134
DL PROFESSIONAL STANDARD OF THE PEOPLE’S REPUBLIC OF CHINA 中华人民共和国行业标准 P DL 5022-1993 Technical Stipulation for the Design of Civil Structure of Thermal Power Plant 火力发电厂土建结构设计技术规定 Issued on June 15, 1993 Implemented on October 1, 1993 Issued by the Ministry of Electric Power Industry of the People’s Republic of China

DL 5022-1993

Embed Size (px)

DESCRIPTION

Dl 5022-1993

Citation preview

Page 1: DL 5022-1993

DL PROFESSIONAL STANDARD

OF THE PEOPLE’S REPUBLIC OF CHINA

中华人民共和国行业标准

P DL 5022-1993

Technical Stipulation for the Design of Civil

Structure of Thermal Power Plant

火力发电厂土建结构设计技术规定

Issued on June 15, 1993 Implemented on October 1, 1993

Issued by the Ministry of Electric Power Industry of the People’s Republic of China

Page 2: DL 5022-1993

Professional Standard of the People’s Republic of China

中华人民共和国行业标准

Technical Stipulation for the Design of Civil Structure of

Thermal Power Plant

火力发电厂土建结构设计技术规定 DL 5022-93

Chief development organization: Northwest Electric Power Design Institute of

Ministry of Power Industry

Approval department: Ministry of Power Industry of the People's

Republic of China

China Water Power Press

水利水电出版社 Beijing 1993

Page 3: DL 5022-1993

Ministry of Power Industry of People's Republic of China

Notice on publishing the power professional standard of "Technical

Stipulation for the Design of Civil Structure of Thermal Power Plant”

Dian Ban (1993) No.132

Design Institute of Power Planning in our department organizes Northwest Electric

Power Design Institute to make revision for the original professional standard "Technical

Stipulation for Soil of Thermal Power Plant" (SDJ 64-84). After the examination by the

ministry, it is now approved to be a power professional standard and to be issued. Standard

serial number is DL 5022-93, which was implemented on October 1st, 1993. The original

bureau standard SDGJ 64-84 shall be abolished simultaneously.

This standard is under the jurisdiction of Design Institute of Power Planning and

Northwest Electric Power Design Institute is responsible for the explanation of this standard.

Please inform the jurisdiction organization the problems and opinions appeared in

implementation process.

This standard is published and distributed by China Water Power Press.

June 15, 1993

Page 4: DL 5022-1993

1

Contents

1 General provisions.................................................................................................................. 1

2 Load........................................................................................................................................ 2

2.1 Basic requirements....................................................................................................... 2

2.2 Live load on roofing and floor (ground) ...................................................................... 4

2.3 Crane load.................................................................................................................. 10

2.4 Wind load shape coefficient........................................................................................11

3 Main building ....................................................................................................................... 14

3.1 Frame (bent) structure................................................................................................ 14

3.2 Roofing structure ....................................................................................................... 21

3.3 Fender structure ......................................................................................................... 29

3.4 Coal scuttle and crane beam ...................................................................................... 31

3.5 Framework of suspensory boiler................................................................................ 35

3.6 Elevator shaft structure of the boilers ........................................................................ 36

3.7 Frame-bent steel structure.......................................................................................... 37

4 Groundwork and foundation................................................................................................. 39

4.1 Fundamental rules...................................................................................................... 39

4.2 Foundation calculation............................................................................................... 40

4.3 Weak foundation ........................................................................................................ 41

4.4 Foundation in mountain area ..................................................................................... 42

4.5 Collapsible loess foundation ...................................................................................... 44

4.6 Foundation ................................................................................................................. 45

4.7 Underdrain ................................................................................................................. 47

5 Dynamic machine foundations ............................................................................................. 49

5.1 Foundations of automobile unit and electric machines.............................................. 49

5.2 Auxiliary machine foundation.................................................................................... 57

6 Fuel buildings ....................................................................................................................... 62

6.1 Coal-fired buildings ................................................................................................... 62

6.2 Fuel oil buildings ....................................................................................................... 71

7 Chimney and flue ................................................................................................................. 72

7.1 General provisions on chimney ................................................................................. 72

7.2 Chimney calculation .................................................................................................. 73

7.3 Measures for controlling the width of longitudinal cracks on chimney..................... 74

7.4 Corrosion resisting measures of chimney .................................................................. 75

7.5 Chimney structure...................................................................................................... 77

7.6 Flue ............................................................................................................................ 77

8 Pipe support .......................................................................................................................... 78

9 Aseismic design.................................................................................................................... 84

9.1 General provisions ..................................................................................................... 84

9.2 Subgrade and foundation ........................................................................................... 89

9.3 Earthquake effect and antiseismic recalculation of structure..................................... 91

9.4 Main workshop .......................................................................................................... 92

9.5 Master control building and distribution equipment building ................................. 100

Page 5: DL 5022-1993

2

9.6 Coal-shifting trestle.................................................................................................. 102

9.7 Silo........................................................................................................................... 102

9.8 Equipment foundation.............................................................................................. 104

9.9 Pipeline support ....................................................................................................... 105

Annex A Calculation Diagram of Transverse Frame (Bent Frame) ...................................... 108

Annex B Vertical And Horizontal Calculation Diagram of Suspended Boiler Framework .. 109

Annex C Determination for Gage Length l0 of the Boiler Framework Frame-Column ........110

Annex D Type-selection, Calculation Diagram and Calculation Formula of Side Wall of

Dumper House and Joint-type Coal Chute .............................................................................111

Annex E Strength Calculation for the Chimney Shaft Opening.............................................117

Annex F Calculation of Wind Load of the Pipeline Support................................................. 120

Annex G Regulation Factor of Theoretical Calculation Period............................................. 123

Annex H Aseismic Calculation Method of Trestle Transverse Direction.............................. 124

Annex I Explanation of Wording in this Code ...................................................................... 128

Additional explanation .......................................................................................................... 129

Page 6: DL 5022-1993

1

1 General provisions

1.0.1 This standard is formulated with a view to go through with national technical economy

policy in the design of civil structure of thermal power plant, and to make safety and usability,

state-of-art technology, economy and rationality as well as guarantee quality.

1.0.2 This stipulation is applicable to the design of civil structure of the thermal power plant

with steam turbine generator capacity is 12-600 MW (hereinafter referred to as power plant).

For the power plant with renovation and other generator capacity, the design may refer to

stipulation and relevant specifications to. Power transformation truss may comply with

"Technical Stipulation for the Design of Building Structure in 35-500 kV Substation".

1.0.3 This stipulation is established according to current relevant standards of the nation and

be combined with characteristics of power plant. Parts not mentioned in this standard shall

still meet the requirement of current relevant standard of the nation.

1.0.4 Structural design shall meet the requirements of strength, stabilization, distortion, crack

resistance and earthquake resistance, etc.

Structural arrangement shall closely cooperate with technology; it shall design according

to unified modular system and give priority to adopting standard design and typical design to

improve level of standardization, serialization, and generalization.

1.0.5 Structural design shall base upon summarization of practical experience and scientific

experiment, and digest and absorb advanced experience in abroad, then closely cooperate

with construction, adopt new technique, new arrangement, new construction, and new

material positively and cautiously.

1.0.6 Spread and apply computer aided design technology positively and increase design level

and work efficiency continually.

1.0.7 When making structural design, it shall adopt different safety classes according to

possible seriousness of consequence caused by structural damage.

Page 7: DL 5022-1993

2

2 Load

2.1 Basic requirements

2.1.1 Design load and load effect combination generally constructed by power plant shall be

adopted according to the stipulation of this Chapter.

Load and load effect combination of special construction in the power plant shall be

adopted according to relevant chapters of this standard.

This specified load is the normal value in the design of building structure.

2.1.2 Load in structures may be divided into the following three kinds:

2.1.2.1 Permanent load (dead load): during application period of structure, the load value will

not vary as time, or its variation may be negligible comparing with average value, such as self

weight structure and earth pressure, etc.

2.1.2.2 Variable load (live load): during application period of the structure, load value varies

as time and its variation is non-negligible comparing with its average value, such as floor

(ground) live load, roofing live load, crane load, wind load and snow load, etc. Note: load on mill construction equipment and pipeline (including sole weight of equipment and pipeline as well as filler

weight in the equipment, pipeline and container shall be considered as live load).

2.1.2.3 Accidental load: load not always appears during application period of the structure,

once it appears, its value is very large, and its duration is short, such as blasting power and

impact force, etc.

2.1.3 Partial load factor of the general load is adopted according to the stipulation of "Load

Specifications for Building Structure.”

Load on equipment and pipeline includes coal (coal dust) in coal (fine coal) scuttle,

deaerator , industrial water tank, tailing classifier and high (low) pressure heater, etc. Its

partial load factor is 1.3.

2.1.4 Load effect combination shall not only comply with "Load Specifications for Building

Structure,” but also comply with the following supplementary provisions:

2.1.4.1 Load effect combination of the main building frame-bent may adopt the following

simplified combination:

1. 1.2Gk+γQiQik+1.3QQk+1.4Qck (2.1.4-1)

1.0Gk+γQiQik+1.3QQk+1.4Qck (2.1.4-2)

2. 1.2Gk+0.85 (γQiQik+1.3QQk+1.4Qck+1.4ωk (2.14-3)

1.0Gk+0.85 (γQiQik+1.3QQk+1.4Qck+1.4ωk (2.14-3)

3. 1.2 (Gk+ψciQik+ψQiQQk+QcG)+1.3Ehk+1.4ψωωk (2.1.4-5)

1.0 (Gk+ψciQik+ψQiQQk+QcG)+1.3Ehk+1.4ψωωk (2.1.4-6)

Where: Gk——Normal value of permanent load;

γQi——Partial load factor of floor live load: when normal value of live load is less

than 4 kN/m2, it takes 1.4; when normal value of the live load is no less than 4

kN/m2, it takes 1.3;

Use normal value of floor live load to calculate mainframe, which shall be adopted

Page 8: DL 5022-1993

3

according to table 2.2.2 of this standard;

Qik——Live load on equipment and pipeline includes coal (coal dust) in coal scuttle,

deaerator and deoxidize water tank (containing water weight), tailing classifier and

high (low) pressure heater, etc. as well as load on supporter and hanger of the

pipeline. For crane load and crane sole weight (earthquake effect combination)

respectively;

ψci, ψQi——Factor of load combination value of floor live load and load on

equipment (pipeline) in making earthquake effect combination respectively, they are

adopted according to table 9.3.4 of this standard;

ψw——Combination value factor of wind load participating in earthquake effect, the

general frame-bent structure ψw=0, boiler cradle takes ψw=0.2;

wk——Normal value of wind load. Note: load effect factors are omitted in formula (2.1.4-1)—formula (2.1.4-6)

2.1.4.2 Load effect combination value of frame beam in main building and column sections,

they may be designed according to the most disadvantageous conditions may be appeared in

the following:

Beam Mmax and its correspondent N, V;

Mmin and its correspondent N, V;

Vmax and its correspondent M, N

Column Mmax and its correspondent N, V;

Mmin and its correspondent N, V;

Nmax and its correspondent M′, V;

Nmin and its correspondent M′, V

Substratum column of the frame shall add the following two combinations besides the

aforementioned combinations:

Vmax and its correspondent M, N;

Vmin and its correspondent M, N Note: M′ is the combination according to positive (+M) and negative (-M) of the correspondent M value, but it only output

one group which is with larger value for the absolute value of M.

2.1.4.3 Buildings give priority to wind load design, such as chimney overhead bridge for coal

conveyer, gable of the main building, open style constructions with tectum, etc. when wind

load combined with dead load and other live load, factor of load combination value of the

wind load takes 1.0.

2.1.4.4 When the frame-bent load effects are combining together, it generally doesn't consider

temporary load of transportation for large pieces and hoisting, etc. during construction and

installation. It shall adopt provisional measures to solve them. If necessary, it may make

strength checkout for individual frame member; its safety class may be adopted by reducing

one level.

2.1.5 When combining design according to long-term effect under normal-use limit state, it

shall adopt would-be permanent value act as representative value for the variable load.

Would-be permanent value of variable load is obtained by normal value of variable load

multiply by would-be permanent value factor of load.

Would-be permanent value factor of floor (ground) live load is adopted according to

numerical value in table 2.2.2, table 2.2.4-1 and table 2.2.4-2 of this standard.

Page 9: DL 5022-1993

4

Would-be permanent value factor of deaerator, industrial water tank, coal, and coal dust in

coal scuttle, tailing classifier and load on pipeline shall all take 1.0.

2.2 Live load on roofing and floor (ground)

2.2.1 When production using, overhauling and constructing/installing the roofing and floor

(ground) of power plant building, load caused by equipment, pipeline, placing of material and

conveyance as well as load of all the equipment, pipeline supporter and hanger on civil

structure shall all be provided by profession of technological design.

2.2.2 When designing according to article 2.1.4 of this standard, load shall take value

according to the following stipulations:

2.2.2.1 When providing load on all the equipments (pipeline) according to technology

profession, floor live load takes value as 2.0 kN/m2.

2.2.2.2 When adopting load on major equipment and pipeline (deaerator, high and low

pressure heater, tailing classifier, industrial water tank, coal scuttle, as well as pipeline such as

main steam, main feedwater, reheat steam, primary air, coal dust system, etc.) provided by

technology profession, floor live load takes value according to floor (roofing) live load for

mainframe calculation in table 2.2.2 of this standard. Table 2.2.2 Live Load on Roofing and Floor (ground) of Main Building in Thermal Power Plant

Normal value

(kN/m2)

Reduction factor for

calculating junior

beam, double T slab

and grid main rib⑧

Single unit

capacity (MW)

No.

Designations

12-125 200-300

Would-be perm

anent value factor

6m≤Spaci

ng of

columns<

9m

9m≤Spac

ing of

columns

≤12m

Reduction

factor when

calculating

major beam

(column)

Floor (roofing) live

load on calculating

main

frame-bent③(kN/m2)

Notices

Firstly Steam turbine house

±0.000m

Site for collective maintenance of basement

top plate① 15—20 25—30 0.5 0.8 0.7 0.7 —

General region of basement top plate 10 10—20 0.5 0.8 0.7 0.7 —

Ground of collective maintenance region 20—30 40 — — — — —

Other leisure ground and trench cover of

reinforced-concrete② 10 10 0.5 — — — — —

1

Steel cover board 2—4 4 0.5 — — — — —

Mesosphere of heater platform — —

Pipeline layer of heater platform④ 4 6 0.7 0.8 — 0.8 —

Heater floor

with low

pressure

High pressure heater platform④ 10 10 0.7 0.8 — 0.8 —

2

Firing floor platform and pedestal platform

of feed pump 15 0.6 0.8 — 0.7 —

3 Mesosphere platform of steam turbine

pedestal 4 6 0.7 0.8 — 0.7 —

Operation of steam turbine house⑤ 4

General region floor slab of heater platform

(including fixed end platform) 8—10 10 0.5 0.8 — 0.7 —

Page 10: DL 5022-1993

5

Passable platform of gable overhanging at

extension end 4 4 0.5 0.8 — 0.7 —

Floor slab of overhauling region for

turbogenerator and turbine pedestal platform15—20 25—30 0.5 0.8 — 0.7 —

Cantilever platform of A organ timbering⑥ 4 6 0.6 1.0 1.0 — 4

Cantilever platform of B organ timbering 8 10 0.6 1.0 1.0 — 5—6

Steel cover board 4 4 0.5 — — — —

5 Roofing of steam turbine house⑦ 1 1 0.2 1.0 1.0 0.7 0.5—0.7

Secondary Oxygen removal house

6 Auxiliary switchgear

floor

4

(10)

4

(10) 0.8 0.8 0.7 — 3 (6)

Values in the parentheses is only for high

voltage switchgear

7

Floor of ventilation

layer and cable grip

layer

4 4 0.7 0.7 0.7 — 3

8 Floor of operation

(pipeline layer) 6—8 6—8 0.7 0.8 0.7 — 5—6

9

Floor of other

(non-operated)

pipeline layer

4 4 0.7 0.8 0.7 — 3

10 Floor of deaerator

layer① 4 6 0.7 0.7 0.7 — 3—4

11 Roofing of oxygen

removal house 4 (2) 4 (2) 0.4 0.7 0.7 3 (1)

Numerical value in the parentheses is for load

on pipeline without any equipment in that layer.

when constructing and installing, it only

permits scattered and few placing of material

Thirdly Bunker bay

12 ±0.000m Terrace of coal

grinding mill 15 20 — — — — —

13 Operation floor 6—8 6—8 0.7 0.8 0.7 — 5—6

14 Platform of feed transfer 4 4 0.7 0.7 0.7 — 3

15 Floor of coal scuttle layer 4 4 0.7 0.7 0.7 3

16 Floor of belt layer 4 4 0.7 1.0 0.8 3

Floor of nose gearing of

conveyer belt 10 10 0.7 0.7 0.7 6

17

Bunker bay roofing 4 (2) 4 (2) 0.4 0.7 0.7 — 3 (1)

Numerical value in the parentheses is for

load on pipeline without any equipment in

that layer. When constructing and

installing, it only permits scattered and few

piling up of materials of equipment.

18

Guiding cantilever

platforms of non-operated

floor in oxygen removal

house and bunker bay

4 4 0.7 0.8 0.7 — 3

Fourthly Boiler room

19 ±0.000m Terrace and trench cover of

reinforced-concrete 10 10 0.5 — — — —

20 Operation floor 8 8 0.6 0.8 0.7 0.7 6

21 Reinforced-concrete platforms of

non-operated floor of boiler cradle

4

(6)

4

(6)0.5 0.7 0.7 — 3 (4)

Taken-values in the

parentheses is only used for

coping platform

22 Roofing of boiler room⑦ 1 1 0.2 1.0 1.0 0.7 0.5—0.7

23 Roofing of penthouse⑦ 1 1 0.0 1.0 1.0 0.8 —

Fifthly Others

24 Floor of central control room 4 4 0.8 0.8 0.8 0.7 3

25 Machinery room floor and platform in 4 4 0.7 — — 0.7 — Floor load of machinery room is

Page 11: DL 5022-1993

6

elevator hoistway provided by manufacturer

26 Steel operating platforms of main

building

2

(4)

2

(4)0.5 — — 0.7 1

Taken-value in the parentheses is

for placing heavier spares as

valve during operating

maintenance

27

Reinforced-concrete stairs (including

main steel stair) in oxygen removal

room and bunker bay)

4 4 0.5 — — — —

28 General steel stair in main building 2 2 0.5 —

29

Other manufacturing building roofing

with possible installation implements

and heat insulator piling up

4 4 0.4 0.8 0.7 0.7

Note: ① When hauling dynamo stator in basement top plate of the steam turbine house or hauling deaerator in the floor, its load

on floor (ground) shall adopt provisional solving measures according to practical hauling scheme.

② When applying ±0.000m equipment operating maintenance (maintenance for fan ground and tube mill) in steam turbine

house and boiler room for reinforced-concrete trench cover and channel (including tunnel) of passage parts, it shall make

calculation according to assemble (or equispaced) live load generated practically. Load on underground facility generated by

temporary heavy lift equipment and transportation hoisting passage during the installation shall be solved by adopting

provisional measures.

③ When spacing of columns is less than 9 m; it takes the larger value, when it is within 9-12 m, it takes the smaller value.

④ Floor live load of high/ low pressure heater in the table is also applicable to horizontal heater floor placing in the oxygen

removal house, but they shall consult to load provided by technology.

⑤ Subarea floor live loads of operation in steam turbine house shall be requiring to be marked on the floor.

⑥ It refers to load on platform of mounting and overhauling of rotor when excluding turbine transverse arrangement, when

it requires to bearing rotor in the platform, it shall provide load by technology.

When turbine is disposed longitudinally, it requires installing overhaul platform in turbine operation platform and cantilever

platform A (B) organ timbering. By this time, load on A (B) organ timbering slab arris (or boundary beam) may be

calculated according to 10 kN/m2 (including sole weight of platform).

⑦ Roofing (including penthouse roofing) live load of steam turbine house and boiler room in the table is only applicable to

reinforced-concrete roofing.

⑧ It shall not consider the reduction factor of junior beam (slab main rib) and reduction factor of main beam (column)

simultaneously.

2.2.3 When designing floor constructional element, floor live load may adopt according to

table 2.2.2, but slab arris (junior beam) shall be counted in pipeline and equipment load (not

considering off-the shelf equipment load such as dial and low tension switch tank, etc.)

2.2.4 When there is no specific requirement for processing set-up, roofing, floor (ground) live

load of other production, auxiliary production and outbuilding may be adopted according to

table 2.2.4-1 and table 2.2.4-2. Table 2.2.4-1 Live Load on Roofing and Floor (Ground) of other Production Building

SN Designations Normal value

(kN/m2)

Would-be

permanent value

factor

Reduction factor

of main beam

(column)

Notices

Firstly Main control floor (grid control building and communication building)

1

Floor of main

control room (grid

control room and

communication

room)

4① 0.8 0.7

2 Floor of cable grip 3 0.8 0.7

Page 12: DL 5022-1993

7

layer

3 Stairs 3 0.5 —

4 Roofing 0.7 0.0 0.7

Secondary 3, 6, 10, 35, and 110 kV indoor-switching arrangement

5 Floor between

buses 4 0.8 0.7

Including isolator

floor

Floor of switch

house

3, 6 and 10 kV

switch house floor 4—7 0.8 0.7

It is provided by

technology when

each block of

switch weight is

larger than 8 kV.

35 and 110 kV

switch house floor 4—8 0.8 0.7

It is provided by

technology when

each block of

switch weight is

larger than 12 kN.

10, 35 and 110 kV

serial switch

cabinet

4 0.8 0.7

It is limited to

each block of

electric appliance

with weight is no

larger than 36 kN.

6

Floor of 110 kV

complete shut-off

combination

electric appliance

10 0.8 0.7

7 Reactor floor

slab② 0.7 0.7

8 Stairs 3 0.5

9 Roofing 0.7 0.0 0.7

Thirdly Coal discharging device building

10

Floor of slot-type

coal chute along

railroad line

10 0.8 1.0

11 Hoist house floor 10 0.7 0.8

12 Scrabble-coal-fee

der hoist house 15 0.7 0.8

Wagon tipper

house

±0.00m floor

(ground) 10 0.7 0.8

Reinforced-concre

te platforms 4 0.7 0.8

13

Roofing 0.7 0.0 0.7

Fourthly Coal store device building

14 Dry coal shed

roofing 0.7③ 0.0

15 Platform of coal

store silo 4—6 0.6 0.8

Fifthly Coal conveyer building

Overhead bridge

for coal conveyer

Floor 3—4④ 0.7 0.6 16

Roofing 0.7 0.0 0.8

Page 13: DL 5022-1993

8

17 Underground coal

shipper tunnel 3—4④

Transfer point

Floor 1 0.7 0.7

Floor of nose

gearing of

conveyer belt

10 0.7 0.8

It shall be

provided by

technology,

generally, it may

be adopted

according to 10

kN/m2

18

Roofing 0.7 0.8

19

Floor between

ground reception

bunkers

4 0.7 0.8

Sixthly Coal-breaker house

Conveyer belt

layer

Floor 4 0.7 0.8

20 Floor of nose

gearing of

conveyer belt

10 0.7 0.8

It shall be

provided by

technology,

generally, it may

be adopted

according to 10

kN/m2

21 Floor of coal

screen layer 4 0.7 0.8

22 Floor of

coal-breaker layer 10—20⑤ 0.7 0.7

23

Substratum of

coal-breaker

house

4 (10) 0.7 0.8

Numerical value

in the parentheses

is only used when

substratum is

terrace

24

Roofing of

coal-breaker

house

0.7 0.2 0.7

25 Roofing of

lighting house 0.7 0.0 0.7

Seventhly Chemical water treatment house

26 Floor of each

layer 3 0.5 0.8

It shall be

provided by

technology,

generally, it may

be adopted

according to 3

kN/m2

27 Testing laboratory 3 0.5 0.8

28 Stairs 3 0.5

29 Roofing 0.7 0.0 0.7

Eighthly Ash pump house

30 Floor 10 0.7 0.7

31

Cantilever

platform of article

entering parts

20—30 0.5 0.7

Page 14: DL 5022-1993

9

32 Other cantilever

platforms 4 0.7 0.8

33 Roofing 0.7 0.0 0.8

Ninthly Pneumatic ash removal building

34 Operation floor 4 0.7 0.7

35 Floor of ash

bucket layer 4 0.7 0.7

36 Roofing 2 0.4 0.7

Tenthly Trench cover

37 Indoor trench

cover 4 0.5

When there is

installation repair

load, it shall be

adopted according

to actual load.

38 Exterior trench

cover 4⑥ 0.5

When there is

installation repair

load, it shall be

adopted according

to actual load.

① When setting up relay bungalow, its floor live load is adopted according to the taken-value of main control room. When

cable in cable floor is suspended on floor slab of main control room or relay bungalow, it shall be considered according to

actual load.

② Floor (ground) live load of reactor is provided by technology.

③ When dry coal shed roofing adopting light roofing as asbestos shingle, corrugated iron and fibreglass tile, etc., its roofing

live load shall be adopted according to 0.3 kN/m2.

④ When belt width is 1.2-1.4 m, live load of trestle bridge floor is adopted according to 4 kN/m2 generally; when belt width

is larger than 1.4 m, it shall be considered as actual load.

⑤ Coal-breaker house frame is combined according to the following two load effects and designed as the most unfavorable

combination among them:

a. When it is combined according to installation conditions, floor live load and reduction factor of main beam (column) is

adopted according to numerical value in this table, live load itemize factor takes 1.3;

b. When it is combined according to operating maintenance condition, coal-breaker load is equipment standard load

multiply by dynamic factor plus relevant floor live load (4kN/m2), equipment and floor load itemize factor takes 1.3.

⑥ Numerical value in the table is only for trench cover basset. When trench cover is inearth, it shall not only consider

overburden layer load, but also adopt possible load according to traffick on the ground and piling up material as well as

reality, but it shall not be less than 4 kN/m2.

Table 2.2.4-2 Roofing, Floor (Ground) Live Load of Auxiliary Production and Outbuilding

SN Designations

Normal

value

(kN/m2)

Would-be

permanent value

factor

Reduction factor of

main beam

(column)

Notices

1

Production office building

(overhaul compartment in the

building)

4 (4—8) 0.7 0.8

2 Administration building 2 (3—5) 0.5 0.8

Numbers in parentheses

are for archives

Material storage and center

maintenance depot

Ground 10—15 — —

It may adopt floor

according to practical

situation

Floor 8 0.8 0.8

3

Roofing 0.7 0.0 0.8

Page 15: DL 5022-1993

10

Overbridge of main building to

buildings

Floor 3 0.7 0.9 4

Roofing 0.7 0.0 0.9

Note: 1. Live load of life welfare building and its would-be permanent value factor are stipulated according to "Load

Specifications for Building Structure"

2. When designing production office building, it shall arrange the overhaul compartment with heavy piece

overhauling within ±0.000 m terrace live load be adopted according to 8 kN/m2. Floor shall be disposed in the

overhaul compartment with lighter equipment (thermodynamical instrument and electrical service compartment,

etc.); its live load may be adopted according to 4 kN/m2.

2.2.5 Roofing of main building and other production, auxiliary production and outbuilding

may not consider dust load.

2.2.6 Power plant with unit capacity is larger than 300 MW shall decide its taken-value of

roofing and floor (ground) live load according to practical situation.

2.3 Crane load

2.3.1 Crane in steam turbine house, boiler room, grey paddle pump room, maintenance depot,

overhaul compartment and induced draft fan, etc. shall be designed according to light-duty.

Bridge type clamshell crane of bunker coal and ash removal building shall be designed

according to heavy-duty.

2.3.2 Vertical load and horizontal load of main building crane shall be adopted according to

the following stipulations:

2.3.2.1 When there is a set of crane in steam turbine house, crane load shall be adopted

according to “load specifications for building structure".

2.3.2.2 When there are two sets of cranes in the steam turbine house, crane load is adopted

according to the following stipulations:

(1) When calculating crane beam and its support bracket, vertical load and horizontal

load shall both be considered according to load-lifting capacity of the two sets of cranes, but

not consider load reduction factor of crane.

(2) When calculating transverse frame-bent in the main building, vertical load of the

crane is considered according to load-lifting capacity of one set of crane, the other set of

crane only considers sole weight function of itself.

Transverse horizontal load of the crane only considers load-lifting capacity of one set of

crane.

(3) When calculating longitudinal frame in the main building, longitudinal horizontal

load of the crane shall be considered according to two sets of cranes with simultaneous and

equidirectional skid. When calculating wheel pressure of the skid wheel, vertical load of two

relevant sets of crane shall be determined according to the taken-value principle in item (2).

2.3.2.3 When boiler room is setting with erection crane (considering one set), it shall be

considered as setting up one set of crane in the steam turbine house, its load taken-value

is same as article 2.3.2.1.

Page 16: DL 5022-1993

11

2.4 Wind load shape coefficient

2.4.1 When determining wind load shape coefficient in the main building, it may not consider

defilade influence of the outdoor boilers generally.

Wind load shape coefficient in the main building may be adopted according to table

2.4.1.

2.4.2 When determining wind load shape coefficient of suspensory boiler furnace shaft in the

open air, it may not consider defilade influence of the main buildings generally.

Wind load shape coefficient of suspensory boiler furnace shaft in the open air may be

adopted according to table 2.4.2. Table 2.4.1 Wind load shape coefficient in the main building

SN Shape and shape coefficient

1

2

3

Page 17: DL 5022-1993

12

4

5

6

Page 18: DL 5022-1993

13

7

8

Table 2.4.2 Wind load shape coefficient of suspensory boiler furnace shaft in the open air

Page 19: DL 5022-1993

14

3 Main building

3.1 Frame (bent) structure

3.1.1 Structural arrangement shall be simple, order and reasonable, with explicit stress and it

shall take extension conditions into consideration.

Frame-bent span, spacing of columns, height of course, etc. shall consider adopting

uniform building modular system.

When it adopts fabricated structure, turbine and boiler should adopt arrangement of unit

system to reduce constructional element varieties and improve assembly level.

3.1.2 Structural style is determined after the comprehensive technical and economic

comparison for factors such as material handling, natural conditions, execution conditions,

attendance, and implementation scheduling, etc.

Frame-bent of the main building shall adopt reinforced-concrete structure, when

conditions permit, it may use composite structure, where platforms in turbine and boiler

operation layer should adopt combination beam structure. Main bearing structure of main

building with machine groups are 300 MW and more than 300 MW, it may adopt steel

structure if necessary.

Composite structure may be designed by referring to "Tentative Specifications for the

Design of Steel-Concrete Composite Structure of Thermal Power Plant.”

Sectional dimension of constructional elements of reinforced-concrete frame-bent shall

be coordinated and unified, beam column sectional dimension of main building frame-bent

should be adopted according to table 3.1.3. Table 3.1.3 Beam column sectional dimension of main building frame-bent (mm)

Constructional element Width Height

500 800 1000 1200 1400 1600

600 800 1000 1200 1400 1600 1800 2000

700 1000 1200 1400 1600 1800 2000 2200 Column

800 1000 1200 1400 1600 1800 2000 2200 2400

400 800 1000 1200 1400 1600

500 800 1000 1200 1400 1600 1800 2000

600 1000 1200 1400 1600 1800 2000 2200 2400 Main beam

700 1600 1800 2000 2200 2400 2600 2800

250 300 350 400 450 500 600 700 800

300 500 600 700 800 900 1000 1200 Junior beam

400 600 700 800 900 1000 1100 1200 1400 1600

Sectionlization of assembler reinforced-concrete frame structure shall be determined

according to construction machinery and site conditions, and it shall reduce constructional

elements and jointed type and quantity.

3.1.4 The maximal spacing of longitudinal temperature expansion joint for the

reinforced-concrete frame structure with cast in-situ structure should not exceed 75 m,

fabricated structure should not exceed 100 m. Spacing of temperature expansion joint shall

adopt integral multiple of boilers unit spacing. Structure lies in dry climate and summer torrid

and rainstorm frequency region may reduce spacing of temperature expansion joint properly

Page 20: DL 5022-1993

15

according to service experience.

When there are adequate argumentation, and calculating by taking effective measures or

with temperature effect, it may augment spacing of temperature expansion joint properly.

3.1.5 Modus operandi of temperature expansion joint shall adopt dual columns and dual roof

trusses, beam slab and fender structure should adopt overhanging structure. Data grade

foundation beam should adopt freely supported beam.

3.1.6 Connection of assembler longitudinal frame beam/column may adopt rigid connection

or swing connection. When adopting swing connection, it shall be set with intercolumnar

bridging or rigidity straddle.

Intercolumnar bridging or rigidity straddle should be set in the middle of temperature

expansion joint zone and along overall height of the column, and approach to one side of the

shaft line or crane beam of the column. When column section height is 1800 mm and more

than 1800 mm, it shall set a beam of support in both sides of the column.

3.1.7 Corbel top level of the bearing roof truss shall be set with longitudinal coupling-wall

beam along full length.

3.1.8 Prefabricate floor should adopt double T plate or trough plate. When slab span is larger

than 9 m, slab main rib shall adopt prestressed reinforcement.

3.1.9 Main building frame may make internal force analysis according to longitudinal and

transverse plane structure system. Transverse structure shall select some representative frame

to make calculation according to process unit and structural arrangement conditions.

Transverse frame-bent shall be solved united in conjunction with outer side column of the

main building.

3.1.10 Frame-bent of the main building may adopt plane trussing design diagram, that is make

frame beam and column centerline act as design diagram of frame geometric shape, column

root takes fundamental top surface. When upper prop eccentric to the lower prop, it shall

consider bending moment influence caused by eccentricity.

3.1.11 When calculating transverse or longitudinal frame load, longitudinal coupling-wall

beam, or transverse frame beam may degenerate into freely supported beam. When

calculating corbel strength, its load shall consider continuity of the beam.

3.1.12 When adopting simplified calculation, it may refer to the method in appendix A.

3.1.13 Steam turbine house outer side column of the main building frame-bent and calculated

length of frame column of the oxygen removal bunker bay may be adopted according to table

3.1.13. Table 3.1.13 Calculated length of frame-bent column of the main building

Designations Structure types Frame

direction

Perpendicular

frame direction

Upper prop 2.5Hc When

considering

crane load Lower prop 0.9Hc

Lower prop 2.0Hc

Outer side column of

steam turbine house When not

considering

crane load Lower prop 1.1Hc

Top layer 1.25Hs

Other layers

1.0Hc

Frame column of oxygen Coping 1.25Hc

Page 21: DL 5022-1993

16

removal bunker bay Rest layers 1.0Hc

Note: Hc is the distance between longitudinal and transverse beam centerline.

3.1.14 For protruding column of outer coal bunker frame and inner coal bunker frame as well

as outer side column of boiler room: when column bottom is regarded as rigid coupling, their

calculated length may be adopted according to table 3.1.14-1.

Calculated length factor μ of protruding column of outer and inner coal bunker frame as well

as outer side column of boiler room may be determined according to formula (3.1.14-1).

μ=αμ0 (3.1.14-1)

Where: μ——Calculated length factor of the column, when calculated value is less than

0.90, it takes μ=0.90;

μ0——Initial calculated length factor of protruding column or outer side

column of the frame, μ0 value sees table 3.1.14-2;

α——Regulation factor, for protruding column of frame: α=1.05, for outer side

column of boiler room: α=1.00 (in the perpendicular frame direction, α=1.00). Table 3.1.14-1 Calculated length l0 of protruding column and outer side column of outer and inner coal

bunker frame

Designations Structure types Frame direction Perpendicular frame

direction

Protruding column

of outer coal bunker

frame

Protruding

column of the

frame

Protruding column

and outer side

column of inner coal

bunker frame

Protruding

column and

outer side

column of

frame

μHc

μHc

Coping 1.25Hc

Rest layers 1.0Hc

Note: Hc is the distance between longitudinal and transverse beam centerline.

Table 3.1.14-2 Initial calculated length factor of protrude column or outer side column of the frame μ0

η1, 2 0 1 2 3 4 5 6 8

μ0 2 1.74 1.56 1.43 1.32 1.24 1.18 1.07

η1, 2 10 12 14 17 20 23 ∞ —

μ0 0.99 0.94 0.89 0.84 0.80 0.78 0.7 —

μ0 value in table 3.1.14-2 is checked by η1,2, η1,2 is parameter of column calculated length,

it may be calculated according to formula (3.1.14-2):

η1,2=2,1

32,11,2

EI

HC (3.1.14-2)

C1,2= kH

EI3

1,2

1,23 (3.1.14-3)

Where: C2,1——Spring stiffness of protruding column or outer side column of two

adjacent frames;

Page 22: DL 5022-1993

17

I1,2——Moment of inertia of protruding column or outer side column of

frames;

H1,2——Height of protruding column or outer side column of frames;

k——factors, k=0.3. Note: tables in this article and corner connectors 1 and 2 in the formula are correspondent to H1 and H2 in table 3.1.14-1.

3.1.15 When the frame-bent is battened column, it should calculate battened column

according to frame or truss. When making internal force analysis for transverse frame-bent,

battened column in the outer side may also be approximately converted to solid web column,

its moment of inertia may be calculated according to formula (3.1.15) (figure 3.1.15).

Figure 3.1.15 Design Schedule of Reduced Moment of Inertia for Battened Column

2

22Iz

fz

LAI (3.1.15)

Where: Iz——the minimal moment of inertia for the single-limb-column, Iz=12

3zbh

;

Az——Cross-sectional area of the single-limb;

Lf——Middle ordinate of the battened column;

β——Reduction factor, battened column of flat web member β=0.7, battened

column of diagonal web member β=0.9.

3.1.16 Intercolumnar bridging of longitudinal frame should adopt steel structure. Longitudinal

horizontal force may be bear by drawbar and pressure bar or only bear by drawbar. Support

bar shall meet the requirement of pressure bar structure.

3.1.17 When making internal force analysis by adopting plane trussing design schedule,

design value Mb of bearing bending moment of the beam takes bending moment value 1.3 b

away from the column centerline;

Mb may also be calculated approximately according to formula (3.1.17). Design value of

bearing bending moment of the beam shall be no less than 70% of the bending moment at the

column centerline section.

Mb=Mz - Vb3

1 (3.1.17)

Where: Mz——Design value of the beam support bending moment at the column

Page 23: DL 5022-1993

18

centerline section;

V——Shearing force design value of beam support correspond to Mz;

b——Section height of the column

3.1.18 When making internal force analysis for transverse frame of the main building, it may

adopt design schedule at the node rigid zone.

Rigid zone length in column direction d1=0.25h

Rigid zone length in beam direction d2=0.25b

Where: h——Section height of the beam;

b——Section height of the column

Figure 3.1.18 Design Schedule at the Node Rigid Zone

3.1.19 H-mode sectional frame shall be checked with beam transverse strength and crack

resistance at construction stage.

3.1.20 Jointed form shall be determined according to design feature and execution conditions,

it strives to make simple structure, direct conducting force and credible, fixing and simple

installation as well as easy-to-adjust errors.

In order to ensure integrity of the joint, cement for quadric cast concrete may adopt placement

cement or cement with micro -swelling.

3.1.21 Among columns, it generally adopts tenon joint, the rabbet's length shall not be less

than 20 d (d is diameter of effective bar), and jointed strength shall be calculated according to

load on operational phase.

When calculating bearing capacity in operational phase, it shall take the correspondent

internal force at the jointed section and multiply by joint improvement factor 1.3. By this time,

it may add transverse reinforcement rigid, inside the rabbet, it shall be set with additional

longitudinal reinforcement, and measures to increase strength level of quadric cast concrete.

When condition permitting, columns may be connected with rigidity insert joint. This

kind of joint is applicable to small eccentric compression member (e0≤0.35h0). When

Page 24: DL 5022-1993

19

eccentricity e0 is larger than 0.35h0, crack resistance calculation is required for the joint

section; its crack width shall not be larger than 0.6 mm.

In order to reduce eccentricity, joint position shall be set in the section with smaller column

bending moment (near to inflection point).

3.1.22 When connection of frame beam and column adopting clear corbel stiff joint of

reinforced-concrete, corbel design may comply with "design specifications for concrete

structure". Vertical force acting on corbel may be calculated according to the following two

phases and being superimposed.

3.1.22.1 Construction phase: beam sets on corbel simply, vertical force acting on corbel is V1,

and it generally includes sole weight of the beam slab.

3.1.22.2 Operational phase: beam and corbel form an integer and it shall consider quadric

crack pouring functions between beam and column as well as shear span ratio's influence of

beam on the action of external load. By this time vertical force acting on corbel may adopt

converted vertical force V2; when beam head is hogging moment, it shall be calculated

according to the following formula:

V2= 2011

1.11

07.0

hbfV c (3.1.22)

λ= 101

Vh

M v

Where: λ——Sectional shear span ratio of the beam support;

V——the maximum shear design value of the beam head in operational phase;

Mv——Correspondent bending moment design value when taking the maximum

shear design value of the beam head in operational phase;

h01——Effective height of the beam head section;

b1——Cross-sectional width of the beam;

fc——Design value of compressive strength at the concrete axle center

3.1.23 Connection of longitudinal coupling-wall beam and column may use joint forms such

as spline, clear corbel and unclear corbel, etc. according to operating requirements and

construction requirements. Structure diagram of spline joint see figure 3.1.23.

Design value of shear bearing capacity of the vertical cross-section for the spline may be

calculated according to the following formula:

V0

30.00.3h

Mnabfv v

ctc (3.1.23)

By this time, it shall also meet the following requirements:

Vh

Mc

v 6.2

13.0

0

Where: c——Improvement factor of shear resistant bearing capacity for spline, it takes

γc= 1.3;

Mv——Design value of bending moment on the spline section corresponding to

V;

Page 25: DL 5022-1993

20

ft——Design value of tensile strength for the concrete;

bc, hc——Length and height of spline respectively;

n——Tooth number on the same section;

a——Reduction factor of spline strength is adopted according to table 3.1.23;

h0——Effective height of the beam section

Figure 3.1.23, Structure Diagram of the Spline Joint

Table 3.1.23 Reduction Factor a

Tooth number ≤3 4—5 ≥6

α 0.9 0.8 0.7

Connecting piece of the joint and weld shall be determined according to the calculation

of bearing capacity.

3.1.24 In order to ensure certain integrity of the floor structure, it shall connect slabs and

beams.

When adopting trough plate, it may infill with pea gravel concrete in flat seam when

adopting double T plate; it may bury ironworks in advance on slab arris top surface through

short tendon or steel plate welding when there are dynamic load generated by technological

equipment on the floor, slab arris shall connect with built-in fitting on the beam. Generally,

attachment weld length is no less than 60 mm; its height is no less than 6 mm.

3.1.25 Picking ears on the beam of the bearing floor slab should be set along full length of the

beam to bear the concentrated load transferred by the slab arris or junior beam. Under the

action of that load, calculated width of the picking ears may be determined according to the

following formula (figure 3.1.25):

Page 26: DL 5022-1993

21

Figure 3.1.25 Design Schedule of Picking Ears

Picking ears of rectangular section

b0=b+3as (3.1.25-1)

Picking ears of trapezoidal section

b0=b+2.5as (3.1.25-2)

Where: b——Bearing width of slab arris or junior beam;

s——Distance from load point to picking ears root, it generally takes 30c

cs ;

a——Improvement factor of plasticity, it takes a=1.3;

c——Picking length of the picking ears;

c0——Bearing length of slab arris or junior beam

Crack resistance and strength of picking ears may be calculated according to

calculated-width and general corbel, but it shall ensure shear bearing capacity of diagonal

section of the picking ears is larger than bent bearing capacity of the normal section.

3.2 Roofing structure

3.2.1 Roofing structure of the main building may select roof system of syncretic of with

purlin, without purlin and plate beam (roof truss).

3.2.2 Roof truss pattern may select trapezoidal roof truss, through-type roof truss and

single-slope roof truss.

3.2.3 Monitor frame of the main building shall adopt steel structure.

3.2.4 When the span is no larger than 18 m, it may adopt reinforced-concrete roof truss. When

span is larger than or equal to 21 m and less than 36 m, it should adopt prestressed concrete

roof truss or steel roof truss. When span is no less than 36 m, it shall adopt steel roof truss.

3.2.5 When span is no larger than 36m, roof truss may take no account of thermal action.

3.2.6 When calculating roof truss chord, it shall consider additional strain or pressure (for

through-type roof truss) generated by column to roof truss chord, its value should be

determined by calculation. Main building may be arranged with bracket or may be adopted

Page 27: DL 5022-1993

22

according to the following data:

For the roof truss in the steam turbine house, it may take 5%-10% of the maximal

calculated strain or pressure of the roof truss chord.

For the roof truss in boiler room, it may take 8%-15% of the maximal calculate d strain

or pressure of the roof truss chord.

3.2.7 Roof truss of prestressed concrete may not calculate deflection.

3.2.8 Roof slope of through-type steel roof truss should not be less than 1/10; height at lower

chord flex section of both ends of the roof truss should not be less than half of the midspan

height of the roof truss.

3.2.9 In order to alleviate roofing weight, it should adopt prestress large-scale roof sheathing

for the main building without purlin system if the execution conditions and material permit.

For the main building with purlin system, it may adopt small trough plate, etc.

3.2.10 Weld of each roof sheathing and chord on roof truss chord or monitor frame shall

ensure weld of three strips of welding. When roof span is no larger than 6 m, weld length is

no less than 60 mm, throat thickness is no less than 6 mm; when roof span is larger than 6m,

weld length is no less than 80 mm, and throat depth is no less than 6 mm.

3.2.11 Disposal on steel roof truss and lower lateral bracing

3.2.11.1 Roof truss and lower lateral bracing should generally be set inside the first roof truss

compartment at both ends of the main building or both ends of the temperature expansion

joint zone (figure 3.2.11-1).

Figure 3.2.11-1 Support Disposal of Roof Truss without Scuttle

(a) Upper cord bracing disposal of roof truss ;

(b) Lower chord bracing disposal of roof truss

3.2.11.2 When scuttle set in the second roof truss compartment at both ends of the main

building or both ends of temperature expansion joint zone, roof truss, and lower lateral

Page 28: DL 5022-1993

23

bracing should general be set in the second roof truss compartment at both ends of the main

building or both ends of temperature expansion joint zone (figure 3.2.11-2).

Figure 3.2.11-2 Scuttle passing through the second Roof Truss Compartment at both ends of the Main

Building or both ends of the Temperature Expansion Joint Zone and Bracing Disposal of Monitor Frame

(a) Upper cord bracing disposal of roof truss;

(b) Lower chord bracing disposal of roof truss;

(c) Upper cord bracing disposal of monitor frame

3.2.11.3 When length of temperature expansion joint zone is larger than 75 m and less than or

equal to 100 mm, it shall set a beam of upper lateral bracing and lower lateral bracing on roof

truss upper chord and lower chord of the roof truss respectively.

3.2.12 Disposal of longitudinal horizontal-bracing of through-type steel roof truss

3.2.12.1 Through-type steel roof truss shall dispose longitudinal bracing (figure 3.2.12-1) on

the first period of the upper chord of the roof truss. It should dispose flexible tied along full

length at the lower chord kink section and connect with lower lateral bracing (figure

3.2.12-2).

Page 29: DL 5022-1993

24

Figure 3.2.12-1 Longitudinal Bracing Disposal of Through-type Roof Truss

Page 30: DL 5022-1993

25

Figure 3.2.12-2 Disposal of Flexible Tied at Kink Section of the Through-type Roof Truss

3.2.13 Disposal of longitudinal horizontal-bracing for trapezoidal steel roof truss:

3.2.13.1 Trapezoidal steel roof truss should dispose longitudinal horizontal-bracing in the

lower chord.

3.2.13.2 Spacing of trapezoidal roof with purlin system is equal to 12m and its span is larger

than 36 m, it should not only dispose longitudinal horizontal-bracing at the lower chord, but

also set up longitudinal horizontal-bracing at the upper chord.

3.2.13.3 Disposal of longitudinal bracing for roof truss shall form closed bracing system with

the transverse horizontal shoring.

3.2.14 Disposal of vertical bracing for steel roof truss:

3.2.14.1 Trapezoidal roof truss parallel chords roof truss shall not only set up a beam of

vertical bracing at both ends of the roof truss, but also set up roof truss middle according to

the following conditions:

(1) When span of roof truss is no larger than 30m, no matter whether there are scuttle or

not, it shall add a beam of vertical bracing inside the montant plane in the middle of the roof

truss (figure 3.2.11-1 and figure 3.2.14-1).

Page 31: DL 5022-1993

26

Figure 3.2.14 - 1 Bracing Disposal of Roof Truss and Monitor Frame when Scuttle extends to both ends of

the Factory Building or through Temperature Expansion Joint

(a) Upper cord bracing disposal of roof truss; (b) Lower chord bracing disposal of roof truss; (c) Upper cord bracing disposal of

monitor frame

(2) When span of roof truss is larger than 30 m and less than or equal to 36 m as well as

without scuttle, it shall still add a beam of vertical bracing inside the montant plane away 1/3

of the span (figure 3.2.14-2). When span of roof truss is larger than 36 m, it shall add a beam

of vertical bracing for each increased 12 m.

(3) When span of roof truss is larger than 30m and with scuttle, it shall add a beam of

vertical bracing inside the roof truss montant plane at the bottom of the scuttle heel post

(figure 3.2.14-3).

Figure 3.2.14-2 Vertical Bracing Disposal of Roof Truss without Scuttle

Page 32: DL 5022-1993

27

Figure 3.2.14-2 Vertical Bracing Disposal of Roof Truss with Scuttle

3.2.15 Disposal of upper and lower chord on the steel roof truss:

3.2.15.1 Factory building without purlin shall dispose horizontal tie in the roof truss

compartment not setting with vertical bracing which is similar to node of upper chord and

lower chord of the roof truss perpendicular to the supporting plane (figure 3.2.11-1, figure

3.2.11-2 and figure 3.2.14-1).

Figure 3.2.16 Disposal of Rigid Tie Bar at the Node connecting with Lower Pressure Bar of the Column

Rigid Connection

Horizontal tie in the roof system and roof truss upper chord may be replaced by purline,

by this time, it only sets horizontal tie along full length at lower chord node of correspondent

roof truss (figure 3.2.11-1, figure 3.2.11-2 and figure 3.2.14-1).

3.2.15.2 For span of roof truss is larger than 30 m and is set with factory building without

Page 33: DL 5022-1993

28

purlin roof system, it shall add a beam of horizontal tie at the node of upper chord peak.

Figure 3.2.18 Rigid Tie Bar Figure added on the Lower Chord of the Roof Truss when setting with Hanging

Crane

3.2.15.3 Horizontal ties along full length setting at the major bracing node of the roof truss

end and peak node of the roof truss upper chord shall all adopt rigid tie bar (pressure bar),

others shall adopt flexible tied (drawbar). When there is bracket chord or reinforced-concrete

collar tie beam or joining beam at the major bracing node of the roof truss end, it may use this

to replace rigid tie bar.

3.2.16 For steel roof truss rigid connecting with column and without lower chord longitudinal

horizontal-bracing, and when internode bar at end of lower chord bearing pressure, it shall set

rigid tie bar along full length at internodal node of the lower chord end, and it shall connect

with lower lateral bracing (figure 3.2.16).

3.2.17 Bracing disposal of steel monitor frame shall coordinate with lateral bracing, vertical

bracing and horizontal tie of the roof truss upper chord, it shall be set within the same roof

truss compartment (figure 3.2.11-2 and figure 3.2.14-1).

Page 34: DL 5022-1993

29

3.2.18 When hanging crane operating along longitudinal direction of the factory building and

the crane rail not passing through lower lateral bracing of the roof truss at both ends of the

factory building and temperature expansion joint zone, it shall add rigid tie bar at the end of

the rail and it shall connect with lower lateral bracing (figure 3.2.18).

3.2.19 Disposal of top lateral bracing for the steel monitor frame:

3.2.19.1 Purlin system or without-purlin system shall both set top lateral bracing at both ends

of the monitor frame (figure 3.2.11-2 and figure 3.2.14-1).

3.2.19.2 When length of temperature expansion joint zone is larger than 75 m and less than or

equal to 100 mm, it shall also set a beam of top lateral bracing at upper chord of monitor

frame in the middle of this zone.

3.2.20 Disposal of vertical bracing for the steel monitor frame:

3.2.20.1 No matter what dimension the monitor frame span is, they shall set vertical bracing

for each in the monitor frame compartment with top lateral bracing and inside the vertical

plane of the both sides upright columns of the scuttle (figure 3.2.11-2 and figure 3.2.14-1).

3.2.20.2 When monitor frame span is larger than 12 m, it shall add a beam of vertical bracing

inside the montant plane in the middle of the monitor frame.

3.2.21 Disposal of top horizontal tie for steel monitor frame

3.2.21.1 Top horizontal tie of the monitor frame with purlin system may be replaced by

purlin.

3.2.21.2 In the without-purlin system, no matter what dimension the monitor frame span is,

they shall set flexible tied at the upper peak node and the monitor frame compartment with

top lateral bracing (figure 3.2.11-2 and figure 3.2.14-1).

3.2.21.3 When the scuttle is set with upper chord horizontal tie at both sides of the monitor

frame may be replaced by side window waler.

3.2.21.4 When scuttle is not set with sash (open style) and other longitudinal members, it shall

set flexible tied at the upper chord tip node of both sides of the monitor frame.

3.2.22 Stipulation for bracing structure is as follows:

3.2.22.1 On the roof truss, lower lateral bracing and longitudinal horizontal-bracing should

adopt cross diagonal member, bracing crossing angle should be within 30°-60°.

3.2.22.2 Section forms of the bracing member by the steel: drawbar may adopt single-angle or

double-angle steel; pressure bar should adopt form sections constituted by double angle steel.

When roof span is equal to or larger than 9m, it may adopt lattice type bracing constituted by

sections.

3.2.23 Bracing disposal of reinforced-concrete roof truss may refer to disposal of bracing

system of the steel roof truss.

3.3 Fender structure

3.3.1 Walling structure of the main building shall be in accordance with bearing structure

system.

When the bearing structure system is reinforced-concrete frame structure, walling

structure should adopt large wall panel. Wallboard type-selection shall be determined by

principles of using local materials and adjusting measures to local conditions according to

operating requirement. When it is difficult to adopt wallboard, it may also adopt masonry

Page 35: DL 5022-1993

30

structure.

If necessary, fender structure may adopt light material such as clad steel plate and metal

die steel plate, etc.

3.3.2 Large wall panel shall make strength and crack resistance calculation according to

construction and operational phase, and it shall checkout deflection in horizontal direction at

the operational phase.

When wallboard bearing sole weight and horizontal wind load at operational phase, it

may be calculated according to unidirectional bending member respectively.

3.3.3 When adopting light wallboard, walling skeleton beam and column section shall be

determined by calculation, calculated deflection of the wall trestle is no larger than l/400,

horizontal calculated deflection of the wall rack beam is no larger than l/200 (l is theoretical

span of the bending member). For wallboard with higher fixing requirement, calculated

deflection of the wall rack beam shall reduce properly.

3.3.4 Binding ironworks of the large wall panel shall be with adequate safety stock. The

binding types shall be simple and convenient to construction. Dimension of the buried iron

shall augment 2 mm and it shall be no less than 8 mm properly by considering influence of

the construction error and increasing its thickness comparing with calculation requirement.

Diameter of the connecting bolt shall also augment 2 mm and it shall be no less than 16

mm comparing with calculation requirement.

3.3.5 Gable skeleton at the fixed end should adopt reinforced-concrete structure. When

adopting assembler reinforced-concrete structure or larger gable span, wind beam may adopt

steel structure.

Walling structure of the gable shall conform to sidewall of the main building.

3.3.6 Gable at the fixed end should be disposed separately from the mill construction. Wind

beam of the gable shall connect with column of the main building, connection of gable

column and roof truss shall all adopt connecting types that can transfer horizontal load and

with free setting function.

3.3.7 When platform structure is set at the fixed end, disposal of gable column should

constitute frame pattern with platform structure. Upper extreme of the gable column may be

set with wind beam bearing and may also be braced at the lower or upper chord node of roof

truss.

3.3.8 When calculating wind load of the fixed end gable, wind load shape coefficient takes

μs=±1.1.

Calculated deflection of the wind beam should not be larger than l/300. When adopting

self bearing bricking-up act as fender structure, calculated-deflection of its wind beam should

not be larger than l/500 in order to prevent from bricking-up crack.

3.3.9 Stipulation for calculated length of the gable column is as follows:

Inside gable plane l0=1.0H1

Outside gable plane l0=1.25Hc

Where: H1——Distance between beams (wind beam or joining beam) inside gable

plane;

Hc——Spacing between wind beams

3.3.10 Under the action of horizontal load, internal force of the gable structure may be

calculated according to cross beam. When stiffness ratio of the wind beam and gable column

Page 36: DL 5022-1993

31

is

l

H

I

I

Ecolumn

EKK

column

beambeam , where H is the height of gable column, l is the wind beam

span bearing on the factory building column, when l is larger than 10, it may make simplified

calculation according to the following principles:

3.3.10.1 Wind beam may be calculated according to freely supported beam with both ends

bearing to main building column; it neglects elastic bearing action of the gable column.

3.3.10.2 Gable column may be calculated according to coupling-wall beam bearing to wind

beam and it shall consider additional bending moment and shearing force generated by

deflection of wind beam in the bearing point to gable column.

3.3.11 Gable at extension end shall consider the handiness of installation and removal.

Skeleton should adopt hybrid combination steel structure or assembler reinforced-concrete

column and steel wind beam. All the connections should adopt screw bolt.

Walling structure shall be light weight, firmness, duration, and simple and convenient

removal according to thermal retardation requirement.

3.3.12 Gable at the extension end may choose direct suspension wallboard form for triangular

truss. Triangular truss is reducible to plane system, and calculated according to general steel

truss, calculated deflection in vertical direction is no larger than l/500.

Upper and lower chord of the truss should adopt close type section, web member may adopt

single-limb angle steel.

Connection of triangular truss and factory building column as well as connection with

wallboard should adopt screw bolt.

3.3.13 When calculating gable wind load of extension end, wind load shape coefficient takes

μs=±0.8.

3.3.14 Extension end gable should adopt single column and simple footing to reduce collision

of dismantle workload and channel when extension.

3.4 Coal scuttle and crane beam

3.4.1 Coal scuttle shall adopt reinforced-concrete structure or steel structure; coal scuttle

shape shall be simple and adopt form easy to break down and with rational resultant.

Coal scuttle of high-capacity machine unit should adopt steel structure. When working

temperature of powder coal scuttle exceeds 80℃, it shall adopt comminuted steel shot scuttle.

3.4.2 Design conditions coal bunker is provided by technology and it shall meet the following

requirements:

3.4.2.1 Coal bunker should adopt silo structure and connect hyperbola or cone exit section at

its bottom, its inside wall shall be lubricious and antifriction, hyperbola exit section shall not

contract suddenly, cut-angle of the cone exit section and horizontal plane is no less than 60°.

3.4.2.2 Included angle of the adjacent two wall intersections and horizontal plane of coal

bunker for the non-silo structure is no less than 55°, and cut-angle of its wall surface and

horizontal plane shall not be less than 60°. For the lignite and soft coal with high-viscosity or

flammability, included angle of its adjacent wall intersections and horizontal plane is no less

than 65°, and cut-angle of its wall surface and horizontal plane shall not be less than 70°.

Inner side of the adjacent wall cut-angles shall be made into circular-arc; radius of the circular

Page 37: DL 5022-1993

32

arc should not be less than 200 mm.

3.4.3 Design for powdered coal bunker shall meet the following requirements:

3.4.3.1 Powdered coal bunker shall be closed, its internal surface shall level off, lubricious

and antifriction, and it shall not accumulate powder and be without steps of detenting coal

dust.

3.4.3.2 Powdered coal bunker shall prevent from wetting; it shall adopt thermal retardation

measures for coal bunker ectotheca of the comminuted steel shot. In the cold area, near to the

external wall of the factory building or powdered coal bunker exerted shall be taken with

thermal retardation measures.

3.4.3.3 Included angle of the two adjacent wall intersection lines and horizontal plane of the

powdered coal bunker shall not be less than 60°, and the cut-angle of wall surface and

horizontal plane shall not be less than 65°, inner side of the adjacent wall cut-angle shall be

made into circular-arc, circular arc radius should not be less than 200 mm.

3.4.4 Physical characteristic factor of coal and coal dust shall consider the feeding material

quality and operating condition properly. Its data shall be provided by technology, if there are

no data, it may select by referring to the data list in table 3.4.4. Table 3.4.4 Physical Characteristic Factor of Coal and Coal Dust

Name of material Gravimetric density (kN/m3) Angle of internal friction φ (°) Friction factor of material to steel plate

Anthracite 8.0—12.0 25—40 0.30

Lignite 7.0—10.0 23—38 0.30

Soft coal 8.0—11.5 25—40 0.30

Coal dust 8.0—9.0 25—30 0.40

3.4.5 When calculating coal bunker load, it shall be considered as full load, load on

crossbeam shall be distributed according to gravity centre of the coal bunker. Powdered coal

bunker and its top floor structure shall be able to bear possible blasting power generated in

the bunker. Dimension of the blasting power shall be designed as 10 kN/m2 (gage pressure).

Floor slab should adopt cast-in-situ plate or set reinforced cast-in-situ layer on precast slab.

Steel bar in cast-in-situ layer shall credibly connect with protruding steel bar on the bearing

structure. Connection of pipeline (or manhole door) and floor shall be able to resist explosion

pressure.

Shallow coal bunker High wall shallow coal bunker

Figure 3.4.6 Shape of Coal Bunker

3.4.6 Internal force calculation of the reinforced-concrete coal bunker shall consider the

Page 38: DL 5022-1993

33

in-tension inside the wainscot plane and bent outside the wainscot plane, it shall also consider

bent inside the wainscot plane for the suspended type coal bunker.

Calculation for bent inside the headwall plane may adopt method of approximation:

shallow coal bunker may make calculation according to theory of folded plate structure

without bending moment; vertical wall of high-wall shallow coal bunker may be calculated

according to deep beam, the skew wall's action is negligible (figure 3.4.6).

3.4.7 Calculation of assembler reinforced-concrete coal bunker is related to structural shape,

block division and node structure, etc. of coal bunker, there are three types in common use:

3.4.7.1 Vertical wall of coal bunker of the bearing lateral blocking (such as cage drawer type)

may be calculated according to close frame, horizontal joint is connected according to

structure.

3.4.7.2 For coal bunker of bearing vertical blocking, vertical wall may be calculated

according to simply supported plate, perpends among the plates are connected according to

structure.

3.4.7.3 Internal force analysis of suspended type coal bunker is same as cast-system coal

bunker and it shall be designed by referring to the joint of general assembler

reinforced-concrete structure.

3.4.8 Headwall thickness of flatbed coal bunker of the reinforced-concrete takes 1/20- 1/30 of

its minimal side length when skew wall of the coal bunker is triangle; it takes 1/20- 1/30 of

the smaller value of its height or average width when skew wall of the coal bunker is

trapezoid. The minimum thickness of cast-in-situ flatbed headwall is no less than 150 mm,

when adopting fabricated structure, it shall be no less than 120 mm. thickness of the steel bar

inhibitory coating in the inner side of the headwall shall not be less than 20 mm, when it

doesn't add inner lining, thickness of the steel bar inhibitory coating shall be thicken to 40

mm.

3.4.9 The maximal crack width allowable value of the reinforced-concrete coal bunker

headwall is 0.2 mm.

3.4.10 Bunker month beam at the coal bunker exit or small steel bunker of built-in fitting

hanging shall consider the influence of abrasion and corrosion, their calculated load shall

consider weight of top coal column and suspensory material.

3.4.11 Headwall thickness of coal bunker for the steel structure shall be thickening for 2 mm

comparing with calculated value, and it shall be no less than 10 mm.

3.4.12 Steel coal bunker should adopt bearing silo, it may adopt bearing with eight points.

Deflection of crossbeam of the bearing coal bunker shall not exceed 1/600 of the span.

Deflection difference between any two bearing points shall not exceed 5 mm.

3.4.13 Bearing coal bunker shall be broken away from the belt layer structure, and it shall

adopt measures to prevent coal dust dissipation.

3.4.14 Connection of steel coal bunker and concrete bearing structure shall be left with certain

fixing clearance and it shall be able to adapt to certain construction errors.

3.4.15 Steel silo shall not only meet strength requirement, but also checkout integer

stabilization of the cylinder if necessary.

3.4.16 Rectangular steel coal bunker may adopt flat steel and angle steel, etc. to act as a

ribbed stiffener. Its carrying capacity may be determined according to compound section of

ribbed stiffener and wainscot, by this time, effective width of compression flange is: when

Page 39: DL 5022-1993

34

plate is No. 3 steel, it takes 30t, when plate is 16 manganese steel, it takes 25t (t is calculated

thickness of the wainscot).

3.4.17 When adopting wainscot of steel coal bunker, wainscot deflection shall not be larger

than 1/150 of the span of slab, deflection of ribbed stiffener shall not be larger than 1/250 of

its span.

3.4.18 When there are screw bolt or stress fillet weld in the inner side of the steel coal bunker,

it shall add some frame covering on it. Frame cover thickness may take 4-6 mm.

3.4.19 Ectotheca of steel coal bunker and inside wall within 1.5 m away from the coal bunker

tip shall be painted with antifouling paint, other parts shall not be painted.

3.4.20 Structure type-selection of crane beam shall be adopted according to table 3.4.20. Table 3.4.20 Structure Type-selection of Crane Beam

Span of crane

beam (m)

Payload capacity of crane

nameplate (t) Structure type-selection

l<9 Q≤75; Q>75 Solid web beam of reinforced-concrete①; it should adopt solid web beam of

prestressed reinforced-concrete②

9≤l≤12 Q≤75; Q<75 It should adopt solid web beam of prestressed reinforced-concrete②; it shall

adopt solid web beam of prestressed reinforced-concrete③

① Condition permitting, it may adopt solid web beam of prestressed reinforced-concrete;

② When construction and material condition is limited, it may adopt solid web beam of reinforced-concrete;

③ When construction and material condition is limited, it may adopt steel crane beam

3.4.21 Crane beam shall combine with engineering condition to checkout load on crane test

and be during the equipment installation (dynamo stator, etc.) process, by this time, its safety

class may reduce one level comparing to operational phase.

3.4.22 When calculating crane beam, it shall consider orbit center and eccentricity of vertical

center line of the beam section, its numerical value is no less than 20 mm.

3.4.23 Crane beam of constant section reinforced-concrete may make carrying-capacity and

crack resistance calculation of midspan in the operational phase according to unidirectional

bending member.

3.4.24 Lateral braking force of the crane may be supposed to act on sectional gravity centre of

the crane beam top flange, and they are all bearing by flange, taking no account of co-action

of web plate and lower flange.

3.4.25 Crane beam should adopt overhanging structure at the expansion joint.

3.4.26 Main reinforcement inside the beam shall not adopt colligating joint, and it should not

adopt welding joint. It shall not weld any appendix to the steel bar (excluding end anchorage).

When the steel bar length is inadequate, it shall be in compliance with relevant clauses in

"Design Specifications for Concrete Structure.”

3.4.27 In order to prevent horizontal fractures generated at the end of the beam when making

prestress construction, it shall set vertical reinforcement along depth of beam and be matched

with lateral stirrup to form puncheon. Diameter of the stirrup is no less than 6 mm, the

spacing is no larger than 100 mm, configuration scope is h/4 (h is the height of beam end).

Diameter of vertical reinforcement is no less than 12 mm; its lower end is welded with

anchorage plate, its upper end diving into top flange of the beam.

3.4.28 When web plate of the crane beam is too wide, connecting bolt of crane beam and

crane rail should adopt imbed method with leaving holes, vug may be cast with sulphur

mortar after screw bolt finding its position.

3.4.29 Steel crane beam shall adopt simple support connection in perpendicular and horizontal

Page 40: DL 5022-1993

35

directions. Connection with column and platform shall adopt screw bolt.

3.4.30 Steel crane beam should adopt I-shaped cross-section with equal altitude and constant

section. Connection of flange and web plate may adopt continuant corner fillet, weld of the

top flange shall not only bear horizontal shear force between flange and web plate, but also

bear vertical shear force generated by crane wheel pressure.

When throat thickness is larger than 16 mm, it shall adopt double-bevel butt weld. Weld

quality shall not be less than the second grade weld standard.

3.4.31 Bearing ribbed stiffener of steel crane beam at expansion joint overhanging section

may adopt flatbed bearing ribbed stiffener, other parts should adopt lug bearing ribbed

stiffener. Both ends of the flatbed bearing ribbed stiffener shall be plane and be close to the

lower flange. Ribbed stiffener lower end of the lug bearing shall be plane. Steel crane beam

end shall be set with dunnage, the dunnage width should not be larger than 100 mm, and its

thickness is determined according to calculation and is no less than 30 mm.

3.4.32 Connection of top flange of the steel crane beam and column shall prevent large stress

caused by partial built-in of crane beam from structure.

3.5 Framework of suspensory boiler

3.5.1 This section is applicable to reinforced-concrete boiler cradle and composite structure

boiler cradle of suspensory boilers with capacity is 670t/h and below.

3.5.2 When designing boiler framework, it shall determine rational design proposal for boiler

cradle according to boiler manufacturer information provided by technology and under close

cooperation of the boiler manufacturer, and it shall require the manufactory satisfying the

following conditions:

3.5.2.1 Large plate beam layer shall be set with sealing lateral bracing by the manufactory to

form rigid diaphragm.

3.5.2.2 Boiler cradle not bear the boiler blasting power

3.5.2.3 When it requires setting shaking point, it should be set on the operation with bigger

rigidity or elevation of the overhauling platform.

3.5.3 Bearing construction mode of large plate beam and framework column shall be

determined by together studying with boiler works. Components such as bearing dunnage, etc.

shall be supplied by manufacturer. Large plate beam and column coupling should adopt swing

joint.

3.5.4 Framework of suspensory boiler should adopt disposal of independent type.

3.5.5 Boiler framework column may adopt single column of rectangular section, battened

column or frame column according to its strength and stability condition. Transverse direction

of boiler framework should add beam (or truss) in the intercolumniation to form multistory

frame structure. Longitudinal direction of boiler framework shall be set with longeron along

column height to form multistory frame structure. When adopting battened column, each

layer of longeron shall disposal in pairs.

3.5.6 When adopting frame boiler cradle, it shall select beam column section reasonably to

reduce additional stress influence owing to axial deformation of columns.

3.5.7 Boiler framework is integer space structure. In order to simplified calculation, it may

make stress analysis according to longitudinal and transverse plane structural system. Design

Page 41: DL 5022-1993

36

schedules of boiler cradle in common use see appendix B.

3.5.8 For boiler framework with open air arrangement, itemize factor of wind load shall take

1.4 in basic combination of the loads, other itemize factor of variable load shall take 1.3.

Combination factor of wind load and other variable load shall take 0.85. Basic wind velocity

pressure shall multiply by factor 1.1. It shall take no account of wind shakiness and 45° wind

load when calculating.

3.5.9 Wind load on boiler body and boiler cradle should be calculated respectively owing to

their different shapes. Wind loads on boiler body are all act on boiler cradle top through

suspensory bar. For the boiler cradle setting with shakiness-resistance device shall be checked

with its local strength of corresponding load-bearing member of the boiler cradle.

3.5.10 When the large plate beam layer in the roof is rigid diaphragm, horizontal load on

framework top shall be distributed according to rigidity proportion of each framework. When

the allocation proportion of middle framework is insufficient to 10%, it should be calculated

as 10%.

3.5.11 Boiler framework shall be with adequate rigidity. Under the action of wind load,

horizontal displacement value of the framework column top shall not be larger than H/750

(H——height from fundamental top surface to column top).

3.5.12 When calculating boiler cradle: it must consider eccentricity influence of construction

error to boiler cradle, that is, it may add an additional bending moment on column top

(calculating respectively for vertical and horizontal directions). Eccentricity may adopt 1‰ of

the column total height and it shall be no less than 50 mm.

3.5.13 Calculated length of frame column of the boiler framework may be determined

according to appendix C.

3.6 Elevator shaft structure of the boilers

3.6.1 Requiring fundamental dimensions when designing elevator shaft structure, floor

elevation of elevator staying and melt pit depth shall be determined according to technology

profession and information submitted by elevator manufacturer.

3.6.2 Elevator shaft structure should adopt outer attached disposal, it may also adopt

independent type and inner attached disposal forms otherwise.

3.6.3 Elevator shaft structure may adopt reinforced-concrete structure when disposing

according to independent type. And it should adopt steel structure when it is according to

attached form. Outer attached steel structure shall be vertical direction and it shall make

boiler cradle platform act as horizontal pivot at some distance. The pivot shall be made into

immobile pivot on the structure.

3.6.4 Wind load on elevator shaft structure shall act as primary load. For the elevator shaft

structure disposed with independent type shall consider wind shake factor when calculating

wind load.

3.6.5 Controlling value of horizontal displacement for the column top of the elevator shaft

structure should not be larger than H/500 (H is height from fundamental top surface to

column top).

3.6.6 Elevator shaft should adopt light material act as fender structure.

Page 42: DL 5022-1993

37

3.7 Frame-bent steel structure

3.7.1 Structural steel design for main building shall comply with current design specifications

of the nation; it shall also meet the requirement of this standard.

3.7.2 Steel structure of main building shall make internal force calculation according to elastic

designation without reference to adopting system with bracing structure or without.

3.7.3 Disposal of floor beam system of oxygen removal bunker bay in the main building shall

make comprehensive consideration for the integer rigidity and stress reasonableness for the

factory building, it may adopt mode of making longeron act as the main beam main beam

(that is, junior beam adopt disposal of transverse direction), or may adopt mode of making

transbeam act as main beam (that is, junior beam adopt disposal of longitudinal direction).

Beams intercolumnar in longitudinal direction should be set in the same shaft line.

3.7.4 Bracing disposal shall consider stabilization of the structural system, integer rigidity,

horizontal load transference, calculated length of the constructional element, etc.

Bracing forms and its disposal shall conform to professional pipeline and cable trend of

relevant technology.

3.7.5 It shall set end vertical bracing in the first intercolumniation within both ends and

temperature joint zone of the factory building. This bracing should be set within the scope of

corbel plane of crane beam to column top and it shall conform to lower lateral bracing of roof

truss. Parts below the crane beam shall adopt double-limb bracing.

3.7.6 Shaft lines perpendicular to support bar should intersect at the crossing point of shaft

line of the beam column. When it is difficult to be satisfied, they may intersect at the edge of

the beam and column flange. By this time, calculation for bearing capacity of beam and

column shall consider eccentricity moment caused by eccentric connection.

3.7.7 Member disposal for bracing system shall be with explicit conducting force, and short

and nimble path. It shall consider the following factors when calculating:

3.7.7.1 When calculating internal force of perpendicular support bar, it may take no account

of additional stress caused by axial deformation of the members.

3.7.7.2 If the bracing is eccentricity connection, its eccentricity end shall be calculated

according to eccentric link without reference to type of the bracing.

3.7.7.3 When the vertical bracing in endostyle compartment of expansion joint interval of the

same columniation is bigger than the first crosspiece, the horizontal force bear may be

determined according to swing rigidity distribution of each crosspiece of the vertical bracing.

When each layer of vertical bracing is not in the same intercolumniation and difference of the

column sectional area is no larger than 30%, it may make internal force analysis as vertical

bracing in the same intercolumniation.

3.7.7.4 Each layer of vertical bracing is not in the same intercolumniation, if it requires

calculating horizontal displacement, it may be determined by delamination calculation and

then superimposes the result.

3.7.7.5 When setting with double-limbs bracing, connecting tie bar used for reducing

calculated length of compression member of the bracing shall be with axial force is 2% of the

bracing axial force.

3.7.7.6 The minimal connection of bracing with column and beam should be 50% of the

calculated resisting power of the pressure bar.

Page 43: DL 5022-1993

38

3.7.8 Bearing capacity of channeled steel plate for reinforced-concrete floor shall not only be

calculated according to "Engineering and Construction Regulation for Metallic Contour

Plate,” but also meets the following requirements:

3.7.8.1 Construction live load of the contour plate takes 2 kN/m2.

3.7.8.2 Connection of contour plate and steel beam should adopt plug welding. Diameter and

spacing of plug welding shall be determined according to calculation and structure.

3.7.8.3 When steel beam is set with shear resistant pieces, contour plate and steel beam flange

compartment may be set with structural weld, contour plates may be not welded.

3.7.8.4 Deflection of contour plate in construction phase shall not be larger than 1/180 of the

span.

Page 44: DL 5022-1993

39

4 Groundwork and foundation

4.1 Fundamental rules

4.1.1 According to the engineering geology investigation, the groundwork foundation design

shall adopt the safe, economic and rational subgrade foundation type by combining the

operating requirements of all kinds of structures in thermal power plant; fully learn the local

architecture experience, and comprehensively considering such factors as the structure type,

material conditions and execution conditions.

4.1.2 According to the seriousness of the destroying consequence on structures caused by the

destruction of foundation, the structures in thermal power plant are classified into three safe

classes (Table 4.1.2). Table 4.1.2 Safe Class of the Foundation of Structure

Safe

class

Destruction

consequence Structure name

Class

I Very severe

Main workshop (including foundation of steam turbine generator and the foundation of the boiler

framework), main control building or network control building, communication building, indoor

220kV power distribution unit building, chimney higher than 100m, dry coal shed with span larger

than 30m, and other plant buildings

Class

II Severe

Other manufacturing buildings, auxiliary and appurtenant structures except those of class I and III

Class

III Not severe

Machine and furnace overhaul room, material storage, engine shed, motor depot, material

warehouse, coal transporter warehouse, guardhouse and gate chamber, enclosing wall of plant site,

bicycle shed, and temporary construction

4.1.3 The groundwork foundation shall be designed according to the engineering geology

investigation information of the corresponding design stage. As for complicated geologic

conditions (such as groundwork in mountainous area and special foundation soil), the

necessary site geological examination shall be carried out at construction stage.

4.1.4 The groundwork design of main workshop should adopt the groundwork of the same

type. Different structural units may also adopt different groundwork type and different pile

supporting course according to the engineering geologic conditions by considering the

settlement characteristics of each unit of the main workshop.

4.1.5 The main workshop foundation should adopt same buried depth or be buried in

sublevels, or may also adopt the partial deeply burying mode (such as the foundation arranged

with water circulation pipe, breach, and sump hole).

4.1.6 The structures of class I and the structure of class II that requires the settlement

observation shall have the settlement observation at the construction period and operating

process, and the field data shall be taken as one of the reference for the quality inspection on

the foundation work of groundwork. The observation procedure and requirement may be

referred to the relevant provisions specified in "Code for Design of Building Foundation"

Annex A and "The Code of Erection and Acceptance for Electric Power

Page 45: DL 5022-1993

40

Construction-Construction Engineering Section".

4.2 Foundation calculation

4.2.1 According to the safe class of structure foundation, the foundation calculation shall be

carried out according to the following requirements:

4.2.1.1 The foundations of all the structures shall have the calculation on ground bearing

capacity.

4.2.1.2 The structures of class I and II not only shall be calculated according to ground

bearing capacity, but also shall have the calculation on foundation deformation, but when one

of the following conditions is met, the deformation computation may be omitted.

(1) When the main workshop foundation is uniform and the standard value of ground

bearing capacity comply with Table 4.2.1. Table 4.2.1 Ground Bearing Capacity when Main Workshop not Having Foundation Deformation

Calculation

Unit capacity

(MW)

Standard value for ground bearing capacity of the main

stressing layer of natural foundation

fk(kPa)

12~25 ≥180

50~100 ≥220

200~300 ≥270

600 >300

Notes: 1. The main stressing layer of foundation refers to the scope of 3b (b is the width at foundation base) in depth and

thickness not less than 5m under the foundation base;

2. The collapsible loess foundation is excluded.

(2) As for the structure of class II, when the geologic condition and structure type comply

with the scope specified in Table 2.0.2 of "Code for Design of Building Foundation".

(3) When the regional mature experience or similar engineering experience may be

available for referring.

4.2.1.3 The structure constructed on slope shall also be recalculated for the foundation

stability. The building structure (such as retaining wall) being frequently under function of

horizontal load shall be recalculated for its foundation stability if necessary.

4.2.2 When calculating the foundation deformation, the load transferred to the foundation

base shall be assembled according to long-term effect, the wind loads and direct-transmitted

shock effect shall not be considered.

The crane load of main workshop shall be considered with the load generated by the

deadweight of crane when calculating the foundation deformation.

4.2.3 The final settling volume of natural foundation and pile foundation should be calculated

according to the "Code for Design of Building Foundation" or the relevant provisions

specified in regional codes.

When calculating the final settling volume of the pile foundation of weak ground, the

pile foundation grind slab, pile group and soil among piles may be taken as solid deep

foundation, and the pressure expansion angle along the pile body shall not be considered. The

thickness of compact layer shall be accounted from the gross section of pile tip to the 20%

Page 46: DL 5022-1993

41

section where the supplementary pressure is equal to the deadweight pressure of soil. The

calculation of supplementary pressure shall take the influence of neighboring fundaments into

consideration; the compression modulus Es of foundation soil under the action of actual stress

shall be adopted.

When calculating the foundation deformation, it may take the foundation rigidity into

consideration.

4.2.4 The permissible deformation value of the main workshop foundation shall comply with

those specified in Table 4.2.4, and the permissible deformation value of the other structures of

class I and II may refer to the "Code for Design of Building Foundation" or the relevant

provisions specified in regional codes. Table 4.2.4 Permissible Deformation Value of Main Workshop Foundation

Permissible differential settlement or

inclination Tolerable settlement, mm.

Main workshop structure Longitudinal

direction

Transverse

direction

Natural

foundation

Pile

foundation

Outside column of turbine room 0.003l — 150~200 100~150

Outside column and framework of turbine

room — 0.003l — —

Main workshop framework 0.003l 0.002l 200 150

Steam turbine generator foundation 0.0015l 150~200 100~150

Boiler foundation 0.002l 150~200 150

Foundation and framework of steam turbine

generator 0.005l —

Foundation and framework of boiler 0.005l — —

Notes: 1. l in the table refers to the centre distance of neighboring pillar supports or the side length of turbine foundation;

2. The pile foundation in the table refers to the foundations of precast concrete pile, pre-stressed centrifuge tubular

pile, bored concrete pile or steel-pipe pile;

3. The supporting course at pile tip shall be the intermediate and low compressible soil layer.

4.3 Weak foundation

4.3.1 The design of weak foundation not only shall comply with those specified in 4.2.1, but

also shall adopt measures to reduce the foundation deformation and the adaptable foundation

deformation of structures.

4.3.2 When the bearing capacity, deformation or stableness of weak foundation does not

comply with the design requirement, the foundation treatment should adopt the mature

method in power plant design such as the shallow layer reinforcement or the pile foundation.

The treatment method and the indices such as ground bearing capacity and compression

modulus after treatment shall pass the test and be determined by combining with the practical

experiences.

4.3.3 The following measures may be adopted in order to make the structure be adaptable to

the deformation and differential settlement of weak foundation:

4.3.3.1 The settlement joints may be set at the following positions:

(1) The joint of main workshop and neighboring structure;

Page 47: DL 5022-1993

42

(2) The joints among the outside column of main workshop, framework, turbine

foundation, heater platform, turbine overhauling platform, boiler cradle, boiler platform, and

gable wall.

(3) The joint of main control building and power distribution unit building;

(4) The joint of chimney and flue (generally, the settlement joint is located at the outer

margin of foundation mat);

(5) The joint if coalbreaker chamber, transfer site as well as the coal storage tank and

coal delivery trestle.

When the settlement joint is disconnected from the top to foundation with adequate

width

When setting the settlement joint is limited, the swing joint or freely supporting mode

may be adopted, but the supporting length shall be appropriately enlarged.

4.3.3.2 The monolayer structure may adopt such statically determinate structures as

trestlework and three-hinged arch rigid frame.

4.3.3.3 The settling volume of structures shall be predicted, and the corrective measures shall

be left such as increasing the clearance between the crane and structure.

4.3.3.4 As for the structure with large predicted settling volume, the design elevation of

terrace and related positions in the structure shall be appropriately heightened.

4.3.3.5 Measures shall be adopted technologically, such as increasing the clearance between

the pipeline and structure by considering the flexonics of pipelines.

4.3.4 The coal yard structure shall take the foundation differential settlement caused by the

large-area surcharge load as well as the influence on superstructure; the following measures

may be adopted:

4.3.4.1 The dry coal shed should adopt the structural style that is adaptable to foundation

subsidence.

4.3.4.2 When the dry coal shed and coal bridge adopt natural foundation, the reinforced

concrete socle should be appropriately strengthened to bear the appended bending moment

resulted from the possible rotation of foundation.

4.3.4.3 The gantry crane and stacker-reclaimer foundation on the natural foundation may be

designed into the sectional strip-shaped stiffening bar, and the corrective measures of pathway

in transverse direction and vertical direction shall be considered. The combined bottom plate

should be adopted when there is coal bulkhead.

4.4 Foundation in mountain area

4.4.1 The design of foundation in mountain area (including the highland) shall determine

rational foundation treatment project according to the torography, geologic condition, general

arrangement, plant superstructure and construction method by considering such factors as

karst (earth cave) side slope, landslide, debris flow, shattered fault zone, collapse (including

crag and creeping rubbles) as well as the excavation, filling, surcharge loading and unloading

in the process of construction.

4.4.2 In the construction in mountain area, proper measures shall be adopted to prevent the

leakage of surface water and industrial water from resulting in adverse effect on building

foundation and such adverse geologic evidence as the landsliding and erosion at construction

Page 48: DL 5022-1993

43

site.

4.4.3 The key structures such as main workshop, major equipment foundation and chimney

shall be set on better foundations and shall be designed according to the following provisions:

4.4.3.1 The mode of building foundation shall be reasonably selected by combining the

underlying bedrock conditions. One foundation shall not be set on the soft and hard

foundations at same time, the foundation with the surface slope of the underlying bedrock of

groundwork in the same structural unit larger than 10% shall be recalculation on foundation

deformation according to Item 4.2.1 of this code. And it shall be treated combining with the

physical circumstances of project when the deformation value exceeds those specified in

Table 4.2.4.

4.4.3.2 As for the karst foundation, the karst area and the unstable area shall be avoided.

4.4.3.3 They shall not be placed at areas where may slide or suffer from the risk of landslide,

collapse, and debris flow.

4.4.3.4 The compacted filled-in foundation should not be adopted.

4.4.4 In the construction in mountain area, the non-solidified foundation at such areas as

covered gutter, covered pond and gulch shall not be used as natural foundation.

4.4.5 With the precondition that the hillside is wholly stable, the slope design shall comply

with the following requirements:

4.4.5.1 The allowable value for the slope of side slope shall be determined according to the

local experience and referring to the stabilized slope value of similar soil (rock) body. The

side slope value shall be proposed by the geological exploration department. The

determination of design side slope value shall also consider such factors as the influence of

the position of side slope on the structure safety.

4.4.5.2 When the geologic condition is good and the soil (rock) is uniform, the allowable

value for the high wall slope of common sites and roads shall comply with the relevant

provisions specified in the "Code for Design of Building Foundation". The side slope of

neighboring key structures may be adopted by referring to the lower limit value of the

allowable side slope value in corresponding provisions.

4.4.5.3 The slope allowable value of the rock high slope may be determined by referring to

Table 4.4.5. Table 4.4.5 Allowable Slope Value of Rock Side Slope

Allowable side slope value Depth-width ratio Rock types Weathering degree

Slope height at 15~30m Slope height at 30~40m

Slightly weathered 1:0.30~1:0.50 1:0.45~1:0.75

Moderately weathered 1:0.50~1:0.75 1:0.75~1:1.00 Hard rock

Highly-weathered 1:0.75~1:1.00 1:1.00~1:1.50

Slightly weathered 1:0.75~1:1.00 -

Moderately weathered 1:1.00~1:1.50 - Soft rock

Highly-weathered - -

Notes: 1. The side slope with height of or bellow 15m shall refer to the national standard "Code for Design of Building

Foundation";

2. When using this table, the conditions such as territorial hydrology and meteorology shall be considered, and the

table shall be adjusted combining with the physical circumstances;

3. When this table is used for the side slope of the buildings that are near to the main body, the side slope value shall

Page 49: DL 5022-1993

44

be determined carefully and shall not be larger the lower limit value of the allowable side slope listed in the table;

4. This table is inapplicable to the side slope where the groundwater evolves or has weak structural plane and the

main joint plane has slipping along the slope aspect.

4.4.5.4 When the side slope height exceeds 8m, it should be designed into setback type for

improving its stability, one platform of 1~2m in width shall be set in the middle, and

corresponding waterproofing and drainage measures shall also be adopted.

4.4.5.5 The ramp of side slope shall be adopted with corresponding protective covering

measures according to the local hydrology and meteorology conditions, side slope soil (rock)

conditions to protect the ramp from being scoured or weathered.

4.5 Collapsible loess foundation

4.5.1 As for the structure constructed on the collapsible loess foundation, the foundation

treatment shall be carried out according to the relevant provisions specified in the "Code for

Building Construction in Collapsible Loess Regions", and corresponding design measures

shall also be adopted.

4.5.2 The structures in power plant are classified into four types according to the possibility

degree the foundation is wet by water and the consequence of settlement by soaking as well

as the strictness degree of the restriction of operation on differential settlement, see Table

4.5.2.

4.5.3 As for the structures of class A that are constructed on the self weight collapse loess site,

measures for eliminating the whole collapsibility of the under he groundwork shall be adopted.

When the collapsible soil layer under the foundation base too thick (generally is not less than

10m) to eliminate the whole collapsibility, it may be treated by adopting comprehensive

measures such as adopting rigid waterproofing measures and the structural measure that is

adaptable to foundation deformation simultaneously when eliminating the collapse settlement

of foundation. Table 4.5.2 Classification Chart of Structures

Types Structure name

A Main workshop and chimney

B Other manufacturing buildings, auxiliary and appurtenant structures except those of class A, C and D

C

Fuel pump room, fuel store, air compressor room, hydrogen production station, circulating water treatment room,

chloridization station, maintenance depot, machine and furnace overhaul room, material storage, engine shed, coal

transporter warehouse, motor depot, and fire station

D Material storage shed, guardhouse and gate chamber, enclosing wall of plant site, bicycle shed, and temporary

construction

Notes: 1. The water basins and water tanks in or near to the structures shall be classified according to the types of the

neighboring structure;

2. It may be of class A when the height of building construction is larger than 40m.

4.5.4 As for structures of class B that are on the self weight collapse loess site with large

feasibility of being wet by water (such as the chemical water treatment room), not only the

treatment measures for eliminating part of the collapse settlement of foundation shall be

adopted, but also the strict waterproofing measures shall be adopted.

4.5.5 The ground foundation design of the structure in the plant site, the adverse effect of the

Page 50: DL 5022-1993

45

partial settlement by soaking caused by the water leakage of hydraulic structure or pipeline

after the power plant is put into production shall be taken into consideration.

4.5.6 As for the treatment on deep collapsible loess foundation, such schemes as high-level

heavy-tamping, compaction method or hole-digging extending bottom pile shall be adopted in

accordance with local conditions. When adopting the pile foundation scheme, the influence of

negative skin friction force resulted from the settlement of soil layer by soaking shall be

counted in.

4.5.7 When treating the foundation with heavy-tamping method, the treatment scope shall be

larger than the scope of building foundation, the width that may be enlarged by 1/3~1/2 of the

planning reinforcement depth from the outer margin of groundwork, and shall not be less than

one row of ramming points. As for the conditions in Item 4.5.3, when the settlement thickness

by soaking is not wholly eliminated, the heavy-tamping width shall also be appropriately

enlarged.

When the expansion project adopts heavy-tamping method, proper measures shall be

adopted to prevent the adverse effect on the normal operation of existed structures and power

plant.

4.6 Foundation

4.6.1 The type of the column fundament in plant shall be dependent on the ground bearing

capacity or the bearing capacity of individual pile. The individual foundation may be adopted

when the geologic condition is good or the bearing capacity of individual pile is large. When

the ground bearing capacity or the bearing capacity of individual pile is small, the

strip-shaped, raft-shaped and coffer foundations may be separately adopted in sequence with

condition that meeting the foundation deformation.

4.6.2 The calculation method of strip foundation include elastic foundation method, inverse

floor slab method and shearing force balance method, which may be designed according to

former experience and be adopted with corresponding structure measures.

The ordinary constructions of the strip foundation of plant:

4.6.2.1 The height of the main girder in the strip foundation of plant should be 1/4~1/5 of the

spacing of columns. The height of the main girder in the strip foundation of other structures

should be 1/4.5~1/6 of the spacing of columns.

4.6.2.2 As for the longitudinal effective bar of strip foundation beam, the critical steel ratio at

its top and bottom shall all be 0.15%, and the more than 1/3 steel reinforcements among the

longitudinal main reinforcements are placed with uniform length.

4.6.3 The cross strip foundation is calculated according to the strip foundation at two

directions, and the column load is distributed with method that the deflections at the

directions are equal.

When the arrangement of cross strip foundation gives priority to one direction, the

calculation may also be simplified by the strip foundation at this direction, and the other

direction shall meet the requirement on the constructional critical steel ratio.

4.6.4 The calculation for the internal force of raft-plate foundation (including two types: with

or without beam) may adopt floor inverse method and shearing force balance method. When

the rigidity of raft plate is small, the elastic foundation method should be adopted.

Page 51: DL 5022-1993

46

The reinforcement of raft plate not only shall comply with the calculation requirement,

but also shall meet that the steel reinforcements with 0.15% reinforcement ratio at pedestal

along the longitudinal and horizontal directions are connected and all the steel reinforcements

at midspan are linked up.

The thickness of raft plate shall be determined according to the requirement on

anti-die-cutting and anti- shearing.

4.6.5 When the column grid of the superstructure is thick and the rigidity is large, the coffer

foundation may be calculated according to local bending (but the integral flection when the

superstructure does not form large rigidity in construction shall also be considered). The

integral bending shall be calculated when the forementioned conditions can not be met.

4.6.6 When adopting pile foundation, good supporting course such as clay soil, sand soil, soil

aggregate or rock with low compressibility shall be selected.

The selection for the pile type shall be determined according to the engineering geology,

execution conditions and site environment through comparative study.

When adopting driven pile, the design elevation of pile and stamping penetration shall be

analyzed by combining with the physical circumstances of project; the friction pile gives

priority to the control of design elevation. The penetration when driving the trial pile shall be

checked, and the point bearing pile gives priority to the control of penetration.

4.6.7 In new construction, the bearing capacity of individual pile at different geologic

conditions shall be determined according to the onsite static load test. The test pile scheme

must be selected combining with the geologic conditions and operating requirements. And the

test shall be carried out before the pile-making and pile-sinking (should be carried out before

the primary setting if the condition permits).

As for the expansion project, if the geologic conditions are different or the pile types and

pile length are different, the pile may also be tested.

The quantity of test piles shall be 1‰~5‰ of the total amount of the project piles, and

shall not be less than three. When various types of piles are adopted in the project, the test

quantity of each type of pile shall also not be less than two.

As for the point bearing pile and the long pile that is controlled according to the

structural strength of pile material, the standard value of the vertical bearing capacity of

clustered piles may be the sum of the standard value of the individual pile bearing capacity; as

for the friction pile, it may be determined according to the deformation controlling principle

(namely, taking the standard value of bearing capacity when satisfy the tolerable settlement

condition, which is equal to or less than the sum of the standard value of individual pile

bearing capacity).

4.6.8 Generally, the pile positions shall be arranged symmetric to the central line of column or

should be in square supporter quincunx. If arranged dissymmetricaly, the centroid of clustered

piles should be coincided with the gravity center of the resultant force of loads that act on pile

foundation for long period. The pile driving sequence shall also be considered when arranged

the piles.

One fundament should have at least three piles. If one foundation is only with two piles,

one joining beam perpendicular to the connecting line of two piles shall be set the grind slab

of pile top to contact with the neighboring grind slab, if one foundation is only with one pile,

then two-way joining beam shall be set to contact with the neighboring grind slab.

Page 52: DL 5022-1993

47

The length of the pile top embedding into the grind slab shall be determined according to

such factors as stressing condition of pile, design assumption and execution conditions, which

generally shall not be less than 50~100mm. The single-pile foundation, double-pile

foundation, single-row pile foundation, piles bearing up- pulling force or mainly bearing

horizontal force, raft plate and boxshaped grind slab as well as piles at periphery and critical

parts under the foundation of large-scale power equipment all shall be built-in the grind slab

and the main reinforcement in pile body shall be anchored into the grind slab as tensile

reinforcement. If required by structure, the protective layer at the four corners at pile top shall

be chipped away, and four steel reinforcements shall be welded and anchored into the grind

slab.

4.6.9 In the construction of pile foundation, the quality monitoring mode of pile shall be

determined based on the conditions of soil layer, pile making and sinking. The quantity of pile

in spot test is 5%~10% of the total amount of the project piles. The precast reinforced

concrete pile and pre-stressed tubular piles should adopt the lower limit, and the filling pile

should adopt the upper limit.

4.6.10 The earthwork excavated from the foundation pit of weak foundation shall be piled up

far away from construction area; the foundation pit should be kept dry and be poured for

foundation and backfilled as soon as possible. As for pit excavation in pile foundation project,

the setting time of the soil around pile shall be kept according to the requirement of design

documents. When the soil quality is poor, the groundwater level is high, the depth of

foundation is large and the stair excavation scheme and large-scale excavators are adopted,

the groundwater level shall be effectively dropped in the under-consolidated soil layer,

drainage consolidation of surface soil in foundation pit shall be facilitated to make the

foundation pit be dry, or other reliable construction measures may be adopted, and the

deflection condition of pile shall also be monitored in the construction period.

In all the projects of driven pile foundation, part of the piles shall be driven in at

extension section in advance (generally the pile shall be driven in for one spacing of

columns).

4.6.11 In weak foundation, the isolated foundation that may have displacement for bearing the

horizontal load generated in construction shall be set with joining beam in addition.

The bottom surface of joining beam shall be at the same elevation with the bottom of

grind slab, and the width of joining beam should not be less than 200mm. Its height may be

determined according to the calculation or may be1/10~1/15 of the centre-to-centre distance

of grind slab. Its steel reinforcement shall be anchored into the grind slab according to the

tensile requirement.

4.6.12 When the groundwater is erosive to the foundation concrete, erosion controlling

measures shall be adopted such as increasing the compactness of concrete, selecting

erosion-resistant cement or being painted with protective coating.

4.7 Underdrain

4.7.1 The underdrain design shall abide by the "protection with drainage" principle. The outlet

of all kinds of sewage shall be reasonably arranged to make them flow into the drainage

system of power plant without obstruction, the physical measures are as follows:

Page 53: DL 5022-1993

48

4.7.1.1 The drained water from the manufacturing and the overhauling of equipments and

pipelines are strictly prohibited to being directly drained into the cable trench or industrial

conduit.

4.7.1.2 The conduit of industrial water, cable trench, sluiceway and drain ditch must be

separated and intercrossed. The intercrossing principle shall abide by: The dry one gives way

to the wet one (as the cable trench gives way to sluiceway), the soft one gives way to the hard

one (as the cable trench gives to industrial water conduit), and the one by pressure gives way

to the gravity current one (as the industrial water conduit gives way to sluiceway). The

drainage system at intersections shall be mutually isolated, and the interstice shall be with

measures for preventing water seepage.

4.7.1.3 The free drainage shall be firstly considered. When trench, chasm and tunnel must

adopt the mechanical drainage, they shall be appropriately centralized in arrangement.

4.7.1.4 The outlet direction of the trench drainage from main workshop should adopt the

mode towards the outer side of turbine room or boiler house. The utility-type unit shall be in

unit of single machine and single furnace, the medium-and small-scale unit may be in unit of

two machines and two furnaces, the drainage should not be drawn out towards the extension

end.

4.7.1.5 The trench shall be set with longitudinal and transverse slopes. Longitudinal slope:

That of cable trench is not less than 5‰, and that of industrial water conduit is not less than

8‰, which may be separately reduced to 3‰ and 5‰ if the difficulty exists on arrangement.

The transverse slope is 1%~3%.

4.7.1.6 In the water treatment system, the trench for draining the acidic production sewage

shall be with acid protection measures. In limestone terrene, it shall pay special attention to

prevent the acidulous water from corroding the foundation.

4.7.2 As for the trench wall of the trenches indoors and outdoors, when adopting the openable

cover board, the stress condition in the operational phase and overhauling phase shall be

considered.

4.7.3 The earth pressure of trench wall may be calculated according to Coulomb Equation.

When the filling soil is clay soil and is tamped in layers, the equivalent internal friction angle

calculation may be adopted. Equivalent internal friction angle value: It may be 25°~30°at the

part above groundwater level when the trench wall is not higher than 4m. It may be 20°~25°at

the part under the groundwater level. The gravimetric density f soil may be the wet

gravimetric density.

4.7.4 The hydraulic bounded layer design of such underdrains as trench, pit and tunnel may

adopt different measures according to the three types of different levels of groundwater level.

The first kind is the maximum groundwater elevation is less than the bottom surface

elevation of trench;

The second kind is the maximum groundwater elevation is less than the bottom surface

elevation of trench, but the trench high requirement on moisture protection (such as the bare

bus bar tunnel);

The third type is that the maximum groundwater elevation is higher than the bottom

surface elevation of trench.

The structure types of the underdrains such as trench, pit and tunnel: The first kind may

adopt the brickwork setting or concrete structure, and the second and third kinds may adopt

Page 54: DL 5022-1993

49

the concrete or reinforced concrete structure.

The hydraulic bounded layer of underdrains such as trench, pit and tunnel: The first kind

may be treated according to common moisture protection, such as finishing by adopting

waterproof mortar; The second kind shall be coated with two layers asphalt or other

underwater paints at the bottom plate and outside of trench wall, and be coated with

waterproof mortar at inner wall; and the third kind generally may adopt the waterproof

concrete.

4.7.5 When adopting the waterproof concrete, the impervious grade of concrete is not less

than 6.S , the thickness of trench wall shall not be less than 250mm when being with

double-row reinforcing bars and not less than 200mm when being with single-row reinforcing

bars.

4.7.6 The indoor trench cover should adopt the steel-wire-net cement plate. The trench cover

at positions where are passed with automobiles in the overhaul site or indoors shall adopt the

reinforced concrete cover board. The outdoor trench should adopt reinforced concrete cover

board. All the reinforced concrete cover boards shall adopt the design with reinforcement at

both surfaces, and should be bounded with edges by adopting steel plate. The trench of

supporting cover board should be wrapped with angle steel at top. The trench cover board that

directly bears the wheel pressure of automobiles shall also have the recalculation on shearing

force.

4.7.7 The intervals among the expansion joints of concrete and reinforced concrete

underdrains and tunnels should be 30m indoors and 20m outdoors.

5 Dynamic machine foundations

5.1 Foundations of automobile unit and electric machines

5.1.1 This section is applicable to the frame foundation of steam turbine generator (electric

motor and rotary condenser) with working speed (n) above 1000r/min and not larger than

3000r/min. The foundation design of the bulk or wall-type electric machines or those with n

not larger than 1000r/min shall be implemented according to the relevant provisions specified

in "Code for Design of Dynamic Machine Foundation".

5.1.2 When designing the foundations of steam turbine set and electric machine, it shall be

closely cooperated with the manufacturer. The foundation design of new style machine set

shall be gone on hand in hand with the machine design with a view to considering integrally

for determining the rational foundation design scheme.

5.1.3 When identifying the dynamic behavior of steam turbine generator foundation, the

vibration condition of the foundation shall not be simply taken as the identification standard

and the internal relations between the vibrations of machine and foundation shall be analyzes

simultaneously.

5.1.4 The frame foundation shall be arranged independently, and the movement joint divided

from other structures shall be left around the top of the frame foundation. If necessary,

Page 55: DL 5022-1993

50

columns may set on the bottom plate of steam turbine set foundation for supporting the

platform of heater and the floor slab of basement.

5.1.5 The major structure of foundation should be arranged decoupling with the intermediate

platform. When it is difficult to arrange it by decoupling, proper measures shall be adopted to

reduce the amplitude of platform.

5.1.6 The strength grade of foundation concrete: That at bottom plate should not be less than

C15, and that at pillar and roof adopt C20~C30; the secondary grouting layer shall adopt the

pea gravel concrete that is one grade higher than that of roof in strength grade. Generally, the

steel reinforcement for foundation adopts the steel of grade I and II.

5.1.7 When the foundation is constructed on high or intermediate compressible foundations,

the permanent settlement observation points shall be separately set on the operating layer and

the ground benchmark post.

5.1.8 The dynamic load shall not be considered either in the calculation of the bearing

capacity of bottom plate or the checking of ground bearing capacity.

5.1.9 The recalculation on the bearing capacity of the foundation soil under foundation shall

comply with the requirement of the following equation:

fp 8.0 (5.1.9)

Where p——Design value of the static pressure at foundation base;

f——Design value of the ground bearing capacity calculated according to "Code for

Design of Building Foundation".

5.1.10 When designing the foundation, the integral gravity center calculated by the sum of

whole dead weight that is transferred onto the foundation and the weight of the foundation

itself shall be at the same vertical line with the centroid of foundation base as much as

possible. When the eccentricity is inevitable, the ratio between the offset value and the side

length of the foundation base that is parallel to the eccentric direction shall not be larger than

3%.

5.1.11 The frame foundation should be analyzed with various schemes according to the

multivariant space mechanical model to reasonably determine the structure type of foundation

(roof, column and bottom plate).

Generally, the structure type may be determined according to the following principle.

5.1.11.1 The roof shall be with adequate mass and rigidity. The mass of the element under the

application point of disturbing force shall be increased to decrease the vibration of foundation.

As for the tail part of foundation (where is initiator is located), the cross section of the

element at roof shall be increased appropriately for fear that the local vibration is oversize.

In order to keep the shaft line straight and even and improve the dynamic behavior of

foundation, the statical deflection of each transverse beam should be equal approximately.

The roof elements shall be stressed simply and reasonably. The longeron and transverse

beam shall avoid the eccentric load as much as possible with a view to decreasing the torque

force of coupled beam.

5.1.11.2 With preconditions meeting the requirements on strength and stableness, the rigidity

of column may be appropriately decreased, but the length-diameter ratio of the column should

not be larger than 14.

Page 56: DL 5022-1993

51

5.1.11.3 The bottom plate shall be with certain rigidity and shall be comprehensively

considered according to the rigidity and bearing capacity of the foundation.

5.1.12 The bottom plate of frame foundation may adopt shaft type, beam slab type or flatbed.

The thickness of the flatbed bottom plate of steam turbine set foundation or the beam

depth of the shaft type and beam slab type shall be determined according to the property of

foundation soil, which should not be less than 1/15 of the length of bottom plate.

5.1.13 When the foundation is constructed on the rock foundation, the rock formation shall

comply with the relevant requirements specified in the "Code for Design of Dynamic

Machine Foundation" or may adopt the anchor bar foundation or isolated foundation.

5.1.14 When the foundation soil is the clay with high or intermediate compressibility, the

rigidity of groundwork and foundation shall be strengthened and effective measures shall be

taken to reducing the differential settlement of foundation. When the foundation soil is of

high compressibility, the artificial foundation should ne adopted.

5.1.15 The cantilever platform of the foundation roof shall be made into solid web type, the

jib length generally shall not be larger than 1.5m, and the profile height at the cantalever

pedestal shall not be less than 0.75 times of the out-suspending length.

5.1.16 When the bottom plate is set one the soil aggregate and weathered bedrock foundations,

the influence of temperature effect in the construction shall b taken into consideration, and the

bottom plate shall be set with insulating layer under it.

5.1.17 In the construction, the may be set with two or three construction joints that shall be

separately set at column top, socle or near to the ground benchmark post.

The construction joint shall be treated, and steel reinforcements with diameter of 8mm,

interval of 200mm and length 600mm (being inserted into the concrete by 300mm) shall be

reserved on the concrete plane. Before the casting, the concrete plane shall be roughened,

cleaned and adequately wet, one layer of cement net slurry mixed with cementing agent shall

be made.

5.1.18 The power calculation of frame foundation may adopt amplitude of vibration method

(that is to take the amplitude value as the guideposts for design). The space multivariant

system should be adopted when calculating the amplitude. Generally, only the amplitude Az at

the vertical direction of the application point of disturbing force needs to be calculated. Az

shall comply with the requirements of the following equation:

AAz (5.1.18)

Where [A]——Allowable amplitude value (mm), see Table 5.1.18.

The disturbing force value adopted when calculating the amplitude shall be supplied by

the machine building plant, which may be selected according to Table 5.1.18 when the

information is unavailable. Table 5.1.18 Allowable Amplitude and Disturbing Force Value

Running rotation speed of machine(r/min) 3000 1500

Allowable amplitude A mm 0.02 0.04

Vertical and horizontal

transverse direction 0.20Ggi 0.16Ggi

Disturbing force Pgi at the ith

point when calculating

amplitude(kN) Horizontal longitudinal 0.10Ggi 0.08Ggi

Page 57: DL 5022-1993

52

direction

Notes: 1. The figures in the table are the allowable amplitude and disturbing force value when the machine is at normal

running.

2. Generally, Ggi, as the weight of the machine rotor at the ith point on foundation, is the rotor weight (kn) that

centralizes at beam and column top.

5.1.19 When calculating the amplitude, the peak amplitude within certain scope of running

rotation speed (generally is±25%) as the calculated amplitude with running rotation speed,

and shall be less than the allowable amplitude value specified in Table 5.1.18.

The calculated amplitude with 0~0.75 times of general range of work speeds shall not be

larger than 1.5 times of allowable amplitude value.

5.1.20 When calculating the amplitude, the disturbing force oiP at any rotation rate shall be

calculated according to the following equation:

2

0

n

nPP gioi (5.1.20)

Where oiP ——The disturbing force value (kN) at the ith point at any rotation rate;

giP ——The disturbing force value (kN) at the ith point at running rotation speed;

0n ——Any rotation rate (r/min);

n——Running rotation speed (r/min).

5.1.21 As for the frame foundation with running rotation speed (n) at 3000r/min, when

calculating the amplitude, the foundation may be considered according to rigidity (the effects

of anelasticity of foundation is not considered); the foundation with n not larger than

1500r/min should be considered with its elasticity, here, the rigidity factor of foundation may

be adopted according to the relevant regulations specified in the "Dynamic Machine

Foundation Design Code".

5.1.22 When there are actions of r disturbing forces, the amplitude 1A (mm) at the ith

particle shall be calculated according to the following equation:

1

2

k

Ar

A iki (5.1.22)

Where kiA ——The amplitude value of the kth disturbing force on the ith particle (mm).

5.1.23 When the foundation is the space frame composed of transverse frame and longeron

and the elasticity of foundation is not considered, it may be simplified as the transverse plane

frame and may adopt the simplified calculation by considering the two freedom systems with

space influence, or may be calculated according to the "Dynamic Machine Foundation Design

Code".

5.1.24 As for the home-made turbogenerator foundation with running rotation speed at

Page 58: DL 5022-1993

53

3000r/min, the foundation is space frame composed of transverse frame and longeron and

meets the conditions specified in Table 5.1.24, the power calculation may not be considered.

When it does not meet the conditions specified in the table, the power calculation should be

carried out according to the method specified in 5.1.18~5.1.23. Table 5.1.24 Conditions for Foundation without Power Calculation

Unit capacity

(MW)

Intermediate frame

Longeron

Side frame

≤125 giGGi 6 giGG 101

200 gii GG 7 giGG 121

Note: Gi is the weight centralizing onto the beam or column top (including the machine weight).

5.1.25 The bearing capacity of the members of turboset and electric machine foundations

shall be calculated according to the following loads:

Permanent load--Self-weight of member, machine weight, weights of other equipments

fitted on foundation and the cylinder expansion force, pipeline thrust force, vacuum pull force

of condenser, and the act of temperature difference;

Variable load--Dynamic load (or equivalent load) and live load of top plate;

Accidental load--Short-circuit moment; and direct-transmitted shock effect

5.1.26 When calculating the dynamic internal force of member, it may be calculated by

adopting the straight forward calculation with multivariant system or have the simplified

analysis according to the equivalent load.

The disturbing force for calculating the dynamic internal force, it shall be four times of

the dynamic internal force when calculating the amplitude and the influence of fatigue of

materials shall also be taken into consideration. As for the reinforced concrete member, the

endurance ratio pr

shall be 2.

Generally, the equivalent load at vertical direction may be assumed to be concentrated

load, and the equivalent load at horizontal direction may be assumed to act on the axial lines

of longeron and beam.

5.1.27 When calculating the dynamic internal force according to equivalent load, the basic

vibration mode and high modal contribution of foundation shall be respectively considered,

the dynamic internal force shall be calculated according to the following provisions and shall

take the larger value as the controlling value.

5.1.27.1 When calculating dynamic internal force according to the basic vibration mode of

foundation, the equivalent load shall be calculated according to the following equation:

(1) The equivalent load NZi at the ith vertical direction on transverse frame shall be

calculated according to the following equation, and shall not be less than four times of rotor

weight.

max42

1

n

nPN gipzi (5.1.27-1)

Where: n1——The first natural vibration frequency (r/min) of transverse frame at vertical

direction shall be calculated according to "Dynamic Machine Foundation Design

Page 59: DL 5022-1993

54

Code".

ηmax——Maximum power coefficient, which adopts 8.

As for the turbo-unit with running rotation speed at 3000r/min, when no power

calculation is required, the vertical equivalent load shall be adopted according to Table

5.1.27-1. Table 5.1.27-1 Vertical Equivalent Load

Power of machine

unit(MW)

≤25 >25 and ≤125 200

ziN(kN)

10Ggi 6Ggi 4Ggi

(2) The total equivalent load at horizontal direction (is Nx at transverse direction and Ny at

longitudinal direction) shall be calculated according to the following equation, and shall not

be less than the gross weight giG

of rotor. The total equivalent load shall be distributed

onto each frame according to rigidity.

pxjd

gix K

G

GxN (5.1.27-2)

pyjd

giy K

G

GyN (5.1.27-3)

Where εx, εy——They are the calculation coefficients (m) at transverse direction and

longitudinal direction, as for the unit with n=3000r/min, 8.12x 10-4,

4104.6 y ; As the unit with n=1500r/min, 41040 x ,

41020 y ;

dG ——The whole permanent load at top plate of foundation (including the

self-weight of top plate, weight of equipment and half of the pillar weight) (kN);

pxjK, pyjK ——The total rigidity in horizontal direction of the jth frame in transverse

direction and longitudinal direction of the foundation (kN/m).

As for the turbo-unit with running rotation speed at 3000r/min, when no power

calculation is required, the total equivalent load in horizontal direction shall be adopted

according to Table 5.1.27-2. Table 5.1.27-2 Total Equivalent Load in Horizontal Direction

Unit capacity (MW) ≤25 >25 and ≤200

Nx, Ny(kN) giG2 giG

(3) The design schedules shall be respectively adopted according to Figure 5.1.27-1 and

Figure 5.1.27-2.

Page 60: DL 5022-1993

55

Figure 5.1.27-1 Design Schedule of Transverse Directional Frame

5.1.27.2 When considering the vibration effect of the high vibration mode of foundation, the

beam and longeron of top plate shall be calculated for dynamic internal force according to the

equivalent load specified in Table 5.1.27-3 and the corresponding design schedules (Figure

5.1.27-3 and Figure 5.1.27-4).

Figure 5.1.27-2 Design Schedule of Longitudinal Directional Frame

Table 5.1.27-3 Equivalent Load by Considering Influence of High Vibration Mode

Direction Vertical direction Transverse direction Longitudinal direction

Load (kN) cizi GN 8.0 cixt GN 8.0 ciyi GN 4.0

Note: Gci is the self-weight of member and the machine weight (distributed equally or concentratedly) it supports.

Figure 5.1.27-3 Design Schedule of Beam

Page 61: DL 5022-1993

56

Figure 5.1.27-4 Design Schedule of Longeron

5.1.28 When calculating the dynamic internal force according to the multivariant system of

space, the maximal dynamic internal force value with in the scope of 1.25 times of running

rotation speed of machine shall be taken as the controlling value.

When r disturbing forces act, the dynamic internal force Si at the ith material particle shall

be calculated according to the following equation:

r

kiki SS

1

2

(5.1.28)

Where ikS ——The dynamic internal force generated by the kth disturbing force at the ith

point.

5.1.29 The calculation for the bearing capacity of the foundation elements shakk be

assembled according to the undermentioned load effect;

Basic assembly——It is assembled by permanent load and dynamic load (or equivalent

load), the dynamic load is only considered with the one-way action and it assembly

coefficient is 1.0.

Occasionla assembly——The assembly of permanent load, dynamic load and

short-circuit torque, the assembly coefficient of dynamic load is 0.25, and the assembly

coefficient of short circuit torque is 1.0.

Direct-transmitted shock effect——It is assembled by permanent load, dynamic load and

direct-transmitted shock effect, the assembly coefficient of dynamic load is 0.25, and the

assembly coefficient of direct-transmitted shock effect is 1.0.

5.1.30 The longeron and crossbeam of foundation roof shall be considered with the stress

generated by the temperature difference at both sides of element, generally, the temperature

steels shall be separately placed at both sides of the beam, and the steel ratio at each side may

reach 0.1%, but when the unit capacity is larger than or equal to 100MW, the steel ratio at the

longitudinal beam side face of its high and intermediate-pressure component side shall be

increased to 0.15%.

When the length of longitudinal framework of foundation is larger than or equal to 40m,

it shall be calculated according to the temperature effect of longitudinal framework. The

Page 62: DL 5022-1993

57

calculated temperature difference at roof and socle may be 20℃ when the information is

insufficient.

5.1.31 When the mobile load of roof is only used at equipment installation, the strength of

roof shall be determined according to the process requirements, which should be adopt

20~30kN/m2.

5.1.32 The partial factor of permanent load may be 1.2, the variable partial load factor may be

1.4, the partial factor of accidental load may be 1.0, and the partial factor of direct-transmitted

shock effect may be 1.3.

5.2 Auxiliary machine foundation

5.2.1 The section is applicable to the auxiliary machine foundation that is constructed on

groundwork (hereinafter referred to as auxiliary foundation).

5.2.2 The infrastructure mode shall be determined according to the functions and capacity of

auxiliary machines, the requirements of manufacturer and the different conditions of

groundwork, which may separately adopt foundation, wall-type and frame foundation.

5.2.2.1 The foundations of draught fan and blower may be designed into massive foundations.

When the capacity of electric motor is above 2000kW, they may be designed to wall-type or

frame foundations.

5.2.2.2 The tube mill foundation may be designed into massive foundation or the wall-type

and stump foundations with common bottom plate, and it may be designed into frame

foundation when the conditions pertmit. When the groundwork is with good conditions (fk is

not less than 250kPa and the differential settlement is very small), it may be designed inyo

isolated foundation with the fore and after bearings separated, but the rotating part and the

large cone bearing must be at the same foundation mat.

Other coal mill foundations should be designed into the massive foundation.

5.2.2.3 The foundations of electrically driven feed pump with motor capacity above 2000kW

and the steam feed pump with motor capacity above 2000kW should be designed into wall

type or frame foundations

5.2.2.4 The coalbreaker foundation may be designed inyo independent wall-type or frame

foundations.

5.2.2.5 Except the forementioned achine foundations, other auxiliary machine foundations

may be designed into massive foundations.

5.2.3 The auxiliary machine foundation should not be connected with the building foundation.

When the tube mill foundation is pressing above the foundation of main workshop framework,

proper vibration isolation measures should be adopted (as rubber blanket or sand bedding

course). When the foundations of other auxiliary machines (such as blower fan, fan mill,

medium-speed coal grinding mill, and feed water pump) must prees above the building

foundation, proper effective vibration isolating measures (such isolation mountings as steel

spring and rubber) shall be adopted. When calculating the foundation of main workshop,

those additional loads must be counted in and the differential settlement shall be taken into

consideration.

5.2.4 The auxiliary machine foundations such as draught fan, blower, coal grinding mill

coalbreaker, electrically driven feed pump and steam feed pump with motor capacity above

Page 63: DL 5022-1993

58

100kW should be placed on the raw soil groundwork. When the arrangement permits, the

basal area of foundation may be increased with condition that not increases the concrete

volume.

Figure 5.2.5 Schematic Diagram for Allowable Elevation Difference of Neighbouring Foundations

5.2.5 when the bottom elevations of the auxiliary machine foundation and neighbouring

foundations are different (as Figure 5.2.5), the following equation shall be met

BtgA (5.2.5)

Where ——Internal friction angle of soil, plain concrete or rubble concrete underlayer

may be set under the foundation when the equation is not met.

5.2.6 The auxiliary machine foundation with motor capacity less than 100kW may be plaved

on the tempered backfilling soil. The treatment of backfilling soil must comply with those

specified in related codes.

5.2.7 The foundations of electrically driven feed pump, steam feed pump, initiator and all

kinds of centrifugal pumps with rotation speed above 1000r/min and not larger than

3000r/min and the power less than 2000kW, if they are massive foundations with weight

larger than five times of machine weight or the wall foundations meeting those specified in

Table 5.2.13, may have no power calculation (excluding the machine foundation with variable

speed).

5.2.8 The power calculation of the massive and wall foundations with the rotation speed of

equipment not larger than 3000r/min shall be carried out according to the relevant provisions

specified in "Code for Design of Dynamic Machine Foundation" (hereinafter referred to as

"Code for Dynamic"), the machine foundation of general type may be simply calculated

(excluding the foundation of equipment with variable speed) according to Equation

(5.2.10-1).

The power calculation of framework machine foundation with the running rotation speed

of equipment not larger than 3000r/min shall be carried out according to the relevant

provisions specified in "Code for Dynamic".

5.2.9 The wall and frame foundations of independent coalbreaker shall have power

calculation according to the corresponding provisions specified in the "Code for Dynamic".

When the independent wall foundation of coalbreaker with production output below 300t/h

meets those specified in Table 5.2.13, it may not have the power calculation.

The massive and wall foundations of tube mill may not have the power calculation.

Page 64: DL 5022-1993

59

5.2.10 When the wall and massive foundations with the rotation speed of equipment not larger

than 1000r/min have simple calculation, only the maximal lateral and horizontal amplitude at

the upper margin of foundation shall be calculated, and the vertical amplitude may not be

calculated. The design schedule of massive foundation is showed as Figure 5.2.10.

The horizontal amplitude xA

of foundation at the top surface shall be calculated

according to the following equation:

h

K

HP

K

PA x

x

xx (5.2.10-1)

21

22

1

2

21

2

41

1

xD

(5.2.10-2)

22

221

1 hK

K x

x

(5.2.10-3)

m

K xx 2 (5.2.10-4)

Where 1 ——The horizontal natural vibration frequency of the approximate first principal

mode of foundation (rad/s);

H——Distance from the rotating main shaft of man machine to the foundation base (m);

h——Height of foundation (m);

1xD ——The damping ratio of the horizontal rotation toward the first vibration mode,

which shall be taken value according to those specified in "Code for Dynamic";

——The working circular frequency of machine (rad/s), =0.105n (one harmony);

n——Running rotation speed of machine (r/min);

h2——Distance from the foundation base to gravity center of foundation (m);

Kx——Shear stiffness of groundwork (kN/m);

K ——Flexural rigidity of groundwork (kN·m);

Page 65: DL 5022-1993

60

Px——Horizontal disturbing force of machine (kN);

xA ——Horizontal amplitude at top surface of foundation (m);

——Amplification coefficient;

x ——Horizontal self-oscillation circular frequency of base cluster (rad/s);

m——Total mass of the foundation and equipment (t).

5.2.11 The disturbing force or excentricity of the machine shall be supplied by the

manufacturers. And they may be selected by referring to Table 5.2.11 if the information is

insufficient.

g

Gm 0 in the table, m is the mass of machine or the rotating part of electric motor, G0

is the gravity of the machine or the rotating part of electric motor, and g is the acceleration of

gravity.

5.2.12 The power calculation of the auxiliary machine foundation with running rotation speed

not larger than 3000r/min shall comply with the following conditions:

zz AA (5.2.12-1)

xx AA (5.2.12-2)

Where: Az and Axφ are the vertical horizontal amplitudes at the application point of calculated

disturbing force or at the top surface of foundation, [Az] and [Axφ] are the maximal allowable

vertical and horizontal amplitudes.

The maximal allowable amplitudes [Az] and [Axφ] shall be adopted according to Table

5.1.12 if this information is unavailable.

5.2.13 The wall foundation with power calculation according to the calculation principle of

massive machine foundation should have rigid connection of its vertical and horizontal walls

with roof, bottom plate to assure their joint work. Due to the process requirements, only the

one-way wall is set, the wall shall be set parallel to the acting direction of horizontal

disturbing force. The structure dimension of wall foundation may be adopted according to

Table 5.2.13. Table 5.2.11 Excentricity and Disturbing Force of Main Subsidiary Foundation

No. Nomenclature of

machinery

Name of the moving

part of machine

Rotation speed of

machine (r/min); Excentricitye0 (mm)

Disturbing

force P0

1 Blower Impeller 0.5~0.7

2 Draught fan and mill

exhauster Impeller 0.7~1.0

3 Fan mill Impeller

4 Impact breaker Rotor

1.0~1.5 of soft coal and

1.5~2.0 of hard coal

5 Plate hammer crusher Rotor 1.0

6 Ring crusher Rotor 0.6~1.0

7 Pumps Impeller n≥1500 0.1

8 Pumps Impeller n =1000 0.2

P0=me0ω2

Page 66: DL 5022-1993

61

9 Pumps Impeller n<1000 0.25~0.5

Note: The unit of disturbing force P0 is N or kN, where the unit of e0 is m.

Table 5.2.12 Maximal Allowable Amplitude of Foundation

Allowable amplitude value(mm) Foundation name Running rotation speed(r/min)

Vertical(Az) Horizontal (AxФ)

Blower fan, pumps, fan mill 3000

1500

1000≥n>750

750≥n≥500

n<500

0.03

0.06

0.10

0.15

0.20

Coalbreaker 300<n≤750

750<n

0.15

0.10

0.20

0.15

Note: The allowable amplitude value of the equipment foundation of 3000r/min and 1500r/min is the requirement on

frame foundation.

5.2.14 The wall foundation is connected with vertical and horizontal walls, and has rigid

connection with upper roof and bottom plate to keep certain rigidity. And its dimension is

adopted by referring to Table 5.2.14.

5.2.15 Reinforcement requirement of massive foundation: The whole foundation may not be

set with steel reinforcement nut only partially set with constructional reinforcement near to

the bolt hole when the volume is less than 40m3; the whole foundation shall be set with

constructional reinforcement when the volume is larger than 40m3; as for the weak positions

such as superstructure or pore space, necessary steel reinforcements shall be set in addition no

matter the size of volume. The specific requirements of reinforcement shall be implemented

according to the relevant provisions specified in the "Code for Dynamic". Table 5.2.13 Structure Dimension of Wall Foundation

Element name of foundation Element size of foundation

Upper top plate Flat plate ≥0.5m

Ribbed slab ≥0.15m

Jiblength of top plate ≤1.5m

Profile height of top plate at pedestal of

cantalever ≥

3

1of jiblength

Wall thickness When the wall is parallel to horizontal disturbing force, it≥

6

1 of clear height

and≥0.5m

When wall is perpendicular to horizontal disturbing force, it≥4

1 of clear

height

Thickness of foundation mat ≥0.6m, and≥ wall thickness

Jiblength of bottom plate Plain concrete bottom plate≤thickness of bottom plate

Reinforced concrete bottom plate≤2.5 times of the thickness of bottom plate

Table 5.2.14 Physical Dimension of Wall Foundation

Element name of foundation Element size of foundation

Wall thickness

Thickness of foundation mat ≥0.5m, ≥

6

1

of the clear height of wall

Page 67: DL 5022-1993

62

Jiblength of bottom plate at foot foundation

Jiblength of upper top plate

Thickness of upper horizontal top plate

Profile height at upper cantalever and beam support part

≥0.6m

≤2.5 times of the thickness of bottom plate

≤1.5m

≥0.1m

≥3

1

Of the extension elongation of cantalever

5.2.16 When determining the dimension of auxiliary machinery foundation according to the

technological information, the following requirements shall also be complied with:

5.2.16.1 The horizontal distance from the edge of auxiliary foundation to edge of foundation

should not be less than 100mm.

5.2.16.2 The distance from the axial line of concealed anchor bolts to the edge of foundation

shall not be less than four times of the bolt diameter, the clear concrete thickness bellow the

bottom surface of concealed anchor bolts shall not be less than 50mm.

5.2.16.3 The distance from the edge of anchor bolt box to the foundation edge shall not be

less than 100mm (including the clear distance of such edges of pore space and hollow of the

foundation); otherwise, the constructional reinforcements must be partially set and be

strengthened. The clear distance from bottom of anchor bolt box to the foundation bottom

shall not be less than 100mm.

5.2.16.4 The cross dimension of anchor bolt hole should be 5~6 times of the diameter of

anchor bolt. The depth (except the thickness of secondary grouted layer) should be the buried

depth of anchor bolt added by 100~150mm. When the pore space depth exceeds 500mm and

the bottom hole is above ground, the sundries cleaning hole should be set.

5.2.17 Burring requirement of anchor bolt: The burring requirement of the anchor bolt of

auxiliary machinery foundation shall be supplied by the machine building plant or by the

process designer. As for the anchor bolt of weighted machine such as hook machine, the

buried depth shall not be less than 20 times of the diameter of bolt; the buried depth of

anchor-slab-type buried depth shall not be less than 15 times of the diameter of bolt.

6 Fuel buildings

6.1 Coal-fired buildings

6.1.1 As for the longitudinal beam directly bearing the mobile load of train in the coal

discharging building, the design load shall adopt the mobile load specified in railway

standards of the People’s Republic of China, that is, the "moderate—mobile load". The

structural design and calculation must comply with those specified in the "Code for Design on

Railway Bridge and Culvert".

6.1.2 The structure selection and design schedule of underground structure should be selected

according to the following principles.

6.1.2.1 Requirement on structure selection of dump chamber

(1) Generally, when setting two rotor type or rotaside tippers, the reinforced concrete

round or box construction may be adopted.

Page 68: DL 5022-1993

63

(2) Generally, when setting one rotor type or rotaside tippers, the reinforced concrete

round or box construction may be adopted.

When the underground structure adopts open caisson scheme, it shall comply with those

specified in the "Technological Provisions of Hydraulic Design in Thermal Power Plant".

6.1.2.2 Requirement on structure selection of slot-type coal chute

(1) When there is no groundwater influence, the sidewall and bottom plate may adopt

block casted or assembling reinforced concrete structure, and the mode of bottom plate may

also adopt slab rib type or separate type.

(2) When there is groundwater influence, the sidewall bottom plate shall adopt the block

casted reinforced concrete structure.

6.1.2.3 Requirements on structure selection of underground coal delivery tunnel:

(1) When there is no groundwater influence, the top plate and sidewall should adopt

reinforced concrete structure; and when the tunnel is shallow, they may also adopt the

concrete or rubble concrete structure.

(2) When there is groundwater influence, they shall adopt the reinforced concrete box

construction.

6.1.2.4 Selection principle of design schedule:

(1) Generally, the subsurface constructions are space structures, they may be simplified

into longitudinal and transverse plane structural system for analyzing the internal force, be

adopted with linking solution or decomposition calculation.

The structure selection and design schedule of common tippler chamber and slot-type

coal chute see Annex D.

(2) If the skew wall of the coal scuttle of tippler chamber and slot-type coal chute is

supported on the terrestrial platform and coal feeder platform together with the bottom

sidewall of basement, when calculating the sidewall, the platform may be taken as the

horizontal elastic bearing point, but the platform plate must be calculated two-way bending

member.

In the calculation, the influence of the elastic deformation of framework column in

sidewall shall be taken into consideration, the coefficient of reaction at supporting point of the

platform plate of coal feeder generally is 0.8~0.9.

6.1.3 When calculating the bearing capacity of the train crossbeam in the coal discharging

building, the train load shall be multiplied by the impact coefficient (1+μγ) after deceleration.

The equation is

VV

V

l kp230

6211 (6.1.3)

Where l——Span of beam (m);

V——Design running speed, which may be V=15km/h;

kpV ——Terminal speed, which may be km/h65kpV .

When calculating the bearing capacity of the crossbeam that directly supports the tippler,

the vertical and horizontal loads shall be multiplied by the power coefficient. This coefficient

shall be supplied by the technical design specialty, or may be adopted according to Table 6.1.3

if the information is unavailable. The vertical and horizontal force generated by the equipment

Page 69: DL 5022-1993

64

shall be implemented according to the relevant provisions of manufacturer Table 6.1.3 Power Coefficient of Tippler Load

Power coefficient Categories of tipplers

Vertical Horizontal

Rotaside type

Rotor type

1.5~2.0

2.5

1.5~2.0

2.0~2.2

6.1.4 The waterproofing design of subsurface construction shall be designed according to the

"Waterpoof Technical Specifications for Underground Works".

6.1.5 The indoor terrace of subsurface construction must be set with drainage slope, drain

ditch and collecting well. The longitudinal slope of drain ditch shall not be less than 0.5%,

and the transverse slope shall be 1%~3%. The slope aspect shall be determined according to

the positions of ditch and well.

6.1.6 The load effect assembly of subsurface construction shall be implemented according to

those specified in the chapter on load, and the following provisions are supplemented, the

loads are classified into:

6.1.6.1 Permanent load (dead load), such as dead load, fixed equipment, earth load, earth

pressure and water pressure.

6.1.6.2 Variable load (mobile load), such as coal weight and the load of train, automobile and

coal transporter.

(1) Variable load of train: when the railways are of two lines, if the twolines entering into

the tippler chamber are all coaler mobile load, and the two lines entering into the slot-type

coal chute are all engine mobile load, the load acting on the frame girder shall be multiplied

by the reduction coefficient 0.9. In particular cases, if it is designed according to that the

engine does not enter into the slot-type coal chute, the marks for prohibiting the engine

passing shall be set.

(2) Variable load in coal scuttle of slot-type coal chute: The coal scuttle shall be filled

with coal that is higher than the coal scuttle by 0.5~1.0m. When it is multi-hole coal scuttle,

the worst assembly of no-load and full-load of coal scuttle shall be taken into consideration.

(3) Variable load of coal transporter: when the coal transporter transporting coal from the

coal yard to ground reception bunker, the pressure effect of the load of coal transporter on the

sidewall, coal grate, and coal scuttle wall shall be taken into consideration.

6.1.7 The coal transporting trestle shall be selected according to the relevant provisions

specified in the "Technical Specification for Design of Thermal Power Plants". The

lightweight construction should be adopted when it is arranged sealed. The lateral truss of

trestle adopts steel structure, reinforced concrete or prestressed reinforced concrete structure.

6.1.8 When the coal transporting trestle is designed according to reinforced concrete

articulated reinforced concrete trestlework, the maximal space between the expansion joints

may be adopted according to the following provisions:

Enclosed trestle 130m

Open trestle 100m

When the length of trestle exceeds the maximal space of expansion joints specified

above, the temperature effect of the trestle column shall be recalculated.

6.1.9 The trestle must with adequate space rigidity and shall comply with the following

requirements:

Page 70: DL 5022-1993

65

6.1.9.1 When adopting trestle as the sidewall framework, the crossbeam and the montants at

two ends of trestle shall be made into∏-shaped rigid frame at top to assure the lateral stability

of trestle (Figure 6.1.9).

Figure 6.1.9 Trestle-type Sidewall Framework

The transverse wind power of trestle shall be bear by the longitudinal horizontal bracings

at upper and lower cambers. This horizontal bracing shall be set along the whole trestle.

6.1.9.2 The upper longitudinal bracing shall be set along the overall length of through truss,

the transverse vertical bracing shall be set simultaneously, their quantity may be determined

according to the span size of trestle, but shall not be less than two in each span.

6.1.9.3 The trestle adopted precast reinforced concrete thin webbed girder, when one end is

supported on the column or beam of coalbreaker chamber or transfer site, the lateral

horizontal bracing shall be set at the head end of flange for assuring the stableness of thin

webbed girder at upper end.

6.1.10 Supporting requirement of trestle truss (or beam):

When the trestle is supported on the pedestal of main workshop framework or side

column, the pedestal shall be designed into roller pedestal, and the one near to coalbreaker

chamber shall be articulated fixedly.

When the trestle and plant are separated, one end is of fixed articulation; the other end

shall be made into cantalever and shall be separated from the plant and coalbreaker chamber.

It shall be fixed articulation at the intermediate span and the two ends.

6.1.11 The node structure of movable hinged support of trestle should adopt roller pedestal.

6.1.12 Computational length of the trestle column:

l0=1.25Hc of the bottom column perpendicular to the coal belt direction;

l0=1.5Hc as for the rest column layers;

l0=1.25H at the direction parallel to the coal belt.

Where Hc ——Distance from the top surface of foundation to the center of beam or the

distance among central lines of beams;

Page 71: DL 5022-1993

66

H——Distance from the top surface of foundation to the bottom of the pedestal of

trestle.

The profile height of trestle column general is H/25~H/20.

6.1.13 The beam directly supporting the coalbreaker must have the calculation on the vertical

vibration and the bearing capacity of cross section.

At regular production operating conditions, the maximal allowable amplitude value

(single ampitude) of the vertical vibration of floor slab structure generally is 0.08mm.

6.1.14 The calculation for the amplitude value of the floor slab of coalbreaker may be carried

out according to the beam-type design schedule.

The maximal allowable excentricity 0e of the rotor of coalbreaker shall be supplied by

the technological design specialty, and may be adopted according to Table 5.2.11 if the

information is unavailable.

6.1.15 The calculation for the crosssectional bearing capacity of the beam that bears dynamic

load may adopt the static calculation method by multiplying the equipment load with power

coefficient. The load shall be calculated as:

P=βQ (6.1.15)

Where β——Power coefficient of coalbreaker, which shall be taken value according to the

rotation speed of coalbreaker, β=5.0 when the rotation speed is at or above

740r/min, otherwise, β=4.0;

Q——Load of all equipments (kN).

6.1.16 The beam that directly supports the coalbreaker may not have calculation on vertical

vibration when its height-to-span ratio meets the value specified in Table 6.1.16.

Page 72: DL 5022-1993

67

Table 6.1.16 Height-to-span Ratio of Beam (h/l)

5<l≤6 6<l≤7 7<l≤8 8<l≤9

One Two One Two One Two One Two

2515 0 P

3525 0 P

4635 0 P

6

1

2.5

1

8.4

1

5.5

1

7.4

1

5.4

1

5.5

1

5

1

7.4

1

5

1

5.4

1

2.4

1

5.5

1

5

1

7.4

1

5

1

5.4

1

2.4

1

5.5

1

7.4

1

5.4

1

5

1

2.4

1

1.4

1

Notes: 1. The width-to-depth ratio of beam generally shall meet3

1/ hb ;

2. The strength grade of concrete shall not be less than C20, and the steel reinforcement shall be of grade II;

3. It shall be treated according to 6.1.22 when kN460 P ;

4. See table 5.2.11 for the calculation equation of the disturbing force P0 of coalbreaker.

6.1.17 The coalbreaker chamber may adopt reinforced concrete frame structure or adopt the

composite structure of bearing brickwall and site-casted beam slab.

The coalbreaker must be arranged on the beam to make the disturbing force direction be

accored with the X-direction of beam. The arrangement of floor slab shall avoid the

cantalever.

6.1.18 The beam slab of coalbreaker floor shall adopt the monolithic reinforced concrete

structure, and the thickness of floor slab shall not be less than 120mm.

6.1.19 As for the walking beam bearing dynamic load, both the beam tip and beam bottom

shall be set with reinforcing bar, and the critical steel ratio shall not be less than 0.15%.

The beam stirrup shall adopt enclosed steel hoop, its diameter shall not be less than

8~10mm; when the beam depth is larger than 2m, the diameter shall not be less than

10~12mm; the bar spacing shall not exceed 200~300mm.

6.1.20 The coalbreaker coal balance room shall be set with vibrationproof slot. The

coalbreaker that is supported onto the floor slab should be adopted with isolation mounting if

the condition permits.

6.1.21 the following structural measures should be adopted for reducing the influence of the

vibration of coalbreaker.

6.1.21.1 The composite structure adopting brickwall for bearing load shall be set with ring

beam at each layer. At the connection part of walls, three horizontal reinforcements with

diameter of 6mm shall be set for every five bricks.

At the crossbeam pedestal that directly bears dynamic load, the reinforced concrete

Girder span l ( m )

Quantity Disturbing

force of

coalbreaker (kN)

Page 73: DL 5022-1993

68

cushion block shall be set and the arranged at two directions with mat reinforcement with

diameter of 8mm and space of 100mm.

6.1.21.2 When filling by adopting the supporting brickwall of reinforced concrete frame

structure, the drawknot among wall, beam and column may be treated according to the

requirement on anti-seismic construction of building.

6.1.22 The supporting structure of the coalbreaker with dynamic disturbing force above 46kN

may adopt independent wall type or framework type foundations, and movement joints shall

be set around its top to separate it from the floor slab structure.

6.1.23 The gantry crane and stacker-reclaimer foundations may adopt reinforced concrete and

concrete structures according to the different types of foundation soil.

6.1.24 The computation module of ground foundation may adopt the elastic bedding value

method or shearing force balance method for the calculation on internal force of foundation.

6.1.25 The foundation beams of gantry crane and stacker-reclaimer shall be designed

according to the medium-grade working system, the fatigue recalculation may be omitted, and

the value of power coefficientβ shall be supplied by the technologicl design speciality.

6.1.26 The foundation structure may adopt strip stiffening bar foundation. When it is

reinforced concrete foundation, the reinforcement ratio should not be less than 0.1%; the

vertical horizontal reinforcement with diameter of 8~10mm shall be set within the height

scope web of girder, the space shall not be larger than 500mm; the hooped reinforcement

should adopt the enclosed steel hoop, the diameter shall be 10mm and the space shall not be

larger than 300mm. When it is concrete foundation, the constructional reinforcement shall be

placed at the tensile area of concrete, and the reinforcement ratio shall not be less than 0.05%.

6.1.27 The design of round silo shall comply with the following requirements:

6.1.27.1 The plan layout of silo shall be determined according to such conditions as

technology, torography, engineering geology and construction after the technical-economic

comparison.

6.1.27.2 The group silo should adopt the connecting type with the excircle of bulkhead be

tangential. The round silo with diameter larger than or equal to 18m should adopt independent

arrangement mode (excluding the rock foundation). The expansion joints shall be set when

the total length exceeds 50m.

6.1.27.3 When round silo with diameter larger than 15m is set with high-capacity motor (not

less than 100kW) at its top, the vibration calculation is required, the vertical allowable

amplitude is not larger than 0.04mm (single amplitude), and the site-casted reinforced

concrete silo top structure shall be adopted.

6.1.28 The wall thickness of round silo generally is

0100t

dt n (6.1.28)

Where t——Wall thickness (mm);

t0——t0=100mm when the diameter of round silo is equal to or less than 15m;

t0=120mm when the diameter of round silo is equal to or larger than 16m;

dn——Internal diameter of round silo (mm).

6.1.29 In power plant, the structure type of the coal silo bottom shall firstly adopt the

interstice-type full-length or ring-shaped headwall and the conical funnels arranged

Page 74: DL 5022-1993

69

symmetrically.

6.1.29.1 The thickness of horn type headwall may adopt 1/20~1/30 of the span at short side.

6.1.29.2 The wall thickness of the interstice-type bottom plate may adopt 1/5~1/10 of the

jiblength of bottom plate.

6.1.30 The lower supporting structure of the round silo should adopt the integral connection

of silo wall and funnel, and the joint supporting type of silo wall and inner column (Figure

6.1.30 (a)); it may also adopt the non-integral connection of silo wall and funnel or the joint

supporting type of inner wall and inner column (Figure 6.1.30 (b)).

Figure 6.1.30 Schematic Diagram of Under-silo Supporting Structure

(a) Supporting mode of silo wall and inner column; (b) Supporting mode of inner wall and inner column

6.1.31 The round silo foundation may adopt round and ring plate foundation or slab raft

foundations, or the assembled foundation of shallow-spherical shell and ring plate.

6.1.32 The top of round silo may adopt site-casted or fabricated bar concrete structure; when

the diameter is equal to or larger than 15m, it may adopt the reinforced concrete abscissus

cone shell and shallow-spherical shell structures; when the diameter of silo is greater than or

equal to 18m, the silo top structure may adopt steel structure framework and light enclosure

wall.

6.1.33 When the round silo is set with eccentrical coal outlet or many coal outlet at the bottom,

the adverse effect of eccentric discharging of coal shall be taken into consideration.

The added value △ph (kPa) of horizontal pressure when discharging coal eccentricaly

may be calculated according to the following equation:

n

vh R

ep.p 0250 (6.1.33)

Where e0——Excentricity, which is the distance (m) from the central line of silo to the central

line of coal outlet.

Rn——Internal diameter (m) of the net section of silo;

pv——The design value (kpa) of the vertical pressure on unit area at silo bottom must be

calculated according to the Equation (3.2.2-2) specified in the "Code for Design

of Reinforced Concrete Silos" (hereafter referred to "Code for Silos"), the

correction coefficient of vertical pressure cv=1.0;

△ph——Assuming that the added value △ph is evenly distributed along the circle, △ph

is a constant within hn/3 bellow the calculated altitude (hn) of stored coal, and

Page 75: DL 5022-1993

70

shrinks to zero in straight line above this scope, see Figure 6.1.33.

When the eccentricity moment e0<0.2R, the adverse effect of discharging coal

eccentrically may not be considered.

6.1.34 The calculation for the top, wall and bottom structures of round silo shall comply with

those specified in the "Code for Silos".

Hoop tension of silo wall:

Hoop tension 0N (kN/m) at any depth s

RphphN )(0 (6.1.34-1)

Where hp ——The horizontal pressure (kPa) of coal on unit area of silo wall must be

calculated according to those specified in "Code for Silos";

R——Radius of round silo (m);

µ——Amplification coefficient,μ=1.3 within 6nh

scope at the silo top and μ=1.0 within

the scope of nh6

5;

Figure 6.1.33 Distribution for the Added Value of Pressure on iNner Wall of Silo

nh ——Calculated altitude of stored coal (m)

Vertical pressure of silo wall:

With action of load at silo top and the deadweight, the vertical pressure )m/kN(1N on

the cross section of silo wall of unit perimeter is

nd

GN

1 (6.1.34-2)

Where G——Dead load above the calculated cross section and the load on silo top (kN).

Page 76: DL 5022-1993

71

The vertical pressure N2 (kN/m) resulted by the coal generating friction force is

)(42 v

n psd

N (6.1.34-3)

Where ——Gravimetric density of bin stock (kN/m3);

s——Depth of calculated cross section (m);

pv——Vertical pressure (kPa) acting on unit area at s section.

Hoop bending moment of silo wall:

The hoop bending moment may be calculated according to the following equation by

considering the non-axial symmetry distribution condition of coal pressure along hoop

direction:

Mθ=0.01phR2 (6.1.34-4)

Vertical bending moment of silo wall:

When the silo wall and interstice-type headwall are connected integrally, the horizontal

force action of headwall on silo wall shall be condsiered, and the internal force at the

connecting part shall be calculated for the edge effect.

6.1.35 The strength calculation structure requirement of the opening of round silo shall be

designed according to the "Code for Silos"; the opening of the silo with diameter larger than

15m may be calculated according to the Annex E of this stipulation.

6.1.36 The horizontal included angle of the headwalls at silo bottom shall not be less than 60°,

the inner lining materials may adopt the cast stone plate or steel shot, and the surface shall be

even and smooth.

6.1.37 The dry coal shed should adopt the reinforced concrete column structure and light roof

cover system. The dry coal shed with span larger than 36m should adopt bow member and

wire frame.

6.1.38 The adverse effect of the coal piled in the dry coal shed on the foundation and

superstructure shall be taken into consideration.

6.2 Fuel oil buildings

6.2.1 The foundation of the overground steel oil tank should adopt sand bedding course above

the raw soil, and its top surface shall be paved with bituminous sand as insulating layer. The

center of tank foundation shall be thicker than the part around it for fear that the center is

accumulated with oil and water after ground subsidence that can not be drained away.

As for the steel oil tank with capacity not larger than 500m3, when not setting the loop

retaining wall, the sand bedding course shall not be higher than the ground level by 1.2m, the

diameter of the top surface of sand bedding course shall be larger than the diameter 3.0m at

tank bottom, its side slope shall not be less than 1:15, and the side slope shall be protected

with its surface by adopting block stones (Figure 6.2.1).

When the steel oil tank is set on the weak foundation, the loop retaining wall shall be set

around the sand bedding course. The hoop tension resulted by the side thrust shall be

considered in the calculation.

When setting oil tank on weak foundation, the water-filling and prepressing measures

may be adopted against excessive settlement.

Page 77: DL 5022-1993

72

Figure 6.2.1 Sand Bedding Course of Steel Oil Tank

6.2.2 The oil discharging trestle work should adopt the prefabricated or cast-in-situ concrete

ground, and the oil and water drainage measures shall be considered.

6.2.3 The support of trestle work should adopt prefabricated battened column, plate and

casted-in-site foundation, and the support may adopt open side type expansion joint.

6.2.4 The design of fuel pump room shall consider the explosion protection and pressure relief

requirements, and the reinforced concrete trestlework load-carrying structure should be

adopted. Underground oil pump room shall be separated from the attached ancillary buildings

such as control-room and overhaul room by the settlement joint.

7 Chimney and flue

7.1 General provisions on chimney

7.1.1 The chimney height and the inside diameter at roof hatch shall be supplied by the

technology and should comply with the following series:

Chimney height——80, 100, 120, 150, 1.8, 210, 240, 270, and 300m

Inside diameter at roof hatch——0.5m shall be taken as modulus when the inside

diameter is among 2.5~8m; and 1m shall be taken as the modulus when the inside diameter is

larger than 8m. Note: The height of telescope-feed and multi-tube chimneys refers to the height of interior flue pipe.

7.1.2 The quantity of boilers that single tube chimney is matched should be:

One plant unit of 600MW grade;

No more than 2 plant units of 300MW grade;

No more than three plant units of 200MW grade;

No more than four plant units of 100MW grade;

Page 78: DL 5022-1993

73

No more than six plant units of or under 50MW grade. Note: The quantity of connected boilers may be properly increased when adopted maintainable chimney.

7.2 Chimney calculation

7.2.1 The chimney calculation in power plant shall not only comply with those specified in

this Section, but also shall comply with the current "Code for Design of Chimneys"

(hereinafter referred to as "Code for Chimneys") and the provisions specified in the

corresponding matching codes.

7.2.2 As for the chimney with height exceeding 240m, the safety coefficient of the strength

calculation of tunnel wall and the stress calculation of horizontal cross-section in operational

phase should be increased by 10%.

7.2.3 The appended bending moment ΔMi of chimney generated by the wind or earthquake

effects may be calculated according to the following equation (see Figure 7.2.3 for design

schedule).

Figure 7.2.3 Design Schedule for Appended Bending Moment of Crosssection

n

ijijji uuGM

1

)( (7.2.3)

Where Gj——Weight of material particle (the vertical earthquake force shall be added when

Page 79: DL 5022-1993

74

considering the vertical earthquake);

μj, μi——Ultimate horizontal displacements at jth and ith material particles.

When calculating the horizontal displacement of material particle, the influence of

sunlight temperature difference and foundation inclination on displacement shall be counted

in simultaneously.

7.2.4 The design of the flue opening of chimney in power plant shall not only comply with the

relevant provisions of "Code for Chimneys", but also shall abide by the conditions specified

in Annex E.

7.3 Measures for controlling the width of longitudinal cracks on chimney

7.3.1 When recalculating the circumferential reinforcement stress at vertical cross-section of

tunnel wall under temperature effect according to the "Code for Chimneys", the structural

safety factor should be increased by 15%.

7.3.2 The tunnel wall of the chimney with height exceeding 120m should adopt bifacial

reinforcements. By this time, if the steel reinforcements at inner side are set according to the

structure, the minimal reinforcement quantity is:

Vertical reinforcement——The minimum diameter is 10~12mm and the maximal space

is 500mm;

Circumferential reinforcement——The minimum diameter is 8~10mm, the maximal

space is 250mm and is not larger than tunnel wall thickness.

7.3.3 The design of flue gas temperature shall take the probable maximal flue gas temperature

value in the whole service life of chimney and shall take such factors as the fume temperature

variation changed or resulted by the abnormal operating condition of boiler and dedusting

equipments.

7.3.4 When adopting the brickwork inner lining, the mortar joint shall be compacted and

straight joint shall be avoided or reduced, the water absorption of brick shall be low, and the

density shall be decreased greatly with condition that the brick tag number is not less than No.

100 with a view to improving the heat-insulating performance.

7.3.5 The chimneys in power plant shall not adopt the occluded air layer as the

thermal-protective coating. Requirements on heat insulating materials are: Good integrity,

uneasy to be broken or deformed, loose and low water absorption, certain strength, and be

convenient for construction.

7.3.6 The principles for determining the thermal conductivity coefficient of materials:

7.3.6.1 The thermal-protective coating shall adopt the thermal conductivity coefficient value

at the water saturation state:

λ=1.25[λ0+ρ(0.5-λ0)] (7.3.6)

Where λ0——Thermal conductivity coefficient of thermal-protective coating materials at dry

state;

ρ——Water absorption (volumetric proportion) of thermal-protective coating materials at

saturated state.

In equation (7.3.6), (0.5-λ0)=0 when (0.5-λ0)≤0. Note: When adopting materials of hydrophobicity, the thermal conductivity coefficient of thermal-protective coating

materials may be calculated according to the practical water absorption.

Page 80: DL 5022-1993

75

7.3.6.2 The thermal conductivity coefficient of tunnel wall shall be taken the value at dry

state.

7.3.6.3 The thermal conductivity coefficient of the inner lining of brickwork shall take the

leakage influence of fluegas in brickwork joint into consideration. The value may be thermal

conductivity coefficient of brick being multiplied by the correction coefficient: As for the

inner lining of half bat thick, the correction coefficient is 1.67; as for the inner lining of one

brick thickness, the correction coefficient shall be 1.25 (the forementioned correction

coefficient shall be multiplied by 0.80 as for the section where the fluegas in chimney is of

negative pressure).

7.4 Corrosion resisting measures of chimney

7.4.1 The fluegas in the following conditions are corrosive fumes:

7.4.1.1 The sulfur content in coal is high and the scaling index kc>0.5~1.0.

kc value shall be supplied by the technology department, which is

ORA

Sk

xy

y

c

100 (7.4.1)

Where Sy, Ay——Separately the percentages of the sulfur and dust contents in coal;

∑RxO——Percentage of the total content of basic oxide in the dust content in coal.

∑RxO=CaO+MgO+Na2O+K2O

7.4.1.2 The sulfur content in coal is not high, but after the humidifying with wet cap collector,

the flue gas temperature is less than or close to the dew-point temperature of flue gas.

7.4.2 See Table 7.4.2 for the classification of the corrosiveness of flue gas on chimney

structure. Table 7.4.2 Gradation Table of Corrosive Flue Gas

Corrosiveness index kc of flue gas Type of dust catcher Flue gas

Gradation >2.0 1.5~2.0 1.0~1.5 0.5~1.0 Wet type Dry type

— — — —

— — — — Strong

— — — —

— — — —

Intermediate

— — — —

Page 81: DL 5022-1993

76

— — — —

Weak

— — — —

Note: When setting with desulfurization plant, the corrosiveness grade of flue gas on chimney may be considered by

reducing the grades in the above table by one grade.

7.4.3 The following factors shall be considered when selecting the corrosion resisting

measures of chimney:

7.4.3.1 Corrosiveness grade of flue gas

7.4.3.2 Possibility that the flue gas is of positive pressure operation in chimney.

7.4.3.3 The total capacity size of the matched generating unit of each chimney and the

importance of the generating unit in power system.

7.4.4 When discharging strong corrosive flue gas, the multi-tube or telescope chimney

structures should be adopted. Namely, the load bearing outer tube and inner tube for

discharging fume are separated to make the stressed structure of outer tube do not contact

with the strong corrosive flue gas. By this time, the inner tube for discharging fume shall be

composed of acid-proof materials.

7.4.5 When discharging weak corrosive fume, the anti-corrosive single-tube chimney

structure may be adopted. By this time, the following anti-corrosive measures shall be

adopted based on the traditional single-tube chimney:

7.4.5.1 The acid-proof lining and acidproof heat insulating materials shall be adopted.

7.4.5.2 The compactness of inner lining structure shall be strengthened for preventing or

reducing the leakage of flue gas.

7.4.5.3 When the inner lining structure can not guarantee the leakage of flue gas, the internal

surface of outer tube shall be adopted with anti-corrosive insulating layer, and the

compactness of the reinforced concrete outer tube shall be improved.

7.4.6 When discharging the medium corrosive flue gas, according to the matching unit

capacity size of chimney and its importance in power system, both the multi-tube or telescope

chimneys and the anti-corrosive single-tube chimney may be adopted.

7.4.7 The operation of flue gas in positive pressure has strong accelerating effect on the

corrosion of chimney, hereby, it should be avoided possibly. By this time, such methods as

cooperating with the technological specialty, improving the shape of or flue pipe, setting flue

gas diffusion head at the chimney top, reducing the flue gas flow velocity and the frictional

resistance of flue gas shall be adopted to make the flue gas be of negative pressure along the

chimney height.

7.4.8 All the positions on the chimney where the flue gas may dew shall be adopted with

measures to prevent the flowing and accumulating of acid liquor.

7.4.9 The corrosion reaction of flue gas at chimney top from the cover shall be taken into

consideration.

If short chimneys exist nearby, the corrosive influence of the fume emission from short

chimney on the external surface of tall chimney shall be noticed.

Page 82: DL 5022-1993

77

7.5 Chimney structure

7.5.1 When the tunnel wall adopts bifacial reinforcements, the circumferential reinforcements

at internal and external layers shall be separately bonded with the longitudinal reinforcements

at internal and external rows into internal and external mat reinforcement, the circumferential

reinforcements should be around outside the longitudinal reinforcements. When the diameter

of the longitudinal reinforcements at internal and external rows is larger than 18mm, the

internal and external mat reinforcements shall be connected with transverse lacing wires.

Generally, the diameter of lacing wire is not less than 6mm, they shall be of staggered

arrangement with vertical and horizontal space at 500~600mm, and be knotted with

longitudinal reinforcements at it two ends.

7.5.2 As for the chimneys constructed in the regions with fortification intensity at or above 7

grades, the longitudinal reinforcements shall be connected by welding. The longitudinal

reinforcements of other chimneys may be welded or overlapped when the diameter is not

larger than 18mm, and shall adopt soldered joint when the diameter is larger than 18mm.

7.5.3 The tube body is corbelled out with the corbel that is used for supporting the inner lining,

and should be poured together with the tube concrete at one time.

7.5.4 The chimney surface shall be coated with aerial signal coloration, the painting initial

elevation may be higher than the roof by 10~20m, and a larger number of chimneys in the

plant shall be painted with same initial elevation with same type.

7.5.5 When setting with two or more than two flue openings, the chimney should be set with

fume-cutting wall in it, and the wall height shall be 0.50~0.75 times of the open height of

flue.

7.5.6 The dust collecting platform should be set at the bottom of flue opening, and the dust

load of the platform see Table 7.6.7.

7.5.7 The access ladder, signal platform, hand rail, connection board, downlead, and bolts of

the chimney shall be galvanized or be adopted with the atmospheric corrosion protection steel

products. The needle tube of lightning arrester (or ring lightning protection strip) shall be

stainless.

7.6 Flue

7.6.1 The flue may adopt sidewall of reinforced concrete frame structure as the brick filler

wall or may also adopt reinforced concrete box structure. When the single-machine capacity

is at or above 300MW, the steel flue should be adopted.

Requirements on flue structure are small structural vibration with flue gas action, smooth

air current moderate flue gas resistance, good airtightness, anticorrosive and few accumulated

dust.

7.6.2 The civil work and technological specialities shall be closely cooperated to jointly get

done with the arrangement of flue and the selection for the sectional dimension of flue:

7.6.2.1 Each suction fan should be set with independent flue, and should not adopt bus flue.

7.6.2.2 The variation in the crosssection of flue shall be moderate to avoid the sharp turning

of gas flow and the rapid change in the flue gas flow velocity and prevent flue gas from

Page 83: DL 5022-1993

78

producing eddy zone.

7.6.2.3 The rational flue gas flow velocity should be larger than 8m/s when adopting the dry

dust separator and should be larger than 12m/s when adopting wet dust catcher.

7.6.2.4 Generally, the space between temperature expansion joints of should not be larger than

25m.

7.6.3 In the design of flue, it shall consider that the flue gas pressure shall not be less than

±0.5kN/m2.

7.6.4 The flue shall be with insulation measures to make the temperature difference inside and

outside the flue structure be limited at certain scope:

Brickwork of masonry flue——The internal and external temperature difference shall

not exceed 40℃ (1.5 times of the thickness of brick) or 60℃ (thickness of one brick).

Reinforced concrete top plate or bottom plate of reinforced concrete flue and brick

flue——Internal and external temperature of plate shall not exceed 40℃.

7.6.5 The partial heated temperature of the concrete structure of flue shall not exceed 100℃.

7.6.6 The flue shall be set with inner lining that is featured of such performances as high

temperature resistance, acid resistance, abrasion proof and protection of thermal-protective

coating.

7.6.7 The dust load at the bottom plate of flue see Table 7.6.7. Table 7.6.7 Dust Load on the Dust Collecting Platform of Chimney and Bottom Plate of Flue

Single-machine capacity (MW) ≥200 ≤125

Dedusting mode Dry type Wet type Dry type Wet type

Bottom plate of flue 10 15 15 20 Load

kN/m2 Dust collecting

platform plate of

chimney

25 30 30 35

Note: When the dust collecting platform is set with flue gas guiding slope structure, the dust load may be appropriately

decreased according to the table above.

7.6.8 The wall structure of flue shall take the side pressure produced by the collected dust on

bottom plate into consideration. When calculating this side pressure, as for the straight wall,

1~2 m from the thickness of dust layer may be taken; a for the arc-like wall and diagonal wall,

2~4m from the thickness of dust layer may be taken

7.6.9 The corrosion resistance requirement of flue may be referred to the Section 7.4.

8 Pipe support

8.0.1 According to the function, stressing and structural style, the pipe support is classified

into fixed pipe support, guiding pipe support, and slide pipe support. See Figure 8.0.1 for the

arrangement schematic diagram of pipe support.

Page 84: DL 5022-1993

79

Figure 8.0.1 Schematic Diagram for Arrangement of Pipe Support

Fixed pipe support: The pipe support may be treated as the fixed supporting point of

pipeline both in the longitudinal direction (along pipeline direction) and in the transverse

direction (perpendicular to pipeline direction), the fixed pipe support hereby shall be with

adequate rigidity to assure the stableness of piping system.

Slide pipe support: The pipeline passes through pipe carrier in longitudinal direction and

transverse direction and may slide or roll on column or crossbeam, and generally has small

stressing.

Guiding pipe support: The pipeline is same as the slide pipe supporting longitudinal

direction and may be restricted for its transverse deflection in transverse direction.

8.0.2 The slide and guiding pipe supports may be designed into the rigid, flexible and semi-

articulated pipe supports.

The pipelines on rigid pipe support and flexible pipe support all may be adopted with the

slide or rolling pipe carrier. The connection of lower end of column and the foundation shall

be semi-articulated along the longitudinal direction and be fixed along the transverse

direction.

8.0.2.1 The rigidity of rigid pipe supporting longitudinal direction is large, the displacement is

small, and the friction force acting on pipe support shall comply with the following equation,

the horizontal force of pipe support shall be calculated as Fm.

323

H

EIuF

FF

f

fm

(8.0.2-1)

Where Fm——Friction force of pipeline, which is supplied by technology;

fF ——Rebounding force of the displacement of pipe support;

zu ——Deformation value of drive pipe, which is supplied by technology;

EI——Support rigidity, in which E is elastic modulus, I is inertia moment, and the

support rigidity shall be 0.85EI for reinforced concrete column;

H——Support height (distance from the bottom of the pipe carrier of drive pipe to the

top surface of foundation).

Page 85: DL 5022-1993

80

The rigid pipe support is applicable to the pipe support of the pipelines with small weight,

large deformation and small height.

8.0.2.2 The rigidity of flexible pipe supporting longitudinal direction is small, the

displacement of pipe support is able to meet requirement on deformation of drive pipe, the

following equation shall be complied with, and the horizontal force of the pipe support shall

be calculated as fF .

fm FF ≥ (8.0.2-2)

The flexible tube support is applicable to the pipe support of the pipelines with large

weight, small deformation and large height.

8.0.2.3 Semi-articulated pipe support: The socle of semi-articulated pipe support shall adopt

incomplete articulation structure along the longitudinal direction, the displacement of pipe

support and the deformation of drive pipe are same, the gradient of displaced pipe support

shall comply with the following equation, and the rebounding of the displacement of pipe

support is ignored.

0.02≤ H

uz (8.0.2-3)

The semi-articulated pipe support is applicable to the pipe support of the pipelines with

large weight and the drive pipes with deformation complying with the gradient requirement of

pipe support.

8.0.3 According to the difference in functions of pipelines on pipe supports, the pipelines on

pipe supports are classified into drive pipe non-drive pipe. The pipeline has controlling action

on the operating condition of pipe support is named as drive pipe; other pipelines are named

as non-drive pipe. The drive pipe shall be arranged near to the center of pipe support, and the

conditions for selecting drive pipe are as follows:

8.0.3.1 Rigid pipe support: The pipeline with largest weight among pipeline shall be taken as

the drive pipe.

8.0.3.2 Flexible pipe support: The pipelines with weight ratio a not less than 0.7 among the

pipelines shall be taken as the drive pipe.

n

i

z

G

Ga

1

(8.0.3-1)

Where iG ——Weight of pipeline;

n——Quantity of pipelines;

zG ——Gravity load of drive pipe, several pipelines of normal temperature may be

regarded as one drive pipe when calculating the zG .

When a is less than 0.7, the pipeline with lesser deformation value zu shall be taken as

the drive pipe. Articulated pipe carrier shall be adopted with the technological approval. By

Page 86: DL 5022-1993

81

this time, the displacement value u of this pipe supportis equal to the deformation value zu

of this pipeline.

Semi-articulated pipe support: The pipeline with larger weight and with its deformation

value zu meeting the Equation (8.0.2-3) shall be adopted, and the technological approval

shall be obtained.

8.0.4 Load and load effect combination

Permanent load:

The dead load of the pipeline, inner lining, insulating layer and accessories of pipeline,

the deadweight of media in pipeline, the deadweight of pipe support and foundation, and the

load of reserved pipeline.

Variable load:

The transverse horizontal force, wind loads and sleet loads produced by the variation in

pipeline temperature.

The load effect combination shall comply with the "Specifications on the Load of

Building Structure", in which the partial factor of permanent load is:

1.20 When its effect is unfavorable for the structure;

1.00 When its effect is beneficial to the structure;

The partial factor of variable load is 1.40;

The combination factor of load is 0.85.

The calculation of wind loads see Annex F.

8.0.5 Calculation of bearing capacity:

8.0.5.1 The pipe support structure shall have the calculation on internal force according to the

elastic system.

8.0.5.2 The pipe support column shall have the strength calculation according to the

two-direction eccentric compression member. With torque function, the pipe support may

only adopt the structure measure, but the T-pipe support column shall have calculation on

torsion resistant if necessary. The precast element shall have the recalculation on

transportation and hoisting if necessary.

8.0.5.3 With the action of vertical and horizontal loads, the crossbeam of pipe support shall be

calculated according to the two-direction bending member; when the bending moment yM

under vertical load action and the bending moment xM under action of horizontal load

comply with that yM is not less than 0.1 xM , the crossbeam may be calculated as

one-direction bending member.

8.0.6 The computational length of the column of pipe support shall comply with the Table

8.0.6-1 and Table 8.0.6-2.

Table 8.0.6-1 Computational Altitude of the Column of Pipe Support 0H

Structural 1 2 3 4

Page 87: DL 5022-1993

82

diagram

In

longitudinal

direction

along

pipelineH0

According to

Table 8.0.6-2

1.50H of column at

upper most layer

1.25H of column at

other layers

1.25H 1.00H

In

longitudinal

direction

along

pipelineH0

2.00H

1.50H of column at

upper most layer

1.25H of column at

other layers

1.25H 1.00H

Note: The calculated altitude value in Diagram 2 is only applicable to the conditions that the linear stiffness ratio of beam

and column is not less than 2.

Table 8.0.6-2 Computational Length of Column when it is Single Column in Longitudinal Direction along

Pipeline 0H

Types of pipe support

Computational altitude Fixed pipe support Rigid pipe support Flexible pipe support

Semi-articulated pipe

support

0H 2.00H 1.50H 1.25 H 1.00 H

Note: The value of column length H:

As for the fixed pipe support and rigid pipe support, it is the distance from the top surface of column to the top surface of

foundation. As for other types of pipe supports, it is the distance from the bottom of the pipe carrier of drive pipe to the top

surface of foundation. When the drive pipe is placed on the beam at lower layer, the column at top layer shall

be sHH 00.20 , (Hs is the distance from the bottom of the pipe carrier of drive pipe to the top surface of column).

8.0.7 Allowable length-diameter ratio of the column of pipe support

300 b

H (8.0.7)

Where 0H ——Computational length of column;

b——The dimension of column section corresponding to the 0H direction.

8.0.8 Structural requirements of pipe support:

The crossbeam width is not less than 150mm and the crossbeam height is not less than

200mm. The depth of beam at cantilever end is not less than 150mm.

The minimal edge of column is not less than 200mm.

8.0.9 The groundwork and foundation of pipe support shall be designed according to the

Page 88: DL 5022-1993

83

related chapters in the "Code for Design of Building Foundation" and shall also comply with

the following requirements:

When being with two-direction eccentric compression:

Foundation of fixed pipe support:

5

1≤

B

eand

A

e yx (8.0.9-1)

Foundations of other pipe supports:

4

1≤

B

eand

A

e yx (8.0.9-2)

When being with uniaxial eccentric compression:

4

1≤

B

eor

A

e yx (8.0.9-3)

Where A and B——Dimension of foundation at bottom margin;

xe and ye ——Excentricity, its value is as follows:

F

Me x

x

F

Me y

x

Where xM and yM ——Design values of bending moment at foundation base along

X-direction and Y-direction;

F——Design value of the vertical force at foundation base.

8.0.10 When the design adopts semi-articulated pipe support, it shall be indicated in the

constructional drawing. In the assembly process, the falsework shall be set and shall not be

demounted until all the pipelines have been installed.

See Figure 8.0.10 for the structure of the socle of semi-articulated pipe support, and the

diameter of the anchor bar of socle may be calculated according to the following equation:

sf

FsMd

ta785.0

5.00

(8.0.10)

Where d0——Thread root diameter of anchor bolt, which is not less than 20mm;

M——Design value of the bending moment that acts on the top surface of

foundation;

F——Design value of the minimal vertical force that acts on the top surface of

foundation at operating condition;

s——Centre distance of anchor bolts;

taf ——Design value of tensile strength of anchor bolts.

Equation (8.0.10) is applicable to the semi-articulation mode showed in Figure

Page 89: DL 5022-1993

84

8.0.10 and it may be free of this limit if other semi-articulated structures are adopted with

practical experience.

Figure 8.0.10 Socle of Semi-articulated Pipe Support

(a) Dual column (b) Single column

9 Aseismic design

9.1 General provisions

9.1.1 The aseismic design of buildings shall implement the state's guideline that prevention

first in seismic operation. Sum up the experience on all previous earthquake disasters,

treatment in accordance with local conditions, positively adopt the aseismatic measures with

reliable technology and rational economy.

9.1.2 This chapter is applicable to the newly-built or extended power plant buildings with

fortification intensity among degree 6 and 9. Note: Generally, this stipulation skips such words as "fortification intensity", as the "fortification intensity" is degree 6 is

named as "degree 6" for short.

9.1.3 The fortification intensity of power plant buildings shall be determined according to the

documents (drawings) examined, approved and awarded according to the state's due authority,

and generally, the basic intensity may be adopted. And it shall be adjusted and determined

according to the following principles.

9.1.3.1 The regions with antiseismic disaster prevention planning may carry out the

earthquake protection according to the approved earthquake protection zoning (fortification

intensity or design earthquake motion parameter).

9.1.3.2 The earthquake effect shall be calculated according to the local fortification intensity

Page 90: DL 5022-1993

85

(excluding the power plant in the region of degree 6 specified by the state shall be fortified by

one more degree).

9.1.3.3 The main manufacturing buildings in the important power plants with planning and

design capacity of 800MW or single-machine capacity at or above 300MW, as well as the

power supply buildings in the lifeline projects of key antiseismic cities shall be of the

first-grade buildings (which are equivalent to second-grade buildings specified in "Code for

Seismic Design of Building").

9.1.3.4 Except those specified in the Sub-section 9.1.3.3 of this section, the main

manufacturing buildings and buildings in continuous production run in general power plants

as well as the public buildings and important material storages shall be of the second-grade

buildings (which is equivalent to the third-grade buildings specified in "Code for Seismic

Design of Building").

The auxiliary buildings shall be of the third-grade buildings (which are equivalent to the

buildings of Grade D specified in "Code for Seismic Design of Building").

The buildings that have no influence on manufacturing, cause no greater loss and are

easy to be repaired may not be fortified.

9.1.4 The fortification intensity of the aseismatic measures of each building in power plant

may be adjusted according to Table 9.1.4.

Page 91: DL 5022-1993

86

Table 9.1.4 Adjustment Table for Fortification Intensity of the Aseismatic Measures of Buildings in Power

Plant

Important power plant General power plant

Local fortification intensity Local fortification intensity

9 8 7 6

Building name

(I) Main manufacturing building

6 7 8 9

9 9 8 7 Main workshop building 6 7 8 9

9 9 8 7 Electrical integral building 6 7 8 9

9 9 8 7 Boiler cradle (reinforced concrete) 6 7 8 9

9 8 7 6 Blower fan room 6 7 8 9

9 8 7 6 Deashing structures 6 7 8 9

9 8 7 6 Dedusting structures 6 7 8 9

9 9 8 7 Chimney 6 7 8 9

9 9 8 7 Flue 6 7 8 9

9 8 7 6 Indoor coal discharging device 6 7 8 9

9 9 8 7 Coalbreaker chamber and transfer site 6 7 8 9

9 9 8 7 Coal transporting trestle 6 7 8 9

9 8 7 6 Coal transporting tunnel 6 7 8 9

9 8 7 6 Defrosting room 6 7 8 9

9 8 7 6 Integral coal transporting building 6 7 8 9

9 8 7 6 Electronic rail-weighbridge building 6 7 8 9

9 8 7 6 Reinforced concrete silo 6 7 8 9

9 8 7 6 Largespan 6 7 8 9

9 8 7 6 Coal shed

General 6 6 7 8

9 8 7 6 Coal discharging platform in coal depot 6 6 7 8

9 8 7 6 Fuel pump room and fuel store 6 7 8 9

9 9 8 7 Network control building and communication building 6 7 8 9

9 8 7 6 Boiler room for start 6 7 8 9

9 8 7 6 Heavy oil storage and petroleum pump room 6 7 8 9

9 9 8 7 Indoor power distribution unit building 6 7 8 9

9 8 7 6 Outdoor type switchgear rack and support 6 7 8 9

9 8 7 6 Mortar pump room and ash-handling pump room 6 7 8 9

9 8 7 6 Ash settling tank 6 6 7 8

9 8 7 6 Negative-pressure pneumatic deashing structures 6 7 8 9

9 8 7 6 Reverse osmosis apparatus room 6 7 8 9

9 8 7 6 Chemical water treatment room 6 7 8 9

9 8 7 6 Heating buildings (structures) 6 7 8 9

Page 92: DL 5022-1993

87

Continued

Important power plant General power plant

Local fortification intensity Local fortification intensity

9 8 7 6

Building name

(I) Main manufacturing building

6 7 8 9

9 8 7 6 Internal and external trenches of plant 6 6 7 8

9 8 7 6 Internal and external tunnels of plant 6 7 8 9

9 8 7 6 Steel flue support 6 7 8 9

9 8 7 6 Dewatering bin 6 7 8 9

9 8 7 6 Electro dedusting switchboard room 6 7 8 9

Important power plant General power plant

Local fortification intensity Local fortification intensity

9 8 7 6

Building name

(II) Auxiliary production workshop and

structures 6 7 8 9

9 8 7 6 Oil purification room 6 6 7 8

9 8 7 6 Open-air oil storage 6 6 7 8

9 8 7 6 Acetylene station 6 7 8 9

9 8 7 6 Hydrogen production station 6 7 8 9

9 8 7 6 Mechanical workshop 6 7 8 9

9 8 7 6 Separate machine and boiler overhaul room 6 7 8 9

9 8 7 6 Precise material storage or

dangerous cargo warehouse 6 7 8 9

8 7 6 6

Material

storage General material storage 6 6 7 8

9 8 7 6 Compressor plant 6 7 8 9

9 8 7 6 Pipe support 6 7 8 9

9 8 7 6 Lightning arrester 6 7 8 9

Important power plant General power plant

Local fortification intensity Local fortification intensity

9 8 7 6

Building name

(III) Appurtenant structures 6 7 8 9

9 8 7 6 Engine room 6 6 7 8

9 8 7 6 Coal transporter warehouse 6 6 7 8

9 8 7 6 Motor depot 6 7 8 9

9 8 7 6 Fire engine house and fire station 6 7 8 9

9 8 7 6 Office building 6 7 8 9

9 8 7 6 Canteen 6 7 8 9

9 8 7 6 Overbridge 6 7 8 9

9 8 7 6 Duty and refreshment building 6 7 8 9

9 8 7 6 Gate chamber 6 7 8 9

6 6 6 6 Enclosing wall at plant site 6 6 6 6

6 6 6 6 Bicycle shed 6 6 6 6

6 6 6 6 Toilet at plant site 6 6 6 6

Notes: 1. The division between important power plant and general power plant is determined according to the "Code for

Page 93: DL 5022-1993

88

Seismic Design of Electric Power Installations".

2. Those improved with fortification intensity in the table are all equivalent to the second-grade buildings specified

in "Code for Seismic Design of Building", their aseismatic measures shall be fortified by adjusting the intensity

according to the table, and the anti-seismic construction measures may not be improved when the building site is

of I type site;

3. In the table the buildings that has adopt antiseismic measures by reducing one degree shall not reduce the

fortification intensity for other reasons, and those that has not reduced the fortification intensity may adopt

anti-seismic construction measures by reducing one degree according to the original fortification intensity, but the

fortification intensity shall not be less than degree 6.

4. In the table, the buildings not improving the fortification intensity are equivalent to the third-grade buildings

specified in "Code for Seismic Design of Building". The buildings with fortification intensity reduced by one

degree are equivalent to the buildings of Class D as specified in "Code for Seismic Design of Building".

9.1.5 The antiseismic grade of the frame structure of power plant buildings shall be divided

according to Table 9.1.5 in accordance with the fortification intensity, structure type and

height of the earthquake resisting wall in framework. Table 9.1.5 Antiseismic Grade of Frame Structure

Main workshop

Frame structure

Main workshop

Framework-earthquake

resisting wall structure

Main control

building

Power distribution

unit building

Coal

transpor

ting

trestle

Pipe

support

Rating

Height

(m)

Ratin

g

Height

(m) Framewo

rk

Earthqua

ke

resisting

wall

Rating Rating Rating

≤25 4 ≤50 4 3 6

>25 3 >50 3 3 3 3 3

≤35 3 ≤60 3 2 7

>35 2 >60 2 2 2 3 3

≤35 2 <50 3 2 8

>35 1 50~80 2 2 2 2 2

≤25 2 1 9 (Note 2)

>25 1 1 1 1 1

Notes: 1. The outside column of main workshop shall comply with the relevant provisions on monolayer industrial factory

buildings specified in the Chapter 8 of "Code for Seismic Design of Building";

2. When the fortification intensity is 9, the structure of main workshop framework shall not be adopted until after

justifying the reliability of its seismic performance according to the structure conditions, and the antiseismic

grade is Grade 1.

3. When the antiseismic grade is Grade 1, the building still needs to be fortified by improving one grade, the

antiseismic grade shall be still Grade 1.

4. The height listed in the table refers to the height from the outdoor ground to the cornice;

5. This table is applicable to the casted-in-site or assembly compound reinforced concrete structures;

6. The column of framework-earthquake resisting wall structure is applicable to the framework-antiseismic support

Tpyes

Antiseismic

gradeFortification

intensity

Page 94: DL 5022-1993

89

structures;

7. The fortification intensity listed in the table refers to fortification intensity adjusted according to the importance

of buildings;

8. When the main workshop framework has aseismic design on the joint of framework and the crosssection of

elements according to those specified in the second section of Chapter 6 in "Code for Seismic Design of

Building", the antiseismic grade of framework may be adopted according to the un-adjusted antiseismic

protection grade.

9.1.6 When the antiseismic grade of framework is Grade 1, the reinforced in- situ concrete

framework shall be adopted.

9.2 Subgrade and foundation

9.2.1 In the regions of degree 8 and 9, the standard value for the static bearing capacity of

active zone of foundation are separately less than 100 and 110kPa. The weak soil layer with

average shearing wave velocity less than 140m/s shall be adopted with appropriate aseismatic

measures according to the importance of buildings.

9.2.1.1 The main workshop, chimney, main control building, coal transporting in the

first-grade buildings should be adopted with measures such as pile foundation, deep

foundation, as well as excavating the weal soil layer to decreasing the differential settlement

that may be caused by earthquake.

9.2.1.2 The second-grade buildings with small load may partially eliminate the settlement that

may caused by earthquake, as excavating part of the weal soil layer when the reinforcement

condition is unavailable, the following measures may be adopted:

(1) Reducing the static bearing capacity of subgrade.

(2) Reducing the load of foundation and adjusting the basal area of foundation.

(3) Strengthening the integrity and rigidity of foundation.

(4) The superstructure should not adopt the structural shape that is sensitive to the

differential settlement.

(5) When reinforcing the foundation by adopting such methods as displacement of soil,

tamping and compacting, the reinforcement depth and width shall meet the requirement on

the bearing capacity and deformation of subgrade.

9.2.2 Generally, the first and second-grade buildings shall avoid adopting the untreated

liquefiable soil layer as the supporting course of natural foundation. The judgment and

treatment of liquefiable foundation soil shall comply with the relevant provisions specified in

"Code for Seismic Design of Building".

9.2.3 According to the types and fortification intensity of buildings, the antiseismic types of

pile foundations should be determined according to Table 9.2.3. Table 9.2.3 Types of the Seismic Performances of Pile Foundation

Types of buildings

Fortification intensity 1 2 3

Page 95: DL 5022-1993

90

6 and 7

8

9

C

B

A

C

B

A

C

C

B

9.2.3.1 Piles of Class C: They shall meet the structure requirements on general pile

foundations.

9.2.3.2 Piles of Class B: They shall meet all the requirements on piles of Class C, and should

meet the following structure requirements: the pile top shall enter into the grind slab for no

less than 100mm, the hook of hooped reinforcement at pile body is not less than 135°, the

diameter of the hooped reinforcement within 1.20m up and down the soft and hard soil

interface that is at 1/3 of the upper pile body and in scope no less than 5m and the hooped

reinforcement at the pile top are same, their space should be 100mm.

The requirements on each kind of pile reinforcements are as follows:

(1) Filling pile. The length of the steel reinforcement placed at top should not be less than

10 times of the pile diameter. When at soft ground subgrade and collapsible loess subgrade

with complicated stratigraphic fluctuation, the reinforcement at pile body should be extended

to the pile toe. The reinforcement ratio should not be less than 0.4%~0.65%, the small pile

shall be taken with the larger value and the pile with diameter of or above 800mm shall be

taken with the smaller value. Within 1000mm at the upper part of pile body, the space

between hooped reinforcements should be 100mm and the spiral hoop should be adopted.

(2) Precast pile. The critical steel ratio of longitudinal reinforcement is 1%, the diameter

of the hooped reinforcement at pile body within 1.6m at joint of pile top and grind slab shall

not be less than 6mm, and the space shall be 100mm. When the piles need to be extended, the

steel plate welding wheel dresser should be adopted.

(3) Steel-pipe pile. When it is uplift pile, the reinforcement bar amount at pile top should

not be less than the withdrawal resistance of this pile. The minimal reinforcement bar amount

of uplift pile and anchored pile all should not be less than 1% of the concrete cross-sectional

area, and shall meet the uplift requirement.

9.2.3.3 The piles of Class A shall comply with all the requirements on piles of Class B and

shall comply with the following requirements:

(1) Filling pile. The maximal space between hooped reinforcements within 1.2m at upper

part of pile body shall be 80mm and shall not be larger than 8d (d is the diameter of

longitudinal reinforcement). When the pile diameter is less than 500mm, those with diameter

of 8mm shall be adopted; those with diameter of 10mm shall be adopted for other pile

diameters.

(2) Precast pile. The critical steel ratio of longitudinal reinforcement is 1.2%, the

diameter of the hooped reinforcement at pile body within 1.6m at joint of pile top and grind

slab shall not be less than 8mm, and the space shall be 100mm.

(3) Steel-pipe pile. The steel-pipe pile and grind slab are connected; the tensile force

value is equal to 1/10 of the compression resistant capability according to the stretch design.

9.2.4 As for the pile of buildings with earthquake protection, according to tensile

reinforcement requirement, the amount of piles with the main reinforcement at pile body

anchored into the grind slab should comply with the following requirements:

9.2.4.1 When it is of degree 6 and 7, the piles at periphery of grind slab should not be

anchored with at least one row.

Page 96: DL 5022-1993

91

9.2.4.2 When it is of degree 8, all the piles within scope of grind slab should be anchored. As

for the steam turbine generator pedestal, boiler foundation and chimney foundation with a

large number of piles, at least two rows of piles shall be anchored at periphery of grind slab.

9.2.4.3 When it is of degree 9, all the piles within scope of grind slab shall be anchored.

9.2.4.4 All the piles shall be anchored when the up-pulling force is produced by earthquake

effect.

9.2.4.5 As for the buildings that need to be adopted with aseismatic measures by improving

one degree, the amount of anchored piles shall be considered according to original

fortification intensity.

9.3 Earthquake effect and antiseismic recalculation of structure

9.3.1 Generally, only the horizontal earthquake effect needs to be considered, and may be

separately recalculated at the two main shaft directions of the buildings.

In the following conditions, the building may not have the antiseismic recalculation of

structure:

9.3.1.1 When the sites of degree 6, 7 and 8 are of sites of types I and II, the height shall not

exceed 60m, and the silo body shall be the masonry stack set with steel reinforcement

according to those specified in "Code for Seismic Design of Building".

9.3.1.2 When sites of degree 6 and 7 are those of class I and II, the transverse part at the coal

transporting trestle of reinforced concrete and steel load carrying structures.

9.3.1.3 When sites of degree 6 and 7 are those of class I and II, the column height does not

exceed 10m, the reinforced concrete monolayer buildings with constant height at each span.

9.3.1.4 When sites of degree 6, 7 and 8 are those of class I, the subsurface constructions such

as buried channel, tunnel, ash settling tank and slot-type coal chute.

9.3.2 As for the chimneys of degree 8 and 9, the structures with wide span (the roof truss,

bracket, trestle and overbridge with span larger than 24m) and long cantalever shall be

considered according to worst situation that the horizontal earthquake effect and vertical

earthquake effect act on the structure simultaneously.

9.3.3 Calculation method of horizontal earthquake effect:

9.3.3.1 The base shearing method may be adopted for the structures with height not exceeding

40m, mainly with shearing deformation and even distribution of mass and rigidity along

height, as well as the architectures approximate to single material particle.

9.3.3.2 Except the building structures specified in the first sub-section, the main workshop

and multistory frame without considering the twisting effect of horizontal earthquake, and the

trestlework and chimney of high and low span should adopt modal decomposition response

spectrum method.

9.3.3.3 When it is degree 8, the main workshop with single-machine capacity of 600MW and

the chimney with height larger than 240m shall not only have the calculation on the horizontal

earthquake effect, but also shall have verification on the weak positions of the structure with

time interval analysis method.

9.3.4 When calculating the earthquake effect, the representative value of the gravity load of

building shall be the sum of the standard value for the gravity load of structure, equipment

and element and the variable combination value of loads. The combination value coefficient

Page 97: DL 5022-1993

92

of each variable load shall be adopted according to Table 9.3.4. Table 9.3.4 Combination Value Coefficient

Load types Combination value

coefficient

Load of general equipments (such as pipeline and equipment supporter)

Mobile load at roof of turbine room

Coal in coal scuttle and the deoxidizer (including gravity load and water weight)

When the main workshop framework is calculated according to the floor mobile load (including the

roof of deoxidation bunker bay) used for calculating the mainframe

Long-term horizontal load (such as tensile force of conductor)

Long-term dynamic load

1.0

Ignored

0.8

0.7

1.0

0.25

Note: The structure mainly bearing wind loads shall be considered for function of wind loads according to "Code for

Seismic Design of Building".

9.3.5 The horizontal earthquake effect on monitor frame and its vertical bracing extruding out

the roof, the detached buildings (control center and switchboard room) in main structure or on

firing floor should be multiplied by the augmenting factor 1.5.

As for the booth and parapet extruding the roof of the top floor of building, their

horizontal earthquake effect should be multiplied by the augmenting factor 3. Note: The partial increased influence on infrastructure shall not be considered.

9.3.6 When the connection points (including anchoring of attachment weld and anchor bar

and the shear resistance, compression and anchoring construction bolts) having antiseismic

recalculation, the earthquake effect should be multiplied by the strengthening coefficient 1.5

(welded connection) or 1.2 (bolted connection).

When the main workshop is of frame-bent structure in transverse direction, the

calculation on the horizontal earthquake effect at head end of roof truss and at fastening piece

of pedestal should take the earthquake effect on the link rod of the column top in this span be

multiplied by the earthquake augmenting factor 2. When recalculating the shearing strength at

the welding seams and bolts at the connection point of roof truss and pillar, the earthquake

effect at each end should be:

9.3.6.1 As for welding, it should be the earthquake effect at link rod of this column top in this

span being multiplied by the augmenting factor 2, and then being multiplied by the

strengthening coefficient 1.5.

9.3.6.2 As for bolted connection, it should be the earthquake effect at link rod of this column

top in this span being multiplied by the augmenting factor 2, and then being multiplied by the

strengthening coefficient 1.2.

9.4 Main workshop

9.4.1 When the horizontal structure of main workshop having shock strength recalculation,

frame-bent structure earthquake resistance may be composed of outside column of turbine

room and framework, and representative framework shall be chosen according to the load or

structural diagram for the internal force analysis.

9.4.2 When the transverse major structure of main workshop having shock strength

recalculation, the following terms of simplification may be made, see Figure 9.4.2-1.

Page 98: DL 5022-1993

93

Figure 9.4.2-1 Distribution of the Material Particles of Structure

9.4.2.1 The rigidity of non-antiseismic wall shall not be considered, and only its weight shall

be taken into account.

9.4.2.2 The influence of foundation deformation shall not be taken into consideration.

9.4.2.3 The mass of the outside column of turbine room system may be centered on the center

of cantalever at firing floor, the bottom of crane beam and the elevation part of column top,

and the mass of the frame system may be centered on the center of the beams at each floor,

the bottom of crane beam and the elevation part of the supporting point of roof truss.

The mass of the lateral column system of boiler room may be separately centered on

some points from the center elevation of firing floor beams to the column top.

The mass of the vertical structural systems may be centered on the center elevation of

each longitudinal beam and the elevation part at column top.

9.4.2.4 When simply calculating the fundamental period of framework, the mass and rigidity

of the lateral column may be neglected, but the roof mass shall be wholly considered yet

(Figure 9.4.2-2).

Figure 9.4.2-2 Frame Structure Diagram

9.4.2.5 When it is 9 degree, the framework set with coal scuttle should be considered with the

influence of additional bending moment.

9.4.2.6 The axial load ratio of main workshop framework column shall not exceed the

following limitation: 0.8 of the first grade, 0.85 of the second grade and 0.9 of the third grade,

Page 99: DL 5022-1993

94

9.4.3 The longitudinal constructions such as outside column of turbine room, lateral column

of boiler room and colonnade of the framework of deoxidation bunker bay may be have the

recalculation on aseismic strength according to the single-row colonnade in the simplified

calculation.

9.4.4 The framework-earthquake resisting wall (support) system in longitudinal constructions

should be considered with the team work and shall comply with the relevant clauses specified

in "Code for Seismic Design of Building".

If adopting simplified calculation, it may be according to that the earthquake resisting

wall and antiseismic support bear 100% of the earthquake effect. The framework shall bear

20% of the corresponding earthquake effect in addition. The percentage may be reduced

appropriately when the quantity of colonnades is small, but should not be less than 10%.

The bending moment of the earthquake effect at top floor of longitudinal framework

shall not be less than the seismic bending moment at nay beam, the longitudinal beam shall be

considered with the transferring the horizontal earthquake effect and the framework column

shall be considered with the vertical internal force produced by the horizontal earthquake

effect.

9.4.5 When each colonnade is taken as one antiseismic calculating unit, the gravity load bear

by each longitudinal construction of main workshop all shall be distributed to each colonnade

according to the lever principle.

9.4.6 The width of earthquake-proof joint shall comply with the relevant provisions specified

in "Code for Seismic Design of Building", and the settlement joint and temperature expansion

joint shall comply with the requirements on earthquake-proof joint.

The earthquake-proof joint shall ensure the freed displacement vertically and

horizontally among adjacent buildings. As for the platform at firing floor of boiler and the

coal transporting trestle, when it is degree 7 and 8, the earthquake-proof joint may not be set

along the transverse direction of element for transferring the earthquake effect.

9.4.7 The longitudinal construction of main workshop may be adopted with different

aseismatic measures according to the size of fortification intensity, and may be adopted

according to Table 9.4.7. Table 9.4.7 Aseismatic Measures for Longitudinal Construction of Main Workshop

Fortification intensity Types of aseismatic measures

6 Reinforced concrete frame structure

7, 8 Reinforced concrete framework or framework-earthquake resisting wall (antiseismic support)

9 Reinforced concrete framework-earthquake resisting wall (antiseismic support)

9.4.8 The antiseismic support among the lateral columns of main workshop shall comply with

the following requirements:

9.4.8.1 The support of lateral column colonnade shall be determined according to calculation.

The support should be set at the center of stretching section in workshop. When the crane is

available, the column support (above crane beam) shall be set at the both ends in addition.

9.4.8.2 The position of the lower node of lower column support shall assure to be able to

directly transfer the earthquake effect onto the foundation.

9.4.8.3 The length-diameter ratio of the members of intercolumnar bridging should not be

larger than 150.

9.4.8.4 As for the intercrossing antiseismic supports among columns, when the

Page 100: DL 5022-1993

95

length-to-diameter ratio of members is not less than 40 and not larger than 150, the

crosssection of the supporting diagonal rod may be recalculated according to tensile force, but

the unloading influence of pressure bar shall be taken into consideration, the crosssection may

be calculated according to Annex 6 of the "Code for Seismic Design of Building".

9.4.9 The thickness of the longitudinal earthquake resisting wall of mainframe should be

1/30~1/40 of the middle ordinate of columns and shall not be less than 140mm. The

two-direction bifacial reinforcements should be adopted, the total reinforcement ratio at each

direction shall not be less than 0.25%, the diameter of reinforcement shall not be less than

12mm and their corresponding space is 200.

9.4.10 The earthquake resisting wall should be set starting from the foundation base, the wall

body should not be punched, and the hole opening, if it is required to be punched, should not

be larger than 1/6 of the plane area of this layer of wall, and the hole opening should not be

set inclindedly. If it requires inclinded hole opening, the distance from the hole edge to

column edge should not be less than 1/6 of the clear span of wallboard. The bearing capacity

at hole opening shall be determined through calculation. Additional bars shall be set at both

sides and upper part and lower part of the hole opening. The quantity of additional bar may be

1.3 times of the total area of cut steel reinforcement at opening. Slant additional bars must be

set at four corners of the opening at 45°direction, and the steel reinforcement at each nook

should be placed not be less than 500mm2 per 100mm according to the wall thickness.

9.4.11 The precast floor cover of framework shall be set with casted-in-site surface layer

according to the following provisions.

9.4.11.1 When the antiseismic grade is the third or fourth grade and the spacing of columns is

larger than 6m, it shall be set every other layer.

9.4.11.2 When antiseismic grade is the second grade, it shall be set at each layer.

9.4.11.3 The thickness of the casted-in-site surface layer of floor cover should not be less than

50mm, and the mat reinforcement with diameter of 6mm and space of 200mm shall be

arranged.

9.4.11.4 The integrity of precast slabs shall be strengthened and the arris of slab shall be

welded with supporting beam at lower ends.

9.4.12 When the antiseismic grade is the first and second, the antiseismic recalculation shall

be carried out in joint of framework, and recalculation may be omitted when it is the third or

fourth grade, but it shall comply with the structure requirement.

9.4.13 The reinforcements of frame girder style table and joint area shall be adopted with the

following aseismatic measures according to the antiseismic grade.

9.4.13.1 Diameter of hooped reinforcement: it shall not be less than 8mm when the

antiseismic grade is the third grade, not be less than 10mm when it is the second grade, and

not less than 12mm when it is the first grade.

9.4.13.2 The densification scope at beam head should be 1~1.5 times of the beam depth, and

the maximal dandifying length may be 1/3 of clear span.

9.4.13.3 When the antiseismic grade is the second grade or under (or site of I and II types of

degree 8), and the longitudinal construction is set with earthquake resisting wall or

antiseismic support, the columns in the longitudinal joint area of framework may not be set

with dandified hooped reinforcement.

9.4.13.4 The distance among hooped reinforcements in the cryptographic area of beam shall

Page 101: DL 5022-1993

96

not be larger than 250mm when the antiseismic grade is the first or second grades and should

not be larger than 250mm when the antiseismic grade is the third or fourth grade.

9.4.14 The longitudinal reinforcement of column should adopt symmetric reinforcements. As

for the column in the framework-earthquake resisting wall (antiseismic support) system, when

the design experience is available, the space among steel reinforcement direction along long

side distraction of column and the space among the limbs of hooped reinforcements

(including lacing wire) shall not be larger than 350mm, and those along the long side

direction of framework column shall not be larger than 250~300mm.

9.4.15 The endless roof truss or gable wall load bearing scheme of roof beam shall not be

adopted, and separate antiseismic beam (also as windward beam) shall be set. The gable wall

column shall not adopt non-reinforced brick construction. Within the roof truss scope, the

gable wall should adopt light materials and shall be fixed onto roof truss.

9.4.16 The corbel reinforcement for supporting the roof truss and the connected embedded

parts shall comply with the following requirements:

9.4.16.1 The diameter of the hooped reinforcement of corbel shall not be less than 10mm,

their space shall not be larger than 100mm and they shall be placed as the twisted hooped

reinforcement.

9.4.16.2 The length of the anchor bars of longitudinal reinforcements in the steel plate at

corbel top surface should be la+50mm (la is the anchoring length of tensile reinforcement);

the weld strength of anchor bar shall be larger than its strength.

9.4.16.3 The longitudinal reinforcements (longitudinal reinforcements bearing tensile force of

horizontal earthquake effect) welded with the top surface steel plate of corbel shall be not less

than two sticks and its diameter shall not be less than 12mm when it is degree 6 or 7; not less

than two sticks and the diameter shall not be less than 14mm when it is of degree 8; and not

less than two sticks and the diameter not less than 16mm when it is of degree 9.

9.4.17 The elements of the roof without purline shall comply with the following requirements:

9.4.17.1 In the site of Class III and Ⅳ of degree 7, the large-scale roof panels in the first row

at both ends of different roof truss shall ensure the four corners are welded with welding seam,

other roof panels shall be with at least three corners being welded with welding seam.

9.4.17.2 As for the roof panel in the first row at both sides when it is degree 7 and when it is

degree 8 and 9, the length of the attachment weld between roof panel and roof truss shall not

be less than 80mm, and the weld bead height shall not be less than 6mm.

9.4.17.3 When it is of degree 8, the roof cover of scuttle should adopt light plates. When the

roof cover adopting large-scale roof panels of degree 7, in the first bay at both ends of the

workshop unit (in all the bays when it is of degree 8 or 9), the hooks of large-scale roof panel

shall be buried near to the ends, and the adjacent hooks shall be welded with bar dowel in

longitudinal direction and transverse direction. When the roof panel is not set with hooks,

embedded parts shall be set at top surface of the four corners on roof panel and the adjacent

embedded parts shall be welded with bar dowel.

9.4.17.4 When it is of or above degree 7, full-length inter-tie shall be set at the top chord and

bottom chord at head ends of roof truss that is with span of roof truss equal to or larger than

18m, and the inter-tie shall be considered as compressed bar.

9.4.17.5 The ring beam shall be firmly connected with column or roof truss. The quantity of

ring beams at column top and the quantity of anchor bars used for column connection shall

Page 102: DL 5022-1993

97

not be smaller than 4, the diameter shall not be less than 12mm, and the length inserting into

concrete column shall not be less than the anchoring length of tensile reinforcement.

9.4.17.6 The plane dimension of concealed parts at top chord of roof truss that is welded with

roof panel should not be less than 200mm×200mm, the quantity of the bent bars of the

embedded plate at top chord ends should not be smaller than 4, and the diameter of bent bar

shall not be less than 12mm.

9.4.18 The length-diameter ratio for the members in roof supporting (including scuttle

supporting) should comply with the following requirements:

Length-diameter ratio of pressure barλ≤200

Length-diameter ratio of drawbarλ≤300 when it is of degree 6 and 7

λ≤250 when it is of degree 8 or 9

9.4.19 Generally, the reinforced concrete precast slabs may be adopted. And light steel plate

such as profile steel plate may be adopted if the main workshop is with proper conditions. The

light roof should be adopted when it is degree 9.

9.4.20 In order to strengthening the longitudinal rigidity at head end of roof, the scuttle at

both ends or one end of the workshop unit may be set starting from the second

intercolumniation at head end. The side plate at both ends of monitor frame and the upright

column of monitor frame should adopt the bolted connection. When it is of degree 8 and 9,

one lateral bracing at the top chord of roof truss shall be set at both ends of the punching

scope of scuttle in addition partially.

9.4.21 Shoring layout of the machine hall cover shall comply with relevant requirements of

"Code for Seismic Design of Buildings"; when transverse box and bent system structure are

present, it shall also meet the following requirements:

9.4.21.1 When the seismic grade is 8°and 9°, the last quarter of roof truss with span of no less

than 24m shall be set with closed horizontal shoring. When the through roof truss adopts

light-duty roof cover, the first quarter shall be set with closed horizontal shoring.

9.4.21.2 When the seismic grade is 8° and 9°, a beam of vertical bracing along full length

shall be set in the center of the trapezia and arched roof truss around every other 12m. When

scuttle is available, it may be set in harmony with the vertical bracing of the scuttle heel post.

When the height of the roof truss end is no less than 900mm, vertical bracing along full length

shall be set on both ends of the roof truss respectively.

9.4.22 Stipulation on boiler cradle is applicable to aseismic design of reinforced concrete and

pendant boiler truss with composite structure possessed of shaking point or set with guiding

mechanism.

9.4.23 When the boiler cradle and roof requires sealing, light-duty steel plate should be

adopted.

9.4.24 The boiler cradle may generally calculate horizontal earthquake effect in the two

principal axes directions, and make aseismic checking. Horizontal earthquake effect in

directions shall be assumed by the side force resistant members in that direction.

9.4.25 When calculating the earthquake effect for the boiler cradle, all of the boiler cradles

supporting the furnace shaft should be connected as an integral part, and major connected

nodes shall consider impact of earthquake effect vertically and horizontally respectively.

When calculating the earthquake effect of the boiler cradle with response spectrum modal

decomposition method, at least vibration modes should be considered.

Page 103: DL 5022-1993

98

9.4.26 When the earthquake effect is calculated for the boiler cradle, the gravity rigidity and

boiler cradle joint work composed of suspended furnace shaft and steeve, and its gravity

rigidity may be calculated by formula (9.4.26).

knl

EI

l

GK

30

6 (9.4.26)

Where

K0——Gravity rigidity (kN/m);

l——Steeve length (m);

G——Gravity loading of suspended furnace shaft (kN);

E——Elastic modulus of the steeve (kN/m2);

I——Inertia moment of the steeve (m4);

n——Total steeve number;

k——Rigidity regulation factor, it is generally 1.5~2.0.

9.4.27 Partial earthquake effect of the boiler cradle shall be calculated by the multi-mass

system; mass of the boiler cradle are focusing on floors separately, the mass of the furnace

shaft is calculated by the gravity rigidity-based spring, and its mechanical model sees Figure

9.4.27.

9.4.28 When calculating the earthquake effect of furnace shaft itself according to Figure

9.4.27, its seismic influence factor shall not be less than 0.2amax.

9.4.29 The normal value of earthquake effect for the suspended furnace shaft shall be

provided by the manufactory. The calculation diagram of the suspended boiler cradle and

furnace shaft sees Figure 9.4.29. When data is lacking, it is simplified calculation, and

earthquake effect caused by the suspended furnace shaft may be calculated according to the

following formula:

Figure 9.4.27 Schema of Boiler Cradle Mechanical Model

BSs GaF 111 (9.4.29)

Where:

F11——Earthquake effect caused by the suspended furnace shaft (kN), the whole value

acts on the column top of the boiler cradle;

ξs——Regulation factor of the modal contribution, ξs=1.2;

a1——Horizontal seismic influence factor correspondent with the fundamental period of

the furnace shaft, and the fundamental period of the furnace shaft may be 1.5s;

BSG ——Total gravity load of the suspended furnace shaft

Page 104: DL 5022-1993

99

Factor a is the product of regulation factor of modal contribution ξs and the horizontal

seismic influence factor a1 (namely a=ξsa1), it may be adopted according to Table 9.4.29-1

and Table 9.4.29-2.

9.4.30 When the aseismic strength is 6°, the aseismic strength may not be checked for the

boiler cradle, but requirement of anti-seismic construction measures shall be met.

Figure 9.4.29 Calculation Diagram of Suspended Boiler Cradle and Furnace Shaft

Table 9.4.29-1 Seismic Coefficient a of Near Earthquake Effect

Strength

Site types 6 7 8

Ⅰ 0.008 0.016 0.032

Ⅱ 0.012 0.023 0.046

Ⅲ 0.015 0.029 —

Ⅳ 0.023 0.045 —

Note: — in the table refers to reinforced concrete structure adopted in that condition, but it has many difficulties from the

aseismic design angle, so it is not recommended any more.

Table 9.4.29-2 Seismic Coefficient a of Distant Earthquake Effect

Strength

Site types 6 7 8

Ⅰ 0.010 0.019 0.038

Ⅱ 0.015 0.029 0.058

Ⅲ 0.020 0.039 —

Ⅳ 0.029 0.058 —

9.4.31 Earthquake effect of columns (or frames) of the boiler cradle may be distributed by the

rigidity proportion of the members. The distribution ratio of the intermediate truss with

smaller rigidity should not be less than 10%.

9.4.32 The normal value of the earthquake effect for the boiler cradle may be calculated by

the following formula:

22lj SSS (9.4.32)

Where

Sj——Normal value of the earthquake effect for the boiler cradle;

Sl——Normal value of the earthquake effect caused by furnace shaft on the column top

9.4.33 When the compartment between the furnace shaft and boiler cradle is set with

horizontal elastic copulation shaking points or guiding mechanism members in places, the

Page 105: DL 5022-1993

100

calculation for the earthquake effect of the boiler cradle should be made according to plane

multi-mass system and with response spectrum vibration mode analytical method. Its

calculation diagram sees Figure 9.4.33.

Figure 9.4.33 Calculation Diagram of Suspended Boiler Cradle

9.4.34 Aseismic design of the boiler cradle shall consider reducing the eccentricity of the

rigidity center and mass center of the boiler cradle. When the eccentricity is large, torsion

impaction shall be considered.

9.4.35 The joint between the large plate beam and column top of the reinforced concrete

boiler cradle, or between the steel column foot and the foundation shall be multiplied by

additional coefficient 1.5 when calculating the earthquake effect. Check the earthquake effect

of the roof structure: when simplified method is adopted to calculate the earthquake effect, its

normal value should be triangularly distributed, and the calculated amount should be

multiplied by augmenting factor 3.

9.4.36 After setting shaking device for the suspended furnace in the seismic area, local

bearing capacity of corresponding load-bearing member shall be checked and it shall comply

with the following relevant requirements:

9.4.36.1 The rigidity of the shaking device should be within 10~20kN/mm, and the force

transferring size is determined by calculation.

9.4.36.2 Free expansion that can comply with the boiler body

9.4.36.3 The stress is definite, but it cannot transfer detonation pressure of the hearth and

vibration when being burnt.

9.4.37 Aseismic structure measures of the reinforced concrete boiler cradle may comply with

Table 9.1.5. When the aseismic grade is the first grade, assembled monolithic reinforced

concrete structure may be adopted under the conditions with reliable measures and design

experience.

9.5 Master control building and distribution equipment building

9.5.1 The Master control building and distribution equipment building may select its

structural shape according to the site soil type and fortification intensity on the basis of Table

Page 106: DL 5022-1993

101

9.5.1. Table 9.5.1 The Structural Shape of Master Control Building and Distribution Equipment Building

Fortification intensity Site type Structural shape

6 ~Ⅰ Ⅳ Masonry structure*

and Ⅰ Ⅱ Masonry structure*

7

~Ⅲ Ⅳ Masonry structure * and frame structure

and Ⅰ Ⅱ Masonry structure * and frame structure

8

and Ⅲ Ⅳ Frame structure

9 ~Ⅰ Ⅳ Frame structure

Note: 1 Masonry structures listed in this table are all set with reinforce concrete tie column and collar tie beam;

2 Frame structure listed in the table is cast-in-situ reinforced concrete frame structure.

* refers to master control building with voltage of 220kV or below and distribution

equipment building with voltage of 110kV or below. Frame structure should be adopted for

the master control with voltage of 220kV or above and distribution equipment building with

voltage of 110kV or above;

9.5.2 The minimum section of the reinforced tie column is 240mm×240mm, the longitudinal

reinforcement should not be less than 4 and the diameter shall not be less than 12mm; the

stirrup diameter should be 6mm and corresponding interval should be 200mm. Tie-bar of the

walling shall dive into the tie column. stirrup in the up-and-down ends of various layers of

columns should be crowded properly. The reinforcing bars of the tie column on the open layer

shall be determined by calculation.

9.5.3 Shelving length of reinforced concrete floor or roof panel diving into the wall shall be

no less than 120mm, and its shelving length on the beam shall be no less than 80mm. The side

of the prefabricated panel near the external wall shall be knot drawn together with the ring

beam.

For the roof cover of bayed floor slab, or building with aseismic strength of 7°, 8° and 9°,

when the ring beam is set on the base plate, joint between plates, plate and beam, or between

tie column and ring beam shall be strengthened.

9.5.4 The ring beam shall be sealed. The top level of ring beam should be identical to that of

the prefabricated panel, and the ring beam should be set close to the panel. The

cross-sectional width of the ring beam is same as the wall thickness and its height should not

be less than 180mm. The ring beam should be cast-in-situ. The top of the bricking-up

partition shall be provided with reinforced concrete capping beam. The ring beam on the

unsealed walling top shall be increased with horizontal rigidity, and its section and reinforcing

bars are determined by calculation.

9.5.5 The stud in the interlayer of the master control building shall be reinforced concrete

column.

9.5.6 The aseismic design of the correspondence building may comply with relevant

regulations of this Section.

Page 107: DL 5022-1993

102

9.6 Coal-shifting trestle

9.6.1 The interval between the trestle and the adjacent buildings shall be set with

earthquake-proof joint. The earthquake-proof joint shall comply with the following

requirements:

9.6.1.1 The earthquake-proof joint may comply with relevant regulations of "Code for

Seismic Design of Buildings". For general trestle, when the aseismic strength is 7, 8 or 9°, its

width should not be less than 70mm, 90mm and 120mm respectively.

9.6.1.2 When earthquake-proof joint is set in the middle of the trestle, support shall be set on

both sides of the joint.

9.6.1.3 When the aseismic strength is 9°, the joint should be two-way deflection

earthquake-proof joint.

9.6.2 When the aseismic strength is 7 or 8°, sliding support shelved on the adjacent buildings

may be adopted to ensure the longitudinal deflection (the coal-shifting trestle leading to the

main building may be set with suspended bearing, sliding support or roller support on its top).

The bearing hereof shall be able to transfer horizontal earthquake effect along the transverse

direction of the structure.

9.6.3 Rigidity of the adjacent transverse frame structures of the trestle should be close to each

other as far as possible. When making the transverse aseismic calculation for the coal-shifting

trestle, integral work of the horizontal structures of the trestle should be considered, and

elastically supported beam structure with different types may be adopted for the calculation

(Annex H). When l/B is no greater than 8 (l is the total trestle length and B is the deck width),

it is rigid deck; when l/B is greater than 8, it is elastic deck.

When the coal-shifting trestle has difficulties in calculating earthquake resistance as an

integral part, weight above the deck may also be distributed to the horizontal structure

according to lever principle, and horizontal structure is calculated separately. Aseismic

bearing capacity of general high-class horizontal structure shall be improved properly.

9.6.4 When the trestle is truss, portal rigid frame shall be set on its both ends. The first quarter

and last quarter of the truss should be set with horizon crossing support along full length.

9.7 Silo

9.7.1 The structural arrangement of the silo shall strive to be simple and regular, and its mass

and rigidity is distributed evenly and symmetrically along the two principal axes directions.

9.7.2 The silo should be disconnected to the adjacent trestle, so that to form independent

structural unit. When the silo is used as supporting structure of the trestle, flexible joint shall

be adopted (such as ball seat and steeve).

9.7.3 The silo should adopt monolithic reinforced concrete structure.

9.7.4 The high-capacity silo in the power plant should adopt tunnel wall supported tower silo,

and shall reduce the punch size of the support ring wall. When arc battened wall is formed by

the setting of large hole, the section of the battened wall shall be equal or similar.

9.7.5 Load-carrying member of the structure on the silo should adopt reinforced concrete

frame or steel frame.

Page 108: DL 5022-1993

103

9.7.6 Roofing of the building on the silo should adopt light roofing or cast-in-situ reinforced

concrete roofing. When the aseismic strength is 8° or below, precast reinforced concrete

roofing may be adopted.

9.7.7 The enclosure walling of the building on the silo may adopt brickwork when it locates

in I or II-type site with aseismic strength of 6, 7 or 8°. When the aseismic strength is above 9°,

building on the silo shall adopt light materials.

9.7.8 When calculating the horizontal earthquake effect of the cylinder silo structural unit, the

effective gravity loading of the bin stock shall be multiplied by the reduction coefficient. For

the cylinder silo, the reduction coefficient is 0.8.

9.7.9 The earthquake effect of the tunnel wall and underpart supporting structure of the

cylinder silo may be distributed according to their relative stiffness respectively. For the

design value of the bending moment on both ends of the support column, it shall be multiplied

by augmenting factor 1.5. The stirrup within up-and-down 1.5 times the long side of the

column section of the support column node shall be crowded.

9.7.10 The maximum axle load ratio of the silo column should meet the following

requirements:

9.7.10.1 General support column: when the strength is 6 or 7°, it is no greater than 0.75; when

it is 8°, it is no greater than 0.7; when it is 9°, it is no greater than 0.65.

9.7.10.2 When the support column id deployed with screw compound stirrup, it is 0.75.

9.7.11 The thickness of the reinforced concrete tower silo wall shall not be less than 180mm

when the strength is 6 or 7°, and it shall not be less than 200mm when the strength is 8 or 9°.

The tunnel wall shall adopt double-layer two-way reinforcement, and the total reinforcement

ratio of vertical or circumferential horizontal reinforcement should neither be less than 0.4%.

The interval between the double-layer steel bar shall be set with tie-bar: when the aseismic

strength is 6 or 7°, the diameter is 6mm and the interval is 700mm; when the aseismic

strength is 8 or 9°, its diameter is 6mm and its interval is 500mm.

When the tunnel wall is set with hole, the holes should be arranged evenly and

symmetrically; the corresponding central angle of the hole shall not be greater than 70°, and

the total punching central angle in the same horizontal cross-section shall not be greater than

140°. When the side length of the opening mouth is less than 1m, sides of the opening shall be

set with at least two additional bars in diameter of 20mm according to Figure 9.7.11. The

sectional area of the additional bar hereof is no less than 1.3 times of the cut off reinforcement

area at the opening. The inside and outside layer of the four corners of the opening are all

deployed with a stick of diagonal reinforcement in diameter of no less than 20mm. When the

opening is large, opening deep frame shall be set, and the reinforcing bars of the deep frame

should not be less than 1.3 times of the cut off reinforcement area at the opening.

Page 109: DL 5022-1993

104

Figure 9.7.11 Reinforcement of Wall at the Opening

9.7.12 When the building on the silo is brickwork, the following structural requirements shall

be met:

9.7.12.1 The interval of reinforced concrete tie columns should not be greater than 4m.

9.7.12.2 The interval between ring beams should not be greater than 3.5m and one beam of

ring beam shall be set on the wall roof.

9.7.12.3 The prefabricated panel joint corresponding with the tie column shall be set with

cast-in-situ reinforced concrete caulked joint belt which is protruding off the steel bar and

anchoring into the tie column.

9.8 Equipment foundation

9.8.1 The aseismic checking of the equipment foundation shall generally check the strength of

the structure itself, and the overturning shall also be checked if necessary.

9.8.2 When calculating the earthquake effect of the equipment foundation, the equipment and

the foundation should be deemed as an integral to determine the structural calculation

diagram (Figure 9.8.2); impaction of connections among equipments may not be considered.

9.8.3 The combination of earthquake effect and other loads effect may refer to Section 9.3 of

this Stipulation, and it should also comply with the following requirements:

Figure 9.8.2 Aseismic Checking Diagram of the Equipment Foundation

Page 110: DL 5022-1993

105

(a) Practical schema; (b) Calculation diagram

Dead load (including gravity load of the equipment)

Design dynamic load of the equipment, its combination coefficient is 0.25.

Incidental dynamic load and installation repair load may not be considered.

9.8.4 When the aseismic strength is 7° or above, the equipment foundation (including the

passable platform) shall not be consolidated with the adjacent buildings. The walkway plate

shall be provided with adequate support length and slip interval.

9.8.5 The supporting structure and foundation of the water film duster shall not adopt

masonry structure.

9.9 Pipeline support

9.9.1 This Section is applicable to independent type support without longitudinal member

connection between brackets and with the pipeline directly laying on the support.

9.9.2 The pipeline support adopts reinforced concrete structure. When the aseismic strength is

8° or above, intermediate support should not adopt half swing joint type.

9.9.3 When the aseismic strength is 6°, the aseismic strength may not be checked, but the

requirement of anti-seismic construction measures shall be met. When the aseismic strength is

8 or 9°, the pipeline support may make aseismic checking and take structural measures

according to the fortification intensity.

9.9.4 The computing unit and calculation diagram of the pipeline support may be selected

according to the following principles:

9.9.4.1 The length (l) of the longitudinal computing unit is the center-to-center distance of the

compensator.

9.9.4.2 The length (l) of the transverse computing unit is the center-to-center distance around

the supports.

Structural calculation diagram in the computing unit may be considered by single mass

point for the monolayer pipeline support, see Figure 9.9.4-2.

Figure 9.9.4-1 Calculation Diagram of Independent Type Support

Page 111: DL 5022-1993

106

Figure 9.9.4-2 Calculation Diagram of Single Mass point

When the pipes are multilayer, it may be simplified to corresponding multi-mass system

according to the pipeline laying positions.

9.9.5 The combination of the effective gravity loading and loads effect of the support shall be

valued according to requirements of this Article.

9.9.5.1 The gravity load includes the following items:

(1) Pipeline gravity, including pipeline, inner lining, insulating layer and deadweight of

the pipeline accessory;

(2) Medium gravity in the pipeline, it is the gravity under normal operation (provided by

the process);

(3) Gravity load of the pipeline support: when it is single-mass-system, the computation

period is 1/4 of the gross weight, and the earthquake effect calculation tales 2/3 of the gross

weight.

(4) Sleet load, it is 50% for cold pipeline.

9.9.5.2 The earthquake effect shall be combined with the following loads effect:

(1) Dead load, including the dead weight of the equipment.

(2) Sleet load, it is 50% for cold pipeline;

(3) Horizontal thrust caused by the thermal expansion of the pipeline during normal

operation;

(4) Wind load, it is valued according to requirements of "Code for Seismic Design of

Buildings".

9.9.6 Longitudinal earthquake effect calculation of the pipeline support: intermediate support

and fixed support earthquake effect may be distributed according to the lateral flowing

rigidity of the support, when the earthquake effect of the intermediate support is greater than

the friction of the pipeline, frictional impact may be reduced.

9.9.7 When the seismic strength is 8 or 9° and one of the following conditions are met,

vertical earthquake effect shall be considered:

9.9.7.1 The combined type support with span of greater than 24m (the pipeline is used as truss

member)

9.9.7.2 For T-shape orⅡ-shape support with overhung outrigger, when their outrigger is set

with large-diameter pipeline;

9.9.8 The beam and column of the pipeline support shall be prefabricated integrally, and the

beam column node shall meet the structure requirement of the frame node.

9.9.9 The support or suspension measures on the pipeline support shall be reliable, and the

Page 112: DL 5022-1993

107

side pipeline on the top layer beam shall be set with measures preventing pipeline shattering.

Page 113: DL 5022-1993

108

Annex A Calculation Diagram of Transverse Frame (Bent Frame)

A1.0.1 Simplified calculation for frame (bent frame) of the main building sees Figure A1.

Figure A1 Simplified Calculation Diagram of Transverse Frame (bent Work)

(a) External coal silos type; (b) Internal coal silos type (single frame); (c) Internal coal silos type (double frame); (d) Suspended

boiler independent type

Page 114: DL 5022-1993

109

Annex B Vertical And Horizontal Calculation Diagram of Suspended

Boiler Framework

B1.0.1 The vertical and horizontal calculation diagram of suspended boiler framework sees

Figure B1.

Figure B1 Vertical and Horizontal Calculation Diagram of Suspended Boiler Framework

(a) single-column multilayer transverse framework; (b) single-column monolayer transverse framework; (c) battened column

multilayer transverse framework; (d) battened column multilayer transverse framework; (e) s framework-type transverse

framework; (f) longitudinal framework on the furnace side

Page 115: DL 5022-1993

110

Annex C Determination for Gage Length l0 of the Boiler Framework

Frame-Column

Gage length l0 of the boiler framework frame- column may be determined according to

the following formula:

Haa

liu

)]11

(2.01[0 (C1)

Where

au——Rigidity ratio of the beam-column line at the upper node of the calculated column

shell;

ai——Rigidity ratio of the beam-column line at the lower node of the calculated column

shell;

H——For the bottom layer column, it is the distance from the top surface of the

foundation to the top surface of the first layer of beam; while for columns on other layers, it is

the distance between the top surfaces of both upper and lower layers of beam.

Rigidity ratio a (namely au and ai) of the beam-column line at the node may be calculated

according to the following formula:

icici

ibibi

HIE

lIEa

/(

)/(

(C2)

Where

Ebi, Ibi and li——They are elastic modulus, sectional inertia moment and axial line span

of the ith beam respectively;

Eci, Ici and Hi——They are elastic modulus, sectional inertia moment and column height

of the ith column respectively;

Summation sigmonium of formula (C2) shall include all of the beams or columns at the

calculated node. When calculating the sectional inertia moment, impact of reinforcing bars

may not be considered. For bottom layer column, the column and foundation are generally

permanent connected, by then, ai=∞.

Ebi, Ibi, Eci, and Ici of composite structure beam and column shall be valued according to

relevant regulations of "Tentative Specifications for Steel-concrete Composite Structure of

Main Buildings in Thermal Power Plant".

Page 116: DL 5022-1993

111

Annex D Type-selection, Calculation Diagram and Calculation

Formula of Side Wall of Dumper House and Joint-type Coal

ChuteD1.0.1 Type-selection and calculation diagram of dumper house see Table D1.

Table D1 Type-selection and Calculation Diagram of Dumper House

Calculation diagram No. Type-selection for structure

Portal and frame system Ditch wall and soleplate system

1

2

3

D1.0.2 The type-selection and calculation diagram of joint-type coal chute see Table D2. Table D2 Type-selection and Calculation Diagram of Joint-type Coal Chute

Calculation diagram No. Type-selection for structure

Portal and frame system Ditch wall and soleplate system

Page 117: DL 5022-1993

112

1

2

3

4

5

6

Headwall, side wall and soleplate may be

calculated by two-way slab or one-way slab

Note: The calculation diagram of portal and frame system may also adopt calculation diagram of combined solution, while

Page 118: DL 5022-1993

113

the soleplate may also be calculated by other diagrams.

D1.0.3 The side wall calculation formula of the dumper house and joint-type coal chute sees

Table D3. Table D3 the Side Wall Calculation Formula of the Dumper House and Joint-type Coal Chute

H

H11

H

H 22

H

H33 21 n

sin

1m

2

1

I

In

2332 )3(

6

1 K

1

313

1 )]1()1(1[3

1VCm

nn

mK n

2333 3

1VCK fk

KKK

KaKaR

3122

22112

1

2221 K

RKaR

32

H

EIV

Load diagram ai Coefficient

)43(24

41 nn

qHa

)]1()1(1[8

414

2 mnn

mqHa n

)331

2321

23

211 23(

12

qHa

)3()(5

1[

6 13212

2121412

n

m

n

qHa

])1( 2231

)44

51(

30

5

1n

n

qHa

)]1()([30

551

551

2 nnn

m

n

qHa

]463[12

331

2321

23

211

qHa

)(9)(6[12

22

23

2123

312

n

m

n

mqHa

)]2

1(122

3)(4 1

32141

32

331

nn

m

Page 119: DL 5022-1993

114

231 2

H

Ma

)2(2 332

H

Ma

)43(12

332

23

22

21 m

qHa

)]496(

)1(6)34(2

[12

2332

2232

13212132

22

n

mm

qHa

)2(12

332

23

22

21 m

qHa

])1(

)32(2

1)

54([

62

132

32321213

22

2

n

mm

qHa

H

H11

H

H 22

sin

1m

2

1

I

In 1

311 )]1(1[

3

1VC

n

mK

)]2([6

11

222 K 2

323 3

1VCK

fKKKK

KaKaR

3122

22112

1

2221 K

RKaR

3

2

H

EIV

Load diagram ai Coefficient

)43(24

4111

qHa

)]1(1[8

412

n

mqHa

)44

51(

30

51

11

qH

a

)]1(1[30

512

n

mqHa

Page 120: DL 5022-1993

115

221

ZH

Ma

)2(2 222

H

Ma

)43(12

321

22

21

21 m

qHa

)]496(2

3[

12321

22

212

31

241

2

2 mn

mqHa

)2(12

321

22

21

21 m

qHa

)5

(6 21

241

3

2 mn

mqHa

Note: 1 Kf is reaction coefficient, generally, Kf=0.8~0.9;

2. C1 and C2 sees the explanation in the end, and its metering unit is kN·m.

Operating instruction of Table D3:

(1) The flexibility factors C1 and C2 may be calculated according to the deflection for the

practical rigidity of ground-based platform plate and coal-feeder platform plate caused under

unit force action (calculation diagram sees Figure D1), with its calculation formula of:

Figure D1 calculation diagram of C1 and C2

Page 121: DL 5022-1993

116

3

4

01 EI

lKC (m/kN)

4

4

02 EI

lKC (m/kN)

Where

l——Plate span of the platform (m);

E——Elastic modulus of the concrete (kN/m2);

I3——Sectional inertia moment of the ground-based platform plate (m4);

I4——Sectional inertia moment of the coal-feeder platform plate (m4);

Ko——Deflection coefficient under the action of unit force, it may be calculated by

5-span continuous beam formula (look up Table D4); or it may be proximately calculated by

single beam. Table D4 K0 Deflection Coefficient

ni span

position n1 n2 n3 n4 n5

x=0

x=l/2

0

0.00644

0

0.00151

0

0.00315

0

0.00151

0

0.00644

(2) Take x=0 or 2

lx , solve supporting resistance R1 and R2, and at last calculate

bending moment Mj.

Page 122: DL 5022-1993

117

Annex E Strength Calculation for the Chimney Shaft Opening

E1.0.1 The design of the chimney shaft shall not only comply with relevant regulations of

chimney design codes, but shall also meet the following requirements:

(1) Thickness of the tunnel wall shall comply with the following conditions:

σh=σhw+σhf≤Rat/Kh (E1)

hwhf dr/

r/b

4

1 (E2)

Where

σh——Compressive stress of tunnel wall concrete on both sides of the opening;

σhw——Non-opening section on the opening top, under dead load and wind load actions,

the calculation method for the compressive stress of the marginal concrete in the compressive

region sees "Code for Design of Chimneys";

σhf——Additional compressive stress of tunnel wall concrete on both sides of the

opening;

Rat——Compression resistant design strength of the concrete, see "Code for Design of

Chimneys";

Kh——Safety factor of the concrete, see "Code for Design of Chimneys";

b——Width of the opening;

r——Mean radius of the tunnel wall section at the opening

(2) The surroundings of the opening shall be deployed with additional reinforcement

steel bar, its reinforcing bars disposal scope sees Figure E1, and the reinforcing bars quantity

is as follows:

1) The total area of the additional bar for both sides of the opening may take the

maximum result of the following three formulas:

Ag2=0.65μδbσgwkg/Rgt (E3)

ggt

g kR

Q

r/

r/HA

32

32 (E4)

Ag2=0.65μδb (E5)

2) The total area of the additional bar on top of the opening may take the maximum

result of the following three formulas:

Page 123: DL 5022-1993

118

Figure E1 Disposal Position of the Additional Bar at the Opening

Symbol descriptions:

θ—Opening semi-angle; δ—Thickness of the tunnel wall; r—Mean radius (at the

elevation in the middle of the hole); d—Bar diameter; b—Width of floss hole; H—Height of

the floss hole

ggt

gb QkbR

HA

8

3 (E6)

gg

hgb k

w

wbA3.0 (E7)

Agb=0.65μ0δ0H (E8)

3) The total area of the additional bar on the lower part of the opening may take the

maximum result of formula (E6) and the following formula:

Agb=0.5μ0δH (E9)

Where

δ——Thickness of the tunnel wall;

b and H——Width and height of the opening;

Rgt and kg——Tensile design strength and safety factor of the steel bar, see "Code for

Design of Chimneys";

Q——Wind shear act on the section on top of the opening;

δ0——Effective height of the tunnel wall;

μ0 and μ——Reinforcement ratio of the circumferential and longitudinal reinforcement,

it is calculated according to the requirements of "Code for Design of Chimneys";

Page 124: DL 5022-1993

119

σhw and σgw——Non-opening section on top of the opening, under dead load and wind

load actions, the calculation method for the edge stress of the compressive region and tensile

region sees "Code for Design of Chimneys";

4) The four corners of the opening must be set with 45° inclined additional bar, and

steel bar of corners is deployed at least 250mm2 every 100mm by the thickness of the

tunnel wall.

Page 125: DL 5022-1993

120

Annex F Calculation of Wind Load of the Pipeline Support

F1.0.1 calculation diagram of the monolayer multi-pipeline wind load sees Figure F1 and its

calculation formula is as follows:

Figure F1 Calculation Diagram of Monolayer Multi-pipeline

Dilww szk 10 (F1)

Where

μz——Variation coefficient of the wind pressure height, it is selected according to "Load

Code for the Design of Building Structures";

w0——Basic wind pressure (kN/m2);

l——Pipeline spans; when the pipe-line spans on both sides of the pipe support are

unequal, the average value is taken (m);

Di——Outside diameter of the pipeline, including the insulating layer (m);

μs1——Shape coefficient of the pipeline wind load, it is looked up from Figure F2.

When the pipe diameters are unequal, therein, the shape coefficient μs3 of the maximum

pipe takes 0.6 (when the pipe diameters are equal, shape coefficient of all the pipe takes 0.6),

the rest pipes is down the wind, with the front of the big pipe is s1/D1 or s2 /D2, and its back is

s3 /D3 or s4/D4… and μs1, μs2, μs3 and μs4 are looked up one by one.

When w0D2 is no less than 0.02, μs1 is directly looked up from Figure F2.

When w0D2 is no greater than 0.003, the looked-up value shall also be multiplied by 2.

When w0D2 is within 0.003~0.02, the looked-up μs1 shall also be multiplied by the

improvement factor looked up from Figure F3.

F1.0.2 Calculation diagram of multilayer multi-pipeline wind load sees Figure F4 and its

calculation formula is as follows:

Page 126: DL 5022-1993

121

Figure F2 Shape Coefficient of Monolayer Multi-pipeline Wind Load

Figure F3 Improvement factor

wki=μ's1wk (F2)

Where

wk——Wind load of some layer of pipeline, it is calculated by formula (F1);

μ's1——Influence coefficient between the upper and lower layers, it is looked up by

Page 127: DL 5022-1993

122

Figure F5. Namely, μ's2 is looked up by s1/D1 and μ's1 is looked up by s1/D2; in like manner,

μ's3 is looked up by s2/D2 and μ's2 is looked up by s2/D3. Influence coefficient of the middle

layer pipeline is the result of influence coefficients sum of both the upper and the lower layers

subtracts 1.0. D1 is the diameter of the maximum pipe on each layer, si is the clear distance

among the maximum pipes, see Figure F4.

F1.0.3 Wind load of the pipe support is calculated according to the following formula:

Figure F4 Calculation Diagram of Multilayer Multi-pipeline

Figure F5 Influence Coefficient among the Multilayer Multi-pipeline inter-layers

wk=μsμzw0b (F3)

Where

μz and μs——They are variation coefficient of the wind pressure height and the shape

coefficient of the pipe support wind support respectively, they are adopted by "Load Code for

the Design of Building Structures".

b——Width of the windward support (m)

Page 128: DL 5022-1993

123

Annex G Regulation Factor of Theoretical Calculation Period

G1.0.1 The following building periods calculated according to engineering mechanics theory

is generally adjusted by coefficient less than 1.0:

(1) Main buildings:

1) The transverse frame structure of the main buildings may be 0.8 of the

computation period

2) Longitudinal structure of the main buildings, it may take 0.7 of the computation

period for the pure frame; when earthquake resisting wall or aseismic support is present,

it may not be adjusted.

(2) Monolayer factory building: it is bent consisted of reinforced concrete roof truss and

steel bar coagulated column; when longitudinal wall is present, it takes 0.8 of the computation

period; when there isn't any longitudinal wall, it takes 0.9 of the computation period.

Page 129: DL 5022-1993

124

Annex H Aseismic Calculation Method of Trestle Transverse

Direction

H.1 The aseismic calculation method for the rigidity deck with the lower extreme of swing

joint (ground impacted end) and others of elastic bearing (Figure H1) is as follows:

Figure H1 system is one degree of freedom, and the formula of its fundamental period (T)

is:

Figure H1 Calculation Diagram of the Rigidity Deck with One End of Swing Joint and others of Elastic

Support

K

JT 2 (H1)

3

3l

g

GJ (H1.a)

n

iii xKK

1

2 (H1.b)

Where

Page 130: DL 5022-1993

125

J——Total mass second moment of the system;

Kθ——The products between the supports' rigidities and the distance square away from

the origin;

n——Support number;

G——Total gravity loads of the trestle, including: dead load, equipment weight, deck

and roofing live load, and partial support weight above the deck; for partial support weight, it

may be selected by the following principles: when calculating the fundamental period, it is

1/4 of the total weight of the support; when calculating the support earthquake effect, it is 2/3

of the total weight of the support;

g——Acceleration of gravity;

l——Total length of the trestle;

Ki is the rigidity of the ith support peak, u

Ki

1 , u is the support deflection when unit

force acting on the support peak;

xi——The distance from the ith support to the origin.

Earthquake effect of the supports' top is:

Fi=a1niGl' (H2)

n

ti

iii

xK

xK

1

21

(H2.a)

Where

a1——Seismic influence factor is calculated according to "Code for Seismic Design of

Buildings";

ηi——Distribution coefficient of the earthquake effect;

l'——1/2 of the total length l of the trestle;

When the total length of the deck is less than 25m, T = 0.3s, and fundamental period may

not be calculated any more.

H.2 The aseismic calculation method of the elastic supported rigidity deck is as follows

(Figure H2):

Figure H2 Calculation Diagram of Elastic Supported Rigidity Deck

Page 131: DL 5022-1993

126

Calculation of natural vibration period:

j

T2

D

DFEEj 2

422

(j=1, 2)

D=mJ

E=mKθ+JKy

F=KyKθ-K2

yx

n

iiy KK

1

i

n

iiyx xKK

1

2

1i

n

ii xKK

(i=1, 2…n, n is the support number)

Where

m——Total mass of the trestlework ( g

Gm

, g is the acceleration of gravity, G is the

total gravity load of the trestle, and the calculation of G is identical to that of other elastic

supported rigidity deck with the lower end swinging);

J——Total mass second moment of the trestlework, J=0.083 ml2, and l is the total length

of the trestle;

Ki——Rigidity of the ith support peak u

Ki

1 ;

xi——Distance from the ith support to the trestle mass center; the mass center is the

origin and xi has plus-minus value

Earthquake effect of the supports' top is:

Fji=Ki(Yj+xiθj) (j=1, 2; i=1, 2, 3···n) (H4)

F

TKFKY jyxj

j

(H4.a)

F

FKTK jyxjyj

(H4.b)

Fj=ajyjYjG (generally, Yj=1) (H4.c)

22j

jJmY

mYy

(Generally, Y=1.0) (H4.d)

Tj=ajyjθ'jJg (H4.e)

Page 132: DL 5022-1993

127

yx

jyj K

mK 2

(when Yj=1.0) (H4.f)

Where

Fj——Normal value of the total earthquake effect of the trestle;

aj——Seismic influence factor of the jth vibration mode, it is calculated according to

"Code for Seismic Design of Buildings";

Tj——Total torsion moment of the trestle

Earthquake effect combination of the supports is:

2

1jjsS (H5)

Where

sj——Earthquake effect of supports when it is jth vibration mode

H.3 The aseismic calculation method of the elastic supported elastic deck is as follows

(Figure H3):

Figure H3 Calculation Diagram of Elastic Supported Elastic Deck

The trestle with elastic deck should make holistic computation by elastically supported

beam-type structure, or it may be calculated with finite-element method or special procedure.

Page 133: DL 5022-1993

128

Annex I Explanation of Wording in this Code

1. Words used for different degrees of strictness are explained as follows in order to mark

the differences in executing the requirements in this Code.

1) Words denoting a very strict or mandatory requirement:

“Must” is used for affirmation; “must not” for negation.

2) Words denoting a strict requirement under normal conditions:

“Shall” is used for affirmation; “shall not” for negation.

3) Words denoting a permission of a slight choice or an indication of the most suitable

choice when conditions permit:

“Should” is used for affirmation; “should not” for negation.

2. “Shall comply with…” or “shall meet the requirements of…” is used in this code to

indicate that it is necessary to comply with the requirements stipulated in other relative

standards and codes.

Page 134: DL 5022-1993

129

Additional explanation

Chief development organization: Northwest Electric Power Design Institute

Participating development organizations: North China Electric Power Design Institute,

Northeast Electric Power Design Institute, East China Electric Power Design Institute,

Southwest Electric Power Design Institute, Central Southern China Electric Power Design

Institute, Hebei Electric Power Survey Design Institute, Electric Power Design Institute of

Jiangsu Province, Shanxi Province Electric Power Survey Design Institute, Heilongjiang

Electric Power Design Institute, Shandong Electric Power Design Institute, Henan Electric

Power Survey Design Institute, Hunan Electric Power Survey and Design Institute,

Guangdong Electric Power Survey and Design Institute and Electric Power Construction

Research Institute.

Major drafting staffs:

NI Shiquan, YANG Zonglie, JING Zhihong, YAO Dekang, YU Zhen’an, JIANG Xianchuan,

ZHU Daojiang, QIU Huixian, ZHUANG Wenfu, HE Ruomei, QIAN Yongrui, JIAN Guoping,

HUANG Yingbo, YAN Shanzhang, ZHANG Fangqi, LI Bingyi, DING Jialiang, LIU

Maosheng, SONG Jingyang and WEN Liangmo