8/10/2019 HMS WBS Complete
1/7
1.0
Hotel Management
System
1.1
System S/W
1.2
Quality
Assurance
1.3
Configuration
Management
1.4
Software
Systems
1.5
Hardware
1.6
Kernal
1.7
Documentation
1.8
Development
Software Support
1.9
Software Support
Environment
1.4.1Reservations/
Booking
1.4.2Food Service
Work Breakdown Structure First Decomposition
1.4.3General
Management
Contd. Contd. Contd.
1.
8/10/2019 HMS WBS Complete
2/7
1.4.1
Reservations/
Booking
1.4.1.3
Preliminary
Design
1.4.1.4
Detailed Design
1.4.1.5
Code Unit
& Test
1.4.1.6
Integration
and Test
1.4.1.7
System Testing
Work Breakdown Structure Reservations/Booking Decomposition
1.4.1.1
Project Initiation
1.4.1.2
Requirements
1.4.1.8
Product Rollout
1.4.1.1.1System
Architec-
ture
1.4.1.1.2Top
level
Project
Plan
1.4.1.2.1Project
Scope
1.4.1.2.2Establish
User
Needs
1.4.1.2.3Model
Process
1.4.1.2.4Analyze
Solution
Alterna-
tives
1.4.1.2.5Recom-
mend
Solutions
1.4.1.3.1Establish
Technical
Frame-
work
1.4.1.3.2Design
System
Frame-
work
Contd. 1.4.1.5.1Code
Test,
Unit
Test
1.4.1.6.1Prepare
& Perform
Integration
Test
1.4.1.7.1Prepare
& Perform
System
Test
1.4.1.8.1Finished
Product
2.
8/10/2019 HMS WBS Complete
3/7
1.4.1
Reservations/
Booking
1.4.1.3
Preliminary
Design
1.4.1.4
Detailed Design
1.4.1.5
Code Unit
& Test
1.4.1.6
Integration
and Test
1.4.1.7
System Testing
1.4.1.4.1Database
Res./Booking
Table
1.4.1.4.2User Interface
Work Breakdown Structure Reservations/Booking Decomposition
1.4.1.3.1.1
Application
Function
1.4.1.3.1.2
Module
Interface
1.4.1.4.3Rep;orts
generated
1.4.1.4.4Internal clock 1.4.1.4.5Adjustable
default rate
1.4.1.4.6Description Field 1.4.1.4.7Customer Feedback
Description Field
1.4.1.3.2.1
Application
Function
1.4.1.3.2.2
Module
Interface
1.4.1.3.3.1
Application
Function
1.4.1.3.3.2
Module
Interface
1.4.1.3.4.1
Application
Function
1.4.1.3.5.1
Module
Interface
1.4.1.3.6.1
Module
Interface
1.4.1.3.7.1
Module
Interface
1.4.1.1
Project Initiation
1.4.1.2
Requirements
1.4.1.8
Product Rollout
3.
8/10/2019 HMS WBS Complete
4/7
1.4.2
Food Service
1.4.2.3
Preliminary
Design
1.4.2.4
Detailed Design
1.42.5
Code Unit
& Test
1.4.2.6
Integration
and Test
1.4.2.7
System Testing
Work Breakdown Structure Food Service Decomposition
1.4.2.1
Project Initiation
1.4.2.2
Requirements
1.4.2.8
Product Rollout
1.4.2.1.1System
Architec-
ture
1.4.2.1.2
Top
level
Project
Plan
1.4.2.2.1
Project
Scope
1.4.2.2.2
Establish
User
Needs
1.42.2.3
Model
Process
1.4.2.2.4
Analyze
Solution
Alterna-
tives
1.4.2.2.5
Recom-
mend
Solutions
1.4.2.3.1
Establish
Technical
Frame-
work
1.4.2.3.2
Design
System
Frame-
work
Contd. 1.4.2.5.1Code
Test,
Unit
Test
1.4.2.6.1Prepare
& Perform
Integration
Test
1.4.2.7.1Prepare
& Perform
System
Test
1.4.2.8.1Finished
Product
4.
8/10/2019 HMS WBS Complete
5/7
1.4.2
Food Service
1.4.2.4.1
Database
Food Order
Tables
1.4.2.4.2
User Interface
Work Breakdown Structure Food Service Decomposition
1.4.2.3.1.1
Application
Function
1.4.2.3.1.2
Module
Interface
1.4.2.4.3
Automatic Charge
To room
1.4.2.3.2.1
Application
Function
1.4.2.3.2.2
Module
Interface
1.4.2.3.3.1
Application
Function
1.4.2.3.3.2
Module
Interface
1.4.2.1
Project Initiation
1.4.2.2
Requirements
1.4.2.3
Preliminary
Design
1.4.2.4
Detailed Design
1.4.2.5
Code Unit
& Test
1.4.2.6
Integration
and Test
1.4.2.7
System Testing
1.4.2.8
Product Rollout
5.
8/10/2019 HMS WBS Complete
6/7
1.4.3
General Management
1.4.3.3
Preliminary
Design
1.4.3.4
Detailed Design
1.43.5
Code Unit
& Test
1.4.3.6
Integration
and Test
1.4.3.7
System Testing
Work Breakdown Structure General Management Decomposition
1.4.3.1
Project Initiation
1.4.3.2
Requirements
1.4.3.8
Product Rollout
1.4.3.1.1System
Architec-
ture
1.4.3.1.2
Top
level
Project
Plan
1.4.3.2.1
Project
Scope
1.4.3.2.2
Establish
User
Needs
1.43.2.3
Model
Process
1.4.3.2.4
Analyze
Solution
Alterna-
tives
1.4.3.2.5
Recom-
mend
Solutions
1.4.3.3.1
Establish
Technical
Frame-
work
1.4.3.3.2
Design
System
Frame-
work
Contd. 1.4.3.5.1Code
Test,
Unit
Test
1.4.3.6.1Prepare
& Perform
Integration
Test
1.4.3.7.1Prepare
& Perform
System
Test
1.4.3.8.1Finished
Product
6.
8/10/2019 HMS WBS Complete
7/7
1.4.3
General Management
Work Breakdown Structure General Management Decomposition
1.4.3.4.1.1
Application
Function
1.4.3.4.1.2
Module
Interface
1.4.3.4.1Hotel Occupancy
Reports
1.4.3.4.2Future Occupancy
Reports
1.4.3.4.3Room Revenue
Reports
1.4.3.4.4Food Revenue
Reports
1.4.3.4.5Exception
Reports
1.4.3.4.6Addition, deletion,
modification of
Information
1.4.3.4.7Creating Users
Assigning
Passwords
1.4.3.4.1.3
User
Interface
Continued
(same as Hotel
Occupancy
continuation)
Continued
(same as Hotel
Occupancy
continuation)
Continued
(same as Hotel
Occupancy
continuation)
Continued
(same as Hotel
Occupancy
continuation)
Continued
(same as Hotel
Occupancy
continuation)
Continued
(same as Hotel
Occupancy
continuation)
1.4.3.1
Project Initiation
1.4.3.2
Requirements
1.4.3.3
Preliminary
Design
1.4.3.4
Detailed Design
1.4.3.5
Code Unit
& Test
1.4.3.6
Integration
and Test
1.4.3.7
System Testing
1.4.3.8
Product Rollout
7.
1.4.3.4.8Database
Report Table
1.4.3.4.8.1
Application
Function
1.4.3.4.8.2
Module
Interface