JSC «Energy solutions»
Project reference
2
JSC «Energy solutions» provide costumers with a list of service:
• all kinds of design and engineering work;
• turnkey construction of power plants and energy facilities (ЕРС);
• project management of power plants and energy facilities construction (ЕРСМ);
• start-up and commissioning works carried out by department within the company.
Development of design and working
documentation , construction
supervision
Supply of Russian and foreign
manufacturers
Construction and
installation work
Start-up and commissioning
works
Feasibility study and investment
feasibility study
EPC/EPCM
JSC «Energy solutions» - EPC|EPCM contractor
2
23
History of the company
JSC «Energy Solutions» was founded in 2011 as a construction management
enterprise with specialization on conduct comprehensive pre-commissioning. The first
successful projects of the company are:
• Reconstruction of turbine house KTC TPP - 3 BF of the «Group Ilim» , Bratsk;
• Implementation of commissioning works in the construction of 150 MW Exhaust
CHP NLMK in Lipetsk;
• Organization of procurement and supply of main and auxiliary equipment at the
construction of CCGT - CHP " GSR Energo" of 110 MW in Kolpino.
High-quality , timely and cost-effective project execution enabled the company to
successfully establish itself in the energy market and to expand the staff by 2012 ,
including in the engineering units , expanding their competence carry out the functions
of the management company for the development of design and working documents .
Company activity spread to the implementation of projects for industrial plants and
utilities.
JSC «Energy solutions» - EPC|EPCM contractor
2
Advantages of JSC «Energy solutions»
The presence of highly qualified personnel with experience in implementing major projects;
Minimal terms of design by:
– use complex PDMS AVEVA,
– the availability of an extensive database of equipment 3d- models.
Mandatory supervision on the construction site;
Rapid response to changes in the project through the use of cloud technologies;
Partnerships with a number of Russian main and auxiliary equipment manufacturers;
The presence of internal standards of the company:
– project management control,
– quality control of equipment and construction materials.
Using the modern software for monitoring projects in real time.
The quality management system for compliance with the quality standard ISO 9001 : 2008 .
24
2
Object: TPP - 3 BF of «Ilim Group», Bratsk
Customer: JSC «Ilim Group»
Contract: reconstruction of the turbine house KTC TPP - 3:
implementation of the management functions of the company to
develop the project and working documentation, supply of main
equipment (incl. supervision of erection and commissioning
supervision)
Terms: April 2011 - October 2013
Main equipment:
• Back pressure turbine with pressure steam 90 bar , the
turbine of the type P - 32 and P - 27 , JSC "KTZ" - 2 pcs .
• Steam turbine generator of the type TTC - 32 , LLC
"Electrotyazhmash - Privod " - 2 pcs.
Projects of JSC «Energy solutions»
25
RECONSTRUCTION OF THE TURBINE HOUSE KTC TPP - 3
2
Object: TPP-1 . Arhangelsk region
Customer: JSC «Arkhangelsk PPM»
Contract: range of works on the development of design and
working documentation under the project of technical re-
equipment with the replacement of turbine unit №5 TPP-1
Terms: October 2011 - June 2012
Main equipment:
• Steam turbine PT- 25 / 30-8,8 / 1,0-1 , produced by JSC
"KTZ", Kaluga, - 1 pc.
26
Projects of JSC «Energy solutions»
2
NOVOGORKOVSKAYA CHP , CCGT - 350MV
Customer:
JSC «TGC-6»
EPC contractor:
JSC «PDC «SOYUZ»
Project management:
JSC «Energy solutions»
The contract was signed:
July 20 , 2012
Project completed:
2015
Main equipment:
• HRSG E- 293/84.02-14/1.5-560/294
production of " Podolsky
Machine-Building Plant " - 2 pcs.
• Block three-phase transformer
TDC- 225000/220 and TDC- 225000/110
with a capacity of 225 MVA - 2 pcs.
• The gas turbine GT13E2 production
Alstom ( France) nominal rating power of
185 MW - 2 units.
• Gas turbine generator TOPAIR
50WY21Z- 095 production Alstom
nominal rating power of 225 MW - 2 units.
27
Projects of JSC «Energy solutions»
2
• Steam turbine type T- 25 / 33-7,6 / 0,12
produced by JSC «Kaluga Turbine Plant»
35 MW - 1 pc.
• HRSG type PC- 64 (E -116 / 162-8,16 /
0,7-535 / 218) produced by JSC " ZIO "
(Podolsk ) - 1 pc.
• Gas turbine type PG6111FA
production of «General Electric»
electrical capacity of 75 MW - 1 pc.
• Gas turbine generator type ELIN 6FA
production of «General Electric» - 1pc.
28
Projects of JSC «Energy solutions»
Customer:
CJSC «GSR Energo»
EPC contractor:
JSC «PDC «SOYUZ»
Project management:
JSC «Energy solutions»
The contract was signed:
November 18, 2010
Project completed:
July 25, 2014
CCGT CHP «GSR ENERGO» PSU - 110MW is completed
Main equipment:
2
EXHAUST CHP NLMK, 150МW is completed
• Steam boiler E - 220-9,8-54OGD with a
single steam capacity 220t / h Production
JSC " Sibenergomash" - 3 pcs.
• The steam turbine PT -40 / 50-8,8 / 1.3
50 MW production JSC «Kaluga Turbine
Plant» - 3 pcs.
• Generator TTK - 50-2UZ -P production
LLC "Electrotyazhmash - Privod " - 3 pcs.
29
Projects of JSC «Energy solutions»
Customer:
JSC «NLMK»
EPC contractor:
JSC «PDC «SOYUZ»
Commissioning works:
JSC «Energy solutions»
The contract was signed:
December 2011
Project completed:
June 2012
Main equipment:
2
CHP - 4, ULAANBAATAR, MONGOLIA is completed
• Steam turbine generator TVF- 125-2U3
nominal rating power of 125 MW
production NPO "ELSIB" - 1 pc.
• Steam turbine T- 120/130 -130-8 MO
nominal rating power of 120 MW production
JSC " Ural Turbine Plant " - 1pc.
210
Projects of JSC «Energy solutions»
Customer:
CJSC «Ural Turbine Plant»
EPC contractor:
JSC «PDC «SOYUZ»
Project management:
JSC «Energy solutions»
The contract was signed:
August 2013
Project completed:
March 2015
Main equipment:
2
CONSTRUCTION of TWO BOILERS in the REPUBLIC OF TYVA,
50 Gcal/h EACH
RECONSTRUCTION of HEAT SUPPLY SYSTEM
of Ak-Dovurak and Shagonar (project works)
• The coal boiler KV - TC - 10-150P
manufactured by JSC " TEP - Holding"
- 2 pcs .
• The coal boiler KV - TC- 20-150P
manufactured by CJSC " TEP - Holding"
- 4 pcs .
211
Projects of JSC «Energy solutions»
Customer:
Ministry of Energy,
Tyva Republic
EPC contractor:
JSC «Energy solutions»
The contract was signed:
December 2014
The project is
under implementation
Project completed:
April 2017
Main equipment:
2
REPLACING the 60 MW TURBINE TG # 5
on CHP - PVA
212
Object: CHP – PVA
Customer: JSC «NLMK»
Contract: development of technical
specifications for the design , supply of turbine
generator , auxiliary equipment and process
control , supervision services
Terms: July 2015 - October 2017
The project is under implementation
Main equipment:
Steam turbine 60 MW – PT 60-8,9/1,9
manufactured by JSC " UTZ "
Generator - TF-60-2U3 manufactured by NPO
"ELSIB"
Projects of JSC «Energy solutions»
2
Projects of JSC «Energy solutions»
CONSTRUCTION of COAL CHP 16 MW,
heat supply 77 MW
213
Object: CHP field Gross, Yakutia
Customer: LLC «Neryungri Metallic» (Severstal)
Contract:
1.Development of working documentation of CHP,
2.General Contracting services for construction of
CHP (EPCM)
Terms: January 2015 – February 2018
The project is under implementation
Main equipment:
Boilers 5-25T/h produced by JSC "TEP-HOLDING“
Steam turbine 2x8 MW produced by JSC "KTZ"
Generator – 2x8 MW produced by RusElprom
2
Projects of JSC «Energy solutions»
CONSTRUCTION of TPP, 7 MW
214
Object: PPM Volga
Customer: OJSC «Volga»
Contract:
Construction of TPP, 7 MW to cover its own energy
needs of OJSC «Volga» in the city of Balakhna,
Russian Federation
Terms: July 2016 – August 2017
The project is under implementation
Main equipment:
Back pressure turbine, SST-110 (Siemens)
2
Licenses and Certificates of JSC «Energy solutions»
JSC "Energy Solutions " has the following licenses and certificates :
• Certificate of SRO dated 20.11.2015 №С-089-08-02695 of admission to work ( according to the list
specified in the SRO), running on particularly dangerous and technically complex capital construction,
up to 3 billion rubles
• Certificate of SRO dated 19.11.2015 №0128-03-15 of admission to work on the design,
up to 300 million rubles
• The certificate of registration of electrical laboratory dated 03.10.2014. №4187-2
• License of the Ministry of emergency situations dated 31.08.2015, №77-Б/02635 for realization of
activity on installation, maintenance and repair of means of maintenance of fire safety of buildings and
structures.
• The certificate of authority of LLC TekhnoPlast Service dated 18.03.2016 №02-16 in the field of
promotion, sales and application of protective and restoration photopolymer materials, «MATERIUM»
• The certificate of authority of LLC MATERIUM-RUS dated 18.03.2016 №18/03/16-02 in the field of
promotion, sales and application of protective and restoration photopolymer materials, «MATERIUM»
215
1915
Contacts
JSC «Energy solutions»