48
Hitec Diesel Rotary UPS systems Case Study: The Malaga Data Centre, Perth, WA A comparison between the original static UPS and standby diesel generator design and the high-voltage Hitec Diesel Rotary UPS solution installed Ride through systems DRUPS systems www.hitec-ups.com

Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Embed Size (px)

Citation preview

Page 1: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Hitec Diesel Rotary UPS systems

Case Study: The Malaga Data Centre, Perth, WA

A comparison between the original static UPS and standby diesel generator design and the high-voltage Hitec Diesel

Rotary UPS solution installed

Ride through systems DRUPS systems

www.hitec-ups.com

Page 2: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

• The Hitec Organisation in APAC

• The Hitec Diesel Rotary UPS System

• Malaga Case Study - Data Centre Design Criteria

- The Original SUPS Scheme

- The HV DRUPS approach

- Reducing CAPEX

- Meeting TIA 942 / Tier III

- Sustainability and efficiency

- The completed facility

- Awards

Page 3: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

The Hitec Organisation

in APAC

Page 4: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

HITEC + HOTEC, Taiwan

HITEC + Power Partners, Singapore

HITEC Malaysia

Hisec, Japan

Hitec+ Metrowest, Australia + NZ

Hi-Rel, India HPS, South Korea

Matech, Thailand

Hitec in Asia Pacific Wide Regional Presence

PBG Indonesia

DP Consulting, Vietnam

Page 5: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Taiwan: 197

China: 28

Singapore: 46

Malaysia: 9

Australia: 20

India: 8

South Korea: 47

Thailand: 16

Asia Installed Base: 371 units

Hitec in Asia Pacific Large installed based

Page 6: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

• Sales and Marketing

• Technical and Design Assistance

• Project Engineering

• Project Management

• After Sales Support

• Service and Maintenance

• Strategic and Consumable Spares

Hitec in Asia Pacific Hitec’s Regional Support

Page 7: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

The Hitec

Diesel Rotary UPS system

Page 8: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

The Hitec DRUPS system

• A complete solution that utilises

stored mechanical energy

to provide continuous power.

• Combines the functionality of

both a UPS and a Standby Diesel Engine in a single module.

• Provides high quality power to support all types of load,

including critical cooling loads and those with a leading

power factor i.e. Blade Servers.

• Suitable for both HV and LV and 50/60 Hz applications.

• A highly reliable tried and tested design.

Page 9: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Standby Diesel

UPS Inverters

Air Conditioning

Switchboards PFC

Standby Batteries

Spark-proof Lighting Busduct & Cabling

Fire Protection & Security

Static UPS

+

The Hitec DRUPS system Ways in which UPS can be achieved

Page 10: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Hitec DRUPS

The Hitec DRUPS system Ways in which UPS can be achieved

Page 11: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Hitec DRUPS

Standby Diesel

Static UPS

UPS Inverters

Air Conditioning

Switchboards PFC

Standby Batteries

Spark-proof Lighting Busduct & Cabling

Fire Protection & Security

The Hitec DRUPS system Ways in which UPS can be achieved

Page 12: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Case Study:

The Malaga Data Centre,

WA

Page 13: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

• Co-location Facility

• Minimal build cost

• UTI Tier III / TIA 942 Certified

• 3000m² of raised floor

• Load to increase over time (3-4 Year Build-out)

• Initial floor loading of 750 Watts/m²

• Ultimate floor loading 1500 Watts/m²

• Pay as you go approach to infrastructure

• Was fully designed around SUPS plus standby generators

Data Centre Criteria

Page 14: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

The Original Scheme

Page 15: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

LV Switchgear

Standby Generators Static UPS #1

Static UPS #2

Tx Tx

The Original Scheme

Floor plan and plantroom take-up

for the SUPS and diesel generator scheme

Page 16: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Issues with the SUPS and diesel generator scheme:

• Cost and availability of the 22kV to 415V transformers

• Restricted space for up to 5 standby diesel generators

• Cooling (recirculation) issues for the diesel generators

• Very high nominal (In) and short-circuit (Isc) currents

• Reliability, control and cost of the ATS switches

• Capacity, quantity and space required for the reticulation

• LV switchgear expanding beyond the available space

• Space and cooling required for the SUPS and batteries

• Chillers unsported by UPS power

The Original Scheme

Page 17: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

The DRUPS challenge!

• Resolve the transformer delivery issue

• Rationalise the distribution scheme, reduce reticulation

• Remove the ATS control and reduce high fault currents

• Support (if possible increase) the avialable UPS power

• Provide continuous power to the chillers

• Reduce the total building load and increase efficiency

• Resolve the spatial and cooling issues with the generators

• If possible increase useable raised floor area

• Deliver a scalable solution – Pay as you Grow!

The DRUPS Approach

Page 18: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

A B

A B

A B

The DRUPS approach Removing transformers, simplifying the scheme, reducing reticulation, increase UPS power

Page 19: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

SUPS + DG’s DRUPS

Total UPS Load 4161.9 kW 4161.9 kW

Total Cooling Load 1872.9 kW* 1664.8 kW

Total Building Load 187.5 kW 187.5 kW

Grand Total 6222.3 kW 6014.2 kW

*Cooling Load is less for DRUPS as it requires no AC and can operate at ambient

Reducing the Building Load SUPS versus DRUPS

Page 20: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Ventialtion and cooling Reverse the modules, remotely sited radiators and a plantroom approach

Page 21: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Space and Expansion Individual fire rated DRUPS rooms, seperate switchgear rooms, redundant control and rooms

Page 22: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Original SUPS Requirement

• 12 x 500 kVA SUPS Modules 2(4 +1)

• 5 x 2.5 MVA Standby Diesel Generators (N+1)

Alternative DRUPS Requirement

• 5 x 2.3 MVA DRUPS Modules (N+1)

Is this the totality of the comparison?

Reducing CAPEX Power Equipment Summary

Page 23: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Reducing CAPEX Removal of the ‘Big Ticket’ items

• 22kV/415V Transformers

• Main LV Switchboards

• Diesel Generators

• Paralleling Switchboard

• SUPS Modules + Batteries

• SUPS Output Switchboard

X X X

X X

X X

X X X

Page 24: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Reducing CAPEX Simplify distribution, reduce In and Isc

• 7000A Busduct

• 20 x 1C 400mm²

• 20 x 1C 500mm²

• 4000A Mains/Gen ATS’s + Controls

Page 25: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

One SUPS String

• 20 x 1C 500mm²

• 4000A Mains/Gen ATS + Controls

• 4 x 3C 300mm² + 3 x 1C 400mm² N+PE

• 5+1 500 kVA SUPS

• 4 x 3C 300mm² + 3 x 1C 400mm² N+PE

• 6000A rated SUPS O/P switchboard

Reducing CAPEX Rationalise reticulation, remove ATS’

Page 26: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Reducing CAPEX Comprehensive evaluation of approaches

Page 27: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

SUPS Equipment Removed

• 22kV/415V Transformers

• Main LV Switchboards

• Diesel Generators

• Paralleling Switchboard

• SUPS Modules + Batteries

• SUPS Output Switchboard

• ATS Switches and Controls

• High Current LV Busduct

• High Current LV Cabling

Reducing CAPEX Comprehensive evaluation of approaches

Page 28: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Addition of:

• Up to 5No 2.3 MVA Hitec DRUPS Modules

• Ancillary DRUPS Equipments

• 22kV UPS Input / Output Switchgear

• Low-current high-voltage cabling

• 22kV to 415 power transformers

• Dual Redundant Control Scheme (Tier III)

Reducing CAPEX Comprehensive evaluation of approaches

Page 29: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Tier Classification: • System component redundancy:

N+1 requirement: for both UPS and Generation equipment, as site Generation is considered to be the primary power source.

• Multiple distribution paths, enabling…

• Concurrent Maintainability: “Any component necessary to support the IT processing environment can be maintained without impact on the IT environment.”

But… • System not ‘Fault Tolerant’:

“The site is susceptible to disruption from unplanned activities.”

UTI Tier III Concurrent Maintainabililty

Page 30: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

DRU

PS 2

DRU

PS 5

DRU

PS 3

DRU

PS 4

DRU

PS 1

• System Component Redundancy (N+1)

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

Page 31: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

DRU

PS 2

DRU

PS 5

DRU

PS 3

DRU

PS 4

DRU

PS 1

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

• Multiple Distribution Paths

Page 32: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

DRU

PS 2

DRU

PS 5

DRU

PS 3

DRU

PS 4

DRU

PS 1

• Concurrent Maintainability

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

Page 33: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

DRU

PS 2

DRU

PS 5

DRU

PS 6

DRU

PS 3

DRU

PS 4

DRU

PS 1

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

• Concurrent Maintainability

Page 34: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

DRU

PS 2

DRU

PS 5

DRU

PS 3

DRU

PS 4

DRU

PS 1

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

• Concurrent Maintainability

Page 35: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

DRU

PS 2

DRU

PS 5

DRU

PS 3

DRU

PS 4

DRU

PS 1

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

• Concurrent Maintainability

Page 36: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Bypass Control Panel

Q3

Q4

Dual Redundant Modbus+ Networks

Unit Control Panel PLC

Bypass Control Panel

Dual PLCs

To other modules

Modbus+ N

etwork

Bypass Control Panel

Dual PLCs

Unit Control Panel PLC

Modbus+ N

etwork

Fibre Optic

Unit Control Panel

Unit Control Panel

Bypass Control Panel

The DRUPS Approach Dual Redundant Control Scheme (Tier III)

Page 37: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Increasing lettable space Reducing Total Plantroom Area

Page 38: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

LV Switchgear

Standby Generators Static UPS #1

Static UPS #2

Tx Tx

Increasing lettable space The Static UPS approach

• 9MVA Static UPS and Diesel Generator arrangement

• Total space required =1,762m²

Page 39: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

DRUPS Modules, HV Switchgear and Controls

SwGr ‘A’

SwGr ‘B’

• 9 MVA Diesel Rotary UPS solution

• Total space required = 1,228m² • Total Space saved = 534m² (30% Space Saving)

Data Centre Expansion

Increasing lettable space The Diesel Rotary UPS approach

Page 40: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Calculating Carbon Footprint Operating efficiency is the key to calculating a ‘systems’ Carbon Footprint

Increasing Effiency

Page 41: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

1 2 3 4 5 6 7 8 9 10

DRUPS Static UPS

$1,939K

$895K

High Efficiency = Low Life Cost Comparative running costs at 50% load based

on 9.5 cents/kWhr (AIR 2.5%) for a UPS requirement of 1600kW

Cost

€’s

Year

Saving of $1,044K over a 10 Year Period

Increasing Effiency

Page 42: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

• Reduced CAPEX

• Simplified the reticulation and reduced fault current

• Used fewer components increased the lettable area

• Reduced the connections between supply and Load

• Provided continuous support to the total facility

• Lowered the overall building load

• Increased environmental and operating efficiency

• Reduced the carbon footprint and OPEX

• Increases the overall system reliability

• Considered as the ‘GREEN’ sustainable power approach

So why HV Hitec DRUPS?

Page 43: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

The Completed Installation

Page 44: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

The Completed Installation

Page 45: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

The Completed Installation

Page 46: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Awards Excellence in Energy Efficiency

Page 47: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Awards Best Building Fit Out Over $20M

Page 48: Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Questions