GHANTT CHART
PROJECT : COMMERCIAL SPACE RENOVATION
LOCATION : FESTIVAL SUPERMALL, ALABANG, MUNTINLUPA CITY
OWNER : MR. & MRS. RODOLFO Q. JANE
SUBJECT : PROJECT ACTIVITY SCHEDULE (GHANTT CHART)
ACT. ID DESCRIPTION PRED REL. SUCC DURATION
JULY 2011
WK 1 WK 210 11 12 13 14 15 1617 18 19 20 21 22
1 PLA 101 Design conceptualization "START" - PLA 102 7 days
2 PLA 102 Plans, drawings and layouts PLA 101STS, STSPLA 103 3 days
3 PLA 103 Budgetary Estimates PLA 102 FTS PLA 104 2 days
4 PLA 104 Scheduling PLA 103 STS MIS 101 2 days
5 MIS 101 Initial approval of Mall admin PLA 104 FTS MIS 102 1 day
6 MIS 102 Building permit application/ releasing MIS 101 FTS MIS 103 7 days
7 MIS 103 Submission to Mall admin MIS 102 FTS CIV 101 1 day
8 CIV 101 Space Clearing MIS 103 STS, FTS CIV 102 1 day
9 CIV 102 Mobilization, Tempacil CIV 101 STS, FTS CIV 103 1 day
10 CIV 103 Materials purchase and delivery CIV 101 STS CIV 105 3 days
11 CIV 104 Layout of Partitions and electrical lines CIV 102 STS CIV 105 1 day
12 CIV 105 Partition frames assembly CIV 104 STS CIV 106 2 days
13 CIV 106 Ceiling frames assembly CIV 105 FTS, STS ELE 101 2 days
14 ELE 101 Electrical rough-ins CIV 106 FTS, STSPLU 101 2 days
15 PLU 101 Relocation of water sprinkler (PF) ELE 101 FTS CIV 107 1 day
16 CIV 107 Installation of gypsum partitions PLU 101 FTS CIV 108 2 days
17 CIV 108 Installation of gypsum ceiling CIV 107 FTS ELE 102 3 days
18 ELE 102 Panel board installation CIV 108 FTS ELE 103 1 day
19 ELE 103 Electrical wiring layout ELE 102 FTS CIV 109 3 days
20 CIV 109 Installation of glass partition and glass do ELE 103STS, FTSPNT 101 2 days
21 PNT 101Painting of drywall and ceiling CIV 109 STS, FTS CIV 110 5 days
22 CIV 110 Installation of tiles PNT 101 FTS ELE 104 2 days
23 ELE 104 Installation of lighting and electrical fixtur CIV 110 FTS CIV 111 1 day
24 CIV 111 Installation of layered glass racks ELE 104 STS, FTS MIS 104 2 days
25 MIS 104 Installation of Signages CIV 111 STS, FTS MIS 105 3 days
26 MIS 105 Cleaning MIS 104 FTS MIS 106 1 day
27 MIS 106 Deliveries of furnitures and product displaMIS 105 FTS MIS 107 2 day28 MIS 107 GRAND LUNCH MIS 106 - "END" 1 day
Prepared By: Owner:
Engr. FRANKLYN P. GENOVE Mr. & Mrs. RODOLFO Q. JANE
Civil Engineer
PRC No.: 0106061
TIN :
PTR No.:
ISSUED ON:
ISSUED AT:
ACT.No.