Chapter7-ADB

Embed Size (px)

Citation preview

  • 8/11/2019 Chapter7-ADB

    1/14

    7. INSTITUTIONAL REQUIREMENTS AND MONITORING PROGRAMME

    7.1 Introduction

    In order to make sure that the proposed mitigatory measures are being implemented, and also to

    check whether the predicted impacts are actually as anticipated, and are being mitigated by themeasures recommended in the Environmental Impact Assessment Report, it is necessary to

    establish a Monitoring Program, and provide the necessary institutional set up to implement it.

    This should be incorporated into the Proect Management !tructure itsel", rather than be

    established as a completely separate unit, so that there is commitment to the environmental

    management and monitoring by Proect Managers, who are responsible "or implementation o"

    the Proect.

    7.2 Institutional R!uir"nts

    7.2.1 Pro#ct Mana$"nt Structur

    The Proect Management !tructure proposed in the #orking $ra"t Environmental Management

    Plan, Road $evelopment Authority %&an '(()* is shown in +ig .-. The Ministry o" ighways /

    Road $evelopment Authority %R$A* is the E0ecuting Agency "or the ighway 1onstruction

    Proect, while the Ministry o" Transport %M2T* is the E0ecuting Agency "or the Road !a"ety

    1omponent %R!1* o" the Proect. There is a Proect $irector %P$* who is responsible "or the

    implementation o" the Proect and will directly report to the !ecretary o" Ministry o" ighways.

    There are two $eputy Proect $irectors %$P$* "or the Proect3 one responsible "or the

    construction and civil works and another responsible "or land ac4uisition, resettlement and

    environmental aspects o" the Proect. The !upervision 1onsultants %!1* are responsible "or the

    supervision o" construction activities o" the highway. alcrow 5roup 6td. is the !1 "or the A$7

    section and P1I "or the &7I1 section o" the Proect. +innroad in association with !urath

    #ickramasinghe 6td is the M1 "or the proect. There are two site proect o""ices8 one "or the

    &7I1 "inanced section and another "or the A$7 "inanced section.

    As shown in +ig .-, the Monitoring o" Environmental and !ocial Impacts and implementation

    o" special proects is the responsibility o" the Proect Managers operating "rom 9alutara 2""ice

    "or the &7I1 section and 5alle 2""ice "or the A$7 section, being implemented by the Regional

    2""icers at 7andaragama and $odangoda "or the &7I1 section and 9urundugahahetekma and

    9amburupitiya "or the A$7 section respectively. At each Regional 2""ice there would be a

    !ocial Impact Monitoring 2""icer, Environmental Impact Monitoring 2""icer, 7usiness

    $evelopment 2""icer and 1ommunity Resettlement 2""icer, the latter two appointments to beterminated a"ter one year o" completion o" the 6and Ac4uisition and Resettlement activities.

    -

  • 8/11/2019 Chapter7-ADB

    2/14

    T.O - Technical Officer

    CRO Community Resettlement Officer up to one year after LAR has been completed

    SIMO Social Impacts Monitoring Officer

    EIMO Enironmental Impacts Monitoring Officer*Grievance Committees are external advisory bodies

    not included in the number o cadres!"O !usiness "eelopment Officer up to one year after LAR has been c ompleted

    #E$" O%%ICE#E$" O%%ICE&& R"$ ' (M)R"$ ' (M)

    SET#SIRI($$SET#SIRI($$

    $ected (ersons + #ouseholds and !usinesses$ected (ersons + #ouseholds and !usinesses

    GrievanceCommittees*

    Oices o the "istrict Secretary

    Total number o sta in Re,ional Oices - / Technical and Administratie# $%

    &inancial # 'Special Resettlement Officers ('

    Support Staff # )'

    %IE0" O%%ICES%IE0" O%%ICES Sta,e 1Sta,e 1

    A"! is proposed to finance incrementalcosts for

    resources mar*ed +ith red frames

    En,ineers 213

    Environmental Ex4ert 253Chie $ccountant 253

    $ccountant 253MIS Mana,er 253

    $dministrative Oicer 253Cler6s 213

    "ata Entry Operators ,("riers ,(

    Office Aides ,(

    EIMO

    (01)

    CRO

    (01)

    SIMO

    (02)

    BDO

    (01)

    DataEntry

    Operator

    (1)

    OfceAide

    (1)

    Watcher

    (2)

    Driver

    (3)Clerk(2)

    BDO

    (01)

    SIMO

    (02)

    EIMO

    (01)

    CRO

    (01)

    DataEntry

    Operator

    (1)

    OfceAide

    (1)

    Watcher

    (2)

    Driver

    (3)Clerk(2)

    EIMO

    (01)

    CRO

    (01)

    SIMO

    (02)

    BDO

    (01)

    DataEntry

    Operator

    (1)

    OfceAide

    (1)

    Watcher

    (2)

    Driver

    (3)Clerk(2)

    BDO

    (01)

    SIMO

    (02)

    EIMO

    (01)

    CRO

    (01)

    DataEntry

    Operator

    (1)

    OfceAide

    (1)

    Watcher

    (2)

    Driver

    (3)Clerk(2)

    (ro7ect Mana,er 28!IC Section3$dministration and Coordination o O4erations and $ssistance to $(s

    9alutaraMain Oice

    (ro7ect Mana,er 2$"! Section3$dministration and Coordination o O4erations

    Galle Main Oice

    Re,ional Oicer"odan,oda Oic

    Re,ional Oicer9urundu,ahahete6ma Oice

    Monitorin, o Socioeconomic andEnvironmental Im4acts

    Im4lementation o S4ecial (ro,rams

    E:TER;$0 MO;ITORI;GE:TER;$0 MO;ITORI;G

    Mana,ement ConsultantsEnvironmental ' Social Im4act

    Monitorin, S4ecialists 213

    I;TER;$0I;TER;$0

    MO;ITORI;GMO;ITORI;GSocio economic and

    environmental Im4actMonitorin, consultants 213

    "e4uty (ro7ect"e4uty (ro7ect

    "irectors 213"irectors 213

    Resettlement Oicer9amburu,amu

  • 8/11/2019 Chapter7-ADB

    3/14

    Environment

    Environmental Monitorin, (ro,ram

    Com4liance $ction (lan 2Miti,ation (lan3Sam4lin, and Measurin, im4acts and 4arameters

    (M)E1ecuting Agency

    Employer

    MO#E%cuti&

    A$nc'

    Contractor2or*s

    Mana,ementConsultant

    E1ternal Monitoring

    ImpactAssessment

    CE$EIA

    Environmental Mana,ement (lan(ro7ect Environmental (ermitS4ecial (ermits and licenses

    $(s

    Enironmental Conditions of Contract

    Employer.s Responsibilities

    Mitigation of Enironmental Impacts

    EnvironmentalMonitorin,Committee

    Su4ervisionConsultant

    &ollo+-up of compliance

    $(s

    Monitoring

    Reporting

    7.2.2 (EA En&iron"ntal Monitorin$ (o""itt

    +or the purpose o" implementing the Environmental Management Plan, an Environmental

    Monitoring 1ommittee %EM1* has been set up under the 1EA. The EM1 comprises

    representatives "rom R$A, proect management unit %PM;*, representatives o" $ivisional!ecretaries o" -< $! o""ices, and representatives "rom other relevant 5overnment Agencies.

    EM1 will have meetings with a""ected persons %AP* or their representatives. The

    implementation o" mitigation measures arising "rom the Environmental Assessment, and as

    outlined in section < o" this Report will be the responsibility o" the PM;, proect consultants,

    and contractors. The independent monitoring team will monitor the implementation o" the EMP

    and will report to the EM1 through the 1EA. +igure .' outlines the process and the reporting

    mechanism.

    7.2.) En&iron"ntal Mana$"nt R!uir"nts

    *i$ 7.2+ En&iron"ntal Monitorin$ Procss and R,ortin$ Mc-anis"

    7.2. Pr/(onstruction Monitorin$0Anal'sis Actions

    Prconstruction n&iron"ntal data ar r,ortd in t- EIA R,ort as t- E%istin$

    En&iron"nt and Sit Dscri,tion.

    =

  • 8/11/2019 Chapter7-ADB

    4/14

    7.2.3 En&iron"ntal Mana$"nt in Pr/(onstruction and (onstruction

    Acti&itis

    $uring the construction phase it is important that the proect area is intensely monitored in order

    to ensure that both M!# produced by the work"orce and construction generated wastes are

    properly managed or that a proper plan to collect and sa"ely dispose the wastes is available. It isalso recommended that daily records are maintained pertaining to the amount o" solid waste

    disposed.

    Moreover the accommodation units given "or the work"orce should be thoroughly inspected to

    ensure that ade4uate "acilities are available with re"erence to toilet and bathroom "acilities, solid

    waste disposal systems and reliable potable water supply. #ith re"erence to proper collection

    and disposal o" M!# it is o" paramount importance to ensure that ade4uate amount o" bins are

    available in the proect area as well as in the accommodation units, hence to ensure that there is

    no unnecessary, nuisance collection o" garbage heaps.

    7.2.4 Su,r&ision o5 O,rational 6aslin Monitorin$ and *urt-r Anal'ss

    7.) Or$aniation and Sta55in$

    7.).1 Pro#ct Mana$"nt Unit 8PMU9

    The PM; will comprise a Proect $irector %P$*, who will responsible "or the implementation

    o" the proect. The P$ will also be responsible to report directly to the !ecretary o" the Ministry

    o" ighways %Mo*. In addition to the P$, there will be ' $eputy Proect $irectors %$P$*.

    2ne o" the $P$s will be a 4uali"ied and well e0perienced 1ivil Engineer who will be

    responsible "or the construction and civil works. The other $P$ will be responsible "or land

    ac4uisition, resettlement and environmental aspects o" the proect. The !upervision 1onsultants

    %!1* alcrow 5roup 6imited will be responsible "or the supervision o" the construction

    activities. The Proect Manager will be assisted by ' engineers, ' technical o""icers and even

    several Regional 2""icers and Resettlement 2""icers %+ig. .-*. The Regional and Resettlement

    2""icers will be responsible to deal with environmental issues, social aspects, etc. and the

    persons to be employed "or these tasks will be persons having 4uali"ications and e0perience in

    the relevant "ields.

    There will be a separate consultancy group responsible "or e0ternal monitoring o"

    environmental and social impacts o" the proect. They would be directly responsible to the P$.

    The consultants will have "ield level o""icers who are undertaking monitoring activities on acontinuous basis. +or the !outhern ighway 1omponent %!1* the 5overnment o" !ri 6anka

    has established a Proect 1oordination 1ommittee %P11*. The P11 will be responsible to

    coordinate the A$7 "inanced components o" the !1, in particular land ac4uisition and

    resettlement, adverse environmental impact mitigation, technical standards, scheduling, etc.

    The 1hairperson o" the P11 is the !ecretary %Mo* and other permanent members include

    representatives "rom E0ternal Resources $epartment %ER$* o" the Ministry o" +inance and

    Planning, Ministry o" Transport, R$A, >ational Planning $epartment, &7I1, A$7, 1EA, M1,

    Road !a"ety consultants and !1. Management 1onsultants %M1* acts as the !ecretary o" the

    P11.

    Management 5roup %M5* will be responsible to coordinate the practical implementationactivities o" the !outhern Transport $evelopment Proect %!T$P* in Mo. The !ecretary

    :

  • 8/11/2019 Chapter7-ADB

    5/14

    %Mo* is the chairman o" the M5. 2ther permanent members include 1hairman %R$A*,

    5eneral Manager %R$A* and P$ %PM;*. M1 acts as the !ecretary o" M5.

    7.).2 En&iron"ntal E!ui,"nt Nds

    7.).) E%,ansion o5 RDA En&iron"ntal Sta55 PMU Dutis

    7. Monitorin$ Pro$ra""

    It is imperative to conduct a comprehensive environmental monitoring programme by the R$A

    with assistance "rom reputed and independent Research and $evelopment 2rgani?ations such as

    Industrial Technology Institute %ITI* or >ational 7uilding and Research 2rgani?ation %>7R2*

    with respect to the di""erent segments o" the environment in the vicinity o" the highway. This is

    very crucial in order to assess the per"ormance or success o" the implemented mitigatory

    measures. In this respect there are ' basic environmental monitoring tasks to assess the success

    o" mitigation and identi"ying residual impacts. They are

    1onstruction compliance monitoring

    Post construction monitoring o" maintenance and operational proect activities including air,

    noise and water 4uality baseline conditions

    Pre@construction monitoring aspects such as sur"ace water 4uality, groundwater 4uality, air

    4uality and noise levels seems to be not necessary in the R$A and combined trace in the A$7

    section. This is because data on sur"ace water 4uality, ground water 4uality, air 4uality and noise

    level measurements in the A$7 section have been undertaken by the ITI and the ;niversity o"Moratuwa as e0plained in 1hapter : %E0isting Environment and !ite $escription*.

    owever in the case o" the 5alle Port Access Road section pre@construction monitoring has to be

    undertaken to determine the baseline conditions in detail in addition to construction compliance

    monitoring and monitoring during the operation o" the highway.

    Although the ;niversity o" Moratuwa has carried out some water 4uality analysis o" the water

    bodies '!# and =(!# in the 5alle Port Access Road !ection as e0plained in 1hapter :

    %E0isting Environment and !ite $escription*, it is still imperative to carry out a detailed

    monitoring o" e0isting sur"ace water 4uality with re"erence to the presence o" heavy metals and

    organic pesticides at least twice a year during both dry and wet seasons. It should be noted thatthe actual positions o" measurements could be slightly di""erent and there"ore e""orts must be

    made to measure downstream o" the road trace.

    In the case o" groundwater 4uality monitoring wells that are likely to be in the vicinity o" the

    construction sites and borrow areas have to be considered. The actual number o" wells "or

    monitoring purposes could be decided by the R$A a"ter a "ield visit. Monitoring o" groundwater

    4uality too should be monitored at least twice a year during both wet and dry bseasons.

    #ith re"erence to air 4uality monitoring the monitoring locations should include any location

    close to 5alle %$evata* and any new sensitive area identi"ied later. It should be noted that air

    4uality measurements have to be undertaken twice a year during both south@west and north@eastmonsoon seasons. E0isting noise level measurements should be undertaken during the day time

    )

  • 8/11/2019 Chapter7-ADB

    6/14

    %de"ined as

  • 8/11/2019 Chapter7-ADB

    7/14

    7...2 2=

    @, TP, organic pesticides and various heavy metals such as Pb, +e, Fn, 1d, 1r, g and

    As. The parameters measured have to be assessed with re"erence to the 1EA proposed ambient

    water 4uality standards "or inland sur"ace waters B 1lass II #aters %!ensitive #aters* B 7athing

    %Ta=l >>*. All other parameters %"or which no ambient standards have been stipulated yet in

    the !ri 6ankan legislation* have to be assessed with re"erence to the A>FE11 %'(((* guidelines

    "or recreational values %Table GGG*.

    Ta=l %%3 Proposed ambient water 4uality standards "or inland waters

    Para"tr Sti,ulatd ?alu

    p

  • 8/11/2019 Chapter7-ADB

    8/14

    1l@%mg/l* @

    2il and grease %mg/l* (.'

    >i %mg/l* (.-

    g %mg/l* (.((-

    Fn %mg/l* -

    As %mg/l* (.()Total coli"orms %MP>/-(( ml* -(((

    +aecal coli"orms %MP>/-(( ml* )(

    Ta=l @@@.A>FE11 %'(((* guidelines "or recreational waters

    Para"tr Guidlin &alus 8 $0L unlss

    ot-r:is statd9

    Inor$anic +

    1admium )

    1hromium )(

    >itrate@> -((((>itrite@> -(((

    Ot-r c-"icals +

    Aluminium '((

    Ammonia %as >* -(

    1opper -(((

    Psticids +

    Aldrin -

    $$T =

    $ieldrin -

    Endosul"an :(

    In addition to water 4uality monitoring it is also imperative to undertake sampling and analysis

    o" sediments "rom various locations in the water bodies o" the A$7 and 5alle Port Access Road

    !ections at least once in < months particularly during the operational phase. This is important to

    be carried out in order to avoid contamination o" sediments hence subse4uent adverse impacts

    on biota especially benthic "auna due to post construction related activities %e.g. disposal o"

    sewage and industrial wastewaters and ha?ardous industrial solid wastes such as slurries and

    sludges, urban run@o"", etc.*. In this respect this task also has to be carried out by the R$A with

    assistance "rom ITI or >7R2. It should be noted that sediments should be collected in duplicate

    and the parameters to be monitored needs to include heavy metals %As, Fn, g, Pb, 1d, 1r, >i*,

    organo@chlorides and other organic pesticides and P2:=@

    . The measured parameters should beassessed with re"erence to the A>FE11 %'(((* guidelines "or sediment 4uality %Table J* in

    view o" the "act that no sediment 4uality guidelines are still available in !ri 6anka.

    Ta=l?.Recommended A>FE11 %'(((* sediment 4uality guidelines

    (onta"inant ISQG/Lo:

    8Tri$$r

    &alu9

    ISQG/;i$-

    METALS 8"$0B$ dr' :t9

    Antimony ' ')

    1admium -.) -(

    1hromium ( =(1opper

  • 8/11/2019 Chapter7-ADB

    9/14

    6ead )( ''(

    Mercury (.-) -

    >ickel '- )'

    !ilver - =.

    Finc '(( :-(

    METALLOIDS 8"$0B$ dr':t.9

    Arsenic '( (

    ORGANOMETALLI(S

    Tributyltin %g !n/kg dry wt.* ) (

    ORGANI( 8$0B$ dr' :t.9b

    Acenaphthene -< )((

    Acenaphthalene :: aphthalene -7R2 to carry out

    the ;! Environmental Protection Agency %;!EPA* developed to0icity characteristics leachingprotocol %T16P* test "or the sediments that are highly contaminated with heavy metals in order

    to evaluate the potential desorption or releasing o" contaminants into the water column, hence

    availability to biota %a scenario that could occur during changing environmental conditions such

    as p and Eh*. The T16P test results obtained have to be assessed with re"erence to the

    standards given in Table ;;;.

    Table ;;;. T16P leaching test B recommended acceptance criteria "or suitability o" industrial

    wastes "or land"ill disposal

    (onta"inant R$ulator' L&l 8"$0l9

    >i @

    1r )

  • 8/11/2019 Chapter7-ADB

    10/14

    Mn )(

    Pb )

    As )

    1d -

    g (.'

    +e -((Ag )

    Fn -((

    1u -((

    !e -

    7...2.2. Ground:atr Qualit' Monitorin$ in t- AD6 Sction and Gall Port Accss

    Road Sction

    In addition to the monitoring o" water 4uality in sur"ace water bodies it is also imperative to

    carry out monitoring o" groundwater 4uality to avoid deterioration arising due to construction

    activities and post construction related activities such as development o" secondary activities

    along the road traces. This task has to be carried out by the contractor and the R$A %as directed

    by the 1EA* during the construction phase and operational phase, respectively with assistance

    "rom ITI or >7R2. The monitoring "re4uency needs to be at least once in < months and the

    monitoring period should include the dry and wet seasons. The monitoring locations should

    include the wells near the construction site and borrow areas. In this respect all the wells

    selected at the pre@construction phase should be selected as monitoring locations during the

    construction phase. I" any construction activity a""ects the groundwater signi"icantly in a given

    area, such locations must be monitored separately. $uring the operational phase wells that have

    been identi"ied as having a high a""inity "or deterioration due to tra""ic should be selected "or

    monitoring. I" any operation activity a""ects the groundwater signi"icantly in a given area, suchlocations must be monitored separately.

    The parameters to be monitored needs to include the depth o" groundwater, p, electrical

    conductivity, total and "aecal coli"orm levels, total hardness, total alkalinity, !2 :'@, 1l@, T!!,

    T$!, 72$), $2, T>, >:@>, >2'@, >2=

    @, TP, organic pesticides and various heavy metals such

    as +e, Mn, Pb, Fn, 1d, 1r, g, etc. The measured physicochemical, microbiological and

    chemical parameters have to be assessed with re"erence to the drinking water guidelines

    stipulated by the #2/!6! -8 Part - C ' "or uman 1onsumption.

    7...) Air Qualit' Monitorin$

    Air 4uality monitoring has to be carried out by the contractor during the construction phase to

    minimi?e air pollution, hence to ensure maintenance o" 1EA stipulated ambient air 4uality

    standards %Ta=l >>*. !imilarly air 4uality monitoring has to be carried out by the R$A during

    the operational phase in order to minimi?e air pollution "rom road usage activities. In this

    respect assistance "rom ITI or >7R2 has to be obtained.

    Monitoring o" air 4uality aspects has to be carried out every ' weeks and depending on

    complaints "rom local people at relevant premises during the construction phase. $uring the

    operational phase the monitoring "re4uency needs to be at least once in < months.

    In the A$7 section the monitoring locations needs to include the locations A to -'A monitoredby the ITI in &une, '((=. In the 5alle Port Access Road !ection any location close to 5alle

    -(

  • 8/11/2019 Chapter7-ADB

    11/14

    %$evata* should be considered "or monitoring purposes. Also any new sensitive area identi"ied

    should be monitored too during the construction and/or operational phase. I" any construction

    activity a""ects an area signi"icantly, then a separate monitoring plan must be carried out at such

    locations. !imilarly i" any operation activity a""ects an area signi"icantly, separate monitoring

    plan must be carried out at the relevant locations.

    It should be noted that during air 4uality monitoring the prevailing weather conditions such as

    wind speed and direction, sunlight intensity, etc. should be taken into consideration. The

    parameters to be monitored during both phases o" the proect should include >20, 12, !2',

    ground level 2=, Pb, PM -(, !PM %!uspended Particulate Matter/dust* and Pb with re"erence to

    1EA stipulated standards "or ambient air 4uality %Table 00*. The necessary air 4uality

    parameters should be measured using the standard approved tests given in Table 00. The values

    e0pressed should be at least hour and ': averages where necessary during the construction

    phase and at least - hour and ': hour averages during the operational phase.

    Table ). 1EA standards "or ambient air 4uality and approved measurement methods "or the air

    4uality parameters to be monitoredPollutant A&ra$in$ Ti" Unit Standard Masur"nt Mt-od

    12 - hr

    hr

    ppm 'on@dispersive in"rared

    spectroscopy

    >2' ': hr

    hr

    - hr

    ppm (.()

    (.(

    (.-=

    1olorimetry using

    !alt?man method or gas

    phase chemiluminescence

    !2' ': hr

    - hr

    hr

    ppm (.(=

    (.(

    (.()

    Pararosamiline method or

    Pulsed "luorescent method

    2= - hr ppm (.(- 1hemiluminescencemethod or ultraviolet

    photometric method

    Pb ': hr g/m= ' igh volume sampling,

    wet ashing and AA!

    !PM ': hr

    - hr

    hr

    g/m= =((

    )((

    =)(

    igh@volume sampling and

    gravimetry

    In addition to air 4uality monitoring regular monitoring o" vehicular emissions would be o"

    paramount importance during the operational phase in order to ensure that air pollution caused

    by vehicles is low or insigni"icant. The parameters to be monitored should include >20, !2',12 and !PM with re"erence to emission standards. Also Pb levels have to be analy?ed in the

    case o" petrol powered vehicles with re"erence to the emission standards. Monitoring o"

    vehicular emissions too has to be carried out by R$A by making arrangements with ITI or

    >7R2 and specially trained Police personnel as has been practiced in some developed

    countries.

    7... Nois0Ground ?i=ration Monitorin$

    >oise level monitoring is essential to ensure that noise emissions arising during construction

    works %due to activities such as trucks transporting construction material "rom 4uarry sites, pile

    driving activities, blasting, etc.* and operational activities %due to e0pected increase in tra""ic"low* are minimal. !imilarly vibration levels should be intensely monitored during the

    --

  • 8/11/2019 Chapter7-ADB

    12/14

    construction phase. The important parameters to be measured should include mean sound level

    %6e4 %':**, day@night sound levels %6dn* %( d7a, day8 )) d7a night*, 6A, e4one hour at day

    time, 6A e4, -) minutes at night time, peak particle velocity and air blast over pressure level

    %A72P*.

    >oise monitoring should be done by the contractor during the construction phase and by theR$A during the operational phase with the consultation and assistance "rom >7R2 or ITI. The

    noise monitoring "re4uency needs to be at least once in ' months during both phases. owever

    during the construction phase monitoring o" noise levels should also be carried out as and when

    re4uired or depending on complaints "rom local people at their premises. Moreover

    vibration/A72P levels too have to be regularly monitored depending on complaints "rom local

    people at their premises and whenever blasting activities or any other vibration inducing

    activities are likely to be carried. In this respect special attention should be paid to the

    development o" cracks and crevices in nearby building structures with care"ul regular

    monitoring. +urther it is recommended that daily records are maintained on the amount o"

    e0plosive material used "or rock blasting. $uring rock blasting the vibration at a distance o" -((

    m should also be measured and records should be maintained.

    The noise monitoring locations needs to include all populated areas in the A$7 section and

    5alle Port Access Road area and other identi"ied noise sensitive areas such as schools and

    religious sites occurring in the A$7 section %i.e. noise sensitive areas located in the vicinity o"

    the highway*. In the case o" the A$7 section the areas that were monitored by ITI in >ovember

    '(('@+ebruary '((= %i.e. the locations > to -'>* should be considered as potential monitoring

    locations during the construction and operational phase "or comparison purposes. In the 5alle

    Port Access Road !ection any location close to 5alle %$evata* and any new sensitive area

    identi"ied should be considered as monitoring locations. +urther the rock blasting sites, crusher

    plant sites, piling sites and sites where concrete and asphalt plants are located should be

    considered as important monitoring locations during the construction phase. owever it should

    be noted that i" any construction activity and/or operation activity causes signi"icant noise and

    vibration, such locations must be monitored separately.

    The noise levels measured during the construction phase has to be assessed with re"erence to the

    ma0imum permissible construction noise levels o" ) d7%A* and )( d7%A* stipulated "or

    daytime %de"ined as

  • 8/11/2019 Chapter7-ADB

    13/14

    e0pressway due to and increased number o" accidents on access roads. In this respect the

    important parameters to be monitored should include law en"orcement e""iciency, su""iciency o"

    programs on road user in"ormation systems /education, tra""ic signs and road markings, success

    o" emergency services and proper "unctioning o" accident review committee. The monitoring

    locations should encompass the sensitive locations B black spots identi"ied by 1onsultants.

    Records o" accident review committee.

    7...C Gar=a$ Dis,osal / Durin$ O,ration

    Regular surveys and supervision works have to be carried out by the R$A at least once in '

    months with assistance "rom the relevant local authorities to ensure that ade4uate bins and

    containers are available "or solid waste collection and disposal and to control garbage disposal

    by road users creating pollution and aesthetic discom"ort. Also there needs to be a regular

    supervision o" the garbage collection "re4uency and cleaning o" roads.

    The parameters to be monitored need to include the e""iciency o" establishment o" relevant

    programmes and success"ulness o" their "unctions, and ade4uacy o" bins "or garbage collectionand e""iciency o" garbage collectors and road cleaners. The monitoring locations should

    encompass places where bins are kept along the highway, crowded areas such as interchanges,

    bus halts, places where vehicles are allowed to park and aesthetically attractive places.

    7... Trans,ortation o5 Dan$rous Goods / Durin$ O,ration

    Transportation o" dangerous goods including prescribed wastes has to be care"ully monitored by

    the R$A with assistance "rom Police, personnel "rom the 1EA and "ire emergency services and

    other law en"orcement agencies on a daily basis in order to control spills and vapour emissions

    and subse4uent environmental pollution. The parameters to be monitored should encompass

    re4uirements/standards "or licensing o" transporting such dangerous chemicals, appropriate

    marking o" the dangerous transport vehicles, speeds o" vehicles, appropriate coverage o" open

    trucks and other vehicles involved in transporting dangerous goods, and care"ul inspection o"

    such vehicles to ensure that other crucial, basic measures %where necessary* described in section

  • 8/11/2019 Chapter7-ADB

    14/14

    !econdary development activities occurring in the neighbourhood o" the roads has to be

    care"ully monitored by R$A with assistance "rom ;$A at least every ' months in order to

    prevent any negative impacts on air 4uality, water bodies and even groundwater 4uality due to

    activities such as illegal dumping o" municipal solid wastes and even industrial solid wastes

    containing ha?ardous materials and disposal o" untreated sewage and industrial wastewaters.This task has to be carried out in the "orm o" surveys. The monitoring locations should be

    care"ully identi"ied with the surveys.

    $uring the operational phase it is anticipated that road maintenance activities would be re4uired

    to be carried. Although these activities are temporary the mitigatory measures applicable "or the

    construction phase with re"erence to minimi?ation o" sur"ace and groundwater 4uality

    deterioration, air 4uality deterioration, high noise generation and generation o" construction

    associated solid wastes are also applicable "or the maintenance construction activities where

    deemed necessary. All the relevant measures should be implemented by the R$A and the

    contractor. It is also imperative that during road maintenance construction works environmental

    monitoring is carried out by the R$A and contractor with assistance "rom ITI or >7R2 in orderto minimi?e or avoid environmental pollution and generation o" high disturbing noise levels.

    This task should be carried out throughout the period o" the maintenance works and depending

    on complaints made by neighbouring communities especially with re"erence to dust and noise

    levels.

    7..3