PROJECT RENOVASI SOUND SYSTEM (RSS)
KOMISI MUSIK + MULTI MEDIA + SARPRAS
Disampaikan dalam rapat PMJ Minggu 9 April 2017
AGENDA
1. TUJUAN KEGIATAN
2. LATAR BELAKANG
3. KAJIAN DAN PELAKSANAAN KEGIATAN
4. TOTAL DANA
5. TOTAL KEBUTUHAN
6. TIMELINE
KOMISI MUSIK
• MOTO
• ONE SPIRIT
• ONE VISION
• ONE MISSION
MOTO WE ARE ONE
ONE SPIRITONE VISIONONE MISSION
VISI DAN MISI KOMISI MUSIK(PIC)
• MOTO
• ONE SPIRIT
• ONE VISION
• ONE MISSION
2016
CONTENTC
INFRASTRUCTURE
I
• PERBAIKAN YG DPT DILAKUKAN UNTUK CONTENT SECARA BERKALA DIADAKAN PELATIHAN UNTUK SELURUH PP DAN PMSK
PEOPLEP
• PEMBINAAN PEMUSIK PIANIST REGENERASI TOTAL 2016 = 6 ORANG• PEMBINAAN PEMANDU
TOTAL = 6• GITARIS UNTUK TAHUN 2016
BELUM DILAKSANAKAN
• PERBAIKAN UNTUK SOUND SYSTEM: RENCANA 2016 PENGECEKAN SELURUH SOUND SYSTEM, TAHUN 2017 PEREMAJAAN, 2018 PENINGKATAN KUALITAS SOUND SYSTEM
• PERBAIKAN UNTUK ALAT2 SPT MC, MUSIC STAND, TEMPAT PENYIMPANAN ANGKLUNG, ALAT MUSIK LAINNYA • PEMBELIAN DIGITAL PIANO YAMAHA TYPE P-45-B YBVZ 02527• RENCANA PEMBELIAN ALAT2 MUSIK LAINNYA DAN PERBAIKAN SARANA MUSIK DI GKI KP
2017 2018
• PEMBINAAN PEMUSIK PIANIST REGENERASI TOTAL 2016 = 6 ORANG• PEMBINAAN PEMANDU
TOTAL = 6• GITARIS UNTUK TAHUN 2016
BELUM DILAKSANAKAN
• PEMBINAAN PEMUSIK PIANIST REGENERASI TOTAL 2016 = 6 ORANG• PEMBINAAN PEMANDU
TOTAL = 6• GITARIS UNTUK TAHUN 2016
BELUM DILAKSANAKAN• TRANSFORMASI / INOVASI
• SOFTCOPY LAGU2 PARTITUR• SOFTCOPY LAGU2 MUSIK DAN
CHORD
• MULAI MEMBANGUN SOFTCOPY LAGU2 DENGAN NOT ANGKA DI GKI KP
• MAZMUR DENGAN NOT ANGKA
• PENDALAMAN MATERI DENGAN CHORD YANG DIBUAT SENDIRI
• CHORD KEYBOARD DAN PIANO• CREATIVE ARRANGEMENT
AGENDA
1. TUJUAN KEGIATAN
Dalam rangka meningkatkan mutu kualitas pengembangan
‘Sound System’ di GKI Kemang Pratama terutama didalammelaksanakan kegiatan Kebaktian Ibadah Umum.
Sejak Gereja GKI Kemang Pratama berdiri sampai saat ini belum pernahdilaksanakan Peremajaan Sound System di GKI Kemang Pratama.
AGENDA
2. LATAR BELAKANG
Mixer Utama yang ada pada saat ini Merek Yamaha dengan
12 Channels. (keadaan sudah lama).
Dari hasil Kajian Komisi Musik kami mendata di Lantai I ada 2
Mixer Analog selain Mixer Utama ada Mixer MELAND MP 803
dengan 8 Channels. Di Lantai II juga terdapat Mixer MELAND
HR 1625 dengan 16 Channels dan Mixer MP 6020 HR dengan 6
Channels.
AGENDA
3. KAJIAN DAN PELAKSANAAN KEGIATAN
3.1 KAJIAN 1 DARI TEAM MUSIK BEKTIM (PAK ERIC TIMISELA)
3.2 KAJIAN 2 DARI TEAM MUSIK GKI KAPUT (PAK YOSEF)
AGENDA
3. KAJIAN DAN PELAKSANAAN KEGIATAN
3.3 TEAM PENGADAAN (PROSES PROCUREMENT)
A. Kegiatan ‘Renovasi Sound System Project’ ini akan diadakan pada :
Waktu : Senin 10 April 2017 sd Senin 28 Mei 2017
Tempat : Lt.1 Ruang Ibadah GKI Kemang Pratama
B. Susunan Team :
Koordinator Kegiatan : Ronny, Ellen, Yopie Chandra, Sutikno
Team Member : Abel, Milda, Ria, Mulat, Rico, Ardian Elkana
Tenaga Ahli : Yosef 0811-149-423 (GKI Kayu Putih)
AGENDA
4. TOTAL DANA
Total Dana IDR 92,5 Juta
1. Budget Komisi Musik / Sarpras
2017 RKAP MJ GKI KP KM IDR 50 Juta
2. Budget Multi Media
2017 RKAP MK GKI KP MM IDR 10 Juta
3. Sumbangan Donatur
(Data Terlampir) IDR 30,5 Juta
4. Kaos Koperasi + Komisi Musik
100 buah Kaos IDR 2 Juta
AGENDA
5. TOTAL PENGELUARAN
A. OPSI 1 – IDR 81,500,000Mixer Analog Yamaha Health QU 32 IDR 20,000,000
Guitar Bass IDR 10,000,000Guitar Semi Electric IDR 10,000,000Cables IDR 10,000,000Speaker Active utk monitor pemain music IDR 7,500,000Speaker Passive IDR 5,000,000Power Speaker IDR 3,000,000Kabel Speaker IDR 3,000,000
Assesoris Mixer dan Speaker IDR 3,000,000Kabel untuk Microphone atau Jack Instrument Microphone IDR 1,000,000Direct Box Passive / Active IDR 1,000,0002 MC Condensor IDR 2,000,0004 MC Pemandu IDR 2,000,0004 Stand Pemandu IDR 2,000,000Perbaikan Conga IDR 2,000,000
TOTAL IDR 81,500,000
AGENDA
5. TOTAL PENGELUARAN
B. OPSI 2 – IDR 87,562,500
AGENDA
5. TOTAL PENGELUARAN
C. OPSI 3 – IDR 68,363,500No Nama Barang Type Quantity Harga Satuan Jumlah Harga
(IDR) (IDR)
1 Mixer "YAMAHA" 20 Ch (12 Mic + 4 Stereo) MG-20XU 1 unit IDR 5,656,000 IDR 5,656,000
2 Speaker 15"HUPER" 15HA400 2 unit IDR 5,000,000 IDR 10,000,000
3 Monitor Speaker 12 "MACKIE" Thump12 2 unit IDR 3,700,000 IDR 7,400,000
4 Equalizer "DBX" 231 2 unit IDR 2,800,000 IDR 5,600,000
5 Bracket Speaker 1 1 set IDR 475,000 IDR 475,000
6 Direct Box "BEHRINGER" DI-Box 4 unit IDR 700,000 IDR 2,800,000
7 Dynamic Mic Mimbar "SHURE" (Non Ori) MX-412N 2 unit IDR 225,000 IDR 450,000
8 Dynamic Mic "SHURE" Vocal (Ori) SM-58 2 unit IDR 1,250,000 IDR 2,500,000
9 Dynamic Mic "SHURE" Music (Ori) SM-57 2 unit IDR 1,175,000 IDR 2,350,000
10 Wireless Tuner + HandHeld 2 Ch "SHURE" (Non Ori) 1 set IDR 2,450,000 IDR 2,450,000
11 Floor Stand 3 unit IDR 365,000 IDR 1,095,000
12 Snake Cable 24 Ch (Non Ori) 15 meter IDR 132,500 IDR 1,987,500
13 Cable Mic "CANARE" L2TS2 1 Roll IDR 1,500,000 IDR 1,500,000
14 Junction Panel 24 Ch + Canon 1 unit IDR 1,700,000 IDR 1,700,000
15 Cable NYM 3 x 1,5 mm 50 meter 1 Roll IDR 900,000 IDR 900,000
16 Canon Male + Female "LINGE" 20 set IDR 875,000 IDR 17,500,000
17 Amply kecil utk Bass dan Akustik IDR 3,000,000 IDR 3,000,000
18 Perbaikan Cojun (Kohun) IDR 1,000,000 IDR 1,000,000
Total IDR 68,363,500
Infrastructure
10 Channel
Altar
Ampli
Roland
Ampli
Gitar
PIA
NO
Keyb
oa
rd
Mic 1
Mic 2
Mic 3
Mic 4
Ampli
Gitar
Listrik
Ampli
Gitar
Akustik
Mic 5
Mic 7
Mic 6
Mic 8
DR
UM
D I
BOX
D I
BOXBass
MIXER
Speaker Speaker
OLD
NEW
6. TIMELINERENOVASI SOUND SYSTEM
3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
p u a s a
I. BIDDING KETOKO MUSIK / DISTRIBUTOR
1.1. PENULISAN SURAT - Specifikasi berdasarkan proposal
- jenis2 alat2 sound system dan harga
- membandingkan harga toko2
- menentukan toko mana yang akan ditunjuk
- surat keputusan MJ/Panitia utk toko/distributor
1.2. PROSES PENGERJAAN
- pembongkaran
- instalasi
- pemasangan sound system baru
1.3. MONITORING
- evaluasi 1 bulan pertama
- evaluasi 2 bulan pertama
- evaluasi 3 bulan pertama
AUG SEP DECOCTREMARKS
MAYACTIVITIES
NOVNO. PROGRAM
APR JUNE JULY
TERIMA KASIH
LAMPIRAN