40
© OECD/IEA 2014 Grid Integration of Renewables Energy Training Week 111 April 2014, Paris Simon Mueller Analyst System Integration of Renewables Renewable Energy Division

Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

Embed Size (px)

Citation preview

Page 1: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Grid Integration of Renewables

Energy Training Week 111 April 2014, Paris

Simon Mueller Analyst – System Integration of Renewables Renewable Energy Division

Page 2: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Context

The integration challenge

Flexibility and system transformation

System friendly VRE deployment

System operation

System planning and investment

Conclusions

Outline

© OECD/IEA 2014 2

Page 3: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Context

The integration challenge

Flexibility and system transformation

System friendly VRE deployment

System operation

System planning and investment

Conclusions

Outline

© OECD/IEA 2014 3

Page 4: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

The Grid Integration of Variable Renewables Project - GIVAR

Third project phase at a glance

7 case studies covering 15 countries, >50 in-depth interviews

Technical flexibility assessment with revised IEA FAST tool

Detailed economic modelling at hourly resolution

© OECD/IEA 2014 4

Page 5: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

0% 5% 10% 15% 20% 25% 30% 35% 40% 45%

Japan

Brazil

India

France

Sweden

ERCOT

NW Europe

Italy

Great Britain

Germany

Iberia

Ireland

Denmark

Wind 2012 PV 2012 Additional Wind 2012-18 Additional PV 2012-18

VRE share of total annual electricity output

Note: ERCOT = Electricity Reliability Council of Texas, United States Source: IEA estimates derived in part from IEA Medium-Term Renewable Energy Market Report 2013.

Large-scale integration accomplished today, but more to come

Instantaneous shares reaching 60% and above

Case studies

© OECD/IEA 2014 5

Page 6: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Context

The integration challenge

Flexibility and system transformation

System friendly VRE deployment

System operation

System planning and investment

Conclusions

Outline

© OECD/IEA 2014 6

Page 7: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

What shapes the challenge?

Interaction of VRE and the system shape challenge

Integration challenge is system specific

But: limited number of factors on each side

Learning from other system contexts is possible!

Properties of variable renewable energy (VRE)

Flexibility of other power system components

© OECD/IEA 2014 7

Page 8: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

The GIVAR III case study regions

Power area size (peak demand)

Grid strength

Inter-connection (actual & potential)

No. of power

markets

Geographic spread of

VRE

Flexibility of dispatchable generation

Investment opportunity

India

Italy

Iberia (ES & PT)

Brazil

NW Europe

ERCOT (Texas, US)

Japan (East)

? © OECD/IEA

2014 8

Page 9: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Location Seconds Years

Properties of variable renewables and impact groups

Systems are different – impacts will vary too

But common groups of effects

Low short run cost

Non synchro-

nous

Stability

Uncertainty

Reserves

Variability

Short term

changes

Abun- dance

Scarcity Asset

utilisation

Location constrained

Trans-mission

grid

Modularity

Distribution grid

© OECD/IEA 2014 9

Page 10: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Power systems already deal with a vast demand variability Can use existing flexibility for VRE integration

No problem at low shares, if …

© OECD/IEA 2014 10

Exceptionally high variability in Brazil, 28 June 2010

No technical or economic challenges at low shares, if basic rules are followed: Avoid uncontrolled, local ‘hot spots’ of deployment

Adapt basic system operation strategies, such as forecasts

Ensure that VRE power plants are state-of-the art and can stabilise the grid

Page 11: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

FAST2 assessment: All power systems can take 25% in annual generation already today.

There is no technical limit on how much variable generation a power system can absorb

But system transformation increased flexibility required for higher shares

Much higher shares technically feasible

© OECD/IEA 2014 11

0 10 20 30 40 50 60

Brazil

ERCOT

Iberia

Italy

Japan (East)

NW EUR

Uncurtailed share of VRE in power generation [%]

Curtailment

none

low

medium

high

VRE share 2012

Source: FAST2 assessment.

Page 12: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

When VRE are added to a system with adequate capacity:

Situations of low load and high VRE generation VRE curtailment if flexibility insufficient

Negative market prices due to inflexible generation and VRE support mechanisms

Grid bottlenecks in regions with high VRE density Limitations feeding production from the distribution to the

transmission grid

Insufficient evacuation capacity in regions with rapid build out of new VRE capacity

Voltage and frequency stability can be an issue in specific situations

Main short-term challenges

© OECD/IEA 2014 12

Page 13: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Higher uncertainty

Larger and more pronounced changes

Main persistent challenge: Balancing

0

10 000

20 000

30 000

40 000

50 000

60 000

70 000

80 000

1 8

15

22

29

36

43

50

57

64

71

78

85

92

99

10

6

11

3

12

0

12

7

13

4

14

1

14

8

Load

leve

l [M

W]

Hours

20% 10% 5% 2.50% 0%

Largerrampsat high shares

More frequent up and down at high

shares

Smoothing effect at low shares

Note: Load data and wind data from Germany 10 to 16 November 2010, wind generation scaled, actual share 7.3%. Scaling may overestimate the impact of variability; combined effect of wind and solar may be lower, illustration only.

Net-load at different annual VRE shares

© OECD/IEA 2014 13

Page 14: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

-10 000

0

10 000

20 000

30 000

40 000

50 000

60 000

70 000

80 000

90 000

1 877 1753 2629 3505 4381 5257 6133 7009 7885

Load

leve

l [M

W]

Hours

0% 2.5% 5.0% 10.0% 20%

Lower minimumAbundance

Maximum remains

highScarcity

Changed utilisationpattern

Netload implies different utilisation for non-VRE system

Main persistent challenge: Utilisation

-10 000

0

10 000

20 000

30 000

40 000

50 000

60 000

70 000

80 000

90 000

1 877 1753 2629 3505 4381 5257 6133 7009 7885

Load

leve

l [M

W]

Hours

0% 2.5% 5.0% 10.0% 20%

Base-load

Mid-merit

Peak

Base-load

Mid-merit

Peak

Lower minimumAbundance

Maximum remains

highScarcity

Changed utilisationpattern

Note: Load data and wind data from Germany 10 to 16 November 2010, wind generation scaled, actual share 7.3%. Scaling may overestimate the impact of variability; combined effect of wind and solar may be lower, illustration only.

© OECD/IEA 2014 14

Page 15: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Context

The integration challenge

Flexibility and system transformation

System friendly VRE deployment

System operation

System planning and investment

Conclusions

Outline

© OECD/IEA 2014 15

Page 16: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Integration vs. transformation

Classical view: VRE are integrated into the rest

Integration costs: balancing, adequacy, grid

More accurate view: entire system is re-optimised

Total system costs

Integration is actually about transformation

Remaining system

VRE

Power system

• Generation • Grids • Storage • Demand Side Integration

© OECD/IEA 2014 16

Page 17: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

2. Make better use of

what you have

Op

eratio

ns

1. Let wind and solar play their

part

3. Take a system wide-strategic

approach to investments!

System friendly

VRE

Technology spread

Geographic spread

Design of power

plants

Three pillars of system transformation

© OECD/IEA 2014 17

Investm

ents

Page 18: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Main idea: minimise total system costs, not VRE generation costs alone!

5 aspects:

Deployment volumes

Location and technology mix

Technical capabilities

System friendly power plant design

Curtailment

Cost-effectiveness does not mean cheapest technology where resources are best

System friendly (V)RE deployment

© OECD/IEA 2014 18 Source: adapted from Agora, 2013

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

Monday Tuesday Wednesday Thursday Friday Saturday Sunday

Share of a

nnua

l gen

eration

[‰]

Conventional turbine configuration

System-oriented turbine configuration

Example: System friendly design of wind turbines reduces variability

Page 19: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

2. Make better use of

what you have

Op

eratio

ns

1. Let wind and solar play their

part

3. Take a system wide-strategic

approach to investments!

System friendly

VRE

Technology spread

Geographic spread

Design of power

plants

Three pillars of system transformation

© OECD/IEA 2014 19

Investm

ents

Page 20: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Forecasting of VRE production key strategy for cost-effective operation

Forecasts improve dramatically with shorter horizon

Real-time generation data key for short-term accuracy

More mature for wind than for PV

VRE production forecasts

© OECD/IEA 2014 20

0%

5%

10%

15%

20%

25%

1 5 9 13 17 21 25 29 33 37 41 45

Mea

n a

bso

lute

err

or

/ av

erag

e p

rod

uct

ion

Forecast horizon (Hours before real-time)

2008 2009

2010 2011

2012

Accuracy of wind forecasts in Spain

Source: REE

Page 21: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Short scheduling intervals (5min best practice)

Adjust schedules up to real time (5min best practice)

Generation and transmission schedules

© OECD/IEA 2014 21

6 7 8 9

Cap

acit

y (M

W)

Time (hours)

Actual load curve

Load schedule -15 minutes

Load schedule -60 minutes

Balancing need 15 min schedule

Balancing need60 min schedule

Impact of scheduling interval on reserve requirements, illustration

Page 22: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Germany has four balancing areas (historic reasons)

Reserve sharing mechanism across four areas

Reduced requirements despite rapid increase of VRE

Co-operation with neighbours

© OECD/IEA 2014 22

0

10

20

30

40

50

60

0

1

2

3

4

5

6

7

8

2008 2009 2010 2011 2012

Inst

alle

d V

RE

cap

acit

y (G

W)

Res

erve

req

uir

emen

t (G

W) VRE

capacity

Upward reserves

Downward reserves

+100%

+0%

-40%

Required frequency restoration reserves in Germany

Page 23: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Are your operating reserve and system service definitions VRE ready?

Example Ireland DS3 programme

System service definitions

© OECD/IEA 2014 23

• Synchronous Inertial Response• Fast Frequency Response• Fast Post-Fault Active Power

Recovery

• Ramping Margin

0 – 5s 5 – 90s 90s – 20min 20min – 12hr

Inertial

Response

Reserve

Ramping

POR

SOR

TOR1

TOR2

RR

Ramping

SIR

FFR

time

Source: EirGrid • Dynamic Reactive Power

ms – s

Transient Voltage Response

Voltage Regulation

Network

Dynamic

Reactive

Power

Network

Adequacy

Grid 25

s – min min – hr

Steady-state

Reactive

Power

• Steady-state Reactive Power

Page 24: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

2. Make better use of

what you have

Op

eratio

ns

1. Let wind and solar play their

part

3. Take a system wide-strategic

approach to investments!

System friendly

VRE

Technology spread

Geographic spread

Design of power

plants

Three pillars of system transformation

© OECD/IEA 2014 24

Investm

ents

Page 25: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

* Compound annual average growth rate 2012-20 , slow <2%, dynamic ≥2%; region average used where country data unavailable This map is without prejudice to the status of or sovereignty over any territory, to the delimitation of international frontiers and boundaries and to the name of any territory, city or area.

Transformation depends on context

© OECD/IEA 2014 25

Stable Power Systems

• Little general investment need short term

Dynamic Power Systems

• Large general investment need short term

Slow demand growth*

Dynamic demand growth*

Maximise the contribution from existing flexible assets

Decommission or mothball inflexible polluting surplus capacity to foster system transformation

Implement holistic, long-term transformation from onset

Use proper long-term planning instruments to capture VRE’s contribution at system level

Page 26: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Large shares of VRE can be integrated without significantly increasing power system costs in the long run.

Achieving this successfully requires a system-wide transformation.

System cost and transformation Test System

© OECD/IEA 2014 26

86-94

104 -119 100 - 112 97-109

0

20

40

60

80

100

120

140

Legacy Transformed

generation

Transformed

generation and 8% DSI

0% VRE 45% VRE penetration

Total system

cost (USD

/MWh)

Grid–high

Grid–low

DSI

Fixed VRE

Emissions

Fuel

Startup

Fixed

non–VRE

Page 27: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Transformation of the generation mix

Significant shift in the dispatchable plant mix due to balancing and flexibility effect

Dispatchable plants need to: Ramp quickly, at short notice and in a wide range

Remain cost-effective at mid-merit and peaking capacity factors

Reservoir hydro can be ideal match

© OECD/IEA 2014 27

Page 28: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Importance of coordinated development of grid and generation well understood

Chicken and egg problem for first-off, distant VRE projects Competitive

Renewable Energy Zones (CREZ), Texas

Irish gate system

Appropriate cost recovery is key!

Planning the grid - transmission

© OECD/IEA 2014 28

345 kV double-circuit upgrades identified in

CREZ transmission plan

CREZ, Texas

Source: NREL

Page 29: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Role of distribution grid bound to change fundamentally with rise of distributed generation

Target levels for in-feed, not just consumption?

Planning the grid - distribution

© OECD/IEA 2014 29

Power flows across HV-MV transformer example form Bavaria, Germany

Source: Bayernwerk, Fraunhofer IWES

Page 30: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Existing planning tools struggle to represent VRE contribution to generation adequacy

Match between power demand and VRE profile has a critical impact on capacity credit of VRE Consider firm capacity from VRE over maximum possible geographic footprint

Seek to include structural shifts in power demand when assessing the capacity credit of VRE (may require new tools!)

Capacity credit of VRE – Interconnection and DSI

© OECD/IEA 2014 30

Contribution of Demand Side Integration (DSI) to shape of electricity demand, Great Britain

Page 31: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Context

The integration challenge

Flexibility and system transformation

System friendly VRE deployment

System operation

System planning and investment

Conclusions

Outline

© OECD/IEA 2014 31

Page 32: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Integration challenged result from interaction

On VRE side: 6 relevant properties

Already at low shares:

Avoid uncontrolled local concentrations of VRE power plants (“hot spots”)

Ensure that VRE power plants can contribute to stabilising the grid when needed

Use state of the art VRE forecast techniques

When VRE impact becomes noticeable:

Optimise system and market operations

Deploy VRE in a system-friendly way to maximise their value to the overall system

Conclusions 1/2

© OECD/IEA 2014 32

Page 33: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Countries with dynamic power systems should

Approach VRE integration as a question of holistic, long-term system transformation from the onset

Consistent approach to entire generation mix

Chicken-and-egg problem with first, distant VRE sites

Shifted role of distribution grid

Use energy planning tools and strategies that appropriately represent VRE’s contribution at system level

Ensure that accurate techniques are capacity credit assessment techniques

Conclusions 2/2

© OECD/IEA 2014 33

Page 34: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Thanks [email protected]

© OECD/IEA 2014 34

Page 35: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Additional backup

© OECD/IEA 2014 35

Page 36: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

-20

0

20

40

60

80

321 322 323 324 325 326 327

GW

Day of the year Wind Solar Demand Net load

Investments in system flexibility – Need for a suite of solutions

© OECD/IEA 2014 36

Solar and wind can be abundant …

… or scarce.

No single resource does it all!

: very suitable, :suitable, o : neutral, : unsuitable Data: Germany 2011, 3x actual wind and solar PV capacity

Example:

Abundance Flexible generation

DSI

Storage

Curtailment

Scarcity Flexible generation

DSI o

Storage

Curtailment

-20

0

20

40

60

80

33 34 35 36 37 38 39

GW

Day of the year Wind Solar Demand Net load

Page 37: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Investment Model for Renewable Energy Systems (IMRES) Test system: Similar size to Germany but isolated system

Dispatchable power plant mix optimised by model

Different levels of VRE penetration – up to 45% in annual generation – were investigated.

Different scenarios: Extreme and purely hypothetical case: a share of 45% VRE in annual

generation was added to the system overnight and only the operation of the remaining system was allowed to change (Legacy case)

Different scenario of the test system considers a more transformative approach. The installed power plant mix is re-optimised in the presence of 45% VRE and additional flexibility options are deployed (Transformed case).

Modelling 45% of wind and solar PV

© OECD/IEA 2014 37

Page 38: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Benefit/cost of flexibility options North West Europe - DSI

Overall system savings of 2.0 bln $/year

DSI costs of 0.9 bln $/year

Note: graph represents the differences between DSI scenario (DSI 8% of overall demand) and baseline scenario

Benefit/cost ratio: 2.2

© OECD/IEA 2014 38

-29 -140-437

-1 539

899128

-2 500

-2 000

-1 500

-1 000

- 500

0

500

1 000

1 500

System benefit DSI costs

Mill

ion

USD

per

yea

r

DSI

Capex CCGT

Fixed Opex

Start up costs

Variable cost incl. fuel

CO2 costs

DSI assumed to be 8% of annual power demand:

• 71% made of heat and other schedulable demand (110 TWh)

• 29% EV demand (44 TWh)

CO2 price USD 30 per tonne Coal price USD 2.7/Mmbtu Gas price USD 8/Mmbtu

Page 39: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

Benefit/cost of flexibility options North West Europe

DSI has large benefits at comparably low costs

Interconnection allows a more efficient use of distributed flexibility options and generates synergies with storage and DSI

Cost effectiveness of hydro plant retrofit depend on project specific measures and associated investment needs

Notes: 1) CAPEX assumed for selected flexibility options: interconnection 1,300$/MW/km onshore and 2,600$/MW/km offshore, pumped hydro storage 1,170$/kW, reservoir

hydro 750 $/kW -1,300$/kW (repowering of existing reservoir hydro increasing available capacity). Cost of DSI is assumed equal to 4.7 $/MWh of overall power demand (adjustment of NEWSIS results)

2) Fuel prices and CAPEX ($/kW) for VRE and flexibility options are assumed constant across all scenarios Source: IEA/PÖYRY

2.3 2.2

1.2 1.1 1.1

0.6 - 1.5

DSI + IC DSI IC Storage + IC Storage Hydro capacity boost

Benefit/cost ratio

1

© OECD/IEA 2014 39

Page 40: Grid Integration of Renewables - International Energy · PDF fileGrid Integration of Renewables Energy Training Week ... Note: ERCOT = Electricity ... Low short run cost Non synchro-nous

© OECD/IEA 2014

2) Better system & market operation

VRE forecasting

Better market operations:

Fast trading Best practice: ERCOT (Texas) – 5 minutes

Price depending on location Best practice: ERCOT – Locational Marginal Prices

Better flexibility markets Example: Reserve provision not always remunerated

Make better use of what you have already!

Example: ERCOT market design

© OECD/IEA 2014 40