LIZ’S BAKERY
DEFINE PHASE
EXECUTIVE SUMMARYProblem/Goal Statement
Tollgate Review Schedule
Business Impact
Core Team
Problem: Our customers are experiencing dissatisfaction with our cookies on a growing basis. The company is experiencing a loss of revenue as well as their reputation for a consistent, high quality cookie is being damaged.
Scope: All of the procedures that are associated within the scope of the production and packaging of our cookies.
Goal: We want to reduce the overall customer complaints by 50% and increase associated revenue by $12,000 (annualized) by April 30, 2015.
Business Case: Through isolation of each segment of the process we will be able to determine the root cause of the customer complaints in order to rectify the issues.
We need to determine the root cause of the increase in complaints. Determining the root cause of the complaints can lead to a solution and an increase in revenues.
Financial impact: $12,000 revenue (annualized)
Operational Impact: Reduce complaints in by 50%
Team Member Role Phase Tool
Angela Harrison SME CTQ Tree
Melinda McClouden SME Comm. Plan
Richard Penny SME Project Charter
Kabir Small SME SIPOC
Phase Schedule StatusDefine 2/20/15 Complete
Measure 3/2/15 In Progress
Analyze 3/20/15 Not Started
Improve 4/2/15 Not Started
Control 4/21/15 Not Started
SIPOC DIAGRAMSuppliers Inputs Processes Outputs Customers
Store
Outside Vendors Shopping Storage
Wholesalers Purchase Order
All Ingredients Warehouse
Raw Material Supplier
iCommercial Equipment
Equipment/Utensils
Store Supplier Raw Materials
Cookie Dough Storage
Wholesalers Recipes Oven
i
Supplier OvenFinish
Product for Packaging
Packaging/ Dept
Machine
i
U-Line Machinery Delivered Goods Shipper
Raw Materials
Received for Processing
Materials used for Mixing
Baking
Packaging
AFFINITY DIAGRAM
CTQ TREE
Premium
Cookies
Fresh
Appearance/
Size
Flavorful
• Bake Date• Delivery Time• Fresh ingredients• Hardness
• Number ingredients
• Bake Time• Cookie Thickness
• Fresh ingredients• Bake Time• Bake Temp• Amount of
Ingredients
• Time• Time• Time• Time/
Count
• Count/Recipe
• Time• Count
• Time• Time• Count• Count/
Recipe
Characteristics MeasureNeed Driver
COMMUNICATION CONNECTIONCommunication Purpose Audience Author Vehicle Frequency
Status ReportsTo keep key stakeholders informed of progress, issues, and solutions.
CCS Marketing management, client contact
Project manager CSU Email Monthly
Team meetingsTo ensure all team members are apprised of progress, changes, and current priorities Project team members Project manager Face-to-face
Weekly, Wednesdays 9:00 – 10:00
Email Communications
Non-Urgent - To distribute meeting minutes, alert team members to document changes posted, share information and answer questions between meetings.
Project Team members, Client contact, CCS Marketing management
Project team members, Client contact, CCS Marketing management
Email As needed
Phone/ in-personEmergencies/ things that require immediate attention Project team members Project team members
Instant Communication - Text - Phone - On site Meetings
As needed
Shared Project Folder Retains all current project documentation. Project team members
Project Manager, project team members <Shared Folder Location>
Upload revisions within 24 hours of the change.
Webex conferences
To ensure all team members are apprised of progress, changes, and current priorities. Allows file sharing and does not requires on sight meeting.
Project Team MembersProject Manager, project team members Web communication Weekly
GroupMe Retains all current project documentation. Project team membersProject Manager, project team members Mobile commonnication app As needed
GANTT CHART
MEASURE PHASE
EXECUTIVE SUMMARYKey Findings
Tollgate Review Schedule
Key Graphic
Core Team
Phase Schedule StatusDefine 2/20/15 CompleteMeasure 3/2/15 Complete
Analyze 3/20/15 In ProgressImprove 4/2/15 Not Started
Control 4/21/15 Not Started
Team Member Role Phase Tool
Angela Harrison SME Process map
Melinda McClouden SME
Customer Complaint C & E
Richard Penny SME Data collection
Kabir Small SME KPIV, KPOV
Objective: To determine the
measurements which caused an
increase in complaints and a decrease
in revenue.
Key Findings: The bake temperature is
out of the upper and lower
specification limits.
Bake Temp
Storage
Sufficient
Q.A.
Cooling
BakingStagingMixingStaging
Distribution
Exit Proces
s
StartReceive
Raw Materials
Packaging SufficientQ.A.
Exit Proces
s
Exit Proces
s
DETAIL PROCESS MAP – NON VALUE ADD (NVA) ANALYSIS
4/15 (28%) activities are value-added
People Process
Environment
Products
Customer Complaint
s
Skills
Standard Process
External storage conditions
Ordering
Timing of customer orders
Storage area
Oven
Lack of training
Multiple recipes
Measurement inaccuracies
High turnover
Capacity
Temperature
Difficult to use
Quality of Ingredients
Delivery schedule
Ingredients
Equipment
DATA COLLECTION PLAN
PROCESS BASELINE: COOKIE HARDNESS (KPIV)
4191
341
920
4192
741
934
4194
141
948
4195
541
962
4196
941
976
4198
341
990
4199
742
004
4201
142
018
4202
542
032
4203
942
046
4205
342
060
4206
642
073
4208
042
087
4209
435
40
45
50
55
60
65• Process in
control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
Old Facility
UCL
USL
LSL
LCL
PROCESS BASELINE: BAKE TIME (KPIV)
4191
341
917
4192
441
930
4193
741
943
4195
041
956
4196
341
969
4197
641
980
4198
741
993
4200
042
006
4201
342
019
4202
642
032
4203
942
043
4205
042
056
4206
342
068
4207
542
081
4208
842
094
9.3
9.5
9.7
9.9
10.1
10.3
10.5
10.7
• Process in control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
Old Facility
UCL
USL
LCL
LSL
PROCESS BASELINE: BAKE TEMPERATURE (KPIV)
4191
341
917
4192
441
930
4193
741
943
4195
041
956
4196
341
969
4197
641
980
4198
741
993
4200
042
006
4201
342
019
4202
642
032
4203
942
043
4205
042
056
4206
342
068
4207
542
081
4208
842
094
325330335340345350355360365370375
• Process is out of control (non-random pattern in data)
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
Old Facility
UCL
USL
LSL
LCL
PROCESS BASELINE: COOKIE WEIGHT (KPIV)
4191
341
917
4192
441
930
4193
741
943
4195
041
956
4196
341
969
4197
641
980
4198
741
993
4200
042
006
4201
342
019
4202
642
032
4203
942
043
4205
042
056
4206
342
068
4207
542
081
4208
842
094
30
30.5
31
31.5
32
32.5
33
33.5
• Process in control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
Old Facility
UCLUSL
LSLLCL
PROCESS BASELINE: TASTE (KPOV)
01-O
ct-14
09-O
ct-14
17-O
ct-14
25-O
ct-14
02-N
ov-1
4
10-N
ov-1
4
18-N
ov-1
4
26-N
ov-1
4
04-D
ec-1
4
12-D
ec-1
4
20-D
ec-1
4
28-D
ec-1
4
05-Ja
n-15
13-Ja
n-15
21-Ja
n-15
29-Ja
n-15
06-F
eb-1
5
14-F
eb-1
5
22-F
eb-1
5
02-M
ar-1
5
10-M
ar-1
5
18-M
ar-1
5
26-M
ar-1
580.00
82.00
84.00
86.00
88.00
90.00
92.00
94.00
96.00
98.00
Old Facility
LSL
Taste (Max 100, Min 90)
PROCESS BASELINE: COOKIE HARDNESS (KPIV)
4191
341
917
4192
341
929
4193
541
941
4194
541
951
4195
741
963
4196
941
973
4197
941
985
4199
141
997
4200
142
007
4201
342
019
4202
542
029
4203
542
041
4204
742
053
4205
742
063
4206
942
075
4208
142
087
4209
137.5
42.5
47.5
52.5
57.5
62.5
• Process in control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
New Facility
UCL
USL
LSL
LCL
PROCESS BASELINE: BAKE TIME (KPIV)
4191
341
917
4192
341
929
4193
541
941
4194
541
951
4195
741
963
4196
941
973
4197
941
985
4199
141
997
4200
142
007
4201
342
019
4202
542
029
4203
542
041
4204
742
053
4205
742
063
4206
942
075
4208
142
087
4209
19.4
9.6
9.8
10
10.2
10.4
10.6
• Process in control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
New Facility
UCL
USL
LSL
LCL
PROCESS BASELINE: BAKE TEMP (KPIV)
• Process out of control (non-random pattern in data
• Process not capable (control limits outside of spec limits
• All data outside spec limits (green lines) are potential complaints
4191
341
917
4192
441
930
4193
741
943
4195
041
956
4196
341
969
4197
641
980
4198
741
993
4200
042
006
4201
342
019
4202
642
032
4203
942
043
4205
042
056
4206
342
069
4207
642
082
4208
9337.5
342.5
347.5
352.5
357.5
362.5New Facility
UCL
USL
LSL
LCL
PROCESS BASELINE: COOKIE WEIGHT (KPIV)
4191
341
917
4192
441
930
4193
741
943
4195
041
956
4196
341
969
4197
641
980
4198
741
993
4200
042
006
4201
342
019
4202
642
032
4203
942
043
4205
042
056
4206
342
069
4207
642
082
4208
930.5
31
31.5
32
32.5
33
33.5• Process out of
control (non-random pattern in data
• Process not capable (control limits outside of spec limits
• All data outside Spec limits (green lines) are potential complaints
New Facility
UCL
USL
LSL
LCL
PROCESS BASELINE: TASTE (KPOV)
01-O
ct-14
09-O
ct-14
17-O
ct-14
25-O
ct-14
02-N
ov-1
4
10-N
ov-1
4
18-N
ov-1
4
26-N
ov-1
4
04-D
ec-1
4
12-D
ec-1
4
20-D
ec-1
4
28-D
ec-1
4
05-Ja
n-15
13-Ja
n-15
21-Ja
n-15
29-Ja
n-15
06-F
eb-1
5
14-F
eb-1
5
22-F
eb-1
5
02-M
ar-1
5
10-M
ar-1
5
18-M
ar-1
5
26-M
ar-1
589.00
90.00
91.00
92.00
93.00
94.00
95.00
96.00
97.00
98.00
99.00
Taste (Max 100, Min 90)
New Facility
ANALYZE PHASE
EXECUTIVE SUMMARYKey Findings
Tollgate Review Schedule
Key Graphic
Core Team
Phase Schedule StatusDefine 2/20/15 CompleteMeasure 3/2/15 Complete
Analyze 3/20/15 Complete
Improve 4/2/15 In Progress
Control 4/21/15 Not Started
Team Member Role Phase Tool
Angela Harrison SME List of Sig. Inputs
Melinda McClouden SME C & E Matrix
Richard Penny SME Scatterplot
Kabir Small SME Hypothesis Test
Bake Temperature
Objective: We identified the bake temperature was initially found to be within the specification limits. The KPIV revealed that the bake temperature was random and out of specification.
There is a gap between the current and desired performance of the bake temperature. This critical input drove complaints that must be improved.
SCATTERPLOT BAKE TEMPERATURE
18-Sep-14 07-Nov-14 27-Dec-14 15-Feb-15 06-Apr-15 26-May-15320.0325.0330.0335.0340.0345.0350.0355.0360.0365.0370.0
Old Facility
CAUSE AND EFFECT MATRIX
Topic Date 3/30/2015 Team Leader
C&E Matrix Outputs TASTE HARDINES
S
Output Weighting 10 5
Ref. Inputs
1 PROPER BAKE TEMP 8 9 125
2 PROPER BAKE TIME 9 9 135
3 COOKIE WEIGHT 3 9 75
4 RECIPE 7 8 110
5 FRESH INGREDIENTS 8 2 90
0
Complaints
Weighted Value of INPUT
Rate the effect of each Input on Each Output
Sum of Input association with each Output 350 0 185 0 0
HYPOTHESIS TESTING
Sample 1 Mean: 94.97
Sample 1 Sample Size: 262
Sample 2 Mean: 89.39
Sample 2 Sample Size: 262Sample 1 Standard Deviation: 1.442Sample 2 Standard Deviation: 2.930
P-Value: 0.000
Recommendation: Sample 1 IS different from Sample 2 to within your confidence level.
Taste Old/New Facility
HYPOTHESIS TESTINGType of test (1 = Paired t, 2 = 2-sample t): 1
Paired t test requires both samples to have equal sample sizes.
Desired Confidence (e.g., 95%): 95%
1- or 2-tail test (default is 2-tail): 2
Sample 1 Mean: 9.98
Sample 1 Sample Size: 262
Sample 2 Mean: 10.01
Sample 2 Sample Size: 262
Sample 1 Standard Deviation: 0.166
Sample 2 Standard Deviation: 0.344
P-Value: 0.231
Recommendation: Sample 1 IS NOT different from Sample 2 within your confidence level.
LIST OF SIGNIFICANT CAUSES
Hypothesis
TestedPotential X's Measurable
(Yes/No)Sourceof 'X'
Data Source Comments
DataType
Yes Bake Temp Yes Fishbone Bake temp is the problem
Continuous
No Bake Time Yes Graphical Tools
Continuous
No Cookie Weight Yes C&E Metrics Continuous
No Recipe No C&E Metrics Continuous
No Freshness No C&E Metrics Continuous
No Ingredients Yes Fishbone Attribute
IMPROVE PHASE
EXECUTIVE SUMMARYKey Findings
Tollgate Review Schedule
Key Graphics
Core Team
Phase Schedule StatusDefine 2/20/15 CompleteMeasure 3/2/15 Complete
Analyze 3/20/15 CompleteImprove 4/2/15 Complete
Control 4/21/15 In Progress
Team Member Role Phase Tool
Angela Harrison SME Future State Process Map
Melinda McClouden SME Quick Hits
Richard Penny SME Pilot Plan
Kabir Small SME Graphical Analysis
Objective: Liz Bakery identified potential solutions through data analysis of the key process variables.
To develop and implement improvement tools using innovative solutions to improve the baking process.
Project Benefit: Reduced complaints by 50%
CriteriaReduce Customer Complaints + + + + 10Improve Taste + S + + 8
Increase Sales + + S S 9Organizational Excellence S S + S 5Productivity S S + S 4Lean Iniatives + + + + 3Continuous Process Improvement + S + + 3
Sum of Positives 5 3 6 4Sum of Negatives 0 0 0 0Sum of Sames 2 4 1 3
Weighted sum of Positives 33 22 33 24Weighted sum of Negatives 0 0 0 0Total Weighted Score 33 22 33 24
PUGH MATRIX
CriteriaReduce Customer Complaints + + + + 10Improve Taste + S + + 8
Increase Sales + + S S 9Organizational Excellence S S + S 5Productivity S S + S 4
Lean Iniatives + + + + 3Continuous Process Improvement + S + + 3
Sum of Positives 5 3 6 4Sum of Negatives 0 0 0 0Sum of Sames 2 4 1 3
Weighted sum of Positives 33 22 33 24Weighted sum of Negatives 0 0 0 0Total Weighted Score 33 22 33 24
Better +Same SWorse -
Concept Legend
QUICK HITS
PILOT PLAN Pilot Test Action Item Success
CriteriaAssigned
To Schedule
1Change thermostat on 10 ovens
Oven Temp within spec limit
Maintenance 3/21/15
2 Calibrate 10 ovens
Ovens are now within spec limits
Maintenance 3/22/15
3Oven temp taken once per hour during 1st shift
Oven temp within spec limit
Oven Operator
3/23-3/30/15
4Oven temp taken once per hour during 2nd shift
Oven temp within spec limit
Oven Operator
3/23-3/30/15
Issue: Baking Temp
PROCESS IMPROVE: COOKIE HARDNESS (KPIV)
4209
642
096
4209
742
097
4209
842
098
4209
942
099
4210
042
100
4210
342
103
4210
442
104
4210
542
105
4210
642
106
4210
742
107
4211
042
110
4211
142
111
4211
242
112
4211
342
113
4211
442
114
30.5
35.5
40.5
45.5
50.5
55.5
60.5
65.5• Process in control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
Old Facility
UCL
USL
LSL
LCL
PROCESS IMPROVE: BAKE TIME(KPIV)
4209
642
096
4209
742
097
4209
842
098
4209
942
099
4210
042
100
4210
342
103
4210
442
104
4210
542
105
4210
642
106
4210
742
107
4211
042
110
4211
142
111
4211
242
112
4211
342
113
4211
442
114
99.29.49.69.810
10.210.410.610.8
• Process in control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
Old Facility
UCL
UCL
USL
LSL
PROCESS IMPROVE: BAKE TEMPERATURE (KPIV)
4209
6
4209
7
4209
8
4209
9
4210
0
4210
3
4210
4
4210
5
4210
6
4210
7
4211
0
4211
1
4211
2
4211
3
4211
4
335
340
345
350
355
360
365• Process in
control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
Old Facility
UCL
USL
LSLLCL
4209
6
4209
7
4209
8
4209
9
4210
0
4210
3
4210
4
4210
5
4210
6
4210
7
4211
0
4211
1
4211
2
4211
3
4211
4
30.5
31
31.5
32
32.5
33
PROCESS IMPROVE: COOKIE WEIGHT(KPIV)
• Process in control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
Old Facility
UCLUSL
LSLLCL
PROCESS IMPROVE: TASTE (KPOV)
28-M
ar-1
5
30-M
ar-1
5
1-Apr
-15
3-Apr
-15
5-Apr
-15
7-Apr
-15
9-Apr
-15
11-A
pr-1
5
13-A
pr-1
5
15-A
pr-1
5
17-A
pr-1
5
19-A
pr-1
5
21-A
pr-1
5
23-A
pr-1
5
25-A
pr-1
5
27-A
pr-1
5
29-A
pr-1
589.00
90.00
91.00
92.00
93.00
94.00
95.00
96.00
Taste (Max 100, Min 90)Old Facility
PROCESS IMPROVE: COOKIE HARDNESS (KPIV)
4209
642
097
4209
842
099
4210
042
103
4210
442
105
4210
642
107
4211
042
111
4211
242
113
4211
442
117
4211
842
119
4212
042
121
4212
4
35
40
45
50
55
60
65• Process in
control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
New Facility
UCL
USL
LSLLCL
PROCESS IMPROVE: BAKE TIME (KPIV)
4209
6
4209
7
4209
8
4209
9
4210
0
4210
3
4210
4
4210
5
4210
6
4210
7
4211
0
4211
1
4211
2
4211
3
4211
49
9.2
9.4
9.6
9.8
10
10.2
10.4
10.6
10.8• Process in
control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
New Facility
UCL
USL
LSL
UCL
PROCESS IMPROVE: BAKE TEMP (KPIV)
4209
6
4209
7
4209
8
4209
9
4210
0
4210
3
4210
4
4210
5
4210
6
4210
7
4211
0
4211
1
4211
2
4211
3
4211
4335
340
345
350
355
360
365• Process in
control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
New Facility
UCL
USL
LSL
LCL
4209
642
096
4209
742
097
4209
842
098
4209
942
099
4210
042
100
4210
342
103
4210
442
104
4210
542
105
4210
642
106
4210
742
107
4211
042
110
4211
142
111
4211
242
112
4211
342
113
4211
442
114
30.5
31
31.5
32
32.5
33
33.5
PROCESS IMPROVE: COOKIE WEIGHT (KPIV)
• Process in control
• Process capable (control limits inside of spec limits)
• All data outside spec limits (green lines) are potential complaints
New Facility
UCL
USL
LSL
LCL
PROCESS IMPROVE: TASTE (KPOV)
2-Apr-15 6-Apr-15 10-Apr-15 14-Apr-15 18-Apr-15 22-Apr-15 26-Apr-15 30-Apr-1589.00
90.00
91.00
92.00
93.00
94.00
95.00
96.00
Taste (Max 100, Min 90)
LSL
New Facility
IMPROVED BAKE TEMPERATURE
340.0
342.0
344.0
346.0
348.0
350.0
352.0
354.0
356.0Old Facility
FUTURE STATE PROCESS MAP
StorageSufficient
Cooling4
minutes
Bake time10
minutes
Put dough on
pansMixing
Distribution
Exit Proces
s
StartReceive Raw Materials
Cookies are sent to
be packaged
Place Order
Check Quality of Ingredients
Yes
No• Refrigerated items
stored at 41 degrees
• Frozen item stored 32 degrees
• Temperature Check
StagingPreheat
Oven350o
• Recipe• Pull only the
needed recipe ingredients
• Prep ingredients• Pan Size• Prep 10 baking
pans per oven
Defective
Cookies
Yes
Exit Proces
s
Exit Proces
s
No
Check Cookie Quality
Sufficient
• Ingredients• Recipe• Mixing time• Mixer
CONTROL PHASE
EXECUTIVE SUMMARYKey Findings
Tollgate Review Schedule
Key Graphics
Core Team
Phase Schedule Status
Define 2/20/15 CompleteMeasure 3/2/15 Complete
Analyze 3/20/15 CompleteImprove 4/2/15 Complete
Control 4/21/15 Complete
Team Member Role Phase Tool
Angela Harrison SME Control Plan
Melinda McClouden SME Implementation
Plan
Richard Penny SME S.O.P.
Kabir Small SME Primary Metric
Objective: Control measures in place to
ensure future performance for KPIV
out of specifications.
Project benefits: Customer complaints
reduced by 61%.
CONTROL PLAN TEMPLATEPROJECT NAME DIVISION Team Members DATE
Improve Bake Temperature Operations Angela Melinda 4/21/2015
PROJECT SPONSOR SERVICE AREA / FUNCTION / SERVICE Richard Kabir
Angela Harrison Food Service/Food Preparation
Control Action
NumberControl Action Responsible
Individual
Applicable Control Charts and Metrics
Freq. Process Step
Target Value
Upper Control
LimitLower Control
Limit Reaction Plan
1 Monitor baking temperature Baker Continuously Baking 350.0 355.0 345.0 Baker adjust temp if needed
2 Measure Oven Temperature Baker Hourly Staging 350.0 355.0 345.0 Baker adjust temp if needed
3 Check oven caliberation Engineer Monthly None 350.0 355.0 345.0 Recalibrate oven
4 Automatic Shut-off Oven As needed Baking 10.0 10.00 10.00 Oven shuts-off
5 High/Low Temperture Alarm Oven Per Batch Baking 350.0 355.0 345.0 Alarm sounds notifying there's a problem
STANDARD OPERATING PROCEDURESControl Item Procedure Who When
Oven Operation Train all bakers and assistants Master Bakers Upon hiring
and quarterly
Measure oven temp
Monitor oven for correct tempAlert maintenance and management for constant issues
Bakers and assistants Per batch
Oven calibrationCheck oven calibrationAlert management with issues
Maintenance Monthly
Auto shut offOven will shut downPull cookies
Bakers Per batch
High/Low temp alarm
Alarm sounds for temps out of zoneCookies pulledmanagement alerted
Bakers Per batch
IMPLEMENTATION PLANPROJECT NAME DIVISION
Team Members DATE
Liz Bakery Angela Harrison
Richard Penny
Thursday, April 29, 2015
PROJECT SPONSORSERVICE AREA / FUNCTION / SERVICE
Melinda McClouden Kabir Smalls
Melinda McClouden
Implementation Number
SolutionControl Action
NumberImprovement
Action
Responsible
Individual/ Solution Owner
Issues/Barriers Risk Mitigation
Target/ Actual
Complete Date
Current Status/ Comments
1 High / Low Temp Alarm 5
Alarm notifies bakers of potential issue
MELINDAInstallation and cost of alarm
Prevent over cooking 4/20/15 Completed. No
Issues
2 Revised Standard Operating Procedure
Ensure operating procedures are standardized
ANGELANot adhering to revised SOP
Further issues with
complaints4/15/15 Completed. No
Issues
3 Oven Maintenance plan
Create plan to maintain properly operational oven
KABIR Production Shutdown
Prevent ovens from having breakdowns
4/18/15 In process.
4 Install Oven Automatic shut-off 4 Prevent over
cooking RICHARDInstallation and cost of shut-off switch
Prevents improper cooking
4/21/15 In process.
5 Oven check 3 Maintain proper oven temperature ANGELA Scheduling
the checksPreventing
temperature variations
4/8/15Completed.
Increased to weekly process.
6 Implement Monthly Collaboration Continuous
improvement MELINDAScheduling the meetings
Hinders continuous
improvement4/11/15
Completed. Increased to weekly
process.
PRIMARY METRIC CHART
01-O
ct-14
15-O
ct-14
29-O
ct-14
12-N
ov-1
4
26-N
ov-1
4
10-D
ec-1
4
24-D
ec-1
4
07-Ja
n-15
21-Ja
n-15
04-F
eb-1
5
18-F
eb-1
5
04-M
ar-1
5
18-M
ar-1
5
01-A
pr-1
5
15-A
pr-1
5
29-A
pr-1
50
10
20
30
40
50
60
70
Complaints
Complaint baseline = 57 per shift
Complaint improved = 22 per shift