Upload
marcworld
View
220
Download
0
Embed Size (px)
Citation preview
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
1/150
1529pk - 1
Power System Stability in the New IndustryEnvironment: Challenges and Solutionspresented by:
Dr. Prabha S. Kundur
Kundur Power Systems Solutions, Inc.
Toronto, Ontario
Canada
Tutorial
Copyright P. Kundur
This material should not be used without the author's consent
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
2/150
1529pk - 2Copyright P. Kundur
Power System Stability and Control
Tutorial Outline
1. Brief Introduction to Power System Stability
Basic concepts
Classification
2. Examples of Major System Blackouts Caused by Different Forms
of Instability
3. Challenges to Secure Operation of today's Power Systems
4. Major System Blackouts in 2003 and 2004
5. Comprehensive Approach to Enhancing Power System Stability
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
3/150
1529pk - 3Copyright P. Kundur
Power System Stability
Refers to continuance of intact operation of power system,
following a disturbance
Recognized as an important problem for secure system operation
since the 1920s
Major concern since the infamous November 9, 1965 blackout of
Northeast US and Ontario
criteria and analytical tools used till now largely based on the
developments that followed
Presents many new challenges for today's power systems
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
4/150
1529pk - 4Copyright P. Kundur
Power System Stability: Basic Concepts
Power System Stability denotes the ability of an electric power
system, for a given initial operating condition, to regain a state of
operating equilibrium after being subjected to a physical
disturbance, with all system variables bounded so that the system
integrity is preserved integrity of the system is preserved when practically the entire power
system remains intact with no undue tripping of generators or loads
Stability is a condition of equilibrium between opposing forces:
instability results when a disturbance leads to a sustained imbalancebetween the opposing forces
Ref: IEEE/CIGRE TF Report, "Definition and Classification of Power System Stability",
IEEE Trans. on Power Systems, Vol. 19, pp. 1387-1401, August 2004
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
5/150
1529pk - 5Copyright P. Kundur
Basic Concepts (cont'd)
Following a transient disturbance, if the power system is stable it will reach a
new equilibrium state with practically the entire system intact:
faulted element and any connected load are disconnected
actions of automatic controls and possibly operator action will eventually
restore system to normal state
On the other hand, if the system is unstable, it will result in a run-away or
run-down situation; for example:
a progressive increase in angular separation of generator rotors, or
a progressive decrease in bus voltages
An unstable system condition could lead to cascading outages, and a shut-
down of a major portion of the power system
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
6/150
1529pk - 6Copyright P. Kundur
Classification of Power System Stability
Classification into various categories greatly facilitates:
analysis of stability problems
identification of essential factors which contribute to instability
devising methods of improving stable operation
Classification is based on the following considerations:
physical nature of the resulting instability
size of the disturbance considered
devices, processes, and the time span involved
We should always keep in mind the overall stability !
solutions to problems of one category should not be at the
expense of another
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
7/1501529pk - 7Copyright P. Kundur
Power System Stability
Frequency
Stability
Small-Signal
Stability
Transient
Stability
Short Term Long Term
Large-Disturbance
Voltage Stability
Small-Disturbance
Voltage Stability
Voltage
Stability
Rotor Angle
Stability
Considerationfor
Classification
Physical
Nature/ Main
System
Parameter
Size of
Disturbance
Time Span
Short Term
Short Term Long Term
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
8/1501529pk - 8Copyright P. Kundur
Rotor Angle Stability
Ability of interconnected synchronous machines to remain insynchronism after being subjected to a disturbance
Depends on the ability to restore equilibrium between electromagnetic
torque and mechanical torque of each synchronous machine
If the generators become unstable when perturbed, it is as a result of
a run-away situation due to torque imbalance
A fundamental factor is the manner in which power outputs of
synchronous machines vary as their rotor angles swing Instability that may result occurs in the form of increasing angular
swings of some generators leading to loss of synchronism with other
generators
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
9/1501529pk - 9
Copyright P. Kundur
Transient Stability
Term traditionally used to denote large-disturbance angle stability
Ability of a power system to maintain synchronism when
subjected to a severe transient disturbance:
influenced by the nonlinear power-angle relationship
stability depends on the initial operating condition and severity of
the disturbance
A wide variety of disturbances can occur on the system:
The system is, however, designed and operated so as to be stablefor a selected set of contingencies
usually, transmission faults: L-G, L-L-G, three phase
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
10/1501529pk - 10
Copyright P. Kundur
Small-Signal (Angle) Stability
Small-Signal (or Small-Disturbance) Stability is the ability of a powersystem to maintain synchronism under small disturbances
disturbance considered sufficiently small if linearization of system
equations is permissible for analysis
Instability that may result can be of two forms:
aperidic increase in rotor angle due to lack of sufficient synchronizing
torque
rotor oscillations of increasing amplitude due to lack of sufficient
damping torque
In today's practical power systems, SSS problems are usuallyassociated with oscillatory modes
local plant mode oscillations: 0.8 to 2.0 Hz
interarea oscillations: 0.1 to 0.8 Hz
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
11/1501529pk - 11
Copyright P. Kundur
Voltage Stability
Ability of power system to maintain steady voltages at all buses in the
system after being subjected to a disturbance
A system experiences voltage instability when a disturbance, increase in
load demand, or change in system condition causes:
a progressive and uncontrollable fall or rise in voltage of buses
in a small area or a relatively large area
Main factor causing voltage instability is the inability of power system to
maintain a proper balance of reactive power and voltage control actions
The driving force for voltage instability is usually the load characteristics
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
12/1501529pk - 12
Copyright P. Kundur
Short-Term and Long-Term Voltage Stability
Short-term voltage stability involves dynamics of fast acting load
components such as induction motors, electronically controlled
loads and HVDC converters
study period of interest is in the order of several seconds
dynamic modeling of loads often essential; analysis requiressolution of differential equations using time-domain simulations
faults/short-circuits near loads could be important
Long-term voltage stability involves slower acting equipment such as
tap-changing transformers, thermostatically controlled loads, andgenerator field current limiters
study period may extend to several minutes
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
13/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
14/150
1529pk - 14Copyright P. Kundur
Frequency Stability (cont'd)
In a large interconnected system, frequency stability could be of
concern only following a severe system upset resulting in the
system splitting into islands
Depends on the ability to restore balance between generation andload of island systems with minimum loss of load and generation
Generally, frequency stability problems are associated with
inadequacies in equipment responses, poor coordination ofcontrol and protection systems
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
15/150
1529pk - 15Copyright P. Kundur
Examples of Major System Blackouts Caused by
Different Forms of Instability
1. November 9, 1965 blackout of Northeast U.S. and Ontario
2. April 19, 1972, blackout of Eastern Ontario
3. July 2, 1996 disturbance of WSCC (Western North
American Interconnected) System
4. August 10, 1996 disturbance of WSCC system
5. March 11, 1999 Brazil blackout
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
16/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
17/150
1529pk - 17Copyright P. Kundur
November 9, 1965 Blackout of NE U.S. and Ontario
Clear day with mild weather; load levels in the region normal
Problem began at 5:16 p.m.
Within a few minutes, there was a complete shut down of electric
service to: virtually all of the states of New York, Connecticut, Rhode Island,
Massachusetts, Vermont
parts of New Hampshire, New Jersey and Pennsylvania
most of Ontario
Nearly 30 million people were without power for about 13 hours
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
18/150
1529pk - 18Copyright P. Kundur
North American Eastern Interconnected System
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
19/150
1529pk - 19Copyright P. Kundur
Events that Caused the 1965 Blackout
The initial event was the operation of a backup relay (zone 3)
at Beck GS in Ontario near Niagara Falls
opened circuit Q29BD, one of five 230 kV circuits connecting
Beck GS to load centers in Toronto and Hamilton
Prior to opening of Q29BD, the five circuits were carrying
1200 MW of Beck generation, and
500 MW import from Western NY State on Niagara ties
Loading on Q29BD was 361 MW at 248 kV;
The relay setting corresponded to 375 MW
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
20/150
1529pk - 20Copyright P. Kundur
Events that Caused the 1965 Blackout (cont'd)
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
21/150
1529pk - 21Copyright P. Kundur
Events that Caused the 1965 Blackout (contd)
Opening of circuit Q29BD resulted in sequential tripping of the
remaining four parallel circuits
Power flow reversed to New York: total change of 1700 MW
Generators in Western New York and Beck GS lost synchronism,
followed by cascading outages: Transient (Angle) Instability !
After about 7 seconds from the initial disturbance
system split into several separate islands Eventually most generation and load lost due to the inability of
islanded systems to stabilize:Frequency Instability !
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
22/150
1529pk - 22Copyright P. Kundur
Formation of Reliability Councils
Northeast Power Coordinating Council (NPCC) formed in January 1966 to improve coordination in planning and operation among utilities
first Regional Reliability Council (RRC) in North America
Other eight RRCs formed in the following months
National/North American Electric Reliability Council (NERC)
established in 1968
Detailed reliability criteria were developed;
Procedures for exchange of data and conducting stability studies were
established
Many of these developments have had an influence on utility practices
worldwide; still largely used !
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
23/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
24/150
1529pk - 24
April 19, 1972 Blackout ofEastern Ontario
Copyright P. Kundur
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
25/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
26/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
27/150
1529pk - 27Copyright P. Kundur
Transient Response of Nuclear Units with Auxiliary
Governor
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
28/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
29/150
1529pk - 29
July 2, 1996 WSCC / WECC
(Western North AmericanInterconnected System)
Disturbance
Copyright P. Kundur
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
30/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
31/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
32/150
1529pk - 32Copyright P. Kundur
WSCC July 2, 1996 Disturbance (cont'd)
LG fault on 345 kV line from Jim Bridger 2000 MW plant in
Wyoming to Idaho due to flashover to a tree
tripping of parallel line due to relay misoperation
Tripping of two (of four) Jim Bridger units as stability control; this
should have stabilized the system
Faulty relay tripped 230 kV line in Eastern Oregon
Voltage decay in southern Idaho and slow decay in central Oregon
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
33/150
1529pk - 33Copyright P. Kundur
WSCC July 2, 1996 Disturbance (contd)
About 24 seconds later, a long 230 kV line (Amps line) from western
Montana to Southern Idaho tripped, due to zone 3 relay operation parallel 161 kV line subsequently tripped
Rapid voltage decay in Idaho and Oregon
Three seconds later, four 230 kV lines from Hells Canyon generation to
Boise tripped
Two seconds later, Pacific intertie lines separated
Cascading to five islands 35 seconds after initial fault
2.2 million customers experienced outages; total load lost 11,900 MW
Voltage Instability!!!
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
34/150
1529pk - 34Copyright P. Kundur
WSCC July 2, 1996 Disturbance (cont'd)
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
35/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
36/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
37/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
38/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
39/150
1529pk - 39Copyright P. Kundur
August 10th, 1996 WSCC Event
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
40/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
41/150
1529pk - 41Copyright P. Kundur
As a result of the undamped
oscillations, the system split
into four large islands
Over 7.5 million customers
experienced outages ranging
from a few minutes to nine
hours! Total load loss 30,500MW
WSCC August 10, 1996 Disturbance (cont'd)
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
42/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
43/150
1529pk - 43Copyright P. Kundur
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
44/150
1529pk - 44Copyright P. Kundur
Sites Selected for PSS Modifications
San Onofre
(Addition) Palo Verde
(Tune existing)
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
45/150
1529pk - 45Copyright P. Kundur
Power System Stabilizers
With existing controls
Eigenvalue = 0.0597 + j 1.771
Frequency = 0.2818 Hz
Damping = -0.0337
With PSS modifications
Eigenvalue = -0.0717 + j 1.673
Frequency = 0.2664Damping = 0.0429
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
46/150
1529pk - 46Copyright P. Kundur
Design of HVDC Modulation
HVDC intertie shown (as expected) to have low participation in themode of interest (0.23 Hz interarea oscillations)
Often however, HVDC can be modulated to improve damping, provided
adequate input signal is found and proper compensator is designed
SSAT used to examine frequency response for several potential inputsignals
Frequency response magnitude identified local bus frequency as
having good operability/controllability of the mode of interest
Frequency response phase used to design compensator which
provides proper modulation signal to HVDC controls
TSAT and SSAT used to verify modulation performance
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
47/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
48/150
1529pk - 48
March 11, 1999 BrazilBlackout
Copyright P. Kundur
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
49/150
1529pk - 49Copyright P. Kundur
March 11, 1999 Brazil Blackout
Time: 22:16:00h, System Load: 34,200 MW
Description of the event:
L-G fault at Bauru Substation as a result of lightning causing a bus
insulator flashover
the bus arrangement at Bauru such that the fault is cleared by opening
five 440 kV lines
the power system survived the initial event, but resulted in instability
when a short heavily loaded 440 kV line was tripped by zone 3 relay
cascading outages of several power plants in Sao Paulo area, followed
by loss of HVDC and 750 kV AC links from Itaipu
complete system break up: 24,700 MW load loss; several islands
remained in operation with a total load of about 10,000 MW
Transient instability followed by voltage problems
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
50/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
51/150
1529pk - 51
Challenges to Secure Operation of
Today's Power Systems
Copyright P. Kundur
Li it ti f T diti l A h t P
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
52/150
1529pk - 52Copyright P. Kundur
Limitations of Traditional Approach to Power
System Stability
Focus largely on one aspect of stability: "transient stability"
Deterministic approach for system security assessment
System designed and operated to withstand
loss of any single element preceded by a fault
referred to as N-1 criterion Analysis by time-domain simulation of selected operating
conditions
scenarios based on judgment/experience
Operating limits based on off-line studies system operated conservatively within pre-established limits
"Adhoc Approach" to application of power system stability
controls
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
53/150
Ch ll t S O ti f T d ' P
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
54/150
1529pk - 54Copyright P. Kundur
Challenges to Secure Operation of Today's Power
Systems (cont'd)
Complex modes of instability
global problems
different forms of instability: rotor angle, voltage, frequency
"Deregulated" market environment
many entities with diverse business interests
system expansion and operation driven largely by economic drivers
lack of coordinated planning
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
55/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
56/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
57/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
58/150
1529pk - 58Copyright P. Kundur
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
59/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
60/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
61/150
1529pk - 61Copyright P. Kundur
Rotor Angles in B.C. and Alberta
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
62/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
63/150
1529pk - 63Copyright P. Kundur
BC Hydro and Alberta Bus Voltages
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
64/150
1529pk - 64Copyright P. Kundur
Rotor Angles in B.C. and Alberta
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
65/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
66/150
1529pk - 66Copyright P. Kundur
Major Power System Blackouts in 2003
and 2004
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
67/150
1529pk - 67Copyright P. Kundur
Blackouts in 2003 and 2004
We had several wake up calls since 2003:
August 14, 2003 blackout of North East USA and Ontario
63,000 MW load loss affecting 50 million people
September 23, 2003 blackout of South Sweden and East Denmark
6,500 MW load loss affecting 4 million people
September 28, 2003 blackout of Italy
50,000 MW load unsupplied affecting 60 million people
August 12, 2004 blackout of three Australian States: Queensland,NSW and Victoria
load loss 1,000 MW
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
68/150
1529pk - 68Copyright P. Kundur
August 14, 2003 Blackout of Northeast US
and Canada
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
69/150
1529pk - 69Copyright P. Kundur
14 August 2003 Blackout of Northeast US - Canada
Approximately 50 million people in 8 states in the US and2 Canadian provinces affected
63 GW of load interrupted (11% of total load supplied by Eastern
North American Interconnected System)
During this disturbance, over400 transmission linesand 531
generatingunits at 261 power plants tripped
For details refer to: "Final Report of Aug 14, 2003 Blackout in the
US and Canada: Causes and Recommendations", US-Canada
Power System Outage Task Force, April 5, 2004.www.NERC.com
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
70/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
71/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
72/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
73/150
1529pk - 73Copyright P. Kundur
Sequence of Events
The Midwest ISO (MISO) state estimator and real-time contingency
analysis (RTCA) software not functioning properly from 12:15 to 16:04
prevented MISO from performing proper "early warning" assessments
as the events were unfolding
At the First Energy (FE) Control Center, a number of computer
software problems occurred on the Energy Management System(EMS) starting at 14:14
contributed to inadequate situation awareness at FE until 15:45
The first significant event was the outage of East Lake generating unit
#5 in the FE system at 13:31:34
producing high reactive power output
voltage regulator tripped to manual on overexcitation
unit tripped when operator tried to restore AVR
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
74/150
1529pk - 74Copyright P. Kundur
East Lake 5 Trip: 1:31:34 pm
ONTARIO
2
1
ONTARIO
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
75/150
1529pk - 75Copyright P. Kundur
Initial line trips in Ohio, all due to tree contact: Chamberlin-Harding 345 kV line at 15:05:41
Hanna-Juniper 345 kV line at 15:32:03
Star-South Canton 345 kV line at 15:41:35
Due to EMS failures at FE and MISO control centers, no properactions (such as load shedding) taken
Critical event leading to widespread cascading outages in Ohio
and beyond was tripping of Sammis-Star 345 kV line at 16:05:57
Zone 3 relay operation due to low voltage and high power flow
Load shedding in northeast Ohio at this stage could have
prevented cascading outages that followed
Sequence of Events cont'd
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
76/150
1529pk - 76Copyright P. Kundur
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
77/150
1529pk - 77Copyright P. Kundur
Tripping of many additional 345 kV lines in Ohio and Michigan by
Zone 3 (or Zone 2 set similar to Zone 3) relays
Tripping of several generators in Ohio and Michigan
At 16:10:38, due to cascading loss of major lines in Ohio and
Michigan, power transfer from Canada (Ontario) to the US on the
Michigan border shifted power started flowing counter clockwise from Pennsylvania through
New York and Ontario into Michigan
3700 MW of reverse power flow to serve loads in Michigan and Ohio,
which were severed from rest of interconnected system except Ontario
Voltage collapsed due to extremely heavy loadings on transmission
lines
Cascading outages of several hundred lines and generators leading
to blackout of the region
Sequence of Events
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
78/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
79/150
Primary Causes of Blackout
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
80/150
1529pk - 80Copyright P. Kundur
Primary Causes of Blackout(as identified by the US-Canada Outage Task Force)
1. Inadequate understanding of the power system requirements:
First Energy (FE) failed to conduct rigorous long-term planning
studies and sufficient voltage stability analyses of Ohio control area
FE used operational criteria that did not reflect actual system
behaviour and needs
ECAR (East Central Area Reliability Council) did not conduct an
independent review or analysis of FE's voltage criteria and operating
needs
Some NERC planning standards were sufficiently ambiguous that FE
could interpret them in a way that resulted in inadequate reliability forsystem operation
cont'd
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
81/150
1529pk - 81Copyright P. Kundur
Causes of Blackout cont'd
2. Inadequate level of situation awareness: FE failed to ensure security of its system after significant
unforeseen contingencies
FE lacked procedures to ensure that its operators were
continually aware of the functional state of their critical
monitoring tools FE did not have adequate backup tools for system monitoring
3. Inadequate level of vegetation management (tree trimming)
FE failed to adequately manage tree growth into transmission
rights-of-way
resulted in the outage of three 345 kV lines and one 138 kV
line
cont'd
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
82/150
1529pk - 82Copyright P. Kundur
Causes of Blackout cont'd
4. Inadequate level of support from the Reliability Coordinator
due to failure of state estimator, MISO did not become aware of
FE's system problems early enough
did not provide assistance to FE
MISO and PJM (Regional Transmission operator) did not have in
place an adequate level of procedures and guidelines for dealing
with security limit violations due to a contingency near their
common boundary
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
83/150
1529pk - 83
September 23, 2003 Blackout of Southern
Sweden and Eastern Denmark
Copyright P. Kundur
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
84/150
Blackout of 23 September 2003 in Southern Sweden
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
85/150
1529pk - 85Copyright P. Kundur
p
and Eastern Denmark
Pre-disturbance conditions:
system moderately loaded
facilities out of services for maintenance:
400 kV lines in South Sweden
4 nuclear units in South Sweden
3 HVDC links to Germany and Poland
The first contingency was loss of a 1200 MW nuclear unit in
South Sweden at 12:30 due to problems with steam valves
increase of power transfer from the north
system security still acceptable
cont'd
Blackout of 23 September 2003 in Southern Sweden
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
86/150
1529pk - 86Copyright P. Kundur
p
and Eastern Denmark (cont'd)
Five minutes later (at 12:35) a disconnector damage caused a
double busbar fault at a location 300 km away from the first
contingency
resulted in loss of a number of lines in the southwestern grid and
two 900 MW nuclear units
At 12:37, voltage collapse in the eastern grid section south of
Stockholm area
isolated southern Sweden and eastern Denmark system from
northern and central grid
The Blackout in Southern Sweden and Eastern
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
87/150
1529pk - 87Copyright P. Kundur
Denmark, September 23, 2003
TenhultStrmma
Horred
Sdersen
Barsebck
Hemsj
Simpevarp
Nybro
Kimstad
Glan
Kolstad
Hallsberg
Breared Alvesta
The voltage collapse
Maintenance work
The fault in Horred
Line outages due to:
TenhultStrmma
Horred
Sdersen
Barsebck
Hemsj
Simpevarp
Nybro
Kimstad
Glan
Kolstad
Hallsberg
Breared Alvesta
The voltage collapse
Maintenance work
The fault in Horred
Line outages due to:
The voltage collapse
Maintenance work
The fault in Horred
Line outages due to:
Voltage Collapse
IsolatedSubsystem
The Blackout in Southern Sweden and Eastern
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
88/150
1529pk - 88Copyright P. Kundur
Denmark, September 23, 2003
The blacked-out area after the grid separation at 12.37
Blackout of 23 September 2003 in Southern Sweden
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
89/150
1529pk - 89Copyright P. Kundur
The isolated system had enough generation to cover only about 30%of its demand
voltage and frequency collapsed within a few seconds, blacking out the
area
Impact of the blackout:
loss of 4700 MW load in south Sweden
1.6 million people affected
City of Malmo and regional airports and rail transportation without
power
loss of 1850 MW in eastern Denmark
2.4 million people affected
City of Copenhagen, airport and rail transportation without power
Result of an (n-3) contingency, well beyond "design contingencies"
p
and Eastern Denmark cont'd
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
90/150
1529pk - 90
September 28, 2003 Blackout of Italy
Copyright P. Kundur
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
91/150
1529pk - 91Copyright P. Kundur
Italian System Blackout of 28 September 2003
Predisturbance conditions (Sunday, 3:00 am):
total load in Italy was 27,700 MW, with 3638 MW pump load
total import from rest of Europe was 6651 MW
Sequence of events:
a tree flashover caused tripping of a major tie-line between Italy and
Switzerland (Mettlen-Lavorgo 380 kV line) at 03:01:22 Sychro-check relay prevented automatic and manual reclosure of line due
to the large angle (42) across the breaker
resulted in an overload on a parallel path
attempts to reduce the overload by Swiss transmission operators by
network change was not successful
at 03:21 import by Italy was reduced by 300 MW but was not sufficient to
mitigate the overload of a second 380 kV line (Sils-Soazza), which tripped
at 03:25:22 due to sag and tree contact
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
92/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
93/150
1529pk - 93
What Can We Do To Prevent
Blackouts?
Copyright P. Kundur
F t I ti S t S it
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
94/150
1529pk - 94Copyright P. Kundur
Factors Impacting on System Security
Regulatory Framework
Governments, Reliability Councils
Business Structure
Owning and operating entities; Financial
and contractual arrangements
Physical System
Integrated Generation,
Transmission, Distribution
System
Comprehensive Approach to Enhancing System
St bilit
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
95/150
1529pk - 95Copyright P. Kundur
Stability
Impractical to achieve 100% reliability of power systems
Good design and operating practices could significantly minimize
the occurrence and impact of widespread outages
Reliability criteria: risk-based security criteria
Improved protective relaying
Robust stability controls
Coordinated emergency controls
Comprehensive stability assessment: analytical tools and models
Real-time system system monitoring and control
Wide-spread use of distributed generation
Reliability Management System
Good vegetation management
R li bilit C it i
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
96/150
1529pk - 96Copyright P. Kundur
Reliability Criteria
At present, systems designed and operated to withstand loss of anysingle element preceded by single-, double-, or three-phase fault
referred to as "N-1 criterion"
formulated nearly 40 years ago after the 1965 blackout
Need for using risk-based security assessment criteria
consider multiple outages
account for probability and consequences of instability
Built-in overall strength or robustness best defense againstcatastrophic failures !
I d P t ti R l i
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
97/150
1529pk - 97Copyright P. Kundur
Improved Protective Relaying
State-of-the-art protective relaying for generating units andtransmission lines
adaptive relaying
Replacement of zone 3 and other backup relaying on important
lines with improved relaying
Improved protection and control at power plants to minimize unit
tripping for voltage and frequency excursions
Protective relay improvements to prevent tripping of critical
elements on overload
control actions to relieve overload
R b t St bilit C t l
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
98/150
1529pk - 98Copyright P. Kundur
Robust Stability Controls
Greater use of stability controls excitation control (PSS), FACTS, HVDC, secondary voltage control
multi-purpose controls
multiple controllers
Coordination, integration and robustness present challenges good control design procedures and tools have evolved
Hardware design should provide
high degree of functional reliability
flexibility for maintenance and testing
Industry should make better use of controls !
E C t l f E t C ti i
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
99/150
1529pk - 99Copyright P. Kundur
Emergency Controls for Extreme Contingencies
Contingencies more severe than normal design contingencies
multiple contingencies
can occur anywhere on the system in any form
Currently, emergency controls used to protect against some
generator tripping, load shedding, dynamic breaking, controlled
system separation, transfer tap-changer blocking
Need for a systematic approach to cover against all likely extreme
contingencies
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
100/150
Examples of Response-Based Emergency Control
S h
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
101/150
1529pk - 101Copyright P. Kundur
Schemes
1. Scheme for prevention of voltage collapse in Eastern Ontario
fully automated and coordinated emergency controls for voltage
stability
2. Transient Excitation Boosting
for enhancing transient (angle) stability of systems with dominant
interarea swing
Example 1: Prevention of Voltage Collapse in
E t O t i
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
102/150
1529pk - 102Copyright P. Kundur
Eastern Ontario
Implemented in early 1980s to cope with delays in building 500 kV
line
Under high load conditions, loss of a major 230 kV line leads to
voltage collapse of Ottawa area
A coordinated scheme consisting of fast line reclosure, load
rejection, shunt capacitor switching, and transformer ULTC
blocking
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
103/150
Example 1: (cont'd)
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
104/150
1529pk - 104Copyright P. Kundur
Example 1: (cont'd)
Coordination provided by appropriate selection of voltage and
time settings
triggered by voltage drop magnitude and duration
Following a contingency, depending on the severity (power flow,
line outage), only the required level of control action provided
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
105/150
1529pk - 105Copyright P. Kundur
1300 MW
1374 MW
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
106/150
1529pk - 106Copyright P. Kundur
Response-Based Emergency Controls
Example 2: Transient Excitation Boosting
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
107/150
1529pk - 107Copyright P. Kundur
Example 2: Transient Excitation Boosting
In situations with dominant interarea swing, PSS reduces
excitation after the first local mode swing
Improvements in TS achieved by keeping excitation at ceiling
until highest composite swing
increase in internal voltage
increase in voltage also increases power consumed by area load
Block Diagram of TSEC Scheme
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
108/150
1529pk - 108Copyright P. Kundur
Block Diagram of TSEC Scheme
Effect of TSEC on Transient Stability
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
109/150
1529pk - 109Copyright P. Kundur
Effect of TSEC on Transient Stability
Example 2: (cont'd)
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
110/150
1529pk - 110Copyright P. Kundur
Example 2: (cont d)
Transient Excitation Boosting, TSEC, applied to four major plants
in Ontario:
Nanticoke (4000 MW), Bruce A and B (6000 MW), Lennox (2000 MW)
signal proportional to angle swing
integrated with PSS and coordinated with terminal voltage limiter
In effect, a nonlinear adaptive closed loop control
may use local or remote signals
imposes little duty on equipment
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
111/150
State-of-the-Art On-Line Dynamic Security
Assessment (DSA)
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
112/150
1529pk - 112Copyright P. Kundur
Assessment (DSA)
Practical tools have been developed with the required accuracy, speedand robustness
a variety of analytical techniques integrated
distributed hardware architecture using low cost PCs
integrated with energy management system
Capable of assessing rotor angle stability and voltage stability
determine critical contingencies automatically
security limits/margins for all desired energy transactions
identify remedial measures
The industry has yet to take full advantage of these developments !
Dynamic Security Assessment Tools Developed and
Used by Powertech for System Design and Operation
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
113/150
1529pk - 113Copyright P. Kundur
Used by Powertech for System Design and Operation
Powerful set of complementary programs:
flexible and detailed models
alternative and efficient solution techniques
Transient (Angle) Stability Assessment: TSAT
Small-Signal (Angle) Stability Assessment: SSAT
Voltage Stability Assessment: VSAT
Frequency Stability Analysis: LTSP*cont'd
LTSP currently not maintained/supported*
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
114/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
115/150
1529pk - 115
On-Line Voltage Stability Assessment Tool
(VSAT)
Copyright P. Kundur
Key Elements of VSAT
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
116/150
1529pk - 116Copyright P. Kundur
Key Elements of VSAT
Interface with EMS; Model Initialization
Contingency screening and selection
Determination of secure operating region
using static analysis
Determination of remedial actions
Fast time-domain simulation
validation and checking
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
117/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
118/150
Security Computation Module
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
119/150
1529pk - 119Copyright P. Kundur
y p
Engine for voltage stability analysis
static analysis with detailed models
Secure region is defined by a number of Coordinates (SRCs)
key system parameters: MW generation, area load, interface
transfers, etc.
Voltage security determined by voltage stability margin
MVAr reserves of key reactive sources
post-contingency voltage decline
Modal analysis of powerflow Jacobian matrix identifies areas prone
to instability
Specialized powerflow dispatcher and solver to quickly search for
stability limit
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
120/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
121/150
Secure Operating Region
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
122/150
1529pk - 122Copyright P. Kundur
p g g
Remedial Measures Module
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
123/150
1529pk - 123Copyright P. Kundur
Determines necessary remedial measures to ensure sufficient stability margins
expand the secure region
Preventative control actions:
taken prior to a contingency
caps/reactor switching, generation redispatch, voltage rescheduling
Corrective (emergency) control actions:
applied following a contingency
load shedding, generator runback, transformer tap changer blocking
Ranking of each remedial measure using:
sensitivity analysis
user-defined priorities
Ranking and Applying Remedial Measures
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
124/150
1529pk - 124Copyright P. Kundur
g pp y g
Objective is to identify the most effective remedial measures to givethe desired stability margin
Obtain solved power flow case for the most severe contingency
gradually introduce the effect of the contingency
bus injection compensation technique
Compute the sensitivities of reactive power (or bus voltage) to
different control measures
rank the remedial measures
Apply controls one at a time in order of ranking until power flowsolves for the most severe contingency
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
125/150
Fast Time-Domain Simulation Module
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
126/150
1529pk - 126Copyright P. Kundur
Determines the essential dynamic phenomena without step-by-stepnumerical integration
when chronology of events significant
for validating the effect of remedial measures
Focuses on the evolution of system dynamic response driven by
slow dynamics
transformer tap changers, field current limiters, switched caps
Captures the effects of fast dynamics by solving associated steadystate equations
Mathematical Formulation
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
127/150
1529pk - 127Copyright P. Kundur
The complete set of differential/algebraic equations of a power
system has the following general form:
Where:
X = state vector
V = bus voltage vector
I = current injector vector
Y = network admittance matrix
Z = variables associated with the slow
control devices including ULTCs, loads, switchable reactors
and capacitors, and field current limiters
Z,V,XfX
Z,V,XIYV
Mathematical Formulation
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
128/150
1529pk - 128
Copyright P. Kundur
At each equilibrium point, Z=Zi and the system operating conditionis obtained by solving the following set of nonlinear algebraic
equations:
As time progresses, the slow control devices operate and the
values of Z change. The above set of nonlinear algebraic equations
is solved every time the values of Z change.
i
i
ZV,X,IYV
ZV,X,f0
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
129/150
1529pk - 129
Copyright P. Kundur
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
130/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
131/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
132/150
A Practical Tool for TSA
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
133/150
1529pk - 133
Copyright P. Kundur
Overall architecture similar to that of VSA
Time-domain program, with detailed models and efficient solution
techniques, forms simulation engine
EEAC used for screening contingencies, computing stability margin,
stability limit search, and early termination of simulation
Prony analysis for calculation of damping of critical modes of
oscillation
A powerflow dispatcher and solver for finding the stability limit
a fully automated process
No modeling compromises;
can handle multi-swing instability
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
134/150
EEAC
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
135/150
1529pk - 135
Copyright P. Kundur
Loss of transient stability in a power system always starts in a
binary splitting of generators:
Critical cluster of generators
Rest of the system
At any given point in the
time-domain trajectory of
the system, the system
can be visualized as a
one-machine-infinite-bus
(OMIB) system
EEAC
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
136/150
1529pk - 136
Copyright P. Kundur
The classical equal area criterion can be extended to the visual OMIBsystem
Stability margin of the system is defined as
da
a
ad
ad
d
ad
AAA
AAx
AA
A
AAx
unstableissystemtheif100
stableissystemtheif100
Thus, -100 , and
if the system is stable if the system is unstable
can be used as a stability index
Use of EEAC Theory
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
137/150
1529pk - 137
Copyright P. Kundur
Contingency screening
stability margin gives an indication of the relative severity
Corrective measures for maintaining secure system operation
critical cluster of generators (CCG) provides valuable information
Power transfer limit search
stability limit can be determined in four iterations using stability margin
each iteration involves a detailed simulation and computation of stability
index
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
138/150
Limit Search Results
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
139/150
1529pk - 139
Copyright P. Kundur
Speed Enhancement: Parallel Processing
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
140/150
1529pk - 140
Copyright P. Kundur
Code parallelization differential equations easily parallelized, but not network equations
speed-ups limited by serial slowdown effect
up to 7 times speed-up can be achieved with 20-30 processors
not an effective way
Conventional serial computers offer much faster computational
per-CPU
For multiple contingencies
perform initialization only once
run contingencies on multiple processors - one processor per
contingency
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
141/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
142/150
Computational Speed of DSA (cont'd)
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
143/150
1529pk - 143
Copyright P. Kundur
Voltage Stability Assessment:
- screening 300 contingencies 20.0 secs
- detailed security analysis 1.2 secs
with 20 critical contingencies- one transfer limit search 12.0 secs
Transient Stability Assessment:
- screening 100 contingencies 75.0 secs
- 10 second simulations with 75.0 secs
10 critical contingencies- one transfer limit search 120.0 secs
- total time for complete assessment < 5 mins
Power System model with 4655 buses, 156 generators, using 1.7 GHz,Pentium 4 PC with 256 MB memory
Future Trends in DSA: Intelligent Systems
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
144/150
1529pk - 144
Copyright P. Kundur
Knowledge base created using simulation of a large number cases and
system measurements
Automatic learning, data mining, and decision trees to build intelligent
systems
Fast analysis using a broad knowledge base and automatic decision making
Provides new insight into factors and system parameters affecting stability
More effective in dealing with uncertainties and large dimensioned problems
We just completed a PRECARN project: "POSSIT"
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
145/150
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
146/150
Distributed Generation (DG)
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
147/150
1529pk - 147
Copyright P. Kundur
Offer significant economic, environmental and security benefits
Microturbines
small, high speed power plants
operate on natural gas or gas from landfills
Fuel Cells combines hydrogen with oxygen from air to generate electricity
hydrogen may be supplied from an external source or generated inside
fuel cell by reforming a hydrocarbon fuel
Not vulnerable to power grid failure due to system instability or
natural calamities
protection and controls should be designed so that units continue to
operate when isolated from the grid
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
148/150
Summary
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
149/150
1529pk - 149
Copyright P. Kundur
1. The new electricity supply industry presents increasing challenges forstable and secure operation of power systems
2. State-of-the-art methods have advanced our capabilities significantly
comprehensive stability analysis tools
automated tools for system planning/design
on-line Dynamic Security Assessment (DSA)
coordinated design of robust stability controls
3. Industry is yet to take full advantage of these developments
cont'd
Summary (cont'd)
7/29/2019 CIGRE PowerSystemStabilityNewIndustry KundurPowerSols CAN PP1
150/150
4. Future directions will be to explore new techniques which canbetter deal with growing uncertainties and increasing
complexities of the problem
risk-based security assessment
intelligent systems for DSA
"self-healing" power systems
real-time monitoring and control
5. Wide-spread use of distributed generation could be a costeffective means of minimizing the impact of power grid failures