Importância do SURGE-Test

Embed Size (px)

Citation preview

  • 8/13/2019 Importncia do SURGE-Test

    1/11

    Forget the controversy. These tests clearly are non-destructive in nature.

    Understanding the advantages these methods have over others can make them

    mighty powerful tools in your PdM program.

    Before any company investigates electrical predictive maintenance (PdM)

    instrumentation, it should know the strengths of its equipment's insulation, thevoltages its motors are exposed to daily, how a motor typically fails and where

    these faults typically exist. Only then can you really make a decision as to which

    electrical PdM equipment is the most appropriate for your operations.

    How a motor typically fails

    The motor stator has two main insulating systems that include the ground wall and

    turn-to-turn insulation. When this insulation is in a good condition it can

    withstand the normal day-to-day voltage spikes that exist during starting and

    stopping. Over time, this insulation will deteriorate as a result of mechanical

    movement of the windings, torque transients, heat, contamination, and other

    environmental contaminates. Once the dielectric strength of this insulation fallsbelow the incoming voltage spikes, another failure mechanism is introduced:

    ozone.

    Ozone is a very corrosive gas that will quickly deteriorate insulation. Although the

    motor will continue to run when this failure mechanism is introduced, as it sees

    continual voltage spikes, the deterioration rate will accelerate. Eventually, the

    dielectric strength of the insulation will fall below operating voltage or deteriorate

    to the point that copper wire will touch turn-to-turn. At this point a turn-to-turn

    or hard welded short has developed.

    According to "Transient Model for Induction Machines with Stator Winding Turn

    Faults" written for IEEE by Rangarajan M. Tallam, Tom G. Habetler and Ronald

    G. Harley, when a hard welded turn-to-turn short develops, the shorted windings

    will develop high circulating currents. These currents, which can be in the order of

    1620 times full-load amps, create excessive heat that the insulation cannot

    withstand. This intense amount of heat will burn quickly through the insulation-

    causing motor failure within minutes.

    A study performed at Oregon State University, by Dr. Ernesto Wiedenbrug,

    looked at a motor specially designed with a turn-to-turn fault by installing two

    wires connected to turn one and turn two of the same phase. These wires were thenbrought out to a switch. The motor was placed on a dynamometer and run at

    about 80% load. When the turn-to-turn short was engaged through the switch, the

    motor began visibly smoking within 45 seconds. While most motors will not run

    for long with a turn-to-turn short, some exceptions do exist. A motor with a high

    resistance or floating ground will run with a shorted phase, but once a second

    phase shorts, the motor will fail catastrophically.

    Recommended tests The tests listed on the next page are recommended in off-line

    field testing:

    Kelvin Method Winding Meg-Ohm

  • 8/13/2019 Importncia do SURGE-Test

    2/11

    Polarization Index (PI) Step-Voltage Surge

    Each of these test methods evaluates a different section of the motor. Brief

    descriptions of the first three tests are given in order to offer a complete array oftesting information. The nature of high-voltage testing and the necessity of the

    Step-Voltage and Surge methods, however, remain the main focus of this article.

    Kelvin Method Winding...

    The Kelvin Method Winding test measures the resistance of the copper wire of the

    motor circuit. If tested in a PdM application, the test is typically performed from

    the Motor Control Center (MCC). This test finds issues with miss connections,

    shorts, opens, unbalanced turn count in one phase to another and different size

    diameter copper in one phase to another. This test is very valuable and should be

    performed for predictive maintenance, troubleshooting and quality assurance.

    Meg-Ohm Test...

    The Meg-Ohm Test applies a DC potential (typically operating voltage) to the

    windings while holding the case to ground. Table I shows the recommended test

    voltages for different voltage class motors. Meg-Ohm testing is typically utilized to

    find grounded motors. It also is a very valuable PdM tool for finding wet and dirty

    motors. It's not typically used for quality assurance because of the low voltage level

    at which the test is performed.

    Polarization Index (PI ) Test...

    This test is much like the Meg-Ohm Test, but it is performed for 10 minutes. Over

    this time period, the molecules in the slot liner paper polarize. When the molecules

    polarize, the insulation resistance values should increase over the10- minute

    period. If the resistance increases during this time, it's an indication of good

    ground wall insulation with no moisture or contamination.

    Insulation testing

    Until now we have only discussed the low-voltage tests. Upon successfully

    completing these tests the following is known: the winding resistance is balanced.

    That means the motor has no shorts, opens or miss connections and the Meg-Ohmand PI indicate that the motor is both clean and dry. These tests, however, still

  • 8/13/2019 Importncia do SURGE-Test

    3/11

    have not confirmed that the motor is capable of starting or running for any length

    of time. The main reason for performing predictive maintenance on a motor is to

    learn if it will continue to provide uninterrupted service. Because low-voltage

    testing is not performed at the voltage a motor typically sees, it can't provide this

    information.

    Many articles have discussed the voltage spikes motors see during starting and

    stopping. As stated in "Turn Insulation Capability of Large AC Motors, Part I

    Surge Monitoring," by B.K. Gupta, B.A. Lloyd, G.C. Stone, and S.R Campbell

    (IEEE Transactions on Energy Conversion, Vol. EC-2, No. 4, December 1987),

    these voltage spikes can be in the order of 5 PU (Per Unit):

    Calculating this formula for a 480V three phase motor, the PU would be 391.9

    volts, or approximately 1960 volts on startup. Logically, if the motor is tested to

    only operating voltage or below the operating voltage, the user can not be sure if

    the spikes have caused damage to the motor's insulation that will interrupt service.

    The other issue is that the turn-to-turn insulation has not been evaluated. In

    addition, the Meg-Ohm and PI do not evaluate the ground wall insulation for

    strength or the ability to withstand the high voltages it sees during daily operation.

    The winding resistance test is only evaluating the motor circuit and not the

    insulation.

    The most effective way to ensure the motor will start and continue to provide

    reliable service is to test it at the voltages the motor sees during normal operation-

    which includes starting and stopping. This is accomplished with two tests: Step-

    Voltage and Surge. These methods evaluate the ground wall and turn-to-turn

    insulation respectively.

    Step-Voltage Test

    This DC Test is performed to a voltage that a motor typically sees during starting

    and stopping. The test voltages, governed by IEEE, are reflected in Table II.

    The DC voltage is applied to all three phases

    of the winding and raised slowly to a preprogrammed voltage step level and held

    for a predetermined time period. It is then raised to the next voltage step and held

    for the appropriate time period. This process continues until the target test voltage

    is reached. Typical steps for a 4160V motor are 1000-volt increments, holding at

    minute intervals. For motors less than 4160V, the step voltages should be 500 volts(see Fig. 1).

  • 8/13/2019 Importncia do SURGE-Test

    4/11

  • 8/13/2019 Importncia do SURGE-Test

    5/11

    During a Surge Test, the equipment will charge up a capacitor inside the unit and

    dissipate it into one phase while holding the other two phases to ground. Then,

    automatically, the test unit will slowly increase the voltage from 0 volts to the

    target test voltage. This generates a waveform, in a shape based upon theinductance of the coil that is displayed on the test equipment screen. If the target

    test voltage is attained without any frequency change in the waveform, the turn-to-

    turn insulation integrity has been realized. Fig. 2 is a graphical representation of

    the waveform at one-third, two-thirds and full voltage of one phase. This is what a

    waveform will look like when the insulation is in a good condition.

  • 8/13/2019 Importncia do SURGE-Test

    6/11

    If, at any time, the test equipment sees weak insulation between the turns, the

    waveform will shift to the left as shown in Fig. 3. The white line on the graph shows

    the failed waveform at about 1000 volts.

    Surge testing theory

    When the capacitor is discharged into the winding, it is performed at a very fast

    rise time (.1 micro second). This produces a nonlinear voltage drop across the

    turns, producing a potential difference between the turns in succession. As the rise

    time slows, the operator will notice that the voltage potential difference between

    the turns is dramatically reduced. This is in contrast to any other signal utilized to

    diagnose motor issues. No DC test (or AC tests such as an inductance, capacitance,

    impedance, phase angle or HiPot) will produce this potential difference between

    the turns.

    Physics provides us with Paschen's Law, which states that two bare wires placed

    next to one another just a thickness of a hair away need a minimum of 325 volts to

    jump the air gap between the two conductors. These two concepts are the core

    reason why Surge testing is the natural choice for testing turn-to-turn insulation.The main reason is that if the test equipment doesn't produce a potential difference

    between the turns above Paschen's Law, the current cannot flow through the fault.

    If current can't flow through the fault, it will continue through all the coils and not

    show a difference.

  • 8/13/2019 Importncia do SURGE-Test

    7/11

    When Surge Testing a coil with weak insulation turn-to-turn, the voltage applied

    can jump across the weak insulation. Removing these bypassed turns from the

    circuit reduces the inductance of the circuit and causes the waveform frequency to

    ring faster. This will produce the frequency shift to the left in the waveform.

    Fortunately, advancements in technology have led to refinements in the analysis ofwaveforms, to the point that some test units automatically recognize failures (see

    sidebar).

    Surge comparison In the past the Surge Test has been called a "Surge Comparison

    Test." Although some individuals believe the Surge Test still needs to be

    performed in this manner, it really depends on what is being analyzed.

    For finding weak insulation, surge comparison is not necessary. As previously

    noted, weak insulation is diagnosed by a frequency shift to the left and is compared

    to successive waveforms within one phase. If, however, the following list reflects

    problems you're seeking to uncover and eliminate, a comparison of each phase is

    recommended.

    Shorts Opens Different size diameter copper between phases Unbalanced turn count between phases Reversed coils Shorted laminations

    Here again, as referenced in the accompanying sidebar, instrumentation thatautomatically detects these problems is now available.

  • 8/13/2019 Importncia do SURGE-Test

    8/11

    Older vs. newer equipment

    Just like computers, high-voltage test equipment has changed vastly over the past

    20 years.

    Today's equipment incorporates modern, high-speed electronic evaluation of

    changes to resistance, leakage current, leakage current versus time, voltage, step-voltage, dielectricabsorption, frequency response, wave shape, corona inception

    voltage (C.I.V.) and more to detect faults at or under the levels of energy exposed

    to the motor during operation. Microprocessor- controlled instantaneous trips

    allow winding conditions to be evaluated without compromising dielectric

    integrity. Moreover, the addition of field-developed PASS/FAIL test criteria now

    makes this testing extremely repeatable.

    One of the greatest advances in high-voltage testing has come from via solid-state,

    highvoltage power supplies replacing the heavy step-up transformer. This has

    resulted in big improvements to equipment portability. Every test is now digitized

    and compared to the previously applied pulse. If any weakness is detected, the testis instantaneously stopped, preserving dielectric. The level of weakness is stored

    for future reference, in the memory bank.

    What to look for

    When evaluating electrical PdM equipment, keep in mind that every manufacturer

    is slightly different. Test units, though, should be able to perform the following

    safety checks to ensure that your motors aren't damaged during testing:

    1. Acceptable Meg-Ohm readings should be obtained.2. Acceptable PI Test should be performed.3. The test unit should evaluate the Meg-Ohm readings at the end of each step.

    If the motor does not meet the criteria the test set should automatically stop

    the test.

    4. Current leakage should be monitored continuously and the unit shouldautomatically stop the test if an over current leakage condition exists.

    Typical over current trip settings are 1, 10, 100 and 1000 micro amps of

    current leakage.

    5. Micro arc detection is crucial; if the test sees a tiny arc the unit shouldautomatically stop the test.

    6. Real-time display on the screen is a must; this allows the operator to see thevoltage and current while the test is in operation. If the operator sees anyabnormal condition, he/she can stop the test.

    Case study: Step-Voltage testing

    Exelon Nuclear, Limerick Station

    The Station Predictive Maintenance program at Limerick routinely performs

    electrical testing of large motors at a two-year frequency. This testing consists of

    winding resistance, insulation resistance, PI Capacitance/dissipation factor and DC

    step-voltage testing to 20kV. The resulting data has been tracked and trended for

    almost 20 years.

    On a few occasions during 2002, Operations personnel reported that an "acrid"odor was present at the 1C Circulating Water Pump Motor. The PdM group had

  • 8/13/2019 Importncia do SURGE-Test

    9/11

    been tracking this motor on a "watch" list that came about as a result of an

    increasing trend in leakage current detected by DC step-voltage testing from 1997

    to 2002 (see Fig. 4).

    As part of its increased troubleshooting activities, the Limerick Station PdM team

    monitored the motor through the summer of 2002, utilizing acoustic monitoring

    and vibration and winding temperature/RTD monitoring on a monthly basis. In

    September 2002, an action request was made to replace the motor in the winter,

    based upon the electrical testing results, increasing vibration at stator slot

    frequencies and higher acoustic/ultrasonic "noise."

    Once the motor was removed, it showed high leakage current on the "A" phasemotor winding compared to the other two windings. After cleaning, a visual

    inspection of the winding identified partial discharge at the junction where the

    core slot winding tap transitions to the end winding/knuckle tape. Investigation

    revealed a lack of "proper" corona suppression tape at this critical junction point

    in the winding.

    Among the lessons learned from this event was the fact that tracking and trending

    leakage current versus applied voltage on a DC Step- Voltage Test, as presented by

    the Baker AWA offline tester, can and does indicate potential problems in the

    winding. Furthermore, when this data is combined with other predictive

    technologies, it will allow for proactive replacement of a motor prior to an in-service failure.

  • 8/13/2019 Importncia do SURGE-Test

    10/11

    Case study: Surge testing

    Pulp & Paper OperationA 2300V form wound motor at a pulp and paper plant was found to have weak

    turn-to-turn insulation. Of all the tests performed on this motor, the only one that

    found the turn-to-turn weakness was the Surge Test. The controversy around

    surge testing, though, is that after finding a problem with insulation, could the

    tester have so degraded the motor that it would not run?

    This Pulp & Paper industry case

    study easily puts this myth to rest. The motor in question was immediately put

    back in service after testing. It was started up and ran for the four months

    required until it could be shut down and removed for repair. Again, as noted inFig. 5, the Surge Test was the only method to identify the insulation weakness. The

  • 8/13/2019 Importncia do SURGE-Test

    11/11

    problem was well above line voltage, so other lowvoltage tests would not have

    approached this threshold. (The surge summary in F ig. 5 highl ights the faul t

    weaknesses found with the tester.)

    This particular Pulp & Paper site motor takes about 6-7 hours to change. Thus, it

    could have cost about $42,000 in downtime had the Surge Test not found theproblem. Interestingly, 80% of all electrical motor failures begin with weak

    insulation turn-to-turn. The Surge Test is clearly the best method available to find

    this problem. That's why it is so important to perform this type of non-destructive

    testing on all motors.

    Summary

    The Step-Voltage and Surge Tests are necessary for an effective PdM program.

    They identify problems that low-voltage tests can't find.

    As the case studies in this article have shown, both of these tests are non-

    destructive in that the tested units were returned to service until the next availabletime could be scheduled to replace them.

    Finally, these tests are performed at voltage levels a motor is exposed to during

    normal operation. If a motor cannot pass the Step-Voltage and Surge Tests, you

    can bank on the fact that it is approaching the end of its service life. Consequently,

    provisions should be made as soon as feasibly possible to have that motor removed

    before unscheduled downtime occurs.

    Joe Geiman holds a B.S. from Colorado State University in I ndustr ial Technology

    Management. He travels extensively within the Western and Southeastern regions of

    the Uni ted States and has tested and analyzed hundreds of motors for a var iety of

    industr ies. Telephone: (800) 752-8272 or (970) 282-1200; e-mail :

    [email protected]

    mailto:[email protected]:[email protected]:[email protected]