53
2014 Vazquez Borragan, Alejandro Master Thesis 10/4/2014 Modelling Internal Erosion Within An Embankment Dam Prior To Breaching

Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

Embed Size (px)

Citation preview

Page 1: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

2014

Vazquez Borragan, Alejandro

Master Thesis

10/4/2014

Modelling Internal Erosion Within An Embankment Dam

Prior To Breaching

Page 2: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

1

Modelling Internal Erosion Within An Embankment Dam Prior To Breaching

M. A. Vazquez ([email protected] , 850323-3432)

KTH Royal Institute of Technology, Stockholm, SWEDEN.

October 2014

ABSTRACT

There are still uncertainties in the safety of existing embankment dams. For instance, the majority of

embankment dams in Sweden were built between 1950s and 1970s, designed and constructed to

standards that might be unacceptable nowadays. Particularly, Vattenfall’s records stated that 40%

owned embankments dams developed sinkholes (Nilsson, 1999). Moreover, internal erosion and its

failure mechanisms of initiation and development are still not fully understood (Bowles et al., 2013).

Also, internal threats are difficult to detect and interpret even using new instrumentation

techniques. The aim of this Master Thesis is to identify failure mechanisms of embankment dams

prior to breaching and hence, verify the reliability of a risk analysis after the breaching of the dam.

The methodology consisted of monitoring an embankment dam prone to fail by internal erosion

mechanisms. Finally the results were modelled using FEM to identify the risk of internal erosion prior

to breaching.

Key words: Internal erosion, numerical modelling, monitoring, embankment dam, risk analysis,

breaching, piping, glacial till, rock-fill, Global Backward Erosion, stress analysis, seepage,

instrumentation, piezometers, laser scanner, deformations, filter, hyperbolic model.

Page 3: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

2

“Sometimes…

Barriers are created with a retaining function.

However, by nature some retained parts react,

finding the mechanisms to get its freedom back.

Meaning that, a wall can be defeated in its action.

…a failure can also be a Victory”.

-Alejandro Vazquez

“A veces…

Las barreras se crean con fines de retención.

Sin embargo, por naturaleza las partes contenidas reaccionan,

Hallando los mecanismos que las liberan.

Significando que, se puede vencer al muro en su acción.

…un fallo también puede ser una Victoria”.

-Alejandro Vázquez.

Page 4: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

3

ACKOWLEDGEMENT

First of all, I would like thank Johan Lagerlund, who has acted on behalf of Vattenfall Vattekraft and Vattenfall

R&D to put his confidence on my skills and knowledge. I really appreciate the interest, time and effort he

invested, which it has greatly helped to the success of this Master Thesis, and also to my professional

development. I am also very pleased with all the members of the staff working at the Vattenfall R&D facilities

in Älvkarleby, especially with Martin Rosenqvist, James Yang and Pelle Enegren(Master Thesis student), who

showed a great interest and support during the performance of the experiments. Second of all, I would like to

thank Stefan Larsson (KTH), especially, for all the advice provided to perform the academic writing and

orientation to accomplish this Master Thesis, but also for being the link between Vattenfall and the university.

Finally, and not for that the least importance, I wish to thank first my brother for his unconditional support;

and to my friends for their support and motivation.

P.D: This work is dedicated to those who unfortunately I am not able to say thank you physically: {Maria Pilar

Vazquez Borragan (Susana, mother) (1955-2008)}, {Eugenio Vazquez Añon (Abuelo, grandfather)(1912-2009}.

Alejandro Vazquez Borragan

Stockholm, Sweden. 2014

Sponsors:

Page 5: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

4

Contents

ABSTRACT ................................................................................................................................................ 1

ACKOWLEDGEMENT ............................................................................................................................... 3

INTRODUCTION ....................................................................................................................................... 7

State-of-art and limitations ................................................................................................................. 7

Summary ............................................................................................................................................. 9

METHODOLOGY ...................................................................................................................................... 9

Dam design and materials properties ............................................................................................... 10

Building the dam ............................................................................................................................... 11

Instrumentation ................................................................................................................................ 14

Soil testing ......................................................................................................................................... 14

Monitoring ........................................................................................................................................ 14

Failure Mode Analysis ....................................................................................................................... 16

Dam Failure ....................................................................................................................................... 20

RESULTS ................................................................................................................................................ 22

Dam design ....................................................................................................................................... 22

Slope stability analysis .................................................................................................................. 22

Monitoring and modelling internal erosion ..................................................................................... 24

Seepage monitoring ...................................................................................................................... 24

Built model (SVFlux) ...................................................................................................................... 25

Deformation monitoring ............................................................................................................... 27

Built model (SVSolid) ..................................................................................................................... 29

Internal erosion factors ..................................................................................................................... 30

Material susceptibility ................................................................................................................... 30

Hydraulic load ............................................................................................................................... 33

Critical stress condition ................................................................................................................. 36

Failure mode analysis (Critical zones) ............................................................................................... 40

Dam failure ........................................................................................................................................ 41

DISCUSSION ........................................................................................................................................... 46

Summary of the experimental results .............................................................................................. 46

Summary of the results from the analysis of the internal erosion factors ....................................... 46

Failure Mode Analysis ....................................................................................................................... 47

Dam failure and event tree (Hypothesis verified) ............................................................................ 48

Conclusion ......................................................................................................................................... 48

Page 6: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

5

REFERENCES .......................................................................................................................................... 50

Figure 1. Dam, viewpoint from downstream side ................................................................................ 10

Figure 2. Sequence of the experimentation ......................................................................................... 10

Figure 3. Design Model (GBE developed) ............................................................................................. 11

Figure 4. Layering sequences ................................................................................................................ 12

Figure 5. Installation of piezometers in the core .................................................................................. 13

Figure 6. Installation of piezometers top view ..................................................................................... 13

Figure 7. No filter at the crest ............................................................................................................... 13

Figure 8. Vertical pipe ........................................................................................................................... 13

Figure 9. No erosion protection on top ................................................................................................ 13

Figure 10. Grain size distribution .......................................................................................................... 14

Figure 11. Hydraulic conductivity test .................................................................................................. 14

Figure 12. Piezometers ......................................................................................................................... 15

Figure 13. Weir and pressure sensor inside the water tank ................................................................. 15

Figure 14. Turbidity meter .................................................................................................................... 15

Figure 15. Laser scanner 3D .................................................................................................................. 15

Figure 16. Venn Diagram, from (ICOLD, 2013). ..................................................................................... 16

Figure 17 Failure mode analysis ............................................................................................................ 17

Figure 18. FOS Empty reservoir (upstream) .......................................................................................... 22

Figure 19. FOS empty reservoir (downstream) ..................................................................................... 22

Figure 20. FOS full reservoir (upstream) ............................................................................................... 23

Figure 21. Rapid drawdawn .................................................................................................................. 23

Figure 22. Monitoring results (Core). .................................................................................................... 25

Figure 23. Monitoring results (Filter). ................................................................................................... 25

Figure 24. SVFlux results (Core). ........................................................................................................... 26

Figure 25. SVFlux results (Filter). .......................................................................................................... 26

Figure 26. Deformations monitored downstream (point of view from upstream) .............................. 28

Figure 27. Deformations monitored upstream (point of view from upstream) ................................... 28

Figure 28. Deformation monitored upstream and downstream (point of view from downstream). .. 29

Figure 29. BUILT MODEL-SVSolid deformation results ......................................................................... 29

Figure 30. Comparison results SVSolid, DAM vs BUILT MODEL ............................................................ 30

Figure 31. Grain size distribution .......................................................................................................... 31

Figure 32. Filter Internal stability .......................................................................................................... 32

Figure 33. Core internal stability ........................................................................................................... 32

Figure 34. Pipe internal stability ........................................................................................................... 32

Figure 35. Pore-water pressure (kPa) ................................................................................................... 34

Figure 36. Hydraulic gradients .............................................................................................................. 34

Figure 37. Water head (m) .................................................................................................................... 35

Figure 38. Pressure head (m) ................................................................................................................ 35

Figure 39. Seepage velocity (m/s) ......................................................................................................... 36

Figure 40. Total stress Sy (kPa) .............................................................................................................. 37

Figure 41. XY Displacements (m) .......................................................................................................... 37

Figure 42. Vertical effective stresses (kPa) ........................................................................................... 38

Page 7: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

6

Figure 43. XY Shear stresses (kPa) ........................................................................................................ 38

Figure 44. X total stresses (kPa) ............................................................................................................ 39

Figure 45. Y total stresses (kPa) ............................................................................................................ 39

Figure 46. Total minimum principle stress (S3) (kPa) ............................................................................ 40

Figure 47. Local Factor of Safety ........................................................................................................... 40

Figure 48 Critical zones of failure mode analysis ................................................................................. 41

Figure 49. Turbidity ............................................................................................................................... 42

Figure 50. Seepage flow, 10 days (Manual readings) ........................................................................... 42

Figure 51. Seepage flow at day 10 (Thomson weir) .............................................................................. 43

Figure 52. Pore-water pressure at day 10............................................................................................. 43

Figure 53. Acoustic emissions, day 10. ................................................................................................. 44

Figure 54. Dam Failure .......................................................................................................................... 45

Figure 55. Event tree of dam failure ..................................................................................................... 48

Page 8: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

7

INTRODUCTION

In Sweden, there are two thousand dams providing 65% of the energy demand, most of them are embankment dams. However, some of these 120 large embankment dams are classified as class 1, 2 and 3 (Kraftnät, 2011) .This means that if a failure may occur, these dams would suppose a risk for people´s life and may cause severe economic damages. Even though, failures of embankment dams along the history of this country have not caused any exceptional consequences (Ekström, 2012), there are still uncertainties in the safety of these dams regarding to internal erosion. For instance, the majority of the dams were built between 1950s and 1970s, designed and constructed to standards that might be unacceptable nowadays. Particularly, Vattenfall’s records stated that 40% owned embankments dams developed sinkholes due to internal erosion (Nilsson, 1999) Furthermore, internal threats are difficult to detect and interpret even using new instrumentation techniques. Perhaps, due to the combination of these uncertainties and the state-of-art in the assessment of internal erosion, justify somehow, why approaches in the Swedish dam safety guidelines, RIDAS (2011), are considering conservative assumptions derived from the consequences of this phenomenon, e.g., extreme leakages, instead of assessing the factors of internal erosion within the dam. The results of the assessments with those assumptions usually imply costs of design and construction of new downstream berms, which may not protect the weakest part of the dam against internal erosion (the crest), and may cause associated risks from the new construction. However, why not facing internal erosion firstly, and see if there is any likelihood to occur? In connection to the last question, the aim of this Master Thesis was to face internal erosion before the consequences. The approach was to identify failure mechanisms of embankment dams prior to breaching, and hence verify the reliability of a failure mode analysis after the breaching. Initially, after the literature review, a hypothesis was set as: “If there is internal erosion within the dam, it is possible to analyse the factors that initiate the failure mechanisms, and thus, assessing the safety of the dam prior to breaching”. Later on, in the experimentation phase, the methodology consisted of monitoring a small embankment dam prone to fail by internal erosion mechanisms, whereas, Finite element models (FEM) were implemented to analyse the likelihood of internal erosion prior to breaching. Finally, the hypothesis was verified when the failure mode analysis pointed out the same location where the dam failed in the experiment. This project is the first research project of a program to study the safety of dams funded by

Vattenfall Vattenkraft. It took place at Vattenfall Research and Development in Älvkarleby where a

new infrastructure for the embankment dam was installed for this purpose.

State-of-art and limitations Internal erosion, by definition, occurs when particles within an embankment or its foundation are carried downstream by seepage flow. It can initiate by concentrated leaks, backward erosion, contact erosion and suffusion (ICOLD, 2013). Even though the problem is known from times of the romans, it was not until the 1970s, when the famous Teton’s dam accident occurred (Solava, 2003), when actually internal erosion was considered a main dam safety issue. This phenomenon has been faced from different perspectives by many authors. Most of the approaches to assess internal erosion have been classified in this literature review in: 1) Hydraulic gradient and grain size of the soils; 2) Dam breach; 3) Surveillance 4) Failure mechanisms and internal erosion factors. 1) Hydraulic gradient and grain size of the soils As Schmertmann (2002) discussed, internal erosion was initially investigated by looking at hydraulic gradients (Bligh, 1910 and Lane, 1935). Later approaches analysed tractive forces of seepage through soil grains (Terzaghi & Peck, 1948 and Sherard & Woodward, 1963). By looking at the particle size distributions of soils it was determined the efficiency of the filters. Sherard (1979) and

Page 9: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

8

Terzaghi (1996) made extended experimentation. These investigations developed the filter criteria, which determine if the filters are capable to stop the transport of particles from the core. Meanwhile, experimentation of Skempton (1994) proofed that certain soils may develop internal erosion even at lower hydraulic gradients than Terzaghi critical gradient, gaining more importance the grain size distributions of the soils. Thus, other investigations combined internal stability analysis, such as Kenny and Lau (1985), and probabilistic methods from historical data of accidents. These assessments still were based on the grain size distribution of the core and filters, such as Rönnqvist (2007), Rönnqvist et al., (2014), Bridle, Delgado & Huber (2007), Foster (2001), Brown (2003). One of the problems of these methods in existing dams, older than the method itself, is that the finer part of the soils (sieve size <0,075 mm) may not be in the old particle size distributions analysis. Therefore, the evaluation with the methodology of Kenny and Lau is sometimes not possible. For instance, if a widely graded core has F(%)=35% at 0,075 mm, the H-F curves cannot evaluate the internal stability. 2) Dam breach Another approach aimed to face the consequences of internal erosion (dam breaching procedure). These methods simulate the effects of a potential failure mechanism, which enables planners to set emergency plans. Some of these methods used parameters from historical accidents as well, such as Evans (1986) and Xu & Zhang (2009). Other authors such as Sellmeijer & Koenders (1991) or Bonelli (2006) used mathematical models to describe the phenomenon of “piping”. In spite of existence of advanced breaching simulation models such as Morris (2008). These methods will not provide realistic consequences unless an approach to assess the most likely failure mechanism is performed before. 3) Surveillance Based on the observational method, attributed to Terzaghi by Peck (1969), surveillance was the other method to assess the behaviour of the dam for safety evaluation (Charles, 1996). Due to extended research in several surveillance methods, it was determined that internal erosion is influenced by other factors than the grain size and hydraulic gradients, for instance; the temperature and resistivity, as shown in research from Johansson (1997). Moreover, nowadays, numerical modelling allows modelling several parameters from monitoring data such as the experiment of Radzicki (2010). Therefore, it is possible to model different parameters for many case scenarios to analyse the failure modes, but in order to assess the safety of the dam, it is not possible to determine if these parameters can develop failure mechanisms. Basically, because of the fact that the only way to verify the assessment from the numerical modelling is to wait for the actual breach of the dams, or performing failure tests such as the experiments made by Sjödahl (2010). 4) Failure mechanisms and internal erosion factors

Even though the failure mechanisms of internal erosion are still not fully understood (Bowles et al., 2013). Wan (2004), Fell (2003), Foster (2001), Fry (2007) investigated internal erosion mechanisms in-depth, defining the failure modes, estimating times and providing methods to assess the safety of the dams. Fell et al.,(2008) have even developed risk analysis of internal erosion, based on experiments and historical failures. However these are still under evaluation. These authors also determined that other soil properties need to be considered for the assessment of internal erosion apart from the grain size distribution. For instance, backward erosion may not develop in soils with high plasticity index. Moreover, Garner & Fannin (2010) unveiled the factors that initiate internal erosion, stating that internal erosion is dependent on three factors (material susceptibility, hydraulic load and stress state). Up to this date, FEM software is in the desktop of many engineers. Hence, due

Page 10: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

9

to the advanced research achieved in: seepage modelling, such as: Fredlund (1994) or Krahn (2004); and stress-strain soil models such as: Duncan & Chang (1970) or Schanz & Vermeer (1999), it is possible to analyse all the factors of internal erosion. Finally, recent laboratory experiments of Chang (2013), and Hunter & Fell (2012) have combined the analysis of the internal erosion factors using soil samples in their tests. However, no experiment modelling the combination of the three factors within dams was found out. This information was considered essential to assess internal erosion (ICOLD, 2013).

Summary Nowadays, Failure mechanisms of internal erosion are still not fully understood and methods to

estimate the probability of failure are under evaluation (Bowles et al., 2013) and (Fell et al., 2008).

Therefore, it is necessary to analyse all the initiating factors of internal erosion (stress state,

hydraulic conditions and material susceptibility). In addition to that, it is necessary to perform more

laboratory tests of dams. For instance, dams developing vertical piping and Global Backward Erosion

(GBE) in broadly graded cohesionless soils such as glacial tills (ICOLD, 2013). Moreover, duration of

the experiments, dimensions of laboratories and characteristics of the test apparatuses cannot

reproduce exactly what occurs within a large dam. Nonetheless, recently with the extended use of

FEM is possible to reproduce stress states and seepage models in a simple fashion, allowing

prediction of different case scenarios within the models. That is why an experiment breaching a

small embankment was considered key to achieve reliable models. For the aim and time of the

experiment 2D modelling was determined to be accurate enough.

METHODOLOGY

The methodology of the experimentation was divided in six phases. In the initial phase, an

embankment dam was designed to fail only by internal erosion mechanisms. Secondly, the

embankment was built in a steel container of 11x2x2 m3 (See Figure 1), carrying out soil testing at

the same time. Due to the reduced dimensions in the container, an instrumentation plan was

specially designed at this phase as well. In the third phase, the dam was monitored in operation

from the first filling. Consequently, in the next phase, numerical models were setup and calibrated

with the results from a period of 10 days of monitoring. Finally, a failure mode analysis prior to

breaching was compared with the actual breaching mechanism that caused the dam failure. The

duration of the Master thesis was six months. It was conducted as it follows in the sequence of

experimentation (See Figure 2).

Page 11: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

10

Figure 1. Dam, viewpoint from downstream side

Figure 2. Sequence of the experimentation

Dam design and materials properties

The geometric design was determined analysing the likelihood of slope instability for different

dimensions. The design achieved was: 1½ meter height, 4(H):3(V) rock fill shoulders with sloped

central core of glacial till (moraine) and a downstream gravel sandy filter. Furthermore, a vertical

pipe was inserted in the dam. This defect can be seen in Figure 3. Moreover, it was included in the

experiment to test if GBE could be developed during the test. Material properties (See Table 1) were

determined using literature values of the soils and soil testing.

DAM DESIGN

MONITORING INTERNAL EROSION

(10 days)

BUILT MODEL

(FEM)

FAILURE MODE ANALYSIS

DAM FAILURE

BUILD DAM

INSTRUMENTATION

SOIL TESTING

Page 12: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

11

Figure 3. Design Model (GBE developed)

Table 1. Material properties

MATERIAL PROPERTIES

MATERIAL

HYD. COND.

KSAT

(m/s)

POROSITY

n

UNIT WEIGHT

γ

(kN/m3)

DRY

DENSITY

ᵨd

(kg/m3)

GRAVI.

WATER

CONTENT

W

COHESION

c’

(kPa)

FRICTION

ANGLE

ф’

(˚)

*YOUNG

MODULUS,

E

(kPa)

*POISSON

RATIO

μ

ROCKFILL *1 x 10-3 *0.3 *21 *1855 *0.16 0 *40 1 x 107 0.4

GLACIAL TILL

/ PIPE 3.5 x 10-9 0.2 23 2120 0.09 10.8 52 10000 0.3

FILTER *2 x 10-7 *0.35 *20 *1723 0.2 0 *33 20000 0.35

* Geotechdata.info(2013), Bowles(1997), Stanford.edu (2014), Bergh (2014)

Building the dam

The embankment was built in eight working days. A plan was set to build the layers (layer thickness:

30 cm) in sequential order (See Figure 4). The core layers were compacted with the weight of the top

layers, and 85 kg of weight acting while building the layers. Furthermore, water was poured with a

hose over the top layers before to fill in the dam.

Page 13: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

12

Figure 4. Layering sequences

There were two elements that needed to be placed carefully; piezometers pipelines and a vertical

pipe through the core. Three piezometers at the core and three at the filter were used for the pore-

water pressure monitoring. The piezometers pipelines were installed at the bottom of the core and

inside the filter. The installation of piezometers pipelines was horizontal and perpendicular to the

flow, wrapping them around with a geotextile to protect them from the soil, and connected with the

piezometers outside through the right sidewall (See Figure 5 and 6).

An aluminium’s pipe , 10 cm diameter, was inserted at the central cross section of the dam. It was

made from the glacial till (core), sieving grains of 0.8 cm and 0.1 cm to achieve a gap graded material

i.e., internally unstable. The pipe was taken away from the embankment once it was finished (See

Figure 8).

The top layer (120-150 cm) had no filter. Moreover, the crest was left unfinished, as it is in Figure 7

for one day. Later on, the acoustic emissions sensor was placed on the right abutment, that device

had a weight of 2 kg inserted in the core with three steel rods of 2 cm diameter and 10 cm long at

the top of the crest (See Figure 7 and 9). Finally, the crest was not protected with rock fill.

Day 6

Day 4

Day 8

Page 14: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

13

Figure 5. Installation of piezometers in the core

Figure 6. Installation of piezometers top view

Figure 7. No filter at the crest

Figure 8. Vertical pipe

Figure 9. No erosion protection on top

Image 1. Piezometers in the core

Page 15: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

14

Instrumentation

For the instrumentation, all stipulated equipment for a dam of consequence class 1 was used,

following the RIDAS guidelines. The instrumentation to monitor the parameters of seepage,

turbidity, deformations, pore-water-pressure and vibrations applied mainly indirect methods (except

the water level) such as; a pressure sensor correlated to a Thomson’s weir downstream and manual

readings filling a bucket to measure seepage; automated piezometers for the core and filter;

acoustic emissions sensor over the crest to detect vibrations of piping; turbidity meter taking

samples downstream; laser scanner of all surfaces of the dam .

Soil testing

Soil testing was carried out before and after the construction of the embankment. Some tests were

performed in the laboratory such as the grain size distributions and gravimetric water content for

filter and glacial till, and hydraulic conductivity tests for the core and the pipe (See Figure 10 and 11).

Also, it was performed a proctor modified test to control the compaction of the core, and determine

volume-mass parameters needed for the setup of the material properties in the FEM.

Figure 10. Grain size distribution

Figure 11. Hydraulic conductivity test

Monitoring

The dam was loaded for 10 days at different water levels. During that time, several methods were

applied to monitor the following parameters, which are included in Table 2; Pore-water pressure

(See Figure 12), flow (See Figure 13), turbidity (See Figure 14), deformations (See Figure 15) and the

stored water level. Apart from these methods, video surveillance was installed downstream and

upstream the dam, recording the full length of the experiment.

All instrumentation installed provided coherent data despite the need to re-calibrate or adjust some

of these apparatuses from time to time. Collected in-data was inserted into the Built Model (FEM)

together with the geometry from the construction of the dam. Thus, a steady-state model was

solved, verifying that this model behaved like the built dam.

Page 16: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

15

Table 2. Monitoring methods

MONITORING METHODS

METHOD PARAMETER FREQUENCY N˚ UNITS LOCATION

MANUAL

PIEZOMETERS LOG

Pore-water

pressure

continuous/each anomaly 6 cm Core/filter

AUTOMATED

PIEZOMETERS LOG

Pore-water

pressure

1 per minute 4 cm Core/filter

THOMSON WEIR Seepage 1 per minute 1 cl/min Downstream

FLOW MEASURE. Seepage continuous/each anomaly 1 cl/min Downstream

TURBIDIMETER Turbidity continuous/each anomaly 1 FNU Downstream

ACOUSTIC SENSOR Vibration 1 per 15 minutes/each

anomaly

1 mm/s Crest

LASER SCANNER Deformations continuous 1 mm Downstream/upstream

RULER Water level continuous 2 cm Upstream

Figure 12. Piezometers

Figure 13. Weir and pressure sensor inside the water tank Figure 14. Turbidity meter

Figure 15. Laser scanner 3D

Page 17: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

16

Failure Mode Analysis

As Garner and Fannin (2010) illustrated in a Venn diagram (Figure 16), internal erosion initiates

when an unfavourable coincidence of material susceptibility, stress conditions and hydraulic load

occurs (ICOLD, 2013). Based on that diagram, the method consisted of performing three analyses

(hydraulic load, material susceptibility and stress state) within cross sections of the dam. Firstly, each

analysis observed the location and magnitude of the factors of internal erosion. For instance, in the

hydraulic load analysis, one of the factors was a maximum hydraulic gradient (magnitude of the

factor) at the crest of the right abutment (location). After that step, critical zones at each cross

section were identified as zones where combination of factors matched, e.g. maximum hydraulic

gradient at the crest of the right abutment and low stresses at the crest. Finally, the combination of

all the analysis pointed out the location of the most likely failure mechanism to breach the dam

(Figure 17).

Numerical modelling was the key tool to analyse the stress state and hydraulic load factors within

the cross sections. But firstly, in order to avoid other failure modes rather than internal erosion, the

slope stability was assessed at design stage. Moreover, a spillway reduced the likelihood of

overtopping. Thus, only internal erosion could occur. The package used for seepage analysis was

SVFlux, for slope instability SVSlope and for stress analysis SVSolid. SoilVision (SV) utilized FlexPDE

generic finite element solver to solve the partial differential equations (SoilVision, 2014). The

FlexPDE for SVSlope and SVFlux solved linear and nonlinear PDE’s. The nonlinear behaviour was

most commonly located in the unsaturated soil portion of the continuum. The solution utilized

automatic mathematically designed mesh generation as well as automatic mesh refinement. The

background theory applied by SoilVision can be obtained in the theory manual of the software or

related literature, and therefore, only the methods and equations applied in the analysis will be

mentioned from the manuals.

Figure 16. Venn Diagram, from (ICOLD, 2013).

Page 18: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

17

Figure 17 Failure mode analysis

Hydraulic load analysis

Two-Dimensional seepage analysis was applied for modelling cross-sections with and without the

pipe at steady-state saturated/unsaturated seepage.

Considering the reference volume V0 constant and the water incompressible, the following partial

differential (PDE) equation was applied for saturated/unsaturated seepage:

𝝏

𝝏𝒙[(𝒌𝒙

𝒘)𝝏𝒉

𝝏𝒙] +

𝝏

𝝏𝒚[(𝒌𝒚

𝒘)𝝏𝒉

𝝏𝒚] = −𝜸𝒘𝒎𝟐

𝒘 𝝏𝒉

𝝏𝒕 Eq(1)

Considering saturated soil and neglecting the vapour flow, the PDE governing steady-state seepage

reduces to:

𝝏

𝝏𝒙[(𝒌𝒙

𝒘)𝝏𝒉

𝝏𝒙] +

𝝏

𝝏𝒚[(𝒌𝒚

𝒘)𝝏𝒉

𝝏𝒚] = 𝟎 Eq(2)

Where kw, is the hydraulic conductivity in the x and y directions. These values are constant for

saturated conditions. For unsaturated soil, it is the function of matric suction (difference of air and

water pore pressures, ua-uw); m2

w, represents the derivative with respect to matric suction from

the soil-water characteristic curve; γw

, the unit weight of water; h, the hydraulic head; x and y are

the horizontal and vertical coordinates in isotropic flow, respectively.

Failure mode analysis

Critical zones from analysis:

-Suffusion

-Hydraulic fracture

-Soil distress

-Cracking

-Bridging

-Piping

Hydraulic load analysis

Factors:

-Gradients

-Pore water pressure

-Seepage velocity

Material susceptibility analysis

Factors:

-Internal Instability

-Filter incompatibility

-Void space

-Free surface

-Low plasticity

-Cracks Stress state analysis

Factors:

-Low stress

-Deformation

-Vibration

-Arching

Page 19: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

18

The software solved the PDE in seconds for different initial conditions. Solutions included in the

results are; the pore-water pressure distribution, range of fluxes, water head distribution within the

core and gradients and water heads. With these results, hydraulic load conditions were assessed.

Slope stability

SVSlope was utilized for limit equilibrium methods of slope stability analysis, and hence, to compute

the factor of safety (FOS), ensuring the dam would not fail due to slope instability. The fully specified

method was applied at different initial conditions for different critical slip surfaces: empty reservoir,

maximum capacity and rapid drawdown transferring the seepage files from SVFlux (Design Model).

The method of slices was assumed to be composite-circular. The shear force mobilized was obtained

for each slice in the saturated soil as:

𝑺𝒎 =𝜷

𝑭𝒔

{𝒄′ + (𝝈𝒏 − 𝒖𝒘) 𝐭𝐚𝐧 𝝋′} Eq (3)

And, for the unsaturated soil, the Phi-b method was applied using the following equation for the

mobilized shear force.

𝑺𝒎 =𝜷

𝑭𝒔{𝒄′ + (𝝈𝒏 − 𝒖𝒂) 𝐭𝐚𝐧 𝝋′ + (𝒖𝒂 − 𝒖𝒘) 𝐭𝐚𝐧𝝋𝒃} Eq (4)

Where, Sm is the shear force mobilized on the base of the slice; 𝛽 is the length along the base of a

slice; Fs is the overall factor of safety; c’ is the effective cohesion; 𝜎𝑛 is the normal stress acting on

the base of a slice; 𝜑′ is the effective angle of internal friction; 𝑢𝑎 is the pore-air pressure at the base

of a slice; 𝑢𝑎 − 𝑢𝑤 is the matric suction and 𝜑𝑏 is the angle defining the rate of increase of strength

due to an increase in the suction.

Stress state conditions

SVSolid modelled the stress-deformation state. The vibration was measured with an acoustic

emission sensor; however results showed no effects to consider in the analysis. SVSolid is based on

the theory of elasticity, a two-dimensional plane strain model was assumed to perform the stress

analysis. These models were expressed in terms of partial differential equations, governing the static

equilibrium of the forces acting on a representative elemental volume of material. The equilibrium

equations were combined with constitutive models relationships, expressing changes in stresses in

terms of strains. The strains were written in terms of the displacements, assuming small

displacements (Lagrangian formulation). In order to express the PDE´s applied for the stress analysis,

strain and displacement relationships, static equilibrium equations and generalized stress-strain

relationship need to be defined firstly:

Relationships between the components of strain and displacements:

𝜺𝒙 =𝝏𝒖

𝝏𝒙, 𝜺𝒚 =

𝝏𝒗

𝝏𝒚 , 𝜸𝒙𝒚 =

𝝏𝒗

𝝏𝒙+

𝝏𝒖

𝝏𝒚 Eq (5)

Where u and v are displacements in the x- and y-directions, respectively.

Static equilibrium equations corresponding to plane-strain conditions:

Page 20: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

19

𝝏𝝈𝒙

𝝏𝒙+

𝝏𝝉𝒙𝒚

𝝏𝒚+ 𝒃𝒙 = 𝟎 Eq (6)

𝝏𝝉𝒙𝒚

𝝏𝒙+

𝝏𝝈𝒚

𝝏𝒚+ 𝒃𝒚 = 𝟎 Eq (7)

Where 𝜎𝑖 and 𝜏𝑖𝑗 are the total normal and shear stresses, respectively, and 𝑏𝑖 the body weight (i.e.,

unit weight).

SVSolid used the displacement components as the primary variables describing the stress-strain field

model. Therefore, in order to obtain the PDE’s that govern the static equilibrium of forces

throughout the continuum, the stresses present in the equilibrium equations must be replaced by

the displacement components. Thus, from the following generalized stress-strain relationship:

𝒅𝜺 = 𝑫−𝟏𝒅𝝈 Eq (8)

Where, in three-dimensions:

𝑫 =

[ 𝑫𝟏𝟏 𝑫𝟏𝟐 𝑫𝟏𝟑

𝑫𝟐𝟏 𝑫𝟐𝟐 𝑫𝟐𝟑

𝑫𝟑𝟏 𝑫𝟑𝟐 𝑫𝟑𝟑

𝑫𝟏𝟒

𝑫𝟐𝟒

𝑫𝟑𝟒

𝑫𝟒𝟏 𝑫𝟒𝟐 𝑫𝟒𝟑 𝑫𝟒𝟒

𝟎 𝟎 𝟎 𝟎𝟎 𝟎 𝟎 𝟎

𝟎 𝟎𝟎 𝟎𝟎 𝟎𝟎 𝟎

𝑫𝟓𝟓 𝟎𝟎 𝑫𝟔𝟔

]

Eq (9)

𝝈𝑻 = {𝝈𝒙 𝝈𝒚 𝝈𝒛 𝝉𝒙𝒚 𝝉𝒙𝒛 𝝉𝒚𝒛 } Eq (10)

And:

𝜺𝑻 = {𝜺𝒙 𝜺𝒚 𝜺𝒛 𝜸𝒙𝒚 𝜸𝒙𝒛 𝜸𝒚𝒛 } Eq (11)

Applying 2D plane-strain conditions; where: 𝜀𝑧 , 𝛾𝑥𝑧, 𝛾𝑦𝑧 , 𝜎𝑧, 𝜏𝑥𝑧 , 𝜏𝑦𝑧 , are zero. The PDE’s can be

reduced to:

𝝏

𝝏𝒙[𝑫𝟏𝟏

𝝏𝒖

𝝏𝒙+ 𝑫𝟏𝟐

𝝏𝒗

𝝏𝒚+ 𝑫𝟏𝟒 (

𝒅𝒗

𝒅𝒙+

𝒅𝒖

𝒅𝒚)] +

𝝏

𝝏𝒚[𝑫𝟒𝟏

𝝏𝒖

𝝏𝒙+ 𝑫𝟒𝟐

𝝏𝒗

𝝏𝒚+ 𝑫𝟒𝟒 (

𝒅𝒗

𝒅𝒙+

𝒅𝒖

𝒅𝒚)] + 𝒃𝒙 = 𝟎 Eq (12)

𝝏

𝝏𝒙[𝑫𝟒𝟏

𝝏𝒖

𝝏𝒙+ 𝑫𝟒𝟐

𝝏𝒗

𝝏𝒚+ 𝑫𝟒𝟒 (

𝒅𝒗

𝒅𝒙+

𝒅𝒖

𝒅𝒚)] +

𝝏

𝝏𝒚[𝑫𝟐𝟏

𝝏𝒖

𝝏𝒙+ 𝑫𝟐𝟐

𝝏𝒗

𝝏𝒚+ 𝑫𝟐𝟒 (

𝒅𝒗

𝒅𝒙+

𝒅𝒖

𝒅𝒚)] + 𝒃𝒚 = 𝟎 Eq (13)

Considering the hyperbolic model, the following constitutive relationships were applied in the

Hook’s law (Eq 7).

𝑫𝟏𝟏 = 𝑬(𝟏 − 𝝁)/[(𝟏 + 𝝁)(𝟏 − 𝟐𝝁)] Eq (14)

𝑫𝟏𝟐 = 𝑬𝝁/[(𝟏 + 𝝁)(𝟏 − 𝟐𝝁)] Eq (15)

𝑫𝟒𝟒 = 𝑬/[𝟐(𝟏 + 𝝁)] Eq (16)

Where, E is the Young Modulus and μ is the Poisson ratio. Assuming that, the Young’s modulus can

be approximated as a tangent modulus. Then, the tangent modulus in the hyperbolic model is

defined as a nonlinear function of the shear strength parameters.

𝑬𝒕 = [𝟏 −𝑹𝒇(𝟏−𝒔𝒊𝒏∅)(𝝈𝟏−𝝈𝟑)

𝟐 𝒄 𝒄𝒐𝒔∅+𝟐 𝝈𝟑 𝒔𝒊𝒏∅]𝟐

𝑲𝑷𝒂𝒕𝒎(𝝈𝟑

𝑷𝒂𝒕𝒎)𝒏 Eq (17)

Page 21: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

20

𝑹𝒇 = (𝝈𝟏−𝝈𝟑)𝒇

(𝝈𝟏−𝝈𝟑)𝒖𝒍𝒕 Eq (18)

Where, 𝑅𝑓 is the failure ratio, equal to the ratio of the stress difference at failure (shear resistance)

and the actuating stress difference; 𝜎1 and 𝜎3 are the major and minor principal stresses,

respectively; K is a modulus of elasticity of reference; 𝑃𝑎𝑡𝑚 is the atmospheric pressure; and, n is an

experimental parameter that defines the ratio of increase of E with 𝜎3. The input values were

obtained from previous triaxial tests performed in similar materials (See Table 3)

Table 3. Hyperbolic equation parameters

HYPERBOLIC EQUATION PARAMETERS*

MATERIAL

FAILURE RATIO

𝑅𝑓

ELASTICITY

MODULUS

K

(KPa)

EXPERIMENTAL

PARAMETER

n

ATMOSPHERIC PRESSURE

𝑃𝑎𝑡𝑚

(KPa)

ROCKFILL 0.73 1450 0.30 101.15

GLACIAL TILL 0.77 520 0.42 101.15

FILTER 0.72 1141 0.20 101.15

* Dong et al., (2013)

Material susceptibility

Considering the factors of material susceptibility in Figure 17, the analysis was mainly focused on the

grain size distributions, therefore performing soil testing. The factors analysed from these tests were

the filter compatibility and the internal stability of the core and filter. The criterion for the

assessment of internal stability of granular filters applied was based on methodology from Kenny

and Lau (1985) and Rönnqvist (2007). The results from these assessments provided the likelihood of

internal erosion for these soils within the dam. Since the foundation was built over the base of a

steel container, backward erosion at foundation was discarded as a failure mode (free surface).

Other factors such as plasticity index, temperature or resistivity were not analysed in this

experiment. However, voids and construction quality details were considered in the failure mode

analysis, since it was believed that compaction rates or defects caused by instrumentation would

make the embankment more susceptible to fail at different zones, e.g. cracks next to

instrumentation or poorly compacted layers.

Dam Failure

Dam failure was the phase of the experiment where the hypothesis was verified, i.e. if the result

from the failure mode analysis matched the actual dam failure at the experiment, the hypothesis

was true. In other words, the failure mode analysis aimed to find what factors and where breaching

mechanisms could occur. Whereas, the dam failure investigation aimed to find what factors caused

the dam failure, and how.

The method to find the reason behind the failure of the dam consisted in to investigate all

monitoring results. It was therefore crucial to find the time for initiation and development of the

Page 22: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

21

failure mechanism to correlate the parameters monitored (pore pressure, deformations, vibrations,

turbidity, leakage and vibrations) with the breaching mechanism. The end of the dam failure

investigation concluded when the release of water was not under control anymore.

Page 23: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

22

RESULTS

The results are described following the steps of the methodology (See Figure 2).

Dam design

Firstly, the slope stability was assessed to guarantee that the experiment would not fail due to slope

instability. The slope stability was assessed for three initial conditions: Empty reservoir, full reservoir

and rapid drawdown (See Figure 18, 19, 20, 21).

The dam designed had a FOS higher than 1.3 applying Bishop’s method for all the cases. From this

analysis it was concluded that the dam would not fail during the experiment due to slope instability.

Slope stability analysis

Figure 18. FOS Empty reservoir (upstream)

Figure 19. FOS empty reservoir (downstream)

Page 24: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

23

Figure 20. FOS full reservoir (upstream)

Figure 21. Rapid drawdawn

Page 25: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

24

Monitoring and modelling internal erosion In this section, the seepage and deformations monitored in the experiment were compared with the

FEM results (or Built Model), using SVFlux and SVSolid.

Seepage monitoring

The piezometers and seepage flow measurements provided huge amounts of data each day. From

all the results collected each day, only steady conditions were used for the analysis. Therefore, when

steady-state conditions were observed each day, it was assumed that a queasy-steady state of

seepage was reached. Thus, in Table 4 are shown the results at queasy-steady state of seepage each

day of the experiment. From these results, there have been plotted graphs showing the variation of

the pore-water pressure of all the piezometers at the core and at the filter, respectively (See Figure

22 and 23). Attending to the pore-water pressure, it was noticed and anomaly behaviour at the right

piezometers with respect to the other piezometers. The anomaly was a higher pore water pressure

than expected, because the tip of the piezometer at the right abutment was placed at the most

forward position into the core, which would suppose the lowest PWP of the 3 piezometers in normal

condition (See Figure 6). Regarding to the seepage measurements, the leakage increased in great

fashion for the last 3 days of the experiment. The Thomson weir was assumed to provide low

reliable data in compare with the manual measurements at low seepage flow. Thus, the manual

measurements were considered the most reliable values, at low flow.

Table 4. Dam values monitored at queasy-steady state seepage

DAY CORE PIEZOMETERS (cm) FILTER PIEZOMETERS (cm) WL

(cm)

SEEPAGE (liters/min)

LEFT CENTRAL RIGHT LEFT CENTRAL RIGHT THOMSON MANUAL

1 19.5 16.5 17 11.5 9 11.5 23.5 n/r n/a

2 54 45.5 44 11.5 9 11.5 65.5 n/r n/a

3 34.5 30.8 40.3 11.5 9 11.5 44 n/r 0.63

4 120 111 114.9 16.5 15 16 130 n/r 4.42

5 121.8 113.7 117 16.5 15 15.5 130 n/r 3.97

6 120 112.8 115.1 16.5 15 16 128 n/r 4.48

7 112.6 106.2 108.1 16.3 15.3 15.7 119 5.66 3.60

8 113.3 106.9 108 16.2 15.3 16 123 13.56 25.14

9 114.3 108 109.5 16.2 15.6 16 124 38.16 56.32

10 114.2 108.3 109.7 16.2 15.5 16 124 38.76 58.16

Page 26: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

25

Figure 22. Monitoring results (Core).

Figure 23. Monitoring results (Filter).

Built model (SVFlux)

The following results in Table 5 were obtained with SVFlux for steady-state conditions. These

seepage results show values of pore-water pressure within the numerical model at the same

location of the piezometers installed. Note that to compare the results at steady-state, the same

reservoir levels from monitoring were applied in SVFlux. Thus, the graphs of the results from Table 5

were also plotted (See Figure 24 and 25). In Table 6, there has been compared the Built Model

(SVFlux results) with the Dam (monitoring results), the table shows that the pore water pressures at

the experiment started to match with the model after the 4th day. However, there were still

differences at the right abutment piezometers. Moreover, the leakage monitored did not match with

the SVFlux results.

0

20

40

60

80

100

120

140

1 2 3 4 5 6 7 8 9 10

PW

P (

cm)

Time (days)

CORE PIEZOMETERS (cm) LEFT

CORE PIEZOMETERS (cm) CENTRAL

CORE PIEZOMETERS (cm) RIGHT

WL (cm)

0

2

4

6

8

10

12

14

16

18

1 2 3 4 5 6 7 8 9 10

PW

P (

cm)

Time (days)

FILTER PIEZOMETERS (cm) LEFT

FILTER PIEZOMETERS (cm) CENTRAL

FILTER PIEZOMETERS (cm) RIGHT

Page 27: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

26

Table 5. Built Model- SVFlux results at steady-state seepage

DAY CORE PIEZOMETERS (cm) FILTER PIEZOMETERS (cm) WL

(cm) SEEPAGE

(liters/min) LEFT CENTRAL RIGHT LEFT CENTRAL RIGHT

1 22.3 21.5 20.3 9.19 9.1 9.1 23.5 1.04 2 60.9 57.5 53 9.8 9.4 9.3 65.5 1.12 3 41.1 39.1 36.3 9.5 9.3 9.2 44 1.04 4 120.6 113.7 104.6 16.05 15.35 15.2 130 1.80 5 120.6 113.7 104.6 16.05 15.35 15.2 130 1.80 6 119 112 103 15.8 15.1 15 128 1.78 7 110.5 104.3 96 16.2 15.6 15.4 119 1.84 8 114.2 107.7 99.1 16.2 15.6 15.5 123 1.84 9 115.1 108.6 100 16.3 15.6 15.5 124 1.84

10 115.1 108.7 100 16.2 15.5 15.4 124 1.83

Figure 24. SVFlux results (Core).

Figure 25. SVFlux results (Filter).

0

20

40

60

80

100

120

140

0 1 2 3 4 5 6 7 8 9 10

PW

P (

cm)

Time (days)

CORE PIEZOMETERS (cm) LEFT

CORE PIEZOMETERS (cm)CENTRAL

CORE PIEZOMETERS (cm) RIGHT

WL (cm)

0

2

4

6

8

10

12

14

16

18

1 2 3 4 5 6 7 8 9 10

PW

P (

cm)

Time (days)

FILTER PIEZOMETERS (cm) LEFT

FILTER PIEZOMETERS (cm)CENTRAL

FILTER PIEZOMETERS (cm) RIGHT

Page 28: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

27

Table 6. Relative differences of results DAM vs BUILT MODEL

DAY CORE PIEZOMETERS FILTER PIEZOMETERS SEEPAGE

RATES LEFT CENTRAL RIGHT LEFT CENTRAL RIGHT

1 -14.36% -30.30% -19.41% 20.09% -1.11% 20.87% N/A

2 -12.78% -26.37% -20.45% 14.78% -4.44% 19.13% N/A

3 -19.13% -26.95% 9.93% 17.39% -3.33% 20.00% 39.69%

4 -0.50% -2.43% 8.96% 2.73% -2.33% 5.00% 59.17%

5 0.99% 0.00% 10.60% 2.73% -2.33% 1.94% 54.54%

6 0.83% 0.71% 10.51% 4.24% -0.67% 6.25% 60.28%

7 1.87% 1.79% 11.19% 0.61% -1.96% 1.91% 49.00%

8 -0.79% -0.75% 8.24% 0.00% -1.96% 3.13% 92.67%

9 -0.70% -0.56% 8.68% -0.62% 0.00% 3.13% 96.74%

10 -0.79% -0.37% 8.84% 0.00% 0.00% 3.75% 96.85%

Deformation monitoring

With the laser scanner it was measured the deformation of the dam after 10 days. The

measurements of deformations were taken independently for the upstream and downstream faces,

although the surveillance equipment still measured points of both sides due to a high location of the

apparatus. Figure 26, shows deformations monitored at downstream face. Note that this is a 3D

view from an upstream point of view. The maximum deformations are represented in red. However,

these deformations were due to water level variations upstream. Therefore, the maximum

deformations within the dam are actually located downstream, and these were lower than 1.5 cm

(green dots downstream slope). There were also deformations at the sidewalls of the container.

In Figure 27, deformations monitored upstream are shown in a 3D view from upstream, the

maximum displacements were lower than 10 cm. It indicates clearly that the maximum settlements

occurred at the crest on the right abutment. The red and grey areas at the slope upstream do not

indicate deformations of the dam, these areas only indicated water level variation.

In Figure 28, there were combined the monitoring results upstream and downstream. In this front

view from downstream face is shown the maximum deformation with red dots at the right abutment

(left side of Figure 28) on the top of the crest. It is also visible deformation within lower zones

through the rock-fill at the right abutment.

Page 29: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

28

Figure 26. Deformations monitored downstream (point of view from upstream)

Figure 27. Deformations monitored upstream (point of view from upstream)

Page 30: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

29

Figure 28. Deformation monitored upstream and downstream (point of view from downstream).

Built model (SVSolid)

With the displacements obtained in SVSolid (See Figure 29) and the deformations monitored, the

results were compared with in Table 7. In Figure 30, the comparison of the results was based on the

maximum deformations monitored at different zones of the dam (crest, upstream and downstream)

distinguishing between right, central and left parts of the dam. There were also drawn linear trend

lines that indicated that the maximum deformations monitored were higher at the right abutment.

In fact, deformations monitored at the right abutment matched closer to the calculation with

SVSolid, at a 20-30% relative error between all the results. Therefore, the results from the model and

the experiment were considered to be close enough for further analysis.

Figure 29. BUILT MODEL-SVSolid deformation results

Page 31: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

30

Table 7. Maximum deformations DAM vs BUILT MODEL

MAXIMUM DEFORMATIONS MONITORED(cm) SVSOLID (cm)

ZONE LEFT CENTRAL RIGHT LEFT CENTRAL RIGHT

DEFORMATIONS UPSTREAM

8 5 10 8 8 8

DEFORMATIONS CREST

8 2,5 10 8 8 8

DEFORMATIONS DOWNSTREAM

1,6 1,6 3 4 4 4

Figure 30. Comparison results SVSolid, DAM vs BUILT MODEL

Internal erosion factors

The results from the analysis of the internal erosion factors (material susceptibility, hydraulic load

and critical stress condition) are mentioned below.

Material susceptibility

Following the diagram in Figure 17, the soils were assessed for initiation and development of

internal erosion due to: filter incompatibility and internal instability. The results were based on four

grain size distributions attached in Figure 31 with a brief soil description. Then, with these results the

filter criteria was applied following the method from Vattenfall (1988), which resulted to be fulfilled

(See Table 8).

The method of Kenny and Lau (1985) was applied to determine the internal stability of granular

filters, core and pipe (See Figure 32, 33 and 34). The samples of soil taken from the filter and the

0

2

4

6

8

10

12

1 2 3

Y D

isp

lace

me

nts

(cm

)

1=LEFT; 2=CENTRAL; 3=RIGHT

Maximum Deformations DAM vs BUILT MODEL

DEFORMATIONS UPSTREAM

DEFORMATIONS CREST

DEFORMATIONS DOWNSTREAM

SVSOLID Max DeformationsDownstream

SVSOLID Max Deformations at Crestand Upstream

Linear (DEFORMATIONS UPSTREAM)

Linear (DEFORMATIONS CREST )

Linear (DEFORMATIONSDOWNSTREAM)

Page 32: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

31

pipe resulted to be internally unstable, whereas the core was stable since it was only possible to

evaluate the fraction smaller than 20% (F<20%).

Finally, the methodology from Rönnqvist (2007) to assess the potential for internal erosion in glacial

till core embankment dams was also applied for the filter incompatibility. The result of the

assessment provided a neutral risk of continuation of erosion at the core, and an increased risk of

continuation at the filter.

Soil description:

- Core (2 samples, to contrast results): Coarse glacial till with almost fifty-fifty distribution of

sand and gravel.

- Filter (1 sample): Coarse material (gravel) with small fraction of fine material (sand <10 %).

- Pipe (1 sample): Gap graded grain size distribution for the fine particles, and uniformly

graded for coarser material.

Figure 31. Grain size distribution

FILTER CRITERIA FINE MAT. <30% FINES (<0.06mm))

Requirements Value Limits Filter criteria

Permeability D15/d15 18.6 4<D15/d15>40 OK

Piping D15/d85 0.4 D15/d85<4 OK

Parallel curves D50/d50 12.0 D50/d50<25 OK

Separation Dmax 50 mm Dmax<60mm OK

Table 8. Filter criteria

0,0

10,0

20,0

30,0

40,0

50,0

60,0

70,0

80,0

90,0

100,0

0,001 0,010 0,100 1,000 10,000 100,000

Perc

en

tag

e p

assin

g

Particle size (mm)

Core filter pipe core 2

SAND GRAVEL SILT

Page 33: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

32

Figure 32. Filter Internal stability

Figure 33. Core internal stability

Figure 34. Pipe internal stability

0

1

2

3

4

5

6

7

8

9

10

0 1 2 3 4 5 6 7 8 9 10

H%

F%

H-F

Critical line internal stability

Unstable

0

5

10

15

20

25

30

35

40

0 5 10 15 20 25 30 35 40

H%

F%

H/F

Critical line stability

Stable

0

2

4

6

8

10

12

14

0 2 4 6 8 10 12 14

H%

F%

H/F

Critical line stability

Unstable

Page 34: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

33

FILTER ASSESSMENT CHECK

D15 7 mm D15<1.4mm

Core Stability Stable Fig 33

Pipe stability Unstable Fig 34

Filter Stability Unstable Fig 32

RISK of CE(core) NEUTRAL

RISK of CE(pipe) INCREASED

Table 9. Filter assessment

Hydraulic load

With the model created in SVFlux, all the factors of hydraulic load were calculated at a water level

upstream of 124 cm, the reason was because the PWP results between the model and the

experiment matched, also because a queasy steady-state condition was reached at day 10, since

there were no changes in the PWP from day 8. The pore water pressure distribution can be seen in

Figure 35. The piezometers are represented with green triangles and vertical black lines. The PWP

distribution indicated that the experiment did not reach the final steady-state seepage. That could

occur in a longer test. However, it was still possible to analyse the experimental hydraulic load

factors at the experiment. These factors indicated that the hydraulic gradient was i=3 within the

saturated zone, and i=5 at the unsaturated, but since there was an anomaly at the right abutment

the gradients could be different at this abutment (See Figure 36). Regarding with the water head

and head pressure, the 124 cm were mainly distributed upstream at the core and the maximum

head pressure at the bottom, upstream. These results were used for the stress/deformation analysis

(See Figures 37 and 38). Furthermore, seepage flow (fluxes) pointed out an anomaly since were very

small in compare with the monitored results (See Figure 39). The conclusions of the results of

hydraulic load factors were:

Steady-state of seepage was not fully achieved at the experiment according to PWP

distribution.

The right abutment piezometer indicated a different behaviour than monitoring results.

Hydraulic gradients at the core were too high (gradients of 3 at saturated zone, and 5 at

unsaturated)

The water head and head pressure were loading mainly the upstream side of the core.

Maximum flux velocity was 1.54 cm/min at the toe. The rest of the dam indicated a seepage

velocity of about 0.06 cm/min.

Seepage flow monitored indicated higher results than the flux obtained with the model.

Hence, the seepage velocity in the experiment could be considered: either, as an indication

of high leakage; and/or a wrong result of modelling.

Page 35: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

34

Figure 35. Pore-water pressure (kPa)

Figure 36. Hydraulic gradients

Page 36: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

35

Figure 37. Water head (m)

Figure 38. Pressure head (m)

Page 37: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

36

Figure 39. Seepage velocity (m/s)

Critical stress condition

In Figure 40, there is a general picture of the stress state of the dam. It is shown that arching effect

occurred; with the centre acting right downstream the filter foundation (blue zone; 𝛔max= 31.3 kPa).

Another zone of high vertical stress is out of the arching effect at the core foundation, where the

pore-water pressure was at its highest (green zone; 20 KPa). Thus, due to the arching effect, slopes

and crest were at a low stress state. It can be seen a decomposition of the horizontal vertical

components of total stress in Figures 44 and 45. The following conclusions from the results are

mentioned below.

The results of deformations with the model seemed to agree with the experiment. The

maximum XY deformations were mainly located within the crest upstream side of the rock

fill and rock fill-core interface (See Figure 41).

Vertical cumulative effective stress exerted maximum compressive stress (31 kPa) at the

filter-rock fill interface downstream, which seemed to be normal. However, at the upstream

part of the core the effective stresses were low between 3-6 KPa, which indicate a weak

zone (See Figure 42).

There were small zones of negative shear stress within the core, at the crest, upstream and

downstream (See Figure 43). The local factor of safety calculation with SVSolid indicated that

it could be a shear failure mode at the top of the crest (See Figure 47). Moreover,

considering the higher deformation of the rock fill, the top part of the core at the crest

would be exposed to local shear failure mode, which agreed with observations at the

experiment.

The horizontal stresses decreased above the 2/3 of the height of the dam, particularly at the

core’s crest, where it became even lower than zero, because there was no hydrostatic

pressure, and the horizontal soil pressure at the crest was low (See Figure 44). In connection

Page 38: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

37

to that, minimum principle stresses (S3) decrease with the height at the core, where if the

pore water pressure becomes higher than S3, hydraulic fracture may occur. The horizontal

stresses are plotted in a clearer diagram called minimum principle stresses (S3), (See Figure

46).

Vibration at the experiment was monitored, and even though the impounding of water

through the pipeline could generate small vibrations, the result did not show any relevance,

and hence, it was disregarded as a factor of internal erosion in this experiment.

Figure 40. Total stress Sy (kPa)

Figure 41. XY Displacements (m)

Page 39: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

38

Figure 42. Vertical effective stresses (kPa)

Figure 43. XY Shear stresses (kPa)

Page 40: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

39

Figure 44. X total stresses (kPa)

Figure 45. Y total stresses (kPa)

Page 41: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

40

Figure 46. Total minimum principle stress (S3) (kPa)

Figure 47. Local Factor of Safety

Failure mode analysis (Critical zones)

In this section are showed the critical zones of the dam, in other words, the location where a failure

mode may occur according to the factors of internal erosion. These zones were marked in a cross

section of the design model. In the discussion, it is explained in more detail the failure mode

analysis. Figure 48, shows; in green, the zones affected by factors of material susceptibility; in red,

the zones affected by hydraulic load factors; in purple, the zones affected by stress factors; and in

blue, the combination of the three factors within the same zone. There was no distinction if the

cross section was at the right, centre or left abutment, that can be found in the discussion. Note that

the pipe only was affected by the material susceptibility factor. Thus, the failure mode analysis

pointed out at the crest, and discarded the pipe inserted in the experiment.

Page 42: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

41

Figure 48 Critical zones of failure mode analysis

Dam failure

In the dam failure investigation, all the monitoring data collected was analysed, from the first day of

the experiment until the dam breached, at day 10. There results of dam failure pointed out three

phases (impounding, piping and breaching). Impounding was initiated at 13:41:41 at maximum

inflow (1440 l/min) into the container. From 13:43:26, piping was initiated and progressed until the

crest collapsed at the right abutment at 13:59:31. Note that the water level inside the container was

limited to 147 cm, so overtopping did not occur. The following results from different

instrumentation show where and how the dam breached, and at what time.

Turbidity

Turbidity was eventually high at days: 3, 5, 6 and 10. After one week of loading, settlements seemed

to reach a limit and no turbidity was measured until the day 10. When the dam breached the

turbidity initiated at 13:50:00 and it reached the maximum value at 14:15:00 (See Figure 49).

Page 43: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

42

Figure 49. Turbidity

Seepage

Seepage flow reached daily values of at least 10 l/min, except at day 4 when values were lower than

7 l/min. Maximum seepage values of over 60 l/min were reached at days 6, 9 and 10. These values

were measured manually (See Figure 50). However, at day 10, due to a high seepage flow the

manual measurements were not as reliable as the Thomson’s weir logs, because the flow was

becoming the same as the inflow from the pump (See Figure 51). Note that there were no manual

reading the first 2 days of the experiment.

Figure 50. Seepage flow, 10 days (Manual readings)

0

200

400

600

800

1000

1200

08

:45

:00

09

:45

:00

10

:15

:00

10

:45

:00

11

:15

:00

11

:45

:00

12

:00

:00

12

:07

:00

12

:20

:00

12

:30

:00

12

:28

:00

12

:42

:00

12

:50

:00

13

:00

:00

13

:15

:00

13

:28

:00

13

:45

:00

13

:50

:00

14

:15

:00

14

:42

:00

14

:58

:00

15

:15

:00

16

:00

:00

16

:45

:00

17

:45

:00

18

:45

:00

19

:45

:00

20

:45

:00

Turb

idit

y (F

NU

)

Time (hour)

day 3

day 4

day 5

day 7

day 8

day 9

day 10

day 6

0

1000

2000

3000

4000

5000

6000

7000

08

:30

:00

08

:40

:00

09

:00

:00

09

:30

:00

10

:00

:00

10

:25

:00

11

:00

:00

11

:15

:00

11

:39

:00

12

:00

:00

12

:10

:00

12

:13

:00

12

:25

:00

12

:28

:00

12

:37

:00

12

:40

:00

12

:56

:00

13

:00

:00

13

:10

:00

13

:30

:00

14

:00

:00

14

:20

:00

14

:25

:00

15

:00

:00

15

:15

:00

15

:57

:00

16

:00

:00

17

:00

:00

18

:00

:00

19

:00

:00

20

:00

:00

21

:00

:00

22

:00

:00

22

:40

:00

See

pag

e (

cl/m

in)

Time (hour)

day 3

day 4

day 5

day 6

day 7

day 8

day 9

day 10

Page 44: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

43

Figure 51. Seepage flow at day 10 (Thomson weir)

Pore-water pressure

Piezometers installed within the core were automatically logged during the whole length of the

experiment. However, only results at dam failure are shown in this section. The PWP at the core for

the whole length of the experiment can be found in Figure 22. In Figure 52, when impounding

started, the right abutment had higher PWP than it should be. Where, the central and left

piezometers followed together a different behaviour. When the leakage was observed (piping) at the

right abutment, the right piezometer increased at a higher rate than the other piezometers

surpassing even the left piezometer. When the right core reached 145 cm of PWP at 14:14:58, which

corresponded with the water level, the right part of the crest collapsed.

Figure 52. Pore-water pressure at day 10

0

20000

40000

60000

80000

100000

120000

140000

160000

13

:28

:01

13

:29

:44

13

:31

:26

13

:33

:09

13

:34

:51

13

:36

:34

13

:38

:16

13

:39

:58

13

:41

:41

13

:43

:23

13

:45

:05

13

:46

:48

13

:48

:30

13

:50

:13

13

:51

:55

13

:53

:38

13

:55

:20

13

:57

:02

13

:58

:45

14

:00

:27

14

:02

:09

14

:03

:52

14

:05

:34

14

:07

:17

14

:08

:59

14

:10

:42

14

:12

:24

14

:14

:06

14

:15

:49

14

:17

:31

14

:19

:13

14

:20

:56

14

:22

:38

14

:24

:21

14

:26

:03

14

:27

:46

See

pag

e (

Cl/

min

)

Time (hour)

100

105

110

115

120

125

130

135

140

145

150

13

:30

:35

13

:33

:09

13

:35

:42

13

:38

:16

13

:40

:50

13

:43

:23

13

:45

:57

13

:48

:30

13

:51

:04

13

:53

:38

13

:56

:11

13

:58

:45

14

:01

:18

14

:03

:52

14

:06

:26

14

:08

:59

14

:11

:33

14

:14

:06

14

:16

:40

14

:19

:13

14

:21

:47

14

:24

:21

14

:26

:54

14

:29

:28

PW

P (

cm)

Time (hour)

Right core

Left core

Central core

IMPOUNDING PIPING BREACHING

PIPING BREACHING IMPOUNDING

Page 45: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

44

Acoustic emissions

The acoustic sensor did not register relevant vibrations until the dam failed at day 10. Longitudinal,

transversal and vertical vibrations were detected by the acoustic emission sensor giving the exact

time of initiation of the breaching failure at 13:59:49. The vibration stopped when the acoustic

sensor was retired from the water after the collapse of the pipe at this point of the crest (See Figure

53).

Figure 53. Acoustic emissions, day 10.

Video surveillance

The following pictures were taken with the cameras installed upstream and downstream the

embankment recording the exact times of failure. Pictures in Figure 54 show the same time of the

breaching’s sequence at two different viewpoints, starting from impounding (a-b) to piping (c-d) and

dam failure (d-e), respectively.

0

50

100

150

200

250

16

:22:1

8

16

:15

:00

16

:00

:00

15

:45:0

0

15

:30

:00

15

:19:0

2

15

:15:0

0

15

:00:0

0

14

:45:0

0

14

:40

:16

14

:36

:54

14

:31

:40

14

:30

:00

14

:15:0

0

14

:00:0

0

13

:59:4

9

13

:57:2

4

13

:51:5

0

13

:49

:30

13

:45:2

0

13

:45

:00

13

:44

:16

13

:30:0

0

13

:15

:00

13

:00

:00

12

:45:0

0

12

:30:0

0

Aco

ust

ic e

mis

sio

ns

(mm

/s)

Time (hour)

long.

trans.

vert.

Page 46: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

45

Figure 54. Dam Failure

a) 13:40:00 – Impounding starts

f) 13:59:31- Pipe collapse e) 13:59:31- Pipe collapse

d) 13:43:26-13:59:31 - Piping c) 13:43:26-13:59:31 - Piping

b) 13:40:00 - Impounding starts

Page 47: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

46

DISCUSSION

Summary of the experimental results

From all the data collected during 10 days of monitoring, one queasy steady-state per day was

selected to set up the numerical model. The results from monitoring after 4 days were starting to get

closer to the ones solved with the Built Model; this is due to the consolidation process, where

steady-state conditions cannot be applied. However, seepage results with SVFlux differed with the

monitoring values in 2 orders of magnitude. This is because there was leakage at the bottom and

sidewalls of the container which was not considered in the model. Nevertheless, the Built Model

provided approximately the same results of pore-water pressure at 5 out of 6 piezometers installed

within the dam at the 10th day, giving a 9% relative error of the pore-water pressure at the right core

piezometer. The pore water pressure at the right core piezometer was presumably higher because

the piezometers pipelines were seeping water from the right sidewall, i.e., leakage (See Figure 5 and

6). Since the other two core piezometers were further from the right sidewall, the water coming

from the right side wall did not seep until those points. It was this anomaly what determined the

location of the leakage. SVSolid, provided nearly (See Figure 29) similar results of maximum

deformation obtained with laser scanning after 10 days, even though triaxial tests were not

performed to set up the hyperbolic model of the soils.

Summary of the results from the analysis of the internal erosion factors

Having verified the model with the experimental results, the factors of internal erosion were

analysed, providing also the location where the dam failure could occur due to a combination of all

the factors. The results are summarized below.

Material susceptibility

Filter assessment was carried out to verify both the filter criteria and the internal stability of the

soils. Even though the filter criterion was fulfilled, the filter assessment indicated an increased risk of

initiation and continuation of internal erosion by suffusion for the pipe inserted; moreover, the filter

was unstable; and there was a neutral risk of continuation of erosion for the core. Also there was no

filter at the top layer. Thus, contact erosion in the core-filter interface and concentrated leaks can be

developed through cracks from desiccation or settlements at the crest (Fell et al., 2008). The pipe

inserted is potentially more likely to develop suffusion and global backward erosion, however

hydraulic conductivity is very low, so it will take a long time for seepage to pass through the pipe.

Nevertheless, monitoring results and observations unveiled initiation signs from day 3 until day 10

(See Figure 49). This was not rare considering the poor compaction of the dam. Potentially, contact

erosion and suffusion at filter/core boundary between layers may have been initiated due to the

“Christmas tree” effect (See Figure 4). In fact, at some points the filter was very thin (< 15 cm) letting

the core material pass through. Soils were considered to be of low plasticity despite laboratory tests

were not performed. Hence, backwards erosion can occur (Fry, 2007). Therefore the crest is

considered the weakest part regarding to this factor. There is an extra risk for concentrated leaks

due the acoustic emission sensor placed at the right top of the embankment. This device might have

caused cracks with the three steel rods inserted and its own weight, which seems to have caused a

differential settlement (See Figures 27 and 28).

Page 48: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

47

Hydraulic load

On the one hand, hydraulic gradients were ascendant with the height of the core, reaching a

maximum of 5.15 at 147 cm, at the unsaturated top layer. So, considering that tests performed with

glacial tills by Hunter and Fell (2012), initiated and progressed backward erosion at hydraulic

gradients higher than 5. On the other hand, the saturated area at the right abutment had higher

seepage forces. Hence, the right abutment at the crest is potentially a critical zone of failure. The

pipe inserted to test development of GBE did not provide relevant results in the seepage analysis

with FEM; hence it was unlikely to develop internal erosion mechanisms within the time of the

experimentation.

Critical stress state

The maximum vertical total stress was concentrated downstream at the filter foundation (arching

effect occurs); hence no critical condition was detected at the foundation in this case. Thus, slopes

and crest were at low stress state, being the crest the main area of concern since the slopes were

assessed at design’s phase. The upstream core indicated low local factor of safety. So, there was risk

of slope instability of small external slices at crest level upstream, moreover maximum deformations

were located in the rock fill upstream at the abutments. Thus, the core was exposed to shear failure

at the top 7-10 cm. Furthermore, minimum principle stresses (S3) decrease with the height at the

core, where if the pore water pressure becomes higher than S3, hydraulic fracture can occur.

Therefore, there was a flaw within the crest zone, particularly at the right abutment.

Failure Mode Analysis

At the failure mode analysis, it was analysed which failure mechanism would breach the dam, and

where; for three different cases of the experiment: 1) constant water level; 2) slow filling; and 3)

rapid filling (tested). The assessment concluded that the most likely failure mode was for a rapid

filling. The failure mode analyses are explained below:

Firstly, if the experiment was kept at constant water level (h=124 cm). In this case, initiation of internal erosion was detected during monitoring, indicating high turbidity, seepage and deformations, particularly at the right abutment. However, the risk of development of a pipe at this water level was low for the short-term of the experiment, because the hydraulic gradient was lower than 3, the pore-water pressure was low to overcome the stress state conditions and there was a filter downstream the current seepage path. Secondly, if the water level rises slowly from current level, the initial stress condition will change due to the increment of pore-water pressure. Although, hydraulic gradients for the initiation of suffusion under compression stress conditions generally increase with the shear stress ratio [1], and then decrease when the soil approaches shear failure (Chang, 2013). In this case, higher compression occurs at the right abutment (highest deformations) but hydraulic gradients increase with the height of the head, up to 5.15, at 147 cm height. Thus, the conditions for development of suffusion at crest level under compression states will remain for a long experimentation as long as the hydraulic gradients are high. Moreover, there was no filter at the crest. And even though the core resulted to be internally stable with Kenny and Lau method, the surveillance detected that initiation occurred. So, suffusion was more likely to occur at a higher rate at the crest than at the pipe inserted. Therefore, piping could have occurred at the right abutment due to suffusion for a slow filling test.

Page 49: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

48

Finally, the risk of hydraulic fracture (Sherard, 1986) is higher if the water level is suddenly increased

because then the core cannot leak off the water at the same rate is passing through the pores

spaces. This will easily increase the pore-water pressure to surpass the effective stress within the

poorly compacted soil, specifically on the right abutment at the crest.

As a result of the assessment for a rapid filling (final test performed at day 10), the failure mode stands on the right abutment, at the crest, due to three factors: 1)high seepage rate at high hydraulic gradients, 2) low stress condition with high deformations, and 3)internally stable, but with initiation records, cohesionless material with no filter downstream, and badly compacted with potential concentrated leaks (cracks).

[1] Shear stress ratio (η=q/p’) , q is the deviatoric stress (𝛔1 - 𝛔3); and p’ is the mean principal stress (𝛔1 + 2 𝛔3)/3.

Dam failure and event tree (Hypothesis verified)

The before mentioned failure mode analysis determined the location of the zone where the risk of

internal erosion could lead to piping and breach the dam. Thus, by breaching the dam it was verified

that piping occurred exactly where and how it was determined in the failure mode analysis (See

Figure 55). The dam failure is represented in an event tree, (See Figure 53) based on the generic

internal erosion failure mode of Fell et al., (2008).

Figure 55. Event tree of dam failure

Conclusion

It has been tested an embankment dam breaching due to internal erosion mechanisms. The

breaching mechanism was visible just 15 minutes prior to dam failure. With the analysis of the

factors of internal erosion, it has been possible to determine the exact location of the most likely

zone of internal erosion prior to breaching, confirming the hypothesis. However, only short-term

risks for a rapid filling have been tested to be detectable by this method. Long-term and other risks

were detected but not verified during the time of the experiment. For instance, low stress zones

could have been eroded more in a longer experiment without rapid filling (Bruthans J. S., 2014).

Reservoir rises • Rapidly!

Initiation was already visible

• Settlement

• High seepage

• Turbidity

Continuation

(no filter at crest)

• PWP is higher at right abutment

• Seepage flow increases

Progression

visible at the right abutment (crest)

• Roof forms to support a pipe

Dam breaches

• Collapse of the pipe

• Uncontrolled release of water occured at right abutment

Page 50: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

49

Moreover, material susceptibility, hydraulic conditions and stress condition were not investigated in

depth. This will require further research such as:

Laboratory experiments of triaxial tests considering internal erosion of Swedish glacial tills

(moraine) for stress analysis.

Transient seepage analysis.

3D modelling.

Temperature, resistivity and other parameters that can be considered to influence the

factors of internal erosion.

After completion of the experiment, potential findings can be described; First of all, according to the

hypothesis, it would be possible to analyse the risks of internal erosion within an existing

embankment dam. Second of all, this approach has determined that internal erosion may develop at

the core even if the assessment of the grain size distribution indicated that the soil was internally

stable (See Figure 33). Third of all, surveillance, soil testing and modelling can allow creating reliable

models of dams. Finally, from the literature review, it can be concluded that by analysing the factors

of internal erosion, a more accurate prediction of the failure mechanism can be obtained. Thus,

decide whether or not, safety measures should be taken into consideration at this respect. Hence,

safety measures can face more realistic consequences of internal erosion, and therefore reduce

potential risks and costs derived from conservative assumptions that do not guarantee the solution

of the problem.

On the other hand, many adversities need to be considered before to reach any potential findings

using these numerical methods. The programmer assumptions are always going to be predominantly

the main uncertainty while trying to extrapolate the interpretation of the results from any model to

reality. However, prior to breaching of any dam, uncertainties are primary the fact that it is not

possible to ensure exactly what occurs within the dam before and during a breach, only

interpretations from indirect measurements of parameters within the dam structure. For instance,

this failure mode analysis has been performed post-hoc, which allows always confirming

uncertainties rose during the experiment and discard others. In reality, there is no opportunity to

discard other uncertainties which usually leads to take conservative decisions in the risk analysis.

Inasmuch as the aim of the results was to identify the failure mechanisms prior to breaching. It is

more than likely that other failure mechanisms were missed in the failure mode analysis and were

developed in a longer duration of the experiment. Moreover, even if results showed those risks it

was not possible to guarantee the reliability of those interpretations at this stage.

Achievement of a reliable numerical model is not an easy task, but the practical applications of its

consecution are worth to bear in mind. The foremost advantages are obviously regarding to assess

the safety of existing dams. Nevertheless, future construction of these types of dams could be

improved due to recommendations to avoid failures and providing a safer instrumentation.

Moreover, new guidelines of safety of dams could apply these models to explain the failure

mechanisms. In this particular case, this research provided in-data and set the requirements to

improve the reliability of the risk analysis using modelling in future research. In which, more cases of

dam’s breaching tests will unveil more risks of internal erosion and contrast theories and methods.

Page 51: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

50

REFERENCES

Stanford.edu;. (2014, 08 25). stanford.edu. Retrieved 2014, from GeoPhysics:

https://web.stanford.edu/~tyzhu

Bergh, H. (2014). Hydraulic Engineering course compendium.KTH, Stockholm.

Bligh, W. (1910). Dams, barrages and weirs on porous foundations. Engineering News, 64(26), 708-

710.

Bonelli, S., Brivois, O., Borghi, R., & Benahmed, N. (2006). On the modelling of piping erosion.

Comptes Rendus Mecanique, 334(8), 555-559.

Bowles et al., (2013). Risk Assessment in Dam Reservoir Safety Management. Bristol, UK:

Environment Agency ISBN: 978-1-84911-295-6.

Bowles, J. (1997). Foundation Analysis and Design. McGraw-Hill .

Bridle, R., Delgado, F., & Huber, N. (2007). Internal erosion: continuation and filtration current

approaches illustrated by a case history. Assessment of the Risk of Internal Erosion of Water

Retaining Structures: Dams, Dykes and Levees. Munich: Intermediate Report of the Working

Group of ICOLD Deutsches Talsperren Komitee, Technical University of Munich.

Brown, A. J., & Tedd, P. (2003). Probability of a safety incident at an embankment dam based on

historical data. J Hydropower and Dams, 10 (2), 122-126.

Bruthans, J., Soukup, J., Vaculikova, J., Filippi, M., Schweigstillova, J., Mayo, A. L., ... & Rihosek, J.

(2014). Sandstone landforms shaped by negative feedback between stress and erosion.

Nature Geoscience, Letter, 7(8), 597-601.

Chang, D. S. (2013). Critical Hydraulic Gradients of Internal Erosion under complex stress states.

Journal of Geotechnical and Geoenvironmental Engineering -ASCE,139(9), 1454-1467.

Charles, J. A. (1996). Investigating embankment dams. A guide to the identification and repair of

defects. Wattford: Building research Establishment Report.

Duncan, J. M., & Chang, C. Y. (1970). Nonlinear analysis of stress and strain in soils. Journal of the Soil

Mechanics and Foundations Division, 96(5), 1629-1653.

Ekström, I. (2012). Recent dam incidents and failures in Sweden. ISCSE6-299. Paris.

Evans, S. G. (1986). The maximum discharge of outburst floods caused by the breaching of man-

made and natural dams. Canadian Geotechnical Journal, 23(3), 385-387.

Fell et al., (2008). A Unified Method for Estimating Probabilities of Failure of Embankment Dams by

Internal Erosion and Piping” Draft Guidance Document dated . CORPS of ENGINEERS, URS,

UNSW.

Fell, R. W. (2003). Time for development of internal erosion and piping in embankment dams.

Journal of Geotechnical and Geoenvironmental Engineering, 129(4), 307-314.

Page 52: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

51

Foster, M. Fell, R. (2001). Assessing embankment dam filters that do not satisfy design criteria.

Journal of Geotechnical and Geoenvironmental Engineering, 127(5), 398-407.

Fredlund, D. G., Xing, A., & Huang, S. (1994). Predicting the permeability function for unsaturated

soils using the soil-water characteristic curve. Canadian Geotechnical Journal, 31(4), 533-

546.

Fry, J. J. (2007). Current practice and new view on granular filter. Freising. Germany, 60-69: ICOLD.

Garner and Fannin. (2010). Understanding internal erosion: a decade of research following a

sinkhole event. International Journal on Hydropower and Dams, 17(3), 93-98.

Geotechdata.info. (2013, 09 17). Geotechdata.info. Retrieved from soil young’s modulus,:

http://geotechdata.info/parameter/soil-elastic-young-modulus.htm

Hunter, G., Fell, R., & Topham, C. (2012). Backward Erosion Piping: What are the chances of that?

ICOLD. (2013). Bulletin 164:Internal erosion of existing dams, levees, and dikes, and their

foundations. ICOLD.

Johansson, S. (1997). Seepage monitoring in embankment dams. Stockholm: Doctoral Thesis, KTH.

Kenney, T. C., & Lau, D. (1985). Internal stability of granular filters. Canadian Geotechnical Journal,

22(2), 215-225.

Kraftnät, S. (2011). Review of the Swedish System for Dam Safety. Reg. nr. 2010/877.

Krahn, J. (2004). Seepage modeling with SEEP/W. Geo-Slope International Ltd.

Lane, E. (1935). Security from under-seepage masonry dams on earth foundations. ASCE

Transactions, (1919), 1235.

Morris, M. H. (2008). Improving the accuracy of breach modelling: why are we not progressing

faster? J. Flood Risk Management, 1(3), 150-161.

Nilsson, Å. E. (1999). Sinkholes in Swedish embankment dams. Elforsk Resport 99:34.

Peck, R. B. (1969). Advantages and limitations of the observational mehtod in applied soil mechanics.

Geotechnique, 19(2), 171-187.

Radzicki, K. &. (2010). Thermical seepage monitoring in the earth dams with impulse Response

Function Analysis Model. . Dam Safety sustainability in a changing environment. 8th ICOLD

European Club symphosium, (pp. 22-23).

RIDAS. (2011). Kraftföretagens riktlinjer för dammsäkerhet (RIDAS) - Fyllningsdammar. Avsnitt 7.2.

Svensk Energi.

Rönnqvist, H., (2007). Assessing the Potential for Internal Erosion in Glacial Moraine Core

Embankment Dams. International Conference on SMall Hydropower. Sri Lanka: Kandy.

Page 53: Modelling Internal Erosion Within An Embankment Dam …kth.diva-portal.org/smash/get/diva2:783478/FULLTEXT01.pdf · Modelling Internal Erosion Within An Embankment Dam ... Modelling

52

Rönnqvist, H., Fannin, J., & Viklander, P. (2014). On the use of empirical methods for assessment of

filters in embankment dams. Géotechnique Letters, 4(October-December), 272-282.

Shantz, T., Vermeer, P. A., & Bonnier, P. G. (1999). The hardening soil model:formulation and

verification. Beyond 2000 in computational geotechnics, 281-296. Balkema, Rotterdam.

Schmertmann J H. (2002). A method for assessing the relative likelihood of failure of embankment

dams by piping: Discussion. Canadian Geotechnical Journal, 39(2): 495-496.

Sellmeijer, J. B., & Koenders, M. A. (1991). A mathematical model for piping. Applied Mathematical

Modelling, 15(11), 646-651.

Sherard, J. L. (1986). Hydraulic Fracturing in Embankment Dams. ASCE Journal of Geotechnical

Engineering, 112(10), 905-927.

Sherard, J. (1979). Sinkholes in dams of coarse, broadly graded soils. 13th Int. Congress on Large

Dams (pp. Q47, R2, 325-334.). New Delhi: International Comission on Large Dams. Paris.

Sherard, J., & Woodward, R. G. (1963). Chapter 2 part 5. In Earth and Earth Rock Dams. New York:

John Wiley and Sons.

Sjödahl, P. D. (2010). Using resistivity method for leakage detection in a blind test at the Rossvatn

embankment dam test facility in Norway. Bulletin of Engineering Geology and the

Evironment, 69(4), 643-658.

Skempton, A. W. (1994). Experiments on piping in sandy gravels. Geotechnique, 44(3), 449-460.

SoilVision. (2014). Theory Manuals of SVSolid, SVFlux and SVSlope. Saskattoon: SoilVision Systems.

Solava, S. D. (2003). Lessons from the Failure of the Teton Dam. In Forensic Engineering. ASCE, 178-

189.

Terzaghi and Peck. (1948). Soil Mechanics in Engineering Practice. New York: Wiley International.

Terzaghi, K. P. (1996). Soil mechanics in engineering preactice. 3rd ed.page 477. New York: John

Wiley & Sons.

Wan, C. F., & Fell, R. (2004). Investigation of rate of erosion of soils in embankment dams. Journal of

Geotechnical and Geoenvironmental Engineering, 130(4), 373-380.

Vattenfall. (1988). Filter Criteria. In Jord- Och Sten- Fyllningsdammar (p. Table 2.3 pp 60.).

Dong, W., Hu, L., Yu, Y. Z., & Lv, H. (2013). Comparisson between Duncan and Chang’s EB Model and

the Generalized Plasticity Model in the Analysis of High Earth-Rockfill Dam. Journal of

Applied Mathematics, 2013 (2013).

Xu, Y., & Zhang, L. M. (2009). Breaching parameters for earth and rockfill dams. Journal of

Geotechnical and Geoenvironmental Engineering, 135(12), 1957-1970.