7
4/6/2016 1 Kuwait Energy Security Vision 2030 Shagaya Initiative Project Kuwait Institute for Scientific Research 2 لعالميت واة في الكواريقة الشمسية الحر بالطاحطة تعمل أول م1979 - 1986 First Solar Thermal Power Plant in Kuwait 1979-1986 صليبية محطة ال100 كيلو واتSulaibiah Plant 100 KWh كانت البداية...... It was the start

Kuwait Energy Security Vision 2030 - MENARECInitiative+progress.pdf4/6/2016 1 Kuwait Energy Security Vision 2030 Shagaya Initiative Project Kuwait Institute for Scientific Research

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Kuwait Energy Security Vision 2030 - MENARECInitiative+progress.pdf4/6/2016 1 Kuwait Energy Security Vision 2030 Shagaya Initiative Project Kuwait Institute for Scientific Research

4/6/2016

1

Kuwait Energy Security

Vision 2030

Shagaya Initiative Project

Kuwait Institute for Scientific Research

2

1986-1979أول محطة تعمل بالطاقة الشمسية الحرارية في الكويت والعالم

First Solar Thermal Power Plant in Kuwait 1979-1986

كيلو وات 100محطة الصليبية

Sulaibiah Plant 100 KWh

It was the start...... البداية كانت

Page 2: Kuwait Energy Security Vision 2030 - MENARECInitiative+progress.pdf4/6/2016 1 Kuwait Energy Security Vision 2030 Shagaya Initiative Project Kuwait Institute for Scientific Research

4/6/2016

2

3

Shagaya Initiative: 2010-2030

Kuwait’s Gateway to Future Energy Security

4

It was a Vision...... كانت رؤية

تقديم رؤية الشقايا2009فبراير

لحضرة صاحب السمو الشيخ صباح األحمد الجابر

أمير البالدالصباح

حفظة هللا ورعاه

February 2009 Shagaya Vision

presented to H.H. The Amir Shaikh

Sabah Al-Ahmad Al-Jaber Al-Sabah

Page 3: Kuwait Energy Security Vision 2030 - MENARECInitiative+progress.pdf4/6/2016 1 Kuwait Energy Security Vision 2030 Shagaya Initiative Project Kuwait Institute for Scientific Research

4/6/2016

3

5

Then Became an Initiative......فأصبحت مبادرة

October 2011 Shagayaتقديم مبادرة الشقايا2011أكتوبر Initiative

was present

6

فأصبحت احد اهم مشاريع الطاقة المتجددة

الشقايااإلعالن الرسمي لمشروع2013يونيو

Then one of the most important Renewable Energy

Projects in the region

June 2013 Official announcement of

Shagaya Project

Page 4: Kuwait Energy Security Vision 2030 - MENARECInitiative+progress.pdf4/6/2016 1 Kuwait Energy Security Vision 2030 Shagaya Initiative Project Kuwait Institute for Scientific Research

4/6/2016

4

7

Shagaya Initiative

2,000MW designed installed capacity

1150MW CSP Plant

700MW PV Plant

150MW Wind Farm

8

Shagaya Initiative

Phase I: 70MW Introductory projects

50MW CSP Plant

10MW PV Plant

10MW Wind Farm

50MW

CSP

10MW PV

Page 5: Kuwait Energy Security Vision 2030 - MENARECInitiative+progress.pdf4/6/2016 1 Kuwait Energy Security Vision 2030 Shagaya Initiative Project Kuwait Institute for Scientific Research

4/6/2016

5

23 Solar Thermal Projects 50 MW each

14 Solar PV projects 50 MW each

140MW Wind Farm

CSP 1CSP 2CSP 3

CSP 7 CSP 6 CSP 5 CSP 4

CSP 9 CSP 8 CRT 2 CRT 1

CSP 12CSP 11CSP 10

CSP 15

CSP 14CSP 13

CRT 6 CRT 7

CRT 3 CRT 4 CRT 5

CRT 8

PV1

PV2PV3PV4PV5

PV8

PV7PV6

PV9 PV10

PV12

PV11PV13

PV15PV14

Wind 1

Wind 2

Wind 3

Shagaya Initiative projects dedicated for IPP

Technology Mix as per Development Master Plan

10

Shagaya Initiative Fact Sheet

Plant Capacity: 2,000 MW multi-technology renewable energy park

Generation

Capability:

5,000 GWh annually

Fuel Saving: 12 Million barrel of equivalent oil

Environment Impact: 5 Million Tone of CO2 from atmospheric emersion

Job Opportunity: 10,000 During Construction and 1,200 O&M

Technologies: - 1150 MW Solar Thermal Technology with 10h TES

- 750 MW Solar PV Technology

- 150MW Wind Power Technology

Infrastructure: - 4 Substations

- Integration to the national Grid

- Emerging Technology testing/demonstration site

- Housing Compound

- Water Treatment Plant

Page 6: Kuwait Energy Security Vision 2030 - MENARECInitiative+progress.pdf4/6/2016 1 Kuwait Energy Security Vision 2030 Shagaya Initiative Project Kuwait Institute for Scientific Research

4/6/2016

6

11

Phase I Project’s Current Statues

Project name Shagaya PV Shagaya Wind Shagaya CSP

Phase I: Plant Capacity 10 MW 10 MW 50 MW

Electricity Guarantee

(MWh/a)20,000 35,160 180,000

Project Cost (MKD) 5.5 7.2 116.5

Contract Signed On 12 Feb. 2015 26 Mar. 2015 12 Sept. 2015

Commercial Operation Day

(COD) August 2016 October 2016 Dec. 2017

O&M6 Years form

COD

6 Years form

COD

6 Years form

COD

LEC ($c/kWh) 9 8 16

12

Phase I Project’s Current Statues

Project nameOverhead line

project

Length (Km) 43

% progress 90%

Commissioning May 2016

Project name Substation project

Size

Big enough to

evacuate power

form Shagaya to the

national electricity

grid

% progress 95%

Commissioning July 2016

Project name Infrastructure and administration building project

Length (Km) 14 Km road

Building Administration building and Renewable energy R&D center

progress Bids evaluation stage

Commissioning 24 months

Page 7: Kuwait Energy Security Vision 2030 - MENARECInitiative+progress.pdf4/6/2016 1 Kuwait Energy Security Vision 2030 Shagaya Initiative Project Kuwait Institute for Scientific Research

4/6/2016

7

13

Shagaya Initiative

Development Time Line: Idea to Reality

Construction

Phase

2030202020182017201620152014201320122011

Complete Plant

Design and RfP

Development

Phase

2015-2025

Private Sector Participation

Achieve

National

Target of

15%

2025

Today

Official Start

Operation

Phase