Concrete Basements the New Design Guide

Embed Size (px)

DESCRIPTION

Concrete Basements the New Design Guide

Citation preview

  • Charles Goodchild CEng., MCIOB, MIStructE

    Principal Structural Engineer

    The Concrete Centre

    Concrete Basements Guidance on the design and construction of in-situ concrete basement structures 8 November 2012

  • Concrete Basements

  • Concrete Basements

    2007, issues for concrete basements:

    Imminent introduction of the Eurocodes Withdrawal of BS 8110, BS 8007 etc Revision to BS 8102

    Recent information: CIRIA C660 CIRIA C580 ICE Reducing the Risk Guide Research

    Previous references CIRIA R139/R140

    IStructE Design and construction of deep basements

    Debate

    Recognised need for up-to-date guidance

    TCC proposal (with BSI B525/2 encouragement)

    Nary Narayanan approached and commissioned.

  • Concrete Basements

    Main Authors Nary Narayanan Clark Smith Partnership Charles Goodchild The Concrete Centre

    Steering Group: Alan Gilbertson Consultant (Chairman) Stuart Alexander WSP; Edwin Bergbaum Waterman; John Caine Curtins; Donal Coughlan Halcrow ; Roger Davies Ramboll ; Graham Hardwick John Doyle ; Bill Hewlett Costain ; Ratnam Kugananthan Laing ORourke ; Andy Lyle Capita ; Stuart Marchand Wentworth House; Mahesh Parmar Team 4 Consulting Alan K Tovey The Basement Information Centre ; Robert Vollum Imperial College ; Bjorn Watson SKM Anthony Hunt ; Rod Webster Concrete Innovation and Design ; Derek S Winsor Mott Macdonald ; Corresponding members: Phil Bamforth The Solution Organisation; Tony Jones Arup; Deborah Lazurus Arup.

    Contributions Robin Atkinson, Stephen Blundell, John Bungey, Sooren Chinnappa, John Clarke, Peter Goring, John Morrison, Zedi Nyirenda, Duncan Oughton, Ian Whyte & thanks to Andrew Bond.

    1st full draft April 2008

    3 full meetings

    15 versions/drafts

  • Concrete Basements

    Symbols 1. Introduction 2. Outline of

    design 3. Planning of

    basements (17 pp)

    4. Ground movements etc.

    5. Selection of materials

    6. Structural design general

    7. Lateral earth pressures (28 pp)

    8. Design for ULS

    9. Design for SLS (26 pp)

    10. Worked example (26 pp)

    11. Specification and details

    12. Case studies

    References

    App. A: Design data App. B: NA

    and SLS stresses

  • Concrete Basements

    1. Establish Clients

    requirements

    2. Site surveys, etc

    3. Outline designs,

    methodology

    and proposals

    4. On approval do

    detailed design

    5. Construction

    2 Outline of the design process

  • Concrete Basements

    3 Planning a basement:

    Grades (BS 8102)

    1 basic utility

    2 better utility

    3 habitable

    (4) special

    Types (BS 8102)

    A Barrier (Membrane) protection

    B Structurally integral protection

    C Drained protection

    Forms

    RC box

    Contiguous/ secant piling

    Diaphragm

  • Concrete Basements

    3 Planning a basement: Types

    Type A

    Barrier protection

    Type B

    Structurally integral

    protection

    Type C

    Drained protection

  • Concrete Basements

    3 Forms Table 3.4?

    Table 3.4

    Forms of rc basement construction related to site conditions and use of basement space

    Water

    table

    Form Method Water excl-uding property

    Likely grade that can be achieved with different levels of vapour exclusion

    Likely

    grade

    Additional measures

    Generally

    below

    lowest

    floor level

    RC box Open

    excavation or

    in temporary

    works

    Good if designed

    as Type B to BS

    EN 1992-3

    1 or 2 No additional measures

    3 (or (4)) Type A or (Type C)

    Otherwise insufficient Should be treated as Type A or as Type C.

    Contiguous

    piling with

    facing wall

    Excavated

    after piling:

    floors act as

    props

    Insufficient.

    Drained cavity

    necessary

    extnl. No additional measures

    1 and 2 Designed concrete facing wallc

    1 and 2 Drained cavity or int. membraneb

    3 and (4) Drained cavity/ membraneb / precautionsa

    Perman-

    ently

    above

    lowest

    basement

    floor level

    variable

    to high

    RC box In open

    excavation -

    managing

    ground water

    Good- if treated

    as Type B and

    design to BS EN

    1992-3

    1 or 2 No additional measures

    3

    (or (4))

    External or internal membrane or

    drained cavity and active

    precautionsa

    Secant

    piling with

    facing wall

    Excavated

    after piling:

    floors act as

    props

    Insufficient.

    Drained cavity

    nec. Piling acc-

    essible for repair

    1 and 2 Drained cavity and internal tanking

    3 and 4 Drained cavity and/or internal

    membrane b and active precautionsa

    Diaphragm

    walling

    Excavated

    after piling:

    floors act as

    props

    Insufficient.

    Drained cavity

    necessary. Wall

    accessible for

    repair

    1 and 2 A designed concrete facing wallc

    1 and 2 Drained cavity and/or membrane

    3

    (or (4))

    Drained cavity and internal

    membraneb and/or precautionsa

    Note : Based on CIRIA Report R140[20].

    Key a Active precautions relate to heating and ventilation requirements to achieve the required internal environment.

    b Fully bonded waterproofing membrane applied on the inside face of the structural walls.

    c Facing walls may be designed to BS EN 1992-3, so where integrated with a designed slab form an RC box with the properties

    and likely grades indicated for RC boxes above.

    Dir

    ecti

    on o

    f in

    cre

    asi

    ng c

    ost

  • Concrete Basements

    3 Planning a basement: Other subjects

    Surveys and ground investigations

    Precautions near underground tunnels, sewers & service mains

    Working adjacent to existing structures: Party walls

    Tolerance of buildings to damage

    Space planning

    Integrating basement with the superstructure

    Fire safety considerations

    Client approval

  • Concrete Basements

    4 Ground movements and construction methods

    Construction methods:

    Open excavation Bottom up Top down Semi-top down Groundwater

    Options for basement walls:

    In open excavations: R C walls Incorporating temporary embedded

    retaining walls

    o King post walls

    o Steel sheet piling

    o Contiguous piled wall

    o Secant piled wall

    o Diaphragm walls

    Facing walls

    Temporary works

  • Concrete Basements

    5 Selection of materials

    Concrete:

    Benign soils:

    RC30/37? Cement IIB-V (CEM I + 21%-35% fly ash) or IIIA

    (CEM I + 36% - 65% ggbs).

    Aggressive soils: Advise producer of DC Class.

    For DC-2: FND-2? (C25/30)?

    More aggressive soils: Cement IIIB (CEM I + 66% - 80%

    ggbs) or IIVB-V (CEM I + 36%-55% fly ash)

    Car Parks: C32/40? + provisos

    cf C35A?: requirements: C28/35 (equiv) -- WCR 0.55 CC 325 CEM I, IIB-V,)

    RC30/37: requirements : C30/37 S3 WCR 0.55 CC 300 CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V B)

  • Concrete Basements

    5 Selection of materials

    Waterproofing membranes and systems:

    Category 1 Bonded sheet membranes Category 2 Cavity drain membranes Category 3 Bentonite clay active membranes Category 4 Liquid applied membranes Category 5 Mastic asphalt membranes Category 6 Cementitious crystallisation active systems Category 7 Proprietary cementitious multi-coat renders, toppings and coatings

    Admixtures for watertightness

    Water stops at construction joints

    Preformed strips rubber, PVC, black steel Water-swellable water stops Cementitious crystalline water stops Miscellaneous post-construction techniques

    (Re) injectable water bars Rebate and sealant

  • Concrete Basements

    6 Structural design general

    Options for basement slabs Soil-structure interaction Beams on elastic foundations FEA

    Options for basement walls Temporary conditions: construction method and sequence Permanent condition

    Loads to be considered: Slabs: column & wall loads, basement slab load, upward water

    pressure, heave.

    Walls, lateral earth pressure, water pressure, compaction, loads from superstructure, imbalances.

    Design ground water pressure

    Normal and maximum levels

    Unplanned excavations Allowances for cantilever retaining systems

  • Concrete Basements

    7 Calculation of lateral earth pressures

    Angle of shearing resistance:

    Granular soils:

    Estimated peak effective angle of shearing resistance

    max = 30 + A + B + C (A - Angularity, B - Grading, C - N blows)

    Clay soils

    In the long term,

    clays behave as

    granular soils

    exhibiting friction

    and dilation.

  • Concrete Basements

    7 Calculation of lateral earth pressures

    Examples:

    1. Active pressures

    2. At-rest pressures

    3. Surcharge from

    imposed loads

    4. Surcharge from

    pad foundation

    5. Compaction

    pressures

  • Concrete Basements

    8 Design for Ultimate Limit State

    EQU Equilibrium Limit State

    STR & GEO Structural and geotechnical Limit States

    Combinations 1 and 2

    gF for ground water

    o Normal gF = 1.35

    o Most unfavourable gF = 1.20

    Structural design

    o As normal elements

    o 3D nature of design

  • Concrete Basements

    9 Design for Serviceability Limit State

    Control of cracking

    9.1 Causes of cracking and general principles of crack control

    9.2 General principles of crack control and minimum reinforcement

    9.3 Sequence for verification of cracking

    9.4 Test for restraint cracking

    9.5 Minimum reinforcement

    9.6 Crack widths and watertightness

    9.7 Crack width calculations

    9.8 Crack control without direct calculation

    9.9 Deflection control

    9.10 Minimising the risk of cracking

  • Concrete Basements

    9 Design for Serviceability Limit State

    9.1 Causes of cracking and general principles of crack control:

    9.1.1 Early thermal effects

    9.1.2 Autogenous and drying shrinkage

    9.1.3 Restraints

    9.1.4 Cracking due to restraint (early thermal and shrinkage

    effects)

    9.1.5 Cracking due to flexure

    9.1.6 Cracking due to combinations of restraint and loading

    Assumed that target limiting crack widths will give satisfactory

    performance

    9.2 General principles of crack control and minimum reinforcement

    Provision of minimum reinforcement does not guarantee any

    specific crack width. It is simply a necessary amount presumed by

    models to control cracking; but not necessarily a sufficient amount

    to limit actual crack widths.

  • Concrete Basements

    9 Design for Serviceability Limit State

    9.3 Sequence for verification of cracking

    8 Design for ULS

    9.4 Check whether section is likely to crack

    9.5 Check minimum reinforcement

    9.6 Determine limiting crack width

    9.7 Calculate crack width

    9.7.1 Crack width and crack spacing, wk = sr,max cr

    Crack inducing strain:

    9.7.2 cr due to edge restraint and early thermal effects.

    9.7.3 cr due to edge restraint and long term effects

    9.7.4 cr due to end restraint

    9.7.5 cr due to flexure (and applied tension)

    9.7.6 cr due to a combination of restraint and loading

  • Concrete Basements

    9 Design for Serviceability Limit State

    9.4 Test for restraint cracking

    A section will crack if:

    r = Rax free = K[([cT1 +ca) R1 + ([cT2 R2) + cd R3] ctu

    where K = allowance for creep = 0.65 when R is calculated using CIRIA C660

    = 1.0 when R is calculated using BS EN 1992-3

    c = coefficient of thermal expansion (See CIRIA C660 for values). See Table A6 for typical values

    T1 = difference between the peak temperature of concrete during hydration and ambient

    temperature C (See CIRIA C660). Typical values are noted in Table A7

    ca = Autogenous shrinkage strain value for early age (3 days: see Table A9) R1, R2,

    R3

    = restraint factors. See Section A5.6

    For edge restraint from Figure L1 of BS EN 1992-3 for short- and long-term thermal and long-

    term drying situations. For base-wall restraint they may be calculated in accordance with

    CIRIA C660. Figure L1 may be used with CIRIA C660 methods providing an adjustment for

    creep is made (See Figure A2 and note).

    For end restraint, where the restraint is truly rigid 1.0 is most often used, for instance in infill

    bays. This figure might be overly pessimistic for piled slabs.

    T2 = long-term drop in temperature after concreting, C. T2 depends on the ambient temperature

    during concreting. The recommended values from CIRIA C660 for T2 are 20C for concrete cast

    in the summer and 10C for concrete cast in winter. These figures are based on HA BD

    28/87[60] based on monthly air temperatures for exposed bridges. Basements are likely to

    follow soil temperatures so T2 = 12C may be considered appropriate at depth.

    cd

    ctu

    =

    =

    drying shrinkage strain, dependent on ambient RH, cement content and member size (see BS

    EN 1992-1-1 Exp. (3.9) or CIRIA C660 or Table A10). CIRIA C660 alludes to 45% RH for internal

    conditions and 85% for external conditions.

    tensile strain capacity may be obtained from Eurocode 2 or CIRIA C660 for both short term and

    long term values

  • Concrete Basements

    9 Design for Serviceability Limit State

    9.5 Minimum reinforcement

    As,min = kc k Act (fct,eff /fyk)

    where

    kc =

    =

    A coefficient to account for stress distribution.

    1.0 for pure tension.

    When cracking first occurs the cause is usually early thermal effects and the whole section is likely

    to be in tension.

    k =

    =

    A coefficient to account for self-equilibrating stresses

    1.0 for thickness h < 300 mm and 0.65 for h > 800 mm (interpolation allowed for thicknesses

    between 300 mm and 800 mm).

    Act = area of concrete in the tension zone just prior to onset of cracking. Act is determined from section

    properties but generally for basement slabs and walls is most often based on full thickness of the

    section.

    fct,eff == fctm

    mean tensile strength when cracking may be first expected to occur:

    for early thermal effects 3 days for long-term effects, 28 days (which considered to be a reasonable approximation) See Table A5 for typical values.

    fyk =

    =

    characteristic yield strength of the reinforcement.

    500 MPa

    [1] CIRIA C660 Recent research[61] would suggest that a factor of 0.8 should be applied to fct,eff in the formula for crack

    inducing strain due to end restraint. This factor accounts for long-term loading, in-situ strengths compared with laboratory

    strengths and the fact that the concrete will crack at its weakest point. TR 59[62] concludes that the tensile strength of

    concrete subjected to sustained tensile stress reduces with time to 6070% of its instantaneous value.

    The area of reinforcement obtained using this value may well

    need increasing during the remaining design process

  • Table 9.2 Tightness Classes

    Concrete Basements

    9 Design for Serviceability Limit State

    9.6 Crack widths and watertightness

  • Tightness Classes- notes:

    Concrete Basements

    9 Design for Serviceability Limit State

    9.6 Crack widths and watertightness

  • Concrete Basements

    9 Design for Serviceability Limit State

    9.6 Crack widths and watertightness -recommendations

    Table 9.4

    Summary of crack width recommendations

    Construction

    typea and water

    table

    Expected

    performance of

    structure

    Crack width requirement Tight

    -ness

    Class

    wk mm

    Flex-ural wk,max[9]

    Restraint/ axial wk,1

    [10]

    A Structure itself is not considered watertight

    Design to Tightness class 0 of BS EN 1992-3. See

    Table 9.2. Generally 0.3 mm for RC structure 0 0.30 0.30e

    B high permanently high

    water table

    Structure is almost

    watertight

    Design to Tightness class 1 of BS EN 1992-3. See

    Table 9.2. Generally 0.3 mm for flexural cracks

    but 0.2 mm to 0.05 mm for cracks that pass

    through the section

    1 0.30b 0.05 to

    0.20 (wrt hd/h)

    B variable fluctuating water

    table

    Structure is almost

    watertight

    Design to Tightness class 1 of BS EN 1992-3. See

    Table 9.2. Generally 0.3 mm for flexural cracks

    but 0.2 mm for cracks that pass through the

    section

    1 c 0.30 b 0.20

    B lowd water table

    permanently below

    underside of slab

    Structure is watertight

    under normal conditions. Some risk under exceptional conditions.

    Design to Tightness class 0 of BS EN 1992-3. See

    Table 9.2. Generally 0.3 mm for RC structures 0 c 0.30 0.30

    C Structure itself is not considered watertight

    Design to Tightness class 0 of BS EN 1992-3. See

    Table 9.2. Generally 0.3 mm for RC structure.

    Design to Tightness Class 1 may be helpful for

    construction type C

    0

    (1)c

    0.30

    (0.3)

    0.30e

    (0.05 to 0.20 or 0.20)

    Key b Where the section is not fully cracked) the neutral axis depth at SLS should be at least xmin (where xmin > max {50 mm or 0.2 section thickness}) and variations in strain should be less than 150 106.

  • Concrete Basements

    9 Design for Serviceability Limit State

    9.7 Crack width calculations

    9.7.1 Crack width, wk = sr,max cr

    where

    sr,max = Maximum crack spacing = 3.4c + 0.425 (k1k2 /p,eff)

    cr = Crack-inducing strain = (Restrained strain effect of crack formation)over 2 debonding lengths = (Mean strain in steel mean strain in concrete)over 2 debonding lengths = (cs - cm ). . . . . . . . . . . . . . .

    where

    c = nominal cover, cnom

    k1 = 0.8

    (CIRIA C660 suggests 1.14)

    k2 =

    =

    =

    1.0 for tension (e.g. from restraint)

    0.5 for bending

    (1 + 2)/21 for combinations of bending and tension = diameter of the bar in mm.

    p,eff = As/Ac,eff

    Ac,eff for each face of a wall is based on 0.5h; 2.5(c + 0.5); (h x)/3 where

    h = thickness of section

    x = depth to neutral axis.

  • sm

    c

    s

    cm = 0

    sm

    c

    s

    cm = 0

    Sr,max

    S0S0S0S0

    Consider a crack in a section:

    sm - cm

    sm

    c

    s

    cm = 0

    sm

    c

    s

    cm = 0

    Sr,max

    S0S0S0S0

    ctu

    Strain

    Plan (or section)

    Strain in reinforcement

    Strain in concrete

    sm

    c

    s

    cm = 0

    sm

    c

    s

    cm = 0

    Sr,max

    S0S0S0S0

    Concrete Basements

    sm

    c

    s

    cm = 0

    sm

    c

    s

    cm = 0

    Sr,max

    S0S0S0S0

    sm

    c

    s

    cm = 0

    sm

    c

    s

    cm = 0

    Sr,max

    S0S0S0S0

    sr,max

    wk = sr,max cr

  • Concrete Basements

    9 Design for Serviceability Limit State

    cr = Crack-inducing strain = . . . . . . . . . . . . . . .

    9.7.2 Early age crack-inducing strain

    cr = K[cT1 +ca R1 0.5 ctu

    9.7.3 Long term crack-inducing strain

    cr = K[([cT1 +ca) R1 + ([cT2 R2) + cd R3] 0.5 ctu

    9.7.4 End restraint crack-inducing strain

    cr = 0.5e kckfct,eff [1 + (1/e ) /Es

    9.7.5 Flexural (and applied tension) crack-inducing strain

    cr = (sm cm) = [s kt (fct,eff /p,eff) (1 + e p,eff /Es

    cr 0.6 (s)/Es

  • Concrete Basements

    9 Design for Serviceability Limit State

    9.8 Crack control without direct calculation

    dont do it!

    9.9 Deflection control

    As normal design

    9.10 Minimising the risk of cracking

    9.10.1 Materials use cement replacements, aggregates with low ac, avoid high strength concretes

    9.10.2 Construction construct at low temperatures, use GRP or steel formwork, sequential pours

    9.10.3 Detailing use small bars at close centres, avoid movement joints, prestress?

  • Concrete Basements

    10 Worked Example

  • Concrete Basements

    10 Worked Example

    Commentary:

    In slab 53T : end restraint critical

    In walls 10T: edge restraint critical

    Iterations required/ refinements: fct,eff, e, ct = 0.8, end restraint, concrete,

    construction methodology

    Use CIRIA C660 rather than BS EN 1992-3

  • Concrete Basements

    11 Specification and construction details

    11.1 Specification:

    BS EN 13670 NSCS / NBS ICE specification for piling and embedded retaining walls

    11.2 Joints

    Construction joints Water stops

    11.3 Miscellaneous

    Kickers Formwork ties Membranes & coatings Admixtures & additives Service penetrations Drainage Underpinning

    11.4 Inspection, remedials & maintenance

    Preformed strips PVC, black steel Water-swellable water stops (Re) injectable epoxy water bars

  • Concrete Basements

    12 Case studies

  • Concrete Basements

    References

  • Concrete Basements

    Appendix A: Design data

    A1 Combination factors

    A2 Design angle of shearing resistance

    A3 Pressure coefficients Kad and Kpd

    A4 Bending moment coefficients for rectangular plates

    A5 Design data for crack width formulae

    A5.1 fctm ( fct,eff), mean tensile strengths of concretes

    A5.2 c, coefficient of thermal expansion

    A5.3 T1, difference between the peak temperature of concrete

    during hydration and ambient temperature C

    A5.4 ca, autogenous shrinkage strain

    A5.5 cd, drying shrinkage strain

    A5.6 R, restraint factors

    A5.7 ctu, tensile strain capacity of concrete

    A5.8 Moduli of elasticity of concrete Ecm and modular ratio, ae

  • Concrete Basements

    Appendix B: Neutral Axes and SLS stresses

    B1 Neutral axis at SLS (cracked

    section and no axial stress)

    B2 SLS stresses in concrete, c and reinforcement, s (cracked section and no axial stress)

    B2.1 Singly reinforced section

    B2.2 Doubly reinforced section

    B3 SLS stresses in concrete, c, and in reinforcement, s due to flexure and axial load (cracked

    section)

  • Concrete Basements

    This guide covers the design and

    construction of reinforced concrete

    basements and is in accordance with

    the Eurocodes.

    The aim of the guide is to assist designers of

    concrete basements of modest depth, i.e.

    not exceeding 10 metres. It will also prove

    relevant to designers of other underground

    structures. It brings together in one

    publication the salient features for the

    design and construction of such water-

    resisting structures.

    The guide has been written for generalist

    structural engineers who have a basic understanding of soil mechanics.

  • Concrete Basements Guidance on the design and construction of in-situ concrete basement structures

    Thank you