Energy saving solution Payback time!
Calculations show you how fast your investment will be repaid by energy saving
6 cases With payback time
Energy saving solution Data gathering
Name of the building owner
( e.g. Building Society name )
Address Name of person
responsible for project
Building datayear of
construction type of
technology number of
Type of heat source
( e.g. central district heating ,
local boiler station )
Details about substation
( type of wheatear compensators, anther details )
Picture of building
1995 1996 1997 1998 1999 2000 2005 2006 2007 2008
1995 1996 1997 1998 1999 2000 2005 2006 2007 2008
instalation cost
unit prices TRV Balancing Valves Zuzycie energii w KW na cele ciepłej wodyDN 15 Moc zamówiona w MW na cele ciepłej wody DN20DN25 Całkowite zuzycie w GJ ( cwu + co ) DN32 Całkowita moc w MW ( cwu + co ) DN40DN50
Zużcie ciepłej wody w m3
Calculation : pay back time
Energy used in GJ for DHW
additioal costs
total cost
Energy consumption
Energy used in GJ for heating Energu used in KW for heating Power order in MW for heating
stocktaking prices design prices ( recalculation ) investment prices products
Reference data for Energy Saving Brochure data
Risers profile
Prices for 1 MW ordered power for hot water per month in local current Prices per 1 m2 for heating if occupants are charge by surface Calculated total heat power for building for heating in KW ……………….
Avarage yearly outdoor temperatureInformation about instalation : heating and hot water
Unit energy prices
Data about building : number of stories .........................surface on the building in m2 ………………Building cubature in m3 ……………number of flats ( apartments ) ……………………..number of occupants ……….Contact person from Danfoss side :
1 GJ - energy prices for heating in local current Prices for 1 MW ordered power for heating per month in local current Price for heat 1m3 hot water in local currency
number of risers DN 40 mm
number of radiators number of risers in heating system number of risers DN 15 mm
Profile of heating systems Profile of hot water systems
Calculated total power for hot water system in KW ……………….
number of risers DN 50 mm
number of TRV's DN 10mmnumber of TRV's DN 15mmnumber of TRV's DN 20 mm
number of hot water circulation risersMTCV - DN 15 MTCV - DN 20
number of risers DN 20 mm number of risers DN 25 mm number of risers DN 32 mm
Information about thermo-modernisation program
Main data about building
Energy prices
System futures Modernization
Energy consumption!!!
Optional footer text Division, SBA or department name 28 februari 2013 | 3 Hydronic Balancing & Control 6 October 2011 l 3 Hydronic Balancing & Control 28 February, 2013 l 3
Evaluation of figures Data collection in a table
Year Energy usage
(heating) [GJ]
Corrected energy usage
to 2,4°C
Saving in % compared to
1995
Saving in % due to automatic balancing valve copm. to 1999
Extra saving in % due to ABV in risers (2002)
Average outdoor
temp. [°C] Action
1995 2084 2,4
1996 2006 1945 6,7% 2,1 TRV, HCA installation
1997 1741 1878 9,9% 3,1
1998 1760 1837 11,9% 2,8
1999 1537 1757 15,7% 3,6
2000 1505 2247 -7,8% 5,57 ∆p contr. in substation
2001 1167 1347 35,4% 23,3% 3,68
2002 1161 1348 35,3% 23,3% 3,73 ∆p contr. in risers
2003 1275 1259 39,6% 28,3% 6,6% 2,28
2004 1068 1240 40,5% 29,4% 8,0% 3,73
2005 978 1126 46,0% 35,9% 16,5% 3,66 Substation separation
2006 960 945 54,6% 46,2% 2,25
2007 676 980 53,0% 44,2% 5,38
2008 853 1248 40,1% 28,9% 5,44
Optional footer text Division, SBA or department name 28 februari 2013 | 4 Hydronic Balancing & Control 28 February, 2013 l 4
Calculation method: based on basic temperature (this temperature is that
yearly average outdoor temperature when the internal temperature will not go bellow ~20°C due to internal/external heat sources)
it is around 12°C at traditionally insulated block of flat (panel buildings)
Compensated energy usage:
avrageyearly
correctedyearlydcompensate t
tQQ_12
12−−
•=
Evaluation of figures Compensation to certain outdoor temperature
Optional footer text Division, SBA or department name 28 februari 2013 | 5
Year
Energy usage
(heating) [GJ]
Corrected energy usage
to 2,4°C
Saving in % compared to
1995
Saving in % due to automatic balancing valve copm. to 1999
Extra saving in % due to ABV in
risers (2002)
Average outdoor
temp. [°C] Action
1995 2084 2,4
1996 2006 1945 6,7% 2,1 TRV, HCA installation
1997 1741 1878 9,9% 3,1
1998 1760 1837 11,9% 2,8
1999 1537 1757 15,7% 3,6
2000 1505 2247 -7,8% 5,57 ∆p contr. in substation
2001 1167 1347 35,4% 23,3% 3,68
2002 1161 1348 35,3% 23,3% 3,73 ∆p contr. in risers
2003 1275 1259 39,6% 28,3% 6,6% 2,28
2004 1068 1240 40,5% 29,4% 8,0% 3,73
2005 978 1126 46,0% 35,9% 16,5% 3,66 Substation separation
2006 960 945 54,6% 46,2% 2,25
2007 676 980 53,0% 44,2% 5,38
2008 853 1248 40,1% 28,9% 5,44
ageyearlya
correctedyearlydcompensate t
tQQvar12
12−−
•=Evaluation of figures Data collection in a table
Optional footer text Division, SBA or department name 28 februari 2013 | 6
Year
Energy usage
(heating) [GJ]
Corrected energy usage
to 2,4°C
Saving in % compared to
1995
Saving in % due to automatic balancing valve copm. to 1999
Extra saving in % due to ABV in
risers (2002)
Average outdoor
temp. [°C] Action
1995 2084 2,4
1996 2006 1945 6,7% 2,1 TRV, HCA installation
1997 1741 1878 9,9% 3,1
1998 1760 1837 11,9% 2,8
1999 1537 1757 15,7% 3,6
2000 1505 2247 -7,8% 5,57 ∆p contr. in substation
2001 1167 1347 35,4% 23,3% 3,68
2002 1161 1348 35,3% 23,3% 3,73 ∆p contr. in risers
2003 1275 1259 39,6% 28,3% 6,6% 2,28
2004 1068 1240 40,5% 29,4% 8,0% 3,73
2005 978 1126 46,0% 35,9% 16,5% 3,66 Substation separation
2006 960 945 54,6% 46,2% 2,25
2007 676 980 53,0% 44,2% 5,38
2008 853 1248 40,1% 28,9% 5,44
%3,23 1757
1347-1757En.saving ==
%7,6 2084
1945-2084En.saving ==
%6,6 1348
1259-1348En.saving ==
Evaluation of figures Data collection in a table
Optional footer text Division, SBA or department name 28 februari 2013 | 7 Hydronic Balancing & Control 28 February, 2013 l 7
Based on actual price list with standard discount
Evaluation of figures Investment cost calculation
Optional footer text Division, SBA or department name 28 februari 2013 | 8
Based on energy saving and energy price
only TRV ABV in SS ASV-P/M Sum4816 1085 2410 7226365,7 476,5 97,6 795,56,49 6,49 6,49 6,492,0 0,4 3,8 1,4
Investment cost [€]Investment type
*Without DH investment the system become ∆p controlled and the energy saving is fixed.
Pay back time [year]Energy price (DH) [€/GJ]Av. yearly energy saving [GJ]
Evaluation of figures Pay back time calculation
Optional footer text Division, SBA or department name 28 februari 2013 | 9 Hydronic Balancing & Control 6 October 2011 l 9 Hydronic Balancing & Control 28 February, 2013 l 9
Case study 1 Two pipe heating system
637 pcs
30 pcs
Optional footer text Division, SBA or department name 28 februari 2013 | 10 Hydronic Balancing & Control 6 October 2011 l 10 Hydronic Balancing & Control 28 February, 2013 l 10
Case study 2 One pipe heating system
291 pcs
Optional footer text Division, SBA or department name 28 februari 2013 | 11 Hydronic Balancing & Control 6 October 2011 l 11 Hydronic Balancing & Control 28 February, 2013 l 11
Case study 3 One pipe heating system
128 pcs
Optional footer text Division, SBA or department name 28 februari 2013 | 12 Hydronic Balancing & Control 6 October 2011 l 12 Hydronic Balancing & Control 28 February, 2013 l 12
Case study 4 Domestic hot water
40 pcs
Optional footer text Division, SBA or department name 28 februari 2013 | 13 Hydronic Balancing & Control 6 October 2011 l 13 Hydronic Balancing & Control 28 February, 2013 l 13
Case study 5 Cooling system
50 pcs
Optional footer text Division, SBA or department name 28 februari 2013 | 14 Hydronic Balancing & Control 6 October 2011 l 14 Hydronic Balancing & Control 28 February, 2013 l 14
Case study 6 Global modernization
130 pcs
5 pcs
26 pcs
estimated
Optional footer text Division, SBA or department name 28 februari 2013 | 15 Hydronic Balancing & Control 6 October 2011 l 15 Hydronic Balancing & Control 28 February, 2013 l 15
Conclusion Very effitient investment If we use suitable solutions energy (money)
savings are significant
We can proof it base on cases studies!
In that cases studies we :
- collected precise data
- made precise calculation
Results you already know.
less than 4 year Payback time