Upload
andre-zardo-cruber
View
215
Download
0
Embed Size (px)
Citation preview
8/13/2019 Importncia do SURGE-Test
1/11
Forget the controversy. These tests clearly are non-destructive in nature.
Understanding the advantages these methods have over others can make them
mighty powerful tools in your PdM program.
Before any company investigates electrical predictive maintenance (PdM)
instrumentation, it should know the strengths of its equipment's insulation, thevoltages its motors are exposed to daily, how a motor typically fails and where
these faults typically exist. Only then can you really make a decision as to which
electrical PdM equipment is the most appropriate for your operations.
How a motor typically fails
The motor stator has two main insulating systems that include the ground wall and
turn-to-turn insulation. When this insulation is in a good condition it can
withstand the normal day-to-day voltage spikes that exist during starting and
stopping. Over time, this insulation will deteriorate as a result of mechanical
movement of the windings, torque transients, heat, contamination, and other
environmental contaminates. Once the dielectric strength of this insulation fallsbelow the incoming voltage spikes, another failure mechanism is introduced:
ozone.
Ozone is a very corrosive gas that will quickly deteriorate insulation. Although the
motor will continue to run when this failure mechanism is introduced, as it sees
continual voltage spikes, the deterioration rate will accelerate. Eventually, the
dielectric strength of the insulation will fall below operating voltage or deteriorate
to the point that copper wire will touch turn-to-turn. At this point a turn-to-turn
or hard welded short has developed.
According to "Transient Model for Induction Machines with Stator Winding Turn
Faults" written for IEEE by Rangarajan M. Tallam, Tom G. Habetler and Ronald
G. Harley, when a hard welded turn-to-turn short develops, the shorted windings
will develop high circulating currents. These currents, which can be in the order of
1620 times full-load amps, create excessive heat that the insulation cannot
withstand. This intense amount of heat will burn quickly through the insulation-
causing motor failure within minutes.
A study performed at Oregon State University, by Dr. Ernesto Wiedenbrug,
looked at a motor specially designed with a turn-to-turn fault by installing two
wires connected to turn one and turn two of the same phase. These wires were thenbrought out to a switch. The motor was placed on a dynamometer and run at
about 80% load. When the turn-to-turn short was engaged through the switch, the
motor began visibly smoking within 45 seconds. While most motors will not run
for long with a turn-to-turn short, some exceptions do exist. A motor with a high
resistance or floating ground will run with a shorted phase, but once a second
phase shorts, the motor will fail catastrophically.
Recommended tests The tests listed on the next page are recommended in off-line
field testing:
Kelvin Method Winding Meg-Ohm
8/13/2019 Importncia do SURGE-Test
2/11
Polarization Index (PI) Step-Voltage Surge
Each of these test methods evaluates a different section of the motor. Brief
descriptions of the first three tests are given in order to offer a complete array oftesting information. The nature of high-voltage testing and the necessity of the
Step-Voltage and Surge methods, however, remain the main focus of this article.
Kelvin Method Winding...
The Kelvin Method Winding test measures the resistance of the copper wire of the
motor circuit. If tested in a PdM application, the test is typically performed from
the Motor Control Center (MCC). This test finds issues with miss connections,
shorts, opens, unbalanced turn count in one phase to another and different size
diameter copper in one phase to another. This test is very valuable and should be
performed for predictive maintenance, troubleshooting and quality assurance.
Meg-Ohm Test...
The Meg-Ohm Test applies a DC potential (typically operating voltage) to the
windings while holding the case to ground. Table I shows the recommended test
voltages for different voltage class motors. Meg-Ohm testing is typically utilized to
find grounded motors. It also is a very valuable PdM tool for finding wet and dirty
motors. It's not typically used for quality assurance because of the low voltage level
at which the test is performed.
Polarization Index (PI ) Test...
This test is much like the Meg-Ohm Test, but it is performed for 10 minutes. Over
this time period, the molecules in the slot liner paper polarize. When the molecules
polarize, the insulation resistance values should increase over the10- minute
period. If the resistance increases during this time, it's an indication of good
ground wall insulation with no moisture or contamination.
Insulation testing
Until now we have only discussed the low-voltage tests. Upon successfully
completing these tests the following is known: the winding resistance is balanced.
That means the motor has no shorts, opens or miss connections and the Meg-Ohmand PI indicate that the motor is both clean and dry. These tests, however, still
8/13/2019 Importncia do SURGE-Test
3/11
have not confirmed that the motor is capable of starting or running for any length
of time. The main reason for performing predictive maintenance on a motor is to
learn if it will continue to provide uninterrupted service. Because low-voltage
testing is not performed at the voltage a motor typically sees, it can't provide this
information.
Many articles have discussed the voltage spikes motors see during starting and
stopping. As stated in "Turn Insulation Capability of Large AC Motors, Part I
Surge Monitoring," by B.K. Gupta, B.A. Lloyd, G.C. Stone, and S.R Campbell
(IEEE Transactions on Energy Conversion, Vol. EC-2, No. 4, December 1987),
these voltage spikes can be in the order of 5 PU (Per Unit):
Calculating this formula for a 480V three phase motor, the PU would be 391.9
volts, or approximately 1960 volts on startup. Logically, if the motor is tested to
only operating voltage or below the operating voltage, the user can not be sure if
the spikes have caused damage to the motor's insulation that will interrupt service.
The other issue is that the turn-to-turn insulation has not been evaluated. In
addition, the Meg-Ohm and PI do not evaluate the ground wall insulation for
strength or the ability to withstand the high voltages it sees during daily operation.
The winding resistance test is only evaluating the motor circuit and not the
insulation.
The most effective way to ensure the motor will start and continue to provide
reliable service is to test it at the voltages the motor sees during normal operation-
which includes starting and stopping. This is accomplished with two tests: Step-
Voltage and Surge. These methods evaluate the ground wall and turn-to-turn
insulation respectively.
Step-Voltage Test
This DC Test is performed to a voltage that a motor typically sees during starting
and stopping. The test voltages, governed by IEEE, are reflected in Table II.
The DC voltage is applied to all three phases
of the winding and raised slowly to a preprogrammed voltage step level and held
for a predetermined time period. It is then raised to the next voltage step and held
for the appropriate time period. This process continues until the target test voltage
is reached. Typical steps for a 4160V motor are 1000-volt increments, holding at
minute intervals. For motors less than 4160V, the step voltages should be 500 volts(see Fig. 1).
8/13/2019 Importncia do SURGE-Test
4/11
8/13/2019 Importncia do SURGE-Test
5/11
During a Surge Test, the equipment will charge up a capacitor inside the unit and
dissipate it into one phase while holding the other two phases to ground. Then,
automatically, the test unit will slowly increase the voltage from 0 volts to the
target test voltage. This generates a waveform, in a shape based upon theinductance of the coil that is displayed on the test equipment screen. If the target
test voltage is attained without any frequency change in the waveform, the turn-to-
turn insulation integrity has been realized. Fig. 2 is a graphical representation of
the waveform at one-third, two-thirds and full voltage of one phase. This is what a
waveform will look like when the insulation is in a good condition.
8/13/2019 Importncia do SURGE-Test
6/11
If, at any time, the test equipment sees weak insulation between the turns, the
waveform will shift to the left as shown in Fig. 3. The white line on the graph shows
the failed waveform at about 1000 volts.
Surge testing theory
When the capacitor is discharged into the winding, it is performed at a very fast
rise time (.1 micro second). This produces a nonlinear voltage drop across the
turns, producing a potential difference between the turns in succession. As the rise
time slows, the operator will notice that the voltage potential difference between
the turns is dramatically reduced. This is in contrast to any other signal utilized to
diagnose motor issues. No DC test (or AC tests such as an inductance, capacitance,
impedance, phase angle or HiPot) will produce this potential difference between
the turns.
Physics provides us with Paschen's Law, which states that two bare wires placed
next to one another just a thickness of a hair away need a minimum of 325 volts to
jump the air gap between the two conductors. These two concepts are the core
reason why Surge testing is the natural choice for testing turn-to-turn insulation.The main reason is that if the test equipment doesn't produce a potential difference
between the turns above Paschen's Law, the current cannot flow through the fault.
If current can't flow through the fault, it will continue through all the coils and not
show a difference.
8/13/2019 Importncia do SURGE-Test
7/11
When Surge Testing a coil with weak insulation turn-to-turn, the voltage applied
can jump across the weak insulation. Removing these bypassed turns from the
circuit reduces the inductance of the circuit and causes the waveform frequency to
ring faster. This will produce the frequency shift to the left in the waveform.
Fortunately, advancements in technology have led to refinements in the analysis ofwaveforms, to the point that some test units automatically recognize failures (see
sidebar).
Surge comparison In the past the Surge Test has been called a "Surge Comparison
Test." Although some individuals believe the Surge Test still needs to be
performed in this manner, it really depends on what is being analyzed.
For finding weak insulation, surge comparison is not necessary. As previously
noted, weak insulation is diagnosed by a frequency shift to the left and is compared
to successive waveforms within one phase. If, however, the following list reflects
problems you're seeking to uncover and eliminate, a comparison of each phase is
recommended.
Shorts Opens Different size diameter copper between phases Unbalanced turn count between phases Reversed coils Shorted laminations
Here again, as referenced in the accompanying sidebar, instrumentation thatautomatically detects these problems is now available.
8/13/2019 Importncia do SURGE-Test
8/11
Older vs. newer equipment
Just like computers, high-voltage test equipment has changed vastly over the past
20 years.
Today's equipment incorporates modern, high-speed electronic evaluation of
changes to resistance, leakage current, leakage current versus time, voltage, step-voltage, dielectricabsorption, frequency response, wave shape, corona inception
voltage (C.I.V.) and more to detect faults at or under the levels of energy exposed
to the motor during operation. Microprocessor- controlled instantaneous trips
allow winding conditions to be evaluated without compromising dielectric
integrity. Moreover, the addition of field-developed PASS/FAIL test criteria now
makes this testing extremely repeatable.
One of the greatest advances in high-voltage testing has come from via solid-state,
highvoltage power supplies replacing the heavy step-up transformer. This has
resulted in big improvements to equipment portability. Every test is now digitized
and compared to the previously applied pulse. If any weakness is detected, the testis instantaneously stopped, preserving dielectric. The level of weakness is stored
for future reference, in the memory bank.
What to look for
When evaluating electrical PdM equipment, keep in mind that every manufacturer
is slightly different. Test units, though, should be able to perform the following
safety checks to ensure that your motors aren't damaged during testing:
1. Acceptable Meg-Ohm readings should be obtained.2. Acceptable PI Test should be performed.3. The test unit should evaluate the Meg-Ohm readings at the end of each step.
If the motor does not meet the criteria the test set should automatically stop
the test.
4. Current leakage should be monitored continuously and the unit shouldautomatically stop the test if an over current leakage condition exists.
Typical over current trip settings are 1, 10, 100 and 1000 micro amps of
current leakage.
5. Micro arc detection is crucial; if the test sees a tiny arc the unit shouldautomatically stop the test.
6. Real-time display on the screen is a must; this allows the operator to see thevoltage and current while the test is in operation. If the operator sees anyabnormal condition, he/she can stop the test.
Case study: Step-Voltage testing
Exelon Nuclear, Limerick Station
The Station Predictive Maintenance program at Limerick routinely performs
electrical testing of large motors at a two-year frequency. This testing consists of
winding resistance, insulation resistance, PI Capacitance/dissipation factor and DC
step-voltage testing to 20kV. The resulting data has been tracked and trended for
almost 20 years.
On a few occasions during 2002, Operations personnel reported that an "acrid"odor was present at the 1C Circulating Water Pump Motor. The PdM group had
8/13/2019 Importncia do SURGE-Test
9/11
been tracking this motor on a "watch" list that came about as a result of an
increasing trend in leakage current detected by DC step-voltage testing from 1997
to 2002 (see Fig. 4).
As part of its increased troubleshooting activities, the Limerick Station PdM team
monitored the motor through the summer of 2002, utilizing acoustic monitoring
and vibration and winding temperature/RTD monitoring on a monthly basis. In
September 2002, an action request was made to replace the motor in the winter,
based upon the electrical testing results, increasing vibration at stator slot
frequencies and higher acoustic/ultrasonic "noise."
Once the motor was removed, it showed high leakage current on the "A" phasemotor winding compared to the other two windings. After cleaning, a visual
inspection of the winding identified partial discharge at the junction where the
core slot winding tap transitions to the end winding/knuckle tape. Investigation
revealed a lack of "proper" corona suppression tape at this critical junction point
in the winding.
Among the lessons learned from this event was the fact that tracking and trending
leakage current versus applied voltage on a DC Step- Voltage Test, as presented by
the Baker AWA offline tester, can and does indicate potential problems in the
winding. Furthermore, when this data is combined with other predictive
technologies, it will allow for proactive replacement of a motor prior to an in-service failure.
8/13/2019 Importncia do SURGE-Test
10/11
Case study: Surge testing
Pulp & Paper OperationA 2300V form wound motor at a pulp and paper plant was found to have weak
turn-to-turn insulation. Of all the tests performed on this motor, the only one that
found the turn-to-turn weakness was the Surge Test. The controversy around
surge testing, though, is that after finding a problem with insulation, could the
tester have so degraded the motor that it would not run?
This Pulp & Paper industry case
study easily puts this myth to rest. The motor in question was immediately put
back in service after testing. It was started up and ran for the four months
required until it could be shut down and removed for repair. Again, as noted inFig. 5, the Surge Test was the only method to identify the insulation weakness. The
8/13/2019 Importncia do SURGE-Test
11/11
problem was well above line voltage, so other lowvoltage tests would not have
approached this threshold. (The surge summary in F ig. 5 highl ights the faul t
weaknesses found with the tester.)
This particular Pulp & Paper site motor takes about 6-7 hours to change. Thus, it
could have cost about $42,000 in downtime had the Surge Test not found theproblem. Interestingly, 80% of all electrical motor failures begin with weak
insulation turn-to-turn. The Surge Test is clearly the best method available to find
this problem. That's why it is so important to perform this type of non-destructive
testing on all motors.
Summary
The Step-Voltage and Surge Tests are necessary for an effective PdM program.
They identify problems that low-voltage tests can't find.
As the case studies in this article have shown, both of these tests are non-
destructive in that the tested units were returned to service until the next availabletime could be scheduled to replace them.
Finally, these tests are performed at voltage levels a motor is exposed to during
normal operation. If a motor cannot pass the Step-Voltage and Surge Tests, you
can bank on the fact that it is approaching the end of its service life. Consequently,
provisions should be made as soon as feasibly possible to have that motor removed
before unscheduled downtime occurs.
Joe Geiman holds a B.S. from Colorado State University in I ndustr ial Technology
Management. He travels extensively within the Western and Southeastern regions of
the Uni ted States and has tested and analyzed hundreds of motors for a var iety of
industr ies. Telephone: (800) 752-8272 or (970) 282-1200; e-mail :
mailto:[email protected]:[email protected]:[email protected]