Isaac project portfolio Page 1
Project Description: VW Water pump - Assembly Plant
Objective Relocate the VW assembly plant from Gud Holdings Pty Ltd (Cape Town plant to Durban plant), the equipment include sealant dispensing Fanuc robot, curing oven, assembly tables, cnc machines and racking for component storage. Making sure that the machines and equipments are safe, health and safety of employees/contractors is maintained throughout the relocation process. Ensure the project to be uneventful and completed on schedule and on budget. Costing: (CapEx + budget)
Isaac project portfolio Page 2
Process flow
Crating
Isaac project portfolio Page 3
Rigging and Transportation
VW Assembly plant installed at Durban site and handed over to production.