AIR CONDITIONING (1) 1. Kapasitas AC Ruangan Q = 0.59 x W x L x H x= 637 Btu/h W = 1 m ( Panjang ruangan) L = 1 m ( Lebar ruangan) H = 3 m ( Tinggi ruangan) I = 18 ( I = 10, jika ruang berisolasi / di lantai bawah / berhim ( I = 18, jika ruang tidak berisolasi / di lantai atas ) E = 20 ( E = 16, jika dinding terpanjang menghadap utara ) ( E = 17, jika dinding terpanjang menghadap timur ) ( E = 18, jika dinding terpanjang menghadap selatan ) ( E = 20, jika dinding terpanjang menghadap barat ) 2. Daya Listrik Unit AC Beban : 9,000 Btu/h 9000 P = x 746 x 1.3 = 970 Watt 9000 3. Daya Listrik AHU/FCU P = - = 350 CFM (Kapasitas Fa Efisiensi * 3600 - Pressure Drop = 375 Pa (Kehilangan te P = 79 Watt - AHU = 1.5 inWg (375 Pa) - FCU = 1 inWg (250 Pa) - = 3 m/s (kecepatan ud - Efisi 0.8 4. Diameter Pipa CHWS/R Pada AHU 1 = 540,000 Btu/h (Kapasitas Pendingi = x = 158.12 kW = 4.2 kJ/kg.K (Konstanta panas g = 1000 kg/m3 (massa jenis air) = 6 d = = 279 = 12 = 285 d = 0.063 m p = 3.14 d = 63 mm v = 2 m/s (Kecepatan air dalam 1.7 * ( Pressure Drop + v 2 * 0 QAC (kW) QAC d 2 1/4 x p x v Cp x g x (t0 - ti) Cp 4 QAC (kW) ti o C (Suhu air masuk AHU) o K v x Cp x g x (t0 - t0 o C (Suhu air keluar AHU) o K

Engineering Calculation

Embed Size (px)

DESCRIPTION

ini perhitungan dalam bentuk microsoft excel untuk designer MEP

Citation preview

Page 1: Engineering Calculation

AIR CONDITIONING (1)

1. Kapasitas AC Ruangan

Q = 0.59 x W x L x H x I x E = 637 Btu/h

W = 1 m ( Panjang ruangan)L = 1 m ( Lebar ruangan)H = 3 m ( Tinggi ruangan)I = 18 ( I = 10, jika ruang berisolasi / di lantai bawah / berhimpit dengan ruangan lain )

( I = 18, jika ruang tidak berisolasi / di lantai atas )E = 20 ( E = 16, jika dinding terpanjang menghadap utara )

( E = 17, jika dinding terpanjang menghadap timur )( E = 18, jika dinding terpanjang menghadap selatan )( E = 20, jika dinding terpanjang menghadap barat )

2. Daya Listrik Unit AC

Beban : 9,000 Btu/h

9000P = x 746 x 1.3 = 970 Watt

9000

3. Daya Listrik AHU/FCU

P = - Q = 350 CFM (Kapasitas Fan)

Efisiensi * 3600 - Pressure Drop= 375 Pa (Kehilangan tekanan)

P = 79 Watt - AHU = 1.5 inWg (375 Pa)- FCU = 1 inWg (250 Pa)

- v = 3 m/s (kecepatan udara keluar dari fan) - Efisiensi = 0.8

4. Diameter Pipa CHWS/R Pada AHU

1 = 540,000 Btu/h (Kapasitas Pendinginan)= x = 158.12 kW

= 4.2 kJ/kg.K (Konstanta panas air)g = 1000 kg/m3 (massa jenis air)

= 6

d = = 279

= 12

= 285d = 0.063 m p = 3.14d = 63 mm v = 2 m/s (Kecepatan air dalam pipa)

Q * 1.7 * ( Pressure Drop + v2 * 0.6 )

QAC (kW) QAC

d2

1/4 x p x v Cp x g x (t0 - ti) Cp

4 QAC (kW) tioC (Suhu air masuk AHU)oK

p x v x Cp x g x (t0 - ti) t0oC (Suhu air keluar AHU)oK

Page 2: Engineering Calculation

5. Kapasitas Pompa CHWS/R

Q = X = 9.1 LPM/TR (Kapasitas air tiap 1 TR)- Air Cooled Chiller = 9.1 LPM/TR

Q = 2848.3 LPM - Water Cooled Chiller = 11.4 LPM/TR

313 TR (Kapasitas chiller)

6. Head Pompa CHWS/R

Panjang seluruh pipa dengan posisi vertikal = 80 mPanjang pipa ke unit AHU/FCU terjauh = 100 mTekanan air keluaran ke unit AHU/FCU = 2 mFaktor kehilangan tekanan dalam pipa per meter = 0.03 m------------------------------------------------------------------------------------------------------------H = 80 + 100 x 0.03 + 0.03 = 83 m

7. Diffuser dan Grillea. Jumlah Titik Diffuser dan Grille

Q * 472 dengan : * Kecepatan Udara Yang Disarankan (dalam m/s)p * l * v No.

Q = 8,087 CFM (Laju aliran udara dari AHU/FCU) 1p = 300 mm (panjang ukuran diffuser/grille) 2

S = 17 bh l = 300 mm (lebar ukuran diffuser/grille)3

v = 2.5 m/s (kecepatan udara dari diffuser/grille)*4

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------b. Ukuran Diffuser dan Grille

L =Q * 472 dengan :

Q = 875 CFM (Laju aliran udara dari AHU/FCU)- Persegi : ---> 446 mm x 446 mm S = 1 titik (jumlah titik diffuser/grille)

v = 2.08 m/s (kecepatan udara dari diffuser/grille)*- Persegi Panjang dengan panjang : 250 mm

---> 250 mm x 794 mm

X * QAC

QAC =

S =

mm2

S * v

Page 3: Engineering Calculation

m/s (kecepatan udara keluar dari fan)

Page 4: Engineering Calculation

* Kecepatan Udara Yang Disarankan (dalam m/s)Aplikasi Diffuser Grille

Rumah/Hotel/Apartemen 2 3Kantor 2.5 4Gedung Umum/Bioskop/

4 5Shopping CenterGudang/Pabrik 5 6

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

CFM (Laju aliran udara dari AHU/FCU)titik (jumlah titik diffuser/grille)m/s (kecepatan udara dari diffuser/grille)*

p 100 296797l 47 158797L kotak 4700 4272.7273Deq 63.9455782 138000

Page 5: Engineering Calculation

L bulat 3212.81477 100000

Deq,f 73.6504119 38000

L bulat 4262.01535 R= 150 mm

D = 0.3 mm 0.4266667e = 0.00015 mRe = 140500 0.0042667f1 = 0.0195

f = 0.019490621675413

0.5

Page 6: Engineering Calculation

AIR CONDITIONING (2)

1. Kapasitas Unit Fan

Volume Ruangan (V) : Pertukaran Udara : SNI-03-6572-2001p = 2 m (panjang) Tipe Pertukaran udara per jaml = 1 m (lebar) Kantor, Parkiran 6t = 3 m (tinggi) Restoran/kantin 6

Toko, Swalayan 6Pertukaran udara = 10 kali/jam Pabrik, Bengkel 6

Kelas, Bioskop 8= 1 unit Lobi, Koridor, tangga 4

V Toilet, Peturasan 10Q = --- x Pertukaran Udara Dapur 20

S= 60= 35 CFM* * : kapasitas per 1 unit fan

2. Kapasitas Pressurized Fan

Q = p = 2 m (Tinggi pintu kebakaran)l = 1 m (lebar pintu kebakaran)

Q = 28,080 3 bh (Jumlah pintu kebakaran yang terbuka ketika terjadi kebakaran, min. 3 bh)v = 1.3 m/s (Kecepatan udara yang keluar dari pintu, min. 1.3 m/s)

= 16,527 CFM* Note : perhitungan lain => 500 - 750 CFM * jumlah seluruh pintu kebakaran

3. Daya Listrik Fan (Ventilating Fan Tanpa Ducting)

P = - Q = 18,970 CFM (Kapasitas Fan)

Efisiensi - v = 4 m/s (kecepatan udara keluar dari fan, 3 - 4 m/s)

P = 2,694 Watt - Efisiensi = 0.8

Jumlah Fan (S)

m3/h (CMH)*

p * l * S * v * 3600

m3/h (CMH) S =

0.0071 * Q * v2

Page 7: Engineering Calculation

bh (Jumlah pintu kebakaran yang terbuka ketika terjadi kebakaran, min. 3 bh)m/s (Kecepatan udara yang keluar dari pintu, min. 1.3 m/s)

* Note : perhitungan lain => 500 - 750 CFM * jumlah seluruh pintu kebakaran

Page 8: Engineering Calculation

ELECTRICAL

1. Resistance of the Cable Conductor (AC)

S = 1.5 (Cross sectional area of insulated conductor)L = 20 m (Length of conductor)

R = = 15.00 0.300 W (Copper Cable)

R = = 24.00 0.480 W (Aluminium Cable)

2. Voltage Dropsa. Single Phase (phase/phase or phase/neutral) b. Balanced 3-phase (with or without neutral)

V = 220 Volt V = 380 Volt

4 A (full load current) 200 A

R = 15 (conductor resistance) R = 0.08

X = 0.08 (conductor reactance) X = 0.08

1 (power factor) 0.8

0.0 (power factor) 0.6

L = 20 m (length of cable) L = 100 m

2.45 V ≈ 1.12 % 3.88 V ≈

Note : - Lighting drop = 3% - Others drop = 5%

3. Ukuran Penampang Kabela. Rangkaian 1-phase

S =22.5

1 (power factor)1.12 % (voltage drop : maximum lighting drop = 3% ; others = 5% )

V = 220 V (Tegangan 1-phase)S = 1.5 1 kW (Daya beban)

L = 20 m (Panjang kabel)X = 0.08

0.0 (power factor)

mm2

22.5 W mm2/kmW/km =

S (c.s.a in mm2)

36 W mm2/kmW/km =

S (c.s.a in mm2)

DU = 2 IB ( R cos j + X sin j ) L/1000 DU = 3 IB ( R cos j + X sin j ) L/1000

IB = IB =

W/km W/km

W/km W/km

cos j = cos j =

sin j = sin j =

DU = DU =

- X = 0.08 W/km, negligible less than 50mm2

g cos j g = W mm2/km (hambat jenis : Cu = 22.5 W mm2/km ; Al = 36 W mm2/km)

DU*V2*cos j * S - X sin j

cos j =2*P*L*100 DU =

mm2 P =

W/km (reaktansi kabel : 0.08 W/km, negligible less than 50mm2)sin j =

Page 9: Engineering Calculation

1 kali (jumlah tarikan kabel per phase)

b. Rangkaian 3-phase seimbang

S =22.5

0.8 (power factor)5 % (voltage drop : maximum lighting drop = 3% ; others = 5% )

V = 380 V (Tegangan 3-phase)S = 296 1,700 kW (Daya beban)

L = 250 m (Panjang kabel)X = 0.08

0.6 (power factor)8 kali (jumlah tarikan kabel per phase)

4. Capacitor Bank

Qc = = 277 kVAR

P = 500 kW0.75 (power factor awal)0.95

5. Short Circuit Current (Isc) / Breaking Capacity

Daya di Gardu Induk S = 500 MVATegangan Menengah U = 20,000 VTegangan Rendah V = 400 V

A). Tegangan Menengah (Di Panel MVDP)1). Jaringan PLN :

Impedansi (Z) =R=0.1 * X X=0.995 * Z

S 87.5600 875.6000

2). Instalasi Kabel Tegangan Menengah (Gardu PLN - MVDP) - Kabel Feeder Tembaga (Cu)

Size = 6 x 1 x 150 mm2 3.0000 1.6000 90.5600 L = 40 m

- Kabel Feeder Aluminium (Al) Size = 3 x 1 x 95 mm2 0.0000 0.0000

L = 0 m

B). Tegangan Rendah (Di Panel LVMDP)1). Jaringan PLN :

Impedansi (Z) =R=0.1 * X X=0.995 * Z

S 0.0350 0.3502

S =

g cos j g = W mm2/km (hambat jenis : Cu = 22.5 W mm2/km ; Al = 36 W mm2/km)

DU*V2*cos j * S - X sin j

cos j =P*L*100 DU =

mm2 P =

W/km (reaktansi kabel : 0.08 W/km, negligible less than 50mm2)sin j =

S =

P * ( tan j1 - tan j2 )

cos j1 = cos j2 = (power factor harapan, lebih besar dari cos j1)

R (mW) X (mW) RT (mW)

1.1 x U2

x 1000 (mW)

1.1 x V2

x 1000 (mW)

Page 10: Engineering Calculation

2). Instalasi Kabel Tegangan Menengah (Gardu PLN - MVDP) - Kabel Feeder Tembaga (Cu)

Size = 6 x 1 x 150 mm2 0.0012 0.0006 L = 40 m

- Kabel Feeder Aluminium (Al) Size = 3 x 1 x 95 mm2 0.0000 0.0000

L = 0 m

3). Instalasi Kabel Tegangan Menengah (MVDP - Trafo) - Kabel Feeder Tembaga (Cu)

Size = 3 x 1 x 70 mm2 0.0026 0.0006 L = 20 m

- Kabel Feeder Aluminium (Al) Size = 3 x 1 x 70 mm2 0.0000 0.0000

L = 0 m

4). Trafo P = 2,500 kVAZ = 7 %

Impedansi (Z) = = 4.480.672 4.4293

P * 100

5). Instalasi Kabel Tegangan Rendah (Trafo - LVMDP) - Kabel Feeder Tembaga (Cu)

Size = 32 x 1 x 300 mm2 1.4063 1.5000 2.1170 L = 150 m

- Kabel Feeder Aluminium (Al) Size = 12 x 1 x 240 mm2 0.0000 0.0000

L = 0 m

C). Tegangan Rendah (Di Panel-panel Distribusi)Instalasi Kabel Tegangan Rendah (LVMDP - Panel Distribusi) - Kabel Feeder Tembaga (Cu)

Size = 32 x 1 x 300 mm2 1.1250 1.2000 3.2420 L = 120 m

Total hambatan kabel feeder dari LVMDP = 1.1250 1.2000

- Kabel Feeder Aluminium (Al) Size = 1 x 4 x 240 mm2 0.0000 0.0000

L = 0 m

Total hambatan kabel feeder dari LVMDP = 0.0000 0.0000

Z * V2

(mW)

Page 11: Engineering Calculation

6. Jumlah Armatur Lampu (N)

E * AN = = 27 bh

= 12,800 Lumen

E = 1,250 I = 80 Lumen/Watt (Kuat cahaya)A = 128 m2 (Luas bidang kerja) P = 40 Watt (Daya lampu)

0.57 4 bh (Jumlah lampu per armatur)

Q = 12,800d = 1 Depresiasi (0.7 - 0.85) Jenis Lampu Kuat Cahaya (I)

----------------------------------------------------------------------------- Pijar 11 - 18TL 50 - 80

perhitungan indeks ruangan (k) " Halogen 16 - 20p * l Mercury 30 - 60

k = = 2.32 Halide 80 - 100h * ( p + l ) Sodium 120 - 140

p = 8 m (panjang ruangan)l = 16 m (lebar ruangan)

h = 2 m (tinggi lampu diatas bidang kerja)

k = 0.5 0.75 1 1.5 2 3 4 >=50.24 0.36 0.44 0.50 0.55 0.60 0.64 0.68

(3). Flux Cahaya (Q) :

h * Q * d Q = S * I * P

Lux (Intensitas penerangan)(1)

h = Efisiensi penerangan(2) S =

Lumen (Flux cahaya lampu)(3)

(2). " Penentuan nilai efisiensi (h) dengan

Hubungan besar nilai (k) dengan (h) :

h =

Page 12: Engineering Calculation

Balanced 3-phase (with or without neutral)

(full load current)

(conductor resistance)

(conductor reactance)

(power factor)

(power factor)

(length of cable)

1.02 %

% (voltage drop : maximum lighting drop = 3% ; others = 5% )

j + X sin j ) L/1000

/km (hambat jenis : Cu = 22.5 W mm2/km ; Al = 36 W mm2/km)

/km, negligible less than 50mm2)

Page 13: Engineering Calculation

% (voltage drop : maximum lighting drop = 3% ; others = 5% )

Isc =V

(kA)

Breaking Capacity di MVDP

877.2000 13.09 kA

/km (hambat jenis : Cu = 22.5 W mm2/km ; Al = 36 W mm2/km)

/km, negligible less than 50mm2)

XT (mW) 3 * RT2 + XT2

Page 14: Engineering Calculation

Breaking Capacity di LVMDP

6.2808 34.84 kA

Breaking Capacitydi Panel Distribusi

7.4808 28.33 kA

Page 15: Engineering Calculation

SNI 03-6197-2000

Jenis Ruangan E (Lux) Jenis Ruangan E (Lux)Rumah Rumah Sakit- Teras/Garasi 60 - Rg. Rawat Inap/rekreasi&rehab 250- Rg. Tamu 120 - 150 - Rg. Operasi/bersalin 300- Rg. Makan/kerja/tidur 120 - 250 - Laboratorium 500

- Kamar mandi/dapur 250 Pertokoan/Rg. PamerPerkantoran - Rg. Pamer/Tk. Mainan 500 - Rg. Direksi/kerja/komp. 350 - Tk. Perhiasan/arloji/pakaian 500 - Rg. Rapat/arsip aktif 300 - Tk. Kulit/sepatu/swalayan 500 - Rg. Gambar 750 - Tk. Kue/makanan/bunga 250 - Gudang arsip 150 - Tk. Listrik/musik/olahraga 250Lembaga Pendidikan - Tk. Buku/alat tulis/gambar 300 - Rg. Kelas 250 Industri - Perpustakaan 300 - Gudang 100 - Laboratorium 500 - Pekerjaan kasar 100 - 200 - Rg. Gambar 750 - Pekerjaan menengah 200 - 500 - Kantin 200 - Pekerjaan halus 500 - 1000Hotel & Restoran 200 - Pekerjaan amat halus 1000 - 2000 - Lobi/Koridor 100 - Pemeriksaan warna 750 - Rg. Serbaguna/Kafe 200 Rumah Ibadah - Rg. Makan 250 - Masjid/Gereja/Vihara 200 - Kamar Tidur 150 - Dapur 300

(1). Intensitas penerangan (E) di ruangan :

Page 16: Engineering Calculation

FIRE FIGHTING

1. Kapasitas Pompa Fire Fighting

a. Electric / Diesel Fire PumpPerkiraan jumlah alat yang berfungsi ketika terjadi kebakaran :1). Sprinkler : 20 bh x 80 LPM = 1,600 LPM2). Indoor Hydrant Box : 2 bh x 400 LPM = 800 LPM3). Hydrant Pillar : 2 bh x 1,000 LPM = 2,000 LPM

4,400 LPM = 1,162 USGPM-----------------------------------------------------------------------------------------------------------------------------b. Jockey Fire Pump

Kapasitas ± 5 - 10 % Electric Fire Pump ---> 5 % dari kapasitas Electric Fire Pump

= 220 LPM = 58.1 USGPM

2. Head Pompa Fire Fighting

- Panjang seluruh pipa dengan posisi vertikal = 75 m- Panjang pipa dengan keluaran IHB/OHB/Sprinker terjauh = 175 m- Tekanan air keluar dari Hydrant = 7 bar- Tekanan air keluar dari Sprinkler = 2 bar- Faktor kehilangan tekanan dalam pipa per meter = 0.05 m

---------------------------------------------------------------------------------------------------------------------------H = 75 + 175 x 0.05 + ( 7 + 2 ) x 10 = 174 m

3. Daya Listrik Pompa

Head = 150 m 1.1 = for electricKapasitas = 4,000 LPM 1.2 = for diesel

0.163 x 150 x 4 x 1.1P = = 179 kW

Efisiensi : 0.6

4. Kapasitas Tangki Fire Fighting

a. Kapasitas Electric Fire Pump = 1,000 USGPMb. Durasi waktu Electric Fire Pump bekerja = 120 menit

memadamkan api

----> Kapasitas tangki fire fighting = 454

5. Volume Pressure Tank

1)

1)

m3

Page 17: Engineering Calculation

Q'e + Q'a P'a + PbV = K * 0.312 * * * 1000 = 2,719 Liter Q'a

2 * Z P'a - P'e =Q'e

Pb = 1.0 bar (tekanan atmosfer)P'a = 7.0 bar (tekanan air saat pompa mati) Q'a/Q'e KP'e = 3.0 bar (tekanan air saat pompa hidup) 0 0Q'e = 34 m3/h (kapasitas pompa saat mati, di grafik pompa) 0.1 0.5Q'a = 27 m3/h (kapasitas pompa saat hidup, di grafik pompa) 0.2 0.78

Z = 7 kali (frekuensi mati/hidup pompa berdasarkan daya) 0.3 0.91 ------> - dibawah 1.5 kW = 15 - 30 kali 0.4 0.97

- 1.5 kW - 15 kW = 8 - 12 kali 0.5 0.99- diatas 15 kW = 6 - 8 kali > 0.5 1

K = 1

6. Ukuran Diameter Pipa

d =200 * Q Q = 284 LPM (Debit air dalam pipa)

v = 4.5 m/s (kecepatan air dalam pipa)3.14

d = 37 mm

7. Jumlah Titik Sprinkler

P = 115 m (Panjang ruangan) * Jarak Antar Sprinkler (X) :L = 65 m (Lebar ruangan) Klasifikasi Bangunan Jarak (m)X = 4.5 m (Jarak antar sprinkler)* Bahaya Ringan 4.25

Bahaya Sedang 3.40S = 390 titik Bahaya Berat 2.55

8. Diameter Pipa Sprinkler

- Banyaknya Sprinkler = 309 titik

----> Diameter Pipa = 200 mm

* Max. 450 titik, jika lebih dari 450 maka dibuat pipa baru

1) Correction Factor :

Correction Factor 1)

3 * p * vp =

Page 18: Engineering Calculation
Page 19: Engineering Calculation

0.8

Correction Factor :

Page 20: Engineering Calculation

PLUMBING

1. Kebutuhan Air Bersih

Estimasi Kebutuhan Air Bersih Berdasarkan Alat Plumbing :

No. Alat PlumbingJangka Waktu Penggunaan Pemakaian Air Faktor

per jam Setiap Kali Pakai

1 WC 210 8 Jam9 kali/jam 12 Liter

0.226 - 12 kali/jam 10 - 14 Liter

2 Kran WC 210 8 Jam9 kali/jam 5 Liter

0.226 - 12 kali/jam 4 - 6 Liter

3 Urinoir 90 8 Jam16 kali/jam 7 Liter

0.3312 - 20 kali/jam 6 - 8 Liter

4 Lavatory 270 8 Jam16 kali/jam 10 Liter

0.2212 - 20 kali/jam 8 - 12 Liter

5 Kitchen Zink 0 0 Jam9 kali/jam 25 Liter

0.556 - 12 kali/jam 20 - 30 Liter

6 Bath Tube 0 0 Jam6 kali/jam 125 Liter

0.004 - 8 kali/jam 100 - 150 Liter

7 Shower 30 8 Jam6 kali/jam 50 Liter

0.404 - 8 kali/jam 40 - 60 Liter

8 Others… 0 0 Jam0 kali/jam 0 Liter

0.00- -

9 Others… 0 0 Jam0 kali/jam 0 Liter

0.00- -

10 Others… 0 0 Jam0 kali/jam 0 Liter

0.00- -

TOTAL

2. Kapasitas Tangki Air Bersih (Ground Tank)

- 0.06 * Qs * T + Vf1000 No. Jenis Gedung

1 Kantor140 2 Apartemen

3 Hoteldengan :

4Restauran/Gedung Pertunjukan

= 188,000 L (Jumlah kebutuhan air per hari) 5 Sekolah

Jumlah

(bh)Pemakaian per hari 1) Keserempakan 2)

1) Tabel Jangka Waktu Pemakaian Rata-rata Dalam Sehari :

Vg =Qd

Vg = m3

Qd

Page 21: Engineering Calculation

= 100 LPM (Kapasitas PAM/Deep Well) 6 Rumah Sakit

T = 8 7 Asrama

= 08

Shopping Centre/Department Store

3. Kapasitas Tangki Air Bersih (Roof Tank)Penentuan kapasitas air bersih di lantai atap :a). Pemakaian Air Rata-rata per Jam

(Pemakaian air rata-rata tiap jam)T

47,000 L/h23,500 L/h

dengan :dengan : 23,500 L/h (Pemakaian air rata-rata

188,000 Liter (Kebutuhan air per hari) tiap jam)

T = 8 2 Konstanta pemakaian airpada jam puncak (1.5 - 2)

b). Pemakaian Air Rata-rata per Menit

(Pemakaian air rata-rata tiap menit)dengan :

60 23,500 Liter (Pemakaian air rata-rata tiap jam)3 Konstanta pemakaian air

1,175 LPM puncak setiap menit (3 - 4)

c). Pompa Pengisi Tangki (Transfer Pump)

dengan :60 47,000 L/h (Kebutuhan air pada jam puncak)

1.5 Konstanta pompa transfer (1 - 2)1175 LPM

d). Kapasitas Tangki Air Bersih (Roof Tank)

-dengan :

60 1,175 LPM (Pemakaian air rata-rata tiap menit)47,000 L/h (Kebutuhan jam puncak)

47 60

1,175 LPM (Pemakaian air rata-rata tiap menit)20 menit (Waktu kerja pompa, 10 - 30 menit)

4. Daya Listrik Pompa

Head = 80 m 1.1 = for electricKapasitas = 5,700 LPM 1.2 = for diesel

Qs

jam (Jangka waktu pemakaian rata-rata per hari) 1)

Vf m3 (Volume air cadangan untuk fire fighting)

Qh =Qd Qh max = C1 * Qh (Kebutuhan jam puncak)

Qh max =Qh =

Qh =Qd =

Jam (Pemakaian air rata-rata per hari)1) C1 =

Qm max =C2 * Qh

Qh =C2 =

Qm max =

Qpu =C3 * Qh max

Qh max = C3 =

Qpu =

VE = {(Qm maxQh max

) * tp + ( Qpu * Tpu )} / 1000Qm max =Qh max =

VE = m3 tp = menit (Waktu kebutuhan puncak, +60 menit)

Qpu =Tpu =

1)

Page 22: Engineering Calculation

0.163 x 80 x 5.7 x 1.1P = = 136 kW

Efisiensi : 0.6

5. Head Pompa

- Panjang seluruh pipa dengan posisi vertikal = 170 m- Panjang pipa ke output terjauh (dari tangki sumber air) = 200 m- Faktor kehilangan tekanan dalam pipa per meter = 0.05- Tekanan air keluaran dari fixture plumbing = 7 m- Safety factor head pompa = 10 %

------------------------------------------------------------------------------------------------------------H = 170 + 200 x 0.05 + 7 + 18.7 = 206 m

6. Volume Pressure Tank

Q'e + Q'a P'a + PbV = K * 0.312 * * * 1000 = 2,719 Liter Q'a

2 * Z P'a - P'e = 0.8Q'e

Pb = 1.0 bar (tekanan atmosfer)P'a = 7.0 bar (tekanan air saat pompa mati) Q'a/Q'e KP'e = 3.0 bar (tekanan air saat pompa hidup) 0 0Q'e = 34 m3/h (kapasitas pompa saat mati, di grafik pompa) 0.1 0.5Q'a = 27 m3/h (kapasitas pompa saat hidup, di grafik pompa) 0.2 0.78

Z = 7 kali (frekuensi mati/hidup pompa berdasarkan daya) 0.3 0.91 ------> - dibawah 1.5 kW = 15 - 30 kali 0.4 0.97

- 1.5 kW - 15 kW = 8 - 12 kali 0.5 0.99- diatas 15 kW = 6 - 8 kali > 0.5 1

K = 1

7. Ukuran Diameter Pipa

d =200 * Q Q = 1,175 LPM (Debit air dalam pipa)

v = 2.5 m/s (kecepatan air dalam pipa)3.14

d = 100 mm

1)

1) Correction Factor :

Correction Factor 1)

3 * p * vp =

Page 23: Engineering Calculation

Faktor Kebutuhan No. Jenis Gedung Jangka Waktu/Hari(per hari) 1 Kantor 8 - 10 Jam

0.22 39,917 Liter2 Apartemen 8 - 10 Jam3 Hotel 8 - 10 Jam

0.22 16,632 Liter 4Restauran/

3 - 5 JamGedung Pertunjukan

0.33 26,611 Liter5 Sekolah 4 - 6 Jam6 Rumah Sakit 8 - 10 Jam

0.22 76,032 Liter7 Asrama 8 - 10 Jam

8Shopping Centre/

5 - 7 Jam0.55 0 Liter

Department Store

0.00 0 Liter

0.40 28,800 LiterNo. Jumlah Dengan Tanpa

Alat (bh) Flush Valve Flush Valve

0.00 0 Liter1 1 1.00 1.002 2 0.50 1.00

0.00 0 Liter3 3 - 4 0.50 0.754 5 - 6 0.40 0.75

0.00 0 Liter5 7 - 10 0.40 0.556 11 - 14 0.30 0.48

TOTAL 187,992 Liter7 15 - 20 0.27 0.458 21 - 28 0.23 0.429 29 - 36 0.19 0.40

10 37 - 45 0.17 0.3911 46 - 57 0.15 0.3712 58 - 80 0.13 0.3513 81 - 105 0.12 0.3314 106 - 140 0.11 0.3015 141 - 190 0.10 0.2616 191 - 275 0.09 0.2217 276 - 400 0.08 0.1818 401 - 700 0.07 0.15

Jangka Waktu/Hari8 - 10 Jam8 - 10 Jam8 - 10 Jam

3 - 5 Jam

4 - 6 Jam

1) Tabel Jangka Waktu Pemakaian Rata-rata Dalam Sehari :

Keserempakan 2)

2) Faktor Keserempakan :

Tabel Jangka Waktu Pemakaian Rata-rata Dalam Sehari :

Page 24: Engineering Calculation

8 - 10 Jam

8 - 10 Jam

5 - 7 Jam

No. Jenis Gedung Jangka Waktu/Hari1 Kantor 8 - 10 Jam2 Apartemen 8 - 10 Jam3 Hotel 8 - 10 Jam

4Restauran/

3 - 5 JamL/h (Pemakaian air rata-rata Gedung Pertunjukan

5 Sekolah 4 - 6 Jam

Konstanta pemakaian air 6 Rumah Sakit 8 - 10 Jampada jam puncak (1.5 - 2) 7 Asrama 8 - 10 Jam

8Shopping Centre/

5 - 7 JamDepartment Store

Liter (Pemakaian air rata-rata tiap jam)Konstanta pemakaian airpuncak setiap menit (3 - 4)

LPM (Pemakaian air rata-rata tiap menit)L/h (Kebutuhan jam puncak)

LPM (Pemakaian air rata-rata tiap menit)menit (Waktu kerja pompa, 10 - 30 menit)

1) Tabel Jangka Waktu Pemakaian Rata-rata Dalam Sehari :

(Kebutuhan jam puncak)

menit (Waktu kebutuhan puncak, +60 menit)

Page 25: Engineering Calculation
Page 26: Engineering Calculation

SOUND SYSTEM

1. Sound Pressure Level (SPL)

SPL = dengan := 100 dB (Tingkat suara pada unit speaker)

SPL = 99.7 dB P = 15 W (Daya listrik speaker)R = 4 m (jarak speaker ke titik pendengar)

(SPL Speaker Unit + 10 log P) - 20 log RSPL Speaker Unit

Page 27: Engineering Calculation

dB (Tingkat suara pada unit speaker)W (Daya listrik speaker)m (jarak speaker ke titik pendengar)