Project name: BEJO VIET NAM PRODUCTION FARM Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LT, TNH LÂM ĐỒNG MONTHLY PROGRESS REPORT No.08 OCTOBER 2014 MAIN CONTRACTOR: TAN VIET TIN CONSTRUCTION CO. LTD CONTRACT PARTICULAR: 1. Site possession : 07March, 2014 2. Completion date : 11 October, 2014 3. Contract period : 219 Days ( 7.3 months ) Prepared by: TAN VIET TIN CONSTRUCTION CO. LTD Verified by Bejo’s Supervise Name: Le Nam Trung Name: Date: October, 2014 Date

MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

Project name: BEJO VIET NAM PRODUCTION FARM

Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG

MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014

MAIN CONTRACTOR:

TAN VIET TIN CONSTRUCTION CO. LTD

CONTRACT PARTICULAR:

1. Site possession : 07March, 2014 2. Completion date : 11 October, 20143. Contract period : 219 Days ( 7.3 months )

Prepared by: TAN VIET TIN CONSTRUCTION CO. LTD

Verified by Bejo’s Supervise

Name: Le Nam Trung Name: Date: October, 2014 Date

Page 2: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

TABLE OF CONTENT Num Page Page

1 PROJECT INTRODUCTION 0 6

2 PROJECT EXECUTIVE SUMMARY 2 8

3 PLANNING REVIEW 4 12

4 PROGRESS WORKS PROGRAMME 2 14

5 WEATHER 3 17

6 MANPOWER RECORD 2 19

7 PLANT & MACHINERY RECORD 2 21

8SUMMARY OF VO 2 23

SUBMITTALS 1 24

A. C&S - SHOPDRAWING REGISTER 1 25

B. C&S - APPROVED SAMPLE/TECHNICAL DATA REGISTER 1 26

A. M&E - SHOPDRAWING REGISTER 2 28

B. M&E - APPROVED SAMPLE/TECHNICAL DATA REGISTER 2 30

10 VARIATIONS AND CLAIMS 1 31

11 HSE REPORT 2 33

12 PROGRESS PHOTOGRAPHS 1 34

TABLE OF CONTENT

9

Page 3: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

PROJECT BRIEF:

Project name: BEJO VIET NAM PRODUCTION FARM

Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG

Owner: BEJO VIET NAM PRODUCTION FARM 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG TEL: 0633.520.337 Project management: VIETNAM PROJECT CONSULTANTS Co. LTD

Design Consultant: THIEN NAM DESIGN CONSUTANCY JSC. 12 YERSIN P10 DA LAT – LAM DONG TEL: 0633577646 Main Contractor: Tan Viet Tin Construction Co., Ltd 456 Nguyen van Luong St, Ward 12, Dist 6, Ho Chi Minh City, Vietnam Email: [email protected] Tel: +84-8.37511384 - +84-8.38756934 Fax: +84-8.37511383 Tax code: 0302227857

Page 4: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111
Page 5: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

Project name: BEJO VIET NAM PRODUCTION FARM

Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG  

Executive summary: 

  Commencement date:  07 March, 2014 

  Completion date :         11 October, 2014 

  Contract period    :          219 days (7,3 Months) 

  Elapsed                 :         219 days ( 7,3 months) 

  Remaining            :        0 days ( 0  months)  

 

Page 6: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

Project name: BEJO VIET NAM PRODUCTION FARM

Location: 51 ĐƯỜNG HÙNG VƯƠNG, PHƯỜNG 9 ĐÀ LẠT, TỈNH LÂM ĐỒNG

Report on overall work done till 30th October 2014 

Month  Schedule Actual work done 

Ahead/Delay

March, 2014  3%  3%  0% ( 0 day) 

April, 2014  11%  10%  ‐1% (2days) 

May, 2014  30%  30%  ‐0% (0days) 

June, 2014  44%  41%  ‐3% (7days) 

July, 2014  65%  57%  ‐8% (16days) 

August, 2014  86%  72%  ‐14% (28days) 

September, 2014  92%  90%  ‐2% (4days) 

October, 2014  100%  92%  ‐8% (16days) 

 

 

 

Page 7: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111
Page 8: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111
Page 9: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

2 Site Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

3 Q.A & Q.C 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

4 Safety Officer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

5 Site Engineer ( C&S ) 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

6 Accountant 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

7 Foreman 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 3 3 3 3 3 3 3 3 3

8 Surveyor and Helper 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

9 Site Engineer (M&E) 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

11 Labour (C&S) 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 65 54 55 55 55 43 43 30 30 30

12 Labour (M&E) 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 8 8 8 8 8 8

93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 81 82 82 81 69 69 56 56 56

744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 744 648 656 656 648 552 552 448 448 448

TAN VIET TIN CONSTRUCTION CO., LTD.456 Nguyen Van Luong ST, Ward 12, Dist 6, HCMC

T: +84-8375-11384 Fax: +84-8375-11383

MANPOWER RECORD

Project : NTPM ( Viet Nam) Factory.

TOTAL

TOTAL HOURS

No. DESCRIPTION

Page 10: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

1 Welding Machine 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 32 Bar Bending Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 13 Bar Cutting Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14 Concrete Truck 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 15 Truck 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 16 Roller Compactor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17 Heavy duty Truck 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 08 Leveling Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 19 Excavator 2 2 2 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 310 Theodolite 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 211 Water Pump 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 412 Vibrator 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 313 Hand compaction machine 2 2 2 2 2 2 2 2 2 2 2 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 414 Mortar mixer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 115 Sewing Machine 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4

TAN VIET TIN CONSTRUCTION CO., LTD.456 Nguyen Van Luong ST, Ward 12, Dist 6, HCMCT: +84-8375-11384 Fax: +84-8375-11383

Project : BEJO VIET NAM PRODUCTION FARM

No. DESCRIPTION

PLANT & MACHINERY RECORD

Page 11: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

08. SUMMARY OF VO 

Page 12: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

THE QUOTATION FOR ADDITIONAL WORKS

NO NAME ITEMS SUBMITTED DATE APPROVED DATE

1 TEMPORARY TOILET FOR WORKERS 28/10/2014

2

3 CONCRETE SLAB FOR IRRIGATION ROOM 6/8/2014 7/8/2014

4 FOUNDATION OF CONDENSER UNIT 10 HP ( COOL ROOM) 7/8/2014 8/8/2014

5 ELECTRIC WORKS TO COOL ROOM 15/8/2014 19/8/2014

6 PUMP PIT AND WATER CHANNEL 11/9/2014 12/9/2014

7 LAVABO STAINLESS STEEL AND GREASE TRAP 12/9/2014 12/9/2014

8 MCCB FOR DB7 12/9/2014 12/9/2014

9 AIR CONDITION 12/9/2014 12/9/2014

10 NETWORK SYSTEM 8/10/2014 8/10/2014

11 CCTV SYSTEM 13/10/2014 18/10/2014

12 CABLE FROM ATS TO MDB 8/10/2014 15/10/2014

13 BEAMER AND SCREEN 10/10/2014 17/10/2014

14

15 SLIDING GATE ‐ AUTOMATIC SYSTEM 4/11/2014 7/11/2014

16 INSTALLATION SOCKET 3 PHASE FOR SEED PROCESSING SHED 4/11/2014 7/11/2014

17 WATER HEATER AND SMALL CABLE 4/11/2014 7/11/2014

18 EXHAUST AIR IN TOILET GREEN HOUSE SHED 5/11/2014

19 ADDITIONAL FENCING  5/11/2014 6/11/2014

20

21 HIT SOAP BOX 13/11/2014 13/11/2014

22

Page 13: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

NO DESIGNTION DRAWING NO TITTLE1 OTHERS SD-02 EXISTING GROUND LEVEL OF CANTEEN, MAIN STORE, SEED

PROCESSING SHEDSD-04 FINISHING LEVEL OF (INTERNAL) ROAD (4m) IN FRONT OF RAM-

UP (OF GREENHOUSE SHED)SD-05 PROPOSED THE FINISHING LEVEL OF MAIN ROAD (A TO E)SD-07 GREEN HOUSE SHED, MAIN STORE, SEED PROCESSING SHED -

GROUND FLOORSD-08 WATER CHANNEL PLAN AND DETAIL ( ALONG MAIN ROAD)SD-11 FINISHING LEVEL - INTERNAL ROAD (4M) - ALL ROAD

SD-14FINISHING LEVEL - 2M ROAD (NEAR THE FENCE) - BICYCLE ROAD

SD-23 ROOF SHEET FOR GUARD HOUSE AND TOILET & STORE

SD-25 INTERNAL ROAD DETAIL

SD-26 MAIN GATE AND GUARD HOUSE DETAIL

SD-27 IRRIGATION ROOM FLOOR SLAB

SD-28 PUMP PIT

SD-35 SOIL EXCAVATION LEVEL INTERNAL ROAD 4000 mmSD-36 ALUMINUM LOUVER FOR OFFICE BUILDING, GUEST HOUSE,

CANTEENSD-42 MAIN ROAD AND ROAD 2000 mm

SD-50 CAR & MOTOBIKE PARKING

SD-51 EXISTING SOIL LEVEL AT MOTOBIKE PARKING

SD-52 100 MM CONCRETE REMAINING FOR 4 M ROADSD-56 FLAG POLE DETAILSD-59 SIGNBOARD DETAIL FOR MAIN GATE

SD-61 ADDITIONAL FENCING NEAR MAIN GATE

2 MAIN STORE SD-12 ARCHITECTURESD-29 LOUVER AND DOOR SD-30 CEILING PLAN

SD-31 MACHINCE SLAB FOR COLD ROOM

SD-48 BEHIND ENTRANCE

3 GREEN HOUSE SHED SD-03 GROUND BEAMS AND SLAB SD-06 RAM UPSD-20 ROOF SHEET AND CANOPYSD-24 BREACING BEAM ON GREEN HOUSE SHED ROOF TOP (Rejected)

SD-33 OUTSIDE STEEL STAIRCASE GL:1 GREEN HOUSE SHEDSD-36 GALVANIZED STAIR-CASE (INSIDE)

SD-37 GREEN HOUSE SHED CEILING

SD-43SPECIFICATION AND SHOP DRAWING FOR SANDWICH PANELS IN GREEN HOUSE SHED

SD-44 LIGHT GREY RESIN FOR 2nd FLOOR

SD-53 HAND WASHING SINK

4 TOILET AND STORE SD-01 FOOTING AND GROUND BEAMSD-09 ARCHITECT SD-10 GROUND FLOORSD-16 EXISTING LEVEL

C & S SHOP DRAWING

Page 14: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

SD-21 ENTRANCE

5 SEED PROCESSING SHED SD-13 DRAIN DETAILSD-17 BRACING BEAMS

6 CANTEEN SD-15 GROUND FLOORSD-18 DRAIN DETAIL (Omitted)SD-32 ROOF EAVES DETAIL (Rejected)SD-44 ENTRANCESD-45 GAS STORAGE

7 PUMP HOUSE SD-22 ROOF SHEET

8 GUEST HOUSE SD-46 STONE ARRANGEMENTSD-54 DETAIL CEILING AT STAIR-CASESD-62 TILING WORKS FOR TOILET WALL UNDER STAIRCASE

9 OFFICE BUILDING SD-41 ALUM DOOR FOR DOOR: D2, FIXED WINDOW: VK1, VK2

Page 15: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

NO NAME ITEMS SUPLLIER BUILDINGS COMMENTS ATTACHED WITH STATUS SUBMITTED DATE

APPROVED DATE

MSA/TVT/001

THE CATALOG FOR STEEL BAR FORM POMINA

POMINA ALL BUILDINGS PLEASE SAMPLES FOR TESTING - RANDOM SIZES 12 MM BAR & 16 MM BAR TENSILE TEST ONLY …PLEASE PROVIDE " TAGS & CERTIFICATE".

CATALOGUES APPROVED ON CONDITION, AS NOTED

27/2/2014 27/2/2014

PICS ATTACHED

MSA/TVT/002

THE CONCRETE GRADE DESIGN 10MPa, 15MPa, 20MPa, 25MPa, 30MPa

ALL BUILDINGS SPECIFICATIONS AND TEST REPORTS

APPROVED 27/2/2014 27/2/2014PICS

ATTACHED

MSA/TVT/003

BACKFILL SOIL FOR FACTORY AND ROAD

FOUNDATION, GROUND SLAB, ROAD

PLEASE GIVE COPY OF DELIVERYNOTES TO BEJO (GEOFF) THESE DELIVERY NOTE SHALL TONAGE (AMOUNT OF SOIL + DATE DELIVERY)

SAMPLES APPROVED 4/3/2014 4/3/2014

PICS ATTACHED

MSA/TVT/004

GALVANIZE STEEL TO BE USED FOR FOOTING SYSTEM

TIEN PHONG ADD BUILDINGS CATALOGUES APPROVED21/3/2014 21/3/2014

PICS ATTACHED

MSA/TVT/005

ANTI-TERMITE TREAMENT CHEMICAL

FOUNDATION & GROUND FLOOR FOR ALL BUILDINGS

TEST REPORTS APPROVED 24/3/2014 24/3/2014PICS

ATTACHED

MSA/TVT/006

ANCHOR BOLTS M16, ANCHOR BOLTS M20.

SUBCONTRACTOR - BMB

ALL BUILDINGS STEEL STRUCTURE

SAMPLES APPROVED 1/4/2014 1/4/2014PICS

ATTACHED

MSA/TVT/007

INSULLATION 1 SIDE ALU-POLYNUM (REFER TO SAMPLES)

CAT TUONG ROOFING SYSTEM FOR ALL BUILDINGS ( MAINSTORE AND SEED PROCESSING SHED)

SAMPLES + TEST REPORTS + CATALOGUES

APPROVED 1/4/2014 1/4/2014

PICS ATTACHED

MSA/TVT/008

SKYLIGHGT TO BE USED FOR ROOFING SYSTEM

NAM VIET MAIN STORE AND SEED PROCESSING SHED

COLOR OPAL CATALOGUES (COLOR CHART)

APPROVED 1/4/2014 2/4/2014PICS

ATTACHED

MSA/TVT/009

PAINTING FOR STEEL STRUCTURE

DONASA ALL BUILDINGS (MAIN STORE AND SEED PROCESSING SHED)

COLOR NO 3076 SILVER CATALOGUES APPROVED 1/4/2014 2/4/2014

PICS ATTACHED

MSA/TVT/010

COLOUR CHART TO BE USED FOR MAIN STORE AND SEED PROCESSING SHED DOOR

TNP & HD MAIN STORE AND SEED PROCESSING SHED

M9029A TO BE USED OVERHEAD DOOR SLIDING DOOR MADE OUT OF PANELSO HAVE PANEL COLOR

CATALOGUES APPROVED 20/5/2014 20/5/2014PICS

ATTACHED

MSA/TVT/011

WELDMESH TO BE USED FOR GROUND FLOOR

SONG HOP LUC

CATALOGUES + SPECIFICATION + TEST

APPROVED 28/5/2014 4/8/2014PICS

ATTACHED

MSA/TVT/012

HOLLOW AND SOILD BRICKS ALL BUILDINGS SAMPLES APPROVED 29/5/2014 29/5/2014 PICS ATTACHED

MSA/TVT/013

NATURAL STONE TO BE USED FOR WATER CHANNEL

LOCAL WATER CHANNEL

SAMPLES APPROVED 29/5/2014 29/5/2014 PICS ATTACHED

MSA/TVT/014

CONCRETE BLOCK MAIN STORE SAMPLES APPROVED 29/5/2014 29/5/2014 PICS ATTACHED

MSA/TVT/015

TILES ROOFING LAMA CANTEEN, GUEST HOUSE, OFFICE BUILDING

L104 - CHARCOAL TO BE USED CATALOGUES, SPECIFICATION, SAMPLE

APPROVED AND APPROVED ON CONDITION, AS NOTED

5/6/2014 10/6/2014PICS

ATTACHED

MSA/TVT/016

ROOF SHEET'S COLOUR CHART HOA SEN GREEN HOUSE SHED, GUARD HOUSE, TOILET, PUMP HOUSE.

BBL01 TO BE USED SAMPLES APPROVED 9/6/2014 9/6/2014PICS

ATTACHED

MSA/TVT/017

ROOF AND WALL SHEET HOA SEN MAIN STORE, SEED PROCESSING SHED.

BBL01 TO BE USED SAMPLES APPROVED 4/4/2014 4/4/2014PICS

ATTACHED

MSA/TVT/018

PVC SHEET TVT GROUND FLOOR - ALL BUILDINGS

SAMPLES APPROVED 1/6/2014 1/6/2014 PICS ATTACHED

MSA/TVT/019

DOWER BAR D16 TVT CONSTRUCTION JONT - ALL BUILDINGS

SAMPLES APPROVED 20/6/2014 20/6/2014PICS

ATTACHED

MSA/TVT/020

WALL SHEET'S COLOUR CHART HOA SEN SAME COLOR WITH FOOR SHEET BMB

SAMPLES APPROVED 9/6/2014 9/6/2014 PICS ATTACHED

MSA/TVT/021

INTERNAL AND EXTERNAL PAINTING

SONATA GUEST HOUSE, OFFICE, GREEN HOUSE SHED, CANTEEN, TOILET & STORE, GUARD HOUSE, PUMP HOUSE.

CATALOGUES, SPECIFICATION.

APPROVED 16/7/2014 4/8/2014

PICS ATTACHED

MSA/TVT/022

TILES FOR FLOOR AND WALL AMERICAN HOME VIET NAM

GREEN HOUSE SHED, CANTEEN, TOILET AND STORE

MICHIGAN 2525 FOR SHOWER AREAS + MICHIGAN 02-2540 FOR OTHERS MORE CATALOGUES/ SAMPLES REQUIRED

CATALOGUES, SPECIFICATION.

APPROVED 29/7/2014 19/8/2014PICS

ATTACHED

MSA/TVT/023

EPS SANDWICH PANEL , 50 MM THICKNESS

VIET NAM MAIN STORE CATALOGUE + SAMPLE

APPROVED 31/7/2014 1/8/2014 PICS ATTACHED

MSA/TVT/024

ALUM CEILING ALUKING OFFICE AND GUEST HOUSE'S TOILET

COLOR TO BE AK009 AS PER SPEC BY HKAP3

CATALOGUE AND SAMPLE

APPROVED 14/8/2014 19/8/2014PICS

ATTACHED

MSA/TVT/025

SINGLE FLUSH WOODEN DOOR (MDF TEAK VENEER). DOUBLE FLUSH GLASS DOOR

VIET NAM OUTSIDE GUEST HOUSE, INSIDE OFFICE AND GUEST HOUSE

SAMPLES APPROVED 18/8/2014 25/8/2014PICS

ATTACHED

MSA/TVT/026

PHENOLIC PARTITION SHED , 10 mm THICKNESS IN WC

THIEN QUY GREEN HOUSE SHED, CANTEEN, TOILET AND STORE

COLOR AS PER SAMPLE STAINLESS STEEL SERIES OT.10B

CATALOGUE AND SAMPLES

APPROVED 18/8/2014 19/8/2014PICS

ATTACHED

MSA/TVT/027

PAINTING COLOR INTERNAL AND EXTERNAL BY THIEN NAM ARCHITECTURE DESIGNER

SONATA ALL BUILDING EXCLUDED COLORS SELECTED BY HKAP3 FOR INTERNAL DESIGN. INTERNAL SI206 EDWARDIAN LACE TO BE USED

CATALOGUE APPROVED 18/8/2014 19/8/2014PICS

ATTACHED

MSA/TVT/028

COMPOUND STONE VU HIEP PHAT

OFFICE, GUEST HOUSE, GREEN HOUSE SHED, CANTEEN.

HP120 GUEST HOUSE BOTTOM PART, SEE MARKED * THIS ONE IN CATALOGUES FOR COLUMNS OFFICE

CATALOGUE + SAMPLES

APPROVED 19/8/2014 22/8/2014PICS

ATTACHED

MSA/TVT/029

SPECIFICATION AND SHOP DRAWINGS FOR THE SANDWICH PANEL IN GREEN HOUSE SHED 100 mm AND 50 mm THICKNESS

METECNO VIET NAM

LAB ROOM GREEN HOUSE SHED

FIRE RATED PANELS TO BE STEEL SHEET BOTH SIDES.

CATALOGUE + SHOP DRAWING + SPECIFICATION

APPROVED 25/8/2014 29/8/2014PICS

ATTACHED

C & S SUBMISSION

Page 16: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

MSA/TVT/030

TEAK NATURE WOOD 23 mm THICK (STAIR-CASE). TEAK NATURE WOOD 155 mm THICK (WALL AREA INSIDE)

VIET NAM OFFICE BUILDING, GUEST HOUSE.

SAMPLES APPROVED 25/8/2014 25/8/2014PICS

ATTACHED

MSA/TVT/031

MARBLE 67 (800 × 800 × 20) mm 

THICK. (GROUND FLOOR) . GRANIT 28 

(600 × 300 × 20)mm THICK (BALCONY 

AREA). GRANIT 95 20 mm THICK 

(BOTTOM DOOR). 

VIET NAM OFFICE BUILDING, GUEST HOUSE.

SAMPLES APPROVED 25/8/2014 25/8/2014

PICS ATTACHED

MSA/TVT/032

CERAMIC TILE (250 × 400) mm AT 

KINCHEN WALL AREA. CERAMIC TILE 

(300 × 300) mm AT WASHING FLOOR 

AREA.

VIET NAM CANTEEN, GREEN HOUSE SHED

GREEN HOUSE SHED GROUND FLOOR: WASHING ROOM, TOILET, HALL, CHANGING ROOM

SAMPLES APPROVED 28/8/2014 30/8/2014PICS

ATTACHED

MSA/TVT/033

MDF TEAKWOOD FINISHING MALAYFLOOR

TRAINNING ROOM STAGE

MODEL DIAMOND CODE 788 (MALAYFLOOR)

SAMPLE APPROVED 9/9/2014 10/9/2014 PICS ATTACHED

MSA/TVT/034

PINE WOOD CANTEEN THE COLOR IS TOO LIGHT. MATERIALS CAN BE ORDERED BUT NEED ON SITE DARKER VERNIS FINISHING

SAMPLES APPROVED 24/09/2014 26/9/2014PICS

ATTACHED

MSA/TVT/035

GRANITE STONE FOR SIGNBOARD

MAIN GATE SUBMIT SAMPLE OF LETTERING ON GRANITE STONE

SAMPLE APPROVED 10/10/2014 11/10/2014 PICS ATTACHED

MSA/TVT/036

NATURAL STONE BROWN/ COPPERISCH

GUEST HOUSE COLUMNS

SAMPLE APPROVED 11/10/2014 11/10/2014 PICS ATTACHED

MSA/TVT/037

SLIDING DOOR HARDWARE D9 IN BATHROOM

GUEST HOUSE CATALOGUE APPROVED 13/10/2014 16/10/2014 PICS ATTACHED

MSA/TVT/038

DOOR HARDWARE HAFELE OFFICE, GUEST HOUSE, GREEN HOUSE SHED, CANTEEN.

CATALOGUE NOT APPROVED YET

18/10/2014PICS

ATTACHED

MSA/TVT/039

CERAMIC TILE (300 × 300) mm PORCELAIN

GUEST HOUSE TOILET FLOOR

SAMPLE APPROVED 18/10/2015 22/10/2014 PICS ATTACHED

MSA/TVT/040

VIET CERAMIC - GSB05 GUEST HOUSE KITCHEN WALL

SAMPLE APPROVED 18/10/2016 23/10/2014 PICS ATTACHED

MSA/TVT/041

WHITE-BLACK TILES/ 30Y01, 30Y06

OFFICE TOILET SIZE 100 × 100 SQUARE APPROVED ON CONDITION, AS NOTED

18/10/2017 22/10/2014PICS

ATTACHED

MSA/TVT/042

AM EXPOXICATE 403SM - RAL 7046, 7047

OFFICE, GREEN HOUSE SHED

BY PASCAL HKAP3 SAMPLE APPROVED 10/11/2014 12/11/2014 PICS ATTACHED

MSA/TVT/043

TEMPERED GLASS 10 mm THICK OFFICE, GUEST HOUSE, CANTEEN

SPECIFICATIONS AND TEST REPORTS

APPROVED 10/11/2014 12/11/2014PICS

ATTACHED

MSA/TVT/044

CEMENT BOARD CEILING, GYPROC REGULAR BOARD, MOISTURE RESISTANT, BOARD

OFFICE, GUEST HOUSE, GREEN HOUSE SHED, CANTEEN, TOILET & STORE

SAMPLES NOT APPROVED YET

18/10/2020

PICS ATTACHED

MSA/TVT/045

MDF MELAMINE FOR OFFICE & GUEST HOUSE CABINET

OFFICE AND GUEST HOUSE

SAMPLE APPROVED 22/10/2014 22/10/2014 PICS ATTACHED

MSA/TVT/046

PINE WOOD FOR CABINET GREEN HOUSE SHED

SAMPLE APPROVED 22/10/2014 22/10/2014 PICS ATTACHED

MSA/TVT/047

POLYCARBONATE EXTERNAL STAIRCASE ROOF GREEN HOUSE SHED

SAME MATERIALS TO BE USED AS EXISTING ROOF

CATALOGUE, SAMPLE

REJECTED 22/10/2014 23/10/2014PICS

ATTACHED

MSA/TVT/048

WHITE MARBLE OFFICE STAIRCASE

AS PER SIGNED SAMPLE SAMPLE APPROVED 6/11/2014 6/11/2014 PICS ATTACHED

MSA/TVT/049

STONE FOR KITCHEN COUNTER AND MELAMIN FOR CABINET

OFFICE, GUEST HOUSE

BY PASCAL HKAP3 SAMPLES APPROVED 10/11/2014 12/11/2014 PICS ATTACHED

Page 17: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

NO DESIGNATION DRAWING NO TITLE

0MAIN DISTRIBUTION BOARD - MDB

TEST REPORT

GALVANOMETER TEST REPORTS

COMPLETE SHOP DRAWING

1 OTHERS M&E/TVT - 008 POWER SUPPLY MASTER PLAN

M&E/TVT - 027 LOCATION INSTALLATION GROUNDING FOR DISTRIBUTION BOARD

M&E/TVT - 029 WATER SUPPLY MASTER PLAN

M&E/TVT - 030 CCTV MASTER PLAN AND SINGLE LINE CCTV

M&E/TVT - 031 SINGLE LINE TEL AND DATA (OVERVIEW)

M&E/TVT - 039 LIGHTING, SOCKET, DATA IN GUARD HOUSE

M&E/TVT - 043 LIGHTNING SYSTEM FOR BUILDING FROM IRRIGATION ROOM UNTIL MAIN ROAD AND SEED PROCESSING SHED

M&E/TVT - 045 MOTOR FOR SLIDING SYSTEM( SYSTEM SLIDING GATE) MAIN GATE

2 CANTEEN M&E/TVT - 007 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN

M&E/TVT - 015 POWER SOCKET OUTLET LAYOUT PLAN

M&E/TVT - 016 DATA & TEL SOCKET OUTLET LAYOUT PLAN

M&E/TVT - 023 LIGHTING LAYOUT PLAN FOR CANTEEN

M&E/TVT - 028 WATER DRAIN FROM ROOF TO GROUND

3 MAIN STORE M&E/TVT - 018 POWER SOCKET OUTLET LAYOUT PLAN

M&E/TVT - 024 LIGHTING LAYOUT PLAN

M&E/TVT - 034 SINGLE LINE FOR MDB ( MAIN DISTRIBUTION BOARD)

M&E/TVT - 035 WATER DRAIN FROM ROOF TO GROUND

M&E/TVT - 040 WASTE WATER AND WATER SUPPLYM&E/TVT - 041 GREASE TRAP

4 GUEST HOUSE M&E/TVT - 005 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN

M&E/TVT - 020 POWER SOCKET OUTLET AND DATA & TEL SOCKET LAYOUT PLAN

M&E/TVT - 021 LIGHTING LAYOUT PLAN

M&E/TVT - 032 WATER DRAIN FROM ROOF TO GROUND

5TOILET AND STORE

M&E/TVT - 006 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN

M&E/TVT - 017 LIGHTING AND POWER SOCKET OUTLET LAYOUT PLAN

6GREEN HOUSE SHED

M&E/TVT - 003 WATER SEWAREGE AND WATER SUPPLY SYSTEM PLAN

M&E/TVT - 009 POWER SOCKET LAYOUT PLAN

M&E/TVT - 010 DATA AND TEL SOCKET LAYOUT PLAN

M&E/TVT - 019 LIGHTING AND LIGHTING POSITIONING AND SINGLE LINE LAYOUT PLAN

M&E/TVT - 037 WATER DRAIN FROM ROOF TO GROUND

M&E/TVT - 038 SINGLE LINE FOR DB7 (GREEN HOUSE)

M & E SHOP DRAWINGS

Page 18: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

M&E/TVT - 044 EXHAUST AIR SYSTEM

7 OFFICE BUILDING M&E/TVT - 004 WATER SEWERAGE AND WATER SUPPLY SYSTEM PLAN

M&E/TVT - 011 POWER SOCKET LAYOUT PLAN

M&E/TVT - 012 DATA AND TEL SOCKET LAYOUT PLAN

M&E/TVT - 022 LIGHTING LAYOUT PLAN

M&E/TVT - 033 WATER DRAIN FROM ROOF TO GROUND

M&E/TVT - 042 AIR-CONDITION

8 SEED PROCESSING SHED

M&E/TVT - 025 WATER SUPPLY PLAN

M&E/TVT - 026 LIGHTING AND SOCKET OUTLET LAYOUT PLAN

M&E/TVT - 036 WATER DRAIN FROM ROOF TO GROUND

Page 19: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

NO NAME ITEMS SUPLLIER BUILDINGS COMMENTS ATTACHED WITH STATUS SUBMITTED DATE

APPROVED DATE

MES/TVT - 001

PVC PIPE TO BE USED FOR WATER SEWAREGE AND WATER SUPPLY SYSTEM

BINH MINH ALL BUILDINGS ENSURE AROMATIC SOLVENTS ARE NOT USED TO GLUE THE PIPEWORK

CATALOGUE + SAMPLE

APPROVED ON CONDITION, AS NOTED

24/3/2014 24/3/2014

MES/TVT - 002

PVC CONDUIT TO BE USED FOR ELECTRICAL SYSTEM

VANLOCK ALL BUILDINGS WHERE ARE THE 'CUPS' FOR FIXING CONDUITS TO WALLS

CATALOGUE + SAMPLE

APPROVED ON CONDITION, AS NOTED

24/3/2014 24/3/2014

MES/TVT - 003

SAMPLE CABLE FOR ALL BUILDINGS CADIVI ALL BUILDINGS SAMPLE APPROVED 21/4/2014 26/4/2014

MES/TVT - 004

CATALOGUE CCTV ALL BUILDINGS CAMERA SNB-5000, SLA-M 3180DN, HOUSING SHB-4200H, SURGE SUPPRESSOR, EPMP 1000 INTERGRATED RADIO.

CATALOGUES APPROVED 16/5/2014 25/7/2014

MES/TVT - 005

LIGHTING PARAGON CHANGING ROOM OF GREEN HOUSE SHED

LIGHTING PIFL228 FOR SOWING AREA, LIGHTING PCFA236 FOR CHANGING ROOM, SEED CLEANING AREA, GERMINATION ROOM, CONTROL ROOM, EXTENDTION OFFICE PHASE 1, PHYTO LAB, SAMPLING ROOM, GERMINATION LAB, POLLEN EXSTRACTION, SUPERVISER ROOM. DOWNLIGHT PRDH70E27 FOR TOILET 1-FLOOR. EXIT LAMP PEXA13SW FOR TRAINING ROOM, EMERGENCY LAMP PEMA25SW FOR CHANGING ROOM.

CATALOGUE APPROVED 9/6/2014 8/8/2014

MES/TVT - 006

CATALOGUES SANITARY EQUIPMENT

CAESAR GREEN HOUSE SHED, TOILET AND STORE, CANTEEN

WATER CLOSET CD1340 + TAP BS304, UNIRAL U0262 + TAP BF412G, LAVABO LF 5236 + TAP BF053, FLOOR DRAIN ST1010B, COAT HANGER Q8807, SOAP HOLDERS ST823V, TOILET PAPER HOLDERS Q7714V, XI PHONG BF 602, WO34-1, SHOWER BFV-28S are to be used. SHOWERHEAD TO BE RE-SUBMITTED

CATALOGUE SELECTIVITY APPROVED, AS NOTED

9/6/2014 15/7/2014

MES/TVT - 007

CATALOGUES SOCKET, SWITCH SCHNEIDER MAIN STORE, GREEN HOUSE SHED, SEED PROCESSING SHED, TOILET & STORE

SWITCH ONE WAY: F50M1-5, SWITCH TWO WAY: F50-2M1-5, COVER: FG1051, FG1052, FG1053, POWER SOCKET: F1426ESM, DATA AND TEL SOCKET: F50RJ5EM

CATALOGUES APPROVED 9/6/2014 25/7/2014

MES/TVT - 008

CABLE TRAY DONG NAM A GREEN HOUSE SHED, SEED PROCESSING SHED

FOR MAINSTORE AND SEED PROCESSIING SHED CABLE TRAYDUCT TYPE TO BE USED 100×50 AND NO COVER.. DIMENSION ACCORDING SHOP DRAWING.

CATALOGUE AND SAMPLE

APPROVED 19/6/2014 23/7/2014

MES/TVT - 009

SOLAR POWER SINGAPORE CAMERA. OUTDOOR

CATALOGUES APPROVED 8/7/2014 29/8/2014

MES/TVT - 010

WATER HEATER ARISTON GUEST HOUSE ARISTON VERO IM-4522EP (BẠC) TO BE USED CATALOGUE APPROVED 10/9/2014 11/9/2014

MES/TVT - 011

NETWORK ALL BUILDINGS CAT 6A TO BE USED. AP-SWITCH - MODULES TO BE LEFT OUT.

CATALOGUE APPROVED 11/8/2014 9/9/2014

M & E SUBMISSION

Page 20: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

MES/TVT - 012

TRUNKING SOCKET L&S GREEN HOUSE SHED

FA 100/40 100 mm × 40mm × 2 mm. FA 

100/60 100 mm × 60 mm × 2 mm.

CATALOGUE APPROVED 4/9/2014 4/9/2014

MES/TVT - 013

ROAD LAMP POLE LU GIA IN SITE 73-F1-010 + KATO 0516010250 CATALOGUE APPROVED 16/8/2014 19/8/2014

MES/TVT - 014

BRASS FITTING VIET NAM ALL BUILDINGS SAMPLE APPROVED 23/8/2014 23/8/2014

MES/TVT - 015

WALL DECORATIVE LIGHTING CHINA GUEST HOUSE CATALOGUE NOT APPROVED YET

26/8/2014 REJECTED. BEJO WILL SUPPLY

MES/TVT - 016

DOWNLIGHT FOR BATHROOM PHILIP GUEST HOUSE CATALOGUE APPROVED 26/8/2014 1/9/2014

MES/TVT - 017

POLE FOR CAMERA LU GIA IN SITE 8 METER POLE TO BE USED CATALOGUE APPROVED 29/8/2014 12/9/2014

MES/TVT - 018

LAVOBO CAESAR MAINSTORE CATALOGUE APPROVED 1/9/2014 1/9/2014

MES/TVT - 019

LAVABO STAINLESS STEEL HA TIEN LAB ROOM AT GREEN HOUSE SHED

CATALOHUE APPROVED 1/9/2014 1/9/2014

MES/TVT - 020

MACHINE AIR CONDITION DAIKIN OFFICE BUILDING

TO BE SURE ALL COMPONENT SUCH AS DUCTS + UNITS FIT IN CEILING AND SPACE

CATALOGUE APPROVED 16/9/2014 18/9/2014

MES/TVT - 021

FAN AIR EXHAUST PANASONIC GUEST HOUSE FV-20AUG TO BE USED CATALOGUE APPROVED 16/9/2014 16/9/2014

MES/TVT - 022

LIGHTNING EQUIPMENT GREEN HOUSE SHED

CATALOGUE APPROVED 22/10/2014 5/11/2014

MES/TVT - 023

SOCKET 3 PHASE SEED PROCESSING SHED

CATALOGUE APPROVED 22/10/2014 23/10/2014

MES/TVT - 024

MOTOR FOR SLIDING SYSTEM MAIN GATE CATALOGUE APPROVED 22/10/2014 3/11/2014

MES/TVT - 025

TV K+ GUEST HOUSE CATALOGUE APPROVED 25/10/2014 25/10/2014

Page 21: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

10. VARIATIONS AND CLAIMS 

Page 22: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

11. HSE REPORT 

Page 23: MONTHLY PROGRESS REPORT No.08 – OCTOBER 2014mamibo.com/bejo/reports/M_October_2014.pdf · 1 Project Manager 111111111111111111111111111111 2 Site Manager 111111111111111111111111111111

No Description As for this month Accumulated

1 Total Exposure Hour 20680 18100M/H

2 Reported Safety Cases 0

A. Fatalities 0 0

B. Lost Workday Cases 0 0

C. Medical Treatment 0 0

D. Restricted Word Cases 0 0

E. First Aid Cases 0 0

F. Motor Fleet Accidents (Light/ Heavy) 0 0

G. Near Miss Incidents 0 0

H. Fires 0 0

I. Major Property Damage 0 0

3 Total Lost Time Injuries (A + B) 0 0

4 Total Reportable Cases (A + B + C + D) 0 0

5 Total No Lost Time 20680 18100M/H

HSE REPORT

The Safety supervisor of TVT, We compliance with safety policy by the Government. Contractor is implementing all possible safety procedures and tight control of subcontractor's workers to maintain high safety standard at Site. Workers trained in basic safety by monitoring building safety.