LH Periode 8 Apr - 14 Apr 2015

  • View
    11

  • Download
    5

Embed Size (px)

DESCRIPTION

a

Text of LH Periode 8 Apr - 14 Apr 2015

Cover LH

DAILY REPORT

P E K E R J A A N

PEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "JALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

NAMA PEMILIK:Mrs. TETI YANI HARTONOKONTRAKTOR :PT. ADHI KARYA (Persero) Tbk.

NOMOR KONTRAK:10/TENDER/TWUJIL/UNG/XII/2014TANGGAL:18 December 2014SPMK:11/TENDER/TWUJIL/UNG/XII/2014TANGGAL:19 December 2014

LAPORAN HARIAN

MINGGU KE:17 ( Tujuh Belas )TANGGAL :08 April 2015s/d TANGGAL :14 April 2015

MANAJEMEN KONSTRUKSI

Rabu

DAILY ACTIVITY REPORT

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNERMANAJEMEN KONSTRUKSIKONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "PT. INDAH SARI LESTARICV. WASTU BUANA ADI CIPTAPT. ADHI KARYA (Persero) Tbk.JALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAHSurat Perintah Mulai Kerja19-Dec-2014PERIODESurat Penyerahan Lapangan18-Dec-2014TANGGALMINGGU KE -HARI KE -SISA HARIWaktu Pelaksanaan210Hari Kalender8-Apr-201517 ( Tujuh Belas )11199U R A I A NTENAGA KERJAJMLKEGIATANHARI INIMANAJEMENNO.PEKERJAAN YANG DILAKSANAKANVOLUMESATUANKET.1.Project Manager11Uitzet dan Bouwplank0.005Ls2.Project Engineer Manager12Sewa kantor direksi/kantor proyek/workshop/gudang0.005Ls3.Project Production Manager13Mobil Tadano (sewa)0.005Ls4.Project Planning14Mob Demob material dan alat0.011Ls5.Project Control1Beton Basement6.Drafter25Kolom Praktis12.857M'LAPANGANBeton Lantai 17.Kepala Pelaksana16Kolom Praktis107.143M'8.Pelaksana (P)37Beton ring balk dan latai107.143M'9.Mandor (M)38Kuda-kuda baja ringan galvanish Giga Steel13.000M210.Surveyor5Pemasangan Bata Ringan area toilet finish plesteran acianTukangPekerja9Lantai 1 Elevasi75.554M211.Kayu173148Pemasangan Bata Ringan area dinding biasa finish plesteran acian12.Batu0.09Lantai 1 Elevasi225.883M213.Besi101424Plesteran Acian Beton mu 29014.Las25711Lantai Basement153.944M215.Listrik0.0Lantai 216.Plumbing5242912Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857M17.Aspal0.013Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN40.571M18.Cat 0.014Pipa PV AW dia.1" (Vent) merk WAVIN76.714M19.Galian0.0Lantai 320.Pembersih0.015Pipa PVC AW dia.4" (air kotor) merk WAVIN33.429M21.Waterproofing0.016Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN62.000M22.Finishing0.017Pipa PV AW dia.1" (Vent) merk WAVIN88.286M23.Pembantu0.055Pekerjaan Drainase Hujan24Pengecoran371018Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4"13.571M25.Operator Alat Berat319Pipa drainase air hujan horizontal ,PVC AW dia.4"41.786M26.Operator/Driver Lainnya220Roofdrain (cast iron tipe meshroom)12.000BhT O T A L147

Bahan/Alat Yang MasukJumlahBahan/Alat yang dipakai JumlahExcavator Pc - 2001Stamper2Mobile Crane 25 Ton2

KEADAAN CUACA HARI INIJAM KERJAPagiCerahMulai8:00SiangCerahSelesai17:00SoreCerahMalamCerahPERMASALAHAN :

PENYELESAIAN :

Menyetujui,Disusun Oleh,Kontraktor PelaksanaManajemen KonstruksiPT. ADHI KARYA (Persero) Tbk.CV. WASTU BUANA ADI CIPTA

Heri Prayono, ST.Hari Sugiarto, ST.Project Production ManagerSupervisi StrukturCatatan :

TANGGALREVISIHAL / .

PERMOHONAN IJIN COR AREA LAINPROYEK: GEDUNG TEKNIK INDUSTRI UNDIP SMGKOP PERUSAHAANPAKET / PEK.: STRUKTURNO.: GTIUS/ AK / XI / 2013PERMOHONAN IJIN PELAKSANAANTanggal : 19 Maret 2013JENIS PEKERJAAN :Pekerjaan pengecoran plat balok lantai atap

LOKASI PEKERJAAN lantai atap

REFERENSIDenah plat balok lantai atap

PENDUKUNG PEKERJAANbeton ready mix K250, concrete pumppipa, thriller, sepatu proyekcangkul, sekop, garuk corhelm proyek, jojoh, gosokan, terpal

WAKTU SIAP DIINSPEKSIRENCANA WAKTU PELAKSANAAN PEKERJAANSelasa, 19 Maret 2013

DIAJUKAN OLEH KONTRAKTOR,MENGETAHUIMENYETUJUIPT. Adhi KaryaUNDIPPT. Cipta Prima Sejahtera

.............................................Ir. Budi SetyawanSite ManagerProject Manager

RESPONPENGAWASSETUJUTIDAK SETUJUPARAFSTRUKTUR

ARSITEKTUR

M E & P

CATATAN: (ALASAN DISETUJUI / TIDAK DISETUJUI)

NO. FORM : CPS / 15TANGGAL :REVISI :HAL : /

Kamis

DAILY ACTIVITY REPORT

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNERMANAJEMEN KONSTRUKSIKONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "PT. INDAH SARI LESTARICV. Wastu Buana Adi CiptaPT. ADHI KARYA (Persero) Tbk.JALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAHSurat Perintah Mulai Kerja19-Dec-2014PERIODESurat Penyerahan Lapangan18-Dec-2014TANGGALMINGGU KE -HARI KE -SISA HARIWaktu Pelaksanaan210Hari Kalender9-Apr-201517 ( Tujuh Belas )11298U R A I A NTENAGA KERJAJMLKEGIATANHARI INIMANAJEMENNO.PEKERJAAN YANG DILAKSANAKANVOLUMESATUANKET.1.Project Manager11Uitzet dan Bouwplank0.005Ls2.Project Engineer Manager12Sewa kantor direksi/kantor proyek/workshop/gudang0.005Ls3.Project Production Manager13Mobil Tadano (sewa)0.005Ls4.Project Planning14Mob Demob material dan alat0.011Ls5.Project Control1Beton Basement6.Drafter25Kolom Praktis12.857M'LAPANGANBeton Lantai 17.Kepala Pelaksana16Kolom Praktis107.143M'8.Pelaksana (P)37Beton ring balk dan latai107.143M'9.Mandor (M)38Kuda-kuda baja ringan galvanish Giga Steel13.000M210.Surveyor5Pemasangan Bata Ringan area toilet finish plesteran acianTukangPekerjaJumlah9Lantai 1 Elevasi75.554M211.Kayu133043Pemasangan Bata Ringan area dinding biasa finish plesteran acian12.Batu0.010Lantai 1 Elevasi225.883M213.Besi111526Plesteran Acian Beton mu 29014.Las25711Lantai Basement153.944M215.Listrik0.0Lantai 216.Plumbing6222812Pipa PVC AW dia.4" (air kotor) merk WAVIN31.857M17.Aspal0.013Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN40.571M18.Cat 0.014Pipa PV AW dia.1" (Vent) merk WAVIN76.714M19.Galian0.0Lantai 320.Pembersih0.015Pipa PVC AW dia.4" (air kotor) merk WAVIN33.429M21.Waterproofing0.016Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN62.000M22.Finishing0.017Pipa PV AW dia.1" (Vent) merk WAVIN88.286M23.Pembantu0.055Pekerjaan Drainase Hujan24Pengecoran371018Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4"13.571M25.Operator Alat Berat419Pipa drainase air hujan horizontal ,PVC AW dia.4"41.786M26.Operator/Driver Lainnya220Roofdrain (cast iron tipe meshroom)12.000Bh

T O T A L144

Bahan/Alat Yang MasukJumlahBahan/Alat yang dipakai JumlahExcavator Pc - 2001Stamper2Mobile Crane 25 Ton2

KEADAAN CUACA HARI INIJAM KERJAPagiCerahMulai8:00SiangCerahSelesai17:00SoreCerahMalamCerahPERMASALAHAN :

PENYELESAIAN :

Menyetujui,Disusun Oleh,Kontraktor PelaksanaManajemen KonstruksiPT. ADHI KARYA (Persero) Tbk.CV. WASTU BUANA ADI CIPTA

Heri Prayono, ST.Hari Sugiarto, ST.Project Production ManagerSupervisi StrukturCatatan :

TANGGALREVISIHAL / .

Jumat

DAILY ACTIVITY REPORT

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNERMANAJEMEN KONSTRUKSIKONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "PT. INDAH SARI LESTARICV. Wastu Buana Adi CiptaPT. ADHI KARYA (Persero) Tbk.JALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAHSurat Perintah Mulai Kerja19-Dec-2014PERIODESurat Penyerahan Lapangan18-Dec-2014TANGGALMINGGU KE -HARI KE -SISA HARIWaktu Pelaksanaan210Hari Kalender10-Apr-201517 ( Tujuh Belas )11397U R A I A NTENAGA KERJAJMLKEGIATANHARI INIMANAJEMENNO.PEKERJAAN YANG DILAKSANAKANVOLUMESATUANKET.1.Project Manager11Uitzet dan Bouwplank0.005Ls2.Project Engineer Manager12Sewa kantor direksi/kantor proyek/workshop/gudang0.005Ls3.Project Production Manager13Mobil Tadano (sewa)0.005Ls4.Project Planning14Mob Demob material dan alat0.011Ls5.Project Control1Beton Basement6.Drafter25Kolom Praktis12.857M'LAPANGANBeton Lantai 17.Kepala Pelaksana16Kolom Praktis107.143M'8.Pelaksana (P)37Beton ring balk dan latai107.143M'9.Mandor (M)38Kuda-kuda baja ringan galvanish Giga Steel13.000M210.Surveyor5Beton Lantai 2TukangPekerja9Kolom K23.159M311.Kayu7334010Kolom K62.592M312.Batu0.011Kolom K102.800M313.Besi82129Beton Lantai 314.Las25712Kolom K25.832M315.Listrik0.013Kolom K102.100M316.Plumbing51722Pemasangan Bata Ringan area toilet finish plesteran acian17.Aspal0.014Lantai 1 Elevasi75.554M218.Cat 0.0Pemasangan Bata Ringan area dinding biasa finish plesteran acian19.Galian0.015Lantai 1 Elevasi225.883M220.Pembersih0.0Plesteran Acian Beton mu 29021.Waterproofing0.016Lantai Basement153.944M222.Finishing0.0Lantai 223.Pembantu0.05517Pipa PVC AW dia.4" (air kotor) merk WAVIN31.857M24Pengecoran371018Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN40.571M25.Operator Alat Berat319Pipa PV AW dia.1" (Vent) merk WAVIN76.714M26.Operator/Driver Lainnya2Lantai 320Pipa PVC AW dia.4" (air kotor) merk WAVIN33.429M21Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN62.000MT O T A L13722Pipa PV AW dia.1" (Vent) merk WAVIN88.286MPekerjaan Drainase Hujan23Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4"13.571M24Pipa drainase air hujan horizontal ,PVC AW dia.4"41.786M25Roofdrain (cast iron tipe meshroom)14.000Bh

Bahan/Alat Yang MasukJumlahBahan/Alat yang dipakai JumlahBeton K-30016.5 M3Excavator Pc - 2001Pasir10 M3Stamper2Sirtu15 M3Mobile Crane 25 Ton2

KEADAAN CUACA HARI INIJAM KERJAPagiCerahMulai8:00SiangCerahSelesai17:00SoreCerahMalamHujanPERMASALAHAN :

PENYELESAIAN :

Menyetujui,Disusun Oleh,Kontraktor PelaksanaManajemen KonstruksiPT. ADHI KARYA (Persero) Tbk.CV. WASTU BUANA ADI CIPTA

Heri Prayono, ST.Hari Sugiarto, ST.Project Production ManagerSupervisi StrukturCatatan :

TANGGALREVISIHAL / .

Sabtu

DAILY ACTIVITY REPORT

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNERMANAJEMEN KONSTRUKSIKONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "PT. INDAH SARI LESTARICV. Wastu Buana Adi CiptaPT. ADHI KARYA (Persero) Tbk.JALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAHSurat Perintah Mulai Kerja19-Dec-2014PERIODESurat Penyerahan Lapangan18-Dec-2014TANGGALMINGGU KE -HARI KE -S