55
In-house Journal of L&T Construction October 2013 - March 2014 Volume - 37, Issue - 1 Welcome to Mumbai’s new gateway to the world!

ECC Concord

  • Upload
    vancong

  • View
    288

  • Download
    3

Embed Size (px)

Citation preview

Page 1: ECC Concord

In-house Journal of L&T Construction

October 2013 - March 2014Volume - 37, Issue - 1

Welcome to Mumbai’s new gateway to the world!

Page 2: ECC Concord

2 ECC CONCORD, October’13 - March’14 3ECC CONCORD, October’13 - March’14

If airports reflect the character and personality of a city, then the new Mumbai International Airport sports all the verve and vibrancy of India’s throbbing commercial capital. And, Larsen & Toubro, is proud to have created a gateway for the world that is truly a landmark of the future. Built to exacting specifications and by overcoming innumerable challenges, this very complex brownfield project is yet another sterling example of L&T’s engineering prowess and reaffirms its leadership position in providing total infrastructure solutions for a new India.

A shining example of

world-class engineering!

Page 3: ECC Concord

4 ECC CONCORD, October’13 - March’14 5ECC CONCORD, October’13 - March’14

What is more difficult than making an elephant dance?

Making a peacock dance!Inspired by the dancing peacock, India’s national bird, the picturesque new Terminal 2 of the Chhatrapathi Shivaji International Airport is a resplendent icon of modern infrastructure.

And it took a lot of doing!

Page 4: ECC Concord

6 ECC CONCORD, October’13 - March’14 7ECC CONCORD, October’13 - March’14

project requires extensive planning; time bound schedules and constant monitoring to ensure timely execution of elaborate engineering. T2 of the Mumbai International Airport represents one of L&T’s best performances and reflects the flawless teamwork and smooth coordination that have become synonymous with us. Now, that the airport is fully operational and has become an important landmark of the

The new Terminal 2 of Mumbai International Airport is truly globally benchmarked for its architecture, design, quality and cost. I have not seen many, in fact, any other airport even outside India that is as good as this one! Unique in terms of the synergy of aesthetics and functioning, this is easily one of the most beautiful airports in the world.

The overall framework and concept for this kind of gigantic

country, every time we pass through it, we will cherish and take pride to have been associated with this dream project.

It is good to have associated with GVK who also share our ideology in partnering only with the best to bring about perfection. I am glad that L&T was a part of creating Mumbai’s first public building that also doubles up as an art project. It is a national symbol!

A. M. Naik Group Executive Chairman

We started our MIAL journey almost 6 years ago and as EPC contractor for the entire project, our challenges were mindboggling! It was one of the most complex brownfield projects that had to be executed without disrupting the operations of a fully-functional airport! We had to double the passenger capacity of India’s busiest airport by building a massive infrastructure right in the heart of Mumbai with no extra land to expand, no time to shut down, highly sensitive from a commercial, political and security point of view; and finally, world-class quality to be delivered in a limited time frame.

The new terminal building, constructed over the footprint of the existing international terminal building, on a built-up area 4 times larger was made possible by demolishing several existing structures. On the Airside, we had to reconstruct two existing runways with defined time windows to carry

out the work. Simultaneously, we had to co-ordinate with airline industries across the world through NOTAM that gave no room for failure or slippages. A concourse was built to join the two terminals while a 3.3 km, 6-lane elevated corridor connected the airport with the Western Express Highway to address Mumbai’s traffic problem. The 83.8 metre tall ATC tower and the terminal building, which incorporates the dancing peacock in every element is an engineering marvel. The latest technologies such as rubbilization for apron construction, high rise jaw crushers for dismantling, hot tapping for diverting live fuel lines, carbon reinforced fiber technology for strengthening an existing bridge under the operating runway, erection of 28000 tons of structural steel roof using launching girder over 40m tall highway trusses, were all a part of the mechanization strategy adopted to quicken this project.

The magnitude of the project was almost too huge to consider. Every day about 15,000 workmen, 1,000 engineers, 200+ sub-contractors and some 4000 of their staff turned up for work. 250 engineers and architects formed the on-site design team while expats were mobilized from the world over for various functions. Project planning, which was globally benchmarked, involved handling of more than 200 specialized national and international agencies.

At the end of the day, we had to live up to the expectations of a lot of stakeholders – the client, the airport authorities, the Government, the local statutory bodies – but none as big as the passengers themselves. And we did that in style, which is typical for every L&T executed project.

Hats-off to the entire MIAL project team for having created such a marvelous edifice!

S. N. Subrahmanyan Whole-time Director & Sr. EVP (Infrastructure & Construction)

Page 5: ECC Concord

8 ECC CONCORD, October’13 - March’14 9ECC CONCORD, October’13 - March’14

V. Ramanathan Deputy Project Director - Electrical & IT works

80,000 light fixtures, 750 kilometers of conduiting and another 250 kilometers of HT/LT cables, 940 chandeliers, 3,000 CCTV cameras, some 26,000 data points, a ‘Diya Wall’ with 1,000 LED lamps … the numbers are totally awesome but that was our challenge in the Electrical and IT space. It was our responsibility to breathe life and infuse light into this huge structure. The magnitude of the task was huge that called for micro-planning. Each and every aspect, however insignificant, had to be checked and approved because back-tracking would have cost us time, which we did not have and erosion of our margins which we could not allow. We were dealing with a plethora of suppliers from around the world and had to be ever-vigilant that deliveries and installations were happening like clockwork. Several new technologies and methodologies were adopted to fast-track the project like using multiple conduits instead of cable trays and flexible cables for wires. Our team was young and dynamic driven by the urge to create systems that shall suffer no downtime! At the end of the project, we are proud for having contributed in the creation of a masterpiece.

Niranjan Simha Project Director

The project was very complex with multifarious challenges that had to be resolved, phase-wise, as we proceeded and kudos to the entire MIAL project team for having succeeded despite

seemingly overwhelming odds. Some of the operative words that describe the MIAL project are ‘Planning’, ‘Co-ordination’, ‘Quality’, ‘Execution’ and ‘Timeliness’. Managing the huge

work force was like leading an army with so many people, who were experts in their various domains, drawn from various parts of the country and the globe. Since

we were working to stringent deadlines, it was imperative to get the right resources at just the right time. Overall, it was one of our toughest assignments but we were able to deliver a world-class facility on time, thanks

to the qualities that sets L&T apart, its design excellence, construction capabilities, the freedom to take calculated risks all brought together by unmatched teamwork which contributed to the creation of this beautiful edifice.

Rajesh KanadeHead - Project Planning and Control & TC; Project Manager - Airport System

For L&T, MIAL was the fourth international airport project in an Indian metro, and although the considerable experience gained from these previous projects did hold the team in good stead, we were yet faced with a whole lot of challenges hitherto not faced that required new and innovative solutions. Considered perhaps the world’s most complex brownfield airport project, the planning for MAIL combined several unprecedented dimensions and the team faced them head-on. Our goal was to create a global landmark. Sharp planning and committed implementation, coupled with rigorous follow-ups, saw the project progress at unbelievable speeds. Once commissioned, the task of testing, commissioning and successfully integrating over 75 MEP, airport and IT systems and carrying out 200 project operation trials was arduous but completed, thanks to seamless cross-functional interfacing. The sophisticated electro-mechanical and IT enabled BHS, HBSS, VHT and PBB airport systems called for impeccable standards of execution and commissioning. The remarkable six-lane elevated corridor constructed right over a busy operational at-grade road has become a marvelous dedicated access to the terminal. The success of the MIAL project was indeed a perfect performance through flawless teamwork and smooth coordination.

C.J.A. DavidrajDeputy Project Director – Finishes

‘Making a thousand peacocks dance’ was the vision with which the finishes team took up the MIAL project. Every single square inch of the terminal, be it interior or exterior, had to have the touch of perfection to not just create a landmark project, but an edifice that would be regarded as one of the world’s most stunning airport terminals. The numbers

were mind blowing, 80,000 sq.m of GFRG canopy, 1.83 lakh sq.m of granite, 1.10 lakh sq.m of metal ceiling and 30,000 sq.m of carpet. With such mega volumes

involved in every procurement item, standardisation was indeed a challenge. Detailed method statements followed by mock-ups and strict adherence to the charted sequence of execution made implementation seamless and smooth. The swank finishes have truly created the intended ‘wow’ effect with even the Prime Minister of India terming the terminal as ‘The Pride of the Nation’.

J. Gopalakrishnan Deputy Project Director

When we embarked upon the project, the entire footprint of the proposed terminal measuring 125,000 sq.m was occupied by various facilities. The team’s primary task therefore was to plan and create the required footprint, inch by meticulous inch by demolishing to commence construction. This called for consistent out of the box thinking from the team in terms of construction sequences, erection methodology and innovative equipment to be deployed. ‘Getting it right the first time’ was the operative phrase for the planning team simply because there was neither the time for rework nor room for deviation. Activities were planned and scheduled in tandem such that when combined with faultless execution, it would bring out nothing but the expected results. An indomitable spirit, steely determination and unfailing commitment became the work culture at the MIAL project site which transformed an ambitious dream into reality. The successful completion of the MIAL project has greatly boosted the self-confidence and pride of everyone involved in it.

M.V. Satish Sr. VP & Head - Buildings & Factories

As the ever-throbbing commercial capital of India, Mumbai has a number of facets to be proud of and we are honoured that we have been able to add to that long and illustrious list with a gateway that is truly world-class and representative of the exuberant spirit of Mumbai. Our journey commenced with a vision to create one of the most sophisticated, state-of-the-art and picturesque airports in the world and I am absolutely delighted that we have been able to translate this lofty vision into breathtaking reality. The challenges that we encountered at MIAL were unique that required an equally unique and robust team that could drive the project with passion. And they did so quite splendidly! The MIAL project has showcased to the world, L&T’s construction prowess and seamless project management capabilities. Perhaps, what is even more satisfying for us is that through this project, we believe, we have been able to take ‘stakeholder satisfaction’ to an all-time high. After all, we are not only in the business of creating landmarks of the future, we are also transforming lives for the better.

Page 6: ECC Concord

10 ECC CONCORD, October’13 - March’14 11ECC CONCORD, October’13 - March’14

40 million by 2015

A master plan was developed with a vision and framework for the long-term but at the same time realistic in the short term, to build a swanky world-class airport factoring in the limitations and challenges. The aim was to increase the present capacity of handling 25.6 million passengers and 0.5 million

tonnes of cargo per year to close to 40 million passengers and about a million tonnes of air cargo shipment by 2015.

Mumbai International Airport Pvt. Ltd.

Mumbai International Airport Pvt. Ltd. (MIAL) is a Public Private Partnership joint venture between GVK, Bid Services Division (Mauritius) Limited (BSDM),

Airports Company South Africa (ACSA) Global and Airports Authority of India (AAI). MIAL was awarded the mandate for operating and modernizing the Chhatrapati Shivaji International Airport (CSIA), Mumbai in April 2006. GVK leads the consortium with 50.5% stake while BSDM holds 13.5%, ACSA Global 10% and AAI the remaining 26%. MIAL’s vision is to transform CSIA to one of the world’s best airports.

Chhatrapathi Shivaji International Airport The swanky gateway

Grand check-in hall

The name of the mighty Maratha king sits well on the Mumbai International Airport for its resplendent splendor. The project is unique as it is perhaps one of the very few airport expansion projects that have been successfully completed despite the challenges of being a brownfield project, in the midst of a fully functional airport with only limited space available to operate smoothly as well as to expand in tandem to futuristic needs.

Facilities Existing Planned

Area for Passenger Terminals

Santacruz 64,000 sq.m 1,08,000 sq.m

Sahar 94,000 sq.m * 4,39,204 sq.m

Total 1,58,000 sq.m 5,47,204 sq.m

Passenger Boarding Bridges at CSIA

Santacruz 5 gate houses/6 bridges 10 gate houses/11 bridges

Sahar13 gate houses/

22 bridges25 gate houses /

52 bridges

Car Parking Spaces

Santacruz 1,050 1,050

Sahar 1,240 5,000

project was that new facilities had to be constructed after a phased dismantling of the existing structures.

Scope of work

Terminal Works

y One-roof new passenger terminal of 4,39,204 sq.m and ancillary facilities

y 63 contact and 10 remote stands

y Connector building (T1 C) for two domestic terminals T1 A and T1 B

Airside Works

y Airfield pavements including runway reconstruction and potential widening of 6.5 km of runways

y 3 new parallel taxiways, associated connectors and rapid exit ways

y 10 million sq.ft. of hard stands for new terminal and for general aviation, airline support and aircraft maintenance

y Taxiways and aprons for large wide-bodied ‘Code F’ aircrafts

y Associated support buildings, systems and utilities

Exterior view of Terminal 2

L&T at MIAL

Larsen & Toubro (L&T) was appointed by MIAL as the main contractor to design, procure and execute the works on the terms and conditions of the contract. As the airport was operational, the users would continue to use the airport during the performance of the work. L&T was to carry out the works with minimal inconvenience to the

airport operations and enable MIAL to meet Operation, Maintenance and Development Agreement (OMDA) requirements for such performance.

L&T was engaged in the planning, design, engineering, procurement, construction, testing and commissioning of the airport facilities on an EPC basis. The existing airport site was land-locked by the city and the biggest challenge for L&T in executing the brownfield

* Excludes unused Terminal 2B

Page 7: ECC Concord

12 ECC CONCORD, October’13 - March’14 13ECC CONCORD, October’13 - March’14

Mumbai International Airport was the country’s busiest airport until 2008 after which Delhi gained the pole position. Put together, Mumbai, Delhi and Chennai airports are estimated to handle more than half the traffic of South Asia.

In 2010, CSIA was ranked the 30th busiest airport in the world in terms of cargo with 671,238 tonnes handled. In 2011, the airport was ranked the third-best in the world in the 25–40 million passengers category by Airports Council International. Also in 2011, the airport was the 44th busiest in the world with 30,439,122 passengers handled, registering a 7.6% growth rate over the previous year.

Today, with a dedicated six-lane elevated corridor leading in to the airport that features world-class amenities, the Chatrapathi Shivaji International Airport is poised to set several benchmarks in India’s civil aviation sector.

Cargo

y Short term domestic cargo and international cargo facility

y International cargo terminal building of approximately 1,00,000 sq.m.

Ancillary Facilities

y 83.8 m high air traffic control tower and multilevel car park with 5000 capacity

Relocation and obstacle removal

y Relocation of contiguous facilities and integration of many duplicated facilities

y Enabling works for sustaining the operations while dismantling the existing buildings

Common utilities

y Power supply

y Drainage

View of Check in Counters

Perspective view of the departure bay

The elevated corridor leads to a 70 meter wide bay at each of the four levels of the terminal building where visitors are treated to tastefully landscaped areas and adequate signage. One can never feel lost in a 4.39 lakh sq.m expanse equipped to handle 40 million passengers per annum.

Resembling an ‘X’ from a bird’s eye view, the T2 has four levels. The uppermost is common for both international and domestic check-in facilities apart from having international security and retail areas. Domestic security and retail outlets

The 3.3 km, tree-lined, six-laned elevated corridor that takes a visitor to the Mumbai International Airport is only a succulent starter! The main course awaits at the swanky new T2 – a terminal that is a class apart and has already set several global benchmarks for airport terminals.

y 10 lakh cu.m concrete

y 58,000 t reinforcement steel

y 36,000 of structural steel

y 36,000 sq.m of skylight roofing

y 1.4 lakh sq.m of roofing

y 28,000 sq.m of façade

y 11,000 sq.m of cablenet wall type façade

y 46,000 sq.m of ceiling & cladding

y 20.6 km of chilled water piping works

y 188 check-in counters

y 5 levels of security screening

y 2.5 lakh sq.m of ducting

y 87 elevators

y 55 escalators

y 41 travelators

y 52 passenger boarding bridges

y 1,98,000 sq.m granite for flooring

Terminal 2 Welcomes you

Page 8: ECC Concord

14 ECC CONCORD, October’13 - March’14 15ECC CONCORD, October’13 - March’14

for domestic passengers and boarding gates are at the third level. The second handles all arrivals with the lowest (at-grade) level dedicated for facilities and added arrivals.

T2 features 188 check-in counters, 60 departure and 72 arrival immigration desks, 52 boarding gates, seats for 10,900 passengers and 102 wash rooms.

A rich collection of some 7,000 works of art is housed in a 3 km long area. Touted as one of the main attractions of the new terminal, it is also the largest in the country in a public structure.

161 elevators, escalators and travelators transport visitors to 16 lounges, a day hotel, a transit hotel, and a wide array of retail areas where they will be spoilt for choice with several popular brands merchandising their ‘latest to market’ on the shelves.

When it comes to food and beverages, there is not a cuisine that a foodie cannot find while at the terminal.

With ritzy retail spaces, luxurious interiors, vibrant lighting and a lot of pampering, the T2 at Mumbai is easily a place where one can spend hours indulging in the features, but

then, anybody who wishes to do that for long enough is reminded by a smooth voice announcing either their flight or their cab. Time to take off!

Project planning & control Winning takes planning

Constructing a brownfield airport in the middle of a fully functional airport which was, by the way, also one of the busiest in the world, called for several levels of planning, deliberations and brainstorming to evolve a plan that was both efficient as well as dynamic.

The project planning team played a vital role not restricting itself to simply scheduling and monitoring but working

y Sequencing of works y Project monitoring

y Airside staging

Phasing of Terminal 2

A potential phasing of projects was proposed well in advance since the new integrated terminal had to be constructed with minimal disruption of existing operations, within a restricted

on a whole spectrum of areas that included:

y Phasing of the terminal building

y Concept design and development of the reverse ramp to enable connectivity between Phases 1 & 2

y Terminal traffic management y Validation of traffic management

plan with IIT Bombay y Logistics management plan

Constructing a brand new airport in the midst of a fully functioning one had its fair share of challenges that required foresight, meticulous planning and considerable co-ordination to address and Team L&T came through with flying colors!

Check-in counters

Service cores at the departure corridor

Illuminated view of GFRC bullnose and ceiling

Page 9: ECC Concord

16 ECC CONCORD, October’13 - March’14 17ECC CONCORD, October’13 - March’14

site and over existing facilities, an operation that Mr. Sanjay Reddy, Vice President of GVK group described as “performing an open-heart surgery on a marathon runner who was running!”

The earmarked area included ramps, car park facilities, a statue, a police station, AAI offices, a temple, and overhead tanks, apart from the apron and contact bridges on the airside. To facilitate a smooth transition, L&T and MIAL developed and implemented a master phasing plan for the New Integrated Terminal 2. Firstly, work started on the south west pier of the new terminal for which a part of the existing Terminal T2 A was dismantled. This reduced the number of operational contact stands for which the team built gate expansions through which 3 new contact stands could be added on the eastern side of the existing terminal. Next, a mezzanine floor was added to the existing International Terminals T2 B and C, to relocate the facilities from T2A. Later, the taxiway was reoriented to accommodate the south west pier of the new terminal 2.

Since a major part of Terminal 2 was to be located on the car park area apart from the Up-Down and central ramps of the existing terminal, the ramps were relocated to the extreme left and right sides. Working in tandem, MIAL created a temporary structural steel multilevel car park on the east side of the terminal.

Work then commenced on the south west side of the new integrated terminal. However, the north side housing the services hub was affected by the presence of a police station and a temple and hence a new police station and temple were built outside the airport area.

Next to be tackled were the overhead storage tanks for drinking water and fire safety facilities for the existing operational terminal and the underground sumps for the sewage facilities. The underground tanks in the newly constructed south west pier were used as interim tanks for the domestic and fire water services for the T2 B and C terminals. The entire sewage network was also diverted to the new sewage sumps constructed in the future apron area.

Due to the severe space constraint, MIAL was unable to provide land for the setup of a proper office hence the project and

client offices were located at the project site and shifted several times within the span of 6 years of construction.

Another major hurdle for the project was the relocation of the Chhatrapati Shivaji memorial on the airport premises. Situated in the heart of the building, it affected the main baggage handling system, MEP rooms, AHU rooms, fire & domestic water tanks, pump rooms and thus had to be shifted. Though a sensitive matter, it was carried out following approvals from all concerned.

The last hurdle for the Phase 2 works was connecting the south west pier with the main terminal building. This was long delayed due to continuous movement of traffic from east to west through the T2 B and C ramps until after a thorough study of the traffic along with IIT Mumbai, a reverse ramp in the eastern side was proposed which facilitated traffic to enter and exit using the same side of the existing terminal, freeing the entire western side.

With this, the Phase 2 works were taken up and completed successfully following which the facilities at the old terminal were shifted seamlessly to the new international terminal.

With the old facilities having been removed, they paved way for the overall completion of the MIAL project which

constituted the 3 buildings on the east side with 43,732 sq.m BUA, 14 fixed link bridges and the entire east side apron measuring 3.3 lakh sq.m. This mammoth task was required to shift the entire domestic facilities to the new terminal and thus making Chhatrapati Shivaji International Airport an integrated terminal catering to both international and domestic passengers.

Concept design and development of reverse ramp to enable connectivity between Phases 1 & 2

This plan was conceived following a lot of brain storming sessions led by L&T’s project planning team and stakeholders such as the MIAL project team, the airport landside operations team, the land development team, and design personnel from L&T Rambøll.

The concept design which was developed with the assistance of L&T Rambøll, was further checked and attested by IIT Bombay for the available curvature and width of the road so that it could accommodate inward and outward traffic.

Terminal traffic management

Traffic bottlenecks at a busy airport which is also a brownfield project can

Sample Logistics Plan

Terminal phasing plan

Page 10: ECC Concord

18 ECC CONCORD, October’13 - March’14 19ECC CONCORD, October’13 - March’14

easily make headlines in a city like Mumbai that is bursting at its seams. The airport witnessed massive amounts of public traffic that had to be managed alongside construction traffic bearing heavy payloads. With work proceeding simultaneously in three mega structures such as the Terminal building, multi-level car park and elevated access road, traffic management which could

have been a nightmare was efficiently managed using Traffic and Interface Management.

Validation of traffic management plan with IIT Bombay

IIT Bombay was approached to validate the traffic management plan

and propose corrective measures, if any. Surveys were conducted by the transportation department of IIT Bombay that included both video graphic and manual methods before developing a circulation plan using simulation of the entire airport traffic. The traffic data of construction vehicles provided by L&T was also added to this data to check the sufficiency of the geometrics of the existing road facilities. Based on the outcome of simulation, the geometric details were upgraded at critical sections and intersections to avoid bottlenecks during peak traffic.

Logistics management

Even before the first step had been taken in the construction of Terminal 2, a huge road block that had to be cleared was to make land available because approximately 308 acres of airport land was encroached upon by 85,000 hutments housing around 400,000 people! This was prime space absolutely necessary to establish the main offices, batching plants, material storage enclosures, offices for subcontractors and labour colonies. Faced with such

View of reverse ramp

Sprint Review - Interior and Fit-outs Sequencing of head house area

daunting circumstances, logistics management played a vital role in setting up facilities away from the project site yet bridging the gaps through meticulous planning and flawless implementation.

As the MIAL project spanned a huge area, individual sub-projects were accorded the status of separate projects and small setups were provided close to each of these operations such as the Domestic Terminal 1C, Air Traffic Control Tower, South West Pier, Terminal 2 and Multi-level car park. Even the airside works were divided into sub-projects such as the Runway 14-32, Intersection works, Delta, Domestic apron works, International Apron works, Mithi river works and the like. The sub-projects operated out of portable container offices within the project area. The canteen facility was, however, centrally located where food was prepared for the entire site team and distributed to various locations for better control on quality and cost.

L&T’s main project office which housed the top management, project leaders and other vital support services department was relocated four times to various locations to make room for upcoming structures as the project progressed. Even the MIAL office was shifted three times with the attendant shifting of connectivity and other

amenities proving to be herculean tasks.

In several cases, contracts were formulated based on the criterion of non-availability of space! Sub-contractors and vendors were encouraged to hire warehouses near the airport site for operations and storage of material. Later, even MIAL hired a common storage warehouse at Bhiwandi to minimise material storage at site for want of space.

The logistics of construction material to the New Terminal Building which is landlocked was another extremely challenging task. Meticulous traffic management and logistics planning ensured that there was no disruption of airport operations or other construction activities.

Expectedly, a huge amount of debris was generated from the construction site on a regular basis and a common disposal point was assigned for all agencies. Further, a common agency was assigned to safely dispose off the debris without harming the environment in any way.

Sequence of works

Every single package was studied in detail at the design stage itself to analyse and understand the relevant interfaces and inter dependencies. The sequence of works was finalized after several rounds

of discussions with various stake holders such as designers, subcontractors and site execution engineers. This concept, however, could not be generalized for all work fronts as it could vary according to factors. For instance, any area involving BHS was given right of preference over all other services.

Project monitoring

At the peak period of construction about 1300 engineers and 14,000 workmen were involved at the MIAL project site. This is a really huge number to monitor and control for complete alignment to a common goal and plan. To enable this, the works were divided into four groups / sprints

a) Sprint 1 – Shell & Core

b) Sprint 2 – MEP & IT works

c) Sprint 3 – Airport Systems

d) Sprint 4 – Finishes

The handover and takeover dates for each of the group was finalized and signed off between all the concerned parties and later, progress was monitored against the planned dates. The strategy for monitoring the progress was also dynamic according to the stage of the project. For instance, during the initial stages, design and manufacturing were closely monitored and later the floor team was formed to play the pivotal role of handing over the areas to the next team. When all the disciplines had completed their respective work, a strategy of ‘Focus Area’ was adopted to complete the final bit of work with the joint efforts of all concerned. This work methodology helped progress without major stoppage of work due to misunderstandings / misinterpretations.

Airside staging

At any given point of time, 24 parking stands were required for the smooth functioning of the airport. This requirement led to granular planning whereby, completed areas were handed over before taking up additional work. The fact that flight schedules are published worldwide to all the aircraft carriers through NOTAM, called for robust planning and tight monitoring.

Page 11: ECC Concord

20 ECC CONCORD, October’13 - March’14 21ECC CONCORD, October’13 - March’14

Baggage handling system Where precision meets perfection

Passenger baggage reclaim area

Picture this. If nearly 3 billion passengers enplane every year at CSIA, one can well imagine the amount of hand and check-in baggage that has to be handled. The thought itself can be intimidating and it would be natural to imagine many thousands of hands and minds working to ensure accuracy and

The baggage handling system of the Mumbai International Airport has been designed and executed, embracing many new features and services, to make the processing of hold baggages easier, less stressful and reassuring for passengers. Initially planned to cater to passenger traffic of 9600 bags/hour up to 2015, the BHS

precision. Surprisingly, the truth is that all this is accomplished by an efficient ‘Baggage Handling System’ (BHS) with a lean team operating and managing it. This becomes critical especially since baggage mishandling can be an expensive affair for it cost the airline industry a whopping $2.06 billion in 2012 alone!

The baggage handling system of the Mumbai International Airport has been designed and executed, embracing many new features and services, to make the processing of hold baggages easier, less stressful and reassuring for passengers.

Baggage make-up area

has provisions for future expansion to manage 10,800 bags/hour.

System planning and conceptualisation

The conceptual design of MIAL’s BHS began with the study of international and domestic flight schedules, passenger ratios, baggage profiles, dimensions, shapes and other relevant data specific to Mumbai which was supplemented with inputs and requirements from MIAL (Client) and the Airports Authority of India.

The layouts, functionalities and architecture are well-defined for the system to provide a world-class baggage facility with enhanced safety, security and service. The common check-in principle has been used to optimise the facilities allowing any airline to use any check-in counter. This centralized system is based on the Tilt Tray Sortation (TTS) technology which transports the bags from inductions to predefined destinations so that bags can be delivered from any check-in counter to any make-up carousel, giving flexibility to the airport/airline operations.

An outstanding feature of the BHS is the state-of–the art, in-line baggage

handling screening system that uses a combination of automated and manual screening processes. The departure security screening system is based on a 5 level screening concept wherein eight EDtS X-Ray machines are utilised for Level 1 screening. At Level 2A (25 workstations) & 2B (12 workstations), an operator can view the alarmed images which are diverted

for processing through Level 3 CT scan machines (4 nos.). If bags alarm at Level 3, an operator can view the images in greater detail at Level 4 (5 nos.) and all images alarming at Level 4 will be diverted onto a manual search area, Level 5 is for Explosive Trace Detection (ETD) and/or passenger reconciliation. In case any threat is identified at the Level 5 screening process, the bag will

BHS departure system layout

Page 12: ECC Concord

22 ECC CONCORD, October’13 - March’14 23ECC CONCORD, October’13 - March’14

be diverted to the bomb cooling pit of the airport through an automated lift system and subsequently to threat bag carrying vehicles.

Design features

The foundation of this well-designed baggage system is an optimised mechanical layout, complete with the conveying lines, maintenance accesses, screening machines and processes complying to the prescribed security standards viz. International air transport association, International civil aviation organisation, Bureau of Indian civil aviation security, European security standards, Transport security, Administration, etc.

The design of the layout had been validated through computer simulations and emulations to verify the design and determine the maximum baggage processing time apart from system throughputs as defined in the specification.

The departure system is laid out declining from check-in hall at Level

4, transporting through Levels 3 and 2 to the make-up carousels in Level 1. The check-in facility has 6 islands for economy passengers with 28 counters on each island totalling to 168 counters. The 2 CIP VIP exclusive check-in facilities have 10 counters on each island. The bags are transported to the 18 make-up carousels after the security and custom screening as per the flight allocation. Majority of these conveyors are designed as suspended structures from the deck above, allowing the space below on the ground for drive-in, loading and drive-out functions.

Tilt Tray Sortation

The ‘Spine’ of the baggage handling system is the Tilt Tray Sortation (TTS) system which distributes the bags to the respective make-up carousels through the tilting mechanism. The airport features 2 sorters with 278 trays on each sorter operating at a speed of 1.9 m/s giving it a capacity to process 5400 bags/hr. The baggage from the check-in/transfer conveyor lines is supplied to two LS-4000E Tilt Tray Sorter via inductions.

The baggage is supplied one by one from the conveyor lines to the first belt on the induction where the TTS control system inducts the baggage onto an empty tray on the sorter, scans its barcode tag, transports it to the sorter and tilts it into a predefined carousel through the chute.

Control system

The ‘lifeline’ of the BHS is the control system that handles all the conveyors and sortation devices which are divided into Low Level Controls (LLC) and High Level Controls (HLC).

LLC includes all elements involved in the PLC (Program Logical Controllers) based control of the equipment such as panels, sensors, actuators, etc. All bags are virtually tracked and sorted to the designations as per the screening results by the PLCs.

HLC includes all elements of the control system above the PLCs, including networking of equipment, servers, workstations, etc. It controls the IT system of BHS which includes sort allocation controls, Message

Aerial view of tilt tray sorter

Distribution Systems (MDS), database management systems, management information systems, baggage information systems and baggage information display systems.

BHS receives flight information, baggage source messages with real time updates and communicates the sort destination

baggage processed messages to the airport host. The HLC equipment and the LLC devices are linked via the networking edge switches located at the BHS field.

The entire BHS system monitoring, control and visualization is centralised via SCADA (Supervisory Control And Data

Level 5 Screening Room

Vertical sorting unit

Page 13: ECC Concord

24 ECC CONCORD, October’13 - March’14 25ECC CONCORD, October’13 - March’14

Vertical sorting unit Security screening room

Acquisition). The status of individual equipment is represented in unique colours so that trained operators and maintenance employees can quickly identify and isolate the location of a fault and determine the cause within the entire system to en-force appropriate procedures.

Loads of risks to be mitigated

The criticality of BHS lies in precision. Even a single bag handled wrongly or reaching the wrong destination can create chaos. The challenges in the physical execution of baggage handling system are:

y Performance risks of the system

y Execution risks

Performance risks include the HLC development and integration, throughput compliance of the BHS layout apart from performance of the electromechanical components. These risks can be mitigated by performing repeated simulations and emulations to check the system and hardware capabilities apart from meticulous evaluation of HLC and LLC configurations through audits.

The optimised selection of special equipment such as high speed diverters, vertical sorting units, merges,

power turns, and the like assists the throughput and load balancing of the layout. This is further evaluated and ensured by analyzing simulation models for required throughput delivery and analysis on failure scenarios and requirement of redundancies. The risks associated with the performance of

electro-mechanical components such as bearings, rollers, motors, in terms of durability, energy efficiency, noise levels, wear & tear were mitigated through a selection of pre-approved makes, warranties, guarantees and factory tests.

Execution risk involves erection and interface coordination of the back-up structural steel assemblies with other terminal services such as fire protection/alarm works, air conditioning & ventilation systems and electrical & cabling works. The likelihood of clashes was mitigated through 3D model clash analysis which displays typical steel structure supports and the interfacing services. The clashes that were still identified at site were resolved by facilitating ‘on-site support’ to effect immediate changes for expediting works. The other challenge of the protection of sensitive equipment installed at site environmental conditions was mitigated through regular maintenance and sufficient protection.

Another innovative feature in the steel structure is the modular design using only clamps and screws thereby completely avoiding major work at site that will be beneficial from a long-term operational perspective for replacements and rectifications.

A bagful of interesting facts y Designed to handle 9600 bags per hour for the current phase with a provision

of expansion up to 10,800 bags per hour to cater to the future demand.

y 168 economy check-in counters, 20 VIP CIP check-in counters and 12 recheck-in counters (expandable from 14 to 17 nos. for future demand)

y India’s first airport to have exclusive VIP/CIP check-in facility

y Around 7 km of conveyors for transporting bags

y India’s first world-class energy efficient automated tilt tray sorters (lS-4000E) using Linear Synchronous Motor (LSM) technology which consumes only 25% of power

y Eight ‘Level 1 EDtS’ X ray machines and four ‘Level 3 CT scan’ machines

y Fully decentralized electrical controls through ASI bus modules aiding ease of installation and reduced cable requirement

y 1000 t of steel structures to support the baggage system

y Over 1400 motors and special equipment provided with variable frequency drives

Passenger Boarding Bridge connected to the first flight that landed at MIAL

The apron drive Passenger Boarding Bridges installed at MIAL are capable of manually or automatically extending, retracting and rotating to facilitate safe docking with commercial aircraft. In the current phase, fourteen fixed link bridges have been commissioned at MIAL with thirteen of them accommodating two boarding bridges and one featuring three bridges for a total of 29 PBBs.

All PBBs are of glass that comply to fire safety norms as per NFPA-415 and manufactured to withstand 5,000 cycles per year frequency of use and having three telescopic retractable tunnels with a maximum length extending to

two Code `C’ air crafts at the same time or serve a single Code ‘F’ or Code `E’ aircraft. For a Code ‘F’ aircraft, two of the PBBs can connect to the lower deck doors while the third PBB to the upper deck.

MARS with Code E feature two PBBs to serve either one wide body aircraft (B747) at two doors, or two narrow body air crafts (A318 & B737) at the same time.

Non MARS with Code E are equipped with 2 PBBs to serve either one wide body aircraft at two doors, or serve one narrow body aircraft at the same time.

43 meters. Advanced automatic leveling systems enable the bridge floors to rise or lower in accordance to the aircraft door sill height which oscillates during aircraft loading and unloading. The PBBs can be controlled using an on-board console apart from being remotely monitored and controlled through the Building Management System.

The Fixed Link Bridges are of three types such as MARS (Multiple Aircraft Ramp System) with Codes ‘F’ and `E’ and non MARS with Code `E’.

MARS with Code F are equipped with three PBBs each and are meant to serve

Passenger Boarding Bridges (PBB) are increasingly being seen as style statements at airports! These enabling structures are efficient and safe ways for passengers to board an airplane in any kind of weather condition.

Passenger boarding bridges Reaching out to an enriching experience

Page 14: ECC Concord

26 ECC CONCORD, October’13 - March’14 27ECC CONCORD, October’13 - March’14

objective of minimal downtime even during the design stage. The complete VHT system has been interfaced with the Building Management System (BMS) for monitoring and well-established brands such as Schindler, TKE and Kone offered international warranties and excellent service support.

No stumbling with these challenges

Logistics

Escalators and travelators were delivered in heavy segments (weighing in tons) after the main façade work was completed so it took some planning and effort to bring these segments into the terminal area through the available openings.

Interiors

The interior of elevators had to be upscale to be in-sync with the ambience of the terminal. To meet the demanding quality parameters of finishes, a specialized and dedicated vendor was engaged to work exclusively on enhancing the interior look and feel of the elevators.

Installation

VHT being supply items with long lead times had to be strictly monitored even during production and dispatch of units from Spain, Germany and China. In addition to stringent factory testing prior to dispatch, experts from these countries were invited to carry out the testing and commissioning.

Vertical & horizontal transportation A notch above!

Escalator set amidst grand interiors

Travelators at the departure corridor

View of elevators and escalators

The vertical and horizontal transportation (VHT) system of travelators, escalators and elevators aim to ease congestion and ensure a seamless flow of passengers (departing and arriving), goods, baggage, staff and visitors.

183 internal transportation equipment have been installed at MIAL of which 177 are located at the terminal area

consumption. The auto start sensors ensure that escalators and travelators start only on detecting approaching passengers to maximise energy efficiency and equipment lifetime.

The VHT blends well with the aesthetic standards and aspirations of the terminal architecture. Consistency in the standard of material used for the escalators and travelators was ensured while factors

alone. The number, location, speed and capacity of the VHT systems to be deployed was arrived at after a detailed traffic study conducted by an expert team.

Design and engineering

MIAL’s VHT systems are capable of non-stop operations, in either direction, and are designed for low energy

All major airports have to envisage heavy passenger flow and hence it is imperative that the building design factors the need for a hassle free and relaxed experience at the terminal.

of public safety were also considered to minimize risks to passengers.

Elevators

There are 87 elevators with stops ranging from 2 to 20 landings with a handling capacity of 544 to 5000 kg and speeds varying from 0.5 to 1 m/s. A high capacity elevator is installed exclusively for moving large show pieces and automobiles into the retail area. Six scenic elevators made entirely of glass greatly enhance the ambience of the terminal.

All elevators feature speed governors and double-up as ‘Fireman Lifts’ in case of emergencies. The elevators are also connected to seismic sensors to prevent people from getting trapped inside the lift in the event of an earthquake. This apart, safety and security features include CCTV, status displays, automatic rescue device and voice announcement & monitoring through BMS.

Escalator

With a capacity to handle 9000 persons / hour, the heavy duty escalators have a rated speed of 0.5 m/s and rise-range from 3 to 11.6 m. Among the 55 escalators installed is ‘India’s tallest airport escalator’ which rises to 11.6 meters going all the way from the 6th to 10th level of the multi-level car parking (MLCP). Eight escalators are exclusively for the transportation of passengers between MLCP and the terminal building.

Travelators

Travelators a.k.a ‘moving walkways’ have been thoughtfully provided around the terminal to improve passenger mobility. MIAL features 41 of such equipment with a handling capacity of 16,200 persons / hour and a rated speed of 0.65 m/s. If installed one behind another, the travelators would measure a whopping 1.3 km in length. MIAL also features the first ‘Pit-less Travelator’ installed in Asia which eliminates the need for a ‘travelator pit’ and simply rests on the finished floor.

Operations and maintenance

The VHT team embarked with an

Page 15: ECC Concord

28 ECC CONCORD, October’13 - March’14 29ECC CONCORD, October’13 - March’14

Electrical works Powering-up with passion

View of one of the substations

Control panels in substation

An array of control panels

Diesel generators for back-up power

Visitors to the airport terminal at Mumbai can now experience a cozy ambience and treated to a magnificent view of an art-wall based on cultural heritage that seamlessly blends life-size murals, art-form and antiques. The hard wood floor, pastel shaded walls and the warm and welcoming lighting evokes a pleasant feeling. Apart from the elegant look and feel, the lounge areas are

for safety, reliability, operability, maintainability and, at the same time, to ensure a modular design so as to allow the electrical services to grow along with the airport during future expansion phases.

Power system network

The main receiving substation at TATA

equipped with plenty of power sockets for visitors to plug in their electronic devices.

The scope under the electrical system broadly involved power distribution to all utilities, customized chandeliers, decorative feature walls and ceilings and life safety equipment with an IT back bone. The entire work was designed

The conceptualisation of lighting and power distribution system for the terminal area went through substantial contemplation for it plays a major role in enhancing the ambience and providing well-spread power availability. The entire focus was therefore on enhancing the ‘WOW’ factor.

Power DSS2, houses an installed capacity of 2 X 20 MVA, 33/11 kV transformer for terminal load, 1 X 20 MVA, 33/11 kV transformer for terminal HVAC and 1 X 20 MVA and 33/11 kV transformer as a standby.

y Two power sources from DSS2 to all the 11 substations (at terminal) that serve at 11 kV level

y A third source (DSSC3) for 4 substations on the western side of the terminal out of the total 11 substations

y Power back-up is from six 3 MVA, 11 kV stand-by diesel generator sets

y The electrical control system has been centralized using the SCADA modular design along with an enormous data handling capacity of 100000 tags

y 5 MVA of UPS power with 30 minute backup has been installed for critical IT system capacity as a 100% standby

SCADA – the control center

The SCADA system provides centralized control and monitoring for the entire terminal that controls emergency power distribution and supply to the essential sections by isolating non-essential BUS during emergencies. The system updates live power data and breaker status to BMS for monitoring apart from providing various historic trends for analysis and maintenance. The SCADA system is interfaced with a GPS clock for precise time stamping of each event and the flow-less graphic interface in ‘Windows’ environment is extremely user friendly.

Billing server

The billing server fetches 3000 various meter data required for commercial billing and is sent to SAP through BMS interface for the various tenants.

Page 16: ECC Concord

30 ECC CONCORD, October’13 - March’14 31ECC CONCORD, October’13 - March’14

Terminal internal electrification

The power received from the utility building is distributed to 11 substations in the terminal for various utility and passenger amenities. 300 km of LT cable was laid through many public and non-public areas mostly above the false ceiling to help interface many services.

Clever daylight harvesting

An efficient daylight harvesting system is in place. At level 4, around 36000 sq.m of sky light enters out of 72000 sq.m of roof area which is 50% of the area and all electrical lights have been integrated with the skylights in such a manner that gradual reduction of sunlight during

transition is so smooth that a visitor at the terminal area will hardly be able to notice when the natural light switches over to electrical lighting.

Chandeliers – magnificence to look up to

Chandeliers designed on the lines of lotus flower motif add to the magnificence of the waiting areas at both the domestic and international terminals. These extravagant light fittings have been customized in design and manufactured to suit the classy environment. Numerous glittering LEDs placed atop the chandeliers resemble fire flies during night.

SCADA panels

Quantities bespeak the size

3 MVA, 11kV DG Set - 6 nos

HT/LT Panels - 290 sets

Transformers - 28 nos

UPS / ATS - 39 nos

HT / LT Cable - 250 km

Cable Tray - 55 km

Distribution Boards - 1800 nos

Conduiting - 750 km

Fire Trace System - 36 sets

the evenings will be compensated by 3 kW metal halide lamps for each skylight fitting. Simply put, the

Lighting works Highlighting the features

Chandeliers resembling lotus petals

Terminal 2 of the Mumbai International airport is exquisitely lit with all areas such as public, non-public, retail and landscape aesthetically treated based on the intended use and functionality of the respective areas. The project team that planned lighting for the key areas of the terminal had more than just the specs to contend with.

Aesthetically bright

The Lighting Control & Monitoring System (LCMS) features advanced innovations such as day-light harvesting, lumen maintenance, time scheduling and scene setting to optimise energy efficiency using DALI, DMX & circuit switching controllers. Interfaced with the BMS, the system is equipped to

They were looking for an integrated and resilient distributed lighting system to optimise energy efficiency, meet LEED requirements, maximise flexibility for the future, and at the same time, enhance passenger experience. They also had the task of ensuring that the lighting blended with the image and identity of the country.

Visitors to the Terminal 2 will always be awed by the exquisiteness of the lighting. All areas such as public, non-public, retail and landscape have been aesthetically treated based on the intended use and functionality of the area.

Page 17: ECC Concord

32 ECC CONCORD, October’13 - March’14 33ECC CONCORD, October’13 - March’14

Lighting that integrates skylight and electrical light

Lighting at the head house roof

provide automated control of lighting by using daylight sensors which responds in real time to varying conditions of daylight and adjusts the lighting based on the extent of daylight available. The lighting changes according to time and date and manual over-rides are possible using touch screens. Mono-colour LEDs, RGB LEDs in retail, landscape and water-feature areas are grouped and controlled through DMX for dimming and creating sequences to create a vibrant atmosphere.

Lighting the art wall

A standout feature of CSIA is an impressive and expansive art wall located on the east and west sides of the T2 processor building that features themes inspired from Indian heritage presented most effectively, creatively and mystically. Each theme captures glimpses of this great country, its passage through history and what sets it on top in the pantheon of countries of the world. The art wall is lit by a wide

array of decorative and combination light fixtures.

Crowning lights

Several decorative ceiling-mounted chandeliers enhance the look, feel and aesthetics of the circulation area that have been custom designed like flower petals to resemble the CSIA logo. The diffusers are made of Borosilicate float glass in amber colour.

There are 943 such chandeliers that crown Terminal 2. Weighing between 65 to 75 kg depending on the type, these are supported by suspension tubes, which are connected to the substructure of the false ceiling such that the mounting height varies between 2.6 to 3.5 meter from the finished floor level. They are also integrated with LCMS to remotely control the lamps and monitor status.

Efficiently lit-up

The non-public area lighting system is designed to enhance task performance, improve appearance and ensure cost and environmental efficiency. Areas such as the MEP rooms, substations, baggage handling systems, office spaces and closets

have been designed for trouble free, safe functioning with sufficient emergency backup. Occupancy sensors located in office spaces automatically adjusts lighting lumens based on the presence or absence of occupants in the room.

Public area light fixtures - 44,000 nos

Non-public area light fixtures - 13,000 nos

Chandelier - 943 nos

LED fixtures - 17,000 nos

Decorative ceiling lights at retail area

Lighting at the retail area bulk head

Page 18: ECC Concord

34 ECC CONCORD, October’13 - March’14 35ECC CONCORD, October’13 - March’14

IT systems Taking IT sky-high

FIDs screen at the check-in counter area

It was no different in the case of MIAL. The IT infrastructure was designed to meet such demanding operational needs by providing complete user friendly access at all passenger interface points apart from ensuring safe operation of the Terminal.

L&T set sky-high benchmarks in providing a robust IT environment and the scope of work of the enabled

radio), airport operations (Airport Operational Database – AODB) and information message broker also fell within its ambit. The IT system is a large scale entity that interconnects the Terminal with the other ancillary buildings.

Network – the backbone

The network infrastructure connects

systems included procurement, design, planning and progress monitoring, QA / QC and project implementation of a dedicated network backbone and flight information display system. Security systems (access control and CCTV), utility systems (public address & voice alarm, building management, distributed antenna and trunk mobile

Operating an airport is like managing a small city with numerous amenities, facilities and systems that need to work seamlessly to enable its smooth functioning. Modern day airports depend heavily on Information Technology to simplify complexities and improve efficiencies.

Interior view of Airport Operations Control Center

IT devices located throughout the facility to equipment located in Telecommunication Closets (TCs), core network switches and servers located in Main Computer Room/s (MCR/s) and IT switch rooms. Devices and systems were interconnected using standard CAT 6 UTP cables which were in turn connected onto the network through access switch ports. Redundancy was provided for across levels for smooth operation using a three tier architecture comprising core distribution, access switches and a built-in capability to allow for future expansions.

The IT network utilises the Juniper network equipment and a 3-tier carrier grade (scalable, converged for voice and data support) secured dual redundant data centre. The network is on a ‘10 Gig’ backbone that is designed to avoid downtime in case of a failure of a link, switch or any other component. A redundant fibre backbone interconnects the TCs and MCR (Master Control Centre)

accommodating servers for the entire airport systems.

The magnitude of the installation task is in the numbers: 2000 km of CAT 6 (UTP) cabling, 250 km of fibre cabling, 500 access switches, 18 distribution switches, 2 core switches, internet and internal firewalls, server aggregation switches, server farm switches and other security devices.

Airport security

Security is one of the most challenging of airport operations. A versatile and robust CCTV system takes care of wide-spread surveillance across the terminal covering all public areas including back of house operations, multilevel car park, elevated road and the ATC. The CCTV system consists of PTZ cameras, IP fixed dome cameras and IP fixed cameras connected to the IP network with video and network storage recorders. The access control system is designed to restrict access at all interface points for staff and

security, airlines and other back of house operational personnel at the piers and international & domestic operations.

The flight information display system informs passengers across the terminal at check-in desks, departure & arrival lounges and is integrated with the airport operational database. The public address systems deliver clear intelligible speech and voice alarms to various zones across the terminal in addition to automated and manual announcements.

Airport Operation Control Centre (AOCC)

The AOCC is located in the heart of the terminal and is the main command and control facility controlling the 24 x 7 operation of the CSIA Terminal at both landside and airside. It also encompasses the Security Operation Control Centre (SOCC), the Crisis Management Centre (CMC), the Terminal Services Centre, Airside

Page 19: ECC Concord

36 ECC CONCORD, October’13 - March’14 37ECC CONCORD, October’13 - March’14

FIDs screen of baggage handling system

Services Centre (ASC), the Engineering Systems Management Centre (ESMC), and the Telecommunications System Management Centre (TSMC). Three large video walls ensures clear monitoring for the operations team. The AOCC also features a dedicated visitors gallery for accommodating high profile visitors and stake holders.

View of master control room

Systems integration and information broker

The systems integration package integrates the various IT systems (IT network, BMS, FIDS and PAVA, ACS and CCTV) with the airport systems (Baggage Handling System, Passenger Boarding Bridges, Visual

Network Data & Voice Point

26,000 nos

CAT 6 UTP Cable 1560 km

OFC Cable 333 km

Active Switches 492 nos

CCTV Cameras 2914 nos

Access Control Points

891 nos

PA Speakers 3931 nos

BMS Points 1211 nos

DAS Antennas 931 nos

TMR System 148 nos

Flight Information Display Screens

1026 nos

The numbers are numbing!

Docking Guidance System). It also integrates the mechanical & electrical systems such as HVAC, fire detection & protection, fuel hydrant system, electrical power and lighting systems and the airport’s operational database.

Various systems have been integrated with the AODB using the Information Message Broker (IMB) which is based on Web Sphere Process Server and Web Sphere MQ. IMB does the transformation, validation and information and data dissemination from one system to others as required.

IMB receives flight data, resource and planning information from AODB to share with other systems, post validation. IMB receives real time updates like on-block, off-block, chute updates, first bag, last bag, baggage statistics, check-in counter updates from BHS, FIDS and VDGS and sends this information to AODB.

Extensive testing was done in the Integrated Test Facility (ITF) as well as in the actual production environment, for flawless integration.

HVAC package A warm welcome to a cool ambience

Cozy interiors that give a soothing experience

Thanks to a well-designed HVAC package, passengers are greeted by a comfortable ambience of 23°C±1°C and RH in comfort zone at the Mumbai T2 Terminal and a suitable atmosphere for the trouble free operation of critical equipment and gadgets. The occupancy and fresh air loads are based on National Building Code (NBC) - 2005 recommendations.

Design Criteria

The terminal area was divided into

100% treated fresh air units supplying treated fresh air to tenant spaces such as retail, duty free shops, restaurants, eateries and CIP/VIP lounges within that zone.

Life safety systems such as smoke extract systems and lift / stairwell processor pressurization systems are based on the respective NFPA codes. The smoke extract systems for public areas include smoke extract fans designed for high temperatures (300°C) and fire rated ducts.

several zones based on various factors, requirements and functions and then accorded weightage based on their functions such as IT, critical services, passenger and retail zones.

The terminal building had 13 zones with each one having a mechanical room that housed the Air Handling Units (AHUs) and the heat recovery units for that particular zone. The heat recovery unit consisted of enthalpy wheel and supply / extracts fans with filters. Some mechanical rooms had

If passengers are greeted by a comfortable ambience of 23°C±1°C and RH in comfort zone at the Mumbai T2 Terminal it is thanks to the well-designed HVAC package.

Page 20: ECC Concord

38 ECC CONCORD, October’13 - March’14 39ECC CONCORD, October’13 - March’14

Detailed Engineering and Installation535 drawings were painstakingly prepared and meticulously checked in ‘3D Naviss Works’ for clash detection prior to releasing it for site execution. For clash resolution, 3D Revit software was used as it required coordination with multiple utility services. The terminal area was divided into buildings and levels to enable better control on

installation. Pipes of about 25 km and over 300 rmt ducting from AHUs were distributed in the building spread over a very large area.

Chilled Water System

The utility room located 1.5 km from T2, pumps 5800 cu.m/hr of water to the terminal through a 1.1 m diameter, pre-insulated underground pipe located below the existing roads. It was essential

that each pipe joint was 100% leak proof as rectification of joint failures would be extremely difficult once commissioned. Extensive radiography tests were conducted prior to hydraulic testing to ensure zero leakage.

Air Distribution System

All AHUs are typically ‘two-tier constructions’ with supply air fans and filters in the lower tier and return

Type of fans CFM Qty.

Smoke exhaust fans 1,155,000

Staircase & lift well pressurization fans

395,000

Baggage area ventilation 1,342,000

Kitchen exhaust 108,000

Toilet fans 1,800,000

Other fans like LV closet, MEP room, pump room

317,000

Major HVAC equipment

Description Units Quantity

Chillers (2500 TR) HT

Nos 6

Cooling tower Nos 6

Pumps Nos 21

AHUs Nos 82

FANs Nos 346

FCUs & CAHUs Nos 410

CRAC units for MCR room

Nos 6

Major HVAC items

Description Units Quantity

Ducting Sqmtr 350,000

Piping Rmtr 25,000

DDC panels Nos 473

Electrical & BMS cabling

Rmtr 150,000

VAVs nos 1,800

Sensors Nos 3,300

CRAC units for MCR room

Nos 6

Chiller plant

air fans in the higher levels. The AHUs are located in the basement area for easy maintenance apart from keeping servicing personnel away from visitor zones to ensure passenger safety. Medium pressure ducting carries dehumidified air from AHUs to conditioned spaces while filters with activated carbon and alumina impregnated with KMnO4 (Potassium Permanganate) are used to combat the effect of exhaust fumes from aircraft that could be present in the fresh air. On the upstream side, pre-filters and back filters have been provided.

Water Flushing and Commissioning

To achieve the desired chiller performance and maintain low power consumption of chillers, it was essential to meet the required water parameters before circulation through chillers and AHU coils. Being a large system, the

water became very dirty on the first fill following installation. About 35 lakh liters of water was used to flush and remove sediments before the final commissioning.

Energy Savings

An airport never sleeps. To operate it 24 x 7, the annual power consumption of the HVAC system alone could run into several millions which is unaffordable. The answer lay in energy conservation at all times through chillers of very low power consumption and high efficiency pumps. The thickness of insulation was also carefully selected to maintain low temperature drop from utility to building distribution. For all to breathe easy considering the high occupancy rates, the building required 14 Lakh cu.m/hr of fresh air which was met by treating exhaust air through heat recovery units to lower the intake of fresh air load

on the HVAC system. The controlled fresh air is then supplied through the CO2 sensors.

The condensate recovery system was commissioned by pumping low temperature condensate generated from AHUs back to the cooling towers to reduce the cooling tower inlet temperature and thereby the power consumption apart from providing savings in the make-up water consumption of cooling tower. Cooling tower fan motors are operated through Variable Frequency Drives (VFDs) for energy savings at part loads.

Building Automation System (BAS)

Yet another unique feature of Terminal T2 is BAS with 936 (473 DDCs + 463 VAV converters) controllers and over 3300 sensors installed for the HVAC equipment alone. This system has been integrated with the Building

Exterior view of utility complex

Page 21: ECC Concord

40 ECC CONCORD, October’13 - March’14 41ECC CONCORD, October’13 - March’14

Management System for remote controlling and monitoring of all HVAC equipment including Variable Air Volume boxes for energy conservation and comfortable air-conditioning. In addition, the Chiller Management System (CMS) has also been integrated with BMS for remote monitoring.

Quality

Several national and international standards have been strictly adhered to, implemented and inspected at every stage during manufacture, delivery and installation.

y Chillers and AHUs are AHRI certified and use environment friendly refrigerant (R134A)

y Motors used in pumps are energy efficient (EFF-1) complying to IS 12615

y Fire dampers meet UL 555 standards

y All fans are AMCA certified

y Smoke extraction ducts are 2 hours fire rated as per BS 476

y A separate fire paint booth was established to ensure uniform coating quality

y The ducting work was carried out as per SMACNA standards using appropriate tools and tackles

y The supports were fabricated in a dedicated workshop and fixed using laser beam technique to maintain a straight line and uniformity

y Piping is done as per IS -1239 & IS 589

y Standard welding procedures were followed as per IS 10234

Piping works for chiller water

Gas suppression system

Air handling units

Fire detection and protection system Warriors always on high alert

MIAL features the world’s most advanced Fire Alarm System (FAS). Systems such as VESDA (Very Early Smoke Detection Apparatus) have been deployed using 60,000 detectors and devices connected in loops using 650 km of cable to offer one of the most efficient fire management systems.

Covering four lakh sq.m of building

Fire Protection Systems

y Internal hydrant system : 400 nos

y External hydrant system : 100 hydrants connected with 4 km long ring fire main

y Sprinklers : 50000 nos covering every nook and corner of the terminal

area, the FAS equips the fire commander with the convenience of extinguishing a fire from a remote and dedicated fire command centre. The Fire Protection System at T2 employs over 50,000 sprinklers connected with 270 km pipe and 500 hydrants. Rooms containing computing systems have been installed with gas suppression system that uses eco-friendly NOVEC -1230 gas.

Risk mitigation at all levels and types are of paramount importance in public buildings such as airports. Large capital is invested for the safe and secure operations of a terminal building and fire detection and protection system is significant among them.

Page 22: ECC Concord

42 ECC CONCORD, October’13 - March’14 43ECC CONCORD, October’13 - March’14

y Gas suppression system: for all communication rooms

y Pre - action sprinkler system: control room equipment protected with pre action sprinkler system, with double interlock using air and detection

y Water curtain system: installed at MLCP to isolate the affected area

y First aid fire extinguishers: 3500 nos installed for first level of protection

y Fire water pumping system : 6 pumps connected to 470 cu.m underground fire water tank

Integration

Integration of the Fire Alarm System is a critical part of the testing and commissioning activity. The complete

terminal building was divided into 350 fire zones as per the fire strategy and all important electromechanical and IT services such as HVAC, access doors, public announcement system, baggage handling system and vertical & horizontal transport system were integrated to meet the requirements of this fire strategy and evacuation plans. A comprehensive cause and effect matrix was also developed to identify the operational mode of the electromechanical and IT systems falling in the respective fire zones in case of fire alarm activation.

The fire alarm panel provides signal to various systems such as air handling units, fire dampers, fans, fire shutters of BHS, travelators, escalators, elevators, access controlled doors and public announcement system

to automatically operate as per the cause and effect matrix.

Never dampened to meet challenges

The biggest challenge was to create a system with global benchmarking while having to interface with various other services of the terminal. Testing & Commissioning of Fire Protection System on finish works such as false ceilings, wall claddings and carpeting was difficult that called for close monitoring. Several advanced pneumatic and leakage tests were carried out for gas based fire suppression systems during the testing and commissioning stage to ensure safety.

Public health engineering Solving watery issues

Meeting the water demands of an airport terminal is crucial that can allow no lapses. The PHE package at MIAL had its own share of complications primarily due the major quantities involved in the scope and due to the large number of vendors being involved for the supply of numerous construction material.

Even the orders for the PHE package came through in a staggered manner throwing planning and implementation out of gear several times over during the course of the project.

The Brihanmumbai Muncipal Corporation supplies domestic water to the terminal while water for flushing is catered to by treated grey water. The internal drainage system is single stack with hubless CI piping and individual venting arrangements. Planning and implementing the drainage gravity flow piping was truly a challenge due to clashes of various other services.

Another striking feature is that all the wash rooms have been provided with pipe chases featuring exposed piping

systems. The water input to this system undergoes a series of treatments including screen, CASS basin, pressure sand filter, UF, RO and finally the treated water is discharged for utilization to cooling towers, flushing purposes, gardening and landscaping.

to avoid wall chasing and for easy maintenance. Rainwater is efficiently harvested across the entire terminal as a green measure and adequate storm water piping drains off the runoff water while manholes at all accessible locations ensure easy maintenance. Several pumping systems of the existing terminal have been refurbished and put to use at the new terminal as a cost saving initiative.

Sewage Treatment Plant

For the very first time in India, a 10 MLD Sewage Treatment Plant employing UK based CASS (Cumulative Activated Sludge System) technology was installed which has substantially reduced sludge volume as compared to conventional

y 10 MLD SBR type Sewerage Treatment Plant

y 4 MLD Sewage Treatment Plant

y 12 Sewage pumping stations

y 120 km of piping

y 15 Hydro-pneumatic systems

y 157 Public / staff washrooms

y 22 De-watering pumps

Central alarm control facility

Sewage treatment plant

Page 23: ECC Concord

44 ECC CONCORD, October’13 - March’14 45ECC CONCORD, October’13 - March’14

Finishing works The final stroke of perfection

Departures - south west pier corridor

Glass Fiber Reinforced Gypsum

Perhaps the first attraction for passengers will be the Head House Roof (HHR) that has been architecturally finished using Gypsum Fiber Reinforced Glass (GFRG). A light weight material, weighing only 8 kg/sq.m, GFRG can be easily molded into various shapes and have been

panels have been electro-galvanized following fabrication and are polyester powder coated using custom colors. Other areas have been finished with a warm wood grain to create a cozy atmosphere. For enhancing the acoustic property of the ceiling and to control sound up to 35 dB, sound absorbent fleece has been used. About 90880 sq.m of such metal false ceiling has been commissioned at the MIAL project.

decorated using dichroic glass to give a vibrant look to terminal roof. The intriguing HRR structure resembles a honeycomb and covering a vast area of 48,100 sq.m.

Acoustic metal false ceiling

The ceiling above most public areas has been covered with attractive acoustic metal panels. 0.6 mm thick, these cold rolled carbon-steel

The new Terminal 2 is perhaps Mumbai’s first public building that doubles up as an art project. Ritzy and magnificent interiors that greet visitors include inspiring works of art, plush seating comforts, posh retailing areas, shiny marble flooring and ceiling panels with awesome chandeliers.

Tikri works

The Rajasthani handmade glass inlay pattern called ‘Tikri works’ is artistically acclaimed the world over. The mega column wall fascia of the terminal are adorned with Tikri works based on a ‘falling leaf ’ theme. About 30000 leaf shaped glass pieces cover an area of 1620 sq.m immersing it in dazzling beauty. A machine cut template was used to achieve 100% accuracy of the design intent.

Mega columns and coffered ceiling

Designed on the likes of the columns of the Fathepur Sikri, the mega columns are some of the most prominent elements of the terminal architecture. 28 mega columns (12920 sq.m) have been architecturally finished using GFRG, of which 19 tower to a height of 26 m from Level 2 all the way to Level 6. The 7 columns placed at the entrance of the terminal tower from Level 1 to Level 4 while 2 columns enclose staircases leading to the head house roof from the departure bay at Level 4. 426 various sizes of GFRG panels have been used for the overall cladding of these mega columns.

Fixed link bridges

The fixed link bridges are the final leg of the airport experience to a traveler just before he/she boards an airplane. To accord a fitting and royal farewell to a visitor who has already been pampered by the splendid interiors right from the entrance, the interiors of the fixed link bridges are exquisitely done with soft carpeted floors, artificial stone clad walls, acoustic metal ceiling and automatic glass doors partitions featuring brush finished steel handrails.

Mega column with Tikri work, water feature and curved glass

Interior view of fixed link bridges

Green wall with waterfall

Page 24: ECC Concord

46 ECC CONCORD, October’13 - March’14 47ECC CONCORD, October’13 - March’14

Floor management Stitching it together

View of the expansive check-in area

The construction of the Mumbai International Airport was very much like solving a huge engineering jigsaw puzzle. It involved several teams working feverishly in tandem at the same location demanding insightful management for targets to be achieved as per schedule or even earlier. Project management had the unenviable task of coordinating between 5 structural

Floor Team which soon became the face of L&T for the client as well as the internal customer, across disciplines. This organization mirrored a typical matrix structure, with the floor manager becoming the focal point for the various disciplines.

Coordination between multiple agencies was thus effectively streamlined and processes were set-up to manage

systems, 11 MEP systems and over 20 interior packages, all working with each other requiring a staggering amount of multi-stage clearances. A multi-functional core team popularly known as the ‘Floor Team’ took on the onus of ensuring that everything went like clockwork. Issue resolutions, interface management and subcontract interactions were all handled by the

The floor team worked upon issue resolutions, interface management and subcontract interactions becoming almost the face of L&T for the client as well as the internal customer, across disciplines.

Baggage reclaim area

disputes, mismatches and site clashes. A floor manager was akin to a project manager for the floor and some of the critical tasks handled by him included:

y Manage and document front clearances

y Interface point among various stakeholders

¾ Design

¾ Procurement

¾ HSE/QA-QC

¾ Package teams

¾ Clients

¾ Subcontractors

y Sequencing, monitoring and de-bottle necking of works in line with schedule

y Ensuring HSE, protection and housekeeping on the floor

y Issue resolution, particularly multidisciplinary problems

y Floor logistics

Floor management expeditiously resolved over 2000 clashes and coordinated the contractual closure of additional items which were critical for the completion of the

project. The functioning involved cordial meetings and joint decisions that kept the client happy at all times. A systematic problem solving methodology was followed that involved weekly log implementation, interface with design and weekly

key issue resolution meetings with clients. Other responsibilities included efficient management of the floor area, creating better working conditions, maintaining workmen discipline and creating a common resource pool comprising access devices and the like.

Page 25: ECC Concord

48 ECC CONCORD, October’13 - March’14 49ECC CONCORD, October’13 - March’14

Testing, commissioning & trials The final sign-off

Cable net wall

Immigration counters

For the final act of a safe and orderly handing over of the MIAL project, testing was the crucial last stage. Commissioning of the airport involves networking with innumerable entities such as the client, consultants, architects and vendors to understand every single technical requirement of the project in detail.

Equipment testing was conducted during manufacturing and factory acceptance tests whereas project site and pre-commissioning tests were done on-site.

Individual system tests included commissioning and performance tests. Commissioning were tests focused on additional levels of complexity and

The Master Testing Plan (MTP) for the project was in accordance to the conditions of the Main Contract (MCoC) which L&T had entered into with MIAL. The main work breakdown for Testing and Commissioning (T&C) was made as per the requirements of the MCoC and was divided into four major stages following a bottom-top approach.

Testing was a crucial stage that preceded the safe and orderly handing over of the MIAL project. The process of testing the specified and quantifiable characteristics of an equipment/system guarantees its operability and for the airport, it was in terms of performance, reliability, safety and traceability apart from ensuring compliance to the design intent and specifications.

interoperability between equipment groups and inter-connecting components. Performance tests ensured load, capacity, throughput, utilization, stress testing, fail over tests, emergency, contingency, equipment recovery behavior and backed-up data (re)configuration tests, including any data network related components.

Integration testing which confirms functionality across systems were conducted in two stages: firstly at the integration test facility and then at the site. The tests were conducted in a controlled test facility. The systems were connected through a mock-up of the network communications to mitigate risks at an early stage with a strong focus on software / firmware functionality of different systems.

Scope of T&C y 35 systems under the scope of L&T

y 21 systems by MIAL

y 68 interface via dedicated cabling

y 110 interface via shared IT network

y 08 interface via IT shared network through IB

y 835 string testing

y 5 group testing

y 55 scenario testing

Considering the size of this project and involvement of different facilities such as utility building housing the multi receiving substation, HVAC chillers, sewage treatment plant; NACIL building, air traffic tower, Terminal 1C where the master computer room 1 is located, it was necessary to have a master interface diagram, a master system interface list and sequence of commissioning for different systems.

The terminal was divided into twelve different blocks identifying the coverage area of different systems and a sequence was developed to have a seamless T&C with proper monitoring

Major responsibilities of T&C team

y Develop guidelines and templates for testing, commissioning, training, project operation trials, operation and maintenance manuals

y Review and validation of test procedures as per the technical specifications, interface control documents

y Identification and incorporation of special requirements of OMDA, specific standards like NFPA, ASHRAE, NEC, and client requirements

y Sequencing, phasing and monitoring the T&C activities of all systems

y Coordination for project operation trials

y Develop sequence of T&C activities between facilities and readiness for project operation trials to commence

y Master system interface matrix as per different PTS and ICD

y Commission sequence for different systems

y Integrate testing sequence for different interfaces

y Develop integrated T&C schedule

Testing, commissioning and integration of multiple airport systems needed special skills and the ability to communicate effectively to define and redefine every single requirement so as to advance the stage of static installation with respect to prescribed requirements.

Project Operation Trials

Integration Tests

Individual System Tests

Equipment Tests

Page 26: ECC Concord

50 ECC CONCORD, October’13 - March’14 51ECC CONCORD, October’13 - March’14

Commissioning and Integration testing of more than 56 systems with 186 interfaces involving different people required considerable projection and planning. Continuous interaction with all participants and keeping them abreast of the developments through timely communication and exchange of information helped mitigate this issue.

T&C workshops and meetings were regularly conducted with the prime objective of facilitating agreements with all sub-contractors regarding roles and responsibilities, timely provision of interface information and identification of critical issues.

Challenges y The most important challenge for

L&T as the main contractor was to play the role of Master System Integrator (MSI) as the scope of the System Integrator (SI) was limited only to Information Broker (IB) centered systems

y Identifying the different types of interfaces and making a particular

subcontractor responsible as system initiator for a group of interface

y To conceptualize the entire business model of the functions of the airport and develop the integrated T&C sequences

y Review, coordinate, monitor, witness of specific requirements during the execution of integration testing

Project operation trials

Project operation trials conform to airport processes and standard operating procedures and have a strong human element focus, predicated on the integration and inter-operability of systems and facilities.

In airport operations, passenger and baggage are prime considerations and hence there were baggage and terminal trials which involved core, support, contingency and emergency processes.

The baggage trials involved different stakeholders like the airlines, airport operations, airport maintenance,

customs, and security team to familiarize themselves to the systems and facilities.

Terminal trials started in May 2013 with single process trials where the focus was on a single process like terminal entry, trolley movement, check-in, staff entry, delivery of goods and waste management. Once the single process trials were completed successfully, integrated trials started where different processes were simulated in an integrated manner like departure trial involving the check-in process, security screening, immigration and boarding. Integrated trials were conducted in non PPE environment involving different stakeholders such as airlines, customs, immigration and CISF. Contingency trials were also conducted for different types of failures like power; network and emergency. During the advance trails the entire facility including multi-level car parking, elevated road network was done with 2000 trial volunteers (trial passengers).

Closer view of the check-in counters

Airside works Soaring above the superlative

Bird’s eye view of the airside

The planning and phasing required relentless coordination between design, engineering, procurement, purchasing, and project controls with granular attention to detail. The initial projects falling under the airside works, such as apron L, 14 loop, 32 loop, taxiway D stages 1 & 2 and the central loop were aimed at enhancing the infrastructure and airport efficiency. These projects were taken up in the early phase so that

the major part of the runway upgrade projects could be delivered on time.

Planning and phasing of airfield works: were divided into ‘Seasons’ with one season defined as the working duration from 1st October to 31st May of a particular year.

Season 2008-09: During this season, the projects executed included the delta

taxiway stage 1 & 2, apron H, central loop, 14 end loop, 32 loop and T1C apron, selected for multiple work front creation and improving the efficiency of the runway.

Season 2009-10: Projects taken up and completed were the runway 14/32 up-gradation, runway intersection works, T2 apron, delta taxiway stage 3 to 6 and runway 09 west end.

The journey towards creating a world-class airport at Mumbai started in mid 2007. The challenge was to strike a balance between undertaking a complex construction project whilst maintaining operations in one of India’s busiest airports. Being a brownfield project, it was absolutely necessary to envisage the complexities involved in executing airside works without disturbing operations.

Page 27: ECC Concord

52 ECC CONCORD, October’13 - March’14 53ECC CONCORD, October’13 - March’14

Aerial view of the apron

Major Quantities

Excavation Filling WMM GSB CTB PQC Asphalt

2008-09 2.84 0.98 0.15 0.04 0.09 0.20 0.17

2009-10 6.19 2.41 0.59 0.16 0.67 1.61 0.63

2010-11 4.41 1.41 0.45 0.17 0.31 1.07 0.76

2011-12 4.80 1.67 0.49 0.28 0.32 1.09 0.07

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

Cum

Quantity in Lakhs

Season 10-11: The projects handled included the runway 09/27 up-gradation, T2 apron, delta taxiway stage 7 to 9 and Mithi River phase 1.

Season 11-12: The Mithi River phase 2, Mithi River bridge strengthening work, taxiway N1, taxiway E3, taxiway N1-N3 junction, engine run-up bay and T2 apron were handled.

14/32 runway and intersection works

The 14/32 runway being the secondary runway was taken up early in the piece for renovation. It was closed for 6 months during the ’09-’10 season for major rehabilitation, including pavement strengthening and widening, slope compliance correction, drainage upgrades, AGL upgrades and construction of new connecting taxiways. One of the major complexities in this was the intersection works of the 09/27 and 14/32 runways. Work was permitted only for 6 hours every Tuesday during which time the airport was completely shut down. The work proceeded rapidly on the intersection for 22 weeks and, as expected from L&T, was completed as scheduled!

09/27 runway runs to completion

Re-carpeting the 3.4 kms long 09/27 main runway involved 1.45 lakh t of asphalt, 59 km of AGL conduiting, 3.3 lakh sq.m of grading, 2.6 km

of drains and 12 km of duct bank along the runway. Work was carried out largely during the restricted hours from 09:00 a.m. to 5:00 p.m. every day for six days a week. To ensure that the runway was handed over in a ‘ready for operations’ condition. Meticulous planning and

View of runway after up-gradation works

coordination among all stakeholders were imperatives on a daily basis. Post construction, runway 09/27 now boasts off the capacity to handle wide-bodied ‘Code F’ aircrafts such as A 380 and B 747-8.

Working without sufficient elbow-room

Space was always a constraint especially for apron development around Terminal 2 at CSIA for

maintaining the existing aircraft parking positions, taxiways, service roads, cargo staging areas and GSE parking.

At every stage of apron development, only a limited number of aircraft and equipment could be shuffled from one place to another. With such moves being typically restricted to 1-3 aircrafts at a time (a single aircraft stand measures around 5,000-10,000 sq.m), developing an apron of approximately 9 lakh sq.m currently occupying over 30 aircrafts, was a herculean task that involved several stages of micro-phasing development and meticulous implementation.

Bridge over River Mithi

As part of Maharashtra Government’s initiative to upgrade and expand urban drainage systems following the devastating 2005 Mumbai floods, the existing Mithi River flowing within the vicinity of CSIA was widened significantly. The part of the river that runs beneath runway 09/27 and parallel taxiway N1 also had to be

Work in progress at the runways intersection

Page 28: ECC Concord

54 ECC CONCORD, October’13 - March’14 55ECC CONCORD, October’13 - March’14

Veiw of remote stand for parking

Mithi River bridge

widened which required closure of the taxiway and shortening of the runway for 15 months to combat which an enormous 2 x 12 m cast in-situ bridge culvert was constructed across the airport to almost double the capacity of the river.

Overcoming multiple challenges

Though Team L&T achieved resounding success in the task of airfield works, it was not without encountering multiple challenges such as:

y The existing airport site is land locked by the surrounding city, complicating logistics planning

y Construction in an operational environment, on top of the existing pavements that are being used daily for aircraft operations and parking had its own complexities

y The Mithi River diversion was a complex job. Since the actual quantity of hard rock encountered

was 600% more than the predicted estimate, 25 rock breakers were deployed all along the location for completing the job on time

y Time restrictions for operations were major challenges

y Frequent disruptions to work due to VIP visits

y The Mumbai climate which can potentially shutdown all works during the monsoon period lasted almost 4 months

y Non-availability of existing underground service layouts

Despite the inherent challenges, the project team successfully completed approximately 24 lakh cu.m of earth work, 8 lakh cu.m of concreting and 4 lakh t of asphalt - a truly amazing feat considering that it was accomplished without any disruptions to a fully functional airport.

Going green

To make the project more economical

and environmental friendly, the project team adopted rubblization and concrete recycling technologies in the T2 apron development works. The existing concrete was either rubblized in-situ or crushed on-site and recycled for reuse as base-course material by using specialist machineries imported from Europe. The base material underneath the existing apron pavement was also recycled. Apart from material being reused, these initiatives also saved a great deal of transportation requirement and thereby reduced the use of fossil fuel.

Many reasons for L&T to take a bow!

y L&T took up the critical work of main runway up-gradation involving restricted timelines from 09 a.m. to 05 pm with complete confidence and experience gained from past projects. The project was handed over for air traffic from 05 p.m. to 09 a.m the following day. Despite this short time period and criticality

of working on a functional runway, the project was handed over one day ahead of schedule.

y An invisible blast fence was procured and installed for the first time in India

y Strengthening of existing Mithi River bridge under operating main runway carriage way was executed before schedule to accommodate A 380 (Code F) aircraft

y E3 Taxiway was constructed in a restricted time during 14/32 runway closure from 10th October 2011 to 12th January 2012 and was handed over 8 days ahead of schedule

y N5 taxiway was constructed during the restricted time period of main runway shutdown for six hours from 20th January 2012 to 20th May 2012. It was completed 10 days ahead of schedule

y Installation of zero radar footprint, invisible blast fence made of fibre glass for the very first time in India

Illuminated view of apron

Page 29: ECC Concord

56 ECC CONCORD, October’13 - March’14 57ECC CONCORD, October’13 - March’14

Airfield ground lightingA trailblazing effort

The Airfield Ground Lighting (AGL) provided at Mumbai international airport is one of the most technologically sophisticated systems with design capabilities complying to CAT II Category as per the ICAO (International Civil Aviation Organization) Annexure 14 & DGCA CAR (Director General of Civil Aviation Compliance and Requirement).

Some glowing features

Since the airport features two cross

Individual Lamp Control and Monitoring System (ILCMS)

All the AGL light fixtures are provided with addressable switching devices for better controlling and monitoring and to reduce maintenance downtime. The system provides ‘lamp on/off’ status, lamp failure status to both the maintenance teams and Air Traffic Controllers. The ILCMS also interfaces with AGL CMS for the Air Traffic Controllers to use the routing facility to guide aircrafts from the runways to the apron stands.

runways - RWY 14/32 & RWY 09/27 - the AGL technology has been designed to cater to cross runway operations even during low visibility conditions. Several more advanced and sophisticated features have been integrated.

SFL system

For the first time in India, the AGL system was designed with Sequential Flash Lighting System to provide additional guidance for approaching aircrafts.

View of air field ground lighting

The Runway and Taxiway Lighting System have been designed to handle Code F Aircraft Airbus (A 380-800) which is presently the biggest flying aircraft and in aviation history too.

Stop bar control system

The stop bar control system is based on microwave sensor based technology with both static and dynamic controls to avoid runway incursions.

AGL Control and Monitoring System (CMS)

The Profibus networking standard has been adopted to control the Constant Current Regulators (CCRs) by the air traffic controllers from the ATC.

PAPI system

Being one of Asia’s busiest runways, Mumbai’s airport is equipped with an advanced Precision Approach Path Indicator System, also known as ‘Instrumental landing’ that ensures displaced threshold design to clear obstacles around the airport.

Power and control network / AGL substations

Two 11/0.433 kV substations are provided to cater to the AGL system, the power supply to which is fed by a 11 kV redundant network system. A dedicated

redundant fiber network takes care of the Airfield Ground Light (AGL) and Control & Monitoring System (CMS).

All the runway circuits are fed through a 250 KVA UPS to ensure reliable operations. In addition, the AGL substations are provided with 100% DG

back-up and ring main supply system will power the system within 15 seconds of a mains power failure.

Apron high mast lighting system

As per ICAO requirements, 38 high

View of PAPI lights

VDGS & high mast lights at apron area

Page 30: ECC Concord

58 ECC CONCORD, October’13 - March’14 59ECC CONCORD, October’13 - March’14

Sheer magnitude of the task

Inset and Elevated lights - 5500 nos

Isolation Transformers - 6000 nos

Primary Cabling - 750 km

Secondary Cabling - 450 km

Taxiway Guidance Signs - 393 nos

CCR Panels - 126 nos

AGL Substations of 1 MVA - 2 nos

AGL CMS & ILCMS System- 1 lot

Ancillary buildings

ATC tower y The ATC tower is equipped with

redundant power supply from 2 x 1000kVA transformers with

Power and control network for AGL

View of transformers

mast lighting systems have been provided to illuminate the apron area which can be controlled remotely through the Building Management System (BMS).

Visual Docking Guidance System (VDGS)

The Mumbai airport is equipped with state-of-the-art laser based VDGS systems to guide aircrafts while docking. Each VDGS unit is interfaced with the Gate Operating System (GOS) to control the system remotely. In turn, the GOS is interfaced with the Flight Information Display System/Airport Operational Database system to automatically control the VDGS units as per the updated flight schedule.

Emergency shut down system for fuel distribution network

The aviation turbine fuel distribution network features emergency shutdown systems comprising push buttons, remote I/O modules and integration with IOCL control system.

Big challenges

Enabling works

To create a work front for civil construction activities as per the phasing plan, the existing services of NAVAID System, RADAR System and Communication System of ATC had to be re-routed.

Runway / taxiway works

Refurbishing the AGL system of the main runway 09-27 during airport operations was completed in 6 months from 1st November 2010 to 31st May 2011 much to the appreciation of the client.

Runway intersection works

Keeping the team in readiness to complete the scheduled activities within 6 hours of closure of RWY intersection for consecutive 22 closures on every Tuesday from 12:00 hrs to 18:00 hrs and handing over the runway back to operation was one of the toughest jobs.

Illuminated view of NACIL hangar

100% DG back-up in view of aviation security. 100% UPS power has also been provided to meet eventualities for all the traffic controller equipment, NAVAID and communication systems.

y India’s tallest ATC has a sandwich busduct from ground to the top floor (level 22) along with tapping provisions at all floors.

y External lights are provided at level 1, level 4 and level 20 to add to aesthetics and grandeur.

y LCMS is provided at all levels to reduce the intensity of lights according to the requirement of the user and to reduce power consumption to save costs.

y All the necessary access control systems, CCTV cameras and building management systems guard this important and security sensitive installation.

Numbers tell a storyElectrical

HT/LT Panels - 18 sets

Transformer - 2 nos

1MVA DG Set - 2 nos

UPS - 6 nos

HT/LT Cables - 9 nos

Distribution Boards - 40 nos

Conduiting - 24 km

Light Fixtures - 924 nos

IT Systems

CCTV Cameras - 15 nos

ACS Points - 23 nos

BMS - 1 lot

Cat 6 Cable - 12 km

NACIL – Air India hangar and annexure buildings

y The Air India hangar has a redundant power source and UPS back-up for all the energy systems

y All hangar lights are approachable through ‘cat walks’ for easy maintenance

y The hanger has been provided with the requisite power sources to meet the maintenance requirements

y External lights provided to the hangar caters to the full requirement of engine run-up bay

Major Quantities

HT / PCC Panels - 3 nos

Transformers - 2 nos

UPS - 2 nos

HT/LT Cables - 6 km

Distribution Boards - 55 nos

Conduiting - 29 km

Light Fixtures - 1624 nos

Page 31: ECC Concord

60 ECC CONCORD, October’13 - March’14 61ECC CONCORD, October’13 - March’14

Forecourt and elevated corridor Flying in to the airport forecourt

Mumbai is perhaps the only metro in India to boast off an airport located right in the heart of the city. Though well connected to the arterial ‘Western Express Highway’, reaching it can be quite harrowing. To address this vexing traffic issue, a dedicated elevated corridor leading to an expansive forecourt was proposed as a part of the MIAL project.

The MIAL elevated corridor features some of the best-in-class technology making it a landmark in its own right. There are 81 spans of cast in-situ spine connected to a precast cantilever with void former of 2200 mm diameter, a first-of-its-kind structure in the country. Another unique aspect is that it contains various types of superstructures comprising of in-situ PSC & RCC voided slabs, PSC & RCC box apart from ‘I’ girder spans. While the superstructure is varied in dimension, the cantilever section was precast and erected using specially designed launching girders.

The centre spine was constructed using conventional cast-in-situ methods with massive staging works whereas the cantilever portion was precast and connected to the main spine using state-of-the-art stitch concreting and post tensioned cables. This four lane access way connects MMRDA’s Sahar elevated portion to the airport’s forecourt with a deck width of 19.2 m that expands to a whopping 73 m (9 lanes along with wide footpaths in front of departure) as it approaches the terminal departure bay. A couple of two lane ramps enable ascent and descent from the departure level leading to Powai and Sakinaka parts of Mumbai. Three connecting ramps at an elevated level of 16 m connect the MMRDA portion and level 10 of the multi-level car park. Tree-lined, the deck of the superstructure features attractive palm trees and shrubs in the median apart from aesthetic lighting that adds to the grandeur.

Page 32: ECC Concord

62 ECC CONCORD, October’13 - March’14 63ECC CONCORD, October’13 - March’14

ATC sky tower Standing tall as an icon

Illuminated view of ATC sky tower

ATC sky tower

The new Air Traffic Control Tower at Mumbai’s Chhatrapati Shivaji International Airport stands tall as an iconic representative of the meteoric rise of the Indian aviation Industry and its entry into global reckoning. The nerve center of one of the busiest airports in the world, the ATC tower, with its futuristic design, rises to a height of 83.8 meters, the tallest of its kind in the country and unique in its placement being located outside the airport premises, in the forecourt of the domestic terminal.

Conceptually designed by the Hong Kong-based global architectural firm, HOK, the tower will be the first sighting for travellers coming into CSIA as it is taller than the existing ATC. Its view will extend beyond by 5 miles from each of the runway’s start and end points.

Features

Built in a site area of 1200 sq.m, the tower consists of 3 floors at its base called the technical block for security and Airport Authority of India (AAI) staff for ATC operation. There are 4 floors at the top called the ‘Stalk and CAB’ that accommodates the ATC operational area, navigation equipment, etc. The rest

Rising above to lord over all it surveys, the new ATC Sky Tower at Mumbai’s International airport stands as a towering example of L&T’s prowess and considerable capabilities.

Multi-level car park The most spacious pit-stop in town

The 10 floor MLCP has a 5000 car and 400 two wheeler capacity and can be accessed from both the elevated and at-grade road levels. Built on a 2.32 lakh sq.m area, it connects to every level of the terminal via 8 elevators and 8 escalators for hassle-free movement. The MLCP is also stacked with adequate trolleys for baggage handling and wheelchairs for the differently abled.

Gardens and water fountains give a relaxing and soothing experience to the passengers. About 20000 sq.m of beautiful landscaping makes it one of the most exquisite parking facilities in the country. The architectural finishes include 1.5 million sq.ft of painting, 95000 sq.m of floor-decking work and 20000 sq.m of external granite flooring.

The HVAC system includes 3324 fans for ventilation and the entire building features a world-class fire detection and protection system apart from CCTV surveillance and public announcement systems for enhanced safety of passengers.

The Multi-level Car Parking (MLCP) at MIAL could easily be India’s largest at an airport packed with some of the most passenger-friendly conveniences.

View of the state-of-the-art floor decking system at the MLCP

Eastern entry into the MLCP

Aesthetic elements such as plants and fountains enliven the ambience

Page 33: ECC Concord

64 ECC CONCORD, October’13 - March’14 65ECC CONCORD, October’13 - March’14

A marvellous beaconThe awe inspiring and magnificent structure rises up in the heart of Mumbai city is a sterling example of L&T’s workmanship apart from its capability to handle highly critical constructions.

The new ATC Sky Tower is already a much-acclaimed piece of construction: it has bagged the ‘Hong Kong Building Information Modeling (BIM) Award – 2009’; ‘Golden Peacock Jury for Occupational Health & Safety in 2011’; ‘ACCE (I) Billimoria Award – 2012’ and ‘ICI Annual Award – 2013’.

of the tower between the technical block and stalk is only a RCC shaft housing lifts and staircases.

Scope of works

Civil works

Plot area: 2800 sq.m (approx.)

PCC = 125 cu.m

RCC = 4546 cu.m

Shuttering = 19550 sq.m

Reinforcement = 705 t

Structural steel = 260 t

PHE- UG sump works

Domestic tank (2 nos) = 30,150 litres

Fire storage tank = 4,24,000 litres

Flush (grey water) = 30,552 litres

Electrical

Transformer (2 nos) = 1000 KVA each

Diesel generator (2 nos) = 1000 KVA each

VHT

Passenger Lift ( 1 no) = 800 kg capacity

Firemen Lift (1 no ) = 1600 kg capacity

HVAC

Air cooled direct expansion type packaged air conditioning units for technical block and cab level with estimated cooling load of 190.6 KW (58 TR) for technical block and 175.5 KW

(50 TR) for cab Level. The staircase and firemen lift has been provided with one duty and one stand-by pressurization fan for each area.

Construction methodology

The ATC sky tower is unique in its design, construction, erection and functional performance. It stands tall from FGL on 11 pile caps of which the central cap supports the central core wall which extends up to +77.80 m (level 0 to level 22) and an inclined skirt wall which connects to the central core at +62.05 m (level 0 to level 18). Passenger and firemen elevators are provided inside the core with a staircase through the core from level 0 to level 22.

The 1st lift core wall (3 m) was executed using conventional formwork while further lifts were executed using climbing formwork. The technical block floors followed after the core and skirt wall completion up to level-4. The skirt wall ascends right up to 3 lifts below the core wall and the staircase inside the core ascends 3 lifts below the core wall using conventional formwork. Concreting was done using pipe line.

The skirt wall is connected to the central core at + 62.05 m (level-18). After the connection of core and skirt, the preparatory slab was taken up for erection. During the same time the core continued leaving the beam embedment at the respective cab level slabs. After erection of the preparatory slab, the structural steel beams along with rolla-deck sheets and rebar was fixed in position for level-18 to 20 and concreted.

Accuracy in profile was achieved by shuttering that involved pre-check and post concrete check surveys. The skirt and core walls were constructed using the jump formwork system. Formwork fixing for concrete and installation of façade glass panels was monitored through an anemometer for wind velocity. The structure has an external coat of anti-fungal, dust resistant, and anti-carbonation paint which involved a critical procedure of heavy staging around the structure and sequential painting from top to bottom.

Project quality management system Near enough is not good enough

Retail area at the terminal

ATC sky tower

Audit

Annual audit plans that covered every department within the project, vendors and sub-contractors were drawn up and status reviewed on a bi-monthly basis with effectiveness measured once every 6 months.

Monitoring of materials

Activity based method statements,

were taken even for small components such as screws and nuts before use at the site.

Third party tests were conducted for every lot of structural and reinforcement steel irrespective of quantity. These tests also took into consideration the structural design intent in terms of durability and seismic conditions. About 28000 tons of structural steel and 30000 tons of reinforcement steel were tested.

inspections and test plans were prepared and implemented during project execution. A material approval system was introduced and over 350 materials were approved in the contractors’ works package. An exclusive system for material approval of sub-contractor works package was also implemented by taking approval from designers and architects from both the L&T and the MIAL teams. So tight was the material approval system that due approvals

For a project of the size and complexity of MIAL, it was imperative to set project specific quality objectives with regard to monitoring, auditing and reviewing so as to exceed the expectations of the client, in specific, and visitors to the airport, in general.

Page 34: ECC Concord

66 ECC CONCORD, October’13 - March’14 67ECC CONCORD, October’13 - March’14

Attractive ceiling made of Glass Fibre Reinforced Concrete

The project involved huge volumes under different disciplines which went through stage-wise process inspections such as on-site and off-site inspections for material and process controlling. Numerous tests were carried out in the well-equipped, on-site labs.

For stringent process control, several inspections were performed including; material on receipt, pre-dispatch and factory inspections. Stage-wise inspections were also conducted for every activity to maintain the exacting standards in conformance to the L&T stamp of excellence.

Management review

Management review meetings were conducted bi-monthly to assess the progress on quality objectives and to formulate action plans to achieve the set objectives. Action plans included product quality ratings, acting on customer complaints, corrective & preventive action on audits and implementation of the same. Non-conformance reports issued by the client were reviewed on a periodic basis to focus on avoiding repetitive complaints and identifying critical areas for timely action.

Due to the large scale of operations, establishing certain facilities enabled L&T to carry out construction in a hassle free manner and achieve the desired quality standards.

Steel Service Center (SSC)

SSC was commissioned for better control and management of huge volumes of reinforcement steel in terms of minimal wastage, better inventory control, enhanced quality apart from on-time and on-schedule delivery

Concrete batching plant

The establishment of a concrete batching plant at the site not only produced economical concrete but also facilitated rapid supply to site locations for achieving progress under the control of QC inspectors round the clock.

Hot mix asphalt plant

Setting up of a hot mix asphalt plant for a brownfield airport project was a critical task but it reduced the trip time of hauling vehicles especially for the runway asphalt works which were carried out in a window of 6 hours a day with assured quality.

Demolition works by hydraulic concrete crusher

Hydraulic concrete crushers with diamond wire cutting were used for demolition of old buildings. About 2500 tons of reinforcement scrap was retrieved from the reinforced concrete members such as slabs, beams and bridge decks.

Clash resolution technique of 3D modeling

Clash resolution technique was adopted for clash analysis of all mechanical, electrical, plumbing services and airport services inside the terminal building.

Green construction technology

Existing rigid pavements were rubblized by advanced machines and used for developing pavements above it. Demolished pavement materials like pavement quality concrete boulders were crushed for reuse as granular sub base for pavement works.

Pre-cast technology

Pre-cast technology was used to cast various structural elements like precast

wall panels, drains, ducts and chambers to reduce construction time and achieve the desired quality.

Light weight concrete

Light weight concrete having density equal to that of water was used to overcome extended thickness to achieve the desired slope and at the same time reduce the load on the RC structure in the multi-level car park.

Gypsum plaster

Gypsum Plaster which is more economical compared to river sand was introduced in place of conventional plaster to save on cost and overcome the quality issue due to silt.

Self Compacting Concrete (SCC)

SCC was used to achieve the desired architectural intent of curvature, slim and corrugated elements. Consistency in surface texture of the ATC sky tower profile stands a tall testimony to this path-breaking technique.

Quick-set concrete

To overcome time constraints during runway overlay works, quick set concrete was used for encasing ducts and pipes so as to allow usage of the runway within 6 hours from the commencement of work.

Milling of asphaltic pavement

Milled asphalt material was used as a substitute to granular sub-base in minor pavements and shoulders, thus reducing cost and consumption of material.

Foundation of quality

The foundation engineering for the terminal building and the ATC tower comprised bored cast in-situ pile foundation. Over 5000 piles of different diameters and 5000 rock anchors were installed and its application in the foundation was monitored to ascertain the designed load to competent sub-strata through various load tests such as vertical load tests, lateral load tests, instrumented cyclic load tests, pull out tests and integrity tests. The strata for

bored piles were completely verified and inspected by deploying a full-time geo-technical engineer along with a QC engineer.

The investigation of raft subsoil of Terminal 2 was carried out to determine the general sub surface conditions and grout underneath the basement surface using ground penetration radar survey which is an electromagnetic geophysical method for mapping of cavity in rock anchor and the grout vicinity.

Best practices

CONQUAS

CONQUAS technique was implemented to ascertain product quality rating for all components of works and take up preventive measures required to improve product quality.

Visual communication

Do’s and Don’ts for concrete works, finishing works and MEP works were displayed at appropriate site locations,

View of airside from the terminal building

Page 35: ECC Concord

68 ECC CONCORD, October’13 - March’14 69ECC CONCORD, October’13 - March’14

tough task that becomes increasingly tougher when the stones are sourced from various locations across the globe. To avoid shade variations and to ensure avoidance of unsuitable shades in the stone works, it was decided to proceed with dry lay of stone before the final wet lay. Architects from L&T & MIAL were involved in identifying the right shades of stones to avoid the use of unsuitable stones with different shades. This exercise was done in addition to source inspection.

Protection of works

Protecting the final finished product inside a terminal building where several other activities were proceeding in tandem was important. For instance, protecting the granite flooring and glazing from breakage or scratches was very difficult. Replacing the damages involved cost, time and other complications since most of such materials were imported. Special protective measures were adopted such as covering the stone works with commercial plywood and wrapping breakable materials like glass with cardboard sheets.

MIAL team, take a bow! y MIAL, ATC Tower: ACCE(I) - Billimoria Award-2012, Excellence in

construction of high rise building/structure

y MIAL, ATC Tower: Commendation award from Golden Peacock Jury for occupational health & safety in 2011

y Rajiv Gandhi National Quality Award-2011, Commendation certificate with a Silver Plaque under the category of large scale service industries from Bureau of Indian Standards.

y MIAL, ATC Tower won the Outstanding Concrete Structure Award-2013 from Indian Concrete Institute

y MIAL twice won L&T’s internal Annual Quality Trophy 2010-11 and 2012-13 in major job sites under Airport business unit.

so as to create awareness on quality. Work methodology was also displayed to achieve consistency in quality.

Vendor Satisfaction Report (VSR)

VSR was implemented to understand the vendors’ perception of project organization and thereby facilitate them to build long-term relationships and maintain enhanced quality levels.

Deployment of pour sequence

Pour sequence concept for all concrete pours were introduced covering the necessary resource, rate of pour and standby arrangement

Shade variation in natural stones

Complying with the approved shades, when it comes to natural stones, is a

Security check-in of international departures

Contracts management Focusing on the finer elements

Work in progress at the bull nose and elevated road network

The contracts management team comprised a clutch of expert talent with world-class specialization to guide and support a young and dynamic mainstream staff team. Backed by the benefit of steep learning curves from three other mega airport construction project contracts at Hyderabad, Bangalore and Delhi, the team formulated experience-based

The lofty aspirations of the client (GVK) to create a world-class airport saw the project team relying on the capabilities of several third party organizations that had no prior presence in India. This considerably increased the need for a robust and efficient risk management strategy.

The strategy of the contracts management team was focused on creating a better

strategies with foresight considering future risks.

However, the MIAL project had certain unique characteristics rendering contracts management, in general, and risk management, in particular, incredibly challenging. The fact that this brownfield project was located in the middle of one of India’s most densely populated areas was a major challenge.

The strategy of contracts management was focused on creating a better understanding of the contract obligations and its implementation at every level of staff involved in the project.

Page 36: ECC Concord

70 ECC CONCORD, October’13 - March’14 71ECC CONCORD, October’13 - March’14

understanding of contract obligations and its implementation at every level of staff involved in the project. In the course of conforming to the obligations of the contracts, care was taken to ensure achievement of cost benefits and customer satisfaction.

Playing the IT advantage

The implementation of contracts relied heavily on the latest innovations in information technology. A case in point being the Electronic Data Management System to deal with the challenges of handling time bound, massive quantum of communications with various stakeholders of the project. This system was inspired by the ACONEX system adopted in the Delhi International Airport Project and based on that experience, a new system was developed and implemented by the in-house team in a cost effective and successful manner.

Every single document had to pass through a contractual screening for verification. Taking into account the

critical contractual response time of the communications with the involvement of various stakeholders, a communication protocol was evolved and strictly adhered to.

Spreading the word

The awareness on contracts was a key to the successful implementation of the project. Team leaders made every single individual involved in the team aware of the contracts by conducting training sessions, monthly meetings and circulation of contractual obligations and highlights. The various tools of contracts management such as claim management, subcontract management, change management and payment management were strategically handled within the established protocols with the client as well as subcontractors. The perennial issues involved in a mega project such as coordination, access, payment strategies were based strongly on earlier experiences.

In the case of the Mumbai International Airport, it was evident to the contracts

management team that a complex brownfield project always had the possibility of increasing the variables in the risk management equation. To mitigate it and handle risk management successfully, the team had to be versatile and constantly sought added information to mitigate risks.

Plugging the brain-drain

The learning that the team acquired from the project is an invaluable resource that had to be carefully documented and archived for future use. The contracts team ensured that specifications, method statements and learning on successes & failures were all recorded for every discipline in a single repository. The sharing of such experiences not only ensures development of a holistic, project-wide understanding and improves interdisciplinary efficiency but also helps immensely for future tender proposals and project implementation.

View of terminal roof area with skylight harvesting system

Site administration Enabling the enablers

In the case of MIAL, the challenge for the admin team was to provide suitable and comfortable accommodation for all the staff members who were trans-located from various parts of the country and, perhaps, the world. This involved a staggering 450 families and about 350 bachelors.

The task was huge: to find suitable residential complexes for such large number of staff members, near the site, in heart of Mumbai city complete with police NOCs and society permissions.

Finally, three societies were identified and selected. At peak period, about 300 apartments were booked in Bhandup, and another 250 flats in Malad to accommodate all the staff members while 25 flats in Powai were earmarked exclusively for senior staff members. Locations were carefully chosen having all amenities and facilities such as schools, hospitals and entertainment in the immediate vicinity.

Once the people were placed, the next big challenge was to arrange for their movement between residence and project site in the bustling city of Mumbai. About 21 buses and 100 cars ensured that people were able to commute conveniently. The catering for the bachelor staff members at all the facilities was also ensured right from the early stages.

In a project of this magnitude and complexity, the employees were always under pressure both to perform and complete the project on time. Several get-togethers and sightseeing trips were organized for them and their families to stress bust and enliven their spirits. Some of them even involved themselves in a few CSR initiatives to give something back to society despite their busy schedules.

An administration team’s work kicks-off way before even the mobilization process begins for a project.

Page 37: ECC Concord

72 ECC CONCORD, October’13 - March’14 73ECC CONCORD, October’13 - March’14

View of TC closet

State-of-the-art design facility

Organizations depend heavily on Information Technology for creating, processing and protecting data. Construction projects are no exception and require extensive exchange of data and information between the project participants on a regular basis. It is therefore of paramount importance that project management remains adaptive to newer developments in information

Fully managed IT support services

y Round-the-clock monitoring of servers, firewalls and critical devices

y Remote support for computer/ EIP issues when identified by monitoring service or help desk

y On-site services

y Voice enabled tech support

technology in order to achieve time, cost, and quality goals.

Project Management

Armed with project management software, contractors were able to manage complicated business processes with planning, organizing and managing the various resource pools available ensuring efficient project execution, high quality results and overall business profitability.

During the construction phases and the life-cycle of a building, large amounts of information are handled that enables task control, data integration, material and resource control and communication exchange between the company and its suppliers. In the MIAL project too information technology played a vital role.

Information systems Live wire support

the challenge of matching the right amount of storage capacity with the back-up need as part of the system design.

EIP based services

y Implemented the in-house EIP Vidhya EDMS (Electronic, Database Management System)

y Over 10000 work orders created using work order management system

y 14,000 unique item codes generated in the work order management system

y Over 1000 bills generated per month

y 1200 vendor (sub-contractor) codes created

y 81412 documents handled in EDMS

y 38,000 purchase orders processed through SCM module

Highlights y 21 different locations were connected through OFC network

y 800 computer systems and 150 laptop users during the peak period of the project

y 30 different types of servers deployed

y Multiple internet and intranet links enabled

y EDRC network license based application shared from MIAL to other locations via MPLS

y Handled 25 TB of data including various types of drawings, mails and other files with properly scheduled back-up

y Wireless CCTV helped monitor site progress activities

y High definition video and audio conferencing solutions used

y 67 printers that includes MFD and plotters pressed into service

y Bio-metric attendance recording system for both staff and 10000 workmen

y 52 nos. of UPS for power back-up

Business continuity and back-up service

y Daily back-up and reporting y Daily monitoring and maintenance

of back-up status y Regular testing of restore

availability y Data recovery

Managing the back-up process

True data protection requires continuous management. As new data is created and changes made, back-up processes and storage devices have to be monitored, tested, and updated. The MIAL IT team successfully addressed

Page 38: ECC Concord

74 ECC CONCORD, October’13 - March’14 75ECC CONCORD, October’13 - March’14

Plant and machinery Resources – propelling productivity

Planning resources such as man & machinery were unique for MIAL due to the sheer volumes and the high fluctuations in requirements due to staggered receipt and packaging of jobs. It was therefore the responsibility of a specially formed central resource planning team to mobilize, deploy and demobilize all critical resources such as batching plants, steel service centre, formwork, plant & machinery apart from workmen and staff with the twin objectives of optimum utilisation of resources at levels and avoidance of any compromise in the progress of the project.

Formwork

Handling 7600 tons of formwork material and reconciling such huge stock periodically is humanly impossible, if attempted manually. A dedicated software was developed for this which also avoided duplication during manual counting. Item-specific 2-D bar-coded stickers were developed and used on the formwork material for faultless inventory management.

Steel service centre

Since huge volumes of rebar had to be cut and customised for concreting, a sophisticated steel service centre with 3000 t per month capacity was established right at the early stages of the project that helped automate rebar works. Wastage was substantially reduced by using bar bending schedules (BBSs) with RC CAD software and other special software to optimize the cutting schedule. The cut rebar were organised

and labelled in detail to ensure easy identification at site.

Plant and machinery

Plant and Machinery (P&M) was the engine that powered the project. The

right machine was made available based on the construction methodology and programme schedule which propelled the progress of work as scheduled. In several packages, the project was completed ahead of schedule due to the innovative deployment of P&M.

Material

Handling enormous quantity of bulk materials such as aggregates could result in erroneous quantification of the physical stock. Hence, third party survey teams were hired to ensure the accurate quantification of available physical stock.

Workmen

Terming the workforce that trudged everyday into the project as ‘an army’ would have been an understatement. The manpower exceeded 15000 during peak periods of construction. Mobilising and retaining workmen of such huge numbers across disciplines of construction was certainly a challenge that was overcome by tying-up with social organizations to source rural unskilled labour. An on-site training centre established with the help of L&T’s Construction Skills Training Institute, trained such raw workforce greatly enhancing their skill levels within short periods. Suitable workmen tenements were planned at the vicinity of the project along with management of daily commute using the dedicated services of 130 buses from Mumbai’s ‘BEST’ undertaking.

Major Plant & Machinery deployed by L&T

Equipment Quantity (nos)

Batching Plant (60 - 120 cu.m, combined capacity - 315 cu.m/hr)

04

Hot Mix Plant (200 TPH) 01

Steel Service Centre - 2000 t / month 01

Tower Crane 11

Weigh Bridge - 330 t capacity 05

Soil Compactor - 10 t 02

Wheel Loader 05

Boom Placer 03

Sensor Pavers 02

Concreting Pumps (30 & 60 cu.m/hr) 06

Transit Mixers 04

Power Generator (6556 KVA) 54

Welding Machine 25

EOT Crane 03

The speed of construction depends on how advanced is the equipment that has been deployed at the site.

Massive formwork used for painting the ATC sky tower

Workmen arriving to start the day’s work at the check-in hall

Page 39: ECC Concord

76 ECC CONCORD, October’13 - March’14 77ECC CONCORD, October’13 - March’14

Innovations at MIAL Inspired by insight

Rubblization work in progress

Demolition by hydraulic concrete crushing machine

‘Destruction for construction’ was an oft used term in the MIAL project as several existing structures had to be demolished to make way for the newer ones. For this a 26 m ‘high reach’ boom hydraulic concrete crusher and a dust boss water spraying machine were used in combination.

was isolated from the remaining portion using ‘diamond wire cutting’ of concrete members such as slabs and beams.

y Reinforcement retrieved from the scrap alone amounted to 2500 tons of steel

y Resulted in 35 % savings in cost when compared to conventional demolition methods

y The total quantity crushed was 32,000 cu.m of which reinforced concrete alone was 16,000 cu.m

y About 13,000 cu.m of RCC ramp at a height of 23 m and about 35,000 sq.m floor area of the 20 m high terminal building was demolished.

y Only a portion of the slab and ramp that was meant to be retained

MIAL had several ‘firsts’ and numerous path breaking innovations to be proud of in the areas of construction, demolition and recycling of construction waste.

Cable net wall structure

MAIL uses a highly transparent structural glass system called the cable net wall structure that eliminates the use of conventional support structures, utilized are pre-tensioned cables arrayed in vertical or horizontal patterns. This glass wall structure gives the transparent facade

a clean and seamless look including all the capabilities of a conventional wall system. MIAL is also benchmarked for using the longest unidirectional cable net wall structure in the world, the only cable wall of its type that uses sharp corners. Three types of systems have been used, such as, building to roof, building to building and roof to roof.

Rubblization

To construct a new pavement, the old one needed to be removed and the breaking, excavation and removal of waste material would have been a massive logistical problem in the already congested airport area. The concept of recycling the existing pavement material was proposed and advanced machines were mobilized from England for rubblizing the pavement and using it as a subgrade. Roughly 75,000 truck trips were saved, thanks to rubblization, apart from saving a massive land fill of excavated material.

Strengthening the bridge over the River Mithi under the main runway

An aircraft takes off from Mumbai airport’s runway every three minutes. To withstand the impact of so many frequent take-offs and to support gigantic aircrafts (such as the Airbus A 380) that weigh close to 600 tons, the bridge over River Mithi had to be strengthened. CFRP (Carbon Fibre Reinforced Polymer) was used to

High-reach jaw crushers in action along with blowers

Structural steel erection using highway truss

Page 40: ECC Concord

78 ECC CONCORD, October’13 - March’14 79ECC CONCORD, October’13 - March’14

Hot tapping method

Bird’s eye view of head house structural steel works

strengthen the slab and beam for a length of 90 metres.

Hot tapping method

To maintain fuel supply to both the operational airport as well as the new one, the innovative Hot Tapping Method was resorted to employing the following methodology:

y A ‘Stopple’ machine was installed and plugs inserted at each of the 4

locations to ensure that the fuel flow was through the 18” bypass line only

y After draining the fuel, the redundant existing pipe section adjacent to bypass line was cut and removed. A new diverted pipeline was fixed to the existing 22” pipeline between the two cut locations

y The ‘Stopple’ plugs were first removed at two intermediate points and then at the two extreme points thereby closing the sandwich

valves to divert fuel flow only through the new pipeline

y The redundant 18” bypasses lines and 22” old main pipeline were removed after draining the leftover fuel

y Fittings were welded to the existing pipeline at four locations, while fuel was flowing at a controlled rate of flow between 5300 to 15700 litres per minute to adequately dissipate the heat of welding and avoid rapid cooling of the weld. Leakage checking was done with nitrogen purging.

Head house structural steel erection

Due to space constraints, a unique methodology was adopted for the erection of structural steel works. A 250 ton structural steel pod each of size 32m x 32m and weighing about 250 tons was erected using a launching mechanism. A highway temporary truss was used to erect the pod from the launching platform at one end to the mega columns which were 40 m free standing columns. 29 out of 30 pods in the structure were erected using this innovative methodology.

T2 goes live Terminal 2 takes off in style

Air India’s AI-343SI from Singapore given a water canon welcome

The national carrier, Air India’s international flight, AI-343SI from Singapore landed to a water canon salute marking its status of being the first ever aircraft to land in the newly built Terminal 2 of the Mumbai International Airport. The Jet Airways flight 9W118LHR to London Heathrow was the first flight to depart from the new terminal and its passengers were given a royal farewell including the traditional Maharashtrian Tutari drums during their departure process.

On its first day of operation, the terminal handled 72 international departures,

12th February 2014 was a red letter day for L&T; the day on which the new Terminal 2 of the Chhatrapati Shivaji International Airport was commissioned and began operations.

Dr. Manmohan Singh unveils new terminal of Chhatrapati Shivaji International Airport in MumbaiDescribing the new airport terminal as “world-class” and an ideal example of a successful public-private partnership (PPP) model, the Prime Minister, Dr. Manmohan Singh inaugurated the state-of-the-art Terminal 2 at Chhatrapati Shivaji International Airport in Mumbai on January 10, 2014. Speaking on the occasion Dr. Singh said, “The terminal is expected to establish new global benchmarks of functional efficiency and operational safety for airports. It also exemplifies our ability as a nation to build world-class infrastructure. I have no doubt that this terminal will fulfil the expectations we have from it and make us all proud.”

The inaugural ceremony was attended by dignitaries such as Union Minister, Sharad Pawar, Civil Aviation Minister Ajit Singh and Maharashtra Chief Minister Prithviraj Chavan apart from other Ministers and Government officials.

received over 14,500 passengers and handled 22,664 bags. On the arrivals front, 77 flights touched down on the first day and 13,296 bags were processed. Handling 3,000 bags per hour, the baggage operation was seamless. It is a matter of great significance that the first passenger’s bag reached the conveyor belt within 6

minutes from landing whereas the global average is around 10 minutes.

Mr. S N Subrahmanyan, Member of the Board & Senior Executive Vice President (Infrastructure & Construction) was present at the terminal on the first day along with senior officials from MIAL and L&T.

Page 41: ECC Concord

Topping the charts in numbers

Terminal 2 • 4,39,204 sq.m built-up

area• 188 check-in counters• 58 self-check-in kiosks • 50 feet high check-in hall • 70 m wide departure bay • 40,000 sq.m canopy • 21,000 sq.m of retail

shopping • 700 chandeliers • Material sourced from

25 countries

Shell and Core • 10 lakh cu.m of concrete • 58,000 t of reinforcement

bar • 36,000 t of structural steel • 36,000 sq.m of skylight • 1.4 lakh sq.m of

membrane roofing • 28,000 sq.m of façade • 12,000 sq.m of cable net

wall • 30 free-standing mega

columns

MEP

• Connected load of 50 MVA capacity

• 6 DG sets of 3 MVA capacity

• Six chillers of 2300 TR capacity

• 14 MLD capacity STP

IT systems• 25 airport IT systems

• 1560 km of CAT 6 cabling

• 333 km of OFC cabling

• 15,600 IT ports

• 2190 CCTV cameras

• 747 access control devices

• 3500 speakers for PA system

• 1026 flight information screens

• 931 antenna systems for mobile network

Airport systems • 10,800 bags / hr baggage

handling system • 10 baggage reclaim

carousels • 160 escalators, travelators

& elevators • 25 fixed link bridges • 52 movable aero

bridges

Finishing works• 80,000 sq.m of GFRG

covered canopy

• 1,83,000 sq.m of granite

• 1,10,000 sq.m of metal ceiling

• 2100 metal doors

• 30,000 sq.m of carpet

• 102 washrooms

• 60 departure counters

• 72 arrival immigration counters

• 4,000 rmt of glazing work

Other highlights• 5,000 capacity multi-level

car parking

• 3.3 km long, 6 lane, elevated corridor

• 83.8 meter ATC sky tower

• 6.5 km of runway and 12 km of taxiway

• 1 million sq.m of apron area

Page 42: ECC Concord

83ECC CONCORD, October’13 - March’14

New Orders

Orders Valued `6718 Crs in the bag!

`13360 Crs worth more orders bagged between Jan-Mar’ 14

L&T Construction has won new orders cumulatively worth ` 6718 crores across various business segments in the period October to December 2013. Among some of the major orders bagged is the construction of a green-field international airport in Kannur, a super speciality facility for the Safdarjung Hospital, New Delhi and the construction of a sinter plant in eastern India. The Waste Water Business secured a major turnkey

order from the Gujarat Water Supply and Sewerage Board for the construction of an underground drainage system in nine towns of Gujarat.

The Heavy Civil Infrastructure Business won orders from the Department of Atomic energy for design, engineering and supply of thermonuclear reactor components for cooling water system, chilled

water system and heat rejection system at Gujarat apart from other orders. The Power Transmission and Distribution business has bagged turnkey orders in several parts of the country and an international order has been won for the construction of a 132 kV transmission line.

L&T Construction has bagged a slew of orders between January and March 2014 aggregating to `13360 Crores. Significant among them in the domestic market is the order from the Government of Gujarat for Saurashtra Narmada Avtaran Irrigation Yojana for the Water Business. The Buildings & Factories business has bagged a large order from the West Bengal Medical Services Corporation Limited for planning, design and construction of health care hospitals across West Bengal.

The Transportation Infrastructure business bagged the single largest international road project job for L&T from ASHGHAL (Public Works Authority), State of Qatar, for design and construction of Al Wakrah Bypass Road (P015) and another road project between Bidbid-Sur Section

from the Ministry of Transport and Communications, Sultanate of Oman. The Railway business has secured EPC orders from Rail Vikas Nigam for various railway packages spread across the northern part of India.

The Heavy Civil Infrastructure business secured EPC orders from the National Highways Authority of India for construction of a new four lane extra dosed heavy bridge across the river Narmada and six laning of a portion of the Vadadora-Surat section of NH-8 in Gujarat and other road projects.

On the Power Transmission & Distribution business front, a major order for the construction of 161 km, 110 kV Double Circuit transmission line in the Western Region of Saudi Arabia has been secured and back home a major contract from

National Thermal Power Corporation involving supply, erection, testing and commissioning of 765 kV & 132 kV switchyards for power evacuation & transmission at Madhya Pradesh has been secured.

“It has been a productive beginning to 2014 and these orders reaffirm our leadership position in our various business verticals,” said Mr. S N Subrahmanyan, Member of the Board & Senior Executive Vice President (Infrastructure & Construction), L&T. “Although there is still sluggishness in our economy, these orders reflect that there is some positive movement in the infrastructure sector which augurs well for both the country and L&T going forward”, he added.

Editor V. S. Ramana

Editorial team Vinod Jacob Chacko V. Ramesh Kumar | Gopi Kannan. S Ashwin Chand | Mayura. K Subha Anand | Shamala Nadendla

PhotographyV. S. Natanavelu | R. Vijay Kumar Tushar Thakur | Nirav Dave

Design & layoutGlobal Print Design, Chennai

Article Co-ordinationRushikesh N Jogdand Manoj G

Contributors for the articles

Project planning & control : Rajesh Kanade, Rushikesh N Jogdand, Manoj G

Baggage handling system : Rajesh Kanade, Ramanujam, Sumesh M

Passenger boarding bridges : Rajesh Kanade, Ramanujam, Manoj Jadhav

Vertical & horizontal transportation : Rajesh Kanade, WE Sampath, Kumar Pranav

Electrical works : D.C. Mallick

Lighting works : G. Bhowmick

IT systems : Sagar Sunil Agrawal

HVAC package : Shrikant Dighe, Suraj G

Fire detection and protection system : Vijay Kumar, Jyothula Somasundara Murthy, K Timothy

Public health engineering : Vijay Kumar, Jyothula Somasundara Murthy, Balathandayutham M

Finishing works : Anil Dureja

Floor management : Suman Chanda, Priyank K

Testing, commissioning & trials : Manigalan Nair

Airside works : Natarajan Namachivayam, Rajesh Pachlot

Airfield ground lighting : DN Nayak

Ancillary buildings : Natarajan Namachivayam, R Inian

Forecourt and elevated corridor : Raveendra Hegde, Tiruvuri Srm Srinivas

Multi-level car park : Shivarajjayadevappa Kubsad, Deepak S Danai

ATC sky tower : Natarajan Namachivayam, Manish Kota

Project quality management system : Kanniah Ranjan

Contracts management : Bhoothalingam N

Site administration : Jayaprakash T K

Information systems : Kamalakannan Rajendiran

Resources & Procurement : Shantanu Guha, Harshal Kajale, Mathew T Ben

Innovations at MIAL : Manoj G

* Figures reported reflect cumulative orders bagged as we go to print – Editor.

Page 43: ECC Concord

84 ECC CONCORD, October’13 - March’14 85ECC CONCORD, October’13 - March’14

L&T completes first-of-its-kind composite slab at TCS Siruseri project in Chennai The steel - concrete composite slab at +94.125 m level of Signature Tower of TCS Siruseri project was successfully cast on 8th of January 2014. This is a first-of-its-kind achievement in L&T, in view of the height at which the composite slab was completed.

This feat was completed amidst challenges that included working at a height of +94.125 m and completing a RCC slab that was embedded with heavy structural steel. The +94.125 m level structural steel girder supports the column at its tip to support the levels above it. The structural steel girders of 1.5 m and 1.60 m depth are embedded into the 2.60 m thick RCC slab. Advanced non-linear analysis using ATENA software was done to predict the behavior of connections, modes of failure and to estimate the load factor.

The slab encompasses 14 plate girders with total weight of 120 t. The maximum weight of a single plate girder erected was 9 t at 24 m radius. Designed by EDRC, the execution was ably supported by CMPC, BSCC & EHS of HQ /CNCL among other stakeholders. No single rebar was lapped and all bars were connected by mechanical bar couplers that warranted meticulous planning of threaded bars. The reinforcement steel were heavily congested (450 kg per cu.m) posing difficulties in execution while tying.

M 40 grade, temperature controlled, SCC was batched using chilled water and crushed ice. Placing of concrete was done in 500 mm layers using a static placer boom and the same was cured for 7 days by baking. The entire execution of the bowl slab activities were completed in a safe manner with zero incident. The bowl deck was supported by structural steel trusses of 5.60 m height to withstand the total load of 1100 t from above. The slab consists of 310 cu.m of concrete and 140 t of reinforcement steel.

Project NewsProject News

L&T signs agreements for three Government medical college projects in Odisha

L&T signed an agreement on the 8th January 2014 at Cuttack for the construction of three Government Medical Colleges, SCB Medical College & Hospital campus at Cuttack, VSS Medical College & Hospital at Sambalpur and MKCG Medical College & Hospital at Berhampur.

Mr. Sukumar Hebbar, Segment Head – Health, B&F IC signed on behalf of L&T with Mr. Pramod Kumar Nayak, Executive Engineer, Buildings representing the Government of Odisha in the presence of L&T’s Mr. Sushanth Shah Deo, Cluster Project Manager and Mr. J.Sengupta, Project Manager.

B&F IC has secured this project on Design & Build basis from Public Works Department of Odisha and the project scope at all three locations covers construction of medical colleges with laboratories, libraries, lecture halls and examination halls, a 1500 seater auditorium along with residential accommodation for students and faculty. The scope also includes complete design and execution of structure, finishes and MEP services apart from a 250 bed capacity super-speciality wing for the Berhampur campus.

Mr. Sukumar Hebbar, Segment Head – Health, B&F IC exchanging documents with Mr. Pramod Kumar Nayak, Executive Engineer, Government of Odisha

Page 44: ECC Concord

86 ECC CONCORD, October’13 - March’14 87ECC CONCORD, October’13 - March’14

Inauguration

The Honourable Chief Minister of Tamil Nadu, Dr. J Jayalalitha inaugurated the design and build project of Apollo Hospital at Aynambakkam, through video conferencing on 6th November 2013. Spread over a built-up area of 2 lakh square feet, the 275 bedded super speciality hospital has a service building area of 8500 sq.ft. in addition to 26 consultation rooms, Imaging and Diagnostics department with MRI, CT scan, Mammography, Ultrasound, X-ray room, Emergency department and their supporting facilities. L&T Construction is the lumpsum turnkey contractor with the scope covering design, project planning, procurement, installation, testing and commissioning of all system with world-class infrastructure to enable Apolo offer sophisticated health care services.

Chennai’s Apollo Hospital project inaugurated

Inauguration

Ganga & Yamuna, the Twin towers of Technopark Phase III, Trivandrum and the largest LEED certified Gold Rated building in India, was inaugurated by the Honourable Chief Minister of Kerala Mr. Oommen Chandy on 15th January 2014. Presided over by Mr.P.K. Kunhalikutty, Minister for Industry and Information Technology, the event was graced by many IT industry leaders including Mr.V.K. Mathews of IBS Software and Mr.P.H. Kurian - IT Principle Secretary to Govt. of Kerala. The efforts of the L&T team were lauded for delivering the project on time with special mention of Mr.K.Kannan, Vice President & Head – IT & Institutional space BU, Mr.T.Nandakumar, Cluster Project Manager, Chennai Cluster-CBA and Mr.G.Sumanth Raju, Project Manager. The phase III campus features

The new Bengaluru International Airport, the Gateway to South India, has been rechristened Kempegowda International Airport by Shri. Siddaramaiah, Hon’ble Chief Minister of Karnataka. It was inaugurated by Shri. Ajit Singh, Hon’ble Union Minister for Civil Aviation, in the august presence of Dr. M. Veerappa Moily, Hon’ble Union Minister for Petroleum & Natural Gas, and other dignitaries from the central & state ministries. With this expansion, the handling capacity of the terminal has increased from eleven million passengers per annum to sixteen million apart from significant enhancements in various other amenities and facilities such as check-in counters, immigration counters and baggage reclaim belts.

Twin Towers of Technopark Phase III inaugurated

Bengaluru International Airport rechristened and inaugurated

Dr. J. Jayalalitha inaugurating the project through video conferencing

Apollo Hospital at Aynambakkam

a built-up area of one million sq.ft developed over 92 acres of land taking the total built-up area of the entire

Technopark campus to 7.2 million sq.ft which is one of the largest such facilities in the country.

Watch out for a detailed coverage of the Kempegowda International Airport, Bengaluru, in the forthcoming April-June 2014 issue - Editor.

Page 45: ECC Concord

88 ECC CONCORD, October’13 - March’14 89ECC CONCORD, October’13 - March’14

Shri. Oommen Chandy, Honourable Chief Minister of Kerala, inaugurated the ESIC Medical College & Hospital Project at Kollam on 21st December 2013 in the presence of senior government dignitaries including Shri. Kodikunnil Suresh, Honourable Minister of State for Labour & Employment and Shri. N. Peethambara Kurup, Honourable Member of Parliament, amongst others.

Shri. Kodikunnil Suresh presented a memento to Shri. S. Vadivazhagan, Project Manager for the successful completion of project and appreciated the commitment and project management capabilities of L&T. The Medical College and Hospital Complex is spread over an area of 35 acres with 36 buildings including hospital blocks, medical college, staff quarters and students hostel. It is a 500 bedded multi-speciality hospital with a total built-up area of 15 lakh sq.ft.

ESIC project at Kollam inaugurated

B&F IC inaugurates Central Civil Testing & Training Centre at Panvel Complex

Central Civil Testing & Training Centre – CCTTC, an initiative taken by B&F IC, was inaugurated by Mr. B N Sheth, GM-Special Initiatives -West & Regional Manager, Mumbai at Panvel Complex in Mumbai on 21st October 2013. CCTTC will aim to create a pool of quality staff who will act as catalysts in their respective sites to deliver the projects of global benchmarks of quality and safety.

The Quest Mall at Kolkata, designed and built by L&T Construction was opened to the public on 31st October 2013, on the eve of Diwali. Located at one of the busiest roads of central Kolkata, the Quest Mall was developed by CESC Limited and designed & built by L&T, based on the concept from RTKL, London and Bliss Fasman, New York. With a built-up area of 7.5 lakh sq.ft, the mall features a double basement, G+5 floors, terrace restaurants and 13 multi-level car parks for 800 cars. With the finest of finishes, elegant architecture and impressive façade, the Quest Mall showcases luxury brands from across the world.

Quest Mall makes a grand opening

Inauguration Inauguration

Page 46: ECC Concord

90 ECC CONCORD, October’13 - March’14 91ECC CONCORD, October’13 - March’14

The iconic ATC Sky Tower of the Mumbai International Airport was jointly inaugurated by Shri Prithviraj Chavan, Hon’ble Chief Minister of Maharashtra and Shri Ajit Singh, Hon’ble Union Minister for Civil Aviation, in the presence of Shri V P Agarwal, Chairman, AAI, Shri GVK Reddy, Executive Chairman of MIAL, Shri G V Sanjay Reddy, MD of MIAL and other ministers and government dignitaries on 18th October, 2013. Mr. M V Satish, Sr. VP & Head B&F IC and other senior team members of L&T were present on the occasion.

Rising to a height of 83.8 m the ATC Sky Tower is the most significant structure in the newly constructed Terminal 2.

ATC sky tower inaugurated

Inauguration

Making its presence felt at the Modern Airports Africa 2013 Expo, NairobiAfrica’s premier summit on airport infrastructure, Modern Airports Africa 2013, was held in Nairobi, Kenya on 19th and 20th November 2013 in which L&T Construction displayed its comprehensive capabilities in providing EPC services for the airport infrastructure sector.

Mr. T.Krishna, Segment Head – Airports, made a presentation on L&T’s comprehensive and multi-dimensional capabilities in airport construction at the conference. He stressed on the advantages of having EPC mode, an emerging trend in the region, for construction in Africa.

An impressive pavilion projected the company’s capabilities in airport construction by displaying signature airport projects and ATC Towers executed in India & the Middle East. Airport Authorities from Kenya, Kenyan Airways, Uganda, Zambia and Ghana

were among the other exhibitors. The double digit growth at the existing Airports coupled with growing

demand of tourism in Africa has created opportunities at regional and international hubs.

The President of India, Mr. Pranab Mukherjee laid the foundation stone for the construction of a 2 MLD Sewage Treatment Plant inside the President’s Estate in Delhi on 17th February 2014. This ceremony was attended by officials from the President’s Estate along with Mr. A R Soni, NW Segment Head- Waster Water, and L&T’s project team. The 2-MLD STP based on extended aeration process comprise two Sewage Pumping Stations and approx. 2.3 km of pipeline carrying sewage water to the Sewage Treatment Plant at President’s Estate. The project aims at utilizing the water generated within the Estate for horticultural purposes.

President of India lays foundation stone for a 2-MLD sewage treatment plant

Inauguration

The Chief Minister of Maharashtra, Mr. Prithviraj Chavan, and Deputy Chief Minister, Mr. Ajit Pawar, inaugurated the Mumbai Monorail on 1st February 2014. The formal flag-off took place at Wadala Station, and a plaque to commemorate the occasion was unveiled at Chembur Station.

Mr. K. Venkataramanan, CEO & MD, L&T, attended the inaugural ceremony, along with several senior political leaders of the city and representatives from the state government. Commenting on L&T’s role in building the country’s first-of-its-kind mass rapid transit system, Mr. Venkataramanan expressed happiness that L&T played a key role in a landmark project that the Chief Minister had said would ‘give Mumbai a new identity’.

The elevated guideways on which the monorail runs was among the many challenging civil construction projects undertaken by L&T. The Company’s role also extended to the DC traction

Maharashtra CM flags off India’s first monorail

system, power supply & distribution, as well as the automated fare collection system and interface management. The Mumbai Monorail is the latest among

the many high-profile infrastructure projects executed by L&T on a total turnkey basis in consortium with Scomi Engineering Bhd. of Malaysia.

Page 47: ECC Concord

92 ECC CONCORD, October’13 - March’14 93ECC CONCORD, October’13 - March’14

Events Events

Indian Green Building Council (IGBC) an organisation established with a vision to build a better living environment conducted its 11th Green Building Congress – an International Conference and Exhibition on Green buildings on 24th and 25th October 2013 at Chennai. During this event, three projects of L&T achieved the Green Building standards required for the following level of certification under LEED India – IGBC rating system:

y Cognizant IT facility, Siruseri Campus– Ph1, Chennai – GOLD rating

y Cognizant IT facility, Hinjewadi Campus – Ph1, Pune – GOLD rating

y West Block 3 @ Knowledge City Campus Vadodara, Gujarat – GOLD rating

Gold rating awarded by Indian Green Building Council to several projects

L&T Construction displayed its capabilities in the construction of green buildings through an 18 sq.m stall displaying live size photographs of LEED certified projects and its green campus. GBC was attended by national/ international experts,

architects, builders, consultants, corporates, manufacturers and other professionals from the Construction Industry. Cognizant, as a client showcased the level of energy efficient and environment friendly practices carried out by L&T.

Presence at the Rail and Urban Transit expo

Confederation of Indian Industries (CII) in association with the Ministry of Railways and the Ministry Of Urban Development organized a Mega Expo covering Rail Transport and Urban Transit at Pragati Maidan, New Delhi from 3rd to 5th October 2013 that included the prominent International Railway Equipment Exhibition (10th IREE 2013 - Focusing on Rail Industry including Rail Infrastructure and Equipments) and the Urban Mass Transit Expo (1st UMTE 2013 - Focusing on Metro sector / Monorails including Rail Infrastructure, Traction, Tracks, Systems works and Equipment)

The expo was inaugurated by Mr. Mallikarjun Kharge (Minister of Railways-GoI), in the presence of Mr. Arunendra Kumar (Chairman-Railway Board), Mr. S Gopalkrishnan (President-CII), other eminent dignitaries

of Indian Railways, MoUD, DMRC, DFCC, CII and Industry professionals from India and abroad.

L&T ‘s Pavilion

L&T’s domain strengths in Rail & Urban Transit spread across various BUs viz; ultra modern station building capabilities of B&F IC, Railway Business of Transportation IC, Metro BU and Tunnels & Special Bridges BU of Heavy Civil Infra IC were showcased along with PT&D IC’s capabilities in associated Transmission line works. Technical experts from all the business units were present to explain the company’s capabilities.

Apart from providing a comprehensive perspective on offering Turnkey Solutions for Rail and Urban Transit

Infrastructure, a ‘video wall’ played a movie made exclusively for the event.

L&T was a mid-level sponsor for the International Railway Conference – 2013 and the Plenary session on Rail Infrastructure and Transportation was co-chaired by Mr. Rajeev Jyoti, Chief Executive, Railway Business along with Mr. Subodh Jain (Member Engg. - Railway Board). The conference provided a platform to receive inputs from Industry experts with regard to Heavy Haul, Freight Corridor, High speed Rail in India, Capacity Enhancement and Technology & Safety.

Other notable delegates to visit the stall included Mr. N K Singhla (GM-Multiple Agencies-Western Corridor-DFCCIL) and Mr. Negi (GM-Co-ordination-Western Corridor-DFCCIL) and other high level officials of Govt. bodies.

Page 48: ECC Concord

94 ECC CONCORD, October’13 - March’14 95ECC CONCORD, October’13 - March’14

Subsidiary company Larsen & Toubro (Oman) LLC put an impressive showing at the international exhibition “INFRA Oman 2013”, held in Muscat, Sultanate of Oman from September 30, 2013 to October 2, 2013.

On display were the company’s multidimensional capabilities through signature projects across India and overseas. Among notable visitors were His Excellency Dr. Rasheed bin al Safi al Huraibi, Chairman of the Tender Board and

Mr. J S Mukul, Indian Ambassador to Sultanate of Oman. Mr. P Surendhra Babu – Chief Executive of Larsen & Toubro (Oman) LLC gave a brief about the company and its operations to the visiting dignitaries.

About 180 companies from various countries took part in the exhibition that featured Country Pavilions from Iran, Italy, Spain, South Africa, Turkey, China, Japan and the United Kingdom. The three days exhibition ended on October 2, 2013.

This international expo is organized in cooperation with the Ministry of Transport and Communications and the Ministry of Commerce and Industry and supported by the German Industry & Commerce Office & Middle East Association (NUMOV), Public Establishment for Industrial Estates, Singapore Business Federation, Spanish Economic & Trade Office, Ministry of Economy, UK Trade & Investment, Concrete Sawing & Drilling Association and Vietnam Association of Construction Contractors.

Comprehensive capabilities displayed at INFRA Oman expo

Events Events

Defence construction capabilities displayed at DEFEXPO 2014

Nobel Laureate, Prof. Kurt Wuthrich, visits L&T

The 8th land, naval and internal homeland security systems exhibition, DEFEXPO 2014, was held at Pragati Maidan, New Delhi from 6th to 9th February 2014. Inaugurated by the Hon’ble Union Defence Minister, Shri. A.K. Anthony, the EXPO was conducted with the aim to encourage joint public-private participation in the defence sector. Showcased were land, sea and air capabilities of the Indian defence sector. Spread over an area of 30,000 sq.m and arguably the largest ever Defence Exposition in Asia, DEFEXPO had over 624 companies from 30 countries displaying their capabilities.

L&T put up an impressive pavilion highlighting its defence construction capabilities through a display of signature defence projects, defence bases, ship-lift facilities and storage facilities executed in India and the Middle East.

Nobel Laureate Prof. Kurt Wuthrich, a Swiss chemist/biophysicist, known for developing Nuclear Magnetic Resonance (NMR) methods for studying biological macromolecules, visited L&T Construction’s Manapakkam campus on 18th January 2014 along with his wife, Ms. Marinne Wuthrich, and professors from IIT Madras. Mr. S.N. Subrahmanyan and Ms. Meena Subrahmanyan welcomed the delegates. In a special gathering organised at Toubro Hall, Prof. Wuthrich interacted with senior executives of L&T Construction and shared extensive information about his experimental projects and R&D efforts that fetched him the much coveted award. He further expressed his reformist ideas and shared his interesting experiences in India.

Page 49: ECC Concord

96 ECC CONCORD, October’13 - March’14 97ECC CONCORD, October’13 - March’14

Events

Solar business releases manuals and documents for effective process flow

The Solar Business recently released Operation & Maintenance training manual, Testing & Commissioning manual, Standard Erection Drawings document for Solar PV Plants and Man-day master for CSP.

These manuals and documents were made by the Solar team for effective process flow and are expected to:

y Achieve operational excellence

y Standardize the procedures and processes

y Improve the efficiency of site operations

y Inculcate a sense of knowledge sharing

The manuals were released by Mr. S. Rajavel, EVP and Head, Water & Renewable Energy IC and were handed over to the respective department heads. The Operation & Maintenance (O&M) manual will greatly help the site team in structuring and constantly reviewing their day to day operations. Not only will it help in the easy induction of new engineers to the team but also in their better understanding of the Solar PV plants for tension free and high quality maintenance practices.

The Testing & Commissioning (T&C) manual details the practices to be followed in a very user friendly and structured manner to improve process quality and efficiency. The

document on Standard Erection Drawings of Solar PV plants was released by Mr. R. Srinivasan, VP and Head, Renewable Energy, Security Solution & Smart Grid BU and will help in standardization of erection procedures, increasing the productivity and quality of work and sub-contractor management.

Man-day Master (CSP Plants) was released by Mr. Shaji John, Head, Solar Business and will act as a ready reckoner for costing, site operations and scheduling, thus improving the reliability of planning and reducing the time.

Events

15th anniversary of L&T Build India Scholarship

To commemorate the milestone of the completion of 15 years of the L&T Build India Scholarship, an unique industry-academia collaboration towards transforming engineers into construction technology managers, a one-day conclave was inaugurated on 21st February 2014, at L&T Construction’s Head Quarters campus in Chennai. Entitled the ‘BIS Conclave’, the event saw the participation of the Dean and professors from IIT, Madras, IIT Delhi, NIT, Suratkal, NIT, Trichy; senior leadership from L&T and more than 300 BIS staff working with L&T including the current batch of BIS students.

“For the last 15 years, L&T has been backing this unique initiative which has become an avenue to transform bright young engineers into great leaders through a structured programme and training at college and project sites,” said Mr. S.N. Subrahmanyan, Member of the Board and Senior Executive Vice President (Infrastructure and Construction), L&T. “With the vision and initial efforts of our former Joint

Managing Director, Dr. A. Ramakrishna, way back in 1997, this programme that began with just 40 engineers has now blossomed into one of the best industry initiatives and has produced more than 500 of the finest engineers and leaders. Since L&T’s projects are spread across the country, we are taking efforts to expand this by getting other institutes of eminence on board,” he added.

Proud of this achievement, he stressed the importance of adding a few crucial areas to the curriculum like quantity survey, estimation, facility management, legal and commercial so that students could acquire both theoretical and practical knowledge of managing mega projects. “L&T Build India Scholarship has already given a fine crop of engineers to L&T, for the industry and for the country and has become a one-point-stop for people who dare to dream and aspire to become leaders,” he concluded.

Earlier in his welcome address, Mr. A.L. Sekhar, Executive Vice President & Head, Heavy Civil

Infrastructure vertical and co-ordinator of the programme, shared the journey of BIS from 1998 and how based on the feedback from all stakeholders at the 10th anniversary in 2009, the programme was greatly enhanced to benefit all.

Significantly, on the sidelines of the BIS Conclave, Mr. S.N. Subrahmanyan and Dr. Srinivasan Sunderrajan, Director, NIT Trichy, signed and exchanged a MoU to adopt and implement the BIS programme in NIT’s Trichy campus too.

Professors from IIT, Madras and Delhi shared their experiences and Professor Koshy Varghese of IIT, Madras, said that BIS was the longest running programme in IIT having achieved several milestones like the first such programme to be awarded the ISO certification. They also referred to various technical advancements made at different L&T project sites contributed by BIS scholars.

Mr. S.N. Subrahmanyan and Dr. Srinivasan Sunderrajan, Director,NIT Trichy exchanging the documents

Page 50: ECC Concord

98 ECC CONCORD, October’13 - March’14 99ECC CONCORD, October’13 - March’14

Events Awards

A Memorandum of Understanding was signed by L&T Construction with the National Institute of Technology-Karnataka, Surathkal on 4th November 2013 to enhance Industry-Institute partnership between the two organizations. The MoU was signed by Mr. S N Subrahmanyan, Sr. Executive Vice President (Infrastructure & Construction) and Prof. Swapan Bhattacharya, Director, NIT-K at an event held in the Manapakkam campus, Chennai.

As per the MoU, NIT-K will partner L&T in implementing the L&T Build India Scholarship (BIS) Programme, under which L&T sponsors a two-year full time M.Tech Programme in Construction Technology & Management (CTM). The L&T BIS Programme is a flagship programme of the company’s Industry-Academia initiative, which has been running for the last fifteen years in partnership with IIT-Madras and IIT-Delhi. Several additional areas of collaboration, like ‘Research to Commercialisation’ were also discussed.

Speaking on the occasion, Prof. Bhattacharya said that L&T was held in high esteem throughout the country for its professionalism and innovative management approach, as well as for its role in building the country’s institutions. He lauded the L&T BIS initiative as an extremely innovative one in the area of Industry-Academia interaction.

SNS stated that with the ever growing need for skilled technical personnel, the time had come to expand the programme in partnership with other premier academic institutions and said that NIT-K Surathkal, with its impeccable academic credentials would greatly enrich this long-term partnership through increasing technical collaboration in the field of Construction Technology, Management, Engineering and Research.

MoU signed with NIT-K Surathkal - to enhance industry-institute partnership

The signing ceremony was also attended by the Business Heads and HR Heads of L&T Construction and by Prof. Katta Venkataramana, Head—

Department of Civil Engineering and Prof. M.B. Saidutta, Dean—Alumni Affairs & Institutional Relations, NIT-K.

L&T bags The Economic Times Good Corporate Citizen AwardThe Finance Minister, Mr. P. Chidambaram, presented to L&T, The Economic Times (ET) Good Corporate Citizen Award at a glittering function in Mumbai on December 07, 2013.

The award was received by Mr. A.M. Naik, Group Executive Chairman. The Corporate Citizen Award is part of the prestigious annual bouquet of Awards for Corporate Excellence presented by ET - India’s largest selling business newspaper.

Accepting the award, Mr. A.M. Naik said, “As a concept, CSR is ingrained in our DNA and has been part of our value system long before it became largely realised to do so. There is no short cut. The only way growth is sustainable is when growth is inclusive”. The awards jury cited L&T’s steadfast commitment to CSR over the years. It said that over 700,000 people among

the marginalised sections of the society have been beneficiaries of L&T’s on-

going interventions in education, skill building, and mother and child care.

KVR conferred with a Life Time Achievement award at the 4th EPC World Awards 2013

Mr. K V Rangaswami, Advisor to the Group Executive Chairman was conferred with a Life Time Achievement Award in recognition of his outstanding contribution to the construction industry, at the 4th EPC World Awards 2013 held on 14th December at Hotel Ashok, New Delhi.

The EPC World award recognizes and honors companies/individuals broadly covering the entire Infrastructure & Construction industry on the basis of their qualitative and quantitative performance during the year 2013.

Page 51: ECC Concord

100 ECC CONCORD, October’13 - March’14 101ECC CONCORD, October’13 - March’14

AwardsAwards

SNS is ‘Leading Engineering Personality’ for Institution of Engineers

Mr. S N Subrahmanyan, Member of the Board and Sr. Executive Vice President (Infrastructure & Construction) was honoured at the 28th Indian Engineering Congress held on 20th December 2013 at The Leela Palace Hotel in Chennai as the ‘leading engineering personality’ in the event ‘Glimpses of Engineering Personalities’. He received this recognition from Mr. S.S.Rathore, President -The Institution of Engineers (India). This event was inaugurated by

Shri. Pranab Mukherjee, Honourable President of India.

Receiving the honour, SNS touched upon L&T’s accomplishments and contribution to the country in terms of Engineering & Construction and thanked IEI for their appreciation. The Institution of Engineers (India) conducts the Indian Engineering Congress every year, in which they honour leading engineering personalities.

Lifetime Achievement Award for Mr. V B GadgilMr. V. B. Gadgil, Chief Executive & Managing Director, L&T Metro Rail (Hyderabad) Limited was honoured with a ‘Lifetime Achievement Award’ by the American Concrete Institute for demonstrating effectiveness and distinction in the field of Infrastructure development, by proven interest and dedicated efforts, towards improving this significant professional field and thereby the society as a whole.

The award was presented by Dr. Anne Ellis, President, American Concrete Institute, on the occasion of R N Raikar Memorial International Conference & Dr. Suru Shah Symposium on ‘Advances in Science & Technology of Concrete’ which was held in Mumbai. Speaking on the occasion Mr. Gadgil expressed that it was an honour to receive this great award and with

this recognition, his responsibility towards the society and infrastructure development has increased manifold. He also appreciated American

Concrete Institute for their efforts and dedication in improving design, construction, maintenance and repair of concrete structures.

HR Leadership Award for Mr. S. Ganguly Acknowledging his contribution to the field of Human Resource Development for more than thirty years, both in India and abroad, Mr. S. Ganguly, Vice President and Head Corporate HR, L&T Metro Rail (Hyderabad) Limited, has been conferred the prestigious “HR Leadership Award” by World HRD Congress on February 16th 2014, in Mumbai. Mr. Ganguly also delivered a session on ‘Change Management’ on the same day at the 22nd World HRD Congress, one of the largest rendezvous of HR Professionals from across the globe that acknowledges the best CEOs, HR Professionals, and Organizations for exemplary contribution to HR.

Page 52: ECC Concord

102 ECC CONCORD, October’13 - March’14 103ECC CONCORD, October’13 - March’14

PT&D IC honouredThe outstanding contribution of PT&D IC to Power Transmission & Distribution (EPC category) was honoured at the 4th EPC World Awards 2013 held on 14th December at Hotel Ashok, New Delhi.

Mr. J.S.Sudarsan – EVP & Head, PT&D IC along with Mr.K.Rajaram – GM & Head, EHV Substations and Utility Power Distribution BU, PT&D IC received this award from Dr. Harsh Vardhan- Former Minister of Education and Shri. Natwar Singh- Former Minister of Steel, Coal & Mines and External affairs in the presence of eminent industry stalwarts from the Infrastructure & Construction space.

This EPC World award recognizes and honors companies/individuals broadly covering the entire Infrastructure & Construction industry on the basis of their qualitative and quantitative performance during 2013. In the light

of PT&D’s exceptional contribution in the Power Transmission & Distribution sector, with fine examples of works & projects delivered, the Organizing

committee, Jury and Knowledge Partner - Ernst & Young unanimously decided to honor L&T Construction’s PT&D IC for its outstanding contribution.

L&T wins the Inter Solar Award 2013The prestigious Inter Solar Award for the Solar Projects in India was won by L&T Construction for supplying solar energy to L&T’s CSTI (Construction Skills Training Institute) and CDC (Competency Development Centre) Campuses in Kancheepuram, Tamil Nadu. The Inter Solar Award honours Solar Projects in India in the areas of Off-Grid Solutions, Industrial and Commercial Use and Utility-Scale Projects as part of the Inter Solar India 2013, India’s largest exhibition and conference for the solar industry that was held in Mumbai from 12th to 14th November.

This coveted innovation prize was received by Mr. R Srinivasan, VP & Head- Renewable Energy BU, Mr. Shaji John, Head- Solar Business and Ms. Harshitha S Kumar, Head- Microgrid and Rooftop PV Systems.

The Solar Business Unit exhibited its comprehensive Solar EPC capabilities at the exhibition displaying the entire spectrum of L&T’s capabilities through executed solar projects. Over 170 exhibitors in the areas of Photovoltaic (PV), PV production technologies, energy storage systems and solar thermal technologies represented the solar industry’s value-added chain at this expo.

Notably, this year L&T was nominated for 3 different projects and was the only company to have nominations in each of the 3 separate categories. The other two nominated projects were - 20 MWp Composite Solar PV Project in Phalodi, Rajasthan under REC Scheme which was highly acclaimed for the superfast track commissioning (the entire project was completed in a record 60 days’ time) and 124 kWp Microgrid Project with Energy Storage at Patna, Bihar (which was another prestigious and one-of-its-kind micro-grid project in the country installed at the Bihar Chief Minister’s House and Office).

AwardsAwards

Company of the Year award for Bulk Material Handling BusinessThe BMH BU was recognized as the Company of the Year in the Bulk Material Handling Market of India in 2013 by Frost & Sullivan. This award is a tribute to the astounding team work and their relentless efforts in delivering exceptional business performance in 2013. It also awards the BU’s approach towards customer value creation, profitability, quality of products and projects and sustainability of operations.

This award was received by Mr. V.P. Singh, Head Power BU along with Mr. Abhijit Gupta - Business Development Manager, Mumbai on 27th November 2013. Frost & Sullivan recognizes outstanding industry achievements by presenting Frost & Sullivan Awards to top companies in regional and global markets.

Page 53: ECC Concord

104 ECC CONCORD, October’13 - March’14 105ECC CONCORD, October’13 - March’14

Pragati Towers project awarded for Engineering Excellence

ICI-Ultratech Award for Technopark Phase III project

Pragati Towers, a multi-storeyed total precast residential building constructed by L&T was conferred the Third Best Engineering Marvel Award 2013 for its innovative features. The project has also won the Public Choice Award 2013 from Engineering Watch Magazine for Engineering Excellence.

This honour was received by Mr. Madhav P Deshpande (Segment Head – Affordable & Mass Housing – RB&F BU) and Mr. K Senou (Head-Precast Initiatives– RB&F BU) from Shri. Sushil Kumar, Member of Parliament and Prof P.B Sharma, Vice Chancellor of Delhi Technological University on 24th October 2013. Pragati Towers is a G+23 storied residential slum rehab towers, Phase -I designed and built

The Indian Concrete Institute & Ultratech Cement Limited awarded L&T Construction’s Technopark Phase III, Trivandrum - the Ultratech award for Outstanding Concrete Structure of Kerala 2013 in the Infrastructure sector. Mr. G. Sumanth Raju, Project Manager received the trophy from the Chief Guest Dr. P.K. Aravindan, Retired Professor in Structural Engineering Division, IIT Madras.

by L&T Construction’s B&F IC using Precast Technology. It consists of three

towers covering 6.3 lakh sq.ft built-up area and 1012 flats.

AwardsAwards

Best Construction Contractor Award for L&T Oman LLCThe Best Construction Contractor Award was bagged by L&T Oman LLC at the Dossier Construction Awards 2013 for innovative and successful steps in the construction industry (commercial, institutional, residential, civil and roads sector) in Oman. The selection was based on clear and consistent leadership, commitment to core Constructing Excellence principles across projects and activities that have left a lasting impression on the industry. This award was validated by the prestigious auditing house KPMG.

Dossier Construction is Oman’s first and only Business to Business (B2B) magazine for the last seven years. Published by United Media Services (UMS), Dossier-Construction is a strategic partner for all major industry trade shows in Muscat.

This award was presented by HE. Dr. Ahmed Mohammed Salem Al-Futaisi, Minister of Transport &

Communications, Sultanate of Oman along with HH. Sayyid Tarik Bin Shabib Al Said to the L&T team.

Elante wins ‘Most Preferred Mall’ awardElante Mall, built by L&T has won the ‘Most Preferred Shopping Mall of the Year’ Award instituted by Franchise India & Estate World magazine at the 5th edition of the Estate Awards 2013 in New Delhi on November 19, 2013.

Elante was developed and is being operated by L&T Realty. Spread over 1.15 million sq.ft. of retail space, Elante is the largest operational mall in this region, with a mix of department stores, international and domestic lifestyle brands, hypermarket, multiplex, entertainment zone, food court and a unique open courtyard.

L&T Realty also won the ‘Best Construction Company of the Year 2013-14’ for its outstanding contribution to the growth of the real estate sector in north India. The awards were received by Mr. S.N. Seth, Chief of

Operation, L&T Realty, and his team, from Mr. Manoj Gaur, MD, Gaursons

India, and Ms. Ritu Marya, Editor–in-chief, Franchise India Media.

Page 54: ECC Concord

106 ECC CONCORD, October’13 - March’14 107ECC CONCORD, October’13 - March’14

EDRC Re-christened ‘AR Centre’

The Engineering Design and Research Centre (EDRC) at L&T’s campus has been re-christened ‘AR Centre’ after its visionary leader, the late Dr. A.Ramakrishna (AR) at a formal function held on December 20, 2013 where KVR and SNS unveiled the name board.

“We are touched” is what Mr. Meher Prasad, eldest son of AR described the Company’s gesture of re-christening the EDRC in an emotional address. He complimented the Company on its strides into new realms and technology frontiers and spoke about his wonderful association with L&T and its people. Also present at the function were the members of AR’s family, senior executives of L&T Construction and the colleagues from EDRC.

AwardsAwards

“My wife and I greatly enjoyed the historical view of L&T”

Nobel Laureate Prof. Kurt Wuthrich, Mrs.Marinne Wuthrich & Professors from

IIT Chennai

“We feel very happy to work with such an excellent company through a long term

partnership” Mr. Nakamura San, Chairman M/s Calsonic Kensai Ltd. Japan

“This is our first step to work together. I really appreciate your hospitality”

Mr.Yoshiharu Watanabe, Senior General Manager, Mr.Hiroshi Fujioka, Chief

Engineer, Mr.Takayuki Hishinuma Senior General Manager Mitsubishi Heavy

Industries Ltd.

“It has been an amazing experience at the HHL Centre and a great learning of what

really drives an excellent organization” Mr. Mohit Singh, Managing Director -

Shipra Estate Group

“This museum is fantastic, thank you all for the warm welcome.”

Mr. Bjarne Moltke Hansen, MD & CEO, Country Head –M/s F L Smidth, India

“Very impressive representation of 75 years of excellence from L&T. Here is the

wishes for the next 75 years” Mr. Martin Mugambi, Managing Director,

Head of Corporate Finance - Sub-Saharan Africa Division, Citibank N. A.

South Africa

Holck-Larsen Centre Visitors’ ImpressionsCSTI Pilkhuwa bags Best Vocational &

Skills Institution award CSTI Pilkhuwa has been adjudged the Best Vocational & Skills Institution at the National Education Summit & ASSOCHAM Education Excellence Awards 2014. CSTI bagged this award under the category of Vocational and Skills Training - Best Use of Technology for Vocational Education & Skills Training. The event was jointly organised by the Planning Commission, Ministry of HRD and NSDC on 19th February at Hotel Shangrila, New Delhi. Padma Vibhushan Dr. Karan Singh, Member of Parliament, presented the trophy to Mr. S. Natrajan, Head CSTD and Col. N.B.Saxena, Regional Training Manager.

Page 55: ECC Concord

Edited by Mr. V.S. Ramana for L&T Construction from L&T Construction Headquarters, Manapakkam, Chennai - 600 089. The views expressed in this magazine are not necessarily those of the Management. The contents of this magazine may not be reproduced without the written permission of the Editor. Not for sale. Only for free circulation among employees of L&T Construction and their customers.

AR posthumously awarded Padma Bhushan

The late Dr. A Ramakrishna (AR), former President and Deputy Managing Director, was posthumously honoured with the Padma Bhushan in the category of ‘Science & Engineering’ on Republic Day 2014. It was a fitting recognition for this ‘Master Builder’ and for his wonderful contribution to the rise of L&T Construction in an association that spanned over four decades.

Speaking about the signal distinction, Group Executive Chairman, Mr. A M Naik, said: “This honour is richly deserved recognition of Dr. Ramakrishna’s accomplishments in the field of infrastructure and construction.”

L&T’s CEO and Managing Director, Mr. K. Venkataramanan described Dr. Ramakrishna as a “doyen of the construction industry” and added that the Padma Bhushan was national recognition of his expertise.

AR, who passed away on August 20th, 2013, has left an indelible mark on L&T Construction through his innovative thinking, inspirational leadership and humane disposition apart from being the moving force behind building some of the country’s most spectacular landmarks.

“A technocrat par excellence who worked his way up through technological excellence and innovative strategies, is how Mr. K V Rangaswami, Advisor to the Group Executive Chairman described AR and added that he was quintessentially “an organization builder.”

Mr. S. N. Subrahmanyan, Member of the Board & Senior Executive Vice President (Infrastructure & Construction), who had the privilege of AR’s tutelage during his formative years was more eloquent in his praise. “I am very happy to know that our beloved AR has been conferred with the Padma Bhushan Award, the most prestigious civilian award in our country. It is really a proud moment for all of us at L&T. It is indeed a most fitting tribute to one of the most outstanding civil engineer and technocrat. He has been a great mentor and boss. Under his leadership, erstwhile ECC witnessed new unprecedented peaks and diversified into many new lines of business. He was seen as a humane leader in L&T with pleasing demeanour, optimism and vision.” We, at L&T, salute the memory and the considerable accomplishments of this great champion of our Company.

The Institute of Engineers, Andhra Pradesh Chapter, Hyderabad has instituted ‘Annual Endowment Lectures’ to commemorate Dr. A. Ramakrishna’s contribution to the infrastructural development of the county at large and to Andhra Pradesh in particular.