IF 3507Manajemen Proyek Perangkat Lunak
2 sks
Elisati Hulu
Department of Informatics
Simbol
Task#/D
ES EF
LFLS
D: Task DurationES: Early StartEF: Early FinishLS: Late StartLF: Late Finish
ES,EF,LS,LF
A/2
0 2
20
B/5
2 7
72
D/6
7 13
13
4
F/3
13
16
16
13
C/3
2 5
96
E/4
5 9
13
9
Critical Path
Free Slack dan Total Slack Free slack
Difference between early finish (EF) time of an activity and the earliest of the early start (ES) times of all its immediate successors
Total Slack Difference between late start (LS) and
early start times (ES)or
Difference between latest finish (LF) and earliest finish times (EF)
Menghitung Free Slack
Aktifitas EF dari (i) ES (i+1) Free Slack
A 2 2 0B 7 7 0C 5 5 0D 13 13 0E 9 13 4F 16 16 0
Menghitung Total Slack
Aktifitas
ES LS EF LF Total Slack
A 0 0 2 2 0B 2 2 7 7 0C 2 6 5 9 4D 7 7 13 13 0E 5 9 9 13 4F 13 13 16 16 0