and feeding
system includes the following components
a) Coal bunker near boiler
Capacity : 4 m3
Height approx. : 8 meters
Location : Mounted above the screw feeders
Material of construction : Mild steel bunker on mild steel
structure
Finish coal : Industrial paint
b) Belt Conveyor
Capacity : 3,000 kg/hr
Drive power : 2.2 kW
Accessories :
Coal receiving hopperCapacity : 2 m3
Material of construction : Mild steel
Location : Below ground level
Finish coal : Industrial paint
12 Chimney (Optional p rice)
Type : Self standing chimney
Diameter : 850 mm at the top
Height : 20 meters
Material construction : Carbon steel
Finish coat : Heat resistant paintAccessories : Ash door
13 Ladder for chimney (Optional price)
Type : ladder with cage
Material : mild steel
Accessories : service platform
Finish coat : Industrial paint
8/9/2019 BHF 08-13_08R0.pdf
7/12
COAL fired fluid bed boi ler
PT Basuki Pratama Engineering Page 7 of 12
D:/Adat/Penawar/Std/BHF-New/BHF22013.doc
14 Water Tank (Optional price)
Type : Horizontal thorispherical disc end
Water contents : 8 m3
Material construction : Carbon steel
Accessories : Discharge Valve and drain valve
Height of the feed water tank at least 2.5 m depending on feed water temperature
15 Instrumentation and control including the following
- Modulating water level control including level transmitter, controller and
motorized three way control valve
- Minimum water safety by independent conductivity type level electrodes
- Boiler pressure safety including two number full lift safety valves, two number
pressure switches
- Flue gas temperature control including temperature switch and alarm
- Water flow meter
- Two bed temperature indicators with control
16. Valves and fittings
The boiler system includes the following valves and fittings. Some of these are installed
on the pressure part. Others have to be installed by the erection contractor in the water
piping.
Globe valve DIN PN 16
DN 20 - 2 No
DN 25 - 1 No
DN 40 - 10 No
DN 65 - 2 No
DN 150 - 1 No
BSP - 5 No
Needle valves PN 40
BSP - 6 No
Blow down valves, Germany PN 40
DN 20 - 3 No
DN 40 - 1 No
Safety valve ARI Germany PN 16
DN 50/80 - 2 No
Non return valve Disco checkDN 40 - 3 No
Three way control valve Regeltechnik Germany, electric motor actuator
DN 40 - 1 No
Y strainer DIN PN 16
DN 65 - 2 No
Butterfly valve PN 6
DN 50 - 4 No
Gauge glass assembly, PN 40
DN 20 - 2 No
Pressure Indicator
Dia. 160 mm - 1 No
8/9/2019 BHF 08-13_08R0.pdf
8/12
COAL fired fluid bed boi ler
PT Basuki Pratama Engineering Page 8 of 12
D:/Adat/Penawar/Std/BHF-New/BHF22013.doc
Dia. 63 mm - 3 No
17. Manufacturi ng certif icate from Depnaker RI
8/9/2019 BHF 08-13_08R0.pdf
9/12
COAL fired fluid bed boi ler
PT Basuki Pratama Engineering Page 9 of 12
D:/Adat/Penawar/Std/BHF-New/BHF22013.doc
EXCLUSIONS
1) All civil works including foundations etc.
2) Piping in between the boiler w/o insulation
3) Air and flue gas ducting
4) Electrica l cabling in between the boiler
5) Chimney, platform & ladder for chimney
6) Coal bunker
7) Water tank
8) Coal belt conveyor
9) Transportation, Erec tion & commissioning
10) Boiler house structure with roof and side panels. Control room with airtight
arrangement
11) Boiler operation certificate
12) All spares for operation and commissioning
8/9/2019 BHF 08-13_08R0.pdf
10/12
COAL fired fluid bed boi ler
PT Basuki Pratama Engineering Page 10 of 12
D:/Adat/Penawar/Std/BHF-New/BHF22013.doc
FEED WATER & BOILER WATER QUALITY
In order to ensure smooth and trouble free operation of the boiler, following
recommendations are specified for combined water tube and fire tube
boilers.
Drum operating pressure 1 to 22 kg/cm g
1. Feed Water
Hardness Ppm < 2
pH at 25 C > 9
Oxygen, mg/l < 0.02
Total iron mg/l < 0.05
Total copper mg/l < 0.01
Oil/ Grease mg/l < 1
KMnO4 consumption mg/l < 10
Conductivity at 25C
measured after cation
exch.in H+ form and after
CO2removal.
s/cm < 500
2. Boiler Water
pH at 25 C 10.5 12
Phosphate residual (PO4) mg/l 10 - 20
Total Hardness Mmol/l < 0.2
Specific electrical
conductivity at 25Cs/cm 30 7500
Silica. mg/l < 150
KMnO4 consumption mg/l < 150
Sodium sulfite as Na2SO3 mg/l 10 - 30
8/9/2019 BHF 08-13_08R0.pdf
11/12
COAL fired fluid bed boi ler
PT Basuki Pratama Engineering Page 11 of 12
D:/Adat/Penawar/Std/BHF-New/BHF22013.doc
TERMINAL POINTSSteam: At outlet flanges of steam stop valve.
Outlet of steam vent lines
Feed water: Inlet of water pump
Inlet of the steam boiler
(The connecting piping is excluded.)
Blowdown/Drain: At the outlet of blow down valves
Flue gas: Outlet of ID Fan
Fuel: Inlet of the coal screw feeder
Electricals: Inlet of instrument control panel.
Instrument air At one point in the boiler house
Ash: Outlet of ash drain ports
combustion air: At the FD fan inlet
8/9/2019 BHF 08-13_08R0.pdf
12/12
COAL fired fluid bed boi ler
PT Basuki Pratama Engineering Page 12 of 12
D:/Adat/Penawar/Std/BHF-New/BHF22013.doc
SUPERVISION OF ERECTION AND COMMISSIONING
We can depute our engineer for supervising the following at additionalcost.
1 ERECTION:
Erection of all units at site.
Installation of control panel and instruments.
Instrument cable lying.
Erection of steel chimney, coal bunker, ducting for flue gas, structures for
accessories, bunker etc.
Erection of boiler feed water pumps and inter-connecting piping.
Erection of steam and water piping
Insulation.
Refractory lining.
All power and instrumentation cabling
All impulse piping
Dust collector
2 COMMISSIONING:
Hydrostatic test
Feed water system flushing.
Chemical cleaning of boiler.
Starting up and initial operation of feed water system, dosing system and
other units.
Commissioning of the units.