    FIDIC CONTRACTS ANDBEST PROCUREMENT PRACTICE

    Ministry of Electricity and Dams

    Dams Implementation Unit

    Contracts Directorate

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    2/40

    FIDIC CONTRACTS

    CONSTRUCTION

    PLANT AND DESIGN-BUILD /

    EPC/TURNK EY PROJECTS

    SHORT FORM OF CONTRACT

    CLIENT/CONSULTANT MODEL SERVI CES AGREEMENT

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    3/40

    CONDITIONS OF CONTRACT

    Guide

    published 2001

    published 1999

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    4/40

    CONTRACT CONTINUITY

    Employer /

    consultant

    design

    Contractor

    design

    Various formats Uniform format and contentsMinistry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    5/40

    WHICH BOOK TO USE?

    STRAIGHTFORWARD

    PROJECT ? EMPLOYER DESIGN ?

    CONTRACTOR DESIGN

    plant and/orhigh

    unforeseenrisks

    fixed price - lump sum

    little employerinvolvement

    no major unforeseenrisks

    DISCUSS IN DETAIL

    Employer srequirements with

    the Contractor, andnegotiate a

    modified FIDIC

    contractMinistry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    6/40

    FEATURES AND ADVANTAGES

    fair apportioning of risks, rights and obligations between the parties

    BALANCED

    WELL TRIED

    long case history for earlier contracts

    ACCEPTED

    known and recognised; in wide use for international contracts

    SUPPORTED

    recommended or required by development banks, etc.

    EFFECTIVE

    clear and complete conditions; time limits; provisions foradjudication

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    7/40

    Key points: CONSTRUCTION

    Employer designs

    Engineer, working for the Employer

    Bill of Quantities

    Payments based upon measurements

    Certification of payments by Engineer

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    8/40

    Key points: PLANT& DESIGN-BUILD

    Contractor designs

    Engineer, working for the Employer

    Lump sum pricing

    Payments according to progress

    Certification of payments by Engineer

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    9/40

    Key points: EPC/TURNKEY PROJECTS

    Contractor designs and takes full responsibility

    Employermayappoint a Representative

    Fixed price, to cover risks taken on by Contractor

    Payments according to progress

    No certification of payments

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    10/40

    Key points: SHORT FORM

    Simple projects

    Design by either

    Employermayappoint a Representative

    Valuation as appropriate; to be agreed

    Payments according to value of Works executed and

    Materials and Plant delivered to site

    No certification of payments

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    11/40

    Key points: CLIENT/CONSULTANT

    Agreed Scope of Services: Appendix A

    Normal, Additional and Exceptional Services

    Normal Services priced as agreed

    Additional and Exceptional Services at rates agreed

    Payment schedule as agreed

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    12/40

    FIDIC GUIDES

    The FIDIC Contracts Guide

    The White Book Guide

    Guide for the preparation of particular conditions

    (in the major contracts)

    Notes for Guidance (in the Short Form of Contract)

    Tendering Procedure and Pre-qualification forms

    Consultant SelectionMinistry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    13/40

    USE OF FIDIC CONTRACTS

    Match contract and project

    Decide early on type of contract

    Draft by professionals

    Do not touch the General Conditions

    Buy originals

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    14/40

    PRINCIPLES OF PROCUREMENT

    Effectiveness

    Economy

    Efficiency

    Accountability

    Transparency / confidentiality /

    Strong competition

    Publicity, wide participation

    Fair and equal conditions

    Standard procedures Standard documentation

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    15/40

    PROCUREMENT CATEGORIES

    Goods

    Works

    Consultant services

    Other services

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    16/40

    TENDERING PROCEDURES

    Development bank / public procurement procedures

    Open tendering / International Competitive Bidding

    Local tendering / National Competitive Bidding

    Restricted tendering / Limited Bidding

    Single source

    Two stage tendering

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    17/40

    SELECTION PROCEDURES/CRITERIA

    Criteria defined and published in advance

    Economically most advantageous offer

    Quality based selection

    Quality and cost based selection

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    18/40

    Establishment Of Project Strategy Comprising:

    Procurement method

    Form of tendering Time schedules

    FIDIC TENDERING PROCEDURE( FOR

    CONSTRUCTION CONTRACTS)

    1.0 ESTABLISHMENT of PROJECT STRATEGY

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    19/40

    Prepare Prequalification Documents Comprising:

    Letter of Invitation Information about prequalification procedure

    Project information

    Prequalification application

    2.1 PREPARATION of PREQUALIFICATION

    DOCUMENTS

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    20/40

    2.2 INVITATION TO PREQUALIFY

    Place Prequalification Advertisement In Press, Embassiesetc. as appropriate stating:

    Employer & Engineer Outline of project (scope, location, programme, source of

    finance)

    Dates for issue of tender documents, & submission of tenders

    Instruction for applying for prequalification

    Minimum requirements for prequalification

    Submission date for contractors prequalification data

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    21/40

    2.3 ISSUE & SUBMISSION OF PREQUALIFICATION DOCUMENTS

    Issue prequalification documents & Questionnaires requesting fromeach company/joint venture:

    Organisation & structure

    Experience in the intended type of work & the region

    Resources:

    - Managerial

    - Technical

    - Labour

    - Plant

    Financial Statement

    Current contract commitments

    Litigation history

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    22/40

    2.4 ANALYSIS OF PREQUALIFICATION APPLICATIONS

    Analysis Prequalification Applications Data:

    Company/joint venture structure

    Experience

    Resources Financial Capability : Annual Turnover, Working

    Capital= Ratio of Current Assets to Current

    Liabilities ( > 1.0 )General suitability

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    23/40

    2.5 SELECTION OF TENDERERS

    Prepare List of Tenderers

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    24/40

    2.6 NOTIFICATION OF APPLICANTS

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    Notify all selected tenderers

  • 7/31/2019 FIDIC Procure

    25/40

    3.1 PREPARATION OF TENDER DOCUMENTS

    Prepare Tender Documents:

    Letter of Invitation to tender

    Instructions to tenderers Condition of Contract

    Form of tender and appendices

    Drawings Bill of Quantities

    Schedule of additional

    information

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    26/40

    3.2 ISSUE OF TENDER DOCUMENTS

    Issue tender documents to

    contractors on list of tenderers

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    27/40

    3.3 VISIT TO SITE BY TENDERERS

    Arrange Date and Time for Visitto Site

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

  • 7/31/2019 FIDIC Procure

    28/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    3.4 TENDERERS QUERIES

    A) CORRESPONDENCE METHODB) TENDERERS CONFERENCE METHOD

    A) Prepare replies

    A) Inform tenders present of queries and replies

    submitted in writing replies to queries atconference

    Send Minutes to all Tenderers ( Parity of

    Tendering)

  • 7/31/2019 FIDIC Procure

    29/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    3.5 ADDENDA TO TENDER

    DOCUMENTS

    Issue Addenda Including Repliesto queries to all tenderers

  • 7/31/2019 FIDIC Procure

    30/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    3.6 SUBMISSION AND RECIPT OF TENDERS

    Record date and time of receipt

    Acknowledge receipt or return unopened

    tenders received late

  • 7/31/2019 FIDIC Procure

    31/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    4.1 OPENING OF TENDERS

    Tender opening by public or restricted opening:

    announce and record the names of tenderersand price, including price for alternative tenders

    if appropriate

    announce and record the names of tenderer (if

    any) disqualified due to late or non arrival of

    tenders

  • 7/31/2019 FIDIC Procure

    32/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    5.1 REVIEW OF TENDERS

    Establish conformity and completeness of tenders:

    Reject Substantially Unresponsive Tenders

    Establish conformity and completeness of tenders:

    Reject Substantially Unresponsive Tenders

    Establish conformity and completeness of tenders:

  • 7/31/2019 FIDIC Procure

    33/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    5.2 TENDERS CONTAINING DEVIATIONS

    Evaluate Deviations, Seek ClarificationsEvaluate Deviations, Seek ClarificationEvaluate Deviations Seek Clarification

  • 7/31/2019 FIDIC Procure

    34/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    5.3 ADJUDICATION OF TENDERS

    Assess tenders in accordance with evaluation criteria .

    Raise further points requiring clarification, if any.

    Complete evaluation.

    Check with funding agency.

    Reject non- conforming tenders & advise tenderer(s) concerned.

  • 7/31/2019 FIDIC Procure

    35/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    6.0 AWARD OF CONTRACT

    Decide on contract award, if necessary afterpre- award discussion

  • 7/31/2019 FIDIC Procure

    36/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    6.1 ISSUE LETTER OF ACCEPTANCE

    Issue Letter of Acceptance

  • 7/31/2019 FIDIC Procure

    37/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    6.2 PERFORMANCE SECURITY

    Obtain Performance Security From Contractor

  • 7/31/2019 FIDIC Procure

    38/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    6.3 PREPARATION OF CONTRACT

    AGREEMENT

    Prepare Contract Documents

    Signing of Contract

  • 7/31/2019 FIDIC Procure

    39/40

    Ministry of Electricity and Dams - Dams Implementation Unit -Contracts Directorate

    6.4 NOTIFICATION OF UNSUCCESSFUL TENDERERS

    Advise Unsuccessful Tenderers And Return TenderSecurity (If Provided)

  • 7/31/2019 FIDIC Procure

    40/40

    Fdration

    Internationale

    des

    Ingnieurs-Conse

    ils

    FIDIC Tendering Procedure

    FIDIC Standard Prequalification Form for Contractors