Actualización del Valor Referencial del Expediente Técnico Elaboración de Estudios Definitivos para el Mantenimiento Periódico de la Red Vial Nacional Carretera Panamericana Sur, Puente Santa Rosa - Puetne Montalvo MOVILIZACION Y DESMOVILIZACION DE EQUIPO A.- EQUIPO TRANSPORTADO D E S C R I P C I O N CANTIDAD PESO (Kg) PARCIAL (Kg) CAMA BAJA SEMITARYLER EQUIPO PROPIO (VIAJE) (VIAJE) BARREDORA MECANICA 10-20 HP 7 p LONGITUD 1.00 1,000.00 1,000.00 1.00 CARGADOR S/LLANTAS 100-115 HP 2-2.25 YD3 (1) 3.00 10,308.00 30,924.00 3.00 CARGADOR SOBRE LLANTAS 160 - 195 HP 1.00 18,585.00 18,585.00 1.00 CARGADOR RETROEXCAVADOR 62 HP 1 YD3 1.00 8,000.00 8,000.00 1.00 COCINA DE ASFALTO 320 GAL 1.00 2,100.00 2,100.00 2.10 COMPACTADOR VIBR. TIPO PLANCHA 7 HP 1.00 160.00 160.00 0.16 COMPRESORA NEUMATICA 87 HP 250-330 PCM 2.00 2,000.00 4,000.00 4.00 CORTADORA DE ASFALTO 1.00 160.00 160.00 0.16 CHANCAD. PRIM / SECUND. 75 HP 46/ 70 Ton/h 2.00 39,000.00 78,000.00 2.00 EQUIPO DE SOLDAR 1.00 200.00 200.00 0.20 EQUIPO MEZCLADOR/CALENTADOR CEMENTO MODIFICAD 1.00 10,000.00 10,000.00 1.00 ESPARCIDORA DE AGREGADOS 1.00 12,000.00 12,000.00 1.00 FRESADORA 1.00 20,000.00 20,000.00 1.00 GRUPO ELECTROGENO 230 HP 150 KW (2) 3.00 2,000.00 6,000.00 1.00 GRUPO ELECTROGENO 75 Kw 116 HP 1.00 1,500.00 1,500.00 1.50 MAQUINA PARA PINTAR PAVIMENTOS 1.00 135.00 135.00 0.14 MEZCLADORA DE CONCRETO 18 HP 11 Pie3 1.00 2,200.00 2,200.00 2.20 MOTOBOMBA 7-10 HP 4" 1.00 295.00 295.00 0.30 MOTONIVELADORA 125 HP 1.00 11,515.00 11,515.00 1.00 MOTONIVELADORA 145-150 HP 1.00 13,540.00 13,540.00 1.00 PAVIMENTADORA SOBRE ORUGA 69 HP 1.00 12,000.00 12,000.00 1.00 PLANTA ASFALTO EN CALIENTE 60-115 TON/H 1.00 38,400.00 38,400.00 4.00 RETROEXCAVADOR SOBRE LLANTAS 58 HP 1.00 9,000.00 9,000.00 1.00 RODILLO NEUMATICO AUTOP. 81 - 100 HP (5.5 - 20 Ton) (1.00 5,500.00 5,500.00 1.00 RODILLO TANDEM ESTATIC AUT 58-70HP 8-10T (1) 2.00 8,800.00 17,600.00 1.00 RODILLO LISO VIBR AUTOP 101-135HP 10-12T 1.00 11,100.00 11,100.00 1.00 RODILLO LISO VIBRATORIO MANUAL 10.8 HP 1.00 800.00 800.00 0.80 RUTEADORA DE GOLPE 1.00 300.00 300.00 0.30 SELLADOR (FUNDIDIR Y APLICADOR) 1.00 2,000.00 2,000.00 2.00 TRACTOR DE ORUGAS 140-160 HP 1.00 14,900.00 14,900.00 1.00 TRACTOR DE ORUGAS 190-240 HP 1.00 20,520.00 20,520.00 1.00 TRACTOR DE TIRO DE 80 HP (1) 2.00 4,320.00 8,640.00 1.00 VIBRADOR DE 4 HP CAP.=1.50" 1.00 10.00 10.00 0.01 ZARANDA VIBRATORIA 4"x6"x14" M.E. 15 HP 1.00 7,000.00 7,000.00 1.00 TOTAL 26.00 0.00 14.86 (1) Dos equipos por cama baja; (2) Tres equipos por camabaja CALCULO NUMERO DE VIAJES POR CARGA PRECIO HORAS PARCIAL TOTAL HORA S/. (IDA - VUELTA) S/. S/. CAMA BAJA 26.00 200.52 32.00 166,832.64 166,832.64 MOVILIZACION 166,832.64 DESMOVILIZACION 166,832.64 SEGUROS 5% 16,683.26 TOTAL MOVILIZACION+DESMOVILIZACION 350,348.54 NOTA: La Planta de asfalto necesita de 4 movilizaciones para su completa instalación. (TENIENDO EN CUENTA LAS DIMENSIONES DE LOS EQUIPOS DE CONSTRUCCION) VEHICULOS CANTIDAD

MOVILIZACION

Embed Size (px)

Citation preview

Page 1: MOVILIZACION

Actualización del Valor Referencial del Expediente TécnicoElaboración de Estudios Definitivos para el Mantenimiento Periódico de la Red Vial NacionalCarretera Panamericana Sur, Puente Santa Rosa - Puetne Montalvo

MOVILIZACION Y DESMOVILIZACION DE EQUIPO

A.- EQUIPO TRANSPORTADO

D E S C R I P C I O N CANTIDAD PESO (Kg)

PARCIAL (Kg) CAMA BAJA SEMITARYLER EQUIPO PROPIO

(VIAJE) (VIAJE)

BARREDORA MECANICA 10-20 HP 7 p LONGITUD 1.00 1,000.00 1,000.00 1.00

CARGADOR S/LLANTAS 100-115 HP 2-2.25 YD3(1) 3.00 10,308.00 30,924.00 3.00

CARGADOR SOBRE LLANTAS 160 - 195 HP 1.00 18,585.00 18,585.00 1.00CARGADOR RETROEXCAVADOR 62 HP 1 YD3 1.00 8,000.00 8,000.00 1.00COCINA DE ASFALTO 320 GAL 1.00 2,100.00 2,100.00 2.10COMPACTADOR VIBR. TIPO PLANCHA 7 HP 1.00 160.00 160.00 0.16COMPRESORA NEUMATICA 87 HP 250-330 PCM 2.00 2,000.00 4,000.00 4.00CORTADORA DE ASFALTO 1.00 160.00 160.00 0.16CHANCAD. PRIM / SECUND. 75 HP 46/ 70 Ton/h 2.00 39,000.00 78,000.00 2.00EQUIPO DE SOLDAR 1.00 200.00 200.00 0.20EQUIPO MEZCLADOR/CALENTADOR CEMENTO MODIFICAD 1.00 10,000.00 10,000.00 1.00ESPARCIDORA DE AGREGADOS 1.00 12,000.00 12,000.00 1.00FRESADORA 1.00 20,000.00 20,000.00 1.00

GRUPO ELECTROGENO 230 HP 150 KW(2) 3.00 2,000.00 6,000.00 1.00

GRUPO ELECTROGENO 75 Kw 116 HP 1.00 1,500.00 1,500.00 1.50MAQUINA PARA PINTAR PAVIMENTOS 1.00 135.00 135.00 0.14MEZCLADORA DE CONCRETO 18 HP 11 Pie3 1.00 2,200.00 2,200.00 2.20MOTOBOMBA 7-10 HP 4" 1.00 295.00 295.00 0.30MOTONIVELADORA 125 HP 1.00 11,515.00 11,515.00 1.00MOTONIVELADORA 145-150 HP 1.00 13,540.00 13,540.00 1.00PAVIMENTADORA SOBRE ORUGA 69 HP 1.00 12,000.00 12,000.00 1.00PLANTA ASFALTO EN CALIENTE 60-115 TON/H 1.00 38,400.00 38,400.00 4.00RETROEXCAVADOR SOBRE LLANTAS 58 HP 1.00 9,000.00 9,000.00 1.00

RODILLO NEUMATICO AUTOP. 81 - 100 HP (5.5 - 20 Ton)(1 1.00 5,500.00 5,500.00 1.00

RODILLO TANDEM ESTATIC AUT 58-70HP 8-10T(1) 2.00 8,800.00 17,600.00 1.00

RODILLO LISO VIBR AUTOP 101-135HP 10-12T 1.00 11,100.00 11,100.00 1.00RODILLO LISO VIBRATORIO MANUAL 10.8 HP 1.00 800.00 800.00 0.80RUTEADORA DE GOLPE 1.00 300.00 300.00 0.30SELLADOR (FUNDIDIR Y APLICADOR) 1.00 2,000.00 2,000.00 2.00TRACTOR DE ORUGAS 140-160 HP 1.00 14,900.00 14,900.00 1.00TRACTOR DE ORUGAS 190-240 HP 1.00 20,520.00 20,520.00 1.00

TRACTOR DE TIRO DE 80 HP(1) 2.00 4,320.00 8,640.00 1.00

VIBRADOR DE 4 HP CAP.=1.50" 1.00 10.00 10.00 0.01ZARANDA VIBRATORIA 4"x6"x14" M.E. 15 HP 1.00 7,000.00 7,000.00 1.00

TOTAL 26.00 0.00 14.86(1) Dos equipos por cama baja; (2) Tres equipos por camabaja

CALCULO NUMERO DE VIAJES POR CARGA

PRECIO HORAS PARCIAL TOTAL

HORA S/. (IDA - VUELTA) S/. S/.

CAMA BAJA 26.00 200.52 32.00 166,832.64166,832.64

MOVILIZACION 166,832.64DESMOVILIZACION 166,832.64

SEGUROS 5% 16,683.26TOTAL MOVILIZACION+DESMOVILIZACION 350,348.54

NOTA: La Planta de asfalto necesita de 4 movilizaciones para su completa instalación.

(TENIENDO EN CUENTA LAS DIMENSIONES DE LOS EQUIPOS DE CONSTRUCCION)

VEHICULOS CANTIDAD

Page 2: MOVILIZACION

Actualización del Valor Referencial del Expediente TécnicoElaboración de Estudios Definitivos para el Mantenimiento Periódico de la Red Vial NacionalCarretera Panamericana Sur, Puente Santa Rosa - Puetne Montalvo

MOVILIZACION Y DESMOVILIZACION DE EQUIPO(TENIENDO EN CUENTA LAS DIMENSIONES DE LOS EQUIPOS DE CONSTRUCCION)

B.- EQUIPO AUTOTRANSPORTADO

PRECIO HORAS PARCIAL TOTAL

HM

HORA S/. (IDA - VUELTA) S/. S/.

CISTERNA 4 x 2 (AGUA) 145 - 165 HP 2,000 GAL 1.00 116.63 30.40 3,545.55CAMION BARANDA 3 ton 1.00 52.44 30.40 1,594.18CAMION IMPRIMADOR 6 x 2 178 - 210 HP 1,800 GAL 2.00 162.58 30.40 9,884.86CAMIONETA PICK - UP C. SIMPLE 1 ton 4.00 56.12 25.00 5,612.00VOLQUETE 6 x 4 330 HP 15 m3 6.00 190.18 30.40 34,688.83

55,325.42SEGUROS 5% 2,766.27

C.- MONTAJE Y DESMONTAJE DE PLANTA DE ASFALTO ESTIMADO 40,000.00

D.- INSTALACION Y DESINSTALACION DE CHANCADORAESTIMADO 30,000.00

E.- INSTALACION Y DESINSTALACION DE ZARANDA VIBRATORIAESTIMADO 20,000.00

F.- LIMPIEZA DEL SITIOESTIMADO 2% SUBTOTAL 1,800.00

COSTO DE MOV. Y DESMOV. DE EQUIPO S/. 500,240.24

DESCRIPCION CANTIDAD