CRONOGRAMA VALORIZADO DE AVANCE DE OBRA PROYECTO: Cliente: MUNICIPALIDAD DISTRITO DE SAN JUAN DE CHACÑA 7/21/2015 UBIICACION SAN JUAN DE CHACÑA - AYMARAES - APURIMAC. Mes 01 Mes 02 Item Descripción Und Metrado Semana 1 Semana 2 Semana 3 Semana 4 Semana 5 Semana 6 Semana 7 Semana 8 Parcial % Parcial % Parcial % Parcial % Parcial % Parcial % Parcial % 01 REDES COLECTORAS 22,545.16 4,567.11 20% 5,242.92 23% 7,957.37 35% 467.01 2% 2,057.14 9% 2,117.24 9% 136.38 01.01 OBRAS PROVISIONALES 417.23 417.23 01.01.01 CARTEL DE OBRA und 1.00 417.23 417.23 417.23 01.02 963.48 963.48 01.02.01 LIMPIEZA DEL TERRENO MANUAL m2 504.00 0.42 211.68 211.68 01.02.02 TRAZO NIVELES Y REPLANTEO m 420.00 1.79 751.80 751.80 01.03 MOVIMIENTO DE TIERRAS 12,617.45 3,186.40 5,242.92 626.89 1,308.05 2,116.81 136.38 01.03.01 EXCAVACION A MANUAL EN TERRENO NORMAL m3 488.88 15.26 7,460.31 2,981.02 4,479.29 01.03.02 EXCAVACION EN ROCA FIJA m3 14.40 34.41 495.50 205.38 290.12 01.03.03 REFINE Y NIVELACION DE ZANJAS m2 420.00 1.41 592.20 473.51 118.69 01.03.04 CAMA DE ARENA E=0.05M APOYO PARA TUB. DE DESAGUE m 420.00 1.21 508.20 508.20 01.03.05 RELLENO COMPACTADO DE ZANJAS m 252.00 12.87 3,243.24 1,308.05 1,935.19 01.03.06 ELIMINACION DE MATERIAL EXCEDENTE m3 50.00 6.36 318.00 181.62 136.38 01.04 SUMINISTRO E INSTALACION DE TUB. Y ACCESORIOS 8,131.20 7,330.48 467.01 333.72 01.04.01 SUMINISTRO E INSTALACION DE TUB. CSN UNION FLEXIBLE 6" m 420.00 19.36 8,131.20 7,330.48 467.01 333.72 01.05 PRUEBA DE HIDRAULICA 415.80 415.37 0.43 01.05.01 PRUEBA HIDRAULICA DE DESAGUE m 420.00 0.99 415.80 415.37 0.43 02 RED DE EMISORES 11,842.53 118.12 1% 7,669.90 65% 1,420.11 12% 2,263.74 19% 370.66 3% 02.01 146.82 118.12 28.70 02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 76.80 0.42 32.26 25.79 6.47 02.01.02 TRAZO NIVELES Y REPLANTEO m 64.00 1.79 114.56 92.33 22.23 02.02 MOVIMIENTO DE TIERRAS 10,061.15 7,641.20 1,420.11 730.02 269.82 02.02.01 EXCAVACION A MANO EN TERRENO NORMAL m3 30.72 289.60 8,896.51 7,622.93 1,273.58 02.02.02 EXCAVACION DE ZANJAS EN TERRENO ROCOSO m3 4.80 4.30 20.64 18.27 2.37 02.02.03 REFINE Y NIVELACION DE ZANJAS m 64.00 1.41 90.24 77.32 12.92 02.02.04 CAMA DE ARENA E=0.05M APOYO PARA TUB. DE DESAGUE m 64.00 1.21 77.44 66.84 10.6 02.02.05 RELLENO COMPACTADO DE ZANJAS m 64.00 12.87 823.68 706.5 117.18 02.02.06 ELIMINACION DE MATERIAL EXCEDENTE m3 24.00 6.36 152.64 152.64 02.03 SUMINISTRO E INSTALACION DE TUB. Y ACCESORIOS 1,571.20 1,533.72 37.48 02.03.01 SUMINISTRO E INSTALACION DE TUB. CSN UNION FLEXIBLE 4" m 64.00 24.55 1,571.20 1,533.72 37.48 02.04 PRUEBA DE HIDRAULICA 63.36 63.36 02.04.01 PRUEBA HIDRAULICA DE DESAGUE m 64.00 0.99 63.36 63.36 03 BUZONES 6,843.50 255.97 4% 137.18 2% 6,239.93 91% 210.43 3% 03.01 MOVIMIENTO DE TIERRAS 297.33 255.97 41.37 03.01.01 TRAZO NIVELES Y REPLANTEO m2 1.13 7.39 8.35 8.36 03.01.02 EXCAVACION A MANO PARA BUZONES EN TERRENO NORMAL m3 7.95 36.35 288.98 247.61 41.37 03.02 CONCRETO SIMPLE 95.85 95.81 0.04 03.02.01 SOLADO DE CONCRETO 1:12 PARA BUZONES m2 0.21 456.43 95.85 95.81 0.04 03.03 CONCRETO ARMADO 6,450.32 6,239.89 210.43 03.03.01 BUZONES 6,450.32 6,239.89 210.43 03.03.01.01 BUZONES TIPO I (H=0.80M) und 1.00 1,403.27 1,403.27 1,403.22 0.05 03.03.01.02 BUZONES TIPO II (H=2.45M) und 1.00 1,540.21 1,540.21 1,540.15 0.06 03.03.01.03 BUZONES TIPO III (H=3.08M) und 2.00 1,753.42 3,506.84 3,296.52 210.32 04 MUROS DE CONTENCION 5,773.61 5,573.38 97% 145.75 3% 54.47 1% 0.01 0% 04.01 EXCAVACION A MANO EN TERRENO NORMAL m3 10.50 289.60 3,040.80 3,040.80 04.02 RELLENO Y COMPACTACION CON MATERIAL PROPIO m3 2.64 19.47 51.40 30.82 20.58 04.03 ELIMINACION DE MATERIAL EXCEDENTE m3 5.33 6.36 33.90 33.89 0.01 04.04 CONCRETO CILOPEO PARA MURO DE CONTENCION. FC=140KG/CM2 + 60% P.G. m3 10.29 257.29 2,647.51 2,532.58 114.93 05 PLAN DE MANEJO AMBIENTAL 4,081.20 2,624.74 64% 1,456.46 36% 05.01 CONFORMACION DE COMITES DE MANTENIMIENTO LIEMPIEZA GENERAL glb 1.00 241.20 241.20 225.74 15.46 05.02 CILINDRO DE BASURA CON RUEDAS und 16.00 240.00 3,840.00 2,399.00 1,441.00 06 FLETE TERRESTRE 1,400.00 1,400.00 100% 06.01 FLETE ABANCAY - CHACÑA glb 1.00 1,400.00 1,400.00 1,400.00 Costo Directo S/. 52,486.00 5,967.11 5,361.04 15,627.27 7,716.47 4,603.81 11,407.04 1,803.28 Gastos Generales 7.55% S/. 3,965.00 450.78 404.99 1,180.55 582.93 347.79 861.73 136.23 Elaboracion Expediente Tecnico S/. 2,000.00 2,000.00 0.00 0.00 0.00 0.00 0.00 0.00 Liquidacion de Obra S/. 1,100.00 0.00 0.00 0.00 0.00 0.00 0.00 1,100.00 Supervicion de Obra S/. 1,337.00 191.00 191.00 191.00 191.00 191.00 191.00 191.00 Presupuesto Total S/. 60,888.00 8,608.89 14.1% 5,957.03 9.8% 16,998.82 27.9% 8,490.40 13.9% 5,142.60 8.4% 12,459.77 20.5% 3,230.51 5.3% AVANCE SEMANAL ACUMULADO 14.1% 23.9% 51.8% 65.8% 74.2% 94.7% 100.0% MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE DESAGUE DEL SECTOR DE UCHUBAMBA, DISTRITO DE SAN JUAN DE CHACÑA, AYMARAES - APURIMAC. LLACLLA, DISTRITO DE ABELARDO PARDO LEZAMETA -BOLOGNESI - ANCASH P. Unit. S/. Parcial S/. TRABAJOS PRELIMINARES TRABAJOS PRELIMINARES

Cronograma Valorizado

Embed Size (px)

DESCRIPTION

cuadro para realizar un cronograma valorizado de una obra un cualquier proyecto

Citation preview

Page 1: Cronograma Valorizado

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

PROYECTO:

Cliente: MUNICIPALIDAD DISTRITO DE SAN JUAN DE CHACÑA7/21/2015

UBIICACION SAN JUAN DE CHACÑA - AYMARAES - APURIMAC.

Mes 01 Mes 02

Item Descripción Und MetradoSemana 1 Semana 2 Semana 3 Semana 4 Semana 5 Semana 6 Semana 7 Semana 8

Parcial % Parcial % Parcial % Parcial % Parcial % Parcial % Parcial %

01 REDES COLECTORAS 22,545.16 4,567.11 20% 5,242.92 23% 7,957.37 35% 467.01 2% 2,057.14 9% 2,117.24 9% 136.38

01.01 OBRAS PROVISIONALES 417.23 417.23

01.01.01 CARTEL DE OBRA und 1.00 417.23 417.23 417.23

01.02 963.48 963.48

01.02.01 LIMPIEZA DEL TERRENO MANUAL m2 504.00 0.42 211.68 211.68

01.02.02 TRAZO NIVELES Y REPLANTEO m 420.00 1.79 751.80 751.80

01.03 MOVIMIENTO DE TIERRAS 12,617.45 3,186.40 5,242.92 626.89 1,308.05 2,116.81 136.38

01.03.01 EXCAVACION A MANUAL EN TERRENO NORMAL m3 488.88 15.26 7,460.31 2,981.02 4,479.29

01.03.02 EXCAVACION EN ROCA FIJA m3 14.40 34.41 495.50 205.38 290.12

01.03.03 REFINE Y NIVELACION DE ZANJAS m2 420.00 1.41 592.20 473.51 118.69

01.03.04 CAMA DE ARENA E=0.05M APOYO PARA TUB. DE DESAGUE m 420.00 1.21 508.20 508.20

01.03.05 RELLENO COMPACTADO DE ZANJAS m 252.00 12.87 3,243.24 1,308.05 1,935.19

01.03.06 ELIMINACION DE MATERIAL EXCEDENTE m3 50.00 6.36 318.00 181.62 136.38

01.04 SUMINISTRO E INSTALACION DE TUB. Y ACCESORIOS 8,131.20 7,330.48 467.01 333.72

01.04.01 SUMINISTRO E INSTALACION DE TUB. CSN UNION FLEXIBLE 6" m 420.00 19.36 8,131.20 7,330.48 467.01 333.72

01.05 PRUEBA DE HIDRAULICA 415.80 415.37 0.43

01.05.01 PRUEBA HIDRAULICA DE DESAGUE m 420.00 0.99 415.80 415.37 0.43

02 RED DE EMISORES 11,842.53 118.12 1% 7,669.90 65% 1,420.11 12% 2,263.74 19% 370.66 3%

02.01 146.82 118.12 28.70

02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 76.80 0.42 32.26 25.79 6.47

02.01.02 TRAZO NIVELES Y REPLANTEO m 64.00 1.79 114.56 92.33 22.23

02.02 MOVIMIENTO DE TIERRAS 10,061.15 7,641.20 1,420.11 730.02 269.82

02.02.01 EXCAVACION A MANO EN TERRENO NORMAL m3 30.72 289.60 8,896.51 7,622.93 1,273.58

02.02.02 EXCAVACION DE ZANJAS EN TERRENO ROCOSO m3 4.80 4.30 20.64 18.27 2.37

02.02.03 REFINE Y NIVELACION DE ZANJAS m 64.00 1.41 90.24 77.32 12.92

02.02.04 CAMA DE ARENA E=0.05M APOYO PARA TUB. DE DESAGUE m 64.00 1.21 77.44 66.84 10.6

02.02.05 RELLENO COMPACTADO DE ZANJAS m 64.00 12.87 823.68 706.5 117.18

02.02.06 ELIMINACION DE MATERIAL EXCEDENTE m3 24.00 6.36 152.64 152.64

02.03 SUMINISTRO E INSTALACION DE TUB. Y ACCESORIOS 1,571.20 1,533.72 37.48

02.03.01 SUMINISTRO E INSTALACION DE TUB. CSN UNION FLEXIBLE 4" m 64.00 24.55 1,571.20 1,533.72 37.48

02.04 PRUEBA DE HIDRAULICA 63.36 63.36

02.04.01 PRUEBA HIDRAULICA DE DESAGUE m 64.00 0.99 63.36 63.36

03 BUZONES 6,843.50 255.97 4% 137.18 2% 6,239.93 91% 210.43 3%

03.01 MOVIMIENTO DE TIERRAS 297.33 255.97 41.37

03.01.01 TRAZO NIVELES Y REPLANTEO m2 1.13 7.39 8.35 8.36

03.01.02 EXCAVACION A MANO PARA BUZONES EN TERRENO NORMAL m3 7.95 36.35 288.98 247.61 41.37

03.02 CONCRETO SIMPLE 95.85 95.81 0.04

03.02.01 SOLADO DE CONCRETO 1:12 PARA BUZONES m2 0.21 456.43 95.85 95.81 0.04

03.03 CONCRETO ARMADO 6,450.32 6,239.89 210.43

03.03.01 BUZONES 6,450.32 6,239.89 210.43

03.03.01.01 BUZONES TIPO I (H=0.80M) und 1.00 1,403.27 1,403.27 1,403.22 0.05

03.03.01.02 BUZONES TIPO II (H=2.45M) und 1.00 1,540.21 1,540.21 1,540.15 0.06

03.03.01.03 BUZONES TIPO III (H=3.08M) und 2.00 1,753.42 3,506.84 3,296.52 210.32

04 MUROS DE CONTENCION 5,773.61 5,573.38 97% 145.75 3% 54.47 1% 0.01 0%

04.01 EXCAVACION A MANO EN TERRENO NORMAL m3 10.50 289.60 3,040.80 3,040.80

04.02 RELLENO Y COMPACTACION CON MATERIAL PROPIO m3 2.64 19.47 51.40 30.82 20.58

04.03 ELIMINACION DE MATERIAL EXCEDENTE m3 5.33 6.36 33.90 33.89 0.01

04.04 CONCRETO CILOPEO PARA MURO DE CONTENCION. FC=140KG/CM2 + 60% P.G. m3 10.29 257.29 2,647.51 2,532.58 114.93

05 PLAN DE MANEJO AMBIENTAL 4,081.20 2,624.74 64% 1,456.46 36%

05.01 CONFORMACION DE COMITES DE MANTENIMIENTO LIEMPIEZA GENERAL glb 1.00 241.20 241.20 225.74 15.46

05.02 CILINDRO DE BASURA CON RUEDAS und 16.00 240.00 3,840.00 2,399.00 1,441.00

06 FLETE TERRESTRE 1,400.00 1,400.00 100%

06.01 FLETE ABANCAY - CHACÑA glb 1.00 1,400.00 1,400.00 1,400.00

Costo Directo S/. 52,486.00 5,967.11 5,361.04 15,627.27 7,716.47 4,603.81 11,407.04 1,803.28

Gastos Generales 7.55% S/. 3,965.00 450.78 404.99 1,180.55 582.93 347.79 861.73 136.23

Elaboracion Expediente Tecnico S/. 2,000.00 2,000.00 0.00 0.00 0.00 0.00 0.00 0.00

Liquidacion de Obra S/. 1,100.00 0.00 0.00 0.00 0.00 0.00 0.00 1,100.00

Supervicion de Obra S/. 1,337.00 191.00 191.00 191.00 191.00 191.00 191.00 191.00

Presupuesto Total S/. 60,888.00 8,608.89 14.1% 5,957.03 9.8% 16,998.82 27.9% 8,490.40 13.9% 5,142.60 8.4% 12,459.77 20.5% 3,230.51 5.3%

AVANCE SEMANAL ACUMULADO 14.1% 23.9% 51.8% 65.8% 74.2% 94.7% 100.0%

MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE DESAGUE DEL SECTOR DE UCHUBAMBA, DISTRITO DE SAN JUAN DE CHACÑA, AYMARAES - APURIMAC.LLACLLA, DISTRITO DE ABELARDO PARDO LEZAMETA -BOLOGNESI - ANCASH

P. Unit.S/.

ParcialS/.

TRABAJOS PRELIMINARES

TRABAJOS PRELIMINARES

Page 2: Cronograma Valorizado

CALENDARIO DE UTILIZACION DE EQUIPO

Item DescripciónPLAZO DE EJECUCION

Semana 1 Semana 2 Semana 3 Semana 4

MANO DE OBRA

1.1 CAPATAZ 1 1 1 1

1.2 OPERARIO 1 1 1 1

1.3 OFICIAL 1 1 1 1

1.4 PEON 1 1 1 1

1.5 TOPOGRAFO 1 1 1 1 1

1.6 MANO DE OBRA - T 2 2 2 2 2

1.7 MANO DE OBRA - LT 1 1 1 1 1

1.8 MANO DE OBRA-A 1 1 1 1 1

1.9 MANO DE OBRA - SEÑALIZACION 2 2 2

1.10 1 1 1 1 1

1.11 MANO DE OBRA - PROTECCION COLECTIVA 1 1 1

1.12 CHARLAS DE CAPACITACION EN SEGURIDAD AL PERSONAL 1 1 1 1 1

1.13 MANO DE OBRA - CAPACITACION EN SEGURIDAD 1 1 1 1 1

MATERIALES

2.1 ALAMBRE NEGRO Nro. 8 1 1 1 1 1

2.2 ALAMBRE NEGRO Nro.16 1 1 1 1

2.3 CLAVOS CON CABEZA DE 2 1/2", 3", 4" 1 1 1 1 1

2.4 CLAVOS CON CABEZA DE 3" 1 1 1 1 1

2.5 CLAVOS CON CABEZA DE 4" 1 1 1

2.6 ACERO 1 1 1

2.7 ARENA GRUESA 1 1 1

2.8 ARENA FINA 1 1 1 1

2.9 PIEDRA CHANCADA DE 1/2” Y 3/4" 1 1 1

2.10 AGUA 1 1 1 1 1

2.11 AGUA 1 1 1 1

2.12 ASFALTO LIQUIDO RC-250 1 1 1 1

2.13 MEZCLA ASFALTICA EN CALIENTE 1 1 1

2.14 TRANSPORTE DE MEZCLA ASFALTICA C/VOLQUETE 10M3 1 1 1 1

2.15 LADRILLO KK TIPO IV 24X13X09 CM 1 1 1 1

2.16 CEMENTO PORTLAND TIPO I (42.5kg) 1 1 1 1

2.17 PEGAMENTO PARA TUBERIA PVC 1 1 1 1

2.18 CAL (BOLSA X 20 kg) 1 1 1 1

2.19 CORDEL 1 1 1 1

2.20 IMPERMEABILIZANTE LIQUIDO PARA CONCRETO 1 1 1 1

2.21 EXTINTOR DE POLVO SECO 1 1 1 1

2.22 DISCO DE CORTE DE 16" 1 1

2.23 CASCO DE PROTECCION 1 1

2.24 BOTINES DE CUERO 1 1

2.25 TAPONES AUDITIVOS 1 1

2.26 GUANTES DE CUERO 1 1

2.27 RESPIRADOR CONTRA POLVO 1 1

2.28 CHALECOS REFLECTIVOS 1 1

CantidadUnd

ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO

Page 3: Cronograma Valorizado

2.29 LENTES DE PROTECCION 1 1

2.30 MATERIALES - PROTECCION COLECTIVA 1 1

2.31 MATERIALES - SEÑALIZACION SEGURIDAD 1 1

2.32 CAMILLA 1 1

2.33 BOTIQUIN CON MEDICINA 1

2.34 CILINDRO VACIO 1

2.35 TAPA DE CONCRETO C/MARCO F°F PARA BUZON ø 0.60m 1

2.36 GASOLINA 95 OCTANOS 1

2.37 HORMIGON 1

2.38 AFIRMADO 1

2.39 MADERA TORNILLO 1

2.40 MADERA TORNILLO-A 1

2.41 KEROSENE INDUSTRIAL 1

2.42 TUBO PVC-SAP - 8" (5M) 1

2.43 TUBO PVC-SAP-4" (3M) 1

2.44 TUBO PVC-SAP - 6" (5M) 1

2.45 TAPON PVC SAL P/DESAGUE 08” 1

EQUIPOS 1

3.1 HERRAMIENTA 1

3.2 HERRAMIENTA-T 1

3.3 HERRAMIENTA - LT 1

3.4 COMP. NEUMATICA - 93 HP - 335/375 PCM 1

3.5 MARTILLO NEUMATICO - 25/29 KG 1

3.6 RETROEXCAVADORA S/LLANT. 62 HP -1 YD3 1

3.7 TRACTOR DE TIRO DE 60HP 1

3.8 PLANCHA COMPACTADORA VIBRAT. 4.0 HP 1

3.9 RODILLO NEUMATICO AUTOP. 81-100HP 5.5-20T 1

3.10 RODILLO TANDEM ESTATIC AUT 58-70HP 8-10T 1

3.11 MEZCLADORA DE CONC.(TAMBOR) 11 P3,18 HP 1

3.12 VIBRADOR A GASOLINA Y 1 3/4", 4 HP 1

3.13 CORTADORA DE CONCRETO 13 HP 1

3.14 CAMION VOLQUETE 4x2, 210/280 HP, 8 M3 1

3.15 TEODOLITO Y MIRA 1

3.16 BARREDORA MECANICA 10-20HP

3.17 PAVIMENTADORA SOBRE ORUGAS 105HP 10-16'

3.18 CAMION IMPRIMADOR 6x2 178-210HP 2000 GLN

Page 4: Cronograma Valorizado

CRONOGRAMA DE ADQUISICION DE MATERIALES

ItemDescripción

Und Cant.PLAZO DE EJECUCION

Semana 1 Semana 2 Semana 3 Semana 4

MANO DE OBRA

1.1 CAPATAZ H-H 85.53 20.06 1715.73

1.2 OPERARIO H-H 486.37 18.24 8871.40

1.3 OFICIAL H-H 147.67 15.28 2256.36

1.4 PEON H-H 1101.79 13.74 15138.61

1.5 TOPOGRAFO H-H 2.99 21.07 63.03

1.6 MANO DE OBRA - T GLB 1.00 70.00 70.00

1.7 MANO DE OBRA - LT GLB 1.00 315.00 315.00

1.8 MANO DE OBRA-A GLB 1.00 360.00 360.00

1.9 MANO DE OBRA - SEÑALIZACION GLB 1.00 102.95 102.95

1.10 GLB 1.00 500.00 500.00

1.11 MANO DE OBRA - PROTECCION COLECTIVA GLB 1.00 118.15 118.15

1.12 CHARLAS DE CAPACITACION EN SEGURIDAD AL PERSONAL GLB 26.00 30.00 780.00

1.13 MANO DE OBRA - CAPACITACION EN SEGURIDAD GLB 260.00 0.30 78.00

30369.23

MATERIALES

2.1 ALAMBRE NEGRO Nro. 8 kg 9.79 2.47 24.18

2.2 ALAMBRE NEGRO Nro.16 kg 28.91 2.47 71.40

2.3 CLAVOS CON CABEZA DE 2 1/2", 3", 4" kg 2.32 2.80 6.49

2.4 CLAVOS CON CABEZA DE 3" kg 0.77 2.80 2.15

2.5 CLAVOS CON CABEZA DE 4" kg 6.55 2.80 18.35

2.6 ACERO kg 622.06 2.40 1492.94

2.7 ARENA GRUESA m3 28.10 58.60 1646.83

2.8 ARENA FINA m3 1.31 102.50 134.48

2.9 PIEDRA CHANCADA DE 1/2” Y 3/4" m3 10.47 70.64 739.74

2.10 AGUA m3 27.87 5.68 158.30

2.11 AGUA GLB 1.00 300.00 300.00

2.12 ASFALTO LIQUIDO RC-250 gal 39.46 9.51 375.29

2.13 MEZCLA ASFALTICA EN CALIENTE m3 16.03 320.00 5130.11

2.14 TRANSPORTE DE MEZCLA ASFALTICA C/VOLQUETE 10M3 m3 16.03 46.64 747.71

2.15 LADRILLO KK TIPO IV 24X13X09 CM und 50.00 0.85 42.50

2.16 CEMENTO PORTLAND TIPO I (42.5kg) bl 182.43 16.95 3092.22

2.17 PEGAMENTO PARA TUBERIA PVC gal 4.11 97.71 401.44

2.18 CAL (BOLSA X 20 kg) bl 16.81 8.43 141.69

2.19 CORDEL M 63.87 0.15 9.58

2.20 IMPERMEABILIZANTE LIQUIDO PARA CONCRETO gal 2.50 13.56 33.85

2.21 EXTINTOR DE POLVO SECO und 1.00 129.80 129.80

2.22 DISCO DE CORTE DE 16" und 0.88 550.85 487.12

2.23 CASCO DE PROTECCION und 10.00 9.24 92.40

2.24 BOTINES DE CUERO par 10.00 44.83 448.30

P. Unit.S/.

ParcialS/.

ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO

Page 5: Cronograma Valorizado

CRONOGRAMA DE ADQUISICION DE MATERIALES

ItemDescripción

Und Cant.PLAZO DE EJECUCION

Semana 1 Semana 2 Semana 3 Semana 4

P. Unit.S/.

ParcialS/.

2.25 TAPONES AUDITIVOS par 10.00 2.12 21.20

2.26 GUANTES DE CUERO par 10.00 12.63 126.30

2.27 RESPIRADOR CONTRA POLVO und 10.00 2.46 24.60

2.28 CHALECOS REFLECTIVOS und 10.00 7.54 75.40

2.29 LENTES DE PROTECCION und 10.00 5.34 53.40

2.30 MATERIALES - PROTECCION COLECTIVA GLB 1.00 1181.52 1181.52

2.31 MATERIALES - SEÑALIZACION SEGURIDAD GLB 1.00 1029.48 1029.48

2.32 CAMILLA und 1.00 250.00 250.00

2.33 BOTIQUIN CON MEDICINA und 1.00 296.61 296.61

2.34 CILINDRO VACIO und 1.00 67.80 67.80

2.35 TAPA DE CONCRETO C/MARCO F°F PARA BUZON ø 0.60m und 5.00 300.00 1500.00

2.36 GASOLINA 95 OCTANOS gal 88.43 11.02 974.52

2.37 HORMIGON m3 0.02 40.14 0.80

2.38 AFIRMADO m3 53.92 33.60 1811.68

2.39 MADERA TORNILLO p2 252.66 4.40 1111.69

2.40 MADERA TORNILLO-A GLB 1.00 240.00 240.00

2.41 KEROSENE INDUSTRIAL gal 9.87 9.55 94.22

2.42 TUBO PVC-SAP - 8" (5M) M 193.20 23.19 4480.26

2.43 TUBO PVC-SAP-4" (3M) M 18.49 7.42 137.18

2.44 TUBO PVC-SAP - 6" (5M) M 17.03 15.40 262.20

2.45 TAPON PVC SAL P/DESAGUE 08” und 4.42 36.76 162.54

29628.27

EQUIPOS

3.1 HERRAMIENTA %MO 958.30

3.2 HERRAMIENTA-T GLB 1.00 280.00 280.00

3.3 HERRAMIENTA - LT GLB 1.00 35.00 35.00

3.4 COMP. NEUMATICA - 93 HP - 335/375 PCM h-m 2.71 99.81 270.11

3.5 MARTILLO NEUMATICO - 25/29 KG h-m 2.71 4.49 12.16

3.6 RETROEXCAVADORA S/LLANT. 62 HP -1 YD3 h-m 6.85 124.08 849.87

3.7 TRACTOR DE TIRO DE 60HP h-m 0.25 57.69 14.23

3.8 PLANCHA COMPACTADORA VIBRAT. 4.0 HP h-m 78.60 24.16 1898.92

3.9 RODILLO NEUMATICO AUTOP. 81-100HP 5.5-20T h-m 1.21 127.67 154.29

3.10 RODILLO TANDEM ESTATIC AUT 58-70HP 8-10T h-m 1.21 93.28 112.73

3.11 MEZCLADORA DE CONC.(TAMBOR) 11 P3,18 HP h-m 14.31 10.65 152.39

3.12 VIBRADOR A GASOLINA Y 1 3/4", 4 HP h-m 12.48 4.95 61.78

3.13 CORTADORA DE CONCRETO 13 HP h-m 60.78 10.00 607.82

3.14 CAMION VOLQUETE 4x2, 210/280 HP, 8 M3 h-m 3.87 196.77 760.75

3.15 TEODOLITO Y MIRA h-m 2.99 13.46 40.27

3.16 BARREDORA MECANICA 10-20HP h-m 0.25 46.79 11.54

3.17 PAVIMENTADORA SOBRE ORUGAS 105HP 10-16' h-m 1.21 133.17 160.94

Page 6: Cronograma Valorizado

CRONOGRAMA DE ADQUISICION DE MATERIALES

ItemDescripción

Und Cant.PLAZO DE EJECUCION

Semana 1 Semana 2 Semana 3 Semana 4

P. Unit.S/.

ParcialS/.

3.18 CAMION IMPRIMADOR 6x2 178-210HP 2000 GLN h-m 0.25 122.29 30.16

6411.24