25
1 City of Oshkosh Stormwater Management Public Information Meetings Public Information Meetings Sawyer Creek Watershed Sawyer Creek Watershed September 15 & 17, 2009 September 15 & 17, 2009 Room 404 / 406, City Hall Room 404 / 406, City Hall

City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

  • Upload
    vanthu

  • View
    215

  • Download
    2

Embed Size (px)

Citation preview

Page 1: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

1

City of OshkoshStormwater Management

Public Information MeetingsPublic Information Meetings

Sawyer Creek WatershedSawyer Creek Watershed

September 15 & 17, 2009September 15 & 17, 2009

Room 404 / 406, City HallRoom 404 / 406, City Hall

Page 2: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

2

Overview

• Sawyer Creek Storm Water Management Plan

• Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

• Water Quality Analysis

• Options Analysis

• Future Direction from Common Council

Page 3: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

3

Sawyer Creek

Page 4: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

4

• Reduce or eliminate street flooding to the maximum extent practicable.

• Reduce 100-year floodplain elevations to remove habitable buildings from the 100-year floodplain, where possible.

• Culverts/Bridges at street crossings should convey stormwater runoff from a 100-year storm event without roadway overtopping, where possible. If this is not possible, provide passage of the greatest storm event possible (25-year to 50-year being desirable).

• Stormwater management practices to be employed should improve stormwater quality by reducing the amount of suspended solids and attached nutrients in the runoff to the maximum extent practicable.

Sawyer Creek Plan Goals

Page 5: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

5

Sawyer Creek Existing Conditions

Flooding Analysis Points:1150 South Oakwood RoadMercy Medical Generator729 North Washburn Street1020 North Westfield Street1036 North Lark Street

Mercy Medical Center

(Looking North from 9th)

Oakwood Road (Looking

East from Ruschfield)

Kienast Bridge

(Looking West)

USH 41

STH 21

Page 6: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

6

Sawyer Creek Existing Conditions

100Sawyer Street

50-100Westfield Drive

100USH 41 and Frontage Roads

5-10Naslund Residence

5-10Pommerening Residence

25-50Westhaven Drive

25-50West 9th Avenue

25-50Oakwood Road

<2Pedestrian Bridge 1

<2Pedestrian Bridge 2

25-50Clairville / CTH K

Approximate Overtopping

Frequency (Design Storm

Event)

Roadway Crossing

Bridge Overtopping Frequency

Page 7: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

7

Considered Detention•Vacant Land N.E. of Clairville/W. 20th

•Vacant Land (17.1 Ac) N. of Mercy•Vacant Land (14.1 Ac) W. of Fleet Farm•Vacant Area S. of Meadow Park Dr. and W. of Badger/Oakwood intersection•Various Locations in Rural Watersheds Upstream of Clairville

Sawyer Creek Alternatives Analysis

USH 41

STH 21

STH 44

Page 8: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

8

Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

• Sawyer Creek

– Alternatives 6 and 7 have best performance based upon flood reduction.

• Alternative 6 impacts Westhaven Golf Course

• Alternative 7 does not impact Westhaven Golf Course

• Campbell Creek

– Alternatives 12 and 13B have best performance based upon flood reduction• Alternative 13B impacts Westhaven Golf Course

• Alternative 12 does not impact Westhaven Golf Course

Page 9: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

9

Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

• Impacting Westhaven

– James Road / STH 91

– Oakwood Road

– Sawyer Creek Dredging

– Tipler Middle School

– Armory

– Westhaven Golf Course

• Not Impacting Westhaven

– James Road / STH 91

– Oakwood Road

– Sawyer Creek Dredging

– Tipler Middle School

– Expanded Armory

– 9th & Washburn

Options for Managing Stormwater

Page 10: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

10

James Road / STH 91 Detention Basin

USH 41

STH 21

STH 44

Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

Page 11: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

11

Oakwood Road Detention Basin(Southwest Industrial Park)

USH 41

STH 21

STH 44

Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

Page 12: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

12

Sawyer Creek Dredging – Westfield Street Locale

Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

Page 13: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

13

Tipler Middle School Dry Detention Basin

Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

Page 14: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

14

Westhaven East

Westhaven West

Sawyer Creek

Westhaven East

Westhaven West

Campbell Creek

Westhaven Golf Course Detention Basins

USH 41

STH 21

STH 44

Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

Page 15: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

15

Westhaven Golf Course Detention Basins

Golf Course Operations are Retained

Oakwood Road

9th Avenue

WesthavenDrive

Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

Page 16: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

16

Armory Detention Basin

Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

Page 17: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

17

Expanded Armory Detention Basin

Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

Page 18: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

18

9th and Washburn Detention Basin

Combined Mitigation Strategies for Sawyer Creek and Campbell Creek Watersheds

Page 19: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

19

Water Quality Analysis

• Wisconsin DNR Storm Water Discharge Permit Coverage issued on January 2, 2007

• Permit requires reduction of pollution to waters of the state

• Pollutant of Interest: Total Suspended Solids (TSS)

• Must reduce Base Load by 40% by 2013

Page 20: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

20

0

100

200

300

400

500

600

700

Storage

Provided (ac-ft)

WithoutWesthaven

WithWesthaven

Options Analysis

0

10000

20000

30000

40000

50000

60000

70000

Cost per ac-ft

WithoutWesthaven

WithWesthaven

Page 21: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

21

Options Analysis

200

250

300

350

400

450

500

550

600

100-year Flood

Plain (acres)

Existing

WithoutWesthaven

WithWesthaven

1000

1200

1400

1600

1800

2000

2200

Dwelling Units

within Flood

Plain

Existing

WithoutWesthaven

WithWesthaven

Page 22: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

22

Options Analysis

6

7

8

9

10

11

12

13

Miles of Street

within Flood

Plain

Existing

WithoutWesthaven

WithWesthaven

0

10

20

30

40

50

60

70

80

90

Tons TSS

Removed

Existing

WithoutWesthaven

WithWesthaven

Page 23: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

23

Summary

Options Analysis

NA

12.37

2,182

683

$ 265,778,500

591

NA

NA

Existing Conditions

1,2951,535Number of Dwelling Units within City within 100-year Flood Plain

$ 36,664,169$ 25,217,169Project Cost

6.408.19Miles of Streets within 100-year Flood Plain

410496Number of Residential City Parcels within 100-year Flood Plain

$ 176,244,500$ 192,006,500Estimated City Parcel Value in 100-year Flood Plain

359385100-year Flood Plain Area (ac)

80.926.6Total TSS Removed (tons/year)

Storage Provided (ac-ft) 677.6365.5

Impacting WesthavenNot Impacting Westhaven

To make up the pollution reduction difference between the two options, approximately 460 acres of Commercial, Industrial and Institutional Land would require treatment with Bio-filters. The estimated construction cost would be $4.2 million, with estimated annual maintenance costs of $620,000 vs. $28,000 for the detention basins.

Page 24: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

24

Future Direction from Common Council

• To utilize Westhaven Golf Course, or not.

• To begin implementation of Sawyer Creek Storm Water Management Plan.

Page 25: City of Oshkosh Stormwater Management · PDF file• Stormwater management practices to be employed should improve ... – Armory – WesthavenGolf Course • Not Impacting Westhaven

25

Discussion