EPS SEDACUSCO S.A.EPS SEDACUSCO S.A.
Gerencia de Ingeniería
REPORTE FINANCIERO
OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”
CUENTA CONTABLE: 339531
ITEM CONCEPTO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO1 MANO DE OBRA 11,762.722 MATERIALES 372,045.693 EQUIPOS 0.004 SERVICIOS DIVERSOS 281.10
TOTAL 0.00 0.00 384,089.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PRESUPUESTO ANALITICO
ITEM CONCEPTO APROBADO EJECUTADO SALDO1 MANO DE OBRA 639,604.64 11,762.72 627,841.922 MATERIALES 869,629.84 372,045.69 497,584.153 EQUIPOS 13,000.00 0.00 13,000.004 SERVICIOS DIVERSOS - OTROS 19,071.23 281.10 18,790.13
TOTAL (SOLES) 1,541,305.71 384,089.51 1,157,216.20
TOTAL(%) 100.00% 24.92% 75.08%
DESCRIPCIONPRESUPUESTO
AVANCE DEL MES AVANCE ACUMULADO SALDO POR EJECUTARDE OBRA S/. % S/. % S/. %
Avance Financiero Programado 1,541,305.71 400,000.00 25.95% 400,000.00 25.95% 1,141,305.71 74.05%Avance Financiero Ejecutado 1,541,305.71 384,089.51 24.92% 384,089.51 24.92% 1,157,216.20 75.08%
REPORTE FINANCIERO
AGOSTO TOTAL 11,762.72
372,045.690.00
281.100.00 384,089.51
Septiembre Octubre Noviembre Diciembre Enero Febrero0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
0 0 0 0 0 0
73,609 73,609 73,609 73,609 73,609 73,609
CONTROL DE AVANCEPROGRAMADO Vs. EJECUTADO
Avance Programado Avance Ejecutado
Meses
Mon
to
EPS SEDACUSCO S.A.EPS SEDACUSCO S.A.
Gerencia de Ingeniería
CONTROL DE AVANCE FISICOPROGRAMADO Vs. EJECUTADO
Mes
Avance Programado Avance Ejecutado Situación de la Obra
Mensual Acumulado Mensual Acumulado Adelanto Atraso
S/. S/. % S/. S/. % % %
Septiembre #NAME? #NAME? #NAME? 73,608.54 73,609 #NAME? #NAME? #NAME?Octubre #NAME? #NAME? #NAME? 73,609 #NAME? #NAME? #NAME?Noviembre #NAME? #NAME? #NAME? 73,609 #NAME? #NAME? #NAME?Diciembre #NAME? #NAME? #NAME? 73,609 #NAME? #NAME? #NAME?Enero #NAME? #NAME? #NAME? 73,609 #NAME? #NAME? #NAME?Febrero #NAME? #NAME? #NAME? 73,609 #NAME? #NAME? #NAME?
Total #NAME? 73,609
DescripciónEn el Mes Acumulado Actual Saldo por Ejecutar
S/. % S/. % S/. %
Programado #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?Ejecutado 73,609 #NAME? 73,609 #NAME? #NAME? #NAME?
A.R. (%)Valorización Acumulada Real
=73,609
= #NAME?Monto del Contrato de Obra #NAME?
A.P. (%)Valorización Acumulada Prog.
=#NAME?
= #NAME?Monto del Contrato de Obra #NAME?
(%)A.R. (%)
=#NAME?
= #NAME?A.P. (%) #NAME?
VALORIZACION EJECUTADA MENSUAL #NAME?
% AVANCE ACTUAL #NAME?
% AVANCE ACUMULADO #NAME?
VALORIZACION PROGRAMADA MENSUAL #REF!
% AVANCE PROGRAMADA MENSUAL #REF!
VALORIZACION EJECUTADA MENSUAL Err:509COMPLEM
VALORIZACION ACUMULADA Err:509
IMPORTE DE LA EJECUCION PRESUPUESTAL ACUMULADA S/. 0.00
IMPORTE DE LA EJECUCION PRESUPUESTAL MENSUAL S/. 0.00
#NAME?
M1 #NAME?M2 #NAME?M3 #NAME?M4 #NAME?M5 #NAME?M6 #NAME?
#NAME?
0.050897004 0.18916146 2863318.12#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME?
2863318.12#NAME?#NAME?#NAME?#NAME?#NAME?#NAME?#NAME?
PRESUPUESTO VALORIZADO
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA
MES DICIEMBRE 2013OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”
MONTO DE OBRA S/. 102,944.52 REGION : CUSCOMONTO ASIGNADO S/. 102,944.52 DEPARTAMENTO : CUSCOFECHA DE INICIO DE OBRA 11/19/2013 PROVINCIA : CUSCOPLAZO DE EJECUCIÓN 60 DIAS DISTRITO : SAN SEBASTIANFECHA DE TERMINO 1/18/2014 LOCALIDAD A.P.V. TRABAJADORES DE CORPAC
FECHA DE PRESENTACIÓN:
ITEM VALORIZACION
PRESUPUESTOAVANCES
ANTERIOR ACTUAL
S/.% % %
1 PROGRAMADO 102,944.52 - 0.00% 71,580.77 69.53% 71,580.77 69.53%
2 MAYOR METRADOS 2,027.77 - 0.00% 2,027.77 1.97% 2,027.77 1.97%
COSTOS TOTAL 102,944.52 - 0.00% 73,608.54 71.50% 73,608.54 71.50%
ACUMULADO Valorizado
S/.Valorizado
S/.Valorizado
S/.
RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA
: SAN SEBASTIANA.P.V. TRABAJADORES DE CORPAC
12/1/2013
SALDO
%
31,363.77 30.47%
- 0.00%
31,363.77 30.47%
ValorizadoS/.
PARTIDAS EJECUTADAS EN ELPROYECTO
Se ha realizado la ejecucion de obra, según el Expediente Tecnico Aprobado, habiendoce ejecutado las siguientes partidas
PARTIDA DESCRIPCION DE LA PARTIDA UNIDAD METRADO
01.00.00 OBRAS PROVISIONALES SISTEMA DE AGUA
01.01.00 Construccion de Oficina, Almacen y Guardiania M2 0.00los beneficiaios proporcionaron ambientes tanto para la residencia y almacen de obra
01.02.00 Energia Electrica Provisional GLB 1.00se tuvo que pagar a los beneficiarios por la energia electrica temporal
01.03.00 Puentes Peatonales de Madera UND 0.00partida no ejecutada
01.04.00 Tranqueras de Madera Para Desvio Vehicular UND 0.00partida no ejecutada
01.05.00 Cartel de Identificacion de Obra UND 0.00partida no ejecutada
01.06.00 Limpieza de Obra M2 1,383.26esta partida se ejecuto mediante faenas de los pobladores del APV Corpac Cusco
01.07.00 Cinta de seguridad M 0.00partida no ejecutada
02.00.00 TRABAJOS PRELIMINARES
02.01.00 Limpieza de Terreno Manual M2 1,383.26esta partida se ejecuto mediante faenas de los pobladores del APV Corpac Cusco
03.00.00 REDES DE DISTRIBUCION
03.01.00 TRABAJOS PRELIMINARES
03.01.01 Trazo Nivelacion y Replanteo M2 549.41
03.01.02 Trazo Nivelacion y Replanteo Durante el Proceso M2 549.51
se realizo el control permanente y minucioso del alineamiento, a fin de evitar modificaciones en el eje de la tuberia instalada
03.02.00 MOVIMIENTO DE TIERRAS
03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 398.00
03.02.02 Perfilado de zanjas M 959.75
03.02.03 Cama de apoyo para tuberias E=0.10m M3 57.58
03.02.04 Relleno y compactado con material propio M3 233.27
03.02.05 Eliminacion y acarreo de material exedente M3 114.46
03.02.06 Entibado y apuntalamiento de zanjas H>2.5m M 90.00se utilizo maderamen adquirido con recursos propios (tablas y listones)
03.03.00 TUBERIAS
03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 959.75
03.04.00 SUMINISTRO Y COLOCACION DE ACCESORIOS Y VALVULAS
03.04.01 Suministro y colocacion de valvula de purga 90mm en red de distribucion PZA 1.00
se utilizo esta valvula de purga al final de la tuberia instalada, en la parte mas baja de la red
03.04.02 Suministro y colocacion de valvula de compuerta de 90mm en red de distribucion PZA 2.00
03.05.00 PRUEBA HIDRAULICA
03.05.01 Prueba hidraulica en tuberias GLB 2.00
03.05.02 Desinfeccion en tuberias M 915.69
una vez realizada la prueba hidraulica se procdio con la desinfeccion de la tuberia para su posterior puesta en marcha
03.06.00 VARIOS
03.06.01 Reposicion de conexiones de agua UND 0.00partida no ejecutada
03.06.02 Demolicion y reposicion de pavimento M2 0.00partida no ejecutada
03.06.03 Puesta en operación del sistema de agua GLB 1.00
NOTA:
se ubico en el terreno l eje de la red de distribucion, habiendoce ubicado ademas el are de empalme, valvulas de compuerta y demas detalles que aparecen en los planos, luego se procedio al trazo del ancho de la zanja con yeso, según lo que indica en los planos de planta
se realizo el corte de la zanja a mano a fin de evitar daños en las instalaciones existentes habiendoce realizado entibaciones para evitar derrumbe de las zanjas excavadas, en tramos donde no existia instalaciones se utilizo maquinaria pesada (retroexcavadora) para aperturar la zanja.
una vez realizada el refine de fondo de la zanja, se utilizo material granular ( piedra chancada de 1/2") como cama de apoyo para la tuberia instalada
se procedio a la selección del terreno, que se utilizo como primer relleno, habiendoce ejecutado este en capas de 15 cm de altura realizandoce la compactacion manual hasta una altura de 60 cm, luego se procedio a realizar el segundo relleno habiendoce utilizado apisonadores tipo pison (compactador canguro)
se elimino una parte del material exedente con maquinaria alquilada, el restante se procedio con apoyo de la municipalidad Distrital de San Sebastian
se utilizo tuberia de PVC con union flexible clase 10 de 90 mm de diametro según norma de fabricacion ISO 4422, con anillo elastomerico, según lo especificado en el expediente tecnico aprobado, habiendoce puesto especial cuidado en el transporte manipuleo evitando ser golpeado y/o arrastrado, el almacenamiento se ralizo en un lugar alquilado bajo techo y ventilcion natural.
las valvulas usadas son de tipo compuerta HD ISO 7259 de 90 mm de diametro según especificado en el expediente tecnico aprobado
para la ejecucion de la prueba hidraulica, se procedio a instalar el balde de prueba con el manometro en el extremo mas bajo del tramo de prueba, una vez taponado los extremos del tramo sometido a la prueba, se realizo el llenado de la red con agua , luego se procedio con el bombeo a travez del valde de prueba en las presiones de 50, 80, 100, 150 psi, se purgo el aire atrapado en la red , luego de llegar a la presion de prueba (1.5 veces la presion de trabajo), se procedio a comprobar la impermeabilidad del tramo observando las posibles variaciones en el manometro durante 1 hora de prueba, lo cual no se tuvo variaciones y se procedio a dar el visto buebo por parte del supervisor y su posterior firmado de los protocolos de calidad.
luego de ejecutar la instalacion de las diferentes tuberias, accesorios y valvulas con la aprobacion de la supervision de obra, se procedio a la puesta de operación del sistema
EL PROYECTISTA EN LA PARTIDA DE EXCAVACION DE ZANJAS PARA LA INSTALACION DE LA TUBERIA CONCIDERA LA UNIDAD EN METROS CUBICOS Y NO EN METROS LINEALES.
VALORIZACION DE AVANCE DE OBRA
PRINCIPAL
MES NOVIEMBRE 2013OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”
MONTO DE OBRA S/. 102,944.52 REGION : CUSCOMONTO ASIGNADO S/. 102,944.52 DEPARTAMENTO : CUSCOFECHA DE INICIO DE OBRA 11/19/2013 PROVINCIA : CUSCOPLAZO DE EJECUCIÓN 60 DIAS DISTRITO : SAN SEBASTIANFECHA DE TERMINO 1/18/2014 LOCALIDAD A.P.V. TRABAJADORES DE CORPAC
FECHA DE PRESENTACIÓN:
PARTIDA DESCRIPCION UNIDAD
PRESUPUESTO PROGRAMADO AVANCESSALDO
METRADOP. UNIT. PRESUP. P. TOTAL ANTERIOR ACTUAL ACUMULADO
S/. S/. S/. Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado01.00.00 OBRAS PROVISIONALES SISTEMA DE AGUA
01.01.00 Construccion de Oficina, Almacen y Guardiania M2 50.00 81.85 4,092.50 4092.5 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 50.00 01.02.00 Energia Electrica Provisional GLB 1.00 500.00 500.00 500.00 0.00 - 0.00% 1.00 500.00 100.00% 1.00 500.00 100.00% - 01.03.00 Puentes Peatonales de Madera UND 20.00 19.47 389.40 389.4 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 20.00 01.04.00 Tranqueras de Madera Para Desvio Vehicular UND 8.00 29.37 234.96 234.96 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 8.00 01.05.00 Cartel de Identificacion de Obra UND 1.00 593.93 593.93 593.93 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 1.00 01.06.00 Limpieza de Obra M2 1,383.26 0.95 1,314.10 1,314.10 0.00 - 0.00% 1,383.26 1,314.10 100.00% 1,383.26 1,314.10 100.00% - 01.07.00 Cinta de seguridad M 1,831.38 0.50 915.69 915.69 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 1,831.38
02.00.00 TRABAJOS PRELIMINARES
02.01.00 Limpieza de Terreno Manual M2 1,383.26 0.95 1,314.10 1,314.10 - 0.00% 1,383.26 1,314.10 100.00% 1,383.26 1,314.10 100.00% -
03.00.00 REDES DE DISTRIBUCION
03.01.00 TRABAJOS PRELIMINARES
03.01.01 Trazo Nivelacion y Replanteo M2 549.41 1.35 741.70 741.70 0.00 - 0.00% 549.41 741.70 100.00% 549.41 741.70 100.00% - 03.01.02 Trazo Nivelacion y Replanteo Durante el Proceso M2 549.51 1.07 587.98 587.98 0.00 - 0.00% 549.51 587.98 100.00% 549.51 587.98 100.00% -
03.02.00 MOVIMIENTO DE TIERRAS
03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 366.28 21.68 7,940.95 7,940.95 0.00 - 0.00% 366.28 7,940.95 100.00% 366.28 7,940.95 100.00% - 03.02.02 Perfilado de zanjas M 915.69 0.63 576.88 576.88 0.00 - 0.00% 915.69 576.88 100.00% 915.69 576.88 100.00% - 03.02.03 Cama de apoyo para tuberias E=0.10m M3 54.94 59.00 3,241.46 3,241.46 - 0.00% 54.94 3,241.46 100.00% 54.94 3,241.46 100.00% - 03.02.04 Relleno y compactado con material propio M3 219.77 18.07 3,971.24 3,971.24 0.00 - 0.00% 219.77 3,971.24 100.00% 219.77 3,971.24 100.00% - 03.02.05 Eliminacion y acarreo de material exedente M3 114.46 14.51 1,660.81 1,660.81 0.00 - 0.00% 114.46 1,660.81 100.00% 114.46 1,660.81 100.00% - 03.02.06 Entibado y apuntalamiento de zanjas H>2.5m M 90.00 17.02 1,531.80 1,531.80 0.00 - 0.00% 90.00 1,531.80 100.00% 90.00 1,531.80 100.00% -
03.03.00 TUBERIAS
03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 915.69 10.48 9,596.43 9,596.43 0.00 - 0.00% 915.69 9,596.43 100.00% 915.69 9,596.43 100.00% -
03.04.00 SUMINISTRO Y COLOCACION DE ACCESORIOS Y VALVULAS03.04.01 Suministro y colocacion de valvula de purga 90mm en red de distribucion PZA 1.00 843.99 843.99 843.99 0.00 - 0.00% 1.00 843.99 100.00% 1.00 843.99 100.00% - 03.04.02 Suministro y colocacion de valvula de compuerta de 90mm en red de distribucion PZA 2.00 674.59 1,349.18 1,349.18 - 0.00% 2.00 1,349.18 100.00% 2.00 1,349.18 100.00% -
03.05.00 PRUEBA HIDRAULICA
03.05.01 Prueba hidraulica en tuberias GLB 1.00 450.59 450.59 450.59 0.00 - 0.00% 1.00 450.59 100.00% 1.00 450.59 100.00% - 03.05.02 Desinfeccion en tuberias M 915.69 0.16 146.51 146.51 0.00 - 0.00% 915.69 146.51 100.00% 915.69 146.51 100.00% -
03.06.00 VARIOS
03.06.01 Reposicion de conexiones de agua UND 21.00 221.12 4,643.52 4,643.52 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 21.00 03.06.02 Demolicion y reposicion de pavimento M2 50.00 98.47 4,923.50 4,923.50 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 50.00 03.06.03 Puesta en operación del sistema de agua GLB 1.00 277.40 277.40 277.40 - 0.00% 1.00 277.40 100.00% 1.00 277.40 100.00% -
COSTO DIRECTO 51,838.62 0.0 0.00% 36,045.1 69.53% 36,045.1 69.53%0.6829368 GASTOS GENERALES 68.29 % 35,402.50 0.00 24,616.54 24,616.54
0.18 IMPUESTO IGV 18% 15,703.40 0.00 10,919.10 10,919.10PRESUPUESTO TOTAL 102,944.52 0.0 0.00% 71,580.77 69.53% 71,580.77 69.53%
VALORIZACION DE AVANCE DE OBRA
ADICIONALES - POR MAYORES METRADOS
MES NOVIEMBRE 2013OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”
MONTO DE OBRA S/. 102,944.52 REGION : CUSCOMONTO ASIGNADO S/. 102,944.52 DEPARTAMENTO : CUSCOFECHA DE INICIO DE OBRA 11/19/2013 PROVINCIA : CUSCOPLAZO DE EJECUCIÓN 60 DIAS DISTRITO : SAN SEBASTIANFECHA DE TERMINO 1/18/2014 LOCALIDAD A.P.V. TRABAJADORES DE CORPAC
FECHA DE PRESENTACIÓN:
PARTIDA DESCRIPCION UNIDAD
PRESUPUESTO PROGRAMADO AVANCESSALDO
METRADOP. UNIT. PRESUP. P. TOTAL ANTERIOR ACTUAL ACUMULADO
S/. S/. S/. Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado03.02.00 MOVIMIENTO DE TIERRAS
03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 31.72 21.68 687.75 687.75 0.00 - 0.00% 31.72 687.75 100.00% 31.72 687.75 100.00% -
03.02.02 Perfilado de zanjas M 44.06 0.63 27.76 27.76 0.00 - 0.00% 44.06 27.76 100.00% 44.06 27.76 100.00% -
03.02.03 Cama de apoyo para tuberias E=0.10m M3 2.64 59.00 155.97 155.97 0.00 - 0.00% 2.64 155.97 100.00% 2.64 155.97 100.00% -
03.02.04 Relleno y compactado con material propio M3 13.50 18.07 243.95 243.95 0.00 - 0.00% 13.50 243.95 100.00% 13.50 243.95 100.00% -
03.03.00 TUBERIAS
03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 44.06 10.48 461.75 461.75 0.00 - 0.00% 44.06 461.75 100.00% 44.06 461.75 100.00% -
03.05.00 PRUEBA HIDRAULICA
03.05.01 Prueba hidraulica en tuberias GLB 1.00 450.59 450.59 450.59 0.00 - 0.00% 1.00 450.59 100.00% 1.00 450.59 100.00% -
COSTO DIRECTO 2,027.77 0.00 0.00% 2,027.77 100.00% 2,027.77 100.00%
VALORIZACION DE AVANCE DE OBRA
ADICIONALES - POR NUEVAS PARTIDAS
MES NOVIEMBRE 2013OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”
MONTO DE OBRA S/. 102,944.52 REGION : CUSCOMONTO ASIGNADO S/. 102,944.52 DEPARTAMENTO : CUSCOFECHA DE INICIO DE OBRA 10/1/2012 PROVINCIA : CUSCOPLAZO DE EJECUCIÓN 210 DIAS DISTRITO : CUSCOFECHA DE TERMINO 4/28/2013 LOCALIDAD : SANTA ANA - JARDINES DEL INCA
FECHA DE PRESENTACIÓN:
PARTIDA DESCRIPCION UNIDAD
PRESUPUESTO PROGRAMADO AVANCESSALDO
METRADOP. UNIT. PRESUP. P. TOTAL ANTERIOR ACTUAL ACUMULADO
S/. S/. S/. Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado
0.00 - 0.00 0.00 - - -
COSTO DIRECTO 0.00 0.00 0.00 0.00
VALORIZACION DE AVANCE DE OBRA
PRINCIPAL
4/21/2023
SALDO
Valorizado S/. %
4,092.50 100.00% - 0.00% 389.40 100.00% 234.96 100.00% 593.93 100.00% - 0.00% 915.69 100.00%
- 0.00%
- 0.00% - 0.00%
- 0.00% - 0.00% - 0.00% - 0.00% - 0.00% - 0.00%
- 0.00%
- 0.00% - 0.00%
- 0.00% - 0.00%
4,643.52 100.00% 4,923.50 100.00% - 0.00%
15,793.50 30.47%10,785.964,784.3031,363.77 30.47%
VALORIZACION DE AVANCE DE OBRA
ADICIONALES - POR MAYORES METRADOS
4/21/2023
SALDO
Valorizado S/. %
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
0.00 0.00%
VALORIZACION DE AVANCE DE OBRA
ADICIONALES - POR NUEVAS PARTIDAS
4/21/2023
SALDO
Valorizado S/. %
-
0.00
VALORIZACION DEDUCTIVOSMES DICIEMBRE 2013
OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”
PARTIDA DESCRIPCION
PRESUPUESTO
UNIDAD METRADOP. UNIT.
S/.01.00.00 OBRAS PROVISIONALES SISTEMA DE AGUA
01.01.00 Construccion de Oficina, Almacen y Guardiania M2 50.00 81.85 01.03.00 Puentes Peatonales de Madera UND 20.00 19.47 01.04.00 Tranqueras de Madera Para Desvio Vehicular UND 8.00 29.37 01.05.00 Cartel de Identificacion de Obra UND 1.00 593.93 01.07.00 Cinta de seguridad M 1,831.38 0.50
03.06.00 VARIOS
03.06.01 Reposicion de conexiones de agua UND 21.00 221.12 03.06.02 Demolicion y reposicion de pavimento M2 50.00 98.47
COSTO DIRECTO
0.6829368 GASTOS GENERALES 68.29 %
0.18 IMPUESTO IGV 18%PRESUPUESTO TOTAL
VALORIZACION DEDUCTIVOS
“CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”
PRESUPUESTO
P. TOTAL
S/.
4092.5389.4234.96593.93915.69
4,643.524,923.50
15,793.5010,785.964,784.3031,363.77
PLANILLA DE METRADOS OBRA PRINCIPAL
PROYECTO: “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”
ITEM DESCRIPCION UND METRADO ANTERIOR ACTUAL ACUMULADOM M J V S D L M M J V S
19 20 21 22 23 24 25 26 27 28 29 30 TOTAL
01.00.00 OBRAS PROVISIONALES SISTEMA DE AGUA
01.01.00 Construccion de Oficina, Almacen y Guardiania M2 50.00 0.00 0.00 0.00 0.0001.02.00 Energia Electrica Provisional GLB 1.00 1 1.00 0.00 1.00 1.0001.03.00 Puentes Peatonales de Madera UND 20.00 0.00 0.00 0.00 0.0001.04.00 Tranqueras de Madera Para Desvio Vehicular UND 8.00 0.00 0.00 0.00 0.0001.05.00 Cartel de Identificacion de Obra UND 1.00 0.00 0.00 0.00 0.0001.06.00 Limpieza de Obra M2 1,383.26 725.4 657.86 1,383.26 0.00 1383.26 1383.2601.07.00 Cinta de seguridad M 1,831.38 0.00 0.00 0.00 0.00
02.00.00 TRABAJOS PRELIMINARES
02.01.00 Limpieza de Terreno Manual M2 1383.26 420 380 405 178.26 1,383.26 0.00 1383.26 1383.26
03.00.00 REDES DE DISTRIBUCION
03.01.00 TRABAJOS PRELIMINARES
03.01.01 Trazo Nivelacion y Replanteo M2 549.41 120 80 180 169.41 549.41 0.00 549.41 549.4103.01.02 Trazo Nivelacion y Replanteo Durante el Proceso M2 549.51 220 180 149.51 549.51 0.00 549.51 549.51
03.02.00 MOVIMIENTO DE TIERRAS
03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 366.28 80.5 70.8 88.5 66.5 59.98 366.28 0.00 366.28 366.2803.02.02 Perfilado de zanjas M 915.69 220 280 180 130 105.69 915.69 0.00 915.69 915.6903.02.03 Cama de apoyo para tuberias E=0.10m M3 54.94 11 10.5 12 11.44 10 54.94 0.00 54.94 54.9403.02.04 Relleno y compactado con material propio M3 219.77 44.5 43.5 46 43 42.77 219.77 0.00 219.77 219.7703.02.05 Eliminacion y acarreo de material exedente M3 114.46 30 15 45 24.46 114.46 0.00 114.46 114.4603.02.06 Entibado y apuntalamiento de zanjas H>2.5m M 90.00 28 25 26 11 90.00 0.00 90.00 90.00
03.03.00 TUBERIAS
03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 915.69 220 195 210 150.5 140.19 915.69 0.00 915.69 915.69
03.04.00 SUMINISTRO Y COLOCACION DE ACCESORIOS Y VALVULAS
03.04.01 Suministro y colocacion de valvula de purga 90mm en red de distribucion PZA 1.00 1 1.00 0.00 1.00 1.0003.04.02 Suministro y colocacion de valvula de compuerta de 90mm en red de distribucion PZA 2.00 1 1 2.00 0.00 2.00 2.00
03.05.00 PRUEBA HIDRAULICA
03.05.01 Prueba hidraulica en tuberias GLB 1.00 1 1.00 0.00 1.00 1.0003.05.02 Desinfeccion en tuberias M 915.69 915.69 915.69 0.00 915.69 915.69
03.06.00 VARIOS
03.06.01 Reposicion de conexiones de agua UND 21.00 0.00 0.00 0.00 0.0003.06.02 Demolicion y reposicion de pavimento M2 50.00 0.00 0.00 0.00 0.0003.06.03 Puesta en operación del sistema de agua GLB 1.00 1 1.00 0.00 1.00 1.00
PLANILLA DE METRADOSPARTIDAS ADICIONALES - POR MAYORES METRADOS
PROYECTO: “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”
ITEM DESCRIPCION UND METRADO ANTERIOR ACTUAL ACUMULADOM M J V S D L M M J V S
19 20 21 22 23 24 25 26 27 28 29 30 TOTAL
03.02.00 MOVIMIENTO DE TIERRAS
03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 31.72 31.723 31.72 0.00 31.72 31.7203.02.02 Perfilado de zanjas M 44.06 44.06 44.06 0.00 44.06 44.0603.02.03 Cama de apoyo para tuberias E=0.10m M3 2.64 2.6436 2.64 0.00 2.64 2.6403.02.04 Relleno y compactado con material propio M3 13.50 13.5 13.50 0.00 13.50 13.50
03.03.00 TUBERIAS
03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 44.06 44.06 44.06 0.00 44.06 44.06
03.05.00 PRUEBA HIDRAULICA
03.05.01 Prueba hidraulica en tuberias GLB 1.00 1 1.00 0.00 1.00 1.00
PLANILLA DE METRADOSPARTIDAS ADICIONALES - POR MAYORES METRADOS NUEVAS PARTIDAS
PROYECTO: “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”
ITEM DESCRIPCION UND METRADO ANTERIOR ACTUAL ACUMULADOL M M J V S D L M M J V
12 13 14 15 16 17 18 19 20 21 22 23 TOTAL
0.00 0.00 0.00 0.00
PLANILLA DE METRADOS OBRA PRINCIPAL
SALDO
CANT %
50.00 100.00%0.00 0.00%
20.00 100.00%8.00 100.00%1.00 100.00%0.00 0.00%
1831.38 100.00%
0.00 0.00%
0.00 0.00%0.00 0.00%
0.00 0.00%0.00 0.00%0.00 0.00%0.00 0.00%0.00 0.00%0.00 0.00%
0.00 0.00%
0.00 0.00%0.00 0.00%
0.00 0.00%0.00 0.00%
21.00 100.00%50.00 100.00%0.00 0.00%
PLANILLA DE METRADOSPARTIDAS ADICIONALES - POR MAYORES METRADOS
SALDO
CANT %
0.00 0.00%0.00 0.00%0.00 0.00%0.00 0.00%
0.00 0.00%
0.00 0.00%
PLANILLA DE METRADOSPARTIDAS ADICIONALES - POR MAYORES METRADOS NUEVAS PARTIDAS
SALDO
CANT %
0.00
METAS DE AVANCE DE OBRA
PARTIDA DESCRIPCION UNIDAD ACTUAL ACUMULADO
% %01.00.00 OBRAS PROVISIONALES SISTEMA DE AGUA
01.01.00 Construccion de Oficina, Almacen y Guardiania M2 0.00% 0.00%01.02.00 Energia Electrica Provisional GLB 100.00% 100.00%01.03.00 Puentes Peatonales de Madera UND 0.00% 0.00%01.04.00 Tranqueras de Madera Para Desvio Vehicular UND 0.00% 0.00%01.05.00 Cartel de Identificacion de Obra UND 0.00% 0.00%01.06.00 Limpieza de Obra M2 100.00% 100.00%01.07.00 Cinta de seguridad M 0.00% 0.00%
02.00.00 TRABAJOS PRELIMINARES
02.01.00 Limpieza de Terreno Manual M2 100.00% 100.00%
03.00.00 REDES DE DISTRIBUCION
03.01.00 TRABAJOS PRELIMINARES
03.01.01 Trazo Nivelacion y Replanteo M2 100.00% 100.00%03.01.02 Trazo Nivelacion y Replanteo Durante el Proceso M2 100.00% 100.00%
03.02.00 MOVIMIENTO DE TIERRAS
03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 100.00% 100.00%03.02.02 Perfilado de zanjas M 100.00% 100.00%03.02.03 Cama de apoyo para tuberias E=0.10m M3 100.00% 100.00%03.02.04 Relleno y compactado con material propio M3 100.00% 100.00%03.02.05 Eliminacion y acarreo de material exedente M3 100.00% 100.00%03.02.06 Entibado y apuntalamiento de zanjas H>2.5m M 100.00% 100.00%
03.03.00 TUBERIAS
03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 100.00% 100.00%
03.04.00 SUMINISTRO Y COLOCACION DE ACCESORIOS Y VALVULAS
03.04.01 Suministro y colocacion de valvula de purga 90mm en red de distribucion PZA 100.00% 100.00%03.04.02 Suministro y colocacion de valvula de compuerta de 90mm en red de distribucion PZA 100.00% 100.00%
03.05.00 PRUEBA HIDRAULICA
03.05.01 Prueba hidraulica en tuberias GLB 100.00% 100.00%03.05.02 Desinfeccion en tuberias M 100.00% 100.00%
03.06.00 VARIOS
03.06.01 Reposicion de conexiones de agua UND 0.00% 0.00%03.06.02 Demolicion y reposicion de pavimento M2 0.00% 0.00%03.06.03 Puesta en operación del sistema de agua GLB 100.00% 100.00%
METAS DE AVANCE DE OBRA
SALDO
%
100.00%0.00%
100.00%100.00%100.00%0.00%
100.00%
0.00%
0.00%0.00%
0.00%0.00%0.00%0.00%0.00%0.00%
0.00%
0.00%0.00%
0.00%0.00%
100.00%100.00%0.00%
RESUMEN DE EJECUCION PRESUPUESTAL
OBRA : “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”F. DE FINANCIAMIENTO : RECURSOS PROPIOS
Nº TIPO DE DOCUMNETO NUMERO DESCRIPCION
COMPRAS1 B/V 36632 COMPRA DE TUBERIA Y ACCESORIOS PARA LA INSTALACION DE AGUA POTABLE 9306.152 B/V 4941 MATERIAL DE FILTRO (CONFITILLO) 250.003 B/V 17012 LUBRICANTE PARA TUBERIA 38.004 PROFORMA 1 CORDEL NYLON 11.005 B/V 4390 SOGA DRIZA 40.006 GASOHOL 44.007 B/V 4950 MATERIAL DE FILTRO (CONFITILLO) 150.008 B/V 4524 BOTAS DE JEBE 36.009 B/V 1239 MATERIAL DE FILTRO (CONFITILLO) 550.00
10 B/V 481 MATERIAL DE FILTRO (CONFITILLO) 250.0011 NOTA PEDIDO 1072 MADERAMEN PARA ENTIBADOS 131.0012 B/V 4399 VARIOS 9.00
B/V MATERIAL DE FILTRO (PIEDRA CHANCADA DE 1/2") 975.0013 B/V 225 GRASA Nº3 VISTONY 20.0014 B/V 1240 VARIOS 18.0015 B/V 483 MATERIAL DE FILTRO (CONFITILLO) 250.0016 B/V 10282 LLAVE CHECK 30.0017 B/V 10281 BOTAS DE JEBE 22.0018 B/V 10286 CEMENTO 24.0019 GASOHOL 50.0020 B/V 9189 VARIOS 56.0021 B/V 1308 MATERIAL DE FILTRO (CONFITILLO) 275.0022 B/V 1028 MANGUERA DE 3/4" 36.0023 B/V 36746 COMPRA DE TUBERIA Y ACCESORIOS PARA LA INSTALACION DE AGUA POTABLE 4907.3024 B/V 36745 ACCESORIOS PARA LA INSTALACION DE AGUA POTABLE 160.0025 B/V 1311 MATERIAL DE FILTRO (CONFITILLO) 275.0026 B/V 1310 MATERIAL DE FILTRO (CONFITILLO) 275.0027 B/V 1309 MATERIAL DE FILTRO (CONFITILLO) 110.0028 B/V CINTA TEFLON 1.5029 B/V 36878 UNION DE REPARACION 20.0030 B/V 36883 ACCESORIOS PARA LA INSTALACION DE AGUA POTABLE 99.5031 B/V 492 MATERIAL DE FILTRO (CONFITILLO) Y CEMENTO 104.0032 B/V 10316 VARIOS (ALQUILER DE LOCALES PARA ALMACENES ENTRE OTROS) 4254.5033 B/V 10339 WINCHA DE 50 MTS 22.00
SUB TOTAL 22799.95
CARGA DE PERSONAL1 NINGUNA MOVILIDAD (PASAJES) 49.002 NINGUNA LEVANTAMIENTO DE OBSERVACIONES EXPEDIENTE TECNICO 3000.003 NINGUNA SERVICIOS DE MANO DE OBRA 1000.004 NINGUNA SERVICIOS DE MANO DE OBRA 700.005 NINGUNA COSTO POR MANO DE OBRA EN LAS FAENAS 26400.006 NINGUNA SERVICIOS DE MANO DE OBRA 1700.00
SUB TOTAL 32849.00
SERVICIO POR TERCEROS1 NOTA DE ENTREGA 81 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 550.002 NOTA DE ENTREGA 82 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 600.003 NOTA DE ENTREGA 83 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 700.004 NOTA DE ENTREGA 85 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 1100.005 NOTA DE ENTREGA 86 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 700.006 NOTA DE ENTREGA 87 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 1070.007 ELIMINACION DE MATERIAL EXEDENTE CON MAQUINARIA ALQUILADA 2135.828 TARBAJOS DE TOPOGRAFIA 2000.009 B/V 3 ALQUILER DE MAQUINARIA LIVIANA 660.00
SUB TOTAL 9515.82
TOTAL
IMPORTE PARCIAL
RESUMEN DE EJECUCION PRESUPUESTAL
: “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”
TOTAL
22799.95
32849.00
9515.82
65164.77