Gant Micro

Embed Size (px)

Citation preview

  • 8/10/2019 Gant Micro

    1/2

    Roy Varghese Micro plan-DMC75H Machine

    DMC 75H-Instalation and Part proving. G

    Project: GANTT CHART Y

    R 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    Activity Respon

    sible

    Duratio

    n

    Start End Status-

    20th

    Nov

    S M T W Th

    e

    F Sa S M T W Th

    e

    F Sa S M T W Th

    e

    F Sa

    1.0 DMC 75 H Machine Installation at GKNSI Ro 72 10-Oct 21-Dec Y

    1.1 Documents in Indian bank from German An a K 29 10-Oct 8-Nov G

    1.2 Pa ment to DMG throu h Bank Mukun 4 12-Nov 16-Nov G

    1.3 Machine arrival at Mumbai Port Florian 33 10-Oct 12-Nov G

    1.4 Excise certificate for documentation Mukun 8 12-Nov 20-Nov G

    1.5 Pre are Documentation for License Mukun 1 19-Nov 20-Nov G

    1.6 Bill of entr , Customs assi nment Mukun 3 20-Nov 23-Nov G

    1.7 Clearin Duties Mukun 14 12-Nov 26-Nov G

    1.8 Lo istic From Mumbai to Pune trans ort+Octroi Mukun 2 26-Nov 28-Nov G

    1.9 Arran in cranes Prashan 1 27-Nov 28-Nov G

    1.10 Unloadin Machine Prashan 1 28-Nov 28-Nov G

    1.11 Availabilit of DMG technician-Local Prashan 23 28-Nov 21-Dec G

    1.12 Pre installation. Prashan 9 28-Nov 7-Dec G

    1.13 Arrival of DMG en ineer at Mumbai Florian 1 8-Dec 9-Dec G

    1.14 Pick u and boardin at Hotel Varsha 1 9-Dec 9-Dec G

    1.15 Arrival of Stroma AG technician Tim 1 8-Dec 9-Dec G

    1.16 Pick u and boardin at Hotel Varsha 1 9-Dec 9-Dec G

    1.17 Local travelin of ersons comin from German Varsha 11 10-Dec 21-Dec Y

    1.18 Food and water arran ement Varsha 11 10-Dec 21-Dec Y

    1.19 Machine final installation&trainin Prashan 4 10-Dec 14-Dec Y

    1.20 Machine commissionin and roovin Prashan 7 14-Dec 21-Dec Y

    1.21 Dro Technicians at Mumbai Air ort Varsha 1 21-Dec 21-Dec Y

    2.00 Tools and Fixtures at GKN SI Ro 25 15-Nov 10-Dec Y

    2.1 Dis atchin tools and fixtures from German An a K 4 15-Nov 19-Nov G

    2.2 Arrival of Tools and Fixtures at Mumbai Port An a K 7 19-Nov 26-Nov G

    2.3 Ke t it at Customs under bond Mukun 37 23-Nov 30-Dec G

    2.4 A lication for Im ort license Mukun 2 26-Nov 28-Nov G

    2.5 Availabilit of Im ort License Mukun 4 29-Nov 3-Dec G

    2.6 Customs dut a and clearin Mukun 2 3-Dec 5-Dec R

    2.7 Arrival of Tools and Fixtures at GKN SI Mukun 3 7-Dec 10-Dec R

    3 Sho floor Ro 40 1-Nov 11-Dec Y

    3.1 Lease a reement Mukun 8 1-Nov 9-Nov G

    3.2 Information to Excise Mukun 2 28-Nov 30-Nov G

    3.3 Sho floor side coverin Prashan 7 9-Nov 16-Nov G

    3.4 Sho floor wall aintin Prashan 5 11-Nov 16-Nov G

    3.5 Sho cleanin Prashan 5 16-Nov 21-Nov G

    3.6 Installation of Com ressor Prashan 4 19-Nov 23-Nov G

    3.7 To Coverin com ressor shed Prashan 3 22-Nov 25-Nov G

    3.8 Fixin of Gate Prashan 13 12-Nov 25-Nov G

    3.9 Electrical connections&earthin Prashan 17 5-Nov 22-Nov G

    3.10 Control anel&steabilzer fixin Prashan 3 19-Nov 22-Nov G

    3.11 Plu in to DMG Machine Prashan 6 29-Nov 5-Dec G

    3.12 Final artition to se arate the lant from febtech Prashan 16 5-Dec 21-Dec G

    3.13 Internal door connectin Assembl to Sho floor Prashan 10-Dec 21-Dec Y

    4.00 Accessories Ro 29 19-Nov 18-Dec Y

    4.1 Installation Washin Machine Prashan 3 24-Nov 27-Nov G

    4.2 Tables and trolle s Prashan 8 19-Nov 27-Nov G

    4.3 Chi trolle Prashan 20 1-Nov 21-Nov R

    4.4 Tool resetter. Prashan 7 19-Nov 26-Nov G

    4.5 Gau es Su ato 14 10-Nov 24-Nov G

    4.6 Water and Fluids Prashan 0 10-Nov 10-Nov G

    4.7 Crane installation Prashan 24 24-Nov 18-Dec Y

    4.8 Man ower availabilit Prashan 64 7-Oct 10-Dec Y

    4.9 Trainin of technician at DMG Ban alore Prashan 5 18-Nov 23-Nov G

    Completed

    In process

    Over due

    Nov.12 Nov.12 Nov.12

    Week45 Week46 Week47

  • 8/10/2019 Gant Micro

    2/2

    Roy Varghese Micro plan-DMC75H Machine in Pune.

    Remarks

    Mr.Venu Gopa arrive rom Banga ore

    Machine is connected and switched on.ATC ali nment is oi

    Ma er s ta s in hol ida inn

    Arran ed

    Mr.Patlar arrivin 10th Dec in Pune

    Hotel is booked. Pick u from Air ort is arran ed

    Arran ed

    Mr.ma er from DMG German arrived.

    Invoice received will be dis atchin this week Liftin consi

    Ex ected to be in Mumbai b 3rd Dec.

    Waitin for bank uarantee

    Bank uarantee received,under custom clearnceCustom clearance toda or tomorrow.toll in Pune b 11th or

    B 1st week of December

    B 1st week of December

    Connection to Machine after Ke t the Machine in lace.

    After uttin the machine in lace.

    Post oned to next month.

    Machine is available,instalation in Week49

    Will be available b 3rd week Dec.12

    Installation com leted Load test on 10th

    Post oned for one more month.

    GKN SIPL