Upload
jackson-a-plus
View
36
Download
14
Embed Size (px)
Citation preview
GSM BSS Swap Guide-20060430-A-1.0 For internal use only
Document
number
Product
numberGSM BSS
Intended forGBSS engineers and
GSM RNO engineers
Product
version
Edited for GSM Product/RNO GEODocument
number
GSM BSS Swap Guide
Prepared byChen Xinting, Yang Jie,
Fan Kai, and Yi HongweiDate 2006-03-02
Reviewed by Si Fazhong, etc. Date
Reviewed by Date
Approved by Date
Huawei Technologies, Co., Ltd.
All rights reserved
2023-04-27 HUAWEI Confiential Page 1 of 117
GSM BSS Swap Guide For internal use only
Revision RecordData Revision Version Version Description Author
2006-02-22 V1.0 Initial Version Chen Xinting, Yang Jie, Fan Kai, and
Yi Hongwei
2023-04-27 HUAWEI Confidential Page 2 of 117
GSM BSS Swap Guide-20060430-A-1.0 For internal use only
Table of Contents
Chapter 1 Swap Principle and Strategy..............................................................................................81.1 Huawei Network Swap Experience...........................................................................................81.2 General Swap Principle...........................................................................................................91.3 Swap Implementation Strategy.................................................................................................91.4 Swap Procedure...................................................................................................................... 9
Chapter 2 Network Information Collection and Evaluation..............................................................132.1 Network Information Collection.............................................................................................13
2.1.1 Basic Information of the Original Network...................................................................132.1.2 Basic Needs and Functions of the Original Network.......................................................182.1.3 Basic Equipment Information of the Original Network...................................................192.1.4 RNP Data of the Original Network...............................................................................232.1.5 Core Network KPI of the Original Network..................................................................252.1.6 Transmission Networking Information of the Original Network......................................262.1.7 Power Supply Configuration of the Original Network....................................................282.1.8 Abnormal Network Information and Customer Complaints.............................................292.1.9 Customers’ Engineering and Maintenance Capability.....................................................292.1.10 Acceptance Information............................................................................................30
2.2 Analysis and Evaluation of the Original Network.....................................................................302.2.1 DT Evaluation............................................................................................................302.2.2 Network KPI Evaluation.............................................................................................312.2.3 Other Evaluations.......................................................................................................322.2.4 Confirmation of the Acceptance Indicators after Network Swap......................................36
Chapter 3 Project Survey, Equipment Installation and Test.............................................................363.1 Survey and Design................................................................................................................36
3.1.1 Survey of BSC/PCU Room.........................................................................................373.1.2 BTS Survey...............................................................................................................393.1.3 M2000 Survey...........................................................................................................433.1.4 Project Design............................................................................................................44
3.2 Hardware Installation............................................................................................................453.2.1 Goods Preparation......................................................................................................453.2.2 BSC Installation.........................................................................................................463.2.3 Huawei PCU Installation.............................................................................................463.2.4 BTS Installation.........................................................................................................463.2.5 M2000 Installation.....................................................................................................483.2.6 Removing the Equipment of the Original Network.........................................................48
3.3 GBSS Test........................................................................................................................... 483.3.1 BSC Test Points.........................................................................................................483.3.2 CDB/CBC Test..........................................................................................................493.3.3 PCU Test................................................................................................................... 503.3.4 BTS Test................................................................................................................... 513.3.5 M2000 Test...............................................................................................................523.3.6 Equipment Function Acceptance..................................................................................53
Chapter 4 Network Swap Planning and Network Parameters...........................................................544.1 Network Swap Planning........................................................................................................54
4.1.1 Whole Network Planning............................................................................................544.1.2 Network Swap Planning Data Design...........................................................................574.1.3 RNP Data Review......................................................................................................61
4.2 Network Interconnection Parameter Confirmation....................................................................614.2.1 A-interface Interconnection Parameters........................................................................614.2.2 Gb-interface Interconnection Parameters.......................................................................63
4.3 Customer Suggestion............................................................................................................64
2023-04-27 HUAWEI Confiential Page 3 of 117
GSM BSS Swap Guide For internal use only
Chapter 5 Network Swap Preparations............................................................................................655.1 Network Swap Solution Design and Review............................................................................65
5.1.1 Overall Swap Solutions...............................................................................................655.1.2 Designing and Reviewing the Solutions Used to Swap Network Elements........................655.1.3 Swap Plan and Customer Confirmation.........................................................................66
5.2 Network Swap Preparations...................................................................................................665.2.1 Coordination Meeting and Customer Cooperation..........................................................665.2.2 Integration Difficulty Analysis and Emergency Measures...............................................675.2.3 Personnel Arrangement, Vehicle Arrangement, Test Tool, Installation Tool, Equipment Preparation, and Emergency Measure....................................................................................675.2.4 Version Confirmation and License Application.............................................................705.2.5 Swap Data Design and BTS Swap Preparation..............................................................715.2.6 Pre-integration...........................................................................................................73
Chapter 6 Swap Implementation.....................................................................................................756.1 Network Integration on the Swap Day.....................................................................................75
6.1.1 Network Integration Schedule......................................................................................756.1.2 Checking Each Network Element (Before Integration)...................................................776.1.3 BSC Integration.........................................................................................................786.1.4 MSC-Related Work during BSC Integration..................................................................796.1.5 BTS Integration..........................................................................................................806.1.6 PCU Integration.........................................................................................................84
BSC overall performance measurement............................................................................................84G-Abis interface performance measurement.....................................................................................84Pb interface performance measurement............................................................................................84
6.1.7 Network Optimization Arrangement.............................................................................856.2 Emergency Measures and Changback for Network Integration..................................................85
6.2.1 Emergency Measures..................................................................................................856.2.2 Changeback Principle Description................................................................................866.2.3 Changeback Measures................................................................................................87
6.3 Network Monitoring on the Day Next to Swap.........................................................................87
Chapter 7 After-Swap Network Quality Monitoring and Optimization.............................................887.1 Online Equipment Problem Handling......................................................................................88
7.1.1 Hardware Problem Handling.......................................................................................887.1.2 Complaint Handling...................................................................................................897.1.3 Alarm Analysis..........................................................................................................89
7.2 Network Monitoring and Optimization....................................................................................907.2.1 OMC Traffic Statistics Analysis...................................................................................907.2.2 Analysis of NSS-Related Radio Indicators....................................................................927.2.3 Analysis of Area DT and CQT and Related Suggestions.................................................937.2.4 After-Swap Network Maintenance...............................................................................937.2.5 Network Optimization................................................................................................93
7.3 Customer Communication.....................................................................................................94
Chapter 8 Swap Acceptance and Document Transformation............................................................948.1 Preliminary Acceptance.........................................................................................................948.2 Network Performance Acceptance..........................................................................................948.3 Document Transformation.....................................................................................................95
Chapter 9 Swap Risk Analysis.........................................................................................................959.1 Network Information Collection and Risk Evaluation...............................................................95
9.1.1 Risks Caused by Inadequate Understanding of the Performance of the Original Equipment959.1.2 Risks Caused by Inaccurate Information.......................................................................959.1.3 Case Study................................................................................................................96
9.2 Project Survey, Equipment Installation and Commissioning......................................................989.2.1 Interconnection Risks.................................................................................................989.2.2 Problems Related to Interconnection of GBSS and G9...................................................989.2.3 Risks Concerning BTS Survey.....................................................................................989.2.4 Quality Risks Caused by Project Installation Team’s Engineering Level..........................99
2023-04-27 HUAWEI Confidential Page 4 of 117
GSM BSS Swap Guide For internal use only
9.2.5 Version Risk..............................................................................................................999.2.6 Case Study..............................................................................................................100
9.3 Network Planning and Optimization Risk..............................................................................1019.3.1 Risk Related to Network Indicators............................................................................1019.3.2 Coverage Risk..........................................................................................................1029.3.3 Inadequate Test before Swap.....................................................................................1029.3.4 Frequency Planning Risk...........................................................................................1039.3.5 Risk Related to Traffic Volume.................................................................................1039.3.6 Case Study..............................................................................................................103
9.4 BSS Integration and Monitoring Risk....................................................................................1049.4.1 Risk Relate to BSS Integration Solution......................................................................1049.4.2 Risk Related to BTS Pre-integration...........................................................................1059.4.3 Risk Related to Transmission Commissioning.............................................................1059.4.4 Risk Related to BTS Integration.................................................................................1059.4.5 Emergency Problems Related to BSC Integration........................................................1069.4.6 Handling of Abnormal Conditions during BTS Integration...........................................1069.4.7 Case Study..............................................................................................................107
9.5 Acceptance Risks................................................................................................................1089.5.1 Risk Related to Customer Communication..................................................................1089.5.2 Risk Related to Acceptance Test before Integration.....................................................1089.5.3 Case Study..............................................................................................................109
9.6 Non-technical Risk Analysis................................................................................................1099.6.1 Risk Related to Contract Items...................................................................................1099.6.2 Risk Related to Project Duration Risk.........................................................................1099.6.3 Management Risk.....................................................................................................1109.6.4 Risk Related to Communication.................................................................................1119.6.5 Risk Related to Contract Implementation....................................................................1119.6.6 Risk Related to Work Flow.......................................................................................1129.6.7 Case Study..............................................................................................................112
Appendix: Reference Document Catalog and Network Integration Checklist...................................1149.7 Reference Document Catalog...............................................................................................1149.8 Network Integration Checklist..............................................................................................114
9.8.1 BSC Service Test.....................................................................................................1149.8.2 GPRS Dialing Test Checklist.....................................................................................1159.8.3 A-interface Dialing Test Checklist.............................................................................1169.8.4 Abis Interface Dialing Test Checklist.........................................................................1169.8.5 BTS Radio Channel Dialing Test Checklist.................................................................117
2023-04-27 HUAWEI Confidential Page 5 of 117
GSM BSS Swap Guide For internal use only
GSM BSS Swap Solution (Template)
Key words: swap, integration, GBSS, network optimization
Abstract:
Compared with the swap documents edited before, this document describes the whole swap
procedures based on the swap experience of the current GBSS (the version is BSC32). As with this
version, the focuses are on the introduction of the specific swap implementation from the perspective
of engineering and the differentiation of the engineering scenarios. In addition, this document also
provides the tips on how to control network quality and what should be paid attention to (especially
the coverage and parameters) during swap. Furthermore, this document gives the risk analysis and
related cases for your reference. In a word, this document can help you improve work efficiency,
avoid unexpected problems, reduce technical requirement on engineers, and ensure swap quality.
2023-04-27 HUAWEI Confidential Page 6 of 117
GSM BSS Swap Guide For internal use only
Preface
What are the characteristics of this document?
Whole swap procedures are described in this document and the focuses are given to four
aspects, including network information collection and evaluation, network optimization,
swap implementation, and risk analysis.
The differentiation of the original network information is available and the information
collected according to the forms provided in this document can meet swap requirement.
Engineering scenarios and detailed swap steps are provided.
Risk analysis and many cases are available.
Delivery according to contract is appreciated.
Control of network swap quality is emphasized.
Swap cases are updated.
How to use this document?Network swap is a systematic project, so it must be implemented according to steps. More
importantly, good planning and network monitoring are necessary.
This document consists of several chapters, but the actual swap process can be divided into
three parts, including network information collection (Chapter 1, 2, and 3), swap
implementation (Chapter 4, 5, and 6), and network monitoring and acceptance (Chapter 7
and 8).
Collecting and evaluating the information of the original network is the most important for a
successful swap. Therefore, the earlier to provide technical service and use this document,
the better for the network swap. Generally, this document must be used after contract
signature but before network swap so that the network information collection and evaluation
can be finished as soon as possible.
The parts for survey, installation and commissioning, and integration preparation are for the
implementation engineers’ reference.
This document can be used as the template of network swap and integration during the
implementation of a swap project.
The parts for RNP and RNO are for the RNO engineers’ reference.
The parts for risk analysis are for project engineers’ reference.
Note:In this document, the “original network” refers to the network need to be swapped but
has not been swapped.
2023-04-27 HUAWEI Confidential Page 7 of 117
GSM BSS Swap Guide For internal use only
Chapter 1 Swap Principle and Strategy
At present, the GSM technology is mature than ever before, and so is the market competition.
Therefore, GSM network swap, especially the swap of the base station system, will surely become
the trend. The GSM network swap is a complex systematic project for the following
considerations:
Multiple operators’ equipments are involved.
The features of the equipments vary with operators.
The network structure will change after swap.
The quality of the swap implementation must be ensured.
The cooperation of different operators’ equipments must be available.
The RNP and RNO level is a great concern during network swap.
The performance of various equipments may be greatly different in the same geographic
environment.
As a leading GSM equipment provider in the world, Huawei has swapped multiple operators’
networks and has acculturated rich experience. Hereunder lists several examples and gives a
general description of the swap strategies.
1.1 Huawei Network Swap Experience
Huawei GSM system has been widely used in the worldwide. By December 2005, Huawei has
swapped 300, 000 TRXs and more than 50,000 BTSs and the equipments of many world-honored
operators are involved, including Motorola, Siemens, Ericsson, Nokia, Bell, Alcatel, Nortel,
Lucent, etc. Huawei has accumulated rich experience in network swap through these projects,
among which the major projects are listed in Table 1-1.
Table 1-1 Major swap projects implemented by Huawei
Country or region Operator Equipment provider of the
original network
Swap scale
Philippines Digitel Alcatel 5893TRX
Nigeria MTN Ericsson 4795TRX
Liaoning Province Unicom Lucent 6241TRX
Indonesia Indosat Siemens 4552TRX
Sichuan Province China Mobile Ericsson 4505TRX
2023-04-27 HUAWEI Confidential Page 8 of 117
GSM BSS Swap Guide For internal use only
Colombia Movil Siemens 1300TRX
Guangdong China Unicom Motorola 4405TRX
Zhejiang China Unicom Nortel 870TRX
Fujian Province China Mobile Nokia 3000TRX
Inner Mongolia China Mobile Nokia 1065TRX
Note: Actually, multiple network elements, such as MSC, HLR, and GPRS part, are involved in
GSM network swap. In this case, you should swap the core network part, and then swap the
base station part.
If network expansion and construction should be performed during the swap, you should swap
the network first so that the smooth transition of the network can be ensured.
The network indicators must be consistent with that specified in the contract for delivery.
1.2 General Swap Principle
The swap of the GBSS is the same as that of other network elements and the following four
principles should be followed:
Security
Excellent quality and low cost
Smooth transition
High efficiency
1.3 Swap Implementation Strategy
From the perspective of the effect against the network, the following strategies can be used for
GBSS swap.
Parallel swap
One-time swap
Batch swap (recommended)
Mixed swap
1.4 Swap Procedure
This document introduces the whole swap procedures, including network information collection
and evaluation, equipment installation and commissioning, network swap planning, integration
2023-04-27 HUAWEI Confidential Page 9 of 117
GSM BSS Swap Guide For internal use only
solution design, swap preparation, integration preparation, after-integration test and optimization,
and swap acceptance. The key tasks are network information collection and swap implementation.
Figure 1-1 shows the whole network swap procedure.
2023-04-27 HUAWEI Confidential Page 10 of 117
GSM BSS Swap Guide For internal use only
2023-04-27 HUAWEI Confidential Page 11 of 117
GSM BSS Swap Guide For internal use only
Figure 1-1 Whole network swap procedures
2023-04-27 HUAWEI Confidential Page 12 of 117
GSM BSS Swap Guide For internal use only
Chapter 2 Network Information Collection and Evaluation
Engineering capability is the key to the success of a swap project. To improve work efficiency and
thoroughly understand customers’ needs, you should collect the related network information
beforehand. This chapter introduces the information needed to be collected before swapping a
network. You can obtain the data through contract review, customer communication, field test, etc.
2.1 Network Information Collection
The following information of the original network must be collected:
Basic information of the network
Basic needs and functions
Basic information on the operation of online equipment
RNP data
Transmission and networking information
Information of power supply configuration
Abnormal network information and customers’ complaints
Customers’ engineering and maintenance capability
2.1.1 Basic Information of the Original Network
I. Network Structure of the Original Network
The network structure of the original network should contain the basic information of the main
equipments, such as the MSC, BSC (PCU), and the overall BTS layout. If packet service is
available in the original network, the information of the packet equipments, such as SGSN and
GGSN, should be included. If the core network needs to be swapped, the basic networking
information of the HLR and MSC should be included. In addition, the description of the
configuration and capacity of the network should also be provided based on the networking
diagram. If possible, you can configure the BTS layout created by MAOINFO.
If you have an all-round understanding of the above information, you can know more about the
total network and see more clearly the order and difficulty of the swap project.
Figure 2-1 shows the schematic drawing of a GSM network.
2023-04-27 HUAWEI Confidential Page 13 of 117
GSM BSS Swap Guide For internal use only
Figure 2-1 Schematic drawing of a GSM network
In the urban area of XX city, the operator S has 2 MSCs. MSC1 can accommodate 270,000 users
and has 5 BSCs. They are S BSC2, S BSC5, S BSC 6, S BSC 12, and Huawei BSC2, responsible
for the covering eastern XX district, XX district, and XX road. MSC2 can accommodate 300,000
users and has 6 BSCs. They are S BSC4, S BSC7, SBSC8, S BSC11, S BSC20 and SBSC4,
responsible for covering XX district and XX road.
In the urban area of XXX city, there is 1 Huawei MSC. MSC4 can accommodate 270,000 users
and has 6 BSCs. They are S BSC1, S BSC3, S BSC10, Huawei BSC1, Huawei BSC5, and Huawei
BSC6, responsible for covering XX district and XX road.
II. Configuration Information of the Original Network
The configuration information of the original network includes equipment configuration
information, capacity information, provider information, BSC home information, BTS number
under BSC, TRX number, etc. For details, see the following two tables.
Table 2-1 MSC information in XXX city
No.
Equipment
Name
Original
Capacity Operator Version BSC Carried
1 MSC1 270,000 S SR9 BSC2, 5, 6, 12, HWBSC12
2 MSC2 300,000 N SR9 BSC4, 7, 8, 11, 20, HWBSC4
3 MSC4 270,000 Huawei G6 BSC1, 3, 10, HWBSC1, 5, 6
4 MSC3 220,000 E R12 BSC9, 13, 14, 18, 19, HWBSC3
Table 2-2 BSC information in XXX city
No. BSC Operator BTS number TRX Coverage area LAI
2023-04-27 HUAWEI Confidential Page 14 of 117
GSM BSS Swap Guide For internal use only
Name number
1 SBSC12 S 44 197
2 HWBSC2 Huawei 47 317
3 HWBSC4 Huawei 30 220
III. OMC Networking Diagram and Network Management System Information
For the networks large in size and the network elements are distributed in vast areas, the OMC
networking is often complex. In this case, multiple routers and switches are needed for
communication. Sometimes the original semi-permanent connection equipment or timeslot
insertion equipment can be used for the networking. Therefore, you are suggested to collect the
OMC networking diagram of the original network. If the original OMC networking is simple and
all the equipments are concentrated in a place, you can use simple local area network for TCP/IP
communication. But before that, you should understand the composition of the local area network.
In a word, it is a must for you to understand the original network management information and the
accessibility of the third party’s equipments.
Before swapping a network, you should have an overall understanding of the following contents:
The topology of the network
The accessibility of the third party’s equipments for alarming and traffic statistics
The formats and interface standards of the original traffic statistics and alarming data
(Generally, TCP/IP is used for data connection and FTP is used for data transmission)
The types of the wide area network, including ISDN, DDN, X.25, frame relay, etc.
The components of the network, including HUB, exchange, router, ATM exchange, WAN
exchange, access server, timeslot integration equipment, etc.
The performance of the network, especially the indicators about bandwidth and delay.
Figure 2-1 shows the OMC networking diagram used in XXX area.
2023-04-27 HUAWEI Confidential Page 15 of 117
GSM BSS Swap Guide For internal use only
Figure 2-1 The OMC networking diagram in XXX area
IV. Traffic Model of the Original Network
The traffic model of the original network should be collected.
Traffic model is the basic data for network capacity planning. Generally, the total network
capacity is predicted according to mathematic models. First the traffic model is used to calculate
the traffic volume of the system, and then the structure of the PLMN can be used to estimate the
traffic volume present of interface, while the traffic volume of each interface can be used to
decide the configuration of the voice circuits and signaling links at the interfaces. Finally, the
TRX channel configuration of the base station can be decided.
Traffic model will be greatly affected by social environment, economy, and main user groups and
will change with the growth of user number. Customers’ RNP departments are responsible for
providing the traffic model, so there is no unified standard. At present, the traffic model for voice
service is mostly emphasized.
Table 2-1 introduces the traffic model for the voice service of a domestic GSM network.
Table 2-1 Traffic model for GSM voice service (a domestic GSM network)
Item Traffic model-1 Traffic model-2
Busy-hour Erlang per subscriber 0.018 0.018
Average call hold time 48 48
Calling mobile subscribers 39 39
Called mobile subscribers 57 57
Calls made by each mobile subscriber at busy
hour1.35 1.35
Call connected ratio 80% 80%
2023-04-27 HUAWEI Confidential Page 16 of 117
GSM BSS Swap Guide For internal use only
Mobile subscriber location update at busy hour 1.21 2.61
Secondary page ratio caused by called mobile
subscriber20% 20%
Handovers for each call made by mobile
subscriber1 1.7
Short messages send by each mobile subscriber
at busy hour128 100
Short messages received by each mobile
subscriber at busy hour384 211
Ratio of mobile subscribers roaming inside to
total mobile subscribers10% 10%
Ratio of mobile subscribers roaming outside to
total mobile subscribers10% 10%
Mobile subscriber activation ratio 100% 100%
Traffic distribution
Mobile-Mobile 40% 40%
Fix-Mobile 36% 36%
Mobile-Fix 24% 24%
Table 2-2 introduces the traffic model for the voice service of a foreign GSM network.
Table 2-2 Traffic model for GSM voice service (a foreign GSM network)
Parameters Value Remark
Average Call Hold Time 72s –
Erlang per Subscriber 0.02 –
BHCA 0.5MO+0.5MT –
Mmobile to Mobile 60% –
Mobile to Other PLMN – –
Mobile to PSTN 20% –
PSTN to Mobile – –
SMS Numbers/BH/SUB(MO) 1 –
SMS Numbers/BH/SUB(MT) 1 –
Ratio of IN subscribers 95% –
location update numbers/BH/SUB 1.5 –
location update numbers/BH/SUB(to HLR) 0.3 –
Authentication numbers/BH/SUB 0.3 –
Table 2-3 introduces the traffic model for packet data service.
2023-04-27 HUAWEI Confidential Page 17 of 117
GSM BSS Swap Guide For internal use only
Table 2-3 Traffic model for packet data serviceItem Value Remark
GOS of circuit service 2% For reference
Busy-hour Erlang per subscriber for circuit service 0.03 For reference
GPRS user penetration rate 50.00%
IP layer bandwidth for each (BYTE/s) 2500
Bandwidth for each GPRS channel (BYTE/s) 2000
Busy-hour bandwidth for each GPRS subscriber (bps) 400
GoS of GPRS service 2%
Note:The increase of the SMS will raise the load on the NO.7 signaling link. Therefore, if the SMS
takes a larger ratio, the configuration of the NO.7 signaling link should be adjusted accordingly;
otherwise the SDCCH and NO.7 signaling link will be congested.
V. Customers’ Charging Setting Information
Generally, you can collect the customers’ charging setting information from their market
departments. There information to be collected includes the followings:
Time for free of charge
Some operators set the time for free call. Generally, in this period of time, the traffic volume
will grow rapidly and thus network congestion may be caused.
Monthly fee policies, including monthly fee for the calls made within the same network,
monthly fee for called services, and monthly fee for packet data service.
Charging policies for SMS
2.1.2 Basic Needs and Functions of the Original Network
You should analyze the basic needs and functions of the network according to the technical
proposals made in contracts, especially you should check if the needs and functions that have been
realized in the original network can be realized by Huawei BSS and if they are supported by
Huawei software. If you find any problem, contact the technical supports as quickly as possible.
Table 2-1 lists the basic services and functions of the original network.
Table 2-1 Basic services and functions of the original network
Item Content Remark
Voice version FR EFR HR AMR –
2023-04-27 HUAWEI Confidential Page 18 of 117
GSM BSS Swap Guide For internal use only
Encryption setting No A50 A51 A52 –
Circuited data service Not support 2.4K 4.8K 9.6K –
TFO Support Not support –
Cell broadcast Support Not support Cell name,
advertisement,
whether reports
LCS Support Not support –
SDCCH dynamic allocation Support Not support –
Mutual aid between main
BCCHs
Support Not support –
MNC digit extension
function
Support Not support –
Concentric cell Support Not support –
CO-BCCH Support Not support –
GS interface Support Not support –
Extended cell Support Not support –
GPRS/EDGE Support Not support –
BSC/BTS intra-exchange Support Not support –
Authentication – – –
Paging mechanism LAC paging LAC and CI
paging
Other paging
2G/3G handover Support Not support –
Acoustic Echo Canceller Support Not support
Noise Suppression Support Not support
2.1.3 Basic Equipment Information of the Original Network
I. GSM Protocol Standard Phase Version
For A-interface, the phase versions are PHASE2+, PHASE2, and PHASE1.
2023-04-27 HUAWEI Confidential Page 19 of 117
GSM BSS Swap Guide For internal use only
Note:To avoid that some functions cannot be realized normally after interconnection, you should check
the protocol phase version supported by the original equipment if the original network has been
there for a long time. You are suggested to use singling analyzer to collect the messages sent
across the A-interface and Abis interface at busy hour and send them to technical supports for
verification.
II. Software Version Information
Table 2-1 lists the software version information of some network elements.
Table 2-1 Software version information of MSC, BSC, and BTSNo. Equipment Operator Type Software version Remark
1 MSC1 S – SR9 –
2 MSC4 Huawei G6 R003 –
3 BSC2 S – SR9 –
4 BSC1 N – R10 –
5 BTS N ULTRASITE DE21 –
III. BSC Configuration Information
Table 2-1 lists the BSC configuration information
Table 2-1 BSC configuration information
BSC Location OperatorBTS
number
TRX
number
Half rate
TRX
number
EDGE
TRX
number
Coverage
area
Slave
MSC
SBSC12 – S 44 197 100 90
Urban area
1 MSC3
HWBSC2 – Huawei 47 317 231 123
Urban area
2 MSC2
HWBSC4 – Huawei 30 220 125 46
Suburban
area MSC3
IV. BTS Configuration Information
Table 2-1 lists the BTS configuration information.
2023-04-27 HUAWEI Confidential Page 20 of 117
GSM BSS Swap Guide For internal use only
Table 2-1 BTS configuration information
BTS Location Operator Type
Cell
configuratio
n
TRX
number
Transmission
mode
E1
number
Slave
BSC
BFM
K XX city S R11 S222 6 Micro wave 1 MSC3
KPR
I XX island Huawei 3002C O1 1 Satellite 1 MSC2
CBI
O XXX Huawei 312 S3443 14 Optical fibre 2 MSC3
V. TRX Configuration, Combiner Information, Set-top Power
Table 2-1 TRX configuration, combiner information, set-top powerBTS
TypeOperator
Configurati
onCombiner Type
Combination
ModeCombiner loss
Set-top
Power
A9100 A S666 ANC+ANY 4-to-1 8dB 7.1W
BTS30 Huawei S222 CDU 2-to-1 4.5 dB 21.4W
BTS312 Huawei S666 2CDU+SCU Concentric cellOverlay:8dB;
underlay:4.5dB
Underlay
:21.4W;
Overlay:
9.5W
Note:You are suggested to select the BTSs with typical configuration and perform field verification of
the set-top power. In addition, you should check if the partner has installed the lightening
protector.
VI. Tower Amplifier Information
If the tower amplifier is configured for the original BTS, you should collect the tower amplifier
information, as listed in Table 2-1.
2023-04-27 HUAWEI Confidential Page 21 of 117
GSM BSS Swap Guide For internal use only
Table 2-1 Tower amplifier information
Specification Operator TypeFrequency
band
Receiver
gain
Working
voltage
Working
current
Power
supply
mode
– – Triplex 900 12dB 12DC 100-200mA
CDU
feeder
– – Duplex 1800 – – – –
– – Simplex – – – – –
VII. Feeder Configuration Principle
The feeders 7/8 and 5/4 are most commonly used. Some operators also use the feeder 18/8.
VIII. BTS Grounding Principle and Feeder Grounding Principle
The BTS grounding principle and feeder grounding principle vary with operators. For example,
the operators in Indonesia have no requirement on feeder grounding, but the operators in Iran do
not allow the feeder to be connected with the tower directly.
IX. Indoor Coverage Distribution System Information
Indoor coverage is used to improve the mobile communication quality for indoor users. The
principle of the indoor coverage system is to use the indoor antenna distribution system to evenly
distribute the signals from the BTS in an indoor environment. At present, the following solutions
are used for indoor coverage.
Repeater + distribution antenna
Macro cell + distribution antenna
Micro cell + distribution antenna
Mini-micro cell + distribution antenna
Mini-micro cell only
You should pay attention to collect the indoor coverage solution used in the original network. If
distribution antenna system is used, you should especially know the feeder configuration principle
of the distribution antenna system and check if there is diversity reception.
X. Repeater Information
The repeater is used in vast areas to cover the indoor dead zones and is the coverage extension of
the surrounding BTSs. The types of repeaters include wireless frequency selection repeater,
optical frequency selection repeater, wireless wide band repeater, and optical wide band repeater.
You should have an overall understanding of the repeaters in the original network and pay special
attention to the repeater location, transmit power, channel number setting, antenna configuration,
etc.
2023-04-27 HUAWEI Confidential Page 22 of 117
GSM BSS Swap Guide For internal use only
Table 2-1 lists the repeater information should be collected.
Table 2-1 Repeater information
Provider and
specification
Type
Band or
Channel
Selective
Power
Downli
nk
(Uplink
)
Gain
/dB
Downli
nk
(Uplink
)
Noise
Figure
/dB
Downli
nk
(Uplink
)
Order
Intercep
t
/dBm
Downli
nk
(Uplink
)
No.
of
Channe
ls
Size
/mm
AFL GSM 900 Band 1,5,10,20
,25 W
30,50,80,
95
(30,50,8
0,95)
4.5
(4.5)
40,47,50,
54
(40,47,5
0,54)
N/A 460 x
550 x
220
(10W)
Allgon AR 120
GSM 900
Channel 24
(20)
dBm
40-60 <6 2 230 (W)
285 (H)
120 (D)
Mikom MR 340 Channel 32 dBm
(2channe
l)
28 dBm
(4channe
l)
85-89
(2channe
l)
82-86
(4channe
l)
6-8 2
channel
modules
per
cabinet
[2]
425 (W)
255 (H)
110 (D)
XI. Movable BTS Information
Movable BTSs are often installed in the cars or in the containers that can be easily moved. The
satellite or micro wave is used to transmit the signals for movable BTSs, so movable BTSs are
often used in emergent communication situations. You should have an overall understanding of
the configuration information of the movable BTSs in the original network and pay special
attention to the TRX configuration, transmission mode, and antenna configuration.
2.1.4 RNP Data of the Original Network
I. Proejct Parameters
Hereunder lists the project parameter information
BTS information: BTS name, BTS number, BTS configuration, equipment specification
2023-04-27 HUAWEI Confidential Page 23 of 117
GSM BSS Swap Guide For internal use only
Cell information: cell number, longitude, latitude, CGI, BSIC, frequency band, channel
number, frequency hopping, cell name
Antenna and feeder system: antenna type, antenna gain, polarization mode, half-power
angle, electrical tilt, frequency scope, mechanical tilt, antenna height, azimuth, down tilt,
feeder length, diversity mode.
Environment information: city, height above sea level, collocation site, coverage area (urban
area or suburban area)
For more information, see RPO201-05 project parameter table (G).
II. Radio Parameters of the Original Network Providers and Special Functions
The radio parameters of the original network providers include cell parameter, system parameter,
handover, power control, access parameter, frequency hopping, adjacent cell, etc.
First you should obtain the RNP parameter configuration files used by the original network
providers from the customer, and then use the parameter conversion tool to convert these
parameters into the ones used by Huawei.
For more information, you can consult technical support engineers and related operation guides.
III. Original Network Traffic Statistical Data and KPI Formula
The original traffic statistical files vary with equipment providers, but they can be converted into
excel documents by corresponding conversion tools. Therefore, you can obtain such files from
customer. For cell-level indicators, the busy-hour data in 7 days should be collected. For total
network indicators, you can use the data reported on the customer maintenance day (one month of
data is needed).
Generally, the following KPIs will be contained in a contract:
TCH drop rate
SDCCH drop rate
TCH congestion rate
SDCCH congestion rate
Handover success rate
TCH assignment success rate
Call setup success rate
Call success rate
Paging success rate
Radio quality
These KPIs are obtained from some basic indicators through certain calculations and they reflect
the statistical points used by the original equipment provider. You are suggested to collect the
remark files of the KPI formulas from customers.
2023-04-27 HUAWEI Confidential Page 24 of 117
GSM BSS Swap Guide For internal use only
IV. Network Planning Principle
For frequency planning principle, you should understand the frequency resource, frequency reuse
pattern, reserved channel numbers, etc.
For cell naming principle, you should understand the composition of cell name, the matching
relationship between cell sequence and azimuth.
For CGI numbering principle, you should understand the matching relationship between the
MCC, MNC, LAC and the areas, and the CI numbering scheme as well.
For BSIC naming principle, you should know the optional scope of the BCC and NCC.
For VIP area, such as the coverage hot-spots, capacity hot-spots, and key organizations, you
should know the related agreements.
For more information, obtain the related documents from the technical support engineers.
V. Channel Configuration
You should know the principles used to configure the CCCH, SDCCH, and PDCH in the original
network. In addition, you should also know the usage of half rate and AMR.
VI. MSC and RNP-related Information
You should collect the following information:
MSC paging modes (paging according to LAC or CGI; TMSI paging, IMSI paging, or mixed
paging; paging times, paging interval; or total network page)
Location update time at the network side
Voice support version
Encryption algorithm selection
Location update success rata and paging success rate
The settings of T305 and T308 have a great effect on call drop rate.
2.1.5 Core Network KPI of the Original Network
I. MSC KPI of the Original Network
The MSC KPI of the original network should be checked. Generally, you can check the following
items:
Subscriber number ratio and intelligent subscriber ratio of the local VLR
Connective rate between MSCs
CPU seizure rate
Traffic volume per line
Traffic load per link
Paging success rate
Location update rate
Inter-MSC handover success rate
2023-04-27 HUAWEI Confidential Page 25 of 117
GSM BSS Swap Guide For internal use only
Short message sending success rate
Average duration
BHCA
II. PS KPI of the Original Network
The PS KPI of the original network should be checked. Generally, you can check the following
items:
ATTACH success rate
PDP activation rate
Packet paging success rate
Attached subscriber number
Average attach time
Average PDP activation time
III. Maximum Rate for User Subscription
The maximum rate for user subscription is the most important user subscription parameters in
HLR. If the peak throughput for the SIM subscription is incorrectly set, the EDGE rate will be
slow. Hereunder gives an example.
A user complained that the data service of the PCU MSC9 was unstable and the MSC9 rate
ranged from 60 to 70 Kbps (the rate is far slower than the theoretical value) when 3 PDCHs were
activated simultaneously. It is found later that the peak throughput was set to only 8000 octets/s
(64Kbps) for SIM subscription. Therefore, the peak throughput the user can enjoy is 64Kbps
during data transmission. After changing the peak throughput to 64000 Octets/s in the subscription
information, engineers found that the average download rate was increased to 150Kb. Thus, this
problem was solved.
2.1.6 Transmission Networking Information of the Original Network
I. BTS Transmission Networking Information
You should collect the following BTS transmission networking information:
The networking modes in common use, including star networking, tree networking, chain
networking, ring networking, and mixed networking, in which the chain networking and ring
networking should be paid special attention to.
If the operators are responsible for maintaining the transmission network by their own or
they rent other operators’ transmission network.
If the original transmission network has adequate capacity and if another one transmission
line can be added to the original site.
II. E1 Reuse Ratio of the Typically-configured BTS
You should pay attention to the E1 configuration of the BTSs with big configuration and the
maximum TRXs that one E1 can support. Generally, the modes include 10:1, 12:1, and 15:1.
2023-04-27 HUAWEI Confidential Page 26 of 117
GSM BSS Swap Guide For internal use only
III. E1 Types
Twisted pair (120 Ω) and coaxial cable (75 Ω) are in common use. For the later one, its connector
types include SMB and BNC.
IV. Microwave Transmission Equipment
If microwave transmission equipments are wilily used in the original network, you should focus
attention on checking the bit error and synchronization function of the equipment, the
transmission alarm, and the alarm for clock out-of-synchronization.
V. Optical Fiber Information
Check if the optical fiber is directly connected to the BTS. If yes, the type of the optical fiber and
the type of the connector should be paid special attention to.
VI. Satellite Transmission Equipment
The information about satellite transmission equipment needs to be collected is listed below:
Specifications and types of the satellite transmission equipment (VSAT or satellite
MODEM)
Leased according to bandwidth or timeslot
Interfaces supported (Abis, Pb, Gb, A, Asub)
Stability requirement of transmission (BTS and satellite), average failure time and
interruption time per year)
Circuit accuracy of satellite transmission (bit error rate)
VII. HDSL and SDSL Transmission Equipment
With the help of twisted pair and digital modulation, HDSL and SDSL transmission technologies
can be used to transmit 2M signals. The disadvantage is that the transmission may be easily
interrupted, and thus the BTS cannot necessarily run normally. Considering the cost, some
operators will use this transmission mode. When swapping a network, therefore, you should check
the stability of the transmission equipment used in the original network.
VIII. Timeslot Consolidation Equipment
The timeslot consolidation equipment can enhance the utilization rate of E1. That is, several BTSs
can share 1 E1, or they can also use the E1 of the other network. For a swap project, you should
especially check the allocation of the timeslots.
IX. Transmission Compression Equipment
To save transmission cost, some operators will use transmission compression equipment to
compress the data flow transmitted through E1. Therefore, to ensure that Huawei equipment can
work normally after swap, you need to collect the compression theory, performance restriction,
and compatibility of the compression equipment and send the information to the technical support
engineers. Whether the equipment is compatible with Huawei BSS should be confirmed as early
as possible.
2023-04-27 HUAWEI Confidential Page 27 of 117
GSM BSS Swap Guide For internal use only
X. BTS Concatention and Transmission Concatention
The information about BTS concatenation and transmission concatenation should be collected,
because the information is used to design concatenation data and decide the BTS swap order.
2.1.7 Power Supply Configuration of the Original Network
Table 2-1 lists the information about the power supply configuration of the original network, and
all the information should be collected.
Table 2-1 Information about the power supply configuration of the original network
Item Content Remark
Voltage of AC power supply – 110V, 220V, 110V (double live line)
Frequency of AC power
supply– 50HZ, 60HZ
AC phase – 3-phase, single-phase
Type of AC socket –English system, European system, American
system
Mains supply –
If the power supply always breaks, the
battery discharge will frequently occur. In
this case, the life expectancy of the battery
will be shortened and the BTS will be out of
service.
Diesel configuration –The power is twice that of the load, in the
unit of KW.
Working hours of the diesel –In the unit of hour, depending on the fuel
configuration.
Capacity of AC power
distribution box– In the unit of KW.
Voltage of DC power – +24V.-48V
Capacity of rectifier – In the unit of KW
Capacity of battery – In the unit of Ah
Feeding duration of battery –In the unit of hour, depending on battery
capacity.
Colour of power cable –
Pay attention to customers’ special
requirements, especially the grounding
cable.
Diameter of power cable –Pay attention to the diameters of the DC
power cables of BSC and BTS equipment.
Lightning requirement on
power supply– Often 50KA
Lightning requirement on – Often 5KA
2023-04-27 HUAWEI Confidential Page 28 of 117
GSM BSS Swap Guide For internal use only
transmission
Grounding requirement –Joint grounding; BTS < 5Ω; exchange room
< 1Ω
Whether to use solar energy
for power supply–
Pay attention to the solar radiation, the total
power supply of battery array, and the
capacity of the battery.
UPS configuration –
Pay attention to the capacity of UPR (in the
unit of KVA).
Types: one-in and one-out; three-in and one-
out; three-in and three-out.
Inverter configuration – Pay attention to the rated power
Power supply mode of
outdoor BTS– Mains, diesel, and solar energy
2.1.8 Abnormal Network Information and Customer Complaints
I. Network Failures and Alarming Information
The following failures and alarms should be paid special attention to:
A-interface/Abs interface transmission alarm
BTS power supply alarm
No.7 signaling break alarm
II. Customer Complaints
The complaints made by the customers in the latest month should be recorded and categorized;
especially the problems concerning the coverage in hot areas and the problems that are mostly
complained by customers should be checked. Generally, the following aspects deserve your
attention:
The signals received by MS are weak and fluctuate greatly.
The subscriber is not in the service area.
The voice quality is poor. There are noise and one-way audio.
Call drop occurs easily.
The complaints about service failures, such as one-way audio, cross talking, call drop,
incoming call failure, outgoing call failure, are made frequently.
There are complaints about PS service.
2.1.9 Customers’ Engineering and Maintenance Capability
The following capabilities should be paid attention to, because they are references for the design
of network integration solutions.
Capability to adjust the transmission ports
2023-04-27 HUAWEI Confidential Page 29 of 117
GSM BSS Swap Guide For internal use only
Capability to adjust the core network data
Capability to adjust BSS network data
Capability to maintain BSS network
Capability to implement projects and maintain organizational structure
2.1.10 Acceptance Information
The acceptance should be performed according to contract. If there are vague descriptions or the
committed indicators are abnormally high in the contract, you need to communicate with the
customer for the confirmation of the acceptance mode and procedures in advance. The agreement
on acceptance time, place, personnel, standard, cases, documentation, and equipment should be
reached with the customer.
2.2 Analysis and Evaluation of the Original Network
2.2.1 DT Evaluation
I. Principle
The DT deserves special attention, because the DT results can be used to understand the operation
of the network and decide the DT line after the swap of the network. In addition, the DT results of
the original network can work as comparative references for the swap. The roads covered by the
major lobes of the cells should be chosen as DT lines and the DT lines should cover all the cells of
the network. Note that the test should be performed at the busy hours during daytime.
II. Area DT
The area DT aims to obtain the coverage signal level, conversation quality, handover, and call
drop in the swap areas. In addition, the BTS distribution and coverage weakness of the original
network should be obtained through area DT.
III. DT for Main Roads and VIP Areas
The main roads and VIP areas should be specially tested, especially the handovers occurred on
main roads should be tested, because the test results will be the references for coverage
comparison and network optimization after swap.
IV. DT Data Analysis
The DT data should be carefully analyzed. For example, you should verify the longitude and
latitude of the BTS, the direction of antenna, and the cell parameters. In addition, you should also
check if the antenna feeder is inversely connected and if there is cross coverage. Also the reasons
for call drop and abnormal handover should be analyzed.
V. DT for Indoor Distribution System
If the Bess to be swapped are connected to an indoor distribution system, you need to use the
corresponding software that supports indoor test. Generally, you should get the permission for
2023-04-27 HUAWEI Confidential Page 30 of 117
GSM BSS Swap Guide For internal use only
entrance before the indoor coverage test. It is better to obtain the plan view of the building
beforehand.
All parts of the building, including upper floors, middle floors, and lower floors, should be tested.
Wrap test should be applied to corridor, meeting room, and offices during pace test. Note that the
outer walls of offices and the areas near windows should be tested.
The test items include signal level, conversation quality, cell reselection at the entrance and exit,
and handover.
For details, refer to the related guides about indoor coverage system acceptance.
A test analysis report is required after the completion of whole test.
In addition, you can also obtain the related references from the technical support engineers.
2.2.2 Network KPI Evaluation
I. Difference of KPI Formulas
The KPI formulas used by Huawei are different from that used by the original network equipment
provider in some aspects. At present, each equipment provider has the ability to design the traffic
statistics and KPI formulas according to customer need, so the statistical points of other providers’
Kips may be different from that of Huawei Kips. Therefore, a full understanding of the original
network (especially the KPI formulas and actual indicators) is quite necessary.
Take the replies made by various equipment providers in an operator’s GSM statistical system for
example; the calculation results of each provider are almost the same. For details, seek help from
the technical support engineers.
You are recommended to measure the paging success rate at MSC side and that measured at the
BSS side should work as a reference only. Before selecting the corresponding Huawei statistical
indicators, you should analyze the actual statistical scope of the Kips of the original network
based on the evaluation of the definition of the statistical points used by the original network
equipment provider. If no corresponding indicator is found, you need to communicate with the
customer for other ones according to the interests of Huawei.
II. Evaluation Principle
The traffic statistics exported by the original network should be used for evaluation. The
evaluation aims to verify if the indicators provided by the customer are real. And the evaluation
results are used as a comparative reference after swap. You can use the customer’s network
maintenance report. If necessary, you can use related test analyzer for the evaluation.
III. Evaluation of Indicators about Voice, Signaling, and Capacity
The traffic volume, SDCCH congestion rate, TCH congestion rate, paging times during busy
hours, and call setup success rate should be evaluated for the understanding of the traffic
distribution of the network. You should pay special attention to the signaling flow at the edges of
location areas. And the pages made during busy hours also deserve your attention.
2023-04-27 HUAWEI Confidential Page 31 of 117
GSM BSS Swap Guide For internal use only
IV. Evaluation of Quality Indicators
The quality indicators, including call drop, handover, immediate assignment, interference, RQ,
etc, should be evaluated. You need to find out the Bess that have great effect against the total
network indicators and the areas where the network quality is quite poor.
V. NSS-related Indicators
The indicators related to NSS, including one-time paging success rate, location update success
rate, A-interface signaling load, and inter-MSC module handover success rate should be analyzed,
because these indicators may affect the radio network.
2.2.3 Other Evaluations
I. CQT for VIP Areas
CQT is the best method to check if the network quality is good or bad. It includes indoor COT and
outdoor CQT. The spots for CQT are co-decided by the customer and Huawei RNO engineers.
According to principle, it is better to choose important organizations, buildings, and prosperous
areas as the test spots. Note that the spots chosen for the test should be consistent and the test
instruments must be the same before and after the swap, otherwise the coverage quality cannot be
effectively compared after the swap.
Table 2-1 lists the main CQT items
Table 2-1 Main CQT items
Item name Test value Remark
Seized channel number
Average signal strength
LAC+CI
Call times
Call connected times
Call drop times
Voice break times
Background noise
One-way audio times
Echo times
Cross talking times
2023-04-27 HUAWEI Confidential Page 32 of 117
GSM BSS Swap Guide For internal use only
You can perform CQT by using MS for spot dialing test. Through analyzing the CQT results, you
can see the network change.
II. GPRS Evaluation
GPRS evaluation includes CQT evaluation, DT evaluation, and traffic statistics evaluation.
GPRS CQT evaluation is used to reflect the network access ability, transmission delay,
transmission rate, and service implementation. The test methods include attach test, WAP browse,
Ping test, FTP test, WWW browse, etc. The test indicators include power, activation time, average
delay, throughput, rate, etc.
GPRS DT evaluation is similar to GPRS CQT evaluation. Besides the indicators tested according
to GPRS CQT, the GPRS DT test indicators include location update, cell reselection, coverage,
call drop, etc.
The traffic statistical indicators include performance indicators and maintenance indicators.
For the related references, seek help from technical support engineers.
III. External Interference Test
The external interference sources include TV station, big-power station, micro wave, radar, high
voltage cable, analog BTS, CDMA network, meeting secrecy equipment, interference unit of gas
station, etc. The interference from some sources is present at certain time. Generally, you can find
out the interference through connecting the spectrum analyzer to the antenna.
The Omni-directional antenna is beneficial for interference measurement. If you intend to locate
the interference, you should use directional antenna. The commonly used directional antennas
include plane antenna, 8-shaped antenna, and digital periodical antenna.
The commonly used spectrum analyzers include HP85XX series and YBT250. The low-noise
amplifier can be used to enhance the receiving sensibility of the test analyzer. For YBT250, the
low-noise amplifier is installed in it.
If the customer requires external inference test, you can refer to the related guides about
interference problem handling.
IV. CW Test
To obtain the radio propagation model fitting the local environment, enhance the accuracy of
coverage prediction, and make a good preparation for network planning, some customers require
the propagation model to be adjusted. CW test stands for continuous wave test and is an important
step for propagation model adjustment. The brief steps of CW test are as follows:
1) Select a suitable site to establish the test platform.
2) Install signal source and antenna.
3) Perform DT using the corresponding software.
4) Process and analyze the DT data through corresponding software
For details, see the related guides about continuous wave test.
2023-04-27 HUAWEI Confidential Page 33 of 117
GSM BSS Swap Guide For internal use only
V. Simulation
Some customers require coverage and quality simulation before and after the swap of the network
and have certain requirements on DT data and simulation results. Generally, they require the
schematic drawings of the coverage and C/I. Simulation software and 3-D digital maps are needed
for simulation. And the adjusted propagation model is recommended. If the propagation has not
been adjusted, you can use the ones provided by the customer. At present, Huawei uses ASSET
and U-NET for simulation.
VI. MOS Test
At present, the QoS of voice quality is evaluated subjectively, and the MOS (mean opinion score)
is the most widely used. However, many objective measures have been used, and the basic ideas
are similar. That is, different measurement technologies are used to simulate people’s auditory and
the equivalent MOS value is provided accordingly. Currently, the PESQ is a mature standard.
Figure 2-1 shows the process.
Figure 2-1 Processing performed in PESQ
As far as the PESQ is concerned, first the input signals and the signals that have been processed
by the system are sent to the test instrument or related software for further processing, and the test
instrument or the software will give the MOS classes.
The value of PESQ ranges from -0.5 to 4.5. The greater the value is, the better the quality is.
Generally, the value ranges from 1 to 4.5. For the matching relationship between the MOS score
and voice quality, see Table 2-1.
Table 2-1 Matching relationship between MOS score and voice quality
MOS score Voice quality
5 Excellent
4 Good
3 Fair
2 Poor
2023-04-27 HUAWEI Confidential Page 34 of 117
GSM BSS Swap Guide For internal use only
1 Bad
At present, many test instruments support MOS test. In many cities, the MOS test is a must now.
Therefore, you should check the contract carefully to see if the MOS test is required and if the test
instrument supports Huawei product.
2023-04-27 HUAWEI Confidential Page 35 of 117
GSM BSS Swap Guide For internal use only
2.2.4 Confirmation of the Acceptance Indicators after Network Swap
I. Coverage Comparison
If the customer requires coverage comparison test in the contract, you should pay attention to the
following points:
Understanding the customer’s real intention.
Understanding the test environment and the coverage of the original network.
Designing the solutions to the interest of Huawei.
Protecting malicious interference.
For details, see the related operation guides about GSM BTS coverage.
II. Statement of Compliance
You should check the RNP&RNO parts for which Huawei is responsible. If there is any vague
point, communicate with the customer for clarification.
III. KPI Formulas and Other Test Methods
You should communicate with the customer for the confirmation of each KPI and traffic statistical
point. In addition, the test methods, such as DT, CQT, and the related test instruments must also be
confirmed. Note that you should better guide the customer to use the methods and instruments
recommended by Huawei.
IV. KPI Commitment Evaluation and Guidance
You should evaluate the network after swap reasonably according to the information of the
original network. If you find that the customer’s requirements on some indicators cannot be met,
you should send the information to the project teams and the staff concerned as early as possible.
In this case, all the departments or engineers concerned should take measures to make sure the
pass of the acceptance test.
Chapter 3 Project Survey, Equipment Installation and
Test
This chapter describes the project survey and design, equipment installation and test. The
engineering duration for this part is the longest and this part is quite important for the success of
the network integration.
3.1 Survey and Design
This section describes the survey of equipment room.
2023-04-27 HUAWEI Confidential Page 36 of 117
GSM BSS Swap Guide For internal use only
3.1.1 Survey of BSC/PCU Room
You can survey the BSC/PCU room according to the related survey guide. The key points are
listed in Table 3-1.
Table 3-1 Key points for BSC/PCU room surveyItem Sub-item Result Remark
Conditions
of equipment
room
Installation
position of
cabinet
The distance between the face of one cabinet and
the face of the opposite cabinet must be equal to
or larger than 1.5m. The distance between the
sides of the cabinet and the wall must be equal to
or greater than 0.8m. The distance between the
commissioning side and the wall must be equal to
or greater than 1m.
Load-bearing
capability
The load-bearing capability of the equipment
room must be greater than 50kg/m2.
The weight of the PCU is 183kg.
The weight of a BSC with full configuration is
280kg.
The weight of the front door and back door is
45kg.
The weight of the two side doors is 42kg.
Temperature and
humidity
The suitable temperature ranges from 15 to℃
30 . The relative humidity ranges from 40% to℃
75%.
Net height
The net height of the equipment room is the
distance between the installation plane and the
girder or the ventilation pipe. Generally, the net
height should be greater than 3m. When
downward cable is used, the net height cannot be
smaller than 2.7m.
SizeThe equipment room should be 2m or more in
height and 1m or more in width.
Power
supply
Capacity of the
rectifier
Generally, power suppliers with high-frequency
switch are required and they should be “N+1”
backup. Each module of the power supplier must
be installed with current equalization output
device.
The total power consumption of a single PCU
must be smaller than 1200W.
The maximum power consumption of a full-
2023-04-27 HUAWEI Confidential Page 37 of 117
GSM BSS Swap Guide For internal use only
configuration BM is 350W.
The maximum power consumption of a full-
configuration AM/CM is 500W.
DC power
distribution box
You should check if the installation position is
suitable and if the wiring terminal configured by
Huawei is normally configured.
Battery capacityDoes the battery capacity meet the design
requirement?
Colour of power
cable
Does the customer have special requirement?
Some customers require that the grounding cable
should be red.
Diameter of
power cable
At present, three specifications are available in
Huawei. They are 240, 120, and 95 mm^2. You
should check if the diameter of the power cable
meets the requirement.
Layout of power
cable
If the power cable delivered can be installed on
the cable rack normally? And if the cable rack is
fixedly stand?
Transmission
Impedance of
trunk75Ω; 120Ω.
Types of
connectors used
for the trunks
(75Ω) at the
DDF side
BNC, SMB, L9
Diameter of
trunks (120Ω) at
the DDF side
Generally, it is 0.4MM. If the customer has special
requirement, the specification of 0.5MM can also
be used.
Lightning
protection
External alarmThe BSC supports external alarm, but the PCU
does not support external alarm.
Outdoor cable
lightning
protection.
You should check if there is outdoor transmission
cable or power supply cable. If yes, check if the
lightning protection measures meet the
requirement.
Others
Responsibility
matrix for
hardware
installation;
You need to confirm the responsibility matrix of
the installation of transmission equipment and
power supplier.
Clock Clock extraction
modes (BITS,
See related cases.
2023-04-27 HUAWEI Confidential Page 38 of 117
GSM BSS Swap Guide For internal use only
MCS, or others)
3.1.2 BTS Survey
Table 3-1 lists the key points for BTS survey
Table 3-1 Key points for BTS surveyItem Sub-item Result Remark
Conditions
of equipment
roomLocation of the
equipment room
If there is special procedures for entry;
If there is restrictions for night entry;
If special tools such as the ladder are needed for
entry;
If the transportation of the equipment is convenient;
If installation conditions are needed for advanced
installation.
Load-bearing
capability
The load-bearing capability of the equipment room
should be greater than 400kg/m2. Since battery free of
maintenance should be installed in the equipment
and if the specification of the battery is 500Ah or
lower, the load-bearing capability of the equipment
room must be greater than 450kg/m2. If the
specification of the battery is 800Ah or higher, the
load-bearing capability must be greater than
600kg/m2.
Communication
method used at
the equipment
room
You should check if the equipment room can receive
the signals from other networks and if there is
available fixed phone.
Temperature and
humidity
You should check if the environment of the
equipment room can support long-time operation of
the equipment and if the air conditioner installed for
the equipment room can work normally. Generally, if
temperature in the equipment room can ranges from
15 to 30 , and the relative humidity can ranges℃ ℃
from 40% to 65%.
Net heightThe net height of the equipment room should be
equal to or greater than 2.7m.
Size of the door
of the equipment
room
It should be 2m or more in height and 1m or more in
width.
2023-04-27 HUAWEI Confidential Page 39 of 117
GSM BSS Swap Guide For internal use only
Installation
position
For the convenience of maintenance, you should
leave a distance between the BTS and the wall.
Installation
conditions of
outdoor BTS
The load-bearing capability, transmission condition,
installation position of the mount set, and grounding
system should meet requirement.
Power
supply
AC power
distribution box
Does the capacity of the AC power distribution box
meet the requirement of Huawei BTS?
Capacity of the
rectifier
Generally, power suppliers with high-frequency
switch are required and they should be “N+1”
backup. Each module of the power supplier must be
installed with current equalization output device. If
the power supply voltage is -48V and +24V, the
charge current of the battery should be additionally
considered (according to 12 TRXs, 2800W). If the
power supply voltage is 220V, you need to check if
the DC power supply cable is installed at the proper
position and the wiring terminal is normally installed
(according to 12 TRXs, 3200W, including the charge
current of the battery).
DC power
distribution box
You should check if the installation position is
suitable and if the wiring terminal configured by
Huawei is normally configured.
Battery capacityDoes the battery capacity meet the design
requirement?
Colour of power
cable
Does the customer have special requirement?
Some customers require that the grounding cable
should be red.
Power supply of
transmission
equipment
If the power supply equipment cannot be reused, you
should check if the power supply cable of the
transmission equipment of the original network is
long enough to be connected to Huawei equipment
and if the diameter of the cable is suitable?
Transmission Impedance of
trunk75Ω; 120Ω.
Types of
connectors used
for the trunks
(75Ω) at the
DDF side
BNC, SMB, L9
2023-04-27 HUAWEI Confidential Page 40 of 117
GSM BSS Swap Guide For internal use only
Diameter of
trunks (120Ω) at
the DDF side
Generally, it is 0.4MM. If the customer has special
requirement, the specification of 0.5MM can also be
used.
Timeslots
allocated for E1
at the Abis
interface
Monitor the equipment timeslot occupancy, the
timeslots of the related integration equipment, and
timeslots used for G/C transmission.
Transmission
line and the label
for DDF
transmission port
Check if the label or the mark is correct.
Transmission
concatenation
relationship
It will affect the swap order.
Lightning
protection
and
grounding
system
Outdoor
lightning
protection cable
Check if there is outdoor lightning protection cable
for the transmission line and power cable. If yes,
check if the lightning protection measures meet the
requirement.
Grounding
system
Check if the grounding cable is present, if there is
adequate room for the grounding bar, and if the
grounding terminal can be normally connected.
Antenna feeder
lightning
protector
Check the installation position, frequency band,
types of the connectors used for the antenna and
related equipment, and the standing wave ratio. The
problems concerning connectors are main factors
affecting the swap progress, so the survey engineers
should check them carefully in advance.
Feeder
grounding rule
Check if the grounding point can be connected to the
feeder grounding clip.
Antenna
feederDiversity
distance between
antennas
The distance of the 900M antennas should be equal
to or greater than 4m, and the distance between the
1800M antennas should be equal to or greater than
2m.
Project
parametersAntenna azimuth and tilt angel.
Feeder layout Check if the connection of the feeder and antenna is
correct. Use test MS to check if the cell
configuration is correct and if the feeder label is
correct and complete.
2023-04-27 HUAWEI Confidential Page 41 of 117
GSM BSS Swap Guide For internal use only
Tower amplifier
Check the installation position, working band, power
supply mode, and alarming mode of the tower
amplifier.
Feeder window
and thru-wall
plane
If other antennas need to be added, you should check
if there is adequate room available in the feeder
window.
Filter and
combiner of
common antenna
If an antenna is shared by other equipment, you need
to check if the filter and combiner meet the
requirement?
Feeder connector
in the equipment
room
If the antenna feeder of the network to be swapped
can be reused, you need to know the specifications
and quality of other equipment providers’ antenna
feeders and check if they can match Huawei
equipment.
BTS type and
combiner and
divider
You should confirm the TRX type of the BTSs to be
swapped and the types of the combiner and divider,
because they are used to calculate the set-top power.
Others
Outdoor
extension alarm
BTS supports 24-channel extension alarm, and the
environment alarm box supports 10-channel
extension alarm.
Engineering
responsibility
matrix of
hardware
installation
Confirm the engineering responsibility of the
installation of the transmission and power supply
equipment.
Note:If you find out that the environment of the equipment room or the installation of the antenna is not
in accordance with Huawei rule, you should discuss with the customer and design adjustment
measures, otherwise the operation of the network or the network indicators will be affected after
the integration of the network. If the customer rejects the adjustment measures, you should ask the
customer to sign a memo. In addition, if you find out that some connectors do not match Huawei
equipment; you should design the corresponding solutions immediately.
2023-04-27 HUAWEI Confidential Page 42 of 117
GSM BSS Swap Guide For internal use only
3.1.3 M2000 Survey
I. Equivalent Network Element
You should calculate the number of the equivalent network elements according to the
configuration of the equipment so as to ensure adequate management capability for M2000.
Table 3-1 provides the calculation of the network element number.
Table 3-1 Network element number calculation
Network typeNumber of network
elementsRemark
BSC+BTS60 cells are equivalent to
1 network element.
If the actual number of the cells is
known, you should perform the
calculation according to the actual
number; otherwise perform the
calculation based on 3 cells
regardless of on BTS or NodeB or
regardless of the network type
(W/C/G).
iMSC 1
tMSC 1
rMSC 1
MSC 1
PCU 1
HLR 0.1
GT800 BSC+BTS60 cells are equivalent to
1 network element.
Table 3-2 provides the matching relationship of the network element number and the server
configuration
Table 3-2 Matching relationship of network element number and server configuration
Server configuration Equipment type
Management capability
(equivalent network
element)
Remark
Mid-range-and-low-end
configuration
Sun Blade 2000 ≤? ?
Sun Netra 20 ≤15
Sun Netra 240 ≤15
High-end configurationSun Fire V880(4CPU)
Sun Fire V880(8CPU)
≤30
≤60
2023-04-27 HUAWEI Confidential Page 43 of 117
GSM BSS Swap Guide For internal use only
Sun Fire V890(2CPU)
Sun Fire V890(4CPU)
Sun Fire V890(8CPU)
≤25
≤50
≤90
Super configuration
Sun Fire 4800(4CPU)
Sun Fire 4800(8CPU)
≤40
≤? ?
Sun Fire E4900(4CPU)
Sun Fire E4900(8CPU)
≤55
≤120
II. About M2000
You should know the networking mode, bandwidth, and installation position of M2000 and if
there is the network management system of the third party.
Networking mode:
The communication between M2000 and each network element is based on TCP/IP. At the
physical layer, partial E1/T1, whole E1/T1, or DDN/X.25 can be used.
M2000 supports LAN and WAN. The networking planning depends on the geographic location of
the network elements and customer needs. If all the network elements locate in the same network
segment, LAN is often used; otherwise WAN is used.
3.1.4 Project Design
Hereunder lists the tasks need to be completed during project design:
Checking the information of the original network equipment
The information include the specification of antenna and feeder, performance indicator,
connector specification, quantity of the transmission links used in the original network, mode
and transmission line, connector specification of the DDF rack.
2023-04-27 HUAWEI Confidential Page 44 of 117
GSM BSS Swap Guide For internal use only
Surveying and checking the installation environment of the Huawei equipment and
confirming the jumper length, trunk length, grounding system, feeder, and jumper connector
information.
Confirming the environment of the equipment room of the original network and collecting
the available resources.
Confirming the installation position of the Huawei BTS and attached equipment and
confirming the configuration solutions used for transmission and power supply.
Completing the engineering drawing related to the equipment installation and integration.
Considering the anti-theft equipment or the anti-vibration equipment because some
customers have special requirement in these aspects.
3.2 Hardware Installation
This section describes hardware installation. For general cases, refer to the related manuals and
pay attention to special cases. You should perform the installation following the design strictly and
make self-check after the hardware installation. In addition, you should also make self-check after
software commissioning.
3.2.1 Goods Preparation
The on-time delivery of the correct goods is the key to the success of a swap project, so you
should pay attention to the followings:
The way of delivery, the time and way of customs clearance.
If the goods are consistent with contract configuration.
The storage of the goods.
At the engineering field, you should pay attention to the followings:
For the convenience of engineering and collocation, it is better to store the goods in a vast
land.
The storage of the goods must be in accordance with the customer’s rules.
You need to communicate with the customer on how to handle the goods in advance.
The package cannot be opened during the handling of the goods and the goods should be
carried and placed lightly.
For the convenience of acceptance and cleanup, the goods should be placed according to
certain principles.
The goods should be categorized according to service.
Pay attention to the storage of small components, such as cable, software, and screw,
especially the small and light expensive goods.
On the arrival of the goods, pay attention to how to allocate the goods to the installation site.
A record is needed before the allocation and the signature of the related project team is
required.
2023-04-27 HUAWEI Confidential Page 45 of 117
GSM BSS Swap Guide For internal use only
If the goods are provided by agents, you need to communicate with the customer fully to
ensure on-time delivery and security shipment.
3.2.2 BSC Installation
I. Constructing a New BSC
For hardware installation, you need to pay attention to the installation of the trunk, optical fiber,
grounding cable, alarming cable, BAM, and loading cable. If there is CDB, you need to check the
connection of CDB and MEM. After the completion of the installation, you need to check the
followings:
If the self-loop checked has been performed for relay transmission?
If the labels are clear? If the optical fiber is bounded according to requirement?
If the there is no cross-connected lines and band connection?
If the self-check has been made according to hardware standard?
If the power-on test has been made?
For software installation, the correct version and license should be used.
II. Expanding the Capacity of an Existing BSC Through Adding BM
For hardware, you need to check if there are cross-connected lines at the A-interface and Abis
interface and if newly-added BM and AM are correctly connected, especially you need to check
the connection of optical fiber.
For software, you need to check if the upgrade and reapplication of License are necessary.
III. Expanding the Capacity of an Existing BSC Through Adding BIE Board Only
For hardware, you need to pay attention to the operation rule, DDF connection, and transmission
test.
For software, you need to pay attention to the version and license.
IV. Expanding the Capacity of an Existing BSC Through Adding BTS Only
There is no special requirement on hardware.
For software, you need to pay attention to the version and license.
3.2.3 Huawei PCU Installation
For PCU installation, you should pay attention to the connection of the power supply cable,
trunks, and network cable. In addition, you should also check if the labels are correctly pasted and
if the power-on test is performed according to requirement.
3.2.4 BTS Installation
BTS installation and test contribute greatly to the success of a swap project. During BTS
installation and test, the workload is heavy and a great number of abnormal conditions may occur.
Hereunder describes the main scenarios about BTS installation and test.
2023-04-27 HUAWEI Confidential Page 46 of 117
GSM BSS Swap Guide For internal use only
I. Antennas and Feeders
You should construct a new site following general procedures and this task should be finished in
advance. In addition, the standing wave test should also be finished in advance. After that, you
need to test if the antennas and feeders are well connected.
If the antennas and feeders of the original network can be reused, you should make sure that
they can be connected to Huawei equipment normally and that the standing wave ratio will
not change greatly after the swap.
If part of the original equipment can be reused while some new equipment should be added
to the network, you should install the new equipment in advance and make sure that the
original equipment and the new equipment can be normally connected.
If the antennas and feeders of other BTSs are used for this BTS, you need to check if the
combiner, filter, and other related specifications meet the requirement.
II. BTS Installation Room
Scenario 1:
If there is adequate room left in the equipment room and the customer agrees that the new cabinet
cannot be installed in another position, you can install the new cabinet in the due position and
prepare the related power supply cable, trunks, antennas, feeders, and jumpers in advance. At the
night for integration or pre-integration, you need to disable the original BTS and enable the new
BTS. Note the original BTS should still be reserved at this time in case of integration failure.
Scenario 2:
If there is inadequate room for BTS installation and the new cabinet should be installed at the
position where the original BTS located, you must replace the original BTS with the new one at
the night for integration. In this case, you can place the new BTS to the equipment room first, and
then prepare the related power supply cable, trunks, antennas, feeders, and jumpers in advance. If
the installation of the new BTS cannot be finished on the integration night for the time being, you
can integrate the new BTS into the network first, and then choose another suitable night to finish
the whole installation.
Scenario 3:
If there is some room left in the equipment room for BTS in stallion, you can install the new
cabinet in advance. If the capacity of the network needs to be expanded, you can install other parts
after removing the rest original cabinet from the equipment room. In this case, you can place the
new BTS to the equipment room first, and then prepare the related power supply cable, trunks,
antennas, feeders, and jumpers in advance. If the installation of the new BTS cannot be finished
on the integration night for the time being, you can integrate the new BTS into the network first,
and then choose another suitable night to finish the whole installation.
Scenario 4:
If there is inadequate room left for the BTS installation, you can finish the whole installation later.
If the new BTS is not so important, you can use the surrounding BTSs for the coverage
2023-04-27 HUAWEI Confidential Page 47 of 117
GSM BSS Swap Guide For internal use only
temporarily. At the night for integration, you should ensure the network quality through adjusting
the surrounding BTSs in advance, and then break the services provided by the original BTS.
III. BTS Transmission
If the transmission resources are adequate, you can finish the whole integration in advance. In this
case, the tasks involved are simple and you can debug the BTS. If the power-on test is not
available, you can perform self-loop test so as to ensure smooth transmission.
If the transmission resources are inadequate, you should debug the transmission when integrating
the network. If a great number of BTSs need to be integrated, the transmission resources are the
key to the success of the swap. In this case, you need to perform off-line test to check if the BTSs
work normally.
IV. BTS Power Supplier
If the capacity of the power supplier needs to be expanded, you need to communicate with the
customer to solve this problem before integration. If the customer cannot provide enough capacity,
you can enable only part of the TRXs.
If there is no room left for the installation of the power supplier, you can also communicate with
the customer for solution.
If there is enough room for the installation of the power supplier, you can install it in advance.
3.2.5 M2000 Installation
It is simple to install the M2000. If the number of network elements is great, you need to replace
the M2000 server and change the IP address accordingly.
3.2.6 Removing the Equipment of the Original Network
Huawei engineers are responsible for removing the equipment of the original network according
to the contract. Generally, you should remove the equipment of the original network after Huawei
equipment works normally in the new network. Here you should pay attention to the following
two points:
You can use packaging material of Huawei equipment to package the removed material.
The removed equipment should be soundly transported to the destination on time.
3.3 GBSS Test
GBSS test must be made before network integration. And this section introduces the GBSS test
points.
3.3.1 BSC Test Points
Hereunder lists the BSC test points:
2023-04-27 HUAWEI Confidential Page 48 of 117
GSM BSS Swap Guide For internal use only
There are many BSC signaling points, so new signaling points should be used for swap.
If the MSC to be swapped is provided by other operator, you need to perform IOT
compatibility test with the help of Huawei technical support engineers.
Since it is the BSC that need to be tested, you are suggested to perform the test according to
the related acceptance manuals provided by Huawei. The customer’s special requirement
cannot go beyond the contract.
If there is cross-BSC handover or cross-MSC handover after Huawei BSC has been
integrated into the network, you need to make handover test.
BSC has great effect against clock, so you need to evaluate the clock in advance. If the
transmission is not good or the MSC clock is not stable, you need to make clock test.
If there is no signaling transmitted at the Abis interface, you should install a temporary BTS
or micro-cell BTS at the suitable place for signaling test.
For G9, A-interface is related to UMG8900 and MSC Server. The UMG8900 is responsible for the
access and exchange of data service and the processing of traffic flow format. In addition,
signaling gateway can be embedded into the UMG8900, so calling messages can be sent to
UMG8900 for adaptation before sent to MSC Server for processing.
3.3.2 CDB/CBC Test
I. Testing Connection between CDB and GMEM
Debugging the connection between GMEM board and host
Testing the connection between GMEM board and CDB server
Testing CDB server
II. Testing Connection between CDB and CBC
Testing the connection between CDB and CBC
Inputting test messages at the maintenance and test console
Monitoring the messages sent across the Abis interface at the BSC maintenance console
III. Testing Short Message Display (MS)
When the BTS works normally, you should use the test MS or the MS supporting cell broadcast to
perform the acceptance test. At this time, if you enable the cell broadcast reception functions and
set received channel number to the ID of the test message, you can see the test message through
MS.
If the MS cannot receive the cell broadcast message, you should first check if the cell broadcast
reception switched is enabled and if the corresponding channel number is set, and then you should
check if the connection between CDB and GMEM is normal. Finally, monitor the messages and
locate the problem at the BTS maintenance console.
By now you have finished debugging the whole CDB cell broadcast database.
2023-04-27 HUAWEI Confidential Page 49 of 117
GSM BSS Swap Guide For internal use only
IV. Precautions about CDB&CBC Test
Hereunder lists the precautions about CDB&CBC test:
You should use the interface monitoring function provided by the OMC to monitor the Abis
signaling and check if the CB messages from BSC to BTS are normal.
If the CDB and CBC cannot be interconnected, you need to check the phase mark carried in
the cdbcfg.ini of the CDB configuration file.
When performing message display test, you need to pay attention to the language used in
that area, because some special characters cannot be displayed through MS.
Since the CDB interface and CBC interface are not standard interfaces according to
protocols, you must test the interconnection between CDB and CBC.
3.3.3 PCU Test
Hereunder lists the precautions about PCU test:
Network configuration test
To perform network configuration test, you need to log in to the system through Telenet.
Hardware data configuration check
You should input the command “slot show all”. If the configuration is normal, the system
will display that the “status” of each slot is “normal”.
E1 configuration check
Input the command “pcu check e1config” to check the E1 configuration.
PCIC status check
You should input the command “mt pcic show available all”. If the results show that the
number of available PCIC is consistent with that of E1 slot, the E1 slot is successfully
configured.
LAPD link status check
You should input the command “mt lapd show state {<BoardNo> all} | <LapdNo> |
<LapdName>”. If the management status is “unlocked” and the operation status is
“available”, the status of the LAPD link is normal.
Cell configuration check (Gb interface)
You should input the command “pcu check cellconfig all” and the result is that the
configuration is intact.
PDCH status check
Input the command “mt pdch show state {<Leno>|<LCName>} {<PdchNo>|all}” to check if
the status of PDCH is normal.
MS attach test
Once the MS is powered up, it will search the GPRS network automatically and initiate the
attach procedure, so you should test if the MS has been attached to the network successfully.
PDP activation test
2023-04-27 HUAWEI Confidential Page 50 of 117
GSM BSS Swap Guide For internal use only
PDP can be activated through the MS directly. Also you can activate the PDP through
connecting the MS to portable equipment.
POMU changeover test
The POMU changeover functions are related to multiple equipments, including LanSwitch,
HSC board, network cable, etc. Therefore, you need to test the changeover function of
POMU to check if the connection between the equipments is normal.
3.3.4 BTS Test
I. Off-line Test
If the transmission is not available, you can use local maintenance console to perform off-line test
for the BTS.
Hereunder lists the test items:
TMU and TRX board check
TMU and TRX must be self checked after powered on. If the TMU self check fails, the ALM
indicator will flash.
Software version check (TMU and TRX)
You should check if the software versions of the TMU and TRX are consistent with the
applied ones. If the software versions are inconsistent, you need to upgrade the software to
the corresponding version.
Local software loading and activation
You need to check if the software is normally loaded and activated.
EAC status check
You should check if the communication between EAC and BTS is normal.
Environment alarming check
You should check if the environment alarm probe works normally and if the alarming
information can be reported to the BTS.
TRX power test
You should test the TRX power at each output port (the TRX board should be preheated for
at least 30 minutes). If there test value is abnormal, you need to replace the TRX board with
another one. (Generally, the normal test value ranges from 46.98 dBm to 49.08 dBm.
II. On-line Test and Coverage Evaluation
To ensure the reliability of Huawei equipment before the implementation of the swap, you need to
perform on-line test for Huawei BTSs. In addition, you also need to test and evaluate the set-top
power of various typically-configured Huawei BTSs, because the information is necessary for
customer communication.
Generally, you can make the test and evaluation according to following steps:
1) Test and evaluate the set-top power of the typically-configured BTSs and record the results.
After that, disconnect the antennas and feeders of the original BTSs and test the indicators
2023-04-27 HUAWEI Confidential Page 51 of 117
GSM BSS Swap Guide For internal use only
(such as the standing wave ratio) of the antenna feeder system to see if the they meet the
requirement of Huawei BTS. If yes, the antennas and feeders of the original network can be
integrated into the Huawei BTS; otherwise you should make corresponding measures
according based on the customer’s permission.
2) Integrate the trunks of the original network into the Huawei BTS temporarily.
3) After the BTS finishes loading the data automatically, you should use frequency locking
function of the MS to make dialing test. Note that each channel number and timeslot should
be tested. In addition, you should also perform DT to test the coverage and handover.
4) After the test, you should recover the equipment to the original state, and then evaluate the
coverage of the original network. This operation can be made before the on-line test.
5) Compare the set-top power and the coverage of the new network with that of the original
network and take anti-risk measures according to actual conditions.
Note:You should report the coverage results to the customer in time to make the customer feels
confident in Huawei equipment. In this case, Huawei is more likely to win the customer’s support.
3.3.5 M2000 Test
If WAN is used for M2000 networking, the LANs can be connected to each other in various ways,
including partial E1/T1 networking, whole E1/T1 networking, and DDN/X.25 networking.
Hereunder introduces the debugging procedures of partial E1/T1 networking.
I. Partial E1/T1 Networking
When partial E1/T1 networking mode is used, the Mercury3600, routers, Ethernet switch, and
other network elements should be configured in the network, as shown in Figure 3-1. If necessary,
you can add set a firewall between the M2000 Server and the network element or the client end.
2023-04-27 HUAWEI Confidential Page 52 of 117
GSM BSS Swap Guide For internal use only
Figure 3-1 Partial E1/T1 networking mode
II. Network Debugging (Partial E1/T1 networking mode)
The following table lists the steps.
Step Operation Reference
1
Connect the M2000 Server, client end, and each
network element to the Ethernet switch through
network cable.
2 Configure the Ethernet switch.
3 Configure routers for network elements.
4 Configure routers for M2000 Server.
5 Configure Mercury3600.
6 Configure firewall if necessary.
3.3.6 Equipment Function Acceptance
The acceptance should be performed according to contract. If the acceptance items provided in the
contract are vague, on-site engineers should communicate with the customer on project
installation, test mode, acceptance mode, and acceptance procedure. In addition, on-site engineers
should also reach agreement with the customer on acceptance time, place, personnel, standard,
cases, documents, and equipment. Especially for BTS acceptance, you should make clear if the
acceptance should be performed one by one or by batch and if the acceptance should be
performed before or after the integration of the network. Furthermore, you need to know the
customer’s special requirement on project engineering. If the customer requires the equipment
2023-04-27 HUAWEI Confidential Page 53 of 117
GSM BSS Swap Guide For internal use only
provider to design the test and acceptance solutions, you should communicate with the customer
before the final solutions are made and get the customer’s written confirmation. In principle, the
network cannot be put into operation before acceptance.
Chapter 4 Network Swap Planning and Network
Parameters
4.1 Network Swap Planning
4.1.1 Whole Network Planning
I. Coverage Planning
It is important to ensure that the coverage capability of the new network is equal to or better than
that of the original network. This is the general swap principle. For details, see the related
coverage planning guides. Hereunder lists the precautions about the swap planning:
To prevent the network coverage from being heavily affected by the swap, you need to check
the antennas and feeders of the original network if they can be reused. If there is any
problem, you should sign a memo with the customer and provide corresponding adjustment
measures.
If new antenna and feeder will be used to replace the old ones, the azimuth and tilt angle of
the new antenna and feeder should be consistent with that of the old one. If the customer
requires you to adjust the azimuth and tilt angle of the antenna to meet special coverage
requirement, you should sign a memo with the customer. In this case, you should integrate
the change of antenna gain and feeder loss into consideration.
To obtain the set-top power used for the swap, you need to analyze the TRX power,
combination mode and loss of the sites of the original network. In addition, you should also
decide the configuration solution according to the TRX power and combiner type of Huawei.
If the set-top power of the original equipment is greater than that of the Huawei equipment,
you should guide the customer to accept the solutions provided by Huawei. Generally, you
can use the 60W/TRX or PBU. Note that you should output a configuration table for each
site.
Hereunder lists several principles for site configuration:
Try best to use the common configuration solution of Huawei or the 60W/TRX to meet the
coverage requirement after swap.
If the set-top power of the new network is lower than that of the original network under
common configuration, you can use PBU if no cabinet should be added.
2023-04-27 HUAWEI Confidential Page 54 of 117
GSM BSS Swap Guide For internal use only
If PBU cannot be added to all the TRXs, you are suggested to use both the PBU and IUO
strategy.
If PBU cannot be added to the original cabinet, you can add PBU and use multi-antenna
configuration.
If the set-top power of some TRXs is still lower than that of the original network when
multi-antenna configuration is used, you are suggested to apply PBU configuration to all the
TRXs.
If multi-antenna configuration is not supported, you can apply PBU configuration to the
newly-added cabinet.
If both PBU configuration and multi-antenna configuration are not supported, you are
suggested to add new sites to the network and enable cell splitting strategy.
However, you need to pay attention to the following three points:
If some sites need to be expanded or their combination modes have changed after swap, you
should swap the sites according to the original configuration and then expand the capacity.
For the swap of the sites with large configuration, you can seek help from the technical
support engineers of Huawei and they will provide you with the corresponding operation
guide.
If the tower amplifier was used for the original site, it should also be used for the new site,
but you should check the power supply mode and working current.
After the completion of coverage planning, you should input the planning information into the
total project parameter table.
II. Capacity Planning
You should swap the network according to its original configuration and the capacity expansion
should be performed after the swap. For details, you can refer to the related guides about capacity
planning.
For signaling channels, you should plan the configuration solution through analyzing the
configuration of the signaling channels (CCCH and SDCCH) used in the original network and
analyzing the characteristics of Huawei equipment. At the intersections between location areas,
you can add SDCCH and enable the SDCCH dynamic allocation function of Huawei equipment.
For details, you can refer to the related guides about SDCCH capacity planning.
You should also follow the configuration of the original network to swap the PDCH. If the
customer requires Huawei to provide GPRS/EDGE services after the swap, you can plan the
capacity according to the related guides about GPRS/EDGE network planning. Note that PBCCH
and PCCCH should not be configured in the original network.
III. Frequency Planning
To ensure the smooth network transition, you are suggested to follow the original frequency
planning for the swap; otherwise the conversation quality may become worse after the swap.
2023-04-27 HUAWEI Confidential Page 55 of 117
GSM BSS Swap Guide For internal use only
If you find that there is serious problem or the frequency planning of the original network will
affect network quality, you can re-plan the frequencies for the total network or for some areas.
Note that the frequencies at the intersections between networks should be properly designed.
For details, see the related guides about frequency planning.
IV. LAC and CI Planning
You should negotiate with the operator concerned to decide the LAC and CI planning. During the
swap, you are suggested to provide new blocks for LAC and CI. The LAC edge of the original
network can be used for the new LAC, but the CI must be re-planned. In this case, you can design
the MSC data and BSC data in advance to ensure the security of the data. If problems are present
at the LAC edge, you can adjust LAC edge from the perspective of total network after the network
has been swapped. If the LAC and CI of the original network are stilled used after the swap, you
need to change lot of MSC data and BSC data on the swap night.
For BSIC planning, the BSICs of the same-frequency BCCHs must be different. When swapping a
project, you are suggested to shift the NCC and follow the BCC of the original network. In this
case, you can configure the adjacent cell relationship in advance; otherwise you must modify the
data on the swap night.
For details, see the related guides about location area capacity planning.
When changing LAC, you should take the charging equipment and MSC routing into
consideration.
V. Radio Parameter Planning
To ensure smooth network transition, you should take the radio parameters of the original network
into consideration. After the completion of the swap, you should optimize these parameters. Some
equipment parameters can be the defaulted ones according to Huawei. If only some of the
parameters can be collected, you should refer to the related parameter planning guides. When
planning radio parameters, you should pay attention to the periodical location update time, uplink
and downlink DTX, radio link expiry, SACCH multi-frame number, ECSC, multi-band report,
minimum access level of RACH, minimum Rxlev of MS, direct retry, CRO, CRH, etc.
VI. Huawei Functional Parameter Planning
Huawei has developed many excellent functional algorithms for its GBSS system, including
handover algorithm and parameter, channel allocation algorithm and parameter, IUO parameter,
etc. To ensure that the network can work normally after swap, you should use the proper handover
algorithms (PBGT handover, emergent handover, edge handover, load handover, or IUO
handover) and plan the related parameters properly. Generally, the PBGT handover algorithm,
load handover algorithm, and IUO handover algorithm, and emergency handover algorithm
(including TA emergency handover algorithm, BQ emergency handover algorithm, and
interference emergency handover algorithm) are needed in a network. In some urban areas where
the traffic volume is heavy, load handover algorithm should be used. For power control, the HW II
2023-04-27 HUAWEI Confidential Page 56 of 117
GSM BSS Swap Guide For internal use only
power control algorithm is used. For channel allocation algorithm, HW II Channel Allocation
algorithm is used.
VII. Special Scenarios
You should pay attention to the coverage planning in some special scenarios, such as indoor
environment, tunnels, railways, subways, etc. For example, you can use indoor distribution
antenna system to provide the coverage for indoor environment and use big-power TRX and high-
gain antenna to provide the coverage for vast area. Pay attention to use repeaters. If the repeaters
to be used are frequency selection repeaters and if the channel number of the donor antenna needs
to be changed after the swap, you should notify the customer to change the repeater data. For
details, you can refer to related planning guides or seek help from technical support engineers.
4.1.2 Network Swap Planning Data Design
Before designing the data, you should use the parameter conversion tool made by Huawei to
convert the parameters of original operator into Huawei parameters.
I. Designing Network Swap Planning Data
The following table lists the data design methods, precautions, advantages, disadvantages, and suggestions.
Data
Types
Design
MethodsRemarks and precautions Advantages Disadvantages
Suggestions
Frequency Take the
data used in
the original
network for
reference
1. Design the frequency
planning data for each
Huawei site according to
the data used in the
original network.
2. If frequency hopping is
used, pay attention to the
allocation of frequency
hopping mode, MA, HSN,
and MAIO.
1. The problems
concerning the
frequencies at edges do
not exist.
2. The understanding of
project parameters will
be more complete and
thorough.
3. The frequency will
be more rational.
1. If the frequencies
in the original
network are poorly
planned, the network
will not be apparently
improved and the old
problems are still
present.
2. Network
expansion, TRX
construction, and
BTS construction
cannot be performed
at the same time with
swap.
1. You can
inherit the
frequency
planning data
used in the
original
network.
2. If the
frequency
planning
methods used
in the
original
network are
irrational,
you can re-
plan the
frequencies
for the total
network.
Re-plan the
data
Prepare new frequency
planning before swap.
1. The problems
concerning the
frequency planning in
the original network can
be corrected.
2. The network
expansion, TRX
1. The network
quality may become
worse because of the
change of the
frequency planning
methods.
2. You need to make
2023-04-27 HUAWEI Confidential Page 57 of 117
GSM BSS Swap Guide For internal use only
construction, and BTS
construction can be
performed during the
swap.
transition data to
prevent frequency
interference
occurring at edges.
LAC and
CI
Inherit the
original
LAC but
re-plan the
CI
When using the LAC of
the original network, you
need to consider if the
capacity of the location
area is large enough.
1. The workload is
small at the swap night.
2. The location areas are
clear and there is no
mixed LAC.
1. You need to re-
apply for the CI
number segment;
otherwise you cannot
prepare the MSC data
in advance.
2. You may need to
re-plan the LAC after
swap.
Inherit the
LAC but re-
plan the CI.
Inherit both
of the LAC
and CI
If only some of the
BTSs under the BSC
can be swapped at
that night, you need
to change plenty of
adjacent cell
information, so the
swap risk is high.
BSIC Take the
data used in
the original
network for
reference
Inherit the BSIC
configuration data used in
the original network.
The planning workload
is light.
The same frequency
may have the same
BSCI and you cannot
design the adjacent
cell in advance.
Shift the
NCC and
keep the
BCC
unchanged.
Re-plan the
data
1. When re-planning the
BSIC data, shift the NCC
only. For example, if the
NCCs of the original
network are 0, 1, and 2,
they can be 3, 4, and 5
after the shift. For BCC,
you should keep it
unchanged.
2. Check if the adjacent
cells are using the same
frequency and same BSIC.
3. Pay attention to modify
the BSIC of the external
adjacent cells at the edges
during batch swap.
1. When the frequencies
of the original network
are reused, you can also
design the data for two
sets of adjacent cells.
2. The swap data can be
loaded to the BSC in
advance and the data for
two sets of adjacent
cells can be operated
simultaneously.
Cell
optimizati
Take the
data used in
1. Use parameter
conversion tools to
The network quality can
be ensured after swap,
It is hard to collect all
the data because the
Design the
data
2023-04-27 HUAWEI Confidential Page 58 of 117
GSM BSS Swap Guide For internal use only
on
parameter
the original
network for
reference
convert the parameters of
the original network into
corresponding Huawei
ones, and then analyze if
these parameters are
applicable according to the
characteristics of Huawei
equipment.
2. If some parameters of
the original network
cannot be obtained, you
can use Huawei empirical
parameters first and
optimize them later.
because most of the
parameters used in the
original network are
inherited.
data format varies
with operators.
according to
the
parameters
used in the
original
network and
use the
related
parameter
collection
tools.
Use
Huawei
empirical
value
1. Take the related
network planning data
guides for example.
2. Configure the data
according to Huawei
empirical value.
The planning method is
simple and the
workload is light.
1. The radio
parameters are no fit
for the actual radio
environment, so the
network indicators
may fluctuate greatly
after swap.
2. The optimization
workload is heavy
after swap.
Adjacent
cell
parameter
Take the
data used in
the original
network for
reference
1. You can make the
adjacent cell data
according to the data used
in the original network,
and then use NASTAR or
MAPINFO for
optimization.
2. For one-time swap, you
need to make the data for
one set of adjacent cells
only. For batch swap, you
need to make the data for
two sets of adjacent cells
at the edges. In addition,
you should notify the
customer to modify the
adjacent cell data designed
by the original operator.
3. If Huawei sites are
under the control of
1. You can inherit the
data of the adjacent
cells that are used for
actual handover to
reduce the planning
workload.
2. The handover will
not be greatly affected
after network
integration, so it is good
for network
optimization.
Some data of the
original adjacent cells
may be missing or
irrational, you need
to check the data for
confirmation.
Modify the
data based on
that used in
the original
network.
2023-04-27 HUAWEI Confidential Page 59 of 117
GSM BSS Swap Guide For internal use only
multiple BSCs, you should
make the adjacent cell
data accordingly.
4. Pay attention to design
the data for the adjacent
cells outside the BSC
edge. The number of
adjacent cells cannot be
greater than 32. For batch
swap, if you need to make
the data for more than 32
adjacent cells, you are
suggested to reserve the
original cells first, and
then delete the old data
before add new data.
5. After the completion of
the whole swap, you need
to cancel the information
of the redundant adjacent
cells.
The calculation of LAC is based on certain traffic model and paging strategy. Since the traffic
models in cities and countries are different, the capacity of a location area may greatly different
from that of another location area. For details, you can refer to corresponding guides and seek
help from technical support engineers. The following table gives the capacity of a location area.
(If the traffic volume of each subscriber is 0.02Erl at busy hours.)
No.BCCH
allocation
Paging
mode
AGCH
reserved
blocks
PCH
blocks
Frame
number
between
same
pages
Subscribers
supported
Traffic
volume
supported
In average, 3
TRXs are
configured for
each cell.
(Suppose that
the call loss rate
is 0.5% and
each cell
supports 11.8
Erl traffic.)
In average, 2
TRXs are
configured for
each cell.
(Suppose that the
call loss rate is
0.5% and each cell
supports 6.6 Erl.)
Remark
1 Main
BCCHIMSI
2 7 2 83785 1676 424 503
2 1 8 2 95754 1915 484 575
3 0 9 2 107724 2154 545 647Immediate assignment
preferred
4 TMSI 2 7 2 130701 2614 661 785
5 1 8 2 149372 2987 756 897
6 0 9 2 168044 3361 850 1009 Immediate assignment
2023-04-27 HUAWEI Confidential Page 60 of 117
GSM BSS Swap Guide For internal use only
preferred
7
Combined
BCCH
IMSI
1 2 2 30238 423 107 127
8 0 3 2 45357 635 161 191Immediate assignment
preferred
9
TMSI
1 2 2 48494 679 172 204
10 0 3 2 72740 1018 258 306Immediate assignment
preferred
Note that in actual calculation, if the traffic models are used in another occasions, you need to change the traffic volume accordingly. In this case, the calculation results
will be different.
After completing planning the data, you need to design RNP parameter design report and project
parameter table.
II. Designing Other Data
For how to design handover algorithm and related parameters, power control algorithm and
related parameters, and channel allocation algorithm and related parameters, refer to the
corresponding guide and seek help from technical support engineers. In addition, you need to
design the related data specified in the RNP parameter design report.
III. Designing Data for Secondary Integration
If a BTS should be integrated into one BSC before being integrated to the destination BSC, you
should design two sets of data for the BTS. The frequency parameters can keep unchanged. You
need to check if adjacent data and LAC needs to be modified.
4.1.3 RNP Data Review
When reviewing the RNP data, you should pay attention to the following points:
If the corresponding documents are output, including project parameter table, swap planning
report, acceptance indicator confirmation and guide record, and RNP parameter design
report.
If the output documents and RNP data are correct, applicable, and complete.
If the network quality meet the customer’s requirement.
4.2 Network Interconnection Parameter Confirmation
4.2.1 A-interface Interconnection Parameters
The following table lists the A-interface interconnection parameters.
Type Item Remark
Relay and
signalling
Signalling point code Hex or decimal notation. The
signalling point code of BSC must
be consistent with that of MSC.
2023-04-27 HUAWEI Confidential Page 61 of 117
GSM BSS Swap Guide For internal use only
Signalling network mark
Domestic equipment is defaulted.
The signalling network mark of
BSC must be consistent with that of
MSC.
Coding scheme
It is defaulted to 14 digits. The
coding scheme of BSC must be
consistent with that of MSC.
G9MSC does not support A-
interface 24-digit coding.
CIC range and CIC of each
E1
Each timeslot of each relay circuit
of MSC and BSC must be
consistent.
TCSM maintenance slotThis slot must be set to unavailable
in MSC.
Signalling link slot
Generally, it is 16. The signalling
link slot of BSC must be consistent
with that of MSC.
Signalling link codeThe signalling link of MSC must be
consistent with that of BSC.
Signalling link number
You are suggested to configure 2
CCS7 links and 2 LPN7 boards for
each module.
TimersSCCP-TIAR length and
SCCP-TIAS length
Generally, they are defaulted
values. Sometimes the BSC data
needs to be modified.
Physical
connection
Selection BSC clock sourceSelect two good E1 lines and
extract clock from them.
Matching impedance of E1
The matching impedance of E1
must be consistent with that of the
transmission equipment.
CRC verificationThe CRC of MSC must be
consistent with that of BSC.
Service
function
Voice version supported
(HR, FR, EFR, AMR) The circuit
number must be corresponding to
the voice version.
Half-rate channel allocation
strategy
It is default to the BSC allocation
strategy.
Mobile country mode,
country code, mobile
network number
They must be consistent among
MSCs.
2023-04-27 HUAWEI Confidential Page 62 of 117
GSM BSS Swap Guide For internal use only
A-interface phase markFor new sites, it is PHASE2+, and
sometimes it is PHASE1.
CGIThe CGI of BSC must be consistent
with that of MSC.
MSC paging mechanism
Paging according to LAC is
recommended; otherwise the A-
interface signalling load will
increase.
Encryption algorithm
(A50, A51, A52). No encryption.
The encryption algorithm of BSC
must be consistent with that of
MSC.
T3212
The location update period of MSC
(VLR) must be longer than that of
BSC (VLR).
Handover relationship
Inter-BSC handover and inter-MSC
handover should be properly
configured.
4.2.2 Gb-interface Interconnection Parameters
Type Item Remark
E1
configuration
FrFormat FR
FR (frame relay) has two formats,
PCM_30 and PCM_31. No matter
which one is used, it should be fit for
SGSN.
CodeClass
There are two code classes, including
hdb3 and ami. No matter which one
is used, it should be fit for SGSN.
FrameType
The Gb-interface frame has two
types, including pcm_df and
crc4_mf. No matter which one is
used, it should be fit for SGSN.
ClockMode
The clock mode is configured as
“master” in SGSN. In PCU, it is
configured as “slave”.
BC
configuration
TimeSlot The timeslot occupied by bearer
channel must be consistent with the
data configured for BC at the SGSN
2023-04-27 HUAWEI Confidential Page 63 of 117
GSM BSS Swap Guide For internal use only
side.
DLCIType
It stands for data link connection
identifier and it must be consistent
with that in SGSN.
FR Mode
FR mode has two types, including
DTE and DCE. No matter which one
is used, it should be corresponding to
SGSN. Generally, it should be
configured as “DTE” in PCU.
FR protocol
The RF protocol must be fit for
SGSN. You are suggested to
configure it as “q933”.
NS-VC PVC
configurationNSEI
Generally, a NSE should be
configured the PCU and each BSC
that is connected to the PCU. The
NSEI must be consistent with that
configured for the SGSN.
Cell data
CellID
Cell ID is 15 bytes or 16 bytes in
length. The first 5 bytes (when the
cell ID is 15 bytes) or the first 6
bytes (when the cell ID is 16 bytes)
should be BCD. The last 10 bytes
should be hex and must be consistent
with the cell ID of the SGSN. In
addition, the last 10 bytes should also
be corresponding to CGI.
BSSID
BSSID is used to identify one BSS
from another. It should be consistent
with the data configured for SGSN.
4.3 Customer Suggestion
You should collect customers’ suggestions on network parameters and service features. If
contradiction is found in the suggestions, you should communicate with the customer for
confirmation in advance.
2023-04-27 HUAWEI Confidential Page 64 of 117
GSM BSS Swap Guide For internal use only
Chapter 5 Network Swap Preparations
After the completion of equipment test, you can prepare for the network integration. This section
introduces the network swap preparations.
5.1 Network Swap Solution Design and Review
5.1.1 Overall Swap Solutions
If a network includes multiple network elements, you should output the overall swap solutions
first. Generally, the overall swap solutions should contain the following points:
Introduction of the original network, including networking mode, network configuration,
network identifier, network characteristics, and swap difficulties.
Introduction of the swap characteristics and order.
Swap principles, such as security, smoothness, low cost, and high efficiency.
General swap ideas based on the characteristics of the original network.
Technical solutions used to swap each network elements, including M2000.
Technical parameters used to swap each network elements.
Precautions about the network swap.
Conclusion.
5.1.2 Designing and Reviewing the Solutions Used to Swap Network Elements
After installing the equipment and finishing the test and after the completion of network swap
planning, you can begin to design the solutions used to swap network elements.
For the specific solutions of swap implementation, see Chapter 6.
The whole solutions include network swap planning report and network integration solutions.
A swap project will affect the BTS configuration and combination mode, so you should
implement the swap according to customer’s requirements specified in tender document. In
addition, you should also provide the coverage and capacity solutions based on full
communication with the customer.
Generally, the coverage should become better after swap. However, you should thoroughly
analyze the tender document before beginning the swap. For some rigorous requirements
beyond engineering capability, you should explain the reasons to the customer and give
reasonable suggestions. In this case, R&D engineers, RNP engineers, and marketing
engineers should cooperate with each other to design a competitive solution.
2023-04-27 HUAWEI Confidential Page 65 of 117
GSM BSS Swap Guide For internal use only
On-site engineers should be familiar with all the coverage solutions provided by Huawei and
use the applicable one according to actual conditions.
Design the detailed swap solutions, including technical solutions, changeover solutions to
swap failure, swap planning, and personnel responsibility matrix. In addition, forms used for
subsequent test are needed, such as dialing test form, data check form, etc.
When designing network integration solutions, you must take all the possible risks into
consideration and communicate fully with the customer on these risks beforehand.
The swap solutions designed for large networks must be submitted to the technical support
engineers of the related regional divisions and the HQ for review before implementation. The
purpose of the review is to ensure the rationality, application, and correctness of the solutions.
Generally, after completing network swap planning report and integration solution, the on-site
project team should send the report and solution to the project monitoring owner and the owner
should organize the engineers concerned to review them. (The project monitoring owner can be
the project manager and the technical owner. If there is no project manager, you should send the
report and solution to the related product manager and RNO manager.). Note that the review
results should be copied to the related technical support engineers. For key projects and sensitive
projects, the on-site project team should organize R&D engineers, RNP engineers, marketing
engineers, and GBSS technical support engineers to hold a meeting to review the project. After
the meeting, a review summary is needed.
To win the customer’s acceptance and recognition of the swap project, you should communicate
fully with the customer on the reviewed swap solutions.
5.1.3 Swap Plan and Customer Confirmation
You should design an applicable swap plan based on manpower resource and confirm the
cooperation affairs from the customer, or you can work together with the customer to design the
swap plan.
5.2 Network Swap Preparations
5.2.1 Coordination Meeting and Customer Cooperation
You should submit the swap solution to the customer before integration and hold a swap
coordination meeting at the necessary time. Hereunder lists the confirmation points:
The swap solution must be recognized by the customer.
The time to start and end the swap; and the mark for successful integration and changeover
conditions.
The responsible swap persons of the customer and Huawei; the responsibility matrix of
project teams; and manpower arrangement. A dispatch management team should be set to
2023-04-27 HUAWEI Confidential Page 66 of 117
GSM BSS Swap Guide For internal use only
coordinate the implementation of the whole project. A supervisor and a skilled engineers
should be allocated for each project team. In addition, a standby team must be available.
Resource requirements, such as vehicles, test MS, test card, emergency lamp, and multi-
meter, light emitting diode, standby transmission equipment, standby board, keys, and other
common tools.
Customer’s coordination departments and related affairs.
When swapping the network, the engineers responsible for transmission, switch, and BSC should
cooperate with each other. The following table gives the responsibility matrix.
No.Cooperation
departmentCooperation affairs
1Transmission
Debug the A-interface transmission and Abis interface transmission for
BSC and debug the Abis interface transmission for BTS.
2 Switch Cooperate with the project team to modify the related data during swap.
3Original BSC
Modify adjacent cell relationship and take measures to change the BTS
back to the original state if integration failure occurs.
4Customer’s BTS
engineer
Coordinate with the project team to integrate BTS and check if the BTS
works normally after swap.
5RNO
Provide DT and CQT; handle problems in time; and optimize the network
after integration.
5.2.2 Integration Difficulty Analysis and Emergency Measures
You should evaluate possible risks and difficulties before network integration and design
corresponding emergency measures. For details, see the last chapter of this document.
In addition, you need to foresee what should be done if failing to integrate the network.
5.2.3 Personnel Arrangement, Vehicle Arrangement, Test Tool, Installation Tool, Equipment Preparation, and Emergency Measure
I. Personnel Arrangement
Network swap is a systematic project, so on-site owners should make good personnel
arrangement. Generally, Huawei personnel can be divided into the following groups:
Leader team
It is responsible for communication, guidance, and resource coordination. Generally, a leader team
consists of PM and local marketing and service leaders.
BSS project engineering team
It is responsible for implement the swap project. Generally, this group consists of general
technical owner, BSC supervisor, BTS integration test personnel. (Partner’s engineers are usually
responsible for the integration test.)
2023-04-27 HUAWEI Confidential Page 67 of 117
GSM BSS Swap Guide For internal use only
Emergency/standby group
If a project team cannot finish the corresponding task due to unexpected reasons, the
emergency/standby group will continue the task. In addition, the emergency/standby group is also
responsible for the equipment delivery and test.
RNP&RNO team
It is responsible for network planning and optimization and it consists of Huawei engineers and
partners’ engineers.
Support team
It consists of the experts from regional divisions and Huawei HQ and R&D experts. These experts
are responsible for emergency cases.
Customer’s cooperation group
The customer should arrange the contact persons for each group mentioned above and a general
contact person. In addition, technical engineers responsible for transmission debugging, data
modification, problem elimination, and network changeover are needed.
For the information of personnel arrangement, it should be provided according to the following
table.
Role Name Telephone Responsibility
Customer’s general
coordinator
Monitor and coordinate the whole swap
project.
Huawei general owner Arrange and dispatch Huawei engineers.
Customer’s cooperation
personnel
Coordinate the personnel, vehicle, SIM card,
dialing test, etc.
Cooperate with Huawei engineers on BSC
integration, transmission, and dialing test.
Responsible for BTS integration, equipment
room entry, and lighting.
Responsible for MSC cooperation and BSC
cooperation.
Customer’s RNO engineers are responsible
for cooperating with Huawei engineers on DT
and parameter adjustment. In addition, they
should monitor the network quality on the
next day after integration and handle
emergency cases.
Huawei BSS integration
personnel
Responsible for on-site BSC integration and
acceptance.
Responsible for on-site BTS integration and
check.
2023-04-27 HUAWEI Confidential Page 68 of 117
GSM BSS Swap Guide For internal use only
Role Name Telephone Responsibility
Owner of network optimization. Responsible
for DT after integration and monitoring the
network on the next day after integration and
handling emergency cases.
Support BSS/NSS/GPRS/M2000 at the
remote end.
Responsible for MSC cooperation if
necessary.
Automotive personnel
Note:Two engineers are needed in BSC room. One is responsible for BSC test and A-interface dialing test. And the other is responsible for confirming the identifiers of A-interface port and Abis-interface port and debugging BTS.
Generally, a team is responsible for integrating two BTSs at most. And the personnel arrangement
depends on actual conditions.
II. Vehicle Arrangement
Vehicles are used to perform DT and send BTS personnel. The vehicle arrangement should be
finished several hours before integration. Generally, each DT team needs a vehicle. For other
cases, the vehicles are arranged according to actual conditions.
III. Test Tool and Installation Tool
Tool Purpose Remark
Digital power meter Test TRX transmit power
Match-terminated line Used for power test
When antennas cannot be
connected, the match-terminated
line can function as the antenna.
Site Master
Test the standing wave of the
antenna and feeder system and
locate antenna failure.
Pay attention to the connectors of
the matching cable and configure
straight filter when installing
tower amplifier.
Test MS
It is used for dialling test and
checking if the handover
relationship, cell direction, and
frequencies are consistent with the
designed ones.
It is used together with the test
card.
Other operators’ SIM cards They are used for the connection
between the equipment room and the
dispatch center when the BTS is
unavailable during integration. Note
It is used to ensure smooth
communication during network
swap.
2023-04-27 HUAWEI Confidential Page 69 of 117
GSM BSS Swap Guide For internal use only
that you should have a
understanding of the coverage of the
original network first.
Portable computerIt is used for local maintenance and
upgrade.
Serial port, BTS maintenance
software, and BTS host software.
BTS local maintenance lineIt is used to connect the TMUs of
each site.
Cutter
ScrewdriverCross screwdriver and shovel
screwdriver
If there is small BTS, you should
use special screwdriver.
Multi-Meter
It is used to measure the voltage of
the BTS and the current of the tower
amplifier.
Light Emitting DiodeIt is used to check if the transceiver
is normally connected.
8/10 ejector lever
12-inch adjustable wrenchIt is used to connect feeder
connectors.
Packet lamp It is used for night swap.
120-Ω clamp tool It is used for 120-Ω transmission.
120-Ω jumper It is used for 120-Ω transmission.
Electric ironIt is used to make the connectors of
75-Ω transmission cable.
Feeder connector making
tool
It is used to make connectors of
feeder and jumper.
IV. Spare Part Preparation
The spare parts should be prepared according to field needs. The spare parts of the BSC, BTS,
TRX, and TMU should be available. Generally, the spare parts are included in contract; otherwise
you need to prepare the related spare parts in advance and take them to the field at the integration
night.
V. Emergency Measures
The emergency measures must be made in advance.
5.2.4 Version Confirmation and License Application
You need to check if the current version support the functions required in the contract and check if
the old license can still be used. Note that the software versions should match BSC, PCU, BTS,
and M2000. For the project supervisors, they should apply for the correct software version
through related electronic process. And the versions are available after the corresponding
technical support engineers have reviewed the application.
2023-04-27 HUAWEI Confidential Page 70 of 117
GSM BSS Swap Guide For internal use only
5.2.5 Swap Data Design and BTS Swap Preparation
I. BSC Swap Data
The BSC swap data includes the data of the Huawei BSC and data of the BSC of the original
network, the former of which should be prepared by Huawei engineers and the later of which
should be prepared and collected by the customer.
Huawei BSC data includes adjacent cell relationship and MSC interconnection data. You
need to confirm if the Huawei data is supported by the customer. In addition, you should
note that if the BSCs of the original network are under the control of one MSC and if the
LAI and CGI of the original network can be reallocated.
For the BSC data of the original network, you need to modify the handover-related data
only. That is, add adjacent cell data to the original cells that have been swapped and
configure the Huawei cells as adjacent cells of the ordinal cells.
Hereunder introduces the steps to design Huawei BSC swap data:
1) Submit the reviewed RNP&RNO data to the project supervisor
After the RNP&RNO data has been reviewed, you should submit the RNP parameter design
report to the project supervisor. For details, see the previous introductions.
2) Design BSC hardware data, BTS hardware data, interconnection data, and network planning
data. After that, the project supervisor should check the data according to the following
instructions:
If the data is fit for the version used for deployment.
If all the data is correctly designed.
If the configuration data of the BSC hardware is consistent with the designed file. For
example, the position of the transparent BIE must be fit for the actual connection and the
FTC board configuration must also fit the actual connection.
If the type and port configuration of the BTS are in accordance with the actual connection.
If external cell data is added to Huawei data. In addition, if the parameters (such as phase
mark and CIC) related to A-interface are necessary.
Make sure that the data can be normally converted on BAM.
Make sure that if the functional hardware supports related functions, such as half rate
function, and check the corresponding 14FTC/34BIE.
3) Check DBF data
After designing the project supervisory data, you should submit the DBF data to the network
planning owner for review. And the network planning owner should use OMC program and Nastar
to check the DBF data. In addition, the network planning owner should also check the followings:
If each algorithm is fit for planning design.
If all the parameters are configured and correct.
If the values of the parameters are greater than the suggested values.
If the adjacent cell data is completely and correctly configured.
2023-04-27 HUAWEI Confidential Page 71 of 117
GSM BSS Swap Guide For internal use only
If the configuration of half rata and MAR is fit for the design.
If any abnormal information is found, you should correct the information. After that, create an
“Autocfg.dat” and put all the above information into the file. And this file should be sent to
engineering personnel for loading.
II. MSC Data
The destination (signaling) point code of the LAC and CI of the BTSs to be swapped should be
changed. Since the BTSs will be under the control of other BSCs after swap, the destination
(signaling) point code stored in the MSC database should be changed accordingly.
To ensure the smooth interconnection and interworking, you should confirm the information of
the Huawei BTSs that need to be added to the original system. In addition, you should also
confirm that the CGIs and LACs of all the cells are defined in MSC. Note that the definitions of
CGI and LAC vary with operators, so you need to check them one by one. If cross-province
handover or cross-region handover will appear, you should notify the customer to modify the
related information after the integration of the network.
For packet service, you need to confirm the data related to LAC and SGSN. For prepaid service,
you need to consider if the routing information of the prepaid subscribers should be modified.
III. PCU Data
You need to check the following data:
IP address configuration (If the IP address is correctly configured.) Routing information (If the routing information is correctly configured.) Hardware data configuration (If the POMU board, RPPU board, L2PU board, and PMC
board are configured at the corresponding slot.) E1 slot configuration (If the RPPU board number, E1 number, and E1 sub-slot number are
correctly configured. And if the E1 slot configuration at the PCIC side is consistent with that of the BSC side.)
LAPD link configuration (If the link configuration is consistent with that configured at the
BSC side.)
ATTR data configuration (Pay attention to check the configuration of CGI and routing area.)
GPRS data configuration (Pay attention to check the network mode of operation and other
defaulted values.)
Dynamic adjustment parameter configuration (CS type and license restriction)
PDCH parameter configuration
E1 configuration at Gb interface (Pay attention to the load sharing principle, the backup
principle, clock, frame format, code, and other interconnection parameters.)
BC configuration (Pay attention to the configuration principle and interconnection setting.)
NS-VC configuration
Cell data configuration at Gb interface (CellID and BSSID)
IV. SGSN Data
The SGSN data is mainly prepared for PCU swap.
2023-04-27 HUAWEI Confidential Page 72 of 117
GSM BSS Swap Guide For internal use only
V. BTS Integration
You need to get the key to the equipment room. The BTS integration is performed according to BTS survey, but you can finish the preparations in advance.If many BTSs are to be integrated, you need to carry computers to load the software; otherwise the load at the BSC side will become heavy.
VI. Network Optimization Integration Preparations
After testing the original equipment, collecting the swap data, and planning the frequencies and
parameters, you should confirm the test time, place, and lines for the integration. For details, see
RPO401-01 DT preparation self-check list (G/C/W).
Note:A work memo is needed for data design and modification. The memo should include modification
contents, required feedback time, name and ID of engineering personnel, engineering time, etc. At
last, this work memo must be confirmed and loop closed.
In addition, you should confirm the transmission according to the following instructions:
The labels of the A-interface, Abis-interface, and Gb interface (the three interfaces locate at
the GBSS side and GBSS is installed on DDF rack) are confirmed and placed in due
position.
The trunks are normal and the status of the indicators of BIE board and MSM board is
normal.
A-interface transmission is fit for CIC configuration according to project file and data.
The connection between each BTS and the concatenation relationship of each are correct
according to project file and data.
Enough jumpers should be prepared.
The A-interface transmission at the MSC side and the Gb interface transmission at the SGSN
side should be confirmed.
5.2.6 Pre-integration
Pre-integration is often used in a swap project. You should judge if the pre-integration is necessary
according to actual conditions. If yes, the pre-integration should also be implemented according to
strict steps and plans. If any problem is found according to the pre-integration, you should correct
them and make a conclusion immediately. All the information collected according to the pre-
integration should be sent to the related experts for analysis.
If the pre-integration results are very good and win the customer’s reorganization, you should
begin formal integration. Before designing the pre-integration solutions, you can communicate
with the customer in advance to reach an agreement on the integration.
2023-04-27 HUAWEI Confidential Page 73 of 117
GSM BSS Swap Guide For internal use only
Chapter 6 Swap Implementation
This chapter introduces the swap implementation. Since there is time restriction on network
integration, detailed arrangement and test are important. Hereunder lists the points that need
special attention:
Network swap is a systematic project. To finish the whole project, you need the customer’s
help. Therefore, the project team should be well managed and the clear responsibility matrix
should be divided.
According to past experiences, transmission debugging has the greatest effect against the
swap project, because it can only be performed at the swap night. Therefore, you need to
fully communicate with the customer on whether to delay the network integration if the
transmission conditions are not met.
Customers often pay much attention on duration during network swap. For Huawei,
however, to enhance the customer satisfaction rate, engineers should ensure the engineering
duration, quality, and cost.
6.1 Network Integration on the Swap Day
6.1.1 Network Integration Schedule
The following table details the network integration schedule and responsibility matrix.
Time Product Owner Responsibility
The day before sw
ap
Technical sup
port engineers
If on-site engineers need remote support,
technical support engineers should notify the
related department to make preparations in time
and provide the integration solution and data in
advance. Note that the technical support
engineers for network integration include the
RNO technical support engineers.
PM Organize integration coordination meeting,
deciding integration time, and confirm other
precautions with customer, including vehicle
arrangement, test tool, personnel cooperation,
contact method, and internal problem reporting.
Daytime of the
swap day
Technical ow
ner or PM
Hold a meeting participated by all the engineers
related to the project to detail the integration
arrangement, announce the integration time and
contact method.
BTS BTS personne
l/customer
Check if BTS has been in the equipment room
2023-04-27 HUAWEI Confidential Page 74 of 117
GSM BSS Swap Guide For internal use only
and if the key to the room is available;
Check if all the hardware is present when
arriving at the engineering site and finishing the
related preparations;
Print the integration steps and precautions.
RNP RNP&RNO engineers prepare for DT, confirm
DT data and DT line with the customer, and
assign the DT task to partner.
Each network el
ement
Check the health condition and status of all the
equipment, and check the necessary terminal
tools and components.
Transmission co
nfirmation
Reconfirm the transmission with the customer.
If the transmission conditions are not met,
cancel the integration.
22:00 o’clock of
the swap day
PM or general
technical
support
coordinator
Communicate problems with the customer’
senior management layer.
General coordinator for on-site affairs.
General
technical
support and
experts of
each network
element
Actual integration, problem collection handling,
HQ contact person.
BSS
Integration problem handling and A-interface int
erconnection.
Supervise engineers to enable BTS;
Perform dialing test for CS/PS;
Check if the antennas of some cells are
inversely connected;
Check if it is necessary to use test MS to test the
environment around the BTS;
Check if the frequency information is consistent
with the corresponding cell;
Locate BTS problems.
Monitor alarming information and traffic
statistics.
Monitor and coordinate the implementation
progress.
RNP Monitor the BSS;
Perform CS test;
Collect and analyze the DT data of each region.
MSC Check A-interface interconnection;
Add handover relationship;
2023-04-27 HUAWEI Confidential Page 75 of 117
GSM BSS Swap Guide For internal use only
Monitoring signaling;
Analyze alarming information.
Analyze traffic statistical data and bill data;
Locate and handle problems;
Monitor signaling.
Cooperate with each other for related test;
Check UMS alarming information;
Coordinate with each other to handle DDF
problems.
PCU Observe the equipment;
Cooperate with each other for related test;
Correct user data;
Check alarming information;
Monitor each registered cell number.
SGSN Gb-interface interconnection and test.
M2000 OMC management;
Problem checking and handling.
The day next to
swap
PM Customer communication;
Integration confirmation
All Watch equipment room;
Check alarming information;
Analyze traffic statistics;
Respond to user complaints.
RNP Continue drive test (data services, such as GPRS
and EDGE, should be tested);
Compare and analyze the data before and after
the drive test;
Optimize related parameters.
6.1.2 Checking Each Network Element (Before Integration)
I. Checking GBSS Running Status
You should record the running status of the system before integration, including the alarming
information, traffic statistics, and the running status of each board and BTS.
1) Query the running status and alarming information of the BTSs attached to the original BSC
and record them. Meanwhile, report them to the related personnel of XXX Company and
require them to solve the problems affecting network integration as quickly as possible.
2) Check the status of each BSC board at the maintenance console and check if the indicator of
each BSC board is correct.
3) Check the status of the relay circuit of the A-interface. The NSS engineers of XXX
Company should cooperate with Huawei engineers to query the status of the relay-circuit of
the A-interface at the MSC side.
2023-04-27 HUAWEI Confidential Page 76 of 117
GSM BSS Swap Guide For internal use only
4) Check the status of each No.7 signaling link and query the status of LAPD link.
5) Check the status of each enabled BTS, BTS board, and channel. (For example, check if there
is congested channel.)
6) Check the status of special equipments, such as the semi-permanent connection equipment
and timeslot extraction equipment.
7) Check if there is other abnormal condition.
II. Confirming GPRS Status
At the BSC side, you need to check the status of the corresponding LAPD link. If the status is
multiframe setup, the communication between BSC and PCU is normal. You are suggested to
sample some BTSs to check the PDCH status at the maintenance console.
If you need to log in to PCU, you can query the working status of the PCU with the guide
provided by related support engineers according to Appendix 4.
III. Checking the Status of Related Network Elements
The status of the A-interfaces of the MSC and SGSN, the signaling status, and the CPU load must
be checked.
6.1.3 BSC Integration
This section details the work that should be finished in the equipment room.
Work related to BSC
After confirming that the BSC hardware runs normally, you should load the integration data
and check if the status of the BSC is normal after integration. In addition, you need also
check if each BSC board runs normally, if there is important alarm, if the traffic statistical
indicator is normal, and if there signaling is normal.
Work related to A-interface
The A-interface resource is scarce, so you should expand the network capacity at the
integration night. In this case, you need to confirm the transmission for A-interface
expansion and check the A-interface circuit status.
Work related to BTS cooperation
After BSC runs normally, you need to notify the engineers concerned to begin BTS
integration; Confirm the transmission interface of the original BTS; Pay attention to use light
emitting diode to confirm the relationship between transmission and reception; Notify the
engineers concerned that the new BTS and the original BTS can be disconnected. After
Huawei BTS is powered on and the transmission of the BTS becomes normal, you should
check the running status of the BTS at the BSC side. If necessary, you need to force the
related software to be activated. If any problem is found, you can coordinate the BTS
supervisor to solve the problem together.
Work related to MSC coordination
2023-04-27 HUAWEI Confidential Page 77 of 117
GSM BSS Swap Guide For internal use only
Confirm that the data of the location area of the corresponding MSC has been set.
Check if the traffic statistics, alarm, and maintenance function of the M2000 network
management system are normal.
Register and observe traffic statistics
Generally, the following tasks should be registered at the traffic statistics console, including
BSC overall performance measurement, CPU performance measurement, MTP link
performance measurement, SDCCH performance measurement, TCH performance
measurement, random access performance measurement, intra-cell handover performance
measurement, power control performance measurement, call drop performance
measurement, Rxqual performance measurement, Rxlev performance measurement, cell
performance measurement (2), cell performance measurement (3), TRX call drop
performance measurement, and A-interface relay performance measurement.
Register the traffic statistical tasks reflecting KPI at the MSC and SGSN.
Alarm query and analysis; alarm solution; abnormal alarms related to BSS; important alarms
related to BSC.
Check the status of the corresponding network element is normal.
Cooperate with the related engineers to handle BTS problems.
Cooperate with the related RNO engineers to correct data.
Record abnormal problems.
6.1.4 MSC-Related Work during BSC Integration
I. Debugging A-interface
The A-interface data should be debugged at the night (from 23:00 to 3:00). In addition, you should
test if the MS can access the network and if the location update and handover can be performed
normally. The overall dialing test contains various services, including intra-office call, calls
corresponding to each handover, toll call, and intelligent service. Moreover, you should verify if
each call procedure is correct.
II. Integrating BSC after A-interface Debugging
To ensure that the transmission between BSC and Huawei MSC is available, you should perform
overall dialing test. The test contains various services, including intra-office call, calls
corresponding to each handover, toll call, intelligent service, call transfer, etc.
If there are multiple BSCs to be integrated, you can perform the integration by steps. During BSC
integration, you need to pay attention to the following points:
If several BSCs belong to the same MSC in the original network, the BSCs must be
integrated to the new MSC in one time.
The handover data applied to the old MSC and new MSC must be adjusted.
During the integration, both the old and new MSC are valid. In this case, you should
preserve adequate inter-change circuit according to the traffic between the old MSC and new
MSC.
2023-04-27 HUAWEI Confidential Page 78 of 117
GSM BSS Swap Guide For internal use only
III. Conclusion
Hereunder summarize the MSC-related work needs to be done during GBSS integration. The
seamless cooperation between MSC and GBSS is the key to a successful swap.
1) Test phaseThe customer needs to prepare redundant E1 for A-interface. The E1 must be interconnected
with Huawei BSC when the BSC and BTS are powered on. The data related to Huawei BSC
must be added to the core network and interconnected with A-interface. Note that all the
services must be tested.
2) Integration preparation
Huawei is responsible for BSC-side transmission, and the customer is responsible for
transmission layout and debugging from core network to DDF rack.
The data related to BSC integration must be made at the core network.
Adjacent cell relationship must be designed before the swap of BSC and MSC. If there is
cross-MSC cell, you need to design the adjacent cell relationship at other MSCs.
If some BTSs are not successfully swapped, you need to recover the data and adjacent cell
relationship related to the corresponding BTSs.
If new LAI is used, the new LAI must match the charging information and intelligent service
if the information and service are available.
3) Resource requirements at the core network Switching side personnel
DDF rack
Power supplier
Relay device (2M)
Relay signaling
Test card and test MS
Dialing personnel
Personnel cooperating with the modification of MSC-related data
Pre-paid service debugging and voice resource test
6.1.5 BTS Integration
BTS integration involves multiple scenarios. Whether there is adequate room for BTS installation,
whether there is standby transmission equipment, and whether the direct current power supply is
available are three main factors affecting the BTS integration. The antenna feeder does not affect
the integration because it will not be installed at the integration night. Eight possibilities are
included in the three factors. Hereunder details the BTS integration:
Disassemble the original BTS. The disassembly has no side or negative effect against the
network.
2023-04-27 HUAWEI Confidential Page 79 of 117
GSM BSS Swap Guide For internal use only
Prepare the related tools and vehicles before integration. After the arrival of the integration
team, the BTS door should be opened and the light in the equipment room should be
enabled. In some special cases, engineers must get the permission of the third party before
entering the equipment room, so you should explain this to the customer and make
preparations in advance.
Only the direct current power supply cabinet is discussed in this document. For alternating
current input, you need to communicate with the customer in advance.
To enhance working efficiency and increase test time, you must finish the related work
before integration.
In some places, you have to move not only the BTSs to be swapped but also other networks
or power supply equipment. In this case, you need to communicate with the customer on this
action.
The partner is always responsible for BTS integration, so you must take measures to ensure
the engineering quality
I. Installation Steps
This section introduces the steps to install the BTS when no standby transmission, no power
supply cabinet used for replacement, and no position restriction.
After the arrival of the BTS, you need to check the places where the power supply cable is long or
the transmission needs to be re-arranged in advance.
1) After confirming the BSC port, confirm that the BTS-side transmission port is correct
through self-loop test.
2) Disconnect the power supply of the BTS and move out the original power supply cabinet and
BTS. When moving out the BTS, you do not have to move the connection line and antenna
feeder so that that the BTS can be changed back to the original position in emergency
conditions.
3) Finish installing Huawei power supply cabinet, power on the cabinet with alternating
current, and observe the running status of each module. After that, disconnect the power
supply.
4) Install Huawei BTS at the corresponding location; connect the transmission line, power
supply cable, and grounding line. If the time is urgent, you do not have to fix the BTS and
secondary installation is allowed.
5) When Huawei BTS is powered on, observe the status of the indicator.
6) Connect transmission to Huawei BTS and check if the status of LIU1 is normal. After the
transmission is normal, check if the BTS runs normally. During this period, do not
disconnect the power supply of the BTS. If software needs to be upgraded, you need to
notify the BSC to upgrade the related software or perform near end upgrade.
7) After the BTS runs normally, you can connect the jumpers and the lightening protector. If
the time is urgent, you do not have to fix them and secondary installation is allowed.
2023-04-27 HUAWEI Confidential Page 80 of 117
GSM BSS Swap Guide For internal use only
8) Finish the standing wave test from the CDU interface is necessary. No instrument can be
used to observe the standing wave indicator of the CDU.
9) After the BTS is initialized, perform dialing test and handover test. In addition, you should
test power and confirm cell direction. Other ATP tests can also be performed.
10) If all the test results are normal, you should perform drive test for network optimization. If
there is no problem, it means that you have succeeded in integrating the network.
11) For the convenience of network maintenance, you should paste labels for the corresponding
cells.
12) Finish connecting the match heads and EAC; install the sensor; and test the EAC connection
and function.
13) Install battery or battery rack.
14) If the drive test results are normal, it means that the BTS has been successfully integrated.
15) Package the old equipment if necessary.
16) Collect the test record and tool; tidy up the engineering field, and return the key.
II. BTS Swap Steps
Hereunder provides a swap example, which specifies the BTS swap steps:
1) Shut down the original BTS
When arriving at the engineering field, the BTS integration team should phone the transmission
changeover team and shout down the power supply of the original BTS. Generally, this action is
taken at 00:00 or later.
In this case, Huawei should wait for the xx company to make preparations, and the xx company is
responsible for shutting down the original BTS.
2) Integrate BTS power supply
After confirming that the polarity, voltage, and label of the power supply are correct, you can
connect the power supply to Huawei BTS.
In this case, Huawei is responsible for providing power cable and putting the cable near the
equipment room, and the xx company is responsible for removing the power supplier of the
original BTS and connecting the Huawei BTS power supplier.
3) Integrate Abis interface relay
Disconnect the Abis interface relay (2M) from the original equipment and connect it to Huawei
BTS through DDF rack.
In this case, Huawei is responsible for providing the transmission from BTS to DDF rack, and the
xx company is responsible for removing the transmission between the original BTS and BSC and
connecting it to the DDF rack for Huawei BTS.
4) Check BTS installation and power-on the BTS
2023-04-27 HUAWEI Confidential Page 81 of 117
GSM BSS Swap Guide For internal use only
After the power supplier and transmission are connected, you need to confirm that the Huawei
BTS is well installed, and then power-on the BTS. Huawei BTS will send loading application to
BSC after performing self-check.
In this case, Huawei is responsible for checking the BTS installation, powering on the BTS, and
testing the BTS transmit power. (The connector of the lightening protector is the test interface, so
you need to check if the power fluctuates at each connector, because the power should keep stable.
Note that digital power meter is preferred.). And the xx company is responsible for cooperate with
Huawei in the test.
5) Dial test phone
After the BTS has finished loading data automatically and all the cells are available, you should
perform dialing test. The called numbers are decided by test engineers. Ten calls should be made
for each cell. Finally, you need to send the test results to the BSC maintenance team.
In this case, Huawei needs to cooperate with the test engineers to solve problems occurred during
the test, and the xx company should perform the dialing test according to plans and confirm the
BTS working status.
6) Integrate antenna feeder system
After the dialing test, you can integrate the antenna feeder system. That is, remove the indoor soft
jumper of the original antenna feeder and connect the corresponding antenna feeder to Huawei
BTS.
In this case, Huawei is responsible for providing BTS interface for the jumper and finishing
standing wave test. (The test interface locates at the CDU antenna connector. so you need to check
if the standing wave ratio fluctuates at each connector, because this ratio should keep stable.).
7) Check drive test
After all the BTSs are integrated, you can perform drive test for them. The test contents include
cell direction, signal strength, handover, and interference.
In this case, Huawei RNO engineers should perform drive test to check the coverage quality, and
the xx company should provide vehicles and cooperate with Huawei RNO engineers in the drive
test.
8) Analyze the integration
To have an overall understanding of the network after integration, you can analyze the drive test
results. The test results can work as reference for next-phase network optimization.
In this case, Huawei is responsible for analyzing the coverage quality after BTS integration and
providing reference data for the next-phase network optimization, and the xx company is
responsible for analyzing the network quality after BTS integration and putting forward network
optimization requirements.
9) Deal with original BTS
2023-04-27 HUAWEI Confidential Page 82 of 117
GSM BSS Swap Guide For internal use only
Huawei engineers are not responsible for dealing with the original BTS. The xx company is
responsible for dealing with these old goods either by themselves or with the help of the third
party.
6.1.6 PCU Integration
Pb interface (it is defined by Huawei) connects PCU to BSC. Before integrating PCU, you need to
debug the Pb interface. For details, see the related deployment guides.
I. Gb Interface Integration Steps and Precautions
1) Check Gb interface data configuration, including E1 configuration, BC configuration, NC-
VC configuration, and cell configuration.
2) Check hardware connection to make sure that the Gb interface board is inserted at the right
position.
3) Test transmission self loop to make sure that the E1 line is correctly configured for Gb
interface.
4) Check E1 connection. If the green light of the PMC board flashes slowly, the E1 connection
is normal.
5) Check BC state through “mt fr bc show statinfo all”. If the link consistency check is
available and the user is not blocked, it means that the BC state is normal.
6) Check the NSE state through “MT BVC SIG SHOW <NSEI>” to see if it is normal.
7) Check the NSVC state through “mt nsvc showstate <NSEI><NSVCI>”. If the NSVC is
unlocked, it means that it is normal.
8) Check the Signal BVS state through “mt bvc signal show state <NSEI>” to see if it is
normal.
9) Check the PTP BVC state through “mt bvc ptp show state <NSEI> {<BVCI>|all” to see if it
is normal.
II. Traffic Statistics Indicator Registration (PCU)
You are suggested to register traffic statistics indicators related to PCU. The seven indicators
reflecting the running condition of PCU must be recorded, including BSC overall performance
measurement, Pb interface performance measurement; G-Abis interface performance
measurement, Um interface performance measurement, etc. The six indicators reflecting the cell
details are recommended. For the following indicators, the ones in black must be registered, and
the others are optional.
CPU measurement
BSC overall performance measurement
G-Abis interface performance measurement
Pb interface performance measurement
2023-04-27 HUAWEI Confidential Page 83 of 117
GSM BSS Swap Guide For internal use only
Cell performance measurement: packet assignment performance measurement; uplink TBF
setup and release performance measurement; downlink TBF setup and release performance
measurement; PDCH resource performance measurement; PDCH peak value performance
measurement, uplink RLC data transmission performance measurement, downlink RLC
transmission performance measurement, radio channel performance measurement, resource
maintenance performance measurement.
6.1.7 Network Optimization Arrangement
The test performed at the swap night is to check if the services are normal and if there are serious
problems.
DT lines should cover each cell and the areas covered by the major lobes of the cells. At least the
bi-directional handover between the edge of one cell and its adjacent cell should be tested. Since
the network integration is often performed at the night; you may not access some areas or section.
In this case, you should plan the DT line in advance.
According to the DT, the coverage should become better after network integration. In addition,
cell parameters should be correctly set, and the frequency and handover should be normal. If some
adjacent cells are missing or the antenna feeder is inversely connected, you should contact the
project team immediately.
The baseband frequency hopping will stop if there is any TRX problem. Therefore, if you
discover the problem of this kind during the test, you should contact the project supervisor
immediately.
In addition, you should check if the GPRS function is available for the GPRS cells.
Note:The RNO team and project team should tell each other the contact persons responsible for the
integration in advance. After enabling the BTS, the project team should notify the standby DT
team to perform drive test. And the project team should wait for the DT results. If the DT team
finds any problem, they should tell the project team to solve the problem immediately. If the
project team has multiple BTSs to be swapped at that night, the nearby BTSs should be swapped
first. In this case, the project team should notify the DT team to perform the drive test after the all
the BTSs are swapped. And the project team should still be present in the field to wait for the DT
results.
2023-04-27 HUAWEI Confidential Page 84 of 117
GSM BSS Swap Guide For internal use only
6.2 Emergency Measures and Changback for Network Integration
6.2.1 Emergency Measures
I. Emergency Measures for BSC
If you meet difficult problems, you can seek help from the technical support engineers of Huawei
to locate the problem. Meanwhile, BSC supervisor must monitor the data such as interface
messages and BTS log for further analysis. If the problem cannot be solved within the time
required by the customer, you should change back the transmission to the original BTS; otherwise
normal communication will be terminated.
II. Emergency Measures for BTS
If you find any problem concerning BTS transmission, you should notify the problem to the
engineers responsible for guaranteeing transmission.
If there are bad components or boards, the BTS emergency group must replace them immediately.
If the Operation and Maintenance Link (OML) or Radio Signaling Link (RSL) cannot be
established, you should contact the engineers responsible for BSC integration immediately.
6.2.2 Changeback Principle Description
You need to confirm the time and condition of changeback. Generally, the changeback can be
divided into BTS changeback and BSC changeback. BSC changeback should be performed before
BTS changeback, so the BSC changeback is a relatively easy task. It is important to find problems
through changeback and solve them accordingly for subsequent operation.
When designing changeback solution, you need to back up the data to be modified for the original
BSC and MSC. During network swap, you are suggested not to modify and delete other data
except the data of the original BSC and the adjacent cells, because this is convenient for secure
changeback. During changeback, you should pay attention to the following points:
Export the frequency planning data (including frequency hopping, BSIC, etc) according to
the backup data of the original network because the data will be used for the changeback. If
there is changeback failure, you need to check the frequencies planned at edges.
If the whole swap fails, you can completely use the backup data for the adjacent cells. If the
swap for some of the sites fails, you need to design new data for the edge adjacent cells and
modify the corresponding adjacent cell relationship between the original BSC and Huawei
BSC.
The planning data, such as LAC and CI, should be exported according to the backup data
during changeback, because the planning data should be modified in the MSC. When the
swap for some of the sites fails and if the planning data such as LAC and CI is different from
that in the original network, you need to decide if the LAC and CI should be changed back to
the original ones; otherwise the network will be negatively affected.
2023-04-27 HUAWEI Confidential Page 85 of 117
GSM BSS Swap Guide For internal use only
If the BSC-related data used in the original network does not have to be deleted, you can use
the backup data.
The concatenation BTSs should be changed back.
The data related to the changeback BTSs should be modified in the MSC.
6.2.3 Changeback Measures
I. BSC Changeback
Generally, BSC can be debugged and interconnected successfully in advance, but the possibility
for you to test the network at the integration night is small, because the time is urgent and the
preparations are inadequate. In addition, some important functions are not supported, the
important boards fails, or the customer’s A-interface is not in due position.
1) If all the BSC is changed back and shares one MSC with the original BSC, you should do the
followings:
Ensure the A-interface transmission of the original BSC
Recover the data of the original BSC
Recover the MSC data
Recover the data of the BTSs under the control of the original BSC
2) If all the BSC is changed back and uses another MSC, you should do the followings:
Ensure the A-interface transmission of the original BSC
Recover the data of the original BSC
Recover the data of the two MSCs
Recover the data of the BTSs under the control of the original BSC
II. BTS Changeback
If BTS integration fails, it should be changed back to the original status. If the new BTS cannot be
opened at the 5:00 a.m or the coverage performance decreases rapidly according to drive test, the
BTS should be changed back before 6:00 a.m. In this case, you should do the followings:
Reset the BTS, power supply, and antenna, and check the working status of the BTS.
Reset the transmission.
Modify the neighbor cell relationship between the original BSC and Huawei BSC.
If the two BSC does not belong to one MSC, the inter-MSC handover relationship will be
present.
If the CGI is used for route analysis in the MSC, you need to modify the related data.
For the convenience of problem location and analysis, Huawei BTS engineers should record the
details and test data, and the BSC supervisor should monitor and save the corresponding data.
2023-04-27 HUAWEI Confidential Page 86 of 117
GSM BSS Swap Guide For internal use only
6.3 Network Monitoring on the Day Next to Swap
The network monitoring on the day next to swap is quite important. You should arrange engineers
to monitor the traffic statistics closely and pay attention to the fluctuation of each indicator and
customer’s complaints. If there is abnormal conditions, engineers should analyze problem from
the following perspectives:
Check if the history alarms of the BTS and BSC are normal, because failures related to
transmission, antenna, and board will affect KPI and result in complaints.
Check if the traffic volume in each cell is normal and if there is no traffic at some sites.
Check if the important indicators, such as call drop rate, handover success rate, and
congestion rate are normal.
Check if the success rate of the handover between different customers’ equipment is normal.
Analyze the customer’s complaints and solve them. After solving the problems, you should
notice the customer immediately. In addition, you need to create a history record for the
complaints to make sure that no problem will be missing.
If no problem is found, the project team should feed back the results (including traffic statistics,
drive test, and dialing test) to the customer. In this case, it can be taken that the network has been
successfully integrated.
Chapter 7 After-Swap Network Quality Monitoring and
Optimization
To ensure that the final network acceptance can pass, you should strictly monitor the network
quality for a period of time after the swap. The tasks involved in network monitoring include
online equipment problem handling, network monitoring, and network optimization.
7.1 Online Equipment Problem Handling
7.1.1 Hardware Problem Handling
The hardware problems occurring after swap must be handled immediately; especially the BTSs
providing converge for VIP areas should be more carefully monitored.
When the project team handles the coverage problems, such inverse connection of antenna feeder
and poor Rxlevel, network optimization supervisor or project supervisor should confirm that the
problems are really solved. To solve conversation problem caused by board failure, you need to
block the OMC and check the utilization of channels and signaling.
2023-04-27 HUAWEI Confidential Page 87 of 117
GSM BSS Swap Guide For internal use only
No alarm will be generated if the performance of some hardware decreases. Once discovering
such problem, network optimization engineers should solve the problem with the coordination of
BSS engineers.
If the traffic volume of a cell is low, the problem may be related to uplink and downlink.
If the channel utilization rate is low, call drop rate is high, and there is great interference, the
problem may be related to the decrease of the TRX performance and combiner and divider
performance.
7.1.2 Complaint Handling
Users’ complaints must be handled quickly. Generally, complaints can be divided into the
following categories:
Coverage complaints
Voice quality complaints (one way audio, no audio, cross-talking, call drop, echo, noise, etc)
Service failure complaints (incoming call failure, outgoing call failure, fax service
unavailable, etc)
PS complaints (slow network connection, GPRS service unavailable, etc)
7.1.3 Alarm Analysis
I. BSS-Focused Abnormal Alarms
The following table lists the alarm names according to BSC32.
Alarm ID Alarm Name Remark
62 Signalling link layer 2 congestion alarm Signaling alarm65 Destination signalling point unavailable alarm
84 Signalling link layer 3 congestion alarm
86 Signalling link unavailable alarm
107 SCCP remote signalling point failure alarm
113 SCCP destination signalling point forbidden alarm
626 Signalling link service interruption alarm
627 Signalling link location failure alarm
311 Digital relay PCM failure alarm Relay alarm
545 Internal flow class change System load
547 Cell flow control class change Cell load
559 BSC reset alarm Circuit failure560 BSC reset acknowledgment alarm
562 BSC reset circuit alarm
571 MS reset alarm
572 MSC overload alarm
605 BSC unequipped with circuit alarm
2023-04-27 HUAWEI Confidential Page 88 of 117
GSM BSS Swap Guide For internal use only
612 MSC unequipped with circuit alarm
695 GCKS clock 10 minutes deviated from reference time Clock source failure696 GCKS clock 24 hours deviated from reference time
II. Important MSC-Related Alarms
The important MSC-related alarms are A-interface relay circuit alarm, signaling link alarm, BSC
overload alarm, and BSC reset alarm.
7.2 Network Monitoring and Optimization
After swapping the network, you should closely monitor the feedbacks from the customers or
users. Generally, users are quite sensitive to the network quality several days after the network
integration and may put forward subjective feelings. For example, they may complain that they
cannot make calls in the rooms where the signals were weak before the network integration. Or
they may also complain that there is great noise, the success rate of the fax service is low, and the
data service is unavailable. The reasons for the problems are that the coverage sensitive area
decreases, or the network parameters are irrationally set, or the cooperation between operators’
parameters are not satisfactory. These problems must be solved as quickly as possible. If the
decrease of the coverage area is caused by improper planning, you need to change the planning
accordingly immediately. Note that you should pay special attention to antenna adjustment;
otherwise new coverage problem will be introduced. To prevent sensitive problems from causing
great negative effect, you need to notify marketing personnel to maintain good customer
relationship.
7.2.1 OMC Traffic Statistics Analysis
You can discover the problems of the original network through monitoring and analyzing the daily
traffic statistics. During this period of time, you should try to register as much as traffic statistics
that are used for network optimization. In addition, you should pay special attention to the traffic
statistics related to traffic volume, congestion, call drop, handover, and interference. Furthermore,
you also should compare the traffic statistical indicators before and after network swap. If an
indicator becomes worse after swap, you should find out the reasons and improve it.
I. KPI Analysis (Voice Service)
In addition to the call drop rate, congestion rate, and handover success rate (for cell-level
indicators), you are suggested to pay attention to the following traffic statistical indicators.
For TRX-level indicators, you should check the assignment and utilization of SDCCH and TCH in
the channel allocation performance measurement and discover the abnormal TRXs immediately.
For the statistics in the path balance performance measurement, you need to monitor the uplinks
and downlinks of the corresponding TRX.
2023-04-27 HUAWEI Confidential Page 89 of 117
GSM BSS Swap Guide For internal use only
You should integrate the Rxlevel performance measurement and Rxqual performance
measurement into consideration, and can analyze the coverage provided by radio signals and also
analyze the interference caused by the radio signals as well.
For the networks with high load, you are suggested to check the signaling link send occupation
percentage (%) and signaling link receive occupation percentage (%) in the MTP link
performance measurement, because these two items indicate the signaling load at the A-interface.
If the values of the two indicators reach 30% respectively, the signaling link will be congested or
signaling may be losing. In this case, you should suggest the customer expand the network.
In BSC overall performance measurement, if the PCH overload times for circuit service at the
Abis interface and the RACH overload times for circuit service at the Abis interface are great, you
should consider readjusting the paging parameters or redividing the location areas.
In LAPD performance measurement, if both the pages discarded due to serious LAPD link
overload and pages discarded due to slight LAPD overload are not 0, it means that the flow
control has been happened during the statistical period.
For the network side, you need to check the following changes.
If the average timeslot occupation time is quite short according to A-interface relay performance
measurement, it is likely that the A-interface relay is inversely connected or mismatched. In this
case, users cannot hear the opposite party’s voice, and then hang up. Therefore, each conversation
only lasts for a short period of time.
The cause values of the inter-BSC outgoing handover failure in cell performance measurement (3)
can be divided into multiple types and they can be used for the analysis of inter-BSC handover.
II. KPI Monitoring (for Each Swap BTS)
You can use NASTAR to monitor the change of the KPIs before and after swap (the traffic data of
the original network should be collected and input into the NASTAR in advance). To discover
problem in time and prevent the traffic fluctuation from reducing analysis deviation, you are
recommended to use the all-day KPIs (24 hours). And you should pay special attention to the
traffic volume, call drop rate, and handover success rate. If there is abnormal case, analyze and
handle it immediately. At last, you need to export a KPI monitoring daily report.
III. KPI Analysis (Packet Service)
The daily GPRS network monitoring is responsible for the monitoring of data throughput,
transmission performance, accessibility, resource utilization rate, and retain ability. The following
table lists the GPRS KPIs.
Data Throughput Downlink NS_PDU mean throughput (kbps)
Transmission
performance
Uplink RLC data block retransmission rate (%)
Downlink RLC data block retransmission rate (%)
2023-04-27 HUAWEI Confidential Page 90 of 117
GSM BSS Swap Guide For internal use only
Uplink EGPRS RLC data block retransmission rate (%)
Downlink EGPRS RLC data block retransmission rate (%)
Accessibility
Uplink assignment success rate
Downlink assignment success rate
Mean interval for packet access request initiated on CCCH (s)
Uplink TBF congestion rate (%)
Downlink TBF congestion rate (%)
Uplink EGPRS TBF congestion rate (%)
Downlink EGRPS TBF congestion rate (%)
Resource
utilization rate
Uplink PDTCH/PACCH utilization rate
Downlink PDTCH/PACCH utilization rate
PDCH utilization rate
Success rate for BSC to reclaim overload dynamic PDCH
PDCH allocation success rate
Mean downlink throughput per PDCH (kbps)
Mean uplink throughput per PDCH (kbps)
Retain ability
Uplink GPRS TBD call drop rate (%)
Downlink GPRS TBF call drop rate (%)
Uplink EGPRS TBF call drop rate (%)
Downlink EGPRS TBF call drop rate (%)
For details, refer to GPRS Traffic Statistics Analysis Guide.
7.2.2 Analysis of NSS-Related Radio Indicators
I. Paging Success Rate and Location Update Success Rate
One-time page and subsequent pages cannot be told from each other according to the Abis
interface circuit pages measured by BSC, so you are suggested to obtain the one-time paging
success rate from the MSC. If the paging success rate is low, you need to check the location
update success rate measured by the MSC and perform further analysis.
2023-04-27 HUAWEI Confidential Page 91 of 117
GSM BSS Swap Guide For internal use only
II. Signaling Load
When analyzing the A-interface signaling load measured by the BSC, you need to check the
signaling load measured by MSC. If the load is heavy, you should discuss with the customer on
whether to expand the signaling link.
III. Intra-MSC Handover Success Rate
If the inter-BSC handover success rate is low, you need to check the intra-MSC handover success
rate or inter-MSC handover success rate.
7.2.3 Analysis of Area DT and CQT and Related Suggestions
The optimized DT lines include but are not limited to the DT lines evaluated before swap. For the
convenience of comparison, you are suggested to use the same DT line, test instrument, and
vehicles for drive test. Note that the position of MS antenna and that of the vehicle mounted
station must keep consistent before and after the swap. In addition, the test should be performed at
the same time in a day.
You should perform corresponding optimization according to the drive test, and then compare the
final DT results with the predicted results. Finally, you should output a network comparison
report.
CQT should be performed for VIP areas and the network quality in the VIP areas must become
better after swap. After CQT, you need to further optimize the network.
7.2.4 After-Swap Network Maintenance
NASTAR, GSM network optimization software developed by Huawei, can be used to monitor the
daily network performance (it can output daily report, weekly report, half-monthly report, and
monthly report). In addition, NASTAR can also be used for frequency analysis, adjacent cell
analysis, performance analysis, and geographic location display.
A specialist should be arranged to update the data for NASTAR according to the change of the
network, and the specialist should check the data with the customer periodically.
Traffic data should be sent back to the performance service platform of the regional division for
analysis and handling.
For details, see NASTAR Operation Guide.
7.2.5 Network Optimization
The following tasks are involved in network optimization:
Adjust and optimize BTS coverage area
Adjust and optimize the interference between adjacent cells or frequencies.
Set and adjust adjacent cell relationship
1) Adjust and optimize handover parameters
2023-04-27 HUAWEI Confidential Page 92 of 117
GSM BSS Swap Guide For internal use only
Prepare dialing test for the cells in which frequency hopping is available
2) Register traffic tasks, monitor and optimize network performance after swap, and check the
change of KPIs.
7.3 Customer Communication
When analyzing and handling network problems, you need to communicate with customers in
time, seek help from them, and notify the results to them in time.
Chapter 8 Swap Acceptance and Document
Transformation
Swap acceptance is based on equipment acceptance. Generally, rough acceptance solution should
be decided in the communication with the customer at the early stage. Swap acceptance includes
preliminary acceptance and network performance acceptance and should be implemented
following the contract strictly.
8.1 Preliminary Acceptance
After the equipment has been running normally for a period of time, you can apply for
preliminary acceptance.
The project supervisor can cooperate with the customer’s engineers to test some indicators during
installation and commissioning. And the test data can be used for the preliminary acceptance if it
is acknowledged by the customer. The project supervisor and the customer should perform the
preliminary acceptance together. If necessary, the customer relationship manager, service
manager, and project manager can be invited to join the acceptance.
The customer’s signature is required for each test item included in the preliminary test.
For the problems which have not been solved yet, you should communicate with the product
manager of the corresponding representative office on them. And the problems cannot be recorded
in the acceptance report. Instead, they should be0020recorded in the project memo.
On the completion of the preliminary test, the customer should leave signature and seal on the
project completion acceptance certificate and system preliminary acceptance certificate.
8.2 Network Performance Acceptance
After the network is monitored for a period of time and all online problems are solved, you can
perform network performance acceptance together with the customer.
2023-04-27 HUAWEI Confidential Page 93 of 117
GSM BSS Swap Guide For internal use only
Network optimization acceptance is divided into traffic statistical acceptance and drive test
acceptance. Before the test, you should collect and evaluate network information in advance and
make rational acceptance standard based on the evaluation. If the network to be accepted is large,
you can divide the network into several smaller areas and preformed the acceptance accordingly.
For details, refer to RPO202-04 Network Optimization Acceptance Standard and Method (G).
8.3 Document Transformation
On the completion of whole swap acceptance, you should transform the documents for
engineering, acceptance, and maintenance to the customer.
Chapter 9 Swap Risk Analysis
GSM network swap is a complex and systematic project, because the duration is long, many
products are involved, and the project scale is large. Therefore, any irrational plan and improper
operation will cause unexpected results. To control risks, this chapter introduces the methods to
predict and evaluate the risks.
From the perspective of customers, they care about the duration most. From the perspective of
Huawei, however, besides the duration, it also cares about engineering quality and cost. According
to the current experience, there are following risks:
The network indicators fail to reach the standard specified in the contract after swap.
The coverage area decreases after swap.
Network integration fails due to unavailability of transmission.
Duration delay is caused by inefficient communication.
9.1 Network Information Collection and Risk Evaluation
9.1.1 Risks Caused by Inadequate Understanding of the Performance of the Original Equipment
[Risk description]
The risks are caused by inadequate understanding of the performance of the original equipment.
[Solution]
You should gain a full understanding of the network before swap. If there is coverage problem,
you should test power first or communicate with the customer and marketing department on
whether to swap the network.
2023-04-27 HUAWEI Confidential Page 94 of 117
GSM BSS Swap Guide For internal use only
9.1.2 Risks Caused by Inaccurate Information
[Risk description]
The project parameters and network parameters provided by the customer may be inaccurate. As a
result, risks may happen during project implementation.
[Solution]
Before swapping the network, you should check and evaluate if the information is valid.
9.1.3 Case Study
I. Case 1: Indoor Coverage Configuration Problem
An operator uses macro cell and distribution antenna system for indoor coverage. The distribution
antenna system has no diversity receive antenna and is connected to the BTS with one feeder.
However, double CDUs are used according to Huawei BSS configuration, so two feeders must be
configured. Therefore, Huawei equipment cannot be connected to the distribution antenna system
of the old network. To solve the problem, engineers have to change the contract configuration. In
this case, SCU and CDU are used.
II. Case 2: Customer Complained that the Coverage Area Became Smaller after Huawei Used BTS3002C to Replace Company N’s Outdoor BTS
According to on-site engineers’ analysis, company N’s outdoor BTS was small in size, which
looked like small BTS. Therefore, the project supervisor took it for another BTS whose power
was 10W. According to later measurement, the actual power of the BTS was 34W, but the power
of the Huawei BTS3002C was 20W.
III. Case 3: Repeaters Caused High Call Drop Rate After Swap
According to traffic statistics, the call drop rate was high for the cells covering the countryside. It
is found that these cells have repeaters. All the repeaters were wireless, some of which were
broadband repeaters, and some of which were frequency selective repeaters. The information
related to the repeaters was not fully collected before swap, so the adjacent cell relationship
between the repeaters and neighboring cells was improperly designed. As a result, high call drop
rate occurred. Especially because of the capacity expansion or frequency change after swap, the
calls controlled by frequency selective repeaters will certainly drop.
In the following case, the call drop rate will also rise.
If a call hands over from a repeater cell to a neighbor cell under the control of the same BTS, the
path difference of the source cell and target cell is great. In this case, if the repeater cell is set to
synchronization handover cell, the TA value cannot be adjusted after handover. As a result, call
drop will easily occur. To solve the problem, you need to change the repeater cell to asynchronous
handover cell.
2023-04-27 HUAWEI Confidential Page 95 of 117
GSM BSS Swap Guide For internal use only
IV. Case 4: Coverage Area Became Smaller Due to Lacking Understanding of the Movable BTS Used in the Original Network
The customer complained that the call quality at a road section was poor after network swap.
According to field survey, it is found that no strong cell was present within this section and the
interference between signals was serious. The call quality was still unsatisfactory even through
adjusting the antennas and frequencies of the surrounding cells. According to further analysis, the
reason was that a movable BTS was used for the coverage of this section. At last, Huawei closed
the movable BTS and installed a new BTS for this section. And the problem was successfully
solved.
V. Case 5: Frequent Intermittence Occurred After Company N’s BTS was Replaced by Huawei BTS3006A
Huawei BTS3006A is configured with 5 PSU power supply modules and the capacity of the
standby battery is 650AH/24V. In addition, 6750W of DC power and 7500W of AC power are
available for BTS3006A. However, in that area the power supply cable was made of aluminum. In
addition, the cable was long and the loop impedance was great. Especially great power was
needed when the battery was in charge. In this case, the power supply system may not be normally
started. Since the difference between the transmit power, battery capacity, and power supply
module of the old equipment and that of the new equipment was great, the AC input power of the
original equipment was required to be lower than that of the BTS3006A. To solve the problem,
engineers reduced the AC power requirement of BTS3006A through changing the charging
current of the power supply module and battery. After that, BTS3006A ran normally.
If you meet problems of this kind later, you should check the power supply network and
communicate with the marketing engineers on the power supply requirement of Huawei
equipment.
VI. Case 6: Information of the Original Network was Not Fully Collected and Analyzed
[Problem]
It was found that the A-interface circuit is inadequate when Huawei BTS was used for a swap
project, which prolonged the project duration. To ease the traffic pressure, the related engineers
expanded the capacity of the A-interface.
[Reason analysis]
The traffic models of the original network were not fully collected and the predict traffic volume
was inconsistent with the actual traffic volume. As a result, the capacity of the A-interface circuit
was inaccurately estimated, and thus the project duration was prolonged. Therefore, the customer
began to doubt Huawei engineers’ capability.
[Reflection]
The traffic information of the original network should be fully collected before swap and provide
the solutions of A-interface expansion to the customer in advance. Though it is GBSS swap, but
2023-04-27 HUAWEI Confidential Page 96 of 117
GSM BSS Swap Guide For internal use only
the information related to NSS, especially the information related to MSC should be noted and
monitored.
VII. Case 7: The Longtitude and Latitude of the BTS were Not Fully Checked
In a network swap project, engineers failed to check the longitude and latitude of the BTS fully.
After the completion of the project, it is found that the several BTSs were locating in the areas
covered by other BSCs. Therefore, the network structure was irrational. After that, the engineers
had to perform rehoming operation.
VIII. Case 8: The Mark of A-interface Was Not Verified
In an area, the customer found that the mark of the A-interface provided in the interconnection
parameter table is Phase 2, but it was Phase 2+ after network integration. If engineers do not
change the mark immediately, many problems will occur.
9.2 Project Survey, Equipment Installation and Commissioning
9.2.1 Interconnection Risks
[Risk description]
If the MSC of the original network is not provided by Huawei during GBSS swap, engineers may
find it hard to perform IOT test. In addition, if the customer conditions are not met or the
customer does not cooperate with the swap project, the engineering duration will be delayed.
[Solution]
Invite related customer relationship manager, service manager, marketing personnel, and PM
to persuade the customer to cooperate with the swap project actively.
Check the environment of the engineering field in advance to ensure that the equipment
installation and commissioning can be finished within the schedule.
Seek help from technical support engineers.
9.2.2 Problems Related to Interconnection of GBSS and G9
The following table lists the similar problems.
No. Problem Description Solution
1 Clock problem caused by G9
integration
BTS clock is installed outside of the UMG
and IP should not be used for clock
transmission.
2 Decrease of CSSR (call setup success
rate) caused by G9 integration.
Enhance A-interface utilization rate through
late assignment.
2023-04-27 HUAWEI Confidential Page 97 of 117
GSM BSS Swap Guide For internal use only
9.2.3 Risks Concerning BTS Survey
[Risk description]
In some cases, the antennas of the original network can be reused, but the antenna connector does
not necessarily match the transmission connector, or the capacity of the power supply cannot meet
requirement. If the previous information is not fully checked before the launch of the project, the
project duration will be delayed.
[Solution]
You should confirm the swap project with the customer in detail. If necessary, you should survey
some of the BTSs. If there is any problem, you need to communicate the problem with the
customer and solve the problem immediately.
9.2.4 Quality Risks Caused by Project Installation Team’s Engineering Level
[Risk description]
At present, many project teams are green hands. They may pursue progress while neglect the
engineering quality. And this problem is commonly seen in overseas projects.
[Solutions]
Product manager should have serious quality consciousness.
Experienced project teams are preferred.
The corresponding representative office should exert strict management on the partner.
Perform strict quality management.
Take measures to solve problems quickly and exert penalty on the responsible party if
necessary.
On-site project supervisor should perform careful self-check after engineers finish installing
the hardware and before the equipment is enabled, especially the set-top power and TRX
power must meet requirement and the cell direction must be correct.
In overseas, corresponding trainings must be provided to the local project team. The
trainings should cover operation rules and flows. And the project supervisor is responsible
for guide the project team to install the project according to rules and flows.
The project team should sample some BTSs for quality check.
The corresponding regional division and representative office should routine check the
engineering quality.
Trainings should be provided to the project teams whose techniques have much to be
improved.
The project supervisor should cooperate with the project manager to monitor the network
quality and supervise the project team to follow swap procedures.
9.2.5 Version Risk
[Risk description]
2023-04-27 HUAWEI Confidential Page 98 of 117
GSM BSS Swap Guide For internal use only
With the evolution of GSM network, many new functions are used, such as half rate and AMR. If
engineers do not understand the functions of the original network or the functions provided in the
contract, the project delivery date may be delayed, and this is especially true at the NSS side.
[Solution]
The on-site project team should check the functions provided in the contract strictly and
communicate with the customer to understand the functions of the original network. In addition,
the features of the current version should also be thoroughly understood.
If the version is available, you can confirm the features of the version from the related
technical owner or the technical support department.
If the version is not provided, you can confirm the features of the version from the product
manager, marketing (CCM) and the general office of the regional division.
The confirmation of functions and needs should be fulfilled in the electronic process of the
requirement and commitment, and each electronic process should be monitored.
The information of the version is inconsistent with the version; you should reach an
agreement with the front marketing and R&D departments.
The plans provided in the version should be listed into the general project plan.
9.2.6 Case Study
I. Case 1: BTS Could Not Run Normally Due to GSM/CDMA Common Transmission
There was alarm generated for a cell of a BTS after network swap and the BTS could not work
normally. However, it could work normally after changeback. According to field survey, engineers
found that this BTS was used for both GSM transmission and CDMA transmission. The network
was expanded after the swap, and thus the transmission resources are inadequate. Therefore, the
BTS could not run normally.
II. Case 2: BTS Clock Synchronization Problem Cause by GSM/CDMA Common Transmission
The clock of the GSM BTS could not synchronize the upper level clock when GSM BTS and
CDMA BTS shared common transmission. The transmission of a swap BTS passed through
CDMA BTS first, and then the timeslot integration equipment extract the transmission. However,
because the synchronization timeslots were not provided, the clock of the GSM BTS could not
synchronize the upper level clock. As a result, the BTS could not work normally after swap.
III. Case 3: Inadequate Capacity of Reused Battery Delayed BTS Installation Progess
In a swap project, the power supply equipment of the original network was reused in the new
network. In addition, the capacity of the BTS was also expanded in the new network. After
installation, however, engineers found that the power supply equipment provided by the customer
could not meet requirement. And it cost some time for engineers to buy new power supply
equipment. Therefore, the BTS installation progress was greatly delayed.
2023-04-27 HUAWEI Confidential Page 99 of 117
GSM BSS Swap Guide For internal use only
IV. Case 4: BTS Integration Date Was Delayed Because of the Transmission Connector Used in the Original Network Mismatched That Used by Huawei
In a swap project, engineers found that the transmission connector used in the original network
mismatched that used by Huawei. Therefore, on-site engineers must remake the E1 line, but no
SMB connector was available then. In this case, the BTS integration date was delayed.
V. Case 5: BTS Installation Schedule Was Delayed Due to Goods Distribution Problem
According to plans of swap project, the project installation should be performed immediately after
customs clearance, but the distance between sites was large, so the transportation period was long.
Therefore, the goods could not be distributed to each site in time. As a result, multiple BTSs were
integrated twice, which delayed the network swap progress. Meeting this kind of problem, the
customer made many complaints. If you meet similar situation later, you should make proper
arrangement in advance.
VI. Case 6: CIC Mistake Caused by Confusion of Transmission Labels
Engineers found that there were many CIC mistakes present at the A-interface after BSC
installation. Through analysis, engineers found that the transmission labels were totally in a mess.
Therefore, when installing cable, you should pay attention to both the quality and correctness of
the project installation.
VII. Case 7: Engineering Quality Resulted in Customer Complaints
The customer complained that the coverage area of the network became smaller after a BTS was
swapped. Through careful analysis, engineers found that the problem was related to the 1/2
jumper locating between the set top and lightening protector. As far as this swap was concerned,
most of the antennas used in the old network were used in the new network. However, the
standing wave of the 1/2 jumper was not tested. Therefore, if you meet similar problem in the
future, you need to test the standing wave ratio of the 1/2 jumper. If necessary, you can design a
work flow to ensure the operation.
VIII. Case 8: M2000 Was Not Installed in Time
In a swap project, the installation conditions for M2000 installation were not met, so it was very
hard for engineers to monitor the BTS performance and locate problems. In this case, you should
communicate with the customer on how to create mature conditions for M2000 installation.
IX. Case 9: BTS Integration Date Was Delayed Because of the Connector of the Jumper to Be Used Was Different from the One Provided by Huawei
In a swap project, the connector of the jumper to be used was different from the one provided by
Huawei, so it cannot be connected to the lightening protector of Huawei. Therefore, on-site
engineers must remake the connector, but no auxiliary equipment was available then, so the
integration date was delayed. If you meet similar situations in the future, you need to confirm if
the connector is available before in advance.
2023-04-27 HUAWEI Confidential Page 100 of 117
GSM BSS Swap Guide For internal use only
9.3 Network Planning and Optimization Risk
9.3.1 Risk Related to Network Indicators
It is a common problem that the network indicators may become worse after BTS swap.
[Risk description]
The network quality may become worse after the swap of the local network from the perspective
of the following four aspects:
The network quality is really poor.
The customer thinks that the network quality is poor.
The customer thinks that the network should be optimized when faced with the pressure
from the indicator requirement.
Other equipment problems make the network quality worse.
[Solution]
Before swapping the network, you should collect the necessary data and test the network in
advance together with the customer. In addition, you should perform comparison test after swap.
Furthermore, you should optimize the network if necessary.
To make the comparison more effective, you can obtain the important indicators of original
network from the customer one month before the swap.
If the antennas of the original network need to be reused, you should test the standing wave ratio
of the antennas before swap. In addition, you should also pay attention to the operation of other
related equipment, such as MSC.
Meanwhile, you should guide the customer to believe in the equipment provided by Huawei and
pursued the customer to accept that the problem can be solved through network optimization.
9.3.2 Coverage Risk
It is the greatest risk that may happen during network swap.
[Risk description]
The coverage area of the network may become smaller after network swap, especially the
coverage area of the BTSs in suburban areas, countryside, and roads may become much smaller.
[Solution]
You must record the set-top power of the original BTS and configure the Huawei BTS
accordingly. If the set-top power of the Huawei BTS is lower than that of the original BTS, you
can apply two EDUs, two CDUs, and 60WTRX to the downlink, and apply tower mounted
amplifier to the uplink.
If receiving customer complaints, you can compare the set-top power before and after network
swap, and then locate the problem.
2023-04-27 HUAWEI Confidential Page 101 of 117
GSM BSS Swap Guide For internal use only
9.3.3 Inadequate Test before Swap
The network integration acceptance test may be affected if the test is inadequate before swap.
To avoid the risk, you should fully understand the coverage and performance of the original
network and design applicable network swap plan according to basic data.
9.3.4 Frequency Planning Risk
If the frequency planning is irrational or the frequencies are inadequate in the original network,
you should adopt new methods to plan the frequencies in the new network; otherwise the
frequency planning will turn out to be a difficult task. In this case, you should communicate with
the customer if new frequencies are to be added to the new network. If new frequencies are not
required, you should lower the customer’s expectation towards the network quality during the
network swap. Note that the parameters of the original network should be used for the swap.
Meanwhile, TRX capacity can be expanded and new sites can be established along with the
network swap. On the completion of the swap, you can plan the frequencies for the overall
network.
9.3.5 Risk Related to Traffic Volume
The traffic volume may become lower after swap, and the reasons are as follows:
The BTS set-top power becomes lower.
The antenna performance becomes worse.
Parameters are irrationally set.
The subscriber number changes.
The methods measuring the traffic volume vary with operators.
9.3.6 Case Study
I. Case 1: BSC Traffic Volume Decreased Sharply After the Swap of Operator A’s BSS System
The reason of this problem was that operator A and Huawei used different methods to measure
BSC traffic volume. In fact, the traffic volume measured at MSC was higher after swap.
II. Case 2: Problems Caused by Imcomplete Parameter Collection
[Risk Description]
The coverage area became smaller after operator N’s large-configuration BTS was replaced by
Huawei equipment in an urban area. In addition, the signals fluctuated greatly after swap.
[Reason Analysis]
The information the original equipment, such as BTS configuration, combiner mode, and antenna
number, were incompletely colleted before swap. After swap, the customer complained that the
combiner loss of Huawei equipment was greater than that of the original equipment, but the set-
2023-04-27 HUAWEI Confidential Page 102 of 117
GSM BSS Swap Guide For internal use only
top power of Huawei equipment was lower than that of the original equipment. Based on
negotiation with the customer, engineers strengthen the coverage through adding antennas and
PBU to the network and changing the BTS type.
[Reflection]
All the parameters of the original network must be colleted before network swap.
III. Case 3: Frequency Interference Was Generated Because of the Coverage Area of a BTS Was Enlarged After Swap.
The reason was that engineers failed to have an overall understanding of the original network.
Huawei 80W BTS was used to replace the operator N’s 40W BTS, but the frequencies of the
original network was still used in the new network, so frequency interference was generated.
IV. Case 4: Paging Success Rate Was Low Because of the Configuration Parameters of the Original Network Were Imcompletely Collected
The one-time paging success rate became lower after network swap. Through careful test and
analysis, engineers found that the operator N’s BTS did not control RACH minimum access level
but supported paging retransmission, so the one-time paging success rate was low.
Therefore, the information of the original network should be fully understood and analyzed. To
solve the previous problem, engineers can set the RACH minimum access level to 0-1.
V. Case 5: Problem Related to CRO Setting
The network ran normally after integration, but the customer complained that it was difficult to
make calls suddenly. Through careful analysis, engineers found that the CRO was set to 0. To
solve the problem, engineers integrated the BTS to another BSC and set the CRO to the default
value.
VI. Case 6: Call Drop Rate Became Higher After Swap
The call drop rate was doubled after network swap in an area. Test found that the original
equipment provider used different standard to measure call drop rate.
9.4 BSS Integration and Monitoring Risk
9.4.1 Risk Relate to BSS Integration Solution
[Risk description]
A swap project was characterized by short duration, large service volume, and complex
networking, so engineers found it hard to write down the integration solution, which may cause
potential risk.
[Solution]
The integration solutions must be written down.
All aspects concerned should considered into the integration solutions.
2023-04-27 HUAWEI Confidential Page 103 of 117
GSM BSS Swap Guide For internal use only
The integration solutions should be detailed enough.
The integration solutions should be reviewed.
Customers are required to participate into the solution design.
The solutions should be prepared in advance.
9.4.2 Risk Related to BTS Pre-integration
[Risk description]
If the pre-integration is not performed, potential risk may occur, because Huawei equipment and
the MSC of the original network cannot necessarily cooperate with each other well.
[Solution]
Both network pre-integration and network integration are key points for network swap, so the
network pre-integration cannot be omitted. If the network pre-integration is perfectly done,
customers will be more confident in Huawei’s engineering capability.
9.4.3 Risk Related to Transmission Commissioning
The transmission commissioning is one of the keys to the success of network integration.
[Risk description]
In some cases, the transmission commissioning workload is heavy at the integration night. The
integration progress will be affected if the transmission commissioning speed is low.
[Solution]
Hereunder lists the technical-based solutions:
Test the trunk with E1 card to ensure that the trunks are correctly connected. If necessary,
you can confirm the transmission and CIC for each line and paste label on each line.
Block half of the trunks before integration and unlock them after integration.
Paste labels on the trunks needing intermediate connection.
Simulate and practice pre-integration.
Connect the lines with transmission to avoid signaling congestion.
Arrange a specialist to check the previous operations.
Hereunder lists the non-technical solutions:
Notify related affairs to the customer in advance
Plan the integration progress according to customer’s transmission adjustment capability.
Apply for more time for transmission commissioning and integration from the customer.
Participate into each responsibility matrix actively.
9.4.4 Risk Related to BTS Integration
[Risk description]
BTS integration is a complex task, and any improper operation will result in integration failure.
2023-04-27 HUAWEI Confidential Page 104 of 117
GSM BSS Swap Guide For internal use only
[Solution]
Hereunder lists the solutions:
Integrate the BTSs by batch and fully consider the BTS location and adjacent cell
relationship.
Discuss the integration solutions with related parties fully and organize the exports for the
HQ of Huawei to review the solutions.
Set up a coordination team.
Make sure each BTS is debugged before integration.
Find the responsible person for each component and arrange a specialist to check if all the
components are available.
Check all the tables needed for the integration, such as BTS project parameter table, BTS
antenna jumper description table, integration time table, etc.
Set up emergency team.
Make related data and simulate the integration.
Create a channel through which engineers can communicate with the customer freely.
Strengthen the project management capability.
Paste labels on the jumpers of the original BTS.
Analyze BSS KPIs and core network KPIs during integration.
Test the dialing test function.
Organize experts from the HQ of Huawei to support the integration and ensure free
communication between experts and on-site engineers.
Optimize and adjust network parameters to ensure network quality.
The parameters of the original network and that of the new network should be consistent
with each other.
9.4.5 Emergency Problems Related to BSC Integration
[Risk description]
Generally, BSC integration should be finished in advance. If emergency problems occur at the
integration night, the whole BSC integration will fail.
[Solution]
You can test the BSC in detail beforehand. If emergency problem occur, you can seek help from
technical support engineers to locate the problem as soon as possible. For further analysis, BSC
supervisor should monitor and save the data such as interface messages and BTS log. If the
problem cannot be solved in time, you should change the data back to recover normal
communication. For details, see BSC Emergency Guide.
2023-04-27 HUAWEI Confidential Page 105 of 117
GSM BSS Swap Guide For internal use only
9.4.6 Handling of Abnormal Conditions during BTS Integration
I. BTS One-time Integration
The BTSs under the control of the same BSC can be integrated into the new network in one time.
To achieve this goal, engineers should design rigid plans. The VIP sites covering indoor
environment and remote areas should be integrated during day time, and the sites covering urban
areas should be integrated at about 00:00.
II. Antenna Problem Happened During BTS Swap
Generally, the antenna system of the original network can be reused, so you should test the
standing wave ratio of the old antennas to see if there is any problem. If the old antennas cannot
be reused, you should handle the problem immediately. If the antennas are inversely connected,
you need to correct the connection in time. If the standing wave ratio of the antennas is great, you
can consider remake the connector or change the feeder.
III. Repeater Reutilization Problem
If a repeater is attached to the BTS to be swapped, the repeater can be reused after swap. If the
frequency of this BTS needs not to be changed, you do not have to adjust the repeater either. If the
frequency of the BTS changes, you should modify the frequency parameters of the repeater.
IV. Indoor Distribution System Problem
Generally, the indoor distribution system can be reused. After the replacing the original BTS,
Huawei BTS is responsible for providing the signals for the indoor distribution system. Note that
the related transmission and antenna connectors are available.
V. VSWR Alarm Handling
The standby connectors must be available at the swap night. In addition, you should notify the
movable team to use instrument to test if the VSWR alarm is true.
VI. Inverse Connection of Antenna
You should install project following the project parameters and design strictly and use MS to test
if the cell direction is correct. If finding that the antenna is inversely connected, you should take
measures to solve this problem immediately.
VII. Abis Interface Error
Both the BTS operation and Abis interface should be tested after integration. The BTS installation
personnel should confirm the CGI through the local maintenance console or check if the CGI is
correct through test MS.
9.4.7 Case Study
I. Case 1: Monitoring Traffic Statistics After Integration Prevented Problems from Spreading
[Problem]
2023-04-27 HUAWEI Confidential Page 106 of 117
GSM BSS Swap Guide For internal use only
On the next day after network swap, engineers found that there was traffic volume in a cell, but no
call was present.
[Reason analysis]
Through checking channels, engineers found that the SDCCHs were in idle state. After changing
TRX, engineers found that the cell worked normally. Therefore, you should closely monitor the
important traffic statistics of the site after swap the next after swap to prevent the potential
problems from spreading.
II. Case 2: The Speed for the MS to Access the Network Was Slow Due to Clock Problem
Engineers found that the speed for the MS to access the network was slow in a site. First
engineers thought that the problem was present at the BSC. Through further analysis, engineers
found that UMG and Msoft3000 were located in different places, but the network was organized
according to IP. Therefore, the UMG could not obtain precise clock from IP transmission, which
resulted in BSC problem. As a result, the speed for the MS to access the network was slow.
9.5 Acceptance Risks
9.5.1 Risk Related to Customer Communication
[Risk description]
The acceptance items were not specified in the contract in detail. Because the engineers did not
communicate with the customer fully in advance, the acceptance speed was slow, so the date for
the equipment to access the network was delayed.
[Solution]
If the acceptance items were clarified in the contract, engineers should perform the acceptance
following the contract strictly. If some acceptance items were not specified in the contract,
engineers should communicate with the customer and obtain the customer’s written confirmation.
9.5.2 Risk Related to Acceptance Test before Integration
[Risk description]
The customer will perform acceptance test before integration. According to past experience,
engineers download the related acceptance manuals from http://support.huawei.com for the
customer, and the customer performs the test with the help of the manuals. However, the manual
update rate is relatively slow. Therefore, if the customer performs the acceptance test following
the manuals strictly, many test items will be unqualified.
[Solution]
Engineers should read the acceptance manuals beforehand and make corresponding correction. In
addition, engineers should accompany the customer with the acceptance test. If any problem is
2023-04-27 HUAWEI Confidential Page 107 of 117
GSM BSS Swap Guide For internal use only
found engineers should feed it back to the related personnel and correct the acceptance manuals
accordingly.
9.5.3 Case Study
I. Case 1: Acceptance Test Could Not be Performed Because the Acceptance Standards Were Not Designed in Detail
The acceptance standards were not detailed in the contract, so the customer always created
difficulties for the engineers during the test.
In fact, there were a number of similar cases. To solve the problem, engineers should detail the
acceptance standards in the contract and communicate with the customer as early as possible.
II. Acceptance Progress Was Slow Because the Distance between BTSs Was Large
In an area, the distance between BTSs was large, so it cost test engineers’ lot of time on road. In
this case, the acceptance progress was affected.
To solve the problem, engineer should perform the acceptance test at the network optimization
stage with the company of the customer.
9.6 Non-technical Risk Analysis
9.6.1 Risk Related to Contract Items
At present, many contracts are not made scientifically. For example, the contract configuration is
incorrect, the KPI commitment is irrational, the engineering duration is too short, the acceptance
items are vague, and the service price was low.
To control the contract effectively, pre-sales department should participate into the contract
review. At the pre-sales stage, you should fully communicate with the marketing staff and
organize all the personnel concerned to review and clarify the contract.
After the contract is signed, you should evaluate the contract and find out solutions to potential
problems.
Some customers may require changing the contract. In this case, you cannot agree with or refuse
the customer directly. Instead, you should consult the related marketing personnel first.
9.6.2 Risk Related to Project Duration Risk
[Risk description]
Generally, the project duration is short, which may generate potential problem.
[Solution]
Prepare the related resources in advance.
Make a detailed plan
Spend some of your spare time on the work if necessary.
2023-04-27 HUAWEI Confidential Page 108 of 117
GSM BSS Swap Guide For internal use only
Implement task parallel.
Seek help from others
9.6.3 Management Risk
[Risk description]
Generally, a swap project involves multiple roles, including PM, Huawei BSC engineers, RNP
engineers, partners, RNO partners, customers, technical support experts, representative offices,
project supervisor, and other equipment providers. Therefore, how to manage these roles
effectively is problem.
[Solution]
Hereunder lists four solutions.
1) Cooperation between network planning and projectHuawei should adapt its networking planning solutions to the local network. The network
adjustment suggestions provided by the RNO teams should be put into practice after confirmed by
both the customer’s RNO owner and Huawei RNO owner. If you need the customer’s cooperation
or modify parameters in MSC, you should prepare corresponding application document. If the
customer or BSS engineers are responsible for the adjustment, you should require them to feed
back the adjustment results. RNO engineers are not allowed to change the BTS configuration by
their own, and RNP engineers are not allowed to change the RNO parameters by their own.
Therefore, the responsibility matrix of the RNO team and RNP team should be clearly defined.
The project team should notify the problem handling progress to the RNO team.
2) Subcontractor Management
Have an understanding of each subcontractor’s engineering capability before beginning the
network. Generally, you should know the experiences, knowledge, team number, vehicles,
and basic instrument owned by the subcontractor.
Set up project report and monitoring system.
Pay more attention to manage teams whose engineering capability is relatively poor.
Keep a good relationship with the engineering team.
Convey responsibility to each person in the contract.
Set up a unified database and report template if multiple subcontractors are responsible for
the project.
3) Customer cooperationFull communication with the customer must be implemented. If necessary, you should prepare
written document for customer cooperation.
4) Supervisor management
2023-04-27 HUAWEI Confidential Page 109 of 117
GSM BSS Swap Guide For internal use only
Supervisor connects the customer to Huawei, so you should fully communicate with the
supervisor. In some cases, the supervisor can help you manage the engineering team. Therefore,
supervisor management should be properly and strictly implemented.
9.6.4 Risk Related to Communication
[Risk description]
If the communication is not smooth and the responsibility matrix is not divided clearly,
unnecessary conflicts will occur and project duration may be prolonged.
[Solution]
The project manager plays a very important role in the project, so a project manager should have
both network planning skill and communication skill. The communication system should be
perfectly established. For example, weekly report and daily report should be submitted to the
customer’s manager.
Within the project team, daily report and weekly report system should be implemented. In
addition, the members of the project team should fix a period of time to communicate with
each other in a week. The daily report includes project progress, difficulty, and support
needed. The weekly report also includes the project progress in terms of a week, difficulty,
support needed, next week’s plan, etc.
Communicate with the related leaders of the representative office on the project. If there is
emergent problem, you should communicate with the leaders immediately.
Communicate with the customer through meetings, weekly report, and summary report. The
customer is expected to know the progress, difficulty, and future plans related to the project.
Note that the engineers responsible for customer communication should be fixed and the
communication with the customer’s senior management team should be emphasized.
Feed back the field conditions to Huawei according to working flows. If necessary, you can
organize the related departments and engineers to have meetings to solve serious problems
together.
9.6.5 Risk Related to Contract Implementation
[Risk description]
According to some contracts, the antennas, transmission, and power supply should be swapped
together with the equipment, but the customer may require that the equipment should be installed
at the position where the original cabinet located. In this case, it will be difficult for block
integration, which will prolong the integration time and affect network indicators; especially the
handover will be seriously affected. Sometimes MSC A-interface will not be expanded, so BTS
integration always carries A-interface integration. If the BSC is frequently adjusted, the stability
and quality of the network will be affected.
[Solution]
2023-04-27 HUAWEI Confidential Page 110 of 117
GSM BSS Swap Guide For internal use only
You are suggested to communicate with the customer on the detailed integration solution to win
the customer’s agreement. In addition, you ensure that the manpower, project supervisor, and
engineering team are available in advance. You are not suggested to assign multiple BTSs for a
project team.
9.6.6 Risk Related to Work Flow
[Risk description]
If the project team do not follow the swap procedures made by Huawei but follow their own
manner to implement the project, great potential problems may be generated.
[Solution]
Engineers should be familiar with the work flow and follow the flow strictly.
New comers should learn from experienced engineers.
Self-reflection is encouraged.
Feed back the customer’s extra requirement to the related party and any self-reply is
forbidden.
9.6.7 Case Study
I. Case 1: Customer’s Senior Management Team Sent Complaints to Huawei Marketing Department Because Engineers Did Not Report the Problem Handling Result in Time
[Problem description]
Customers’ senior management departments complained about echo problem to bidding
department directly.
[Reason Analysis]
Engineers from cooperation partners were in charge of the echo problems, but they did not notify
the processing progress to customers, so customers thought that the project was not paid enough
attention to. Considering the seriousness of the complaint, representative offices established a
special group to solve the problem. After four weeks’ effort, engineers found that circuit from the
local exchange to the site A had been adjusted recently and there were two E1 Loop backs. That is
why the echo problem occurred. In addition, Huawei engineers reported the processing progress
to customer’ senior management departments every week. After the problem was solved, Huawei
engineers submitted a formal report to customers. After that, customer’s doubt towards Huawei
gradually changes.
[Reflection]
Problems should be solved in time and real-time communication with customers should be
emphasized.
2023-04-27 HUAWEI Confidential Page 111 of 117
GSM BSS Swap Guide For internal use only
II. Case 2: Customer Complained About the Document Problem
In a swap project, engineers failed to consider customer’s cooperation needs. The document
submitted to the customer was modified for several times, which was greatly to the unsatisfactory
of the customer.
III. Case 3: Important Cooperation Affairs Should be Confirmed by the Customer’s Senior Management Team at the Project Coordination Meeting
The customer’s engineers promised Huawei that they could perform secondary shipment by their
own, but the vice president refused it, which delay the duration and increased cost.
The project coordination meeting is rather important to Huawei, so you should invite the
customer’s senior manager to participate into the meeting. The cooperation affairs should be
submitted to representative offices for review.
IV. Case 4: Shortage of Project Duration Made the Swap Plan in a Mess.
The customer required a swap to be finished in a shorter time than planned, which made the swap
plan in a mess. As a result, the network quality was greatly affected and customers always
complained about network problems. To solve the problems, Huawei explained the reasons to
customers and guides them to accept the planned swap strategies. Results proved that the planned
strategies were applicable.
V. Case 5: Hastened Progress Caused Secondary Integration
In a swap project, multiple BTSs could not connect to the planned BSC directly due to various
reasons, such as hastened progress, limit of transmission progress, and low speed of BSC
establishment. As a result, the network structure was in a mess. Therefore, the secondary
integration was a must. As for the second handover, however, it both added up to the workload
and brought quality risk to the network.
2023-04-27 HUAWEI Confidential Page 112 of 117
GSM BSS Swap Guide For internal use only
Appendix: Reference Document Catalog and Network
Integration Checklist
9.7 Reference Document Catalog
All the reference documents are provided in http://support.huawei.com/. You can download the
one you need from the website.
9.8 Network Integration Checklist
9.8.1 BSC Service Test
Note that if the test results are abnormal, you need fill in the remark in the following table.
No. Test Item Sub-item Conclusion Evaluation Standard Remark
1 Basic service Location update
when the MS is
powered on or
powered off.
Normal
Abnormal
1) Location update succeeds and MS can
access network successfully.
2) The complete location update procedure
can be seen through the window
monitoring Um interface, Abis
interface, and A-interface.
2 Call service Both calling party
and called party are
MSs.
Normal
Abnormal
Call is successfully made and there is no
one-way audio, cross talking, and echo.
3 Call service Call made between
MS and fixed phone
Normal
Abnormal
Call is successfully made and there is no
one-way audio, cross talking, and echo.
4 Call service Extended cell call test Normal
Abnormal
Call is successfully made and there is no
one-way audio, cross talking, and echo.
5 Short
message
service
MS sends and
receives short
message
Normal
Abnormal
Short message can be sent, received, and
displayed correctly.
6 Handover
service
Intra-cell handover Normal
Abnormal
1) Intra-cell handover is successfully made
2) There is record for successful intra-cell
handover according to traffic statistics.
2023-04-27 HUAWEI Confidential Page 113 of 117
GSM BSS Swap Guide For internal use only
7 Handover
service
Overlay-to-underlay
handover
Normal
Abnormal
1) IUO handover is successfully made.
2) There is record for successful IUO
handover according to traffic statistics.
8 Handover
service
Inter-cell handover
within BSC
Normal
Abnormal
1) Inter-cell handover within BSC is
successfully made.
2) There is record for successful inter-cell
handover within BSC according to
traffic statistics.
9 Handover
service
Inter-BSC handover Normal
Abnormal
1) Inter-BSC handover is successfully
made.
2) There is record for successful inter-
BSC handover according to traffic
statistics.
10 Basic service Dual band network Normal
Abnormal
1) MS can perform location update in the
dual band network.
2) MS can work as either calling party or
called party normally.
3) The handover between dual band is
normal.
9.8.2 GPRS Dialing Test Checklist
No. Test Item Sub-item Conclusion Evaluation Standard Remark
1 Basic service If the MS attach
function is normal.
Normal
Abnormal
Check if the service is normal through
spot test and drive test.
2 Basic service If the MS PDP
activation function
is normal.
Normal
Abnormal
Check if the service is normal through
spot test and drive test.
3 Basic service If the MS cell
update is normal.
Normal
Abnormal
Check if the service is normal through
spot test and drive test. Note that the
tests should be performed during and
after cell update.
4 Basic service If the MS routing
area update is
normal.
Normal
Abnormal
Check if the service is normal through
spot test and drive test. Note that the
tests should be performed during and
after cell update.
2023-04-27 HUAWEI Confidential Page 114 of 117
GSM BSS Swap Guide For internal use only
No. Test Item Sub-item Conclusion Evaluation Standard Remark
5 Basic service If the MS can enjoy
services normally,
such as www
service.
Normal
Abnormal
Check if the service is normal through
spot test and drive test.
6 Basic service If the MS service
rate is normal.
Normal
Abnormal
Record and analyze the MS service rate
through PING and FTP service.
9.8.3 A-interface Dialing Test Checklist
PCM Module
No.
FTC
Board
NO.
BSC
DDF
Port No.
Transmis
sion DDF
Port No.
Starting
CIC
Terminat
ing CIC
Test Results Problem
Timeslot
Problem
CIC
1
2
3
4
5
6
7
8
9
10
Note:
For each blank, if the test result is normal, mark the blank with √; and if the test result is abnormal, mark the blank with ×, and write down the abnormal timeslot and CIC number.
9.8.4 Abis Interface Dialing Test Checklist
BSC Name: Owner: Test Time:
Abis Interface Dialing Test Checklist
Modul
e No.BIE
Group
BIE
Port
BSC-
DDF
Trans
missio
BTS
NameConfi
gurati
Norm
al
Board
StateChann
el
Succe
ss
Chann
el
2023-04-27 HUAWEI Confidential Page 115 of 117
GSM BSS Swap Guide For internal use only
No. No.Port
No.
n
DDF
Port
No.
onInitiali
zationState
Locati
on
Updat
e
Dialin
g Test
9.8.5 BTS Radio Channel Dialing Test Checklist
2023-04-27 HUAWEI Confidential Page 116 of 117
GSM BSS Swap Guide For internal use only
Site No. Site Name Site Type Site
Configurati
on
Test Result Problem TRX
No.
Problem
Timeslot No.
Remark
Note:
The site number, site name, site type (such as BTS30), and configuration type (S3/3/3) must be recorded if they
are tested. Each TRX and each timeslot of a site must be tested. If the test result is normal, mark the blank with
√; and if the test result is abnormal, mark the blank with ×, and write down the abnormal timeslot and CIC
number.
2023-04-27 HUAWEI Confidential Page 117 of 117