DAFTAR BAHAN DAN UPAH KEGIATAN PEKERJAAN LOKASI TAHUN HARGA SATUAN NO J E N I S B A H A N SATUAN BAHAN KETERANGAN ( Rp ) A. AGREGAT KASAR, BAHAN PEREKAT DAN BAHAN JADINYA 1 Tanah urug m3 120.120,00 DIPROYEK 2 Pasir Mahakam m3 219.000,00 DIPROYEK 3 Pasir Tenggarong m3 300.000,00 DIPROYEK 4 Pasir Palu m3 445.000,00 DIPROYEK 5 Batu pecah 2/3 m3 550.000,00 DIPROYEK 6 Batu gunung m3 497.000,00 DIPROYEK 7 Bata merah Bh 1.650,00 DIPROYEK 8 Paving block lokal (warna) Bh 5.030,00 DIPROYEK Segi Empat, 10,5x21x6 cm ( 43 bh/m2) 9 Semen PC 50 kg/zak Zak 113.750,00 DIPROYEK 10 Semen PC Kg 2.275,00 DIPROYEK 11 Semen warna Zak 131.250,00 DIPROYEK 12 Semen warna Kg 2.625,00 DIPROYEK 13 Air Bersih (PDAM) 11.500,00 DIPROYEK 14 Kansteen Beton Ukuran 10 x 20 x 50 Bh 32.500,00 DIPROYEK 15 Buis Beton U-30 Bh 75.000,00 DIPROYEK Hal 1 - 2 HARGA SATUAN NO J E N I S B A H A N SATUAN BAHAN KETERANGAN ( Rp ) B. BAHAN KAYU BERIKUT BAHAN JADINYA 1 Papan Bengkirai m3 8.043.750,00 DIPROYEK 2 Papan Meranti m3 4.772.620,00 DIPROYEK 3 Papan Kapur m3 7.239.370,00 DIPROYEK 4 Balok Meranti m3 3.700.120,00 DIPROYEK 5 Balok Bengkirai m3 7.239.370,00 DIPROYEK 6 Balok Ulin m3 5.280.000,00 DIPROYEK 7 Balok Kapur m3 5.630.620,00 DIPROYEK Papan Bouwplank m3 3.539.250,00 DIPROYEK C. BAHAN LOGAM DAN PAKU 1 Paku kayu 2"-6" kg 20.125,00 DIPROYEK D. UPAH KERJA 1 Pekerja JE 8.000,00 2 Mandor JE 12.250,00 3 Pekerja biasa Hari 80.000,00 PERORANG 4 Mandor Hari 145.000,00 PERORANG 5 Tukang batu Hari 125.000,00 PERORANG 6 Kepala Tukang batu Hari 135.000,00 PERORANG 7 Tukang kayu Hari 125.000,00 PERORANG 8 Kepala Tukang kayu Hari 135.000,00 PERORANG 9 Tukang Cat Hari 125.000,00 PERORANG 10 Kepala Tukang Cat Hari 135.000,00 PERORANG 11 Tukang Besi Hari 125.000,00 PERORANG 12 Kepala Tukang Besi Hari 135.000,00 PERORANG Hal 2 - 2

Harga Bahan Dan Upah

Embed Size (px)

DESCRIPTION

harga

Citation preview

  • DAFTAR BAHAN DAN UPAH

    KEGIATAN

    PEKERJAAN

    LOKASI

    TAHUN

    HARGA SATUAN

    NO J E N I S B A H A N SATUAN BAHAN KETERANGAN

    ( Rp )

    A. AGREGAT KASAR, BAHAN PEREKAT DAN

    BAHAN JADINYA

    1 Tanah urug m3 120.120,00 DIPROYEK

    2 Pasir Mahakam m3 219.000,00 DIPROYEK

    3 Pasir Tenggarong m3 300.000,00 DIPROYEK

    4 Pasir Palu m3 445.000,00 DIPROYEK

    5 Batu pecah 2/3 m3 550.000,00 DIPROYEK

    6 Batu gunung m3 497.000,00 DIPROYEK

    7 Bata merah Bh 1.650,00 DIPROYEK

    8 Paving block lokal (warna) Bh 5.030,00 DIPROYEK

    Segi Empat, 10,5x21x6 cm ( 43 bh/m2)

    9 Semen PC 50 kg/zak Zak 113.750,00 DIPROYEK

    10 Semen PC Kg 2.275,00 DIPROYEK

    11 Semen warna Zak 131.250,00 DIPROYEK

    12 Semen warna Kg 2.625,00 DIPROYEK

    13 Air Bersih (PDAM) M 11.500,00 DIPROYEK

    14 Kansteen Beton Ukuran 10 x 20 x 50 Bh 32.500,00 DIPROYEK

    15 Buis Beton U-30 Bh 75.000,00 DIPROYEK

    Hal 1 - 2

    HARGA SATUAN

    NO J E N I S B A H A N SATUAN BAHAN KETERANGAN

    ( Rp )

    B. BAHAN KAYU BERIKUT BAHAN JADINYA

    1 Papan Bengkirai m3 8.043.750,00 DIPROYEK

    2 Papan Meranti m3 4.772.620,00 DIPROYEK

    3 Papan Kapur m3 7.239.370,00 DIPROYEK

    4 Balok Meranti m3 3.700.120,00 DIPROYEK

    5 Balok Bengkirai m3 7.239.370,00 DIPROYEK

    6 Balok Ulin m3 5.280.000,00 DIPROYEK

    7 Balok Kapur m3 5.630.620,00 DIPROYEK

    Papan Bouwplank m3 3.539.250,00 DIPROYEK

    C. BAHAN LOGAM DAN PAKU

    1 Paku kayu 2"-6" kg 20.125,00 DIPROYEK

    D. UPAH KERJA

    1 Pekerja JE 8.000,00

    2 Mandor JE 12.250,00

    3 Pekerja biasa Hari 80.000,00 PERORANG

    4 Mandor Hari 145.000,00 PERORANG

    5 Tukang batu Hari 125.000,00 PERORANG

    6 Kepala Tukang batu Hari 135.000,00 PERORANG

    7 Tukang kayu Hari 125.000,00 PERORANG

    8 Kepala Tukang kayu Hari 135.000,00 PERORANG

    9 Tukang Cat Hari 125.000,00 PERORANG

    10 Kepala Tukang Cat Hari 135.000,00 PERORANG

    11 Tukang Besi Hari 125.000,00 PERORANG

    12 Kepala Tukang Besi Hari 135.000,00 PERORANG