International Case Study

A pilot project in Lebanon

Page 3: International Case Study A pilot project in Lebanon

SELE

CTION

INTEROPER

ABILITY

DEPLOYMENTPLANNING

START-UP

MAINTENANCE

Page 4: International Case Study A pilot project in Lebanon

Three different places:• Urban areas• Semi-Urban areas• Rural areas

Page 5: International Case Study A pilot project in Lebanon

We need to know the network topology

Page 6: International Case Study A pilot project in Lebanon

ASPECTS TO CONSIDER

• Distances• Number of clients• Power topology (number of

transformers)• Type of lines (air, underground)• …………

Page 7: International Case Study A pilot project in Lebanon

SELE

CTION

INTEROPER

ABILITY

DEPLOYMENTPLANNING

START-UP

MAINTENANCE

Page 8: International Case Study A pilot project in Lebanon

THE IMPORTANCE OF TESTING

CERTIFICATION

DEPLOYMENT

APPROVAL IN LABORATORY

APPROVAL IN FIELD

Page 9: International Case Study A pilot project in Lebanon

CERTIFICATION• BASIC (Metrological,.......etc.)• DLMS APPROVAL: METER PROTOCOL• PRIME APPROVAL: MODEM plc (SERVICE NODE)

NECESSARY…. BUT NOT ENOUGH

PENDING: Integration, functional test...…

Page 10: International Case Study A pilot project in Lebanon

APPROVAL IN LABORATORY

• Interoperability Test• Functionality• Performance• Stability• …

NEW DEVELOPMENTS NEW TEST

MAINTENANCE

Page 11: International Case Study A pilot project in Lebanon

APPROVAL IN FIELD

• SELECT 1-2 secondary substations for test• Represent the different scenarios• With the same version of PRIME SW• Detailed analysis• Monitoring the test

Page 12: International Case Study A pilot project in Lebanon

DEPLOYMENT

• As a last step• After the test

WITH GUARANTEES

Page 13: International Case Study A pilot project in Lebanon

SpecsProof of concept

Prototyping

Lab testingField deployment

Page 14: International Case Study A pilot project in Lebanon

SELE

CTION

INTEROPER

ABILITY

DEPLOYMENTPLANNING

START-UP

MAINTENANCE

Page 15: International Case Study A pilot project in Lebanon

GPRSGPRS

SELECT THE TECHNOLOGY SOLUTIONS

Page 16: International Case Study A pilot project in Lebanon

Remote reading(scheduled)

PLC MT, GPRS, ADSL,

etc.

LAN

DLMS overPLC PRIME

MDM

FRONT-END

Concentrators DC

Smart meters

Interface DC-METERS

Interface FE-DC

Interface MDM-FRONT-END

4

3

2

1

time

end

time

Operations

6

3

1

5

4

2

end

SMART METERING ARCHITECTURE

Page 17: International Case Study A pilot project in Lebanon

Start

DC Communi.

Test

Meter Comm.

Test

DC Config.

Test

Meter Config.

Test

DC Functio. & Operation

Test

Meter Functio. & Operation

Test

END

TESTING PROCESS

Page 18: International Case Study A pilot project in Lebanon

SELE

CTION

INTEROPER

ABILITY

DEPLOYMENTPLANNING

START-UP

MAINTENANCE

Page 19: International Case Study A pilot project in Lebanon

INSTALL + VALIDATEThe importance of validation

Page 20: International Case Study A pilot project in Lebanon

CONSIDER

• We need to be clear the deployment plan, and steps to certify an installation I coordinate the installation of data

concentrators and meters? or are they two completely independent activities?

How can I validate an installation? What tools do I need?

• Thinking on how to adapt our IT systems to the new way of working

Page 21: International Case Study A pilot project in Lebanon

INSTALL IN THE SECONDARY SUBSTATION

• Cabinet installation• Installation of current transformers• Power Supply• Checking operation equipment

DC Communications

Page 22: International Case Study A pilot project in Lebanon

INSTALL IN THE CENTRALIZATION

• Installing Meters• Power supply• Check functioning and registration

LED PRIME!!!!

Page 23: International Case Study A pilot project in Lebanon

• LED PRIME– PLM: Activity PRIME– PLM: Try to register– PLM: Registered

• 1000 Imp /KWh – Imp/KVArh flashing: load

• PHONE: 432 connection

INSTALL IN THE CENTRALIZATION (II)

Page 24: International Case Study A pilot project in Lebanon

INSTALL IN THE CENTRALIZATION (III)

Sequence LED PRIME

1. FLASHING FAST

2. TURNS OFF

3. FLASHING 30 seconds

4. GOES TO Try to register

5. GOES TO Registered

Page 25: International Case Study A pilot project in Lebanon

VALIDATION OF THE INSTALLATION

* Use the DC to validate

Monitoring the network PRIME1. Availability2. Availability launching measurement cycles

<cycles><cycle name="TEST_ciclos" period="1" immediate="true"

stop="2010/10/28 01:00">

<get obis="1-0:1.8.10.255" class="3" element="2"/><get obis="0-0:21.0.6.255" class="7" element="2"/>

</cycle></cycles>

Page 26: International Case Study A pilot project in Lebanon

VALIDATION OF THE INSTALLATION (II)

Page 27: International Case Study A pilot project in Lebanon

SELE

CTION

INTEROPER

ABILITY

DEPLOYMENTPLANNING

START-UP

ROLL-OUT

Page 28: International Case Study A pilot project in Lebanon

Poor conditions of some metering rooms

Page 29: International Case Study A pilot project in Lebanon

DIAGNOSIS OF THE NETWORK

meter as a switch40:40:22:10:1e:88

meter as a switchc0:ac:54:f4:73:89

meter as terminal00:80:e1:13:08:94

Page 30: International Case Study A pilot project in Lebanon

DIAGNOSIS

A network diagnostic for:

Topology MAC traffic Noise spectrum …………

Page 31: International Case Study A pilot project in Lebanon

TopologyMAC Traffic

Noise Spectrum

Page 32: International Case Study A pilot project in Lebanon

SOME EXAMPLES

SELECTIVE NOISE IN FREQUENCY IMPULSE NOISE

Page 33: International Case Study A pilot project in Lebanon

THANK YOU VERY MUCH