82
BOSNIA AND HERZEGOVINA MINISTRY OF FINANCE AND TREASURY FIRST LEVEL CONTROL OPERATIONAL MANUAL Cross Border Co-operation Programmes under shared management mode Version Approved by Signature 2.0, July 2013 Vera Letica, Assistant minister

FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

BOSNIA AND HERZEGOVINA MINISTRY OF FINANCE AND TREASURY

FFIIRRSSTT LLEEVVEELL CCOONNTTRROOLL OOPPEERRAATTIIOONNAALL

MMAANNUUAALL

CCrroossss BBoorrddeerr CCoo--ooppeerraattiioonn PPrrooggrraammmmeess

uunnddeerr sshhaarreedd mmaannaaggeemmeenntt mmooddee

Version Approved by Signature

2.0, July 2013

Vera Letica, Assistant minister

Page 2: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

Table of Contents List of Abbreviations

1.PURPOSE OF THE FLCOM………………………………………………………………….2

1.1 Register of modifications……………………………………………………………..3

2. INSTITUTIONAL AND REGULATORY FRAMEWORK……………………………4

2.1 Sharedmanagement……………………………………………………………………..4 2.2 Programme management structures……………………………………………4 2.3 EC Regulations……………………………………………………………………………..7 2.4 BIH Regulations………………………………………………………………………......7 2.5 Programme specific Regulations……………………………………………….….8

3. DESCRIPTION OF FIRST LEVEL CONTROL (FLC) SYSTEM IN BIH……….…9

3.1 System in place………………………………………………………………………….….9 3.2 Internal organisation of the Control Body………………………………….…10

4. PROCEDURES OF VERIFICATION OF EXPENDITURE…………………………..11

4.1 Objective of the FLC………………………………………………………………………11 4.2 Steps of the FLC/Validation process…………………………………………..…12 4.3 Reporting, verification and retention periods and deadlines….…...14 4.4 Desk-based administrative check………………………………………………...15 4.4.1 Staff costs………………………………………………………………………….…18 4.4.2 Overhead………………………………………………………………………….….21 4.4.3 Travel and accomodation…………………………………………………..…22 4.4.4 External expertise………………………………………………………………...25 4.4.5 Meetings and events………………………………………………………….…28 4.4.6 Promotion costs……………………………………………………………….…..30 4.4.7 Equipment……………………………………………………………………………32 4.4.8 Investments………………………………………………………………………….36 4.4.9 Financial charges and guarantee costs…………………………………40 4.5 On the spot checks……………………………………………………………………….41 4.5.1 Definition and purpose…………………………………………………………41 4.5.2 Risk assesment and sampling………………………………………… …..42 4.5.3 On the spot checks activity plan……………………………………….…..46 4.6 Documenting FLC checks………………………………………………………………47 5. SUBSTANTIVE PROCEDURES……………………………………………….……………48 5.1 Checks of completeness……………………………………………………….………49 5.2 Checks of compliance…………………………………………………………………..49 5.3 Checks of plausibility……………………………………………………………………51 5.4 Checks of existence and reality…………………………………………………….52

6. SUB PROCEDURES……………………………………………………………………………54

6.1 Inspection of documents and records…………………………………………..54 6.2 Reconciliation………………………………………………………………………………..55 6.3 Recalculation…………………………………………………………………………………56 6.3 Inquiry and interviews……………………………………………………………………57 6.4 Observation of events and processes…………………………………………….58 6.5 Walk- through………………………………………………………………………………..59 7. IRREGULARITIES………………………………………………………………………………63

Page 3: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

3

7.1. Background, definitions and types of irregularities…………………..63 7.1.1 Background……………………………………………………………………….63 7.1.2 Definitions…………………………………………………………………………63 7.1.3 Types of irregularities…………………………………………..……..…...64 7.1.4 Irregularities by type of infliction………………………………………65 7.1.5 Irregularities by type of impact………………………………………….66 7.1.6 Irregularities by nature………………………………………………………67 7.2 7.2.1 Detection and prevention…………………………………………………67 7.2.2 Reporting irregularities……………………………………………………..68 7.2.3 Recording irregularities…………………………………………………….71 7.2.4 Recovery of funds……………………………………………………………..73 8. PUBLIC PROCUREMENT………………………………………………………………..73 8.1 Rules on public procureemnt……………………………………………………..74 8.2 Basic rules to be respected…………………………………………………………74 8.2.1 Nationality and origin………………………………………………………..74 8.2.2 Language…………………………………………………………………………..75 8.3 Tender procedure walk-through…………………………………………………76 ANNEXIES

Page 4: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

LIST OF ABBREVIATIONS (IN ALPHABETICAL ORDER)

AA Audit Authority

AF Application Form

AR Activity Report

BiH Bosnia and Herzegovina

CBC Cross Border Co-operation

CFCU Central Financing and Contracting Unit

CNP Competitive Negotiated Procedure

DEI Directorate for European Integration

DVE Declaration on Validation of Expenditure

EC European Commission

EU European Union

FA Financing Agreement

FB Final Beneficiary

FLC First Level Control

FLCO First Level Control Office

FR Financial Report

FwA Framework Agreement

INF Irregularity Notification Form

IO Irregularity Officer

IPA Instrument for Pre-accession Assistance

JMC Joint Monitoring Committee

JTS Joint Technical Secretariat

KM Konvertible Mark

LB Lead Beneficiary

MA Managing Authority

MED Transnational Mediterranean Programme

MIS Management Information System

MoFT Ministry of Finance and Treasury

NA National Authority

NCF National Co-financing

NAO National Authorising Officier

OP Operational Programme

PMCM Programme Management and Control Manual

PRAG Practical Guide to contract procedures for EU external actions

SEE South East Europe Programme

TA Technical Assistance

VAT Value Added Tax

WD Working day

WP Work Package

Page 5: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

2

1. THE PURPOSE OF THE MANUAL

The purpose of this manual is to summarise and explain the procedures applicable within Cross Border Co-operation (CBC) Programmes under shared management in which either lead or final beneficiaries from Bosnia and Herzegovina (BiH) participate with respect to the validation of expenditure by the national First Level Control Office (FLCO) of approved projects as well as the handling of irregularities and recoveries. At the time of drafting this manual, programmes implemented under shared management in Bosnia and Herzegovina (BiH) are:

IPA Adriatic CBC Programme

South East Europe Programme (SEE)

Transnational Mediterranean Programme (MED)

The manual is designed primarily for use by the staff of the Central Financing and Contracting Unit (CFCU) within the Ministry of Finance and Treasury (MoFT) which has been appointed by means of a Decision by the Council of Ministers (Session 153) on 14 June 2011 and formally announced in the Official Gazette No 66/11 of 22 August 2011. With this decision the CFCU is officially designated as the national First Level Control Office (FLCO) in Bosnia and Herzegovina (BiH) for the above-mentioned programmes.

At the same time the manual can be consulted by beneficiaries from Bosnia and Herzegovina (BiH) that are part of a project implemented under any of the three programmes subject to this manual so as to get a better insight into the nature and kinds of checks performed by the First Level Controllers and to be drawn attention to some of the more challenging and potentially problematic areas such as adequate presentation of supporting documentation and public procurement of services, supplies and works.

Inherent to the nature of manuals of procedures is the fact that they may become subject to changes. Changes can be either small or substantial.

Page 6: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

3

Smaller changes (e.g. a row in a checklist) will be made by the person noticing the need to change it after having obtained prior approval from the Head of the CFCU and without changing the number of the version of the manual.

More substantial changes will be discussed in staff meetings and agreed upon, following the final approval of the Head of the CFCU who will nominate and appoint a member of staff in charge of effectuating the change prior to an agreed deadline.

The following procedures apply whenever there is a need to modify the manual:

Whenever a user identifies the need for a modification of the manual, s/he notifies the Head of the CFCU and prepares a proposal for the change to be implemented in writing. Once the change has been approved by the Head of the CFCU and the change is reflected in the updated manual, the Register of Modifications (as presented below) will be completed.

1.1. REGISTER OF MODIFICATIONS

Version

No.

Date of

change

Section modified Nature of the change

1.0 Juni 2012 N/A Final version for approval

2.0 July 2013 N/A Final version for approval

Page 7: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

4

2. INSTITUTIONAL AND REGULATORY FRAMEWORK

2.1. SHARED MANAGEMENT

According to IPA Implementing Regulation1, under component 2 – Cross-Border Co-operation, there are two types of Cross-Border Programmes (CBPs):

Programmes between Members States (MSs) and one or more IPA beneficiary countries Programmes between two or more IPA Beneficiary countries.

Programmes between IPA Beneficiary countries are managed separately, according to decentralised or centralised management system respectively, whereby each of the participating countries has it’s own Operating Structure (OS) and each of the OSs is responsible for implementation of contracts of beneficiaries from their respective part of the programme area. Programmes with MSs, however, are implemented according to the shared management, whereby authorities in the Member State of the programme bear responsibility for implementation of the cross-border programme as a whole and single contract is signed with Lead Partner/Beneficiary. The rules of these programmes are de facto a modification of ERDF rules and are represented in a separate chapter of IPA Implementing Regulation (Chapter 2, Section 2, Articles 101 – 138). In addition to these two types of cross-border programmes, cross-border cooperation component of IPA programme supports participation of the beneficiary countries in the transnational ERDF programmes under European Territorial Cooperation objective.2 Unlike IPA cross-border co-operation programmes, these programmes are funded by 2 different funding instruments and are hence defined by 2 different sets of regulations (ERDF and IPA). A form of shared management principle is introduced to the transnational programmes (TPs) as of the second term of the financial perspective and with the amended IPA Implementing Regulation in January 20103. Article 86 of IPA Implementing Regulation is rephrased to state: “The rules governing the participation of beneficiary countries in the above programmes shall be established in the relevant programming documents and/or in the relevant financing agreements, as appropriate.” The new version of the regulation thus gives relative flexibility to the participating countries to define the implementing modalities for cooperation in ERDF/IPA transnational programmes, but for all the programmes management by the Member State is introduced.

2.2. PROGRAMME MANAGEMENT STRUCTURES

These procedures cover exclusively programmes implemented under the shared management mode and the managing structures involved under shared management usually include:

Structure Role and responsibility

Responsible for selecting and approving operations

1 Commission Regulation (EC) No 718/2007, Art.86

2 Commission Regulation (EC) No 718/2007, Art.86 3 Commission Reulgation (EU) No 80/2010 amending Regulation (EC) No 718/2007

Page 8: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

5

Joint Monitoring Committee (JMC)

Verifies the effectiveness and quality of the implementation

of the Programme

Reviews and approves Annual Implementation Reports

Approves amendments to the Programme

Is composed of representatives at national, regional and local

level of all countries involved in the Programme

Managing Authority (MA)

Overall responsibility for the financial management of the

programme and projects

Selection of projects

Ensuring compliance with EU and national rules

Ensuring programme evaluation

Providing information and reporting to the JMC and EC

In the case of IPA CBC programmes the MA is located in an EU

Member State (EU MS)

Certifying Authority (CerAut)

Receiving payments from the Commission and transferring

funds to Beneficiaries

Certifying expenditure

Preparation and submission of payment claims to the

Commission

Recovery of funds

In the case of IPA CBC programmes the CA is located in an EU

Member State (EU MS)

Audit Authority (AA)

Responsible for the functioning of the management and

control systems in accordance with the Programme and

European Regulations

Ensuring audits are carried out to (i) verify the effective

functioning of the programme’s management and control

system and (ii) on specific projects

In the case of IPA CBC programmes the AA is located in an EU

Member State (EU MS) and supported by a Group of Auditors

comprising one representative of each participating country

Joint Technical Secretariat (JTS)

Responsible for the day-to-day management of the

Programme

Assists the Managing Authority (MA) and all the other

Programme structures and bodies in performing their tasks

Normally organises Calls for Proposals (CfP) and receives

and assesses the project proposals

Page 9: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

6

Monitors the implementation of the Programme

In the case of IPA CBC programmes the lead JTS is usually

located in the same country as the Managing Authority (MA)and

consists of representatives from all participating countries

First Level Control (FLC)

Verification whether expenditure reported is in line with

the Subsidy Contract and all relevant EC, national and

programme regulations and procedures

Checking the eligibility, regularity and legality of

expenditure reported

Validation of expenditure reported and issuance of the

Declaration on Validation of Expenditure (DVE)

Programme management structures can involve additional bodies including national or regional contact points for each country participating in the programme.

In Bosnia and Herzegovina the Directorate for European Integration (DEI), Sector for Coordination of EU Assistance, Cross Border Cooperation (CBC) department acts as the National Authority (NA) and is responsible for the provision of support to overall management to the Managing Authority (MA), ensuring publicity and visibility of the programme throughout the eligible areas on the territory of Bosnia and Herzegovina (BiH) and provision of information and advice with respect to the rules of the programme concerned to potential applicants in BiH. The DEI also provides three representatives as members of the Joint Monitoring Committee (JMC).

With respect to the programmes subject to these procedures the main management structures are the following:

IPA Adriatic CBC South East Europe (SEE) Mediterranean Programme

(MED) *

Managing

Authority

(MA)

Regione Abruzzo Servizio Attivita

Internazionali (Italy)

National Development

Agency, Managing Authority

for International Cooperation

Programmes (Hungary)

Provence Alpes Côte d’Azur

Région (France)

Certifying

Authority (CA)

Regione Abruzzo Servizio Autorita

di Certificazione (Italy)

Ministry for National

Economy of Hungary – NAO

Office

Caisse des dépôts et

consignations (CDC)

Audit

Authority (AA)

Regiona Abruzzo Struttura

Speciale di Supporto «Controllo

Ispettivocontabile»

Directorate General for Audit

of European Funds (Hungary)

Commission interministérielle de

coordination des contrôles (CICC)

Joint Technical Vanja Bozic Mrs. Mirjana Vidanovic Mr. Kirill Dimanopoulos

Page 10: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

7

Secretariat

(JTS)4

[email protected] (vidanovic@southeast-

europe.net)5

([email protected])

* In addition there are two liaison offices, one in Valencia and one in Thessaloniki.

2.3. EC REGULATIONS

The main EC regulations and documents related to the control system and the verification of expenditure of the IPA Adriatic CBC Programme are:

Council Regulation (EC) No 1085/2006 of 17 July 2006 establishing an instrument for pre-accession assistance (IPA)

Commission Regulation (EC) No 718/2007 of 12 June 2007 implementing Council Regulation (EC) No 1085/2006 establishing an instrument for pre-accession assistance (IPA)

Commission Regulation (EU) No. 80/2010 of 28 January 2010 amending Regulation (EC) No 718/2007 implementing Council Regulation (EC) No 1085/2006 establishing an instrument for pre-accession assistance

Commission Decision C (2007) 2034 of 24 May 2007 on the rules and procedures applicable to service, supply and works contracts financed by the general budget of the European Communities for the purpose of cooperation with third Countries, with the exclusion of Section II, 8.2 (hereinafter “IPA procurement rules”) and the related EC guide on procurement and contracting procedures and rules which apply to EC external aid contracts “Practical Guide to contract procedures for EU external actions” (PRAG) which fully replaces public procurement rules of participating countries within the limits set out by the decision C (2007) 2034 Council Regulation (EC) No 1083/2006 as General Regulation

The Practical Guide to contract procedures for EU external actions (the “PRAG”) the latest version of which (March 2013) which can be found on the following website

http://ec.europa.eu/europeaid/work/procedures/implementation/practical_guide/

2.4. BOSNIA AND HERZEGOVINA REGULATIONS

IPA Framework Agreement (FwA) between the European Commission and the Government of Bosnia and Herzegovina signed on 20 February 2008

The main specific national provisions according to legislation in place in BiH and which may have an impact on the financial management, eligibility and verification of expenditure incurred and declared by beneficiaries from BiH are contained in the BIH Control Guidelines developed for each of the three on going cross border co-operation programmes under shared management (i.e. IPA Adriatic CBC programme, South East Europe transnational cooperation programme and the transnational MED

5 For both SEE and MED there is no dedicated representative from Bosnia and Herzegovina on the JTS at the time of

drafting these procedures.

Page 11: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

8

programme) and which are also published on the website of the Ministry of Finance and Treasury (MoFT).

2.5. PROGRAMME SPECIFIC REGULATIONS

The main programme documents specific to the IPA Adriatic CBC Programme are:6

IPA Adriatic Operational Programme (OP)

IPA Subsidy Contract applicable under the Call for Proposals (CfP) under which the project is

financed

IPA Partnership Agreement

Application form

Programme Management and Control Manual (PMCM)

Guidance for First Level Controllers

The main programme documents specific to the South East Europe Programme (SEE) are:7

South East Europe Transnational Cooperation Programme approved by the European

Commission on 20 December 2007, Decision No. C (2007) 6590

SEE Programme Manual (relevant Call for Proposals) which contains the programme specific

rules for the eligibility of expenditure

SEE Implementation Manual laying down the programme specific rules for the implementation

of the SEE projects

SEE Control Guidelines version 3.1 which is the second amendment dated 27 May 2011 to the

initial guidelines developed on 10 June 2009 and amended for a first time on 6 July 2009

Information on the Control Systems in the Member States of the SEE Programme

Guidance to the Declaration on validation of expenditure in the SEE Partner Report

SEE Project Implementation Package

SEE Partner Report Tool and Guidelines

The main programme documents specific to the MED are8

the MED Operational Programme (OP)

6 Documents can be found at the following link: http://www.adriaticipacbc.org

7 Documents can be found at the following link: http://www.southeast-

europe.net/en/downloads_section/programme_related_documents/

8 Documents can be found at the following link: http://www.programmemed.eu/

Page 12: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

9

Implementation Guide of the Programme (March 2010)

Guidelines on First Level Control (July 2011)

Communication Plan MED Programme (April 2008)

The above list of Community, national and programme specific regulations and documents is not exhaustive and may have to be amended and/or complemented during the implementation of the Programme.

3. DESCRIPTION OF THE FIRST LEVEL CONTROL (FLC) SYSTEM IN BIH

3.1. FLC SYSTEM IN PLACE

In line with Article 108 of Commission Regulation (EC) No 718/2007 of 12 June 2007 implementing Council Regulation (EC) No 1085/2007 establishing an instrument for pre-accession assistance (IPA) each participating country shall set up a control system in order to validate expenditure at national level. Each participating country shall designate the controllers responsible for verifying the legality and regularity of the expenditure declared by each Beneficiary participating in the operation.9

Bosnia and Herzegovina has opted to use a centralised control system at national level through a public administrative body for ensuring First Level Control (FLC).

To this end the body designated as the national First Level Control Office (FLCO) in BiH is the Central Financing and Contracting Unit (CFCU) within the Ministry of Finance and Treasury (MoFT). This decision was taken by the Council of Ministers (Session 153) on 14 June 2011 and formally announced in the Official Gazette No 66/11 of 22 August 2011.

Since FLC function is assured by means of a centralised control system at national level by a public administrative body, the costs related to FLC in BIH are not borne by the beneficiaries.

The Head of the CFCU, who is also Assistant Minister, is the sole responsible person for the formal issuance of the Declarations on Validation of Expenditure (DVE) whereas the actual verification will be carried out by a number of his/her staff as determined by him/her whereby each controller will be assigned the responsibility for the verification of a dedicated number of projects.

The BiH First Level Controllers are civil servants and their salaries are paid out of the national budget. Other costs related to the execution of first level control (such as those related to on-the-spot checks, participation of controllers in training/seminars either within the territory of BiH or abroad, participation in events organised by Interact in Vienna etcetera may be financed out of the budget allocated by means of the Technical Assistance (TA) Subsidy Contract.

9 Whenever the terminology “Beneficiary” is used, reference is made to either “Lead Beneficiary” or “Final

Beneficiary”.

Page 13: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

10

3.2. INTERNAL ORGANISATION OF THE CONTROL BODY

From the above it can be seen that there are ten (10) members of staff of the CFCU that are currently involved in first level control (FLC) with regard to cross border co-operation (CBC) programmes under shared management.

The profile of first level controllers foresees that they should posses at least the following qualifications:

university or college degree

working experience in financial / project management

at least one (1) year working experience in a similar field

knowledge of the relevant EU and national regulations

knowledge of English (at least intermediate level)

Their job descriptions provide for the following activities (non-exhaustive list):

ensure the formal registration of all relevant documents in the programme level management

information systems and in the internal registry of the Ministry of Finance and Treasury (MoFT)

perform desk-based administrative and on-the-spot checks whereby s/he checks:

o the delivery of services and products in accordance with the Subsidy Contract

Department for Management

of Programmes and Projects

of EU Assistance (8)

Head of Unit *

Expert Adviser (1)

Senior Specialist (3) * (2)

Specialist (3) * (2)

Department for Finance and

Accounting (4)

Head of Unit *

Expert Adviser (1) *

Senior Specialist (1) *

Specialist (1) *

Head of CFCU (1)

Quality Control Advisers (2)

Expert Adviser (2)

Administrative/Technical Officer (1)

Page 14: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

11

o the soundness of the expenditure declared for operations (or parts of operations)

implemented in Bosnia and Herzegovina (BiH)

o the compliance of such expenditure and or related operations (or parts of operations)

with Community, programme and national rules and legislation

validating expenditure incurred by the Beneficiary by means of the preparation of Declarations

on the Validation of Expenditure (DVE) and submission to the Head of the CFCU for control and

signature

drafting checklists and reports on the controls performed according to the templates contained

in the programme documents / Control Guidelines at national level

continuous liaison with the relevant programme bodies (Managing Authority – MA, Joint

Technical Secretariat – JTS) and national bodies (National Authority – NA)

use of the relevant templates, management information systems and control guidelines

keeping track of changes in programme documentation and relevant legislation and reflection of

such in this Manual and the Control Guidelines at national level accordingly when required

4. PROCEDURES FOR VERIFICATION OF EXPENDITURE

4.1. OBJECTIVE OF FLC

The primary objective of First Level Control (FLC) is to guarantee that expenditure reported and claimed by Beneficiaries is justified, substantiated, real, actual and incurred and in line with the provisions of the Subsidy Contract / Partnership Agreement concerned and are in line with all legal provisions governing the Programme (EC, national and programme specific – see 2 “Legislative and Regulatory Framework” above).

In view of that Controllers shall:

check the regularity and legality of expenditure incurred and declared by Beneficiaries from Bosnia and Herzegovina (BiH) by conducting desk-based administrative and on-the-spot checks

validate the expenditure incurred by Beneficiaries from Bosnia and Herzegovina (BiH) validate the content of both the activities and the finances of the partner report draft a report and a checklist on the control performed (templates are usually developed at

programme level) sign and issue a Declaration on Validation of Expenditure (DVE) keep complete files on the validation process in lien with both programme as well as national

requirements

FLC is the most extensive level of control whereby 100% of the expenditure is checked.

Page 15: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

12

FLC is the first step in the expenditure certification / validation process and is performed prior to EC reimbursement of validated expenditure. This means in effect that Beneficiaries incur costs before being reimbursed from Programme funds. FLC requires a 100% check of expenditure declared.

Verifications comprise 2 key elements: Administrative verification, i.e. desk-based verifications (in principle of 100% of project

expenditure) On-the-spot verifications (potentially of a sample of operations).

4.2. STEPS OF THE FLC/VALIDATION PROCESS

Submission of Activity Report (AR) and Financial Report (FR) by A national Beneficiary in electronic

version through the programme specific information system and hard copy to the national First Level

Control Office (FLCO)

Desk-based administrative check of Activity Report (AR) and Financial Report (FR), including all

supporting documentation by the national FLCO

If the project is included in the on-the-spot check activity plan (or otherwise decided on a case by case

basis), an on-the-spot check visit will be performed by the national FLCO

Establishment of the eligible costs and approval of the Beneficiary’s report by the national FLCO

Issuing the Declaration on Validation of Expenditure (DVE) by the national FLCO

The project partner from BiH prepares a Progress Report (PR) in the defined format as per the specific programme and as per the time schedules laid down for each particular programme specifying activities (Activity Report) and the related costs (Financial Report) incurred during the period covered by the report.

The Progress Report is uploaded electronically in the Management Information System (MIS) developed for each specific programme and a hard copy of the report, together with all original supporting documentation proving the expenses, is submitted for validation to the designated body in charge of first level control of the expenditure declared which in the case of BiH is the Central Finance and Contracting

Page 16: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

13

Unit (CFCU) within the Ministry of Finance and Treasury (MoFT) located at the following address and with the following contact details:

Trg BiH 1

Sarajevo

Bosnia and Herzegovina

Tel: +387 33 70 30 24, +387 33 70 25

Fax: +387 33 70 31 28

Each project is assigned by the management of the CFCU to a designated First Level Controller who will be in charge of validating expenditure under the projects assigned to him / her.

The First Level Control Office, i.e. the CFCU, will perform an administrative desk-based check of 100% of the expenditure declared, both in terms of form and content on the basis of the control guidelines developed for each particular programme, and, in addition, will perform on a regular basis on-the-spot checks (see also section 6.3.1 above).

Once the checks (either administrative desk-based check alone or an administrative desk-based check followed up by an on-the-spot check) have been completed, the CFCU in its role as FLCO will determine the amount of the eligible costs and validate the eligible expenditure in the MIS by means of issuing of a “Declaration on Validation of Expenditure (DVE)” expressed in euro.

The DVE is supported by several annexes which are:

additional information concerning the administrative check and on-the-spot check, if any as well

as irregularities determined during the period covered by the report (see section 8 below)

summary of costs according to the individual budget lines and work packages.

Under normal circumstances the FLCO is given a predetermined period from the receipt of the hard copy of the report to complete the validation process. Beneficiaries are drawn attention to the fact however that this initial period can be interrupted or suspended if outstanding issues are identified during the verification process and in which case a letter will be sent to the Beneficiary by the FLCO requesting for clarification(s) and / or additional documentation.

FLC checks are being performed on the basis of control checklists agreed on programme level and which are contained in the guidelines for first level control and/or implementation manuals developed for each specific programme and which can be downloaded from the respective programme’s website.

Page 17: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

14

4.3. REPORTING, VERIFICATION AND RETENTION PERIODS AND DEADLINES

The work of the FLCO involves a continuous process which normally starts with the receipt of a hard copy of a signed Progress Report (consisting of an Activity Report as well as a Financial Report) submitted by a beneficiary, the check and verification of 100% of the expenditure incurred and declared by means of a desk-based administrative check (see Section 4.4 below) and on-the-spot checks on a sample basis (see Section 4.5 below) and which results in the issuing of a Declaration on Validation of Expenditure (DVE) while constantly monitoring projects with respect to irregularities, fraud and corruption.

The deadlines for the submission of reports by Beneficiaries, the time allocated to perform and finalise the first level control checks, the time given to Beneficiaries to submit clarifications or additional documentations, if any, to the FLCO and the period during which all documentation related to expenditure and the FLC process needs to be retained as per the programme rules established for each of the three programmes covered by these procedures is presented in the table below:

IPA Adriatic CBC SEE MED

Reporting by Beneficiary quarterly (i.e. by 31st

January, by 30th

April, by

30th

June, by 31st

October)10

six-monthly six-monthly (by 31st

October

and 30th

April)

Time allowed for Controllers

to issue the Declaration on

Validation of Expenditure

(DVE)

3 months 60 days 20 – 30 calendar days11

Time allowed to Beneficiaries

to submit additional

documentation or

clarifications upon specific

request by FLCO

14 calendar days (i.e. 10

working days)

14 calendar days (i.e. 10

working days)12

8 calendar days13

Retention deadline of FLC

documentation by the

Beneficiaries / Controllers

3 years after the official

closure of the programme

(see Partnership

Agreement Article 3.3)

31 December 2022 31 December 2021

10

This is according to Section 6.1.1.2 “Timing for Reporting” of the Programme Management and Control Manual

(PMCM) developed specifically for the IPA Adriatic CBC Programme which also specifies that “Beneficiaries may

report expenditure whenever they are ready given that at least the spending forecasts planned in the Application

Form will be respected”. 11

In line with the “Guidelines for First Level Control for the MED programme of July 2011. 12

There is no such deadline given in the programme rules and this time period has therefore been set by the BiH

national FLCO. 13

In line with the “Guidelines for First Level Control” for the MED programme of July 2011.

Page 18: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

15

i.e. 31 December 2021

On average an initial desk-based administrative check takes between five (5) and fifteen (15) working days and depends on the complexity of the project, the value and nature of the expenditure declared, the number and quality of the supporting documentation, the experience of the first level controller and the fact whether or not discrepancies (e.g. between the Activity and Financial Report) are discovered and whether clarifications are required from the Beneficiary. In addition the process may be substantially slowed down if Beneficiaries are slow in providing the additional information requested by the first level controller.

On average an on-the-spot check takes maximum five (5) working days and includes activities related to planning, preparation, travel, the actual on-the-spot check and reporting.

The templates to be used for reporting purposes by the Beneficiaries are published on the programme websites and are contained in the Control Guidelines developed for each programme.

4.4. DESK-BASED ADMINISTRATIVE CHEKS

As soon as the First Level Control Office (FLCO), and more in particular the First Level Controller within the Central Finance and Contracting Unit (CFCU) assigned to the project concerned, has received the hard copy of the Activity Report (AR) and the Financial Report (FR) including all necessary supporting documentation from the Beneficiary, a desk-based administrative check is initiated.14

This check is performed at the premises of the FLCO (i.e. CFCU).

The First Level Controller first checks the completeness of the documentation submitted and the conformity with standard templates and formats developed for the specific Programme. In this respect it is to be noted that the Application Form (AF) as approved by the Joint Monitoring Committee (JMC), the IPA Subsidy Contract and the Partnership Agreement (including all annexes) needs to be attached to the first report submitted by the Beneficiary.

Subsequently the First Level Controller continues to perform the following formal checks and judges whether or not there is satisfactory evidence that:

ITEM / ISSUE TO BE CHECKED DOCUMENTS USED / CHECKED

Expenditure reported is real and incurred and is

supported by accurate and acceptable documents as

to their form and content

Original invoices, receipts or accounting documents

of equivalent probative value

Services or products have been actually delivered

and are in line with the approved Application Form

Timesheets and outputs (e.g. reports) of project

staff (both employees of the Beneficiary as well as

14

The time period within which FLC has to be completed determined at programme level starts to counts as of the

receipt by the FLCO of the hard copies of all due reports.

Page 19: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

16

and the Subsidy Contract external staff)

Acceptance documents for supply or work

components

Approved Application Form

Subsidy Contract

Activity Report

Financial Report

Expenditure reported is in line with the eligibility

rules of the EU, specific Programme and national

legislation

Programme Management and Control Manual

(PMCM)

Guidance for First Level Controllers

Programme Implementation Guide / Programme

Management and Control Manual

EU and national legislation

Eligibility period of the reporting period / project

(start and end date)

Eligible area of the Programme

Subsidy contract (where the approval date, start

and end date of the project are given)

Expenditure reported can be traced back / linked to

activities reported in the Activity Report

Comparison of expenses with activities described in

the Activity Report

Expenditure incurred in local currency (KM) is

correctly converted into €

InforEuro exchange rate

IPA Adriatic CBC: InforEuro exchange rate of the

month in which the report was submitted by the

Beneficiary to the national FLCOI

SEE: InforEuro exchange rate of the last month of the

reporting period (for SEE)15

MED: InforEuro exchange rate of the month in which

the invoice was paid or the of the month in which the

costs were reported to the Lead Partner or 6-months

average of the InforEuro exchange rate or market

exchange rate of the day the invoice was paid or

market exchange rate of the last day of the reporting

period (Note: in those cases where the beneficiary

has sent their figures to the Lead Partner in their

national currency and it is the Lead Partner that

converts these figures into euro then the Lead

15

As the KM is pegged to the euro, the fixed exchange rate is € 1 to KM 1.95583.

Page 20: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

17

Partner must use the average monthly exchange rate

set by the EC of the last month of the reporting

period or the market exchange rate of the last day of

the reporting period

Net revenue, if any, has been properly

communicated and deducted from the eligible

expenditure declared

Approved Application Form (should, whenever

possible, contain an estimate of revenues if

foreseen)

Calculation method by Beneficiary to report net

revenues

Statement by the Beneficiary that the project

does not generate revenues16

Recoverable Value Added Tax (VAT) has been

deducted from the eligible expenditure declared

Check VAT status of Beneficiary in the Section on

VAT of Activity Report

Expenditure is charged to the correct Work Package

(WP) and correct budget line and budgets by WP and

budget line have been respected

Approved Application Form

IPA Subsidy Contract

Double financing is avoided Original invoices / receipts / accounting

documents are voided (stamped) by FLCO upon

approval

The Beneficiary maintains either a separate

accounting system or an adequate accounting code

This will be normally subject to verification during

on-the-spot checks

EU requirements concerning information and

publicity are respected

Materials produced by the Beneficiary (e.g.

brochures, leaflets, press releases, …) comply with

EU visibility and information rules

Supportive documents to the reported expenditure provided by BIH project partner are accompanied with the necessary copies together with the list of expenditures to the controller, verified by signatures and stamps in relevant cases. If the project partner has filled the reporting materijals inadequately, documentation is missing or instructions have not been followed, First Level Controller should ask the project partner to correct the mistakes or clarify the unclear issues.

The First Level Controller will then perform an in-depth check of the expenditure claimed under the various budget lines. These are per programme:

16

If at any time during the implementation of the project the FLC reveals that the project is generating revenues

which are not declared by the Beneficiary and thus not deducted from the eligible expenditure, this is considered an

irregularity and the irregularity procedure and recovery procedure need to be initiated (see Section 8 below).

Page 21: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

18

Budget line

No.

IPA ADRIATIC CBC SEE MED

1 Staff costs Staff costs Staff costs

2 Overheads Overheads Durable goods

3 Travel and accommodation Travel and accommodation Consumable goods

4 External expertise External expertise and

services

Travel and accommodation

5 Meetings and events Equipment Services (other than external

expertise)

6 Promotion costs Small scale investments External expertise

7 Equipment Financial charges and

guarantee costs

Promotion, information and

publications

8 Investments N/A Overheads

9 Financial charges and guarantee

costs

N/A Other

From the above it can be noticed that the structure of the budgets of the subsidy contracts slightly differs from programme to programme and that sometimes particular costs are eligible under a given programme whereas for others this is not the case (e.g. no investment component under the MED programme).

The sections below contain general information regarding each individual major budget line, the nature of costs that can be claimed, the kind of supporting documentation that is required and the nature of the checks that will be performed by the First Level Controllers. More detailed information including specific requirements according to relevant legislation in Bosnia and Herzegovina are contained in the Control Guidelines at national level developed separately for each of the three programmes (IPA Adriatic CBC, SEE and MED).

4.4.1 Staff costs

The first budget line is entitled “staff costs” and covers the salaries (i.e. gross salary including possible salary for overtime, sickness, holidays plus any other benefit, reward, bonus payment plus all legal provisions such as insurance, health and social security charges paid by both the employee and the employer) of the staff of the Beneficiary working either on a full-time or part-time basis on the project, as indicated in the Application Form.

Typically personnel working on these kinds of projects are personnel such as a Project Coordinator, a Project Manager, an Assistant, a Financial Manager etc) and it is compulsory for the Beneficiary to prove

Page 22: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

19

that members of staff for which salaries are claimed under the project are directly employed by the Beneficiary organisation on the basis of a regular work contract or any similar type of contract according to the national rules (e.g. service contract of predefined duration as a self-employed person).

Staff costs should be calculated in hourly rates and presented as such.

First Level Controllers will inter alia verify whether staff costs are claimed in accordance with the envisaged work of the different employees on the project as indicated in the Application Form (e.g. ensure that no full salaries are claimed for staff envisaged to work only part-time on the project) as well as reconcile the information provided on the timesheets with the proof of payment of salaries (e.g. if the timesheet reveals that a person worked 120 hours i.e. 8 working days on the project in a given month then only a fraction – 120/176 or 68.18% - of that staff member’s salary can be charged to the project.17

This cost category normally makes up the largest part of the overall project budget and expenditure claimed in each individual report and therefore the necessary attention and care should be allocated in verifying the eligibility and acceptability of claim under this budget line.

Checks related to claiming staff costs include18:

ITEM / ISSUE TO BE CHECKED DOCUMENTS USED / CHECKED

Information is available concerning expenditure

claimed for all staff working in the project

Full list of staff working in the project is

attached / included in the first report stating as

a minimum: name of the employee,

qualification, position in the project, percentage

of work allocated to the project, gross salary,

indicative costs to be funded under the project’s

budget

Employment contracts / job descriptions stating

as a minimum: tasks, start and end date,

indication whether full-time or part-time

Payslips / proof of payment (e.g. bank

statements)

Monthly timesheets (stating as a minimum

name of the employee, date, time, detailed

description of activity) and signed by both

employee and employer or activity reports

17

As a general rule the EC uses 22 working days per month as an average. Salary calculations should however be based on the real number of working days in a given month e.g. February 12 only has 21 working days whereas May 2012 has 23 working days. 18

For all expenditure claimed, proof of payment should be provided (in the form of e.g. bank statement, not transferable at-sight checks, bank checks, payment orders, daily book for cash payment, …).

Page 23: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

20

Calculation method for calculating hourly rates /

total staff costs (based on real costs and

excluding any fringe benefits and for time

exclusively worked on the project)

Declaration by the responsible person within

the employer institution for overtime

performed

To further proof and substantiate the costs claimed for salaries, beneficiary organisations from Bosnia and Herzegovina may be requested by the FLCO to provide their internal book of rule (“pravilnik o platama”) or equivalent.

The basic calculation principle to charge staff costs against the project’s budget is:

monthly gross salary + social charges

_______________________________ X hours worked on the project in the given month

total working hours in the given month

Staff costs are based on the normal remuneration the employee receives when not working on the project and no ad-hoc salary increases or arbitrary hourly rates for project purposes are possible.

Below is an example of the various elements making up a gross salary and the method for calculation for both the Federation (FBIH) as well as the Republika Srpska (RS):

PIO iz ld

17% ZDRAVSTVENO

OSIG. Iz ld 12,5% NEZAPOSLENOST iz

ld 1,5% BRUTO PLATA

PIO na ld 6%

ZDRAVSTVENO OSIG. na ld 4%

NEZAPOSLENOST na ld 0,5%

POREZ OD ELEMENT. NEP. 0,5%

POREZ 10%

NETO PLATA

ISPLATA

FBIH 265.54 195.25 23.43 1562.00 93.72 62.48 7.81 5.00 77.78 1000.00 1731.01

BRUTO PLATA

BRUTO DOPRINOSI

OSNOVICA ZA POREZ

POREZ 10% PIO 17% ZDRAVSTVENO

OSIG. 12% ZAPOŠLJAVANJE 1,5% NETO PLATA ISPLATA

RS 1658.38 547.26 1111.11 111.11 281.92 199.01 24.88 1000.00 1616.92

Page 24: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

21

4.4.2 Overheads

The second budget line concern “Overheads“ by which reference is made to expenditure such as utilities or office costs including electricity, heating, lighting, water, cleaning, administrative costs such as telephone, fax, internet, mailing/postal/courier services, stationary, office supplies and bank costs/charges for NATIONAL financial transactions related to the normal bank account of the organisation (i.e. in case a separate dedicated account was NOT opened for the project): For more information on other kinds of bank costs / charges (e.g. for the ones related to a specific dedicated account which was opened for the project or costs / charges related to INTERNATIONAL financial transactions – see 6.3.1.9 below). There are two categories of overheads for which there are different reporting and calculation requirements:

(i) direct general costs (overheads directly allocated to the project): This method is to be applied when it is possible to allocate overheads directly to the project or in other words where it is possible to determine those overheads derived exclusively from the project. In this case no lump sums, estimations or arbitrary keys are allowed.

(ii) Indirect general costs (overheads allocated proportionally to the project): This method is to be applied when overheads cannot be directly allocated to the project and when actual cost is shared with organisational non-project related costs. In this case overheads must be allocated proportionally to the project and calculated, using a duly justified fair and equitable method, on flat rates, not exceeding 25% of those direct costs of an operation that can affect the level of overheads, based on average costs.

In those cases where apportionment is used, the method for calculating and allocating overheads to the project should be clearly stated and explained in the first Progress Report and can be reviewed yearly.

Depending on the type of cost claimed, the basis for apportionment could be any of the below three:

number of people working for the project divided by the number of people working in the organisation

number of hours worked on the project divided by the total number of hours worked in total in the organisation (i.e. including work on other activities than the particular project)

surface used by the personnel working for the project divided by the total surface of the organisation (most suitable for costs of utilities such as heating, lighting, electricity, water etc)

Checks related to the overheads budget line include19:

ITEM / ISSUE TO BE CHECKED DOCUMENTS USED / CHECKED

19

For all expenditure claimed, proof of payment should be provided (in the form of e.g. bank statement, not transferable at-sight checks, bank checks, payment orders, daily book for cash payment, …).

Page 25: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

22

Information is available concerning expenditure

claimed for overheads incurred during the

implementation of the project

In case of direct general costs, the costs show a

direct link to the project’s activities, are based

on actual costs and can be verified (no lump

sums, estimations or arbitrary keys are allowed)

Method for calculating overheads including a

list of the cost items – in case of indirect

general costs - is clearly stated in the first

Progress Report (if changes to this calculation

method, then explained and substantiated in

any of the next reports bearing in mind that the

calculation method can only be reviewed yearly)

Proof of payment (e.g. invoices, receipts, postal

account bulletin, debit note, telephone bill with

clear indication which calls were project related

providing as a minimum person/institution

called and reason for the call)

Overheads claimed are in line with the eligibility

rules governing the Programme

It is important to note that the Beneficiary should make the calculation method available to the First Level Controllers (FLC) in a way that is easy to understand and the calculation method may be subject to verification at the Beneficiary’s premises during an on-the-spot check.

4.4.3 Travel and accommodation

This cost category refers to the travel and accommodation costs of the employees of the Beneficiary (note: travel and accommodation costs of external experts participating in the project have to be charged against the budget line “External expertise” – see section 6.2.1.4 below). Expenditure claimed should be carefully checked to assess whether they are reasonable, had been foreseen, are approved internally within the Beneficiary, are in line with the organisation’s internal rules, occurred in eligible areas covered by the Programme etc…20

The basic rules governing this budget line are:

20

Travel outside the Programme eligible area must have been previously authorised by the Managing Authority

(who will inform the national FLCO accordingly).

Page 26: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

23

economy of transport: the cheapest way / most economical way of transportation should be

used (demonstrated on the basis of an assessment by the Beneficiary) and this would normally

be public transport (bus, train, boat, plane) whereby business or first class tickets are ineligible

(even if this is allowed by the internal rules of the Beneficiary). Exceptions, if any, must be duly

justified in each case

only travelling and accommodation costs of “project staff” is eligible

reasonability of board and lodging costs: the accommodation and costs of meals should be

reasonably priced and higher price ranges must be duly justified in each case

reporting method: costs should be reported in line with national rules or specific internal

regulations of the Beneficiary

assignment of costs: costs should be borne by the Beneficiary and thus proof of direct payment

by the employee is insufficient. If costs are paid by the employee on the basis of an advance

paid by the Beneficiary to him / her then there should be proof of the advance paid and the

balance reimbursed by the employee to the Beneficiary at the end of the mission.

duration: the duration of the travel should be reasonable and should normally start the day

before the event / meeting / reason for travelling until the day after

So-called daily allowances/per diems (fixed daily rates / flat rates for meals; accommodation, local travel) can be eligible provided these are foreseen in the national rules as the only way of reimbursement of such costs.

According to national legislation in place the amounts eligible for the countries participating in the three programmes concerned are (effective June 2012):

Country State level Federation Republika Srpska

Albania 130 KM 90 KM 20 €

Austria 145 KM 140 KM 45 €

BiH 25 KM 25 KM 25 €

Bulgaria 108 KM 90 KM 25 €

Croatia 121 KM 100 KM 20 €

Cyprus 117 KM 110 KM 40 €

France 143 KM 140 KM 45 €

Page 27: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

24

Greece 126 KM 110 KM 40 €

Hungary 117 KM 100 KM 30 €

Italy 140 KM 130 KM 45 €

The former Yugoslav

Republic of Macedonia

109 KM 90 KM 20 €

Malta 117 KM 110 KM 40 €

Moldova 114 KM 100 KM 35 $

Montenegro 113 KM 90 KM 20 €

Portugal 117 KM 110 KM 40 €

Romania 119 KM 110 KM 25 €

Serbia 113 KM 100 KM 20 €

Slovak Republic 117 KM 100 KM 30 €

Slovenia 117 KM 100 KM 30 €

Spain 134 KM 110 KM 40 €

Ukraine 130 KM 110 KM 40 $

United Kingdom 148 KM 140 KM 45 €

Checks related to the travel and accommodation budget line include21:

ITEM / ISSUE TO BE CHECKED DOCUMENTS USED / CHECKED

All necessary information is available concerning

expenditure claimed for travel and accommodation

costs incurred during the implementation of the

project; travel is directly related to the project and

occurred within the programme eligible area

Analytical documentation / itemised list of

travel and accommodation costs effectively

incurred by the employee accompanied by all

receipts / bills / invoices proving the

expenditure stated (e.g. bus/train/metro tickets,

meal receipts, plane ticket with boarding passes,

car rental invoice, …)

Calculation sheet prepared according to

21

For all expenditure claimed, proof of payment should be provided (in the form of e.g. bank statement, not transferable at-sight checks, bank checks, payment orders, daily book for cash payment, …).

Page 28: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

25

national or institutional rules for travel by

company/own car stating at least the distance,

unit rate and total cost and accompanied by

additional proof documents such as highway

tickets/stamps

Invitation, agenda, list of participants, minutes

etc. of the event are available and from which

the name of the participant and date, reason

and place of the mission can be seen

Mission report duly signed by the person(s) who

travelled

Class of car (maximum class C) in case of travel

by rental car

Proof of payment: either paid directly by the

Beneficiary or reimbursement of costs incurred

to the employee

One can notice from the above that the First Level Controller will often have to use personal judgment or carry out a small market research in order to be able to assess whether the costs claimed are indeed going rates which do not exceed going market rates.

To further proof and substantiate the costs claimed for travel and accommodation, beneficiary organisations from Bosnia and Herzegovina may be requested to provide to the FLCO their internal book of rule (“pravilnik o sluzbenim putovanjima”) or equivalent.

4.4.4 External expertise

This budget line includes costs paid for professional services of an external expert, consultant or supplier exclusively engaged for the project purposes to perform certain activities / tasks outside the knowledge base of the Beneficiary (examples include financial management, project management, legal advice, notarial fees, studies, researches, surveys, translation…).22

The following primary conditions have to be met:

the work of the external expert(s) is essential to the project

22

Translation can only be charged against the budget line «External expertise» if they are not related to any other particular budget line. Whenever reproduction or translation of project documents is linked to specific events, the related costs shall be charged against the budget line entitled “Meetings and events”.

Page 29: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

26

rates charged are reasonable and in relation to the level of expertise and experience

Project Partners cannot be contracted as external experts or subcontractor

The same person already charged under the budget line “Staff costs” cannot be

contracted under the budget line “External expertise”.

Recruitment of external experts / consultants needs to fully respect the relevant procurement rules under the programme concerned. Usually the procurement procedures to be used are the rules and procedures applicable to service, supply and works contracts financed by the general budget of the European Communities for the purposes of cooperation with third countries (see Article 121 “Procurement” of the IPA Implementing Regulations). In effect this means that the provisions of the “Practical Guide to contract procedures for EU external actions (PRAG)” need to be consulted by the Beneficiaries whereby PRAG templates are encouraged to be used albeit that it is not obligatory.23

In addition Interact Point Vienna has produced a document entitled “Public procurement in IPA cross-border cooperation programmes with EU Member States in shared management” which can also be consulted by Beneficiaries.24 It has to be noted however that Beneficiaries are not obliged to use any standard formats or templates contained in any of the documents mentioned above but the public procurement needs to respect the basic underlying philosophies (e.g. transparency, equal treatment, non-discrimination, fair competition, open competition, impartiality, best value for money, nationality and origin).

Furthermore national public procurement rules may be used and this would be in fact the normal way of proceeding (in fact they have to be used whenever they are more restrictive than the PRAG or Interact rules). The Law on Public Procurement provides in Article 5.1.c however that, in those cases where the project is (co)funded by international donors, the latter’s procurement rules may be used. The link to the Public Procurement Agency of Bosnia and Herzegovina where the Public Procurement Law can be found is stated in the footnote below.25

The First Level Controller (FLC) will judge on a case by case basis whether there is sufficient written evidence that the evaluation of the offers and the award of the contract was carried out in a professional, objective, fair and transparent manner and therefore will check the existence of basic documents justifying the choice of the selected service provider or supplier and the most important of which are Technical Specifications (supplies) / Terms of Reference (services), information about the potential Tenderers approached, request for offer to several potential service providers or suppliers,

offers received, evidence of the evaluation of the offers (members of the Evaluation Committee, evaluation report), contract with the selected supplier / service provider (making clear reference to the project and the programme), outputs etc.

23

The document can be found on: http://ec.europa.eu/europeaid/work/procedures/implementation/practical_guide/ 24

The document can be found on: http://www.interact-eu.net/ipa_interact_publications/interact_ipacbc_documents/319/4867 25

http://www.javnenabavke.ba/index.php?id=10zak&zak=1&jezik=en

Page 30: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

27

The days and hours of work of the external expert shall be fixed on the basis of the laws, regulations and customs of Bosnia and Herzegovina more details of which can be found in the Control Guidelines developed for each individual programme.

In case the days and work of the external expert are not regulated by any means, the number of working days (WD) that usually can be worked by an external expert is limited to a maximum of 220 working days per year. If the number of days worked is less (e.g. if the expert is only employed for a fraction of a year) then the fees should be calculated on the basis of a maximum of 20 working days per month.

It is important that the First Level Controller (FLC) uses his / her own judgment to ascertain that rates charged and paid are in line with going market rates in Bosnia and Herzegovina (BiH) for such services and fee rates are in line with the level of experience, expertise and competence of the service provider selected (e.g. a daily fee of 1,000 KM should be seriously questioned).

Difference is made between fee-based service and global price contracts whereby the latter can (exceptionally) be used where the work of the external expert leads to a clearly defined specific outcome (e.g. studies).

Checks related to the external expertise budget line include26:

ITEM / ISSUE TO BE CHECKED DOCUMENTS USED / CHECKED

All necessary information is available concerning

expenditure claimed for external expertise incurred

during the implementation of the project

Services delivered by external experts are

directly related to the project and activities are

explicitly foreseen in the latest approved

Application Form

Evidence of compliance to procurement rules

(i.e. it is clear on what basis the external expert

has been selected and the following basic

documentation is available: Technical

Specifications (supplies) or Terms of Reference

(services), information about external experts

approached to submit an offer, request for

offer, offers received, evaluation report /grid,

members of the Evaluation Committee, …)

External experts are not already employed by

the Beneficiary as regular staff

Rates charged by the external expert are

conform to going market rates and in line with

26

For all expenditure claimed, proof of payment should be provided (in the form of e.g. bank statement, not transferable at-sight checks, bank checks, payment orders, daily book for cash payment, …).

Page 31: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

28

the expert’s level of expertise, experience and

competence

The contract concluded with the external expert

is available and reference is made to the project

and the programme and states as a minimum a

description of the services provided, total price,

deadlines for the delivery of outputs, names of

the experts, …)

Evidence of the work is available (timesheets,

outputs)

Deliverables / outputs respect EU visibility and

publicity requirements applicable under the

programme under which they are financed

4.4.5 Meetings and events

This budget line includes costs related to the organisation of conferences, seminars, meetings, workshops or events directly related to the project and traceable from the latest approved Application Form.

Examples of eligible costs include:

renting of equipment for above-mentioned events

interpretation at events

translation of documents linked to specific events

printing of materials directly related to eventsµ

catering expenses

speaker’s fees

costs of external participants

Eligibility of costs under this budget line is subject to the full respect of both the prevailing procurement rules and publicity rules (see also above under 6.3.1.4 “External expertise” and 6.3.1. 7

Page 32: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

29

“Equipment” below). In other words it should be clear from the supporting documentation submitted by the Beneficiary on what basis the service provider has been selected (request for offer to several potential service providers, offers received, evidence of the evaluation of the offers received (members of the Evaluation Committee, evaluation report etc), the contract between the Beneficiary and the service provider (making clear reference to the event, the project and programme) should be available at the FLCO. It is important to ensure that the most cost-efficient option has been selected (value for money).

In addition for each event where the participation of external experts was required and for which costs are declared, the following information should be readily available:

purpose

agenda

location

duration

list of participants

minutes

copy of the materials produced directly linked to the event

number of languages for which translation has been provided, if any

In order to further substantiate the occurrence of these types of events, beneficiary organisations are encouraged to take pictures or make videos of the event which can be subsequently checked by the First Level Controllers (FLC).

Checks related to the meetings and events budget line include27:

ITEM / ISSUE TO BE CHECKED DOCUMENTS USED / CHECKED

All necessary information is available concerning

expenditure claimed for meetings and events

incurred during the implementation of the project

Services delivered are directly related to the

project and activities are explicitly foreseen in

the latest approved Application Form

Evidence of compliance to procurement rules

(i.e. it is clear on what basis the service provider

has been selected and the following basic

documentation is available: Technical

Specifications (supplies) or Terms of Reference

(services), information about service providers

approached to submit an offer, request for

27

For all expenditure claimed, proof of payment should be provided (in the form of e.g. bank statement, not transferable at-sight checks, bank checks, payment orders, daily book for cash payment, …).

Page 33: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

30

offer, offers received, evaluation report /grid,

members of the Evaluation Committee, …)

Evidence of compliance to EU publicity and

visibility rules

Evidence that the most cost-efficient option has

been chosen (“value for money”)

The contract concluded with the service

provider is available and reference is made to

the project and the programme

All material proving that the event was actually

carried out (including list of participants,

agenda, minutes, location, duration etc) is

available

4.4.6 Promotion costs28

This budget line includes costs related to information and communication activities related to the project.

Examples of eligible costs include:

brochures

leaflets

newsletters

press releases

inserts / advertisements in newspapers

design and maintenance of a website for the project

publication costs related to the project and not linked to specific events (such as display panels,

commemorative plaques, banners, promotional items, photographs, audio or video production)

28

Under the Transnational Mediterranean Programme (MED) this budget line is referred to as “Promotion, information and publications”.

Page 34: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

31

If an external service provider is used to carry out promotion activities, the FLCO will have to ensure that the prevailing procurement and visibility rules have been respected (see also 6.3.1.4 “External expertise” and 6.3.15 “Meetings and events” above and 6.3.1.7 “Equipment” below).

Checks related to the promotion costs budget line include29:

ITEM / ISSUE TO BE CHECKED DOCUMENTS USED / CHECKED

All necessary information is available concerning

expenditure claimed for promotion costs incurred

during the implementation of the project

Promotion costs are directly related to the

project and are explicitly foreseen in the latest

approved Application Form

Evidence of compliance to procurement rules

(i.e. it is clear on what basis the service provider

has been selected and the following basic

documentation is available: Technical

Specifications (supplies) or Terms of Reference

(services), information about service providers

approached to submit an offer, request for

offer, offers received, evaluation report /grid,

members of the Evaluation Committee, …)

Evidence of compliance to publicity and

visibility rules

The contract concluded with the service

provider is available and reference is made to

the project and the programme

All material proving that the promotion costs

were actually carried out (e.g. copy of

brochures, leaflets etc or existence of the

website) is available

29

For all expenditure claimed, proof of payment should be provided (in the form of e.g. bank statement, not transferable at-sight checks, bank checks, payment orders, daily book for cash payment, …).

Page 35: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

32

4.4.7 Equipment30

This budget line includes costs related to:

purchase of equipment

rent of equipment

lease of equipment

Examples of eligible costs include:

IT equipment (computer, printer, software)

office furniture

machineries

All purchase of equipment needs to respect fully the procurement procedures established for the programme concerned as well as the publicity rules (see also section 6.3.1.4 “External expertise”, 6.3.1.5 “Meetings and events” and 6.3.1.6 “Promotion costs”).

The FLCO will pay attention to whether or not the most economic option (“value for money”) has been chosen.

All equipment purchased must have been clearly foreseen in the last updated version of the Application Form (AF) and if this is not the case, the equipment purchased must have been approved by the Managing Authority (MA), the Joint Technical Secretariat (JTS) and or the Joint Monitoring Committee (JMC) beforehand.

The FLCO will regularly verify the existence of equipment by means of on-the-spot checks.

The FLCO will also check whether:

the equipment has not already been financed by other subsidies (e.g. EU, national, regional)

the equipment has not already been completely depreciated

the equipment is not claimed in another budget line (e.g. overheads costs)

30

Under the Transnational Mediterranean Programme (MED) this budget line is referred to as “goods” and broken down between “durable goods” and “consumable goods”

Page 36: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

33

With respect to the purchase of second hand equipment the situation is the following for the three programmes:

IPA ADRIATIC CBC SEE MED

Ineligible Eligible Eligible

Where second hand equipment is purchased the following provisions apply:

price of the equipment is in line with its market value and less than the price of similar new

equipment

the equipment has the technical characteristics necessary for the project

depreciation costs are only eligible if the equipment has not yet been already completely

amortised

Depending on the option selected to acquire the equipment (i.e. purchase, rent or lease) the following must also be respected:

a) Purchase of equipment

Where equipment is purchased exclusively for use under the project:

either 100% full cost can be charged to the project

or the equipment will be depreciated

100% full cost can be charged to the project where:

the equipment is of low-cost value and thus not depreciable

the period from the date of purchase until the end date of the project is longer than (or equal to)

the normal depreciation period

the period from the date of purchase until the project closure is shorter than the normal

depreciation period but:

o the equipment is used for the same purpose at least 5 years after the end of the project

o the equipment is part of a specific goal of the project (e.g. office furniture of one of the

objectives of the project is to set up an office that will provide services for the target

group also after project completion)

Note: In both the two above-mentioned cases the Beneficiary should submit a declaration to the FLCO that this is

the case. This can be done with the submission of the first Progress Report (and then full price can be reported) or

if the declaration is submitted at a later stage, then only the depreciation amounts can be reported until the

submission of the declaration).

Page 37: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

34

Depreciation method should be used whenever the full purchase price is not charged to the project.

Depreciation refers the decrease in value of assets over time and the allocation of the cost of those assets to periods in which the assets are used.

The depreciation method and the way of calculation should respect fully the provisions of the legislation in force in the entity in which the beneficiary is located. In view of that reference is made to the following laws and provisions:

For the Republika Srpska (RS):

Law on tax on profit of legal entities (Official Gazette RS nr. 25/2001, 80/2002, 43/2003, 84/2004

and 18/2010

Manual of methods of classifying fixed assets according to group and method of determining

depreciation for tax purposes (Official Gazette RS nr. 116/2004 and 99/2010)

For the Federation of Bosnia and Herzegovina (FBiH):

Law on tax on profit of enterprises (Official Gazette FBIH nr 32a/97)

Decision on the amount and method of calculating depreciation and the revaluation of fixed

assets that are recognised as expenditures in tax balance (Official Gazette FBiH nr. 27/98)

The main difference in the treatment of depreciation between the entities is the allocation of depreciation which in RS is done on a regressive basis whereas in FBiH the straight line method is used.

The depreciation allowances have to be charged proportionally in each Progress Report until the end of the project and the depreciation costs can of course never exceed the initial purchase price.

The Beneficiary needs to demonstrate to the FLCO which depreciation method has been used for each piece of equipment and show that this is in line with the prevailing accounting regulations / tax legislation of Bosnia and Herzegovina.

Where the equipment purchased is not used exclusively for the purpose of the project, the costs should be charged on a pro-rata basis also as far as depreciation is concerned. In other words, only a part of the purchase price (or depreciation rate) can be allocated to the project.

Page 38: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

35

b) Rent of equipment

This is only possible provided that renting is the most economic and cost-effective way of obtaining the equipment (this will have to be proven by the Beneficiary).

c) Leasing of equipment

This is only eligible if the total cost of leasing does not exceed the cost of renting.

Checks related to the equipment budget line include31:

ITEM / ISSUE TO BE CHECKED DOCUMENTS USED / CHECKED

All necessary information is available concerning

expenditure claimed for equipment incurred during

the implementation of the project

Equipment purchased, rented or leased is

necessary for the implementation of the project

and is explicitly foreseen in the latest approved

Application Form

If equipment is rented then this should be the

most cost-effective way (i.e. cheaper than

purchase or lease)

If equipment is leased the total leasing fee

should not exceed that of rental for the same

period.

Kind of equipment is eligible according to the

Programme rules and guidelines (e.g.

Programme Management and Control manual if

such exists)

Evidence of compliance to procurement rules

(i.e. it is clear on what basis the supplier has

been selected and the following basic

documentation is available: Technical

Specifications (TS), information about potential

suppliers approached to submit an offer,

request for offer, offers received, evaluation

report /grid, members of the Evaluation

Committee, contract…)

31

For all expenditure claimed, proof of payment should be provided (in the form of e.g. bank statement, not transferable at-sight checks, bank checks, payment orders, daily book for cash payment, …).

Page 39: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

36

Evidence of compliance to publicity and

visibility rules

The contract concluded with the selected

supplier is available and reference is made to

the project and the programme

Evidence of the existence of the equipment (e.g.

inventory) is available

Purchase price is in line with market value

If the economic lifetime of the equipment goes

beyond the duration of the project, only

depreciation costs are reported and the

calculation method is available and correct

If the economic lifetime of the equipment goes

beyond the duration of the project, a separate

declaration by the Beneficiary that it undertakes

to avoid any substantial change to the

equipment for at least 5 years following project

completion

If equipment is NOT used exclusively for the

purpose of the project, only a share of the

actual cost can be allocated pro rata to the

project calculated using a fair, justified and

equitable method.

Changes in the quantity of equipment: have to

be confirmed by the Lead Beneficiary

Changes in the type of equipment: have to be

approved by the Managing Authority

4.4.8 Investments32

This budget line refers to small scale investments with a demonstrated transnational impact approved in the Application Form and includes costs related to:

32

This budget line is referred to as “Small scale investments” under the South East Europe Programme (SEE).

Page 40: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

37

construction works (either from the beginning or adaptation of something which already exists

purchase of land33

When awarding contracts for the realisation of works the procurement procedures established for the programme concerned need to be fully respected as well as the publicity rules (see also section 6.3.1.4 “External expertise”, 6.3.1.5 “Meetings and events” and 6.3.1.6 “Promotion costs”).

The FLCO will pay attention to whether or not the most economic option (“value for money”) has been chosen.

All construction works realised must have been clearly foreseen in the last updated version of the Application Form (AF) and if this is not the case, they must have been approved by the Managing Authority (MA), the Joint Technical Secretariat (JTS) and or the Joint Monitoring Committee (JMC) beforehand.

The FLCO will regularly verify the existence of construction works by means of on-the-spot checks.

Depending on the nature of the investment, the respect of environmental policies (e.g. feasibility study, environmental impact assessment, building permission etc) needs to be ensured. Costs related to this needed prior to realisation of the investment and delivered during project implementation should be allocated to the budget line “Investments”.

Beneficiaries should possess a valid construction permit prior to signing the IPA Subsidy Contract and the owner of the permit should be a partner in the project.

a) Construction works

These can take the form of construction from scratch or reconstruction, expansion or renovation of already existing buildings or infrastructure.

For these kinds of costs either the full cost may be eligible or a share of the actual cost to be allocated pro-rata to the project depending on the use.

1. 100% full cost can be charged to the project where:

The construction work is used exclusively for the project’s purpose and will remain In use for the same purpose for at least 5 years after project completion without any substantial modification.

2. Share of the actual cost allocated pro rata to the project where:

The construction work is NOT exclusively used for the project’s purpose.

33

Up to a limit of 10% of the total project budget.

Page 41: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

38

b) Land purchase

Land not yet built on can be purchased and be eligible under four conditions:

1. There should be a clear direct link between the land purchase and the project’s objectives

2. The cost does not exceed 10% of the project’s total budget

3. Certificate from an independent qualified assessor (or duly authorised official body) confirming

that the price does not exceed the market value.

4. Copy of draft sales contract showing that the land is free of any burden (to be submitted before

signing the IPA Subsidy Contract).

Checks related to the investments budget line include34:

ITEM / ISSUE TO BE CHECKED DOCUMENTS USED / CHECKED

All necessary information is available concerning

expenditure claimed for investments incurred during

the implementation of the project

The investment (i.e. construction works or

purchase of land) is explicitly described in the

Application Form

Nature of the investment is eligible according

to the Programme rules and guidelines (e.g.

Programme Management and Control manual if

such exists)

Evidence of compliance to procurement rules

(i.e. it is clear on what basis the works

contractor has been selected and the following

basic documentation is available: Tender

Dossier, information about potential works

contractors approached to submit an offer,

request for offer, offers received, evaluation

report /grid, members of the Evaluation

Committee, contract…)

The contract concluded with the selected works

contractor is available and reference is made to

the project and the programme

34

For all expenditure claimed, proof of payment should be provided (in the form of e.g. bank statement, not transferable at-sight checks, bank checks, payment orders, daily book for cash payment, …).

Page 42: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

39

Evidence of the existence of the construction /

renovation (e.g. documentation of the works at

community and / or national level, photographs)

is available

If construction will NOT be used exclusively for

the purposes of the project, then only a share of

the actual cost can be allocated pro rata to the

project using a fair, justified and equitable

method

A valid and legal construction permit (or other

document required by community / national

law) is available and the owner of the permit is

beneficiary in the project

If owner is not a beneficiary in the project,

proof of ownership of the real estate (which

could be state-owned) is available

If the real estate is owned by private legal or

natural persons (companies or individuals) the

partner has submitted a long-term hiring or

lease agreement with a minimum validity of 5

years upon completion

LAND PURCHASE

If land is purchased, up to 10% of the eligible

expenditure of the operation is used at the

moment of project closure

If land is purchased, contract is available

Evidence is available that the price of the land is

in line with market values (certificate from

independent qualified assessor or duly

authorised official body)

Copy of sales contract showing that the land is

free of any other burden is available

Page 43: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

40

4.4.9 Financial charges and guarantee costs

This budget line includes costs related to:

charges for transnational financial transactions

bank charges for opening and administering the accounts where the implementation of an

operation requires (a) separate account(s) to be opened

cost of guarantees provided by a bank (or other financial institutions) to the extent that such

guarantees are required by national or Community legislation

cost of guarantee requested from the private Lead Beneficiary up to the same amount of the

cost of the guarantee covering the amount of the pre-financing

a) Financial charges

In case of separate bank accounts opened specifically for project purposes, the bank charges paid by the Beneficiary for setting up and administering the account are eligible.

Bank charges which are eligible include:

periodical or lump sum fees

registration costs for each entry

annual costs for cash dispenser management

bank statement or communication despatch costs

costs for (periodical) closure

Charges related to a bank account not specifically opened for the purposes of the project (e.g. where the Beneficiary has decided to use an existing account) cannot be charged against the budget line “Financial charges and guarantee costs” but should instead be reported under the budget line “Overheads”.

b) Guarantee costs

Costs related to guarantees provided by a bank (or other financial institutions) are eligible to the extent that they are required by national or Community legislation.

In the framework of some programmes, private Beneficiaries may be required to provide a financial guarantee prior to the signature of the IPA Subsidy Contract. In these cases, the cost of the guarantee is eligible only up to the cost of the guarantee covering the amount of the pre-financing.

Page 44: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

41

Checks related to the financial charges and guarantee costs budget line include35:

ITEM / ISSUE TO BE CHECKED DOCUMENTS USED / CHECKED

All necessary information is available concerning

expenditure claimed for financial charges and

guarantees incurred during the implementation of

the project

Costs are real and directly related to the project

Costs have not been declared under other

budget lines

If charges for opening and administering a

bank account are declared, a dedicated bank

account for the specific purpose of the project

has been opened (Note: if an existing account of the

Beneficiary is used, then charges should be reported

under “Overheads”)

If costs of guarantees are claimed, such

guarantee is required by national or Community

legislation

The costs claimed for guarantees is up to the

amount of the pre-financing

4.5. ON THE SPOT CHECKS

4.5.1 DEFINITION AND PURPOSE

The above-described desk-based administrative checks are complemented by so-called on-the-spot checks carried out by the First Level Control Office (FLCO).

On-the-spot checks make it possible for the First Level Controller (FLC) to get better acquainted with the project and to verify in real life the existence and realities of the project and thus are of added value to the checks performed on the basis of the documents in the FLCO premises.

In addition, on-the-spot checks make it possible for the First Level Controller (FLC) concerned to ensure that the activities as stated in the Activity Report (AR) have been in effect carried out, that the outputs of such activities have in effect been delivered (e.g. equipment purchased can be located at the premises of the Beneficiary, construction works are undergoing etc…) and to have a general discussion with the Beneficiary on planned activities during the next reporting period, problems encountered so far and how to avoid them in the future etc.

35

For all expenditure claimed, proof of payment should be provided (in the form of e.g. bank statement, not

transferable at-sight checks, bank checks, payment orders, daily book for cash payment, …).

Page 45: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

42

It is good practice for the FLCO to perform regular on-the-spot checks but it is of course impossible to systematically visit all projects and therefore they are done on a sample basis (for further information on risk assessment and sampling strategy see section 6.3.2.3 below). However the FLCO should strive to visit a maximum of projects at least once during the project’s lifetime and for projects that have an investment component, it is recommend paying at least two visits (one at an appropriate point of time during the implementation period of the project and one close to the end).

During an on-the-spot check the FLC in charge will verify at least:

the reality of the operation

existence and / or proof of delivery of services / equipment / investments declared

compliance with publicity and visibility rules applicable to the programme under which the

project is financed

a more in-depth check of all documentation related to the respect of the public procurement

procedures (for further information see section 6.3.2.2 below)

the adequacy of all sorts of supporting documentation and the existence of an adequate audit

trail

the existence and effective functioning of an accounting system (either a separate system

dedicated to the project or an analytical system that allows tracking of expenditure back to the

project)

On-the-spot checks should be planned and prepared for in advance so as to render them as effective as possible. Generally sufficient notification should be given to the Beneficiary (e.g. two weeks) to ensure that the relevant staff and documentation will be available to the FLC. It is nevertheless left at the discretion of the FLC to perform an unannounced on-the-spot check.

4.5.2 RISK ASSESSMENT AND SAMPLING

First Level Controllers will perform at an early stage (i.e. as soon as possible after a contract is signed and the project implementation period starts) a risk assessment of the projects for which they are responsible and risk factors that will be taken into account include inter alia:

the type of beneficiary i.e. is the Beneficiary a public institution, a relatively big municipality, a small municipality, a NGO, a private company etc

the size of the Beneficiary i.e. a large institution with major resources and high capacity or a small organisation with limited resources and small capacity

the type of contract e.g. projects containing a lot of public procurement, value of contract, value of investments

Page 46: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

43

the complexity of project operations, activities and environment i.e. is the project routine to the Beneficiary, are many implementation problems expected (e.g. number of participants in project events, number of external stakeholders, legal and regulatory framework of the project)

the experience of the Beneficiary’s employees i.e. do key staff members (e.g. Managing Director, Financial Manager or Accountant, …) have had prior experience with the implementation of similar projects funded by the international donor community

the internal control systems of the Beneficiary i.e. do they exist and are they adequate

previous experience with the Beneficiary i.e. has the Beneficiary implemented projects in the past for which FLC was performed by the CFCU, have there been any problems detected during previous on-the-spot checks, have irregularities, fraud or corruption been identified in the past

The information to be gathered can arise from discussions with other people / institutions that have experience with the Beneficiary (e.g. the Delegation of the European Union to Bosnia and Herzegovina) or consulting different sources of information including media such as Internet, newspapers, government databases etc and the Beneficiary itself.

The risk factors are then given a risk level coefficient ranging from low over average to high and given a weighting and based on the results of the risk assessment exercise a final selection of projects to be visited on-the-spot will be made and an on-the-spot checks activity and time plan will be developed, ideally for each calendar year (“annual on-the-spot checks plan” – see below).

The risk assessment exercise will culminate in a risk assessment table, an illustrative example of which is presented below:

Page 47: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

44

RISK ASSESSMENT TABLE (illustrative example) (Period: from … / …. / …. to …. / …. / …..)

Project Code / Project Acronym / Name of Beneficiary

RISK LEVEL RISK FACTORS

LOW 1

2

MEDIUM 3

4

HIGH 5

WEIGHT ∑=100%

ADJUSTED for Year 1

Cumulative Risk Coefficient

RISK COEFFICIENT 0.2 0.4 0.6 0.8 1.0

1. Type and size of final beneficiary:

Type X 10% 12.5% 5.0

Size X 10% 12.5% 2.5

2. Contract characteristics:

Value of contract X 10% 12.5% 12.5

Total of procurement and investments X 10% 12.5% 7.5

3. Complexity of a particular project operations and environment

X 10% 12.5% 10.0

4. Experience of staff involved:

Experience of Final Beneficiary employees X 10% 12.5% 12.5

Experience of First level controllers X 10% 12.5% 12.5

5. Internal control systems of the Final beneficiary X 10% 12.5% 5.0

6. Previous experience with the beneficiary

On-the-spot checks carried out during the previous year and current year

10% -36

Any significant irregularities previously detected 10% -

Total 100% 100% 67.5

Value in money (in €) 100,000

Monetary value adjusted to risk level 67,500

36

Please note that during the first year of performance of on-the-spot checks, this criterion should be disregarded. The respective weighting should be distributed to other

categories.

Page 48: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

45

A final result of the risk assessment is a so-called risk ranking table, an illustrative example of which is presented here:

RISK RANKING TABLE – BASIS FOR SAMPLING FOR ON-THE-SPOT CHECKS (illustrative example) (Period : from … / … / …. to …. / ….. / ….)

There are several criteria for scheduling certain projects for testing by means of on-the-spot checks. The key criterion is value of the project adjusted to risk level. However, attention needs to be paid and use only value of the project that is according to the project budget falling within the period under review.40 Additional criteria include foreseen end date of the project, the number of controllers and their availability, readiness of beneficiary to prepare necessary documentation and provide assistance etc.

Based on the Risk Ranking Table above an annual on-the-spot check activity plan will be prepared, the template of which is provided in the following section:

37

At this stage a preliminary schedule for on-the-spot checks should be prepared i.e. it should be decided which projects will be visited in which quarter of the current year. 38

See Risk Assessment Table 39

For projects that due to high risk level have priority in terms of early scheduling of on-the-spot check, additional follow-up visits should be tentatively scheduled. However, this will also depend upon the results of the first on-the-spot checks. 40

If a project has a budget of 3 million that is evenly spread over 3 years, and if our period of review is 1 year, value used for risk assessment should be € 1 million.

Beneficiary Value (€) Risk coefficient

Value adjusted to

risk level

Ranking Preliminary on-the-spot scheduling

37

Q1 Q2 Q3 Q4

1 Organisation XYZ 100,000 67.538

67,500 H X X39

2 NGO ABC 50,000 82.5 41,125 M X

3 Municipality QPR 70,000 50 35,000 L X

4 ...

5 ....

Page 49: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

46

4.5.3 ON-THE-SPOT CHECK ACTIVITY PLAN

Illustrative example for calendar year 2012 as per 09/02/2012

Project

acronym

Project

code

Beneficiary

from BiH

FLC in

charge

Project value

(budget of BiH

beneficiary)

Risk level (L

/ M / H)

First on-the-spot check

Second on-the-spot check

Planned

date

(month /

quarter)

Date of

execution

Findings Planned

date

(month /

quarter)

Date of

execution

Findings

ABC 123 AAA Ms. AB € 213,111.20 M 01/2012 06-08/01/2012 see report Q2/2013

DEF 456 BBB Mr. CD € 134,765.89 L Q4/2012 Q2/2013

GHI 789 CCC Ms. EF € 74,982.15 H Q2/2012 Q1/2013

Notes:

(i) The above table caters for two on-the-spot checks to be carried out per project; however for those projects where more than two on-the-spot checks are

warranted by the project situation more columns can be added.

(ii) If the execution date differs substantially from the planned date for the on-the-spot check, the reasons for such should be explained.

(iii) The on-the-spot check activity plan will be updated on a monthly basis.

Page 50: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

47

4.6. DOCUMENTING FLC CHECKS

Experience has shown that sometimes controllers perform excellent work but fail to document the work carried out in a way that would enable audits at a later stage to fully understand and demonstrate what was done at the time. It is important to realise that auditors normally have neither experience nor prior knowledge of the project, the beneficiary or the controller and therefore need to have access to as much information as possible to get a clear picture of the project situation in its entirety.

In view of that First Level Controllers should systematically keep sufficient and well-organised documentation and records, in electronic version and/or paper copy, of (i) the various controls performed (ii) the results and evidence obtained by means of these controls and (iii) the conclusions and corrective measures taken.

Such documentation and records include as a minimum:

approved Application Form (copy)

signed Subsidy Contract and its amendments, if any (copy)

signed Partnership Agreement and its amendments, if any (copy)

original signed paper version and electronic version of each Declaration on Validation of

Expenditure (DVE) including the control report and control checklist

Beneficiary report in hard copy (original) and electronic version

copy of each invoice and/or accounting document of probative value (originals are sent to

the FLCO by the Beneficiary for verification purposes, voided by the FLCO and sent back to

the Beneficiary and a copy is kept at the FLCO)

copy of each supporting document included in the Beneficiary report (e.g. payslips, bank

statements, public procurement documentation, contract with external service providers,

suppliers etc)

project deliverables (i.e. all materials produced during the project period)

control checklists filled in and signed by the Controller (original)

control reports

personal notes taken by the FLC during the administrative desk-based or on-the-spot check

personal memos by the first level controller

correspondence with beneficiaries on clarifications / missing information requested (letters

sent by postal service / courier service, email) (copy)

copies of the beneficiary’s main documents (contracts, agreements, invoices, promotional

brochures, training material etc)

photographs taken

Page 51: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

48

all documentation related to any on-the-spot check carried out

audit reports, if any

The verification of expenditure (‘”first level checks”) is to be documented by the Controllers and the work records are to be retained for audit purposes for at least three years after the date of closure of the programme concerned and in practice this means that all documents need to be kept until the dates specified below:

IPA Adriatic CBC Programme December 31, 2021

South East Europe Programme (SEE) December 31, 2022

Transnational Mediterranean Programme (MED) December 31, 2021

It is recommended to store documents during the programme implementation period at the premises of the Controllers and after that to be archived for audits until the dates specified above.41

Records should state the work done, the results of the verifications as well as the measures taken in case of irregularities and errors.

5. SUBSTANTIVE PROCEDURES

The key procedures that underlie checklists and control reports are:

Check of completeness

Check that costs are supported by all necessary documents (e.g. for

staff costs items such as time sheets, employment contracts,

calculation methods that demonstrate the (part of the) salary charged

against the project

Check of compliance Check that costs comply with all relevant legislation and rules

governing the programme / project

Check of plausibility (acceptability) Check that costs are credible and probable (e.g. for staff costs issues

such as: hours worked and related outputs generated, rates)

Check of existence and reality

Check that costs declared have been incurred in reality and relate to

existing and verifiable outputs (e.g. for staff costs: verify during an on-

the-spot check that project staff exist in reality)

41

The official archiving procedure of the Ministry of Finance and Treasury (MoFT) will be respected.

Page 52: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

49

5.1. CHECKS OF COMPLETENESS

These intend to verify whether the information provided by the Beneficiary is complete and can relate, for instance, to the completeness of the documents attached to the financial report but also to the completeness of revenues deducted, if any. They are commonly used during the desk-based administrative check and to a lesser extent during the on-the-spot checks.

What do controllers check in terms of completeness?

Examples include:

verification that all expenditure items listed in the List of Expenditure and declared in the financial report are supported by invoices or documents of equivalent probative value

check whether there is an adequate audit trail

check whether there is an adequate filing system in place

check whether the Beneficiary maintains an accounting system

How can the checks be documented?

The checks can be documented by ticking the foreseen box in the checklist (e.g. “document sent by the Beneficiary are complete”) and, if necessary, including comments on missing documents or documents which do not meet the minimum criteria set by either the Programme, Community or national rules or legislation.

5.2. CHECKS OF COMPLIANCE

These intend to verify whether the Beneficiary complies with all relevant legislation, both on Programme, Community as well as national / entity level governing the project.

Many compliance checks are straightforward with a clear control objective, a clear outcome and immediate effects on eligibility (e.g. expenditure was incurred during the eligible time period). Other compliance checks can be less straightforward such as those related to horizontal issues (e.g. “equal opportunity and non-discrimination”) or more complex rules or legislation (e.g. “public procurement”).

What do controllers check in terms of compliance?

Examples include:

correctness of the application for reimbursement

Page 53: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

50

verification that expenditure relates to the eligible period

verification that the expenditure relates to an approved operation (or part of an operation)

compliance with programming documents including, where applicable, compliance with the

approved co-financing rate

compliance with EC and/or national procurement rules

respect of rules on visibility and publicity

Sometimes it is not necessary, or impossible, to draw a clear line between compliance and other kinds of checks as ultimately all checks refer to rules, regulations and legislation.

In a centralised control system (such as the one in place in Bosnia and Herzegovina) it may be useful for the Controller to cross-check different projects implemented by the same Beneficiary whereby the Controller will pay special attention to staff costs (as this generally makes up the biggest cost of any project) and more specifically cross-checking of timesheets of employees working for more than one project.

It can also be useful to use Internet search engines (such as Google) to inspect information about a Beneficiary (e.g. field of expertise, other projects and funding sources) or management personnel (e.g. their activities in other organisations, roles in other projects). This can be an effective means to get a better understanding of the beneficiary and to detect, for instance, potential cases of double financing. The number of projects implemented by a Beneficiary should also be included in the risk assessment prepared to select projects that will be subjected to an on-the-spot check.

How do controllers check compliance?

They often use sub-procedures such as inspections, interviews, observations or walk-trough (for more information see section 3.2 below).

Controllers could verify that all the conditions outlines in the Subsidy Contract are complied with by inspecting relevant documentation and records, by inspecting project evidence (e.g. deliverables or outputs) or by interviewing project personnel.

How can the checks be documented?

Compliance checks are very definite by nature and a well developed first level control (FLC) system includes compliance checks in its checklists, especially those related to compliance with EU and national / entity legislation and programme rules. Therefore tick marks on the checklist or control report and references to the legislation concerned can be sufficient. Checks performed can be then documented by making a copy of the rule / regulation / legislation concerned which are kept on file.

Page 54: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

51

5.3. CHECKS OF PLAUSIBILITY

These kinds of checks verify whether expenditure incurred and declared are plausible or, in other words, credible and probable.

Basically any check involving professional judgment on the side of the controller such as checking value for money or the allocation method for overheads is a plausibility check.

In addition almost every check whether or not an expense was economically justified is a plausibility check and usually Controllers will check during an on-the-spot check (by means of interviews) what exactly people work on to get an idea of the plausibility of staff costs declared.

Plausibility checks are used in both desk-based administrative checks as well as during on-the-spot checks and may involve inspections, reconciliations, recalculations or interviews.

What do controllers check in terms of plausibility?

It is neither necessary nor possible to check every Beneficiary and report in terms of every single potential plausibility aspect. Instead controllers apply professional judgment and decide which plausibility checks are especially required or useful for a given project and Beneficiary based on the risk assessment carried out at the beginning of the project. As an example controllers could decide to make certain plausibility checks on staff costs for those employees that have very high project-related costs.

Examples include:

plausibility of project outputs in relation to staff hours claimed

plausibility of hours worked on the project in relation to other assignments / tasks of that

staff

plausibility of overheads charged to the project in relation to the time spent by the

Beneficiary on the project

Controllers do not check the quality of project activities and outputs in principle as the role of FLC is not to evaluate the project and there are quite often limitations for the Controller to assess results, especially with regard to specialist areas or studies (e.g. environmental impact assessments, training curriculae).

How do controllers check plausibility?

Controllers often need to rely ion their experience and apply professional judgment in order to come to a conclusion.

There are three approaches to plausibility checks:

Page 55: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

52

(i) checks within the project itself (e.g. comparing the expenditure incurred and declared to the overall progress of the project and outputs generated)

(ii) checks with respect to other activities of the Beneficiary (e.g. comparing the allocation of overheads across the various projects the Beneficiary is involved in)

(iii) checks in relation to what is usual / common on the market (e.g. comparing costs with benchmarks, maximum / average costs i.e. what is an average or maximum salary in the country for the type of personnel / expert employed, what is an average cost of renting an office in a particular town etc)

Examples of checks include:

interview with the project accountant

inspection of timesheets: check if time worked on the project as indicated on the timesheets equals the hours claimed and whether or not they exceed daily working hours

inspection of pay slips: check if payment of salaries contain ineligible expenditure (e.g. bonuses)

compare salaries with what is typical in the sector taking into account the job description, the position, work experience etc

How can the checks be documented?

For checks requiring substantial professional judgment it can be useful to prepare a memo and in case the check involved the review of specific documents, it is also useful to include these documents in the working papers.

5.4. CHECKS OF EXISTENCE AND REALITY

The objective of these kinds of checks is checking if the Beneficiary, the project, products or services as described in project reports exist in reality.

They can also helpful in gaining a better understanding and insight of the project as well as the organisation that implements the project and its environment and to identify potential risks.

They are mostly used during on-the-spot checks but can also be used during the desk-based administrative checks (e.g. verification of the existence of written outputs generated such as studies).

What do controllers check in terms of existence and reality?

Page 56: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

53

The EC guidance on management verifications highlights the importance of checks of existence and reality during on-the-spot checks in particular where operations are intangible and where little or no physical evidence remains upon completion (e.g. training courses).

Depending on the kind of Beneficiary, the nature of the project and the controller’s own risk considerations, potentially useful checks of existence and reality can include:

the overall situation of the Beneficiary i.e. office environment, staff, organisational structure, its legal environments

the role of the Beneficiary in the overall project

the Beneficiary’s financial management systems including audit trail and filing and archiving

systems

purchased goods written outputs such as studies, manuals, …

information on project activities such as trainings, seminars, conferences, information events, press conferences etc

How do controllers check existence and reality?

Checks of existence and reality aim at comparing a written or oral statement (a “plan”) to the actual reality. Therefore controllers will always look at the “plan” first and then compare it to the actual situation. The “plan” may include for instance obtaining and inspecting an inventory of purchased goods which then will be counter checked during an on-the-spot check.

How can the checks be documented?

Controllers often document existence and reality by including evidence in the working papers such as:

evidence of the project site such as plans of the project office, photos of the project office

copies of project outputs (e.g. studies, manuals)

other evidence such as training materials, attendance lists of meetings / workshops / seminars, press releases, photos of project events

evidence of goods purchased (e.g. inventory which is ticked off) or photos of equipment

In cases where serious issues are detected such as no evidence of the project being implemented, fake evidence, double financing) it can become necessary to draft a separate memo on the situation to be included in the controller’s working papers.

Page 57: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

54

6. SUB PROCEDURES

A set of sub-procedures underlie the above-stated substantive procedures:

Inspection of documents and

records

Reading and understanding of any relevant document, electronic

record or print out of an electronic record

Reconciliation

Double check of figures to ascertain that what is stated in one

document is identical with the same figure included in another

document

Recalculation

Verification whether a figure was calculated correctly, i.e. a re-

performance of a calculation executed by the beneficiary is

undertaken

Inquiry and interview Documented discussions with beneficiary staff (extensive inquiries are

usually referred to as interviews)

Observation of events and

processes

Watching people while they execute project-related activities either at

the premises of the beneficiary or any other site where projects

activities take place

Walk-through Tracing of a specific process or transaction step by step (e.g. tender

process)

The first three sub procedures are normally undertaken during the administrative desk-based checks whereas the last three would normally be performed during on-the-spot checks but they can also be used interchangeably.

6.1. INSPECTION OF DOCUMENTS AND RECORDS

This is referred to as the reading and understanding of any relevant document, electronic record or print out of an electronic record and are an essential part of substantive procedures such as checking completeness, plausibility ort compliance and are used both during desk-based administrative checks as well as during on-the-spot checks.

What do controllers inspect?

Controllers will check for each payment claim whether the supporting documentation includes as a minimum:

a list of expenditure showing the individual cost items and a total amount of expenditure

Page 58: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

55

references of underlying invoices or documents of equivalent probative value, date of payment and payment reference number

copies of invoices / receipts

proof of payment for expenditure items

However the above minimum requirements are considered insufficient in CBC programmes under shared management and it is common practice to inspect a much wider set of documents including relevant contracts, documentation of public procurements, written project outputs, publicity material, travel documents, calculation schemes (e.g. for the calculation of overheads), documentation of project meetings and events etc.

Standard checklists outline a minimum set of documents and thus provide certainty that key documents are covered. However although some checklists are quite comprehensive and lengthy, no list can ever be complete and cover all potential cases and therefore controllers have to decide on a case-by-case basis whether or not certain additional documents (not included in the checklist) should be inspected.

How can the inspections be documented?

Checklists usually require information that cannot be obtained without inspection of the relevant documents and records. E.g. “checking whether all expenditure is directly related to the project and necessary for the development of the project” requires the inspection of invoices, Application Form, Subsidy Contract etc.

Although the basic method is simple, inspections can easily become quite demanding and time consuming and some inspections may also require specific technical expertise that may not be readily available.

It is very useful to inform Beneficiaries (e.g. by incorporating this into the letter announcing the on-the-spot check) in advance about the documents that should be prepared for inspection as this helps saving time during the on-the-spot check.

6.2. RECONCILIATION

This is a basic check whether or not a figure included in one document is identical with the same figure included in another document (e.g. amounts stated in the Financial Report should be exactly the same as the ones stated in the Activity Report – see also the Section 6.1.2.2 “Financial Report” of the Programme Management and Control Manual – PMCM – developed for the IPA Adriatic CBC Programme).

Usually when reconciling figures, Controllers do not stop just there but continue by re-calculating figures to ensure that they are mathematically correct (see below).

Page 59: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

56

If figures cannot be reconciled, Controllers either reject the figure or ask the Beneficiary to submit a clarification.

What do controllers reconcile?

In principle each single figure included in the Financial Report should be substantiated with supporting documents and Controllers usually reconcile all these figures with the relevant supporting documentation.

Examples include: reconciling the Financial Report with invoices and other supporting documents

reconciling the Financial Report with the list of expenditure, the bank account statements and the Beneficiary’s accounting system

reconciling staff costs with timesheets, hourly rates, payslips etc

reconciling overheads with overhead calculation methods

reconciling depreciation allocated to the project with the national rules in this respect

Some reconciliations (e.g. the reconciliation of the Financial Report with the list of expenditure) are usually done during the desk-based administrative checks whereas others, such as the reconciliation of declared costs with the Beneficiary’s accounting system will be carried out during on-the-spot checks.

How can reconciliations be documented?

Some checklists include questions related to reconciliations like “do lists of expenditure and Financial Report match”? Controllers then indicate on the checklist which reconciliations were carried out and what were the results.

In case of complicated reconciliations, Controllers may decide to include a memo in the working papers.

6.3. RECALCULATION

This aims at verifying that a figure was calculated correctly and is thus arithmetically correct.

Therefore a re-calculation is a re-performance of a calculation done by the Beneficiary in order to calculate eligible expenditure for a specific cost item.

If figures cannot be re-calculated, Controllers either reject the figure or ask the Beneficiary for a clarification.

Re-calculation often follows reconciliation as a logical next step.

Page 60: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

57

Examples include:

re-calculation of the sum of items included in the list of expenditure

re-calculation of staff costs (hourly rates, sums in time sheets etc)

re-calculation of overheads (way of allocation to the project)

re-calculation of depreciation allocated to the project

re-calculation of revenues generated, if any

How can re-calculations be documented?

Some checklists include questions related to re-calculation e.g. “are staff costs calculated correctly”? Controllers can then document in the checklist which checks were done and what were the results.

In case of complicated re-calculations, Controllers may decide to include a memo in the working papers.

Regularly inexperienced Beneficiaries have problems providing controllers with calculation schemes or methods and they leave it essentially up to the controller to come up with the calculated figure. However it is the responsibility of the Beneficiary to provide a traceable and verifiable calculation scheme / method for any cost allocated to the project.

6.4. INQUIRY AND INTERVIEWS

These are documented discussions with Beneficiaries.

They can be either short and relate to a specific outstanding issue or be quite extensive (e.g. so as to get a better understanding of the accounting process, procurement) and then they are often called interviews. Inquiries and interviews are mostly used during on-the-spot checks but can also be part of the desk-based administrative checks for instance in cases where Beneficiaries are invited to the premises of the controller to discuss the project.

What do controllers inquire about? Controllers can inquire about any subject they consider relevant for FLC purposes.

During an on-the-spot check it is quite normal and useful to conduct a general opening interview and a closing interview with the key personnel in order to obtain general information and to gain a better

Page 61: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

58

understanding of the project (the project set-up, its process and progress), the Beneficiary (legal status, organisational set-up, staff, internal processes and controls, responsible persons with regard to accounting, public procurement etc) and the project environment (industry or sector activity, legal and organisational relations to other entities e.g. framework contracts with specific suppliers, outsourced personnel, funding sources including other projects co-financed by EU or national sources etc).

It is good practice to start an on-the-spot visit with an interview on how the project progresses.

Additional specific interviews with a view on obtaining information on specific (e.g. high risk) issues or transactions (e.g. specific public procurement) and discuss these with the person in charge.

In order to do efficient and focused interviews, a list of questions prepared in advance and based on inter alia findings from preceding controls and audits can be very helpful.

Controllers should identify and contact the persons to be interviewed in advance so as to ensure that they will be present during the on-the-spot check.

How are inquiries and interviews conducted?

Even though inquiries and interviews sometimes directly lead to the detection of an error, they are often not sufficient in itself and need to be complemented by further control procedures.

Controllers may decide to first hold interviews with key personnel so as to better understand the project and then continue to verify whether the information obtained is true by applying other control procedures such as the inspection of documents, re-calculation etc…

How can inquiries and interviews be documented?

Controllers can prepare a memo of an inquiry and interview and include it into the working papers.

In those cases where someone explained a specific document it could be sufficient to include this document in the working papers and put a short handwritten notice on it indicating the person that has been asked the question and the information obtained.

6.5. OBSERVATION OF EVENTS AND PROCESSES

These involve watching people while they execute project-related activities such as an event or an internal process at the premises of the Beneficiary or at any other site where project activities take place.

They are particularly useful if no “hardcopy” outputs of a process or event exists.

Page 62: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

59

What do controllers observe?

Controllers make individual decisions on what to observe on the basis of information obtained (e.g. during a desk-based administrative check) and / or own risk considerations related to the project (e.g. projects with many training events).

Examples include:

observation of a project event (e.g. seminar, conference, training etc)

observation of an internal process (e.g. the execution of a payment)42

Observations may or may not be announced in advance.

How can observations be documented?

Observations can be documented in a memo describing the event or internal process that was observed.

It can be useful to include copies of outputs or other evidence of the event or process observed (e.g. pictures) in the working papers.

In cases where dates of project events are not made publicly available or are not indicated in project documentation, controllers can ask the beneficiary for a list of such planned events and respective dates and venues.

It is also good practice that controllers request the beneficiary to inform them about planned tenders. Controllers can then decide to participate in evaluation meetings (as observer) or can request a copy of the Tender Dossier so as to check compliance with the prevailing procurement rules. These are considered pro-active checks which contribute to the prevention of serious problems during the implementation of the project.

6.6. WALK-THROUGH

During a walk-through controllers trace a specific transaction or process of the Beneficiary step by step (e.g. a particular public procurement).

A walk-through can be useful in order to gain a better understanding of the Beneficiary’s processes and internal controls and identify potential error sources or risks.

42

This can be an effective method to detect potential error sources and to learn how the process is performed by

the Beneficiary.

Page 63: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

60

What do controllers “walk through”?

A walk-through can be very time consuming and controllers therefore have to make own professional judgment about whether or not to use the walk-through procedure and to what extent. An option regularly used in the FLC community is to perform a walk-through of the most risky transactions only (e.g. the major public procurement under a given project). Another option is the walk-through of a single expense of each cost category (e.g. staff costs of one employee, overheads of a given reporting period) or to simply trace one invoice through the beneficiary’s accounting system from receipt to payment.

Examples include:

tracing of one or more public procurement processes from the decision on the procurement

procedure to be used to the conclusion of the contract

tracing of one or more salary payments from the filling in of the time sheets by the employee

to the payment to the employee’s account

tracing of travel costs from the handing in by the employee to reimbursement by the

organisation

tracing depreciation from the calculation of the eligible depreciation costs chargeable to the

project to the inclusion in the accounting system

How do controllers conduct a walk-through?

An example of a basic walk-through for public procurement contains the following steps: conduct a specific interview on public procurement with the person responsible within the

Beneficiary’s organisation (e.g. how do you usually perform public procurement?) and

inspect related documents (e.g. internal manual on public procurement if existing)

select one public procurement as a sample and walk through in chronological order together

with the Beneficiary and obtain all documents and records related to it (e.g. request for

offers, offers received, evaluation, selection, contract)

document the walk-through (e.g. in a memo)

if material deviations from the processes (as identified during the interview or internal

manual) are discovered, discuss these issues with the Beneficiary and where applicable

define the error(s) and determine the financial effects

Page 64: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

61

How can a walk-through be documented?

A walk-through is basically a comparison between a planned process and an actual process.

Therefore as a first step the controller can document the planned process by documenting the interview in a memo clearly describing the individual steps of the process and their expected outputs. The memo should be included in the working papers.

As a second step the controller will document the results of the walk-through in a memo on the basis of the description of the planned process (as identified during the interview mentioned above) and the actual findings.

An example of documentation of a walk-through of a procurement process related to services (single tender) may look like this:

Page 65: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

62

Information obtained during the interview with the person responsible for public

procurement within the Beneficiary’s organisation

Documentation of the steps of the process that have been subjected to a walk-through

Process step Output Output available?

Y / N

Output correct?

Y / N

Controller notes

Planning of the services required

and decision on the procurement

procedure to be applied

Documentation on preliminary research and

decision on the selection of the procurement

procedure to be used

Initiation of the tender procedure

(description of the services

requested and definition of the

evaluation and selection criteria)

Clear description of the services (e.g. Terms of

Reference – ToR)

Clear, unambiguous and non-discriminatory

evaluation and selection criteria have been

defined

Launch of the tender procedure Letters to potential service providers

Receipt of offers Offers have been duly received and filed

Evaluation of the offers Offers have been evaluated on the basis of

the pre-agreed evaluation matrix

Information to successful and

unsuccessful Tenderers

All Tenderers that submitted a bit have been

informed about the result

Signature of contract Signed contract

Page 66: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

63

7. IRREGULARITIES AND RECOVERIES

7.1 BACKGROUND, DEFINITIONS AND TYPES OF IRREGULARITIES

7.1.1 Background

The provisions with respect to the detection, reporting and ensuring the necessary follow-up measures with respect to suspected or actual irregularities in using EU funds, in combination with the recovery of amounts unduly paid, are laid down in a number of legal texts:

Commission Regulation (EC) No. 1828/2006 of 8 December 2006 setting out rules for

implementing Council Regulation No. 1083/2006 laying down general provisions on the ERDF,

ESF and Cohesion Fund and Council Regulation No. 1080/2006 on the ERDF

Council Regulation (EC, Euratom) No. 2185/1996 of 11 November 1996 concerning on-the-spot

checks and inspections by the Commission to protect EC financial interests

Council Regulation (EC, Euratom) No. 2988-95 on protection of EC financial interests

Council Regulation (EC, Euratom) No. 1073-1999 concerning investigations conducted by the

European Anti-Fraud Office (OLAF)

Framework Agreement between Bosnia and Herzegovina and the Commission of the European

Communities on the rules for cooperation concerning EC financial assistance to Bosnia and

Herzegovina in the framework of the implementation of the assistance under the Instrument for

Pre-accession Assistance (IPA)

Council Regulation (EC) No. 718/2007 implementing Council Regulation (EC) No. 1085/2006

establishing an instrument for pre-accession assistance (IPA) and more in particular Article 114

and Article 138 of the IPA Implementing Regulations (IPA IR)

Commission Regulation (EU) No. 80/2010 of 28 January 2010 amending Regulation (EC) No.

718/2007 implementing Council Regulation (EC) No. 1085/2006 establishing an instrument for

pre-accession assistance (IPA)

Basically the above-mentioned legal provisions state that participating countries shall be responsible for the management and control of cross-border programmes in particular preventing, detecting and correcting irregularities and recovering amounts unduly paid together with interest on late payment (if applicable). Beneficiary countries are obliged to notify such irregularities to the Commission and keep the Commission informed of the progress of administrative and legal proceedings.

7.1.2 Definitions

IRREGULARITY - Any infringement of a provision of Community and/or national law resulting from an act

or omission by an economic operator which has, or would have, the effect of prejudicing the general

budget of the Communities by reimbursing an unjustified item of expenditure.

Page 67: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

64

FRAUD - Any intentional act or omission relating to:

(i) the use or presentation of false, incorrect or incomplete statements or documents which has

as its effect the misappropriation or wrongful retention of funds from the general budget of

the European Communities or budgets managed by, or on behalf of, the European

Communities

(ii) non-disclosure of information in violation of a specific obligation with the same effect

(iii) the misapplication of funds for purposes other than those for which they are originally

granted43

CORRUPTION -

Active: deliberate action of whosoever promises or gives, directly or through an intermediary, an

advantage of any kind whatsoever to an official for himself or for a third party for him / Her to

act or to refrain from acting in accordance with his / her duty or in the exercise of his / her

functions in breach of his / her official duties in a way which damages or is likely to damage the

financial interests of the European Communities

Passive: deliberate action of an official who, directly or through an intermediary, requests or

receives advantages of any kind whatsoever, for himself or a third party, or accepts a promise of

such advantage, to act or to refrain from acting in accordance with his/her duty or in the

exercise of his / her functions in breach of his / her official duties in a way which damages or is

likely to damage the financial interests of the European Communities

7.1.3 Types of irregularities

Irregularities can take different forms and shapes and may be caused by a variety of reasons. They can be:

Technical: arise due to the supply of material or workmanship of a lower quality than that

specified in the contract (most especially for supplies and works types of contracts). Quality

control should be ensured in the first place by the Beneficiary and double checked by the FLC

when exercising on-the-spot checks.

Contractual: arise due to an incorrect application of the contractual legal rules. A thorough

knowledge and understanding of the contract is essential to avoid this kind of irregularities.

Contractual irregularities include:

43

Whenever fraud is suspected it gives rise to the initiation of administrative of judicial proceedings at national

level. Remember that fraud is a crime and therefore it is the relevant court that will qualify it as such.

Page 68: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

65

- an incorrect delegation of powers and duties

- incorrect site instructions

- incorrect presentation of addenda / variation orders

- failure to respect deadlines

- incomplete or lack of supporting documentation

- total lack of or insufficient accounting records

Financial: can arise from fraud or error whereby financial irregularities are caused by fraudulent

application or theft of funds which may include corrupt practices and are caused by mistakes in

the processing of financial transactions resulting in erroneous movement of EU funds or a threat

to the financial interests of the European Communities.

The below is a non-exhaustive list of examples of financial irregularities, whether intentional (fraudulent) or unintentional (error):

- costs declared which had not been foreseen in the original or revised (and

approved) budget

- expenditure which is apportioned to the project in an incorrect way

- disrespect for the ratio between EU and national co-financing

- revenue generated by the project but not declared by the Beneficiary

Note: The FLC will use professional judgment and following an in-depth analysis of the issue concerned decide on a case-by-case

basis whether the deviation from what should have been correct is serious enough to be taken to a higher level and to be put

into the irregularity reporting system and recovery procedure mechanism. Please note in this respect as well that the FLC’s main

role and responsibility is to control and validate expenditure declared PRIOR to reimbursement by the programme concerned so

expenses rejected at the level of FLC result in non-payment anyway and therefore the financial interests of the European

Communities are not damaged as such.

Administrative: arise from non-compliance with applicable rules established under the

programme concerned and quite often concern matters of incorrect presentation of

documentation (e.g. not using the standard formats / templates agreed at programme level).

7.1.4 Irregularities by type of infliction

Intentional:

arise from actions of any player / institution involved in the overall process (Lead Beneficiary,

Final Beneficiary, First Level Control Office - FLCO, National Authority – NA, National Fund - NF,

Page 69: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

66

Joint Technical Secretariat – JTS, Managing Authority – MA, Certifying Authority – CerAut, …) in

order to enrich himself or any other person and which is in conflict with the contract between

the Beneficiary and the Managing Authority (MA).

Examples include:

- invoices issued for undelivered services, goods or works (fictitious invoices, dummy contracts)

- invoices issued by non-existent firms

- (original) invoices issued in duplicate (whereby one is charged to a given project and the

duplicate to another with a view on obtaining reimbursement twice i.e. double-financing)

- falsification or manipulation of accounting records and/or supporting documentation

- transfers of funds to accounts not related to the project

With respect to public procurement some of the most common irregularities that may be encountered include (non-exhaustive list):

- artificial split of the envisaged services / supplies / works so as to be able to use the lesser

demanding procedure given the lower threshold

- proven conflict of interest between the Beneficiary and the Tenderer / Contractor

- failure to state all the selection and award criteria in the tender notice / tender dossier

- application of unlawful / discriminatory contract award criteria

Unintentional:

arise from actions of any player / institution involved in the overall process (Lead Beneficiary,

Final Beneficiary, First Level Control Office - FLCO, National Authority – NA, National Fund – NF,

Joint Technical Secretariat – JTS, Managing Authority – MA, Certifying Authority – CA, …) caused

by negligence and resulting, in most cases, from an infringement of approved procedures.

7.1.5 Irregularities by type of impact

With financial impact: those irregularities which have already resulted in the payment of

unjustified expenditure to the Beneficiary (Note: one of the most important roles of the FLCO is avoiding

validating unjustified expenditure) and which should be claimed back from the Beneficiary by means of

the procedures in place (Note: if repayment by the Beneficiary cannot be ensured for whatever reason, the

recovery procedure mechanism as explained below will be initiated).

Page 70: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

67

Without financial impact: those irregularities which are identified prior to the reimbursement of

unjustified expenditure to the Beneficiary (i.e. those expenses rejected and declared ineligible by

the FLCO)

7.1.6 Irregularities by nature

Systemic: arise from a fundamental weakness in the management and control systems and have

a high probability of re-occurrence and can therefore occur in more than one project. Attention

needs to be given to the fact that notwithstanding the fact that initially systemic irregularities

may arise unintentionally, the system weakness can be eventually be exploited for fraudulent

purposes.

One-off: occur only in a specific project, are not system related and arise out of specific project

situations and should, in principle, not occur throughout the system or in other projects if the

management and control systems in place are properly functioning

7.2 DETECTION, PREVENTION, REPORTING AND RECORDING OF IRREGULARITIES AND

RECOVERY FUNDS

7.2.1 Detection and prevention

Irregularities can occur at any stage in the lifecycle of a project / programme and systems established for the detection and prevention of irregularities must therefore cover the entire project / programme life cycle. Main preconditions to prevent as much as possible irregularities include:

strong commitment from top management

transparent, comprehensive and easy to use written procedures

segregation of duties thereby ensuring lack of conflict of interest

effective internal control system

independent audit function

a well-functioning monitoring and evaluation system

regular on-the-spot checks based on adequate risk assessment

comprehensive system for filing and archiving of all documents (electronic as well as paper-

based)

proper procedures for reporting of irregularities

Page 71: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

68

The FLC has a crucial role regarding the detection of irregularities since they are the only body performing 100% check of project expenditure. At the same time they have an important role in the prevention of irregularities by proposing improvements, through the Joint Technical Secretariat (JTS), the Managing Authority (MA) or the Working Group of First Level Controllers, to the financial management and control system and to assist, to a certain extent, the beneficiaries with their financial implementation issues and reporting duties.

Irregularities can be detected on the basis of the verification of supporting documentation during the administrative desk-based checks or by means of findings during an on-the-spot check or a combination of the two (e.g. information provided on paper does not match the situation found in reality on site).

7.2.2 Reporting irregularities

Whenever a First Level Controller (FLC) identifies, or suspects, an irregularity, s/he immediately informs the Irregularity Officer (IO) appointed within the CFCU.44

The IO is responsible for:

acting as a focal point for the collection of any information regarding suspected and / or actual

cases of fraud, corruption or malpractice which may arise during the implementation of a CBC

programme under shared management

collect all required documentation both from within as well as outside his / her organisation

record the data in the Register of Irregularities (see below)

establish a single file per suspected or actual irregularity

provide active and unrestricted assistance to any authorised body investigating a suspected or

actual irregularity (e.g. internal / external auditors, financial police, economic crime department,

OLAF, …)

participate in monitoring visits and on-the-spot checks, as required

review and improve, if necessary, the existing system on the detection, prevention and reporting

of irregularities

The IO within the CFCU will examine each individual case submitted to him / her and if considered necessary draw up an “Irregularity Notification Form (INF) in the format provided below.

44

Suspicion is the situation in which there are indications that an irregularity has occurred but not all facts and

circumstances are clear yet.

Page 72: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

69

IRREGULARITY NOTIFICATION FORM (INF)

DETAILS ABOUT THE PROJECT

Programme title: ……………………………………………………………………

Programme number: …………………………………………………………………….

Priority: …………………………………………………………………….

Measure: …………………………………………………………………….

Project title: …………………………………………………………………….

Project acronym: …………………………………………………………………….

Contract number: …………………………………………………………………….

Contract signature date: …. / …. / ….

Contract duration: ….. months

Contract end date: …. / …. / ….

DETAILS ABOUT THE BENEFICIARY

Name: ……………………………………………………………………..

Address: ……………………………………………………………………..

Contact person: ……………………………………………………………………...

Email: ………………………………………………………………………

Tel / fax: ………………………………………………………………………

DETAILS ABOUT THE IRREGULARITY

Date of detection: …. / …. / ….

Project stage: ………………………………………………………………………..

How was the irregularity detected? ……………………………………………………………….

Description of irregularity: ………………………………………………………………..

List of documents proving and substantiating the irregularity:

(i) ……………………………………………………………………..

(ii) ……………………………………………………………………..

(iii) ……………………………………………………………………..

Name of person initiating the irregularity procedure: ………………………………….

Date of initiating the irregularity procedure: …. / …. / ….

Signature: ………………………………….

Page 73: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

70

At the same time the IO within the CFCU will register the actual or suspected irregularity in the so-called “Register of Irregularities”:

REGISTER OF IRREGULARITIES FOR PROGRAMME …………………………………

Last updated: …. / …. / …. (to be updated on a monthly basis by the IO within the CFCU)

Project

No

Project

acronym

Beneficiary Date

irregularity

was

committed

Date

irregularity

was

detected

Type of

irregularity

Source of

information

Body /

person that

detected

irregularity

Amount affected by

irregularity

Amount to be

recovered

Amount recovered Remarks

IPA NCF Total IPA NCF Total IPA NCF Total

Page 74: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

71

The IO within the CFCU then submits the Irregularity Notification Form (INF) to the IO appointed within the office of the National Authorising Officer (NAO) / National Fund (NF) who will analyse it and ultimately determine whether any further action is required.

The IO within the office of the NAO will immediately inform the NAO who will decide on the most appropriate course of action which could entail as a first recourse either a further unplanned on-the-spot check by the FLC in charge of the project, accompanied by both the IO of the CFCU and the IO of the NAO, to further investigate the case or a request to internal auditors to perform an audit mission. Based on the outcome of the additional checks, the NAO may decide to report the irregularity to the Managing Authority (MA), in the format designed under the specific programme and who will make a final decision. Upon receipt of all required information from the NAO, the MA in close cooperation with the Commission, decides whether or not the case requires further action in the form of e.g. judicial proceedings. Depending on the situation and following instructions from the MA and / or the Commission, the national irregularity and recovery procedure will be initiated which ultimately will lead to a request issued by the European Commission (EC) to the Government of Bosnia and Herzegovina (BiH) to refund the programme.

The procedure related to detection and reporting of irregularities can be presented in a schematic way as follows:

Action

No.

Description of the action Person responsible Deadline Audit trail / document

1 Detection of the suspected / actual

irregularity

FLC Upon

detection

Irregularity Notification Form (INF) and

Register of Irregularities (RI)

2 Compilation of evidence / supporting

documents

FLC 5 WDs Supporting documentation in electronic

version / hard copy

3 Notification to Irregularity Officer within

the CFCU (IO CFCU)

FLC 1 WD Email all of the above

4 Review of irregularity file and decision on

further action (if further action required

notification to Irregularity Officer within

NF / NAO office)

IO CFCU 5 WDs INF / RI + supporting documentation

5 Review of irregularity file and decision on

further action (if further action required

notification to the Managing Authority of

the programme concerned)

IO NAO / NF 5 WDs INF + RI + supporting documentation

7.2.3 Recording irregularities

Upon detection of an irregularity, the person in charge of irregularities (IO) within the CFCU / FLCO must ensure that an “Irregularity File” is opened. Such files will be available to any auditing body investigating the irregularity. The purpose of the “Irregularity File” is to:

Page 75: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

72

provide a history of the irregularity and the way in which it was treated

provide information and evidence which might be needed in the case of e.g. criminal

proceedings

provide information in a consistent way if the details of the irregularity need to be

communicated to relevant and authorised persons or institutions

As a minimum the following data have to be recorded in irregularity files:

project acronym

project code

project title

priority measure (number and title)

name of Lead Beneficiary

country of Lead Beneficiary

contact details of responsible person within Lead Beneficiary

name of beneficiary from Bosnia and Herzegovina

contact details of responsible person within beneficiary from Bosnia and Herzegovina

budget managed by beneficiary from Bosnia and Herzegovina

overall project budget

First Level Controller in charge of the project

type of irregularity

reference to laws or other legal provisions which have been broken

date when the irregularity occurred

date when the irregularity was detected

source of information on the basis of which the irregularity was detected

irregularity has a financial impact (i.e. expenses had been validated and paid already)

date when the irregularity was reported to the Irregularity Officer within the CFCU / FLCO

date when the irregularity was reported to the Irregularity Officer within the office of the NAO

date when the irregularity was reported to the Managing Authority

date when the irregularity was reported to the European Commission

information on any previous irregularities committed by this beneficiary, if applicable

actions taken to resolve and eliminate the irregularity

information about the progress and result of any action initiated to recover funds that have

already been validated and paid out

date on which the funds were recovered and the details of the account on which they were

received

Page 76: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

73

date of receipt of the recovery order from the European Commission

deadline for repayment to the European Commission

date on which the funds were transferred to the European Commission

7.2.4 Recovery of funds

In addition Article 114 of the IPA IR states that it is the responsibility of the Certifying Authority (CerAut) of the programme concerned to ensure that any amount paid as a result of an irregularity is recovered from the Lead Beneficiary (LB). Final Beneficiaries shall repay the Lead Beneficiary the amounts unduly paid in accordance with the agreement existing between them. If the Lead Beneficiary does not succeed in securing repayment from a Final Beneficiary, the participating country on whose territory the relevant Final Beneficiary is located shall reimburse the Certifying Authority (CerAut) the amount unduly paid to that Final Beneficiary (FB).

According to Instruction of the Minister of finance and Treasury No 08-02-1-9583-1/12 from November 11, 2012 ; Point 8., the recovery of funds is been regulated as follows:

“If the MA of CBC Programme submits a request for a reimbursement of unduly paid out amounts to the MFT, the Ministry shall, in accordance with the Financial agreement between BIH, EC and the MA of that CBC Programme repay the requested amount from the budgetary position: Direct transfers - Funds appropriated for the withdrawal of IPA, a part of unallocated funds for projects. The Ministry shall take all actions in accordance with the laws of Bosnia and Herzegovina in order to compensate the reimursed funds from the BIH project beneficiary/project partner/LB. A claim for the executed recovery will be recorded in the Treasury General Leger.“

8.PUBLIC PROCUREMENT

8.1 RULES ON PUBLIC PROCUREMENT

The purchase of goods and services, as well as the ordering of works is subject to obligatory procurement

rules as followes:

IPA Adriatic CBC South East Europe (SEE) Mediterranean Programme

(MED)

PRAG is SUGGESTED45

Public procurement in the IPA cross-border cooperation programmes with EU Member State in shared management by Interact

46

BIH Public procurement legislation

47

PRAG PRAG

45http://ec.europa.eu/europeaid/work/procedures/implementation/practical_guide/index_en.htm) 46 http://www.interact-eu.net/downloads/1909/Public_procurement_in_IPA_crossborder_

cooperation_programmes_with_EU_Member_States_in_shared_management.pdf 47 http://www.javnenabavke.ba/index.php?id=10zak&zak=1&jezik=en

Page 77: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

74

8.2 BASIC RULES TO BE RESPECTED

8.2.1 Nationality and origin

Nationality : grants are made to beneficiaries according to programme rules and the territorial eligibility

for applicants is usually specified in the programme documents such as Calls for Proposals. This

restriction does not apply to experts (external expertise) recruited under a specific grant contract as they

may be of any nationality.

Origin: all supplies and materials purchased under the IPA Subsidy Contract must EITHER originate in

one of the 27 Member States of the European Union (EU MS)

Austria Finland Latvia Romania

Belgium France Lithuania Slovakia

Bulgaria Germany Luxembourg Slovenia

Czech Republic Greece Malta Spain

Cyprus Hungary Netherlands Sweden

Denmark Ireland Poland United Kingdom

Estonia Italy Portugal

OR in one of the countries eligible under the programme that provides the financing and as this is the

Instrument for Pre-accession Assistance (IPA) equipment can be purchased also from the following

countries:

Any country that is beneficiary of the Instrument for Pre-accession Assistance (IPA):

Serbia including Kosovo Turkey Montenegro Croatia

former Yugoslav Republic of

Macedonia

Albania Bosnia and

Herzegovina

Any country that is beneficiary of the European Neighbourhood and Partnership Instrument (ENPI):

Algeria Georgia Moldova Tunisia

Page 78: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

75

Armenia Israel Morocco Ukraine

Azerbaijan Jordan Palestinian Authority of

the West Bank and

Gaza Strip

Russian Federation

Belarus Lebanon Libya Syria

Egypt

Any country that is a Member State of the European Economic Area (EEA):

Iceland Liechtenstein Norway

International organisations:

international public-sector organisations set up by intergovernmental agreements and

specialised agencies set up by such organisations

the International Committee of

the Red Cross (ICRC)

The International Federation of

National Red Cross and Red

Crescent Societies

The European Investment Bank

(EIB) and the European

Investment Fund (EIF)

For unit purchases exceeding € 5,000 the beneficiary should be able to submit proof of the origin of the

equipment (to be obtained from the contractor). However In exceptional cases a derogation from the

rule of origin can be obtained from the Contracting Authority (i.e. the Managing Authority in the case of

CBC programmes under shared management) but this has to be duly justified and substantiated and

such derogation has to be obtained prior to initiating the procurement procedure as normally no

retroactive approvals are granted48.

8.2.2 Language

It is recommended to use English wherever possible (accompanied if required by a translation into the

local language).

48

Exceptional circumstances include (i) unavailability of services or products in eligible countries (ii) extreme

urgency (iii) the realisation of the project or action will be impossible or exceedingly difficult if no derogation is

obtained.

Page 79: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

76

Expenditure related to public procurement of services, supplies and / or works that do not comply with the requirements prescribed may be considered ineligible by the First Level Controllers (FLC) and may give rise to, given the nature of the activity, the opening of an irregularity investigation and in the worst case scenario to a need for recovery of substantial amounts wrongly paid.

8.3 TENDER PROCEDURE WALK-THROUGH

Given the fact that public procurement of services (external expertise), supplies (e.g. IT equipment) and works (e.g. infrastructure) needs to respect the procurement rules applicable under the programme concerned and in all cases must respect the basic principles of fair competition, transparency, equal treatment and non-discrimination, the First Level Controllers will systematically carry out additional checks (complementary to the desk-based administrative check of all documentation submitted by the Beneficiary) on any tender procedures carried out by the Beneficiary during the implementation of the project.

In view of that the following “tender walk through” procedure will be executed by the First Level Controllers during an on-the-spot check (non-exhaustive list of checks):

STEPS IN THE TENDER

PROCESS

NATURE OF CHECKS BY FLC DOCUMENTS USED

1. PROCUREMENT PLANNING

Definition of needs The tender process is related to an

activity in the project as it was approved

Approved Application Form

Modifications to the Subsidy

Contract

Procurement plan

Estimated budget and sources of

financing

Budget limitations are respected Subsidy Contract

Modifications to the Subsidy

Contract

Identification of and adherence

to the regulatory framework

All legal preconditions are fulfilled and

respected (e.g. the correct procurement

rules have been used, any

permits/licences/documents proving

ownership etc have been obtained)

Relevant EU and national

legislation

Programme documents

Manuals, guidelines and

instructions

Choice of tender procedure Correct tendering procedure according

to type (services, supplies, works) and

amount (e.g. local open tender, single

Approved Application Form

Subsidy Contract

Modifications to the Subsidy

Page 80: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

77

tender etc) was chosen Contract

Procurement plan

Tender Dossier

2. PREPARATION OF TENDER DOCUMENTATION

Preparation of tender

documentation (Terms of

Reference – ToR, Technical

Specifications- TS etc)

Non-discrimination

Principle of origin observed

Tender Dossier

Clarifications

Formal requirements related to

submission of bids by Tenderers

(standard templates, deadline,

language, packaging etc)

Equal treatment, non-discrimination, fair

competition principles observed

Tender Dossier

Clarifications

Eligibility criteria (origin,

nationality, grounds for

exclusion)

Equal treatment, non-discrimination, fair

competition principles observed

Tender Dossier

Clarifications

Selection criteria (technical,

financial)

Equal treatment, non-discrimination, fair

competition principles observed

Tender Dossier

Clarifications

Award criteria (best value for

money, economically most

advantageous offer, lowest price)

Equal treatment, non-discrimination, fair

competition principles observed

Tender Dossier

Clarifications

3. LAUNCH OF TENDER

Decision to launch the tender and

nomination of Evaluation

Committee (see also below)

Launch of the tender procedure was

formalised

Timing corresponds to the schedule of

activities

Approved Application Form

Decision

Procurement plan

Publication of Procurement

Notice / Invitations to Tender

Tender was properly advertised

Minimum number of Tenderers invited

according to the procedure

Procurement Notice

Invitations to Tender

4. SUBMISSION AND RECEIPT OF BIDS

Period of preparation of offers Required minimum period for the

preparation of offers by Tenderers is

respected

Publication / Invitations to

Tender

Register of offers received

Proofs of receipt

Additional information during the

bid preparation period

Additional information was provided to

all (potential) Tenderers and within the

Requests for clarification from

(potential) Tenderers

Page 81: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

78

time limits set by the procedure

concerned.

No illegal modifications to the tender

conditions occurred

Deadlines were respected

Replies to (potential) Tenderers

Deadline for the submission of

bids

Tenders submitted before the deadline

were accepted and those submitted

after the deadline have been rejected

Publication / Invitations to

Tender

Register of offers received

5. TENDER EVALUATION

Evaluation Committee An Evaluation Committee was appointed

consisting of the minimum number of

voting members possessing over the

necessary skills and competence

Order for the nomination of the

Evaluation Committee

CVs of the members of the

Evaluation Committee

Declarations of Impartiality and

Confidentiality

Tender Opening Session and

formal check

Public opening of offers (if applicable) Tender Opening Report

Clarifications Clarifications do not amend tender

conditions

Requests for clarification and

replies received

Administrative compliance check Eligibility and selection criteria were

observed

Evaluation Report

Evaluation of technical and

financial offers

Award criteria were observed Evaluation Report

Conclusions of the Evaluation

Committee and Evaluation

Report

Procedure was carried out in a

transparent and objective way

Evaluation Report

6. CONTRACTING

Contract with successful

Tenderer

A contract was signed with the

successful Tenderer

Letter to successful Tenderer

Contract

Letters to unsuccessful Tenderers Unsuccessful Tenderers were duly

notified about the result and the

reasons for not awarding the contract to

them

Letters to unsuccessful Tenderers

Page 82: FIIRRSSTT TLLEEVVEE LL RCCOONNTRROOLL …cfcu.gov.ba/.../02/National-Level-Procedures-Manual... · these programmes are funded by 2 different funding instruments and are hence defined

79

ANNEXIS:

1. ORGANIGRAMME OF THE MINISTRY

2. INTERNAL PROCEDURES OF THE FLCO BIH (LOCAL LANGUAGE)

BIH Control Guidelines IPA Adriatic, Ver. 2, September 2013

http://cfcu.gov.ba/ BIH Control Guidelines for SEE, ver. 3 – July 2013

BIH Control Guidelines for MED, Ver. 1

from September 4, 2013

Interna procedura o kontroli javnih nabava,

Ver. 1.8.2013. (LOCAL LANGUAGE)

3. Instruction on how to return the funds, reimbursement of funds and recording in the General

Ledger paid less grant funding from the EC, endorsed by the Minister of Finance and Treasury,

No 08-02-1-9583-1/12 from November 11, 2012 (LOCAL LANGUAGE)