Upload
duongminh
View
215
Download
0
Embed Size (px)
Citation preview
© 2014 Toshiba Corporation
Eri Isono November 19th 2014
Energy Storage at Substations
― Virtual Battery Application for Load Frequency Control ―
Disclosure: Any unauthorized use of these Materials is prohibited
© 2014 Toshiba Corporation 2
• Introduction to Yokohama Smart City Project
• Battery SCADA demonstration
– Background and challenges
– Application
– Participants and schedule
– System overview
• Three considerations for battery application to LFC
– Control value allocation
– Inherent loss supplement
– Rating update
• Conclusion
Table of contents
© 2014 Toshiba Corporation 3
• Introduction to Yokohama Smart City Project
• Battery SCADA demonstration
– Background and challenges
– Application
– Participants and schedule
– System overview
• Three considerations for battery application to LFC
– Control value allocation
– Inherent loss supplement
– Rating update
• Conclusion
Table of contents
© 2014 Toshiba Corporation 4
Introduction to Yokohama Smart City Project
• YSCP
– Japanese government funded smart grid demonstration
– 6 demonstrations and research undertaken by 32 partners
– Duration: 5 years (2010/4 to 2015/3)
– Budget: 850million US dollar
• 6 Demonstrations
– Home EMS
– Building EMS
– Factory EMS
– Community EMS
– Electric Vehicle
– Battery aggregation
CEMS
HEMS
EV
BEMS
FEMS
Battery SCADA
© 2014 Toshiba Corporation 5
• Background
– Storage batteries has become realistic option to counter against power quality disturbances, and lack of LFC reserve
• Challenges
– Requires quantity
– Unrealistic to control each storages
• Differences among the types, rating, output of batteries,..
• Propose “Battery SCADA” system to control numerous and various storages as one “Virtual Battery” for grid operation
Battery SCADA demonstration
Battery
SCADA Virtual
Battery
Customer side Battery
Grid EMS
Stationary Battery
© 2014 Toshiba Corporation 6
• Load Frequency Control
– New power plant for frequency control
– Increase frequency control reserve
– Easier controllability of numerous storage batteries
• Peak Shifting
– Grid expansion deferral
– Incentive from participation to electricity market
• Spinning Reserve
– Provide spinning reserve capacity
– UPS for critical applications
Applications of Battery SCADA
Utility benefit Customer benefit
© 2014 Toshiba Corporation 7
Participants and schedule
Sponsor:
Ministry of Economy, Trade and Industry (JAPAN)
7 Participants:
Utility Tokyo Electric Power Company
Kansai Electric Power Company
System Integrator,
Demonstration managing
Toshiba
Stationary Battery Manufacturer Toshiba, Hitachi, Meidensha & NEC
Customer’s side battery
Manufacturer
Sharp, Sony Energy Devices
Other Mitsubishi Heavy Industry
Project Schedule 2010 2011 2012 2013 2014 2015
System development
Demonstration
Development Installation
Demonstration
© 2014 Toshiba Corporation 8
• Commissioned in October 2012
Demonstration site photo
Battery SCADA
Demonstration Center
Toshiba Stationary Battery 300kW-100kWh
Meiden/NEC
Stationary Battery 250kW-250kWh
Hitachi Stationary Battery 300kW-101kWh
© 2014 Toshiba Corporation 9
Sony ED
Customer BESS
3.5kVA/8.4kWh
Sony ED
Customer BESS
3.5kVA/8.4kWh
Demonstration system overview
Upper EMS
simulator
Battery SCADA Customer BESS simulator
Sony ED
Customer BESS
3.5kVA/8.4kWh
Low latency line, Protocol:IEEE1815 DNP3
(Distributed Network Protocol )
6.6kV 100V 100V 100V 100V
Toshiba
Data aggregator
Hitachi
Data aggregator
Hitachi BESS
100kW/100kWh
250kW/51kWh
6.6kV 6.6kV
Meidensha/NEC BESS
250kW/250kWh
Toshiba BESS
300kW/100kWh
Sharp
Customer BESS
22kW/45kWh
Internet
Protocol: HTTP
TEPCO distribution grid
© 2014 Toshiba Corporation 10
• Introduction to Yokohama Smart City Project
• Battery SCADA demonstration
– Background and challenges
– Application
– Participants and schedule
– System overview
• Three requirements for battery application to LFC
– Control value allocation
– Inherent loss supplement
– Rating update
• Conclusion
Table of contents
© 2014 Toshiba Corporation 11
• Three recommendations of applying storage batteries to LFC
– Control value allocation
– Inherent loss supplement
– Rating update
• Demonstration condition
Requirements for battery aggregation system
Grid EMS
Simulator
Toshiba BESS
300kW/100kWh
Meiden/NEC BESS
250kW/250kWh
Hitachi BESS
300kW/101kWh
Battery SCADA
6.6kV power line
Two control signals used
- TEPCO LFC hydro
- PJM LFC signal
© 2014 Toshiba Corporation 12
• Maximize charge/discharge ability
– Maintain SOC in same range
• Measurements
1. Control value allocation
Stationary Battery 01
-250
-150
-50
50
150
250
11:50 12:10 12:30 12:50 13:10
Time
Output [kW]
0
20
40
60
80
100
SOC [%]
01 Control Value 01 Output 01 SOC
Virtual Battery
-250
-150
-50
50
150
250
11:50 12:10 12:30 12:50 13:10
Time
Output [kW]
VB Control Value VB output
Stationary Battery 02
-250
-150
-50
50
150
250
11:50 12:10 12:30 12:50 13:10
Time
Output [kW]
0
20
40
60
80
100
SOC [%]
02 Control Value 02 Output 02 SOC
Stationary Battery 03
-250
-150
-50
50
150
250
11:50 12:10 12:30 12:50 13:10
Time
Output [kW]
0
20
40
60
80
100
SOC [%]
03 Control Value 03 Output 03 SOC
© 2014 Toshiba Corporation 13
• LFC operation will eventually lead battery SOC to zero
• An algorithm to charge and maintain SOC required
• Measurements
2. Inherent loss supplement
-200
-150
-100
-50
0
50
100
150
200
-100
-50
0
50
100
2013/10/24 12:30:00 2013/10/24 22:30:00 2013/10/25 08:30:00
Supplement charging (red) and SOC transition (blue) 2013/10/24 ~ 2013/10/25
Supplement charging [kW]
SOC transition [%]
© 2014 Toshiba Corporation 14
• Interface for Plug & Play functionality and reacquisition of information necessary
3. Rating update
Battery Battery SCADA
【Send Data item】
ID number
Rated chargeable power
Rated dischargeable power
Short time chargeable power
Short time dischargeable power
Chargeable capacity
Dischargeable capacity
Control frequency
Charge and discharge efficiency
Functionality to reacquire same
information as initial data acquisition
Initial data acquisition to acquire basic
information of the connected battery
Battery Battery SCADA
Set information
update flag
【Notification of
information update】
【Request to obtain Data item】
【Resend Data item】
【Periodic information transfer
(1 second)】
【Send Data item】
© 2014 Toshiba Corporation 15
• 2 years successful demonstration
• LFC operation strategies successful
• Requirements of battery aggregating system recognized
– Control value allocation
– Inherent loss supplement
– Rating update
• Demonstration project will provide basis for future storage deployments with dedicated purposes
Conclusion