Rencana Anggaran Biaya Daftar Harga BarangNoNama MaterialSatuanHarga Satuan (Rp)
1MCB Schneider Domae 32 ABh34.000
2MCB Schneider Domae 10 ABh34.000
3Box MCB Bh38.000
4Sakelar Tunggal BrocoBh7.000
5Sakelar Seri BrocoBh15.000
6Stop Kontak Broco GracioBh11.500
7Stop Kontak AC PanasonicBh50.000
8Fitting Plafon Persegi BrocoBh9.000
9Variasi lampu tamanBh70.000
10Lampu Philips 5 WattBh23.000
11Lampu Philips 10 WattBh26.000
12Lampu Philips 12 WattBh27.000
13Lampu Philips 15 WattBh31.000
14Lampu Philips 20 WattBh28.000
15Lampu Philips 25 WattBh36.000
16Lampu Philips 50 WattBh115.000
17Kotak Hubung T-dos ClipsalBh4.500
18Inbowdoss PanasonicBh2.000
19Klem Pipa 5/8"Bh500
20Elbow PVC 5/8Bh8.500
21Isolasi UnibelBh8.000
22Arde Pancang 15 mm2Meter16.000
23Pipa Galvanis 5/8Meter37.500
24Pipa PVC 5/8Btg10.000
25Kabel NYA 2,5 mm2 Merah Meter2.300
26Kabel NYA 2,5 mm2 Biru Meter2.300
27Kabel NYA 2,5 mm2 Kuning Hijau Meter2.300
28Kabel NYY 2 x 2,5 mm2 Meter11.000
29Kawat BC 6 mm2Meter6.500
Biaya Material`NoNama MaterialSatuanHarga Satuan(Rp)Volume1 unitRumahHargaTotal(Rp)
1MCB Schneider Domae 32 ABh34.000134.000
2MCB Schneider Domae 10 ABh34.0003102.000
3Box MCB Bh38.000276.000
4Sakelar Tunggal BrocoBh7.000856.000
5Sakelar Seri BrocoBh15.0008120.000
6Stop Kontak Broco GracioBh11.50030345.000
7Stop Kontak AC PanasonicBh50.0008400.000
8Fitting Plafon Persegi BrocoBh9.00034306.000
9Variasi lampu tamanBh70.0005350.000
10Lampu Philips 5 WattBh23.0005115.000
11Lampu Philips 10 WattBh26.0004104.000
12Lampu Philips 12 WattBh27.00029783.000
13Lampu Philips 15 WattBh31.000262.0000
14Lampu Philips 20 WattBh28.000128.000
15Lampu Philips 25 WattBh36.0004144.000
16Lampu Philips 50 WattBh115.0001115.000
17Kotak Hubung T-dos ClipsalBh4.50074333.000
18Inbowdoss PanasonicBh2.00053106.000
19Klem Pipa 5/8"Bh500500250.000
20Elbow PVC 5/8Bh8.50041348.500
21Isolasi UnibelBh8.000864.000
22Arde Pancang 15 mm2Meter16.0001.524.000
23Pipa Galvanis 5/8Meter37.50011,5431.250
24Pipa PVC 5/8Btg10.00035350.000
25Kabel NYA 2,5 mm2 Merah Meter2.300108248.400
26Kabel NYA 2,5 mm2 Biru Meter2.300104239.200
27Kabel NYA 2,5 mm2 Kuning Hijau Meter2.30046105.800
28Kabel NYY 3 x 2,5 mm2 Meter11.00036396.000
29Kawat BC 6 mm2Meter6.5001597.500
Biaya Total Material6.133.650
Biaya Pekerja (buruh)
Perhitungan jam kerja untuk melaksanakan pemasangan dan kabel untuk 1 Unit RumahNoNama MaterialVolume 1 Unit RumahSatuanWaktu Pemasangan (jam)Jumlah Waktu Pemasangan (jam)
1Pipa PVC 5/8"105Meter0.4345.15
2Pipa Galvanis 5/8"11.5Meter0.434.945
3Kotak sambung, saklar, atau stop kontak128Bh0.451.2
4Kabel NYA 2.5 mm2 Merah108Meter0.038.64
5Kabel NYA 2.5 mm2 Biru104Meter0.033.12
6Kabel NYA 2.5 mm2 Kuning46Meter0.031.38
7Kabel NYY 2 x 2.5 mm236Meter0.4315.48
Total Waktu Pemasangan129.915
Apabila pekerja untuk tukang listrik adalah Rp. 7.500 per jam, maka biaya pelaksanaan atau biaya pekerja adalah :Untuk Biaya Pekerja untuk 1 Unit rumah := 129.915 x Rp. 7500 = Rp 974.363
Biaya Keseluruhan Proyek
Biaya Keseluruhan Proyek 1 Unit Rumah :
Biaya MaterialRp. 6.133.650Biaya Pekerja (buruh) Rp. 974.363
Biaya Peralatan ditaksir Rp. 2.000.000
Jumlah Rp. 9.108.013Biaya Tak terduga di taksir 10%Rp. 910.801
Total Biaya Rp. 10.018.814Keuntungan 10% dari total biaya Rp. 1.001.881
Jumlah biaya keseluruhan proyek Rp. 11.020.692PPN 10%Rp. 1.102.062TotalRp. 12.122.757DibulatkanRp. 12.123.000